TRANSMISSION LINE & SUBSTATION PROJECTS COMPANY: ENTERGY SERVICES, INC. CUSTOMER: ENTERGY SERVICES (SPO) FACILITIES STUDY EJO NO. F4PPMS0280 ICTT-2012-077 TRANSMISSION SERVICE FACILITIES STUDY OASIS 77025018 Revision: 0 Rev Issue Date Description of Revision Prepared By Approved By A 11/20/12 Submitted to PD KC ED B 11/20/12 TPD Approval RB BW 0 11/29/12 ICT Determines Upgrade Classification Sherri Maxey Benjamin Roubique

Upload: others

Post on 25-Apr-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: TRANSMISSION SERVICE FACILITIES STUDY · 2012-11-29 · transmission service. ... • Install 3-230kv Arrester equipment pedestal foundations • Install 12-230kv, 1phase (low bus)

TRANSMISSION LINE & SUBSTATION PROJECTS

COMPANY: ENTERGY SERVICES, INC.

CUSTOMER: ENTERGY SERVICES (SPO)

FACILITIES STUDY

EJO NO. F4PPMS0280

ICTT-2012-077

TRANSMISSION SERVICE FACILITIES STUDY OASIS 77025018

Revision: 0

Rev Issue Date Description of Revision Prepared

By Approved

By

A 11/20/12 Submitted to PD KC ED

B 11/20/12 TPD Approval RB BW

0 11/29/12 ICT Determines Upgrade Classification Sherri Maxey

Benjamin Roubique

Page 2: TRANSMISSION SERVICE FACILITIES STUDY · 2012-11-29 · transmission service. ... • Install 3-230kv Arrester equipment pedestal foundations • Install 12-230kv, 1phase (low bus)

OASIS 77025018 Entergy Services, Inc.(SPO) Facilities Study

2

TABLE OF CONTENTS

1. PROJECT SUMMARY ....................................................................... 3

1.1. Background and Project Need............................................................................... 3 1.2. Scope Summary .................................................................................................... 3

1.2.1. Construct a new China – Amelia 230 kV line ............................................ 3

1.3. Cost Summary ....................................................................................................... 3 1.4. Schedule Summary ............................................................................................... 4 1.5. Automatic Generation Control ............................................................................... 4

2. SAFETY REQUIREMENTS ................................................................ 4

3. GENERAL ASSUMPTIONS ............................................................... 4

4. SCOPE OF WORK ............................................................................. 5

4.1. China Substation ................................................................................................... 5 4.2. Amelia Substation ................................................................................................. 9 4.3. New 230 kV Line between China to Amelia ........................................................ 12

5. COST ............................................................................................... 14

6. UPGRADE CLASSIFICATION ......................................................... 14

7. SCHEDULE ...................................................................................... 15

8. RISK ASSESSMENT ....................................................................... 16

9. CONFIRMED RESERVATIONS ....................................................... 17

10. PRE-888 TRANSACTIONS .............................................................. 22

11. STUDY QUEUE ................................................................................ 24

12. ATTACHMENTS .............................................................................. 25

12.1. Table of Acronyms .............................................................................................. 25 12.2. Substation One lines & Layout Drawings ............................................................ 26 12.3. Duration Schedule Summary............................................................................... 26

Page 3: TRANSMISSION SERVICE FACILITIES STUDY · 2012-11-29 · transmission service. ... • Install 3-230kv Arrester equipment pedestal foundations • Install 12-230kv, 1phase (low bus)

OASIS 77025018 Entergy Services, Inc.(SPO) Facilities Study

3

1. PROJECT SUMMARY

1.1. Background and Project Need The purpose of this Facilities Study is to determine the availability of transfer capability across Entergy’s transmission system from Entergy (EES) to Entergy (EES) to evaluate the Entergy Services (SPO) request for 9 MW of yearly network transmission service. The time period for this transfer is from 1/1/2013 until 1/1/2033. The direction of the transaction is EES to EES. The study was performed on the latest available January 2013 – May 2014 monthly models, 2014-2023 winter and 2014-2023 summer peak seasonal models using PSS/E and MUST software by Power Technologies Incorporated (PTI). The Facilities Study identifies any transmission constraints resulting from the requested power transfer. The Facilities Study also includes cost estimates to correct any transmission constraints.

1.2. Scope Summary

The Facilities Study has identified some transmission constraints.

Rollover rights are available.

The following project is required to be in-service prior to 1/1/2019 for ATC to be available.

1.2.1. Construct a new China – Amelia 230 kV line

The China – Amelia 230 kV transmission line overloads for the loss of the China – Amelia 230 kV transmission line. Also, the China – Amelia 230 kV transmission line overloads for the loss of the China-Amelia 230 kV transmission line. A second 230 kV transmission line from China to Amelia will alleviate these constraints. This project is proposed in the 2012-2016 Entergy Construction Plan with an expected ISD of Summer 2016.

1.3. Cost Summary

The estimated total project cost is $36,642,178. This includes AFUDC and does not include Tax Gross Up which may apply if and where applicable (Tax Gross Up rate at this time is 24.85%). The estimate includes AFUDC and it will be waived should customer elect to make prepayment The ICT has assigned $36,642,178 as Base Plan upgrades and $0 as Supplemental Upgrade based on Attachment T of Entergy’s Open Access Transmission Tariff (“OATT”).

Page 4: TRANSMISSION SERVICE FACILITIES STUDY · 2012-11-29 · transmission service. ... • Install 3-230kv Arrester equipment pedestal foundations • Install 12-230kv, 1phase (low bus)

OASIS 77025018 Entergy Services, Inc.(SPO) Facilities Study

4

1.4. Schedule Summary The requested date for the start of network transfer is 1/1/2013. Construction of all constraints would be completed by 5/30/2016.

1.5. Automatic Generation Control Not applicable.

2. SAFETY REQUIREMENTS

Safety is a priority with Entergy. Safety will be designed into substations and lines. The designs will be done with the utmost safety for personnel in mind for construction, operation, and maintenance of the equipment. All employees working directly or indirectly for Entergy shall adhere to all rules and regulations outlined within the Entergy Safety manual. Entergy requires safety to be the highest priority for all projects. All Entergy and Contract employees must follow all applicable safe work procedures.

3. GENERAL ASSUMPTIONS

• Sufficient time will be allowed in approving the project enabling Entergy to prepare a

Project Execution Plan and be able to complete the project as per outlined in the schedule described below.

• Assumptions have been made in developing estimates without performing site visits, surveys, and soil borings. During Project Execution Plan these tasks will be completed and could have an impact on estimates and schedule.

• All costs above represent good faith estimates in 2012 dollars and are based on existing data and could change considerably after development of a detailed project execution plan. Price escalation for work in future years has not been included.

• Relay settings and RTU configurations Details need to be specified during Project Execution (PEP) Plan stage, such as equipment and schemes for pilot protections.

• System changes will be modeled in ASPEN. Relay Impact Analysis will be performed by a settings engineer during PEP stage to identify requirements for relay/CT replacement and settings revisions at the local and remote stations in the area..

• Communicate the project and protection coordination with nuclear, generation plants, load customers and other interconnected utilities as appropriate.

• Comply with PRC-001, PRC-023 and relevant procedures, standards and guidelines as appropriate.

• New RTU configurations or revisions will be necessary for stations where new equipment is installed or equipment replacement takes place. For example, there may be a need to map the additional points from a new or different relay.

