week 9 performance management erletshaqe

94
Project Management 9. Performance Management

Upload: juan-dela-cruz

Post on 21-Nov-2015

7 views

Category:

Documents


3 download

DESCRIPTION

Week 9 Performance Management

TRANSCRIPT

  • Project Management9. Performance Management

  • Week 9

  • Performance management

  • Once you have selected a project

  • Once you have selected a project

    And planned it

  • Once you have selected a project

    And planned it

    And hired the team

  • Once you have selected a project

    And planned it

    And hired the team

    And started the work

  • Once you have selected a project

    And planned it

    And hired the team

    And started the work

    How do you stay on track?

  • How do you even know if you are

    progressing to plan?

  • Gray & Larson, 2006, Ch 13.

  • What is a Project Monitoring System

    Examples of Progress Reports

    What is the Project Control Process and why is it useful?

    How do I Monitor Time Performance

    The shortcomings of monitoring Systems

    Earned Value Management a silver bullet?

    Integrated Cost/Schedule System

    Project Baselines

  • What is a Project Monitoring System?

  • It involves determining what data to collect, how, when an who will

    collect the data; analysis of the data; and reporting progress

    Monitoring System

    Gather Analyse Report

  • You need to know what

    information is needed to

    satisfy you and your

    stakeholders.

  • Think about the

    Information System

    Structure

  • What data are

    collected?

  • current status of project

    (schedule and cost)

    remaining cost to compete

    project

    date that project will be

    complete

    potential problems to be

    addressed now

    out-of-control activities

    requiring intervention

    Cost and/or schedule overruns

    & their reasons

    Forecasting overruns at time

    of completion

    What data are

    collected?

  • Collecting data and

    analysis

    who will collect project data?

    how will data be collected?

    when will the data be collected?

    who will compile and analyze the

    data?

    who will receive the reports?

    how will the reports be transmitted?

    when will the reports be distributed?

    Photo by germanium

  • What is a Project Monitoring System

    Examples of Progress Reports

    What is the Project Control Process and why is it useful?

    How do I Monitor Time Performance

    The shortcomings of monitoring Systems

    Earned Value Management a silver bullet?

    Integrated Cost/Schedule System

    Project Baselines

  • Progress Report Format

    Progress since last report

    Current status of project

    Schedule

    Cost

    Scope

    Problems and issues since last report

    Actions and resolution of earlier problems

    New variances and problems identified

    Corrective action planned

  • How long

    should a

    project

    status

    report be?

  • 1 page

  • office.microsoft.com/en-us/templates/TC011417231033.aspx

    http://saulcarliner.home.att.net/idbusiness/statusreport.htm

    http://www.projectperfect.com.au/info_status_report.php

    More info

    www.ic.arizona.edu/~profcomm/writing/samples/stat_samp_s1.htm

    www.projectconnections.com/knowhow/subsets/sample-templates/StatusReports.doc

  • What is a Project Monitoring System

    Examples of Progress Reports

    What is the Project Control Process and why is it useful?

    How do I Monitor Time Performance

    The shortcomings of monitoring Systems

    Earned Value Management a silver bullet?

    Integrated Cost/Schedule System

    Project Baselines

  • Project Control Process

  • The process of comparing actual performance against plan to identify

    deviations, evaluate courses of action, and take appropriate

    corrective action

    Pensiero

  • Project Control Steps

    Set and

    baseline a

    plan

    Measuring

    progress and

    performance

    Comparing the

    plan to the

    facts

    Taking Action

  • What is a Project Monitoring System

    Examples of Progress Reports

    What is the Project Control Process and why is it useful?

    How do I Monitor Time Performance

    The shortcomings of monitoring Systems

    Earned Value Management a silver bullet?

    Integrated Cost/Schedule System

    Project Baselines

  • Monitoring Time Performance

  • Monitoring Time Performance

    Tools used to catch negative variances from plan and communicate project schedule status:

  • Monitoring Time Performance

    Tools used to catch negative variances from plan and communicate project schedule status:

    Tracking and baseline Gantt charts

    show expected, actual, and trend data for event duration performance

  • Figure 13.1 Baseline Gantt Chart(Gray & Larson, 2006, p414)

    Time

    A Gantt Chart

  • Monitoring Time Performance

    Tools used to catch negative variances from plan and communicate project schedule status:

    Tracking and baseline Gantt charts

    show expected, actual, and trend data for event duration performance

    Control charts

    plot the difference in scheduled time on the critical path with the actual point on the critical path

  • Figure 13.2 Project Schedule Control Chart(Gray & Larson, 2006, p415)

    A Control Chart

  • What is a Project Monitoring System

    Examples of Progress Reports

    What is the Project Control Process and why is it useful?

