asx announcement for further information: benga … power project attached is a presentation on the...
TRANSCRIPT
23 July 2009 ASX Announcement
Benga Power Project Attached is a presentation on the Benga Power Project in Mozambique. This update was presented to the SADC/SAPP/RERA Investor Roundtable Conference in Livingstone, Zambia between Wednesday 15th and Friday 17th July.
The Riversdale/Elgas SARL Joint Venture project for a proposed 500MW coal-fired thermal power station was one of ten short-listed Southern African power projects presented to potential investors and financiers at the conference.
Whilst good progress has been made in advancing this prospective project, its development is dependent upon, inter alia:
• Access to existing Mozambique power transmission networks
• Finalization of a Framework Agreement with the Mozambique Government, and
• Concluding satisfactory Power Purchase Agreements with various off-take parties.
The Riversdale/Elgas SARL Joint Venture is well advanced in its discussion and negotiation on each of the three pre-conditions outlined above.
Further progress will be provided on this project in the second half of 2009.
Steve Mallyon Managing Director
For further information: Michael O’Keeffe Executive Chairman Ph: +612 8299 7900 Steve Mallyon Managing Director Ph: +612 8299 7900 or Media: Fortbridge Bill Kemmery Ph: +612 9331 0655 Mob: +61 400 122 449 Riversdale Mining Limited ABN 53 006 031 161 Level 1 50 Margaret Street Sydney NSW 2000 PO Box 5371 Sydney NSW 2001 Tel: +61 2 8299 7900 Fax: +61 2 8299 7999 Website www.riversdalemining.com.au ASX Symbol RIV Riversdale Mining Limited ABN 53 006 031 161 Office Level 1, 50 Margaret Street
Sydney NSW 2000
Mail GPO Box 5371 Sydney NSW 2001
Phone +61 2 8299 7900 Fax +61 2 8299 7999 Email [email protected] Web riversdalemining.com.au
For
per
sona
l use
onl
y
RIVERSDALE /ELGAS
1
THE 500 MW BENGA POWER PLANT“a fast track implementation coal fired project”
SADC-SAPP-RERA Pre-Investors’ Conference Workshop15 July 2009
Disclaimer: The information in this document is provided for information purposes only by Riversdale Mining Limited and ELGAS, S.A.R.L.. No representation or warranty is made as to the accuracy, completeness or reliability of the information. Any forward looking information in this presentation has been prepared on the basis of a number of assumptions which may prove to be incorrect. This presentation should not be relied upon as a recommendation or forecast by Riversdale Mining Limited and ELGAS, S.A.R.L.
An invitation for stakeholder and shareholder participation in this exciting Regional project!!F
or p
erso
nal u
se o
nly
RIVERSDALE /ELGAS
2
Agenda
I. Project Summary
II. Country Overview
III. Project Structure
IV. Project Description
V. Tariff Summary Analysis
VI. Funding Plan
VII. Project Agreements, Licenses & Permits
VIII.Project Development Programme
IX. Summary
X. Questions and answers
For
per
sona
l use
onl
y
RIVERSDALE /ELGAS
3
I. PROJECT SUMMARY
For
per
sona
l use
onl
y
RIVERSDALE /ELGAS
4
I. Benga Power Plant Overview
The Benga Power Plant (“BPP”) will be located in the Tete province of Mozambique on Riversdale’s Mining Concession 3365C (formerly EL 881L)
The BPP will develop a 500MW coal-fired, mine-mouth power station (Phase I) expected to be completed during 2013 using existing transmission assets
Upgrade of the BPP to a generation capacity of 2,000MW (Phase II) depending upon the proposed transmission backbone and other transmission capacity
The BPP will help fill the regional power shortage:
Mozambique (local) demand – EDM
Regional demand – Eskom and others
Mine supply
Expected operational life of 20+ years
Highly attractive project to help meet the power needs of the region:
Strategically located and competitive cost advantages over other proposals due to proximity to mine location and Zambezi River
