value engg ppt final
TRANSCRIPT
CEL 766 SYSTEMS DESIGN & VALUE ENGINEERING
Value Engineering : Merely, a Methodology or a Philosophy - Valuation through Some Case Studies
Presented By;Amrita Mitra 2010CEC3863
Vikalp Awasthi 2010CEC3853
Arneet Singh Sarna 2010CEC3837
Overview
What is Value Engineering?
How Do we Apply VE?
When is it used?
Value Engineering Six Steps Plan?
VE Case Studies
What is VALUE???
Hummer.. $50,000+
$50000 + Tata Nano $2000
•Use Value
•Cost Value
•Exchange Value
•Esteem Value
•Goodwill
•“Feel good” Value
Both Nano and Jaguar are owned by TATA
What is Creativity???
“Every man with new ideas is a crank until those ideas actually work” - Mark Twain
Creativity is the art of
bringing something new into existence.
It has the art of making, inventing, or producing something new and different.
VE combines concepts of VALUE with CREATIVITY
Originally called Value Analysis by its inventor, Larry
Miles, an engineer in GE's purchasing operation in 1947,
VA/VE uses a value equation that says value is equal to
function divided by cost. If, for example, the buyer wants
to get more item value, he/she needs to either increase the
item's functionality at the same time he/she is containing
cost; or he/she needs to reduce cost while holding or
improving its functionality. Either way, the result is more
value for the customer.
VALUE ENGINEERING - A FORGOTTEN TECHNIQUE??
Value Engineering (VE) is an intensive, Interdisciplinary problem solving activity that focuses on improving the value of the functions that are required to accomplish the goal, or objective of any product, process, service, or organization.
VALUE METHODOLOGY “The systematic application of recognized techniques which identify the functions of the product or service, establish the worth of those functions, and provide the necessary functions to meet the required performance at the lowest overall cost.”
WHAT IS VALUE ENGINEERING???
Concept of Value
FUNCTION
VALUE =
COST
V.E. Objective is to make F/C~ =1.00
Best Value is not about cost cutting, it is about improving the understanding of the business/project needs and improving utility value for the end user.
•Value Engineering is used to determine the best design alternatives for Projects.
•Value Engineering is used to reduce cost on existing Projects.
•Value Engineering is used to improve quality, increase reliability and availability, and customer satisfaction.
•Value Engineering is also used to improve organizational performance. •Value Engineering is used to improve schedule •Value Engineering is used to reduce risk •Value Engineering is a powerful tool used to identify problems and develop recommended solutions.
9
WHEN VALUE ENGINEERING IS USED??
Potential Saving from VE
Re-Test Feasibility
Drawings Released Design Changes
Net Savings from VE Cost
Total Cost of VE Implementation
VE Implementation beyond this point results in a net loss.
Construction Construction Design Concept Dwgs Release
TIME 10
Ideal- Enhanced Value at Reduced Cost
Enhanced Value
Enhanced Value
How do we Improve Value of a function?
Function performance Cost of function?
Resulting Value Needed performance
Enhanced Value
Value Engineering uses a combination of creative and analytical techniques to identify alternative ways to achieve objectives.
The use of Function Analysis differentiates Value Engineering from other problem solving approaches.
Function Analysis Systems Technique
F A S T
HOW IS VALUE ENGINEERING APPLIED???
Value Study Diagram
SIX STEPS VE PLAN
Information Phase: Fact Finding
•What do you need to know about the problem that you don’t know now? •What facts are known?•What are the requirements of the system?•Are these facts, opinions, assumptions, or prejudices?
•Where or how can information be obtained?
FUNCTIONAL PHASEFunctions - Describe what something does
Functions - Use active verb and measurable noun
FAST (Function Analysis System Technique) - A logic diagram to describe how a system works.
Examples : Secondary Functions 1 Plan Finishing Material 2 Magnify Living Room Area 3 Reduce Wall Thickness 4 Design Exposure 5 Minimize Defect 6 Design Finishing
Key Function :
Satisfy Tenant
Creative Phase
The Creative Workshop
•Record creative ideas on a flip chart
•Begin with high cost functions
•Structured & facilitated brainstorming
•Number ideas for cross-referencing
•List every idea no matter how unconventional
•No ridicule or judgment
•Enjoy!!
Functions →Ideas
Mind is like a parachute: It works best when open!
Evaluation Phase• Developing & ranking ideas against performance criteria
•Pass / fail test
• Eliminating ideas that don’t have champions
•Feasible / realistic / lack of champions
• Voting on ideas through ‘Gut Feel Criteria’
GFI (Gut Feel Index) -Discuss pro/con and vote. GFI is team average. -Combine ideas; add new ideas. -Record all assumptions when voting.
WASTE• Make it tangible • Make it VISIBLE• Seek / Identify opportunities to eliminate/modify Small / large ideas, build on others ideas..
