19001447 ewt annual construction monitoring report 2019

201
i May 26, 2020 August 20, 2020 – Revised NEXTBRIDGE INFRASTRUCTURE LP 2019 Compliance Report for EastWest Tie Transmission Line Project EA File No 030303; EA Reference No 13136

Upload: others

Post on 18-Feb-2022

6 views

Category:

Documents


0 download

TRANSCRIPT

i

May 26, 2020  

August 20, 2020 – Revised  

NEXTBRIDGE INFRASTRUCTURE LP 

2019 Compliance Report for East‐West Tie  

Transmission Line Project 

EA File No 03‐03‐03; EA Reference No 13136 

ii  

  

TABLE OF CONTENTS 

1 INTRODUCTION ................................................................................................................ 4

1.1 CONSTRUCTION ACTIVTIES DURING 2019 ..................................................................... 4

2 CONSTRUCTION MONITORING COMPONENTS ................................................................. 5

2.1 DPP STATUS TRACKER ................................................................................................... 7

2.2 WF CONSTRUCTION SCHEDULE ..................................................................................... 7

2.3 ONGOING CONSULTATION ............................................................................................ 8

2.4 COMPLAINT REPORTING ............................................................................................. 11

2.5 EA COMMITMENTS ..................................................................................................... 12

2.6 GEOLOGY, TERRAIN, AND SOILS .................................................................................. 12

2.7 SURFACE WATER ......................................................................................................... 12

2.8 GROUNDWATER .......................................................................................................... 17

2.9 AIR QUALITY ................................................................................................................ 17

2.10 GREENHOUSE GASES ................................................................................................... 17

2.11 ACOUSTIC ENVIRONMENT........................................................................................... 17

2.12 VEGETATION AND WETLANDS ..................................................................................... 17

2.13 FISH AND FISH HABITAT .............................................................................................. 19

2.14 WILDLIFE AND WILDLIFE HABITAT ............................................................................... 20

2.15 RECLAMATION CONCERNS .......................................................................................... 20

2.16 ARCHAEOLOGICAL RESOURCES ................................................................................... 20

2.17 CULTURAL HERITAGE RESOURCES ............................................................................... 23

2.18 TRADITIONAL LAND AND RESOURCE USE .................................................................... 23

2.19 SOCIO‐ECONOMICS ..................................................................................................... 23

2.20 NON‐TRADITIONAL LAND AND RESOURCE USE ........................................................... 24

2.21 VISUAL ENVIRONMENT ............................................................................................... 24

2.22 HUMAN HEALTH .......................................................................................................... 24

2.23 ENVIRONMENTAL PROTECTION PLAN ......................................................................... 24

3 CONCLUSIONS ................................................................................................................ 24

 

   

iii  

 

FIGURES 

1  Project Route 

 

TABLES 

1  DPP Status Tracker 

2  WF Construction Schedule and Status 

3  Complaint Log 

4  Monitoring ESC Measures 

5  Monitoring Water Quality 

6  Water Taking 

7  Monitoring Water Body Crossing 

8  Water Quality Monitoring in Sensitive Areas 

9  Monitoring Soil Piles 

10  Monitoring for Weeds 

11  Monitoring of Water Body Installations 

12  Monitoring of Archaeological Resources 

 

ATTACHMENTS 

A  Table 2‐1 Commitments and Compliance Monitoring  

B  Table 3‐1 EA Act Approval Conditions Compliance Monitoring 

 

   

 

1 INTRODUCTION 

This annual compliance report describes the programs and practices that NextBridge Infrastructure LP (NextBridge) has implemented prior to and throughout the construction phase of the East‐West Tie Transmission Project (the Project) during 2019.    This report details compliance with the construction monitoring commitments made in the Environmental Assessment (EA No. 13136), Minister’s 41 EA Act Approval Conditions, Detailed Project Plan (DPP), and general environmental protection measures listed in the Construction Environmental Protection Plan (CEPP).   Specifically, this annual report follows the plan outlined in the Environmental Assessment Compliance Monitoring Program (EACMP), the Section 23.1.1 Table 23.1 of the EA and Section 2.4.4.8 Table 2.15 of the DPP.  

1.1 CONSTRUCTION ACTIVTIES DURING 2019 

Figure 1. Project Route 

  Project construction has been divided into eleven segments, also known as Workfronts (WFs). Construction of the Project started in October 2019 with the release of partial permits within WFs 1 and 2 and included the following activities. 

Right‐of‐way surveying and flagging 

Right‐of‐way clearing and access 

Access road construction 

Water body crossing installations 

Foundation installation 

Assembly of infrastructure components   

 

2 CONSTRUCTION MONITORING COMPONENTS 

As outlined in the DPP, the NextBridge construction team is comprised of a Senior Project Manager, Construction Manager, Construction Inspectors, Environmental Lead, Environmental Coordinator, Environmental Monitors, Valard (the constructor) Construction Manager, Construction Superintendents, Supervisors, Foremen, Environmental Manager, Environmental Coordinators, Environmental Inspectors (EI), and Resources Specialists. The EI and Resource Specialists monitor construction activities to ensure the implementation of the approved best management practices (BMPs), protection measures, and construction monitoring program.   To ensure the Project complies with all 1,061 commitments outlined in the EA, NextBridge and Valard have teams in place to track, complete, and follow up on the commitments assigned to each entity such as Owner, Contractor, and Operations during each phase of the Project including pre‐construction, construction, and post‐construction/operations. Specifically, Valard has created an Environmental Management System (EMS) to aid in tracking the contractor’s construction compliance.   The Valard EMS is an overarching systematic process by which compliance with the Project CEPP and/or regulatory requirements can be consistently achieved across the Project. The EMS includes tools to support environmental management, monitoring and reporting (i.e., risk assessment and pre‐screening, mitigation planning, monitoring, document control, reporting and communications). The EMS is designed to ensure that: 

Project environmental constraints, commitments, permit conditions or other 

regulatory or stakeholder and Indigenous requirements are proactively 

identified, documented, understood and communicated before mobilization or 

construction activities begin; 

Valard staff and contractors receive adequate environmental awareness training 

and that Project‐specific environmental issues and risks are discussed during 

routine project orientation, team meetings and tailboard discussions; 

The proposed project construction schedule is achievable within known or 

suspected work timing constraints, or adjusted accordingly; 

While construction activities are taking place, environmental constraints, 

commitments, permit conditions or other regulatory or stakeholder and 

Indigenous requirements are adhered to; 

Environmental compliance performance is monitored, tracked and/or 

documented to the NextBridge and/or regulatory standards and requirements; 

and, 

User feedback, technological updates and/or lessons learned are routinely 

reviewed and incorporated to promote continuous improvement of the EMS. 

 

The Valard EMS tools utilized on the Project to support compliance include:  

EMS Tracking Table: Valard’s primary tool for all task and issue tracking for 

environmental compliance on the Project. The EMS Tracking Table is used to 

assign accountability and timelines for the actions required to maintain 

compliance and the construction schedule. 

Permit Condition Matrix: Used to track permit specific compliance requirements 

on the Project and provide visibility on when and how key permit conditions 

have been met. 

EA Compliance Matrix: Used by Valard to track EA commitments on the Project. 

Environmental Monitoring and Field Data Reports: 

o Daily Environmental Monitoring Report: Used by Valard environmental 

field staff to record daily observations and photos in support of 

environmental compliance. Information collected in the daily reports 

covers multiple environmental compliance themes including erosion and 

sediment control, water crossing and water quality, environmental 

monitoring and site‐specific inspections. 

o Wildlife Sighting Forms: Used by Valard environmental field staff to 

collect all wildlife observations on the Project to satisfy Project 

requirements. 

o Environmental Incident Notifications and Incident Reports: Used to 

notify and report all environmental incidents on the Project. Includes 

reporting for all spills and ‘other’ incidents such as trespass, permit 

condition non‐compliance, etc. 

o Pre‐construction Survey Forms: Records data collected during the pre‐

construction surveys. Includes field validation and flagging of mapped 

environmental features based on the Environmental Alignment 

Sheets/DPPs and collection of data for new features. Includes delineation 

of wetlands, rare vegetation, watercourses, and habitat features such as 

dens, stick nests, etc. 

o Wildlife Survey Forms: Used to collect wildlife survey data for raptors, 

migratory birds, amphibians, etc. Surveys will be conducted to support 

construction activities as required based on timing periods outlined in the 

Project CEPP. 

The following sections provide monitoring activities separated by topic.  

 

 

2.1 DPP STATUS TRACKER 

Please see below for the updated DPP status tracker.  

Table 1. DPP Status Tracker 

WF ID  DPP Type  Status/Remarks 

Overarching DPP  Overarching  Approved 

WF 1  WF Specific  Approved 

WF 2 WF Specific  Approved 

Parks  Black Sturgeon River Provincial Park ‐ Approved 

WF 3 

WF Specific  Approved 

Parks  Ruby Lake Provincial Park ‐ Submitted 

Conservation 

Reserve 

Kama Cliffs Conservation Reserve & Gravel River 

Conservation Reserve – In Progress 

WF 4 

WF Specific  Approved 

Parks  Gravel River Provincial Park – In Progress 

Conservation 

Reserve Gravel River Conservation Reserve – In Progress 

WF 5  WF Specific  Approved 

WF 6  WF Specific  Approved 

WF 7  WF Specific  Approved 

WF 8 

WF Specific  Approved 

Conservation 

Reserve 

Kwinkwaga Ground Moraine Uplands Conservation 

Reserve ‐ Submitted 

WF 9 WF Specific  Approved 

Parks  Pukaskwa River Provincial Park – Submitted 

WF 10 WF Specific  Approved 

Parks  Nimoosh Provincial Park – In Progress 

WF 11  WF Specific  Approved 

2.2 WF CONSTRUCTION SCHEDULE 

Please see below for the updated WF construction schedule and status which reflects the current schedule at the end of 2019.  

Table 2. Workfront Construction Schedule and Status 

WF ID 

Construction Schedule  

(estimated timelines and dates)  Status/Remarks 

WF 1  Construction commenced October 2019  In Progress 

WF 2  Construction commenced October 2019  In Progress 

 

WF ID 

Construction Schedule  

(estimated timelines and dates)  Status/Remarks 

WF 3  Construction to commence March 2020  Not Started 

WF 4  Construction to commence July 2020  Not Started 

WF 5  Construction to commence August 2020  Not Started 

WF 6  Construction to commence  January 2020  Not Started 

WF 7  Construction to commence January 2020  Not Started 

WF 8  Construction to commence February 2020  Not Started 

WF 9  Construction to commence February 2020  Not Started 

WF 10  Construction to commence December 2020  Not Started 

WF 11 Construction to commence September 

2020 Not Started 

2.3 ONGOING CONSULTATION 

NextBridge has undertaken ongoing engagement and consultation activities with the 18 identified Indigenous communities, non‐Indigenous communities, property owners, and other potentially impacted individuals and groups. The ongoing engagement and consultation activities include routine updates regarding the environmental and socio‐economic components of the Project, in‐person issues resolution meetings, teleconference briefings, field participation, technical updates, and the provision of capacity funding. The below information outlines specific highlights of engagement and consultation efforts associated with conditions outlined in the approved amended EA.   

2.3.1 Indigenous Monitoring Program  

The provincial approval of the Project’s EA on March 25, 2019 and NextBridge’s commitments to building relationships with Indigenous groups involved with the Project included conditions associated with the Indigenous Monitoring Program. NextBridge is continuing to consult with Indigenous communities during the construction of the Project and is providing these communities with the opportunity to be involved in ongoing engagement and environmental monitoring.  NextBridge clarified that the Indigenous Monitoring Program (Indigenous Facilitator Program) would be focused on ensuring the Aboriginal and Treaty rights of the communities were being respected through the construction and mitigation measures being implemented. The details of the program were enumerated, in cooperation with Indigenous communities, in the Indigenous Facilitation Plan of June 2019.  NextBridge retained Supercom Industries LP (Supercom) as the overall administrator for the Indigenous Facilitation Program; however, communities were responsible for 

 

appointing their respective Indigenous Facilitator (up to 2 individuals, with only 1 on‐site at any given time) to engage in this important work, in partnership with the non‐Indigenous environmental monitors.   As a part of this structure, Supercom is responsible for managing the program administration while the Indigenous Facilitators are independent and accountable to their respective Chief and Council. Paramount to the decision to partner with Supercom was the desire to ensure a safe working environment for the Indigenous Facilitators.   Prior to the commencement of construction, traditional land ceremonies, organized in collaboration with Indigenous communities, were also held across the Project area prior to tree clearing activities. Furthermore, in October 2019, all community‐appointed Indigenous Facilitators received training at the beginning of their employment term. Training was focused on traditional knowledge, environmental monitoring, reporting, and safety on the construction site.   Supercom, in partnership with NextBridge and subcontractor Atwell Consulting (Canada) ULC, (Atwell) assigned seven Indigenous Facilitators from seven Indigenous communities in the field on a daily basis to monitor the construction activities. NextBridge engages in ongoing communication with Project partners, Indigenous Facilitators, and Indigenous communities to improve the Indigenous Facilitator Program structure and delivery.  

2.3.2 Indigenous Traditional Knowledge and Values  

NextBridge continued to offer the opportunity for the incorporation of feedback and Traditional Ecological Knowledge provided by Indigenous communities throughout 2019. The Project has committed to ongoing collaboration, issues resolution, and consultation with the communities if new information becomes available. Beyond this work, any sites identified as being of cultural/archeological significance are protected and/or avoided by utilizing mitigation measures to ensure construction activities do not adversely impact the sites. In the event of a discovery of an unknown site during construction, contingency plans and mitigation measures will be immediately implemented to prevent impacts and to ensure protocols implemented adhere to the Indigenous Land and Resource Use Site Contingency Plan and the Discovery of Heritage or Archaeological Resources Contingency Plan.   

2.3.3 Permitting Workshops and Review 

Throughout 2019, NextBridge consistently notified all 18 identified Indigenous communities of the opportunity to review all WF DPPs. This notification was conducted at the same time as notification to regulators such as the Ministry of Natural Resources and Forestry (MNRF). As part of the notification process, the 18 identified Indigenous communities were offered an opportunity to access a secure SharePoint site that stored 

10 

 

all WF DPP documentation and mapping. If access was not sufficient through the SharePoint site, NextBridge had also offered the materials in other formats including pre‐loaded USB keys, hard copies, etc. if requested. NextBridge requested communities to provide the Project with comments or feedback within 30 days of the notification. NextBridge also communicated to the Indigenous communities that if issues arose in the future, they could raise them directly with NextBridge and efforts would be undertaken to address the issue. Engagement and consultation with Indigenous communities on the Project is ongoing and continual.  NextBridge has conducted numerous permitting workshops which were made available to all 18 Indigenous communities and continues to work directly with the communities on their reviews of the DPPs and permitting documents. To ensure Indigenous communities had the ability to participate in this review, NextBridge offered capacity funding to each community that had been engaged.  With regard to consultation specific to Provincial Parks & Conservation Reserves DPPs, NextBridge has notified all 18 Indigenous communities of the availability of applicable DPP documentation for review. NextBridge has provided interested communities with associated Provincial Parks & Conservation Reserves DPPs and mapping linked to any parks of interest, where applicable.   NextBridge has consistently reassured Indigenous communities that throughout the pursuit of authorizations for the remaining DPPs and permits, engaging with communities on permit‐specific concerns is an ongoing process. NextBridge remains committed to addressing concerns at any point, even post issuance of permits.  

2.3.4 Economic and Employment Opportunities  

NextBridge, in partnership with Supercom, provides information on work and procurement opportunities to the 18 identified Indigenous communities. Supercom works closely with Valard to hire qualified candidates from Indigenous communities. Current employment opportunities and procurement processes can be found on the Supercom website (www.supercomindustries.com/employment) and are updated regularly for public access.    

2.3.5 Ongoing Engagement and Consultation  

NextBridge is committed to providing Indigenous communities, non‐Indigenous communities, property owners, and other potentially impacted individuals and groups with ongoing updates regarding construction schedules and timetables. As the Project progresses through the permitting and construction phases, NextBridge will continue to update the anticipated schedule posted on the Project website (www.NextBridge.ca).  

11 

 

NextBridge has documented and responded to inquiries and questions received from Indigenous communities, non‐Indigenous communities, property owners, and other potentially impacted individuals and groups with respect to the Project. Ongoing engagement has promoted open dialogue, bringing new interests and concerns to the forefront as the Project progresses. NextBridge has committed to addressing issues and concerns in collaboration Indigenous communities, non‐Indigenous communities, property owners, and other potentially impacted individuals and groups as they arise. With respect to Indigenous communities, NextBridge is demonstrating an understanding that knowledge sharing, and awareness of traditional Indigenous values are not fixed or finite.    Consistent with the conditions in the approved EA, NextBridge continues to provide regulators with monthly Records of Consultation  (both Indigenous and non‐Indigenous logs) that include updates on all Project consultation and engagement activities. Summaries of engagement with non‐Indigenous communities, property owners, and other potentially impacted individuals and groups are regularly reported in the East‐West Tie Line Quarterly Construction Report which is submitted to the Ontario Energy Board each quarter.  

2.4 COMPLAINT REPORTING 

Please see below for the summary of complaints that were reported through the established protocol in 2019.  

Table 3. Complaint Log 

Date 

Received 

Date 

Resolved  Complaint Information 

Resolution 

Status 

       

10/09/2019  10/29/2019 

The property owner contacted the Land Agent to address 

the implementation of a gate on his property prior to 

construction as committed to by NextBridge in a 

Commitment Letter 

10/29/19 ‐ The landowner agreed to have a third party 

install the gate and NextBridge would reimburse for 

expenses. 

Resolved 

10/13/2019  ‐‐ 

The property owner requested construction activities on 

the ROW be stopped until the impending appraisal on the 

parcel is complete and payment for the ROW was 

received.   

02/28/20 ‐ The property owner requested compensation 

for driveway damage and believes an aquifer on the 

property has been damaged by construction activities. 

Ongoing 

12 

 

Date 

Received 

Date 

Resolved  Complaint Information 

Resolution 

Status 

       

11/22/2019  ‐‐ 

The property owner contacted the Land Agent regarding 

aggregate on the parcel. 11/26/19 – Construction is 

coordinating with the property owner for resolution.  

Ongoing 

11/25/2019  11/25/2019 

The Land Agent called the municipality office to inquire 

about replacing the damaged property owner sign. The 

municipality suggested that the sign has been temporarily 

fixed and will be permanently replaced when construction 

leaves the area.  

Resolved 

12/17/2019  ‐‐ 

The property owner contacted the Land Agent to notify 

that the merchantable timber was not delimbed when it 

was processed as it was requested in prior negotiations.  

Ongoing 

 

2.5 EA COMMITMENTS 

Please see Attachment A and Attachment B for Table 2‐1 and Table 3‐1 depicting compliance during the 2019 construction activities.  

2.6 GEOLOGY, TERRAIN, AND SOILS 

As outlined in Section 23.1.1 Table 23.1 of the EA, no monitoring programs are proposed or required for this Project.  

2.7 SURFACE WATER 

2.7.1 Monitoring Soil Erosion and Sediment Control Practices 

The Project is following the erosion and sediment control (ESC) practices as outlined in the DPP and CEPP.  The ESC measures being implemented by the construction team includes Ontario Provincial Standard Specifications (OPSS) BMPs 21‐29:  

Silt fence 

Straw bale barrier 

Berm barrier 

Brush or rock berm 

Check dam 

Fibre rolls and wattles 

Diversion ditches 

Temporary stream diversions 

13 

 

 The overall Project ESC plan is outlined in Section 8.1 and Appendix J of the CEPP. The Valard EMS provides the tools Valard utilizes to track and document compliance with the Project ESC plans. When site‐specific ESC plans are developed, the EMS Tracking Table and Daily Environmental Monitoring Reports are used to track ESC prescriptions (e.g., actions and timelines) and monitor effectiveness. 

Table 4. Monitoring ESC Measures 

WF ID 

Number of ESC 

Weekly Inspections  ESC Location IDs 

1  8 118.00, 120.00, 121.00, 4771.00, 4790.00, 4801.00, 

4860.01, 4950.01, 4960.02 

2  N/A  N/A 

 

2.7.2 Monitoring Water Quality 

During the 2019 construction activities, one culvert was installed at water crossing ID 4950.01 between structures A039 and A040. All other water crossings were clear span bridges that did not require in‐water work. During the installation of the culvert at water crossing ID 4950.01 the Project followed the water quality monitoring commitments outlined in the DPP and CEPP during construction to ensure the regulatory permit requirements and approval were adhered to. These commitments included but were not limited to turbidity, total suspended solids (TSS), streamflow rate, and water level monitoring. Compliance was achieved by regular site inspections and monitoring by the EIs during construction to monitor the water quality at the water crossing location.  As part of the construction monitoring, the EIs utilize the EMS to record and document each construction monitoring site inspection. Specifically, the following water crossings were installed during 2019. 

Table 5. Monitoring Water Quality  

Water Crossing ID  Crossing Method 

Date of EI 

Inspection 

Technique(s) Used to Ensure 

Compliance 

4801.00  Clear‐span Oct 7, Nov 6, Nov 

25, 2019 Active monitoring and ESC  

4790.00  Clear‐span Oct 24, Nov 4, 6, 

25, 2019 Active monitoring and ESC 

4860.01  Clear‐span Oct 25, Nov 6 – 7, 

2019 Active monitoring and ESC 

120.00  Clear‐span  Oct 25 ‐ 27, 2019  Active monitoring and ESC 

118.00  Timber‐mat  Oct 24, 2019  Active monitoring and ESC 

14 

 

Water Crossing ID  Crossing Method 

Date of EI 

Inspection 

Technique(s) Used to Ensure 

Compliance 

4950.01  Culvert  Dec 18, 2019  Active monitoring and ESC 

4960.02  Clear‐span  Dec 1 – 2, 8, 2019  Active monitoring and ESC 

121.00  Clear span  Dec 1 – 2, 2019  Active monitoring and ESC 

5321.00  Clear‐span  Dec 19, 2019  Active monitoring and ESC 

5740.00  Clear‐span  Dec 17 – 18, 2019  Active monitoring and ESC 

 

2.7.3 Monitoring Water Taking or Discharging 

As part of construction activities in 2019, the Project conducted water taking activities for use in mixing grout as part of the installation of transmission structure foundations and guy anchors. The water taking activities have not exceeded 50,000 litres per day. The table below lists each water taking event: 

Table 6. Water Taking   

Water Taking Location 

Date (Day, 

Month, Year)  Volume (L) 

McGregor Road Access  22/11/2019  3,407 

McGregor Road Access  23/11/2019  3,029 

McGregor Road Access  24/11/2019  1,136 

McGregor Road Access  05/12/2019  2,650 

McGregor Road Access  06/12/2019  2,650 

McGregor Road Access  07/12/2019  2,461 

McGregor Road Access  08/12/2019  2,271 

Beck Road Access  10/12/2019  2,650 

Beck Road Access  12/12/2019  2,366 

Beck Road Access  13/12/2019  3,596 

Beck Road Access  15/12/2019  3,123 

A007, 4801.00  05/12/2019  3,028 

A007, 4801.00  07/12/2019  2,650 

A007, 4801.00  08/12/2019  3,785 

A007, 4801.00  10/12/2019  3,785 

A007, 4801.00  11/12/2019  2,271 

A007, 4801.00  13/12/2019  3,785 

A007, 4801.00  15/12/2019  3,785 

15 

 

Water Taking Location 

Date (Day, 

Month, Year)  Volume (L) 

A007, 4801.00  16/12/2019  2,650 

A007, 4801.00  17/12/2019  1,893 

 

2.7.4 Monitoring Water Body Crossings 

The Project is following the water body crossing monitoring commitments outlined in Section 6.2.1 of the CEPP during construction to ensure the regulatory permit requirements and approvals are adhered to. This is achieved by regular site inspections and monitoring by the EIs during construction to monitor the installation method(s) at each water crossing location.  As part of the construction monitoring, the EIs utilize the EMS to record and document each construction monitoring site inspection. Specifically, the following water crossings and/or roadside drainage culverts were installed in 2019. 

Table 7. Monitoring Water Body Crossings 

Water Crossing ID  Crossing Method 

Date of EI 

Inspection 

Technique(s) Used to 

Ensure Compliance 

4801.00  Clear‐span 

Oct 7, Nov 6, 

Nov 25, 

2019 

Active monitoring and ESC  

4790.00  Clear‐span 

Oct 24, Nov 

4, 6, 25, 

2019 

Active monitoring and ESC 

4860.01  Clear‐span Oct 25, Nov 

6 – 7, 2019 Active monitoring and ESC 

120.00  Clear‐span Oct 25 ‐ 27, 

2019 Active monitoring and ESC 

118.00  Timber‐mat  Oct 24, 2019  Active monitoring and ESC 

4950.01  Culvert  Dec 17, 2019  Active monitoring and ESC 

4960.02  Clear‐span Dec 1 – 2, 8, 

2019 Active monitoring and ESC 

121.00  Clear span Dec 1 – 2, 

2019 Active monitoring and ESC 

5321.00  Clear‐span  Dec 19, 2019  Active monitoring and ESC 

5740.00  Clear‐span Dec 17 – 18, 

2019 Active monitoring and ESC 

 

16 

 

2.7.5 Monitoring Water Quality in Sensitive Areas 

As described in the DPP, Environmentally Sensitive Areas (ESA) include water bodies, wetlands, rare vegetation communities and significant wildlife habitats. The Environmental Alignment Sheets and the Access and Construction Environmental Maps illustrate the location of these features and Table 5‐I‐2: Vegetation and Wetlands Mitigation and Table 5‐II‐2: Vegetation and Wetlands Mitigation outline both the Owner and Contractor mitigation measures.   The Project is following the water quality monitoring commitments outlined during the permitting process for identified sensitive areas to ensure the regulatory permit requirements and approval are adhered to. This is achieved by regular site inspections and monitoring by the EIs during construction to monitor the installation method(s) at each location.  As part of the construction monitoring, the EIs utilize the EMS to record and document each construction monitoring site inspection. Specifically, the following sensitive areas were crossed during the 2019 construction activities.  

Table 8. Water Quality Monitoring in Sensitive Areas 

Sensitive Area ID  Crossing Method 

Date of EI 

Inspection 

Technique(s) Used to Ensure 

Compliance 

4801.00‐WC‐A  Clear‐span bridge  October 3, 2019 

Environmental Monitor (EM) 

monitoring during bridge installation. 

ESC (silt fence) installed after 

completion of bridge installation. 

AT‐WT‐5  Corduroy Road November 27, 

2019 

EM inspected access trail construction 

in wetland. Approved overlanding 

method (corduroy) used to construct 

access trail. 

4960.02‐WC‐A  Clear‐span bridge  December 2, 2019 

EM monitoring during bridge 

installation. ESC (silt fence) installed 

after completion of bridge 

installation. 

4950.01‐WC‐A  Culvert December 17, 

2019 

Qualified Environmental Professional 

(QEP) monitoring during culvert 

installation activities as per 

requirements in Water Crossing 

Selection and Installation: Culverts 

and Snowfills SOP. Mitigation 

measures  (e.g. dewatering sediment 

laden water into well vegetated area 

during “dam and pump” activities) 

17 

 

Sensitive Area ID  Crossing Method 

Date of EI 

Inspection 

Technique(s) Used to Ensure 

Compliance 

implemented during installation to 

ensure compliance. 

 

2.8 GROUNDWATER 

2.8.1 Monitoring Private Water Wells 

No water discharges occurred within 100 metres of a private water well during 2019, therefore no monitoring was required.   

2.8.2 Pre‐blast Surveys 

No blasting activities occurred in 2019, therefore no pre‐blast surveys of water wells were required.  

2.9 AIR QUALITY 

2.9.1 Monitoring Near Residential Properties 

The 2019 construction activities did not occur within 100 metres of a residence, therefore no monitoring was required.  

2.10 GREENHOUSE GASES 

As outlined in Section 23.1.1 Table 23.1 of the EA, no monitoring programs are proposed or required for this Project.  

2.11 ACOUSTIC ENVIRONMENT 

As outlined in Section 23.1.1 Table 23.1 of the EA, no monitoring programs are proposed or required for this Project.  

2.12 VEGETATION AND WETLANDS 

2.12.1 Monitoring for Incidental Sensitive Features 

The 2019 construction activities did not incidentally identify any sensitive features (rare plants, rare vegetation communities, and/or wetlands), therefore no monitoring activities were required.   

18 

 

2.12.2 Monitoring Soil Piles 

As outlined in Section 6.2 of the CEPP, soil storage requires specific soil management monitoring activities.   Soil stripping was limited on the Project in 2019 resulting in no large soil stockpiles requiring monitoring. For construction of foundation pads, stripping was limited/not required based on the foundation selection (e.g. rock anchor, drilled pipe pile, micropile) and use of mulch/wood chips to support pad building for equipment. 

Table 9. Monitoring Soil Piles 

Structure or Span 

ID 

Location of Soil 

Pile 

Date of EI 

Inspection 

Technique(s) Used to Ensure 

Compliance 

N/A  N/A  N/A  N/A 

 

2.12.3 Monitoring for Weeds 

As required, the Project will follow the Weed Management Plan outlined in Section 8.4 of the CEPP which focuses on implementation of appropriate measures to reduce the spread of noxious weeds species. Compliance is achieved by regular site inspections and monitoring by the EIs during construction to monitor for noxious weeds.   Construction activities occurred outside of the growing season for weed observations (October 2019 ‐ December 2019). Therefore, no monitoring of weeds occurred during 2019.   No wash stations were utilized for equipment cleaning for the Project in 2019; however, prior to equipment being mobilized to the Project, it was inspected and confirmed clean in accordance with EA commitments and the requirements outlined in the CEPP (Halloran et al. 2013). Additionally, prior to equipment being moved along clearing work fronts, mechanical cleaning (i.e. cleaning of tracks to remove soil clumps and vegetation) was completed to minimize the risk of unintentional introduction or movement of invasive species. 

Table 10. Monitoring for Weeds 

Structure of 

Span ID 

Noxious 

Weed 

Species 

Name  Density 

Management Strategy 

Implemented 

Assessment Methods 

for Success (or 

Failure) of 

Management Strategy 

N/A  N/A  N/A  N/A  N/A 

 

19 

 

2.13 FISH AND FISH HABITAT 

2.13.1 Monitoring of Water Body Crossings 

One culvert was installed during construction activities in 2019. This culvert was installed at water crossing ID 4950.01 between structures A039 and A040. An independent third‐party environmental company was employed to oversee the installation of the new culvert. 

Table 11. Monitoring of Water Body Installations 

Water Crossing ID 

Crossing 

Method 

Mitigation 

Measures 

Date of EI 

Inspection 

Technique(s) Used to 

Ensure Compliance 

4801.00  Clear‐span One‐time fording 

Oct 3 – 4, 2019 Active monitoring and 

ESC  

4790.00  Clear‐span One‐time fording 

Oct 5 – 6, 2019 Active monitoring and 

ESC  

4860.01  Clear‐span One‐time fording 

Oct 15, 2019 Active monitoring and 

ESC  

120.00  Clear‐span One‐time fording 

Oct 25 ‐ 27, 2019 Active monitoring and 

ESC 

118.00  Timber‐mat One‐time fording 

Oct 24, 2019 Active monitoring and 

ESC 

4950.01  Culvert Dam and pump 

around 

Dec 13, 16 – 17, 

2019 

Active monitoring and 

ESC 

4960.02  Clear‐span  One‐time fording Nov 30, Dec 1 – 

2, 2019 

Active monitoring and 

ESC 

121.00  Clear span One‐time fording 

Dec 1 – 2, 2019 Active monitoring and 

ESC 

5321.00  Clear‐span One‐time fording 

Dec 19, 2019 Active monitoring and 

ESC 

5740.00  Clear‐span Existing bridge 

(overtop) 

Dec 17 – 18, 

2019 

Active monitoring and 

ESC 

 

2.13.2 Post‐Construction Monitoring of Waterbody Crossings 

No water body crossings were removed during 2019. Therefore, post‐construction monitoring activities were not necessary.   

2.13.3 Monitoring and Adaptive Management 

The one water crossing culvert (4950.01) installed in 2019 was installed under the supervision of a third‐party environmental company and the installation was conducted as proposed and permitted. Refer to Section 2.8.1 above for additional details.  

20 

 

2.14 WILDLIFE AND WILDLIFE HABITAT 

2.14.1 Construction Monitoring for Incidental Sensitive Features 

During  the  EI’s monitoring  activities  in  2019,  no  undocumented  sensitive  features  or habitats were observed.  

2.15 RECLAMATION CONCERNS 

No reclamation activities occurred during 2019, therefore, no monitoring occurred.  

2.16 ARCHAEOLOGICAL RESOURCES 

The Project conducted both preconstruction archaeological surveys and construction monitoring in 2019. The monitoring program included identification, surveying, documentation, reporting, avoidance measures, protective measures, and construction monitoring efforts to ensure compliance. Specifically, construction monitoring was conducted at one site during 2019. The construction monitoring was conducted by a licensed archaeologist as well as multiple Indigenous Facilitators. The monitoring reports will be submitted to the Ministry of Heritage, Sport, Tourism, and Culture Industries (MHSTCI) once the work is complete.  

Table 12. Monitoring of Archaeological Resources  

Feature ID Work 

Front Archaeological Investigation Type 

Date Conducted 

(Day, Month, Year) 

A039  1  Stage 2 Archaeological Assessment  29‐07‐2019 

A053  1  Stage 3 Archaeological Assessment  04‐09‐2019 

A053  1  Stage 3 Archaeological Assessment  05‐09‐2019 

A053  1  Stage 3 Archaeological Assessment  06‐09‐2019 

A053  1  Construction Monitoring  28‐10‐2019 

A053  1  Construction Monitoring  29‐10‐2019 

A053  1  Construction Monitoring  30‐10‐2019 

A053  1  Construction Monitoring  31‐10‐2019 

A053  1  Construction Monitoring  01‐11‐2019 

A053  1  Construction Monitoring  03‐11‐2019 

A053  1  Construction Monitoring  05‐11‐2019 

A053  1  Construction Monitoring  10‐11‐2019 

A053  1  Construction Monitoring  12‐11‐2019 

A053  1  Construction Monitoring  09‐12‐2019 

A053  1  Construction Monitoring  10‐12‐2019 

21 

 

Feature ID Work 

Front Archaeological Investigation Type 

Date Conducted 

(Day, Month, Year) 

A053  1  Construction Monitoring  11‐12‐2019 

A053  1  Construction Monitoring  12‐12‐2019 

A053  1  Construction Monitoring  13‐12‐2019 

A071  1  Stage 2 Archaeological Assessment  30‐07‐2019 

A105  1  Stage 2 Archaeological Assessment  24‐07‐2019 

A109  1  Stage 2 Archaeological Assessment  25‐07‐2019 

A110  1  Stage 2 Archaeological Assessment  25‐07‐2019 

A112  1  Stage 2 Archaeological Assessment  25‐07‐2019 

A127  1  Stage 2 Archaeological Assessment  27‐07‐2019 

A128  1  Stage 2 Archaeological Assessment  27‐07‐2019 

B021  2  Stage 2 Archaeological Assessment  28‐07‐2019 

B028  2  Stage 2 Archaeological Assessment  31‐07‐2019 

B029  2  Stage 2 Archaeological Assessment  31‐07‐2019 

B030  2  Stage 2 Archaeological Assessment  01‐08‐2019 

B036  2  Stage 2 Archaeological Assessment  01‐08‐2019 

B074  2  Stage 2 Archaeological Assessment  19‐07‐2019 

B085  3  Stage 2 Archaeological Assessment  28‐07‐2019 

B085  3  Stage 2 Archaeological Assessment  09‐09‐2019 

B086  3  Stage 2 Archaeological Assessment  28‐07‐2019 

B106  3  Stage 2 Archaeological Assessment  01‐08‐2019 

B122  3  Stage 2 Archaeological Assessment  09‐09‐2019 

B136  3  Stage 2 Archaeological Assessment  22‐07‐2019 

B142  3  Stage 2 Archaeological Assessment  15‐08‐2019 

B149  3  Stage 2 Archaeological Assessment  06‐08‐2019 

B155  3  Stage 2 Archaeological Assessment  12‐09‐2019 

B155  3  Stage 2 Archaeological Assessment  04‐11‐2019 

B158  3  Stage 2 Archaeological Assessment  20‐07‐2019 

Nipigon Base Camp 

Access Road 3 

Stage 2 Archaeological Assessment 11‐12‐2019 

C013  4  Stage 2 Archaeological Assessment  20‐08‐2019 

C028  5  Stage 2 Archaeological Assessment  23‐07‐2019 

C035  5  Stage 2 Archaeological Assessment  30‐09‐2019 

C048  5  Stage 2 Archaeological Assessment  23‐10‐2019 

22 

 

Feature ID Work 

Front Archaeological Investigation Type 

Date Conducted 

(Day, Month, Year) 

C051  5  Stage 2 Archaeological Assessment  02‐08‐2019 

C054  5  Stage 2 Archaeological Assessment  02‐08‐2019 

C075  5  Stage 2 Archaeological Assessment  22‐10‐2019 

C078  5  Stage 2 Archaeological Assessment  03‐08‐2019 

C101  5  Stage 2 Archaeological Assessment  25‐10‐2019 

C128  5  Stage 2 Archaeological Assessment  07‐08‐2019 

C144  6  Stage 2 Archaeological Assessment  19‐10‐2019 

C168  6  Stage 2 Archaeological Assessment  08‐08‐2019 

C173  6  Stage 2 Archaeological Assessment  10‐08‐2019 

C213  6  Stage 2 Archaeological Assessment  14‐09‐2019 

C217  6  Stage 2 Archaeological Assessment  09‐08‐2019 

C250  6  Stage 2 Archaeological Assessment  20‐10‐2019 

C277  6  Stage 2 Archaeological Assessment  20‐10‐2019 

D078  7  Stage 2 Archaeological Assessment  17‐07‐2019 

D081  7  Stage 2 Archaeological Assessment  18‐07‐2019 

D094  7  Stage 2 Archaeological Assessment  16‐07‐2019 

D106  7  Stage 2 Archaeological Assessment  11‐09‐2019 

D115  7  Stage 2 Archaeological Assessment  15‐07‐2019 

D143  7  Stage 2 Archaeological Assessment  15‐07‐2019 

Marathon Camp  7  Stage 1‐2 Archaeological Assessment  21‐08‐2019 

E008  8  Stage 2 Archaeological Assessment  08‐07‐2019 

E016  8  Stage 2 Archaeological Assessment  06‐07‐2019 

E017  8  Stage 2 Archaeological Assessment  06‐07‐2019 

E019  8  Stage 2 Archaeological Assessment  06‐07‐2019 

E021  8  Stage 2 Archaeological Assessment  06‐07‐2019 

E034  8  Stage 2 Archaeological Assessment  12‐07‐2019 

E121  9  Stage 2 Archaeological Assessment  13‐07‐2019 

E133  9  Stage 2 Archaeological Assessment  09‐07‐2019 

E137  9  Stage 2 Archaeological Assessment  09‐07‐2019 

E138  9  Stage 2 Archaeological Assessment  09‐07‐2019 

E139  9  Stage 2 Archaeological Assessment  09‐07‐2019 

E141  9  Stage 2 Archaeological Assessment  09‐07‐2019 

E218  9  Stage 2 Archaeological Assessment  18‐09‐2019 

23 

 

Feature ID Work 

Front Archaeological Investigation Type 

Date Conducted 

(Day, Month, Year) 

F004  9  Stage 2 Archaeological Assessment  11‐07‐2019 

F032  10  Stage 2 Archaeological Assessment  13‐08‐2019 

F034  10  Stage 2 Archaeological Assessment  13‐08‐2019 

F035  10  Stage 2 Archaeological Assessment  13‐08‐2019 

F037  10  Stage 2 Archaeological Assessment  13‐08‐2019 

F060  10  Stage 2 Archaeological Assessment  13‐08‐2019 

F154  11  Stage 2 Archaeological Assessment  20‐09‐2019 

F158  11  Stage 2 Archaeological Assessment  19‐09‐2019 

Michipicoten First 

Nation Camp 11  Stage 1‐2 Archaeological Assessment  19‐09‐2019 

 

2.17 CULTURAL HERITAGE RESOURCES 

The Project conducted both preconstruction archaeological surveys and construction monitoring in 2019. The monitoring program included identification, surveying, documentation, reporting, avoidance measures, protective measures, and construction monitoring efforts to ensure compliance. Specifically, construction monitoring was conducted at one site during 2019. The construction monitoring was conducted by a licensed archaeologist as well as multiple Indigenous Facilitators. The monitoring reports will be submitted to the MHSTCI once the work is complete.   Please refer to the table above outlining the cultural heritage  field work completed  in 2019.  

2.18 TRADITIONAL LAND AND RESOURCE USE 

2.18.1 Monitoring Activities 

The Project has implemented an Indigenous Facilitation Plan with Supercom that allows one Indigenous Facilitator from seven Indigenous communities, who has requested it, to monitor the daily construction activities. The facilitators complete daily reports which are submitted to Supercom for distribution to each community.  

2.19 SOCIO‐ECONOMICS 

As outlined in Section 23.1.1 Table 23.1 of the EA, no monitoring programs are proposed or required for this Project.  

24 

 

2.20 NON‐TRADITIONAL LAND AND RESOURCE USE 

As outlined in Section 23.1.1 Table 23.1 of the EA, no monitoring programs are proposed or required for this Project.  

2.21 VISUAL ENVIRONMENT 

As outlined in Section 23.1.1 Table 23.1 of the EA, no monitoring programs are proposed or required for this Project.  

2.22 HUMAN HEALTH 

As outlined in Section 23.1.1 Table 23.1 of the EA, no monitoring programs are proposed or required for this Project.  

2.23 ENVIRONMENTAL PROTECTION PLAN 

In addition to the environmental protection measures listed in the EACMP, DPP, and CEPP, the contractor implemented an EMS as described above in Section 2 during the 2019 construction activities.   

3 CONCLUSIONS 

The Project is committed to environmental compliance. This has been illustrated during the project development process through the creation of the EA, DPP, and CEPP. The applicable environmental compliance conditions and measures outlined within these documents were implemented during construction activities that occurred in 2019.  Additionally, during the construction phase Valard has implemented a robust EMS system to track, document, and record compliance activities. If additional information is requested, do not hesitate to reach out. Requests can be made via email to [email protected] or by contacting 1‐888‐767‐3006.    

25 

 

              

ATTACHMENT A  

TABLE 2‐1 COMMITMENTS AND COMPLIANCE MONITORING     

1 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

Table 2-1: Commitments and Compliance Monitoring

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2-1 1 CEPP Section 1.0 Introduction The owner will appoint Environmental Inspector to oversee implementation of the environmental protection measure and mitigation described in this CEPP during the Project.

●  ●    Use of Environmental Inspectors

Complete Yes

2-2 2 CEPP Section 1.0 – Introduction The environmental setting, environmental concerns, and associated protection measures and mitigation will be updated and included in future versions of the CEPP, Environmental Alignment Sheets, and Access and Construction Environmental Maps as the Project moves through the EA and environmental permitting, and through detailed engineering and construction planning.

●  ●    Environmental Alignment Sheets (EAS), and Access and Construction Environmental Maps

Ongoing over Project construction

In Progress

2-3 3 CEPP Section 1.0 – Introduction No changes to the mitigation measures as they appear in this CEPP, the Environmental Alignment Sheets, and the Access and Construction Environmental Maps will be made without the approval of the Owner.

●  ●    Adherence to DPP, EAS and the Access and Construction Environmental Maps

No changes in mitigation measures were necessary during 2019 activities

Yes

2-4 4 CEPP Section 1.0 – Introduction;

OEMP Section 1.1 – Introduction – Scope of Operation Environmental Management Plan

In the event that an unforeseen environmental issue arises for which no mitigation measures are approved, or for which new or innovative mitigation measures are deemed appropriate, the Owner shall consult with the appropriate government agencies.

  ●  ●  Adherence to DPP; Consultation and Engagement Summary Table

No changes in mitigation measures were necessary during 2019 activities

Yes

2-5 5 CEPP Section 1.0 – Introduction If regulatory requirements discussed in this CEPP differ from requirements outlined in Project approval conditions, or if the direction given by regulators is found to be conflicting, the Owner will work with the regulator to resolve the discrepancy with the available representatives of the affected government agencies.

●  ●    Adherence to DPP; Consultation and Engagement Summary Table

No changes in mitigation measures were necessary during 2019 activities

Yes

2-6 6 CEPP Section 3.0 – Notification of Affected Parties – Federal, Provincial and Municipal Agencies – Owner Measures #1

Notify applicable federal and provincial regulatory agencies and interested municipal officials of the Project as warranted.

●      Valard EMS; Consultation and Engagement Summary Table

Complete for 2019; ongoing for remaining Project construction

Yes

2-7 7 CEPP Section 3.0 – Notification of Affected Parties – Regulatory Liaison – Owner Measures #2

Applicable regulatory agencies, including:

Ministry of Energy, Northern Development and Mines (MENDM),

Ministry of Natural Resources and Forestry (MNRF),

Ministry of the Environment, Conservation and Parks (MECP),

Ministry of Tourism, Culture and Sport (MTCS),

Fisheries and Oceans Canada (DFO),

Environment and Climate Change Canada;

Transport Canada;

Indigenous Services Canada (ISC);

Infrastructure Ontario; and

Lakehead Region Conservation Authority (LRCA)

will be kept apprised of general construction schedules, as required by environmental regulatory requirements and will be consulted during construction as required by approval conditions.

●  ●    Valard EMS; Construction Letters Notification Schedule Updates on Project Website and Regular Project Updates sent to Project Stakeholder List

Complete for 2019; ongoing for remaining Project construction

Yes

2-8 8 CEPP Section 3.0 – Notification of Affected Parties – Regulatory Liaison – Owner Measures #3

Regular liaison with government field representatives will be the responsibility of the Owner. ●  ●    Valard EMS; Consultation and Engagement Summary Table

Complete for 2019; ongoing for remaining Project construction Yes

2 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2-9 9 CEPP Section 3.0 – Notification of Affected Parties – Landowners – Owner Measures #4;

CEPP Section 4.0 – General Environmental Protection Measures – Noise – Contractor Measures #42;

EA Report – Section 2 – Consultation and Engagement Summary;

EA Report – Section 11 – Acoustic Environment

EA Report – Section 18 – Socio-Economics

EA Report – Section 19 – Non-Traditional Land and Resource Use

Notify landowners along the route of the general construction schedule at least 45 days before the start of construction to fulfill land agreements and prevent or reduce impacts to their operations or activities.

●  ●    Construction Letters Notification

Letter dated September 6, 2019

Yes

2-10 10 CEPP Section 3.0 – Notification of Affected Parties – Road Authorities – Owner Measures #5

CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan – Notification – Owner Measures #4

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 18 – Socio-Economics

EA Report – Section 19 – Non-Traditional Land and Resource Use

Notify road authorities (e.g., local roads boards, municipalities, Ministry of Transportation of Ontario [MTO], the Crown managed, landowners and other authorities) of the planned access restrictions and detours at least 10 days before start of construction to prevent or reduce impacts to their operations or activities.

●  ●    Valard EMS; Consultation and Engagement Summary Table

Complete for 2019; ongoing for remaining Project construction

Yes

2-11 11 CEPP Section 3.0 – Notification of Affected Parties – Water Users – Owner Measures #6

EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 19 – Non-Traditional Land and Resource Use

Notify appropriate authorities and licensees, at least 45 days prior to a permitted use of water. ●      Valard EMS; Consultation and Engagement Summary Table

No permitted use of water occurred on the Project in 2019

Yes

2-12 12 CEPP Section 3.0 – Notification of Affected Parties – Indigenous Communities – Owner Measures #7

CEPP Section 4.0 – General Environmental Protection Measures – Noise – Contractor Measures #43

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 11 – Acoustic Environment

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 18 – Socio-Economics

EA Report – Section 19 – Non-Traditional Land and Resource Use

Notify Indigenous communities of the general construction schedule 45 days before the start of construction to allow sufficient time for harvesting of traditional use plant species prior to the start of construction.

●  ●    Construction Letters Notification; Schedule Updates on Project Website and Ongoing Engagement with Indigenous Community Leadership

Letter dated September 6, 2019

Yes

2-13 13 CEPP Section 3.0 – Notification of Affected Parties – Crown Interest Holders – Owner Measures #8

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Notify Crown interest holders (e.g. mining lease holders, unpatented claim holders, aggregate permit holders, non-freehold disposition holders, Sustainable Forest License (SFL) holders, and other interest holders) of the general construction schedule at least 45 days before the start of construction to minimize potential disturbance to their operations.

●      Construction Letters Notification; Schedule Updates on Project Website Regular Project Updates sent to Project Stakeholder List

Letter dated September 6, 2019

Yes

3 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2-14 14 CEPP Section 3.0 – Notification of Affected Parties – Recreational Users – Owner Measures #10

CEPP Section 4.0 – General Environmental Protection Measures – Protected Areas – Owner Measures #24

CEPP Section 4.0 – General Environmental Protection Measures – Noise – Contractor Measures #41

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincial Parks – Owner Measures #16

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 11 – Acoustic Environment

EA Report – Section 18 – Socio-Economics

EA Report – Section 19 – Non-Traditional Land and Resource Use

The Owner will provide at least 45 days advanced notice of construction activities to recreational users through formal notification in local newspapers and at protected parks and campsites locations (e.g., park entrances).

●  ●    Construction Letters Notification

Letter dated September 6, 2019

Yes

2-15 15 CEPP Section 3.0 – Notification of Affected Parties – Third Party Agreements and Notifications – Contractor Measures #1

The General Contractor (Valard) will notify affected parties where applicable per third party agreements (e.g., crossing agreements, road use agreements, and landowner agreements).

●  ●    Valard EMS; Consultation and Engagement Summary Table

Complete for 2019; ongoing for remaining Project construction

Yes

2-16 16 CEPP Section 4.0 – General Environmental Protection Measures – Project Documents – Owner Measures #1

This CEPP serves as a guide to mitigate environmental issues and fulfill commitments during construction of the Project. This CEPP will be updated 30 days prior to construction of the Project to include pertinent environmental information from the EA, environmental permitting requirements and pre-construction surveys. Specific mitigation measures discussed in this CEPP are also shown on the Environmental Alignment Sheets and Access and Construction Environmental Maps.

●  ●    CEPP July 2019 Complete; submitted on July 15, 2019

Yes

2-17 17 CEPP Section 4.0 – General Environmental Protection Measures – Project Documents – Owner Measures #2

Project personnel will be supplied with relevant Project documents, including the most recent updates, revisions, amendments, conditions and requirements, before construction.

●  ●    Valard OEWTL Online Site Orientation

Orientation documents developed and provided to on-site personnel

Yes

2-18 18 CEPP Section 4.0 – General Environmental Protection Measures – Project Documents – Owner Measures #3

The Owner will maintain an up to date record of Project documents. ●  ●    Project record, compliance trackers

Complete for 2019; ongoing for remaining Project construction

Yes

2-19 19 CEPP Section 4.0 – General Environmental Protection Measures – Regulatory Approvals – Owner Measures #4

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources

EA Report – Section 19 – Non-Traditional Land and Resource Use

Local, municipal, provincial and federal licenses, permits and approvals will be obtained that are necessary for this Project. The Owner, its authorized representatives, contractor(s), and subcontractors, will comply with the conditions as presented to the Owner on permits, approvals, licenses, certificates and Project-specific management plans. Inconsistencies between conditions of different licenses, permits, and approvals will be resolved prior to construction of each workfront.

●  ●    Valard EMS; Adherence to DPP; Environmental Construction & Operations Compliance and Assurance Matrix

Complete for 2019; ongoing for remaining Project construction

Yes

2-20 20 CEPP Section 4.0 – General Environmental Protection Measures – Permits/ Reporting – Owner Measures #5

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincial Parks – Owner Measures #12

Work Permits and Land Use Permits will be obtained from MNRF within provincial parks as applicable. ●      Valard EMS; Environmental Construction & Operations Compliance and Assurance Matrix

Complete for 2019; ongoing for remaining Project construction

Yes

2-21 21 CEPP Section 4.0 – General Environmental Protection Measures – Permits/ Reporting – Owner Measures #6

Compliance reports will be submitted to appropriate regulatory agencies by the Owner where required in permit conditions. These records shall be retained with other appropriate Project documentation in Project files.

  ●    Valard EMS No compliance reports were required in 2019

Yes

4 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2-22 22 CEPP Section 4.0 – General Environmental Protection Measures – Third Party Agreements – Owner Measures #7

CEPP Section 4.0 – General Environmental Protection Measures – Third Party Agreements – Owner Measures #8

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 19 – Non-Traditional Land and Resource Use

The Owner will consult with landowner and interested holders (e.g. mining lease holders, unpatented claim holders, aggregate permit holders, non-freehold disposition holders, SFL holders, and other interest holders) forestry, mining claim and aggregate license holders and, where appropriate, to develop mutually beneficial agreements with the affected landowner and tenure holders. Third-party agreements will be obtained prior to construction of each workfront.

●      Adherence to regulations and requirements identified if applicable permits and authorizations

Complete for 2019; ongoing for remaining Project construction

Yes

2-23 23 CEPP Section 4.0 – General Environmental Protection Measures – Third Party Agreements – Owner Measures #9

CEPP Section 4.0 – General Environmental Protection Measures – Third Party Agreements – Contractor Measures #1

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 19 – Non-Traditional Land and Resource Use

The Owner, its authorized representatives, contractor(s), and subcontractors, will comply with the conditions outlined in the third-party agreements (e.g., crossing agreements, road use agreements, landowner agreements, overlapping agreements)

●  ●    Valard EMS; Adherence to regulations and requirements identified if applicable permits and authorizations

Complete for 2019; ongoing for remaining Project construction

Yes

2-24 24 CEPP Section 4.0 – General Environmental Protection Measures – Environmental Inspector – Owner Measures #10

CEPP Section 4.0 – General Environmental Protection Measures – Protected Areas – Owner Measures #25

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincial Parks – Owner Measures #17

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Significant Wildlife Habitat – Owner Measures #25

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 9 – Air Quality

EA Report – Section 10 – Greenhouse Gases

EA Report – Section 11 – Acoustic Environment

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources

EA Report – Section 18 – Socio-Economics

EA Report – Section 19 – Non-Traditional Land and Resource Use

EA Report – Section 20 – Visual Environment

The Owner will employ the services of qualified Environmental Inspector(s) to guide implementation, monitor and report on the effectiveness of the construction procedures and mitigation measures for minimizing potential impacts.

●  ●    Valard EMS Complete Yes

2-25 25 CEPP Section 4.0 – General Environmental Protection Measures – Environmental Inspector – Owner Measures #11

An Environmental Inspector will have the following:

sufficient environmental knowledge to make appropriate field decisions; and sufficient linear project construction experience to understand the constraints of construction.

●  ●    Valard EMS Complete Yes

5 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2-26 26 CEPP Section 4.0 – General Environmental Protection Measures – Records Line List – Owner Measures #12

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 19 – Non-Traditional Land and Resource Use

Prior to construction of each workfront, the Owner will provide the General Contractor (Valard) with a Construction Line List that describes special requirements requested by landowners and Crown interest holders (e.g., timber salvage, restoration measures, fencing requirements).

●      Construction Line Lists

Complete for 2019; ongoing for remaining Project construction

Yes

2-27 27 CEPP Section 4.0 – General Environmental Protection Measures – Pre-Job Meeting – Owner Measures #13

Prior to construction of the Project, the Owner will hold a pre-job meeting with engineering, safety and environment employees, inspectors, and contractor supervisors to review this CEPP, environmental concerns, mitigation measures, methods and regulations specific to the work, specific stakeholder conditions, and specific conditions on associated permits and regulatory approvals.

●      Valard OEWTL Online Site Orientation

Orientation documents developed and provided to on-site personnel.