Page 5: TRANSMISSION SERVICE FACILITIES STUDY · 2012-11-29 · transmission service. ... • Install 3-230kv Arrester equipment pedestal foundations • Install 12-230kv, 1phase (low bus)

OASIS 77025018 Entergy Services, Inc.(SPO) Facilities Study

5

4. SCOPE OF WORK 4.1. China Substation

General • Line and line equipment at terminal would need to be rated at a minimum of 2000

amps (797 MVA). • 230kv IPO breakers are assumed.

Site No site work is required. Foundations All foundation work shall be performed in accordance with current Entergy Standards. All new structures will be tied to the existing grid with 19#9 copperweld conductor as per Entergy grounding standards. Foundation Work will include installation of the following: • Install 3-230kv breaker foundation • Install 1-230kv full tension dead end foundations • Install 6-230kv CVT equipment pedestal foundations • Install 3-230kv Arrester equipment pedestal foundations • Install 12-230kv, 1phase (low bus) bus support foundations • Install 2-230kv, 3 phase (low bus) bus support foundations • Install 2-230kv, 3 phase (high bus) bus support foundations • Install 2-230kv, switch support (low bus) pedestal foundation • Install 2- substation yard light foundations • Install 2,000’ of ground grid 4/0 copper conductor • Install 1,000’ of pigtails for equipment, structures and dead end grounding to

ground grid • Install approximately 600’ of conduits to new breakers, CVTs and cable trough • Install approximately 600’ of precast cable trough • Install 2 pull boxes • Install 1,200 tons of crushed rock in disturbed areas

Electrical All electrical work shall be performed in accordance with current Entergy Standards. Electrical Work will include installation of the following:

• Install 1-230kv full tension dead end structures • Install 6-230kv CVT equipment pedestal • Install 3-230kv Arrester equipment pedestal • Install 12-230kv, 1 phase (low bus) bus support pedestals • Install 2-230kv, 3 phase (low bus) bus support pedestals • Install 2-230kv, 3 phase (high bus) bus support pedestals

Page 6: TRANSMISSION SERVICE FACILITIES STUDY · 2012-11-29 · transmission service. ... • Install 3-230kv Arrester equipment pedestal foundations • Install 12-230kv, 1phase (low bus)

OASIS 77025018 Entergy Services, Inc.(SPO) Facilities Study

6

• Install 4-230kv, switch support (low bus) pedestal (1 existing pedestal currently used as bus support)

• Install 3-230kv,3000A, 63kA, IPO breaker • Install 3-230kv, 3000A, Vert bk switch, man op (27 porcelain insulators) • Install 2-230kv, 3000A, Vert Bk switch w/gnd switch and man op (18 porcelain

insulators) • Install 6-230kv CVTs • Install 3-230kv Station class Arrester • Install 2-yard lights • Install 700’ of rigid bus (4” Al Sch. 40 and 700’ of damper cable) including 21-

230kv polymer post insulators (on bus supports and dead-ends) • Install 300’ of rigid bus (6” Al Sch. 40 and 300’ of damper cable) including 9-

230kv polymer post insulators on bus • Install 1,500’ of strung bus (bundled 1590 ACSR) between dead-ends and

jumpers to switches and equipment

Relays Control House General Equipment • It is assumed that all control house equipment will fit within the existing control

house. • The existing RTU will be expanded, if required. • A redundant DC system is required. Size, purchase and install one (1) 125VDC

Lead Acid Battery sets including two-step rack rated for a seismic zone 1, per Entergy Standard PM0203, latest revision. It is estimated that a 200Ah set will be required.

• Size, purchase and install one (1) 130V battery charger. Reference Entergy Standard PM0302, latest revision, for sizing guidelines. It is estimated that a 25A battery charger will be needed.

• Purchase, design and install one (1) battery switch panel per Entergy Standard PN0103, latest revision. It is estimated that a 200A panel will be needed.

• Purchase, design and install one (1) stand alone DC panel per Entergy Standard PM0101, latest revision.

• Install two (2) fiber optic patch panels for communications with Amelia 230kV substation. Purchase and install additional fiber equipment as dictated by the Telecom group needed to interface with fiber optic cables and relaying circuits.

• Entergy will install ADSS fiber optic cable from the final line splice box on the line termination tower and the fiber optic termination panel in the control house for the new 230kV line.

• Purchase, design, and install one (1) Breaker Control Panel referencing Entergy standard PM0501, latest revision. This panel will be used for protection and control of the center bay new 230kV circuit breaker.

• Purchase and install two (2) three-phase bus potential distribution boxes per Entergy Standard for internal control house distribution of bus potential.

230kV Bus Protection • Purchase, design and install three (3) Bus Differential Panels referencing Entergy

standard PM0602, latest revision. This panel uses a Schweitzer Engineering Lab model. The bus protection will be configured in a primary and backup scheme and is required due to the rearrangement of the substation from a ring bus

Page 7: TRANSMISSION SERVICE FACILITIES STUDY · 2012-11-29 · transmission service. ... • Install 3-230kv Arrester equipment pedestal foundations • Install 12-230kv, 1phase (low bus)

OASIS 77025018 Entergy Services, Inc.(SPO) Facilities Study

7

configuration to a breaker and a half configuration. New 230kV busses shall be referenced as “North” and “South” busses. The existing PVD bus differential protecting the north bus will be modified to accept current input from the new north bay breaker. The system oneline shows a mix of 3000A and 2000A breakers associated with this bus. 3000:5 Slipover CTs are in use for PVD relaying on breaker 5965.

Substation Yard General Equipment • Install six (6) 230kV CVTs with carrier accessories per Entergy standard PN0201,

latest revision. These CVTs will be used for hot 230kV line or bus indication, breaker sync, and reclosing.

• Purchase and install two (2) three-phase CVT junction boxes per Entergy Standard PM2402, latest revision.

230kV New Amelia Line

• Purchase, design and install one (1) new line relay/breaker control panel

referencing Entergy standard PM1803, option B, latest revision. The panel will interface with the new 230kV line/breaker control or line relay panel at Amelia 230kV.

Setting & RTU configuration • Develop (3) Bus Diff protection for North and South busses and modify the

existing PVD bus diff. • Develop (1) new line settings for Amelia 230kV line • Revise Relay settings for • Jacinto – China 230kV • Porter – China 230kV • Sabine – China 230kV

Environmental Permits • Wetland Delineation and Phase I ESA (Environmental Site Assessment) Screen • Wetland Permits • Phase I Cultural Resources Review • USFWS (US Fish and Wildlife Service) Threatened and Endangered Species

Review • Possible Wetland Mitigation • Construction Storm Water Permit • Weekly Storm Water Inspections

Long Delivery Items

Quantity Material Description *Lead Time (weeks)

3 230kv breaker 22-24 5 230kv switch 14-16 3 230kv Arrester 12-14

Numerous Structures tubular/standard 16-18 27 230kv Insulators porcelain 22-24

Page 8: TRANSMISSION SERVICE FACILITIES STUDY · 2012-11-29 · transmission service. ... • Install 3-230kv Arrester equipment pedestal foundations • Install 12-230kv, 1phase (low bus)

OASIS 77025018 Entergy Services, Inc.(SPO) Facilities Study

8

21 230kv Insulators polymer 12-14 1500’ Rigid bus 8-10 3000’ Strung bus ACSR 22-24

Construction methodology • Right of Way along line 6 needs to be confirmed for easement. • All work to be contracted out through procurement process up to and including

Relay if grid personnel resources are not available. • Build new foundations and all electrical install up to north bus tie and L822

interconnect prior to outages • North bus outage for connection to new line bay and install of new bus panel. • Dayton L822 outage for breaker replacements and switch upgrades. • End to end satellite test between China and Porter will be required. • South bus for new L822 line side switch and bus protection panel install.

