Roads and Maritime Services I September 2019 Berry to Bomaderry Princes Highway upgrade Project Update Looking north along the newly-constructed carriageway between Jaspers Brush Road and Wileys Creek which will soon be opened to traffic. Use U-turn facilities to access properties Lateral traffic shifts during construction Speed limits in place during construction 60

Upload: others

Post on 10-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Berry to Bomaderry - Princes Highway upgrade - …...Roads and Maritime Services I September 2019Berry to Bomaderry Princes Highway upgrade Project Update Looking north along the newly-constructed

Roads and Maritime Services I September 2019

Berry to Bomaderry Princes Highway upgradeProject Update

Looking north along the newly-constructed carriageway between Jaspers Brush Road and Wileys Creek which will soon be opened to traffic.

Use U-turn facilities to access properties

Lateral traffic shifts during construction

Speed limits in place during construction 60

Page 2: Berry to Bomaderry - Princes Highway upgrade - …...Roads and Maritime Services I September 2019Berry to Bomaderry Princes Highway upgrade Project Update Looking north along the newly-constructed

Right turn intoLamonds Lanepermitted

Right turn intoBoxsells Lanepermitted

Right turn into Strongs Road permitted

Right turn intoCroziers Roadpermitted

Right turn intoMullers Lane

permitted

Right in/right outpermitted at Meroo Road

Andersons Lane

Mullers Lane

Croziers Road

Jaspers

Brush Road

Turners Lane

Mor

sche

lls L

ane

Dev

itts

LaneBoxsells Lane

Lamonds Lane

Mer

oo R

oad

Pestells LaneAbernethys Lane

See i

nset

for d

etail

Cambew

arra

Road

Strongs

Ison

Road

LaneSilos Estate

Broughton Cre

ek

To Berry

Bomaderry

MerooMeadow

JaspersBrush

Wileys C

reek

Princes Highway

To N

owra

Tandingulla Creek

The intersection at Meroo will be a new (standard) one which deviates from in front of the �rst house on the Northern side of the road to a point just to the south of the existing. It basically overlays the new overpass. This is a small lateral shift to get tra�c o� the existing Meroo intersection so we can work in that area.

KEY

Abernethys Lane

Pest

ells

Lan

e

Mer

oo R

oad

Lamonds Lane

Boxsells Lane

Abernethys

Creek Tullia

n Creek

Stron g

s

Roa d

Princes Highway

Princes Highway

See inset for detail

Ison

Lan

e

Silos Estate

350,000m3 of earth moved

10 of 11 bridges underway

23,000m2 of paving laid

2.1km of 15 kilometreof drains now in place

Roads and Maritime Services Berry to Bomaderry - Princes Highway upgrade

Traffic movements - during construction

Upcoming traffic changesThe Berry to Bomaderry project team is preparing for a series of traffic switches which will happen between now and the end of 2019.

We will have three separate “lateral shifts” where traffic is moved from the existing road onto sections of the newly-constructed southbound carriageway.

Motorists should follow the directional signage and directions of traffic controllers during these lateral shifts.

This allows the project team to begin work on demolishing and rebuilding the existing highway.

These shifts will occur through September and October 2019 and include shifting traffic to the east between: • Jaspers Brush Road and Silos Estate• Tandingulla Creek and Meroo Road• Meroo Road and Abernethys Lane.

Page 3: Berry to Bomaderry - Princes Highway upgrade - …...Roads and Maritime Services I September 2019Berry to Bomaderry Princes Highway upgrade Project Update Looking north along the newly-constructed

Privacy: Roads and Maritime Services (“RMS”) is subject to the Privacy and Personal Information Protection Act 1998 (“PPIP Act”) which requires that we comply with the Information Privacy Principles set out in the PPIP Act. All information in correspondence is collected for the sole purpose of assisting in the assessment of this proposal/ delivering this project. The information received, including names and addresses of respondents, may be published in subsequent documents unless a clear indication is given in the correspondence that all or part of that information is not to be published. Otherwise RMS will only disclose your personal information, without your consent, if authorised by the law. Your personal information will be held by RMS. You have the right to access and correct the information if you believe that it is incorrect.

September 2019RMS. 19.1366

DSWJV foreman Rob Usher shows Flagstaff employees how it’s done

Berry to Bomaderry project teams up with local workers with disabilitiesThe Berry to Bomaderry project team has partnered with Flagstaff Group to offer work opportunities to local people with a disability.

The team at Flagstaff will be filling sand bags for use across the project for a variety of purposes including weights for traffic signage, erosion and sediment control on site and temporary retaining walls.

The Flagstaff Group provides employment, life skills and training for people with a disability across the Illawarra and Shoalhaven. The Shoalhaven site has 86 employees working in diverse roles including lawn maintenance, woodwork, light engineering, laundry, packaging and assembly and recycling.

Contact us:If you have any questions or would like more information on the Berry to Bomaderry upgrade please contact our project team:

1800 506 976 (press 3)

[email protected]

rms.nsw.gov.au/bbu

PO Box 309 Berry NSW 2535

Have your say

If you need help understanding this information, please contact the Translating and Interpreting Service on 131 450 and ask them to call us on 1800 506 976, option 3.131 450