wind power expansion: key development and integration issues

33
Wind Power Expansion: Wind Power Expansion: Key Development and Integration Key Development and Integration Issues Issues Issues Impacts Myths Kansas Wind and Prairie Task Force Meeting Kansas Wind and Prairie Task Force Meeting March 19, 2004 Topeka, Kansas March 19, 2004 Topeka, Kansas Ed DeMeo Renewable Energy Consulting Services, Inc. National Wind Coordinating Committee Member (EPRI Renewable Energy Programs, 1976- 1998)

Upload: isha

Post on 11-Feb-2016

52 views

Category:

Documents


0 download

DESCRIPTION

Wind Power Expansion: Key Development and Integration Issues. Issues. Impacts. Myths. Ed DeMeo Renewable Energy Consulting Services, Inc. National Wind Coordinating Committee Member (EPRI Renewable Energy Programs, 1976-1998). Kansas Wind and Prairie Task Force Meeting - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Wind Power Expansion: Key Development and Integration Issues

Wind Power Expansion:Wind Power Expansion:Key Development and Integration IssuesKey Development and Integration Issues

IssuesImpacts

Myths

Kansas Wind and Prairie Task Force MeetingKansas Wind and Prairie Task Force MeetingMarch 19, 2004 Topeka, KansasMarch 19, 2004 Topeka, Kansas

Ed DeMeoRenewable Energy Consulting Services, Inc.

National Wind Coordinating Committee Member(EPRI Renewable Energy Programs, 1976-1998)

Page 2: Wind Power Expansion: Key Development and Integration Issues

Major IssuesMajor Issues

Costs (capital, energy, O&M)

Transmission Requirements

Wind Variability Impacts

Environmental Benefits and Impacts

Siting and Permitting

Economic Development Benefits

Citizens’ Views and Utility Responses

Page 3: Wind Power Expansion: Key Development and Integration Issues

Wind Energy Cost Trend

1979: 40 cents/kWh

• Increased Turbine Size

• R&D Advances• Manufacturing

Improvements• Operating

Experience

NSP 107 MW Lake Benton wind farm4 cents/kWh (unsubsidized)

2004: 3 - 5 cents/kWh(no subsidy)

2000:4 - 6 cents/kWh(no subsidy)

Page 4: Wind Power Expansion: Key Development and Integration Issues

Natural Gas SituationNatural Gas Situation

Today’s tight natural gas markets have been a long time in coming, and distant futures prices suggest that we are not apt to return to earlier periods of relative abundance and low prices anytime soon

– Alan Greenspan, Federal Reserve Chairman, Testimony at Senate hearing, July 10, 2003

Wellhead gas costs - 2002-2003: $3 - $5/MMBTU

Page 5: Wind Power Expansion: Key Development and Integration Issues

Cost ComparisonCost Comparison

Wind total capital cost: $1,000 - $1,100 kW today

Wind energy cost: about 3¢/kWh (4¢ without PTC)Wind energy cost: about 3¢/kWh (4¢ without PTC)

Includes 0.5 to 1.0¢/kWh for O&M

Wind energy costs are Wind energy costs are stable stable over plant lifetimeover plant lifetime

Natural-gas plant fuel cost (HR 7,000 - 10,000)

$/MMBTU: 2 4 5 6 8 gas cost

¢/kWh: 1.4 - 2 2.8 - 4 3.5 - 5 4.2 - 6 5.6 - 8 fuel only Wind-gas synergy: save gas when wind blows; burn Wind-gas synergy: save gas when wind blows; burn

gas to provide system reliability during low windsgas to provide system reliability during low winds

Page 6: Wind Power Expansion: Key Development and Integration Issues

Transmission RequirementsTransmission Requirements

In general, transmission costs make up less than 10% of customers’ electricity bills

Good winds are often remote, so transmission is needed

Usually worthwhile to extend lines to access a good site

Cost of 25 to 50 miles of transmission may add only 10% to total wind plant cost

Active debate over allocation of these costs

But siting is highly contentious

And financing is a major challenge

Widely accepted principles needed for considering transmission additions (new NWCC product)

Page 7: Wind Power Expansion: Key Development and Integration Issues

Large Transmission Investments Have Large Transmission Investments Have Very Small Retail Bill ImpactsVery Small Retail Bill Impacts

Average Monthly Retail Bill: $ / 1,000 kWhAverage Monthly Retail Bill: $ / 1,000 kWh