Outage Planning No detail identification work done at this time – extensive sub and line outages depending on final scope to be submitted into AORS. To include New North and South bus protection panel install outages. • Dayton L822 outage for breaker replacement should be 7 to 10 days. Depending

on state of new breakers and north bus tie, possible to shorten outage and work each side of SW23046 (switch not being replaced) with only limited outage to line for connection to north bus.

• South bus outage for 5 to 7 days for SW upgrade and bus protection panel install. • Cap bank/North bus outage to be approximately 1-2 days for bus tie and possibly

5 days for bus panel install.

Outage for each line with settings upgrade will be approximately one (1) day each.

Safety consideration during construction

Live substation work and proximity of other circuits to be addressed. Clearances, grounding and work zone flagging should be discussed and enforced.

Page 9: TRANSMISSION SERVICE FACILITIES STUDY · 2012-11-29 · transmission service. ... • Install 3-230kv Arrester equipment pedestal foundations • Install 12-230kv, 1phase (low bus)

OASIS 77025018 Entergy Services, Inc.(SPO) Facilities Study

9

4.2. Amelia Substation

General

• Line and line equipment at terminal would need to be rated at a minimum of 2,000 amps (797 MVA).

• 230kv IPO breakers are assumed.

Site

No site work is required.

Foundations

All foundation work shall be performed in accordance with current Entergy Standards. All new structures will be tied to the existing grid with 19#9 copperweld conductor as per Entergy grounding standards. Arresters, CVT and switches will be mounted on existing foundations and no foundations are required for this equipment. New breaker will be installed on an existing foundation. Foundation Work will include installation of the following: • Install 300’ of ground grid pigtails for equipment, structures and dead end

grounding to existing ground grid • Install approximately 200’ of conduits to new breaker, CVT and existing cable

trough • Install 50 tons of crushed rock in disturbed areas

Electrical

All electrical work shall be performed in accordance with current Entergy Standards. Electrical Work will include installation of the following:

• Install 1-230kv CVT equipment pedestal • Install 3-230kv Arrester equipment pedestal • Install 1-W truss to existing bay for switch • Install 2-N trusses for additional strung bus • Install 1-230kv,3000A, 63kA, IPO breaker • Install 1-230kv, 2000A, Center side break switch, man op on existing steel (6

porcelain insulators) • Install 1-230kv, 2000A, Vert Bk switch w/gnd switch and motor operator on new

steel (9 porcelain insulators) • Install 1-230kv CVTs • Install 3-230kv Station class Arrester • Install 600’ of strung bus (bundled 750 Copper) between bays and jumpers to

switches and equipment including 6-230kv suspension polymer insulators and 6 polymer post insulators

Page 10: TRANSMISSION SERVICE FACILITIES STUDY · 2012-11-29 · transmission service. ... • Install 3-230kv Arrester equipment pedestal foundations • Install 12-230kv, 1phase (low bus)

OASIS 77025018 Entergy Services, Inc.(SPO) Facilities Study

10

Relays

Control House General Equipment

• It is assumed that all control house equipment will fit within the existing control house.

• The existing RTU will be expanded, if required. • A redundant DC system is required. Size, purchase and install one (1) 125VDC

Lead Acid Battery sets including two-step rack rated for a seismic zone 1, per Entergy Standard PM0203, latest revision. It is estimated that a 200Ah set will be required.

• Size, purchase and install one (1) 130V battery charger. Reference Entergy Standard PM0302, latest revision, for sizing guidelines. It is estimated that a 25A battery charger will be needed.

• Purchase, design and install one (1) battery switch panel per Entergy Standard PN0103, latest revision. It is estimated that a 200A panel will be needed.

• Purchase, design and install one (1) stand alone DC panel per Entergy Standard PM0101, latest revision.

• Install one (1) fiber optic patch panel for communications with China 230kV substation. Purchase and install additional fiber equipment as dictated by the Telecom group needed to interface with fiber optic cables and relaying circuits.

• Entergy will install ADSS fiber optic cable from the final line splice box on the line termination tower and the fiber optic termination panel in the control house for the new 230kV line.

230kV Bus Protection

• Purchase, design and install one (1) Bus Differential Panel referencing Entergy standard PM0602, latest revision. This panel uses a Schweitzer Engineering Lab. The bus protection will be configured in a primary and backup scheme. The existing PVD bus differential protecting the bus #1will be modified to accept current input from the new China line breaker. The system oneline shows a mix of 3000A and 2000A breakers associated with this bus with all CTs tapped at 2000:5. This issue must be resolved with a retrofit bus diff solution, slipover CTs, or a new bus diff panel. For the purposes of this facility study, a new bus diff panel has been estimated.

Substation Yard General Equipment

• Install one (1) 230kV CVT with carrier accessories per Entergy standard PN0201, latest revision. This CVT will be used for hot 230kV line indication, breaker sync, and reclosing.

• Purchase and install one (1) CVT junction boxes per Entergy Standard.

230kV New China Line

• Purchase, design and install one (1) new line relay/breaker control panel referencing Entergy standard PM1803, option B, latest revision. The panel will interface with the new 230kV line/breaker control or line relay panel at China 230kV.

Page 11: TRANSMISSION SERVICE FACILITIES STUDY · 2012-11-29 · transmission service. ... • Install 3-230kv Arrester equipment pedestal foundations • Install 12-230kv, 1phase (low bus)

OASIS 77025018 Entergy Services, Inc.(SPO) Facilities Study

11

Setting & RTU configuration

• Develop (1) Bus Diff protection. • Revise the existing PVD bus diff protection for Bus 1 • Develop (1) new line settings for china 230kV line • Revise Relay settings for China - Amelia 230kV

Environmental Permits

• Wetland Delineation and Phase I ESA (Environmental Site Assessment) Screen • Wetland Permits • Phase I Cultural Resources Review • USFWS (US Fish and Wildlife Service) Threatened and Endangered Species

Review • Possible Wetland Mitigation • Construction Storm Water Permit • Weekly Storm Water Inspections

Long Delivery Items

Quantity Material Description *Lead Time (weeks)

1 230kv breaker 22-24 2 230kv switch 14-16 3 230kv Arrester 12-14 4 Structures standard 16-18

15 230kv Insulators porcelain 22-24 12 230kv Insulators polymer post & suspn 12-14

600’ Strung bus Copper 10-14

Construction methodology

• Right of Way along line 6 needs to be confirmed for easement. • All work to be contracted out through procurement process up to and including

Relay if AM (Asset Maintenance) resources are not available. • Build new foundations and all electrical install up to bus tie prior to outages • Bus outage for connection to new line bay and install of new bus panel. This

outage disables T1 and T3, distribution must field tie or request mobile sub for 34.5kv system support.

• China L599 outage for movement to new bay to coincide with bus outage. This move will prevent new line crossing underneath existing on entry to Amelia.

• Remote settings changes to take approximately one (1) day per line affected.

Outage Planning No detail identification work done at this time – extensive sub and line outages depending on final scope to be submitted into AORS. To include new bus protection panel install outages. • Bus outage for breaker/new node connection should be 3 to 5 days.

Page 12: TRANSMISSION SERVICE FACILITIES STUDY · 2012-11-29 · transmission service. ... • Install 3-230kv Arrester equipment pedestal foundations • Install 12-230kv, 1phase (low bus)

OASIS 77025018 Entergy Services, Inc.(SPO) Facilities Study

12

• L599 outage should be 5 to 7 days to move over to new bay and should coincide with bus outage.

• L162 and L6 possibly require outages for crossings.