Mining Concession issued by Government
4
For
per
sona
l use
onl
y
RIVERSDALE /ELGAS
5
I. Status Update
Benga Coal Mine can proceed regardless of power station
Conceptual Engineering design completed
Full Category “A” EIA with all specialist studies completed
Designed to meet World Bank Standards
Record of Decision end September 2009
Transmission grid connection analysis completed and awaiting results from EDM appointed consultants on available capacity
Expressions of Interest received from internationally recognised power producers interested in taking a major equity stake
Pre-feasibility study completed
Project Information Memorandum completed
Socio-economic impact study completed
For
per
sona
l use
onl
y
RIVERSDALE /ELGAS
6
I. Benga Power Plant Location
Located on current mine tenement and adjacent to future tenements
Proximity to fuel supply
28 km from Matambo s/sBi-directional supply to HCB and EDMNear Malawi interconnector
Proximity to transmission infrastructure
Adjacent to the perennial Zambezi river offering cost-effective water supply
Proximity to water supplyFor
per
sona
l use
onl
y
RIVERSDALE /ELGAS
7
I. Mine & Power Plant Design
The BPP will be operated as a base load power station
Phase I - 500MW
2 x 250MW units or 4 x 125MW units (all nett)
Unit sizing will be determined by availability, cost and PPA requirements
Phase II - 2,000MW, depending on:
Development of new regional transmission infrastructure
Ramp-up in mining operations at Riversdale’s Mining Concession / development of new mining operations at neighbouring tenements
Plant on a unitised basis (matched boiler and turbine alternator)For
per
sona
l use
onl
y
RIVERSDALE /ELGAS
8
I. Benga Coal Mine
Mining Contract approved and awaiting environmental approval expected in September 2009
Significant pre-preparation work already completed
4 billion tonne Coal Resource estimated, comprising Measured Resources of 313Mt, Indicated Resources of 720 Mt and Inferred Resources of 2,990Mt
Coal Reserves total 273.3Mt, comprising Proved Reserves of 181.3Mt and Probable Reserves of 92.0Mt (Coal Resources are reported inclusive of Coal Reserves)
Domestic quality thermal coal which will supply the BPP is ideally suited for a power plant – moderate ash, low sulphur, good energy value and combustion characteristics for high boiler efficiency
Staged development:
1.7Mtpa premium hard coking coal0.3Mtpa export quality thermal coal (22% ash)Sufficient domestic quality thermal coal to fuel Phase 1 of the BPP
Stage 1 - 2010
3.3Mtpa premium hard coking coal2.0Mtpa export quality thermal coal (28% ash), OR3.0Mtpa domestic quality thermal coal (35% ash)
Stage 2 - 2014
For
per
sona
l use
onl
y
RIVERSDALE /ELGAS
9
II. Country Overview
For
per
sona
l use
onl
y
RIVERSDALE /ELGAS
II. Macro Economic Overview
Country location: South Eastern Coast of Africa
Capital: Maputo
Currency: Meticais (1 USD = MT 26,7)
Population: 20,366,795
Legal system: Roman Germanic (“Civil Law”)
Languages: Portuguese official language with English being widely used as
business language
Banking system: Central Bank – Banco de Mocambique (9 Commercial banks)
Macroeconomic Indicators:
2002 2003 2004 2005 2006
Nominal GDP (US$ Millions)
4.093,85 4.789,39 6.086 6.636 7.296
Real GDP Growth (%) 8,2 7,9 7,2 7,0 7,9
Average Annual Inflation (%)
16,7 13,4 12,6 6,4 12,5
Exports (US$ Millions) 680 1.043,9 1.452,9 1.745 2.381,1
Imports (US$ Millions) 1.262,9 1.671,7 1.753,9 2.242 2.869,3
GDP Per Capita (US$) 226,3 258,6 311,7 314,7 366,8
For
per
sona
l use
onl
y
RIVERSDALE /ELGAS
11
III. Project Structure
For
per
sona
l use
onl
y
RIVERSDALE /ELGAS
12
III. Project Owners and Advisors
Riversdale Mining Limited:
Riversdale is an Australian Mining Company
Market Capitalisation of A$1bn
Strong balance sheet
Experienced African coal mine operator
Largest land holder in Tete Province ~250,000 hectares
Elgas S.A.R.L.