Yes

2-28 28 CEPP Section 4.0 – General Environmental Protection Measures – Project Orientation – Owner Measures #14

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 18 – Socio-Economics

The Owner will develop the environmental and safety orientation program, to be implemented by the General Contractor (Valard) at least 45 days prior to construction.

●      Valard OEWTL Online Site Orientation; EWT Safety Orientation; MOL Safety Orientation

Orientation documents developed and provided to on-site personnel.

Yes

2-29 29 CEPP Section 4.0 – General Environmental Protection Measures – Project Orientation – Owner Measures #15

Prior to construction of the Project, the Owner will also develop and deliver advanced environmental training to relevant Project personnel (e.g., Environmental Inspectors, Contractor managers and Contractor supervisors).

●      Valard OEWTL Online Site Orientation; EWT Safety Orientation; MOL Safety Orientation

Orientation documents developed and provided to on-site personnel.

Yes

2-30 30 CEPP Section 4.0 – General Environmental Protection Measures – Environmental Hazard Assessment – Owner Measures #16

Prior to construction of the Project, the Owner will provide orientation to relevant Project personnel (e.g., Environmental Inspectors, Contractor managers and Contractor supervisors) on an Environmental Hazard Assessment program (refer to Appendix C).

●      Valard OEWTL Online Site Orientation; EWT Safety Orientation; MOL Safety Orientation

Orientation documents developed and provided to on-site personnel.

Yes

2-31 31 CEPP Section 4.0 – General Environmental Protection Measures – Spill Prevention and Response Contingency Plan – Owner Measures #17

OEMP Section 5.1 General Mitigation Measures – Spill Prevention

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands EA Report – Section 13 – Fish and Fish Habitat EA Report – Section 14 – Wildlife and Wildlife Habitat

In the event that any spills occur, implement the reporting measures provided in the Spill Prevention and Response Contingency Plan (refer to Appendix 4-II, Section 7.1).

  ●  ●  Valard EMS; Environmental Incident Notification and Reports

Complete for 2019; ongoing for remaining Project construction

Yes

2-32 32 CEPP Section 4.0 – General Environmental Protection Measures – Contaminated Soils – Owner Measures #18

CEPP Section 4.0 – General Environmental Protection Measures – Environmental Contaminated Sites – Contractor Measures #7

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 8 – Groundwater

In the event that contaminated soils are suspected during construction, implement the contaminated soils measures provided in the Spill Prevention and Response Contingency Plan (refer to Appendix 4-II, Section 7.1).

  ●    Valard EMS; Environmental Incident Notification and Reports

Complete for 2019; ongoing for remaining Project construction

Yes

6 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2-33 33 CEPP Section 4.0 – General Environmental Protection Measures – Care – Owner Measures #20

CEPP Section 4.0 – General Environmental Protection Measures – Environmental Discipline – Contractor Measures #8CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincial Park – Contractor Measures #31

EA Report – Section 19 – Non-Traditional Land and Resource Use

OEMP Section 6 – Environmental Training

Project personnel who show neglect for the environment or disregard for the CEPP may be removed from the Project by the Owner.

  ●  ●  Valard EMS; Environmental Incident Notification and Reports

Complete for 2019; ongoing for remaining Project construction

Yes

2-34 34 CEPP Section 4.0 – General Environmental Protection Measures – Suspending Work – Owner Measures #21

Should the Owner determine that construction activities are contravening the CEPP or the terms and conditions of a regulatory license or permit, the Owner can suspend construction until a solution that is compliant is established.

  ●    Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

Complete for 2019; ongoing for remaining Project construction

Yes

2-35 35 CEPP Section 4.0 – General Environmental Protection Measures – Air Quality – Owner Measures #22

EA Report – Section 9 – Air Quality

EA Report – Section 18 – Socio-Economics

EA Report – Section 21 – Human Health

Identify and confirm the potential receptors within 100 metres (m) of construction activities prior to construction of each workfront. If the receptor is confirmed to be an occupied residence, implement the following measures:

If the construction activities are anticipated to be negligible sources of fugitive dust and tailpipe emissions (e.g., surveying and flagging, geotechnical investigations, conductor stringing and tensioning, decommissioning of temporary infrastructures, and clean up and reclamation) then no further action is required.

Construction activities that may trigger the need for monitoring include site access development, material hauling, transmission foundation and anchor construction, transmission structure assembly and erection. If these activities are being undertaken within 100 m of the confirmed occupied residence, the Owner will assess the general construction schedule, environmental conditions, and season and evaluate the need for monitoring.

Monitoring will be undertaken when emission generating activities have the potential to impact the receptor. Handheld portable monitors will be used by a qualified person within approximately 10 m of confirmed occupied residences to provide real-time concentrations that can be compared to ambient air quality criteria.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2-36 36 CEPP Section 4.0 – General Environmental Protection Measures – Protected Areas – Owner Measures #23

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincial Parks – Owner Measures #13

EA Report – Section 19 – Non-Traditional Land and Resource Use

The Owner will actively consult with the MNRF, MECP, and other relevant stakeholders on proposed measures to minimize interruption of recreational use and access restrictions to protected areas.

●  ●    Valard EMS; Adherence to DPP; Consultation and Engagement Summary Table

Complete for 2019; ongoing for remaining Project construction

Yes

2-37 37 CEPP Section 4.0 – General Environmental Protection Measures – Protected Areas – Owner Measures #26

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincial Parks – Owner Measures #18

EA Report – Section 19 – Non-Traditional Land and Resource Use

Clearly mark the boundaries of protected areas along the right-of-way (ROW). ●  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

7 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2-38 38 CEPP Section 4.0 – General Environmental Protection Measures – Protected Areas – Owner Measures #27

CEPP Section 4.0 – General Environmental Protection Measures – Noise – Contractor Measures #50

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincial Parks – Owner Measures #20

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincial Park – Contractor Measures #29 OEMP Section 5.1 – General Mitigation Measures – Noise Concerns

EA Report – Section 11 – Acoustic Environment

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 18 – Socio-Economics EA Report – Section 19 – Non-Traditional Land and Resource Use

Address noise concerns as they arise through a noise complaint process.   ●  ●  Valard EMS; Adherence to CEPP and DPP; Construction Complaint Log

Complete for 2019; ongoing for remaining Project construction

Yes

2-39 39 CEPP Section 4.0 – General Environmental Protection Measures – Protected Areas – Owner Measures #28

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Signage and Setbacks – Owner Measures #5

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincial Parks – Owner Measures #21

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Significant Wildlife Habitat – Owner Measures #29

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

The Owner will review protective and mitigative measures with the General Contractor (Valard). ●      Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete Yes

2-40 40 CEPP Section 4.0 – General Environmental Protection Measures – Environmental Incidents – Contractor Measures #2

In the event of an environmental incident, work will be suspended in the vicinity of the incident and the General Contractor (Valard) will report it to the Owner as soon as it is safe to do so. Work will be suspended until a solution that is compliant is established. Environmental incidents include, but are not limited to:

Any reportable spills as defined in the provincial requirements (refer to Appendix 4-II, Table 4-II-3);

any release to water, on or off site, directly related or attributable to the Project;

any activity conducted that is not in compliance with environmental regulations or permits, the Owner’s environmental procedures, the CEPP (refer to Appendix 4-II), and/or Project environmental commitments (as communicated to an external stakeholder or regulator); and/or

any incident that results or could result in an impact to fish, wildlife or the environment (air, land, or water) that

does not include a release or a non-compliance.

  ●    Valard EMS; Environmental Incident Notification and Reports

Ongoing In Progress

8 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2-41 41 CEPP Section 4.0 – General Environmental Protection Measures – Environmental Incidents – Contractor Measures #3

Document environmental incident using the Spill Reporting Form (refer to Appendix D) and submit to the Owner.   ●    Valard EMS; Environmental Incident Notification and Reports

Ongoing In Progress

2-42 42 CEPP Section 4.0 – General Environmental Protection Measures – Environmental Incidents – Contractor Measures #4

EA Report – Section 6 – Geology, Terrain and Soils EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

In the event that any spills occur, implement the Spill Prevention and Response Contingency Plan (refer to Appendix 4-II, Section 7.1).

  ●    Valard EMS; Environmental Incident Notification and Reports

Ongoing In Progress

2-43 43 CEPP Section 4.0 – General Environmental Protection Measures – Environmental Emergency Response Plan – Contractor Measures #5

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

Prior to construction of the Project, the General Contractor (Valard) will develop an Environmental Emergency Response Plan for review and approval by the Owner that describes response procedures to potential environmental incidents or emergencies (e.g., spills, fire, erosion or sedimentation), clearly indicates responsibilities for communication and reporting, and provides contact names and details for individuals to be contacted in case of emergency.

●      Valard Environmental Emergency Response Plan

Document developed Yes

2-44 44 CEPP Section 4.0 – General Environmental Protection Measures – Environmental Emergency Response Plan – Contractor Measures #6

The Environmental Emergency Response Plan can be developed as a stand-alone document or as part of the Project’s Emergency Response Plan.

●      Valard Environmental Emergency Response Plan

Document developed Yes

2-45 45 CEPP Section 4.0 – General Environmental Protection Measures – Environmental Project Training and Orientation – Contractor Measures #9

EA Report – Section 18 – Socio-Economics

The General Contractor (Valard) will deliver the general environmental and safety orientation to Project personnel. ●  ●    OEWTL Online Site Orientation; EWT Safety Orientation; MOL Safety Orientation

Orientation documents developed and provided to on-site personnel.

Yes

2-46 46 CEPP Section 4.0 – General Environmental Protection Measures – Environmental Project Training and Orientation – Contractor Measures #10

The General Contractor (Valard) will provide orientation records to the Owner. ●  ●    Valard Safety Records

Ongoing In Progress

2-47 47 CEPP Section 4.0 – General Environmental Protection Measures – Environmental Hazard Assessment – Contractor Measures #11

The General Contractor (Valard) will be responsible for implementing the Environmental Hazard Assessment program developed by the Owner (refer to Appendix C).

  ●    Valard EMS Ongoing In Progress

9 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2-48 48 CEPP Section 4.0 – General Environmental Protection Measures – Schedule – Contractor Measures #12

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – General – Contractor Measures #47

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – Fish – Contractor Measures #66

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Schedule – Contractor Measures #12

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Construction will be completed as quickly and efficiently as possible near environmentally sensitive features to minimize the disturbance to fish and wildlife.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2-49 49 CEPP Section 4.0 – General Environmental Protection Measures – Road Restrictions – Contractor Measures #13

EA Report – Section 19 – Non-Traditional Land and Resource Use

Implement road weight restriction and road bans during the spring break up period as regulated by the applicable regulatory authority.

  ●    Valard EMS; Adherence to DPP

Not Applicable to 2019 construction activities

Not Started

10 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2-50 50 CEPP Section 4.0 – General Environmental Protection Measures – Project Site – Contractor Measures #14

CEPP Section 5.2 –Environmentally Sensitive Features Protection Measure – Provincial Park – Contractor Measures #16

CEPP Section 5.2 – Environmentally Sensitive Features Protection Measure – Significant Wildlife Habitat – Contractor Measures #35

CEPP Section 5.2– Environmentally Sensitive Features Protection Measure – Critical Landform/ Vegetation Association – Contractor Measures #71

CEPP Section 5.2 – Environmentally Sensitive Features Protection Measure – Research Plots – Contractor Measures #77

CEPP Section 5.2– Environmentally Sensitive Features Protection Measure – Rare Plants / Rare Vegetation Communities – Contractor Measures #80

CEPP Section 6.1– Site Preparation – Surveying and Flagging – Contractor Measures #7

CEPP Section 6.2– Access Roads –Surveying and Flagging – Contractor Measures #9

CEPP Section 6.4– Temporary Workspaces – Survey and Flagging– Contractor Measures #7

CEPP Section 6.4– Temporary Workspaces – Survey and Flagging– Contractor Measures #11

CEPP Section 6.5– Transmission Foundation and Anchor Construction – Surveying and Flagging – Contractor Measures #6

CEPP Section 6.6– Transmission Structure Assembly and Erection – Survey and Flagging – Contractor Measures #6

CEPP Section 8.5– Traffic Management Plan – Traffic Management – Contractor Measures #7

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Construction activities associated with the Project will be confined to the surveyed and marked areas.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

11 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2-51  51  CEPP Section 4.0 – General Environmental Protection Measures – Project Site – Contractor Measures #15

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Signage and Setback – Contractor Measures #4

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincial Park – Contractor Measures #17

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Significant Wildlife Habitat – Contractor Measures #36

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Critical Landform/ Vegetation Association – Contractor Measures #72

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Research Plots – Contractor Measures #78

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Rare Plants / Rare Vegetation Communities – Contractor Measures #81

CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Surveying and Flagging – Contractor Measures #11

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads –Surveying and Flagging – Contractor Measures #10

CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Survey and Flagging– Contractor Measures #12

CEPP Section 6.6 – Transmission Line Construction Environmental Protection Measures – Transmission Structure Assembly and Erection – Survey and Flagging – Contractor Measures #7

CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan – Traffic Management – Contractor Measures #8

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Project personnel will avoid areas that are flagged or temporarily fenced and abide by restrictions on in/out privileges that are implemented in areas requiring special protection due to environmentally sensitive features 

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

In Progress

12 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2-52 52 CEPP Section 4.0 – General Environmental Protection Measures – Equipment – Contractor Measures #16

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat EA Report – Section 19 – Non-Traditional Land and Resource Use

Construction equipment will arrive on the Project Site clean (i.e., free of soil and vegetative debris) in accordance with the Clean Equipment Protocol for Industry (refer to Appendix H1; Halloran et al. 2013) and in good working order (i.e., no oil or hydraulic fluid leaks). Equipment will be inspected for leaks routinely throughout the duration of construction.

  ●    Valard EMS Complete for 2019; ongoing for remaining Project construction

Yes

2-53 53 CEPP Section 4.0 – General Environmental Protection Measures – Equipment – Contractor Measures #18

CEPP Section 4.0 – General Environmental Protection Measures – Air Quality / Emissions– Contractor Measures #29

CEPP Section 4.0 – General Environmental Protection Measures – Noise – Contractor Measures #45

CEPP Section 4.0 – General Environmental Protection Measures – Air Quality / Emissions– Contractor Measures #30

CEPP Section 4.0 – General Environmental Protection Measures – Air Quality / Emissions– Contractor Measures #30

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincial Park – Contractor Measures #27

CEPP Section 7.3 – Contingency Plans – Fire Prevention Contingency Plan – Equipment – Contractor Measures #7

OEMP Section 5.2 – Access and Travel on Right-of-Way – Vehicles and Equipment

OEMP Section 5.5 – Environmental Management During Operation –Fire Prevention

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils EA Report – Section 7 – Surface Water

EA Report – Section 9 – Air Quality

EA Report – Section 10 – Greenhouse Gases

EA Report – Section 11 – Acoustic Environment

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 18 – Socio-Economics

EA Report – Section 19 – Non-Traditional Land and Resource Use

EA Report – Section 21 – Human Health

Noise abatement, emission and pollution control equipment on machinery should be in place, properly maintained and in good working order.

  ●  ●  Valard EMS Complete for 2019; ongoing for remaining Project construction

Yes

13 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2-54 54 CEPP Section 4.0 – General Environmental Protection Measures – Wet Areas – Contractor Measures #19 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincial Park – Contractor Measures #18

CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Schedule – Contractor Measures #3

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads –Schedule – Contractor Measures #1

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Schedule – Contractor Measures #11

CEPP Section 6.3 – Transmission Line Construction Environmental Protection Measures – Geotechnical Investigations – Schedule – Contractor Measures #2

CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Schedule – Contractor Measures #2

CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Schedule – Contractor Measures #1

CEPP Section 6.6 – Transmission Line Construction Environmental Protection Measures – Transmission Structure Assembly and Erection – Schedule – Contractor Measures #2

CEPP Section 6.7 – Transmission Line Construction Environmental Protection Measures – Conductor Stringing and Tensioning – Schedule – Contractor Measures #3

CEPP Section 8.1 – Environmental Management Plans – Erosion and Sedimentation Control Plan – Schedule – Contractor Measures #2EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

When construction schedule allows, plan construction activities in wet areas during frozen conditions.    ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

14 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2-55 55 CEPP Section 4.0 – General Environmental Protection Measures – Erosion and Sedimentation Control – Contractor Measures #20

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincial Park – Contractor Measures #24

CEPP Section 6.2 – Access Roads – Erosion and Sedimentation Control – Contractor Measures #16, #31, #62

CEPP Section 6.3 – Geotechnical Investigations – Erosion and Sediment Control – Contractor Measures #15

CEPP Section 6.4 – Temporary Workspaces – Erosion and Sedimentation Control – Contractor Measures #34

CEPP Section 6.5– Transmission Foundation and Anchor Construction – Erosion and Sedimentation

Install, monitor and manage appropriate erosion and sedimentation controls as outlined in the preliminary Erosion and Sedimentation Control Management Plan (refer to Appendix 4-II, Section 8.1).

  ●    Valard EMS Complete for 2019; ongoing for remaining Project construction

Yes

    Control – Contractor Measures #26

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

       

2-56 56 CEPP Section 4.0 – General Environmental Protection Measures – Firearms – Contractor Measures #21

OEMP Section 5.1 – Environmental Management During Operation – General Mitigation Measures – Wildlife and Wildlife Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Project personnel will be prohibited from carrying firearms on the Project Site.   ●  ●  Adherence to CEPP and DPP; Online Site Orientation; Valard Policy

Ongoing Yes

2-57 57 CEPP Section 4.0 – General Environmental Protection Measures – Pets – Contractor Measures #22

OEMP Section 5.1 – Environmental Management During Operation – General Mitigation Measures – Wildlife and Wildlife Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Project personnel will be prohibited from bringing pets (e.g., dogs and cats) on site.   ●  ●  Adherence to CEPP and DPP; Online Site Orientation; Valard Policy

Ongoing Yes

2-58 58 CEPP Section 4.0 – General Environmental Protection Measures – Fire – Contractor Measures #23

In the event of a fire, follow the Environmental Emergency Response Plan developed by the Contractor for this Project.

  ●    Valard OEWTL Online Site Orientation; Atwell Health and Safety Plan; Valard POD “Safety” contacts

Ongoing Yes

15 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2-59 59 CEPP Section 4.0 – General Environmental Protection Measures – Fire – Contractor Measures #24

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincial Park – Contractor Measures #21

CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Timber and Brush Disposal – Contractor Measures #54

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Significant Wildlife Habitat – Contractor Measures #39

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

The General Contractor (Valard) will follow fire prevention measures outlined in the Fire Prevention Contingency Plan (refer to Appendix 4-II, Section 7.3).

  ●    Valard OEWTL Online Site Orientation; Adherence to CEPP and DPP; OEWTL Industrial Operations Fire Prevention and Preparedness Plan

Complete for 2019; ongoing for remaining Project construction

Yes

2-60 60 CEPP Section 4.0 – General Environmental Protection Measures – Waste Management – Contractor Measures #25

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincial Park – Contractor Measures #22

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Significant Wildlife Habitat – Contractor Measures #40

CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Waste Management – Contractor Measures #19

CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Garbage and Debris – Contractor Measures #5EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

The General Contractor (Valard) will adhere to the Waste Management Plan (refer to Appendix 4-II, Section 8.2).   ●    Valard EMS Complete for 2019; ongoing for remaining Project construction

Yes

2-61 61 CEPP Section 4.0 – General Environmental Protection Measures – Waste Management – Contractor Measures #26

EA Report – Section 7 – Surface Water

The General Contractor (Valard) will develop a detailed Waste Management Plan for review and approval by the Owner at least 30 days prior to construction of each workfront.

●      Waste Management Plan

Development of document complete in CEPP

Yes

16 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2-62 62 CEPP Section 4.0 – General Environmental Protection Measures – Transportation, Storage and Handling – Contractor Measures #27

CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Transportation, Storage, and Handling – Contractor Measures #9

CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Transportation, Storage, and Handling – Contractor Measures #7

CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan – Transportation, Storage, and Handling – Contractor Measures #14

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 18 – Socio-Economics

The transportation, storage, and handling of hazardous materials (e.g., fuel, hydrocarbon, brake fluids) will be in compliance with the Technical Standards and Safety Act, 2000, the Transportation of Dangerous Good Act, 1992, the National Fire Code (National Fire Code of Canada 2010), the Explosives Act (Government of Canada 1985), and the Occupational Health and Safety Act (Government of Ontario 1990b).

  ●    Valard EMS; Adherence to CEPP, regulations and requirements identified if applicable permits and authorizations

Complete for 2019; ongoing for remaining Project construction

Yes

2-63 63 CEPP Section 4.0 – General Environmental Protection Measures – Air Quality / Emissions– Contractor Measures #28

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincial Park – Contractor Measures #26

CEPP Section 4.0 – General Environmental Protection Measures – Noise – Contractor Measures #46

OEMP Section 5.2 – Access and Travel on Right-of-Way – Vehicles and Equipment

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 9 – Air Quality

EA Report – Section 10 – Greenhouse Gases

EA Report – Section 11 – Acoustic Environment

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 18 – Socio-Economics

EA Report – Section 19 – Non-Traditional Land and Resource Use

EA Report – Section 21 – Human Health

Turn off vehicles and equipment when not in use and minimize idling unless weather and/or safety conditions dictate the need for them to remain turned on and in a safe operating condition.

  ●  ●  Adherence to CEPP and DPP

Ongoing Yes

17 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2-64 64 CEPP Section 4.0 – General Environmental Protection Measures – Air Quality / Emissions– Contractor Measures #31

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 9 – Air Quality EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 21 – Human Health

Burning of slash will be in accordance with regulatory approvals and permits and subject to agreements with landowners, SFL holders (e.g., overlapping agreements).

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

2019 burning completed in accordance with municipal and provincial burn permits

Yes

2-65 65 CEPP Section 4.0 – General Environmental Protection Measures – Air Quality / Emissions– Contractor Measures #32

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 9 – Air Quality

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 18 – Socio-economics

EA Report – Section 19 – Non-Traditional Land and Resource Use

EA Report – Section 21 – Human Health

Implement dust control measures (e.g., spray dust control solution that holds moisture for a long period of time causing dust to settle) as advised by the Environmental Inspector.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

Dust control measures not required for 2019 construction activities

Yes

2-66 66 CEPP Section 4.0 – General Environmental Protection Measures – Air Quality / Emissions– Contractor Measures #33

CEPP Section 7.2 – Contingency Plans – Soil Handling Contingency Plan –Soil Erosion – Contractor Measures #8

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use

Suspend or postpone topsoil handling during high wind or wet conditions, where practicable. If it is not possible to suspend or postpone the construction activities, a site-specific Erosion and Sedimentation Control Plan will be implemented in consultation with the Owner.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

18 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2-67 67 CEPP Section 4.0 – General Environmental Protection Measures – Air Quality / Emissions– Contractor Measures #34

CEPP Section 7.2 – Contingency Plans – Soil Handling Contingency Plan –Soil Erosion – Contractor Measures #9

EA Report – Section 6 – Geology, Terrain and Soils EA Report – Section 7 – Surface Water

EA Report – Section 9 – Air Quality

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

EA Report – Section 21 – Human Health

To minimize drifting soils and loss of topsoil in areas prone to wind or water erosion stabilize the disturbed area as soon as practicable by:

sowing a fast growing ground cover (e.g., cereal crop); installing erosion control blankets; or walking down tree and shrub debris over exposed soils (rollback).

  ●    Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2-68 68 CEPP Section 4.0 – General Environmental Protection Measures – Air Quality / Emissions– Contractor Measures #35

CEPP Section 7.2 – Contingency Plans – Soil Handling Contingency Plan –Soil Erosion – Contractor Measures #10

CEPP Section 8.1 – Environmental Management Plans – Erosion and Sedimentation Control Plan – Vegetation Cover – Contractor Measures #6EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils EA Report – Section 7 – Surface Water

EA Report – Section 9 – Air Quality

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

EA Report – Section 21 – Human Health

Retain compatible vegetation (e.g., below 2 metres (m) in height) where practicable on areas prone to wind erosion, steep slopes, drainage ways or next to a water body.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019, clearing and disturbance limited where practicable; ongoing for remaining Project construction

In Progress

19 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2-69 69 CEPP Section 4.0 – General Environmental Protection Measures – Air Quality / Emissions–Contractor Measures #36

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Soil Storage – Contractor Measures #52

CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Soil Storage – Contractor Measures #31

CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Soil Storage– Contractor Measures #25

CEPP Section 7.2 – Contingency Plans – Soil Handling Contingency Plan –Soil Erosion – Contractor Measures #11

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 9 – Air Quality

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

EA Report – Section 21 – Human Health

Tackify, cover, seed, apply water or pack the topsoil stockpiles and windrows with approved equipment, if soils prone to wind erosion. 

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

No topsoil stockpiles requiring wind erosion measures in 2019

Not started

2-70 70 CEPP Section 4.0 – General Environmental Protection Measures – Air Quality / Emissions– Contractor Measures #37

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Vehicle Use – Contractor Measures #27

CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan – Vehicle Use – Contractor Measures #13

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 9 – Air Quality

EA Report – Section 10 – Greenhouse Gases

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Land Resource Use

EA Report – Section 18 – Socio-economics

EA Report – Section 21 – Human Health

Use multi-passenger vehicles to transport workers to site when practicable.   ●    Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

20 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2-71 71 CEPP Section 4.0 – General Environmental Protection Measures – Air Quality / Emissions– Contractor Measures #38

CEPP Section 4.0 – General Environmental Protection Measures – Noise – Contractor Measures #47 EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 9 – Air Quality

EA Report – Section 11 – Acoustic Environment

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 18 – Socio-economics

EA Report – Section 19 – Non-Traditional Land and Resource Use

Where occupied residences are confirmed within 100 m of construction, schedule activities within 5 kilometre (km) radius in a manner that reduces the number of construction activities occurring at the same time.

  ●    Adherence to CEPP and DPP

Ongoing In Progress

2-72 72 CEPP Section 4.0 – General Environmental Protection Measures – Noise – Contractor Measures #39

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincial Park – Contractor Measures #25

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 11 – Acoustic Environment

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 18 – Socio-Economics

EA Report – Section 19 – Non-Traditional Land and Resource Use

EA Report – Section 21 – Human Health

Comply with local municipal noise by-laws or MECP Noise Guideline NPC-300 (MOECC 2013) and the MECP Model Municipal Noise Control Bylaw NPC-115 (MOECC 1978).

  ●    Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2-73 73 CEPP Section 4.0 – General Environmental Protection Measures – Noise – Contractor Measures #40

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincial Parks – Owner Measures #14

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 11 – Acoustic Environment

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 18 – Socio-Economics

EA Report – Section 19 – Non-Traditional Land and Resource Use

EA Report – Section 21 – Human Health

The Owner will work with the Ontario Parks to plan construction around the peak park season, from June to September, where the Project Site is located within a provincial park.

●  ●    Valard EMS; Adherence to DPP

Refer to park DPPs Yes

2-74 74 CEPP Section 4.0 – General Environmental Protection Measures – Noise – Contractor Measures #44

CEPP Section 8.3 – Environmental Management Plans – Blasting Management Plan – Notification – Owner Measures #3

EA Report – Section 2 – Consultation and Engagement Summary EA Report – Section 11 – Acoustic Environment

EA Report – Section 18 – Socio-Economics

EA Report – Section 19 – Non-Traditional Land and Resource Use

Notify applicable federal and provincial regulatory agencies and local municipal officials, and other affected parties 45 days prior to commencing blasting activities and implosion operations as required by approval conditions.

●  ●    Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

2019 construction activities did not include blasting activities.

Not Started

21 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2-75 75 CEPP Section 4.0 – General Environmental Protection Measures – Noise – Contractor Measures #48 CEPP Section 4.0 – General Environmental Protection Measures – Protected Areas – Contractor Measures #52

CEPP Section 8.3 – Environmental Management Plans – Blasting Management Plan – Schedule – Contractor Measures #4

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 11 – Acoustic Environment

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 18 – Socio-Economics

EA Report – Section 19 – Non-Traditional Land and Resource Use

No blasting near operating campgrounds, Ontario Trail Network trails or canoe routes on weekends and holidays beginning May Long weekend and ending Labour Day weekend, inclusive.

  ●    Valard EMS; Adherence to DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include blasting activities

Not Started

2-76 76 CEPP Section 4.0 – General Environmental Protection Measures – Noise – Contractor Measures #49

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincial Park – Contractor Measures #28

CEPP Section 8.3 – Environmental Management Plans – Blasting Management Plan – Schedule – Contractor Measures #5

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 11 – Acoustic Environment

EA Report – Section 18 – Socio-Economics

EA Report – Section 19 – Non-Traditional Land and Resource Use

No blasting near provincial parks on weekends and holidays beginning May Long weekend and ending Labour Day weekend, inclusive.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Refer to park DPPs; 2019 construction activities did not include blasting activities

Not Started

2-77 77 CEPP Section 4.0 – General Environmental Protection Measures – Noise – Contractor Measures #51

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincial Park – Contractor Measures #30

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 4 – Project Description

EA Report – Section 11 – Acoustic Environment

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 18 – Socio-Economics

EA Report – Section 19 – Non-Traditional Land and Resource Use

Construction activities will occur during the daytime period from 07:00 to 19:00. In the event that construction will occur beyond the daytime period, the Owner will re-evaluate the potential Project-related effects and if required, review mitigation requirements and revise Project planning documents as necessary.

  ●    Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2-78 78 CEPP Section 4.0 – General Environmental Protection Measures – Protected Areas – Contractor Measures #53

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Signage and Setback – Contractor Measures #5

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Place warning signs 150 m upstream and 100 m downstream of water crossings on scheduled waterways prior to and during construction.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

No scheduled waterways crossed in 2019

Not Started

22 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2-79 79 CEPP Section 4.0 – General Environmental Protection Measures – Protected Areas – Contractor Measures #54

OEMP Section 5.3 – Vegetation Management Program – Canoe Routes and Portages EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

EA Report – Section 20 – Visual Environment

Implement the following mitigation measures for canoe routes and portages:

vegetation clearing within a minimum of 90 m around Category A canoe routes (i.e., Pukaskwa River canoe route, White River canoe route and Pukaskwa River canoe route) and their associated portage will be limited

to where necessary for safety and compatible vegetation (e.g., below 2 m in height) will be retained where practicable (MNRF 2015);

vegetation clearing within a minimum of 30 m around Category B canoe route (i.e., White River canoe route, Michipicoten River canoe route and Magpie River canoe route) and their associated portage will be limited to

where necessary for safety and compatible vegetation (e.g., below 2 m in height) will be retained where practicable (MNRF 2015);

vegetation clearing around a canoe route will be limited to where necessary for safety and compatible vegetation (e.g., below 2 m in height) will be retained where practicable to meet regulatory requirements and

minimize visual evidence of disturbance from activities;

retain compatible vegetation (e.g., below 2 m in height) around a portage, where practicable to meet regulatory requirements;

maintain visibility of portage on either side of the ROW (e.g., no stockpiled vegetation or soils at the portage access points) and access roads for recreational user accessibility;

during construction, keep portages cleared of vegetation debris and maintain the existing grade of the portage in a manner that it is safe for the recreational users; and

no disturbance of portages outside of the Project Site and access roads will be permitted.

  ●  ●  Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

No clearing activity around Category A or B canoe routes occurred in 2019

Yes.

2-80 80 CEPP Section 5.0 – Environmentally Sensitive Features – Recommended Construction Timing Windows and Restrictions

A summary of the recommended construction timing windows and restrictions that are expected to apply during the construction of the Project are presented in Table 4-II-1 (refer to Appendix 4-II). Additional timing windows and restrictions will be confirmed as Project planning and design progress.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

2019 construction activities occurred outside of applicable timing windows

Yes

2-81 81 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Regulatory Approval – Owner Measures #1

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

Obtain necessary environmental permits and approvals prior to construction of each workfront in environmentally sensitive areas.

●      Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2-82 82 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Environmental Surveys – Owner Measures #2

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – General – Owner Measures #35

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – Fish – Owner Measures #47

CEPP Section 7.4 – Contingency Plans – Discovery of Heritage or Archaeological Resources Contingency Plan – Due Diligence – Owner Measures #1

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources

EA Report – Section 19 – Non-Traditional Land and Resource Use

The Owner will arrange for a preliminary pre-construction field reconnaissance to ground-truth the Project footprint, followed by pre-construction environmental surveys as required in the approval conditions, or as per federal or provincial requirements.

●      Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Seasonal pre-construction environmental surveys completed for 2019 under guidance of resource specialists; ongoing for remaining Project construction

Yes

23 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2-83 83 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Environmental Surveys – Owner Measures #3 EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources

EA Report – Section 19 – Non-Traditional Land andResource Use

The Owner will monitor the Project Site during construction for incidental sensitive features (e.g., water body, rare plant, rare vegetation community, wildlife species of concern, archaeological resources) that have not been previously identified on the Project Site. In the event that a sensitive feature is suspected, the contingency plans in Section 7 will be implemented.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2-84 84 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Resources Specialist – Owner Measures #6

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

The Owner will provide the appropriate resource specialist, if required, to assess sensitive features and to inspect or monitor Project activities at or near sensitive areas.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2-85 85 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Project Sites – Owner Measures #7

EA Report – Section 14 – Wildlife and Wildlife Habitat

Perform local route refinements or refine Project infrastructure in the planning stage to avoid known environmentally sensitive features, species at risk, and species of concern and/or their habitat, if required.”

●      Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Not local route refinements were required/completed in 2019

Yes

2-86 86 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Archaeological and Heritage Resources – Owner Measures #8

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 15 – Archaeological Resources

Archaeological and heritage resources studies will be completed, the archaeological and heritage resource sites identified and the associated mitigation identified prior to construction of each workfront. This information will be provided by the Owner to the Contractor.

●      Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2-87 87 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Archaeological and Heritage Resources – Owner Measures #9

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources

Adhere to conditions of the compliance letter from the MTCS for the Project under the Ontario Heritage Act prior to and during construction if necessary.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

Complete for 2019; ongoing for remaining Project construction

Yes

24 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2-88 88 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Archaeological and Heritage Resources – Owner Measures #10

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Heritage and Archaeological Resources – Contractor Measures #10

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

In the event that a previously unidentified heritage or archaeological resources (e.g., arrow heads, modified bone, pottery fragments, fossils) are suspected or encountered unexpectedly during construction, follow the Discovery of Heritage and Archaeological Resources Contingency Plan (refer to Appendix 4-II, Section 7.4).

  ●    Valard EMS; Adherence to the CEPP; Indigenous monitors on-site during construction, Ongoing engagement with Indigenous communities

No previously unidentified heritage or archaeological resources found during 2019 construction activities

Yes

2-89 89 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Indigenous Land and Resource Use Site – Owner Measures #11

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Indigenous Land and Resource Use Site – Contractor Measures #13

CEPP Section 7.8 – Contingency Plans – Indigenous Land and Resource Use Site Contingency Plan – Incidental Discovery – Contractor Measures # 2EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

OEMP Section 5.3 – Vegetation Management Program – Traditional Use Plant Species

In the event that a previously unidentified Indigenous land and resource use site is suspected or encountered within the Project site, follow the Indigenous Land and Resource Use Site Contingency Plan (refer to Appendix 4-II, Section 7.8).

●  ●  ●  Valard EMS; Adherence to the CEPP; Indigenous monitors on-site during construction, Ongoing engagement with Indigenous communities

No previously unidentified heritage or archaeological resources found during 2019 construction activities; no formal Indigenous land or resource sites have been identified. In January 2020, Pic Mobert First Nation notified NextBridge of the potential for Indigenous land and resource potential in the area of White Lake and Nursery Lake. NextBridge remains engaged with community to ensure proper mitigation plans are in place, in the areas concerned.

Yes

2-90 90 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincial Parks – Owner Measures #15

EA Report – Section 19 – Non-Traditional Land and Resource Use

Construction activities will be staged in protected areas to avoid or minimize potential effects on ecologically sensitive areas, life cycle periods, and peak visitor periods, when construction schedule allows. Mitigation will be applied to reduce negative effects on protected areas.

●  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include protected areas

Not Started

25 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2-91 91 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincial Parks – Owner Measures #19

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Significant Wildlife Habitat – Owner Measures #28

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Weeds – Owner Measures #57

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

The Owner will follow weed control and management measures outlined in the Weed Management Plan (refer to Appendix 4-II, Section 8.4).

  ●    Adherence to CEPP and DPP

2019 construction activities did not include weed management activities

Not Started

2-92 92 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincially Significant Wetlands – Owner Measures #22

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 19 – Non-Traditional Land and Resource Use

Avoidance of the Nipigon River Provincially Significant Wetlands (PSW) was achieved via Project design. Although the transmission line is shown as crossing the Nipigon River PWS on the Environmental Alignment Sheets, the Project is not expected to disturb this PWS as the transmission structures will be placed at the setback distance of approximately 30 m from the PSW.

●      Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not occur near the Nipigon River PSW

Not Started

2-93 93 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincially Significant Wetlands – Owner Measures #23 EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 19 – Non-Traditional Land and

Resource Use

If additional transmission structures are required, avoid locating the transmission structures within a PSW or within its associated 30 m setback

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Not Applicable to 2019 construction activities

Yes

2-94 94 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Significant Wildlife Habitat – Owner Measures #24

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 19 – Non-Traditional Land and Resource Use

Avoid disturbance to SWH (Significant Wildlife Habitat; MNR 2000, 2010b, 2014) and their associated setbacks to the extent practicable. Where avoidance is not practicable, adhere to the recommended construction timing windows a n d restrictions (refer to Appendix 4-II, Table 4-II-1).

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete; 2019 construction activities occurred outside of applicable timing windows

Yes

2-95 95 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Significant Wildlife Habitat – Owner Measures #26

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Signage and Setbacks – Owner Measures #4

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Clearly identify known environmentally sensitive features (e.g., rare plant, wetland, water body, SWH) and associated setbacks as shown on the Environmental Alignment Sheets and Access and Construction Environmental Maps.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Seasonal pre-construction environmental surveys completed for 2019 under guidance of resource specialists; ongoing for remaining Project construction

Yes

26 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2-96 96 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Significant Wildlife Habitat – Owner Measures #27

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

Flag undisturbed adjacent areas to the extent required to protect adjacent seed sources from being affected.   ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019 to delineate work are boundaries; ongoing for remaining Project construction

Yes

2-97 97 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Areas of Natural and Scientific Interest – Owner Measures #30

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 19 – Non-Traditional Land and Resource Use

Avoidance of the Magpie River / Terraces Area of Natural and Scientific Interest (ANSI) was achieved via Project design.

●      Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Not Applicable to 2019 construction activities

Not Started

2-98 98 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Areas of Natural and Scientific Interest – Owner Measures #31

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 19 – Non-Traditional Land and Resource Use

If additional transmission structures are required, avoid locating the transmission structures within an ANSI or within its associated 50 m setback and consult with appropriate regulatory agency.

  ●    Valard EMS; EAS and Construction Access Alignment Sheets; Adherence to CEPP and DPP

Not Applicable to 2019 construction activities

Not Started

2-99 99 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Critical Landform/ Vegetation Association – Owner Measures #32

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes EA Report – Section 19 – Non-Traditional Land and Resource Use

Avoidance of the Critical Landform/Vegetation Association (CLVA) in Gravel River Conservation Reserve was not practicable as a change in routing design at that location would result in additional greenfield disturbances. The following measures will be implemented to mitigate potential effect of the Project on this CLVA:

Obtain a work permit from the MNRF under the Provincial Parks and Conservation Reserves Act for development within a CLVA;

The Owner will employ the services of qualified Environmental Inspector(s) to guide implementation, monitor and report on the effectiveness of the construction procedures and mitigation measures for minimizing potential impacts;

Clearly mark known site-specific features (e.g., rare plant, wetland, water body, SWH) and associated setbacks as shown on the Environmental Alignment Sheets and the Access and Construction Environmental Maps.

Flag undisturbed adjacent areas to the extent required to protect adjacent seed sources from being affected. The Owner will review protective and mitigative measures with the General Contractor (Valard).

The Owner will follow weed control and management measures outlined in the Weed Management Plan (refer to Section 8.4).

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Not Applicable to 2019 construction activities

Not Started

2- 100

100 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Critical Landform/ Vegetation Association – Owner Measures #33

EA Report – Section 19 – Non-Traditional Land and Resource Use

The proposed mitigation measures will be reviewed and agreed upon in consultation with MNRF. ●  ●    Valard EMS; Adherence to CEPP and DPP; Environmental Construction & Operations Compliance and Assurance Matrix

Complete for 2019; ongoing for remaining Project construction

Yes

2- 101

101 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Research Plots – Owner Measures #34

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 19 – Non-Traditional Land and Resource Use

Avoid disturbance to research plots to the extent practicable. If avoidance is not practicable, the Owner will implement the following mitigation measures:

The Owner will consult with MNRF, Crown interested holders (e.g. mining lease holders, unpatented claim holders, aggregate permit holders, non-freehold disposition holders, SFL holders, and other interest holders) forestry, mining claim and aggregate license holders and, where appropriate, to develop mutually beneficial agreements with the affected tenure holders.

The Owner will employ the services of qualified Environmental Inspector(s) to guide implementation, monitor and report on the effectiveness of the construction procedures and mitigation measures for minimizing potential impacts.

Clearly mark known site-specific features (e.g., rare plant, wetland, water body, SWH) and associated setbacks as shown on the Environmental Alignment Sheets and the Access and Construction Environmental Maps.

●  ●    Valard EMS; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

27 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 102

102 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – General – Owner Measures #36

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Environmental training for workers will include information on den identification and procedures to follow if a den is identified.

●      Valard OEWTL Online Site Orientation

Orientation documents developed and provided to on-site personnel.

Yes

2- 103

103 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – Caribou – Owner Measures #37

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – Caribou – Contractor Measures #55

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 14 – Wildlife and Wildlife Habitat

Within a caribou range, avoid activities within 10 km of known or potential high use areas (e.g., nursery areas, winter use areas, travel corridors) as shown on the Environmental Alignment Sheets and the Access and Construction Environmental Maps to the extent practicable.

●  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities were not conducted within 10 km of known or potential high use areas.

Not Started

2- 104

104 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – Caribou – Owner Measures #38

EA Report – Section 2 – Consultation and Engagement Summary

If avoidance of caribou high use areas is not possible, the Owner will obtain a permit under the Endangered Species Act (Government of Ontario 2007), if required by the MECP.

●  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities were not conducted in caribou high use areas.

Not Started

2-

105

105 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – Birds – Owner Measures #39

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – Birds – Contractor Measures #57

EA Report – Section 2 – Consultation and Engagement Summary EA Report – Section 14 – Wildlife and Wildlife Habitat

Avoid vegetation clearing activities during the migratory bird nesting period (refer to Appendix 4-II, Table 4-II-1) when construction schedule allows.

●  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities were conducted outside the migratory bird nesting period.

Not Started

28 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 106

106 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – Birds – Owner Measures #40

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – Birds – Contractor Measures #58CEPP Section 7.5 – Contingency Plans – Wildlife Features of Concern Discovery Contingency Plan – Due Diligence – Owner Measures #1

OEMP Section 5.3 – Vegetation Management Program – Wildlife and Wildlife Habitat

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

If vegetation removal must be completed during the migratory bird nesting period, notify the Owner as soon as possible, and implement the procedures in the Nest Sweep Protocol (refer to Appendix 4-II, Appendix G). Similar measures will be taken for vegetation removal during routine ROW maintenance.

  ●  ●  Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities were conducted outside the migratory bird nesting period.

Not Started

2- 107

107 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – Bats – Owner Measures #42

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – Birds – Owner Measures #39

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – Birds – Contractor Measures #57

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – Bats – Contractor Measures #60

EA Report – Section 14 – Wildlife and Wildlife Habitat

Avoid vegetation clearing activities during the bat maternity roosting period (refer to Appendix 4-II, Table 4-II-1). If avoidance of bat maternity roosting period is not possible, the Owner will obtain a permit under the Endangered Species Act (Government of Ontario 2007), if required by the MNRF/MECP.

●  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities were conducted outside the bat maternity roost period.

Not Started

2- 108

108 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – Bats – Owner Measures #43

EA Report – Section 14 – Wildlife and Wildlife Habitat

If vegetation removal must be completed during the bat maternity roosting period (refer to Table 4-II-1), a resource specialist will conduct pre-construction surveys in suitable roosting habitat affected by the Project to determine occupancy. If sensitive features are identified, a site-specific mitigation will be developed and implement in consultation with appropriate regulatory agencies (e.g., MNRF, Environment Canada) to avoid and/or offset the removal of maternity roosting habitat (e.g., through the installation of bat boxes).

●  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities were conducted outside the bat maternity roost period.

Not Started

2- 109

109 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – Bats – Owner Measures #44

EA Report – Section 14 – Wildlife and Wildlife Habitat

Avoid construction activities during the bat hibernation period within 400 m up to 1,000 m from a known bat hibernacula entrance (refer to Table 4-II-1). If adherence to the timing and/or setback restrictions is not possible, site-specific mitigation will be developed and implemented in consultation with MNRF to avoid and/or offset the removal of maternity roosting habitat (e.g., through the installation of bat boxes).

●  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities were not conducted near known bat hibernacula.

Not Started

29 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 110

110 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – Bats – Owner Measures #45

EA Report – Section 14 – Wildlife and Wildlife Habitat

Continue to engage with the MNRF regarding permitting requirements for little brown myotis and northern long-eared myotis

●  ●    Valard EMS; Consultation and Engagement Summary Table

Ongoing In Progress

2- 111

111 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – Amphibian and Reptiles – Owner Measures #46

OEMP Section 5.3 – Vegetation Management Program – Wildlife and Wildlife Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

Where clearing or construction activities are planned during the amphibian breeding season (refer to Table 4-II-1), the Owner or the Environmental Inspector will visually assess the Project Site for active breeding habitat. If potential active breeding habitats are identified, the Owner will identify locations for exclusion fence or capture and relocate amphibians and reptiles off the Project Site prior to or during construction.

●  ●  ●  Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities were conducted outside the amphibian breeding season.

Not Started

2- 112

112 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – Fish – Owner Measures #48

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – Fish – Contractor Measures #67

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Schedule – Contractor Measures #8

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Avoid construction activities below the high-water mark (e.g., clearing vegetation, installing or removing equipment crossing structures or fill) during the restricted in-water work timing window (refer to Appendix 4-II, Appendix I).

●  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

One culvert install completed in 2019 on LRCA watercourse in compliance with permits and under supervision of a resource specialist. No other activities below the high-water mark.

Yes

2- 113

113 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – Fish – Owner Measures #50

EA Report – Section 2 – Consultation and Engagement

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

If in-water work timing restrictions cannot be adhered to, a resource specialist may need to survey the area for sensitive fish and fish habitat and based on the results of the survey, a site-specific mitigation and monitoring plan w i l l be developed. An application with a description of the fish and fish habitat in the water body and site-specific mitigation measures will be submitted to MNRF, DFO and/or LRCA prior to construction of each workfront. Based on the regulatory review, additional permits may be required from MNRF, DFO and/or LRCA to complete work within the restricted activity timing window.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

One culvert install completed in 2019 on LRCA watercourse in compliance with permits. Work completed under supervision of a resource specialist. No other activities below the high-water mark.

Yes

2- 114

114 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Rare Plants/ Rare Vegetation Communities – Owner Measures #52

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 19 – Non-Traditional Land and Resource Use

Avoidance to three provincially imperiled (S2) rare plant species, alpine woodsia (Woodsia alpina), floating marsh marigold (Caltha natans) and purple bluejoint (Calamagrostis purpurascens), was not achieved during Project design. The following measures will be implemented to mitigate potential effect of the Project on these three rare plant occurrences:

Prior to construction of each workfront, the Owner will contact a resource specialist to assess the known species or habitat and identify the magnitude of disturbance to the vegetation feature.

Depending on the species or habitat and the magnitude of disturbance, the resources specialist will determine a suitable course of action in consultation with the Owner and, if necessary, the appropriate regulatory agencies.

●  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Seasonal pre-construction environmental surveys completed for 2019 under guidance of resource specialists; ongoing for remaining Project construction

In Progress

2- 115

115 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Rare Plants/ Rare Vegetation Communities – Owner Measures #53

CEPP Section 7.6 – Contingency Plans – Rare Plant Discovery Contingency Plan –Due Diligence – Owner Measures #1

EA Report – Section 12 – Vegetation and Wetlands

A search for potential rare plant and rare vegetation community in the Project Site shall be completed prior to construction of each workfront, in order to document incidences.

●      Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Seasonal pre-construction environmental surveys completed for 2019 under guidance of resource specialists; ongoing for remaining Project construction

In Progress

30 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 116

116 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Rare Plants/ Rare Vegetation Communities – Owner Measures #54

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Rare Plants / Rare Vegetation Communities – Contractor Measures #84

OEMP Section 5.3 – Vegetation Management Program – Rare Plants/ Rare Vegetation Communities

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 19 – Non-Traditional Land and Resource Use Land and Resource Use

In the event that a previously unidentified rare plant species or a rare vegetation community are suspected or encountered unexpectedly, implement the Rare Plant Discovery Contingency Plan (refer to Appendix 4-II, Section 7.6).

  ●  ●  Valard EMS; Adherence to CEPP and DPP

Seasonal pre-construction environmental surveys completed for 2019 under guidance of resource specialists; ongoing for remaining Project construction

In Progress

2- 117

117 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wetlands – Owner Measures #55

CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Transmission Structure Placement – Owner Measures #1

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 19 – Non-Traditional Land and Resource Use

Transmission structures and associated infrastructure will be located to avoid environmentally sensitive features (e.g., rare plant, wetland, archaeological sites) that were identified during pre-construction surveys, to the extent practicable.

●  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 118

118 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wetlands – Owner Measures #56

CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Transmission Structure Placement – Owner Measures #2

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

Avoid placement of transmission structures and associated infrastructure within a wetland or within the 30 m water body buffer (i.e., 30 m area extending from the high-water mark surrounding the water body).

●  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 119

119 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Weeds – Owner Measures #58

CEPP Section 8.4 – Environmental Management Plans – Weed Management Plan – Weed Management – Contractor Measures #7

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 21 – Human Health

The use of herbicides during construction is prohibited   ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include weed management activities

Not Started

31 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 120

120 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Water Wells – Owner Measures #59

EA Report – Section 8 – Groundwater

Conduct a pre-excavation survey of identified private wells within 100 m of the excavated locations by a licensed water well technician in accordance with the Wells Regulation (O.Reg. 903). Where landowner permission is granted, the pre-excavation survey will include completion of a well questionnaire to obtain details about the well, measurement of water levels and collection of a water quality sample.

●  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

No excavations occurred within 100 m of private wells in 2019

Yes

2- 121

121 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Regulatory Approvals – Contractor Measures #1

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

The General Contractor (Valard) will follow all environmental permitting approval conditions. ●  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 122

122 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Schedule – Contractor Measures #2

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

The General Contractor (Valard) will adhere to the recommended construction timing windows and restrictions (refer to Appendix 4-II, Table 4-II-1).

●  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities occurred outside of applicable timing windows

Yes

2- 123

123 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Schedule – Contractor Measures #3

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

If adherence to the timing windows and restrictions is not possible, the General Contractor (Valard) will develop a site-specific mitigation and monitoring plan in consultation with the Owner and appropriate regulatory agencies (e.g., MNRF, DFO, and/or LRCA).

●  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities occurred outside of applicable timing windows

Yes

2- 124

124 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Signage and Setback – Contractor Measures #6

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Post signs warning of high use wildlife areas as shown on the Environmental Alignment Sheets and the Access and Construction Environmental Maps to the extent practicable.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 125

125 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Signage and Setback – Contractor Measures #7

CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Surveying and Flagging – Contractor Measures #12

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads –Surveying and Flagging – Contractor Measures #11

CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Survey and Flagging – Contractor Measures #13

Inspect the flags or temporary fences around environmentally sensitive features on a regular basis so that they are in place and maintained during clearing and construction Replace markings as soon as practicable and as necessary.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

32 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2-

126

126 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Heritage and Archaeological Resources – Contractor Measures #8

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 15 – Archaeological Resources

Destruction or collection of archaeological resources by Project personnel is prohibited.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 127

127 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Heritage and Archaeological Resources – Contractor Measures #9

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 15 – Archaeological Resources

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

No clearing or construction activity within flagged or temporarily fenced areas that contain archaeological resources.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets; Indigenous monitors on-site during construction

Complete for 2019; ongoing for remaining Project construction

Yes

2- 128

128 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Indigenous Land and Resource Use Site – Contractor Measures #11

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Destruction or use of Indigenous land and resource use sites (e.g., cultural site, camp, or trapline equipment) by Project personnel is prohibited.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets; Indigenous monitors on-site during construction

Complete for 2019; ongoing for remaining Project construction

Yes

2- 129

129 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Indigenous Land and Resource Use Site – Contractor Measures #12

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

No clearing or construction activity within flagged or temporarily fenced areas that contain Indigenous land and resource use site.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets; Indigenous monitors on-site during construction

Complete for 2019; ongoing for remaining Project construction

Yes

2- 130

130 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincial Park – Contractor Measures #14

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

Reduce unauthorized users and access to protected areas by installing signage and other appropriate barriers on access roads where permissible by MNRF/MECP.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

33 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 131

131 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincial Park – Contractor Measures #15

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Implement the following mitigation measures when construction is required in provincial parks:

Construction equipment, including rig mats, will arrive on the Project Site clean (i.e., free of soil and vegetative debris);

confine grubbing and stripping to the transmission structure locations and new access roads;

seed areas prone to erosion with a native cover crop (e.g., cereal crop) and certified seed mix approved by the applicable regulatory agency as soon as feasible after construction;

plant conifers when reclaiming laydown yards, construction camps, and storage yards and other disturbances located off of the transmission line ROW and in consultation with the landowner or communities and applicable regulatory authority.

the use of herbicides during construction is prohibited.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include provincial parks

Not Started

2- 132

132 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincial Park – Contractor Measures #19

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Significant Wildlife Habitat – Contractor Measures #37

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Rare Plants / Rare Vegetation Communities – Contractor Measures #83

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Weeds – Contractor Measures #85

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes EA Report – Section 19 – Non-Traditional Land and Resource Use

The General Contractor (Valard) will follow weed control and management measures outlined in the Weed Management Plan (refer to Appendix 4-II, Section 8.4).

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include weed management activities

Not Started

34 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 133

133 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincial Park – Contractor Measures #23

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Significant Wildlife Habitat – Contractor Measures #41

CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Surface Conditions – Contractor Measures #4

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads –Surface Conditions – Contractor Measures #3

CEPP Section 6.3 – Transmission Line Construction Environmental Protection Measures – Geotechnical Investigations – Surface Conditions – Contractor Measures #3

CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Surface Conditions – Contractor Measures #4

CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction Surface Conditions – Contractor Measures #3

CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction Topsoil Stripping – Contractor Measures #11

CEPP Section 6.6 – Transmission Line Construction Environmental Protection Measures – Transmission Structure Assembly and Erection – Surface Conditions – Contractor Measures #4 CEPP Section 6.7 – Transmission Line Construction Environmental Protection Measures – Conductor Stringing and Tensioning – Surface Conditions – Contractor Measures #6

CEPP Section 8.1 – Environmental Management Plans – Erosion and Sedimentation Control Plan – Schedule – Contractor Measures #4

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 19 – Non-Traditional Land and Resource Use

Follow measures outlined in the Soil Handling Contingency Plan (refer to Appendix 4-II, Section 7.2) when working under wet conditions.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 134

134 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincially Significant Wetland – Contractor Measures #32

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 19 – Non-Traditional Land and Resource Use

If additional temporary workspaces are required, avoid locating the workspaces within a PSW or within its associated 30 m setback.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Ongoing In Progress

2- 135

135 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincially Significant Wetland – Contractor Measures #33

EA Report – Section 19 – Non-Traditional Land and Resource Use

Install, monitor and manage appropriate erosion and sedimentation controls as outlined in the Erosion and Sedimentation Control Management Plan (refer to Appendix 4-II, Section 8.1) to prevent sediment and other material entering the Nipigon River.

