Hope all of you had a good weekend

The following is a record of what was done during the last working week and a forecast of the Next week.....

Initial Points

Projects and Deadlines

Design

Installation Panel Build

Mater Dei Hospital PPM

Business Development

Page 3: TW@ESI 5th February 2017

As of Monday 6th Feb Kimberly Gijsbers (Dutch Nationality) will be joining ESI. Kimberly will be assisting TBr and KJa in Sales Department. She is going to stay with us till 16th June 2017.

Note that I will be on long leave from 13th Feb to 24th Feb (both days

included)

Some Points Before Starting

Also note that Shridar will be on long leave from 17 Feb 2017 to 20th

March

Page 4: TW@ESI 5th February 2017

Projects and Deadlines

16_051_Baxter_AHU

Project put to sleep – well done to all!! Some minor snags but on in all done-

Dennis to address the snags pending- there are also some issues regarding un stable velocity readings which Trevor is taking care of

16_041_RSM_Security

We have done some good progress here – well done to all pulling the ropes!!!

We need to close off here – the sooner the better

16_025_DeLaRue_OFX

Design will be ready this week , materials have been delivered and training by overseas specialists was delivered last week- thanks to CFH/TBR/MPA on organising the required logistics

14_069_OTM Additions

Q019 AS410 – We are proceeding with works here in conjunction with Gruppo Sett in Italy- our high level target is to change over in May/June 2017

Q021_TF4- Panel is on site and installed- we need to power up and start connecting and powering up MOVs- we have made some target dates which we need to keep

16_007_LeMeridien

We have started working on phase 1 panels – phase 1 which has to be completed by Feb 2017-

We have so far done 2 panels – we need to do 5 by end of Feb 2017- so we are a little behind here

Page 5: TW@ESI 5th February 2017

Projects and Deadlines

16_023_GGY

We have some snags pending (Savant with Android TV, integration with Acs, under floor heating functionality) - we also have to transfer the old GGY system to the new platform

15_011- Sliema apartments

We have done most terminations and panel build is completed too. We are trying to finalise the installation and then testing and commissioning would be next... The completion date here is for March 2017

15_023_FM panels

We have a new 2 panels for FM environmental (D5M-110) ... The delivery date is not know – design is completed

We have also received a new order for D20 ASRD400 - DU_P D/A- it is to be completed by first week of March 2017- this will be done by a new sub contracted panel builder

16_058_Methode

Another fast tack project Jace Based AHU control system here –Panel design is completed

Panel build to start on Monday/Tuesday - use required overtime to complete- Installation to commence with cable pulling by Sub contractors – for this project , in my absence, I will need Dennis/Clifton and Claudio to take over and ensure we deliver on time

14_083_Interconti

We have commissioned the system with snags - we will return to site when snags are done by others-

we also have to deliver the pool panel

Page 6: TW@ESI 5th February 2017

Projects and Deadlines

12_043_LSP

We have an important and urgent snag to be rectified ASAP – treating the rust on enclosures

There are some points on the tenant billing application which we are tackling

13_031_CCA

We have a number of snags here , which are to be put to bed once and for all!!

The snags are centred around the AC controls and the NUOO CCTV system

12_027- Parliament

We have finalised the documentation and eventually need to integrate ProWatch.

15_038_new_HA_Ovt and 15_026_Apap

Residence

These two home automation projects are now urgent- we need to complete all installation

We also need to start working of the software development- they are urgent and we have to perform

14_08_Siggiewi School-

We have made a commitment to do training1. Training/ Data gathering and back up / Preventative maintenance on hardware /Transfer of server to SHE set up at MITA/Reactive maintenance/emergency call outs/Fine tuning / re commissioning of louvers

Page 7: TW@ESI 5th February 2017

Projects and Deadlines

12_025_SCM PH2

The last issues on the DAC for SCM PH2- IT IS NOW A PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION- SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this

13_070- SCM Lagoona Plant room

We need to conclude all pending installation works – we will also try to finish the programming but commissioning will be on hold till the client asks us to continue

13_075_Bosch_ProWatch_Genetec_Interface

The Bosch HSDK interface is well advanced and we have documented and we should shortly be expecting to go overseas to commission

