acss511 statutory control lecture 06/03/12

Post on 12-Jun-2015

670 Views

Category:

Technology

4 Downloads

Preview:

Click to see full reader

DESCRIPTION

Building Control Part 2

TRANSCRIPT

Tuesday 6th March 2012

ACSS511: Statutory Control 3

Describe the various procedures by which the building control system is administered.

ACSS511: Statutory Control 4

ACSS511: Statutory Control 5

Full Plans procedure

Building Notice procedure

ACSS511: Statutory Control 6

Prepare plans, spec, calcs etc.

Submit application form with supporting info and fee

LA scrutinise proposals Approval or rejection

ACSS511: Statutory Control 7

Site / location plans Detailed plans,

sections Technical details Calculations Drainage info Means of access

ACSS511: Statutory Control 8

ACSS511: Statutory Control 9

Minimum: two copies If Regulatory Reform

(Fire Safety) Order 2005 applies – further copies required.

ACSS511: Statutory Control 10

Payable in two stages

First fee accompanies plan submission

Second fee payable after first site inspection

ACSS511: Statutory Control 11

Scrutinise for compliance with regs

Consult other authorities (e.g. fire)

Prescribed period of 5 weeks, or 2 months with consent of applicant

ACSS511: Statutory Control 12

If plans comply with Building Regs - approval notice issued

If plans don’t comply they may be rejected, and defects specified

Conditional approval may be issued with consent of applicant

ACSS511: Statutory Control 13

Usually resubmitted with amendments

Applicant may refer matter to DCLG for determination

ACSS511: Statutory Control 14

A notice is submitted to LA

Work may commence 48 hours later

ACSS511: Statutory Control 15

Building notice form

Block plan? Insulation details? Hot water system

details?

ACSS511: Statutory Control 16

BN cannot be used if Regulatory Reform (Fire Safety) Order 2005 applies to building in question.

BN is intended for small scale minor works

ACSS511: Statutory Control 17

Single fee payable Same as combined

plan / inspection fee

ACSS511: Statutory Control 18

LA does not approve or reject notice

Further information may be demanded

ACSS511: Statutory Control 19

If FP procedure used – advisable to wait for LA approval notice

However, regardless of which procedure used – work may commence 48 hours after notice is given to LA

ACSS511: Statutory Control 20

Commencement – 2 days Foundation excavated – 1 day Foundation constructed – 1 day DPC – 1 day Oversite preparation – 1 day Drains ready for inspection – 1 day Drains backfilled /ready for test – within 5

days Occupation prior to completion – 5 days Completion of work – within 5 days

ACSS511: Statutory Control 21

Mandatory if Regulatory Reform (Fire Safety) Order 2005 applies to building

In other cases – only if requested

LA not required to issue if BN procedure used

ACSS511: Statutory Control 22

Full Plans◦ Proposals appraised – proceed with

confidence◦ Time taken – up to 2 months

Building Notice◦ Speed and simplicity◦ Risk that work may have to be taken down if

not in compliance

ACSS511: Statutory Control 23

Two possible contraventions:◦ Procedures not followed◦ Work doesn’t comply with

Regs LA’s duty to enforce

Building Regs Usually seek to do it

informally Formal proceedings Fines up to £5000+

A form of ‘self-certification’ of compliance by firms judged as competent

Installers registered Client does not need

to notify local authority

ACSS511: Statutory Control 24

ACSS511: Statutory Control 25

Provisions introduced by Building Act 1984

ACSS511: Statutory Control 26

Must be approved by Sec of State or designated body: CICAIR

Knowledge base / interview / insurance cover

ACSS511: Statutory Control 27

AI cannot supervise work if they have an interest in it

ACSS511: Statutory Control 28

Agree terms Initial notice LA accept or reject

notice Responsibility

passes to AI Plans certificate Final certificate

AI has no power to enforce regs

AI may try to resolve situation with developer

If not – notify LA – cancel initial notice

Control function reverts to LA Enforcement proceedings may

commence

ACSS511: Statutory Control 29

ACSS511: Statutory Control 30

Single design approval for use in multiple locations

ACSS511: Statutory Control 31

One-to-one relationship with single local authority for pre-submission and plan checking

Site inspections carried out by different LAs

ACSS511: Statutory Control 32

Nationwide chain of pubs and restaurants About to embark on a large refurbishment

programme Most works involve minor structural

alterations and extensions Consider the relative advantages and

disadvantages of using LABC or Approved Inspector

ACSS511: Statutory Control 33

Impartial advice Liaison with other council departments Local knowledge Comprehensive, impartial plan checking

service Responsive inspection service Provision of Completion Certificates

ACSS511: Statutory Control 34

Part of design team. Proactive service – innovative solutions Consultative approach Commercially aware Operate nationally Consistency of advice Backed by insurance Regulated and monitored by CIC Risk-based approach

ACSS511: Statutory Control 35

ACSS511: Statutory Control 36

Consultation exercise 2012 Download document from

DCLG website Proposals include changes

to:◦ Completion certificates◦ Statutory notifications◦ Enforcement◦ Competent person schemes

top related