    How do I Monitor Time Performance

    The shortcomings of monitoring Systems

    Earned Value Management a silver bullet?

    Integrated Cost/Schedule System

    Project Baselines

  • Monitoring Systems Disparities

    Picture by

    Pensiero

  • Time-Phase Baseline Plan

    Picture by

    Pensiero

  • Corrects the failure of most monitoring systems to

    connect a projects actual performance to its schedule and forecast budget

    Picture by

    Pensiero

  • Systems that measure only cost variances do not

    identify resource and project cost problems associated

    with falling behind or progressing ahead of schedule

    Picture by

    Pensiero

  • Earned Value Cost/Schedule System

    An integrated project management system based on the earned value

    concept that uses a time-phased budget baseline to compare actual

    and planned schedule and costs

    Picture by airgap

  • What is a Project Monitoring System

    Examples of Progress Reports

    What is the Project Control Process and why is it useful?

    How do I Monitor Time Performance

    The shortcomings of monitoring Systems

    Earned Value Management a silver bullet?

    Integrated Cost/Schedule System

    Project Baselines

  • Earned Value Management

  • What is Earned Value Management (EVM)?

  • What is Earned Value Management (EVM)?

    A project performance measurement technique

    that integrates scope, time, and cost data.

  • What is Earned Value Management (EVM)?

    A project performance measurement technique

    that integrates scope, time, and cost data.

    Given a baseline (original plan plus approved changes), you can

    determine how well the project is meeting its goals.

    You must enter actual information periodically to use EVM.

  • What is Earned Value Management (EVM)?

    A project performance measurement technique

    that integrates scope, time, and cost data.

    Given a baseline (original plan plus approved changes), you can

    determine how well the project is meeting its goals.

    You must enter actual information periodically to use EVM.

  • Terms to learn

    PV

    AC

    EV

    Planned Value

    Actual Cost

    Earned Value

    CV Cost Variance

    SV Schedule Variance

    CPICost Performance

    Indicator

    SPISchedule Performance

    Indicator

  • (Also called the budget)

    This is that portion of the approved

    total cost estimate planned to be

    spent on an activity during a given

    period

    PV Planned Value

  • The total of direct and indirect costs

    incurred in finishing work on an

    activity during a given period

    AC Actual Cost

  • An estimate of the value of the

    physical work actually completedEV Earned Value

  • Earned value minus the actual cost.

    Shows the difference between the

    estimated cost of an activity and the

    actual cost of that activity

    TABLE 13.1

    CV Cost Variance

  • Earned value minus the planned

    value. Shows the difference between

    the schedule completion of an

    activity and the actual completion of

    that activity

    TABLE 13.1

    SV Schedule Variance

  • The ratio of earned value to actual

    cost and can be used to estimate the

    projected cost of completing the

    project.

    If the CPI is equal to 1 or 100% then

    the planned and actual costs are

    equal, or the costs are as budgeted.

    If the CPI is less than 1 or less than

    100%, the project is over budget.

    If the CPI is greater than 1 or more

    than 100%, the project is under

    budget

    CPICost Performance

    Indicator

  • The ratio of earned value to planned

    value and can be used to estimate

    the projected time to complete the

    project.

    Similar to the CPI, an SPI of 1 or

    100% means the project is on

    schedule.

    If the SPI is greater than 1 or 100%

    then the project is ahead of

    schedule.

    If the SPI is less than 1 or 100%, the

    project is behind schedule

    SPISchedule Performance

    Indicator

  • TABLE 13.1

    Quick EVM quiz

    What can we say

    if CPI > 1

  • Quick EVM quiz

    What can we say

    if CPI > 1

    If the CPI is greater

    than 1 or more than

    100%, the project is

    under budget

  • Quick EVM quiz

    What is EV minus

    AC?

  • Quick EVM quiz

    What is EV minus

    AC?

    EV AC = SV

    Earned Value (what was done)

    Minus

    Actual Cost (what has been paid)

    =

    Schedule Variance

  • Scenario Example

  • Purchasing & Installing Web Server

    Duration 1 week,

    Budget $10,000.

    Scenario Example

  • Purchasing & Installing Web Server

    Duration 1 week, Budget $10,000.