  ●    Valard EMS; Adherence to DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not occur near the Nipigon River

Not Started

35 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 136

136 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Significant Wildlife Habitat – Contractor Measures #38

CEPP Section 4.0 – General Environmental Protection Measures – Equipment – Contractor Measures #17

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Provincial Park – Contractor Measures #20

EA Report – Section 6 – Geology, Terrain and Soils EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

The General Contractor (Valard) will adhere to the Spill Prevention and Response Contingency Plan (refer to Appendix 4-II, Section 7.1) to prevent spills and/or release.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 137

137 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Significant Wildlife Habitat – Contractor Measures #39

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

The General Contractor (Valard) will follow the fire prevention measures outlined in the Fire Prevention Contingency Plan (refer to Appendix 4-II, Section 7.3).

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 138

138 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Significant Wildlife Habitat – Contractor Measures #42

EA Report – Section 12 – Vegetation and Wetlands EA Report – Section 19 – Non-Traditional Land and Resource Use

Install, monitor and manage appropriate erosion and sedimentation controls as outlined in the Erosion and Sedimentation Control Management Plan (refer to Appendix 4-II, Section 8.1) to prevent sediment and other material entering the SWH.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 139

139 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Significant Wildlife Habitat – Contractor Measures #43

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Reduce the removal of compatible vegetation (e.g., below 2 m in height) within SWH and associated setbacks to the extent practicable.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

In Progress

2- 140

140 CEPP Section 5.2– Environmentally Sensitive Features Protection Measure – Significant Wildlife Habitat – Contractor Measures #44

CEPP Section 5.2– Environmentally Sensitive Features Protection Measure – Wetlands – Contractor Measures #88

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

Conduct ground level cutting/mowing/mulching of vegetation instead of grubbing. Confine grubbing and stripping to the transmission structure locations and new access roads.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

In Progress

36 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 141

141 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Significant Wildlife Habitat – Contractor Measures #45

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wetlands – Contractor Measures #89

OEMP Section 5.3 – Vegetation Management Program – Wildlife and Wildlife Habitat

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

Retain snags (i.e., standing or partially fallen dead trees) to provide wildlife habitat, where retention is not considered a safety hazard.

  ●  ●  Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Ongoing In Progress

2- 142

142 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Significant Wildlife Habitat – Contractor Measures #46

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Critical Landform/ Vegetation Association – Contractor Measures #74

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wetlands – Contractor Measures #94

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 8 – Groundwater

EA Report – Section 19 – Non-Traditional Land and Resource Use EA Report – Section 12 – Vegetation and Wetlands EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 19 – Non-Traditional Land and

Resource Use

Use low ground pressure equipment and prevent ground disturbance by using a protective layer such as frost packing, snow, ice or matting (refer to Appendix 4-II. Appendix B, Figure B-13) or biodegradable geotextile and clay ramps between root/seed bed and construction equipment.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

In Progress

2- 143

143 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – General – Contractor Measures #48

CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan – Wildlife – Contractor Measures #27

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

Report wildlife sightings, issues and incidents with wildlife or nuisance wildlife as soon as it is safe to do so to the Owner, who shall determine corrective and/or emergency action to be taken in the field. The Owner will determine what regulatory reporting is required. Discuss recent wildlife sightings and appropriate mitigation measures during daily tailgate meetings.

  ●    Valard EMS; Adherence to CEPP and DPP; Incident Notification Form; Valard POD and Tailboards

Complete for 2019; ongoing for remaining Project construction

In Progress

37 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 144

144 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – General – Contractor Measures #49

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – Birds – Contractor Measures #59

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – Bats – Contractor Measures #64

CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Wildlife Habitat Contractor Measures #40

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

In the event that sensitive wildlife features (e.g., active nest, bat roost, bat hibernaculum, burrow or den) are found unexpectedly during construction, implement Wildlife Features of Concern Discovery Contingency Plan (refer to Appendix 4-II, Section 7.5).

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

In Progress

2- 145

145 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – General – Contractor Measures #50

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Hunting and fishing on the Project Site by Project personnel is prohibited.   ●    Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2- 146

146 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – General – Contractor Measures #51 OEMP Section 5.1 – Environmental Management During Operation – General Mitigation Measures – Wildlife and Wildlife Habitat EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Harassing or feeding wildlife is prohibited by Project personnel.   ●  ●  Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

38 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 147

147 CEPP Section 5.2 – Environmentally Sensitive Features Protection Measure – Wildlife – General – Contractor Measures #52

CEPP Section 6.2 – Access Roads – Vehicle Use – Contractor Measures #25

CEPP Section 8.5 – Traffic Management Plan – Vehicle Use – Contractor Measures #12

OEMP Section 5.1 – Environmental Management During Operation – General Mitigation Measures – Wildlife and Wildlife Habitat

OEMP Section 5.2 – Access and Travel on Right-of-Way – Vehicles and Equipment

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Recreational use of all-terrain vehicles by Project personnel is prohibited in the Project Site. Vehicles, including all-terrain vehicles, are to be driven in a responsible and environmentally respectful manner.

  ●  ●  Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2- 148

148 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – General – Contractor Measures #53

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Vehicle Use – Contractor Measures #22

CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan – Vehicle Use – Contractor Measures #11

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 18 – Socio-economics

EA Report – Section 19 – Non-Traditional Land and Resource Use

Vehicles will not exceed speed limits established by the Owner and will lower speeds in specific conditions such as areas of high erosion hazard and blind corners. Clearly mark speed limits along the access roads.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Ongoing In Progress

2- 149

149 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – General – Contractor Measures #54

CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan – Wildlife – Contractor Measures #26 OEMP Section 5.1 – General Mitigation Measures – Wildlife and Wildlife Habitat

OEMP Section 5.2 – Access and Travel on Right-of-Way – Wildlife and Wildlife Habitat EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Vehicles will yield to wildlife on the roads when safe to do so.   ●  ●  Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

39 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 150

150 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – Caribou – Contractor Measures #56

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads –Access Roads Placement – Contractor Measures #17

CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan – Access Roads Placement – Contractor Measures #19

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 14 – Wildlife and Wildlife Habitat

If avoidance is not possible, the following measures will be implemented to mitigate potential effect of the Project on caribou:

Notify the Owner as soon as possible to obtain the appropriate regulatory approvals;

follow all environmental permitting approval conditions;

time construction to limit disturbance to caribou during sensitive periods such as reproduction and rearing, winter aggregation and foraging, and seasonal dispersal (refer to Appendix 4-II, Table 4-II-1);

consider installing natural barriers such as earth berms (e.g., mounding) or retaining compatible vegetation (e.g., below 2 m in height) in the ROW to reduce the line of sight;

design and construct bends in the temporary access roads in caribou ranges to restrict the line of sight along the road in a manner that it is safe for vehicle travel;

minimize new access in caribou ranges;

where new access is required in caribou ranges, construct only winter grade access (snow roads), when practicable, and decommission roads after construction by implementing clean-up and reclamation measures in Appendix 4-II, Section 5.8 and installing rollback; and

plant conifers when reclaiming laydown yards, construction camps, and storage yards located off of the transmission line ROW and in consultation with the landowner or communities and applicable regulatory authority.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Refer to Project ESA permit. 2019; construction activities were not conducted near the caribou ranges

Not Started

2- 151

151 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – Bats – Contractor Measures #61

Avoid construction activities during the bat hibernation period within 400 m up to 1,000 from a known bat hibernacula entrance (refer to Appendix 4-II, Table 4-II-1) as shown on the Environmental Alignment Sheets and Access and Construction Environmental Maps.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Refer to Project ESA permit; 2019 construction activities were not conducted near known bat hibernacula

Not Started

2- 152

152 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – Bats – Contractor Measures #62

EA Report – Section 14 – Wildlife and Wildlife Habitat

If adherence to the timing and/or setback restrictions is not possible, notify the Owner as soon as possible. The Owner will bring in the appropriate resource specialist to survey the area for sensitive features.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Refer to Project ESA permit 2019; construction activities were not conducted near known bat hibernacula or in maternity roosting period

Not Started

2- 153

153 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – Bats – Contractor Measures #63

OEMP Section 5.2 – Access and Travel on Right-of-Way – Wildlife and Wildlife Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

Avoid physical disturbance to existing anthropogenic structures located off of the Project ROW and access roads that could be roosts for bats (e.g., sheds, barns, houses, buildings, and bridges).

  ●  ●  Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Refer to Project ESA permit 2019; construction activities were not conducted near known bat hibernacula or in maternity roosting period

Not Started

2- 154

154 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – Amphibians and Reptiles – Contractor Measures #65

Construction in identified amphibian and reptile habitat during the breeding period (refer to Appendix 4-II, Table 4-II-1) may require exclusion fencing. Installation and maintenance of amphibian or reptile exclusion fencing will be done by the General Contractor (Valard) under the supervision of the Owner.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities were not conducted during the breeding season

Not Started

40 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 155

155 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wildlife – Fish – Contractor Measures #68

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Schedule – Contractor Measures #10

EA Report – Section 13 – Fish and Fish Habitat

If timing restrictions cannot be adhered to, notify the Owner as soon as possible. The Owner may contact the appropriate regulating agency and bring in the appropriate resource specialist to survey the area for sensitive features if required.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets; Incident Notification Form

2019 construction activities were not conducted during the breeding season

Yes

2- 156

156 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure –Areas of Natural and Scientific Interest – Contractor Measures #69

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 19 – Non-Traditional Land and Resource Use

The General Contractor (Valard) will develop a site-specific Erosion and Sedimentation Control Plan for review and approval by the Owner to prevent sediment and other material entering the Magpie River. Appropriate regulators may be contacted if required.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Not applicable. 2019 construction activities did not occur near the Magpie River.

Not Started

2- 157

157 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection– Areas of Natural and Scientific Interest – Contractor Measures #70

EA Report – Section 12 – Vegetation and Wetlands

If additional temporary workspaces are required, avoid locating the temporary workspaces within an ANSI or within its associated 50 m setback.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities were not within 50 m of ANSI sites

Not Started

2- 158

158 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Critical Landform/ Vegetation Association – Contractor Measures #73

OEMP Section 5.3 – Vegetation Management Program – Areas with Critical Landform/ Vegetation Association

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Reduce the removal of compatible vegetation (e.g., below 2 m in height) in CLVA to the extent practicable.   ●  ●  Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not occur in known CLVA areas.

Yes

2- 159

159 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Critical Landform/ Vegetation Association – Contractor Measures #75

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

Mechanical clearing and other equipment activity will be minimized within a CLVA.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not occur in known CLVA areas.

Yes

2- 160

160 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Critical Landform/ Vegetation Association – Contractor Measures #76

CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Cleaning Equipment – Contractor Measures #15

EA Report – Section 2 – Consultation and Engagement Summary

Clearing may be accomplished by harvesting equipment, mulchers, and hand cutting. Clear merchantable timber by hand, where practicable.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

41 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 161

161 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Research Plots – Contractor Measures #79

If construction cannot avoid research plots, notify the Owner as soon as possible.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets; Incident Notification Form

Complete for 2019; ongoing for remaining Project construction

Yes

2-162 162 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Rare Plants / Rare Vegetation Communities – Contractor Measures #82 EA Report – Section 12 – Vegetation and Wetlands

Install, monitor and manage appropriate erosion and sedimentation controls as outlined in the Erosion and Sedimentation Control Management Plan (refer to Appendix 4-II, Section 8.1) to protect rare plant habitat and/or rare vegetation community from runoff water and sediments as directed by the Environmental Inspector.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Ongoing In Progress

2- 163

163 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wetlands – Contractor Measures #86

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 19 – Non-Traditional Land and Resource Use

Avoid the construction of temporary workspaces in wetlands, to the extent practicable.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 164

164 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wetlands – Contractor Measures #87

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 19 – Non-Traditional Land and Resource Use

Reduce the removal of compatible vegetation (e.g., below 2 m in height) in wetlands and associated setbacks to the extent possible.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 165

165 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wetlands – Contractor Measures #90

EA Report – Section 19 – Non-Traditional Land and Resource Use

Install berms, cross ditches and/or silt fences between wetlands and disturbed areas when there is a risk of sedimentation into the wetland (refer to Appendix 4-II, Appendix B, Figure B-3 and Figure B-4).

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 166

166 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wetlands – Contractor Measures #91

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Topsoil Stripping – Contractor Measures #37CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Topsoil Stripping – Contractor Measures #21

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 12 – Vegetation and Wetlands

Do not strip topsoil within wetlands with the exception of soil salvage to accommodate geotechnical investigation and transmission foundation construction.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

42 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 167

167 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wetlands – Contractor Measures #92

CEPP Section 6.3 – Transmission Line Construction Environmental Protection Measures – Geotechnical Investigations – Soil Storage – Contractor Measures #9CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Soil Storage– Contractor Measures #20

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 12 – Vegetation and Wetlands

When the wetland organic layer is salvaged to accommodate for geotechnical investigations and transmission foundation construction, store the layer separately from upland soils for restoration.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include organic layer salvage in wetlands.

In Yes

2- 168

168 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wetlands – Contractor Measures #93 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Timber and Brush Disposal – Contractor Measures #58

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 12 – Vegetation and Wetlands

Avoid locating burn piles in peat rich areas where residual fires could persist after construction.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 169

169 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wetlands – Contractor Measures #95

EA Report – Section 7 – Surface Water

EA Report – Section 19 – Non-Traditional Land and Resource Use

Re-fueling or equipment maintenance activities will follow mitigation measures outlined in the Spill Prevention and Response Plan (refer to Appendix 4-II, Section 7.1).

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 170

170 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wetlands – Contractor Measures #96

CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Seeding Revegetation – Contractor Measures #32

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Natural recovery is the preferred method of reclamation in wetlands.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include reclamation activities

Not Started

2- 171

171 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Wetlands – Contractor Measures #97

CEPP Section 8.4 – Environmental Management Plans – Weed Management Plan – Seeding and Revegetation – Contractor Measures #15

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Do not seed wetland areas unless re-vegetation is needed (e.g. where a noxious weed seed source is identified within 200 m of disturbed soil in a wetland) to avoid weed invasion.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include seeding activities

Not Started

43 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 172

172 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Water Wells – Contractor Measures #98

EA Report – Section 8 – Groundwater

Avoid construction activities within 100 m of identified private wells. If avoidance is not practicable, notify the Owner as soon as possible. A resource specialist may need to conduct a pre-excavation survey prior to excavating.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Ongoing In Progress

2- 173

173 CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Water Wells – Contractor Measures #99

CEPP Section 8.3 – Environmental Management Plans – Blasting Management Plan – Water Wells – Contractor Measures #9

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 8 – Groundwater

Blasting will not be conducted within 50 m of identified water wells.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include blasting activities

Not Started

2- 174

174 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Regulatory Approvals – Owner Measures #1

EA Report – Section 2 – Consultation and Engagement Summary

On provincial Crown land, approval will be obtained from MNRF prior to clearing of each workfront, as appropriate (e.g., Work Permit, Land Use Permit, and supporting consents from impacted Crown interest holders).

●      Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 175

175 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Regulatory Approvals – Owner Measures #2

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 19 – Non-Traditional Land and Resource Use

On private land, approval will be obtained from the landowner prior to clearing of each workfront. Crown Patent will also be obtained from the local registry office or MNRF to confirm if any trees on private lands are reserved to the Crown. If there is Crown reservation on any tree, the Owner will consult with MNRF and approval may be required prior to clearing of each workfront.

●      Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 176

176 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Regulatory Approvals – Owner Measures #3

Obtain appropriate MNRF, DFO, and/or LRCA approval prior to construction of each workfront if clearing of vegetation is required below the high-water mark for the installation of equipment water body crossings within the restricted activity timing window for in-water work.

●      Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities did not include clearing below the high-water mark

Not Started

44 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 177

177 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Regulatory Approvals – Contractor Measures #1

EA Report – Section 2 – Consultation and Engagement Summary

Overlapping license agreements will be negotiated with SFL holders and Forest Resource License (FRL) obtained as appropriate.

●      Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 178

178 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Schedule – Contractor Measures #2

Refer to the Environmental Alignment Sheets and the Access and Construction Environmental Maps for Project-specific environmental timing restrictions.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Ali t Sh t

Complete for 2019; ongoing for remaining Project construction

Yes

2- 179

179 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Surface Conditions – Contractor Measures #5

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads –Surface Conditions – Contractor Measures #4

CEPP Section 6.3 – Transmission Line Construction Environmental Protection Measures – Geotechnical Investigations – Surface Conditions – Contractor Measures #4

CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Surface Conditions – Contractor Measures #5

CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Surface Conditions – Contractor Measures #4

CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Structure Assembly and Erection – Surface Conditions – Contractor Measures #5

CEPP Section 6.7 – Transmission Line Construction Environmental Protection Measures – Conductor Stringing and Tensioning – Surface Conditions – Contractor Measures #5

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 8 – Groundwater

When working under frozen conditions, use probes or other techniques to asses that the frost is deep enough (i.e., below the depth of topsoil) to proceed without causing excessive soil rutting and compaction.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 180

180 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Surveying and Flagging – Contractor Measures #6 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads –Surveying and Flagging – Contractor Measures #5

CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Survey and Flagging– Contractor Measures #6

The Project Site will be surveyed and marked prior to the start of construction activities of each workfront to establish the Project Site.

●      Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Reconnaissance and seasonal pre-construction environmental surveys completed for 2019 under guidance of resource specialists; ongoing for remaining Project construction

Yes

45 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 181

181 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Surveying and Flagging – Contractor Measures #8

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads –Surveying and Flagging – Contractor Measures #6

Environmentally sensitive features and their associated setbacks will be flagged prior to clearing or construction as described on the Environmental Alignment Sheets and Access and Construction Environmental Maps.

●  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Reconnaissance and seasonal pre-construction environmental surveys completed for 2019 under guidance of resource specialists; ongoing for remaining Project construction

Yes

2- 182

182 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Surveying and Flagging – Contractor Measures #9

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads –Surveying and Flagging – Contractor Measures #7

CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Survey and Flagging– Contractor Measures #9

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

There minimum 30 metre vegetation buffer will be flagged prior to the start of clearing activities. Vegetation buffer may increase for slope dependent consideration to reduce sedimentation (30m - 90m slope dependent).

●  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 183

183 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Surveying and Flagging – Contractor Measures #10

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads –Surveying and Flagging – Contractor Measures #8

EA Report – Section 19 – Non-Traditional Land and Resource Use

Roads, pipelines, railroad or other crossings will be flagged so that they are crossed as indicated in crossing agreements and/or as per conditions of regulatory approvals.

●  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 184

184 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Surveying and Flagging – Contractor Measures #13

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads –Surveying and Flagging – Contractor Measures #12

CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Survey and Flagging– Contractor Measures #14

Supplement markings with signage prior to and after clearing. ●  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 185

185 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Cleaning Equipment – Contractor Measures #14

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 8 – Groundwater EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

Use equipment that minimizes surface disturbance, soil compaction and topsoil loss (e.g., equipment with low ground pressure tires, or wide pad tracks), when working in wet areas, under wet conditions, or during spring break-up.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

46 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 186

186 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Water Bodies – Contractor Measures #16

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Construction Monitoring – Owner Measures #8

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Regulatory Approvals – Contractor Measures #4CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Vehicle Use – Contractor Measures #24

OEMP Section 5.2 – Access and Travel on Right-of-Way – Water Bodies

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 4 – Project Description

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Fording of a water body is not permitted to prevent direct injury or mortality to eggs or fish unless approved by the appropriate regulatory agency. If fording is approved by the appropriate regulatory agency (e.g., MNRF, DFO, and/or LRCA), it will be limited to a one-time event (i.e., over and back) and will occur only if an existing crossing at another location is not available or practical to use, only where there is a rock bed and minimal bank, and in accordance with the conditions of the regulatory approval. If repeated crossings of the water body are required, a temporary crossing structure will be installed. If fording is approved by the appropriate regulatory agency, a site inspection will be completed prior to construction to determine whether bed, banks, and fish habitat conditions at specific water bodies are suitable for the use of a ford.

●  ●  ●  Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 187

187 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Water Bodies – Contractor Measures #17

EA Report – Section 7 – Surface Water

EA Report – Section 13 – Fish and Fish Habitat

Clearing of the riparian zone will consider DFO’s Measures to Avoid Causing Harm to Fish and Fish Habitat Including Aquatic Species at Risk (DFO 2016) and MNRF’s Environmental Guidelines for Access Roads and Water Crossings (refer to Appendix 4-II, Appendix H2; MNR 1990), and Forest Management Guide for Conserving Biodiversity at the Stand and Site Scales (refer to Appendix 4-II, Appendix H3; MNR 2010a) and its associated Background Rationale document (MNR 2010b).

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 188

188 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Water Bodies – Contractor Measures #18

EA Report – Section 13 – Fish and Fish Habitat

Equipment shall be operated above the high-water mark in a manner that minimizes disturbance to the bed and banks of the water body.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 189

189 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Water Bodies – Contractor Measures #19

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

The vegetation buffer will be slope dependent (30m - 90m). Buffer and height will be increased around water bodies with steep slope if it is determined to be suitable or necessary to protect the water body from sediment mobilization.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

47 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 190

190 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Water Bodies – Contractor Measures #20

EA Report – Section 7 – Surface Water EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 16 – Cultural Heritage Resources

Vegetation clearing within the 30 m water body buffer will be limited to where vegetation may present a safety hazard during construction or operation.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 191

191 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Water Bodies – Contractor Measures #21

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

Clearing of vegetation within the 30 m – 90m water body buffer, including the removal of selected plants, may be necessary to accommodate the equipment crossing. This should be kept to a minimum and within the Project Site.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 192

192 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Water Bodies – Contractor Measures #22

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

Clear merchantable timber by hand in the 30 m – 90 m water body buffer. Minimal encroachment may be required to harvest very large trees. The merchantable timber will be winched outside the 30 m – 90m water body buffer.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 193

193 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Water Bodies – Contractor Measures #24

CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan – Water Bodies – Contractor Measures #25

OEMP Section 5.2 – Access and Travel on Right-of-Way – Water Bodies

OEMP Section 5.3 – Vegetation Management Program – Erosion and Sedimentation Control

OEMP Section 5.3 – Vegetation Management Program – Water Bodies

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 16 – Cultural Heritage Resources

No turning of equipment, or vehicles will be allowed within the 30 m – 90 m water body buffer (i.e. straight in, straight out) to minimize soil disturbance to the extent practicable.

  ●  ●  Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 194

194 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Water Bodies – Contractor Measures #25

OEMP Section 5.3 – Vegetation Management Program – Water Bodies

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

EA Report – Section 13 – Fish and Fish Habitat

Immediately remove debris (i.e., except trees) or soil inadvertently deposited during construction below the high-watermark of water bodies.

  ●  ●  Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

48 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 195

195 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Water Bodies – Contractor Measures #26

OEMP Section 5.3 – Vegetation Management Program – Water Bodies

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

EA Report – Section 13 – Fish and Fish Habitat

Trees naturally or accidently felled below the high-watermark of water bodies will be left where they fall.   ●  ●  Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 196

196 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Water Bodies – Contractor Measures #27

EA Report – Section 7 – Surface Water

Deleterious substances (e.g., slash, litter, soil, rock, oil) will not be placed into or near a water body.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 197

197 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Water Bodies – Contractor Measures #28

OEMP Section 5.3 – Vegetation Management Program – Water Bodies

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water EA Report – Section 13 – Fish and Fish Habitat

Will not skid logs across or push logs into water bodies.   ●  ●  Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 198

198 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Water Bodies – Contractor Measures #30 EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

Maintain low vegetation, vegetative ground mat and root structure within the 30 m – 90 m water body buffer to the extent practicable by walking, storing material or constructing over the undisturbed areas.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 199

199 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Steep Slopes and Soils Prone to Erosion – Contractor Measures #32

OEMP Section 5.3 – Vegetation Management Program – Erosion and Sedimentation Control

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 16 – Cultural Heritage Resources

Selectively cut vegetation and restrict grubbing within vegetation buffers and areas with steep slopes or soil types prone to erosion.

  ●  ●  Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 200

200 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Clearing – Merchantable Timber – Contractor Measures #33

EA Report – Section 2 – Consultation and Engagement Summary

Merchantable timber will be cleared in accordance with the FRL, Overlapping Agreements, Renewal Agreements (Crown Reserved Trees) or in accordance with landowner agreements when trees are not reserved to the Crown.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

49 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 201

201 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Clearing – Merchantable Timber – Contractor Measures #34

EA Report – Section 12 – Vegetation and Wetlands

Timber will be felled away from standing trees and vegetation buffers and water bodies to prevent damaging adjacent trees and aquatic habitat. If this is not achievable with conventional logging equipment, hand falling may be required.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 202

202 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Clearing – Merchantable Timber – Contractor Measures #35

EA Report – Section 12 – Vegetation and Wetlands

Fell timber onto the ROW during clearing. No fallen or leaning trees shall be permitted off the Project Site or in water bodies.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 203

203 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Clearing – Merchantable Timber – Contractor Measures #36 EA Report – Section 12 – Vegetation and Wetlands

Stockpile merchantable timber at landings near the edge of the boundaries in a manner that is accessible to hauling trucks. Timber is not to be piled or stored within any environmentally sensitive feature vegetation setback including water body slope dependent vegetation buffer or other overhead or underground utility or crossing unless specified by the Owner.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 204

204 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Brushing – Non-Merchantable Timber – Contractor Measures #37

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 12 – Vegetation and Wetlands

Use equipment that minimizes soil disturbance (e.g., equipment with low ground pressure tires, or wide pad tracks), when brushing non-merchantable timber in areas where grading is not warranted.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 205

205 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Wildlife Habitat Contractor Measures #39

EA Report – Section 2 – Consultation and Engagement Summary

Will not clear trees and associated setbacks for trees that contain active stick nests or wildlife habitat for species of concern or species at risk, as shown on the Environmental Alignment Sheets and the Access and Construction Environmental Maps or during pre-construction nest surveys (refer to Appendix 4-II, Appendix G). Apply appropriate timing restrictions for construction activities in areas identified."

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

No active stick nests or wildlife habitat for species of concern or species at risk nest identified in 2019; construction clearing completed outside of timing windows

Yes

50 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 206

206 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Wildlife Habitat Contractor Measures #41

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Salvage and retain coarse woody debris at select locations (e.g., temporary disturbed area in mature/old growth forest or caribou high use area) and as needed to establish or re-establish suitable wildlife habitat after construction.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 207

207 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Stumping – Contractor Measures #42

Reduce the width of stumping through wet areas to facilitate the restoration of shrub communities.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 208

208 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Stumping – Contractor Measures #43

Restrict stumping in wet areas to avoid creation of flooded areas with little soil.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 209

209 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Stumping – Contractor Measures #44

EA Report – Section 8, Groundwater

Restrict stumping to area to be excavated at transmission structure sites to reduce surface disturbance.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 210

210 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Stumping – Contractor Measures #45

Restrict stumping within 2 m of the edge of the ROW to prevent damaging adjacent trees unless required for transmission structure or ROW access.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 211

211 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation -Stumping – Contractor Measures #46

Restrict stumping near water bodies. Do not stump within the 30 m water body buffer with the exception of access to water body crossings.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 212

212 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Stumping – Contractor Measures #47

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

Restrict stumping on slopes prone to erosion and difficult terrain to reduce soil disturbance and erosion.   ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2-

213

213 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Leaning and Damaged Trees – Contractor Measures #48

Immediately cut and remove off-ROW trees damaged during construction activities that may pose a safety hazard. Do not postpone removing of damaged trees until clean-up.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

51 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 214

214 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Rollback – Contractor Measures #49

EA Report – Section 14 – Wildlife and Wildlife Habitat

Rollback (i.e., process of “rolling back” felled and cleared logs into areas that were cleared during construction) may be installed at key points near existing access roads, water bodies, and wildlife habitat and may be required as part of environmental approval conditions.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activity did not include rollback activities

Not Started

2- 215

215 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Timber and Brush Disposal – Contractor Measures #50

EA Report – Section 2 – Consultation and Engagement Summary

Timber and brush disposal options are subject to agreements with landowners, SFL holders and the appropriate regulatory agency.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 216

216 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Timber and Brush Disposal – Contractor Measures #51

Dispose of timber material not salvaged for merchantability through burning or mechanical chipping.   ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

Complete for 2019; ongoing for remaining Project construction

Yes

2- 217

217 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Timber and Brush Disposal – Contractor Measures #52

Slash will be chipped and spread over the ROW or burned in compliance with O. Reg. 207/96.   ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements

Complete for 2019; ongoing for remaining Project construction

Yes

2- 218

218 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Timber and Brush Disposal – Contractor Measures #53

EA Report – Section 12 – Vegetation and Wetlands

Obtain applicable permits and approval from MNRF, municipality and the fire department prior to burning.   ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if

Complete for 2019; ongoing for remaining Project construction

Yes

2- 219

219 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Timber and Brush Disposal – Contractor Measures #53

EA Report – Section 12 – Vegetation and Wetlands

Burn timber and brush (non-merchantable) in accordance with the rules and conditions for outdoor fires regulations under the Forest Fires Prevention Act, acquired permits (Municipal and Provincial) and follow practices as outlined in the Fire Prevention Contingency Plan (refer to Appendix 4-II, Section 7.3) and Timber Salvage Plan.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

Complete for 2019; ongoing for remaining Project construction

Yes

2- 220

220 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Timber and Brush Disposal – Contractor Measures #55

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 12 – Vegetation and Wetlands

Avoid burning slash when a fire hazard is present.   ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

Complete for 2019; ongoing for remaining Project construction

Yes

2- 221

221 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Timber and Brush Disposal – Contractor Measures #56

EA Report – Section 2 – Consultation and Engagement Summary

Implement the conditions outlined in the Forest Fire Prevention Act and MNRF permitting with regard to slash pile burning. This may include limiting pile size, minimizing moisture content and maintaining loose burning piles with minimal soil.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

Complete for 2019; ongoing for remaining Project construction

Yes

52 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 222

222 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Timber and Brush Disposal – Contractor Measures #57

EA Report – Section 2 – Consultation and Engagement Summary

Minimize burning within 100 m of a water body to the extent practicable.   ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

Complete for 2019; ongoing for remaining Project construction

Yes

2- 223

223 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Timber and Brush Disposal – Contractor Measures #59

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 12 – Vegetation and Wetlands

Strip the topsoil at burn locations to prevent sterilization of the soil.   ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

Complete for 2019; ongoing for remaining Project construction

Yes

2- 224

224 CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Timber and Brush Disposal – Contractor Measures #60

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 12 – Vegetation and Wetlands

If timber and brush are disposed of by mechanical means (i.e., mulching or chipping), the material must be dispersed in a way to avoid accumulation of flammable material and comply with the Forest Fires Prevention Act. Obtain landowner authorization prior to spreading material.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

Complete for 2019; ongoing for remaining Project construction

Yes

2- 225

225 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Roads required to access the transmission line ROW and temporary workspaces will use existing roads as much as possible and new temporary roads will be properly decommissioned after construction phase if not required to maintain the transmission line.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

2019 construction activities did not include decommissioning activities

Not Started

2- 226

226 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads –Access Roads Placement – Owner Measures #1

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Construct upgraded existing and new access roads in consultation with landowners, industrial land users (e.g., forestry and mining) and in compliance with applicable legislation, regulations and requirements identified in permits and authorizations.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

53 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 227

227 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads –Access Roads Placement – Owner Measures #2

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads –Access Roads Placement – Contractor Measures #13

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 18 – Socio-Economics

EA Report – Section 19 – Non-Traditional Land and Resource Use

Implement the traffic measures outlined in the Traffic Management Plan (refer to Appendix 4-II, Section 8.5).   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 228

228 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Topsoil Stripping – Owner Measures #3

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 12 – Vegetation and Wetlands

Monitor the condition of the soils throughout construction and further assess whether topsoil is being subject to degradation that will eventually impact soil capability.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 229

229 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads –Topsoil Stripping – Owner Measures #4

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands

If topsoil is being degraded, consider stripping topsoil as outlined below or implement the measures outlined in the Soil Handling Contingency Plan (refer to Appendix 4-II, Section 7.2).

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 230

230 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads –Schedule – Contractor Measures #2

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Topsoil Stripping – Contractor Measures #42CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Schedule – Contractor Measures #3

CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Schedule – Contractor Measures #2

CEPP Section 6.6 – Transmission Line Construction Environmental Protection Measures – Transmission Structure Assembly and Erection – Schedule – Contractor Measures #3

CEPP Section 6.7 – Transmission Line Construction Environmental Protection Measures – Conductor Stringing and Tensioning – Schedule – Contractor Measures #4

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 12 – Vegetation and Wetlands

For construction scheduled to occur during frozen conditions, and where topsoil stripping is required attempt to pre-strip topsoil prior to freeze-up, where conditions permit.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

54 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 231

231 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads –Access Roads Placement – Contractor Measures #14

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources

EA Report – Section 17 – Indigenous Land and Resource Use

EA Report – Section 19 – Non-Traditional Land and Resource Use

EA Report – Section 20 – Visual Environment

Use existing roads and trails as identified on the Access and Construction Environmental Maps (refer to Appendix 5-II) and comply with conditions outlined in road use agreements.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 232

232 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads –Access Roads Placement – Contractor Measures #16

EA Report – Section 18 – Socio-Economics

Use appropriate road signage during construction activities.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 233

233 CEPP Section 6.2 – Access Roads –Access Roads Placement – Contractor Measures #18 CEPP Section 8.5 – Traffic Management Plan – Access Roads Placement – Contractor Measures #20

EA Report – Section 14 – Wildlife and Wildlife Habitat

Where new access is required, construct only winter grade access (snow roads), when practicable, and decommission roads after construction by implementing clean-up and reclamation measures in Section 6.8, installing rollback, and in accordance with approval requirements.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include decommissioning activities

Not Started

2- 234

234 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads –Access Roads Placement – Contractor Measures #19

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Regulatory Approvals – Contractor Measures #5

CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Regulatory Approvals – Contractor Measures #1

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

Follow applicable measures from MNRF’s Environmental Guidelines for Access Roads and Water Crossings (refer to Appendix 4-II, Appendix H2; MNR 1990), and Forest Management Guide for Conserving Biodiversity at the Stand and Site Scales (refer to Appendix 4-II, Appendix H3; MNR 2010a) and its associated Background Rationale document (MNR 2010b), Ontario’s Provincial Standards for Temporary Erosion and Sediment Control Measures (refer to Appendix 4-II, Appendix H4; OPSS 805), General specifications for Environmental Protection for Construction in Waterbodies and on Waterbody Banks (refer to Appendix 4-II, Appendix H5; OPSS 182), and Construction Specifications for Control of Water from Dewatering Operations (refer to Appendix 4-II, Appendix H6; OPSS 518).

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

55 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 235

235 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads –Access Roads Placement – Contractor Measures #20

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 15 – Archaeological Resources

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 16 – Cultural Heritage Resources

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Unless approved by the appropriate regulatory agency, all access roads will be setback 30 m from all water bodies, except at water body crossing locations as identified in the crossing lists (i.e., access roads will not cross into the 3 0 m water body buffer).

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 236

236 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Vehicle Use – Contractor Measures #21

CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan – Vehicle Use – Contractor Measures #10

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Vehicle use on access roads will be in accordance with applicable laws (e.g., speed limit, road weight restriction) and road use agreements (e.g., load restrictions).

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 237

237 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Vehicle Use – Contractor Measures #23 CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan – Water Bodies – Contractor Measures #22

OEMP Section 5.2 – Access and Travel on Right-of-Way – Vehicles and Equipment

OEMP Section 5.2 – Access and Travel on Right-of-Way – Water Bodies

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA R t S ti 17 I di C t U

Vehicles and equipment will cross water bodies using existing and/or approved equipment crossings.    ●  ●  Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 238

238 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Vehicle Use – Contractor Measures #26

OEMP Section 5.2 – Access and Travel on Right-of-Way – Vehicles and Equipment

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 8 – Groundwater

Project personnel will avoid unnecessary wheel spin.   ●  ●  Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

56 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 239

239 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Vehicle Use – Contractor Measures #28

CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan – Transportation, Storage, and Handling – Contractor Measures #16

EA Report – Section 10 – Greenhouse Gases

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Minimize the frequency of the transport of goods and equipment, where practicable.   ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 240

240 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Snow Management – Contractor Measures #29

Windrowed snow will be stored on the allotted ROW and/or workspace (i.e., not pushed into the trees).   ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 241

241 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Snow Management – Contractor Measures #30

Install breaks in snow banks along the access road to allow passage by ungulates.   ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 242

242 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Snow Management – Contractor Measures #32

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 8 – Groundwater

Imported fill materials must be clean and free of contaminants, as classified under the Environmental Protection Act Ontario Regulation 153/4 Records of Site Condition – Part XV.1 of the Act (MOECC 1978).

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 243

243 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Bedrock – Contractor Measures #33 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction– Bedrock – Contractor Measures #13

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

Ripping is preferred over blasting where rock is encountered.   ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include blasting activities

Not Started

2- 244

244 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Bedrock – Contractor Measures #34

CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Bedrock – Contractor Measures #14

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

Use of explosives for foundation excavations and access roads will be limited to conditions that do not allow for typical or standard drilling methods.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include blasting activities

Not Started

57 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 245

245 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Bedrock – Contractor Measures #35

CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Bedrock – Contractor Measures #15

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

In the event that blasting is required, adhere to the Blasting Management Plan (refer to Appendix 4-II, Section 8.3).   ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include blasting activities

Not Started

2- 246

246 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Bedrock – Contractor Measures #36

CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Bedrock – Contractor Measures #17

EA Report – Section 6 – Geology, Terrain and Soils

Import additional or replacement backfill, if warranted, from approved locations.   ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

Complete for 2019; ongoing for remaining Project construction

Yes

2- 247

247 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Topsoil Stripping – Contractor Measures #38 EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 12 – Vegetation and Wetlands

Apply geotextile, matting (refer to Appendix 4-II, Appendix B, Figure B-13) or fill material (e.g., gravel) as appropriate. Place a membrane (filter fabric) between fill material and soil to minimize admixing.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable

Complete for 2019; ongoing for remaining Project construction

Yes

2- 248

248 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Topsoil Stripping – Contractor Measures #39

Follow measures outlined in the Soil Handling Contingency Plan (refer to Appendix 4-II, Section 7.2) when working under wet conditions.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 249

249 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Topsoil Stripping – Contractor Measures #40

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 12 – Vegetation and Wetlands

Strip topsoil within the Project Site, except where prohibited based on site-specific features.

  ●    Adherence to CEPP and DPP; Alignment Sheets

Limited soil stripping and topsoil stockpiling required for construction activity in 2019, ongoing for remaining Project construction

Yes

2- 250

250 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Topsoil Stripping – Contractor Measures #41

CEPP Section 6.3 – Transmission Line Construction Environmental Protection Measures – Geotechnical Investigations – Topsoil Stripping – Contractor Measures #5

CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Topsoil Stripping – Contractor Measures #22

CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Topsoil Stripping – Contractor Measures #9EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 12 – Vegetation and Wetlands

Remove soil in lifts and strip available topsoil in one lift.

  ●    Adherence to CEPP and DPP

Limited soil stripping and topsoil stockpiling required for construction activity in 2019, ongoing for remaining Project construction

Yes

58 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 251

251 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Topsoil Stripping – Contractor Measures #43

CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Topsoil Stripping – Contractor Measures #23

CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Topsoil Stripping – Contractor Measures #10EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 12 – Vegetation and Wetlands

Rip frozen topsoil to the same depth as the stripping requirements. Do not over rip and overstrip.

  ●    Valard EMS; Adherence to CEPP and DPP

Limited soil stripping and topsoil stockpiling required for construction activity in 2019, ongoing for remaining Project construction

Yes

2- 252

252 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Topsoil Stripping – Contractor Measures #44

If working under wet conditions, implement the measures outlined in the Soil Handling Contingency Plan (refer to Appendix 4-II, Section 7.2).

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 253

253 CEPP Section 6.2 – Access Roads – Topsoil Handling Contingency Measures – Contractor Measures #45

CEPP Section 6.3 – Geotechnical Investigations – Topsoil Handling Contingency Measures – Contractor Measures #6

CEPP Section 6.4 – Temporary Workspaces – Topsoil Handling Contingency Measures – Contractor Measures #24

CEPP Section 6.5 – Transmission Foundation and Anchor Construction – Topsoil Handling Contingency Measures – Contractor Measures #12

EA Report – Section 6 – Geology, Terrain and Soils

Implement the Soil Handling Contingency Plan (refer to Appendix 4-II, Section 7.2) during topsoil stripping if one of the following are encountered:

little or no topsoil;

uneven boundary between topsoils and subsoils;

poor colour separation between topsoils and subsoils;

stony soils;

wet conditions;

high winds; or

requests for alternate topsoil handling methods that the Owner has received from a landowner.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 254

254 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Soil Storage – Contractor Measures #46

CEPP Section 6.3 – Transmission Line Construction Environmental Protection Measures – Geotechnical Investigations – Soil Storage – Contractor Measures #7

CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Soil Storage – Contractor Measures #25

CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Soil Storage– Contractor Measures #18

Soil piles should be staked indicating the soil layer being stored for identification during replacement.   ●    Valard EMS; Adherence to CEPP and DPP

Limited soil stripping and topsoil stockpiling required for construction activity in 2019, ongoing for remaining Project construction

In Progress

2- 255

255 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Soil Storage – Contractor Measures #48

CEPP Section 6.3 – Transmission Line Construction Environmental Protection Measures – Geotechnical Investigations – Soil Storage – Contractor Measures #10

Stockpile topsoil adjacent or near the access road for use during reclamation and clean-up and in such a way as to not interfere with Project activities.

  ●    Valard EMS; Adherence to CEPP and DPP

Limited soil stripping and topsoil stockpiling required for construction activity in 2019, ongoing for remaining Project construction

In Progress

59 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 256

256 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Soil Storage – Contractor Measures #49

CEPP Section 6.3 – Transmission Line Construction Environmental Protection Measures – Geotechnical Investigations – Soil Storage – Contractor Measures #11

CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Soil Storage – Contractor Measures #28

CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Soil Storage– Contractor Measures #22EA Report – Section 12 – Vegetation and Wetlands

Stripped soil is to be stored on level ground outside the protective vegetative setbacks for the associated environmentally sensitive features (wetlands, waterbodies, SWH).

  ●    Valard EMS; Adherence to CEPP and DPP

Limited soil stripping and topsoil stockpiling required for construction activity in 2019, ongoing for remaining Project construction

In Progress

2- 257

257 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Soil Storage – Contractor Measures #50

CEPP Section 6.3 – Transmission Line Construction Environmental Protection Measures – Geotechnical Investigations – Soil Storage – Contractor Measures #12

CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Soil Storage – Contractor Measures #29

CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Soil Storage– Contractor Measures #23

Do not place stripped soils in surface drainage channel or wetland.   ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 258

258 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Soil Storage – Contractor Measures #51

CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Soil Storage – Contractor Measures #30

CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Soil Storage– Contractor Measures #24

CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Fill Material – Contractor Measures #5

EA Report – Section 7 – Surface Water

Install, monitor and manage appropriate erosion and sedimentation controls as outlined in the Erosion and Sedimentation Control Management Plan (refer to Section 8.1) to filter or direct runoff away from water bodies.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 259

259 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Grading – Contractor Measures #53

Strip topsoil from areas to be graded and store in a location that will not allow for mixing of topsoil with excavated subsoil and graded material. The area stripped is to correspond to the area to be graded.

  ●    Valard EMS; Adherence to CEPP and DPP

Limited soil stripping and topsoil stockpiling required for construction activity in 2019, ongoing for remaining Project construction

In Progress

2- 260

260 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Grading – Contractor Measures #54

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 12 – Vegetation and Wetlands

Do not mix topsoil and subsoil disturbed during grading with foreign material (e.g., stumps and brush).   ●    Valard EMS; Adherence to CEPP and DPP

Limited soil stripping and topsoil stockpiling required for construction activity in 2019, ongoing for remaining Project construction

In Progress

60 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 261

261 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Grading – Contractor Measures #55

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

Limit grading on slopes prone to erosion or steep slopes.   ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 262

262 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Grading – Contractor Measures #56

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 13 – Fish and Fish Habitat

Reduce grading near water bodies. Limit the width of grading to reduce the potential for erosion and subsoil compaction.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 263

263 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Grading – Contractor Measures #57

EA Report – Section 7 – Surface Water

EA Report – Section 13 – Fish and Fish Habitat

Conduct grading away from water bodies to reduce the risk of sediment and other material entering the water body.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 264

264 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Grading – Contractor Measures #58

EA Report – Section 6 – Geology, Terrain and Soils

Limit disturbance to natural drainages during grading; avoid blocking drainages with graded material; install culverts if necessary.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2-

265

265 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Grading – Contractor Measures

#59

Do not place windrowed or graded material in water bodies during grading.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 266

266 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Grading – Contractor Measures #60

Do not store graded material in low or wet areas.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 267

267 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Grading – Contractor Measures #61

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Leave gaps in the windrows, at drainage courses, access roads/trails and wildlife trails.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 268

268 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Road Salt – Contractor Measures #63

EA Report – Section 7 – Surface Water

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

If the General Contractor (Valard) plans to use salt on access roads constructed, or within the Project Site, it must prepare, and submit for approval to the Owner, a Salt Management Plan. Owner will consult with applicable regulatory agency (MNRF, MECP, MTO) if required.

  ●    Valard EMS; Adherence to CEPP and DPP; Adherence to Salt Management Plan

No salt was used on access roads in 2019.

Not Started

61 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 269

269 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Road Salt – Contractor Measures #64

EA Report – Section 7 – Surface Water

EA Report – Section 14 – Wildlife and Wildlife Habitat

The Salt Management Plan should consider Industry Best Management Practices for road salt management.   ●    Valard EMS; Adherence to CEPP and DPP; Adherence to Salt Management Plan

No salt was used on access roads in 2019.

Not Started

2- 270

270 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Regulatory Approvals – Owner Measures #1

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

Obtain regulatory approvals as required from applicable regulatory agencies (MNRF, DFO, and/or LRCA) prior to installation of water body crossing structures. The Owner will consult with the appropriate regulatory agency to discuss any alternatives or modifications to the crossing requirements specified in approvals before construction begins.

●  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Ongoing

In Progress

2- 271

271 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Regulatory Approvals – Owner Measures #2

If water taking is required for the purposes of construction and/or water supply, register the activity on the Environmental Activity and Sector Registry (EASR) or obtain a Permit To Take Water (PTTW) from the MECP as appropriate.

●  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; Water taking was less than 50,000 L/day, no EASR or PTTW required; ongoing for remaining Project construction

Yes

2- 272

272 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Regulatory Approvals – Owner Measures #3

CEPP Section 6.3 – Transmission Line Construction Environmental Protection Measures – Geotechnical Investigations – Regulatory Approval – Owner Measures #2

CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Regulatory Approvals – Owner Measures #4

Short-term water diversions (active or passive) will be conducted in accordance with O. Reg. 387/04 as amended by O. Reg. 64/16 under Ontario Water Resources Act.

●  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 273

273 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Regulatory Approvals – Owner Measures #4 EA Report – Section 13 – Fish and Fish Habitat

Obtain regulatory approval from the appropriate regulator, as applicable, and salvage any fish behind isolation structures and relocate under the guidance of a qualified fisheries expert prior to instream construction. The fish salvage will involve techniques to capture all of the fish potentially present, including northern brook lamprey where the habitat is likely to support this species.

●  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

62 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 274

274 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Regulatory Approvals – Owner Measures #5

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

It is anticipated that regulatory approval under the Navigation Protection Act will be required at scheduled navigable waters crossed by the Project (Lake Superior and Nipigon River) and may be required at non-scheduled navigable waters. The Owner will provide Navigation Protection Act approval conditions prior to construction of each workfront, which may include notifications.

●      Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

No scheduled or non-scheduled waters were crossed in 2019.

Not Started

2- 275

275 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Notification – Owner Measures #5

Regulatory approvals for water body crossings may require notifications; the Owner will notify regulators as required. ●  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 276

276 CEPP Section 6.2 – Access Roads – Water Body Crossings – Construction Monitoring – Owner Measures #7

CEPP Section 6.2 – Access Roads – Water Body Crossings – Undocumented Water Body – Contractor Measures #14

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

In the event that a previously unidentified water body is suspected or encountered, the Undocumented Water Body Discovery Contingency Plan (refer to Appendix 4-II, Section 7.7) will be implemented.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 277

277 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Construction Monitoring – Owner Measures #9

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

Environmental Inspectors will be on-site during construction to monitor the installation of temporary equipment water body crossing structures.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; crossings installed under supervision of a resource specialist as required and according to LRCA or MNRF Work Permit and DFO Letter of Advice; ongoing for remaining Project construction

Yes

2- 278

278 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Construction Monitoring – Owner Measures #10

CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Construction Monitoring – Owner Measures #4

The Owner will provide the appropriate resource specialist, if required, to assess the potential impacts to the water body as required.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; crossings installed under supervision of a resource specialist as required and according to LRCA or MNRF Work Permit and DFO Letter of Advice; ongoing for remaining Project construction

Yes

63 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 279

279 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Construction Monitoring – Owner Measures #11

CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Construction Monitoring – Owner Measures #5

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 13 – Fish and Fish Habitat

Monitoring of turbidity and/or total suspended solids, streamflow rates, and/or water levels, at water body crossings in accordance with the requirements of regulatory permits and approvals.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; crossings installed under supervision of a resource specialist as required and according to LRCA or MNRF Work Permit and DFO Letter of Advice; ongoing for remaining Project construction

Yes

2- 280

280 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Construction Monitoring – Owner Measures #12

CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Construction Monitoring – Owner Measures #6

EA Report – Section 13 – Fish and Fish Habitat

Pump intakes will be continually inspected for entrained or impinged fish where instream work is completed.   ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; crossings installed under supervision of a resource specialist as required and according to LRCA or MNRF Work Permit and DFO Letter of Advice; ongoing for remaining Project construction

Yes

2- 281

281 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Construction Monitoring – Owner Measures #13

EA Report – Section 13 – Fish and Fish Habitat

The integrity of the water body crossing structures will be inspected regularly and during periods of high run-off, such as the spring freshet. Any changes to the morphology of the water body channel will be identified and addressed, as needed.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; crossings installed under supervision of a resource specialist as required and according to LRCA or MNRF Work Permit and DFO

f

Yes

2- 282

282 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Regulatory Approvals – Contractor Measures #1

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Construct water body crossing structures according to the crossing method identified on the Environmental Alignment Sheets and the Access and Construction Environmental Maps and summarized in the water body crossing lists ( refer to Appendix 4-II, Appendix I) and in accordance with regulatory approvals.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; crossings installed under supervision of a resource specialist as required and according to LRCA or MNRF Work Permit and DFO Letter of Advice; ongoing for remaining Project construction

Yes

2- 283

283 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Regulatory Approvals – Contractor Measures #2

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

EA Report – Section 13 – Fish and Fish Habitat

Water body crossings will be designed and constructed in compliance with LRCA, DFO and/or MNRF regulatory permits and approvals, if applicable, recognizing that all newly installed or upgraded crossing structure at mapped or unmapped water bodies are expected to require permitting through one or more of O. Reg. 239/13 under the Public Lands Act (administered by MNRF for water body crossings on Public/Crown land), O. Reg. 454/96 under the Lakes and Rivers Improvements Act (administered by MNRF for water body crossings on Private or Crown Land), the Provincial Parks and Conservation Reserves Act (PPCRA) (administered by MNRF for water body crossings within provincial parks and conservation reserves), the Fisheries Act and Species at Risk Act (administered by DFO), and O. Reg. 180/06 for the Development, Interference with Wetlands and Alterations to Shorelines and Watercourses under the Conservation Authorities Act (Government of Ontario 1990a; administered by LRCA for water body crossings in LRCA jurisdiction).

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; crossings installed under supervision of a resource specialist as required and according to LRCA or MNRF Work Permit and DFO Letter of Advice; ongoing for remaining Project construction

Yes

64 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 284

284 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Regulatory Approvals – Contractor Measures #6 OEMP Section 5.1 – General Mitigation Measures – Water Bodies

OEMP Section 5.2 – Access and Travel on Right-of-Way – Water Bodies

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land

and Resource Use

Follow applicable measures from DFO’s Measures to Avoid Causing Harm to Fish and Fish Habitat Including Aquatic Species at Risk (DFO 2016).

  ●  ●  Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; crossings installed under supervision of a resource specialist as required and according to LRCA or MNRF Work Permit and DFO Letter of Advice; ongoing for remaining Project construction

Yes

2- 285

285 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Regulatory Approvals – Contractor Measures #7

EA Report – Section 13 – Fish and Fish Habitat

Water diversion hoses will be screened as per the Freshwater Intake End of Pipe Fish Screen Guidelines (refer to Appendix 4-II, Appendix H7; DFO1995).

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; crossings installed under supervision of a resource specialist as required and according to LRCA or MNRF Work Permit and DFO Letter of Advice; ongoing for remaining Project construction

Yes

2- 286

286 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Schedule – Contractor Measures #13

EA Report – Section 12 – Vegetation and Wetlands

Postpone instream construction if excessive flows or flood conditions are present or anticipated. Resume activities when water levels have subsided or equipment/techniques suitable for conditions are deployed.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 287

287 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Equipment and Material – Contractor Measures #15

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

Necessary equipment and materials required for water body crossing structures will be on site and ready for installation prior to commencing instream work. Clean construction equipment in accordance with the Clean Equipment Protocol for Industry (refer to Appendix 4-II, Appendix H1; Halloran et al. 2013) prior to constructing water body crossings.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

65 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 288

288 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Erosion and Sedimentation Control – Contractor Measures #17

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Follow applicable measures from Ontario’s Provincial Standards for Temporary Erosion and Sediment Control Measures (refer to Appendix 4-II, Appendix H4; OPSS 805).

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 289

289 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Erosion and Sedimentation Control – Contractor Measures #18

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Erosion and sedimentation control measures will be implemented to prevent site runoff from reaching the water body.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 290

290 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Erosion and Sedimentation Control – Contractor Measures #19

OEMP Section 5.1 – General Mitigation Measures – Erosion and Sedimentation Control

EA Report – Section 7 – Surface Water EA Report – Section 13 – Fish and Fish Habitat EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes EA Report – Section 19 – Non-Traditional Land and Resource Use

Specific measures such as the use of berms or check dams, sediment fences, sumps or settling ponds will be undertaken as required to prevent sediment laden water from entering a water body.

  ●  ●  Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 291

291 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Water Body Crossing Structures – Contractor Measures #20

EA Report – Section 7 – Surface Water

EA Report – Section 13 – Fish and Fish Habitat

Where feasible, water body crossings structures will not be located on meander bends, braided watercourses, alluvial fans, active flood plains, or any other area that is inherently unstable and may result in the alteration of natural drainage, erosion, and/or scour.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

66 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 292

292 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Water Body Crossing Structures – Contractor Measures #21

EA Report – Section 7 – Surface Water

EA Report – Section 13 – Fish and Fish Habitat

Water body crossings shall not impede or reduce natural water flows at any time of year.   ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 293

293 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Water Body Crossing Structures – Contractor Measures #22

EA Report – Section 7 – Surface Water

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

Repair or replace the water body crossing structures, if warranted, as soon as practicable after noticing repairs or replacements are necessary.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 294

294 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Clear-Span Structure – Contractor Measures #23

CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan – Water Bodies – Contractor Measures #23

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Use existing bridges to cross water bodies and comply with conditions outlined in road use agreements.   ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 295

295 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Clear-Span Structure – Contractor Measures #24

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 13 – Fish and Fish Habitat

Under non-frozen conditions and where regulatory approvals allow, clear-span structures (e.g., clear-span bridges or rig mats) will be installed to limit impacts to water bodies.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 296

296 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Clear-Span Structure – Contractor Measures #25

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

Install clear-span structures using best management practices and following all environmental approval conditions (refer to Appendix 4-II, Appendix B, Figures B-7, B-8 and B-9).