Unnecessary & secondary functions are like waste that may be eliminated by creativity
Development Phase
Objectives:
• Review Customer’s values and objectives
• Expand Ideas
• Develop the chosen ideas into written recommendations that include:
Sketches
Calculations
Cost Analysis
Advantages and Disadvantages
Risks (cost and time) if possible
ACTION PLAN
• “What needs to be done?”
• Plan ahead for anticipated Road Blocks.
• “Who should be assigned the action?” Assign a Team Member• Assign a completion date for the action.
• “When should the task be completed?” Plan regular team status meetings. • Anticipate 4-6 weeks to complete the actions.
Reporting/Presentation Phase
• Give oral presentation. • Support it with written executive brief. • Be clear, concise, and positive. • Anticipate roadblocks.• Use good human relations. • Inspire Confidence.
Follow –up Activity
• Recognize the participants.
• Publicize the results.
• Audit the performance of the implemented actions.
• Close out the project.
Critical Success Factors for VE
METHODOLOGY
VE job plan must be followed systematically
Attitude of Participants
Right attitude, appropriate stakeholders, awareness of process
Executive support
VE workshops, sponsorship, implementation of results
Management of Process
Clear objectives, timelines, follow-up actions, review and feedback
Professional Workshop Facilitation
Probing with right questions, using appropriate tools, managing
the process, maintaining momentum of team, etc. etc.
Case Studies
In order to present our views further and to bring out the importance of a VALUE ENGINEERING exercise in construction projects, we have taken up a case study. The following case study was published by OGC (Office of Government Commerce), Ministry of Commerce, U.K along with a series of other value engineering case studies in order to promote it’s use all across the United Kingdom for Construction Projects.
Case Studies by OGC
Case Study No.2
Among all the projects that were subjected to VM by OGC the second project namely, THE OPEN UNIVERSITY PROJECT was the one where maximum transformation was observed. Hence, we shall discuss the same during the course of our presentation.
The OPEN UNIVERSITY Project
•Project Objective of the VM team: Getting more for less and Increasing User SatisfactionThe End Result:•VM supported team learning at the OPEN UNIVESITY LIBRARY PROJECT resulted in benefit to cost ratio of more than 10:1.•Cost savings of £1.3m were achieved at aVM study cost of £120,000 – a benefit-to-costratio of more than 10:1.
The OPEN UNIVERSITY ProjectThe Open University’s objectives were:
A new library building which: did not exceed the capped capital budget would be ready for occupation by the stated
moving-in date met user requirements.
The total and focused involvement of the wider client body, in particular users of the building and those responsible for its upkeep.
A project team that would: identify and enhance value develop a common understanding of user needs define common objectives.
Major issues
The proposed library site was constrained by existing buildings, car parking and natural features- including a large tree and a pond that was home to a colony of great crested newts.
The failure to gain approval for previous proposals had engendered doubts that a properly-functioning building could be delivered within budget, on time and also satisfy the aspirations of user groups, such as the management, library staff, library users and researchers.
Successful Initiatives: CORE GROUPA core group was established which:
comprised a representative from each partnering organisation
met monthly to maintain an overview of the process and to support decision-making
who would be the arbitrator in the event of a major issue worked together in a structured programme of VM
workshops and other full-team workshops aimed to add value by increasing client and user
satisfaction aimed to reduce costs, waste and time spent on re-
working and resolving confusions. The team also focused on achieving satisfaction,
enjoyment and pride in an exemplary building, adding value for all.
Successful Initiatives: Trust
The increase in positive experiences, created by the successful series of VM workshops, significantly raised the level of trust within the team.
When team morale weakened it was apparent in the team satisfaction KPIs. Consequently, the June workshop was limited to the morning, followed by a Thames cruise in the afternoon. In the context of a £17m project, this cost was minimal but it turned the morale and team-working around, as evidenced by the KPIs ( Key Performance Indicators)
Successful Initiatives: KNOWLEDGE SHARING
One of the principles of VM is that added value is driven by the sharing of explicit and tacit knowledge throughout the project.
During review workshops, all team members benefited from communicating their views on project and team successes and opportunities.
Successful Initiatives: MITIGATING RISK
The University had previously endeavoured to procure the new library by traditional means.
This did not yield proposals that could be delivered within time and budget constraints and to the satisfaction of the end-users.
The VM programme was implemented to help reduce uncertainties.
Successful Initiatives: REDUCING BUDGET UNCERTAINITY As the project developed, it became clear
that there was a potential mismatch between resources and expectations.
Workshops, during the design, development and procurement stages, provided more opportunities for both costs savings and enhancements to meet user needs.
The outcome of the workshops was a reduction in construction costs of 20% whilst retaining essential client and end-user functionality.