    PV Planned Value for that activity for that week = $10,000

    AC Actual Cost suppose it actually took 2 weeks and cost $20,000. Assume $15,000 were incurred in week 1, and $5,000

    in week 2. These costs are the actual costs for that activity

    each week

    EV Earned Value earned value after one week is $7,500. (10,000 * 75%)

    Example: CP829_Lecture_Week9_EarnedValue.xls

    Scenario Example

  • Earned Value Chart for Project after 5-Months

  • Max Wideman

  • Rules for Earned Value Numbers

    Negative numbers for cost and schedule variance indicate problems in

    those areas

    The project is costing more than planned or taking longer than

    planned

    CPI and SPI less than 100% indicate problems

  • Table 13.3 Interpretation of Indexes

    (Gray & Larson, 2006, p429)

  • An alternative

    Source:

    http://www.mountaingoatsoftware.com/release_burndown

  • Week 2

    lecture

  • So, what do you do when your plan changes?

  • There are methods used to revise

    estimates of future project costs

    EVM allows experts in the field to change original baseline durations and costs because new information tells them the original estimates are not accurate

    EVM uses actual costs-to-date plus an efficiency index to project final costs in large projects where the original budget is unreliable

  • What is a Project Monitoring System

    Examples of Progress Reports

    What is the Project Control Process and why is it useful?

    How do I Monitor Time Performance

    The shortcomings of monitoring Systems

    Earned Value Management a silver bullet?

    Integrated Cost/Schedule System

    Project Baselines

  • Developing an Integrated Cost/Schedule System

  • Compute

    Calculate

    Collect

    Schedule

    Resource

    plan

    WBS

    Budget

    Pla

    nM

    onit

    or

  • Define the work using a WBS

    Scope

    Work packages

    Deliverables

    Organization units

    Resources

    Budgets

    Develop work and resource

    schedules

    Schedule resource to

    activities

    Time-phase work packages

    into a network

    Photo by shimonkey

  • Develop a time-

    phased budget

    using work

    packages

    included in an

    activity.

    Accumulate

    budgets (PV)

    At the work

    package level,

    collect the

    actual costs for

    the work

    performed (AC)

    Multiply

    percent

    complete times

    original budget

    (EV)

    Compute the

    schedule

    variance (EV-

    PV) and the

    cost variance

    (EV-AC)

  • Figure 13.3 Project Management Information Systems Overview(Gray & Larson, 2006, p419)

    Integrate

    d Cost/

    Schedules

  • What is a Project Monitoring System

    Examples of Progress Reports

    What is the Project Control Process and why is it useful?

    How do I Monitor Time Performance

    The shortcomings of monitoring Systems

    Earned Value Management a silver bullet?

    Integrated Cost/Schedule System

    Project Baselines

  • Project Baselines

  • Week 4

    lecture

  • a Baseline is an anchor

    point for measuring

    performance

    Photo by

    _Robert C_ @

    flickr

  • a planned cost and expected schedule

    against which actual cost and schedule

    are measured

    Gold by

  • a basis for cash flows and

    awarding progress payments

    Photo by quaziefoto

    @ flickr

  • a summation of time-phased

    budgets (cost accounts as

    summed work packages) along a

    project timeline

    Picture by Network

    Osaka @ flickr

  • What Costs Are Included in Baselines?

    Labor

    Equipment

    Materials

    Project direct overhead costs (DOC)

  • Figure 13.14 Scope Changes to a Baseline

    (Gray & Larson, 2006, p436)

  • What is a Project Monitoring System

    Examples of Progress Reports

    What is the Project Control Process and why is it useful?

    How do I Monitor Time Performance

    The shortcomings of monitoring Systems

    Earned Value Management a silver bullet?

    Integrated Cost/Schedule System

    Project Baselines

  • ReviewProject monitoring system include; data collection; analysis and

    reporting.

    Project control steps include; baseline plan, progress measurement,

    comparing actual against projected plan, and actions.

    Performance can be monitored using tools such as; tracking Gantts,

    control charts, baseline plans and earned value management.

    Earned value management (EVM) is a technique which incorporated

    scope, time and cost data to determine the health of the project.

    Integrated Cost/Schedule systems are developed creating; WBS,

    work/resource schedules, budget, and EVM.

    Project baselines are an anchor point for measuring performance.

  • ReferencesHorodyski, K. (1995). Managing and developing teams. Footscray, Vic.: Open

    Training Services.

    Greenberg, J. & Baron, R. (1993). Behavior in organizations (4th ed.). Syd.,

    NSW: Allyn and Bacon.

    Robbins, S., et al. (1998). Organisational behaviour (2nd ed.). Sydney:

    Prentice-Hall

  • www.dualibra.com

    Awesome title page picture by Derek Farr ( DetroitDerek )