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

67 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 297

297 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Clear-Span Structure – Contractor Measures #27

EA Report – Section 13 – Fish and Fish Habitat

Line clear-span bridges with impervious geotextile.   ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 298

298 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Clear-Span Structure – Contractor Measures #28

EA Report – Section 13 – Fish and Fish Habitat

Side containment for clear-span bridges must be constructed of plywood or logs.   ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 299

299 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Culvert – Contractor Measures #29

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 13 – Fish and Fish Habitat

Install culverts in accordance with environmental guidelines for access roads and water crossings.   ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; crossings installed under supervision of a resource specialist as required and according to LRCA or MNRF Work Permit and DFO Letter of Advice; ongoing for remaining Project construction

Yes

2- 300

300 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Culvert – Contractor Measures #30

EA Report – Section 7 – Surface Water

EA Report – Section 13 – Fish and Fish Habitat

Instream construction will be completed in isolation of flowing water (i.e., use isolation methods for the installation and removal of culverts where surface water exists at the time of construction) (refer to Appendix B, Figure B 5).

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; crossings installed under supervision of a resource specialist as required and according to LRCA or MNRF Work Permit and DFO Letter of Advice; ongoing for remaining Project construction

Yes

2- 301

301 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Culvert – Contractor Measures #31

CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Culvert – Contractor Measures #20

EA Report – Section 7 – Surface Water

EA Report – Section 13 – Fish and Fish Habitat

Use the dam and pump method during culvert installations and removals to maintain downstream flow and reduce sediment mobilization caused by instream construction (refer to Appendix 4-II, Appendix B, Figure B-5), recognizing that the dam and pump system will be implemented in accordance with the conditions outlined in O.Reg. 64/16 (i.e., exemption conditions for PTTW), as well as applicable MNRF approvals (e.g., Work Permits under the Public Lands Act, License to Collect Fish under the Fish and Wildlife Conservation Act, and work permits under the Lakes and Rivers Improvement Act, if required).

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; crossings installed under supervision of a resource specialist as required and according to LRCA or MNRF Work Permit and DFO Letter of Advice; ongoing for remaining Project construction

Yes

68 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 302

302 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Culvert – Contractor Measures #32

CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Culvert – Contractor Measures #21

EA Report – Section 7 – Surface Water

EA Report – Section 13 – Fish and Fish Habitat

Construct upstream and downstream dams of sandbags, cube bags, meter bags, steel plates or Aquadams™. Clean, non-earthen materials will be used to isolate the workspace. Earthen berms will not be used to isolate the workspace.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; crossings installed under supervision of a resource specialist as required and according to LRCA or MNRF Work Permit and DFO Letter of Advice; ongoing for remaining Project construction

Yes

2- 303

303 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Culvert – Contractor Measures #33

EA Report – Section 7 – Surface Water

EA Report – Section 13 – Fish and Fish Habitat

Pump bypass water from upstream, across the isolated workspace through a hose and onto an energy dissipation device prior to entering the water body downstream from the isolated workspace.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; crossings installed under supervision of a resource specialist as required and according to LRCA or MNRF Work Permit and DFO Letter of Advice; ongoing for remaining Project construction

Yes

2- 304

304 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Culvert – Contractor Measures #34 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures –Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Culvert – Contractor Measures #23

CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Dewatering – Contractor Measures #28

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 13 – Fish and Fish Habitat

Pump grey water (i.e., water that cannot be returned into a water body) onto stable, well vegetated areas, sheeting, rocks, sand bags, or into settling ponds, or other appropriate sediment filtering devices. Complete dewatering in a manner that does not cause erosion or allow sediment to re-enter a water body (at least 50 m away). Grey water should not flow directly into a water body. 

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; crossings installed under supervision of a resource specialist as required and according to LRCA or MNRF Work Permit and DFO Letter of Advice; ongoing for remaining Project construction

Yes

2- 305

305 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Culvert – Contractor Measures #35

CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Culvert – Contractor Measures #24

EA Report – Section 7 – Surface Water

EA Report – Section 13 – Fish and Fish Habitat

Continuously monitor dams for proper seal.   ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; crossings installed under supervision of a resource specialist as required and according to LRCA or MNRF Work Permit and DFO Letter of Advice; ongoing for remaining Project construction

Yes

69 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 306

306 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Culvert – Contractor Measures #36

CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Culvert – Contractor Measures #25

EA Report – Section 7 – Surface Water

EA Report – Section 13 – Fish and Fish Habitat

Place the pumps and generators in a secondary containment as described to prevent fuel and any other deleterious substance from impacting soil, vegetation, or a water body.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; crossings installed under supervision of a resource specialist as required and according to LRCA or MNRF Work Permit and DFO Letter of Advice; ongoing for remaining Project construction

Yes

2- 307

307 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Culvert – Contractor Measures #37

CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Culvert – Contractor Measures #26

EA Report – Section 7 – Surface Water

EA Report – Section 13 – Fish and Fish Habitat

Pump intakes should not disturb the bed.   ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; crossings installed under supervision of a resource specialist as required and according to LRCA or MNRF Work Permit and DFO Letter of Advice; ongoing for remaining Project construction

Yes

2- 308

308 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Culvert – Contractor Measures #38

CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Culvert – Contractor Measures #27

EA Report – Section 7 – Surface Water

EA Report – Section 13 – Fish and Fish Habitat

Monitor the pumping operation at all times, and adjust the pump as necessary to maintain 100% downstream flow of water and near-normal water levels upstream and downstream from the isolated workspace.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; crossings installed under supervision of a resource specialist as required and according to LRCA or MNRF Work Permit and DFO Letter of Advice; ongoing for remaining Project construction

Yes

2- 309

309 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Culvert – Contractor Measures #39

CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Culvert – Contractor Measures #28

EA Report – Section 7 – Surface Water

EA Report – Section 13 – Fish and Fish Habitat

A backup pump and extra hoses of equal or greater capacity must be on site at all times in case the primary pump fails.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; crossings installed under supervision of a resource specialist as required and according to LRCA or MNRF Work Permit and DFO Letter of Advice; ongoing for remaining Project construction

Yes

2- 310

310 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Culvert – Contractor Measures #40

CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Culvert – Contractor Measures #29

EA Report – Section 7 – Surface Water

Prior to removal of the isolation, accumulated sediment and spoil materials within the isolated area will be removed to a location where they will not re-enter any water body.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; crossings installed under supervision of a resource specialist as required and according to LRCA or MNRF Work Permit and DFO Letter of Advice; ongoing for remaining Project construction

Yes

70 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 311

311 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Culvert – Contractor Measures #41

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Routinely (e.g., before and/or after spring freshet) inspect and maintain culverts to prevent blockages from forming and causing ponding or backwater effects. Where culverts are installed at fish-bearing water bodies, debris removal activities will follow MNRF and DFO’s guidance (i.e., gradual removal such that flooding downstream, extreme flows downstream, release of suspended sediment, and fish stranding can be avoided).

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; crossings installed under supervision of a resource specialist as required and according to LRCA or MNRF Work Permit and DFO Letter of Advice; ongoing for remaining Project construction

Yes

2- 312

312 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Ice Bridge – Contractor Measures #43

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 13 – Fish and Fish Habitat

During winter construction, ice bridge may be used as temporary crossing structures to travel over frozen water bodies if approved by the appropriate regulatory agency.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities did not include ice bridges

Not Started

2- 313

313 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Ice Bridge – Contractor Measures #44

Install ice bridge using clean (ambient) water drawn from an approved source and/or clean snow ploughed-in from surrounding areas (refer to Appendix 4-II, Appendix B, Figures B-11 and B-12).

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities did not include ice bridges

Not Started

2- 314

314 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Ice Bridge – Contractor Measures #45

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Ice Bridge – Contractor Measures #46EA Report – Section 13 – Fish and Fish Habitat

Install ice bridges only at sites with gently sloping banks. Use snow and ice to slope approaches. Use the following best management practices during ice bridge or snow fill construction:

Construct ice bridge approaches using clean, compacted snow and ice to a sufficient depth to protect the banks of the water body. Do not place any fill below the high-water mark of the water body (except temporary snow fill). However, clean logs may be used to stabilize approaches.

Where logs are used to stabilize the approaches of an ice bridge: • The logs are clean and securely bound together so they can be easily removed. • No logs or woody debris are to be left within the water body or on the banks or shoreline where they

can wash into the water body.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities did not include ice bridges

Not Started

2- 315

315 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Snow Fill – Contractor Measures #48

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Snow Fill – Contractor Measures #49

EA Report – Section 13 – Fish and Fish Habitat

Install snow fill only at sites with gently sloping banks. Use snow and ice to slope approaches.

Use the following best management practices during ice bridge or snow fill construction:

Construct snow fill approaches using clean, compacted snow and ice to a sufficient depth to protect the banks of the water body. Do not place any fill below the high-water mark of the water body (except temporary snow fill). However, clean logs may be used to stabilize approaches.

Where logs are used to stabilize the approaches of a snow fill:

• The logs are clean and securely bound together so they can be easily removed. • No logs or woody debris are to be left within the water body or on the banks or shoreline where

they can wash into the water body.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities did not include ice bridges

Not Started

71 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 316

316 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Beaver Dam Removal or Dewatering – Contractor Measures #50

EA Report – Section 13 – Fish and Fish Habitat

Any fish within the beaver dam impoundment will be salvaged and relocated under the guidance of a qualified fisheries expert prior to and during dewatering, provided it is safe to do so and appropriate. Regulatory approval from the MNRF will be obtained to complete the fish salvage. The fish salvage will involve techniques to capture all of the fish potentially present, including Northern Brook Lamprey where the habitat is likely to support this species. Following dewatering, fish stranded in pools or newly flooded areas will be salvaged and relocated.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities did not include beaver dam alteration or removal

Yes

2- 317

317 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Beaver Dam Removal or Dewatering – Contractor Measures #51

EA Report – Section 13 – Fish and Fish Habitat

Beaver dam removal will be completed gradually, with removal works completed by hand if possible to allow for more gradual draining that minimizes scour, sedimentation, and fish stranding.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities did not include beaver dam alteration or removal

Yes

2- 318

318 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Beaver Dam Removal or Dewatering – Contractor Measures #52

Beaver dam removal will be avoided in the winter when the impoundment is frozen to avoid causing stress to overwintering fish and discharging potentially oxygen depleted water into downstream fish habitat.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities did not include beaver dam alteration or removal

Yes

2- 319

319 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Beaver Dam Removal or Dewatering – Contractor Measures #53

EA Report – Section 13 – Fish and Fish Habitat

If the beaver dam is altered, the width of the opening in the beaver dam will not exceed the width of the original channel.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities did not include beaver dam alteration or removal

Yes

2- 320

320 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Beaver Dam Removal or Dewatering – Contractor Measures #54

EA Report – Section 13 – Fish and Fish Habitat

If a series of beaver dams is being removed, the removal will be completed in a downstream to upstream order to minimize downstream flooding and erosion.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities did not include beaver dam alteration or removal

Yes

72 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 321

321 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Beaver Dam Removal or Dewatering – Contractor Measures #55

EA Report – Section 13 – Fish and Fish Habitat

Beaver dam removal will avoid damaging the original channel bed and banks. If any disturbance occurs, banks will be restored to a stable condition.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities did not include beaver dam alteration or removal

Yes

2- 322

322 CEPP Section 6.3 – Transmission Line Construction Environmental Protection Measures – Geotechnical Investigations

EA Report – Section 4 – Project Description

Geotechnical investigations will be undertaken for consideration in the detailed foundation design.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 323

323 CEPP Section 6.3 – Transmission Line Construction Environmental Protection Measures – Geotechnical Investigations – Regulatory Approval

Owner Measures #1

CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Regulatory Approvals – Owner Measures #1

CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction

Regulatory Approvals – Owner Measures #3

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water EA Report – Section 8 – Groundwater

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

All short-term water takings from surface water and/or groundwater sources for construction purposes will be conducted in accordance with O. Reg. 387/04 as amended by O. Reg. 64/16 under the Ontario Water Resources Act and industry best standards, where applicable, recognizing that designated water taking activities will require registration on the EASR or a PTTW from the MECP.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; Water taking was less than 50,000 L/day, no EASR or PTTW required; ongoing for remaining Project construction

Yes

2- 324

324 CEPP Section 6.3 – Transmission Line Construction Environmental Protection Measures – Geotechnical Investigations – Survey and Flagging – Contractor Measures #1

The boundary of the structure locations will be surveyed and marked prior to the start of geotechnical investigations.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 325

325 CEPP Section 6.3 – Transmission Line Construction Environmental Protection Measures – Geotechnical Investigations – Soil Replacement – Contractor Measures #13

Upon completion of the investigations, replace and compact soils back in the drill hole.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

73 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 326

326 CEPP Section 6.3 – Transmission Line Construction Environmental Protection Measures – Geotechnical Investigations – Soil Replacement – Contractor Measures #14

CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Backfilling – Contractor Measures #47

CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Subsoil Replacement – Contractor Measures #13

Spread surplus excavated subsoil as evenly as possible throughout stripped areas of Project Site.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 327

327 CEPP Section 6.4 –Transmission Line Construction Environmental Protection Measures – Temporary Workspaces –Regulatory Approvals – Owner Measures #2

CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Regulatory Approvals – Owner Measures #5

CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Regulatory Approval – Owner Measures #1

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

All discharges of Project wastewater will be conducted in accordance with O. Reg. 387/04 as amended by O. Reg. 64/16 under the Ontario Water Resources Act or O. Reg. 63/16 under the Environmental Protection Act, where applicable, recognizing that these discharge activities will require permitting or approvals through EASR, PTTW, or an Environmental Compliance Approval.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities did not include discharges requiring permitting or approvals through EASR, PTTW, or an Environmental Compliance Approval

Not Started

2- 328

328 CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces –Regulatory Approvals – Owner Measures #3

CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Regulatory Approvals – Owner Measures #6

CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Regulatory Approval – Owner Measures #2

EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

As part of the permitting and/or approvals process associated with EASR, PTTW and Environmental Compliance Approval (ECA), a discharge plan and supporting technical analysis will be developed for each source of wastewater discharge.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities did not include discharges requiring permitting or approvals through EASR, PTTW, or an Environmental Compliance Approval

Not Started

2- 329

329 CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Construction Monitoring

Owner Measures #4

CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction

Construction Monitoring – Owner Measures #7

CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Construction Monitoring – Owner Measures #4

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

Monitoring of one or more surface water quantity and quality parameters at water taking locations to satisfy the conditions/requirements of applicable EASR or PTTWs related water taking and discharge plans.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Water taking was less than 50,000 L/day, no EASR or PTTW required

Yes

74 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 330

330 CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Regulatory Approvals – Contractor Measures #1

CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Regulatory Approval – Contractor Measures #1

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

EA Report – Section 8 –Groundwater

Obtain necessary environmental regulatory approvals from applicable municipality for sewage, water supply and solid waste disposal.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 331

331 CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Survey and Flagging– Contractor Measures #8

Environmentally sensitive areas and their associated setbacks, as shown on the Environmental Alignment Sheets and the Access and Construction Environmental Maps will be flagged.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 332

332 CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Survey and Flagging– Contractor Measures #10

Roads, pipelines, railroad or other crossings will be flagged so that they are crossed as indicated in crossing agreements and/or as per conditions of regulatory approvals.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 333

333 CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Temporary Workspaces Placement – Contractor Measures #15

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources

Temporary workspaces are shown on the Environmental Alignment Sheets and the Access and Construction Environmental Maps.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 334

334 CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Temporary Workspaces Placement – Contractor Measures #16

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources

If additional temporary workspaces are required, identify the workspace location as soon as possible prior to construction of each workfront so the Owner can acquire applicable environmental permits and approvals.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include additional temporary workspace

Not Started

2- 335

335 CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Temporary Workspaces Placement – Contractor Measures #17

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources

The additional temporary workspaces should be located within previously disturbed areas, and/or at reasonably flat locations with stable soil, wherever practicable.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include additional temporary workspace

Not Started

75 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 336

336 CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Temporary Workspaces Placement – Contractor Measures #18

EA Report – Section 2 – Consultation and Engagement Summary EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Locate temporary workspaces outside the appropriate vegetation buffer/setback for the feature (e.g. 30-90 m slope dependent buffer). and apply appropriate mitigation and remediation measures, wherever practicable. If Project activities require equipment within the appropriate vegetation buffer/setback for the feature (e.g. 30-90 m slope dependent buffer). and apply appropriate mitigation and remediation measures (e.g., line stringing), the General Contractor (Valard) will notify the Owner to obtain the appropriate regulatory approvals.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include additional temporary workspace

Not Started

2- 337

337 CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Topsoil Stripping – Contractor Measures #20

Strip topsoil within the temporary workspaces.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include additional temporary workspace

Not Started

2- 338

338 CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Soil Storage – Contractor Measures #27

CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Soil Storage– Contractor Measures #21

Stockpile topsoil adjacent to each workspace on the Project Site for use during reclamation and clean-up and in such a way as to not interfere with Project activities.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Ongoing In Progress

2- 339

339 CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Fill Material – Contractor Measures #32

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Snow Management – Contractor Measures #31

Obtain fill material (e.g., gravel, shipped rock) from a legal source.   ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

Complete for 2019; ongoing for remaining Project construction

Yes

2- 340

340 CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Erosion and Sedimentation Control – Contractor Measures #35

CEPP Section 8.1 – Environmental Management Plans – Erosion and Sedimentation Control Plan – Temporary Erosion Control Measures – Contractor Measures #9

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources

Temporary erosion control measures must be:

properly installed; installed before or initial disturbance; and regularly inspected and properly maintained (e.g., repaired, replaced or supplemented with functional materials) throughout construction until permanent erosion control is established, or reclamation is complete.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

76 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 341

341 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Construction Monitoring – Owner Measures #8

EA Report – Section 8 – Groundwater

Monitor and manage excavation dewatering activities during the installation of transmission structure foundations.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not require excavation dewatering

Not Started

2- 342

342 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Surveying and Flagging – Contractor Measures #5

The boundaries of the transmission structure foundations (e.g., tower legs, stub-anchor and guy-anchor) will be surveyed and marked with stakes prior to the start of foundation construction.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 343

343 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Topsoil Stripping – Contractor Measures #7

Strip all topsoil within the transmission structure foundations areas.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Limited soil stripping and topsoil stockpiling required for construction activity in 2019, ongoing for remaining Project construction

Yes

2- 344

344 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Topsoil Stripping – Contractor Measures #8

Topsoil stripping may not be required at micro pile or anchor sites. .   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Limited soil stripping and topsoil stockpiling

required for construction activity in

2019, ongoing for remaining Project

construction

Yes

2- 345

345 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Bedrock – Contractor Measures #16

EA Report – Section 6 – Geology, Terrain and Soils EA Report – Section 8 – Groundwater

Fractures created from blasting adjacent to the transmission foundation may be filled with grout.   ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include blasting activities

Not Started

2- 346

346 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Soil Storage– Contractor Measures #19

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Soil Storage – Contractor Measures #47

CEPP Section 6.3 – Transmission Line Construction Environmental Protection Measures – Geotechnical Investigations – Soil Storage – Contractor Measures #8

CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Soil Storage – Contractor Measures #26

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 12 – Vegetation and Wetlands

Sufficient space (approximately 1 m) shall be left between the topsoil and subsoil piles. If space is limited, separate stripped topsoil and excavated subsoil using a visible separation barrier (e.g. biodegradable filter cloth, geotextile fabric, snow).

  ●    Valard EMS; Adherence to CEPP and DPP

Limited soil stripping and topsoil stockpiling required for construction activity in 2019, ongoing for remaining Project construction

Yes

2- 347

347 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Wildlife – Contractor Measures #27

Temporarily fence off open excavations or auger holes left unsupervised to prevent wildlife mortality.   ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

77 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 348

348 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Dewatering – Contractor Measures #29

Dewatering locations must be discussed with the Owner prior to starting discharge. No water will be discharged off the Project Site, without prior discussion with the Owner.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not require excavation dewatering

Not Started

2- 349

349 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Dewatering – Contractor Measures #30

If water is released onto private land, landowner consent must be acquired prior to release.   ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not require excavation dewatering

Not Started

2- 350

350 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Dewatering – Contractor Measures #31

Hoses and pumps shall have the sufficient length and capacity to transfer water to the desired location.   ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not require excavation dewatering

Not Started

2- 351

351 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Dewatering – Contractor Measures #32

Place pumps in a secondary containment tub to prevent spill and follow spill prevention measures outlined in the Spill Prevention and Response Contingency Plan (refer to Appendix 4-II, Section 7.1).

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not require excavation dewatering

Not Started

2- 352

352 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Dewatering – Contractor Measures #33

Hoses must be in good working condition, and hoses with tears or ruptures will be repaired or replaced.   ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not require excavation dewatering

Not Started

2- 353

353 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Artesian Groundwater – Contractor Measures #34

EA Report – Section 8 – Groundwater

Identify artesian conditions before excavating for foundations and dewatering measures adjusted accordingly.   ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not require excavation dewatering

Not Started

2- 354

354 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Artesian Groundwater – Contractor Measures #35

EA Report – Section 8 – Groundwater

If artesian conditions are encountered during construction, implement the following measures:

Maintain an adequate supply of grout and water on site to mix cement grouting; maintain an adequate supply of containment to respond to large volumes of water; the General Contractor (Valard) will also provide a list of required stand-by equipment (e.g., blow out preventers, packers, additional riser pipe and couplings, pumps and tubing);

use a blasting emulsion that is not readily soluble; implement other measures that are deemed necessary to:

• control or stop the discharge of water from within the excavated area;

• prevent the surface water discharge into the excavated area; and • prevent groundwater originating near the well from discharging at the surface at a distance that will prevent

the water to flow back into the excavated area.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not encounter artesian conditions

Yes

78 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 355

355 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Concrete Management – Contractor Measures #36

EA Report – Section 8 – Groundwater

The following measures in the concrete management section apply to concrete, cement, mortars, grouts and other Portland cement or lime-containing construction materials.

Isolate concrete work areas to prevent direct flow into water bodies so that water does not become more alkaline during construction.

Prevent water that contacts uncured or partly cured concrete during activities from directly or indirectly entering a water body.

Water that contacts uncured or partly cured concrete and does not meet provincial water quality criteria will not be released directly to the environment.

Do not use crushed concrete as fill material for foundation excavations.

Do not deposit, directly or indirectly, uncured concrete, cement, mortar, grout or other lime containing construction materials into or near a water body.

Do not wash concrete delivery trucks, concrete pumping equipment and other tools and equipment within 100 m of a water body.

Remove excess concrete from the Project Site and dispose of in accordance with construction waste disposal requirements in the Waste Management Plan.

Isolate and hold any water that contacts uncured or partly cured concrete until the pH is between 6.5 and 8.5 and water meets provincial water quality criteria the turbidity is less than 25 nephelometric turbidity units (NTU) measured to an accuracy of +/- 2 NTU.

The owner/operator of a concrete batch plant (i.e., General Contractor (Valard)) must have an ECA for the plant and comply with the conditions of the ECA.

Report spills of sediments, fines, concrete fines, wash or contact water to the Owner. Implement the Spill Prevention and Response Contingency Plan (refer to Appendix 4-II, Section 7.1).

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 356

356 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Concrete Management – Contractor Measures #37

EA Report – Section 8 – Groundwater

If concrete work is required within the 30 m water body buffer, the General Contractor (Valard) will develop a Concrete Management Plan and submit to the Owner for review and approval prior to start of foundation construction.

●  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 357

357 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Concrete Management – Contractor Measures #38

EA Report – Section 8 – Groundwater

The Concrete Management Plan should consider the following:

Frequently monitor the pH immediately downstream of the isolated work area until completion of the concrete work. Emergency measures shall be implemented if downstream pH exceeds provincial water quality standards.

Maintain complete isolation of cast-in-place concrete and grouting from fish-bearing waters for a minimum of 48 hours if the ambient air temperature is above 0°C and for a minimum of 72 hours if ambient air temperature is below 0°C.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 358

358 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Welding – Contractor Measures #39

Project personnel will dispose of welding rods, and other hot or burning items appropriately to reduce fire hazard.   ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include welding activities

Not Started

2- 359

359 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Welding – Contractor Measures #40

If the fire hazard is high, follow fire prevention measures outlined in the Fire Prevention Plan (refer to Appendix 4-II, Section 7.3).

  ●    Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2- 360

360 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Welding – Contractor Measures #41

CEPP Section 7.3 – Contingency Plans – Fire Prevention Contingency Plan – Equipment – Contractor Measures #6

OEMP Section 5.5 – Environmental Management During Operation –Fire Prevention

EA Report – Section 12 – Vegetation and Wetlands

Each vehicle will carry the fire-fighting equipment required by the Forest Fires Prevention Act and Fire Protection and Prevention Act. Each crew must carry a two-way radio or cell phone.

  ●    Valard EMS; Valard OEWTL Online Site Orientation; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 361

361 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Backfilling – Contractor Measures #42

Use excavated subsoil to backfill the excavation, wherever practicable.   ●    Adherence to CEPP and DPP

2019 construction activities did not require foundation excavation and backfill

Not Started

79 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 362

362 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Backfilling – Contractor Measures #43

To the extent practicable, attempt to schedule delivery of imported fill material so it can be installed directly into the excavation upon arrival at the transmission structure site rather than being temporarily stored on the ROW prior to being backfilled.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not require foundation excavation and backfill

Not Started

2- 363

363 CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Snow Management – Contractor Measures #32

CEPP Section 6.4 – Transmission Line Construction Environmental Protection Measures – Temporary Workspaces – Fill Material – Contractor Measures #33

CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Backfilling – Contractor Measures #44

Imported backfill materials must be clean and free of contaminants, as classified under the Environmental Protection Act Ontario Regulation 153/4 Records of Site Condition – Part XV.1 of the Act (Government of Ontario 2014).

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

Complete for 2019; ongoing for remaining Project construction

Yes

2- 364

364 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Backfilling – Contractor Measures #45

Backfill each lift in the correct sequence.   ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not require foundation excavation and backfill

Not Started

2- 365

365 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Backfilling – Contractor Measures #46

Backfill to the surface and mound to allow for drainage away from the transmission structure and settlement of soils.   ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not require foundation excavation and backfill

Not Started

2- 366

366 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Backfilling – Contractor Measures #48

Evenly replace topsoil upon completion of backfilling.   ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not require foundation excavation and backfill

Not Started

2- 367

367 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Backfilling – Contractor Measures #49

Avoid scalping sod and/or topsoil during backfilling. Use suitable equipment to reduce the potential for scalping.   ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not require foundation excavation and backfill

Not Started

2- 368

368 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Backfilling – Contractor Measures #50

Use suitable equipment to break up clods or frozen soils if required.   ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not require foundation excavation and backfill

Not Started

2- 369

369 CEPP Section 6.5 – Transmission Line Construction Environmental Protection Measures – Transmission Foundation and Anchor Construction – Backfilling – Contractor Measures #51

Avoid mixing snow into backfill material.   ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not require foundation excavation and backfill

Not Started

2- 370

370 CEPP Section 6.6 – Transmission Line Construction Environmental Protection Measures – Transmission Structure Assembly and Erection

Previously disturbed areas will be selected for laydown yards wherever possible. It is anticipated that, depending on terrain and access, some transmission structures will be assembled in laydown yards, some transmission structures will be assembled at suitable locations along the ROW, and some transmission structures will be assembled at the foundation location.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 371

371 CEPP Section 6.6 – Transmission Line Construction Environmental Protection Measures – Transmission Structure Assembly and Erection

For easily accessed areas, parts of the structures (e.g., cross arms) may be brought to the site via truck using access roads and/or the existing ROW and assembled onsite. Where access is difficult or not available, transmission structures may be delivered to the installation locations and erected using a helicopter.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 372

372 CEPP Section 6.6 – Transmission Line Construction Environmental Protection Measures – Transmission Structure Assembly and Erection – Regulatory Approvals – Owner Measures #1

Adherence to lighting and marking requirements under the Canadian Aviation Regulations Standard 621 – Obstruction Marking and Lighting for the installation of transmission structure and for the use of crane during transmission structures erection.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include tower erection

Not Started

2- 373

373 CEPP Section 6.6 – Transmission Line Construction Environmental Protection Measures – Transmission Structure Assembly and Erection – Project Site – Contractor Measures #1

Confine transmission structure assembly, erection and setting work to the Project Site.   ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include tower erection

Not Started

80 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 374

374 CEPP Section 6.6 – Transmission Line Construction Environmental Protection Measures – Transmission Structure Assembly and Erection – Survey and Flagging – Contractor Measures #8 EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Avoid placement of equipment or any other construction materials within a wetland or within the 30 m water body buffer.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 375

375 CEPP Section 6.7 – Transmission Line Construction Environmental Protection Measures – Conductor Stringing and Tensioning

Conductor stringing efforts may begin once transmission structure assembly and erection of a stringing section is complete.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include tower installation activities or stringing

Not Started

2- 376

376 CEPP Section 6.7 – Transmission Line Construction Environmental Protection Measures – Conductor Stringing and Tensioning – Regulatory Approval and Notification – Owner Measures #1

It is anticipated that regulatory approval under the Navigation Protection Act will be required at scheduled navigable waters crossed by the Project (Lake Superior and Nipigon River) and may be required at non-scheduled navigable waters. The Owner will provide Navigation Protection Act approval conditions prior to start stringing, which may include notifications.

●      Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include stringing

Not Started

2- 377

377 CEPP Section 6.7 – Transmission Line Construction Environmental Protection Measures – Conductor Stringing and Tensioning – Stringing Sites Placement – Contractor Measures #1

If stringing sites are required these should be located within previously disturbed areas and/or at reasonably flat locations with stable soil, wherever practicable.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include stringing

Not Started

2- 378

378 CEPP Section 6.7 – Transmission Line Construction Environmental Protection Measures – Conductor Stringing and Tensioning – Stringing Sites Placement – Contractor Measures #2

For stringing sites, avoid environmentally sensitive features. If avoidance is not possible, Project-specific environmental resources mitigation and timing restrictions will apply (refer to Appendix 4-II, Appendix I).

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include stringing

Not Started

2- 379

379 CEPP Section 6.7 – Transmission Line Construction Environmental Protection Measures – Conductor Stringing and Tensioning – Stringing over Navigable Waterways and Water Bodies – Contractor Measures #7

It is anticipated that regulatory approval under the Navigation Protection Act will be required at scheduled navigable waters crossed by the Project (Lake Superior and Nipigon River) and may be required at non-scheduled navigable waters. The General Contractor (Valard) will follow all approval conditions.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include stringing

Not Started

2- 380

380 CEPP Section 6.7 – Transmission Line Construction Environmental Protection Measures – Conductor Stringing and Tensioning – Implosive Connectors – Contractor Measures #8

Adhere to the Blasting Management Plan (refer to Appendix 4-II, Section 8.3) when engineered implosive charge are used to splice transmission conductor (wire) joints.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include blasting activities

Not Started

2- 381

381 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures

Temporary workspaces that are not required for Project operation will be decommissioned following completion of Project construction. This will include the decommissioning of laydown yards, storage yards, construction camps, construction easement, temporary access roads and temporary water body crossing structures. No temporary buildings or structures associated with the temporary infrastructure will be left on the Project Site upon completion of decommissioning, unless in accordance with third-party agreements.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include decommissioning activities

Not Started

2- 382

382 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures

The goals of decommissioning temporary infrastructure are to remove the temporary infrastructure, stabilize and revegetate disturbed areas and return site as close as possible to its natural state while maintaining access and appropriate drainage to support operation and maintenance standards.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include decommissioning activities

Not Started

81 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 383

383 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Regulatory Approvals – Owner Measures #1

EA Report – Section 13 – Fish and Fish Habitat

Obtain regulatory approval from the applicable regulatory agencies (MNRF, DFO, and/or LRCA), as applicable, and salvage any fish behind isolation structures and relocate under the guidance of a qualified fisheries expert prior to instream construction. The fish salvage will involve techniques to capture all of the fish potentially present, including Northern Brook Lamprey where the habitat is likely to support this species.

●      Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

One culvert installation completed in 2019 on LRCA watercourse in compliance with permits and under supervision of a resource specialist. No other activities below the high-water mark.

Yes

2- 384

384 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Final Inspection – Owner Measures #2

CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Final Inspection – Owner Measures #2

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 13 – Fish and Fish Habitat

The Owner will conduct a final site inspection to assess that clean-up, reclamation, and erosion and sediment controls are complete and satisfactory before equipment is removed from the Project Site.

  ●  ●  Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Not applicable to 2019 construction activities

Not Started

2- 385

385 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Construction Monitoring – Owner Measures #3

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Construction Monitoring – Owner Measures #9

EA Report – Section 13 – Fish and Fish Habitat

Environmental Inspector will be on-site during construction to monitor the removal of temporary equipment water body crossing structures.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include the removal of temporary equipment water body crossings

Not Started

2- 386

386 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Fill Material – Contractor Measures #2

EA Report – Section 8 – Groundwater

Remove fill material (e.g., gravel, shipped rock) and geotextile membrane if used during construction.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include decommissioning activities

Not Started

2- 387

387 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Fill Material – Contractor Measures #3

EA Report – Section 12 – Vegetation and Wetlands

Fill material requiring temporary storage will be placed on level ground and outside of the appropriate setback based on the site specific feature (e.g. slope dependent, wetland etc.).

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 388

388 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Fill Material – Contractor Measures #4

Do not place temporarily stored fill material in surface drainage channel or wetland.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

82 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 389

389 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Rig Mats, Matting, Geotextiles – Contractor Measures #6

EA Report – Section 12 – Vegetation and Wetlands

Remove geotextiles, rig mats and matting from the Project Site. Materials that could be reused elsewhere on the ROW will be cleaned of mud and vegetation before transferring and using at a different location. The Owner may inspect equipment and vehicles arriving on site or at the General Contractor’s (Valard) project staging/marshalling area prior to Project Site entry. Record cleaning locations.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities did not include decommissioning activities

Yes

2- 390

390 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – General – Contractor Measures #7

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Remove temporary water body crossing structures and associated fill materials when the crossing is no longer required after construction, unless otherwise agreed upon in third-party agreements and/or approved by appropriate regulatory agency.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities did not include the removal of temporary water body crossings

Not Started

2- 391

391 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – General – Contractor Measures #8

EA Report – Section 2 – Consultation and Engagement

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 2 – Consultation and Engagement

Summary Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Temporary water body crossing structures must be removed prior to spring freshet unless they are appropriately sized by a qualified engineer to convey the design flow event and approved by the appropriate regulatory agency (e.g., MNRF, DFO, and/or LRCA).

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities did not include the removal of temporary water body crossings

Not Started

2- 392

392 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – General – Contractor Measures #9

If removal of crossing materials requires work below the high-water mark and water is present at the time of construction, isolate the crossing location, maintain 100% of downstream flow, complete a fish salvage, remove the crossing materials, restore the bed and banks of the channel to their original profile, and stabilize disturbed areas, as necessary, to prevent soil erosion.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities did not include removal of any water crossings

Not Started

83 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 393

393 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Clear-Span Structure – Contractor Measures #10

EA Report – Section 13 – Fish and Fish Habitat

Clear-span structures (e.g., clear-span bridges and rig mats) will be removed in a manner that protects the banks from erosion and maintains flow in a water body.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities did not include the removal of temporary water body crossings

Not Started

2- 394

394 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Clear-Span Structure – Contractor Measures #11

For clear-span structures, no work will take place below the high-water mark.   ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 395

395 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Clear-Span Structure – Contractor Measures #12

EA Report – Section 13 – Fish and Fish Habitat

Temporary clear-span structures will be removed in a manner that protects the banks from erosion and maintains flow in a water body.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities did not include the removal of temporary water body crossings

Not Started

2- 396

396 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Clear-Span Structure – Contractor Measures #13

EA Report – Section 13 – Fish and Fish Habitat

Temporary bridges on private land or First Nation Reserve will be decommissioned in consultation with the landowner or community.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities did not include the removal of temporary water body crossings

Not Started

84 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 397

397 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Clear-Span Structure – Contractor Measures #14

CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Culvert – Contractor Measures #30

CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structure – Ice Bridge – Contractor Measures #36

CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Snow Fill – Contractor Measures #42

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

Stabilize disturbed areas (e.g., cover exposed areas with erosion control blankets or tarps to keep the soil in place and prevent erosion).

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

85 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 398

398 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Clear-Span Structure – Contractor Measures #15 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures –Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Culvert – Contractor Measures #31

CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structure – Ice Bridge – Contractor Measures #37

CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Snow Fill – Contractor Measures #43

CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Access Roads – Contractor Measures #49

CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Workspaces – Contractor Measures #55

CEPP Section 8.1 – Environmental Management Plans – Erosion and Sedimentation Control Plan – Cleanup – Contractor Measures #11

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife

Erosion and sedimentation control measures will remain in place until the construction activities are completed and the disturbed area has been stabilized, restored and revegetated. 

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 399

399 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Clear-Span Structure – Contractor Measures #16

Remove any waste materials from the work site to prevent them from entering the water body.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

86 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 400

400 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Culvert – Contractor Measures #17

Obtain approval from MNRF, DFO, and/or LRCA to salvage any fish in the work area prior to removal of culverts. ●  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities did not include removal of any water crossings

Not Started

2- 401

401 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Culvert – Contractor Measures #18

EA Report – Section 13 – Fish and Fish Habitat

Culverts on private land or First Nation Reserve will be decommissioned in consultation with the landowner or community.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities did not include decommissioning activities

Not Started

2- 402

402 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Culvert – Contractor Measures #19

EA Report – Section 13 – Fish and Fish Habitat

Instream construction will be completed in isolation of flowing water (i.e., isolation methods will be used for the removal of culverts where surface water exists at the time of construction) (refer to Appendix 4-II, Appendix B, Figure B-5).

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include removal of any water crossings

Not Started

2- 403

403 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Culvert – Contractor Measures #22

EA Report – Section 13 – Fish and Fish Habitat

Pump bypass water from upstream, across the isolated workspace through a hose and onto an energy dissipation device prior to entering the water body downstream from the isolated workspace.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; one culvert installation completed in 2019 on LRCA watercourse in compliance with permits and under supervision of a resource specialist

Yes

87 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 404

404 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Culvert – Contractor Measures #32

CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structure – Ice Bridge – Contractor Measures #38

CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Snow Fill – Contractor Measures #44

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

Restore disturbed banks and approaches immediately following the removal of temporary water body crossing structures as outlined in Section 6.9.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include removal of any water crossings

Not Started

2- 405

405 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structure – Ice Bridge – Contractor Measures #33

EA Report – Section 13 – Fish and Fish Habitat

Ice bridges on private land or First Nation Reserve will be decommissioned in consultation with the landowner or community.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include decommissioning activities

Not Started

2- 406

406 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structure – Ice Bridge – Contractor Measures #34 EA Report – Section 13 – Fish and Fish Habitat

A v-notch will be created in the centre of the ice bridge to allow the ice bridge to melt from the centre and to prevent blocking fish passage, channel erosion and flooding.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Not applicable. 2019 construction activities occurred during the winter months and did not include removal of any water crossings

Not Started

2- 407

407 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structure – Ice Bridge – Contractor Measures #35

CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Snow Fill – Contractor Measures #41

EA Report – Section 13 – Fish and Fish Habitat

Logs used to stabilize approaches will be removed prior to spring freshet. ●  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Not applicable. 2019 construction activities occurred during the winter months and did not include removal of any water crossings

Not Started

88 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 408

408 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Snow Fill – Contractor Measures #39

EA Report – Section 13 – Fish and Fish Habitat

Snow fills on private land or First Nation Reserve will be decommissioned in consultation with the landowner or community.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Not applicable. 2019 construction activities occurred during the winter months and did not include removal of any water crossings

Not Started

2- 409

409 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Water Body Crossing Structures – Snow Fill – Contractor Measures #40

Remove compacted snow from snow fills prior to the spring freshet. ●  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Not applicable. 2019 construction activities occurred during the winter months and did not include removal of any water crossings

Not Started

2- 410

410 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Access Roads – Contractor Measures #45

Temporary access roads on private land or First Nation Reserve will be decommissioned in consultation with the landowner or community.

●  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities did not include decommissioning activities

Not Started

2- 411

411 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Access Roads – Contractor Measures #46

Decommissioning of temporary access roads will be completed under non-frozen conditions when construction schedule allows.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities did not include decommissioning activities

Not Started

2- 412

412 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Access Roads – Contractor Measures #47

During decommissioning, fill material (e.g., gravel, shipped rock) and geotextile membrane will be removed from temporary access roads so the area is returned to the original road grade.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities did not include decommissioning activities

Not Started

89 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 413

413 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Access Roads – Contractor Measures #48

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

When undesired public access is a possibility, consider placing woody debris, planting conifers or other vegetation to limit public access.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities did not include decommissioning activities

Not Started

2- 414

414 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Access Roads – Contractor Measures #50

CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Workspaces – Contractor Measures #56

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 15 – Archaeological Resources EA Report – Section 16 – Cultural Heritage Resources

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Reclaim temporary access roads after decommissioning by implementing clean-up and reclamation measures in Section 6.9 (refer to Appendix 4-II).

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include decommissioning activities

Not Started

2- 415

415 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Workspaces – Contractor Measures #51

Laydown yards, storage yards, and construction camps on private lands or First Nation reserve lands may be left in place or partially decommissioned in consultation with the landowners or communities.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include decommissioning activities

Not Started

2- 416

416 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Workspaces – Contractor Measures #52

Decommissioning of laydown yards, storage yards and construction camps will be completed under non-frozen conditions when construction schedule allows.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include decommissioning activities

Not Started

2- 417

417 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Workspaces – Contractor Measures #53

Any in-ground infrastructure (e.g., water line, sewage) may be removed. If in-ground infrastructure cannot be removed, in-ground infrastructure will be emptied prior to capping.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include decommissioning activities

Not Started

2- 418

418 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Workspaces – Contractor Measures #54

EA Report – Section 8 – Groundwater

Concrete pads used as temporary fueling storage areas will be removed when removing surface infrastructure.   ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include decommissioning activities

Not Started

90 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 419

419 CEPP Section 6.8 – Transmission Line Construction Environmental Protection Measures – Decommissioning of Temporary Workspaces, Access Roads and Water Body Crossing Structures – Temporary Workspaces – Contractor Measures #56

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

Reclaim temporary workspaces after decommissioning by implementing clean-up and reclamation measures in Section 6.9 (Appendix 4-II).

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include reclamation or decommissioning activities

Not Started

2- 420

420 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation

Project Site clean-up and interim reclamation activities will take place throughout the construction of the Project. These activities will include, but not be limited to, removing refuse, grading disturbed areas, contouring disturbed slopes to a stable profile, and re-establishing natural drainage patterns.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include reclamation activities

Not Started

2- 421

421 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation

The final reclamation of temporary infrastructure (e.g., laydown yards, storage yards, construction camps, temporary access roads and temporary water body crossing structures) will be conducted after they have been decommissioned and removed.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include reclamation activities

Not Started

2- 422

422 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Construction Monitoring – Owner Measures #1

CEPP Section 8.1 – Environmental Management Plans – Erosion and Sedimentation Control Plan – Construction Monitoring – Owner Measures #1

Routinely (e.g., after spring freshet) inspect erosion and sediment control mitigation measures and bank stabilization features to verify effectiveness.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 423

423 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Schedule – Contractor Measures #1

EA Report – Section 6 – Geology, Terrain and Soils EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources

Complete clean-up and interim reclamation of the Project footprint under non-frozen conditions as soon as possible after decommissioning, when Project schedule allows.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include reclamation activities

Not Started

2- 424

424 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Schedule – Contractor Measures #2

Complete final reclamation during non-frozen conditions.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include reclamation activities

Not Started

2- 425

425 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Schedule – Contractor Measures #3

Revegetation and/or seeding will follow as close as possible to clean-up and topsoil material replacement pending seasonal or weather conditions.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include revegetation activities

Not Started

91 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 426

426 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Surveying and Flagging – Contractor Measures #4

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Flagging, signage or other markings will be removed upon construction completion.   ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include decommissioning activities

Not Started

2- 427

427 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Garbage and Debris – Contractor Measures #6

Remove remaining garbage and debris from the Project Site.   ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include decommissioning activities

Not Started

2- 428

428 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Cleanup – Contractor Measures #7

Fill material on provincial Crown lands will be removed from Project Site and disposed of appropriately (e.g., reclaimed fill returned to source aggregate pits or quarries).

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

2019 construction activities did not include decommissioning activities

Not Started

2- 429

429 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Cleanup – Contractor Measures #8

Removed culverts and other structural materials will be properly disposed (e.g., recycled, repurposed or disposed of in a landfill).

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include decommissioning activities

Not Started

2- 430

430 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Cleanup – Contractor Measures #9

All waste, geotextile, silt fencing, filter fabric, wood debris, and other Project waste will be removed from Project Site and disposed.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include decommissioning activities

Not Started

2- 431

431 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Subsoil Compaction – Contractor Measures #10

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands

Decompact subsoils throughout stripped areas of Project Site, and soils damaged during wet weather using stripping or other appropriate method.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include reclamation activities

Not Started

2- 432

432 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Subsoil Compaction – Contractor Measures #11

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 8 – Groundwater

Use appropriate equipment on decompacted subsoils to break up lumps and to smooth the surface.   ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include reclamation activities

Not Started

2- 433

433 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Subsoil Compaction – Contractor Measures #12

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 12 – Vegetation and Wetlands

Postpone decompaction of subsoils, if soils are moist, until soils dry so that the soils fracture when ripped.   ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include reclamation activities

Not Started

92 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 434

434 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Re-contouring – Contractor Measures #14

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

Re-contour disturbed areas to restore drainage patterns and the approximate pre-construction profile.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include reclamation activities

Not Started

2- 435

435 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Re-contouring – Contractor Measures #15

OEMP Section 5.1 – General Mitigation Measures – Erosion and Sedimentation Control

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water EA Report – Section 13 – Fish and Fish Habitat EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage

Resources

Regrade areas with vehicle ruts and erosion gullies to conform to the local topography to maintain drainage patterns.   ●  ●  Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 436

436 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Topsoil Replacement – Contractor Measures #16

Before replacing topsoil, smooth subsoil.   ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include reclamation activities

Not Started

2- 437

437 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Topsoil Replacement – Contractor Measures #17

Replace topsoil as evenly as possible throughout stripped areas of Project Site.   ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include reclamation activities

Not Started

2- 438

438 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Topsoil Replacement – Contractor Measures #18

EA Report – Section 6 – Geology, Terrain and Soils

Postpone replacing topsoil during wet conditions or high winds to prevent damaging soil structure and erosion of topsoil, unless construction activities must continue to adhere to construction timing windows and/or restrictions. If required, appropriate mitigation measure will be implemented to protect environmentally sensitive features and or notify the appropriate regulating agency.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include reclamation activities

Not Started

2- 439

439 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Wetlands – Contractor Measures #20

Do not apply fertilizer or coarse woody debris (e.g., mulch) in wetlands.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include reclamation activities

Not Started

2- 440

440 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Bank Stabilization – Contractor Measures #21

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 13 – Fish and Fish Habitat

Restore disturbed banks and approaches immediately following the removal of temporary water body crossing structures. Restore bed and bank to the full extent of the disturbed area including upstream and downstream of the water body crossing location.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include removal of any water crossings

Not Started

2- 441

441 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Bank Stabilization – Contractor Measures #22

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 13 – Fish and Fish Habitat

Restore disturbed bed and banks to their original contour and gradient. If the original gradient cannot be restored due to stability, a stable gradient that does not obstruct fish passage will be constructed.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include removal of any restoration activities.

Not Started

93 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 442

442 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Bank Stabilization – Contractor Measures #23

EA Report – Section 6 – Geology, Terrain and Soils EA Report – Section 13 – Fish and Fish Habitat

Install rollback or other bank stabilization methods (e.g., live willow cuttings) at water crossings when reconstructing water body banks, as required or request by landowner, to improve stability and to re-establish cover and habitat for fish-bearing water bodies.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include removal of any water crossings and restoration

Not Started

2- 443

443 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Bank Stabilization – Contractor Measures #25

EA Report – Section 6 – Geology, Terrain and Soils EA Report – Section 13 – Fish and Fish Habitat

If replacement rock reinforcement/armouring is required to stabilize eroding or exposed areas of the bank, appropriated sized clean rock will be used and installed at a similar slope, maintaining a uniform bank/shoreline and natural stream/shoreline alignment. These materials will be placed in a manner that generally matches the configuration and shape of adjoining sections of channel or shoreline to further augment the overall physical stability of the system.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include removal of any water crossings and restoration

Not Started

2- 444

444 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Bank Stabilization – Contractor Measures #26 EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

Revegetation of the riparian zone if necessary will consider DFO’s Measures to Avoid Causing Harm to Fish and Fish Habitat Including Aquatic Species at Risk (DFO 2016) and MNRF’s Environmental Guidelines for Access Roads and Water Crossings (refer to Appendix 4-II, Appendix H2; MNR 1990), and Forest Management Guide for Conserving Biodiversity at the Stand and Site Scales (refer to Appendix 4-II, Appendix H3; MNR 2010a) and its associated Background Rationale document (MNR 2010b).

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include revegetation activities

Not Started

2- 445

445 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Seeding Revegetation – Contractor Measures #27

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 12 – Vegetation and Wetlands

On private lands, reclaim as per landowner specifications and base on the availability of seed at the time of reclamation.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include reclamation activities

Not Started

2- 446

446 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Seeding Revegetation – Contractor Measures #28

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

On federal land, provincial Crown land or municipal land, allow for natural regeneration or use certified native seed in consultation with appropriate Land Administrator. Natural recovery is the preferred method of reclamation on level terrain where erosion is not expected.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include reclamation activities

Not Started

2- 447

447 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Seeding Revegetation – Contractor Measures #29

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 19 – Non-Traditional Land and Resource Use

Where necessary, seed the disturbed areas using certified native seed mix and seed application rate appropriate for the final land use.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include revegetation activities

Not Started

94 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 448

448 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Seeding Revegetation – Contractor Measures #30

Seed erosion prone areas with a native cover crop (e.g., cereal crop) and certified seed mix approved by the applicable regulatory agency as soon as feasible after construction.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include revegetation activities

Not Started

2- 449

449 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Seeding Revegetation – Contractor Measures #31

CEPP Section 8.4 – Environmental Management Plans – Weed Management Plan – Seeding and Revegetation – Contractor Measures #14

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Do not accept seed that contains noxious weeds.   ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include seeding activities

Not Started

2- 450

450 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures –Project Site Cleanup and Reclamation – Seeding Revegetation – Contractor Measures #33

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Land Resource Use EA Report – Section 19 – Non-Traditional Land and Resource Use

Plant conifers when reclaiming laydown yards, construction camps, and storage yards located off of the transmission line ROW and in consultation with the landowner or communities and applicable regulatory authority.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include revegetation activities

Not Started

2- 451

451 CEPP Section 6.9 – Transmission Line Construction Environmental Protection Measures – Project Site Cleanup and Reclamation – Erosion and Sedimentation Control – Contractor Measures #34

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources

Where vegetation has established, or risk for sedimentation and erosion has been mitigated, remove temporary erosion and sediment control measures.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include removal of any erosion and sediment control measures following vegetation establishment

Not Started

2- 452

452 CEPP Section 6.10 – Transmission Line Construction Environmental Protection Measures – Post-Construction Monitoring

A detailed Post-Construction Monitoring Plan will be developed prior to the start of construction of each workfront based on permit approval conditions. The detailed Post-Construction Monitoring Plan will include detailed monitoring methods and a plan to address outstanding environmental issues or areas that require further reclamation or monitoring of reclamation efforts, as identified during and following construction.

●      Valard EMS; Adherence to CEPP and DPP

Post-construction monitoring plan was developed. 2019 construction activities did not include post-construction monitoring.

Yes

95 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 453

453 CEPP Section 6.10 – Transmission Line Construction Environmental Protection Measures – Post-Construction Monitoring

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources

Post-construction environmental monitoring will be conducted after the completion of the construction activities and continue into the operation phase of the Project and will include such activities as examining and documenting the success of reclamation measures.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include reclamation activities

Not Started

2- 454

454 CEPP Section 6.10 Post-Construction Mitigation Measures – Environmental Inspector – Owner Measures #1

The Owner will employ the services of qualified Environmental Inspector(s) to monitoring the effectiveness of implementation of mitigation and identify any reclamation concerns.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include reclamation activities

Not Started

2- 455

455 CEPP Section 6.10 – Transmission Line Construction Environmental Protection Measures– Post-Construction Mitigation Measures – Resource Specialist – Owner Measures #2

CEPP Section 7.5 – Contingency Plans – Wildlife Features of Concern Discovery Contingency Plan – Post-Construction Measures – Owner Measures #12

Following construction, a resource specialist may evaluate the success of mitigative measures, particularly environmentally sensitive features (i.e. relocated nests, wetlands etc.) if habitat features (like nests) or individuals are relocated.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Not applicable to 2019 construction activities

Not Started

2- 456

456 CEPP Section 6.10 – Transmission Line Construction Environmental Protection Measures– Post-Construction Mitigation Measures –Post-Construction Monitoring – Owner Measures #3

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat EA Report – Section 19 – Non-Traditional Land and Resource Use

Post-construction monitoring of the Project Site will begin following reclamation, within one growing season, and annually during operations to identify and address any reclamation concerns, including but not limited to soil erosion, revegetation, slope stability and weeds.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include post-construction monitoring activities

Not Started

2- 457

457 CEPP Section 6.10 – Transmission Line Construction Environmental Protection Measures– Post-Construction Mitigation Measures – Post-Construction Monitoring – Owner Measures #4

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 20 – Visual Environment

Post-construction monitoring at water body crossing location should be conducted after the first spring freshet and routinely until the site has become stable and re-vegetated.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include post-construction monitoring activities

Not Started

2- 458

458 CEPP Section 6.10 – Transmission Line Construction Environmental Protection Measures– Post-Construction Mitigation Measures – Remedial Measures – Owner Measures #5

EA Report – Section 19 – Non-Traditional Land and Resource Use

Implement remedial measures to achieve the goal of the reclamation that is to stabilize and revegetate disturbed areas, while maintaining access and appropriate drainage to support operation and maintenance standards.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include reclamation activities

Not Started

2- 459

459 CEPP Section 6.10 – Transmission Line Construction Environmental Protection Measures– Post-Construction Mitigation Measures – Reporting – Owner Measures #6

Monitoring report including results of monitoring activities will be prepared and submitted to applicable regulatory agency as described in permit approval conditions.

  ●    Annual Compliance Monitoring Report

Annual compliance monitoring report will be submitted annually.

In Progress

96 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 460

460 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Reporting – Owner Measures #1 

The Owner will report spills in accordance with the provincial requirements (refer to Appendix 4-IITable 4-II-3).

Table 4-II-3: Reportable Spill Quantities

Substance Quantity External Reporting Requirements

Any Spill Any amount N/A

≥100 litres

Oil and Waste Oil Any amount of material in areas that are outside of the ROW Call within 24 hours:

Oil with >50 ppm PCB ≥1 kilogram Ontario Spills Action Center Spills Action Center

Flammable or

Non-Flammable Gas ≥10 kilograms 1-800-268-6060 (toll-free, province-wide, 24/7)

Toxic or Corrosive Waste ≥5 kilograms 1-855-515-3759 (TTY) Hazardous Waste ≥5 litres or kilograms *record file number

Any quantity that could Explosives pose a danger to the

public or 50 kilograms

>= greater than; >= greater than or equal to; ppm = parts per million; PCB = polychlorinated biphenyl; N/A = not applicable; TTY = a special device that lets people who are deaf, hard of hearing, or speech-impaired use the telephone to communicate.