Outage for each line with settings upgrade will be approximately one (1) day each.

Safety consideration during construction

Live substation work and proximity of other circuits to be addressed. Clearances, grounding and work zone flagging should be discussed and enforced.

4.3. New 230 kV Line between China to Amelia

Line Data MVA Required Line Rating (Minimum) 1957A Proposed Line Rating (based on Equipment to be installed) 1957A

Affected line length 11 miles

Build a new 230 kV line, approximately 11 miles long with a proposed route north from China along existing China – Jacinto 230 kV line 568 for approximately 2.5 miles, then east to Amelia. ROW

Approximately 11 miles of 100’ wide new Right of Way, or approximately 133 acres, would be required. It would take approximately 12-18 months to acquire this Right of Way. Three (3) permits would be required to cross LNVA (Lower Neches Valley Authority) freshwater canals. It will take an estimated 1-3 months to finalize the permits once the crossing permit drawings are finalized. One (1) railroad crossing permit will be required. It will take an estimated three (3) months to finalize the permit once the crossing permit drawing is finalized. No state or federal highway crossing permits are anticipated. Environmental

The following Permits / Studies will be required:

• Wetland Delineation and Phase I ESA (Environmental Site Assessment) Screen • Wetland Permits • Phase I Cultural Resources Review • USFWS (US Fish and Wildlife Service)Threatened and Endangered Species

Review • Possible Wetland Mitigation • Construction Storm Water Permit • Weekly Storm Water Inspections

Page 13: TRANSMISSION SERVICE FACILITIES STUDY · 2012-11-29 · transmission service. ... • Install 3-230kv Arrester equipment pedestal foundations • Install 12-230kv, 1phase (low bus)

OASIS 77025018 Entergy Services, Inc.(SPO) Facilities Study

13

Line route The proposed line route runs north from China Substation along existing 230kV L-568 (China – Jacinto) for approximately 2.5 miles, then runs east to Amelia for a total run of approximately 11 miles.

Structures and Foundations It is estimated that this project will require eight (8) single-pole baseplated steel dead end structures in drilled pier foundations, 35 single-pole socket steel tangent structures in vibratory pile foundations, and 35 single-pole direct embedded steel tangent structures. A topographic survey and geotechnical studies would be required in order to perform a detailed design of structures and foundations. Conductor and Insulators 1272 ACSS “Bittern” conductor has been used to develop this estimate. This conductor can supply 1957 Amps at 347ºF. Approximately 261,621 lbs of conductor would be required to complete the 22 mile job. It is estimated that 54 polymer dead end, 210 2.5” polymer braced post, and 15 polymer jumper line post insulator assemblies would be required for this project. OPGW Entergy standard 48-fiber -0.528” Alumacore OPGW will be installed as the primary shield wire for this project. Approximately 61,000’ of cable and three (3) splice boxes would be required. Shield Wire 7#7 Alumoweld would be used as the secondary shield wire in areas where it is required, such as the last span into the substations on each end of the line. A small amount of this cable has been assumed in the estimate. Long Delivery Items

Quantity Material Description *Lead Time (weeks)

78 Steel Poles 20 8 Anchor Bolt Cage Foundations 20

35 Steel Vibratory Piles 20 279 Polymer Insulator Assemblies 12

261,621 lb. 1272 ACSS Conductor 52 61,000’ 48-Fiber Alumacore OPGW 18

Construction methodology for new line construction • Right of Way along line 6 needs to be confirmed for easement. • Preliminary one line issued with study should be re-arranged to have existing line

swapped to new bay to eliminate crossing. Swapping east/west locations with existing line to china.

• Build line end to end with cut in to substations after work is complete.

Page 14: TRANSMISSION SERVICE FACILITIES STUDY · 2012-11-29 · transmission service. ... • Install 3-230kv Arrester equipment pedestal foundations • Install 12-230kv, 1phase (low bus)

OASIS 77025018 Entergy Services, Inc.(SPO) Facilities Study

14

• Line following line 6 along sour lake road after transition from North.

Outage Planning • Possible L162 and L6 for crossings and clearances. • L599 for swap to new bay.

5. COST

The ICT has reviewed and determined whether each required upgrade will be considered a Base Plan Upgrade or a Supplemental Upgrade. For more information on cost responsibility for Base Plan and Supplemental Upgrades, see Attachment T to Entergy’s OATT. The costs shown in the table include all applicable overheads but do not include tax gross up. Entergy incurs a tax liability proportional to the amount of customer contributions.

2013 2014 2015 2016 Total

4.1 China Substation 52,724$ 72,349$ 2,444,257$ 1,891,762$ 4,461,092$ 4.2 Amelia Substation 12,029$ 52,483$ 944,607$ 673,529$ 1,682,648$ 4.3 China - Amelia line 719,158$ 5,019,604$ 13,861,733$ 10,897,944$ 30,498,438$ Total 783,910$ 5,144,437$ 17,250,596$ 13,463,235$ 36,642,178$ 6. UPGRADE CLASSIFICATION

The ICT has reviewed and determined whether each required upgrade will be considered a Supplemental Upgrade. For more information on cost responsibility for Base Plan and Supplemental Upgrades, see Attachment T to Entergy’s OATT.

Task Total Cost Base Plan Supplemental FFR

Payment Section

China Substation $ 4,461,092 $ 4,461,092 Section 4.1

Amelia Substation $ 1,682,648 $ 1,682,648 Section 4.2

China - Amelia line $ 30,498,438 $ 30,498,438 Section 4.3

Total: $ 36,642,178 $ 36,642,178

Page 15: TRANSMISSION SERVICE FACILITIES STUDY · 2012-11-29 · transmission service. ... • Install 3-230kv Arrester equipment pedestal foundations • Install 12-230kv, 1phase (low bus)

OASIS 77025018 Entergy Services, Inc.(SPO) Facilities Study

15

7. SCHEDULE

A detailed schedule will be prepared subsequent to customer approval to proceed with the project. Based on the Task duration schedules listed below, the overall project in-service date is projected to be 30 May 2016. This assumes customer approval to proceed with the development of Project Execution Plan by 1 Jan 2014.

Summary: Completed by end of:

Submit facility Study Nov-12 Customer Approval Apr-13 FP/WO Approval May-13 Complete PEP Nov-13 Customer approval + Revised FP approval Jan-14 Commence design/ROW acquisition/environmental permitting/Order IPO breakers/CCN 14-Feb

order material 15-Jul Issue design packages for SS and lines Aug-14 Receive all SS and line material May-15 Receive ROW and environmental permits Jul-15 CCN approval received Aug-15 Begin t-line and SS construction Oct-15 Complete construction May-16

Notes to Duration Schedules:

• Pre-existing scheduled line outages may prevent the commencement of work. Scheduled outages cannot be confirmed until a firm construction schedule is submitted.

• All construction work requiring outages will be performed during off-peak load season. Line outages will be discussed with the SOC and TOC and the assumption is made that line outages will be executed as planned. However, last minute denial of outages by the SOC/TOC along with resulting schedule delay is possible.

• Design and Construction resources are available when required. • Different resource is used for each design, so all designs start at same time. • Transmission Line and Substation projects will begin subsequent to completion of

Definition phase preparing Project Execution Plan and having customer approval to proceed with the design/procurement and construction.

