Scope of Services 1. Data Collection and Early Coordination A. Initial Meeting with Villages Prior to our initial meeting with the Villages, the Phase II staff will review the approved Project Development Report (PDR) to familiarize ourselves with the design and commitments made during Phase I. We will come to the meeting prepared to discuss the Phase I report and project schedule, discuss permitting submittals and agency coordination, and request any outstanding or updated information from the Villages. B. Obtain/Update and Review Record Data We will obtain and review available Village data including, but not limited to, subdivision plans and plats, record plans, airport data, geotechnical reports, right-of-way data, sewer videos, aerial photography and contour mapping, other existing plans, and municipal utility atlases. C. Obtain and Review Potential Development Plans The RFP indicated that there are potential developments along Rodenburg Road within the project limits. We will obtain the plans for developments from the Villages and review the project for any potential impacts to the proposed improvements. D. Preliminary Utility Company Coordination We will call in a Design J.U.L.I.E. and send letters and project location maps to the utility companies within the project limits in order to confirm or update the information obtained during Phase I. E. Geotechnical Investigation (Coordination Only) Pavement cores and borings were previously performed during Phase I. However, based on the results of one of the borings and a review of the soil mapping, it is anticipated that there will be compressible organic sub- grade soils in the areas where the roadway is adjacent to existing wetlands. We will have our geotechnical sub-consultant (Midland Standard Engineering and Testing) perform additional soil borings in these areas to determine the extents of this material and to develop the most appropriate remediation strategies. We will report any project budget impacts immediately to the Villages. F. Field Visit We will perform a “plan in hand” field check during which we will: Verify the completeness and accuracy of the design and supplemental survey while familiarizing ourselves with the project area and any special conditions in the field. Review the project area for any problematic drainage conditions that could be remedied as part of this project. Prepare a detailed inventory of existing signage and any other topographic features which may impact or be impacted by the proposed design. Establish as accurately as possible, the locations of existing private utilities in the field using atlases obtained during the Data Collection and Early Coordination Phase. Photo document the project area for use during design. Statement of Qualifications for Phase II Engineering Services Rodenburg Road Improvements - Central Ave to Irving Park Rd (IL-19) Village of Schaumburg and Village of Roselle

Upload: others

Post on 18-Feb-2022

4 views

Category:

Documents


0 download

TRANSCRIPT

SECTION 4

Scope of Services1. Data Collection and Early Coordination

A. Initial Meeting with VillagesPrior to our initial meeting with the Villages, the Phase II staff will review the approved Project Development Report (PDR) to familiarize ourselves with the design and commitments made during Phase I. We will come to the meeting prepared to discuss the Phase I report and project schedule, discuss permitting submittals and agency coordination, and request any outstanding or updated information from the Villages.

B. Obtain/Update and Review Record DataWe will obtain and review available Village data including, but not limited to, subdivision plans and plats, record plans, airport data, geotechnical reports, right-of-way data, sewer videos, aerial photography and contour mapping, other existing plans, and municipal utility atlases.

C. Obtain and Review Potential Development PlansThe RFP indicated that there are potential developments along Rodenburg Road within the project limits. We will obtain the plans for developments from the Villages and review the project for any potential impacts to the proposed improvements.

D. Preliminary Utility Company CoordinationWe will call in a Design J.U.L.I.E. and send letters and project location maps to the utility companies within the project limits in order to confirm or update the information obtained during Phase I.

E. Geotechnical Investigation (Coordination Only)Pavement cores and borings were previously performed during Phase I. However, based on the results of one of the borings and a review of the soil mapping, it is anticipated that there will be compressible organic sub-grade soils in the areas where the roadway is adjacent to existing wetlands. We will have our geotechnical sub-consultant (Midland Standard Engineering and Testing) perform additional soil borings in these areas to determine the extents of this material and to develop the most appropriate remediation strategies. We will report any project budget impacts immediately to the Villages.

F. Field VisitWe will perform a “plan in hand” field check during which we will:❯ Verify the completeness and accuracy of the design and supplemental survey while familiarizing ourselves

with the project area and any special conditions in the field.❯ Review the project area for any problematic drainage conditions that could be remedied as part of this

project.❯ Prepare a detailed inventory of existing signage and any other topographic features which may impact or

be impacted by the proposed design.❯ Establish as accurately as possible, the locations of existing private utilities in the field using atlases

obtained during the Data Collection and Early Coordination Phase.❯ Photo document the project area for use during design.

Statement of Qualifications for Phase II Engineering ServicesRodenburg Road Improvements - Central Ave to Irving Park Rd (IL-19)

Village of Schaumburg and Village of Roselle

G. Structure Inventory We will prepare a structure inventory report which will include the type and condition for each manhole, catch basin, inlet, and valve vault within the project limits. We will assess the need for adjustment, reconstruction or replacement of these structures. Village staff will be invited to attend this field inventory.

H. Pavement Patching and Bike Path Condition SurveyWe will prepare a patching survey of the existing pavement along Rodenburg Road. We will also review the condition of the existing bike path. This work will be performed by one of Civiltech’s Resident Engineers experienced in overseeing patching projects.

