unit processes design criteria for existing sci site ... · influent isolation gate - motorized...
TRANSCRIPT
-
Unit Processes Design Criteria for Existing SCI Site - Option A Phase 1
Design FlowsUnits Design Criteria
Average Day Flow (ADF) m3/d 2,805,204ADF x 1.5 peaking factor m3/d 4,207,806ADF x 2.0 peaking factor m3/d 5,610,408
Rapid Mix ChemicalsUnits Design Criteria
Ferric ChlorideAverage Dose mg/l 10Maximum Dose mg/l 40
PolymerAverage Dose mg/l 0.1Maximum Dose mg/l 1.0
Rapid Mix Chambers - Existing SCI PlantUnits Design Criteria
No. of Chambers (Trains) - 4Compartments Per Chambers (Each Train) - 2Size of Each Compartment (W x L x SWD) m x m x m 5 x 5 x 10Volume of Each Compartment m3 250Type of Mixer - Vertical ShaftNo. of Mixers (Total) - 8Drive - 2 speedInfluent Isolation Gate - Motorized Penstock
Rapid Mix Chambers - For Stage 2 Flows
No. of Chambers (Trains) - 2Compartments Per Chambers (Each Train) - 2Size of Each Compartment (W x L x SWD) m x m x m 3.3 x 10 x 10Volume of Each Compartment m3 330Type of Mixer - Vertical ShaftNo. of Mixers (Total) - 4Drive - 2 speedInfluent Isolation Gate - Motorized Penstock
Flocculation Tanks - Existing SCI Plant
No. of Trains - 2Units Per Train - 2 pairs in seriesCapacity Each Train m3/d 295914
591828Size Each Tank (W x L x SWD) m x m x m 7 x 64 x 8.5Volume, Each Tank m3 3808Detention Time, Each Tank min 25.4
min 6.35Type of Flocculator - Air*Aeration System
Air Supply System m3/min/m 0.47 (minimum)Length of each train m 240Total of air required, each train m3/min 115
No. of Blowers unit 6Each Stage duty 2
standby 1Blower Size, Each m3/min 60 (minimum)Discharge Pressure mbar 800 (minimum)Type of Blower - Positive DisplacementInstalled Power, Each kW 132Type of Diffusers - Tube-type rubber membrane
Appendix FAppendix F.xls/SCI Option A Phase 1 1 of 4
-
Type of Diffuser Head - Swing-type with control valve
Flocculation Tanks - For Stage 2 Flows
No. of Trains - 2Units Per Train - 1Capacity Each Train m3/d 298917 @ ADF
597834 @ PDFSize Each Tank (W x L x SWD) m x m x m 7 x 58.2 x 10Volume, Each Tank m3 4074Detention Time, Each Tank min 19.6 @ ADF
9.8 @ PDFType of Flocculator - Air*
* Proposed flocculators would connect into the existing flocculation air supply system
Sedimentation Tank System - For Existing SCI and Stage 2 Flows
Process with chemicalType of Tank Double trayNo. of Tanks
New - 14Total - 52
Capacity Each Tank @ ADF m3/d 54361Tank Dimensions
Effective LengthUpper Tank m 56Lower Tank m 60.5Width (upper and lower) m 7Liquid Depth (upper and lower) m 3.5 +/-Effective Surface Area, Each Tank m2 815.5Total Surface Area (New Tanks) m2 11417Total Surface Area (All Tanks) m2 42406
Volume Each Tank m3 2855Tank Detention Time @ ADF hrs 1.27Surface Loading Rates
All Basins (design value = 66.7) @ ADF m3/m2/d 66.24 tanks out of service @ ADF m3/m2/d 71.7All Basins @ 1.5X m3/m2/d 99.2All Basins @ 2.0X m3/m2/d 132.3
Weir Length/Tank m 12.5Weir Loading Rate m3/m/d 4316Sludge Generated (Total) t/d 717
Sludge Collection MechanismType of Mechanism Chain and flightChain Material Non-metallicNo. of Flight Scraper Mechanisms 104
Sludge Solids Concentration % 2-4 (+/-)Scum Collection Mechanism
Type of Mechanism Tilting WeirNo. of Scum Mechanisms 104
Appendix FAppendix F.xls/SCI Option A Phase 1 2 of 4
-
New Influent Pumping Station
Peak Phase 2 Flow m3/s 25.2Type -Number (Duty, Standby) - 6 , 2Power hpDrive - VFD
Disinfection Facilities
Chlorine Contact TankContact Time
at maximum flow min 13 (exclude 7min in effluent tunnel)at ADF min 20 (exclude 10min in effluent tunnel)
No. of Trains - 4Volume of each Train m3 10,100
Chlorine On-site GenerationSeawater pumping station
Type - Dry WellNumber (Duty, Standby) - 2 , 1Flow Rate l/s 243
Electrochlorination PlantNumber (Duty, Standby) - 4 , 1Production Rate kg Cl/hr 875
Sodium Bisulphite Storage Tank
Number of Storage Tanks (Duty, Standby) 1 , 1Height m 10Diameter m 5
Total Storage Time Provided day 7
Sludge Processing Facilities
Sludge Quantities
Primary SludgeQuantity kg DS/d 716,753Volume m3/d 23,892Percent Solids % 3
Liquid Sludge Storage
Existing Storage Tanks - 5Volume of Tanks (each) m3 2,400Total Tank Volume m3 12,000
Additional Storage Tanks - 1Volume of Tanks (each) m3 2,400Total Tank Volume m3 2,400
Total Storage Provided m3 14,400Total Storage Time Provided hrs 14.47
Sludge Dewatering
Total Volume m3/d 23,892Sludge Flow m3/hr 996Existing Centrifuges - 10Existing Centrifuge Capacity m3/hr 80
Total Required CentrifugesOperating - 12
Appendix FAppendix F.xls/SCI Option A Phase 1 3 of 4
-
Standby - 4
Additional Centrifuges - 6
Additional Sludge Feed Pumps - 8
Sludge Cake Storage Silos
Quantity of Dry Sludge Solids kg DS/d 607,630Sludge Cake Solids Percent % 30Quantity of Dewatered Wet Sludge Solids kg WS/d 2,025,433Sludge Density 1.075Volume of Dewatered Sludge per Day m3/d 1,884Desired Cake Storage Time hrs 13Volume of Cake Storage Required m3 1,021Number of Existing Silos (Duty, Standy) 4 , 1Volume of Existing Silos
Each m3 200Total m3 800
Number of Additional Silos - 2 , 0Volume of Additional Silos
Each m3 200Total m3 400
Actual Cake Storage Time hrs 15.29
Sludge Cake Transfer Containers
Tonnes of Wet Solids to be Hauled t WS/d 2,025Capacity of Each Container tonnes 14.5Number of Containers per day 140Total Number of Containers Required (5 Sets) - 698Existing Containers - 400Additional Containers Required - 298
Filtered Effluent Tunnel
Number of Conduits - 1Diameter m 7Velocity
ADF m/s 0.8ADF x 1.5 peaking factor m/s 1.3ADF x 2.0 peaking factor m/s 1.7