• This schedule does not account for adverse weather conditions. • Schedule durations are high level estimates at this time. A detailed schedule will be

prepared upon project approval. • Scheduling assumption and completion dates for the project:

Page 16: TRANSMISSION SERVICE FACILITIES STUDY · 2012-11-29 · transmission service. ... • Install 3-230kv Arrester equipment pedestal foundations • Install 12-230kv, 1phase (low bus)

OASIS 77025018 Entergy Services, Inc.(SPO) Facilities Study

16

8. RISK ASSESSMENT

Risk Comment Impact

Right of Way (ROW) and Permits

Scope and estimate to secure for new ROW and permits is based on limited knowledge of individuals using the aerial views, etc on the internet and could vary considerably

****

Material costs steel & Equipment Rising steel, copper, fuel and other market conditions could greatly affect estimated cost.

****

Storm-water plan implementation

Best guess on SWPPP creation, implementation and monitoring can vary greatly dependant on outcome of environmental study.

**

Weather & Equipment Lead Times

Unexpected delays on material lead times, unusually inclement weather will impact schedule but might impact AFUDC costs as well.

**

Wetland mitigation Undetermined until environmental analysis is complete. ***

Outages may not be available

Preliminary schedule only considers general outage constraints. Specific project schedule may be delayed by days, weeks or months dependant on system conditions. Delays of months = increased project costs.

**

CCN and other permitting could take longer than assumed in developing schedule

Need revision to schedule *

Cost of IPO breakers Prices could be higher at the time of placing the order **

Scope based on design assumptions which may change Varied impact on cost and schedule. ***

*-low impact to cost, ** - moderate impact to cost, ***- high impact to cost, **** - very high

Page 17: TRANSMISSION SERVICE FACILITIES STUDY · 2012-11-29 · transmission service. ... • Install 3-230kv Arrester equipment pedestal foundations • Install 12-230kv, 1phase (low bus)

OASIS 77025018 Entergy Services, Inc.(SPO) Facilities Study

17

9. CONFIRMED RESERVATIONS

The following transactions were included in this Facilities Study: OASIS PSE MW Begin End 569011 Entergy Services, Inc. (EMO) 242 3/1/2000 1/1/2014 759196 Entergy Services, Inc. (EMO) 143 1/1/2001 1/1/2021 759294 East Texas Electric Cooperative 31 1/1/2001 1/1/2018 1096986 Tennessee Valley Authority 73 9/1/2003 9/1/2013 1099991 (renewal) City Water & Light, Jonesboro 83 1/1/2010 1/1/2016 1099997 (renewal) City Water & Light, Jonesboro 168 1/1/2010 1/1/2016 1105665 Entergy Services, Inc. (EMO) 236 2/1/2003 2/1/2016 1105666 Entergy Services, Inc. (EMO) 91 2/1/2003 2/1/2027 1105668 Entergy Services, Inc. (EMO) 77 2/1/2003 2/1/2027 1126821 Entergy Services, Inc. (EMO) 101 5/1/2004 5/1/2029 1151106 Entergy Services, Inc. (EMO) 20 6/1/2010 6/1/2029 1168061 Entergy Services, Inc. (EMO) 80 8/1/2004 2/1/2028 1168408 Entergy Services, Inc. (EMO) 247 8/1/2004 2/1/2028 1289686 (undesignation) Entergy Services, Inc. (EMO) 1 6/1/2007 6/1/2030 1294132 Entergy Services, Inc. (EMO) 526 1/1/2006 1/1/2035 1309874 (renewal) East Texas Electric Cooperative 75 1/1/2009 1/1/2017 1309875 (renewal) East Texas Electric Cooperative 50 1/1/2009 1/1/2017 1309876 (renewal) East Texas Electric Cooperative 50 1/1/2009 1/1/2017 1356328 Muni Energy Agcy of Miss 40 6/1/2010 6/1/2040 1373643 City of Conway 25 3/1/2010 3/1/2040 1375299 Louisiana Generating LLC 11 3/1/2006 3/1/2013 1375559 CLECO Power LLC (Gen) 675 12/1/2006 12/1/2016 1380484 Osceola Light & Power 9 9/1/2009 9/1/2039 1383852 Arkansas Electric Cooperative Corp. 550 1/1/2007 1/1/2017 1385158 NRG Power Marketing 13 10/1/20070 10/1/2027 1387272 CLECO Power LLC (Gen) 11 4/1/2006 4/1/2016 1422708 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2007 1/1/2027 1425495 East Texas Electric Cooperative 50 3/1/2010 3/1/2045 1442453 NRG Power Marketing 320 6/1/2007 6/1/2026 1449495 Entergy Services, Inc. (EMO) 322 6/1/2009 6/1/2059 1460876 Aquila Networks-MPS 75 3/1/2009 3/1/2029 1460878 Aquila Networks-MPS 75 3/1/2009 3/1/2029 1460879 Aquila Networks-MPS 75 3/1/2009 3/1/2029 1460881 Aquila Networks-MPS 75 3/1/2009 3/1/2029 1460898 Louisiana Energy & Power Authority 3 1/1/2009 1/1/2030 1460899 Louisiana Energy & Power Authority 5 1/1/2009 1/1/2030 1461442 Louisiana Energy & Power Authority 12 1/1/2009 1/1/2030 1464028 East Texas Electric Cooperative 168 1/1/2010 1/1/2040 1470484 City of West Memphis 20 1/1/2011 1/1/2041 1470811 East Texas Electric Cooperative 186 1/1/2010 1/1/2040 1477069 Entergy Services, Inc. (EMO) 10 11/1/2007 11/1/2037 1480164 Entergy Services, Inc. (EMO) 725 1/1/2005 9/1/2033 1495910 Southwestern Electric 78 5/1/2010 5/1/2013 1498122 Constellation Energy Commodities Grp. 30 4/1/2012 4/1/2042

Page 18: TRANSMISSION SERVICE FACILITIES STUDY · 2012-11-29 · transmission service. ... • Install 3-230kv Arrester equipment pedestal foundations • Install 12-230kv, 1phase (low bus)