I. Verify ESR Limits and Update Environmental Sign-OffsWe will obtain a copy of the original ESR submittal from the Villages and confirm that the area of any new easements were included. If the detailed design requires any work outside the original limits, we will submit an ESR Addendum to IDOT. We anticipate that the clearances in the PDR will expire prior to construction, therefore we will coordinate with IDOT to obtain updated clearances.

J. Special Waste Investigations (Coordination Only)An updated PESA will need to be prepared based on the age of the original PESA prepared during Phase I. Sampling will also be performed to determine whether excess material can be disposed of at a Clean Construction and Demolition Debris (CCDD) site. Additional information regarding our approach to this investigation is included in the proposal from Huff and Huff, who will complete this work as a sub-consultant to Civiltech.

K. IDOT Project Kick-off MeetingWe will conduct a joint meeting with the Illinois Department of Transportation to discuss the project and gain everyone’s acceptance of the project schedule and commitment to timely reviews.

2. Preliminary (60%) EngineeringA. Plan Base Sheet Preparation

We will plot the existing topographic survey information and develop Phase II plan base sheets at a scale of 1" = 20' and 1"=50' for use in the development of contract plans. Cross sections will be prepared within the reconstruction section at 50-foot intervals and will include full sections at intersections and high and low points along the roadway profile. Half width cross sections will be prepared at driveways and access points. Any updated existing utility information that has been obtained during the data collection phase will also be plotted on the base sheets.

B. Drainage DesignDrainage design will be in accordance with the Phase I Proposed Drainage Plan (PDP), as well as MWRD and DuPage County requirements. With this project spanning both Cook and DuPage Counties, separate permitting is expected to be required to meet each respective County stormwater ordinance.

C. Pavement DesignWe will review and finalize the pavement designs completed during Phase I based on the latest IDOT mix designs and specifications. The pavement designs will be in accordance with the geotechnical report, and IDOT specifications and procedures.

Statement of Qualifications for Phase II Engineering ServicesRodenburg Road Improvements - Central Ave to Irving Park Rd (IL-19)

Village of Schaumburg and Village of Roselle

D. Lighting DesignThere are four existing light poles on the west side of Rodenburg Road just south Irving Park Road. There is a controller for these four lights. There is also a lighting system at Irving Park Road that appears to be IDOT’s. None of the IDOT system poles are affected by the improvement. Three out of the four Village poles and the controller are in conflict with the proposed improvement. Per the PDR report the poles with be updated to latest Village standard and relocated per outside of improvements. Lighting photometrics will be run to determine proper spacing for the latest Village pole. A new lighting controller will be designed. The scope does not include lighting the entire project limits, however we will investigate extending the lighting system to the new development on the west side of Rodenburg Road, depending on the timing of the development.We will perform photometric calculations to meet the IDOT District 1 lighting levels per the “District 1 General Guidelines for Lighting Design” and Illuminating Engineering Society (IES) guidelines. A lighting design report will be completed providing preliminary layout, photometric calculations, catalog cuts of proposed fixtures, voltage drop calculations and any other applicable information.

E. Review and Confirm Right-of-Way RequirementsWe will review the proposed roadway alignment and horizontal and vertical geometrics with respect to the existing right-of-way. The survey subconsultant will establish the location of the existing right-of-way throughout the project limits. The Phase I report indicates the need for temporary easements. We will review the project to verify the size, type, and location of easements required. This work will be performed early in the design phase so that the right-of-way acquisition process can begin as soon as possible to ensure that the project remains on schedule.

F. Preliminary Plans (60%) We will prepare preliminary plans containing the following drawings:❯ Cover Sheet❯ Index of Sheets and List of State and Local Standards❯ Summary of Quantities❯ Typical Sections❯ Alignment, Ties, and Benchmarks (1"=100')❯ Resurfacing Plan – Central to N. of Travis Parkway (1"=20') (dual pane)❯ Existing Conditions and Removal Plan (1”=20’ dual view) - Reconstruction Section Only❯ Roadway Plan and Profile (1”=20’) - Reconstruction Section Only❯ Drainage and Utilities (1”=20’) Reconstruction Section Only❯ Maintenance of Traffic Concept – 2 stages❯ Detour Plan❯ Pavement Marking and Signing Plan 1”=50’ (dual pane)❯ Lighting Plan (1”=20’)❯ Cross Section; 1"=5’ H: 1"=10' V – Reconstruction Section Only

Preliminary Plans will be developed using the findings and recommendations of the approved PDR and the design criteria contained in the Illinois Department of Transportation’s Bureau of Local Roads and Streets (BLRS) manual. The Preliminary Plan preparation and submittal will serve as a progress submittal for review by the Village staff, in an effort to identify and address any significant design issues prior to completing pre-final plans. We will communicate with the Village throughout the design process to resolve any current design issues.

Statement of Qualifications for Phase II Engineering ServicesRodenburg Road Improvements - Central Ave to Irving Park Rd (IL-19)

Village of Schaumburg and Village of Roselle

In an effort to alert the various utility companies of possible conflicts and to advise them of the overall project schedule, we will submit the preliminary plans for their review. It is our intention that this submittal will allow the utility companies to review the plans to determine where additional information is needed concerning the location of their facilities.