Page 8: TW@ESI 5th February 2017

01 02 03 04

DesignFor the Past week we have been working on the following

Completed RSM Security Panel DrawingsRSM Security DAC Drawings

Methode – released MCC-SMT for Panel BuildingMethode- populated ‘Notes for Programmers’ on Points list with SAA

FM Env D20-ASRD – concluded Panel Draughting for CFH review

Design

OTM – Q020 - Netherlocks – started Panel Design TF3_NVC_004_ESI (complete by 10/2)

Page 9: TW@ESI 5th February 2017

01 02 03 04

DesignAnd next week… we will work on

OTM – Q020 - Netherlocks – release Panel Design TF3_NVC_004_ESI to Silvio review & feedback (complete & submit by 10/2)

FM Env – D20-ASRD – conclude CFH feedback, print labels for Panel Build

Preparation design works for new project

Design

Page 10: TW@ESI 5th February 2017

This is what the Installation team have been working on last week

Modification on Dali at RSM

Energized the new 5DP02 extension panel at OTM

RSM Security Terminated all intruder and DAC panels

Installation

Continued with works at Mosta workshop

Maintenance works at offices

Page 11: TW@ESI 5th February 2017

….. And this is what is planned for next week

Start commissioning at RSM

Restart with works at OVT

Installation

OTM Terminate outgoers on 5DP02OTM 5DP02 IO testingOTM Terminations on JB 20

Page 12: TW@ESI 5th February 2017

Next week we will • 16_058_Methode- Gas Down – Full speed ahead please• FM Env D20-ASRD – This will be built by a sub contractor as

soon as we get the parts

Panel Build

Panel Build

Page 13: TW@ESI 5th February 2017

Week 06PPMYearly Field devices checks, IR images & coordinated tests Feb-- D11-CC2, D12-CC1, F02-CC1, F05-CC1, F05-CC4, F05-CC5

Quarterly panel checks Feb -- D00-CC1, D01-CC1, DP1-CC1, D02-CC1, DP2-CC1, D04-CC1, DP3-CC1, D04-CC2, D04-CC3, DO5-CC1, D05-CC2, D06-CC1, DP4-CC1, D06-CC2, D06-CC3D07-CC1, D07-CC2, D08-CC1, DP5-CC1, D08-CC2, D08-CC3, D09-CC1, D09-CC2, D10-CC1, D10-CC2, D10-CC3, DP6-CC1, D11-CC1, D11-CC2,D12-CC1Weekly update of antivirus on all BMS stationsTwo yearly S7-300 CPU V2 Replacement Battery D08-CC1, D08-CC2, D09-CC2, D11-CC1, D11-CC2, D10-CC1, D10-CC2, P04-CC1, CF1-CC1

Mater Dei Maintenance

ReactiveHandling of reactive work orders OthersParticipating in weekly fire drillsTraining of new team memberWO- 116184572 (Q131)To supply and replace existing control gear for F2-CHW1-P2 with a new simocode and sirus soft starter

Mater Dei Maintenance

Page 14: TW@ESI 5th February 2017

Sterling Chemicals Line 2 PLC system

lighting control systems in Qatar

Quote for Fire alarm

Building automation in a private clinic

And…. We may still have a chance to win a VERY large BMS jobThese are the quotes the business development

team have been working on

Business Development

Page 15: TW@ESI 5th February 2017

Some Last Thoughts

I need to bring up a point and remind you all – we need to be cordial, mannered, professional and respectful to clients- I know that most of the times we are that and it is a trait which differentiates our company from others....

But

I need to remind you and insist that we are all cordial, mannered, professional and respectful to each other

Page 16: TW@ESI 5th February 2017

I await all your feedback on all the ESI discussions – without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment

Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for

I urge you all to follow this blog and keep up to

date with what is happening at ESI

Lets all work to get the work done on time, on

budget and to the required quality

We need to communicate, pull the rope in the

same direction to make our projects a success

and profitable

Some Last Thoughts

Page 17: TW@ESI 5th February 2017

I wish you all a good and productive

week