Final Effluent Conduit
Number of Conduits - 2Dimension (each) mxm 4.3 x 4.3Velocity
ADF m/s 0.9ADF x 1.5 peaking factor m/s 1.3ADF x 2.0 peaking factor m/s 1.7
Appendix FAppendix F.xls/SCI Option A Phase 1 4 of 4
-
Unit Processes Design Criteria for PRT Site - Option A Phase 2
Conduits from SCI to PRT Site
Number of Conduits - 2Dimensions m x m 4 x 4Velocity
ADF m/s 1.0ADF x 1.5 peaking factor m/s 1.5ADF x 2.0 peaking factor m/s 2.0
Conduits Feeding BOD Filters
Number of Conduits - 4Dimensions m x m 2.5 x 2.5Velocity
ADF + Backwash m/s 1.51.5X Flow + Backwash m/s 2.12.0X Flow + Backwash m/s 2.8
BOD Filters
Design Parameters @ ADFOrganic Loading Rate kg/m3-media-d 5.4Hydraulic Loading Rate m3/m2/hr 10.9
No. of TanksRequired - 100Total Provided - 120Allowance for Redundancy - 20
Filter Effective DimensionsLength m 12Width m 9Media Depth m 4Effective Surface Area
Each Filter m2 108Total m2 12960
Media Volume (each filter)Each Filter m3 432Total m3 51840
Media Type - expanded clayMedia Size mm 3.5 - 6Weir Length m 4.1
Tank Wall Thickness m 1
Hydraulic Loading RatesADF + Backwash (All Tanks) m3/m2/hr 10.5ADF + Backwash (4 out of service) m3/m2/hr 10.81.5X Flow + Backwash (All Tanks) m3/m2/hr 15.02X Flow + Backwash (All Tanks) m3/m2/hr 19.5
BOD Filters Effluent Conduits
Type of Channel - TaperedNumber of Channels - 8Width m 2Depth (varies) m 0.17 - 2.5Velocity (at largest channel area)
Appendix FAppendix F.xls/SCI Option A Phase 2 1 of 7
-
ADF + Backwash m/s 0.941.5X Flow + Backwash m/s 1.32.0X Flow + Backwash m/s 1.75
Nitrification Filters Influent Conduits
Type of Channel - TaperedNumber of Channels - 8Width m 2Depth (varies) m 0.15 - 2.5Velocity (at largest channel area)
ADF + Backwash m/s 0.941.5X Flow + Backwash m/s 1.32.0X Flow + Backwash m/s 1.75
Nitrification Filters
Design Parameters @ ADFOrganic Loading Rate kg/m3-media-d 1.4Hydraulic Loading Rate m3/m2/hr 9.3
No. of TanksRequired - 117Total Provided - 136Allowance for Redundancy - 19
Filter Effective DimensionsLength m 12Width m 9Media Depth m 4Effective Surface Area
Each Filter m2 108Total m2 14688
Media Volume (each filter)Each Filter m3 432Total m3 58752
Media Type - expanded clayMedia Size mm 2.5 - 5Weir Length m 4.1
Tank Wall Thickness m 1
Hydraulic Loading RatesADF + Backwash (All Tanks) m3/m2/hr 9.23ADF + Backwash (4 out of service) m3/m2/hr 9.511.5X Flow + Backwash (All Tanks) m3/m2/hr 13.22X Flow + Backwash (All Tanks) m3/m2/hr 17.2
Nitrification Filters Effluent Conduits
Type of Channel - TaperedNumber of Channels - 8Width m 2Depth (varies) m 0.15 - 2.5Velocity (at largest channel area)
ADF + Backwash m/s 0.941.5X Flow + Backwash m/s 1.32.0X Flow + Backwash m/s 1.75
Appendix FAppendix F.xls/SCI Option A Phase 2 2 of 7
-
Backwash Channel/Wet Well
Number of Channels - 1Dimensions (w x h) m x m 6.4 x 6.4Velocity
ADF + Backwash m/s 0.921.5X Flow + Backwash m/s 1.32.0X Flow + Backwash m/s 1.7
Denitrification Feed Channel
Number of Channels - 1Dimensions (w x h) m x m 6.1 x 6.1Velocity (BW water has been removed)
ADF m/s 0.871.5X Flow m/s 1.32.0X Flow m/s 1.74
Denitrification Filters
Design Parameters @ ADFOrganic Loading Rate kg/m3-media-d 2.6Hydraulic Loading Rate m3/m2/hr 17.7
No. of TanksRequired - 61Total Provided - 73Allowance for Redundancy - 12
Filter Effective DimensionsLength m 12Width m 9Media Depth m 3Effective Surface Area
Each Filter m2 108Total m2 7884
Media Volume (each filter)Each Filter m3 324Total m3 23652
Media Type - expanded clayMedia Size mm 4 - 8Weir Length m 4.1
Tank Wall Thickness m 1
Hydraulic Loading RatesADF + Backwash (All Tanks) m3/m2/hr 17.2ADF + Backwash (4 out of service) m3/m2/hr 18.21.5X Flow + Backwash (All Tanks) m3/m2/hr 24.62X Flow + Backwash (All Tanks) m3/m2/hr 32.0
Conduit to Effluent Pump Station
Number of Conduits - 2Dimensions (w x h) m x m 3.9 x 3.9Velocity
ADF m/s 1.11.5X Flow m/s 1.62.0X Flow m/s 2.1
Effluent Pump Station
Appendix FAppendix F.xls/SCI Option A Phase 2 3 of 7
-
Type of Pump - vertical mixed flowNumber of Pumps - 14Capacity of Each Pump m3/s 4.7Total Dynamic Head m 30Number of Pump Station Effluent Channels - 2Effluent Channel (w x h) m x m 4.5 x 4.5Velocity
ADF m/s 0.801.5X Flow m/s 1.22.0X Flow m/s 1.6
Filter Backwash System
BOD FiltersBackwash Air Flow Rate Nm/hr 95Backwash Water Flow Rate m3/m2/hr 35Duration of Backwash Water Flow min 25
Nitrification FiltersBackwash Air Flow Rate Nm/hr 75Backwash Water Flow Rate m3/m2/hr 20Duration of Backwash Water Flow min 25
Denitrification FiltersBackwash Air Flow Rate Nm/hr 95Backwash Water Flow Rate m3/m2/hr 35Duration of Backwash Water Flow min 25
Backwash Flow (Based on flows and durations abovem3/d 365,175Backwash Flow (16% of ADF) m3/d 448,833* Used 16% of ADF to be conservative
Backwash PumpsType -Number (Duty, Standby) - 6 , 4Power hp 500Drive - VFDMax Flow (each pump) m3/s 1
Waste Backwash System Rapid Mix Chambers
No. of Chambers (Trains) - 4Compartments Per Chambers (Each Train) - 1Size of Each Compartment (W x H x SWD) m x m x m 6.1 x 6.1 x 10Volume of Each Compartment m3 372Type of Mixer Vertical Shaft
Waste Backwash System Flocculation Tanks
No. of Trains - 4Units Per Train - 1Size Each Tank (W x L x SWD) m x m x m 6.1 x 26.3 x 8.5Volume, Each Tank m3 1364Volume, Total m3 5455Detention Time, Each Train min 17.5Type of Flocculator - Air
Backwash Chemically Enhanced Sedimentation (BCES) Tanks
Process with chemical
Appendix FAppendix F.xls/SCI Option A Phase 2 4 of 7
-
Type of Tank Double trayNo. of Tanks - 10Tank Dimensions