Public Private partnership
Mozambican registered since 2000
Cross border equity holders – RSA
EDM major shareholder (27,5%)
Experienced in Mozambican energy sector
For
per
sona
l use
onl
y
RIVERSDALE /ELGAS
13
III. Project Owners and Advisors
Joint venture received despatch from the Minster of Energy providing permission for development and the Framework Agreement is expected to be signed shortly
Actively seeking the involvement of an internationally recognised power generator to take a majority equity interest in the BPP
The Strategic Equity Partner will:
Take a significant stake in project – 50% - 80%
Have a proven development and operational capabilities and references in coal-fired power stations
Have a track record of development/investment in Africa
Evaluation process to be completed within 60 days
Aided by a strong team of advisors
FIRST TECH
t/a Power Projects Africa
Financial advisors Project technical consultants
International EIA consultants
Mozambique EIA consultants
For
per
sona
l use
onl
y
RIVERSDALE /ELGAS
14
III. Pro Forma Equity Structure
Opportunity exists for additional strategic or equity partners who could provide financial support or strategic benefits to the project
Strategic Development and Operational Equity
Holder
Financial Equity Holder(s)
MozambiqueEquity Holder(s)
Benga Power Plant
50 – 80% 0 – 30% 10 – 30%
For
per
sona
l use
onl
y
RIVERSDALE /ELGAS
15
IV. Project Description
For
per
sona
l use
onl
y
RIVERSDALE /ELGAS
16
IV. Power Evacuation – Phase 1
16
Located 28km from the Matambo substation hence power can be evacuated via exisitng transmsission options
Dedicated transmission lines will connect the BPP to Matambo
Matambo will be the point of supply for offtake to EDM
From Matambo, electricity can be transmitted to the Songo substation via the existing 90km double circuit (2 x 220kV lines):
From Songo, power can be evacuated into regional locations:
Two potential transmission routes have been envisaged via the HV DC link or via EDM/ ZESA/ CTC (Zimbabwe)
For
per
sona
l use
onl
y
RIVERSDALE /ELGAS
17
IV. Power Evacuation – Phase II
17
The proposed Mozambique Transmission Backbone will facilitate the upgrade of the BPP to a generation capacity of 2,000MW
The transmission backbone will be a North – South carrier which would allow the evacuation of 6,000MW of power from the Northern region of Mozambique to the Southern region of Mozambique and to South Africa
Given it will be operating prior to the completion of the backbone, Benga will provide a suitable base load that can be further expanded to underwrite/utilise the capacity on the backbone
Significant coal resources on Riversdale’s Mining Concession and surrounding 21 tenements will provide a long term fuel supply for the power plant
For
per
sona
l use
onl
y
RIVERSDALE /ELGAS
18
IV. Project Incentives
Regulated by Law 4/2009 of 12 April 2009 – Code of Fiscal Benefits
Exemption from Customs Duties and Value added tax on Class K items for first 5 years of operation
Accelerated depreciation – up to 50% increase of approved legal rates
Professional training allowance of up to 5% of taxable income for first 5 years
An allowance during first 5 years of 110% of the value of expenditure in the construction of works that are considered to be of public utility (roads, schools, water supply, etc)
Investment tax credit of 20% of investment realised deductable from Corporate Tax for first 5 years
Tax credits may be carried forward and used in the five successive tax years
Current corporate tax rate – 32%
Above is standard and additional incentives can be negotiated during negotiations of terms and conditions of concession agreementF
or p
erso
nal u
se o
nly
RIVERSDALE /ELGAS
19
V. Tariff Analysis
For
per
sona
l use
onl
y
RIVERSDALE /ELGAS
V. Tariff Analysis
Mozambique
South Africa
3.1 US$c / KWh (Approximate average of Megaflex TOU)Industrial
4.7 US$c / KWh (Business rate 2 ZAR 0.3834c / KWhCommercial
4.88 US$c / KWh (Homepower Bulk Rate ZAR 0.3906c / KWhDomestic
Current TariffTariff Type
Note: Subject to 34% escalation, but based upon averages from Eskom 2008 Tariffs excluding VAT, extension fees and reactive power at ZAR8 =US$1.00
Current TariffTariff Type
4,5 to 6,5 US$c / kWhIndustrial
8,5 to 10 US$c / kWhCommercial
7,5 to 9,0 US$c / kWhDomestic
3,5 to 5 US$c / kWhLife Line Tariff
For
per
sona
l use
onl
y
RIVERSDALE /ELGAS
21
VI. Funding Plan
For
per
sona
l use
onl
y
RIVERSDALE /ELGAS
22
VI. Financial Analysis
SOURCES OF FUNDS $US MILLION
APPLICATION OF FUNDS
$US MILLION
Equity (30%) 383 EPC Turnkey costs 1,250
ECA covered debt 214 Owners costs 18
Development agencies 200 Financing costs 9
Commercial debt 480
TOTAL 1,277 1,277