Total $65.75 Total $66.62Transmission 6%

Generation 74%

Distribution 20%

Source: FERCSource: FERC

75

60

45

30

15

0

Impact from $12.6 billion increase

(20%) in Transmission Infrastructure

4.58

48.66

13.38

3.71

48.66

13.38

$ / m

onth

$ / m

onth

Current Average Retail Bill

Bill With Added Transmission

Page 8: Wind Power Expansion: Key Development and Integration Issues

Wind Variability:Wind Variability: Impact onImpact on Transmission AccessTransmission Access

Firm Transmission Rights • Blocks for specified

times• Underutilized by wind• Too costly

Wind-plant financing requires assured path to market

Transmission often contractually constrained -- but not physically

Non-Firm Rights• Can be curtailed, but

often OK for wind• Not available long-term• Insufficient assurance

Middle ground? Flexible-firm?

Page 9: Wind Power Expansion: Key Development and Integration Issues

Time (hour of day)0 4 8 12 16 20 24

System Load (MW)

seconds to minutes

Regulation

tens of minutes to hours

LoadFollowing

day

Scheduling

Days

UnitCommitment

• Regulation -- seconds to a few minutes -- similar to variations in customer demand (loads)

• Load-following -- tens of minutes to a few hours -- usage follows predictable patterns, wind less so

• Scheduling and commitment of generating units -- one to several days -- wind impacts unclear

Wind VariabilityWind Variability:: Power-System Operation ImpactsPower-System Operation Impacts

Wind controlled by nature, not power-plant operators!

Page 10: Wind Power Expansion: Key Development and Integration Issues

Wind VariabilityWind Variability Can Increase Can Increase Power System Operating CostsPower System Operating Costs

• Committing unneeded generation • Scheduling unneeded generation• Allocating extra load-following capability• Violation of system performance criteria • Increased cycling operation• These are reflected in ancillary services costs

Incremental cost added by wind’s variability?Utility Wind Interest Group case study:

$1.85/MWh of wind energy (<10% of value)

Page 11: Wind Power Expansion: Key Development and Integration Issues

System Operating Costs Impacts: System Operating Costs Impacts: Results from Recent Studies (Results from Recent Studies ($/MWh)$/MWh)

StudyUWIG/Xcel

Pacificorp

BPA/Hirst

We Energies (a)

We Energies (b)

Penetra- tion (%)

3.5

20

7

4

29

Regula- tion

0

0

0.19

1.12

1.02

Load- Follow

0.41

2.5

0.28

0.09

0.15

Unit- Commit

1.44

3.0

1.40

0.69

1.75

Total Total ImpactImpact

1.851.85

5.55.5

1.871.87

1.901.90

2.922.92

Page 12: Wind Power Expansion: Key Development and Integration Issues

Environmental Environmental ImpactsImpacts

Avian mortality: raptors and migrating songbirds Wind now: about 50,000 out of about 1 billion Effective procedures to avoid problem locations

Wildlife habitat Some local issues; productive dialog underway

Visual Highly subjective Concerns often subside after installation

Property values Studies show no negative impacts

Noise no longer an issue

We need to evaluate environmental impacts on a relative basis. No energy-generation approach is without impacts.

The choice is wind vs. something -- not wind vs. nothing.

Page 13: Wind Power Expansion: Key Development and Integration Issues

Environmental Environmental BenefitsBenefits

No emissionsNo emissions of any kind during operation No SOx, NOx, particulates or mercury No contributions to regional haze Hedge against environmental regulations No greenhouse gases

Global climate changeGlobal climate change is a serious concern to every major political entity worldwide exceptexcept the current Administration in Washington, DC Avoidance not politically sustainable in the U.S. or

worldwide No toxic wastes or health impactsNo toxic wastes or health impacts

Nuclear waste transport and storage unresolved Respiratory diseases of growing concern

Page 14: Wind Power Expansion: Key Development and Integration Issues

What Does Energy What Does Energy Really Cost?Really Cost?