G. Preliminary Quantity Calculations and Estimate of CostIn order to ensure that the project is tracking within the projected budget, a cost estimate will be prepared using the portions of the plans that have been completed. Estimated costs will be included for those items that have not yet been designed or detailed. The estimates will be split based on the Village boundaries.

H. Preliminary Design Review MeetingsWe will coordinate a meeting with Village staff in order to discuss the project. The meetings will be scheduled such that all parties will have had an opportunity to review the preliminary plans and provide comments.

3. Pre-Final (90%) Plans, Special Provisions and EstimatesA. Pre-Final Plans

The development of Pre-Final Contract Plans and documents will proceed throughout the Village’s review of the Preliminary Plan Submittal. We will prepare pre-final contract plans based on comments received on the preliminary plans and in accordance with the approved PDR, the applicable sections of the BLRS manual, BDE manual, applicable IDOT Standards and in accordance with current Village standards and practices. We anticipate that the contract plans will contain the following drawings:

❯ Cover Sheet ❯ Index of Sheets and List of State and Local

Standards❯ General Notes and List of Commitments❯ MWRD General Notes❯ MWRD Sewer Routing Map❯ Summary of Quantities❯ Schedule of Quantities❯ Typical Sections❯ Alignment, Ties, and Benchmarks (1"=100')❯ Resurfacing Plan – Central to N. of Travis

Parkway (1"=20') (dual pane)❯ Existing Conditions and Removal Plan (1”=20’

dual view) - Reconstruction Section Only❯ Roadway Plan and Profile (1”=20’) -

Reconstruction Section Only❯ Drainage and Utilities (1”=20’) Reconstruction

Section Only❯ Stages of Construction – Sequences and Typical

Sections❯ Stages of Construction – 2 stages, 1”=50’ (dual

pane)

❯ Detour Plan❯ Detour Notes❯ Erosion Control Plan (1”=50’) (dual pane)❯ Plat of Highways❯ Rail Crossing Details 1”=10’❯ ADA Ramp Details 1”=5’ (dual pane)❯ Pavement Marking and Signing Plan 1”=50’

(dual pane)❯ Traffic Signal Loop Replacement Detail❯ Lighting Legend, Notes and Bill of Materials❯ Temporary Lighting Plan (1”20’)❯ Temporary Lighting Circuit Diagram and Details❯ Lighting Plan (1”=20’)❯ Lighting Circuit Diagram❯ Lighting Details❯ Cross Section; 1"=5’ H: 1"=10' V – Reconstruction

Section Only❯ Construction Details / IDOT District One

Standards

Statement of Qualifications for Phase II Engineering ServicesRodenburg Road Improvements - Central Ave to Irving Park Rd (IL-19)

Village of Schaumburg and Village of Roselle

The pre-final contract documents will be submitted to the Villages and IDOT for review. We will also submit the contract plans to the various utility companies. This submittal will sufficiently define the conflicts so that the utility companies can, at a minimum, perform the necessary engineering for any required utility relocations. This allows relocations to be performed in advance of the actual construction. Civiltech will perform the necessary coordination with the utility companies and follow up as needed on each of our submittals to ensure that no utility company is neglecting the project. Depending on the complexity of the utility involvement it may be necessary to conduct periodic coordination meetings.

We have assumed that the only landscaping design will be replacement of parkway trees where possible throughout the corridor.

B. Pre-Final Special ProvisionsWe will prepare special provisions that supplement or amend the specifications contained in the latest edition of the Standard Specifications for Road and Bridge Construction adopted by the Illinois Department of Transportation and the latest edition of the Standard Specifications for Sewer and Watermain Construction in Illinois. Applicable Village special provisions will be utilized to supplement the Standard Specifications. In addition, we will include the latest IDOT Recurring Special Provisions Check Sheet. The most recent set of IDOT’s Bureau of Design and Environment (BDE) Special Provisions and District 1 Special Provisions will be reviewed and included in the special provisions where applicable.

C. Pre-Final Quantity CalculationsWe will perform detailed quantity calculations at the pre-final stage of the plan development. Two sets of calculations will be performed by separate engineers in order to ensure the accuracy of the calculations.

D. Pre-Final Estimate of Cost and Construction TimeWe will use the quantities of work in order to calculate an Engineer’s Estimate of Cost and Time. The unit prices for the various items of work will be developed based on review and analysis of recent bid tabulations for projects of similar scope and magnitude.

E. Pre-Final QC/QA ReviewPrior to submission of the pre-final plans for review, we will perform an internal Quality Control / Quality Assurance review of the work completed. The review will be performed by a professional engineer independent of the design team. The Construction Engineer will also complete a full contract document review at this time. The review will consider constructability issues as well as identification of missing pay items, quantities of work, and special provisions required. The design team will also perform a “plan-in-hand” field check to confirm the existing conditions and design.

F. Pre-Final Project Review Meeting A project review meeting will be held with the Villages and IDOT to address design issues and plan comments generated from the pre-final contract document review.

4. Final (100%) Plans, Special Provisions and EstimatesA. Final Plans

After completion of all agency reviews and resolution of any other agency or utility company concerns, the contract plans will be finalized.

