Digital I&C Systems Configuration Management

Presented By:

David E WoodsSenior Engineer – Electrical/I&C Design Engineering

June 21, 2011

2

Digital I&C Systems Configuration Management

Gaps Digital I&C Systems Standards, Guides and

Regulatory Requirements EPRI Digital I&C CM Guidelines

3

Gaps

The proliferation of diverse digital I&C equipment for plant upgrades and equipment replacements has challenged station personnel to develop and implement effective configuration management methods.

4

Gaps

High level requirements and guidance provided by industry standards are not being effectively translated into practical methods to manage the configuration of digital I&C equipment.

5

Digital I&C Systems

Wide Range of Applications & Technology

6

Digital I&C Systems

Architecture and Expanse of a Complex Digital System

7

Digital I&C Systems

Hardware & Software Tightly Integrated

Digital systems hardware and software are much more tightly integrated and far more pervasive throughout plant systems. Therefore, the traditional approach to handling software design (and configuration management) in digital systems is not always adequate.

The hardware and software components of a digital system cannot be adequately controlled separately from each other.

The integration of the hardware and software is paramount to achieving a high quality system and adequate system integrity.

8

Digital I&C Systems

Digital Systems Configuration Items

• more than just software

• they include – hardware items – configuration data items– document and media items– setpoints, tuneable parameters, end user

parameters

9

Digital I&C Systems

Digital System Layer

Digital System Layer

Interface LayerHardware Layer

Software Layer

Platform Layer

Interface LayerHardware Layer

Software Layer

Application Layer

Digital System Layer

I&C Layer

Mechanical Layer

Electrical Layer

Plant System

© 2002 ProDesCon - Used with permission

10

Standards, Guides andRegulatory Requirements

CM is governed by an elaborate array of industry committees, regulatory bodies, and benchmarking activities.

11

EPRI Digital I&C CM Guideline

EPRI Guideline on Configuration Management for Digital Instrumentation

& Control Equipment and Systems

1022991

Project Manager: Ray Torok - [email protected]

Program Manager: Robert Austin - [email protected]

12

EPRI Digital I&C CM Guideline

Provides focused guidance for implementing configuration management for digital I&C equipment and systems. It addresses both software and hardware issues.

Best practices and effective methods are identified and developed into practical guidance for utility engineers and their contractors.

13

EPRI Digital I&C CM Guideline

Identifies the requirements, explain the issues and options, and provides examples of effective methods and good practices, including detailed guidance that can be used by utility engineers in developing procedures.

Addresses the finer points of digital CM, including methods for identifying hardware and software configuration items, controlling application logic, controlling configuration data, and optimizing and controlling documentation.

14

EPRI Digital I&C CM Guideline

Differentiates methods for user-controlled data, tunable parameters, Technical Specification (T/S) set points and other data sets.

Complements existing methods for design control, document control, parts control, and other Appendix B program criteria.

15

Basic principles underlying Digital Configuration Management

Digital CM is not a program separate from other safety or management programs and serves as an integrating activity rather than a stand-alone functional or operational program.

Digital CM must, therefore, be integrated with existing plant programs and policies.

16

Interfacing Plant Programs

17

Digital I&C CM Guidelines - Topics

Definition of the critical elements of digital systems configuration management

Digital systems configuration management processes that address the unique and integrated nature of digital system hardware and software

Documentation methods that address the needs of various users (e.g., design & system engineers, vendors, operations and maintenance personnel)

18

Digital I&C CM Guidelines - Topics

Change control methods that are rigorous, but flexible enough to address various kinds of changes such as:

– Design & Equivalent Engineering Changes– Set points – Minor Changes below the threshold of an Engineering

Change – Field Configurable Parameters – Field Tuning – Calibration Settings – Maintenance Changes – Problem/Error Correction

19

Digital I&C CM Guidelines - Topics

Methods to achieve integration with the overall Plant Configuration Management Processes

Sample/Guide Procedures that incorporate effective, best practice methods

20

Digital Configuration Management Methods and Procedures

Identifying Configuration Items Configuration Control Configuration Status Accounting Configuration Audits, Internal Reviews and Self

Assessments Interface Control Contractor/Vendor Control

21

Identifying Configuration Items

• Identifying Software Configuration Items (CI) • Identifying Data Configuration Items • Identifying Backup and Disaster Recovery

Libraries • Identifying Engineering Tool Configuration Items • Identifying Document Configuration Items • Relationship Between Digital CIs and Existing

Plant CM Programs • Configuration Items that May Require Digital

Configuration Controls

22

Configuration Control• Establishing Baselines • Changes to Configuration Items • Change Initiation • Changes Under the Engineering Change

Process • Other Changes • Software Configuration Management Plans

(SCMP) • Media Control • Graded approach

23

Configuration Status Accounting

• Software Configuration Item Releases and Versions

• Software Configuration Item Libraries• System Images • Backup and Restoration

• Configuration Status Accounting Metrics

24

Configuration Audits, Internal Reviews and Self Assessments

• Configuration Audits

• Configuration Reviews

• Self Assessments

25

Interface Control

• Interface with Plant Design Basis Requirements

• Interfaces Between Software Configuration Items

• System Data Interfaces• System Boundaries

26

Contractor/Vendor Control

• Contractor Activities and Products

• Vendor Products

• Lifeycle Interfaces

27

EPRI Digital I&C CM Guideline

Planned to be published by the end of 2011

EPRI Guideline on Configuration Management for Digital Instrumentation

& Control Equipment and Systems

1022991

Project Manager: Ray Torok - [email protected] Program Manager: Robert Austin - [email protected]

28