OASIS 77025018 Entergy Services, Inc.(SPO) Facilities Study

18

OASIS PSE MW Begin End 1498129 City of Conway 50 4/1/2012 4/1/2042 1499610 Entergy Services, Inc. (EMO) 300 1/1/2008 1/1/2038 1500582 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2008 1/1/2038 1500584 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2008 1/1/2038 1514102 East Texas Electric Cooperative 29 1/1/2008 1/1/2017 1514104 East Texas Electric Cooperative 35 1/1/2008 1/1/2017 1514105 (undesignation) East Texas Electric Cooperative 1 1/1/2008 1/1/2017 1517005 (renewal) NRG Power Marketing 103 1/1/2011 1/1/2026 1525820 (renewal) NRG Power Marketing 3 7/1/2009 7/1/2014 1530287 Empire District Electric 50 3/1/2010 3/1/2030 1530288 Empire District Electric 50 3/1/2010 3/1/2030 1546108 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2011 1/1/2051 1552148 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2009 1/1/2014 1555717 (undesignation) East Texas Electric Cooperative 1 1/1/2010 1/1/2015 1555718 Entergy Services, Inc. (EMO) 158 1/1/2010 1/1/2015 1557220 (undesignation) Entergy Services, Inc. (EMO) 1 7/1/2009 7/1/2018 1557221 Entergy Services, Inc. (EMO) 520 7/1/2009 7/1/2018 1557602 (undesignation) East Texas Electric Cooperative 1 1/1/2009 1/1/2017 1564001 (renewal) Louisiana Energy & Power Authority 6 4/1/2009 4/1/2014 1564356 (renewal) NRG Power Marketing 5 9/1/2009 9/1/2025 1566302 NRG Power Marketing 300 1/1/2008 1/1/2013 1585225 (renewal) City of Prescott 22 4/1/2009 4/1/2039 1585239 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2009 1/1/2013 1585240 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2009 1/1/2013 1598022 (renewal) NRG Power Marketing 103 7/1/2010 7/1/2015 1598291 Entergy Services, Inc. (EMO) 206 6/1/2012 6/1/2042 1598885 (renewal) Morgan Stanley Commodities Group 102 1/1/2009 1/1/2014 1598886 (renewal) Morgan Stanley Commodities Group 102 1/1/2009 1/1/2014 1601111 Constellation 5 1/1/2010 1/1/2015 1615102 (renewal) MidAmerican Energy, Inc. 50 1/1/2009 1/1/2014 1615103 MidAmerican Energy, Inc. 50 1/1/2009 1/1/2014 1615105 MidAmerican Energy, Inc. 50 1/1/2009 1/1/2014 1615108 MidAmerican Energy, Inc. 50 1/1/2009 1/1/2014 1629240 MidAmerican Energy, Inc. 7 3/1/2009 3/1/2014 1630065 NRG Power Marketing 40 1/1/2010 1/1/2015 1632265 Merrill Lynch Commodities 1 4/1/2009 4/1/2014 1633701 NRG Power Marketing 20 1/1/2010 1/1/2019 1633702 NRG Power Marketing 20 1/1/2010 1/1/2016 1633703 NRG Power Marketing 20 1/1/2010 1/1/2016 1639337 Entergy Services, Inc. (EMO) 587 3/1/2009 1/1/2019 1639338 Entergy Services, Inc. (EMO) 103 3/1/2009 1/1/2019 1639339 Entergy Services, Inc. (EMO) 32 3/1/2009 1/1/2019 1639340 Entergy Services, Inc. (EMO) 122 3/1/2009 1/1/2019 1639341 Entergy Services, Inc. (EMO) 134 3/1/2009 1/1/2019 1640629 CLECO Power Marketing 58 5/1/2001 1/1/2021 1640630 CLECO Power Marketing 32 5/1/2001 1/1/2021 1643983 (renewal) NRG Power Marketing 300 1/1/2010 1/1/2015 1643984 (renewal) NRG Power Marketing 100 9/1/2010 9/1/2015 1644155 CLECO Power Marketing 9 4/1/2009 5/1/2016

Page 19: TRANSMISSION SERVICE FACILITIES STUDY · 2012-11-29 · transmission service. ... • Install 3-230kv Arrester equipment pedestal foundations • Install 12-230kv, 1phase (low bus)

OASIS 77025018 Entergy Services, Inc.(SPO) Facilities Study

19

OASIS PSE MW Begin End 1644215 NRG Power Marketing 83 1/1/2010 1/1/2025 1644908 CLECO Power Marketing 41 5/1/2009 5/1/2018 1648049 (undesignation) Entergy Services, Inc. (EMO) 1 6/1/2010 6/1/2013 1648050 Entergy Services, Inc. (EMO) 100 6/1/2010 6/1/2013 1655366 Missouri Joint Municipal 6 10/1/2009 10/1/2014 1658087 Entergy Services (SPO) 1 6/1/2012 6/1/2042 1658088 SMEPA 21 6/1/2012 6/1/2042 1659388 NRG Power Marketing 25 1/1/2011 1/1/2016 1665288 Merrill Lynch Commodities 15 1/1/2011 1/1/2017 1665492 (renewal) Merrill Lynch Commodities 16 11/1/2009 11/1/2014 1665493 (renewal) Merrill Lynch Commodities 4 11/1/2009 11/1/2014 1665899 Ameren Energy, Inc. 75 9/1/2009 9/1/2014 1668165 Entergy Services (SPO) 600 1/1/2013 1/1/2043 1669126 (renewal) Cargill Power Markets, LLC 103 1/1/2011 1/1/2016 1669127 (renewal) Cargill Power Markets, LLC 103 1/1/2011 1/1/2016 1676674 NRG Power Marketing 100 1/1/2011 1/1/2020 1676675 NRG Power Marketing 100 1/1/2011 1/1/2020 1677749 Entergy Services, Inc. (EMO) 1 1/1/2013 1/1/2015 1679179 (renewal) NRG Power Marketing 100 1/1/2011 1/1/2016 1679181 (renewal) NRG Power Marketing 100 1/1/2011 1/1/2016 1685869 (renewal) Muni Energy Agcy of Miss 19 1/1/2010 1/1/2018 1689499 Missouri Joint Municipal 3 9/1/2009 9/1/2014 1690613 NRG Power Marketing 25 1/1/2011 1/1/2016 1694305 Entergy Services (SPO) 15 5/1/2010 5/1/2020 1694306 Entergy Services (SPO) 30 5/1/2010 5/1/2020 73454527 Hope Water & Light 10 10/1/2009 10/1/2032 73457918 South Miss Electric Power Assoc. 180 10/1/2009 10/1/2014 73573797 (renewal) American Electric Power 45 1/1/2011 1/1/2029 73586299 (renewal) American Electric Power 6 1/1/2011 1/1/2029 73595626 NRG Power Marketing 13 1/1/2012 1/1/2017 73724303 Arkansas Electric Cooperative Corp. 104 1/1/2010 1/1/2015 73741113 (renewal) Entergy Services, Inc. (EMO) 150 5/1/2010 5/1/2020 73741122 (renewal) Entergy Services, Inc. (EMO) 135 5/1/2010 5/1/2020 73820650 MOWR 5 3/1/2010 3/1/2040 73884547 MOWR 35 8/1/2010 8/1/2040 73884558 MOWR 40 8/1/2010 8/1/2040 73942862 (renewal) Muni Energy Agcy of Miss 13 6/1/2010 6/1/2015 73970673 Cargill Power Markets, LLC 40 1/1/2012 1/1/2016 73987480 South Miss Electric Power Assoc. 100 5/1/2010 5/1/2040 73987507 South Miss Electric Power Assoc. 180 6/1/2010 6/1/2015 73990804 South Miss Electric Power Assoc. 100 5/1/2010 5/1/2040 74001787 NRG Power Marketing 100 1/1/2011 1/1/2016 74001895 NRG Power Marketing 100 1/1/2011 1/1/2016 74001897 NRG Power Marketing 22 1/1/2011 1/1/2016 74001904 NRG Power Marketing 28 1/1/2011 1/1/2016 74001930 NRG Power Marketing 42 8/1/2006 8/1/2036 74001931 NRG Power Marketing 60 3/1/2010 3/1/2040 74001934 NRG Power Marketing 60 4/1/2012 4/1/2042 74233619 WRGS 15 4/1/2012 4/1/2017

Page 20: TRANSMISSION SERVICE FACILITIES STUDY · 2012-11-29 · transmission service. ... • Install 3-230kv Arrester equipment pedestal foundations • Install 12-230kv, 1phase (low bus)