Releases that require external report include spills that:

cause harm or material discomfort to any person;

injure or damages property or animal life;

impair the quality of the natural environment air, water or land;

cause adverse health effects;

present a safety risk;

render property, plant or animal life unfit for use;

lead to the loss of enjoyment of the normal use of property; or

interfere with the normal conduct of business. The immediate report must include:

your name and phone number;

name of the company or individual responsible for the spill;

time and location of the spill;

type and quantity of material spilled (if you know); and

status of the spill, including actions being taken to control the spill. Information provided to the center will be forwarded to Environment Canada, who will in turn contact DFO if warranted. The following information will be required during the notification process:

your name and phone number;

name of the company or individual responsible for the spill;

time and location of the spill;

type and quantity of material spilled (if you know); and

status of the spill, including actions being taken to control the spill.

  ●    Valard EMS and Valard OEWTL Environmental Incident Notification and Reports

Complete for 2019; ongoing for remaining Project construction

Yes

2- 461

461 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Contaminated Soils – Owner Measures #2

EA Report – Section 6 – Geology, Terrain and Soils

If the presence of contaminated soils and associated water is suspected, the Owner will immediately assess the situation and may shut down or remove equipment from the area.

  ●    Valard EMS and Valard OEWTL Environmental Incident Notification and Reports; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

97 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 462

462 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Contaminated Soils – Owner Measures #3

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 8 – Groundwater

The Owner or the Environmental Inspector will visually assess the suspected material and surrounding area and determine the extent of potential contamination, if any.

  ●    Valard EMS and Valard OEWTL Environmental Incident Notification and Reports; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 463

463 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Contaminated Soils – Owner Measures #4

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 8 – Groundwater

The Owner or the Environmental Inspector may collect (or arrange to have collected) soil samples at the suspected contamination location.

  ●    Valard EMS and Valard OEWTL Environmental Incident Notification and Reports; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 464

464 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Contaminated Soils – Owner Measures #5

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 8 – Groundwater

The Owner will notify relevant federal and provincial regulatory authorities as required.   ●    Valard EMS and Valard OEWTL Environmental Incident Notification and Reports; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 465

465 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Contaminated Soils – Owner Measures #6

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 8 – Groundwater

The Owner will develop a suitable course of action (e.g., excavate, stockpile, sample, remediate and/or contain and dispose) in consultation with the appropriate regulatory agencies, if necessary.

  ●    Valard EMS and Valard OEWTL Environmental Incident Notification and Reports; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 466

466 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Contaminated Soils – Owner Measures #7

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 8 – Groundwater

The Owner will identify local licensed landfill that would be able to receive soils if confirmed to be contaminated.   ●    Valard EMS and Valard OEWTL Environmental Incident Notification and Reports; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 467

467 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Contaminated Soils – Owner Measures #8 EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 8 – Groundwater

The Owner will prepare a contaminated soil and associated water notification report (refer to Appendix 4-II, Appendix E) and support from the General Contractor (Valard) may be required.

  ●    Valard EMS and Valard OEWTL Environmental Incident Notification and Reports; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

98 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 468

468 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Equipment – Contractor Measures #1

OEMP Appendix C – Spill Prevention and Response Contingency Plan – Equipment – Contractor Measures #1

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

Maintain an adequate supply of spill prevention and emergency response equipment onsite at all times and train Project personnel on the use of this equipment. The risk for site-specific spills will be used to determine the appropriate type of response equipment and suitable location for storage. The General Contractor (Valard) will also provide a list of required stand-by equipment and required spill response container supplies to respond to large volume spills.

  ●  ●  Valard EMS; Valard OEWTL Online Site Orientation; EWT Safety Orientation; Adherence to CEPP and DPP; IEnvironmental Incident Notification and Reports; Valard POD and Tailboards

Complete for 2019; ongoing for remaining Project construction

Yes

2- 469

469 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Equipment – Contractor Measures #3

OEMP Appendix C – Spill Prevention and Response Contingency Plan – Equipment – Contractor Measures #4

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

Maintain equipment in good operating condition and inspect regularly for cleanliness, leaks, excess oil or grease. Identified problems or deficiencies shall be corrected in a timely manner.

  ●  ●  Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 470

470 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Equipment – Contractor Measures #4

CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Transportation, Storage, and Handling – Contractor Measures #15

OEMP Appendix C – Spill Prevention and Response Contingency Plan – Equipment – Contractor Measures #5

OEMP Appendix C – Spill Prevention and Response Contingency Plan – Transportation, Storage, and Handling – Contractor Measures #16

Maintain documentation (e.g., inspection record) in accordance with applicable regulations and local requirements.   ●  ●  Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 471

471 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Equipment – Contractor Measures #5

OEMP Appendix C – Spill Prevention and Response Contingency Plan – Equipment – Contractor Measures #6

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands EA Report – Section 13 – Fish and Fish Habitat EA Report – Section 14 – Wildlife and Wildlife Habitat

Fuel and servicing vehicles will carry at a minimum:

fire extinguishers;

shovels;

an impermeable barrier for placing under vehicles to be serviced; and

hydrocarbon spill kits complete with a minimum of 10 kilograms (kg) of sorbent material for clean-up of small spills.

  ●  ●  Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

99 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 472

472 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Equipment – Contractor Measures #5

OEMP Appendix C – Spill Prevention and Response Contingency Plan – Equipment – Contractor Measures #6

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

The contents of spill kit must be replenished as soon as possible following its use.   ●  ●  Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 473

473 CEPP Section 7.1 –Spill Prevention and Response Contingency Plan – Equipment – Contractor Measures #6

OEMP Appendix C – Spill Prevention and Response Contingency Plan – Equipment – Contractor Measures #7

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

Re-fueling or equipment maintenance activities are not to occur within 100 m of a water body. If re-fueling within 100 m of a water body cannot be avoided, the General Contractor (Valard) is to provide and implement a site-specific spill prevention plan.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 474

474 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Equipment – Contractor Measures #7

OEMP Appendix C – Spill Prevention and Response Contingency Plan – Equipment – Contractor Measures #8

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

Perform equipment servicing, such as oil changes and hydraulic repairs with potential for spills over an impervious tarp to contain spills when done on site or within the ROW.

  ●  ●  Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 475

475 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Equipment – Contractor Measures #8

OEMP Appendix C – Spill Prevention and Response Contingency Plan – Equipment – Contractor Measures #9

EA Report – Section 6 – Geology, Terrain and Soils EA Report – Section 7 – Surface Water EA Report

– Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

Employ the following measures to reduce the risk of fuel spills containers, hoses, nozzles are free of leaks; equip fuel nozzles with automatic shutoffs; and

if both ends of the hose are not visible have operators stationed at both ends of the hose during fueling

  ●  ●  Valard EMS and Valard OEWTL Environmental Incident Notification and Reports; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

100 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 476

476 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Transportation, Storage, and Handling – Contractor Measures #10

OEMP Appendix C – Spill Prevention and Response Contingency Plan – Transportation, Storage, and Handling – Contractor Measures #11

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

Project personnel will be trained for handling, receiving, shipping hazardous materials.   ●  ●  Valard EMS; Adherence to CEPP and DPP; Valard OEWTL Online Site Orientation; EWT Safety Orientation; MOL Safety Orientation

Complete for 2019; ongoing for remaining Project construction

Yes

2- 477

477 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Transportation, Storage, and Handling – Contractor Measures #11

CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Hazardous Wastes – Contractor Measures #16

OEMP Appendix C – Spill Prevention and Response Contingency Plan – Transportation, Storage, and Handling – Contractor Measures #12

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

Hazardous materials will be transported in approved containers in licensed vehicles.   ●  ●  Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations; Valard OEWTL Online Site Orientation; EWT Safety Orientation; MOL Safety Orientation

Complete for 2019; ongoing for remaining Project construction

Yes

2- 478

478 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Transportation, Storage, and Handling – Contractor Measures #12

OEMP Appendix C – Spill Prevention and Response Contingency Plan – Transportation, Storage, and Handling – Contractor Measures #13

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

Hazardous materials will be stored in appropriate containers and placed in suitable designated areas:

Store fuel storage tanks in a secondary containment tub to prevent fuels from escaping; store fuel storage tanks larger than 25 litres (L) in a secondary containment system (e.g., tidy-tank,

double-walled containment tub) with a holding capacity equal to 110% of the volume stored; and

store hydrocarbon storage containers greater than 23 L in a secondary containment (e.g., polyethylene containment tub) with a holding capacity of 110% of the volume stored.

  ●  ●  Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations; Valard OEWTL Online Site Orientation; EWT Safety Orientation; MOL Safety Orientation

Complete for 2019; ongoing for remaining Project construction

Yes

101 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 479

479 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan –Transportation, Storage, and Handling – Contractor Measures #13

OEMP Appendix C – Spill Prevention and Response Contingency Plan – Transportation, Storage, and Handling – Contractor Measures #14

EA Report – Section 6 – Geology, Terrain and Soils EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

Fuel storage tanks will be visually inspected on a regular basis to ensure that they do not leak, sealed with a properly fitting lid and labelled accordingly. Identified problems or deficiencies shall be corrected in a timely manner.

  ●  ●  Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations; Valard OEWTL Online Site Orientation; EWT Safety Orientation; MOL Safety Orientation

Complete for 2019; ongoing for remaining Project construction

Yes

2- 480

480 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Transportation, Storage, and Handling – Contractor Measures #14

OEMP Appendix C – Spill Prevention and Response Contingency Plan – Transportation, Storage, and Handling – Contractor Measures #15

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

Implement controls and utilize containment and/or spill trays when transferring hazardous materials between containers or working near surface drainage and environmentally sensitive features.

  ●  ●  Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 481

481 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Reporting – Contractor Measures #16

Report all spills and releases immediately to the Owner.   ●    Valard EMS and Valard OEWTL Environmental Incident Notification and Reports; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 482

482 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Reporting – Contractor Measures #17

CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Contaminated Soils – Contractor Measures #19

Prepare a spill report using the Spill Reporting Form (refer to Appendix 4-II, Appendix D) and submit all spill reports to the Owner.

  ●    Valard EMS and Valard OEWTL Environmental Incident Notification and Reports; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 483

483 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Contaminated Soils – Contractor Measures #18

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 8 – Groundwater

In the event that contaminated soils (e.g., hydrocarbon odours is present or soils is obviously darker that the surrounding soil) or fill material is suspected within the Project Site: IMMEDIATELY HALT WORK IN THAT LOCATION, isolate the area or suspect contaminated material and notify the Owner.

  ●    Valard EMS and Valard OEWTL Environmental Incident Notification and Reports; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

102 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 484

484 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Contaminated Soils – Contractor Measures #20

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 8 – Groundwater

Segregate or separately store contaminated soils on a high-density polyethylene liner or equivalent (within a bermed area), at minimum 100 m away from permanent water features and on relatively flat surface. Label and/or install signs at the contaminated soils piles.

  ●    Valard EMS and Valard OEWTL Environmental Incident Notification and Reports; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 485

485 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Contaminated Soils – Contractor Measures #21

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 8 – Groundwater

Protect contaminated soil piles from erosion by installing silt fence or using plastic tarps to cover the pile as necessary.

  ●    Valard EMS and Valard OEWTL Environmental Incident Notification and Reports; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 486

486 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Release – Contractor Measures #22

OEMP Appendix C – Spill Prevention and Response Contingency Plan – Release – Contractor Measures #19

Contain and clean-up all spills on land immediately and/or as quickly as possible when safe to do so.   ●  ●  Valard EMS and Valard OEWTL Environmental Incident Notification and Reports; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 487

487 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Release – Contractor Measures #23

OEMP Appendix C – Spill Prevention and Response Contingency Plan – Release – Contractor Measures #20

OEMP Appendix C – Spill Prevention and Response Contingency Plan – Release – Contractor Measures #21

Spill containment will depend on the physical and chemical properties of the substance:

If solid, cover material with plastic. Contain plastic bags in the spill kit for temporary storage of soiled material and place the bags in a pickup or a designated area for transport to an appropriate waste disposal facility.

If liquid, contain the spill using spill booms or other materials designed for this purpose. Hazardous waste drums may be utilized to contain free agent or contaminated liquids cleaned from a site.

Isolate/block any pathways to watercourses or surface drainage.

  ●  ●  Valard EMS and Valard OEWTL Environmental Incident Notification and Reports; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 488

488 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Release – Contractor Measures #24

OEMP Appendix C – Spill Prevention and Response Contingency Plan – Release – Contractor Measures #22

Recover contained liquid spill material through suction methods (e.g., vacuum trucks) wherever practicable. If such equipment is not readily available or cannot access the spill site, other appropriate recovery techniques (e.g., burning, absorbents) should be applied.

  ●    Valard EMS and Valard OEWTL Environmental Incident Notification and Reports; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 489

489 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Release – Contractor Measures #25

OEMP Appendix C – Spill Prevention and Response Contingency Plan – Release – Contractor Measures #23

Identified leaks shall be contained and repaired as soon as possible. Relocate leaking equipment to a level ground away from environmentally sensitive features provided that temporary containment is in place and moving the equipment does not increase the risk of environmental contamination.

  ●  ●  Valard EMS and Valard OEWTL Environmental Incident Notification and Reports; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 490

490 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Release – Contractor Measures #26

Restore the areas to the satisfaction of the Owner and/or regulatory agencies.   ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

103 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 491

491 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Instream and Onshore Release – Contractor Measures #27

OEMP Appendix C – Spill Prevention and Response Contingency Plan – Instream and Onshore Release – Contractor Measures #25

OEMP Appendix C – Spill Prevention and Response Contingency Plan – Instream and Onshore Release – Contractor Measures #26

Instream and onshore containment and clean-up objectives include the following: Instream

divert water around the fluid release to the extent practicable; install silt fencing around the release point, if conditions permit; remove fluid from the water body by pumping or other suitable means; and dispose of recovered fluid in accordance with MECP requirements.

Onshore

contain the fluid release immediately to limit the area affected and prevent the fluid from entering the water body; and dispose of recovered fluid in accordance with MECP requirements.

Consider the following options for removal of fluid from instream:

Use trash pumps or vacuum truck. If trash pumps are used, the water pumped to the discharge must not drain back into a water body, or construct a sediment/water holding area if there is potential for sedimentation from discharge water.

In consultation with MECP and DFO biologists, leave fluid if current water body levels and flow inhibit removal or if removal will result in unacceptable shore or instream damage.

  ●    Valard EMS and Valard OEWTL Environmental Incident Notification and Reports; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 492

492 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Instream and Onshore Release – Contractor Measures #28

OEMP Appendix C – Spill Prevention and Response Contingency Plan – Instream and Onshore Release – Contractor Measures #27

If not accessible, construct bale and filter cloth weirs and a containment area where appropriate.   ●  ●  Valard EMS and Valard OEWTL Environmental Incident Notification and Reports; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 493

493 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Instream and Onshore Release – Contractor Measures #29

OEMP Appendix C – Spill Prevention and Response Contingency Plan – Instream and Onshore Release – Contractor Measures #28

Conduct water quality sampling as appropriate.   ●  ●  Valard EMS and Valard OEWTL Environmental Incident Notification and Reports; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 494

494 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Instream and Onshore Release – Contractor Measures #30

OEMP Appendix C – Spill Prevention and Response Contingency Plan – Instream and Onshore Release – Contractor Measures #29

The General Contractor (Valard) will prepare a report summarizing the events leading to the release and the measures taken to minimize the impact on the environment. As directed by the regulatory agencies, written reports may be required.

  ●  ●  Valard EMS and Valard OEWTL Environmental Incident Notification and Reports; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 495

495 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Waste Management – Contractor Measures #31

Implement the hazardous wastes measures outlined in the Waste Management Plan (refer to Appendix 4-II, Section 8.2).

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 496

496 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Waste Management – Contractor Measures #32

Collect and dispose of heavily saturated vegetation, soil and used absorbent material and/or contaminated soils and associated water at an approved industrial waste disposal facility. Truck manifests will be collected.

  ●    Valard EMS and Valard OEWTL Environmental Incident Notification and Reports; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 497

497 CEPP Section 7.1 – Contingency Plans – Spill Prevention and Response Contingency Plan – Waste Management – Contractor Measures #33

OEMP Appendix C – Spill Prevention and Response Contingency Plan – Waste Management – Contractor Measures #30

Dumping of oil or other deleterious materials on the ground or in any water body is strictly prohibited.   ●  ●  Valard EMS and Valard OEWTL Environmental Incident Notification and Reports; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

104 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 498

498 CEPP Section 7.2 – Contingency Plans – Soil Handling Contingency Plan – Little or No Topsoil – Contractor Measures #1

Overstrip shallow topsoils to a depth of 15 centimetres (cm).   ●    Valard EMS; Adherence to CEPP and DPP

Limited soil stripping and topsoil stockpiling required for construction activity in 2019, ongoing for remaining Project construction

Yes

2- 499

499 CEPP Section 7.2 – Contingency Plans – Soil Handling Contingency Plan – Uneven Boundary Between Topsoil and Subsoil – Contractor Measures #2

Use equipment capable of fine depth adjustments when salvaging topsoil.   ●    Valard EMS; Adherence to CEPP and DPP

Limited soil stripping and topsoil stockpiling required for construction activity in 2019, ongoing for remaining Project construction

Yes

2- 500

500 CEPP Section 7.2 – Contingency Plans – Soil Handling Contingency Plan – Uneven Boundary Between Topsoil and Subsoil – Contractor Measures #3

Strip topsoil so that the exposed surface has a mottled pattern composed of 50% topsoil and 50% subsoil. Once this is done, begin the transition layer lift.

  ●    Valard EMS; Adherence to CEPP and DPP

Limited soil stripping and topsoil stockpiling required for construction activity in 2019, ongoing for remaining Project construction

Yes

2- 501

501 CEPP Section 7.2 – Contingency Plans – Soil Handling Contingency Plan –Wet Conditions – Contractor Measures #4

EA Report – Section 14 – Wildlife and Wildlife Habitat

If construction occurs or is anticipated within wet areas, under wet conditions (e.g. excessive rain, wet weather, or flood-like conditions), or during spring break-up (e.g., thawing soil conditions), implement one or more of the following:

Notify the Owner that contingency measures may be required to reduce potential for erosion and sedimentation;

use equipment that minimizes surface disturbance, soil compaction and topsoil loss (e.g., equipment with low ground pressure tires, or wide pad tracks);

restrict construction activity to the narrowest possible area or in areas where soils are subject to degradation;

limit construction activity to well-drained and/or well-vegetated areas, where practicable;

Use a protective layer such as matting (refer to Appendix 4-II, Appendix B, Figure B-13) if wet conditions are anticipated or encountered.

pump standing water to a vegetated area; and

back blade ruts to disperse water and allow faster drying.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 502

502 CEPP Section 7.2 – Contingency Plans – Soil Handling Contingency Plan –Wet Conditions – Contractor Measures #5

If soils are excessively saturated, suspend or postpone construction activities. Saturated soils are indicated by:

extensive wheel slip;

build-up of mud on tires and cleats;

ruts through topsoil into subsoil; and

tracking of mud down roads.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 503

503 CEPP Section 7.2 – Contingency Plans – Soil Handling Contingency Plan –Wet Conditions – Contractor Measures #6

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

If it is not possible to suspend or postpone the construction activities, a site-specific Erosion and Sedimentation Control Plan will be implemented in consultation with the Owner.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 504

504 CEPP Section 7.2 – Contingency Plans – Soil Handling Contingency Plan –Wet Conditions – Contractor Measures #7

Construction activities will not resume until permission is received by the Owner.   ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

105 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 505

505 CEPP Section 7.3 – Contingency Plans – Fire Prevention Contingency Plan – Regulatory Approvals – Contractor Measures #1

OEMP Section 5.5 – Environmental Management During Operation –Fire Prevention

EA Report – Section 4 – Project Description

All work will adhere to the Forest Fires Prevention Act (R.S.O. 1990) and Regulation O. Reg. 207/96. The Act provides direction for the prevention and suppression of wildland fires in forest areas within the fire region during the fire season, normally April 1 to October 31.

  ●  ●  Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

Complete for 2019; ongoing for remaining Project construction

Yes

2- 506

506 CEPP Section 7.3 – Contingency Plans – Fire Prevention Contingency Plan – Fire Hazards – Contractor Measures #2

If the fire hazard is high, implement protection measures such as the use of fire resistant mats or wetting down the area prior to work commencing or having a water truck and/or appropriate fire-fighting equipment on site.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 507

507 CEPP Section 7.3 – Contingency Plans – Fire Prevention Contingency Plan – Fire Hazards – Contractor Measures #3

Project personnel will dispose of cigarette butts, welding rods, and other hot or burning items appropriately to reduce fire hazard.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 508

508 CEPP Section 7.3 – Contingency Plans – Fire Prevention Contingency Plan – Fire Hazards – Contractor Measures #4

Keep worksite free of debris and combustible materials.   ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 509

509 CEPP Section 7.3 – Contingency Plans – Fire Prevention Contingency Plan – Equipment – Contractor Measures #5

OEMP Section 5.5 – Environmental Management During Operation –Fire Prevention

Maintain an adequate supply of fire-fighting equipment on hand that is capable of controlling fire that may occur as a result of their activities, as regulated by provincial regulations and government agencies.

  ●  ●  Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 510

510 CEPP Section 7.3 – Contingency Plans – Fire Prevention Contingency Plan – Equipment – Contractor Measures #8

OEMP Section 5.5 – Environmental Management During Operation –Fire Prevention

Turn-off engines prior to refueling of equipment.   ●  ●  Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 511

511 CEPP Section 7.3 – Contingency Plans – Fire Prevention Contingency Plan – Transportation, Storage, and Handling – Contractor Measures #9

EA Report – Section 12 – Vegetation and Wetlands

The transportation, storage, and handling of flammable materials (e.g., fuel) will be in compliance with the Technical Standards and Safety Act, 2000, the Transportation of Dangerous Good Act, 1992, the National Fire Code (National Fire Code of Canada 2010), the Explosives Act (Government of Canada 1985), and the Occupational Health and Safety Act (Government of Ontario 1990b).

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

Complete for 2019; ongoing for remaining Project construction

Yes

2- 512

512 CEPP Section 7.3 – Contingency Plans – Fire Prevention Contingency Plan – Transportation, Storage, and Handling – Contractor Measures #10

Store flammable materials in certified unit load container (ULC).   ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

Complete for 2019; ongoing for remaining Project construction

Yes

2- 513

513 CEPP Section 7.3 – Contingency Plans – Fire Prevention Contingency Plan – Smoking – Contractor Measures #11

Smoking is only permitted in designated areas.   ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 514

514 CEPP Section 7.3 – Contingency Plans – Fire Prevention Contingency Plan – Smoking – Contractor Measures #12

No smoking allowed near any flammable storage facility.   ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 515

515 CEPP Section 7.3 – Contingency Plans – Fire Prevention Contingency Plan – Reporting – Contractor Measures #13

Report fire using the Fire Report Form (refer to Appendix 4-II, Appendix F). Submit all reports to the Owner.   ●    Valard EMS; Adherence to CEPP and DPP; Incident Notification Form

No Fire Report Forms required during 2019 construction activities

Yes

106 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 516

516 CEPP Section 7.4 – Contingency Plans – Discovery of Heritage or Archaeological Resources Contingency Plan – Incidental Discovery – Owner Measures #3

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources

In the event that a previously unidentified heritage or archaeological resources (e.g., arrow heads, modified bone, pottery fragments, fossils) are suspected or encountered unexpectedly during construction, the Owner may bring in a resource specialist and contact the regulators (e.g., MTCS, LRCA, or the municipality), as required.

  ●    Valard EMS; Adherence to CEPP and DPP

No previously unidentified heritage or archaeological resources found during 2019 construction activities

Yes

2- 517

517 CEPP Section 7.4 – Contingency Plans – Discovery of Heritage or Archaeological Resources Contingency Plan – Incidental Discovery – Owner Measures #4

EA Report – Section 2 – Consultation and Engagement Summary

If human remains are suspected, the Owner will immediately contact the Ontario Provincial Police, and implement the following measures:

IMMEDIATELY HALT WORK IN THAT LOCATION;

flag off the affected area to prevent additional disturbance;

cover any exposed bones with plastic sheeting, a garbage bin liner, blanket, or other clean covering;

assign an employee to watch the affected area until the Ontario Provincial Police arrives; and

ensure that the remains are treated with full dignity and respect.

  ●    Valard EMS; Adherence to CEPP and DPP; Environmental Incident Notification and Reports

No previously unidentified heritage or archaeological resources found during 2019 construction activities

Yes

2- 518

518 CEPP Section 7.4 – Contingency Plans – Discovery of Heritage or Archaeological Resources Contingency Plan – Incidental Discovery – Owner Measures #5

EA Report – Section 2 – Consultation and Engagement Summary

For archaeological or heritage discovery, suspend activity at that location until the resource specialist has assessed the feature and determined a suitable course of action in consultation with the Owner and, if necessary, the appropriate regulatory agencies.

  ●    Valard EMS; Adherence to CEPP and DPP

No previously unidentified heritage or archaeological resources found during 2019 construction activities

Yes

2- 519

519 CEPP Section 7.4 – Contingency Plans – Discovery of Heritage or Archaeological Resources Contingency Plan – Incidental Discovery – Owner Measures #6

CEPP Section 7.8 – Contingency Plans – Indigenous Land and Resource Use Site Contingency Plan – Incidental Discovery – Owner Measures #5

EA Report – Section 2 – Consultation and Engagement Summary

The resource specialist may deem it necessary to visit the site and will, regardless of whether a site visit is required, develop an appropriate mitigation plan in consultation with the Owner and, if necessary, the appropriate regulatory agencies.

  ●    Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table; Indigenous monitors on-site during construction

No previously unidentified heritage or archaeological resources found during 2019 construction activities

Yes

2- 520

520 CEPP Section 7.4 – Contingency Plans – Discovery of Heritage or Archaeological Resources Contingency Plan – Incidental Discovery – Owner Measures #7

If assessment of the resource is deemed necessary, the site will be assessed based on the following criteria:

the significance of the site;

the location of the site with respect to the Project Site;

the feasibility of alternate routing or siting to avoid the resource; and

the decision of MTCS.

  ●    Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

No previously unidentified heritage or archaeological resources found during 2019 construction activities

Yes

2- 521

521 CEPP Section 7.4 – Contingency Plans – Discovery of Heritage or Archaeological Resources Contingency Plan – Incidental Discovery – Owner Measures #8

EA Report – Section 2 – Consultation and Engagement Summary

Based on site assessment, recommendation will be made in consultation with MTCS (e.g., documenting, removing and salvaging).

  ●    Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

No previously unidentified heritage or archaeological resources found during 2019 construction activities

Yes

2- 522

522 CEPP Section 7.4 – Contingency Plans – Discovery of Heritage or Archaeological Resources Contingency Plan – Incidental Discovery – Owner Measures #9

EA Report – Section 2 – Consultation and Engagement Summary

Protect archaeological sites identified adjacent to the ROW, if deemed appropriate based on the assessment.   ●    Valard EMS; Adherence to CEPP and DPP

No previously unidentified heritage or archaeological resources found during 2019 construction activities

Yes

107 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 523

523 CEPP Section 7.4 – Contingency Plans – Discovery of Heritage or Archaeological Resources Contingency Plan – Incidental Discovery – Contractor Measures #1

EA Report – Section 2 – Consultation and Engagement Summary

In the event that not previously identified heritage or archaeological resources (e.g., arrow heads, modified bone, pottery fragments, fossils) are suspected or encountered unexpectedly during construction: IMMEDIATELY HALT WORK IN THAT LOCATION and notify the Owner. Potential archaeological or heritage resources should be suspected when the following are discovered:

artifacts of stone or other material, including single or scattered artifacts;

old-looking pits in the ground (large or small, circular or rectangular);

cabins and other old-looking structures;

old industrial, ranching, and others remains of possible heritage significance;

culturally modified tress, mature trees with well-defined bark scars; or,

trails, burial sites, fire pits, or hearths.

  ●    Valard EMS; Adherence to CEPP and DPP; Environmental Incident Notification and Reports

No previously unidentified heritage or archaeological resources found during 2019 construction activities

Yes

2- 524

524 CEPP Section 7.4 – Contingency Plans – Discovery of Heritage or Archaeological Resources Contingency Plan – Contingency Measures – Contractor Measures #2 EA Report – Section 2 – Consultation and Engagement Summary

Suspend work immediately in the vicinity of newly discovered feature. Work at that location may not resume until permission is received from the Owner.

  ●    Valard EMS; Adherence to CEPP and DPP

No previously unidentified heritage or archaeological resources found during 2019 construction activities

Yes

2- 525

525 CEPP Section 7.4 – Contingency Plans – Discovery of Heritage or Archaeological Resources Contingency Plan – Contingency Measures – Contractor Measures #3

EA Report – Section 2 – Consultation and Engagement Summary

Temporarily flag off the 5 m around the resource to protect the feature.   ●    Valard EMS; Adherence to CEPP and DPP

No previously unidentified heritage or archaeological resources found during 2019 construction activities

Yes

2- 526

526 CEPP Section 7.4 – Contingency Plans – Discovery of Heritage or Archaeological Resources Contingency Plan – Contingency Measures – Contractor Measures #4

CEPP Section 7.5 – Contingency Plans – Wildlife Features of Concern Discovery Contingency Plan – Contingency Measures – Contractor Measures #3

Follow measures provided by the Owner.   ●    Valard EMS; Adherence to CEPP and DPP

No previously unidentified heritage or archaeological resources found during 2019 construction activities

Yes

2- 527

527 CEPP Section 7.5 – Contingency Plans – Wildlife Features of Concern Discovery Contingency Plan – Incidental Discovery – Owner Measures #3

In the event that a previously unidentified wildlife feature of concern is suspected, the Owner may contact a resource specialist to identify the species or habitat and identify the magnitude of disturbance to the wildlife feature.

  ●    Valard EMS; Adherence to CEPP and DPP

No previously unidentified wildlife features of concern found during 2019 construction activities

Yes

2- 528

528 CEPP Section 7.5 – Contingency Plans – Wildlife Features of Concern Discovery Contingency Plan – Incidental Discovery – Owner Measures #4

EA Report – Section 14 – Wildlife and Wildlife Habitat

Clearly flag the areas around a wildlife feature or environmentally sensitive feature and their associated vegetation setbacks prior to construction to protect the feature. .

  ●    Valard EMS; Adherence to CEPP and DPP

No previously unidentified wildlife features of concern found during 2019 construction activities

Yes

2- 529

529 CEPP Section 7.5 – Contingency Plans – Wildlife Features of Concern Discovery Contingency Plan – Incidental Discovery – Owner Measures #5

CEPP Section 7.6 – Contingency Plans – Rare Plant Discovery Contingency Plan – Incidental Discovery – Owner Measures #5

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

Suspend activity at that location until the resource specialist has assessed the feature and determined a suitable course of action in consultation with the Owner and, if necessary, the appropriate regulatory agencies.

  ●    Valard EMS; Adherence to CEPP and DPP

No previously unidentified wildlife features of concern found during 2019 construction activities

Yes

2- 530

530 CEPP Section 7.5 – Contingency Plans – Wildlife Features of Concern Discovery Contingency Plan – Incidental Discovery – Owner Measures #6

EA Report – Section 14 – Wildlife and Wildlife Habitat

The Owner will document the location, photograph the feature (if safe to do so) and report the incidence to the appropriate regulatory agencies, as needed.

  ●    Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

No previously unidentified wildlife features of concern found during 2019 construction activities

Yes

108 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 531

531 CEPP Section 7.5 – Contingency Plans – Wildlife Features of Concern Discovery Contingency Plan – Contingency Measures – Owner Measures #7

EA Report – Section 14 – Wildlife and Wildlife Habitat

Depending on the species or habitat, the nature of the discovery and the activity status of the nest (i.e., presence of eggs and/or nestlings), burrow or den, recommendations will be made based on consultation with a resource specialist and, if necessary, the appropriate regulatory agencies.

  ●    Valard EMS; Adherence to CEPP and DPP

No previously unidentified wildlife features of concern found during 2019 construction activities

Yes

2- 532

532 CEPP Section 7.5 – Contingency Plans – Wildlife Features of Concern Discovery Contingency Plan – Contingency Measures – Owner Measures #8

After consultation with regulatory agency nest or other habitat features may be relocated, if practicable, and monitor the post construction response of relocation.

  ●    Valard EMS; Adherence to CEPP and DPP

No previously unidentified wildlife features of concern found during 2019 construction activities

Yes

2- 533

533 CEPP Section 7.5 – Contingency Plans – Wildlife Features of Concern Discovery Contingency Plan – Construction Monitoring – Owner Measures #9

EA Report – Section 14 – Wildlife and Wildlife Habitat

A resource specialist may monitor stress to species during construction, if warranted.   ●    Valard EMS; Adherence to CEPP and DPP

No previously unidentified wildlife features of concern found during 2019 construction activities

Yes

2- 534

534 CEPP Section 7.5 – Contingency Plans – Wildlife Features of Concern Discovery Contingency Plan – Construction Monitoring – Owner Measures #10

EA Report – Section 14 – Wildlife and Wildlife Habitat

The Owner will report successes or challenges to the appropriate regulatory agencies to keep them informed of the situation in regard to species at risk.

  ●    Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

No previously unidentified wildlife features of concern found during 2019 construction activities

Yes

2- 535

535 CEPP Section 7.5 – Contingency Plans – Wildlife Features of Concern Discovery Contingency Plan – Construction Monitoring – Owner Measures #11

The Owner reserves the right to suspend work or revise the construction strategy due to the discovery of a feature of concern (e.g., habitat).

  ●    Valard EMS; Adherence to CEPP and DPP

No previously unidentified wildlife features of concern found during 2019

Yes

2- 536

536 CEPP Section 7.5 – Contingency Plans – Wildlife Features of Concern Discovery Contingency Plan – Post-Construction Measures – Owner Measures #13

EA Report – Section 14 – Wildlife and Wildlife Habitat

Revegetate with plant species that will maintain habitat quality (i.e., maintain the location as a feeding area).   ●    Valard EMS; Adherence to CEPP and DPP

No previously unidentified wildlife features of concern found during 2019 construction activities

Yes

2- 537

537 CEPP Section 6.9 – Project Site Cleanup and Reclamation – Wildlife – Contractor Measures #19

CEPP Section 7.5 –Wildlife Features of Concern Discovery Contingency Plan – Post-Construction Measures – Owner Measures #14

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 14 – Wildlife and Wildlife Habitat

Install nest boxes or platforms to replace or enhance habitat during reclamation or restoration.   ●    Valard EMS; Adherence to CEPP and DPP

No previously unidentified wildlife features of concern found during 2019 construction activities

Yes

2- 538

538 CEPP Section 7.5 – Contingency Plans – Wildlife Features of Concern Discovery Contingency Plan – Incidental Discovery – Contractor Measures #1

In the event that a previously unidentified wildlife feature of concern (e.g., nest, ground nest, burrow, den) is suspected within the Project Site: IMMEDIATELY HALT WORK IN THAT LOCATION and notify the Owner.

  ●    Valard EMS; Adherence to CEPP and DPP

No previously unidentified wildlife features of concern found during 2019 construction activities

Yes

2- 539

539 CEPP Section 7.5 – Contingency Plans – Wildlife Features of Concern Discovery Contingency Plan – Contingency Measures – Contractor Measures #2

Suspend work immediately in the vicinity of newly discovered wildlife feature. Work at that location may not resume until permission is received from the Owner.

  ●    Valard EMS; Adherence to CEPP and DPP

No previously unidentified wildlife features of concern found during 2019 construction activities

Yes

2- 540

540 CEPP Section 7.6 – Contingency Plans – Rare Plant Discovery Contingency Plan – Incidental Discovery – Owner Measures #3

EA Report – Section 12 – Vegetation and Wetlands

In the event that a previously unidentified rare plant species or rare vegetation community is suspected, the Owner may contact a resource specialist to identify the species or habitat and identify the magnitude of disturbance to the vegetation feature and determine appropriate mitigation actions for the rare plant species or community. Consult with appropriate regulatory agency if required.

  ●    Valard EMS; Adherence to CEPP and DPP

No previously unidentified wildlife features of concern found during 2019 construction activities

Yes

2- 541

541 CEPP Section 7.6 – Contingency Plans – Rare Plant Discovery Contingency Plan – Incidental Discovery – Owner Measures #4

EA Report – Section 12 – Vegetation and Wetlands

Clearly flag the areas around the vegetation feature to protect the feature.   ●    Valard EMS; Adherence to CEPP and DPP

No previously unidentified vegetation features found during 2019 construction activities

Yes

109 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 542

542 CEPP Section 7.6 – Contingency Plans – Rare Plant Discovery Contingency Plan – Incidental Discovery – Owner Measures #6

EA Report – Section 12 – Vegetation and Wetlands

The Owner will document the location, photograph the feature, and report the incidence to the appropriate regulatory agencies, as needed

  ●    Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

No previously unidentified vegetation features found during 2019 construction activities

Yes

2- 543

543 CEPP Section 7.6 – Contingency Plans – Rare Plant Discovery Contingency Plan – Contingency Measures – Owner Measures #7

EA Report – Section 12 – Vegetation and Wetlands

Depending on the discovery recommendations will be made based on consultation with a resource specialist and, if necessary, the appropriate regulatory agencies.

  ●    Valard EMS; Adherence to CEPP and DPP

No previously unidentified vegetation features found during 2019 construction activities

Yes

2- 544

544 CEPP Section 7.6 – Contingency Plans – Rare Plant Discovery Contingency Plan – Contingency Measures – Owner Measures #8

EA Report – Section 12 – Vegetation and Wetlands

Protect rare plant species or rare vegetation community identified adjacent to the Project Site, if deemed appropriate based on the assessment (adjust slopes to protect root zones or facilitate shade or sun conditions).

  ●    Valard EMS; Adherence to CEPP and DPP

No previously unidentified vegetation features found during 2019 construction activities

Yes

2- 545

545 CEPP Section 7.6 – Contingency Plans – Rare Plant Discovery Contingency Plan – Contingency Measures – Owner Measures #9

EA Report – Section 12 – Vegetation and Wetlands

Temporarily fence off undisturbed adjacent areas to protect adjacent seed sources from being disturbed. Remove temporary fence during Project Site clean-up.

  ●    Valard EMS; Adherence to CEPP and DPP

No previously unidentified vegetation features found during 2019 construction activities

Yes

2- 546

546 CEPP Section 7.6 – Contingency Plans – Rare Plant Discovery Contingency Plan – Contingency Measures – Owner Measures #10

EA Report – Section 12 – Vegetation and Wetlands

Propagate species or component species, in the case of rare vegetation communities, via vegetative or reproductive means (e.g., harvesting of seed, salvaging and transplanting portions of sod and surrounding vegetation or collecting of cuttings).

  ●    Valard EMS; Adherence to CEPP and DPP

No previously unidentified vegetation features found during 2019 construction activities

Yes

2- 547

547 CEPP Section 7.6 – Contingency Plans – Rare Plant Discovery Contingency Plan – Construction Monitoring – Owner Measures #12

EA Report – Section 12 – Vegetation and Wetlands

A resource specialist may be requested by the Owner to remain on the site until additional soil disturbance in the remainder of that area is completed, in order to monitor whether additional incidences are possible. Mitigation measures (avoiding, relocating the specimen) can be implemented proactively if complete avoidance is not possible. Monitor the success of protection or relocation measures during post-construction monitoring, as required.

  ●    Valard EMS; Adherence to CEPP and DPP

No previously unidentified vegetation features found during 2019 construction activities

Yes

2- 548

548 CEPP Section 7.6 – Contingency Plans – Rare Plant Discovery Contingency Plan – Post-Construction Measures – Owner Measures #13 EA Report – Section 12 – Vegetation and Wetlands

Revegetate with appropriate certified native seed mixes that will maintain habitat quality.   ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include reclamation or restoration activities

Not Started

2- 549

549 CEPP Section 7.6 – Contingency Plans – Rare Plant Discovery Contingency Plan – Incidental Discovery – Contractor Measures #1

CEPP Section 7.6 – Contingency Plans – Rare Plant Discovery Contingency Plan – Contingency Measures – Contractor Measures #2EA Report – Section 12 – Vegetation and Wetlands

In the event that a previously unidentified rare plant species or rare vegetation community is suspected or encountered unexpectedly in the Project Site: IMMEDIATELY HALT WORK IN THAT LOCATION and notify the Owner. Work at that location may not resume until permission is received from the Owner.

  ●    Valard EMS; Adherence to CEPP and DPP; Incident Notification Form

No previously unidentified vegetation features found during 2019 construction activities

Yes

2- 550

550 CEPP Section 7.6 – Contingency Plans – Rare Plant Discovery Contingency Plan – Contingency Measures – Contractor Measures #3

EA Report – Section 12 – Vegetation and Wetlands

Do not disturb the plant or community and temporarily flag off the area around the location to reduce disturbance until proper flags or temporary fences are installed as needed.

  ●    Valard EMS; Adherence to CEPP and DPP

No previously unidentified vegetation features found during 2019 construction activities

Yes

2- 551

551 CEPP Section 7.6 – Contingency Plans – Rare Plant Discovery Contingency Plan – Contingency Measures – Contractor Measures #4

CEPP Section 7.7 – Contingency Plans – Undocumented Water Body Discovery Contingency Plan – Contingency Measures – Contractor Measures #4

CEPP Section 7.8 – Contingency Plans – Indigenous Land and Resource Use Site Contingency Plan – Incidental Discovery – Contractor Measures # 3

EA Report – Section 12 – Vegetation and Wetlands

Follow mitigation measures provided by the Owner.   ●    Valard EMS; Adherence to CEPP and DPP

No previously unidentified vegetation features found during 2019 construction activities

Yes

110 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 552

552 CEPP Section 7.6 – Contingency Plans – Rare Plant Discovery Contingency Plan – Contingency Measures – Contractor Measures #5

EA Report – Section 12 – Vegetation and Wetlands

Use geotextiles/protective matting, and/or snow c o v e Rs during the winter, over the area to protect occurrences from scraping and compacting.

  ●    Valard EMS; Adherence to CEPP and DPP

No previously unidentified vegetation features found during 2019 construction activities

Yes

2- 553

553 CEPP Section 7.6 – Contingency Plans – Rare Plant Discovery Contingency Plan – Contingency Measures – Contractor Measures #6

EA Report – Section 12 – Vegetation and Wetlands

Follow proper soil handling techniques and weed control measures to prevent the introduction of competitive or invasive species.

  ●    Valard EMS; Adherence to CEPP and DPP

No previously unidentified vegetation features found during 2019 construction activities

Yes

2- 554

554 CEPP Section 7.6 – Contingency Plans – Rare Plant Discovery Contingency Plan – Contingency Measures – Contractor Measures #7

EA Report – Section 12 – Vegetation and Wetlands

Restore surface drainage patterns in the vicinity of the rare plant occurrence to pre-construction conditions as much as practicable.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include reclamation or restoration activities

Not Started

2- 555

555 CEPP Section 7.7 – Contingency Plans – Undocumented Water Body Discovery Contingency Plan – Due Diligence – Owner Measures #1

CEPP Section 6.2 – Transmission Line Construction Environmental Protection Measures – Access Roads – Water Body Crossings – Construction Monitoring – Owner Measures #6

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

EA Report – Appendix 1-V-A-2 – MNRF Comments on the Amended EA Report

A reconnaissance for undocumented water bodies in the Project Site will be completed prior to construction of each workfront to document water bodies not included on the water body crossing lists (refer to Appendix 4-II, Appendix I).

●      Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Reconnaissance and seasonal pre-construction environmental surveys and flagging completed for 2019 under guidance of resource specialists; ongoing for remaining Project construction

Yes

2- 556

556 CEPP Section 7.7 – Contingency Plans – Undocumented Water Body Discovery Contingency Plan – Incidental Discovery – Owner Measures #3

EA Report – Section 13 – Fish and Fish Habitat

In the event that a previously undocumented water body is suspected, the Owner may contact a resource specialist to assess the water body.

  ●    Valard EMS; Adherence to CEPP and DPP; Incident Notification Form

No previously undocumented water bodies found during 2019 construction activities

Yes

2- 557 CEPP Section 7.7 – Contingency Plans – Undocumented Water Body Discovery Contingency

Plan – Incidental Discovery – Owner Measures #4

Clearly flag the area around the suspected water body.   ●    Valard EMS; Adherence to CEPP and DPP

No previously undocumented water bodies found during 2019 construction activities

Yes

2- 558

558 CEPP Section 7.7 – Contingency Plans – Undocumented Water Body Discovery Contingency Plan – Incidental Discovery – Owner Measures #5

Suspend activity within 30 m of the location until the resource specialist has assessed the suspected water body and determined a suitable course of action in consultation with the Owner and, if necessary, the appropriate regulatory agencies.

  ●    Valard EMS; Adherence to CEPP and DPP

No previously undocumented water bodies found during 2019 construction activities

Yes

2- 559

559 CEPP Section 7.7 – Contingency Plans – Undocumented Water Body Discovery Contingency Plan – Incidental Discovery – Owner Measures #6

The Owner will document the location, photograph the suspected water body, and report the findings to the appropriate regulatory agencies, as needed.

  ●    Valard EMS; Adherence to CEPP and DPP

No previously undocumented water bodies found during 2019 construction activities

Yes

2- 560

560 CEPP Section 7.7 – Contingency Plans – Undocumented Water Body Discovery Contingency Plan – Contingency Measures – Owner Measures #7

Depending on the nature of the discovery, recommendations for construction methods, appropriate mitigation measures, and permitting requirements will be made by the resource specialist and, if necessary, the appropriate regulatory agencies.

  ●    Valard EMS; Adherence to CEPP and DPP

No previously undocumented water bodies found during 2019 construction activities

Yes

111 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 561

561 CEPP Section 7.7 – Contingency Plans – Undocumented Water Body Discovery Contingency Plan – Contingency Measures – Owner Measures #8

The Owner will obtain the necessary permits prior to construction of each workfront near or in the water body. ●      Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

No previously undocumented water bodies found during 2019 construction activities

Yes

2- 562

562 CEPP Section 7.7 – Contingency Plans – Undocumented Water Body Discovery Contingency Plan – Construction Monitoring – Owner Measures #9

Once a plan is in place for the water body, monitor the crossing construction per Section 6.2.1.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

No previously undocumented water bodies found during 2019 construction activities

Yes

2- 563

563 CEPP Section 7.7 – Contingency Plans – Undocumented Water Body Discovery Contingency Plan – Post-Construction Monitoring – Owner Measures #10

EA Report – Section 13 – Fish and Fish Habitat

Post-construction monitoring/inspections of new permanent water body crossing structures and new roadside drainage features.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include reclamation or restoration activities

Not Started

2- 564

564 CEPP Section 7.7 – Contingency Plans – Undocumented Water Body Discovery Contingency Plan – Post-Construction Monitoring – Owner Measures #11

EA Report – Section 13 – Fish and Fish Habitat

Post-construction monitoring of total suspended solids and streamflow rates to verify the effectiveness of reclamation measures at selected water bodies those with greater sensitivity or implication to change from the standpoint of fish habitat, species at risk, channel stability, drainage pattern, or other environmental considerations. The specific monitoring locations will be determined during the permitting phases of the Project; however, it is expected that water bodies of varying size (small, medium, large) would be captured, recognizing that this would allow the performance/effectiveness of mitigation measures to be evaluated at a range of scales.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include post-construction monitoring activities

Not Started

2- 565

565 CEPP Section 7.7 – Contingency Plans – Undocumented Water Body Discovery Contingency Plan – Incidental Discovery – Contractor Measures #1

In the event that a previously undocumented water body is suspected or encountered in the Project Site: IMMEDIATELY HALT WORK IN THAT LOCATION and notify the Owner.

  ●    Valard EMS; Adherence to CEPP and DPP; Incident Notification Form

No previously undocumented water bodies found during 2019 construction activities

Yes

2- 566

566 CEPP Section 7.7 – Contingency Plans – Undocumented Water Body Discovery Contingency Plan – Contingency Measures – Contractor Measures #3

Temporarily flag off the lag off 30 m-90 m slope dependent vegetation buffer area around the water body to reduce disturbance until proper mitigation measures are implemented as needed.

  ●    Valard EMS; Adherence to CEPP and DPP

No previously undocumented water bodies found during 2019 construction activities

Yes

2- 567

567 CEPP Section 7.8 – Contingency Plans – Indigenous Land and Resource Use Site Contingency Plan – Incidental Discovery – Owner Measures #3

Clearly flag the features associated setback (slope dependent 30-90 metre) around the site to protect the value.   ●    Valard EMS; Adherence to CEPP and DPP; Indigenous monitors on-site during construction

No previously undocumented water bodies found during 2019 construction activities

Yes

2- 568

568 CEPP Section 7.8 – Contingency Plans – Indigenous Land and Resource Use Site Contingency Plan – Incidental Discovery – Owner Measures #4

Suspend activity at that location until the resource specialist has assessed the site and determine a suitable course of action in consultation with the Owner and, if necessary, the appropriate local Indigenous communities and regulators.

  ●    Valard EMS; Adherence to CEPP and DPP; Indigenous monitors on-site during construction, and Ongoing engagement with Indigenous communities

No previously undocumented water bodies found during 2019 construction activities. In January 2020, Pic Mobert First Nation notified NextBridge of the potential for Indigenous land and resource potential in the area of White Lake and Nursery Lake. NextBridge remains engaged with community to ensure proper mitigation plans are in place, in the areas concerned.

Yes

112 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 569

569 CEPP Section 7.8 – Contingency Plans – Indigenous Land and Resource Use Site Contingency Plan – Incidental Discovery – Owner Measures #6

If assessment of the site is deemed necessary, the site will be assessed based on the following criteria:

the location of the site with respect to the Project Site;

the feasibility of alternate routing or siting to avoid the resource; and

input from local Indigenous communities.

  ●    Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table; Indigenous monitors on-site during construction, and ongoing engagement with Indigenous communities

No previously undocumented water bodies found during 2019 construction activities. In January 2020, Pic Mobert First Nation notified NextBridge of the potential for Indigenous land and resource potential in the area of White Lake and Nursery Lake. NextBridge remains engaged with community to ensure proper mitigation plans are in place, in the areas concerned.

Yes

2- 570

570 CEPP Section 7.8 – Contingency Plans – Indigenous Land and Resource Use Site Contingency Plan – Incidental Discovery – Owner Measures #7

Based on site assessment, recommendation will be made in consultation with local Indigenous communities (e.g., moving the resource; documenting, removing and salvaging the resource).

  ●    Valard EMS; Adherence to CEPP and DPP; ongoing engagement with Indigenous communities

No previously undocumented water bodies found during 2019 construction activities. In January 2020, Pic Mobert First Nation notified NextBridge of the potential for Indigenous land and resource potential in the area of White Lake and Nursery Lake. NextBridge remains engaged with community to ensure proper mitigation plans are in place, in the areas concerned.

Yes

2- 571

571 CEPP Section 7.8 – Contingency Plans – Indigenous Land and Resource Use Site Contingency Plan – Incidental Discovery – Owner Measures #8

Protect Indigenous land and resource use sites identified adjacent to the ROW, if deemed appropriate based on the assessment.

  ●    Valard EMS; Adherence to CEPP and DPP; Indigenous monitors on-site during construction, and ongoing engagement with Indigenous communities

No previously undocumented Indigenous land and resource use sites found during 2019 construction activities

Yes

2- 572

572 CEPP Section 7.8 – Contingency Plans – Indigenous Land and Resource Use Site Contingency Plan – Incidental Discovery – Contractor Measures # 2

CEPP Section 7.7 – Contingency Plans – Undocumented Water Body Discovery Contingency Plan – Contingency Measures – Contractor Measures #2

Suspend work immediately in the vicinity of the suspected site. Work at that location may not resume until permission is received from the Owner.

  ●    Valard EMS; Adherence to CEPP and DPP; Indigenous monitors on-site during construction, and ongoing engagement with Indigenous communities

No previously undocumented water bodies or Indigenous land and resource use sites found during 2019 construction activities. In January 2020, Pic Mobert First Nation notified NextBridge of the potential for Indigenous land and resource potential in the area of White Lake and Nursery Lake. NextBridge remains engaged with community to ensure proper mitigation plans are in place, in the areas concerned.

Yes

113 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 573

573 CEPP Section 8.1 – Environmental Management Plans – Erosion and Sedimentation Control Plan

An Erosion and Sedimentation Control Plan will be implemented for the Project to minimize sediment mobilization from disturbed areas and to prevent sediment to reach environmentally sensitive features. This conceptual Erosion and Sedimentation Control Plan outlines control measures to be implemented during construction of the Project.

  ●    Valard EMS; Adherence to CEPP and DPP

Document has been developed.

Yes

2- 574

574 CEPP Section 8.1 – Environmental Management Plans – Erosion and Sedimentation Control Plan

Site-specific Erosion and Sedimentation Control Plans will be developed by the General Contractor (Valard) for review and approval by the Owner prior to construction activities in erosion-prone areas or within environmentally sensitive features that require additional erosion and sedimentation controls.

●      Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 575

575 CEPP Section 8.1 – Environmental Management Plans – Erosion and Sedimentation Control Plan – Erosion and Sedimentation Control Plan – Contractor Measures #1

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 13 – Fish and Fish Habitat

The General Contractor (Valard) may develop site-specific Erosion and Sedimentation Control Plan for review and approval by the Owner, when under wet conditions (e.g. excessive rain, wet weather, or flood-like conditions), saturated soils, or during spring break-up, or where soils prone to erosion are present.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 576

576 CEPP Section 8.1 – Environmental Management Plans – Erosion and Sedimentation Control Plan – Schedule – Contractor Measures #3

When schedule allows, plan construction activities in areas prone to erosion under dry or frozen conditions.   ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 577

577 CEPP Section 8.1 – Environmental Management Plans – Erosion and Sedimentation Control Plan – Equipment – Contractor Measures #5

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

Maintain an adequate supply of erosion and sedimentation control materials on site prior to commencement of construction at site specific locations and train Project personnel on the use of this equipment. Standard erosion and sedimentation control materials that may be kept on site include:

a. silt fencing with stakes or straw bales; b. geotextile fabric, landscape fabric, tarps or similar products for ground cover or stockpiles; c. sand/plastic bags and/or poly rolls (for use in temporary dams, catchment areas or sumps); d. shovels and small sledge hammers; e. certified weed-free seed mix appropriate for the area; and f. pumps, hoses, and other fittings as needed to collect, settle and/or discharge sediment laden water away from

water bodies.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 578

578 CEPP Section 8.1 – Environmental Management Plans – Erosion and Sedimentation Control Plan – Water Bodies – Contractor Measures #7

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Install, monitor and manage appropriate erosion and sedimentation control measures to minimize or avoid sedimentation and suspended sediment mobilization from the disturbed areas to environmentally sensitive features (drainages or water bodies, rare plants, wetlands).

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 579

579 CEPP Section 8.1 – Environmental Management Plans – Erosion and Sedimentation Control Plan – Water Bodies – Contractor Measures #8

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

EA Report – Section 13 – Fish and Fish Habitat

Use biodegradable fabric matting on approach slopes, runoff diversion berms and cross ditches, as required, to stabilize soil for vegetation to establish (refer to Appendix 4-II, Appendix B, Figure B-4).

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 580

580 CEPP Section 8.1 – Environmental Management Plans – Erosion and Sedimentation Control Plan – Temporary Sediment Barriers – Contractor Measures #10

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water EA Report – Section 13 – Fish and Fish Habitat

Install temporary sediment barriers (e.g., berms, silt fences; refer to Appendix 4-II, Appendix B, Figures B-3 and B-4):

installed before the ground is disturbed; at the base of slopes leading to a water body; between the edges of the disturbed area and a water body; at other sloped areas with a water body downslope; at the base of slopes leading to road crossings where vegetation has been disturbed; and at the edge of the ROW as needed to prevent siltation of a water body downslope of the ROW.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 581

581 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan

EA Report – Section 4 – Project Description

Construction waste will be deposited in accordance with applicable legislation and transported by MECP licensed waste haulers to MECP registered disposal sites.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

114 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 582

582 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan

Temporary storage of wastes on site will include the use of secured containers in designated sites away from environmentally sensitive areas.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 583

583 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan

Solid waste will be collected and disposed of appropriately in accordance with applicable regulations in a waste disposal facility.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 584

584 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan

A detailed Waste Management Plan will be developed by the General Contractor (Valard) for review and approval by the Owner prior to arriving at the Project Site.

