tw@esi 19th june 2016
TRANSCRIPT
TW@ESI19th June 2016
Good to be back on the rock The following is a record of what was done during the past week and a forecast of the next week.....
A General Note before we start- New premises
The new premises.... Most works have now been completed- well done to all for their efforts done. The following is to be done before we can say we are really ready! a) Intercom on old door entranceb) Air Conditioning controls with JACEc) Re installation of all wall mounted items in tech area. This
area is to be made a show case and it is to reflect organisation and technology
d) Automation system integrated with lighting and the other systems installed
e) Snag list is pending which is with Dennis to implement- Dennis please give me an update of this list
A General Note before we start- Some General Notes•Clifton and Claudio are nearly done with the NIAGARA4 on line training•Next Friday 24th we will be going for after work drinks at the bar near Exiles waterpolo pitch at 1630hrs. It would be great if everyone could join- There will be another activity on Friday 8th July- sailing club and a taster on MoonDance Sailing yaucht •A new intern Dalma Eszenyi – will be joining CVA and CCI team as of 27th June 2016 till 2nd August 2016
Projects and deadlines• 15_044_Hilton_Restaurant_Kitchen_AHU and
15_034_Hilton_Calorifier_Monitoring. We have managed to commission basic closed loop controls ... Next would be the full commissioning of the CVA can you confirm when this will be completed. We will have the VSD built as of tomorrow 20th June and DSH should co ordinate to install this permanently on site
• 15_033_Westin_7-AHU- Most of the T&C should by now be completed. Pending is documentation CCI I would like a target date on the completion here
• 15_008 - Aurobindo PH02 BMS- We have made progress on commissioning here- we are stuck on a lot of issues by the client – We must do all we can to close items which are our control
Projects and deadlines• 12_027- Parliament installation of St James lift
intercom and DAC system- Well done on the St James Lift- We now need to proceed on all pending issues down to ESI (Original contract- Server software, Intruder alarm mainly)
• 13_070- SCM Lagoona Plant room – DSH we need to identify which is the date when we can conclude all installations possible here
• 15_041- has been concluded and we now have to close off all as fitted and O&M as well as assist in creating a VPN with site- A very very well done to all who made this a successful overseas endeavour.
DesignLast week• AAP – concluded Panel Sizing• OVT & AAP – requote Rittal for Enclosure
quotes• MDH – various labels for JGa• Life Sciences – O&M CDs for MPa• AAP – received pending info, concluded &
submitted ELV P&IDs & Plans
DesignNext Week:• My Fadlallah update for CVA• Westin 7AHUs – get As Built feedback from CCI,
implement• Hilton Kitchen AHUs - get As Built feedback from DSH,
implement. Then distribute to Alex & Mark Picc.• OVT & AAP – Conclude Rittal Parts list, send to Manuel to
order• OVT – update UFH details on P&ID, & re-submit to all• AAP – ELV meeting with client & contractor• OVT – Helvar & Tridium order• AAP - Helvar & Tridium order
InstallationPast week:
• Assisted Claudio at Aurobindo• Fitted level switches on SCM FF diesel tank
manhole• Continued with electrical, plumbing installation
and plastering in garage with roller shutter• Passed new supply for BMS panel• Plastering works in garage• Irrigation for terrace plants and water tap• Installed light fittings on Facade
InstallationNext week:
• Sterling PPM• Continue at SCM Lagoon• CCTV repairs at SCM• Complete garage
Panel BuildWe have the Hilton VSD design and material list ready
we will be sub contracting this as a Trial
Next panels planned are for
a) OVT panelsb) APP panels
Mater DeiThe following are the tasks being worked on and planned for the next weeks• MCC Panel Checks/UPS in BMS Panel E01-CC1, E02-CC1, EP1-CC1, F01-CC1,
F02-CC1, F05-CC4, F05-CC5, F03-CC1, F04-CC1, F05-CC1• MCC PANEL CHECKS/UPS IN BMS PANEL D00-CC1, D01-CC1, DP1-CC1, D02-
CC1, DP2-CC1, D04-CC1, DP3-CC1, D04-CC2, D04-CC3, DO5-CC1, D02-CC2, D06-CC1, DP4-CC1, D06-CC2, D06-CC3