Statement of Qualifications for Phase II Engineering ServicesRodenburg Road Improvements - Central Ave to Irving Park Rd (IL-19)

Village of Schaumburg and Village of Roselle

In order to assist the Resident Engineer (RE) we will furnish the Villages, as part of our deliverables, detailed information including all design and quantity calculations. We will also prepare a technical memorandum to the RE highlighting any key issues, commitments, or special concerns that arose during the design stage of the project.

Since this is a Federal-aid project, IDOT will be responsible for letting the project. Therefore, we will provide IDOT with one full size set of the original plans and bid documents, as well as the number of reduced size copies that they request. We will also furnish the Villages the requested type and number of copies of the final documents.

B. Final Special ProvisionsAll comments received pertaining to the pre-final special provisions and bid documents will be addressed and reflected in the final bid documents. The status and schedule of all utility relocations, as of the date of the final plans, will be included in the bid documents.

C. Final Quantity CalculationsThe quantities will be updated based on changes made to the plans after the pre-final stage.

D. Final Estimate of Cost and Construction TimeThe estimates will be updated based on the revised quantities. Civiltech will assist the Villages and prepare a draft version of the joint agreement (BLR 05310) for construction between IDOT and the Villages. We will work with the Planning Liaison (PL) at both the NWMC and DMMC to finalize the agreement before it gets submitted to IDOT BLRS for approval by the planning liaisons.

E. Final QC/QA ReviewPrior to the final submittal a second QC/QA review of the plans and special provisions will be performed according to our documented Quality Control / Quality Assurance Plan.

5. Project Administration, Coordination and PermitsA. Project Administration

This item includes project setup, monthly invoicing, and preparation of status reports. In addition, this item includes coordinating meetings with the Villages as well as internal project team coordination.

B. Project SubmittalsAs noted above, we will make the necessary document submittals, and follow through with each agency in regards to their review comments or arrange a review meeting to discuss plan changes necessary to resolve conflicts if possible. We will provide to the Villages all reports, plans, studies and other information as requested in digital format.

C. Utility Company CoordinationAs noted above, we will analyze the project for potential impacts to existing utilities. We will provide the utility companies with a list of areas of potential conflict so that additional information, such as horizontal locates or depth borings, can be obtained where necessary to further define the extent of conflicts. We will first attempt to address utility conflicts through design modifications while considering the impact those changes will have on the overall improvement.

Statement of Qualifications for Phase II Engineering ServicesRodenburg Road Improvements - Central Ave to Irving Park Rd (IL-19)

Village of Schaumburg and Village of Roselle

Should any utility relocation work be necessary, we will work with the utility companies as they develop relocation plans, provide them with electronic files when requested and review those plans when they are submitted. We anticipate meeting with each utility one time during the preparation of their relocation plans.

D. GIS IntegrationAll of the information related to the existing and proposed municipal facilities will be incorporated into the Villages’ GIS systems. Civiltech’s GIS Analyst will work closely with the each Village’s GIS group to either access the Village’s system or provide the information to be added.

E. IDOT BLRS/NWMC/DMMC Coordination and Joint Agreement PreparationWe have included a nominal amount of time to work with the Villages, IDOT, and Councils of Mayors in the preparation of project update forms, the Project Program Information Form, and the joint agreements for construction. This item will also include ongoing coordination with NWMC and DMMC to ensure that they are up to date on the project status from schedule and funding standpoints.

F. Metra Railroad CoordinationCiviltech will proactively coordinate the project design with Metra’s engineering and right-of-way staff. We will keep them informed about the project status and schedule. Civiltech will also provide any requested input and/or information regarding the agreement between Metra and the Villages for this project.

G. FAA CoordinationWe will coordinate with the FAA regarding the temporary and permanent construction within the zone required for the Schaumburg Municipal Airport. We anticipate that this will include the submittal of the electronic Notice of Proposed Construction or Alteration.

H. Prepare and Update Wetland Delineation and ReportThe March 2018 Wetland Delineation Report will need to be updated within DuPage County per the DuPage County Ordinance, which specifies that the wetland boundary verification within the county is valid for two years. The Wetland Delineation Report will follow methodology outlined in the USACE Regional Supplement to the Corps of Engineers Wetland Delineation Manual: Midwest Region (Version 2.0), and the DuPage County Stormwater and Floodplain Ordinance.

I. DuPage County Stormwater and Wetland Permitting and DocumentationFor the project section located in DuPage County all stormwater elements of the project will be designed to comply with the requirements of the DuPage County Stormwater and Floodplain Ordinance.

Based on the scope of the project and wetland impacts, and since the Village of Roselle is a partial waiver community, we anticipate a permit submittal to the DuPage Stormwater Management Department. Wetland impacts will be mitigated through the purchase of bank credits or fee in lieu. We will also prepare a Maintenance and Monitoring Plan and Wetland Buffer Technical Memorandum as required under the DuPage County Stormwater and Floodplain Ordinance.

J. MWRD Stormwater and Wetland Permitting and Documentation For the project section located in Cook County all stormwater elements of the project will be designed to comply with the requirements of the WMRD Watershed Management Ordinance.

Based on the scope of the project and wetland impacts, we anticipate a permit submittal to MWRD to comply with the Watershed Management Ordinance. We will also prepare the required Permit Schedules and

Statement of Qualifications for Phase II Engineering ServicesRodenburg Road Improvements - Central Ave to Irving Park Rd (IL-19)

Village of Schaumburg and Village of Roselle

attachments, included the General Form, Schedule P for erosion control and Schedule W Forms and Wetland Buffer Technical Memorandum as required. Wetland impacts will be mitigated through the purchase of bank credits.