●      Adherence to Waste Management Plan

Document has been developed.

Yes

2- 585

585 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Regulatory Approval – Owner Measures #2

EA Report – Section 7 – Surface Water

Obtain a Generator Registration Number under O. Reg. 347 of the Environmental Protection Act in the event hazardous wastes will be generated during construction.

  ●    Valard EMS; Adherence to CEPP and DPP

Generator Registration Numbers: ON6162796, ON5949958, ON7966095, ON5303006, ON5527323

Yes

2- 586

586 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Construction Monitoring – Owner Measures #3

EA Report – Section7 – Surface Water

EA Report – Section 14 – Wildlife and Wildlife Habitat

The Environmental Inspector will monitor management and disposal of waste.   ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 587

587 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Regulatory Approval – Contractor Measures #2

EA Report – Section 7 Surface Water

Waste management will be carried out in compliance with the conditions and requirements of regulatory approvals and permits, EASR or ECA under the Environmental Protection Act.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 588

588 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Waste Management Plan – Contractor Measures #3

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

The General Contractor (Valard) will develop a detailed Waste Management Plan for review and approval by the Owner at least 30 days prior to the construction of each workfront that describes the appropriate management of waste, including segregation, storage and handling of:

construction-related garbage, recycle, and other waste (i.e., wood waste);

hazardous materials such as used oil, filter and grease cartridges, lubrication containers, and,

domestic garbage and camp waste (i.e., food and grey water).

●      Waste Management Plan

Document has been developed.

Yes

2- 589

589 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Waste Management Plan – Contractor Measures #4

The Waste Management Plan shall describe the training and awareness requirements necessary for its effective implementation.

●  ●    Waste Management Plan

Appropriate documents have been developed and provided to on-site personnel as necessary.

Yes

2- 590

590 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Waste Management Plan – Contractor Measures #5

The plan shall be periodically reviewed and as necessary updated.   ●    Valard EMS; Adherence to Waste Management Plan

Ongoing In Progress

2- 591

591 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Waste Management – Contractor Measures #8

The General Contractor (Valard) is responsible to coordinate and manage day-to-day responsibilities for waste management and disposal throughout the construction period including appropriate collection, segregation, treatment and transfer of waste.

  ●    Valard EMS; Adherence to Waste Management Plan

Complete for 2019; ongoing for remaining Project construction

Yes

2- 592

592 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Waste Management – Contractor Measures #9

Maintain sufficient resources (e.g., containers, trained personal) to achieve effective implementation of the Waste Management Plan.

  ●    Valard EMS; Adherence to Waste Management Plan

Complete for 2019; ongoing for remaining Project construction

Yes

115 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 593

593 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Waste Management – Contractor Measures #10

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

EA Report – Section 14 – Wildlife and Wildlife Habitat

Collect waste material on a regular basis, or as needed to maintain a neat and clean Project Site.   ●    Valard EMS; Adherence to Waste Management Plan

Complete for 2019; ongoing for remaining Project construction

Yes

2- 594

594 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Waste Management – Contractor Measures #11

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

Designated areas for waste segregation and recycling, with appropriate containers for each type of waste material will be made readily available on the Project Site. Waste will be collected, sorted and segregated on-site for disposal as follows:

hazardous wastes: petroleum products, fuels, solvents, coolants, etc.;

construction materials: wood, tires, etc.;

recyclable wastes: aluminum, steel, etc.;

domestic solid waste: non-recyclable waste, food waste; and

E-waste: computers, batteries.

  ●    Valard EMS; Adherence to Waste Management Plan

Complete for 2019; ongoing for remaining Project construction

Yes

2- 595

595 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Waste Management – Contractor Measures #12

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

Temporarily store inert wastes (e.g., scrap steel, wood) in designated staging area until disposal to an approved waste disposal facility occurs.

  ●    Valard EMS; Adherence to Waste Management Plan

Complete for 2019; ongoing for remaining Project construction

Yes

2- 596

596 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Waste Management – Contractor Measures #13

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

EA Report – Section 14 – Wildlife and Wildlife Habitat

Dumping or burying of garbage, non-wood construction wastes, food wrappings, bottles/cans, sanitary wastes or other non-wood materials is strictly prohibited.

  ●    Valard EMS; Adherence to Waste Management Plan

Complete for 2019; ongoing for remaining Project construction

Yes

2- 597

597 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Waste Management – Contractor Measures #14

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

EA Report – Section 14 – Wildlife and Wildlife Habitat

Dispose of waste material on a regular basis at appropriate and approved waste disposal facility.   ●    Valard EMS; Adherence to Waste Management Plan

Complete for 2019; ongoing for remaining Project construction

Yes

2- 598

598 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Waste Management – Contractor Measures #15

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

Wastes will be hauled by either a local waste management contractor or appropriately trained/certified Project personnel.

  ●    Valard EMS; Adherence to Waste Management Plan

Complete for 2019; ongoing for remaining Project construction

Yes

2- 599

599 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Hazardous Wastes – Contractor Measures #17

EA Report – Section 7 – Surface Water

Hazardous wastes will be stored in appropriate containers that meet that following criteria:

good condition with no visible defects that could result in leaking or spilling of by-products; leak-resistant and include seals containing liquid by-products; removable tops if storing non-liquid by-products; kept upright and closed at all times unless adding or removing contents; clearly labeled containers according to Workplace Hazardous Materials Information System (WHMIS) regulations and with the following information: “Hazardous By-Product” or “Used Oil For Recycle”;

• name of the by-product (e.g., Used Oil);

• type of hazard (e.g., toxic, ignitable); and

• the date the container was placed in the storage area.

  ●    Valard EMS; Adherence to Waste Management Plan

Complete for 2019; ongoing for remaining Project construction

Yes

2- 600

600 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Hazardous Wastes – Contractor Measures #18

EA Report – Section 7 – Surface Water

Hazardous wastes and used oil containers will be stored in designated areas to optimize control and ensure non-compatible by-products are segregated. Designate areas will be:

located on level ground away from environmentally sensitive features; located at minimum 100 m away from permanent water features and other environmentally sensitive features; and label and/or install signs to ensure proper segregation

  ●    Valard EMS; Adherence to Waste Management Plan

Complete for 2019; ongoing for remaining Project construction

Yes

116 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 601

601 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Hazardous Wastes – Contractor Measures #19

EA Report – Section 7 – Surface Water

Waste containers will be visually inspected on a regular basis to ensure that they do not leak, sealed with a properly fitting lid, and labelled accordingly. Identified problems or deficiencies shall be corrected in a timely manner.

  ●    Valard EMS; Adherence to Waste Management Plan

Complete for 2019; ongoing for remaining Project construction

Yes

2- 602

602 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Sanitary and Liquid Waste – Contractor Measures #20

Sanitary and liquid waste will be held and discharged according to required permits and authorizations for construction and operation of grey water treatment.

  ●    Valard EMS; Adherence to Waste Management Plan

Complete for 2019; ongoing for remaining Project construction

Yes

2- 603

603 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Sanitary and Liquid Waste – Contractor Measures #21

Do not discharge sanitary wastes into water body or on the soil surface.   ●    Valard EMS; Adherence to Waste Management Plan

Complete for 2019; ongoing for remaining Project construction

Yes

2- 604

604 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Sanitary and Liquid Waste – Contractor Measures #22

Equip all temporary toilets with approved septic tanks with closed holding tanks that are emptied only into approved treatment plants or sewage tanker trucks.

  ●    Valard EMS; Adherence to Waste Management Plan

Complete for 2019; ongoing for remaining Project construction

Yes

2- 605

605 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Sanitary and Liquid Waste – Contractor Measures #23

Locate on-site temporary toilets away from environmentally sensitive features and secure them to avoid or minimize damage from vandalism.

  ●    Valard EMS; Adherence to Waste Management Plan; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 606

606 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Sanitary and Liquid Waste – Contractor Measures #24

In the event of a major sewage leak or spill, implement Spill Prevention and Response Contingency Plan (refer to Appendix 4-II, Section 7.1).

  ●    Valard EMS; Adherence to Waste Management Plan

Complete for 2019; ongoing for remaining Project construction

Yes

2- 607

607 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Food Waste and Domestic Garbage – Contractor Measures #25

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

EA Report – Section 14 – Wildlife and Wildlife Habitat

Littering is strictly prohibited.   ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 608

608 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Food Waste and Domestic Garbage – Contractor Measures #26

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 14 – Wildlife and Wildlife Habitat

Collect, segregate, store and dispose of food waste and domestic garbage on a regular basis, or as needed to reduce potential human/wildlife encounters.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 609

609 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Food Waste and Domestic Garbage – Contractor Measures #27

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 14 – Wildlife and Wildlife Habitat

Implement a recycling program at the construction camps to reduce the amount of waste generated.   ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 610

610 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Food Waste and Domestic Garbage – Contractor Measures #28

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 14 – Wildlife and Wildlife Habitat

Retain food wastes (e.g., lunch wastes, wrappers) and return to appropriate on-site waste containers.   ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

117 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 611

611 CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Food Waste and Domestic Garbage – Contractor Measures #29

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 14 – Wildlife and Wildlife Habitat

Ensure food waste and domestic garbage is stored in designated areas within appropriate wildlife-proof containment to avoid attracting nuisance wildlife.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 612

612 CEPP Section 8.3 – Environmental Management Plans – Blasting Management Plan

A Blasting Management Plan will be implemented for areas where explosives are used to create level areas for transmission structures and roads, and for foundation excavations and where implosions are used to splice the transmission conduction (wire) joints.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include blasting activities

Not Started

2- 613

613 CEPP Section 8.3 – Environmental Management Plans – Blasting Management Plan

A detailed Blasting Management Plan will be developed by the General Contractor (Valard) for review and approval by the Owner prior to blasting and implosion operations.

●      Valard EMS; Adherence to CEPP and DPP

Development of Blasting Management Plan has been completed.

Yes

2- 614

614 CEPP Section 8.3 – Environmental Management Plans – Blasting Management Plan – Regulatory Approval – Owner Measures #1

EA Report – Section 6 – Geology, Terrain and Soils EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 13 – Fish and Fish Habitat

Obtain regulatory approvals as required from applicable regulatory agencies prior to blasting and implosion operations.

●      Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include blasting activities

Not Started

2- 615

615 CEPP Section 8.3 – Blasting Management Plan – Regulatory Approval – Owner Measures #2

CEPP Section 8.3 – Blasting Management Plan – Water Bodies – Contractor Measures #12

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 13 – Fish and Fish Habitat

Blasting in a water body will not be permitted unless otherwise approved by the appropriate regulatory agency.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include blasting activities

Not Started

2- 616

616 CEPP Section 8.3 – Environmental Management Plans – Blasting Management Plan – Construction Monitoring – Owner Measures #4

CEPP Section 5.0 – Environmentally Sensitive Features – Environmentally Sensitive Features Protection Measure – Water Wells – Owner Measures #60

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 8 – Groundwater

Conduct a pre-blast survey of identified wells within 250 m of all blast locations by a licensed water well technician in accordance with the Wells Regulation (O. Reg. 903). Where landowner permission is granted, the pre-blast survey will include completion of a well questionnaire to obtain details about the well and measurement of water levels.

●  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include blasting activities

Not Started

2- 617

617 CEPP Section 8.3 – Environmental Management Plans – Blasting Management Plan – Construction Monitoring – Owner Measures #5

EA Report – Section 6 – Geology, Terrain and Soils EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

The Environmental Inspector will monitor blasting operations.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include blasting activities

Not Started

2- 618

618 CEPP Section 8.3 – Environmental Management Plans – Blasting Management Plan – Post-Construction Monitoring – Owner Measures #6

If changes in groundwater quantity are observed during construction, then a post-construction monitoring event should be conducted to confirm that the groundwater quality and/or quantity returns to pre-construction conditions.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include post-construction monitoring activities

Not Started

118 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 619

619 CEPP Section 8.3 – Environmental Management Plans – Blasting Management Plan – Regulatory Approval – Contractor Measures #2

EA Report – Section 4 – Project Description

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater EA Report – Section 13 – Fish and Fish Habitat

Blasting operations will adhere to applicable regulations and guidelines for transportation, handling, storage and use of explosives:

Natural Resources Canada’s permit under the Explosives Act (Government of Canada 1985) for the use, storage, or transportation of explosives;

Ontario Ministry of Labour’s safety regulations per the Occupational Health and Safety Act (Government of Ontario 1990b), including the filing of a notice of Project at least 30 days prior to the start of construction;

NAV Canada’s Land Use Assessment Form per the Land Use Program for blasting operations;

local Municipalities’ Noise Bylaws;

DFO’s Measures to Avoid Causing Harm to Fish and Fish Habitat Including Aquatic Species at Risk (DFO 2016); and

Guidelines for the Use of Explosives in or Near Canadian Fisheries Waters (refer to Appendix 4-II

Appendix H8; Wright and Hopky 1998) for setback distances from fish-bearing water bodies or wetlands).

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include blasting activities

Not Started

2- 620

620 CEPP Section 8.3 – Environmental Management Plans – Blasting Management Plan – Project Orientation – Contractor Measures #3

CEPP Section 8.2 – Environmental Management Plans – Waste Management Plan – Project Orientation – Contractor Measures #6

CEPP Section 8.4 – Environmental Management Plans – Weed Management Plan – Project Orientation – Contractor Measures #1

CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan – Project Orientation – Contractor Measures #4

EA Report – Section 18 – Socio-Economics

During the Project orientation, Project personnel will be made aware of the Project Site rules and environmental management strategies.

●  ●    Valard OEWTL Online Site Orientation

Orientation documents developed and provided to on-site personnel.

Yes

2- 621

621 CEPP Section 8.3 – Environmental Management Plans – Blasting Management Plan – Blasting Management Plan – Contractor Measures #6

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater EA Report – Section 13 – Fish and Fish Habitat

The General Contractor (Valard) will develop a detailed Blasting Management Plan for review and approval by the Owner prior to blasting and implosion operation that describes specific measures that would be implemented if blasting is required. The plan will also include safety and exclusions zones, emergency and response procedures and contact information.

●      Valard EMS; Adherence to CEPP and DPP

Development of Blasting Management Plan has been completed.

Yes

2- 622

622 CEPP Section 8.3 – Environmental Management Plans – Blasting Management Plan – Blasting Operations – Contractor Measures #7

The General Contractor (Valard) is responsible to coordinate and manage the day-to-day responsibilities for blasting operations throughout the construction period.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include blasting activities

Not Started

2- 623

623 CEPP Section 8.3 – Environmental Management Plans – Blasting Management Plan – Blasting Operations – Contractor Measures #8

Maintain sufficient resources to achieve effective implementation of the Blasting Management Plan.   ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include blasting activities

Not Started

2- 624

624 CEPP Section 8.3 – Environmental Management Plans – Blasting Management Plan – Artesian Groundwater – Contractor Measures #10

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 8 – Groundwater

To the extent practicable, blasting will not be conducted in areas of artesian groundwater conditions.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include blasting activities

Not Started

2- 625

625 CEPP Section 8.3 – Environmental Management Plans – Blasting Management Plan – Artesian Groundwater – Contractor Measures #11

EA Report – Section 8 – Groundwater

Where shallow water table or artesian conditions are encountered the General Contractor (Valard) may use a blasting emulsion that is not readily soluble. The explosive emulsion will be pumped into the bottom of the hole and the emulsion allowed to fill upwards towards the surface

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include blasting activities

Not Started

2- 626

626 CEPP Section 8.3 – Environmental Management Plans – Blasting Management Plan – Waste Disposal – Contractor Measures #13

Blast or waste rock will be spread on the ROW or removed from the ROW in accordance with regulatory requirements.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include blasting activities

Not Started

119 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 627

627 CEPP Section 8.3 – Environmental Management Plans – Blasting Management Plan – Reporting – Contractor Measures #14

Following blasting operations, the General Contractor (Valard) may be required to submit documents to the Owner that includes:

a blast loading plan showing the depth of each blast hole;

quantity of explosive in each blast hole;

the uncharged stemming length;

reconciled explosive quantities used versus the designed quantity; and

any variations accounted for.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include blasting activities

Not Started

2- 628

628 CEPP Section 8.3 – Environmental Management Plans – Blasting Management Plan – Environmental Incident – Contractor Measures #15

In the event of an environmental incident, work will be suspended in the vicinity of the incident and the General Contractor (Valard) will report it to the Owner as soon as it is safe to do so. Work will be suspended until a solution that is compliant is established.

  ●    Valard EMS; Adherence to CEPP and DPP; Environmental Incident Notification and Reports

2019 construction activities did not include blasting activities

Not Started

2- 629

629 CEPP Section 8.3 – Environmental Management Plans – Weed Management Plan

EA Report – Section 12 – Vegetation and Wetlands

A Weed Management Plan will be implemented for the Project to minimize the potential project effects related to weeds.

  ●  ●  Valard EMS; Adherence to CEPP and DPP

The Weed Management Plan has been developed, but 2019 construction activities did not include weed management activities

In Progress

2- 630

630 CEPP Section 8.3 – Environmental Management Plans – Weed Management Plan

During the operation phase, a Vegetation Management Program will be implemented with a goal to ensure vegetation does not interfere with the safe and reliable operation and maintenance of the transmission line, or prohibit access to the transmission line structures, with a compatible vegetation (e.g., below 2 m in height) (refer to Appendix 4-III of the amended EA Report).

    ●  Vegetation Management Plan

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 631

631 CEPP Section 8.4 – Environmental Management Plans – Weed Management Plan – Regulatory Approvals – Owner Measures #1

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

The Owner, its authorized representatives, contractor(s), and subcontractors, shall implement appropriate measures to reduce spreading of noxious weeds in accordance with the Weed Control Act

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include weed management activities

Not Started

2- 632

632 CEPP Section 8.4 – Environmental Management Plans – Weed Management Plan – Construction Monitoring – Owner Measures #2

EA Report – Section 6 – Geology, Terrain and Soils EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

The Owner or the Environmental Inspector may inspect equipment and vehicle arriving on Project Site prior to entry.   ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 633

633 CEPP Section 8.4 – Environmental Management Plans – Weed Management Plan – Construction Monitoring – Owner Measures #3

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

The Environmental Inspector will monitor the implementation of the Weed Management Plan and provides recommendations to improve the Weed Management Plan on an ongoing basis.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities were conducted outside the growing season and did not include weed management activities

Not Started

2- 634

634 CEPP Section 8.4 – Environmental Management Plans – Weed Management Plan – Post-Construction Monitoring – Owner Measures #4

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

Weed survey to identify and map occurrence of weed on ROW (on an annual basis for the first year following construction) for species composition and abundance.

  ●  ●  Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include weed survey activities

Not Started

120 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 635

635 CEPP Section 8.4 – Environmental Management Plans – Weed Management Plan – Project Orientation – Contractor Measures #2 OEMP Section 5.1 – General Mitigation Measures – Noxious Weeds

Project personnel will also be reminded that all vehicles and equipment must be clean (i.e., free of soil and vegetative debris) in accordance with the Clean Equipment Protocol for Industry (refer to Appendix 4-II, Appendix H1; Halloran et al. 2013) prior to Project Site entry, and of the importance of maintaining clean equipment, and minimizing transportation of weed seeds.

  ●  ●  Valard OEWTL Online Site Orientation; Adherence to CEPP and DPP; Valard POD and Tailboards

Complete for 2019; ongoing for remaining Project construction

Yes

2- 636

636 CEPP Section 8.4 – Environmental Management Plans – Weed Management Plan – Weed Management – Contractor Measures #3

The General Contractor (Valard) will be responsible to coordinate and manage day-to-day responsibilities for weed control and management throughout the construction period including identify weed infestations on the Project Site, keep records and document the data.

  ●    Valard EMS; Adherence to CEPP and DPP; Valard POD and Tailboards

2019 construction activities were conducted outside the growing season and did not include weed management activities

Not Started

2- 637

637 CEPP Section 8.4 – Environmental Management Plans – Weed Management Plan – Weed Management – Contractor Measures #4

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

Weed control measures options are subject to agreements with landowners, or other third parties.   ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities were conducted outside the growing season and did not include weed management activities

Not Started

2- 638

638 CEPP Section 8.4 – Environmental Management Plans – Weed Management Plan – Weed Management – Contractor Measures #5

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

In the event that a species of weed becomes problematic to control and management, a site-specific Weed Management Plan will be developed and implemented in order to remove the population, or if that is not possible, minimize any further spread and impacts of the population.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities were conducted outside the growing season and did not include weed management activities

Not Started

2- 639

639 CEPP Section 8.4 – Environmental Management Plans – Weed Management Plan – Weed Management – Contractor Measures #6

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

The General Contractor (Valard) may contact a local resource specialist (e.g., Weed Inspector or Agriculture Information Center) for assistance.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities were conducted outside the growing season and did not include weed management activities

Not Started

2- 640

640 CEPP Section 8.4 – Environmental Management Plans – Weed Management Plan – Equipment and Materials – Contractor Measures #8

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Construction equipment, including vehicles and rig mats, will arrive on the Project Site clean (i.e., free of soil and vegetative debris) in accordance with the Clean Equipment Protocol for Industry (refer to Appendix 4-II, Appendix H1; Halloran et al. 2013).

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 641

641 CEPP Section 8.4 – Environmental Management Plans – Weed Management Plan – Equipment and Materials – Contractor Measures #9

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Any equipment, which arrives in a dirty condition, will not be allowed on the Project Site until the equipment has been cleaned either by hand (track shovel), high pressure water, or compressed air in a controlled, clean environment as to prevent the spread of weeds and invasive species.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 642

642 CEPP Section 8.4 – Environmental Management Plans – Weed Management Plan – Equipment and Materials – Contractor Measures #10

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

Clean construction equipment in accordance with the Clean Equipment Protocol for Industry (refer to Appendix 4-II, Appendix H1; Halloran et al. 2013) prior to constructing water body crossings.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

121 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 643

643 CEPP Section 8.4 – Environmental Management Plans – Weed Management Plan – Equipment and Materials – Contractor Measures #11

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Re-clean vehicles and equipment if an area of weed infestation is encountered on the Project Site prior to advancing to a weed-free area.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities were conducted outside the growing season and did not include weed management activities

Not Started

2- 644

644 CEPP Section 8.4 – Environmental Management Plans – Weed Management Plan – Equipment and Materials – Contractor Measures #12

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

Cleaning stations may be implemented along the Project.   ●    Valard EMS; Adherence to CEPP and DPP

No cleaning stations were implemented on the Project footprint in 2019

Not Started

2- 645

645 CEPP Section 8.4 – Environmental Management Plans – Weed Management Plan – Seeding and Revegetation – Contractor Measures #13

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Use certified native seed mix as required for site revegetation and provide the analysis certificate to the Owner.   ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include revegetation activities

Not Started

2- 646

646 CEPP Section 8.4 – Environmental Management Plans – Weed Management Plan – Construction Monitoring – Contractor Measures #16 EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife

Habitat

The General Contractor (Valard) will monitor and manage weed infestations on a regular and ongoing basis along the ROW and on topsoil stockpiles to determine need for additional weed control measures.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities were conducted outside the growing season and did not include weed management activities

Not Started

2- 647

647 CEPP Section 8.4 – Environmental Management Plans – Weed Management Plan – Reporting – Contractor Measures #17

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

Keep records of cleaning locations.   ●    Valard EMS; Adherence to CEPP and DPP

No cleaning stations were implemented on the Project footprint in 2019

Not Started

2- 648

648 CEPP Section 8.4 – Environmental Management Plans – Weed Management Plan – Reporting – Contractor Measures #18

The General Contractor (Valard) may be required to submit an annual report to the Owner that includes:

summary and mapping of any weed infestations including species, location, density and area;

management strategy implemented to manage and control the infestations;

assessment of the success (or failure) of the management strategy;

discussion of how to improve weed management plan in subsequent years; and

assessment of any changes that may be required in order to ensure weeds are quickly detected and removed.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities were conducted outside the growing season and did not include weed management activities

Not Started

2- 649

649 CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan

A Traffic Management Plan will be implemented to minimize potential effects related to traffic associated with construction of the Project.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

Follow Valard SOP Traffic Accommodation Plan and Highway Corridor Management Permit Conditions

Yes

122 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 650

650 CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan

Vehicles will use provincial numbered highways and local roads to access the Project Site. Vehicles will travel along designated off-ROW access roads and along the ROW to access laydown yards used for tower assembly.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

2019 construction activities utilized approved access based on authorizations, agreements and permits

Yes

2- 651

651 CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan – Regulatory Approvals – Owner Measures #1

File a notice of Project at least 30 days prior to the start of construction with Ontario Ministry of Labour’s safety regulations per the Occupational Health and Safety Act (Government of Ontario 1990b).

●      Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

Complete for 2019; ongoing for remaining Project construction

Yes

2- 652

652 CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan – Regulatory Approvals – Owner Measures #2

Obtain entrance permits for proposed entrances, including temporary entrances to construct or service a proposed development, onto provincial highways per the Public Transportation and Highway Improvement Act, 1990.

●      Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

2019 construction activities occurred with the required entrance permits in place

Yes

2- 653

653 CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan – Regulatory Approvals – Owner Measures #3

Obtain encroachment permits to place, alter, or erect any power line, pole line, or other transmission line within a highway corridor per the Public Transportation and Highway Improvement Act.

●      Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

2019 construction activities occurred with the required encroachment permits in place

Yes

2- 654

654 CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan – Construction Monitoring – Owner Measures #5

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

The Owner will conduct visual inspection of the construction area and Project access roads to monitor adherence to traffic protocols and speed limits by all Project personnel.

  ●    Valard EMS; Adherence to the CEPP, DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 655

655 CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan – Construction Monitoring – Owner Measures #6

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

A Safety Manager may be designated to monitor traffic safety for the Project Site.   ●    Valard EMS; Adherence to the CEPP, DPP,

Complete for 2019; ongoing for remaining Project construction

Yes

2- 656

656 CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan – Regulatory Approval – Contractor Measures #1

Obtain permits for road signage within 400 m of any limit of a provincial highway per the Public Transportation and Highway Improvement Act, 1990.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified in applicable permits and authorizations

No permits required per correspondence with MTO, compliance with Project Traffic Management Plan

Yes

123 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 657

657 CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan – Regulatory Approval – Contractor Measures #2

Obtain oversize/overweight permits for the transportation of overweight vehicles and loads on provincial highways under the Highway Traffic Act.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified in applicable permits and authorizations

Complete for 2019; ongoing for remaining Project construction

Yes

2- 658

658 CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan – Regulatory Approval – Contractor Measures #3

EA Report – Section 18 – Socio-Economics

Project traffic will follow the conditions and requirements of regulatory approvals and permits.   ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

Complete for 2019; ongoing for remaining Project construction

Yes

2- 659

659 CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan – Traffic Management – Contractor Measures #5

The General Contractor (Valard) will be responsible to coordinate and manage day-to-day responsibilities for traffic management throughout the construction period including safe movement of vehicles and equipment to, within and from the Project Site.

  ●    Valard EMS; Valard POD and Tailboards

Complete for 2019; ongoing for remaining Project construction

Yes

2- 660

660 CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan – Traffic Management – Contractor Measures #6

The Project Site will be surveyed and marked prior to the start of clearing activities of each workfront to establish the Project Site.

  ●    Valard EMS; Adherence to the CEPP, DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 661

661 CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan – Traffic Management – Contractor Measures #9

All existing trails or ROW will remain clear of vehicles and debris.   ●    Valard EMS; Adherence to the CEPP, DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 662

662 CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan – Transportation, Storage, and Handling – Contractor Measures #15

EA Report – Section 12 – Vegetation and Wetlands

Fuel and hazardous materials will be transported in approved containers in licensed vehicles.   ●    Valard EMS; Adherence to the CEPP, DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 663

663 CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan – Transportation, Storage, and Handling – Contractor Measures #17

Materials, equipment and vehicles necessary for the Project construction are stored or parked only in designated areas.

  ●    Valard EMS; Adherence to the CEPP, DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 664

664 CEPP Section 8.5 – Environmental Management Plans – Traffic Management Plan – Water Bodies – Contractor Measures #24

CEPP Section 6.1 – Transmission Line Construction Environmental Protection Measures – Site Preparation – Water Bodies – Contractor Measures #23

OEMP Section 5.2 – Access and Travel on Right-of-Way – Water Bodies

OEMP Section 5.3 – Vegetation Management Program – Water Bodies

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Travel in the 30m - 90m slope dependent vegetation buffer at water body crossing locations will be perpendicular to the water body.

  ●  ●  Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

124 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 665

665 CEPP Appendix G – Nest Sweep Protocol Nest sweeps are to be conducted by a qualified Avian Biologist or trained Environment Inspector under appropriate conditions, following protocols that have been designed to identify active nests, singing males and/or other behaviour indicative of a breeding territory/active nest (i.e., alarm calls, distraction displays or adults carrying nesting materials/food) (Environment Canada 2014).

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities were conducted outside the bird nesting period

Not Started

2- 666

666 CEPP Appendix G – Nest Sweep Protocol Nest sweeps for the Project will be conducted, when required, in wetlands between April 15 and August 31. These windows indicate when 90% of the nesting activity is likely to occur.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities were conducted outside the bird nesting period

Not Started

2- 667

667 CEPP Appendix G – Nest Sweep Protocol Nest sweeps will be conducted a maximum of 7 calendar days prior to the commencement of clearing, construction or reclamation activities for appropriate habitats and level of habitat disturbance activities. Once site preparation (e.g., grading) has commenced, no additional nest sweeps are required within that portion of the construction site.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities were conducted outside the bird nesting period

Not Started

2- 668

668 CEPP Appendix G – Nest Sweep Protocol Nest sweeps, when required, will be conducted on lands identified as having wildlife habitat potential (e.g., treed areas, riparian areas, shrub and tame pasture).

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities were conducted outside the bird nesting period

Not Started

2- 669

669 CEPP Appendix G – Nest Sweep Protocol The area that is covered by the nest sweep will be dependent upon land use, existing disturbance in the vicinity of the ROW, the level of construction activity and the potential for species presence and historical occurrences of species o f concern. On lands determined to have high potential for breeding and nesting migratory birds (e.g., where the ROW has not been pre-cleared), the Project Site as well as the appropriate setback restricted activity buffer on either side will be surveyed for active nests.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities were conducted outside the bird nesting period

Not Started

2- 670

670 CEPP Appendix G – Nest Sweep Protocol All nest sweeps completed for the Owner will adhere, at minimum, to the following protocol:

Surveyor(s) will walk along the Project Site in a systematic manner to cover as much ground as practicable in an efficient manner. As the surveyor is walking the construction ROW, the surveyor will stop regularly to look

for behavioural clues to the presence of nesting birds (e.g., presence of territorial males, distraction displays, alarm calls and adults carrying nesting material/food); and listen for the audio calls of birds within the search area.

Wetlands/water bodies within 100 m of the Project Site will be searched for breeding waterfowl and waterbirds. The entire outer boundary of the wetland/water body will be searched, where land access is available, the size of the wetland/water body is such that activity at one end will not affect breeding or nesting behavior at the other end

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities were conducted outside the bird nesting period

Not Started

2- 671

671 CEPP Appendix G – Nest Sweep Protocol In the event that an active nest is found, appropriate mitigation will be implemented based on Environment and Climate Change Canada’s Risk Factors for Migratory Birds.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities were conducted outside the bird nesting period

Not Started

2- 672

672 CEPP Appendix G – Nest Sweep Protocol A risk-based assessment will be completed for each active nest discovered and the mitigation measures will be determined based on the status of the bird, land use, the current level of disturbance or barriers to disturbance (i.e., roads, facilities, highways and farming activities), the construction activity taking place, the sensitivity of the bird to disturbance and the order of bird nesting.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities were conducted outside the bird nesting period

Not Started

125 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 673

673 CEPP Appendix G – Nest Sweep Protocol If a bird species with special conservation status with a federally or provincially recommended setback distance is found, a setback distance will be applied around the nest based on site-specific risk factors.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities were conducted outside the bird nesting period

Not Started

2- 674

674 CEPP Appendix G – Nest Sweep Protocol In the event that an active nest is found on the Project Site or within the search area, the following will be recorded:

adult birds flushing from nest;

species of bird (if identified) or order of the bird and any additional information about the adult bird;

distance to the applicable Project component;

the stage of development (i.e., construction stage, eggs, including number, hatchlings, almost fledged);

UTM coordinates;

photographs; and

any additional wildlife features (e.g., leks, dens, breeding ponds and hibernaculum) that are found will also be photographed and documented.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities were conducted outside the bird nesting period

Not Started

2- 675

675 CEPP Appendix G – Nest Sweep Protocol Any nest found will be protected with a buffer zone determined by a setback distance appropriate to the species, the intensity of disturbance and the surrounding habitat until the young have naturally and permanently left the vicinity of the nest. Any implemented protective buffers will remain in place until the nest is revisited and deemed inactive.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities were conducted outside the bird nesting period

Not Started

2- 676

676 CEPP Appendix G – Nest Sweep Protocol To minimize the risk of nest abandonment or failure, or to increase the risk of predation, nest checks should be timed no less than 3 calendar days apart.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities were conducted outside the bird nesting period

Not Started

2- 677

677 CEPP Appendix G – Nest Sweep Protocol If the nest is found to no longer be active within the migratory bird nesting period, a second nest sweep of the area within the restricted activity buffer will be conducted to identify any other potential nests or key wildlife features.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities were conducted outside the bird nesting period

Not Started

2- 678

678 CEPP Appendix G – Nest Sweep Protocol In addition, any nests or key wildlife features for species with special conservation status (e.g., leks, dens, breeding ponds and hibernacula) that are observed in the vicinity of the construction ROW during the nest sweep will be recorded.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities were conducted outside the bird nesting period

Not Started

2- 679

679 CEPP Appendix G – Nest Sweep Protocol Site-specific mitigation recommendations will be provided based on the biology of the species observed, the location in relation to the Project Site, relevant mitigating factors (e.g., existing industrial disturbance), the scope of the activities to be performed and professional knowledge.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities were conducted outside the bird nesting period

Not Started

2- 680

680 CEPP Appendix G – Nest Sweep Protocol All nests or key wildlife features found will be reported daily to the Owner, along with details on the site-specific restricted activity buffer and/or other additional site-specific mitigation or information.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities were conducted outside the bird nesting period

Not Started

126 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 681

681 OEMP Section 1.1 – Introduction – Scope of Operation Environmental Management Plan

Upon commissioning, the Project will operate on a continuous basis and will be maintained by NextBridge Infrastructure LP (NextBridge).

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 682

682 OEMP Section 1.1 – Introduction – Scope of Operation Environmental Management Plan

EA Report – Section 4 – Project Description

Electricity being transmitted will be monitored and managed by NextBridge’s Control Centre using a Supervisory Control and Data Acquisition (SCADA) or Operational Data System.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 683

683 OEMP Section 1.1 – Introduction – Scope of Operation Environmental Management Plan

As the EA review and environmental permitting processes are ongoing, it is anticipated that additional mitigation, commitments or conditions may be identified in consultation with regulators, Indigenous communities, and stakeholders. As such, it is anticipated that this OEMP will be updated with the following as required:

Commitments and approval conditions arising from the EA review process;

provincial and federal environmental permitting commitments and conditions; or,

applicable updates to provincial and federal environmental regulatory requirements between construction start and the start of Project operation

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 684

684 OEMP Section 1.1 – Introduction – Scope of Operation Environmental Management Plan

The transmission line will be inspected on a semi-annual to annual basis for signs of physical damage (e.g., broken or missing insulators), loose or eroded parts (e.g., bolts), and condition of the conductors (e.g., frayed or areas of reduced clearance).

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2-

685

685 OEMP Section 1.1 – Introduction – Scope of Operation Environmental Management Plan

The transmission line ROW will be patrolled once each year to identify damaged infrastructure (water crossings and road washouts) as well as vegetation which could pose a risk to the transmission line.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 686

686 OEMP Section 1.1 – Introduction – Scope of Operation Environmental Management Plan

Annual patrols will ensure that vegetation that could grow into or fall into the transmission line are identified and removed before they could cause a potential power outage. These inspections will be done from the air or by ground access using the ROW and permanent access roads.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 687

687 OEMP Section 1.1 – Introduction – Scope of Operation Environmental Management Plan

Information collected throughout the implementation of this OEMP will be used to evaluate predictions made in the environmental assessment of the Project and allow NextBridge to make corrective plans and take corrective actions where necessary. Therefore, the OEMP is a ‘live’ document and will be updated as the Project progresses.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 688

688 OEMP Section 2 – Environmental Regulations and Requirements

A preliminary list of relevant environmental regulations and requirements applicable to the Project operation phase is provided in Table 4-III-1. This list will be updated when there are additional requirements identified from the regulatory consultation and review process.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 689

689 OEMP Section 3 – Roles and Responsibilities The Area Operations Lead (refer to Appendix 4-II, Appendix A for contact information) will be responsible for implementation of all aspects of the OEMP. This position is responsible for providing the resources necessary to complete the required tasks and in a manner consistent with this OEMP

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 690

690 OEMP Section 4.1 – Environmental Compliance – Approvals, Permits and Licenses for Operations

Any permits required during operation activities will be appended in this OEMP. All designated NextBridge personnel shall review and clearly understand the conditions relating to operation activities that are attached to the permit documents. The required additional approvals will be confirmed as Project planning and design progress.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

127 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 691

691 OEMP Section 4.2 – Environmental Compliance – Environmental Inspection

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 8 – Groundwater

EA Report – Section 7 – Surface Water

EA Report – Section 11 – Acoustic Environment EA

Report – Section 12 – Vegetation and Wetlands EA

Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources

EA Report – Section 19 – Non-Traditional Land and Resource Use

EA Report – Section 20 – Visual Environment

EA Report – Section 21 – Human Health

NextBridge will oversee implementation of the environmental management measures described in the OEMP during operation and maintenance.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 692

692 OEMP Section 4.2 – Environmental Compliance – Compliance Reporting

Permits typically require submission of compliance reports at specified intervals during the life of the Project. These records will be retained with other appropriate Project documentation in Project files.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 693

693 OEMP Section 4.2 – Environmental Compliance – Compliance Reporting

A compliance self-assessment will be carried out to document compliance with the commitments made in the amended EA Report for the Project, including implementation of mitigation (impact management measures) and conditions of approval. The MECP will be updated regarding compliance at regular intervals during operation, depending on the monitoring reporting requirements specified in approval conditions

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 694

694 OEMP Section 5 – Environmental Management During Operation

Upon commissioning, the Project will operate on a continuous basis and will be maintained by NextBridge.     ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 695

695 OEMP Section 5 – Environmental Management During Operation

Maintenance activities will include regular inspection of the transmission line and associated infrastructure, and vegetation management along the ROW.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 696

696 OEMP Section 5 – Environmental Management During Operation

Operation and maintenance activities will be conducted in accordance with permits and regulations.     ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 697

697 OEMP Section 5 – Environmental Management During Operation

The maintenance inspections may indicate that repairs may be required that could involve the replacement of insulators, anchors, or guy wires, requiring the use of heavier equipment such as backhoes or cranes. NextBridge will attempt to fix identified issues during maintenance inspections but return trips may be required.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 698

698 OEMP Section 5 – Environmental Management During Operation

Emergency repairs will be carried out in a time sensitive manner.     ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

128 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 699

699 OEMP Section 5 – Environmental Management During Operation

Spare parts and poles will be stored in a storage yard or warehouse in proximity to the transmission line in case emergency repairs are required. The quantity of this material and storage location will be determined by NextBridge

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 700

700 OEMP Section 5 – Environmental Management During Operation

NextBridge anticipates the permanent access roads and ROW will be sufficient access to maintain and operate the Project. If there is a maintenance or emergency response activity that requires additional access or additional permitting requirements, NextBridge will identify these requirements and consult with the appropriate regulatory authorities and relevant stakeholders (e.g., landowners of private land), as required.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 701

701 OEMP Section 5.1 – General Mitigation Measures – Regulatory Approvals and Notifications

Acquire applicable local, municipal, provincial and federal licenses, permits and approvals for operation and maintenance, and adhere to applicable conditions throughout the lifecycle of the Project.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 702

702 OEMP Section 5.1 – General Mitigation Measures – Regulatory Approvals and Notifications

Notify applicable federal and provincial regulatory agencies, interested municipal officials and relevant stakeholders (e.g., landowners of private land) of maintenance activities as warranted.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 703

703 OEMP Section 5.1 – Environmental Management During Operation – General Mitigation Measures – Wildlife and Wildlife Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Contractors will report issues and incidents with wildlife or nuisance wildlife as soon as it is safe to do so to NextBridge, who shall determine corrective and/or emergency action to be taken in the field. NextBridge will determine what regulatory reporting is required.

    ●  Adherence to OEMP

Ongoing In Progress

2- 704

704 OEMP Section 5.1 – Environmental Management During Operation – General Mitigation Measures – Wildlife and Wildlife Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Hunting and fishing on the Project footprint by Project personnel is prohibited.     ●  Adherence to OEMP

Ongoing In Progress

2- 705

705 OEMP Section 5.1 – Environmental Management During Operation – General Mitigation Measures – Wildlife and Wildlife Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Vehicles will not exceed speed limits established for the Project footprint.     ●  Adherence to OEMP

Ongoing In Progress

2- 706

706 OEMP Section 5.1 –General Mitigation Measures – Water Bodies

OEMP Section 5.2 – Access and Travel on Right-of-Way – Water Bodies

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Follow applicable measures from MNRF’s Environmental Guidelines for Access Roads and Water Crossings (MNR 1990), Forest Management Guide for Conserving Biodiversity at the Stand and Site Scales (MNR 2010a) and its associated Background Rationale document (MNR 2010b).

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

129 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 707

707 OEMP Section 5.1 –General Mitigation Measures – Water Bodies

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes EA Report – Section 19 – Non-Traditional Land and Resource Use

Periodically (e.g., before and/or after spring freshet) inspect and maintain culverts to prevent blockages from forming and causing ponding or backwater effects. Where culverts are installed at fish bearing water bodies, debris removal activities will follow DFO’s guidance (i.e., gradual removal such that flooding downstream, extreme flows downstream, release of suspended sediment, and fish stranding can be avoided).

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 708

708 OEMP Section 5.1 –General Mitigation Measures – Water Bodies

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Re-fueling or equipment maintenance activities are not to occur within 100 m of a water body.     ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 709

709 OEMP Section 5.1 – General Mitigation Measures – Noxious Weeds

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

The Weed Management Plan outlined in the CEPP (refer to Appendix 4-II, Section 8.4) will be implemented, when required.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 710

710 OEMP Section 5.1 – General Mitigation Measures – Noxious Weeds EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

During the Project orientation, Project personnel will be made aware of the weeds management strategies.     ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 711

711 OEMP Section 5.1 – General Mitigation Measures – Noxious Weeds

EA Report – Section 12 – Vegetation and Wetlands

NextBridge may inspect equipment and vehicles prior to Project footprint entry.     ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 712

712 OEMP Section 5.1 – General Mitigation Measures – Erosion and Sedimentation Control

OEMP Section 5.3 – Vegetation Management Program – Erosion and Sedimentation Control

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources

Specific measures such as installing temporary sediment barriers (e.g., berms, silt fences) will be undertaken as required to prevent sediment laden water from entering a water body.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

130 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 713

713 OEMP Section 5.1 – General Mitigation Measures – Erosion and Sedimentation Control

EA Report – Section 2 – Consultation and Engagement

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources

In areas where reseeding is required for erosion control, seeds will be applied in low reseeding rates to encourage the growth of native vegetation.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 714

714 OEMP Section 5.1 – General Mitigation Measures – Spill Prevention

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

NextBridge will adhere to the Spill Prevention and Response Contingency Plan (refer to Appendix 4-II, Appendix C) to prevent spills and/or release.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 715

715 OEMP Section 5.1 – General Mitigation Measures – Spill Prevention

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Equipment for ROW maintenance activities will be routinely inspected for leaks.     ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 716

716 OEMP Section 5.1 – General Mitigation Measures – Spill Prevention

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Equipment is to arrive on site in a clean condition in accordance with the Clean Equipment Protocol for Industry (Halloran et al. 2013) and is to be maintained free of fluid leaks.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

131 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 717

717 OEMP Section 5.1 – General Mitigation Measures – Spill Prevention

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Re-fueling or equipment maintenance activities will follow mitigation measures outlined in the Spill Prevention and Response Contingency Plan (refer to Appendix 4-III, Appendix C).

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 718

718 OEMP Section 5.1 – General Mitigation Measures – Spill Prevention

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

In the event that any spills occur, implement the reporting measures provided in the Spill Prevention and Response Contingency Plan (refer to Appendix 4-II, Appendix C).

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 719

719 OEMP Section 5.1 – General Mitigation Measures – Noise Concerns

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 11 – Acoustic Environment

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Maintenance activities will typically occur during the daytime period from 07:00 to 19:00. In the event maintenance will occur beyond the daytime period, NextBridge will re-evaluate the potential Project-related effects and if required, review mitigation requirements.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 720

720 OEMP Section 5.1 – General Mitigation Measures – Noise Concerns

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 11 – Acoustic Environment

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

Comply with local municipal noise by-laws and the MECP draft guidance (i.e., DRAFT – MOECC Guideline for Assessing Audible Noise from High Voltage Electricity Transmission Lines, 2011).

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 721

721 OEMP Section 5.1 – General Mitigation Measures – Reporting

In addition to annual reports summarizing activities and general findings, technical reports will be prepared at appropriate intervals during the operation and maintenance phase of the Project. These reports will include compilation and analysis of monitoring results during the relevant period, and make recommendations concerning the need for any changes to the mitigation or monitoring approach.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 722

722 OEMP Section 5.2 – Environmental Management During Operation – Access and Travel on Right-of-Way

Access roads required during the operation of the Project will be maintained by NextBridge and used to access the Project area for maintenance purposes, to complete inspections, and for emergency purposes.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 723

723 OEMP Section 5.2 – Environmental Management During Operation – Access and Travel on Right-of-Way

Maintenance associated with these roads will include regular inspections (annually) and vegetation maintenance.     ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

132 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 724

724 OEMP Section 5.2 – Access and Travel on Right-of-Way – Access Management

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Existing roads and trails identified in Access and Construction Environmental Maps will be used.     ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 725

725 OEMP Section 5.2 – Access and Travel on Right-of-Way – Access Management

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

If there is a maintenance or emergency response activity that requires additional access or additional permitting requirements, NextBridge will identify these requirements and consult with the appropriate regulatory authorities, as required.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 726

726 OEMP Section 5.2 – Access and Travel on Right-of-Way – Access Management

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Access roads required during the operation of the Project will be maintained by NextBridge and used to access the Project area for maintenance purposes, to complete inspections, and for emergency purposes.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 727

727 OEMP Section 5.2 – Access and Travel on Right-of-Way – Access Management EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Maintenance associated with these roads will include regular inspections (annually) and vegetation maintenance as per road use agreement.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 728

728 OEMP Section 5.2 – Access and Travel on Right-of-Way – Access Management

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

If the General Contractor (Valard) plans to use salt on access roads constructed, or within the Project footprint, it must prepare, and submit for approval to NextBridge, a Salt Management Plan. The Salt Management Plan should consider Industry Best Management Practices for road salt management.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 729

729 OEMP Section 5.2 – Access and Travel on Right-of-Way – Vehicles and Equipment

OEMP Section 5.3 – Vegetation Management Program – Noxious Weeds

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

The Weed Management Plan outlined in the CEPP (refer to Appendix 4-II, Section 8.4) will be implemented, when required.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 730

730 OEMP Section 5.2 – Access and Travel on Right-of-Way – Vehicles and Equipment

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Vehicles will not exceed speed limits established by NextBridge and will lower speeds in specific conditions such as areas of high erosion hazard.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

133 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 731

731 OEMP Section 5.2 – Access and Travel on Right-of-Way – Wildlife and Wildlife Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

NextBridge will post signs warning Project personnel of high use wildlife areas to the extent practicable.     ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 732

732 OEMP Section 5.2 – Access and Travel on Right-of-Way – Wildlife and Wildlife Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

NextBridge will provide the appropriate resource specialist, if required, to assess sensitive features and to inspect or monitor Project activities at or near sensitive areas.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 733

733 OEMP Section 5.2 – Access and Travel on Right-of-Way – Wildlife and Wildlife Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Project personnel will receive wildlife awareness training.     ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2-

734

734 OEMP Section 5.3 – Environmental Management During Operation – Vegetation Management Program

A Transmission Vegetation Management Program (TVMP) is required by North American Electric Reliability Corporation (NERC) Standard FAC-003 for transmission lines operating at 200 kV and higher (NERC 2006).

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2-

735

735 OEMP Section 5.3 – Environmental Management During Operation – Vegetation Management Program

The TVMP will also include vegetation management standards to be implemented with a goal to ensure vegetation does not interfere with the safe and reliable operation and maintenance of the transmission line, or prohibit access to the transmission line structures, with a compatible vegetation height of approximately 2 m or less.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2-

736

736 OEMP Section 5.3 – Environmental Management During Operation – Vegetation Management Program

Vegetation maintenance will be required to ensure worker and public safety.     ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2-

737

737 OEMP Section 5.3 – Environmental Management During Operation – Vegetation Management Program

Vegetation management vehicles can include pickup trucks and other vehicles necessary to perform vegetation management duties adjacent to and in the ROW.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2-

738

738 OEMP Section 5.3 – Environmental Management During Operation – Vegetation Management Program

A summary of anticipated vegetation maintenance activities is provided in Table 4-III-3. Table 4 III-3: Anticipated Vegetation Management Activities

Activity Estimated Frequency

Comprehensive vegetation management (NERC -FAC-003)

Annually by air and ground patrol

ROW inspections Annually by air and ground patrol

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2-

739

739 OEMP Section 5.3 – Environmental Management During Operation – Vegetation Management Program

It is anticipated that vegetation will not be removed in areas where clearance-to-ground levels allow for increased vegetation height (i.e., where the line spans water bodies and in canyons and ravines). 

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

134 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2-

740

740 OEMP Section 5.3 – Environmental Management During Operation – Vegetation Management Program 

Vegetation removal will be required in areas with lower clearance levels as tall-growing vegetation has potential to fall onto the conductors and interfere with electricity transmission.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2-

741

741 OEMP Section 5.3 – Environmental Management During Operation – Vegetation Management Program EA Report – Section 4 – Project Description

Prior to vegetation clearing, conductor-to-ground clearances will be matched with acceptable vegetation retention levels to minimize the amount of clearing required while maintaining appropriate safety margins.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2-

742

742 OEMP Section 5.3 – Environmental Management During Operation – Vegetation Management Program

Maintenance activities associated with vegetation will generally include mechanical, manual, and chemical (herbicide) methods for keeping vegetation at an appropriate height to protect the facility and improve public and worker safety.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2-

743

743 OEMP Section 5.3 – Environmental Management During Operation – Vegetation Management Program

Determination of the method to be used (i.e., mechanical, manual, or chemical) will be based on season (time of year), the type of vegetation, site-specific features (i.e., topography, terrain, sensitivity), cost, aesthetics, and environmental and socio-economic features and in consultation with potentially impacted Indigenous communities.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2-

744

744 OEMP Section 5.3 – Environmental Management During Operation – Vegetation Management Program

Visual ground and aerial patrols will be completed to identify areas that require vegetation clearing, and the schedule will be based on growth cycles, system security, public health/safety, protecting the environment, and maintenance associated with the existing East-West Tie transmission line. Based on the results, spot treatment via ground crews may occur.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2-

745

745 OEMP Section 5.3 – Environmental Management During Operation – Vegetation Management Program EA Report – Section 2 – Consultation and Engagement Summary EA Report – Section 4 – Project Description EA Report – Section 8 – Groundwater EA Report – Section 7 – Surface Water EA Report – Section 12 – Vegetation and Wetlands EA Report – Section 13 – Fish and Fish Habitat EA Report – Section 14 – Wildlife and Wildlife Habitat EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes EA Report – Section 21 – Human Health

No aerial application of herbicides is planned in the preferred route ROW. If herbicide use is necessary, it will be applied on the ground as spot application.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 746

746 OEMP Section 5.3 – Environmental Management During Operation – Vegetation Management Program

EA Report – Section 4 – Project Description EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

Use of herbicides within the 30 m water body buffer will be prohibited unless the herbicide application is conducted b y ground application equipment or otherwise approved by the relevant regulatory agency. If other methods cannot be used within the slope dependent vegetation buffer (30-90 metres) and., only approved herbicides would be used.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 747

747 OEMP Section 5.3 – Environmental Management During Operation – Vegetation Management Program

EA Report – Section 12 – Vegetation and Wetlands

NextBridge will develop and implement a TVMP that is similar to the TVMP developed by NextEra (refer to Appendix 4-II, Appendix D), as required by NERC Standard FAC-003 for transmission lines operating at 200 kV and higher.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

135 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 748

748 OEMP Section 5.3 – Vegetation Management Program – Activity Schedule

EA Report – Section 13 – Fish and Fish Habitat

NextBridge, its authorized representatives, contractor(s), and subcontractors, will adhere to the recommended timing windows and restrictions described in Appendix 4-III, Table 4-III-4.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 749

749 OEMP Section 5.3 – Vegetation Management Program – Activity Schedule

EA Report – Section 13 – Fish and Fish Habitat

Planning of mechanical vegetation management will consider the sensitive wildlife periods described in Appendix 4-III, Table 4-III-4.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 750

750 OEMP Section 5.3 – Vegetation Management Program – Wildlife and Wildlife Habitat

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

In the event that a nest is found, implement the Wildlife Features of Concern Discovery Contingency Plan outlined in the CEPP (refer to the Appendix 4-II, Section 7.5).

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 751

751 OEMP Section 5.3 – Vegetation Management Program – Wildlife and Wildlife Habitat

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Allow compatible vegetation in the ROW to grow back to a maximum height of 2 m to provide cover and reduce line-of-sight for predators.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 752

752 OEMP Section 5.3 – Vegetation Management Program – Wildlife and Wildlife Habitat

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Identify hazard trees that are located off-ROW. Permission will be obtained from the landowner or MNRF to fell hazardous trees.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 753

753 OEMP Section 5.3 – Vegetation Management Program – Clearing Equipment

OEMP Section 5.3 – Vegetation Management Program – Areas with Critical Landform/ Vegetation Association

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 12 – Vegetation and Wetlands

Use clearing equipment that minimizes surface disturbance, soil compaction and topsoil loss (e.g., equipment with low ground pressure tires, or wide track), when working in wet areas, under wet conditions, or during spring break-up).