Effective LengthUpper Tank m 51.62Lower Tank m 56.15Width (upper and lower) m 7Liquid Depth (upper and lower) m 3.5 +/-Effective Surface Area, Each Tank m2 754.6Total Surface Area (All Tanks) m2 7546
Volume Each Tank m3 2641Tank Detention Time at Backwash Flow of 16% hrs 1.41Surface Loading Rate
All Basins (design value = 55.7) m3/m2/d 59.52 tanks out of service m3/m2/d 74.3
Weir Length/Tank m 12.5Weir Loading Rate m3/m/d 3591Sludge Generated (Total) t/d 263
Sludge Collection MechanismType of Mechanism Chain and flightChain Material Non-metallicNo. of Flight Scraper Mechanisms 104
Sludge Solids Concentration % 2 (+/-)Scum Collection Mechanism
Type of Mechanism Tilting WeirNo. of Scum Mechanisms 104
Waste Backwash Pumps
Type -Number (Duty, Standby) - 6 , 4Power hp 500Drive - VFDMax Flow (each pump) m3/s 1
BOD and Nitrification Air Supply System
Type -Number (Duty, Standby) - 5 , 2Total Power hp 3200Drive - VFDTotal Maximum Flow scfm 63000
BAF HVAC SystemBlowers Required (1 per 24 BAF units) - 14Power hp 50Air Changes per hour - 6Volume of Ventilated space m3 55,650
Appendix FAppendix F.xls/SCI Option A Phase 2 5 of 7
-
Methanol Storage
Methanol Required m3/d 568Methanol Purity (as delivered) % 96Source of Motive Water - Nitrified EffluentDilution for Transfer - 20:1Number of Tanks - 5Tank Size
Diameter m 3.5Length m 13
Volume m3 125Storage Provided d 3
Fine Screen
Type - BandNumber - 18Height m 8.45Headloss (clean water) mm 97
Sludge Processing Facilities
Sludge Quantities
Primary SludgeQuantity kg DS/d 716,753Volume m3/d 23,892Percent Solids % 3
BAF SludgeQuantity kg DS/d 278,031Volume m3/d 14,048Percent Solids % 1.98
Total SludgeQuantity kg DS/d 994,784Volume m3/d 37,940
Liquid Sludge Storage
Existing Storage Tanks - 5Volume of Tanks (each) m3 2,400Total Tank Volume m3 12,000
Storage Tanks for Phase 1 - 1Volume of Tanks (each) m3 2,400Total Tank Volume m3 2,400
Additional Storage Tanks - 2Volume of Tanks (each) m3 2,400Total Tank Volume m3 4,800
Total Storage Provided m3 19,200Total Storage Time Provided hrs 12.15
Sludge Dewatering
Total Volume m3/d 37,940Sludge Flow m3/hr 1,581Existing Centrifuges - 10Centrifuge for Phase 1 - 6
Appendix FAppendix F.xls/SCI Option A Phase 2 6 of 7
-
Existing Centrifuge Capacity m3/hr 80
Total Required CentrifugesOperating - 20Standby - 2
Additional Centrifuges - 6
Additional Sludge Feed Pumps - 6
Sludge Cake Storage Silos
Quantity of Dry Sludge Solids kg DS/d 895,306Sludge Cake Solids Percent % 30Quantity of Dewatered Wet Sludge Solids kg WS/d 2,984,353Sludge Density 1.075Volume of Dewatered Sludge per Day m3/d 2,776Desired Cake Storage Time hrs 13Volume of Cake Storage Required m3 1,504Number of Existing Silos (Duty, Standy) 5 , 0Number of Silos for Phase 1 (Duty, Standy) 2 , 0Volume of Existing & Phase 1 Silos
Each m3 200Total m3 1400
Number of Additional Silos - 1 , 0Volume of Additional Silos
Each m3 200Total m3 200
Actual Cake Storage Time hrs 13.83
Sludge Cake Transfer Containers
Tonnes of Wet Solids to be Hauled t WS/d 2,984Capacity of Each Container tonnes 14.5Number of Containers per day 206Total Number of Containers Required (5 Sets) - 1029Existing Containers - 400Containers for Phase I - 298Additional Containers Required - 331
Appendix FAppendix F.xls/SCI Option A Phase 2 7 of 7
-
Unit Processes Design Criteria for Existing SCI Site - Option B Phase 1
Design FlowsUnits Design Criteria
Average Day Flow (ADF) m3/d 2,207,369ADF x 1.5 peaking factor m3/d 3,311,054ADF x 2.0 peaking factor m3/d 4,414,738
Rapid Mix ChemicalsUnits Design Criteria
Ferric ChlorideAverage Dose mg/l 10Maximum Dose mg/l 40
PolymerAverage Dose mg/l 0.1Maximum Dose mg/l 1.0
Rapid Mix Chambers - Existing SCI PlantUnits Design Criteria
No. of Chambers (Trains) - 4Compartments Per Chambers (Each Train) - 2Size of Each Compartment (W x H x SWD) m x m x m 5 x 5 x 10Volume of Each Compartment m3 250Type of Mixer - Vertical ShaftNo. of Mixers (Total) - 8Drive - 2 speedInfluent Isolation Gate - Motorized Penstock
Flocculation Tanks - Existing SCI Plant
No. of Trains - 2Units Per Train - 2 pairs in seriesCapacity Each Train m3/d 295914
591828Size Each Tank (W x L x SWD) m x m x m 7 x 64 x 8.5Volume, Each Tank m3 3808Detention Time, Each Tank min 25.4
min 6.35Type of Flocculator - Air*Aeration System
Air Supply System m3/min/m 0.47 (minimum)Length of each train m 240Total of air required, each train m3/min 115
No. of Blowers unit 6Each Stage duty 2
standby 1Blower Size, Each m3/min 60 (minimum)Discharge Pressure mbar 800 (minimum)Type of Blower - Positive DisplacementInstalled Power, Each kW 132Type of Diffusers - Tube-type rubber membraneType of Diffuser Head - Swing-type with control valve
Appendix FAppendix F.xls/SCI Option B Phase 1 1 of 4
-
Sedimentation Tank System - For Existing SCI and Future Flows
Process with chemicalType of Tank Double trayNo. of Tanks
New - 6Total - 44
Capacity Each Tank @ ADF m3/d 54361Tank Dimensions
Effective LengthUpper Tank m 56Lower Tank m 60.5Width (upper and lower) m 7Liquid Depth (upper and lower) m 3.5 +/-Effective Surface Area, Each Tank m2 815.5Total Surface Area (New Tanks) m2 4893Total Surface Area (All Tanks) m2 35882
Volume Each Tank m3 2855Tank Detention Time @ ADF hrs 1.37Surface Loading Rates
All Basins (design value = 66.7) @ ADF m3/m2/d 61.54 tanks out of service @ ADF m3/m2/d 67.7All Basins @ 1.5X m3/m2/d 92.3All Basins @ 2.0X m3/m2/d 123.0
Weir Length/Tank m 12.5Weir Loading Rate m3/m/d 4013Sludge Generated (Total) t/d 517
Sludge Collection MechanismType of Mechanism Chain and flightChain Material Non-metallicNo. of Flight Scraper Mechanisms 104