K. USACE 404 Wetland Permitting and Documentation Based on the scope of the project and wetland impacts, we anticipate a 404 Regional Permit from USACE. We will submit an updated Jurisdictional Determination Request, should wetland boundaries change as a result of the updated wetland delineation in DuPage County. Wetland impacts will be mitigated through the purchase of bank credits.

L. Soil and Water Conservation District Permit It is anticipated that a review of the project’s erosion control plan will be a condition of the USACE Permit. The Corps has delegated this review to the North Cook County Soil and Water Conservation District and the Kane-DuPage Soil Water Conservation District. We will make the required submittal and address all comments received. A conditional approval will likely be received since the Contractor will be required to provide a detailed in stream work plan for their specific plans for any work within the Waters of the US.

M. PESA ResponseThe PESA report for Irving Park Road was prepared by IDOT. We will prepare and submit the PESA Response Form and the required calculations and exhibits in order to initiate the PSI that will be performed by IDOT.

N. NPDES Permitting and DocumentationThe NPDES permit, along with a Stormwater Pollution Prevention Plan, will also be prepared for inclusion in the contract documents for final execution by the successful bidder. All erosion control design will be in accordance with the latest IEPA, Village, and County requirements.

O. Coordination with Appraisers and NegotiatorsThis item includes work involved with coordination between the Phase II design team and the appraisers and negotiators. This work typically includes providing the appraisers and negotiators with exhibits for use during meetings with the property owners, and providing information regarding the design and potential modifications to the same.

P. Bid Phase AssistanceSince this project involves federal funds, IDOT will be responsible for letting the project. We will be available to respond to questions submitted to IDOT by contractors. We will also review the total bid numbers received by IDOT and make a recommendation to the Villages regarding accepting the bids.

Q. Pre-Construction Meeting Attendance We will attend the pre-construction meeting at IDOT to answer any questions regarding the project.

Statement of Qualifications for Phase II Engineering ServicesRodenburg Road Improvements - Central Ave to Irving Park Rd (IL-19)

Village of Schaumburg and Village of Roselle

Statement of Qualifications for Phase II Engineering ServicesRodenburg Road Improvements - Central Ave to Irving Park Rd (IL-19)Village of Schaumburg and Village of Roselle

COST PROPOSAL - COST ESTIMATE OF CONSULTANT SERVICES

Prepared by: Civiltech Engineering, Inc.,

Preliminary Engineering Cost Estimate of Consultant's ServicesExhibit A

Page 1 of 2

BLR 05610 (Rev. 11/09/17)

Route:Local Agency: *Firm's approved rates on file with IDOT's Section: Bureau of Accounting and Auditing:Project:Job No: Overhead Rate (OH) 1.2488

Complexity Factor (R) 0.000Calendar Days 550

Method of Compensation:

Cost Plus Fixed Fee 1 14.5%[DL + R(DL) + OH(DL) + IHDC] See Exhibit A-1 for Scope of Services

Cost Plus Fixed Fee 2 14.5%[DL + R(DL) + 1.5(DL) + IHDC] See Exhibit A-2 for a detailed Workhour Estimate.

Cost Plus Fixed Fee 3 14.5%[(2.3 + R)DL + IHDC] See Exhibit A-3 for detailed Services by Others and In-House Direct Costs.

Specific Rate

Lump Sum

Man-hours

PayrollRate

PayrollCosts (DL) Overhead* Services by

Others Profit Total

1 Early Coordination and Data Collection 45,903.20$ -$ 45,948.00$ 4 70.00$ 280.00$ 349.66$ 91.30$ 720.97$

18 63.00$ 1,134.00$ 1,416.14$ 369.77$ 2,919.91$ 37 42.50$ 1,572.50$ 1,963.74$ 512.75$ 4,048.99$ 40 32.00$ 1,280.00$ 1,598.46$ 417.38$ 3,295.84$ 0 59.00$ -$ -$ -$ -$ 2 43.00$ 86.00$ 107.40$ 28.04$ 221.44$ 4 48.50$ 194.00$ 242.27$ 63.26$ 499.53$ 0 35.00$ -$ -$ -$ -$

2 Preliminary (65%) Engineering 27,908.67$ -$ 28,431.07$ 10 70.00$ 700.00$ 874.16$ 228.25$ 1,802.41$ 60 63.00$ 3,780.00$ 4,720.46$ 1,232.57$ 9,733.03$

246 42.50$ 10,455.00$ 13,056.20$ 3,409.12$ 26,920.33$ 290 32.00$ 9,280.00$ 11,588.86$ 3,025.99$ 23,894.85$

Traffic Signals Engineer V 0 59.00$ -$ -$ -$ -$ 0 43.00$ -$ -$ -$ -$ 0 48.50$ -$ -$ -$ -$ 0 35.00$ -$ -$ -$ -$

3 Pre-Final (90%) Plans, Special Provisions and Estimates 11,200.00$ -$ 17,122.40$ 16 70.00$ 1,120.00$ 1,398.66$ 365.21$ 2,883.86$ 91 63.00$ 5,733.00$ 7,159.37$ 1,869.39$ 14,761.76$