OASIS 77025018 Entergy Services, Inc.(SPO) Facilities Study

20

OASIS PSE MW Begin End 74233670 (undesignation) Entergy Services, Inc. (EMO) 1 8/1/2012 1/1/2038 74236787 NRG Power Marketing 75 6/1/2012 6/1/2017 74236794 NRG Power Marketing 100 6/1/2012 6/1/2017 74236798 NRG Power Marketing 100 6/1/2012 6/1/2017 74305315 NRG Power Marketing 10 1/1/2014 1/1/2017 74305339 NRG Power Marketing 10 1/1/2013 1/1/2023 74356639 NRG Power Marketing 103 1/1/2011 1/1/2016 74356652 NRG Power Marketing 206 6/1/2012 6/1/2017 74356666 NRG Power Marketing 50 1/1/2013 1/1/2014 74408208 Louisiana Energy & Power Authority 13 9/1/2010 9/1/2015 74408225 Louisiana Energy & Power Authority 45 9/1/2010 9/1/2015 74514903 Entergy Services, Inc. (EMO) 20 6/1/2013 6/1/2029 74514911 Entergy Services, Inc. (EMO) 101 6/1/2013 6/1/2029 74691007 NRG Power Marketing 60 1/1/2013 1/1/2018 74728415 Brazos Electric Cooperative 100 1/1/2012 1/1/2017 74758974 Entergy Services, Inc. (EMO) 804 5/1/2013 5/1/2058 74777205 (renewal) NRG Power Marketing 300 1/1/2013 1/1/2033 74777208 (renewal) NRG Power Marketing 300 1/1/2015 1/1/2035 74789476 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2012 1/1/2016 74829975 (renewal) CLECO Power LLC (Gen) 35 1/1/2011 1/1/2016 74835023 AECI / APM 103 1/1/2012 1/1/2017 74881866 (renewal) NRG Power Marketing 8 3/1/2011 3/1/2021 74899933 Entergy Services (SPO) 322 2/1/2011 2/1/2041 74899954 (undesignation) Entergy Services, Inc. (EMO) 1 2/1/2012 2/1/2014 74899956 Entergy Services, Inc. (EMO) 100 2/1/2012 2/1/2014 74899968 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2013 1/1/2015 74899969 (undesignation) Entergy Services, Inc. (EMO) 1 1/1/2012 1/1/2015 74899972 (undesignation) Entergy Services (SPO) 1 1/1/2015 1/1/2045 74899974 (undesignation) Entergy Services (SPO) 1 1/1/2015 1/1/2045 74899976 (undesignation) Entergy Services (SPO) 1 1/1/2015 1/1/2045 74899980 Entergy Services (SPO) 584 1/1/2015 1/1/2045 74899988 (undesignation) Entergy Services (SPO) 1 6/1/2012 6/1/2042 74899989 Entergy Services (SPO) 485 6/1/2012 6/1/2042 74901827 (undesignation) Entergy Services, Inc. (EMO) 1 2/1/2011 2/1/2041 74958042 NRG Power Marketing 34 1/1/2006 1/1/2036 74958045 NRG Power Marketing 34 1/1/2006 1/1/2036 74958047 NRG Power Marketing 17 1/1/2006 1/1/2036 74958048 NRG Power Marketing 17 1/1/2006 1/1/2036 75207302 (renewal) Entergy Services, Inc. (EMO) 1 7/1/2011 7/1/2016 75259845 South Miss Electric Power Assoc. 2 4/1/2012 1/1/2040 75265640 (renewal) South Miss Electric Power Assoc. 75 6/1/2011 6/1/2016 75299243 AECI 103 1/1/2012 1/1/2017 75342276 Cargill Power Markets 202 12/1/2012 12/1/2017 75342281 Cargill Power Markets 202 12/1/2012 12/1/2017 75460486 MOWR 103 4/1/2012 4/1/2037 75495258 (renewal) NRG Power Marketing 13 1/1/2017 1/1/2019 75564309 ETEC 50 5/1/2014 5/1/2044 75826033 CPWM 600 4/1/2014 4/1/2033 75831107 Muni Energy Agcy of Miss 20 6/1/2013 6/1/2041

Page 21: TRANSMISSION SERVICE FACILITIES STUDY · 2012-11-29 · transmission service. ... • Install 3-230kv Arrester equipment pedestal foundations • Install 12-230kv, 1phase (low bus)

OASIS 77025018 Entergy Services, Inc.(SPO) Facilities Study

21

OASIS PSE MW Begin End 76120007 renewal CLECO Power Marketing 10 10/1/2012 10/1/2017 76234876 Entergy Services (SPO) 1 6/1/2012 6/1/2042 76234879 Entergy Services (SPO) 194 6/1/2012 6/1/2042 76234889 Entergy Services (SPO) 256 1/1/2016 1/1/2043 76234897 Entergy Services (SPO) 35 1/1/2016 1/1/2043 76234904 Entergy Services (SPO) 1 6/1/2012 6/1/2042 76234916 Entergy Services (SPO) 140 6/1/2012 6/1/2042 76234922 Entergy Services (SPO) 1 5/1/2013 5/1/2042 76234951 Entergy Services (SPO) 5 5/1/2013 5/1/2042 76234980 Entergy Services (SPO) 1 1/1/2014 1/1/2043 76234993 76235000 76235003 Entergy Services (SPO) 475 1/1/2014 1/1/2043 76238089 Entergy Services (SPO) 20 1/1/2014 1/1/2043 76280552 (undesignation) Entergy Services (SPO) 1 6/1/2012 6/1/2042 76280558 (undesignation) Entergy Services (SPO) 1 5/1/2013 5/1/2042 76336174 (redirect) NRG Power Marketing 206 6/1/2013 6/1/2017

76449800 Arkansas Electric Cooperative Corp.

250 1/1/2012 1/1/2013 275 1/1/2013 1/1/2014 300 1/1/2014 1/1/2015 320 1/1/2015 1/1/2017

76449828 Arkansas Electric Cooperative Corp.

78 1/1/2012 1/1/2013 80 1/1/2013 1/1/2014 82 1/1/2014 1/1/2015 84 1/1/2015 1/1/2016 86 1/1/2016 1/1/2017

76513126 (undesignation) Constellation Energy Commodities Grp. 1 1/1/2012 1/1/2017 76513148 (undesignation) Constellation Energy Commodities Grp. 1 1/1/2012 1/1/2017 76513215 EWOM 60 11/1/2009 11/1/2014 76513304 (renewal) EWOM 60 11/1/2014 11/1/2019 76533177 EWOM 25 4/1/2009 4/1/2014 76533260 (renewal) EWOM 25 4/1/2014 4/1/2019 76583976 Arkansas Electric Cooperative Corp. 660 9/1/2012 9/1/2017 76583995 Arkansas Electric Cooperative Corp. 200 9/1/2012 9/1/2017 76744580 (deferral) South Miss Electric Power Assoc. 2 1/1/2013 1/1/2040 76767669 NRG Power Marketing 103 6/1/2013 6/1/2017 76794321 NRG Power Marketing 10 1/1/2013 1/1/2025

Page 22: TRANSMISSION SERVICE FACILITIES STUDY · 2012-11-29 · transmission service. ... • Install 3-230kv Arrester equipment pedestal foundations • Install 12-230kv, 1phase (low bus)