Nuclear power Federal government underwrites accident liability Waste-handling costs significant and unknown

Coal power Respiratory concerns becoming prominent $350 M/yr to coal miners with black lung disease Numerous health-costs estimates: 2 - 4¢/kWh

(highly uncertain but not zero) Oil and gas

Depletion allowances DOD expenses to maintain supply channels

These costs are paid in tax and health bills -- not electricity bills. The federal Production Tax Credit

(PTC) for wind compensates to a degree

Page 15: Wind Power Expansion: Key Development and Integration Issues

Wind Plant Siting and PermittingWind Plant Siting and Permitting

The wind industry is now mature; major players are responsible, thorough, sophisticated and responsive

Widely accepted siting and permitting guidelines NWCC: Permitting of Wind Energy Facilities, August

2002 (available at www.nationalwind.org) AWEA: Industry best practices under development

Siting case studies to be undertaken immediately by NWCC

Cardinal Rule: Early and significant involvement of the local community is critical

Page 16: Wind Power Expansion: Key Development and Integration Issues

Economic Development OpportunitiesEconomic Development Opportunities

Land Lease Payments: 2-3% of gross revenue ($2500-4000/MW/year)

1-2 jobs/MW during construction 2-5 permanent O&M jobs per 50-100 MW, Local construction and service industry:

concrete, towers, some electrical Local property tax revenue: 100 MW brings in

about $500,000/yr Equity investors and lenders: returns on

investment, interest payments Potential for manufacturing and assembly

plants (e.g., blade factory in ND)

Page 17: Wind Power Expansion: Key Development and Integration Issues

NWCC Economic NWCC Economic Development ReportDevelopment Report

Assessing the Economic Development Impacts of Wind Power

Northwest Economic AssociatesVancouver, WA

February 2003

available at www.nationalwind.org

Highlights for NWCC Business Meeting June 18, 2003 Norman, OK Ed DeMeo

Page 18: Wind Power Expansion: Key Development and Integration Issues

Project ObjectivesProject Objectives

• Methodology: Assemble credible approach for evaluating positive and negative impacts of wind power development

• Illustration by Example: Exercise methodology in three case-study locations

• Results: Obtain quantitative results for the three locations; identify common economic experiences

• Limitations: Describe limitations in data, method and results

Page 19: Wind Power Expansion: Key Development and Integration Issues

Methodology (I)Methodology (I)

• Identify Project Phases: Separate the analysis into two phases: (a) Construction and (b) Operation and Maintenance

• Identify Inputs: Determine products and services necessary to conduct each phase; monetize these

• Identify Sources of Inputs: Usually the majority are external to the region; those from within the region have the greatest impact -- focus most effort here

• Approach Project Developer: Best source of inputs, but information often proprietary

Page 20: Wind Power Expansion: Key Development and Integration Issues

Methodology (II)Methodology (II)

• Interview Local Sources: Contact local suppliers of services and goods; also local government offices

• Estimate Direct Effects: How many local residents employed; where did workers from outside stay; how did they spend their money; what items were provided locally;etc. These constitute first round of buying and selling, or direct effects.

• Estimate Indirect and Induced Effects: Income from direct effects enables subsequent rounds of buying and selling, resulting in indirect effects. Increases in household income result in additional local spending or induced effects.

Page 21: Wind Power Expansion: Key Development and Integration Issues

Methodology (III)Methodology (III)

• Use Established Economic Model to Estimate These Effects: These models contain detailed, annually updated descriptions of hundreds of economic sectors by county. NEA used IMPLAN. Ratio of all effects to direct effects is called multiplier.

• Apply Reality Check to Supplement Model Results: Some jobs can be buried too deeply in the model to stand out clearly.

• Consider Returns on Invested Capital: In all cases NWCC has studied, the capital came from external sources. Returns on investment can be a significant local impact, so should be addressed directly.

