willbros a good job on time hydrostatic testing practices establishing verifiable, traceable, and...

21
WILLBROS A Good Job On Time Hydrostatic Testing Practices Establishing Verifiable, Traceable, and Accurate Documentation August 20, 2013 Hal Ozanne Willbros Engineers

Upload: rosalind-anderson

Post on 22-Dec-2015

216 views

Category:

Documents


0 download

TRANSCRIPT

WILLBROSA Good Job On Time

Hydrostatic Testing PracticesEstablishing Verifiable, Traceable,

and Accurate Documentation

August 20, 2013

Hal OzanneWillbros Engineers

WILLBROS

2

Hydrostatic Testing Practices

• Verifiable, Traceable, Accurate Documentation Hydrostatic Testing Calculations Hydrostatic Test Plans Hydrostatic Test Reports Data Collection and Final Verification

• Pipeline and Hazardous Materials

Safety Administration (PHMSA) Audits Record Keeping Approvals/Signatures

WILLBROS

3

Hydrostatic Testing Practices

• Hydrostatic Testing Calculations Detailed calculations based on pipe characteristics and specifications

– OD, wt, grade, weld/seam type, length of segment

– Flange or no flanges (ANSI rating could be limiting factor for pressure)

– Based on 100% SMYS or 125% MAOP

– Surveyed pipe elevations

– Test medium, volume, and temperature constraints

Segment lengths based on elevations and SMYS requirements

Project Management Review and Approval– Engineering Project Manager

– Client Project Manager

WILLBROS

4

Hydrostatic Testing Practices

• Hydrostatic Testing Calculations MAOP Verification calculated and determined by final hydro test results

TEST SEGMENT 1 PIPE UNITS

Pipe OD (in) 12.75 IN

Pipe WT (in) 0.25 IN

Pipe Grade 60,000 PSI

MAOP (psig) 1,440 PSIG

Segment Legnth (ft) 100,000 FT

Design Factor 0.72 Determined by Class Location

Required Testing Factor 1.25 Based on design factor for the Class Location

SMYS Pressure 2,353 PSIG

DETERMINE WHICH MINIMUM TEST PRESSURE BELOW WILL BE USED AT HIGH POINT OF TEST SEGMENT

Minimum Test Pressure 1,800 Per code based on required testing factor and MAOP

Minimum Test Pressure 2,118 = 90% SMYS

Selected Min Test Pres. 2,118 PSIG

DETERMINE WHICH MAXIMUM TEST PRESSURE BELOW WILL BE USED AT LOW POINT OF TEST SEGMENT

Maximum Test Pressure 2,160 Test Factor of 1.5 based on 1.25 min test pressure above

Maximum Test Pressure 2,353 = 100% SMYS

Selected Max Test Pres. 2,353 PSIG

612,211 GAL

14,576 BBL

CHECK NOTES BELOW REGARDING DEAD WEIGHT PRESSURES COMPARED TO TEST PRESSURES

Dead Weight Pres. Min 2,118 PSIG

Dead Weight Pres. Max 2,353 PSIG

Dead Weight Elevation 5,902 FT

STATION # TEST PSIG % SMYS CALCULATED MAOP

Begin Point Elevation, FT 5,902 0+00 Calculated Min Test Pressure 2,247 95.5% Test pressure is within range of minimum and maximum test pressure 1,618

Begin Point Elevation, FT 5,902 0+00 Calculated Max Test Pressure 2,219 94.3% Test pressure is within range of minimum and maximum test pressure N/A

Low Point Elevation, FT 5,594 1107+35 Calculated Min Test Pressure 2,381 101.2% TEST PRESSURE OUT OF ACCEPTABLE RANGE - CHECK SEGMENT 1,714

Low Point Elevation, FT 5,594 1107+35 Calculated Max Test Pressure 2,353 100.0% Test pressure is within range of minimum and maximum test pressure N/A

High Point Elevation, FT 6,201 590+86 Calculated Min Test Pressure 2,118 90.0% Test pressure is within range of minimum and maximum test pressure 1,525

High Point Elevation, FT 6,201 590+86 Calculated Max Test Pressure 2,090 88.8% TEST PRESSURE OUT OF ACCEPTABLE RANGE - CHECK SEGMENT N/A

