1 Unique Design Concrete Preheater Tower z Preheater tower constructed of concrete with steel floors z Concrete section 105m high (35 storey building) z Additional 10m cyclone structure z Footprint 25.3m by 20.4m z 1 720 tons steel reinforcing & 9 540 m³ concrete z 1 270 tons structural steel for floors z Important to have ‘vertical’ aspect of preheater constructed when preheater parts started arriving at site z Time saving z Only achieved by utilising concrete & sliding to a special design z Cost effective (+7% saving compared to steel) z Aesthetically pleasing z Used our product

Upload: vothuy

Post on 01-Sep-2018

249 views

Category:

Documents


2 download

TRANSCRIPT

1

Unique Design Concrete Preheater Tower

Preheater tower constructed of concrete with steel floorsConcrete section 105m high (35 storey building)

Additional 10m cyclone structureFootprint 25.3m by 20.4m

1 720 tons steel reinforcing & 9 540 m³ concrete

1 270 tons structural steel for floorsImportant to have ‘vertical’ aspect of preheater constructed when preheater parts started arriving at site

Time savingOnly achieved by utilising concrete & sliding to a special design

Cost effective (+7% saving compared to steel) Aesthetically pleasing Used our product

2

In-Line Calciner Plus Six-Stage Preheater

Kiln 4.55m diameter x 54m Calciner 6.6m diameter x 27m

268oC

Cyclones 1-2: 6.9m diameter

Cyclones 3-6: 7.2m diameter

3 Air 2.5m diameter

3

Pre-Heater H2

4

Pre-Heater H2

5

Pre-Heater H3

6

Pre-Heater H4

7

Pre-Heater H5

8

Pre-Heater H6

9

Pre-Heater H7

10

Pre-Heater H8

11

Pre-Heater H9

12

Pre-Heater H9

13

1200 Metres of Piling Installed

March 2007

1.2metre diameter piles

14

Constructed Using 80 ton Slide Platform

15

16

Around the Clock Construction

17

18

19

20

Preheater Topped-Out After 58 Days

May 2007

21

Preheater Structure Dominates the Skyline

22

Mechanical Installation Began Immediately

June 2007

23

Kiln Drive Installation Kiln Pier 2

Preheater Steelwork: Level H3

Structural Steel Floor H3

24Steel Fixing in Preheater: Level H3

25MMC Clinker Cooler Frame

26

Kiln Shell Arriving on Site

27

Kiln 2 LT Substation

New Clinker Return System

Kiln 2 Cooler ESP

Burners Platform

Coal Mill Building

Clinker CoolerKiln Pier 1

New Kiln Shell Sections

August 2007

28

Riding Ring Hoisted into Position

29August 2007

30

31

32

33

34

35

36Raw Mill Building: Sept 2007

37

‘Kopanelang’ Contractors Village

Feb 2006

38

Contractors Camp Catering Facilities

39

28 New Staff Houses Built

Nov 2006

Existing Village

New Houses

40

2 Lost Time Injuries Recorded to Date

More than 2 million man

hours worked to dateMore than 2 million man

hours worked to date

41

One of PPC’s core values: ‘We assist with up-liftment in communities in which we operate’

Dwaalboom situated near three (very rural) communities Rate of unemployment in area >50%

Important to ensure maximum economic spin-off from the project into the disadvantaged Dwaalboom communities‘Labour’ component comes from these areas only

>40% of staff at site from local communityRecruitment centre built

Daily transport to & from home provided

One good meal per day at site for every worker

Focus on Local Community Involvement

Excellent labour relations between contractors & local community employeesExcellent labour relations between contractors & local community employees

Opening of Holfontein Pension Payout & Recruitment Centre (June 2006)

Batsweledi in the Community

43

Jupiter Clinker Milling Facility Upgraded

Jupiter plant commissioned 1970

Mothballed in 1998 (eight years)

Used as bag/bulk cement depot

44

Upgrade Programme at Jupiter

Environmental Issues AddressedEnclosed & de-dusted clinker storeEnclosed all dust-generating beltsOverhaul/addition of dust collectorsAutomatic doors to tippler enclosure

Improvements AffectedNew Haver & Boecker packer & Beumer palletiser All spillage eliminated Upgrade of extender-blending facility

Major RefurbishmentsAll electric motors/gearboxes overhauledOverhauled overhead crane, tippler, cement transport system etc.Plant clean up & extensive painting

45

Clinker Storage Facility Enclosed

46

Raw MillClinker Store

Kiln ESPTippler

Dust Collectors Upgraded

47

Other Projects in the Pipeline

Batsweledi project first phase of 20 year modernisation programmeBased on combination of capacity replacement & expansion

New cement milling complex under construction at Hercules plant1Mt/yr capacity Loesche vertical roller mill (3150kW)35kt clinker silo, 10kt cement silo, tippler upgrade Cost~€61mCommissioning planned for July 2009Replace two old mills, maximise product extension (~0.3Mt/yr) &balance clinker/milling capacity in Inland Region

Planned new 1.25Mt/yr factory at Riebeeck (Western Cape) Greenfields projectIn feasibility stage (in middle of EIA approval process)Capital cost estimated at ~€340mCommissioning planned for 2010/2011

Studies underway for next Inland Region expansion

48

Summary

Batsweledi PPC’s first new factory in over 20 yearsPart of PPC’s 20 year modernisation programmeMost modern South African cement factory Utilises latest technology Lowest cost producing factoryEnvironmentally friendly & energy efficientProject within budget & on timeSafety is not negotiableCommunity involvement keyOther projects planned to meet country’s future cement demandOnly 6 months to commissioning date & counting!

For ongoing project update refer PPC website: www.ppccement.co.zaFor ongoing project update refer PPC website: www.ppccement.co.za

Thank You

Port Elizabeth Cement Silo