274 42.50$ 11,645.00$ 14,542.28$ 3,797.16$ 29,984.43$ 321 32.00$ 10,272.00$ 12,827.67$ 3,349.45$ 26,449.13$

8 59.00$ 472.00$ 589.43$ 153.91$ 1,215.34$ 0 43.00$ -$ -$ -$ -$ 8 48.50$ 388.00$ 484.53$ 126.52$ 999.05$ 0 35.00$ -$ -$ -$ -$

Traffic Signals Engineer VGIS Analyst

GIS Analyst

Traffic Signals Engineer VGIS Analyst

Senior Project ManagerProject Manager

522.40$

Engineer IVEngineer II

Environmental Scientist IIIResident Engineer IV

Exhibit A - Preliminary Engineering

Cost Estimate of Consultant's Services in Dollars

Employee Classification In-House Direct Costs (IHDC)

44.80$ Senior Project ManagerProject Manager

Element of Work

Rodenburg RoadVillages of Schaumburg/Roselle

Engineer IV

Senior Project ManagerProject Manager

5,922.40$

Engineer IV

Engineer II

Resident Engineer IV

Engineer II

Environmental Scientist IIIResident Engineer IV

Environmental Scientist III

Statement of Qualifications for Phase II Engineering ServicesRodenburg Road Improvements - Central Ave to Irving Park Rd (IL-19)Village of Schaumburg and Village of Roselle

COST PROPOSAL - COST ESTIMATE OF CONSULTANT SERVICES

Prepared by: Civiltech Engineering, Inc.,

Preliminary Engineering Cost Estimate of Consultant's ServicesExhibit A

Page 2 of 2

BLR 05610 (Rev. 11/09/17)

Man-hours

PayrollRate

PayrollCosts (DL) Overhead* Services by

Others Profit Total

Cost Estimate of Consultant's Services in Dollars

Employee Classification In-House Direct Costs (IHDC)Element of Work

4 Final (100%) Plans, Special Provisions and Estimates -$ -$ 722.40$ 10 70.00$ 700.00$ 874.16$ 228.25$ 1,802.41$ 22 63.00$ 1,386.00$ 1,730.84$ 451.94$ 3,568.78$ 48 42.50$ 2,040.00$ 2,547.55$ 665.20$ 5,252.75$ 48 32.00$ 1,536.00$ 1,918.16$ 500.85$ 3,955.01$ 6 58.00$ 348.00$ 434.58$ 113.47$ 896.06$ 0 43.00$ -$ -$ -$ -$ 8 48.50$ 388.00$ 484.53$ 126.52$ 999.05$ 0 35.00$ -$ -$ -$ -$

5 Project Administration, Coordination and Permits -$ -$ 7,972.40$ 21 70.00$ 1,470.00$ 1,835.74$ 479.33$ 3,785.07$ 92 63.00$ 5,796.00$ 7,238.04$ 1,889.94$ 14,923.98$

202 42.50$ 8,585.00$ 10,720.95$ 2,799.36$ 22,105.31$ 113 32.00$ 3,616.00$ 4,515.66$ 1,179.09$ 9,310.75$

0 59.00$ -$ -$ -$ -$ 16 43.00$ 688.00$ 859.17$ 224.34$ 1,771.51$ 16 48.50$ 776.00$ 969.07$ 253.03$ 1,998.10$

190 35.00$ 6,650.00$ 8,304.52$ 2,168.41$ 17,122.93$

Totals 2,221 92,370.50$ 115,352.28$ 85,011.87$ 30,119.80$ 338,038.85$

Traffic Signals Engineer VGIS Analyst

Senior Project ManagerProject ManagerEngineer IVEngineer II

Environmental Scientist III

Senior Project ManagerProject Manager

Engineer IIEngineer IV

Resident Engineer IV

15,184.40$

Traffic Signals Engineer VGIS Analyst

722.40$

7,972.40$

Resident Engineer IVEnvironmental Scientist III

Statement of Qualifications for Phase II Engineering ServicesRodenburg Road Improvements - Central Ave to Irving Park Rd (IL-19)Village of Schaumburg and Village of Roselle

COST PROPOSAL - WORKHOURS

Senior Project

Manager

Project Manager

Engineer IV Engineer IITraffic Signals

Engineer VGIS Analyst

Resident Engineer IV

Environmental Scientist III

Scope of Services1 Early Coordination and Data Collection

A. Initial Meeting with Villages 2 2 2 6 5.7%B. Obtain/Update and Review Record Data 2 2 2 6 5.7%C. Obtain and Review Potential Development Plans 2 4 6 5.7%D. Preliminary Utility Company Coordination 4 4 3.8%E. Geotechnical Investigations (Coordination Only) 1 2 3 2.9%F. Field Visit 6 6 6 18 17.1%G. Structure Inventory 2 2 4 3.8%H. Pavement Patching and Bike Path Condition Survey 2 2 4 3.8%I. Verify ESR Limits and Update Environmental Sign-Offs 4 8 32 44 41.9%J. Special Waste Investigations (Coordination Only) 1 2 3 2.9%K. IDOT Project Kick-Off Meeting 2 2 3 7 6.7%