• Field Device PPm D08-CC1, DP5-CC1 / D08-CC2, D08-CC3 / D09-CC1, D09-CC2• COORDINATED CHECKS OF ALARMS FROM 3RD PARTY DEVICES D08-CC1, DP5-
CC1, D08-CC2, D08-CC3, D09-CC1, D09-CC2• WEEKLY UPDATE OF ANTI-VIRUS ON ALL BMS STATIONS• Handling of reactive work orders• Quotation works new angiography project• Cont WinCC Upgrade HMIs- which are now all on line- well done all!!• To Add 2 new Alarms from volt free contacts of medical fridges in rooms
D113051 and D113052• New Medical gas alarm in B212005
Development and Commissioning• Parliament project - NEXT IS TO TACKLE SNAGS ON
PARLIAMENT so as to close off the whole job • The last issues on the DAC for SCM PH2- IT IS NOW A
PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION
• 12_043_Life Sciences – Collecting the KWhr monthly data and finishing off what we can is a huge urgency- we need to start on water meter commissioning
• SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this
• The Bosch HSDK interface is well advanced and we have documented and we should shortly be expecting to go overseas to commission
Development and Commissioning• OTM urgent jobs and snags – P12/ Tank Field 3• CCA Villa - AC snags and ILPS. • Oncology 14_066- We have done most of the
work here and are waiting from Panta on this• Aurobindo we are proceeding with software
development and we have done quite some progress –we have met the client and have ways ahead to close whatever can be closed
Development and Commissioning• 16_004_Microbiz_PW_Otis_Interface- is now urgent and
must meet our deadlines- we have fixed the commissioning dates in the US here
• 14_081_Siggiewi School- Lets move on concluding issues related to Data acquisition and analysis.... We need good data to prove our systems- CCI we need to assess the data requirements of the client and report back
• 16_017_BMIT_DAC- We have done first and second fix and now need to proceed to commission
• 16_011_Intruder_UOM- We have started installation on this project and we need to plan on completion dates
Data, data and more data• We have a lot of projects which are giving us a lot
of data and I would like to start telling “stories” by data
• I have received Data from MDH and need the data from CCI (for siggiewi) and what type of data we can get from SCM (From CVA) – Once I have these I will start writing our stories with the data
• I should have had this data by 13th June- I need feedback from CCI and CVA- or tell me by when I can get this data
Sales and Business Development• We have been working on a quote for Actavis,
2 other Home automation projects and a quote for OTM for the change over of their PLC/Operating system and re writing of their core software
• We have been successful in winning a new lighting control system in a show area for Nestle - 15_039
Birthday wishes go to
Christian Fenech 20th June John Fenech 21st June
Team ESI- Reminders• Quality Tasks- I need to know your plan to complete quality tasks
– the deadline was 15th June ... Am still awaiting the dates from some of you (sent out reminders... You have till end of week 24th June to give me your dates)
• I sent out some e mails to some of you to give me feedback on what tools and instruments you have so as to have a log of everyone- I need your feedback by 30th June 2016
• Quality questions for new employees – I sent these out and need them returned by 13th July 2016
• Strengths, Weaknesses, Opportunities and Threats... I would like all your feedback by end of June 2016.... This is what I came up with so far
Team ESI• I urge you all to follow this blog and keep up to date with
what is happening at ESI • I await all your feedback on all the ESI discussions –
without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment
• Please urge and assist all you colleagues to have a linkedin profile and join this discussion group
• Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for
Team ESI• Lets all work to get the work done on time, on budget
and to the required quality• We need to communicate, pull the rope in the same
direction to make our projects a success and profitable• I have been seeing a lot of encouraging actions
showing teamwork- people working and helping each other as a team – this needs to go on and we must work to achieve what we persist for- success!!!
• Have a good week