Successful Initiatives: Cost-effectiveness of VM process The overall cost of conducting the
VM programme, including the salaries of those who attended and the professional facilitation fees, was about £120,000. The realised cost savings were £1.3m, representing a payback of over 10:1.
Successful Initiatives: Early involvement of all parties Bringing the full team together early
on enabled the client to take advantage of the knowledge of all professionals, including key specialist contractors.
Each workshop featured a team exercise to reinforce a learning point or introduce a process. These 15- minute activities also helped to breakdown barriers.
Successful Initiatives: Continuous Improvement The information and knowledge generated
from the workshops has been used to improve subsequent schemes for the Open University.
All the data leading up to the team’s decisions was listed in detail within the workshop reports.
This formed an audit trail of objective decision-making and also provided an information base to guide users, specifiers, designers and constructors involved in future Open University projects.
Lessons learned
The success of the VM workshop programme has led the client to adopt the same approach on subsequent projects.
The process allowed the client to feel part of the project and also involved the end-users, enabling both client and user needs to be met in a resourceful and value-adding manner.
Lessons learned
The workshops helped the team to push the boundaries of cost, time and quality. Normally, one would expect a gain in one of these criteria at the expense of the other two, but in this project the team achieved better than-expected performance in all three criteria.
SUMMARY OF CHANGES
Before:The procurement route was
traditional. After:The revised procurement route
involved partnering with regular VM reviews.
As observed, just bringing about one small change can do wonders for a Construction Project.
Achievements and Benefits
Involvement of department heads and end-users.
Benefit: Library usage is double the pre-project estimate.
Excellent value for money. Benefit: Savings of £1.3m were
achieved for a cost of £120,000 (the VM studies) – a payback of over £1.1m.
Achievements and Benefits
Users’ needs were identified before value adding proposals were generated.
Benefit: The team evaluated the potential for value enhancement before spending time on the detailed development of proposals, which might have resulted in little improvement.
Achievements and Benefits
All members were encouraged to attend meetings regardless of their position within the team.
Benefit: Fuller briefings with input from end-users.
Good team spirit. Benefit: Team members could raise
controversial topics without fear.
Achievements and Benefits
Joint solutions to problems encouraged.
Benefit: Reduced delays and costs associated with time consuming referrals to senior management.
Development of trust within the team. Benefit: Reduced correspondence.
BENEFITS OF VM EXERCISE:
increasing collaboration as the project progressed
clients’ and end users’ expectations met in full
costs reduced by 20% to remain within capped budget
effective VM reduced uncertainty of unproven procurement route to acceptable levels.
Typical Case Study (The Technical Aspect):
A typical scenario for the suitability of crushed aggregate in construction has been selected as our case study.
Crushed fine aggregates have been regularly used to make quality concrete for decades in India and abroad.
Demand for crushed fine aggregates for making concrete is increasing because natural sand cannot meet the rising demand of construction sector.
Advantages of Crushed Aggregate over Natural Sand: Because of its limited supply the cost of
natural sand has sky rocketed and its consistent supply cannot be guaranteed.
Natural sand in many parts of the country is not graded properly and has excessive silt on other hand crushed sand does not contain silt/ organic impurities and can be produced to meet desired gradation and fineness as per requirement.
Comparison with Natural Sand:
Property Natural Sand Crushed fineAggregate
Shape Spherical Particles Cubical
Gradation Cannot be controlled Can be controlled
Particles passing 75micron
Presence of SiltShould be Less than 3%
Presence of DustLess than 15%
Specific Gravity 2.6 to 2.8 2.7 to 2.9
Water Absorption 2 to 3 % 3 to 4%
Ability to holdsurface moisture
Up to 7% Up to 10%
Comparison in concrete when compared with well graded silt free natural sand:
Crushed sand gives comparable /better strength when compared with natural sand
It gives lower workability It gives lower workability retention It gives lower cohesion
However, commonly available natural sand is rarely well graded and silt free.
Long Term Effects (Durability)Durability depends on permeability of concrete & long term stability of cement matrix from alkali aggregate reaction, chlorides present in cement, aggregates and admixture. There is no evidence that concrete made from crushed fine aggregates is less durable than that with natural fine aggregates.