Item 1 Subtotal 4 18 37 40 0 2 4 0 105 100.0%

2 Preliminary (65%) Engineering A. Plan Base Sheet Preparation 24 24 4.0%B. Drainage Design 2 2 24 32 60 9.9%C. Pavement Design 2 8 10 1.7%D. Lighting Design 4 40 44 7.3%E. Review and Confirm Right-of-Way Requirements 4 8 12 2.0%F. Preliminary Plans (65%) Sheets

Cover Sheet 1 1 2 2 5 0.8%Index of Sheets and List of State and Local Standards 1 2 2 4 0.7%Summary of Quantities 6 2 2 4 0.7%Typical Sections 2 2 8 16 26 4.3%Alignment, Ties, and Benchmarks (1"=100') 1 2 4 8 14 2.3%Resurfacing Plan - Central to N. of Travis Pkwy. (1"=20') (dual pane) 2 2 8 16 26 4.3%Existing Condition and Removal Plans (1”=20’ dual view) - Recon. Section Only 3 4 8 24 36 5.9%Roadway Plan and Profile (1”=20’) Recon. Section Only 6 2 8 24 32 66 10.9%Drainage and Utilities (1”=20’) Recon. Section Only 6 2 8 24 32 66 10.9%Maintenance of Traffic Concept - 2 stages 4 4 12 16 32 5.3%Detour Plan 1 1 2 4 7 1.2%Pavement Marking and Signing Plan 1”=50’ (dual pane) 2 2 4 8 14 2.3%Lighting Plan (1"=20') 1 2 16 18 3.0%Cross Sections; 1"=5’ H: 1"=10' V - Recon. Section Only 16 2 8 24 40 74 12.2%

G. Preliminary Quantity Calculations and Estimate of Cost 2 24 32 58 9.6%H. Preliminary Design Review Meeting 2 2 2 6 1.0%

Item 2 Subtotal 10 60 246 290 0 0 0 0 606 100.0%

Item No.

Task Total Workhours

% of Workhours

Staff Classifications & Workhours

Statement of Qualifications for Phase II Engineering ServicesRodenburg Road Improvements - Central Ave to Irving Park Rd (IL-19)Village of Schaumburg and Village of Roselle

COST PROPOSAL - WORKHOURS

3 Pre-Final (90%) Plans, Special Provisions and Estimates A. Pre-Final Plans Sheets

Cover Sheet 1 1 1 1 3 0.4%Index of Sheets and List of State and Local Standards 1 1 1 1 3 0.4%General Notes and List of Commitments 2 1 2 2 5 0.7%MWRD General Notes 1 1 1 2 0.3%MWRD Sewer Routing Map 1 1 2 4 7 1.0%Summary of Quantities 6 2 2 4 0.6%Schedule of Quantities 5 4 8 12 1.7%Typical Sections 2 2 4 8 14 1.9%Alignment, Ties, and Benchmarks (1"=100') 1 1 1 2 4 0.6%Resurfacing Plan - Central to N. of Travis Pkwy. (1"=20') (dual pane) 2 2 4 8 14 1.9%Existing Condition and Removal Plans (1”=20’ dual pane) - Recon. Section Only 3 2 4 8 14 1.9%Roadway Plan and Profile (1”=20’) Recon. Section Only 6 2 4 8 16 30 4.2%Drainage and Utilities (1”=20’) Recon. Section Only 6 2 4 16 32 54 7.5%Stages of Construction – Sequences and Typical Sections 1 2 8 16 26 3.6%Stages of Construction – 2 stages, 1”=50’ (dual pane) 4 4 8 16 28 3.9%Detour Plan 1 1 2 2 5 0.7%Detour Notes 1 1 2 2 5 0.7%Erosion Control Plan (1”=50’) (dual pane) 2 4 16 24 44 6.1%Landscaping Plan (1”=50’) (dual pane) 2 4 12 16 32 4.5%Plat of Highways 10 2 4 6 0.8%Rail Crossing Details 1”=10’ 1 2 4 8 14 1.9%ADA Ramp Details 1”=5’ (dual pane) 7 16 40 64 120 16.7%Pavement Marking and Signing Plan 1”=50’ (dual pane) 2 1 2 4 7 1.0%Traffic Signal Loop Replacement Detail 2 4 4 0.6%Lighting Legend, Notes and Bill of Materials 1 1 4 5 0.7%Temporary Lighting Plan (1"=20') 1 1 12 13 1.8%Temporary Lighting Circuit Diagram and Details 3 1 6 7 1.0%Lighting Plan (1"=20') 1 2 16 18 2.5%Lighting Cirucit Diagram 1 1 4 5 0.7%Lighting Details 4 1 12 13 1.8%Cross Sections; 1"=5’ H: 1"=10' V - Recon. Section Only 16 2 8 16 24 50 7.0%Construction Details / IDOT District One Standards 8 2 8 16 26 3.6%

B. Pre-Final Special Provisions 8 24 2 34 4.7%C. Pre-Final Quantity Calculations 24 32 2 58 8.1%D. Pre-Final Estimate of Cost and Construction Time 2 2 0.3%E. Pre-Final QA/QC Review 8 8 8 24 3.3%F. Pre-Final Project Review Meetings 2 2 2 6 0.8%