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 754

754 OEMP Section 5.3 – Vegetation Management Program – Clearing Equipment

OEMP Section 5.3 – Vegetation Management Program – Areas with Critical Landform/ Vegetation Association EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 12 – Vegetation and Wetlands

Clearing may be accomplished by harvesting equipment, mulchers, and hand cutting.      ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

136 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 755

755 OEMP Section 5.3 – Vegetation Management Program – Erosion and Sedimentation Control

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 15 – Archaeological Resources

Mechanical clearing and other equipment activity will be minimized within the 30-90 m vegetation buffer.     ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 756

756 OEMP Section 5.3 – Vegetation Management Program – Areas with Critical Landform/ Vegetation Association

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

EA Report – Section 21 – Human Health

Clear merchantable timber by hand, where required.     ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 757

757 OEMP Section 5.3 – Vegetation Management Program – Areas with Critical Landform/ Vegetation Association

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

EA Report – Section 21 – Human Health

Mechanical clearing and other equipment activity will be minimized and no turning of equipment, or vehicles (i.e., straight in general application, straight out) to the extent practicable.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 758

758 OEMP Section 5.3 – Vegetation Management Program – Areas with Critical Landform/ Vegetation Association

EA Report – Section 2 – Consultation and Engagement Summary EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

EA Report – Section 21 – Human Health

Restrict the general application of herbicide in CLVAs to the extent practicable.     ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 759

759 OEMP Section 5.3 – Vegetation Management Program – Water Bodies

EA Report – Section 2 – Consultation and Engagement Summary EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

Vegetation clearing within the slope dependent vegetation buffer "30m - 90m will be limited to where vegetation may present a health, safety and environmental (HSE) hazard to Project operation and maintenance.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

137 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 760

760 OEMP Section 5.3 – Vegetation Management Program – Water Bodies

EA Report – Section 7 – Surface Water

Multi-stage drainage and sediment controls will be employed at work sites as appropriate.     ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 761

761 OEMP Section 5.3 – Vegetation Management Program – Water Bodies

EA Report – Section 2 – Consultation and Engagement Summary EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

Maintain low vegetation or vegetated ground mat within the 30 m water body buffer to the extent practicable.     ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 762

762 OEMP Section 5.3 – Vegetation Management Program – Noxious Weeds

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 14 – Wildlife and Wildlife Habitat

NextBridge will conduct a weed monitoring program to identify and prioritize weeds for removal.     ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 763

763 OEMP Section 5.3 – Vegetation Management Program – Use of Herbicides

EA Report – Section 2 – Consultation and Engagement Summary EA Report – Section 8 – Groundwater

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 21 – Human Health

Use of herbicides/pesticides will follow requirements under the Ontario Pesticides Act.     ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 764

764 OEMP Section 5.3 – Vegetation Management Program – Use of Herbicides

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 8 – Groundwater

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 21 – Human Health

Necessary permits will be obtained for the application, transportation, storage, and disposal of pesticides. Only herbicide products registered for use in Canada by the Pest Management Regulatory Agency of Health Canada will be used.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 765

765 OEMP Section 5.3 – Vegetation Management Program – Use of Herbicides

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 8 – Groundwater

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes EA Report – Section 21 – Human Health

No herbicides will be used in sensitive areas including reserve lands, protected areas, within slope dependent vegetation buffer" and certain other edible and medicinal plant harvesting areas the communities have identified.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

138 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 766

766 OEMP Section 5.3 – Vegetation Management Program – Use of Herbicides

EA Report – Section 2 – Consultation and Engagement Summary EA Report – Section 8 – Groundwater

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 21 – Human Health

Apply approved herbicides under the direction of a provincially-licensed applicator.     ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 767

767 OEMP Section 5.3 – Vegetation Management Program – Use of Herbicides

OEMP Section 5.3 – Vegetation Management Program – Rare Plants/ Rare Vegetation Communities

OEMP Section 5.3 – Vegetation Management Program – Traditional Use Plant Species

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 8 – Groundwater

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

EA Report – Section 21 – Human Health

Restrict the general application of herbicide near rare plants or rare ecological communities. Spot spraying, wicking, mowing, or hand-picking are acceptable measures for weed control in these areas.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 768

768 OEMP Section 5.3 – Vegetation Management Program – Use of Herbicides

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 8 – Groundwater

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 21 – Human Health

Prohibit the use of herbicides within the "slope dependent vegetation buffer (30m - 90m)". unless the herbicide application is conducted by ground application equipment or otherwise approved by the relevant regulatory agency.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 769

769 OEMP Section 5.3 – Vegetation Management Program – Use of Herbicides

EA Report – Section 2 – Consultation and Engagement Summary EA Report – Section 8 – Groundwater

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 21 – Human Health

Storage, handling and application of herbicide will comply with the Ontario Clean Water Act. Do not use herbicides within 100 m of identified wells.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

139 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 770

770 OEMP Section 5.3 – Vegetation Management Program – Use of Herbicides

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 8 – Groundwater

EA Report – Section 7 – Surface Water

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 21 – Human Health

NextBridge will post on their website (www.nextbridge.ca) relevant information about the application of herbicide (e.g., anticipated dates, areas to be sprayed, sprayed dates) to advise the public of herbicide use along the ROW at least 45 days prior to application.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 771

771 OEMP Section 5.3 – Vegetation Management Program – Use of Herbicides

NextBridge will communicate relevant information about the application of herbicide (e.g., anticipated dates, areas to be sprayed, sprayed dates) to advise the Indigenous communities of herbicide use along the ROW and to allow sufficient time for the Indigenous communities to harvest traditional use plant species at least 45 days in advance of application. If additional time is requested based on consultation with Indigenous communities NextBridge will take all reasonable efforts to accommodate.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 772

772 CEPP Section 6.9 – Project Site Cleanup and Reclamation – Seeding and Revegetation

OEMP Section 5.3 – Vegetation Management Program – Traditional Use Plant Species

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 14 – Wildlife and Wildlife Habitat

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Specific plant and/or material harvesting sites such as blueberry patches identified by First Nation communities will be allowed to naturally revegetate (i.e., will not be removed as incompatible vegetation) in the ROW.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 773

773 OEMP Section 5.4 – Environmental Management During Operation – Emergency Response Plan

An Emergency Response Plan will be developed for the Project operation and maintenance phase and will also include procedures for responding to environmental emergency incidents.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 774

774 OEMP Section 5.4 – Environmental Management During Operation – Emergency Response Plan

Mitigation measures for spill prevention and response to environmental incidences are outlined in Appendix C (refer to Appendix 4-III).

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 775

775 OEMP Section 5.5 – Environmental Management During Operation –Fire Prevention

The transmission line will be maintained in accordance with the Ontario Occupational Health and Safety Act (Government of Ontario 1990b) and other relevant regulations that establish clearances from other man-made and natural structures as well as tree-trimming requirements to reduce/avoid fire hazards.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 776

776 OEMP Section 5.5 – Environmental Management During Operation –Fire Prevention

NextBridge will maintain the transmission line ROW and immediate area in accordance with existing regulations and accepted industry practices that will include identification and abatement of fire hazards.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 777

777 OEMP Section 5.5 – Environmental Management During Operation –Fire Prevention

EA Report – Section 4 – Project Description

EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

Adhere to the Industrial Operations Protocol (MNRF 2015) and provide to MNRF upon request fire prevention and preparedness plans, planned fire preparedness activities and planned modifications and/or mitigation actions.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2-

778

778 OEMP Section 6 – Environmental Training NextBridge will make sure that Project personnel receive environmental orientation in relation to the OEMP.     ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

140 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 779

779 OEMP Section 6 – Environmental Training Project-personnel will be made aware and have an understanding of commitments, their obligations and duties described in this OEMP.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 780

780 OEMP Section 6 – Environmental Training NextBridge will also develop and deliver advanced environmental training to relevant Project personnel (e.g., inspectors, consultants resources specialists, contractors)

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 781

781 OEMP Section 6 – Environmental Training NextBridge will provide orientation on the Environmental Hazard Assessment program (refer to Appendix 4-II, Appendix B).

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 782

782 OEMP Appendix C – Spill Prevention and Response Contingency Plan – Reporting – NextBridge Measures #1

NextBridge will report spills in accordance with the provincial requirements (refer to Table Appendix 4-III, 4-III-C-1).     ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 783

783 OEMP Appendix C – Spill Prevention and Response Contingency Plan – Reporting – NextBridge Measures #2

Releases that require external report include spills that:

cause harm or material discomfort to any person; injure or damages property or animal life; impair the quality of the natural environment air, water or land; cause adverse health effects; present a safety risk; render property, plant or animal life unfit for use; lead to the loss of enjoyment of the normal use of property; or interfere with the normal conduct of business.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 784

784 OEMP Appendix C – Spill Prevention and Response Contingency Plan – Reporting – NextBridge Measures #3

The immediate report must include:

your name and phone number; name of the company or individual responsible for the spill; time and location of the spill; type and quantity of material spilled (if you know); and status of the spill, including actions being taken to control the spill. Information provided to the center will be forwarded to Environment Canada, who will in turn contact DFO

if warranted. The following information will be required during the notification process: your name and phone number; name of the company or individual responsible for the spill; time and location of the spill; type and quantity of material spilled (if you know); and status of the spill, including actions being taken to control the spill.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 785

785 OEMP Appendix C – Spill Prevention and Response Contingency Plan – Transportation, Storage, and Handling – Contractor Measures #10

EA Report – Section 6 – Geology, Terrain and Soils EA Report – Section 12 – Vegetation and Wetlands

EA Report – Section 13 – Fish and Fish Habitat

The transportation, storage, and handling of hazardous materials (e.g., fuel, hydrocarbon, brake fluids) will be in compliance with the Technical Standards and Safety Act (Government of Ontario 2000), the Transportation of Dangerous Good Act, 1992, the National Fire Code (National Fire Code of Canada 2010),, and the Occupational Health and Safety Act (Government of Ontario 1990b).

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 786

786 OEMP Appendix C – Spill Prevention and Response Contingency Plan – Reporting – Contractor Measures #17

Report all spills and releases immediately to NextBridge.     ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 787

787 OEMP Appendix C – Spill Prevention and Response Contingency Plan – Reporting – Contractor Measures #18

Prepare a spill report using the Spill Reporting Form (refer to Appendix 4-II, Appendix E) and submit all spill reports to NextBridge.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

141 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 788

788 OEMP Appendix C – Spill Prevention and Response Contingency Plan – Release – Contractor Measures #24

Restore the areas to the satisfaction of the Area Operations Lead and/or regulatory agencies.     ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 789

789 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will continue to engage with trapper and fur manager groups to keep them informed of the Project and will give them advanced notice of the construction schedule and clearing activities.

●      Valard EMS; Consultation and Engagement Summary Table

Ongoing In Progress

2- 790

790 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge continues to work with MNRF to confirm all Crown interests impacted by the Project, to make sure that appropriate consultation occurs.

●  ●    Valard EMS; Consultation and Engagement Summary Table

Ongoing In Progress

2- 791

791 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will be requesting appropriate land agreements from the railways for the crossing of their infrastructure. Engagement with Canadian Pacific Railway and Canadian National Railway is documented in the Property Owner and Interest Holder Interaction Record (Appendix 2-III-A).

●      Valard EMS; Consultation and Engagement Summary Table

Ongoing In Progress

2- 792

792 EA Report – Section 2 – Consultation and Engagement Summary

Meetings with SFLs have been initiated by the General Contractor (Valard) to discuss overlapping agreements and conditions which will continue through the course of the Project and into construction.

●  ●    Valard EMS; Consultation and Engagement Summary Table

Ongoing In Progress

2- 793

793 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge continues to engage local governments to address new concerns as they arise. ●  ●    Valard EMS; Consultation and Engagement Summary Table

Ongoing In Progress

2- 794

794 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will continue working with potentially affected Indigenous communities, stakeholders, such as landowners and interest holders to keep them informed of proposed tower locations as tower placement work progresses to address concerns related to recreational use and trail access.

●  ●    Valard EMS; Consultation and Engagement Summary Table; Indigenous monitors on-site during construction, ongoing engagement with Indigenous communities

Ongoing In Progress

2- 795

795 EA Report – Section 2 – Consultation and Engagement Summary

Concerns related to visual effects have been and will continue to be investigated on a case by case basis and NextBridge commits to taking reasonable measures to minimize the potential environmental and visual effects of the Project.

●  ●    Valard EMS; Consultation and Engagement Summary Table

Ongoing In Progress

2- 796

796 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge has committed to ongoing consultation with the Ski Club throughout Project development to minimize right-of-way clearing and access disruptions where possible in the area of the Ski Club’s trails.

●  ●    Valard EMS; Consultation and Engagement Summary Table

Ongoing In Progress

2- 797

797 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge is reviewing clearing requirements to minimize the amount of clearing required, while still meeting regulatory requirements and safety clearances. NextBridge will review access and construction plans and consult further with the Ski Club.

●  ●    Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 798

798 EA Report – Section 2 – Consultation and Engagement Summary

Public access will be maintained but may be controlled if required for safety of recreational users. ●  ●    Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 799

799 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will continue to work with land use permit (LUP) holder and the MNRF for use of existing roads within LUP.

●  ●    Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

142 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 800

800 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge and the General Contractor (Valard) will discuss Project access with SFL holders and negotiate Road Use Agreements (refer to Section 19.7.14.1.2 of the Amended EA Report).

●  ●    Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 801

801 EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 19 – Non-Traditional Land and Resource Use

NextBridge has a compensation policy that includes compensation to directly affected mining, aggregate, and unpatented claims. Therefore, directly affected commercial industrial operators who lose access to their businesses (mining claims or aggregate pits) because it falls within the Project footprint will be compensated for lost revenue due to the Project.

  ●    Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 802

802 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will continue to engage with and use best practices to minimize effects to nearby potential claim holders, license holders and other tenure holders to the extent practical.

●  ●    Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 803

803 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will continue to engage with and use best practices to minimize effects to SFL holders and other tenure holders to the extent practical.

●  ●    Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 804

804 EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 19 – Non-Traditional Land and Resource Use

NextBridge and the General Contractor (Valard) will continue engagement with SFL holders to:

review planned harvest allocations from approved Forest Management Plans (FMPs) as they relate to Project construction activities including clearing of the ROW and use of land for temporary Project components such as construction camps and laydown yards;

coordinate harvesting where possible in areas where there is overlap between the Project and planned harvest allocations, including the negotiation of Forest Resource Licenses with the SFL holders and their overlapping licensees in circumstances where NextBridge and its contractors are carrying out clearing activities;

stockpile merchantable timber at landings near the edge of the boundaries in a manner that is accessible to hauling trucks. Timber is not to be piled within the slope dependent vegetation buffer (30m-90m) or wet areas. or other overhead or underground utility or crossing unless specified by SFL holder;

discuss Project access as it relates to planned access road construction and access management strategies (including decommissioning) in approved FMPs to reduce effects to SFL holders and eliminate the need for amendments to forest management plans where possible;

negotiate Road Use Agreements to clarify access road use and management strategies including upgrading, use, maintenance, monitoring, decommissioning and ownership of roads and water crossings; and

identify silviculturally treated areas and negotiate compensation for investments (to Forest Renewal Trust [FRT] or Forestry Futures Trust [FFT]) where required.

●  ●    Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 805

805 EA Report – Section 2 – Consultation and Engagement Summary

. NextBridge will continue to work with LUP holder and the Ministry for use of existing roads within LUP. ●  ●    Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 806

806 EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 19 – Non-Traditional Land and Resource Use

Notify affected parties of the general construction schedule 45 days before the start of construction (e.g., registered trapline holders, and registered Bait Management Areas (BMA) and Bait Harvest Area (BHA) clubs along the route).

●      Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 807

807 EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 19 – Non-Traditional Land and Resource Use

Negotiate with affected BMA license holders and/or the MNRF to develop a mutually agreeable solution to offset any identified access or harvest effects on tenured BMAs (e.g., compensation or relocation of BMAs for affected outfitters and operators).

●      Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

143 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 808

808 EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 19 – Non-Traditional Land and Resource Use

Negotiate with affected baitfish harvesters, to develop a mutually agreeable solution with tenure holders to offset any identified access or harvest effect (e.g., compensation or relocation).

●      Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 809

809 EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

Negotiate with affected registered trapline holders who would no longer are able to trap within the Project Site, or whose trapline areas will be severed or isolated as a result of the Project (e.g., compensation or relocation). Where feasible, coordinate the relocation of traps in advance of construction and maintain ongoing communication with local trapping groups and associations.

●      Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table; Indigenous monitors on-site during construction

Ongoing In Progress

2- 810

810 EA Report – Section 2 – Consultation and Engagement Summary EA Report – Section 4 – Project Description

EA Report – Section 18 – Socio-Economics

To increase visibility and reduce risk of accidents, all guy wires (typically four per guyed structure) will be marked or covered with high-visibility plastic markers (sleeves), from ground level to above the anticipated typical snow depths (i.e., the seasonal high snow embankment), and will comply with applicable codes and standards. This will also help to protect the guy wires at the base of the structures.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include installation activities

Not Started

2- 811

811 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge is committed to engaging with property owners in an open and respectful manner, with a commitment to timely, meaningful and transparent dialogue as it relates to property owner compensation and land rights. For a more detailed response to these comments, refer to Appendix 1-IV-C of the amended EA Report.

●  ●  ● Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 812

812 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will continue to engage stakeholders and other interested parties through regular, transparent, and open communication.

●  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 813

813 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge is planning to continue outreach activities through the Amended EA Report review period and the construction and operation phases of the Project. Additional outreach is expected to include pre-construction open houses or suitable engagement events approximately four to six weeks in advance of construction. Specific timing and nature of the engagement events will be influenced by timing of EA and LTC approvals.

●  ●    Consultation and Engagement Summary Table

Ongoing In Progress

2- 814

814 EA Report – Section 2 – Consultation and Engagement Summary

Information and feedback collected during pre-construction engagement events will be used to plan and help mitigate local Project construction and operational effects and continued engagement with stakeholders in relation to the Project.

●  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 815

815 EA Report – Section 2 – Consultation and Engagement Summary

The relationship between NextBridge and property owners and interest holders will continue through Project development activities, construction, and operation, by way of the ongoing personal, one-window contact provided by land agents.

●  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 816

816 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will continue to support local community investment and review donation requests for the life of the Project.

●  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 817

817 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will continue to seek out and support community investment opportunities and initiatives with various organizations to assist in building and maintaining long-term collaborative relationships.

●  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

144 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 818

818 EA Report – Section 2 – Consultation and Engagement Summary

Activities that NextBridge has carried out, and will be carrying out, to fulfill the provincial EA process will adhere to the MECP’s expectations for consultation as described in the Code of Practice: Preparing and Reviewing Terms of Reference for Environmental Assessments in Ontario (MOECC 2014b).

●  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 819

819 EA Report – Section 2 – Consultation and Engagement Summary

All Indigenous communities will be provided with information on the methodology of construction, timing of construction, safety and communication channels for construction and how the Project has avoided or minimized potential adverse impacts to the environment, and will be provided with the opportunity to engage in a direct dialogue, to allow both NextBridge and the community to understand if there will be any potential effects resulting from the Project on their Aboriginal or treaty rights or interests.

●  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table; Community Permitting Workshops, Access to and review of DPPs, Provision Of capacity funding for active participation, Indigenous monitors on-site during construction, and ongoing engagement with Indigenous communities

Ongoing In Progress

2- 820

820 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will continue to work with each of the identified Indigenous communities in the development of appropriate processes to ensure that each Indigenous community and its members has access to information concerning the Project in a form that is useful to them.

●  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table; Indigenous monitors on-site during construction, and ongoing engagement with Indigenous communities

Ongoing In Progress

2- 821

821 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge and the six Bamkushwada LP communities will continue to be respectful of each other’s rights and interests and will continue to engage and have dialogue with each other and work cooperatively during the development, construction and operation of the Project.

●  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 822

822 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will consult with Indigenous groups about the Project and will consider Traditional Ecological Knowledge (TEK) and Traditional Land and Resource Use (TLRU) information that is shared during further detailed Project planning processes (e.g. post-EA processes). The continued engagement and consultation with potentially affected Indigenous communities through the life of the Project will provide an opportunity for communities to identify additional land and resource use sites that have the potential to be affected by the Project.

●  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table; Indigenous monitors on-site during construction, and ongoing engagement with Indigenous communities

Ongoing; no formal Indigenous land or resource sites have been identified. In January 2020, Pic Mobert First Nation notified NextBridge of the potential for Indigenous land and resource potential in the area of White Lake and Nursery Lake. NextBridge remains engaged with community to ensure proper mitigation plans are in place, in the areas concerned.

In Progress

145 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 823

823 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge intends to take the following actions when additional TEK and TLRU information is received:

Review the information for any site-specific interactions with the Project footprint.

In the event there is an interaction between a location identified by an Indigenous community and Project footprint, NextBridge will engage the identifying community to discuss the importance of the site to the community, and potential mitigation measures.

Appropriate mitigation measures are expected to be dependent on the proximity of the site in relation the Project footprint and the nature of the site (e.g., hunting location versus camping site). NextBridge intends to discuss appropriate mitigation measures with the identifying Indigenous community. Potential mitigation measures may include:

detailed mapping, recording, flagging and avoidance of the location, where possible;

in the event that avoidance of the site not be feasible, NextBridge will discuss other alternatives with the identifying Indigenous community;

implementation of mitigation measures to reduce potential for indirect effects on the site such as measures designed to reduce noise, or, where possible, the scheduling of construction outside of periods when the site will be used by Indigenous land users; and

sites requiring non-standard mitigation will be added to the CEPP (refer to Appendix 4-II), OEMP (refer to Appendix 4-III), Environmental Alignment Sheets (refer to Appendix 5-I), and Access and Construction Environmental Maps (refer to Appendix 5-II).

●  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 824

824 EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 18 – Socio-Economics

NextBridge commits to hire local qualified personnel where appropriate. ●  ●    Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2- 825

825 EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 18 – Socio-Economics

NextBridge commits to support local and regional procurement where practicable. ●  ●    Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2- 826

826 EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 18 – Socio-Economics

NextBridge commits to prioritize employment opportunities for local qualified Indigenous candidates. ●  ●    Valard EMS; Adherence to CEPP and DPP; ongoing engagement with Supercom, and Indigenous communities

Ongoing; As of March 27, 2020, 65% of the EWT construction workforce is Indigenous

In Progress

2- 827

827 EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 18 – Socio-Economics

NextBridge will communicate employment requirements to Indigenous communities in the labour market and economic development local study area (LSA).

●  ●    Valard EMS; Adherence to CEPP and DPP; ongoing engagement with Supercom, and Indigenous communities

Ongoing In Progress

2- 828

828 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge commits to minimize environmental effects whenever possible during construction and operation.   ●  ●  Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2- 829

829 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge is committed to transparency in all activities it undertakes. NextBridge is committed to include the Indigenous communities affected by the Project in archaeological assessments, environmental and construction monitoring activities. NextBridge will continue to offer monitoring opportunities, site tours and visits in order to ensure communities understand the activity taking place. NextBridge is further committed to ensuring monitors, employees, contractors and site tours and visits are implemented during construction.

  ●    Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table; Indigenous monitors on-site during construction, and ongoing engagement with Indigenous communities

Ongoing In Progress

2- 830

830 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will continue to consult with AZA in response to any identified (new or existing) community issues and concerns as they are raised.

●  ●  ●  Valard EMS; Consultation and Engagement Summary Table

On Going In Progress

146 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 831

831 EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 13 – Fish and Fish Habitat

EA Report – Section 19 – Non-Traditional Land and Resource Use

Schedule Project clean-up and reclamation to avoid or minimize interference to wildlife, migratory birds and fish spawning as much as possible.

  ●    Adherence to CEPP and DPP

Not Applicable to 2019 construction activities

Not Started

2- 832

832 EA Report – Section 2 – Consultation and Engagement Summary

The local forest company in the area with the forest license and the property owner will have the first opportunity to collect timber. NextBridge can discuss the possibility of the community having access to the timber if the forestry license operation and property owner are not interested in the timber.

  ●    Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 833

833 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will continue to consult with BN in response to any identified (new or existing) community issues and concerns as they are raised.

  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 834

834 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will continue to consult with BZA in response to any identified (new or existing) community issues and concerns as they are raised.

  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 835

835 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will continue to consult with BNA in response to any identified (new or existing) community issues and concerns as they are raised.

  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 836

836 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will continue to consult with FWFN in response to any identified (new or existing) community issues and concerns as they are raised.

  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 837

837 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will continue to consult with GFN in response to any identified (new or existing) community issues and concerns as they are raised.

  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 838

838 EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Access along the ROW will not be restricted during construction for Indigenous land users except where required for health and safety.

  ●    Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2- 839

839 EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

Engage with potentially affected Indigenous communities to discuss appropriate mitigation related to traditional use sites or areas located on the Project footprint.

  ●    Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table; Permitting Workshops, Indigenous monitors on-site during construction, and ongoing engagement with Indigenous communities

Ongoing In Progress

147 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 840

840 EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

Monitoring/inspections of new permanent water body crossing structures and roadside drainage features (on a bi-annual basis for the first two years following post-construction and then annually thereafter until pre-existing conditions are reached) for physical function and condition.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include post-construction monitoring activities

Not Started

2- 841

841 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will continue to consult LL58FN in response to any identified (new or existing) community issues and concerns as they are raised.

  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 842

842 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will continue to consult with MFN in response to any identified (new or existing) community issues and concerns as they are raised.

  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 843

843 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will continue to consult with MCFN in response to any identified (new or existing) community issues and concerns as they are raised.

  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 844

844 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will continue to consult with BFN in response to any identified (new or existing) community issues and concerns as they are raised.

  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 845

845 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will continue to consult with GRFN in response to any identified (new or existing) community issues and concerns as they are raised.

  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 846

846 EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 19 – Non-Traditional Land and Resource Use

In addition to tenure holders, NextBridge will continue to consult with local First Nations and the Métis that address potential effects of Project-related wood harvesting. Ongoing discussions with First Nations and the Métis on the use of merchantable timber and wood fiber will continue. NextBridge will commit to ongoing discussions with Métis, however the Province of Ontario has clear regulations regarding merchantable timber and NextBridge is committed to following established regulatory oversight. Discussions regarding rights to harvest firewood should be addressed to MNRF

  ●    Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 847

847 EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 13 – Fish and Fish Habitat

Where culverts are proposed, a fish and fish habitat survey will be completed prior to construction to determine the suitability of the crossing structure. Any potential alterations to the crossing structure or location will be incorporated into the permitting phase of the Project

●      Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Ongoing In Progress

2- 848

848 EA Report – Section 2 – Consultation and Engagement Summary

In response to a Pays Plat First Nation recommendation that a formal recognition and thank you be provided to trappers, land users and Elders in the community prior to construction, NextBridge is committed to discussing recognition of land users with PPFN.

●  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 849

849 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge is committed to working with PPFN at all stages of the project including ensuring opportunities are made available to conduct community ceremonies.

●  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

148 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 850

850 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will continue to make reasonable efforts to consult with PPFN and will continue to respond to new community issues and concerns as they are raised.

●  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 851

851 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will continue to consult with PMFN in response to any identified (new or existing) community issues and concerns as they are raised.

●  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 852

852 EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 13 – Fish and Fish Habitat

Monitoring/inspections of erosion and sediment management measures, bank stabilization features, and coffer dams to verify effectiveness

  ●    Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2- 853

853 EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 14 – Wildlife and Wildlife Habitat

Industry standards to avoid electrocutions have been incorporated in structure design (CSA C22.3, CSA 2015b).   ●    Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2- 854

854 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will continue to consult with RRIB in response to any identified (new or existing) community issues and concerns as they are raised.

  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 855

855 EA Report – Section 2 – Consultation and Engagement Summary

Monitoring of total suspended solids (TSS) and/or turbidity (instrumented measurements and/or visual observations), and monitoring of streamflow rates and/or water levels at water body crossings during construction, as well as immediately before construction (to capture baseline water quality conditions at locations downstream of the planned works) and immediately following construction (to confirm that water quality conditions have stabilized).

  ●    Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2- 856

856 EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 7 – Surface Water

Monitoring of TSS and/or streamflow rates at water bodies that include greater sensitivity or implication to change from the standpoint of fish habitat, species at risk, channel stability, drainage pattern, or other environmental considerations. The specific monitoring locations will be determined during the permitting phase of the project; however, it is expected that water bodies of varying size (small, medium, large) would be captured, recognizing that this would allow the effectiveness of mitigation measures to be evaluated at a range of scales.

  ●    Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2- 857

857 EA Report – Section 2 – Consultation and Engagement Summary

EA Report – Section 13 – Fish and Fish Habitat

Post-construction monitoring at water body crossings to verify that erosion and sediment control measures have b e e n successful (e.g., bank restoration and re vegetation). The integrity of the crossing structures will be inspected regularly and during periods of high run-off, such as the spring freshet. Changes to the morphology of the water body channel or to sediment loading will be identified and addressed, as needed.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include post-construction monitoring activities

Not Started

2- 858

858 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will continue to consult with MNO in response to any identified (new or existing) community issues and concerns as they are raised.

  ●    Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 859

859 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will continue to consult with RSMIN in response to any identified (new or existing) community issues and concerns as they are raised.

  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 860

860 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge commits to responding to all written comments received from the Indigenous communities. ●  ●    Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table; ongoing engagement with Indigenous communities

Ongoing In Progress

149 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 861

861 EA Report – Section 2 – Consultation and Engagement Summary

For written comments received outside the MECP amended EA Report review period, NextBridge will respond to the Indigenous community comments directly to the Indigenous community and the response will be provided to MECP in a monthly Indigenous consultation log update.

●  ●    Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table; ongoing engagement with Indigenous communities, and consultation log

Ongoing In Progress

2- 862

862 EA Report – Section 2 – Consultation and Engagement Summary

For any new comments received after the amended EA Report is finalized, NextBridge will discuss and resolve issues with Indigenous communities through meetings and teleconferences as required.

      Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table; ongoing engagement with Indigenous communities

Ongoing In Progress

2- 863

863 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge is committed to working with Indigenous communities to receive their feedback on the Project and the amended EA Report, and incorporate feedback into the Project design and planning, as appropriate.

●  ●    Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table; ongoing engagement with Indigenous communities

Ongoing In Progress

2- 864

864 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will continue to provide affected Indigenous communities with updates on Project design, construction planning, and schedule.

●  ●    Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table; Project website, and ongoing engagement with Indigenous communities

Ongoing In Progress

2- 865

865 EA Report – Section 2 – Consultation and Engagement Summary

Meeting minutes will, unless decided otherwise by agreement of the majority of the Aboriginal Community Advisory Board (ACAB) members present at any given meeting, be taken by a NextBridge representative and sent to the Chairperson for review, following which, will be disseminated to all members of the ACAB. Pending approval of the minutes by all ACAB members, the meeting minutes will be disseminated to NextBridge as well as to each First Nation and Métis community and its governance or representative communities.

●  ●    Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 866

866 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge will implement the commitments in the ACAB as described in the ACAB and above. In lieu of the ACAB being established as described (e.g., due to ongoing engagement with the 18 identified Indigenous communities), the proposed Terms of Reference may be altered and further developed in collaboration with Indigenous communities to ensure ongoing consultation occurs before, during and after construction and into operations. Alternatively, other mechanisms may be used to continue consultation with communities.

●  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table; ongoing engagement with Indigenous communities

Ongoing; in place of the formal establishment of the ACAB, NextBridge has engaged directly with Indigenous communities, as it was the preferred approach outlined by community leadership. NextBridge is considering the establish of the ACAB during the construction phase and post-construction period

In Progress

150 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 867

867 EA Report – Section 2 – Consultation and Engagement Summary

NextBridge commits to ongoing consultation and continuing dialogue with the 18 identified Indigenous communities for the life of the Project.

●  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table; ongoing engagement with Indigenous communities, and consultation log

Ongoing In Progress

2- 868

868 EA Report – Section 3 – Evaluation of Alternatives Mitigation measures that have been applied during Project design or will be implemented during construction and operation are provided in Sections 6 through 21 of the amended EA Report, the CEPP (refer to Appendix 4-II), the OEMP (refer to Appendix 4-III). The CEPP and OEMP will be living documents that will be updated with additional mitigation measures identified through the preparation of the Workfront Detailed Project Plans and the permitting processes.

  ●    Valard EMS; Adherence to CEPP and DPP, CEPP and OEMP

Ongoing In Progress

2- 869

869 EA Report – Section 3 – Evaluation of Alternatives NextBridge will continue to refine the construction and access plan as Project development continues and will continue to consult with stakeholders.

  ●    Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2- 870

870 EA Report – Section 3 – Evaluation of Alternatives If additional laydown yards, storage yards and construction camps are required these will be located within previously disturbed areas, and/or at reasonably flat with stable soil sites, wherever practicable.

  ●    Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2-

871

871 EA Report – Section 4 – Project Description Should revisions to Project design occur that result in an alteration to the conclusions of the effects assessment, NextBridge will discuss these changes with applicable regulatory agencies to determine required next steps such as appropriate stakeholder and Indigenous engagement and revisions to the Amended EA including the DPPs.

●      Adherence to CEPP and DPP; Consultation and Engagement Summary Table; ongoing engagement with Indigenous communities

Ongoing In Progress

2- 872

872 EA Report – Section 4 – Project Description Construction of the Project will be completed in accordance with industry best practices and applicable NextBridge guidelines. In particular, the Project will comply with North American Electric Reliability Corporation (NERC), Northeast Power Coordinating Council, Inc., and Independent Electricity System Operator (IESO) reliability standards. Likewise, it will meet the Canadian Standards Association minimum vertical clearances for transmission lines.

  ●    Engineering Design

Ongoing In Progress

2- 873

873 EA Report – Section 4 – Project Description During operations, the ROW will be maintained, and the transmission line inspected and repaired as needed, as discussed in Section 4.3.2.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 874

874 EA Report – Section 4 – Project Description In addition to the minimum vertical clearance, NextBridge will add construction and survey tolerances so the line is constructed to meet the CSA 22.3 No.1 and OEB minimum technical requirements.

●  ●    Engineering Design

Ongoing In Progress

2- 875

875 EA Report – Section 4 – Project Description Appropriate aerial marking for aviation and boating safety will comply with applicable codes and standards.   ●    Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2- 876

876 EA Report – Section 4 – Project Description The transmission structures will be designed to withstand loadings associated with a 100-year return period meteorological event (i.e., a wind or icing event that is statistically expected to occur once every 100 years).

  ●    Engineering Design

Ongoing In Progress

2- 877

877 EA Report – Section 4 – Project Description Water body crossings will meet CSA 22.3 No.1 and OEB minimum technical requirements for 230 kV conductor clearance over water bodies.

  ●    Engineering Design

Ongoing In Progress

2- 878

878 EA Report – Section 4 – Project Description Soil profiling and ground resistance measurements will be completed during the construction phase of the Project to confirm the grounding system meets technical requirements.

  ●    Engineering Design

Ongoing In Progress

151 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 879

879 EA Report – Section 4 – Project Description Off-ROW access roads will be used where travel in the ROW with heavy equipment is not possible due to terrain or environmental sensitivities (i.e., ground conditions), or where access can be gained by using other off-ROW access, thereby reducing environmental impact (e.g., reduced water body crossings, avoidance of sensitive habitat or poor ground conditions).

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

2019 construction activities complied with access permits, agreements and authorizations

Yes

2- 880

880 EA Report – Section 4 – Project Description The specific number, location, and characteristics of existing, improvement/widening, and new access roads to be used for the Project will be finalized as part of ongoing Project engineering and design, and will be planned and developed in consultation with Project stakeholders and in compliance with applicable legislation, regulations, and requirements identified in permits and authorizations. These details will be included in the Workfront DPPs.

●  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

2019 construction activities complied with access permits, agreements and authorizations

Yes

2- 881

881 EA Report – Section 4 – Project Description Construction or upgrade of the access roads will follow Ministry of Natural Resources and Forestry guidelines for access roads, including the Environmental Guidelines for Access Roads and Water Crossings document (MNR 1990).

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

2019 construction activities complied with access permits, agreements and authorizations

Yes

2- 882

882 EA Report – Section 4 – Project Description The access roads will be all-weather and will be located within a cleared and grubbed approximately 20-m-wide road ROW.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

2019 construction activities complied with access permits, agreements and authorizations

Yes

2- 883

883 EA Report – Section 4 – Project Description Where possible, the existing Hydro One transmission line ROW and existing access roads to the Hydro One ROW will be used during both construction and operations.

  ●  ●  Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

2019 construction activities complied with access permits, agreements and authorizations

Yes

2- 884

884 EA Report – Section 4 – Project Description All new access will have “cross drains” (culverts) installed where the topography requires natural ground water flow to take place.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities complied with access permits, agreements and authorizations

Yes

2- 885

885 EA Report – Section 4 – Project Description Active construction sites will not be gated or fenced; however, during construction, gates and fencing for both temporary and permanent access roads may be used to restrict access to active construction sites for safety purposes. Such measures would be taken in consultation with the relevant stakeholders and appropriate regulating agency.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

152 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 886

886 EA Report – Section 4 – Project Description NextBridge will not construct permanent fences on provincial Crown land unless requested by Crown agencies.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 887

887 EA Report – Section 4 – Project Description If access controls are required during construction, NextBridge will consider on site (i.e., where construction is taking place) security personnel.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 888

888 EA Report – Section 4 – Project Description The vehicle movement on Project access roads will follow all posted speed limits and not exceed road and highway maximum height and weight requirements.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 889

889 EA Report – Section 4 – Project Description Existing Roads: Municipal and provincial roads and highways that provide existing access that are maintained by municipalities or the province and do not require any repairs to support construction access will be used where feasible. These existing roads will be used as either permanent or temporary access roads to limit disturbance resulting from construction of road improvements or new access roads.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable

2019 construction activities complied with access permits, agreements and authorizations

Yes

2- 890

890 EA Report – Section 4 – Project Description Road Improvement/Widening: Existing roads have been assessed to identify whether they could be used for construction and the extent of improvements that may be required. Existing roads will be upgraded to be typically 8-m-wide within a 20 m road ROW, if required.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities complied with access permits, agreements and authorizations

Yes

2- 891

891 EA Report – Section 4 – Project Description New Roads: In some areas, a new road will be required to support construction access. Construction of new access roads will be limited to areas where required and where terrain prevents the use of existing roads or the ROW.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities complied with access permits, agreements and authorizations

Yes

2- 892

892 EA Report – Section 4 – Project Description Prior to blasting, NextBridge will review blasting locations and make sure regulatory requirements are being followed with respect to residents, wildlife and fish. Specifically, blast operations shall be carried out in accordance with DFO guidelines and Ontario Provincial Standard Specification 120 “General Specification for the Use of Explosives.”

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include blasting activities

Not Started

153 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 893

893 EA Report – Section 4 – Project Description Use of the ROW: Equipment will use the ROW to build access roads, as identified in the categories above and as depicted on the Access and Construction Environmental Maps (Appendix 5-II). A travel lane along the complete ROW will not be built for the purpose of construction; however, some equipment may travel down the ROW where road access is not available, e.g., for a geotechnical program. The ROW will not be used as a primary access for assembly, erection, stringing or related activities; however, equipment will use the ROW (particularly in proximity to the access roads) during foundation, anchor, and assembly, erection, stringing and related activities.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities complied with access permits, agreements and authorizations

Yes

2- 894

894 EA Report – Section 4 – Project Description Temporary access roads that are required only for construction will be reclaimed following construction, unless an exception is made in agreement with the relevant stakeholders (i.e., the landowners).

  ●    Adherence to CEPP and DPP

Not applicable to 2019 construction activities

Not Started

2- 895

895 EA Report – Section 4 – Project Description Where required, gravel used for the temporary access roads will be removed as directed by the regulatory agencies, unless otherwise agreed upon with the relevant stakeholders.

  ●    Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 896

896 EA Report – Section 4 – Project Description Any gates and fencing for both temporary and permanent access roads will be removed unless otherwise requested and agreed upon by relevant stakeholders (e.g., landowners of private land, or the Crown). Where gates are left in place, they will be maintained in accordance with agreements with the landowner(s).

  ●    Adherence to CEPP and DPP

On Going In Progress

2- 897

897 EA Report – Section 4 – Project Description Operation requires permanent access to the ROW for lighter vehicles to conduct inspections, maintenance, emergency repairs, and vegetation management. A subset of the construction access roads has been identified for permanent access and will be maintained for operation and maintenance of the Project.

    ●  Adherence to CEPP and DPP

Not applicable to 2019 construction activities

Not Started

2- 898

898 EA Report – Section 4 – Project Description Use of the ROW: Operations personnel will access the ROW using permanent access roads intersecting the ROW. Once on the ROW, personnel will traverse along the ROW using the appropriate vehicle in compliance with any required permits or authorizations. It is expected that there will be sufficient access on the ROW to traverse using an all-terrain vehicle, Argo, pickup truck or snowmobile, where terrain allows.

    ●  Adherence to CEPP and DPP

Not applicable to 2019 construction activities

Not Started

2- 899

899 EA Report – Section 4 – Project Description Personnel may use existing water body crossings where they exist on access roads; however, new permanent crossing structures are not expected to be built for the sole purpose of operations. Therefore, personnel will travel down the ROW until a water body with no crossing structure is encountered, and then turn around and return to the access road used to enter the ROW.

    ●  Adherence to CEPP and DPP

Not applicable to 2019 construction activities

Not Started

2- 900

900 EA Report – Section 4 – Project Description If Operations personnel determine that an additional water body crossing will be necessary, this will be discussed with the appropriate regulatory authority and any required permits or authorizations will be obtained prior to proceeding with the work.

    ●  Adherence to CEPP and DPP

Not applicable to 2019 construction activities

Not Started

2- 901

901 EA Report – Section 4 – Project Description Where Operations personnel cannot access a structure location using the permanent access roads, helicopters may be used. For example, some patrol during operations will be conducted via helicopter.

    ●  Adherence to CEPP and DPP

Not applicable to 2019 construction activities

Not Started

2- 902

902 EA Report – Section 4 – Project Description Where not required by the landowner or Crown agencies, gates will not be installed.     ●  Adherence to CEPP and DPP

Not applicable to 2019 construction activities

Not Started

2- 903

903 EA Report – Section 4 – Project Description Temporary water body crossings will be installed on the temporary access roads, and permanent water body crossings will be installed on the permanent access roads, where required.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities complied with crossing permits

Yes

154 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 904

904 EA Report – Section 4 – Project Description Crossing types and construction methods are identified in Appendix 13-II, Tables 13-II-1 and 13-II-2 and will be finalized as part of ongoing Project engineering and design, in consultation with appropriate regulators. These details will be included in the Workfront DPPs.

●  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

2019 construction activities complied with crossing permits

Yes

2- 905

905 EA Report – Section 4 – Project Description\

EA Report – Section 19 – Non-Traditional Land and Resource Use

Regulatory approvals will be obtained from the applicable regulatory agencies prior to installation of the temporary or permanent water body crossing structures, as required. Permanent and temporary water body crossings will be constructed and operated to conform with DFO Measures to Avoid Causing Harm to Fish and Fish Habitat Including Aquatic Species at Risk (DFO 2016) and Ministry of Natural Resources and Forestry Environmental Guidelines for Access Roads and Water Crossings (MNR 1990), including the application of sediment and erosion control measures.

  ●  ●  Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; crossings installed according to LRCA permit or MNRF Work Permit and DFO Letter of Advice.

Yes

2- 906

906 EA Report – Section 4 – Project Description Vegetation clearing will be limited to the extent practicable for water bodies as per industry standard practices and government agency requirements.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 907

907 EA Report – Section 4 – Project Description For temporary access roads, crossing materials (i.e., temporary crossing structures) will be removed following completion of the construction phase of the Project.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include reclamation activities.

Not Started

2- 908

908 EA Report – Section 4 – Project Description Sediment and erosion control measures will be installed prior to commencing removal activities. Upon removal of the crossing materials, the water body banks will be returned to their original profile and disturbed areas will be stabilized, as necessary, to prevent soil erosion and monitored for effectiveness.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include reclamation activities.

Not Started

2- 909

909 EA Report – Section 4 – Project Description The storage yards will be approximately 400 m by 400 m in size and will be located outside water body slope dependent vegetation buffer (30m -90m) and wet areas.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Not Applicable to 2019 construction activities

Not Started

2- 910

910 EA Report – Section 4 – Project Description Where feasible, existing disturbed areas have been selected for the storage yards. The storage yard sites will be cleared of vegetation, grubbed and levelled where reasonable, and graveled as needed.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Not applicable to 2019 construction activities

Not Started

155 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 911

911 EA Report – Section 4 – Project Description Vegetation will generally be cleared using mechanical harvesters to remove the merchantable timber and bulldozers to remove the remaining woody vegetation.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Not applicable to 2019 construction activities

Not Started

2- 912

912 EA Report – Section 4 – Project Description Gravel will only be added where needed for safety and stability. The storage yards may be equipped with perimeter lighting and fencing for safety and security.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Not applicable to 2019 construction activities

Not Started

2- 913

913 EA Report – Section 4 – Project Description Materials from the storage yards will be transported by truck to laydown yards or to structure locations on the ROW as required.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Not applicable to 2019 construction activities

Not Started

2- 914

914 EA Report – Section 4 – Project Description The General Contractor (Valard) may choose to transport materials by helicopter to structure locations not accessible by ground vehicles. Existing sites with appropriate land use designations that can accommodate the Project requirements have been identified as priority locations for the storage yards. The appropriate permits and authorizations will be acquired prior to use.

●  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

Not applicable to 2019 construction activities

Not Started

2- 915

915 EA Report – Section 4 – Project Description Storage yards will be reclaimed and replanted with conifers to address concerns related to Crown land camping.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include reclamation activities.

Not Started

2- 916

916 EA Report – Section 4 – Project Description Laydown yards will be established along the preferred route ROW to receive and temporarily store materials and equipment during construction.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Not applicable to 2019 construction activities

Not Started

2- 917

917 EA Report – Section 4 – Project Description The laydown yards will be cleared of vegetation, grubbed and levelled where reasonable, and graveled as required.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Not applicable to 2019 construction activities

Not Started

2- 918

918 EA Report – Section 4 – Project Description Gravel will only be added where needed for safety and stability (refer to Section 4.2.10 [Aggregates] of the amended EA Report).

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Not applicable to 2019 construction activities

Not Started

156 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 919

919 EA Report – Section 4 – Project Description Laydown yards will be located at least 30 meters (outside vegetation buffer) from water bodies and situated to avoid or limit potential environmental effects.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Not applicable to 2019 construction activities

Not Started

2- 920

920 EA Report – Section 4 – Project Description Laydown yards will be reclaimed and replanted with conifers to address concerns raised by stakeholders, for example, in relation to caribou habitat and Crown land camping.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include reclamation activities

Not Started

2- 921

921 EA Report – Section 4 – Project Description Camp facilities will comply with the Ontario Occupational Health and Safety Act. Required permits, authorizations, and approvals will be obtained before construction of the camps. Specific camp features and/or layout may vary due to local topography and site conditions.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

Camps not applicable for 2019 construction activities

Not Started

2- 922

922 EA Report – Section 4 – Project Description In accordance with the Ontario Water Resources Act, Permit(s) To Take Water will be obtained, or Environmental Activity and Sector Registry will be completed prior to taking and discharging groundwater.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Camps not applicable for 2019 construction activities

Not Started

2- 923

923 EA Report – Section 4 – Project Description Municipal sewage disposal services will be sourced where available, with the construction camps hooking up to municipal services for sewage disposal. Where municipal systems are not available, septic fields, on-site treatment and trucking off-site would be options. The appropriate approvals (e.g., municipal approvals or ECAs) will be obtained as appropriate).

  ●    Valard EMS; Adherence to CEPP and DPP

Camps not applicable for 2019 construction activities

Not Started

2- 924

924 EA Report – Section 4 – Project Description Grey water will be held and discharged according to required permits and authorizations for construction and operation of grey water treatment.

  ●    Valard EMS; Adherence to CEPP and DPP

Camps not applicable for 2019 construction activities

Not Started

2- 925

925 EA Report – Section 4 – Project Description NextBridge proposes to use on-site waste incinerators for domestic waste at the construction camps. The appropriate approvals including an ECA will be in place prior to the use of any waste incinerators.

●  ●    Valard EMS; Adherence to CEPP and DPP

Camps not applicable for 2019 construction activities

Not Started

2- 926

926 EA Report – Section 4 – Project Description Organic solid waste disposal at the camps will be in compliance with applicable guidelines and regulatory

requirements. Organic solid waste may be temporarily stored in bear‐proof containers before being transported to an approved waste disposal site.

  ●    Valard EMS; Adherence to CEPP and DPP

Camps not applicable for 2019 construction activities

Not Started

2- 927

927 EA Report – Section 4 – Project Description A recycling program will be implemented at the camps to reduce the amount of solid waste generated as a requirement of the construction contract with the General Contractor (Valard).

  ●    Valard EMS; Adherence to CEPP and DPP

Camps not applicable for 2019 construction activities

Not Started

2- 928

928 EA Report – Section 4 – Project Description Electricity will be supplied to construction camps through the existing power grid where possible, otherwise temporary diesel generators will be used where there are no rural distribution powerlines. The diesel generators will be operated in compliance with applicable regulations and guidelines, including acquiring necessary permits and approvals.

  ●    Valard EMS; Adherence to CEPP and DPP

Camps not applicable for 2019 construction activities

Not Started

2- 929

929 EA Report – Section 4 – Project Description Construction camps will be reclaimed and replanted with conifers to address concerns related to Crown land camping.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include reclamation activities

Not Started

2-

930

930 EA Report – Section 4 – Project Description The construction easements are not required for operations and will be decommissioned and reclaimed during the construction clean-up stage.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include decommissioning activities

Not Started

157 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 931

931 EA Report – Section 4 – Project Description The General Contractor (Valard) will establish temporary construction offices with access to all-weather roads and communications infrastructure.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 932

932 EA Report – Section 4 – Project Description The construction offices established in the temporary workspaces will be decommissioned following completion of construction activities. This would include disconnection of services, demobilization of temporary structures, clean-up of debris, site preparation, and seeding/planting consistent with reclamation of the construction camps

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include decommissioning activities

Not Started

2- 933

933 EA Report – Section 4 – Project Description During construction, fuel will be transported by tanker trucks, in drums, or other approved containers. Fueling areas will be established at laydown yards, storage yards and/or construction camps, with steel aboveground storage tanks featuring secondary containment.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 934

934 EA Report – Section 4 – Project Description The aboveground storage tanks will be registered under, and in compliance with, applicable federal and provincial legislation. Aboveground storage tanks will meet the Canadian Council of Ministers of the Environment Environmental Code of Practice for Aboveground and Underground Storage Tank Systems Containing Petroleum and Allied Petroleum Products (CCME 2003).

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

Complete for 2019; ongoing for remaining Project construction

Yes

2- 935

935 EA Report – Section 4 – Project Description Transport, storage and handling will meet the Ontario Technical Standards and Safety Act, 2000 and Canada’s Transportation of Dangerous Goods Act. The transport vehicles will be licensed and maintained according to safety requirements.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

Complete for 2019; ongoing for remaining Project construction

Yes

2- 936

936 EA Report – Section 4 – Project Description Generally, vehicles will be fueled at the camps; however, if fueling of vehicles and other mobile equipment is required on the Project footprint, then fueling will not be permitted within 100 m of a water body.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 937

937 EA Report – Section 4 – Project Description

EA Report – Section 8 – Groundwater

If concrete batch plants are required, the owner/operator of the concrete batch plant will operate the plant in compliance with applicable regulatory requirements (e.g., ECA).

  ●    Valard EMS; Adherence to CEPP and DPP

Not applicable to 2019 construction activities

Not Started

2- 938

938 EA Report – Section 4 – Project Description Construction activities are expected to continue year-round, with some construction activities being staged as practicable to avoid or minimize potential effects on ecologically sensitive areas and life cycle periods, and sensitive receptors. Details regarding construction staging and sequencing will be refined in ongoing discussions with regulators as they confirm the restricted activity periods for certain activities, such as clearing. These details will be included in the Workfront DPPs.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 939

939 EA Report – Section 4 – Project Description Subject to contractor-employee labour agreements or contractor detailed construction plans, longer shifts may be required. NextBridge will re-evaluate the potential Project-related effects and if required, review mitigation requirements if construction will occur beyond the daytime period. These details will be included in the Workfront DPPs.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 940

940 EA Report – Section 4 – Project Description Vegetation that is not within the Project footprint will not be cleared, unless there is a risk that it could fall onto the transmission line and interfere with electricity transmission during operation. While not anticipated, such vegetation clearing would be conducted with appropriate approvals on a case-by-case basis.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 941

941 EA Report – Section 4 – Project Description “Incompatible” vegetation will be cleared in the preferred route ROW.   ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 942

942 EA Report – Section 4 – Project Description Vegetation will generally be cleared using mechanical harvesters to remove the timber.   ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 943

943 EA Report – Section 4 – Project Description Chainsaws may be used for small-scale clearings (e.g., tree removal adjacent to a water body), as required. Small trees and branches will be chipped on site, and the chips may be spread over the preferred route ROW. In some cases, it may be more practicable to burn cleared wood, and the required permits and authorizations will be acquired prior to burning.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

158 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 944

944 EA Report – Section 4 – Project Description Timber removal will be coordinated with affected timber owners, as applicable, and offered accordingly. Affected timber owners will either be the private property owner, the Crown where timber rights were reserved, or in most cases the Sustainable Forest License holder.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

Complete for 2019; ongoing for remaining Project construction

Yes

2- 945

945 EA Report – Section 4 – Project Description If the timber can be removed from the preferred route ROW and delivered to local mills for processing economically, it will be sold. Slash and debris will be chipped or will be burned in accordance with provincial Forest Fires Prevention Act and O. Reg. 207/96 Outdoor Fires under this Act.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

Complete for 2019; ongoing for remaining Project construction

Yes

2- 946

946 EA Report – Section 4 – Project Description Diseased or damaged trees located at the edge of the ROW that may fall onto the overhead line conductors or structures will also be removed. The General Contractor (Valard) will make arrangements to dispose of wood left on site during preferred route ROW clearing.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 947

947 EA Report – Section 4 – Project Description Vegetation clearing for access roads will vary based on terrain and soil type but will include a combination of manual and machine techniques. Manual vegetation clearing may be required in areas with steep slopes and to remove "incompatible" vegetation within vegetation buffers for environmentally sensitive features.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 948

948 EA Report – Section 4 – Project Description Construction of the access roads, construction camps, storage yards and laydown yards will be conducted prior to transmission line construction within each workfront, as described in Section 4.2.

●  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 949

949 EA Report – Section 4 – Project Description Following preferred route ROW clearing and construction of the temporary workspaces, field survey crews will mark (i.e., stake) the specific locations of the structures, foundations, and guy anchors using Global Positioning System (GPS) technology, data from the LiDAR survey, and detailed design. Staked locations will be field verified and shifted if necessary to avoid sensitive features or other obstacles.

●  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 950

950 EA Report – Section 4 – Project Description Laydown yards will be used to receive and temporarily store materials and equipment during construction. Material will be transported to the transmission line ROW using line trucks and flatbed transport trucks where possible. Off-road track units will be used where trucks cannot drive if possible.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 951

951 EA Report – Section 4 – Project Description Construction materials will be distributed from the laydown yards using trucks, or other appropriate equipment as dictated by the terrain or other environmental considerations.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 952

952 EA Report – Section 4 – Project Description Prior to blasting, NextBridge will review blasting locations and make sure regulatory requirements are being followed with respect to residents, wildlife and fish. Specifically, blast operations shall be carried out in accordance with DFO guidelines and Ontario Provincial Standard Specification 120 General Specification for the Use of Explosives.

●  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Development of blasting plan completed. 2019 construction activities did not include blasting activities.

In Progress

2- 953

953 EA Report – Section 4 – Project Description NextBridge will develop a blasting plan for the Project for avoiding and mitigating Serious Harm to Fish and engaging with DFO on the plan, as appropriate. Blasting will be regulated under the Explosives Regulations, 2013, and permits will be obtained for any activities where explosives and blasting are used to create level areas for transmission structures, roads and for foundation excavations.

  ●    Valard EMS; Adherence to CEPP and DPP

Development of blasting plan completed. 2019 construction activities did not include blasting activities.

In Progress

2- 954

954 EA Report – Section 4 – Project Description While every attempt will be made to locate structure foundations out of wetlands, it may be necessary to locate some structures in wet conditions. In this case, an assessment will be completed in advance of disturbance to wetlands to identify impacts and identify whether additional mitigation is required. These assessments will be reported to the MNRF as part of the Workfront DPPs. .

