Hello to all , hope you all had a good weekend.

The following is a record of what was done during the last working week and a forecast of the Next week.....

Initial Points

Projects and Deadlines

Design

Installation Panel Build

Mater Dei Hospital PPM

Business Development

Page 3: TW@ESI 19th March 2017

New employee - Miltiadis Charalampidis (AKA Miltos) – Please join us on Linkedin

Some Points Before Starting

Shridar is finally back tomorrow and boy does he have along list of to dos

Dennis Smith has resigned from his post and will leave a void which is to be filled by me for now- till a new person fills in the position

A New employee - Francisco Rupérez Herrera (Spanish

Nationaliity) has joined us on Linkedin

Steve Azzopardi has given in his resignation as a Junior

Developer- I will soon be announcing his last working

day

Clifton will soon be going on long leave from 6/7/2017 – 18/8/2017 both days included – here too we need to plan for the void whihch will be left

Page 4: TW@ESI 19th March 2017

Projects and Deadlines

16_025_DeLaRue_OFX

50% of the machines have been commissioned by CFH

14_069_OTM Additions

Q019 AS410 – We are proceeding with works here in conjunction with Gruppo Sett in Italy- our high level target is to change over in May/June 2017

Q021_TF4- Panel is on site and installed- we have powered up the panel and started connecting and powering up MOVs

16_007_LeMeridien

We have started working on phase 1 panels – phase 1 which has to be completed by Feb 2017-

We have so far done 2 panels – we needed to achieve 5 by end of Feb 2017- so we are a little behind here- I am suggesting that a plan for when the next 3 panels may be done so as to plan resurces

16_066_Sterling_DCS_Line2

We have started some preliminary engineering here.... We will now proceed to detailed engineering

16_040_Playmobil_Factory

We are well advanced design and engineering here on MCC1 and 2 and I have started placing major orders- next will be panel build for MCC1 and 2

Page 5: TW@ESI 19th March 2017

Projects and Deadlines

16_023_GGY

We have some snags pending (Savant with Android TV, integration with Acs, under floor heating functionality) - we also have to transfer the old GGY system to the new platform

15_011- Sliema apartments

We have done most terminations and panel build is completed too. We are trying to finalise the installation and then testing and commissioning would be next... The completion date here is for March 2017DDC and DAC panels are to be installed on site – then the electrical meters and the PIRs in terraces

15_023_FM panels

15_023 Q012 [D10 Endicare 230V] - Beginning april 2017

Q004_013_D5M ASRD 110 PPA is scheduled for 30th April – we also have another scheduled for 30th Sept

16_041_RSM_Security

We need to close off here – the sooner the better

SAI needs to give a date by when ESI will be completed from all works (works pending from others excluded)

16_058_Methode

Another fast tack project Jace Based AHU control system here

This projects should be handed over by next Wednesday 23/3

Page 6: TW@ESI 19th March 2017

Projects and Deadlines

12_043_LSP

There are some points on the tenant billing application which we are tackling

13_031_CCA

We have a number of snags here , which are to be put to bed once and for all!!

The snags are centred around the AC controls and the NUOO CCTV system

14_08_Siggiewi School-

We have made a commitment to give our contractual obligation of 100 hours as follows Training/ Data gathering and back up / Preventative maintenance on hardware /Transfer of server to SHE set up at MITA/Reactive maintenance/emergency call outs/Fine tuning / re commissioning of louvers –

14_083_Interconti

We have commissioned the system with snags - we will return to site when snags are done by others-

We also have to deliver the pool panel

15_038_new_HA_Ovt and 15_026_Apap

Residence

These two home automation projects are now urgent- we need to complete all installation

We also need to start working of the software development- they are urgent and we have to perform

Page 7: TW@ESI 19th March 2017

Projects and Deadlines

12_025_SCM PH2

The last issues on the DAC for SCM PH2- IT IS NOW A PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION- SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this