Sludge Solids Concentration % 2-4 (+/-)Scum Collection Mechanism
Type of Mechanism Tilting WeirNo. of Scum Mechanisms 104
New Influent Pumping Station
Peak Phase 2 Flow m3/s 11.35Type -Number (Duty, Standby) - 6 , 2Power hpDrive - VFD
Disinfection Facilities
Chlorine Contact TankContact Time
at maximum flow min 13 (exclude 7min in effluent tunnel)at ADF min 20 (exclude 10min in effluent tunnel)
No. of Trains - 4Volume of each Train m3 8,170
Chlorine On-site GenerationSeawater pumping station
Type - Dry WellNumber (Duty, Standby) - 2 , 1Flow Rate l/s 192
Appendix FAppendix F.xls/SCI Option B Phase 1 2 of 4
-
Electrochlorination PlantNumber (Duty, Standby) - 3 , 1Production Rate kg Cl/hr 920
Sodium Bisulphite Storage Tank
Number of Storage Tanks (Duty, Standby) 1 , 1Height m 8Diameter m 4.6
Total Storage Time Provided day 7
Sludge Processing Facilities
Sludge Quantities
Primary SludgeQuantity kg DS/d 561,440Volume m3/d 18,715Percent Solids % 3
Liquid Sludge Storage
Existing Storage Tanks - 5Volume of Tanks (each) m3 2,400Total Tank Volume m3 12,000
Additional Storage Tanks - 0Volume of Tanks (each) m3 2,400Total Tank Volume m3 0
Total Storage Provided m3 12,000Total Storage Time Provided hrs 15.39
Sludge Dewatering
Total Volume m3/d 18,715Sludge Flow m3/hr 780Existing Centrifuges - 10Existing Centrifuge Capacity m3/hr 80
Total Required CentrifugesOperating - 10Standby - 3
Additional Centrifuges - 3
Additional Sludge Feed Pumps - 6
Sludge Cake Storage Silos
Quantity of Dry Sludge Solids kg DS/d 478,134Sludge Cake Solids Percent % 30Quantity of Dewatered Wet Sludge Solids kg WS/d 1,593,780Sludge Density 1.075Volume of Dewatered Sludge per Day m3/d 1,483Desired Cake Storage Time hrs 13Volume of Cake Storage Required m3 803Number of Existing Silos (Duty, Standy) 4 , 1Volume of Existing Silos
Each m3 200
Appendix FAppendix F.xls/SCI Option B Phase 1 3 of 4
-
Total m3 800Number of Additional Silos - 1 , 0Volume of Additional Silos
Each m3 200Total m3 200
Actual Cake Storage Time hrs 16.19
Sludge Cake Transfer Containers
Tonnes of Wet Solids to be Hauled t WS/d 1,594Capacity of Each Container tonnes 14.5Number of Containers per day 110Total Number of Containers Required (5 Sets) - 550Existing Containers - 400Additional Containers Required - 150
Filtered Effluent Tunnel
Number of Conduits - 1Diameter m 6Velocity
ADF m/s 0.9ADF x 1.5 peaking factor m/s 1.4ADF x 2.0 peaking factor m/s 1.8
Final Effluent Conduit
Number of Conduits - 2Dimension (each) mxm 4 x 4Velocity
ADF m/s 0.8ADF x 1.5 peaking factor m/s 1.2ADF x 2.0 peaking factor m/s 1.6
Appendix FAppendix F.xls/SCI Option B Phase 1 4 of 4
-
Unit Processes Design Criteria for PRT Site - Option B Phase 2
Conduits from SCI to PRT Site
Number of Conduits - 2Dimensions m x m 3.5 x 3.5Velocity
ADF m/s 1.0ADF x 1.5 peaking factor m/s 1.6ADF x 2.0 peaking factor m/s 2.1
Conduits Feeding BOD Filters
Number of Conduits - 4Dimensions m x m 2.5 x 2.5Velocity
ADF + Backwash m/s 1.21.5X Flow + Backwash m/s 1.72.0X Flow + Backwash m/s 2.2
BOD Filters
Design Parameters @ ADFOrganic Loading Rate kg/m3-media-d 5.4Hydraulic Loading Rate m3/m2/hr 10.9
No. of TanksRequired - 91Total Provided - 110Allowance for Redundancy - 19
Filter Effective DimensionsLength m 12Width m 9Media Depth m 4Effective Surface Area
Each Filter m2 108Total m2 11880
Media Volume (each filter)Each Filter m3 432Total m3 47520
Media Type - expanded clayMedia Size mm 3.5 - 6Weir Length m 4.1
Tank Wall Thickness m 1
Hydraulic Loading RatesADF + Backwash (All Tanks) m3/m2/hr 9.0ADF + Backwash (4 out of service) m3/m2/hr 9.31.5X Flow + Backwash (All Tanks) m3/m2/hr 12.92X Flow + Backwash (All Tanks) m3/m2/hr 16.7
Appendix FAppendix F.xls/SCI Option B Phase 2 1 of 7
-
BOD Filters Effluent Conduits
Type of Channel - TaperedNumber of Channels - 8Width m 2Depth (varies) m 0.17 - 2.5Velocity (at largest channel area)
ADF + Backwash m/s 0.741.5X Flow + Backwash m/s 1.062.0X Flow + Backwash m/s 1.38
Nitrification Filters Influent Conduits
Type of Channel - TaperedNumber of Channels - 8Width m 2Depth (varies) m 0.15 - 2.5Velocity (at largest channel area)
ADF + Backwash m/s 0.741.5X Flow + Backwash m/s 1.062.0X Flow + Backwash m/s 1.38
Nitrification Filters
Design Parameters @ ADFOrganic Loading Rate kg/m3-media-d 1.4Hydraulic Loading Rate m3/m2/hr 9.3
No. of TanksRequired - 106Total Provided - 122Allowance for Redundancy - 16
Filter Effective DimensionsLength m 12Width m 9Media Depth m 4Effective Surface Area
Each Filter m2 108Total m2 13176
Media Volume (each filter)Each Filter m3 432Total m3 52704
Media Type - expanded clayMedia Size mm 2.5 - 5Weir Length m 4.1
Tank Wall Thickness m 1
Hydraulic Loading RatesADF + Backwash (All Tanks) m3/m2/hr 8.1ADF + Backwash (4 out of service) m3/m2/hr 8.41.5X Flow + Backwash (All Tanks) m3/m2/hr 11.62X Flow + Backwash (All Tanks) m3/m2/hr 15.1
Appendix FAppendix F.xls/SCI Option B Phase 2 2 of 7
-
Nitrification Filters Effluent Conduits
Type of Channel - TaperedNumber of Channels - 8Width m 2Depth (varies) m 0.15 - 2.5Velocity (at largest channel area)
ADF + Backwash m/s 0.741.5X Flow + Backwash m/s 1.062.0X Flow + Backwash m/s 1.38
Backwash Channel/Wet Well
Number of Channels - 1Dimensions (w x h) m x m 6.4 x 6.4Velocity
ADF + Backwash m/s 0.721.5X Flow + Backwash m/s 1.042.0X Flow + Backwash m/s 1.35
Denitrification Feed Channel
Number of Channels - 1Dimensions (w x h) m x m 6.1 x 6.1Velocity (BW water has been removed)
ADF m/s 0.691.5X Flow m/s 1.032.0X Flow m/s 1.37
Denitrification Filters