Debt / Equity 70 / 30Project return on Equity 18%Debt tenor 15 yearsInterest rates 10%DSCR 2+Sent out tariff dependent on finalization of EPC, Coal Supply and PPA agreementsF
or p
erso
nal u
se o
nly
RIVERSDALE /ELGAS
23
VII. Project Agreements, Licences & Permits
For
per
sona
l use
onl
y
RIVERSDALE /ELGAS
24
VII. Critical Agreements
Power Purchase agreement:
Ongoing discussions with EDM and Eskom
Coal Supply agreement:
Riversdale will supply the thermal coal on a long term contract basis
Framework agreement:
In process of being finalised
EPC:
Seeking lowest cost EPC solution
Water supply agreement:
Studies and abstraction plans completed
Draft supply agreement under review
EIA:
Studies completed and awaiting Record of DecisionFor
per
sona
l use
onl
y
RIVERSDALE /ELGAS
25
VIII. Project Development Programme
For
per
sona
l use
onl
y
RIVERSDALE /ELGAS
26
VIII. Timelines
Activity Status Expected completion date
Date Completed
Outstanding
Formalising the development company or joint venture (shareholders agreement)
X August 2009
Completing the feasibility study X October 2009
Obtaining EIA approval to proceed X September 2009
Negotiating and formalising PPAs with off-takers X October 2009
Negotiating and formalising:a land purchase or lease agreement a water supply agreementa fuel supply agreementconcession agreementsinvestment agreement
N/AXXX
On mine concessionOctober 2009
November 2009September 2009
Formalising all licences and approvals required by local legislation (ref Section xx PIR)
X November 2009
Finalising the plant designs and procurement documentation X September 2009
Award of an EPC or construction contracts X October 2009
Issue of PIM (information memorandum) X March 2009
Indicative term sheets X September 2009
Lender due diligence X December 2009
Financial close and fulfilment of CP’s X January 2010
Commissioning of the plant X April 2013
Note: Above timelines subject to BPP getting transmission access by end August 2009
For
per
sona
l use
onl
y
RIVERSDALE /ELGAS
27
IX. Summary
For
per
sona
l use
onl
y
RIVERSDALE /ELGAS
28
IX. Summary
Highly attractive project supported by already approved mine development
Substantial fuel supply through delineated coal reserves
Feasibility and project analysis well progressed with Environmental Approval expected in September 2009
Project designed to meet World Bank Standards
Key supplier and part of the solution to Southern Africa’s power needs
Significant potential to expand as additional transmission capacity is developed in this power hungry region
Process well progressed to identify cornerstone strategic equity holder
Opportunity exists for additional equity investors and financiers to participate in the BPP
For
per
sona
l use
onl
y
RIVERSDALE /ELGAS
Competent Persons Report
Benga Coal ResourcesThe Coal Resources quoted in this announcement are based on the Competent Person Report, Coal Resources, Benga Coal Project as at 15th April
2009, compiled by Mr Tri Yoso, who is a Member of the Australasian Institute of Mining and Metallurgy and the Resource Geologist for Riversdale Mining Limited. Tri Yoso has more than 12 years experience as a coal geologist in the resources industry involving exploration and evaluation
assignments at operating coal mines and coal exploration areas in a number of coal basins throughout the world. With this level of experience, he is adequately qualified as a Competent Person as defined in the 2004 edition of the JORC Code. The Coal Resource estimate for the Benga Licence, (881L) Mozambique presented in this report has been carried out in accordance with the “Australasian Code for Reporting of Exploration Results,
Mineral Resources and Ore Reserves” (2004) prepared by the Joint Ore Reserves Committee of the Australasian Institute of Mining and Metallurgy, Australian Institute of Geoscientists and Minerals Council of Australia.
Benga Coal ReservesThe Coal Reserves quoted in this announcement are based on Report No 3517M, Benga Coal Project as at 15th April 2009, compiled under the supervision of Mr. Rob Mackenzie, who is a Member of the Australasian Institute of Mining and Metallurgy and is a full time employee of Minarco
Mineconsult. Rob is a mining engineer with extensive experience, working for over 30 years with major mining companies. With this level of experience, he is adequately qualified as a Competent Person as defined in the 2004 edition of the JORC Code. The Coal Reserve estimate for the
Benga Licence, (881L) Mozambique presented in this report has been carried out in accordance with the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves” (2004) prepared by the Joint Ore Reserves Committee of the Australasian Institute of
Mining and Metallurgy, Australian Institute of Geoscientists and Minerals Council of Australia.
For
per
sona
l use
onl
y