13_070- SCM Lagoona Plant room

We have concluded the required installation and programming but commissioning is on hold till the client asks us to continue

13_075_Bosch_ProWatch_Genetec_Interface

The Bosch HSDK interface is well advanced and we have documented and we should shortly be expecting to go overseas to commission

Page 8: TW@ESI 19th March 2017

01 02 03 04

DesignFor the Past week we have been working on the following

OTM – Q020 Netherlocks – finalized TF3_NVC_001 & submitted to client

Playmobil HF80 – Draughting for both MCC1 and 2

Design

Page 9: TW@ESI 19th March 2017

01 02 03 04

DesignAnd next week… we will work on

Assist CCI with minor RSM Asbuilt update, in order for CCI to close-off O&M

Design

NFH – Playmobil HF80 – Complete Draughting of MCC2, gather & print labels, Print Materials list, prepare & print dimensions for Panel Build – will be complete by Tuesday 21/3/2017.

Playmobil HF80 – print Materials list & Dimensions & print labels for MCC1Playmobil HF80 – revise & re-submit MCC1 & MCC2 P&IDs

Sterling – Review Lessons Learnt, and see what is applicable for SterlingSterling DCS Line2 – Start-up meeting, Start-up design – Points List, P&IDs, Panel Design

Page 10: TW@ESI 19th March 2017

This is what the Installation team have been working on last week

Continued with commissioning at Methode

Sterling PPM (cleaning)

Installation

Testing of louvers at Siggiewi primary

Tested and labeled data cables at Le Meridien

Updated panel drawings at OTM

Page 11: TW@ESI 19th March 2017

….. And this is what is planned for next week

Tackle snags at Methode

Install outdoor cameras at RSM

CCA SISA

Installation

OVT install phonos and KNX switchesStart intruder installation at OVT

Servicing of cameras at City Gate

Page 12: TW@ESI 19th March 2017

Installation Planning

Installation

For the next 2 weeks the following is the schedule

https://calendar.google.com/calendar/embed?src=esimalta1%40gmail.com&ctz=Europe/Malta

Anyone needing scheduling of jobs for week commencing 3rd April , please adviseClint is available on 27/3- please advise for any tasks for this resource on this dayJPO is available on 27/3 and 28/3 - please advise for any tasks for this resource on this day

Page 13: TW@ESI 19th March 2017

Next week we will • Methode snags• FM Env D10_Endicare_230– This will be built by a sub

contractor• Start up MCC1

Panel Build

Panel Build

Page 14: TW@ESI 19th March 2017

Week 11PPMYearly Field devices checks, IR images & coordinated tests Mar-- E01-CC1, E02-CC1, EP1-CC1, E01-CC2, E01-CC3 Quarterly panel checks Mar -- H01-CC1, HP1-CC1, P04-CC1, P02-CC1, P03-CC1, T01-CC1, T02-CC1 E01-CC1, E02-CC1, EP1-CC1, F01-CC1, F02-CC1, F05-CC4, F05-CC5, F03-CC1, F04-CC1, F05-CC1 Weekly update of antivirus on all BMS stations

Mater Dei Maintenance

ReactiveHandling of reactive work orders OthersParticipating in weekly fire drillsTraining of new team memberQxxx_NewCPRalarmsWO-000117205926_ModifyC01-AHU1

Mater Dei Maintenance

Page 15: TW@ESI 19th March 2017

Crane Currency BMS and ELV Proposals

Actavis Solvent area Process quote

De La Rue BMS

These are the quotes the business development

team have been working on

Business Development

Page 16: TW@ESI 19th March 2017

I await all your feedback on all the ESI discussions – without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment

Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for

I urge you all to follow this blog and keep up to

date with what is happening at ESI

Lets all work to get the work done on time, on

budget and to the required quality

We need to communicate, pull the rope in the

same direction to make our projects a success

and profitable

Some Last Thoughts

Page 17: TW@ESI 19th March 2017

I wish you all a good and productive

week