Design Parameters @ ADFOrganic Loading Rate kg/m3-media-d 2.6Hydraulic Loading Rate m3/m2/hr 17.7
No. of TanksRequired - 56Total Provided - 64Allowance for Redundancy - 8
Filter Effective DimensionsLength m 12Width m 9Media Depth m 3Effective Surface Area
Each Filter m2 108Total m2 6912
Media Volume (each filter)Each Filter m3 324Total m3 20736
Media Type - expanded clayMedia Size mm 4 - 8Weir Length m 4.1
Tank Wall Thickness m 1
Hydraulic Loading RatesADF + Backwash (All Tanks) m3/m2/hr 15.4ADF + Backwash (4 out of service) m3/m2/hr 16.51.5X Flow + Backwash (All Tanks) m3/m2/hr 22.12X Flow + Backwash (All Tanks) m3/m2/hr 28.7
Conduit to Effluent Pump Station
Number of Conduits - 2Dimensions (w x h) m x m 3.9 x 3.9Appendix FAppendix F.xls/SCI Option B Phase 2 3 of 7
-
VelocityADF m/s 0.841.5X Flow m/s 1.262.0X Flow m/s 1.68
Effluent Pump Station
Type of Pump - vertical mixed flowNumber of Pumps - 14Capacity of Each Pump m3/s 4.7Total Dynamic Head m 30Number of Pump Station Effluent Channels - 2Effluent Channel (w x h) m x m 4.5 x 4.5Velocity
ADF m/s 0.631.5X Flow m/s 0.952.0X Flow m/s 1.26
Filter Backwash System
BOD FiltersBackwash Air Flow Rate Nm/hr 95Backwash Water Flow Rate m3/m2/hr 35Duration of Backwash Water Flow min 25
Nitrification FiltersBackwash Air Flow Rate Nm/hr 75Backwash Water Flow Rate m3/m2/hr 20Duration of Backwash Water Flow min 25
Denitrification FiltersBackwash Air Flow Rate Nm/hr 95Backwash Water Flow Rate m3/m2/hr 35Duration of Backwash Water Flow min 25
Backwash Flow (Based on flows and durations above) m3/d 291,150Backwash Flow (16% of ADF) m3/d 353,179* Used 16% of ADF to be conservative
Appendix FAppendix F.xls/SCI Option B Phase 2 4 of 7
-
Backwash PumpsType -Number (Duty, Standby) - 6 , 4Power hp 500Drive - VFDMax Flow (each pump) m3/s 1
Waste Backwash System Rapid Mix Chambers
No. of Chambers (Trains) - 4Compartments Per Chambers (Each Train) - 1Size of Each Compartment (W x H x SWD) m x m x m 6.1 x 6.1 x 10Volume of Each Compartment m3 372Type of Mixer Vertical Shaft
Waste Backwash System Flocculation Tanks
No. of Trains - 4Units Per Train - 1Size Each Tank (W x L x SWD) m x m x m 6.1 x 26.3 x 8.5Volume, Each Tank m3 1364Volume, Total m3 5456Detention Time, Each Train min 22.2Type of Flocculator - Air
Backwash Chemically Enhanced Sedimentation (BCES) Tanks
Process with chemicalType of Tank Double trayNo. of Tanks - 8Tank Dimensions
Effective LengthUpper Tank m 51.62Lower Tank m 56.15Width (upper and lower) m 7Liquid Depth (upper and lower) m 3.5 +/-Effective Surface Area, Each Tank m2 754.6Total Surface Area (All Tanks) m2 6036.8
Volume Each Tank m3 2641Tank Detention Time at Backwash Flow of 16% hrs 1.79Surface Loading Rate
All Basins (design value = 55.7) m3/m2/d 58.52 tanks out of service m3/m2/d 78.0
Weir Length/Tank m 12.5Weir Loading Rate m3/m/d 3532Sludge Generated (Total) t/d 157
Sludge Collection MechanismType of Mechanism Chain and flightChain Material Non-metallicNo. of Flight Scraper Mechanisms 104
Sludge Solids Concentration % 2 (+/-)Scum Collection Mechanism
Type of Mechanism Tilting WeirNo. of Scum Mechanisms 104No. of Scum Mechanisms 104
Appendix FAppendix F.xls/SCI Option B Phase 2 5 of 7
-
Waste Backwash Pumps
Type -Number (Duty, Standby) - 6 , 4Power hp 500Drive - VFDMax Flow (each pump) m3/s 1
BOD and Nitrification Air Supply System
Type -Number (Duty, Standby) - 5 , 2Total Power hp 3200Drive - VFDTotal Maximum Flow scfm 63000
BAF HVAC SystemBlowers Required (1 per 24 BAF units) - 14Power hp 50Air Changes per hour - 6Volume of Ventilated space m3 55,650
Methanol Storage
Methanol Required m3/d 455Methanol Purity (as delivered) % 96Source of Motive Water - Nitrified EffluentDilution for Transfer - 20:1Number of Tanks - 4Tank Size
Diameter m 3.5Length m 13
Volume m3 125Storage Provided d 3
Fine Screen
Type - BandNumber - 15Height m 8.45Headloss (clean water) mm 97
Sludge Processing Facilities
Sludge Quantities
Primary SludgeQuantity kg DS/d 561,440Volume m3/d 18,715Percent Solids % 3
BAF SludgeQuantity kg DS/d 197,546Volume m3/d 9,982Percent Solids % 1.98
Total SludgeQuantity kg DS/d 758,986Volume m3/d 28,697
Liquid Sludge Storage
Existing Storage Tanks - 5Volume of Tanks (each) m3 2,400Total Tank Volume m3 12,000
Appendix FAppendix F.xls/SCI Option B Phase 2 6 of 7
-
Storage Tanks for Phase 1 - 0Volume of Tanks (each) m3 2,400Total Tank Volume m3 0
Additional Storage Tanks - 2Volume of Tanks (each) m3 2,400Total Tank Volume m3 4,800
Total Storage Provided m3 16,800Total Storage Time Provided hrs 14.05
Sludge Dewatering
Total Volume m3/d 28,697Sludge Flow m3/hr 1,196Existing Centrifuges - 10Centrifuge for Phase 1 - 3Existing Centrifuge Capacity m3/hr 80
Total Required CentrifugesOperating - 15Standby - 1
Additional Centrifuges - 3
Additional Sludge Feed Pumps - 4
Sludge Cake Storage Silos
Quantity of Dry Sludge Solids kg DS/d 683,087Sludge Cake Solids Percent % 30Quantity of Dewatered Wet Sludge Solids kg WS/d 2,276,957Sludge Density 1.075Volume of Dewatered Sludge per Day m3/d 2,118Desired Cake Storage Time hrs 13Volume of Cake Storage Required m3 1,147Number of Existing Silos (Duty, Standy) 4 , 1Number of Silos for Phase 1 (Duty, Standy) 1 , 0Volume of Existing & Phase 1 Silos
Each m3 200Total m3 1000
Number of Additional Silos - 1 , 0Volume of Additional Silos
Each m3 200Total m3 200
Actual Cake Storage Time hrs 13.60
Sludge Cake Transfer Containers
Tonnes of Wet Solids to be Hauled t WS/d 2,277Capacity of Each Container tonnes 14.5Number of Containers per day 157Total Number of Containers Required (5 Sets) - 785Existing Containers - 400Containers for Phase I - 150Additional Containers Required - 235