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

159 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 955

955 EA Report – Section 4 – Project Description The grounding assemblies will be tested individually and as a system and additional grounding may be installed if required to meet NextBridge operational and safety requirements.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include grounding assembly activities

Not Started

2- 956

956 EA Report – Section 4 – Project Description Temporary workspaces that are not required for Project operation will be decommissioned and reclaimed following completion of construction. This will include the decommissioning of construction camps, construction offices,

temporary access roads and crossing structures, storage and laydown yards, and clean‐up and reclamation of the

sites

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include decommissioning activities

Not Started

2- 957

957 EA Report – Section 4 – Project Description The construction camps and offices will be decommissioned upon completion of Project construction. Buildings will be removed.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include decommissioning activities

Not Started

2- 958

958 EA Report – Section 4 – Project Description Water and sewer systems and in‐ground infrastructure will be decommissioned in accordance with applicable

regulatory requirements   ●    Valard EMS;

Adherence to CEPP and DPP

2019 construction activities did not include decommissioning activities

Not Started

2- 959

959 EA Report – Section 4 – Project Description Surface infrastructure will be removed from the storage and laydown yards. In-ground infrastructure will be decommissioned in accordance with applicable regulatory requirements

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include decommissioning activities

Not Started

2- 960

960 EA Report – Section 4 – Project Description Temporary construction fencing will be removed or replaced with permanent fencing or gates where requested based on consultations with relevant stakeholders (e.g., private property owners and Crown agencies) and access control requirements.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include decommissioning activities

Not Started

2- 961

961 EA Report – Section 4 – Project Description

EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

NextBridge will consult with property owners about the placement of permanent fencing and gates as applicable. The location of gates and fencing will be negotiated with the property owner and, where gates are installed, a lock system will be agreed to with the property owner. The other gates and fences will be decommissioned and removed using applicable and appropriate methods and standards. Where not required by the landowner or Crown agencies, gates will not be installed.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Ongoing In Progress

2- 962

962 EA Report – Section 4 – Project Description Water body crossings will be removed, and sediment and erosion control measures will be installed prior to their removal. Upon removal of water body crossings, water body banks will be returned to a stable condition.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include removal of any water crossings.

Not Started

2- 963

963 EA Report – Section 4 – Project Description Clean-up and reclamation will be conducted after temporary workspaces have been decommissioned

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include decommissioning activities

Not Started

2- 964

964 EA Report – Section 4 – Project Description NextBridge will replant laydown yards, construction camps and storage yards with conifers. Where appropriate, natural recovery will be the preferred method of revegetation; however, re-seeding will be done to re-establish a native cover crop such as ground juniper or other low-growing shrubs to stabilize soils (e.g., mitigate erosion risk), to limit the establishment of fast-growing tree species such as poplar and white birch, to minimize noxious weed risk, or where specifically required by the regulator. Seeding is anticipated to occur using spreaders.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include replanting activities

Not Started

2- 965

965 EA Report – Section 4 – Project Description Mitigation measures for site clean-up and reclamation are provided in Section 5.8 of the CEPP (refer to Appendix 4-II) and a draft Decommissioning Plan has been provided in Section 6.8 of the CEPP (refer to Appendix 4-II). These details will be included in the Workfront DPPs.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include decommissioning activities

Not Started

2- 966

966 EA Report – Section 4 – Project Description Waste disposal/recycling, including hazardous and excavated materials, will comply with applicable regulations and disposed of at authorized facilities.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

160 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 967

967 EA Report – Section 4 – Project Description

EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 13 – Fish and Fish Habitat

Post-construction environmental monitoring will be conducted after the completion of the construction activities and continue into the operation and maintenance phase and will include such activities as examining and documenting the success of reclamation measures. Indigenous participation will be discussed with communities.

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include post-construction monitoring activities

Not Started

2- 968

968 EA Report – Section 4 – Project Description 45 days prior to construction, a detailed spill prevention and response plan will be developed to prevent spills and describe contamination during construction.

●      Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2- 969

969 EA Report – Section 4 – Project Description Blasting will be carried out in accordance with DFO Guidelines on the Use of Explosives in or near Canadian Fisheries Waters (DFO 1998).

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

2019 construction activities did not include blasting activities.

Not Started

2- 970

970 EA Report – Section 4 – Project Description Waste will be appropriately stored, transported, and disposed of according to applicable provincial and federal laws and regulations

  ●    Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2- 971

971 EA Report – Section 4 – Project Description Maintenance activities will include regular inspection of the transmission line and associated infrastructure, and vegetation management in the transmission line ROW. Operation and maintenance activities will be conducted in accordance with permits and regulations. Measures set out in the OEMP will be implemented as appropriate (refer to Appendix 4-III).

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 972

972 EA Report – Section 4 – Project Description The Project will operate on a continuous basis and will be maintained by NextBridge.     ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 973

973 EA Report – Section 4 – Project Description The transmission line will be inspected on a semi-annual to annual basis. The inspection will primarily be completed by air. The transmission line will be inspected for signs of physical damage (e.g., broken or missing insulators), loose or eroded parts (e.g., bolts), and condition of the conductors (e.g., frayed or areas of reduced clearance). Minor adjustments such as bolt tightening may be done during the inspections.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 974

974 EA Report – Section 4 – Project Description Use of the ROW: Where needed, ground access will be conducted with one pick-up truck or all-terrain vehicle using the ROW and permanent access roads. Ground access patrols will likely be conducted by a single person. Personnel will drive on the ROW where terrain permits; however, a dedicated road that follows a direct path from structure to structure in the ROW will not be built, used or maintained during operations.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 975

975 EA Report – Section 4 – Project Description Vegetation Management: Vegetation management surveys will also be completed by ground (e.g., by all-terrain vehicles) or air. The preferred route ROW will be patrolled once each year to identify vegetation that could pose a risk to the line. Annual patrols will be conducted on that vegetation. Any vegetation that could grow into or fall into the line are identified and removed before they could cause a potential power outage. Refer to Section 4.3.2.5 of the amended EA Report for details about vegetation management.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 976

976 EA Report – Section 4 – Project Description Specially trained and equipped linemen or subcontractors will undertake the repairs NextBridge will attempt to fix identified issues during maintenance inspections but return trips may be required by specially trained and equipped linemen personnel to undertake the repairs.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 977

977 EA Report – Section 4 – Project Description Emergency repairs may be required in the event of bad weather or power outages. Emergency repairs will be carried out in the most time sensitive manner. Spare parts and poles will be stored in a storage yard or warehouse in proximity to the transmission line in case emergency repairs are required. The quantity of this material and storage location will be determined by NextBridge.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 978

978 EA Report – Section 4 – Project Description NextBridge anticipates the permanent access roads and preferred route ROW will be sufficient access to maintain and operate the Project. If there is a maintenance or emergency response activity that requires additional access or additional permitting requirements NextBridge will identify these requirements and consult with the appropriate regulatory authorities, as required.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

161 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 979

979 EA Report – Section 4 – Project Description Access roads will be required during the operation of the Project and used to access the Project area for maintenance purposes, to complete inspections, and for emergency purposes. Unless otherwise maintained by the province or the municipality, these roads will be maintained by NextBridge in accordance with any long-term road maintenance agreements in place with relevant landowners. Maintenance associated with these roads will include regular inspections (annually), vegetation maintenance, and repairing areas affected by erosion.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 980

980 EA Report – Section 4 – Project Description Visual ground and aerial patrols will be completed to identify areas that require vegetation management, and the schedule will be based on growth cycles, system security, public health/safety, protecting the environment, and maintenance associated with the existing Hydro One transmission line. Based on the results, spot treatment via ground crews may occur.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 981

981 EA Report – Section 4 – Project Description A response plan will be developed to allow for isolation of components in response to system events (e.g., lightning strike).

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 982

982 EA Report – Section 4 – Project Description EA Report – Section 18 – Socio-Economics

NextBridge will identify potential safety, health, and environmental concerns related to the Project phases. Prevention measures and response procedures will be described in a Spill Prevention and Response Contingency Plan that is included in the CEPP (refer to Section 23 and Appendix 4-II). Project personnel will receive applicable training in health and safety and emergency response.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 983

983 EA Report – Section 4 – Project Description The following stakeholders will be consulted during the design of the transmission line: NAV CANADA as the authority responsible for air navigation and Transport Canada as the regulatory authority. Applicable standards will be followed

The following forms shall be completed prior to construction:

NAV CANADA Land Use Proposal Submission Form; and

Transport Canada Obstruction Clearance Form

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 984

984 EA Report – Section 4 – Project Description The transmission line will be designed, constructed, and maintained in accordance with the Occupational Health and Safety Act and other relevant regulations that establish clearances from other man-made and natural structures as well as tree-trimming requirements to reduce/avoid fire hazards. NextBridge will maintain the preferred route ROW and immediate area in accordance with existing regulations and accepted industry practices that will include identification and abatement of fire hazards.

    ●  Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 985

985 EA Report – Section 4 – Project Description The General Contractor (Valard) will also be required to have a Health and Safety Plan in place.   ●    Valard OEWTL Online Site Orientation; EWT Safety Orientation

Complete. Orientation and safety documents developed and provided to on-site personnel

Yes

2- 986

986 EA Report – Section 4 – Project Description Work opportunities will be provided to qualified Indigenous persons.   ●    Adherence to CEPP and DPP; ongoing engagement with Supercom and Indigenous communities

Ongoing; as of March 27, 2020, 65% of the EWT construction workforce is Indigenous

Yes

2- 987

987 EA Report – Section 4 – Project Description Staffing for the Project will be the responsibility of the General Contractor (Valard). ●  ●    Adherence to CEPP and DPP

Ongoing Yes

2- 988

988 EA Report – Section 4 – Project Description Approximately two full-time employees will be required to oversee routine operations and maintenance of the Project. Specialized services will also be required in the event repairs are needed.

●  ●    Adherence to OEMP

Ongoing In Progress

2- 989

989 EA Report – Section 6 – Geology, Terrain and Soils

EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands

Soil quality issues such as compaction, rutting and admixing will be visually assessed throughout the Project footprint during construction.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

162 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 990

990 EA Report – Section 6 – Geology, Terrain and Soils

Design new bridges to extend beyond the channel width to avoid erosion and damage to banks. Do not place fill within primary banks for bridge abutment construction, unless approved by the appropriate regulatory agencies (refer to Appendix 4 II, Figures B 7 and B 8). Bridge abutments with wings may require hauling in of fill material and placing geotextile fabric between the fill material and the surface layer.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

Complete for 2019; crossings installed according to LRCA permit or MNRF Work Permit and DFO Letter of Advice.

Yes

2- 991

991 EA Report – Section 7 – Surface Water Monitoring of TSS and/or turbidity (instrumented measurements and/or visual observations), and monitoring of streamflow rates and/or water levels at all water body crossings during construction, as well as immediately before construction (to capture baseline water quality conditions at locations downstream of the planned works) and immediately following construction (to confirm that water quality conditions have stabilized).

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

Complete for 2019; crossings installed according to LRCA permit or MNRF Work Permit and DFO Letter of Advice.

Yes

2- 992

992 EA Report – Section 7 – Surface Water Monitoring of TSS and/or turbidity (instrumented measurements and/or visual observations), and streamflow rates and/or water levels will be carried out on a twice annual basis at new and permanent water body crossings during the early stages of the operation phase until pre-existing conditions are reached (to verify the effectiveness of reclamation measures). To the extent possible, the monitoring will be carried out during a period of high flows (e.g., spring) and low flows (e.g., mid- to late summer) in an effort to assess water quality conditions under a wide range of flow conditions. The monitoring program may be discontinued thereafter if conditions are observed to align with pre-construction conditions.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

Complete for 2019; crossings installed according to LRCA permit or MNRF Work Permit and DFO Letter of Advice.

Yes

2- 993

993 EA Report – Section 7 – Surface Water Potable water for most construction camps will be obtained from municipal supplies where available for use. Groundwater wells will not be drilled unless municipal supplies are not available for use.

  ●    Valard EMS; Adherence to CEPP and DPP

Camps not applicable for 2019 construction activities

Not Started

2- 994

994 EA Report – Section 7 – Surface Water Construction offices will be typically established within construction camps; however, supporting office may be leased or rented in communities with existing water supplies, where practicable.

  ●    Valard EMS; Adherence to CEPP and DPP

Camps not applicable for 2019 construction activities

Not Started

2- 995

995 EA Report – Section 7 – Surface Water No permanent sewage works will be developed for the construction camps. Sewage disposal will be achieved through hook up to municipal systems, septic fields, on site treatment or trucking off-site. Grey water will be held and discharged according to required permits and authorizations for construction and operation of grey water treatment.

  ●    Valard EMS; Adherence to CEPP and DPP

Camps not applicable for 2019 construction activities

Not Started

2- 996

996 EA Report – Section 7 – Surface Water Construction offices will typically be established at construction camps. Potable water for most construction camps w i l l be obtained from municipal sources where available, or from groundwater wells where municipal supplies are not available for use.

  ●    Valard EMS; Adherence to CEPP and DPP

Camps not applicable for 2019 construction activities

Not Started

2- 997

997 EA Report – Section 7 – Surface Water

EA Report – Section 8 – Groundwater

EA Report – Section 15 – Archaeological Resources

EA Report – Section 16 – Cultural Heritage Resources EA Report – Section 19 – Non-Traditional Land and Resource Use

Temporary access roads will be decommissioned in accordance with regulatory approvals and will follow MNRF’s Environmental Guidelines for Access Roads and Water Crossings (refer to Appendix 4-II, Appendix H2; MNR 1990).

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations

2019 construction activities did not include decommissioning activities

Not Started

2- 998

998 EA Report – Section 8 – Groundwater

EA Report – Section 12 – Vegetation and Wetlands

Use equipment that minimizes surface disturbance when brushing non-merchantable timber in areas where grading is not warranted.

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 999

999 EA Report – Section 8 – Groundwater Terrain distribution on the Project footprint will be monitored for changes to surface and ground water flows and slope instability during the construction and reclamation phases of the Project

  ●    Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 1000

1000 EA Report – Section 8 – Groundwater Upon completion of the Project, camp wells that are no longer in use will be decommissioned in accordance with Wells Regulation (O. Reg. 903).

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include decommissioning activities

Not Started

163 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 1001

1001 EA Report – Section 8 – Groundwater Well water will be tested before being used at construction camps.       Valard EMS; Adherence to CEPP and DPP

Camps not applicable for 2019 construction activities

Not Started

2- 1002

1002 EA Report – Section 11 – Acoustic Environment The electrical transmission line will be designed to minimize noise associated with corona discharge. ●      Engineering design

Ongoing In Progress

2- 1003

1003 EA Report – Section 13 – Fish and Fish Habitat Operate equipment on land or on ice and in a manner that minimizes disturbance to the banks of the water body.   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 1004

1004 EA Report – Section 16 – Cultural Heritage Resources

Avoid the Angler Internment Camp:

Prohibit use of the ATV trail west of the existing Hydro One transmission corridor as a temporary access road

  ●  ●  Valard EMS; Adherence to CEPP and DPP

Not applicable to 2019 construction activities

Not Started

2- 1005

1005 EA Report – Section 16 – Cultural Heritage Resources

Angler Internment Camp: If this section of trail must be used as an access road, the following actions should be prohibited;

Improvements beyond basic re-surfacing;

Excavation; and

Removing existing access road infrastructure. If cultural material such as artifacts are found while making improvements to the trail or during use of the temporary access route, implement the Project Discovery of Heritage or Archaeological Resources Contingency Plan

  ●  ●  Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Not applicable to 2019 construction activities

Not Started

2- 1006

1006 EA Report – Section 16 – Cultural Heritage Resources

Site plan control and communication:

The Angler Internment Camp site should be clearly marked on project mapping and communicated to all project personnel for avoidance during construction phases of the Project.

  ●  ●  Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Not applicable to 2019 construction activities

Not Started

2- 1007

1007 EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use EA Report – Section 20 – Visual Environment

Site preferred route ROW to take advantage of existing screening offered by topography and/or vegetation   ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Ongoing In Progress

2- 1008

1008 EA Report – Section 17 – Indigenous Current Use of Lands and Resources for Traditional Purposes

EA Report – Section 19 – Non-Traditional Land and Resource Use

EA Report – Section 20 – Visual Environment

Consider adjusting locations of transmission structures along the preferred route ROW to reduce effects to visual quality and reduce effects to visual quality and environmentally sensitive features (e.g., wetlands, SWH), where possible

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Ongoing In Progress

2- 1009

1009 EA Report – Section 18 – Socio-Economics Implementation of service agreements that pay market rates for publicly-funded services   ●  ●  Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2- 1010

1010 EA Report – Section 18 – Socio-Economics Support local hiring and procurement where feasible to minimize size of workforce hired from outside the criterion-specific LSAs

  ●    Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2- 1011

1011 EA Report – Section 18 – Socio-Economics NextBridge will communicate employment requirements to Indigenous communities in the temporary accommodation LSA to avoid over-estimation of employment volume, and potential associated speculative in-migration to Indigenous communities

  ●    Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2- 1012

1012 EA Report – Section 18 – Socio-Economics The majority of temporary workers hired from out of the criterion-specific LSAs will be housed in construction camps   ●    Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

164 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 1013

1013 EA Report – Section 18 – Socio-Economics Provide first aid stations at construction camps and job sites.   ●    Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2- 1014

1014 EA Report – Section 18 – Socio-Economics Train employees in standard first aid.   ●    Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2-

1015

1015 EA Report – Section 18 – Socio-Economics Maintain at least one licensed emergency medical technician on site with a fully equipped response vehicle that will respond to and handle all medical incidents.

  ●    Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2- 1016

1016 EA Report – Section 18 – Socio-Economics Maintain a zero-tolerance policy towards workers being under the influence of drugs or alcohol while working, or while travelling to and from work.

  ●    Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2- 1017

1017 EA Report – Section 18 – Socio-Economics Maintain drug-free construction camps and worksites.   ●    Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2- 1018

1018 EA Report – Section 18 – Socio-Economics Hold workers to both a Worker Code of Conduct and a Health and Safety Management Plan.   ●    Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2- 1019

1019 EA Report – Section 18 – Socio-Economics Project construction and operation activities will be undertaken with appropriate safety measures in place   ●  ●  Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2- 1020

1020 EA Report – Section 18 – Socio-Economics Contractors will be required to comply with the Ontario Occupational Health and Safety Act, 1990 and other legislated safety requirements. The General Contractor (Valard) will also be required to have a HASP in place

  ●    Valard EMS; Adherence to CEPP and DPP; EWT Safety Orientation; MOL Safety Orientation

Ongoing In Progress

2- 1021

1021 EA Report – Section 18 – Socio-Economics During Project training and orientation, the requirement for respectful use of community facilities and the need for respectful behavior will be stressed

  ●    Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

2- 1022

1022 EA Report – Section 18 – Socio-Economics Obtain permits for all road signage within 400 m of any limit of a provincial highway per the Public Transportation and Highway Improvement Act, 1990.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified in applicable permits and authorizations

No permits required per correspondence with MTO, compliance with Project Traffic Management Plan

Yes

2- 1023

1023 EA Report – Section 18 – Socio-Economics Obtain oversize/overweight permits for the transportation of overweight vehicles and loads on provincial highways under the Highway Traffic Act.

  ●    Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified in applicable permits and authorizations

Complete for 2019; ongoing for remaining Project construction

Yes

2- 1024

1024 EA Report – Section 18 – Socio-Economics Vehicle use on roads will be in accordance with applicable laws (e.g., speed limit, road weight restriction), and road use agreements (e.g., load restrictions).

●  ●  ●  Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 1025

1025 EA Report – Section 18 – Socio-Economics Workers will be required to adhere to an Employee and Contractor Code of Conduct that outlines appropriate behavior at the worksite, construction camps, in community well-being LSA communities, and while travelling to and from work rotations

  ●  ●  Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 1026

1026 EA Report – Section 19 – Non-Traditional Land and Resource Use

Adhere to required federal, provincial and municipal provisions/conditions for land use policy, designation and by law compatibility (i.e., associated with federal patent lands (external), First Nations reserve lands, the Provincial Policy Statement (PPS), Crown Use Policy Atlas (CLUPA) Crown Use Atlas Harmonization), CLUAH Management Guidelines, D-1 and D-6 Environmental Land Use Planning Guides, municipal official plans).

●  ●    Valard EMS; Adherence to CEPP and DPP

Ongoing In Progress

165 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 1027

1027 EA Report – Section 19 – Non-Traditional Land and Resource Use

Mitigation measures and buffers will seek to be consistent with D-1 Land Use and Compatibility (Government of Ontario 1995a), D-6 Compatibility between Industrial Facilities (Government of Ontario 1995b) to the extent feasible.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Ongoing In Progress

2- 1028

1028 EA Report – Section 19 – Non-Traditional Land and Resource Use

Negotiate with the affected outdoor tourism operators to develop appropriate strategies to facilitate continued, uninterrupted use and access to outdoor tourism and recreation resources, to the extent feasible.

  ●    Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Ongoing In Progress

2- 1029

1029 Appendix 1-V-A-1a – MECP Comments on the Amended EA Report (EAPB)

Appendix 1-V-A-2 – MNRF Comments on the Amended EA Report

NextBridge commits to providing a DPP for each construction workfront and each provincial park and conservation reserve where construction will occur. Per the tables of contents agreed upon with the MECP and MNRF, the DPPs will include, but not be limited to, the following information:

the pre-construction field reconnaissance approach;

detailed construction schedule and design information;

approaches to protecting environmental values;

training and employment opportunities for Indigenous communities; and

Traditional Ecological Knowledge (TEK)/Traditional Land and Resource Use (TLRU) protocol. The DPPs will be submitted to the MECP and MNRF for review prior to the submission of MNRF permit applications.

●      Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 1030

1030 Appendix 1-V-A-1b – MECP Comments on the Amended EA Report (Indigenous Consultation)

Appendix 1-V-B-1 – MNO Comments on the Amended EA Report

Appendix 1-V-B-4a – SVS Comments on the Amended EA Report

Appendix 1-V-B-4d – BZA Comments on the Amended EA Report

Appendix 1-V-B-5 – Pic Mobert Comments on the Amended EA Report

Michipicoten First Nation Consultation Issues and Concerns

SVS Consultation Issues and Concerns

NextBridge has committed to providing interested Indigenous (First Nation and Métis) communities the opportunity to conduct Project update and permitting workshops. Permitting Workshops are intended to get feedback on the permitting process prior to submission of permit applications, and will involve:

Indigenous communities will be encouraged to identify areas of concern or specific locations of areas of importance;

NextBridge will seek input from Indigenous communities on mitigation measures to address identified areas of concern;

opportunity for revision of the maps of access roads, crossing locations, crossing types and methods;

opportunity for revision of the draft framework for the vegetation management plan;

discussion on the Environmental Emergency Response Plan that will be shared with Indigenous communities once drafted.

Permit applications will be finalized after the permitting workshops.

●      Adherence to CEPP and DPP; Consultation and Engagement Summary Table; permitting workshops completed, ongoing engagement with Indigenous communities

Ongoing In Progress

2- 1031

1031 Appendix 1-V-A-1b – MECP Comments on the Amended EA Report (Indigenous Consultation)

Appendix 1-V-B-1 – MNO Comments on the Amended EA Report

Michipicoten First Nation Consultation Issues and Concerns

SVS Consultation Issues and Concerns

NextBridge has an Aboriginal training and employment program and is committed to working with all interested Indigenous communities through existing relationship frameworks to determine interest in and opportunities to participate in environmental monitoring and environmental inspection work prior to, during and post-construction (decommissioning and operations). NextBridge is also committed to providing MNO with a draft Participation Plan.

●  ●    Adherence to CEPP and DPP; Consultation and Engagement Summary Table; ongoing engagement with Supercom and with Indigenous communities

Ongoing; NextBridge has provided training in environmental monitoring for the Indigenous monitoring program

In Progress

2- 1032

1032 Appendix 1-V-A-1d – MECP Comments on the Amended EA Report (Northern Region)

Appendix 1-V-B-4a – SVS Comments on the Amended EA Report

Appendix 1-V-B-4d – BZA Comments on the Amended EA Report

NextBridge provides the MECP with a monthly Indigenous Consultation Update. The monthly update includes a discussion of consultation and engagement activities by Indigenous community and an update on the status of TEK and TLU reports. NextBridge is committed to providing these monthly updates on an ongoing basis until approval of the environmental assessment.

●      Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 1033

1033 Appendix 1-V-A-1e – MECP Comments on the Amended EA Report (Surface Water)

Appendix 1-V-A-2 – MNRF Comments on the Amended EA Report

Appendix 1-V-A-3 – DFO Comments on the Amended EA Report

Michipicoten First Nation Consultation Issues and Concerns

NextBridge is planning a substantial field program starting in Q2 2018 to survey fish and fish habitat and to collect hydrologic data to inform the design of crossing structures and to support the necessary permits and approvals for the Project. This data will be provided to the MECP and MNRF and included in the applicable DPPs and permit applications.

●      Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Complete Yes

166 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 1034

1034 Appendix 1-V-A-2 – MNRF Comments on the Amended EA Report

NextBridge will undertake field studies at points along the Loon Lake/Dorion greenfield route in spring and summer of 2018. These studies will include the field investigations as contemplated for 2017 (i.e., for species at risk bats) and for waterbody crossings. The results of these field studies will be submitted to the MECP and MNRF in the applicable DPPs prior to the submission of relevant final permit applications.

●      Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Complete Yes

2- 1035

1035 Appendix 1-V-A-2 – MNRF Comments on the Amended EA Report

NextBridge will undertake a pre-construction site reconnaissance to ground-truth the Project footprint and structure placement, and identify which wetlands have the potential to be avoided during the detailed design phase, and which wetlands cannot be avoided during the detailed design phase. An assessment will be completed in advance of disturbance to wetlands to identify impacts and identify whether additional mitigation is required. This information will be submitted to the MECP and MNRF in the applicable DPPs.

●      Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Reconnaissance and seasonal pre-construction environmental surveys and flagging completed for 2019 under guidance of resource specialists; ongoing for remaining Project construction

Yes

2- 1036

1036 Appendix 1-V-A-2 – MNRF Comments on the Amended EA Report

NextBridge commits to prepare the following documents updated against detailed design, results of field surveys and approval conditions from permits to the applicable regulators 30 days prior to construction:

Construction Environmental Protection Plan (CEPP);

Operation Environmental Management Plan (OEMP);

Transmission Vegetation Management Program; and

Decommissioning Plan for Temporary Project Infrastructure.

●      Submitted to Agencies on July 15, 2019

Appropriate documents have been developed and submitted to the agencies

Yes

2- 1037

1037 Appendix 1-V-A-2 – MNRF Comments on the Amended EA Report

A Timber Salvage Plan will be prepared and submitted to regulators at least 30 days prior to construction. ●      Included with the DPPs

Appropriate documents have been developed and submitted to the agencies

Yes

2- 1038

1038 Appendix 1-V-A-2 – MNRF Comments on the Amended EA Report

Appendix 1-V-C-1 – RCCSC Comments on the Amended EA Report

NextBridge commits to install the structure at this location (the Kama Cliffs Conservation Reserve) via helicopter and to remove the access road overlapping the Mazukama Falls area from the Project footprint.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Not applicable to 2019 construction activities

Not Started

2- 1039

1039 Appendix 1-V-A-3 – DFO Comments on the Amended EA Report

NextBridge commits to continue early and frequent consultation with DFO as detailed designs proceed to ensure that:

the site-specific blasting plan is adequately designed to avoid or minimize causing serious harm to fish for blasting operations located in or near-water;

proposed temporary workspaces are not likely to result in serious harm to fish; and

proposed culverts are adequately sized to not impede fish migration between upstream and downstream habitats.

●      Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

2019 construction activities completed under DFO LOA; did not include blasting activities.

Yes

2- 1040

1040 Appendix 1-V-A-3 – DFO Comments on the Amended EA Report

NextBridge commits to continue early and frequent consultation with DFO and the MNRF to identify the new/improvement access road equipment water body crossings within species-at-risk critical habitat.

●      Valard EMS; Adherence to the CEPP, DPP, regulations and requirements identified if applicable permits and authorizations Consultation and Engagement Summary Table

Complete for 2019; ongoing for remaining Project construction

Yes

167 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 1041

1041 Appendix 1-V-A-4 – ISC Comments on the Amended EA Report

Appendix 1-V-B-4a – SVS Comments on the Amended EA Report

NextBridge commits to abide by the 30 to 90 metre (m) slope dependent buffer method listed in the MNRF’s Forest Management Guide for Conserving Biodiversity at the Stand and Site Scales (MNR 2010a) in order to protect adjacent water bodies.

  ●    Valard EMS; Adherence to CEPP and DPP, regulations and requirements identified if applicable permits and authorizations; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

2- 1042

1042 Appendix 1-V-B-1 – MNO Comments on the Amended EA Report

Should additional TWS be required that will trigger a duty to consult. Specifically, NextBridge will ensure that MNO is notified of changes to the Project footprint and will be consulting with the regulators such as the MNRF regarding use of lands as part of the Crown land permitting and other permitting processes.

●      Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 1043

1043 Appendix 1-V-B-1 – MNO Comments on the Amended

EA Report

Appendix 1-V-B-4a – SVS Comments on the Amended EA Report

Michipicoten First Nation Consultation Issues and Concerns

NextBridge commits to develop a detailed Vegetation Management Plan that outlines the types and uses of herbicides, and protocols to control invasive species. NextBridge is committed to providing a draft framework for this plan to Indigenous communities for consultation and incorporating feedback before finalization of the plan. The Vegetation Management Plan will be distributed to communities, and updates to the Vegetation Management Plan will be provided in writing to interested communities.

●      Adherence to CEPP and DPP; Consultation and Engagement Summary Table; permitting workshops completed, ongoing engagement with Indigenous communities

Ongoing In Progress

2- 1044

1044 Appendix 1-V-B-1 – MNO Comments on the Amended EA Report

NextBridge commits to working with the MNO on an Access Management Agreement. ●      Completion of a Project Agreement

No further action

Yes

2- 1045

1045 Appendix 1-V-B-3 – RSMIN Comments on the Amended EA Report

NextBridge committed to a meeting between RSMIN and NextBridge’s licensed archaeology consultant. This meeting took place June 4, 2018. The purpose of the meeting was for RSMIN to identify sites of concern directly to the consultant. NextBridge is committed to sharing the results of the finalized Stage 2 reports after they have been accepted by MTCS.

●      Meeting completed

No further actions Yes

2- 1046

1046 Appendix 1-V-B-3 – RSMIN Comments on the Amended EA Report

NextBridge is committed to ensuring a clear and respectful relationship with RSMIN including that Aboriginal rights are respected and NextBridge’s regulatory obligations are upheld. NextBridge is committed to ensuring that RSMIN is fully informed about procurement and training opportunities and NextBridge views procurement and training opportunities as potential economic benefits from the Project but they are separate from the Duty to Consult obligations. NextBridge is committed to facilitating discussions between RSMIN and Supercom to ensure that RSMIN is informed about procurement and training procedures.

●      Valard EMS; Adherence to CEPP and DPP, Consultation and Engagement Summary Table; EAS and Construction Access Alignment Sheets

Ongoing In Progress

2- 1047

1047 Appendix 1-V-B-4a – SVS Comments on the Amended EA Report

Michipicoten First Nation Consultation Issues and Concerns

NextBridge has committed to focusing potential herbicide application during a 2-month window in the fall in order to avoid or mitigation potential impacts. See Vegetation Management Plan commitments above.

    ●  Adherence to Vegetation Management Plan

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 1048

1048 Appendix 1-V-B-5 – Pic Mobert Comments on the Amended EA Report

NextBridge will consider Pic Mobert’s feedback when surveying the location of the temporary construction easement crossing the tributary to Doss Lake. If crossing the tributary cannot be avoided, NextBridge will implement appropriate mitigation measures, including to not encroach into the 30 m buffer where feasible and to comply with approval conditions for the temporary construction easement. NextBridge also commits that no equipment will ford or be placed in the tributary.

  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Not applicable to 2019 construction activities

Not Started

168 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 1049

1049 Appendix 1-V-C-1 – RCCSC Comments on the Amended EA Report

NextBridge commits that the permanent access road to transmission structures B088 and B089 will be a temporary access road for use during construction. NextBridge will access these structures on foot from the Trans-Canada Highway to the west or from B090 and Maatas Road to the east during the operation phase for routine maintenance. As previously indicated, NextBridge commits to consult on how to decommission the roads.

●  ●  ●  Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Not applicable to 2019 construction activities

Not Started

2- 1050

1050 Appendix 1-V-C-1 – RCCSC Comments on the Amended EA Report

NextBridge commits that the height of transmission structures B088 and B089 will be raised to span over the canopy and to limit the clearing. This change can be reviewed with RCCSC during a future consultation meeting.

●      Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Not applicable to 2019 construction activities

Not Started

2- 1051

1051 Appendix 1-V-A-5 – MNRF Comments on the Amended EA Report

Temporary access roads will be decommissioned in consultation with the MNRF and in accordance to the MNRF’s Forest Management Guide for Conserving Biodiversity at the Stand and Site Scales (OMNR 2010).

  ●    Valard EMS; Adherence to CEPP and DPP

2019 construction activities did not include decommissioning activities

Not Started

2- 1052

1052 Appendix 1-V-A-5 – MNRF Comments on the Amended EA Report

Where there are no reasonable alternatives to avoid the CLVA in Gravel River Conservation Reserve, NextBridge will use low-pressure tread equipment and rig mats, and other mitigation measures agreed upon with the MNRF

  ●    Valard EMS; Adherence to CEPP and DPP

Not applicable to 2019 construction activities

Not Started

2- 1053

1053 Appendix 1-V-A-6 – MNRF Comments on the Amended EA Report

An overlapping agreement will be in place with the SFL holder in advance of harvest ●      Valard EMS; Adherence to CEPP and DPP

Complete for 2019; ongoing for remaining Project construction

Yes

2- 1054

1054 SVS Consultation Issues and Concerns NextBridge continues to be committed to establishing an Aboriginal Community Advisory Board (ACAB) for interested Aboriginal communities. The Terms of Reference (TOR), which has been circulated to all communities as well as the MECP and the Ontario Energy Board, identifies, the mandate, roles and responsibilities, geographic scope, principles and values, expenses and dissemination of information and reports. NextBridge is committed to re-circulating the revised Terms of Reference, which will explicitly outline the decision-making and oversight role of ACAB representatives, specify that environmental reports from regulatory needs will be provided to ACAB members in the Fall of 2018, and requesting feedback and comments.

  ● ● Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 1055

1055 SVS Consultation Issues and Concerns NextBridge is committed to discussing environmental initiatives such as exploration of potential partnerships (conservancy, GHG reduction, etc.), water protection initiatives and support opportunities for locally-based environmental improvements in operating communities) with interested Indigenous communities for the EWT Line Project

    ● Adherence to OEMP

Operational activity commitments are not currently applicable. Project is still under construction.

Not Started

2- 1056

1056 SVS Consultation Issues and Concerns NextBridge commits to using the ACAB as a vehicle to work closely with each community to identify post-construction relationship issues such as: environmental monitoring, data collection and analysis opportunities.

  ● ● Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 1057

1057 SVS Consultation Issues and Concerns NextBridge will discuss the need for proper planning and early and meaningful communication regarding environmental monitors' schedules.

●      Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 1058

1058 SVS Consultation Issues and Concerns NextBridge commits to ensuring all 18 identified First Nation and Métis communities have capacity resources to undertake tasks and engagement for the Project. The ACAB is the proposed vehicle to identify long-term tasks and activities communities wish to undertake. Development and undertaking of community-identified projects during operations will be supported by the ACAB including capacity resources.

●  ●  ●  Valard EMS; Adherence to CEPP and DPP; Consultation and Engagement Summary Table

Ongoing In Progress

2- 1059

1059 SVS Consultation Issues and Concerns The identification of merchantable timber and the processing and disposal of that resource is governed by Ontario regulations. NextBridge is committed to ensuring that it meets applicable regulations and consults with potentially impacted First Nation and Métis communities regarding these activities, while identifying that discussions about rights to harvest firewood should be addressed to the MNRF.

●  ●    Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Complete for 2019; ongoing for remaining Project construction

Yes

169 2019-06-21_Nextbridgeewt_Condition4_Compliance-Monitoring-Program_Rev3  

ID No.

EA Commitment

Number

Reference to Commitment in EA Report

EA Commitment

Implementation Schedule

Evidence of Compliance

Status/Remarks

Compliance Achieved?

(Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

2- 1060

1060 SVS Consultation Issues and Concerns As part of the proposed construction-phase, First Nation and Métis monitoring program, NextBridge will discuss with those interested in participating the opportunity to specifically address moose sightings and recording. In addition, through the proposed ACAB, NextBridge is committed to ensuring long-term tasks and activities are identified and environmental reporting is discussed and distributed to ensure communities are aware of the ongoing impacts of the Project on wildlife and habitat.

●  ●    Valard EMS; EAS and Construction Access Alignment Sheets; Adherence to CEPP and DPP

On Going In Progress

2- 1061

1061 RSMIN Consultation Issues and Concerns NextBridge is committed to working with RSMIN during the permitting phase to develop a capacity funding agreement (CFA) that includes updating GIS Analysis of the Project; updating archeological mapping analysis; capacity for RSMIN to conduct internal information gathering; capacity to engage with NextBridge via in-person meetings, teleconferences and other correspondences; and reasonable technical and administrative costs. NextBridge is committed to incorporating permit phase advice and feedback from RSMIN into the Environmental Protection Plan and relevant Environmental Alignment Sheets. NextBridge is committed to working with RSMIN to ensure any outstanding costs and expenses related to their engagement to date on the Environmental Assessment phase of the Project are reimbursed based on submission of invoices.

●      Valard EMS; Adherence to CEPP and DPP; EAS and Construction Access Alignment Sheets

Ongoing In Progress

 

26 

 

                  

ATTACHMENT B TABLE 3‐1 EA ACT APPROVAL CONDITIONS COMPLIANCE 

MONITORING  

1  

Table 3-1: EA Act Approval Conditions Compliance Monitoring

ID No.

Reference to

Approval Condition

in EA Report

EA Act Approval Condition

Implementation Schedule

Evidence of Compliance

Status/Remarks Compliance

Achieved? (Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

General Requirements      

3-1 Applicable (N.A.), see Notice of Approval to Proceed with the Undertaking (March 21,

2012)

2.1 The proponent shall comply with the provisions in the environmental assessment which are hereby incorporated in this approval by reference except as provided in these conditions and as provided in any other approval or permit that may be issued for the undertaking.

●  ●  ●  Adherence to CEPP, DPP, Environmental Alignment Sheets (EAS), Construction Access Alignment Sheets, and regulations and requirements identified within the applicable permits and authorizations.

Complete for 2019, ongoing for remaining for remaining Project construction

Yes

3-2 N.A. The proponent shall fulfill all commitments made in the environmental assessment. ●  ●  ●  Adherence to CEPP, DPP, EAS, Construction Access Alignment Sheets, and regulations and requirements identified within the applicable permits and authorizations.

Complete for 2019, ongoing for remaining for remaining Project construction

Yes

3-3 N.A. These conditions of the Notice of Approval do not prevent more restrictive conditions being imposed under other statutes.

●  ●  ●  Adherence to CEPP, DPP,

EAS, Construction Access Alignment Sheets, and regulations and requirements identified within the applicable permits and authorizations.

N.A Yes

Public Record      

3-4 N.A. 3.1 Where a document is required for the public record, the proponent shall post the document on the proponent website and shall provide one hardcopy and one electronic copy of the document to the Director.

●  ●  ●  Refer to the proponents website: https://www.nextbridge.ca/

All required public documents are posted on https://www.nextbridge.ca/

Yes

3-5 N.A. 3.2 The environmental assessment Reference Number 13136 and the File Number 03-03-03 shall be quoted on all documents submitted to the ministry pursuant to this Notice of Approval.

●  ●  ●  The EA reference number and file number have been included on all reports submitted to MECP.

Refer to each report cover page.

Yes

3-6 N.A. 3.3 For every document submitted to the ministry, the proponent shall clearly identify which condition of approval the document is meant to fulfill.

●  ●  ●  The documents submitted to MECP by the proponent have clearly identified the condition(s) of the approval is meant to fulfill.

Refer to each submittal. Yes

Compliance Monitoring Program      

3-7 N.A. 4.1 The proponent shall prepare and submit to the Director for approval and for the public record an environmental assessment compliance monitoring program.

●      Refer to the East-West Tie Transmission Project Environmental Assessment Compliance Monitoring Program, submitted to the ministry on April 30, 2019 and approved on June 26, 2019. Posted on the proponents website: https://www.nextbridge.ca/public-record-documents.

Refer to the Compliance Monitoring Program submitted to the ministry on April 30, 2019 and approved on June 26, 2019.

Yes

2  

ID No.

Reference to

Approval Condition

in EA Report

EA Act Approval Condition

Implementation Schedule

Evidence of Compliance

Status/Remarks Compliance

Achieved? (Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

3-8 N.A. 4.2 The compliance monitoring program shall be submitted to the Director for approval within one year from the Date of Approval, or 60 days before the commencement of construction, whichever is earlier; or by another date agreed upon by the Director.

●      Refer to the East-West Tie Transmission Project Environmental Assessment Compliance Monitoring Program, submitted to the ministry on April 30, 2019 and approved on June 26, 2019. Posted on the proponents website: https://www.nextbridge.ca/public-record-documents

Refer to the Compliance Monitoring Program submitted to the ministry on April 30, 2019 and approved on June 26, 2019.

Yes

3-9 N.A. 4.3 The compliance monitoring program shall include a description of how the proponent will: a. monitor implementation of the undertaking in accordance with the environmental assessment with respect to mitigation measures, public consultation, indigenous consultation and additional studies and work to be carried out; b. monitor compliance with the conditions in this Notice of Approval; and c. monitor compliance with all commitments made in the environmental assessment with respect to mitigation measure, public consultation, and additional studies and work to be carried out.

●      Refer to the East-West Tie Transmission Project Environmental Assessment Compliance Monitoring Program, dated June 2019.

Refer to the June, 2019 Compliance Monitoring Program

Yes

3-10 N.A. 4.4 The compliance monitoring program must contain an implementation schedule for monitoring activities to be completed.

●      Refer to the East-West Tie Transmission Project Environmental Assessment Compliance Monitoring Program, dated June 2019.

Refer to the June, 2019 Compliance Monitoring Program.

Yes

3-11 N.A. 4.5 The Director may require the proponent to amend the compliance monitoring program at any time. Should an amendment be required, the Director will notify the proponent in writing of the required amendment and the date by which the proponent must complete and submit the amendment to the Director.

●  ●  ● A request for amendment from the Director has not been received at this time.

N.A. Yes

3-12 N.A. 4.6 The proponent shall submit the amended compliance monitoring program to the Director within the time period specified by the Director in the written notice.

●  ●  ●  A request for amendment from the Director has not been received at this time.

N.A. Yes

3-13 N.A. 4.7 The proponent shall implement the compliance monitoring program and any amendments to it.

●  ●  ●  Adherence to CEPP, DPP, EAS, Construction Access Alignment Sheets, and regulations and requirements identified within the applicable permits and authorizations.

Complete for 2019, ongoing for remaining for remaining Project construction

Yes

Compliance Reporting      

3-14 N.A. 5.1 The proponent shall prepare an annual compliance report outlining the results of the compliance monitoring program (Condition 4).

  ●  ●  A 2019 Compliance Report

dated May 26, 2020 was submitted to the Director of MECP.

Submitted to the Director of the MECP.

Yes

3-15 N.A. 5.2 The first compliance report shall be submitted to the Director for review and for the public record no later than on year following the Date of Approval. Each subsequent annual compliance report shall be submitted on the date that is the anniversary of the Date of Approval thereafter. Each report shall cover the previous year.

  ●  ●  A 2019 Compliance Report dated May 26, 2020 was submitted to the Director of MECP on May 27, 2020 based on an extension granted March 19, 2020.

Submitted to the Director of the MECP.

Yes

3-16 N.A. 5.3 The proponent shall submit annual compliance report until all conditions in this Notice of Approval are satisfied or the proponent is instructed otherwise in writing by the Director.

  ●  ●  An annual compliance report will be submitted until all conditions of the Notice of Approval are satisfied or until otherwise instructed by the MECP.

Complete for 2019, ongoing for remaining Project construction

In Progress

3-17 N.A. 5.4 The proponent shall notify the Director in writing when the final annual compliance report is being submitted. The ministry will confirm whether the annual compliance reporting requirements in Conditions 5.1 to 5.3 have been fulfilled and the Director will confirm this in writing to the proponent.

  ●  ●  A 2019 Compliance Report dated May 26, 2020 was submitted to the Director of MECP on May 27, 2020 based on an extension granted March 19, 2020.

Submitted to the Director of the MECP.

Yes

3  

ID No.

Reference to

Approval Condition

in EA Report

EA Act Approval Condition

Implementation Schedule

Evidence of Compliance

Status/Remarks Compliance

Achieved? (Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

3-18 N.A. 5.5 The proponent shall retain, either in the proponent’s office or in another location approved by the Director, copies of the annual compliance reports for each reporting year and any associated documentation of compliance monitoring activities. The proponent shall post the annual compliance reports for each reporting year on its website.

  ●  ●  The 2019 annual compliance report has been retained within the proponents office.

The 2019 annual compliance report will be posted at https://www.nextbridge.ca/ once the Director has determined the report is complete.

In Progress

3-19 N.A. 5.6 The proponent shall make the compliance reports and associated documentation available to the Director or any designate in a timely manner when requested to do so by the ministry.

  ●  ●  A 2019 Compliance Report dated May 26, 2020 was submitted to the Director of MECP on May 27, 2020 based on an extension granted March 19, 2020.

Submitted to the Director of the MECP.

Yes

Complaint Protocol      

3-20 N.A. 6.1 The proponent shall prepare and implement a compliant protocol for dealing with and responding to inquiries and complaints during all stages of the undertaking. The complaint protocol shall include a procedure for notifying the Regional Director of any complaints received by the proponent.

●  ●  ●  The Complaint Protocol was submitted to the ministry on June 7, 2019 and approved on June 26, 2019. The approved Complaint Protocol is accessible at https://www.nextbridge.ca/

Complete Yes

3-21 N.A. 6.2 The proponent shall submit the complaint protocol to the Director for approval and for the public record within one year from the Date of Approval, or 30 days before the start of construction, whichever is earlier; or by another date agreed upon by the Director.

●      The Complaint Protocol was submitted to the ministry on June 7, 2019 and approved on June 26, 2019. The approved Complaint Protocol is accessible at https://www.nextbridge.ca/

Complete Yes

3-22 N.A. 6.3 The Director may require the proponent to amend the compliant protocol at any time. Should an amendment be required, the Director shall notify the proponent in writing of the amendment required and when the amendment must be completed.

●  ●  ●  A request for amendment from the Director has not been received at this time.

N.A. Yes

3-23 N.A. 6.4 The proponent shall submit the amended complaint protocol to the Director within the time period specified by the Director. ●  ●  ●  A request for amendment from the Director has not been received at this time.

N.A. Yes

3-24 N.A. 6.5 The proponent shall implement the complaint protocol and any amendments to it.       Formal Complaint Protocol accessible at https://www.nextbridge.ca/

Ongoing In progress

3-25 N.A. 6.6 The proponent shall provide a summary on the complaints received and how they were addressed in each of the annual compliance repots required by Condition 5.

●  ●  ●  A 2019 Compliance Report dated May 26, 2020 was submitted to the Director of MECP.

Refer to Table 3 within the 2019 Compliance Report

Yes

Consultation with Indigenous Communities      

3-26 N.A. 7.1 The proponent shall prepare, in consultation with Indigenous Communities, an Indigenous consultation plan that sets forth: a. how, during implementation of the undertaking, the proponent will consult with Indigenous Communities and provide them with opportunities to be involved in environmental monitoring activities; b. how the proponent will notify Indigenous Communities, using a notification protocol, if archaeological resources or Indigenous remains are encountered during implementation of the undertaking; c. how the proponent will consider any additional traditional ecological knowledge and traditional land and resource use information that Indigenous Communities may provide during the implementation of the undertaking; and d. how the proponent will issue notices and updates to Indigenous communities on key steps during the implementation of the undertaking.

●      The original Indigenous consultation plan was submitted on April 15, 2019 and approved on July 8, 2019.

N.A. Yes

4  

ID No.

Reference to

Approval Condition

in EA Report

EA Act Approval Condition

Implementation Schedule

Evidence of Compliance

Status/Remarks Compliance

Achieved? (Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

3-27 N.A. 7.2 At least 30 days prior to the start of construction of by such other date as may be agreed to in writing by the Director, the proponent shall submit the Indigenous consultation plan to the Director for approval, including details of the consultation that was undertaking with Indigenous Communities on the plan, as required by Condition 7.1.

●      The original Indigenous consultation plan was submitted on April 15, 2019 and approved on July 8, 2019.

N.A. Yes

3-28 N.A. 7.3 The Director may require the proponent to amend the Indigenous consultation plan at any time. Should an amendment be required, the Director shall notify the proponent in writing of the amendment required and when the amendment must be completed.

●  ●  ●  A request for amendment from the Director has not been received at this time.

N.A. Yes

3-29 N.A. 7.4 Once the Director is satisfied with the Indigenous consultation plan, the proponent shall implement the Indigenous consultation plan and any amendments to it.

●  ●  ●  Consultation and Engagement Summary Table

Complete for 2019; ongoing for remaining Project construction

Yes

Detailed Project Plans      

3-30 N.A. 8.1 The proponent shall prepare Detailed Project Plan(s) to verify and supplement the information in the environmental assessment. This information will be submitted as an over-arching plan for the undertaking as well as multiple individual workfront plans according to how the proponent phases the construction of the undertaking, such as by geographic groupings, timing window and/ or types of project activities. Detailed Project Plan(s) will be used to fulfill the requirements of this Condition and to assist in fulfilling the permitting requirements of the Ministry of Natural 4-31Resources and Forestry and the Ministry of Environment Conservation and Parks.

●      Overarching DPP and workfront specific DPPs were submitted on: Overarching July 30, 2019; WF1 July 17, 2019; WF2 August 9, 2019; WF3 August 27, 2019; WF4 October 25, 2019; WF5 November 8, 2019; WF6 September 13, 2019; WF7 July 24, 2019; WF8 August 01, 2019; WF9 October 15, 2019; WF10 October 25, 2019; WF11 November 14, 2019; Black Sturgeon River PP July 31, 2019; Ruby Lake PP September 24, 2019; Kwinkwaga CR September 07, 2019; Pukaskwa River PP November 26, 2019

Complete Yes

3-31 N.A. 8.2 Over-arching Detailed Project Plan(s) shall describe and include: a. plans and/or protocols, including, but not limited to, Timber Salvage Plan, Unmapped Stream Assessment Protocol, Best Management Practices, Sediment Control Plan, Road Use Management Strategy, Vegetation Management Plans; and b. details for how all phases of the project (i.e. pre-construction, construction, maintenance, decommissioning) as it relates to significant environmental features, as well as plans and/or protocol described in 8.2 (a).

●      Overarching DPP has been submitted July 30, 2019.

Complete Yes

5  

ID No.

Reference to

Approval Condition

in EA Report

EA Act Approval Condition

Implementation Schedule

Evidence of Compliance

Status/Remarks Compliance

Achieved? (Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

3-32 N.A. 8.3 Workfront Detailed Project Plan(s) shall describe and include project specific impacts and information outlining: a. the final locations and footprint of project components, inclusive of any amendments that are approved under Condition 10; and project activities planned to occur within a specific individual workfront of the undertaking and the timing window for these activities, including the construction, operation, maintenance and decommissioning phases, as applicable; b. significant environmental features (including, but not limited to, Species at Risk, wetlands, watercourses, significant wildlife habitat, Protected Areas); environmental constraints; and unexpected environmental conditions in the area(s) where specific project activities are planned; c. site-specific mitigation for significant environmental features (including, but not limited to, wetlands, Species at Risk, significant wildlife habitat, Protected Areas); and maintaining vegetation setbacks on all waterbodies and watercourses; d. monitoring plans for the project activities; e. consultation plan with Indigenous communities, and stakeholders; and, f. detailed mapping at sufficient scale to display the information listed above.

●      Overarching DPP and workfront specific DPPs were submitted on: Overarching July 30, 2019; WF1 July 17, 2019; WF2 August 9, 2019; WF3 August 27, 2019; WF4 October 25, 2019; WF5 November 8, 2019; WF6 September 13, 2019; WF7 July 24, 2019; WF8 August 01, 2019; WF9 October 15, 2019; WF10 October 25, 2019; WF11 November 14, 2019; Black Sturgeon River PP July 31, 2019; Ruby Lake PP September 24, 2019; Kwinkwaga CR September 07, 2019; Pukaskwa River PP November 26, 2019

Complete Yes

3-33 N.A. 8.4 The proponent shall submit the Detailed Project Plan(s) to: a. the Director, b. the Ministry of Natural Resources and Forestry’s Director of Northwest Region, and c. Indigenous Communities.

●      The DPPs have been provided to the Director MNRF Director of NW Region and were provided to Indigenous communities via proponent’s Sharepoint site as per dates outlined in Indigenous Consultation Log.

Complete Yes

3-34 N.A. 8.5 The proponent shall provide over-arching Detailed Project Plan(s) prior to workfront Detailed Project Plan(s). The proponent shall provide a minimum of 30 days review for each Detailed Project Plan by the parties listed in Condition 8.4 prior to carrying out any construction activities for any portion of the undertaking covered by those plans.

●      Overarching DPP has been submitted

Complete Yes

3-35 N.A. 8.6 The proponent shall post the Detailed Project Plan(s) on the proponent’s website and provide notification to interested stakeholders that were notified of the undertaking during the environmental assessment.

●      Refer to the proponent’s website: https://www.nextbridge.ca/public-record-documents

DPP documents are posted on https://www.nextbridge.ca/public-record-documents

Yes

3-36 N.A. 8.7 If adverse impacts on Aboriginal or treaty rights are identified through consultation with Indigenous communities on the Detailed Project Plan(s), the proponent must notify the Director in writing. The Director may require the proponent to amend the Detailed Project Plan(s) or carry-out additional consultation at any time to address potential adverse impacts on Aboriginal or treaty rights. The proponent shall consult with the ministry about any consultation requirements that may apply.

●      No adverse impacts on Aboriginal or treaty rights were identified

Complete Yes

3-37 N.A. 8.8 If changes are required to be made to Detailed Project Plan(s) after it has been submitted, the proponent shall determine if the proposed change: a. would result in a change to the undertaking that is outside of the Limits of Work; or b. could result in greater adverse environmental effects than were identified in the environmental assessment

If the proposed changes to the Detailed Project Plan(s) would result in either (a) or (b) above, the proponent shall notify the minister in accordance with Condition 10. Otherwise, the proponent may proceed with the proposed change, subject to any permitting requirements.

●  ●  ●  No changes to the Limits of Work have occurred, and no changes to the overarching or workfront specific DPPs have been made.

N.A. Yes

3-38 N.A. 8.9 At the end of the construction phase of the undertaking, the proponent shall provide the ministry with a summary of how Condition 8 has been satisfied in the following compliance require requirement by Condition 5.

    ●  N.A. N.A. Not Started

Vegetation Removal      

3-39 N.A. 9.1 Use mechanical methods to remove unwanted vegetation whenever possible and only using chemical means when deemed necessary, in consultation with Indigenous communities and the Ministry of Natural Resources and Forestry.

●  ●  ●  Adherence to CEPP, DPP, and EAS.

Mechanical clearing methods are being used.

In Progress

6  

ID No.

Reference to

Approval Condition

in EA Report

EA Act Approval Condition

Implementation Schedule

Evidence of Compliance

Status/Remarks Compliance

Achieved? (Yes / In Progress / Not

Started)

Prior to

Construction

Construction

Operation

Change to the Undertaking      

3-40 N.A. 10.1 The proponent shall notify the Director in writing of any proposed change to the undertaking that is outside of the Limits of Work or that could result in greater adverse environmental effects that were identified in the environmental assessment. The proponent shall consult with the ministry about any consultation requirements that may apply, and whether any changes can be permitted without an amendment to the environmental assessment.

●  ●  ●  No changes to the Limits of Work have been proposed at this time.

N.A. Yes

Duration of Approval      

3-41 11.1 If construction of the undertaking has not commenced within 10 years of the Date of Approval, this Notice of Approval shall expire unless otherwise extended by the Minister.

●  ●    Construction will be completed within 10 years of the Notice of Approval.

N.A. Yes