acss511 statutory control lecture 06/03/12
Post on 12-Jun-2015
670 Views
Preview:
DESCRIPTION
TRANSCRIPT
Tuesday 6th March 2012
ACSS511: Statutory Control 3
Describe the various procedures by which the building control system is administered.
ACSS511: Statutory Control 4
ACSS511: Statutory Control 5
Full Plans procedure
Building Notice procedure
ACSS511: Statutory Control 6
Prepare plans, spec, calcs etc.
Submit application form with supporting info and fee
LA scrutinise proposals Approval or rejection
ACSS511: Statutory Control 7
Site / location plans Detailed plans,
sections Technical details Calculations Drainage info Means of access
ACSS511: Statutory Control 8
ACSS511: Statutory Control 9
Minimum: two copies If Regulatory Reform
(Fire Safety) Order 2005 applies – further copies required.
ACSS511: Statutory Control 10
Payable in two stages
First fee accompanies plan submission
Second fee payable after first site inspection
ACSS511: Statutory Control 11
Scrutinise for compliance with regs
Consult other authorities (e.g. fire)
Prescribed period of 5 weeks, or 2 months with consent of applicant
ACSS511: Statutory Control 12
If plans comply with Building Regs - approval notice issued
If plans don’t comply they may be rejected, and defects specified
Conditional approval may be issued with consent of applicant
ACSS511: Statutory Control 13
Usually resubmitted with amendments
Applicant may refer matter to DCLG for determination
ACSS511: Statutory Control 14
A notice is submitted to LA
Work may commence 48 hours later
ACSS511: Statutory Control 15
Building notice form
Block plan? Insulation details? Hot water system
details?
ACSS511: Statutory Control 16
BN cannot be used if Regulatory Reform (Fire Safety) Order 2005 applies to building in question.
BN is intended for small scale minor works
ACSS511: Statutory Control 17
Single fee payable Same as combined
plan / inspection fee
ACSS511: Statutory Control 18
LA does not approve or reject notice
Further information may be demanded
ACSS511: Statutory Control 19
If FP procedure used – advisable to wait for LA approval notice
However, regardless of which procedure used – work may commence 48 hours after notice is given to LA
ACSS511: Statutory Control 20
Commencement – 2 days Foundation excavated – 1 day Foundation constructed – 1 day DPC – 1 day Oversite preparation – 1 day Drains ready for inspection – 1 day Drains backfilled /ready for test – within 5
days Occupation prior to completion – 5 days Completion of work – within 5 days
ACSS511: Statutory Control 21
Mandatory if Regulatory Reform (Fire Safety) Order 2005 applies to building
In other cases – only if requested
LA not required to issue if BN procedure used
ACSS511: Statutory Control 22
Full Plans◦ Proposals appraised – proceed with
confidence◦ Time taken – up to 2 months
Building Notice◦ Speed and simplicity◦ Risk that work may have to be taken down if
not in compliance
ACSS511: Statutory Control 23
Two possible contraventions:◦ Procedures not followed◦ Work doesn’t comply with
Regs LA’s duty to enforce
Building Regs Usually seek to do it
informally Formal proceedings Fines up to £5000+
A form of ‘self-certification’ of compliance by firms judged as competent
Installers registered Client does not need
to notify local authority
ACSS511: Statutory Control 24
ACSS511: Statutory Control 25
Provisions introduced by Building Act 1984
ACSS511: Statutory Control 26
Must be approved by Sec of State or designated body: CICAIR
Knowledge base / interview / insurance cover
ACSS511: Statutory Control 27
AI cannot supervise work if they have an interest in it
ACSS511: Statutory Control 28
Agree terms Initial notice LA accept or reject
notice Responsibility
passes to AI Plans certificate Final certificate
AI has no power to enforce regs
AI may try to resolve situation with developer
If not – notify LA – cancel initial notice
Control function reverts to LA Enforcement proceedings may
commence
ACSS511: Statutory Control 29
ACSS511: Statutory Control 30
Single design approval for use in multiple locations
ACSS511: Statutory Control 31
One-to-one relationship with single local authority for pre-submission and plan checking
Site inspections carried out by different LAs
ACSS511: Statutory Control 32
Nationwide chain of pubs and restaurants About to embark on a large refurbishment
programme Most works involve minor structural
alterations and extensions Consider the relative advantages and
disadvantages of using LABC or Approved Inspector
ACSS511: Statutory Control 33
Impartial advice Liaison with other council departments Local knowledge Comprehensive, impartial plan checking
service Responsive inspection service Provision of Completion Certificates
ACSS511: Statutory Control 34
Part of design team. Proactive service – innovative solutions Consultative approach Commercially aware Operate nationally Consistency of advice Backed by insurance Regulated and monitored by CIC Risk-based approach
ACSS511: Statutory Control 35
ACSS511: Statutory Control 36
Consultation exercise 2012 Download document from
DCLG website Proposals include changes
to:◦ Completion certificates◦ Statutory notifications◦ Enforcement◦ Competent person schemes
top related