Appendix FAppendix F.xls/SCI Option B Phase 2 7 of 7
-
Unit Processes Design Criteria for Lamma Island - Option B Phase I
Design FlowsUnits Design Criteria
Average Day Flow (ADF) m3/d 597,834ADF x 1.5 peaking factor m3/d 896,751ADF x 2.0 peaking factor m3/d 1,195,668
Rapid Mix ChemicalsUnits Design Criteria
Ferric ChlorideAverage Dose mg/l 10Maximum Dose mg/l 40
PolymerAverage Dose mg/l 0.1Maximum Dose mg/l 1.0
Rapid Mix ChambersUnits Design Criteria
No. of Chambers (Trains) - 2Compartments Per Chambers (Each Train) - 2Size of Each Compartment (W x H x SWD) m x m x m 7 x 5.7 x 10Volume of Each Compartment m3 399Type of Mixer - Vertical ShaftNo. of Mixers (Total) - 4Drive - 2 speedInfluent Isolation Gate - Motorized Penstock
Flocculation Tanks
No. of Trains - 2Units Per Train - 2Total No. of Tanks - 4Size Each Tank (W x L x SWD) m x m x m 11.8 x 33.1 x 9Volume, Each Tank m3 3515.2Type of Flocculator - AirAeration System
Air Supply System m3/min/m 0.47 (minimum)Length of each train m 33.1Total air required, each train m3/min 15.6
Type of Blower - Positive DisplacementType of Diffusers - Tube-type rubber membraneType of Diffuser Head - Swing-type with control valve
Sedimentation Tank System
Process with chemicalType of Tank Double trayNo. of Tanks
Total - 20Capacity Each Tank @ ADF m3/d 28789Tank Dimensions
Effective Length (Upper and Lower) m 42
Appendix FAppendix F.xls/Lamma Option B Phase 1 1 of 3
-
Width (Upper and Lower) m 7Depth (Upper and Lower) m 3.7Effective Surface Area, Each Tank m2 588Total Surface Area (All Tanks) m2 11760
Volume Each Tank m3 2175.6Tank Detention Time @ ADF hrs 1.75Surface Loading Rates
All Basins (design value = 66.7) @ ADF m3/m2/d 59.04 tanks out of service @ ADF m3/m2/d 73.7All Basins @ 1.5X m3/m2/d 84.4All Basins @ 2.0X m3/m2/d 109.8
Sludge Generated (Total) t/d 199
Sludge Collection MechanismType of Mechanism Chain and flightChain Material Non-metallicNo. of Flight Scraper Mechanisms 48
Sludge Solids Concentration % 2-4 (+/-)Scum Collection Mechanism
Type of Mechanism Tilting WeirNo. of Scum Mechanisms 48
Inlet Pumping Station
Peak Phase 2 Flows m3/s 13.84Type -Number (Duty, Standby) - 4, 2Power hpDrive - VFD
Disinfection Facilities
Chlorine Contact TankContact Time
at maximum flow min 13 (exclude 7min in effluent tunnel)at ADF min 20 (exclude 10min in effluent tunnel)
No. of Trains - 4Volume of each Train m3 4,050
Chlorine On-site GenerationSeawater pumping station
Type - Dry WellNumber (Duty, Standby) - 2 , 1Flow Rate l/s 52
Electrochlorination PlantNumber (Duty, Standby) - 3 , 1Production Rate kg Cl/hr 250
Sodium Bisulphite Storage Tank
Number of Storage Tanks (Duty, Standby) 1 , 1Height m 6Diameter m 4.0
Appendix FAppendix F.xls/Lamma Option B Phase 1 2 of 3
-
Total Storage Time Provided day 7
Sludge Processing Facilities
Sludge Quantities
Primary SludgeQuantity kg DS/d 212,328Volume m3/d 7,078Percent Solids % 3
Liquid Sludge Storage
Storage Tanks - 3Volume of Tanks m3 2,400Total Tank Volume m3 7,200
Total Storage Provided m3 7,200Total Storage Time Provided hrs 24.41
Sludge Dewatering
Total Volume m3/d 7,078Sludge Flow m3/hr 295Centrifuge Capacity m3/hr 80
Total Required CentrifugesOperating - 4Standby - 0
Centrifuges - 4
Sludge Feed Pumps - 6
Sludge Cake Storage Silos
Quantity of Dry Sludge Solids kg DS/d 129,496Sludge Cake Solids Percent % 30Quantity of Dewatered Wet Sludge Solids kg WS/d 431,653Sludge Density 1.075Volume of Dewatered Sludge per Day m3/d 402Desired Cake Storage Time hrs 13Volume of Cake Storage Required m3 217Number of Silos - 2 , 1Volume of Silos
Each m3 200Total m3 400
Actual Cake Storage Time hrs 23.91
Sludge Cake Transfer Containers
Tonnes of Wet Solids to be Hauled t WS/d 432Capacity of Each Container tonnes 14.5Number of Containers per day 30Total Number of Containers Required (5 Sets) - 149
Appendix FAppendix F.xls/Lamma Option B Phase 1 3 of 3
-
Unit Processes Design Criteria for Lamma Site - Option B Phase 2
BOD Filters Influent Conduits
Type of Channel - squareNumber of Channels - 2Width m 2Depth m 2Velocity (at largest channel area)
ADF + Backwash m/s 1.001.5X Flow + Backwash m/s 1.442.0X Flow + Backwash m/s 1.87
BOD Filters
Design Parameters @ ADFOrganic Loading Rate kg/m3-media-d 5.4Hydraulic Loading Rate m3/m2/hr 10.9
No. of Tanks Required - 25Total No. of Tanks Provided - 32Allowance for Redundancy - 7
Filter Effective DimensionsLength m 12Width m 9Media Depth m 4Effective Surface Area
Each Filter m2 108Total m2 3456
Media Volume (each filter)Each Filter m3 432Total m3 13824
Media Type - expanded clayMedia Size mm 3.5 - 6
Hydraulic Loading RatesADF + Backwash (All Tanks) m3/m2/hr 8.4ADF + Backwash (4 out of service) m3/m2/hr 9.51.5X Flow + Backwash (All Tanks) m3/m2/hr 12.02X Flow + Backwash (All Tanks) m3/m2/hr 15.6
BOD Filters Effluent Conduits
Type of Channel - squareNumber of Channels - 2Width m 2Depth m 2Velocity (at largest channel area)
ADF + Backwash m/s 1.001.5X Flow + Backwash m/s 1.442.0X Flow + Backwash m/s 1.87
Nitrification Filters Influent Conduits
Type of Channel - square
Appendix FAppendix F.xls/Lamma Option B Phase 2 1 of 5
-
Number of Channels - 2Width m 2Depth m 2Velocity (at largest channel area)
ADF + Backwash m/s 1.001.5X Flow + Backwash m/s 1.442.0X Flow + Backwash m/s 1.87
Nitrification Filters
Design Parameters @ ADFOrganic Loading Rate kg/m3-media-d 1.4Hydraulic Loading Rate m3/m2/hr 9.3