Item 3 Subtotal 16 91 274 321 8 0 8 0 718 100.0%

Statement of Qualifications for Phase II Engineering ServicesRodenburg Road Improvements - Central Ave to Irving Park Rd (IL-19)Village of Schaumburg and Village of Roselle

COST PROPOSAL - WORKHOURS

4 Final (100%) Plans, Special Provisions and EstimatesA. Final Plans 2 12 24 32 2 72 50.7%B. Final Special Provisions 4 8 2 14 9.9%C. Final Quantity Calculations 16 16 2 34 23.9%D. Final Estimate of Cost and Construction Time 2 2 1.4%E. Final QC/QA Review 8 4 8 20 14.1%

Item 4 Subtotal 10 22 48 48 6 0 8 0 142 100.0%

5 Project Administration, Coordination and PermitsA. Project Administration 4 12 16 2.5%B. Project Submittals 4 8 16 28 4.3%C. Utility Company Coordination 8 80 88 13.5%D. GIS Integration 16 16 2.5%E. IDOT BLRS/NWMC/DMMC Coordination and Joint Agreement Preparation 2 8 1 11 1.7%F. Metra Railroad Coordination 4 24 12 40 6.2%G. FAA Coordination 4 16 20 3.1%H. Prepare/Update Wetland Delineation and Report 2 2 16 60 80 12.3%I. DuPage County Stormwater and Wetland Permitting and Documentation 2 4 20 24 50 100 15.4%J. MWRD Stormwater and Wetland Permitting and Documentation 2 4 20 24 40 90 13.8%K. USACE 404 Permitting and Documentation 2 4 20 20 40 86 13.2%L. Soil and Water Conservation District Permit 2 4 4 10 1.5%

M. PESA Response 2 4 16 22 3.4%N. NPDES Permitting and Documentation 1 2 8 8 19 2.9%O. Coordination with Appraisers and Negotiators 4 8 12 1.8%P. Bid Phase Assistance 4 4 8 1.2%Q. Pre-Construction Meeting Attendance 2 2 4 0.6%

Item 5 Subtotal 21 92 202 113 0 16 16 190 650 100.0%

Total Workhours: 61 283 807 812 14 18 36 190 2,221% of Workours: 2.7% 12.7% 36.3% 36.6% 0.6% 0.8% 1.6% 8.6% 100.0%

COST PROPOSAL - DIRECT COSTS

Item No.

TaskIn-House

Direct CostSub-Consultant

Cost

1 Early Coordination and Data Collection

Sub-Consultant: Midland Standard Engineering and Testing (Geotech) $19,405.00Sub-Consultant: Huff & Huff (Special Waste and CCDD Testing) $26,498.20Mileage: 4 trips @ 20 mi./round trip @ $0.56/mi. $44.80

Item 1 Subtotal $44.80 $45,903.20

2 Preliminary (65%) Engineering

Sub-Consultant: Jorgensen and Associates (Right-of-Way Documents) $22,720.22Sub-Consultant: Jorgensen and Associates (Supplemental Survey) $5,188.45Printing: $300.00Shipping: 8 packages @ $25/ea. $200.00Mileage: 2 trips @ 20 mi./round trip @ $0.56/mi. $22.40

Item 2 Subtotal $522.40 $27,908.67

3 Pre-Final (90%) Plans, Special Provisions and Estimates

Appraisals: Dave White (In-house Direct Cost)2 Parcels at $2,600 per parcel $5,200.00

Sub-Consultant: T Engineering (Review Appraisals)2 Parcels at $1,000 per parcel $2,000.00

Sub-Consultant: Santacruz Associates (Negotiations) $9,200.00Printing: $500.00Shipping: 8 packages @ $25/ea. $200.00Mileage: 2 trips @ 20 mi./round trip @ $0.56/mi. $22.40

Item 3 Subtotal $5,922.40 $11,200.00

Statement of Qualifications for Phase II Engineering ServicesRodenburg Road Improvements - Central Ave to Irving Park Rd (IL-19)

Village of Schaumburg and Village of Roselle

COST PROPOSAL - DIRECT COSTS

4 Final (100%) Plans, Special Provisions and Estimates

Printing: $500.00Shipping: 8 packages @ $25/ea. $200.00Mileage: 2 trips @ 20 mi./round trip @ $0.56/mi. $22.40

Item 4 Subtotal $722.40 $0.00

5 Project Administration, Coordination and Permits

Printing: $200.00Shipping: 4 packages @ $25/ea. $100.00Mileage: 2 trips @ 20 mi./round trip @ $0.56/mi. $22.40Permit Application Fee (NCCSWCD): $2,250.00Permit Application Fee (Kane-Dupage SWCD): $2,650.00Permit Application Fee (DuPage County): $2,750.00

Item 5 Subtotal $7,972.40 $0.00

Total In-House Direct Costs: $15,184.40 -Total Subconsultant Costs: - $85,011.87

TOTAL IN-HOUSE DIRECT & SUBCONSULTANT COSTS: $100,196.27

Statement of Qualifications for Phase II Engineering ServicesRodenburg Road Improvements - Central Ave to Irving Park Rd (IL-19)

Village of Schaumburg and Village of Roselle