week 9 performance management erletshaqe
DESCRIPTION
Week 9 Performance ManagementTRANSCRIPT
-
Project Management9. Performance Management
-
Week 9
-
Performance management
-
Once you have selected a project
-
Once you have selected a project
And planned it
-
Once you have selected a project
And planned it
And hired the team
-
Once you have selected a project
And planned it
And hired the team
And started the work
-
Once you have selected a project
And planned it
And hired the team
And started the work
How do you stay on track?
-
How do you even know if you are
progressing to plan?
-
Gray & Larson, 2006, Ch 13.
-
What is a Project Monitoring System
Examples of Progress Reports
What is the Project Control Process and why is it useful?
How do I Monitor Time Performance
The shortcomings of monitoring Systems
Earned Value Management a silver bullet?
Integrated Cost/Schedule System
Project Baselines
-
What is a Project Monitoring System?
-
It involves determining what data to collect, how, when an who will
collect the data; analysis of the data; and reporting progress
Monitoring System
Gather Analyse Report
-
You need to know what
information is needed to
satisfy you and your
stakeholders.
-
Think about the
Information System
Structure
-
What data are
collected?
-
current status of project
(schedule and cost)
remaining cost to compete
project
date that project will be
complete
potential problems to be
addressed now
out-of-control activities
requiring intervention
Cost and/or schedule overruns
& their reasons
Forecasting overruns at time
of completion
What data are
collected?
-
Collecting data and
analysis
who will collect project data?
how will data be collected?
when will the data be collected?
who will compile and analyze the
data?
who will receive the reports?
how will the reports be transmitted?
when will the reports be distributed?
Photo by germanium
-
What is a Project Monitoring System
Examples of Progress Reports
What is the Project Control Process and why is it useful?
How do I Monitor Time Performance
The shortcomings of monitoring Systems
Earned Value Management a silver bullet?
Integrated Cost/Schedule System
Project Baselines
-
Progress Report Format
Progress since last report
Current status of project
Schedule
Cost
Scope
Problems and issues since last report
Actions and resolution of earlier problems
New variances and problems identified
Corrective action planned
-
How long
should a
project
status
report be?
-
1 page
-
office.microsoft.com/en-us/templates/TC011417231033.aspx
http://saulcarliner.home.att.net/idbusiness/statusreport.htm
http://www.projectperfect.com.au/info_status_report.php
More info
www.ic.arizona.edu/~profcomm/writing/samples/stat_samp_s1.htm
www.projectconnections.com/knowhow/subsets/sample-templates/StatusReports.doc
-
What is a Project Monitoring System
Examples of Progress Reports
What is the Project Control Process and why is it useful?
How do I Monitor Time Performance
The shortcomings of monitoring Systems
Earned Value Management a silver bullet?
Integrated Cost/Schedule System
Project Baselines
-
Project Control Process
-
The process of comparing actual performance against plan to identify
deviations, evaluate courses of action, and take appropriate
corrective action
Pensiero
-
Project Control Steps
Set and
baseline a
plan
Measuring
progress and
performance
Comparing the
plan to the
facts
Taking Action
-
What is a Project Monitoring System
Examples of Progress Reports
What is the Project Control Process and why is it useful?
How do I Monitor Time Performance
The shortcomings of monitoring Systems
Earned Value Management a silver bullet?
Integrated Cost/Schedule System
Project Baselines
-
Monitoring Time Performance
-
Monitoring Time Performance
Tools used to catch negative variances from plan and communicate project schedule status:
-
Monitoring Time Performance
Tools used to catch negative variances from plan and communicate project schedule status:
Tracking and baseline Gantt charts
show expected, actual, and trend data for event duration performance
-
Figure 13.1 Baseline Gantt Chart(Gray & Larson, 2006, p414)
Time
A Gantt Chart
-
Monitoring Time Performance
Tools used to catch negative variances from plan and communicate project schedule status:
Tracking and baseline Gantt charts
show expected, actual, and trend data for event duration performance
Control charts
plot the difference in scheduled time on the critical path with the actual point on the critical path
-
Figure 13.2 Project Schedule Control Chart(Gray & Larson, 2006, p415)
A Control Chart
-
What is a Project Monitoring System
Examples of Progress Reports
What is the Project Control Process and why is it useful?