No. of Tanks Required - 29Total No. of Tanks Provided - 34Allowance for Redundancy - 5
Filter Effective DimensionsLength m 12Width m 9Media Depth m 4Effective Surface Area
Each Filter m2 108Total m2 3672
Media Volume (each filter)Each Filter m3 432Total m3 14688
Media Type - expanded clayMedia Size mm 2.5 - 5Weir Length m 4.1
Tank Wall Thickness m 1
Hydraulic Loading RatesADF + Backwash (All Tanks) m3/m2/hr 7.9ADF + Backwash (4 out of service) m3/m2/hr 8.81.5X Flow + Backwash (All Tanks) m3/m2/hr 11.32X Flow + Backwash (All Tanks) m3/m2/hr 14.7
Nitrification Filters Effluent Conduits
Type of Channel - squareNumber of Channels - 2Width m 2Depth m 2Velocity (at largest channel area)
ADF + Backwash m/s 1.001.5X Flow + Backwash m/s 1.442.0X Flow + Backwash m/s 1.87
Denitrification Feed Channel
Number of Channels - 2DimensionsWidth m 2
Appendix FAppendix F.xls/Lamma Option B Phase 2 2 of 5
-
Depth m 2Velocity (BW water has been removed)
ADF m/s 0.861.5X Flow m/s 1.302.0X Flow m/s 1.73
Denitrification Filters
Design Parameters @ ADFOrganic Loading Rate kg/m3-media-d 2.6Hydraulic Loading Rate m3/m2/hr 17.7
No. of Tanks Required - 15Total No. of Tanks Provided - 18Allowance for Redundancy - 3
Filter Effective DimensionsLength m 12Width m 9Media Depth m 3Effective Surface Area
Each Filter m2 108Total m2 1944
Media Volume (each filter)Each Filter m3 324Total m3 5832
Media Type - expanded clayMedia Size mm 4 - 8Weir Length m 4.1
Tank Wall Thickness m 1
Hydraulic Loading RatesADF (All Tanks) m3/m2/hr 12.8ADF (4 out of service) m3/m2/hr 16.11.5X Flow (All Tanks) m3/m2/hr 19.22X Flow (All Tanks) m3/m2/hr 25.6
Filter Backwash System
BOD FiltersBackwash Air Flow Rate Nm/hr 95Backwash Water Flow Rate m3/m2/hr 35Duration of Backwash Water Flow min 25
Nitrification FiltersBackwash Air Flow Rate Nm/hr 75Backwash Water Flow Rate m3/m2/hr 20Duration of Backwash Water Flow min 25
Denitrification FiltersBackwash Air Flow Rate Nm/hr 95Backwash Water Flow Rate m3/m2/hr 35Duration of Backwash Water Flow min 25
Backwash Flow (16% of ADF) m3/d 95,653
Appendix FAppendix F.xls/Lamma Option B Phase 2 3 of 5
-
* Used 16% of ADF to be conservative
Methanol Storage
Methanol Required m3/d 40Methanol Purity (as delivered) % 96Source of Motive Water - Nitrified EffluentDilution for Transfer - 20:1Number of Tanks - 4Tank Size
Diameter m 3.5Length m 13
Volume m3 125Storage Provided d 3
Fine Screen
Type - BandNumber - 6Height m 8.45Headloss (clean water) mm 97
Sludge Processing Facilities
Sludge Quantities
Primary SludgeQuantity kg DS/d 212,328Volume m3/d 7,078Percent Solids % 3
Liquid Sludge Storage
Storage Tanks for Phase 1 - 3Volume of Tanks (each) m3 2,400Total Tank Volume m3 7,200
Additional Storage Tanks - 0Volume of Tanks (each) m3 2,400Total Tank Volume m3 0
Total Storage Provided m3 7,200Total Storage Time Provided hrs 24.41
Sludge Dewatering
Total Volume m3/d 7,078Sludge Flow m3/hr 295Centrifuge for Phase 1 - 4Existing Centrifuge Capacity m3/hr 80
Total Required CentrifugesOperating - 4Standby - 1
Additional Centrifuges - 1
Appendix FAppendix F.xls/Lamma Option B Phase 2 4 of 5
-
Additional Sludge Feed Pumps - 0
Sludge Cake Storage Silos
Quantity of Dry Sludge Solids kg DS/d 191,095Sludge Cake Solids Percent % 30Quantity of Dewatered Wet Sludge Solids kg WS/d 636,983Sludge Density 1.075Volume of Dewatered Sludge per Day m3/d 593Desired Cake Storage Time hrs 13Volume of Cake Storage Required m3 321Number of Silos for Phase 1 (Duty, Standy) 2 , 1Volume of Existing & Phase 1 Silos
Each m3 200Total m3 400
Number of Additional Silos - 1 , 0Volume of Additional Silos
Each m3 200Total m3 200
Actual Cake Storage Time hrs 24.30
Sludge Cake Transfer Containers
Tonnes of Wet Solids to be Hauled t WS/d 637Capacity of Each Container tonnes 14.5Number of Containers per day 44Total Number of Containers Required (5 Sets) - 220Containers for Phase I - 149Additional Containers Required - 71
Appendix FAppendix F.xls/Lamma Option B Phase 2 5 of 5
-
Unit Processes Design Criteria for Lamma Island - Option Bm
Design FlowsUnits Design Criteria
Average Day Flow (ADF) m3/d 597,834ADF x 1.5 peaking factor m3/d 896,751ADF x 2.0 peaking factor m3/d 1,195,668
Rapid Mix ChemicalsUnits Design Criteria
Ferric ChlorideAverage Dose mg/l 10Maximum Dose mg/l 40
PolymerAverage Dose mg/l 0.1Maximum Dose mg/l 1.0
Rapid Mix ChambersUnits Design Criteria
No. of Chambers (Trains) - 2Compartments Per Chambers (Each Train) - 2Size of Each Compartment (W x H x SWD) m x m x m 7 x 5.7 x 10Volume of Each Compartment m3 399Type of Mixer - Vertical ShaftNo. of Mixers (Total) - 4Drive - 2 speedInfluent Isolation Gate - Motorized Penstock
Flocculation Tanks
No. of Trains - 2Units Per Train - 2Total No. of Tanks - 4Size Each Tank (W x L x SWD) m x m x m 11.8 x 33.1 x 9Volume, Each Tank m3 3515.2Type of Flocculator - AirAeration System
Air Supply System m3/min/m 0.47 (minimum)Length of each train m 33.1Total air required, each train m3/min 15.6
Type of Blower - Positive DisplacementType of Diffusers - Tube-type rubber membraneType of Diffuser Head - Swing-type with control valve
Sedimentation Tank System
Process with chemicalType of Tank Double trayNo. of Tanks
Total - 20Capacity Each Tank @ ADF m3/d 28789Tank Dimensions
Effective Length (Upper and Lower) m 42Width (Upper and Lower) m 7Depth (Upper and Lower) m 3.7Effective Surface Area, Each Tank m2 588Total Surface Area (All Tanks) m2 11760
Volume Each Tank m3 2175.6Tank Detention Time @ ADF hrs 1.75
Appendix FAppendix F.xls/Lamma Option Bm 1 of 6
-