End Point Elevation, FT 5,650 1278+29 Calculated Min Test Pressure 2,357 100.2% Test pressure is within range of minimum and maximum test pressure 1,697

End Point Elevation, FT 5,650 1278+29 Calculated Max Test Pressure 2,329 99.0% Test pressure is within range of minimum and maximum test pressure N/A

Elevation Change 607 FT

Note 1:

Note 2:

Note 3:

If the test pressure calcualted at any point along the test segment is less than the minimum test pressure, then the minimum dead weight pressure required will need to be increased, provided it does not exceed the maximum test pressure.If the test pressure calculated at any point along the test segment is greater that the maximum test pressure, then the maximum dead weight pressure required will need to be lowered provided that the new lower maximum test pressure is not below the minimum required test pressure.If the minimum and maximum dead weight test pressure range cannot be adjsuted within the test segment to keep the test pressure within the range of the minimum and maxiumum test pressure, the the test segment will need to be broken into smaller segments.

Test Segment Volume

WILLBROS

5

Hydrostatic Testing Practices

• Hydrostatic Test Plan Set it up right and make it fully complete with Environmental Input

– To comply with permits, environmental needs to be involved to ensure compliance (BLM, Corps of Engineers, FERC, NEPA, etc)

– Advise on supply sources and discharge areas

Fabrication Test (4hr) or Mainline Test (8 hr)– Fabrication Test for HDDs and long bores prior to installation

– Mainline Test for mainline (including HDDs) once in ground

WILLBROS

6

Hydrostatic Testing Practices

• Hydrostatic Test Plan Environmental Requirements and Stipulations

– Water Source

– Discharge Location

– Water Quality

Detailed to describe all parts of Hydro Test– Filling and pressuring up

– Performing Test

– Gathering Data

– Completion of test

– Dewatering of segment

– Move water from one segment to the next or new water each segment

– Drying and Cleaning

– Final Verification and sign off

WILLBROS

7

Hydrostatic Testing Practices

• Hydrostatic Test Plan Max and min test pressures for each Segment

– Provide location of expected occurrence in plan

– Provide expected test site location pressure

DOT/PHMSA Requirements (also use API RP1110)– Depends on type of test (spike test, strength test, leak

test)

– Pressure test medium, equipment, and materials

– Qualifications of contractor and personnel performing test

– Test period, failures, leaks

– Test records and drawings kept for useful life of pipeline

– Approval Signatures (operator of test, witness of test, personnel certifying the test)

WILLBROS

8

Hydrostatic Testing Practices

• Hydrostatic Test Plan Acceptance Criteria established prior to conducting test

Proper Approvals and Signatures– Project Engineer

– Project Manager

– Construction Manager

– Client Project Manager

WILLBROS

9

Hydrostatic Testing Practices

• Hydrostatic Test Report Set it up in the beginning so that all data required to be gathered is

understood by test operators

Based on Operating Company Standards and DOT/PHMSA Requirements (also API RP 1110)

Attention to Detail

WILLBROS

10

Hydrostatic Testing Practices

• Hydrostatic Test Report Proper Recording of Measurements

– Pipe Diameter and wall thicknesses

– Pipe Grade and SMYS and/or ANSI rating

– Location and elevation

– Test Medium description, source, and volumes

– Any additives description and volumes

– Date and time of start and stops

– Pressure vs. Time log

– Temperature (ambient and pipe or test medium)

– Weather conditions

– Segment length

WILLBROS

11

Hydrostatic Testing Practices

• Hydrostatic Test Report Completeness of Forms and Records

Proper Approvals and Signatures– Test Operator

– Operator Supervisor

– Construction Manager

– Project Engineer

– Client Authorized Representative (can be construction manager or project engineer in many cases)

WILLBROS

12

Hydrostatic Testing Practices

• Hydrostatic Test Data Collection Planning and Preparation

Understanding Test Report and Forms– Anyone involved in the test or reviewing/approving of the test data

– Allows those involved to know exactly what is required to be gathered and what is required to be approved based on what is provided