Page 22: Wind Power Expansion: Key Development and Integration Issues

Results:Results:Economic SnapshotEconomic Snapshot

County Lincoln MN Culberson TX Morrow OR Umatilla OR

Wind Plant 107 MW 30 MW <----25 MW (shared)---->

Population 6,429 2,975 10,995 70,548

Employment 3,523 1,565 5,344 39,267

Earnings $62.9M $33.4M $114.4M $970.0M

Unempl Rate 3.5% 10.2% 12.0% 6.4%

Income (p.c.) $19,935 $14,803 $16,841 $22,024

Below Pov Lev 12% 32.6% 7.0% 15.6%

Page 23: Wind Power Expansion: Key Development and Integration Issues

County Lincoln Culberson MorrowUmatilla

Wind Plant 107 MW 30 MW <----25 MW (shared)---->

Personal Income Construction $98,400 $391,300 $105,400

O&M $909,200 $346,100 $103,600

Employment (jobs) Construction 8 jobs 26 jobs 4 jobs

O&M 31 jobs 11 jobs 6 jobs

Taxes (annual)O&M only $611,200 $387,300 $241,580

Landowner Revenues (annual)O&M only $501,125 $51,000 $64,300

Results (I): Wind-Results (I): Wind-Development ImpactsDevelopment Impacts

Page 24: Wind Power Expansion: Key Development and Integration Issues

County Lincoln Culberson MorrowUmatilla

Wind Plant 107 MW 30 MW <----25 MW (shared)---->

Personal Income ($/MW) Construction 920 13,040 4,220

O&M 8,500 11,540 4,140

Employment (jobs/MW) Construction 0.08 0.87 0.16

O&M 0.29 0.37 0.24

Taxes (annual $/MW)O&M only 5,710 12,910 9,660

Landowner Revenues (annual $/MW)O&M only 4,680 1,700 2,570

Results (II): Wind-Results (II): Wind-Development ImpactsDevelopment Impacts

Page 25: Wind Power Expansion: Key Development and Integration Issues

Qualitative General Qualitative General ResultsResults

• Wind development boosts local economic activity

• New jobs are created -- some for construction and some for O&M

• Beneficial tax effects occur• Redistribution of tax burden increases household income• Or increased tax revenues can improve local infrastructure

• Land-leasing revenues increase household income

• Several other points:• Low multiplier effects in rural areas; many inputs from outside• Wind impacts more important in areas with depressed economies• Local investment would keep returns on capital local

Page 26: Wind Power Expansion: Key Development and Integration Issues

Major LimitationsMajor Limitations• Obtaining needed data is likely to be difficult; need to gather

information from many local sources to overcome problem

• Results limited to one county (two for OR project)• Impacts on adjacent counties can be just as important• Presents incomplete picture of local impact

• Need to consider larger regions to get representative picture

• Although qualitative impacts are expected to transfer from region to region, quantitative results will vary substantially in different regions.

• Without in-depth on-the-ground local investigation, Without in-depth on-the-ground local investigation, economic benefits almost certainly underestimated.economic benefits almost certainly underestimated.

Page 27: Wind Power Expansion: Key Development and Integration Issues

Citizens’ Views on Wind Citizens’ Views on Wind Energy and Utility ResponsesEnergy and Utility Responses

Ask customers how they feel about renewables

Solid positive response across the nation

Can offer green-priced product in response

Green pricing helped get the ball rolling, but it may be an idea whose time has come and gone

Strong positive response from the customer base justifies addition and ratebasing of wind power

Almost everyone is willing to pay a small premium -- and they may not need to!

Page 28: Wind Power Expansion: Key Development and Integration Issues

Nebraska Public Power District Nebraska Public Power District Deliberative Polling Deliberative Polling

Customer Meeting on Energy AlternativesCustomer Meeting on Energy Alternatives

• NPPD Customer Meeting on Energy Alternatives held August 9, 2003 in Grand Island, NE

• 109 participants from 80 Nebraska communities served at Retail or by Wholesale Distributors.

• Great discussion on Energy Generation Alternatives including coal, natural gas, wind, methane and solar.

Page 29: Wind Power Expansion: Key Development and Integration Issues

96% 94%

2% 1% 2%5%

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

Yes No Don't know

Do you think NPPD should go forward with a 200 megawatt wind farm?

Without tax incentive With tax incentive

Page 30: Wind Power Expansion: Key Development and Integration Issues

How do you feel NPPD should invest in renewable energy?

Don't know4%

By building for customers who

commit and having them pay.

2%

By building for all customers and divide

the cost among all.94%

Page 31: Wind Power Expansion: Key Development and Integration Issues

Contrasting Approaches to ChangeContrasting Approaches to Change

Europe Wind power is environmentally preferred. How can we best accommodate it within the existing power system?

U.S. How can we integrate wind into the existing system with minimal impact on traditional rules and procedures?

Wind needs fair -- not preferential -- treatment in the marketplace. This is most likely with leadership from the public-policy sector.

Page 32: Wind Power Expansion: Key Development and Integration Issues

Who Should Take the Lead?Who Should Take the Lead?

Power Utilities? No– Main job: Keep the lights on!– Natural aversion to change

Legislators and Regulators?– Encouragement of wind and

other renewables is a public policy issue

Bottom Line: States can make a commitment to wind power without fear of breaking the bank!

Page 33: Wind Power Expansion: Key Development and Integration Issues

Affordable costs

Hedge gas price volatility

Operational synergy

Environmentally responsible

Economic development opportunities

Is Wind Power a Prudent Investment?