Surface Loading RatesAll Basins (design value = 66.7) @ ADF m3/m2/d 59.04 tanks out of service @ ADF m3/m2/d 73.7All Basins @ 1.5X m3/m2/d 84.4All Basins @ 2.0X m3/m2/d 109.8
Sludge Generated (Total) t/d 199
Sludge Collection MechanismType of Mechanism Chain and flightChain Material Non-metallicNo. of Flight Scraper Mechanisms 48
Sludge Solids Concentration % 2-4 (+/-)Scum Collection Mechanism
Type of Mechanism Tilting WeirNo. of Scum Mechanisms 48
BOD Filters Influent Conduits
Type of Channel - squareNumber of Channels - 2Width m 2Depth m 2Velocity (at largest channel area)
ADF + Backwash m/s 1.001.5X Flow + Backwash m/s 1.442.0X Flow + Backwash m/s 1.87
BOD Filters
Design Parameters @ ADFOrganic Loading Rate kg/m3-media-d 5.4Hydraulic Loading Rate m3/m2/hr 10.9
No. of Tanks Required - 25Total No. of Tanks Provided - 32Allowance for Redundancy - 7
Filter Effective DimensionsLength m 12Width m 9Media Depth m 4Effective Surface Area
Each Filter m2 108Total m2 3456
Media Volume (each filter)Each Filter m3 432Total m3 13824
Media Type - expanded clayMedia Size mm 3.5 - 6
Hydraulic Loading RatesADF + Backwash (All Tanks) m3/m2/hr 8.4ADF + Backwash (4 out of service) m3/m2/hr 9.51.5X Flow + Backwash (All Tanks) m3/m2/hr 12.02X Flow + Backwash (All Tanks) m3/m2/hr 15.6
BOD Filters Effluent Conduits
Type of Channel - squareNumber of Channels - 2Width m 2
Appendix FAppendix F.xls/Lamma Option Bm 2 of 6
-
Depth m 2Velocity (at largest channel area)
ADF + Backwash m/s 1.001.5X Flow + Backwash m/s 1.442.0X Flow + Backwash m/s 1.87
Nitrification Filters Influent Conduits
Type of Channel - squareNumber of Channels - 2Width m 2Depth m 2Velocity (at largest channel area)
ADF + Backwash m/s 1.001.5X Flow + Backwash m/s 1.442.0X Flow + Backwash m/s 1.87
Nitrification Filters
Design Parameters @ ADFOrganic Loading Rate kg/m3-media-d 1.4Hydraulic Loading Rate m3/m2/hr 9.3
No. of Tanks Required - 29Total No. of Tanks Provided - 34Allowance for Redundancy - 5
Filter Effective DimensionsLength m 12Width m 9Media Depth m 4Effective Surface Area
Each Filter m2 108Total m2 3672
Media Volume (each filter)Each Filter m3 432Total m3 14688
Media Type - expanded clayMedia Size mm 2.5 - 5Weir Length m 4.1
Tank Wall Thickness m 1
Hydraulic Loading RatesADF + Backwash (All Tanks) m3/m2/hr 7.9ADF + Backwash (4 out of service) m3/m2/hr 8.81.5X Flow + Backwash (All Tanks) m3/m2/hr 11.32X Flow + Backwash (All Tanks) m3/m2/hr 14.7
Nitrification Filters Effluent Conduits
Type of Channel - squareNumber of Channels - 2Width m 2Depth m 2Velocity (at largest channel area)
ADF + Backwash m/s 1.001.5X Flow + Backwash m/s 1.442.0X Flow + Backwash m/s 1.87
Denitrification Feed Channel
Appendix FAppendix F.xls/Lamma Option Bm 3 of 6
-
Number of Channels - 2DimensionsWidth m 2Depth m 2Velocity (BW water has been removed)
ADF m/s 0.861.5X Flow m/s 1.302.0X Flow m/s 1.73
Denitrification Filters
Design Parameters @ ADFOrganic Loading Rate kg/m3-media-d 2.6Hydraulic Loading Rate m3/m2/hr 17.7
No. of Tanks Required - 15Total No. of Tanks Provided - 18Allowance for Redundancy - 3
Filter Effective DimensionsLength m 12Width m 9Media Depth m 3Effective Surface Area
Each Filter m2 108Total m2 1944
Media Volume (each filter)Each Filter m3 324Total m3 5832
Media Type - expanded clayMedia Size mm 4 - 8Weir Length m 4.1
Tank Wall Thickness m 1
Hydraulic Loading RatesADF (All Tanks) m3/m2/hr 12.8ADF (4 out of service) m3/m2/hr 16.11.5X Flow (All Tanks) m3/m2/hr 19.22X Flow (All Tanks) m3/m2/hr 25.6
UV Disinfection System
Minumum Transmissivity % 50Number of Lamps - 2,340Number of Channels - 12Channel Dimensions (l x w) m x m 17 x 2Maximum Electrical Load* kW/kVA 843/887
*Based on 60% Transmissivity
Filter Backwash System
BOD FiltersBackwash Air Flow Rate Nm/hr 95Backwash Water Flow Rate m3/m2/hr 35Duration of Backwash Water Flow min 25
Nitrification FiltersBackwash Air Flow Rate Nm/hr 75Backwash Water Flow Rate m3/m2/hr 20Duration of Backwash Water Flow min 25
Appendix FAppendix F.xls/Lamma Option Bm 4 of 6
-
Denitrification FiltersBackwash Air Flow Rate Nm/hr 95Backwash Water Flow Rate m3/m2/hr 35Duration of Backwash Water Flow min 25
Backwash Flow (16% of ADF) m3/d 95,653* Used 16% of ADF to be conservative
Sludge Processing Facilities
Sludge Quantities
Primary SludgeQuantity kg DS/d 212,328Volume m3/d 7,078Percent Solids % 3
Liquid Sludge Storage
Desired Sludge Storage Time hrs 13
Number of Storage Tanks (Duty, Standy) 1 ,1Height m 10Diameter m 5
Total Storage Time Provided day 7
Sludge Dewatering
Sludge Flow m3/hr 295
Total Required Centrifuges - 5Operating - 4Standby - 1
Sludge Feed Pump - 6
Sludge Cake Storage Silos
Quantity of Dry Sludge Solids kg DS/d 191,095Sludge Cake Solids Percent % 30Quantity of Dewatered Wet Sludge Solids kg WS/d 636,983Sludge Density 1.075Volume of Dewatered Sludge per Day m3/d 593Desired Cake Storage Time hrs 24Volume of Cake Storage Required m3 594Number of Silos - 3Volume of Silos
Each m3 200Total m3 600
Actual Cake Storage Time hrs 24
Sludge Cake Transfer Containers
Tonnes of Wet Solids to be Hauled t WS/d 637Capacity of Each Container tonnes 14.5Number of Containers per day 44Total Number of Containers Required (5 Sets) - 220
Methanol Storage
Appendix FAppendix F.xls/Lamma Option Bm 5 of 6
-
Methanol Required m3/d 40Methanol Purity (as delivered) % 96Source of Motive Water - Nitrified EffluentDilution for Transfer - 20:1Number of Tanks - 2Tank Size
Diameter m 3.5Length m 13
Volume m3 125Storage Provided d 5
Fine Screen
Type - BandNumber - 6Height m 8.45Headloss (clean water) mm 97
Appendix FAppendix F.xls/Lamma Option Bm 6 of 6