Thus Crushed Fine aggregate can be used for all types of concrete including: High Performance concrete Self Compacting Concrete Pumpable Concrete Roller Compacted Concrete Precast concrete products Brick Work and plaster Mortars Flooring Water proofing
Trouble Shooting practical problems encountered while using crushed fine aggregate:Problems
Reason Remedy
Concrete does not give adequate workability
The particle shape is not spherical but cuboidal or flaky
Controlling shape and gradation
Usually has higher % of fines
Use of plasticizers
Use of flyash
Concrete tends to set quickly
Higher water absorption removes free water
Wetting of fine aggregates in case it is bone dry
Lower particle size results in faster absorption
Use of retarding plasticizers
Greater surface area results in faster evaporation
Use of flyash
Protecting the green concrete from drying
Problems
Reason Remedy
Concrete tends to segregate
Flaky shape Controlling the shape and gradation of particles
Lack of adequate fines Preventing segregation during transportation by spraying water
Segregation of Particles while transportation and Unloading
Use of Flyash
Inadequate mixing Blending with natural sand
Use of fibres to increase cohesion
Using better mixers
Concrete gives lower strength
Flaky particles or higher fines increase water demand
Controlling the quality of incoming material by visual inspection and regular sieve analysis
Higher water demand translates in to higher water cement ratio
Controlling the water cement ratio by using plasticizers
Segregation of concrete results in non - uniform distribution of cement paste
Take steps to control segregation
Problems
Reason Remedy
Concrete has Honeycombs
Lower workability and lower slump retention
Use of plasticizers, retarders and flyash
Inadequate vibration Complete compaction and finishing as early as possible
Segregation of particles during transportation and unloading
Use well graded crushed sand with adequate fines
Lack of fines Ensure cohesion of concrete
Segregation of concrete
Concrete surface shows irregular shaped voids
Concrete with excessive fines and flaky particles is prone to bleeding
Ensure crushed sand is well graded and particle shape is not flaky
Bleeding is phenomena when water comes to vertical faces and top surface through capillaries
Ensure that it is not stone dust
Bleeding water gets trapped between concrete and form work to form water pockets
Non absorbent form surfaces like Plastic coated ply are more prone for trapping water pockets
This water evaporates and shows irregular shaped pockets on surface
Regular tamping of concrete member with mallets will bring bleed water to the top surface
Economics of Crushed fine aggregates
Natural Sand – 2000 to 2500 Rs per 100 cft Rs. 0.4/- to 0.6/- per Kg
Crushed Sand –1500 to 2000 Rs per 100 cftRs. 0.3/- to 0.5/- per Kg
Net difference: Rs. 0.1/- per Kg
Economics in concrete:
1 m3 of M20 concrete requires approximately 800 to 1000 Kg of fine aggregates
Cost difference of using crushed fine aggregates: Rs. 80/- to 100/- per m3 Incremental cost of using admixture: Rs. 50/- to Rs 100/- per m3
Economics in Mortars:
100 kg of 1:5 mortar requires:i. 17 Kg of cement Cost: Rs. 50/- (@Rs. 3/- per Kg)ii. 84 Kg of Natural SandCost: Rs 42/- (@Rs. 0.5/- per Kg) Total Cost: Rs. 92/- Replace natural sand by crushed
sand @Rs. 0.4/- per Kg Saving per 100 kg of Mortar: Rs
8.5/-
Additional cost of admixture: Rs. 4/-(Dosage 0.5% by weight of cement @ Rs. 40/- per Kg) Additional cost of fibres: Rs. 5/- to Rs.
10/-(125 gm per 50Kg @ Rs. 20/- to Rs. 40/- per pouch) Saving by flyash replacement (@Rs1.5
per kg:• 25% replacement - Rs. 5/-• 50% replacement - Rs. 10/-
Net cost saving per 100Kg of mortar
• Crushed sand (saving) - Rs. 8.5/- • Admixture (additional) - Rs. 4/- • Fibres (additional) - Rs. 5/- • Flyash 50% (saving ) - Rs. 10/- Net saving: Rs. 10/- per 100cft
Economics in Overall Building• Building requires 100 to 150 Kg
of fine aggregate per sq. feet• Building requires 75 to 100 Kg
of mortar Net saving: Rs. 6/- to Rs. 8/- per
sq. feet
(Note: Above calculations are based on price levels in Pune Region)
Precautions to be taken: Ensure that well graded and well
shaped crushed sand is obtained at site
Ensure that a mixture of stone dust and grit at the cost of crushed sand is not being procured at site
Ensure that crushed sand is received in wet condition and does not segregate while unloading
Conclusions to the case study:
Natural sources of fine aggregates cannot meet the demand of the industry
Natural sources of fine aggregate cannot meet the quality requirements of the industry
Crushed fine aggregate can be used for all applications in construction
Crushed fine aggregate can deliver a good product and will save costs
References
Value Engineering Methodology In Construction by Fadi Elayache, Dubai 2010
Value of Project Management – a Case Study PASI OJALA.
Value management in Construction (Case Studies) Published by OGC, Sep 2007.
Crushed sand, a reality for construction Industry, HCC value engg division, Published Dec,2009
The Synergy between Value Engineering and Sustainable Construction Abdulaziz S. Al-Yousefi, CVS-Life, FSAVE
VE Research Group of SANNO Management Institute (1999) New Essentials of VE (in Japanese). Publication Department of SANNO Management Institute, Tokyo.
Thank You