How do I Monitor Time Performance
The shortcomings of monitoring Systems
Earned Value Management a silver bullet?
Integrated Cost/Schedule System
Project Baselines
-
Monitoring Systems Disparities
Picture by
Pensiero
-
Time-Phase Baseline Plan
Picture by
Pensiero
-
Corrects the failure of most monitoring systems to
connect a projects actual performance to its schedule and forecast budget
Picture by
Pensiero
-
Systems that measure only cost variances do not
identify resource and project cost problems associated
with falling behind or progressing ahead of schedule
Picture by
Pensiero
-
Earned Value Cost/Schedule System
An integrated project management system based on the earned value
concept that uses a time-phased budget baseline to compare actual
and planned schedule and costs
Picture by airgap
-
What is a Project Monitoring System
Examples of Progress Reports
What is the Project Control Process and why is it useful?
How do I Monitor Time Performance
The shortcomings of monitoring Systems
Earned Value Management a silver bullet?
Integrated Cost/Schedule System
Project Baselines
-
Earned Value Management
-
What is Earned Value Management (EVM)?
-
What is Earned Value Management (EVM)?
A project performance measurement technique
that integrates scope, time, and cost data.
-
What is Earned Value Management (EVM)?
A project performance measurement technique
that integrates scope, time, and cost data.
Given a baseline (original plan plus approved changes), you can
determine how well the project is meeting its goals.
You must enter actual information periodically to use EVM.
-
What is Earned Value Management (EVM)?
A project performance measurement technique
that integrates scope, time, and cost data.
Given a baseline (original plan plus approved changes), you can
determine how well the project is meeting its goals.
You must enter actual information periodically to use EVM.
-
Terms to learn
PV
AC
EV
Planned Value
Actual Cost
Earned Value
CV Cost Variance
SV Schedule Variance
CPICost Performance
Indicator
SPISchedule Performance
Indicator
-
(Also called the budget)
This is that portion of the approved
total cost estimate planned to be
spent on an activity during a given
period
PV Planned Value
-
The total of direct and indirect costs
incurred in finishing work on an
activity during a given period
AC Actual Cost
-
An estimate of the value of the
physical work actually completedEV Earned Value
-
Earned value minus the actual cost.
Shows the difference between the
estimated cost of an activity and the
actual cost of that activity
TABLE 13.1
CV Cost Variance
-
Earned value minus the planned
value. Shows the difference between
the schedule completion of an
activity and the actual completion of
that activity
TABLE 13.1
SV Schedule Variance
-
The ratio of earned value to actual
cost and can be used to estimate the
projected cost of completing the
project.
If the CPI is equal to 1 or 100% then
the planned and actual costs are
equal, or the costs are as budgeted.
If the CPI is less than 1 or less than
100%, the project is over budget.
If the CPI is greater than 1 or more
than 100%, the project is under
budget
CPICost Performance
Indicator
-
The ratio of earned value to planned
value and can be used to estimate
the projected time to complete the
project.
Similar to the CPI, an SPI of 1 or
100% means the project is on
schedule.
If the SPI is greater than 1 or 100%
then the project is ahead of
schedule.
If the SPI is less than 1 or 100%, the
project is behind schedule
SPISchedule Performance
Indicator
-
TABLE 13.1
Quick EVM quiz
What can we say
if CPI > 1
-
Quick EVM quiz
What can we say
if CPI > 1
If the CPI is greater
than 1 or more than
100%, the project is
under budget
-
Quick EVM quiz
What is EV minus
AC?
-
Quick EVM quiz
What is EV minus
AC?
EV AC = SV
Earned Value (what was done)
Minus
Actual Cost (what has been paid)
=
Schedule Variance
-
Scenario Example
-
Purchasing & Installing Web Server
Duration 1 week,
Budget $10,000.
Scenario Example
-
Purchasing & Installing Web Server
Duration 1 week, Budget $10,000.
