Project Goal
Expand the VLBA’sdata-path bandwidth to
4 Gbps by 2011
Goal has been widely and frequently announced within the radio astronomy, astrometry, and geodesy communities. VLBA users are waiting to exploit it to enable a variety of
compelling new science.
7th US VLBI Technical Coordination Meeting
32009 / 11 / 3-4 – jdr
Implementation
Goal Corresponds to:2 IFs @ 500 MHz BW @ 2-bit Nyquist samples[i.e., retaining VLBA’s original IF system.]
New ElementsRDBE sampler/filter unit.Mark 5C recording system.DiFX software correlator.
7th US VLBI Technical Coordination Meeting
42009 / 11 / 3-4 – jdr
Project Status
DiFX Software Correlator OperationalComparisons with original VLBA correlator yielded excellent results.
Exactly matched integrations show amplitude and phase agreeing far better than realistic expectations.
Science use cases, analyzed by expert VLBA users, finding primarily limitations of data-analysis algorithms, not problems in correlator results.
DiFX alone enables some new scientific techniques.High spectral resolution.Wide-field imaging.Special pulsar processing.
Announced for correlation of all observations proposed Oct. 1.Observation trimester beginning mid-January.
Planning to ramp up use beginning as soon as possible.But DiFX can’t really come into its own without wideband observations.
7th US VLBI Technical Coordination Meeting
52009 / 11 / 3-4 – jdr
Status, continued
RDBE & Mark 5CAbsolutely central to achieving 4-Gbps goal.Some initial efforts successfully behind us:
ROACH final design, layout, exhaustive testing, beginning of production.Mark 5C concept design, development and production of 10 Gig E interface
mezzanine board.But both efforts have encountered schedule slippages, sufficient to
become serious concerns.Both NRAO &Haystack have major competing priorities: EVLA & MWA.Conduant also?
To recover schedule, we need to consider alternative approaches, possibly including
Additional personnel resources.(Matt Luce recently joined NRAO team, for FPGA development.)
Simplified, less comprehensive design “at least initially”.We hope to revisit these points throughout this meeting!