Maintain and Include Raw Data Gathered into Final Test Report Book

WILLBROS

13

Hydrostatic Testing Practices

• Hydrostatic Test Data Collection Calibration of Instruments and Equipment

– High volume pump and associated piping and meter for line fill

– Injection pump for corrosion inhibitors, leak detection dyes or gases, or other chemicals

– Variable speed PD pump for pressurization with known volume per stroke and a stroke counter

– Pressure sensing device and deadweight tester

– Continuous pressure recording device

– Test medium temperature sensing device and display

– Ambient temperature sensing device and display

– Continuous temperature recording device for test medium and ambient

– Test medium sampling equipment

– Gas/oxygen detecting equipment

WILLBROS

14

Hydrostatic Testing Practices

• Hydrostatic Test Data Collection Collecting/Recording All Details and Information Required on Reports

and Forms– Test medium volumes, pressures, temperatures, times

– Ambient pressures, temperatures, weather conditions

– Pipe conditions and specifications (OD, wt, grade, high/low point, etc)

– Instrument/Equipment calibration information

– Failures, leaks, condition changes

– Approvals

Maintain and Clean up All Field Notes on Drawings and Books– Incorporate into overall Test Report

Maintain All Failure Record Data for Final Book

WILLBROS

15

Hydrostatic Testing Practices

• Hydrostatic Test Data Collection Temperature Recorders

– Weather condition changes can affect volume of test medium to maintain constant pressure on pipeline

– Secure temperature bulb directly to bare pipe, insulate, and backfill to ground level 12 hr prior to test

– 12 hr allows for fill medium, pipe, and ground temps to stabilize

– Locate temperature bulbs on pipe a minimum of 500’ from exposed pipe

WILLBROS

16

Hydrostatic Testing Practices

• Hydrostatic Test Data Collection Temperature Changes

– As temp increases, pressure increases

– As temp decreased, pressure decreases

– Temp changes can affect volume of medium in pipe

– Important to not conduct test during periods of day when temperature change is significant (frost levels play important role in test temperature as well)

WILLBROS

17

Hydrostatic Testing Practices

• Hydrostatic Test Data Collection Small Leak or Change in Temperature?

– Compare change in pipe temp to change in weather conditions

– Change in pipe temp should correlate to change in ambient temp (changes show up on temperature plot for test)

– Corrected volume equations at beginning and end of test account for change in pressure and temperature which correlates to change in volume

– Spreadsheet set up to determine corrected volumes - part of test plan/report

Test Start Date: Test End Date:

(24 Hr. Clock)

Month Day, Year Month Day, Year Readings should be taken every 15 minutes for test

TEMP. TEMP. REMARKS: (Note any additions/withdrawals of test medium, start and stop of test, pressure reductions, weather changes, or anything else that may affect the test.Buried Pipe, 1 Buried Pipe, 2

TIME OBS. PRESSURE TEMP. TEMP.

(Deadweight Reading) Ambient Exposed Pipe

Test Supervisor Signature

Test Operator Signature

* Contractor shall provide means of volumetric changes to line prior to test.

WILLBROS

18

Hydrostatic Testing Practices

• Final Verification Verify that final book is complete and contains all information in one

location– Hydro Test Plan and Calcs

– Test specifications

– Survey data

– Calibration certificates

– Hydro test reports

– Original test charts

WILLBROS

19

Hydrostatic Testing Practices

• Final Verification If all required data is in one place, then it is easier to gather, maintain,

and deliver to auditors Ensure that the following people have signed off on the Test Report and

Data Collected– Field Person Responsible for Gathering Data

– Field Supervisor Over Hydro Test

– Construction Manager

– Project Engineer

– Project Manager

– Client Project Manager

WILLBROS

20

Hydrostatic Testing Practices

• PHMSA Audits

– Checks during construction to verify proper records being kept

– Documentation is the first thing to be checked during a field audit

– First impression set the tone for the audit

Record Keeping– Records should have proper approvals and signatures on them

– Should be same throughout duration of project

– Fabrication testing (HDDs) and Mainline testing (main pipeline)

Documentation Approvals/Signatures– Checks for field personnel, engineering personnel, and Company personnel

signatures and approvals of test records and reports

WILLBROSA Good Job On Time

www.willbros.com