PV Planned Value for that activity for that week = $10,000
AC Actual Cost suppose it actually took 2 weeks and cost $20,000. Assume $15,000 were incurred in week 1, and $5,000
in week 2. These costs are the actual costs for that activity
each week
EV Earned Value earned value after one week is $7,500. (10,000 * 75%)
Example: CP829_Lecture_Week9_EarnedValue.xls
Scenario Example
-
Earned Value Chart for Project after 5-Months
-
Max Wideman
-
Rules for Earned Value Numbers
Negative numbers for cost and schedule variance indicate problems in
those areas
The project is costing more than planned or taking longer than
planned
CPI and SPI less than 100% indicate problems
-
Table 13.3 Interpretation of Indexes
(Gray & Larson, 2006, p429)
-
An alternative
Source:
http://www.mountaingoatsoftware.com/release_burndown
-
Week 2
lecture
-
So, what do you do when your plan changes?
-
There are methods used to revise
estimates of future project costs
EVM allows experts in the field to change original baseline durations and costs because new information tells them the original estimates are not accurate
EVM uses actual costs-to-date plus an efficiency index to project final costs in large projects where the original budget is unreliable
-
What is a Project Monitoring System
Examples of Progress Reports
What is the Project Control Process and why is it useful?
How do I Monitor Time Performance
The shortcomings of monitoring Systems
Earned Value Management a silver bullet?
Integrated Cost/Schedule System
Project Baselines
-
Developing an Integrated Cost/Schedule System
-
Compute
Calculate
Collect
Schedule
Resource
plan
WBS
Budget
Pla
nM
onit
or
-
Define the work using a WBS
Scope
Work packages
Deliverables
Organization units
Resources
Budgets
Develop work and resource
schedules
Schedule resource to
activities
Time-phase work packages
into a network
Photo by shimonkey
-
Develop a time-
phased budget
using work
packages
included in an
activity.
Accumulate
budgets (PV)
At the work
package level,
collect the
actual costs for
the work
performed (AC)
Multiply
percent
complete times
original budget
(EV)
Compute the
schedule
variance (EV-
PV) and the
cost variance
(EV-AC)
-
Figure 13.3 Project Management Information Systems Overview(Gray & Larson, 2006, p419)
Integrate
d Cost/
Schedules
-
What is a Project Monitoring System
Examples of Progress Reports
What is the Project Control Process and why is it useful?
How do I Monitor Time Performance
The shortcomings of monitoring Systems
Earned Value Management a silver bullet?
Integrated Cost/Schedule System
Project Baselines
-
Project Baselines
-
Week 4
lecture
-
a Baseline is an anchor
point for measuring
performance
Photo by
_Robert C_ @
flickr
-
a planned cost and expected schedule
against which actual cost and schedule
are measured
Gold by
-
a basis for cash flows and
awarding progress payments
Photo by quaziefoto
@ flickr
-
a summation of time-phased
budgets (cost accounts as
summed work packages) along a
project timeline
Picture by Network
Osaka @ flickr
-
What Costs Are Included in Baselines?
Labor
Equipment
Materials
Project direct overhead costs (DOC)
-
Figure 13.14 Scope Changes to a Baseline
(Gray & Larson, 2006, p436)
-
What is a Project Monitoring System
Examples of Progress Reports
What is the Project Control Process and why is it useful?
How do I Monitor Time Performance
The shortcomings of monitoring Systems
Earned Value Management a silver bullet?
Integrated Cost/Schedule System
Project Baselines
-
ReviewProject monitoring system include; data collection; analysis and
reporting.
Project control steps include; baseline plan, progress measurement,
comparing actual against projected plan, and actions.
Performance can be monitored using tools such as; tracking Gantts,
control charts, baseline plans and earned value management.
Earned value management (EVM) is a technique which incorporated
scope, time and cost data to determine the health of the project.
Integrated Cost/Schedule systems are developed creating; WBS,
work/resource schedules, budget, and EVM.
Project baselines are an anchor point for measuring performance.
-
ReferencesHorodyski, K. (1995). Managing and developing teams. Footscray, Vic.: Open
Training Services.
Greenberg, J. & Baron, R. (1993). Behavior in organizations (4th ed.). Syd.,
NSW: Allyn and Bacon.
Robbins, S., et al. (1998). Organisational behaviour (2nd ed.). Sydney:
Prentice-Hall
-
www.dualibra.com
Awesome title page picture by Derek Farr ( DetroitDerek )