OASIS 77025018 Entergy Services, Inc.(SPO) Facilities Study

22

10. PRE-888 TRANSACTIONS

OASIS

PSE MW Begin End 1332606

East Texas Electric Cooperative 55 1/1/2006 1/1/2017

1412156

Entergy Services, Inc. (EMO) 741 1/1/2007 1/1/2038

1412158

Entergy Services, Inc. (EMO) 1867 1/1/2007 1/1/2038

1412160

Entergy Services, Inc. (EMO) 1142 1/1/2007 1/1/2038

1412161

Entergy Services, Inc. (EMO) 59 1/1/2007 1/1/2038

1412162

Entergy Services, Inc. (EMO) 148 1/1/2007 1/1/2038

1412164

Entergy Services, Inc. (EMO) 1157 1/1/2007 1/1/2038

1412165

Entergy Services, Inc. (EMO) 1219 1/1/2007 1/1/2038

1412166

Entergy Services, Inc. (EMO) 683 1/1/2007 1/1/2038

1412167

Entergy Services, Inc. (EMO) 140 1/1/2007 1/1/2038

1412168

Entergy Services, Inc. (EMO) 456 1/1/2007 1/1/2038

1412169

Entergy Services, Inc. (EMO) 739 1/1/2007 1/1/2038

1412171

Entergy Services, Inc. (EMO) 64 1/1/2007 1/1/2038

1412172

Entergy Services, Inc. (EMO) 870 1/1/2007 1/1/2038

1412173

Entergy Services, Inc. (EMO) 129 1/1/2007 1/1/2038

1412175

Entergy Services, Inc. (EMO) 130 1/1/2007 1/1/2038

1412176

Entergy Services, Inc. (EMO) 65 1/1/2007 1/1/2038

1412178

Entergy Services, Inc. (EMO) 61 1/1/2007 1/1/2038

1412179

Entergy Services, Inc. (EMO) 304 1/1/2007 1/1/2038

1412181

Entergy Services, Inc. (EMO) 692 1/1/2007 1/1/2038

1412183

Entergy Services, Inc. (EMO) 433 1/1/2007 1/1/2038

1412184

Entergy Services, Inc. (EMO) 1946 1/1/2007 1/1/2038

1412185

Entergy Services, Inc. (EMO) 946 1/1/2007 1/1/2038

1498278

Entergy Services, Inc. (EMO) 75 8/1/2007 1/1/2017

1498281

Entergy Services, Inc. (EMO) 86 8/1/2007 1/1/2017

1498283

Entergy Services, Inc. (EMO) 68 8/1/2007 1/1/2017

1498284

Entergy Services, Inc. (EMO) 78 8/1/2007 1/1/2017

1498285

Entergy Services, Inc. (EMO) 11 8/1/2007 1/1/2044

1498286

Entergy Services, Inc. (EMO) 69 8/1/2007 1/1/2044

1498287

Entergy Services, Inc. (EMO) 14 8/1/2007 1/1/2044

1528114 Replaces 1412186 Entergy Services, Inc. (EMO) 1523 1/1/2008 1/1/2038

1528115 Replaces 1412177 Entergy Services, Inc. (EMO) 1039 1/1/2008 1/1/2038

1528116 Replaces 1412182 Entergy Services, Inc. (EMO) 1834 1/1/2008 1/1/2038

76120467 Renewal for 1412178 Entergy Services, inc. (EMO) 61 1/1/2038 1/1/2045

76120472 Renewal for 1412172 Entergy Services, inc. (EMO) 870 1/1/2038 1/1/2045

76120479 Replaces 1412155 Entergy Services, Inc. (EMO) 1738 1/1/2012 1/1/2045

76234797 Renewal for 1412163 Entergy Services, Inc. (EMO) 194 1/1/2038 1/1/2043

76234817 Renewal for 1412174 Entergy Services, Inc. (EMO) 140 1/1/2038 1/1/2043

76234827 Renewal for 1412170 Entergy Services, Inc. (EMO) 183 1/1/2038 1/1/2043

76234836 Renewal for 1412180 Entergy Services, Inc. (EMO) 351 1/1/2038 1/1/2043

76292988 Replaces 1412163 Entergy Services, Inc. (EMO) 190 1/1/2012 1/1/2043

76292990 Replaces 1412174 Entergy Services, Inc. (EMO) 144 1/1/2012 1/1/2043

Page 23: TRANSMISSION SERVICE FACILITIES STUDY · 2012-11-29 · transmission service. ... • Install 3-230kv Arrester equipment pedestal foundations • Install 12-230kv, 1phase (low bus)

OASIS 77025018 Entergy Services, Inc.(SPO) Facilities Study

23

OASIS

PSE MW Begin End 76292992 Replaces

1412170 Entergy Services, Inc. (EMO) 210 1/1/2012 1/1/2043

76292993 Replaces 1412180 Entergy Services, Inc. (EMO) 324 1/1/2012 1/1/2043

76528782 Constellation Energy Commodities Grp 5 7/1/1998 7/1/2027

Page 24: TRANSMISSION SERVICE FACILITIES STUDY · 2012-11-29 · transmission service. ... • Install 3-230kv Arrester equipment pedestal foundations • Install 12-230kv, 1phase (low bus)

OASIS 77025018 Entergy Services, Inc.(SPO) Facilities Study

24

11. STUDY QUEUE

OASIS PSE MW Begin End 74846159 AEPM 65 1/1/2015 1/1/2020 75206836 ETEC 125 1/1/2015 1/1/2020 76523750 SRMPA 180 6/1/2012 6/1/2018 76523753 SRMPA 30 6/1/2012 6/1/2016 76523754 EWOM 45 6/1/2012 6/1/2016 76744419 SMEPA 280 1/1/2014 1/1/2025 76794133 (undesignation) NRG Power Marketing 1 1/1/2014 1/1/2022 76794134 (undesignation) NRG Power Marketing 1 1/1/2014 1/1/2022 76794135 (undesignation) NRG Power Marketing 1 1/1/2014 1/1/2022 76794138 (undesignation) NRG Power Marketing 1 1/1/2014 1/1/2022 76794140 NRG Power Marketing 309 1/1/2014 1/1/2019 76794150 (undesignation) NRG Power Marketing 1 1/1/2014 1/1/2019 76794151 NRG Power Marketing 309 1/1/2014 1/1/2019

SPP 74240998_1004_ 1007_1231_1265 AEP 20-116 1/1/2011 1/1/2020

76902738 CPWM 80 1/1/2013 1/1/2018 76975184 Entergy Services (SPO) 28 1/1/2013 1/1/2033

Page 25: TRANSMISSION SERVICE FACILITIES STUDY · 2012-11-29 · transmission service. ... • Install 3-230kv Arrester equipment pedestal foundations • Install 12-230kv, 1phase (low bus)

OASIS 77025018 Entergy Services, Inc.(SPO) Facilities Study

25

12. ATTACHMENTS

12.1. Table of Acronyms

Acronym Description ACSR Aluminum Conductor Steel Reinforced ACSS Aluminum Conductor Steel Supported ADEQ Arkansas Department of Environmental Quality ADSS All Di-Electric Self-Supporting AFUDC Allowance for Funds Used During Construction ATC Available Transfer Capability BAB Bus air break CYDS Cubic Yards EES Entergy Control Area EHV Extra-High Voltage ERIS Energy Resource Interconnection Service ICT Independent Coordinator of Transmission IPO Independent Pole operated JSA Job Safety Analysis KCMIL Kilo-circular mil kV Kilo-Volt MCM (M) Thousand Circular Mils MCOV Maximum continuous operating voltage MDOT Mississippi Department of Transportation MVA Mega-Volt Amp MW Mega-Watt NPDES National Pollution Discharge Elimination System NOI Notice of Intent NRIS Network Resource Interconnection Service OASIS Online Access and Same-time Information System OATT Open Access Transmission Tariff POD Point of Delivery POR Point of Receipt SES Steam Electric Station SOC System Operations Center SHV Super High Voltage SW Switch Station TOC Transmission Operations Center

Page 26: TRANSMISSION SERVICE FACILITIES STUDY · 2012-11-29 · transmission service. ... • Install 3-230kv Arrester equipment pedestal foundations • Install 12-230kv, 1phase (low bus)

OASIS 77025018 Entergy Services, Inc.(SPO) Facilities Study

26

12.2. Substation One lines & Layout Drawings

One Lines

Item Description Page G1137S05 Amelia Bulk 230 kV Substation 27 G1164S05 China 230 kV Substation 28

12.3. Duration Schedule Summary

Duration Schedule Summary (See Section 7) Page 15