BW0621-G
Item Unit Quantity Rate AmountNo
BILL NO 1
PRELIMINARIES
NOTES:
The Conditions of Contract for Construction for Building andEngineering Works Designed by the Employer as issued by theFederation Internationale des Ingenieurs-Conseils (FIDIC),2010 Edition shall be the applicable contract for the execution ofthe Works
The Model Preliminaries (1988 edition) as approved andrecommended by the Namibian Institute of Quantity Surveyorsand as published by the Association of South African QuantitySurveyors shall be taken to be incorporated herein
Contractors are referred to the above-mentioned documents for thefull intent and meaning of each clause thereof
These clauses are hereinafter referred to by clause number only.Where standard clauses or alternatives are not applicable to thecontract, such modifications / corrections as are necessary, aregiven under each relevant clause
Items that are not relevant to this contract have been listed and aremarked "N/A" (not applicable)
The Model Preambles for Trades (2008 edition) as approvedand recommended by the Namibian Institute of QuantitySurveyors and as published by the Association of South AfricanQuantity Surveyors shall be deemed to be incorporated in thesebills of quantities
Supplementary preambles to the Model Preambles coveringclauses of a general nature, clauses pertaining to specific materialsand amendments to clauses in the Model Preambles areincorporated in these bills of quantities to satisfy the requirementsof this project
The contractor's prices for all items throughout these bills ofquantities must take account of and include for all of theobligations, requirements and specifications given in the ModelPreambles and Supplementary Preambles
SECTION A - CONDITIONS OF CONTRACT FORCONSTRUCTION
Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 1 -
BW0621-G
Brought Forward N $
CLAUSE 1 - GENERAL PROVISIONS
1 Clause 1.1 - Definitions Item
2 Clause 1.2 - Interpretation Item
3 Clause 1.3 - Communications Item
4 Clause 1.4 - Law and language Item
5 Clause 1.5 - Priority and documents Item
6 Clause 1.6 - Contract Agreement Item
7 Clause 1.7 - Assignment Item
8 Clause 1.8 - Care and supply of documents Item
9 Clause 1.9 - Delayed drawings or instructions Item
10 Clause 1.10 - Employer's use of Contractor's documents Item
11 Clause 1.11 - Contractor's use of Employer's documents Item
12 Clause 1.12 - Confidential details Item
13 Clause 1.13 - Compliance with laws Item
[a] Contractor to comply with the Namibia EnvironmentalManagement Act No. 7 of year 2007 as well as the EnvironmentalAssessment Policy of year 1995 by implementing theEnvironmental Management Plans (EMP) documented separatelyas part of this contract
Bidder's are compelled to price this Line Item in accordance withthe cost estimate required in Form: Environmental and SocialDocuments
[b] Contractor to comply with the Namibia Public Health andSafety Management Policy under Act No. 11 of year 2007 byimplementing the Public Health and Safety Awareness Plan(PHSAP) documented separately as part of this contract
Bidder's are compelled to price this Line Item in accordance withthe cost estimate required in Form: Health and Safety Documents
Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 2 -
BW0621-G
Brought Forward N $
14 Clause 1.14 - Joint and several liability Item
CLAUSE 2 - THE EMPLOYER
15 Clause 2.1 - Right of access to the site Item
16 Clause 2.2 - Permits, Licences of Approvals Item
17 Clause 2.3 - Employer's personnel Item
18 Clause 2.4 - Employer's financial arrangement Item
CLAUSE 3 - THE ENGINEER
The Engineer will be deemed to be the Principal Agent, Architector any other person as appointed by the Client to fulfil such duties
19 Clause 3.1 - Engineer's duties and authority Item
20 Clause 3.2 - Delegation by the Engineer Item
21 Clause 3.3 - Instructions of the Engineer Item
22 Clause 3.4 - Replacement of the Engineer Item
23 Clause 3.5 - Determinations Item
CLAUSE 4 - THE CONTRACTOR
24 Clause 4.1 - Contractor's general obligations Item
25 Clause 4.2 - Performance security Item
26 Clause 4.3 - Contractor's security Item
27 Clause 4.4 - Sub-Contractors Item
28 Clause 4.5 - Assignment of benefit of Sub-contract Item
29 Clause 4.6 - Co-operation Item
30 Clause 4.7 - Setting out Item
31 Clause 4.8 - Safety procedures Item
32 Clause 4.9 - Quality assurance Item
Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 3 -
BW0621-G
Brought Forward N $
33 Clause 4.10 - Site data Item
34 Clause 4.11 - Sufficiency of accepted Contract Amount Item
35 Clause 4.12 - Unforeseeable physical conditions Item
36 Clause 4.13 - Right of way and facilities Item
37 Clause 4.14 - Avoidance of interference Item
38 Clause 4.15 - Access route Item
39 Clause 4.16 - Transport of goods Item
40 Clause 4.17 - Contractor's equipment Item
41 Clause 4.18 - Protection of the environment Item
42 Clause 4.19 - Electricity, water and gas Item
43 Clause 4.20 - Employer's equipment and free-issue material Item
44 Clause 4.21 - Progress reports Item
45 Clause 4.22 - Security of the site Item
46 Clause 4.23 - Contractor's operations on site Item
47 Clause 4.24 - Fossils Item
CLAUSE 5 - NOMINATED SUB-CONTRACTORS
48 Clause 5.1 - Definition of "nominated Sub-Contractor" Item
49 Clause 5.2 - Objection to nomination Item
50 Clause 5.3 - Payments to nominated Sub-Contractors Item
51 Clause 5.4 - Evidence of payments Item
CLAUSE 6 - STAFF AND LABOUR
52 Clause 6.1 - Engagement of staff and labour Item
53 Clause 6.2 - Rates of wages and conditions of labour Item
Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 4 -
BW0621-G
Brought Forward N $
54 Clause 6.3 - Persons in the service of the Employer Item
55 Clause 6.4 - Labour laws Item
56 Clause 6.5 - Working hours Item
57 Clause 6.6 - Facilities for staff and labour Item
58 Clause 6.7 - Health and safety Item
59 Clause 6.8 - Contractor's superintendence Item
60 Clause 6.9 - Contractor's personnel Item
61 Clause 6.10 - Records of Contractor's personnel and equipment Item
62 Clause 6.11 - Disorderly conduct Item
CLAUSE 7 - PLANT, MATERIALS AND WORKMANSHIP
63 Clause 7.1 - Manner of execution Item
64 Clause 7.2 - Samples Item
65 Clause 7.3 - Inspection Item
66 Clause 7.4 - Testing Item
67 Clause 7.5 - Rejection Item
68 Clause 7.6 - Remedial work Item
69 Clause 7.7 - Ownership of plant and material Item
70 Clause 7.8 - Royalties Item
CLAUSE 8 - COMMENCEMENT, DELAYS ANDSUSPENSION
71 Clause 8.1 - Commencement of works Item
72 Clause 8.2 - Time for completion Item
73 Clause 8.3 - Programme Item
74 Clause 8.4 - Extension of time for completion Item
Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 5 -
BW0621-G
Brought Forward N $
75 Clause 8.5 - Delays caused by authorities Item
76 Clause 8.6 - Rate of progress Item
77 Clause 8.7 - Delay damages Item
78 Clause 8.8 - Suspension of work Item
79 Clause 8.9 - Consequences of suspension Item
80 Clause 8.10 - Payment for plant and materials in event ofsuspension Item
81 Clause 8.11 - Prolonged suspension Item
82 Clause 8.12 - Resumption of work Item
CLAUSE 9 - TESTS ON COMPLETION
83 Clause 9.1 - Contractor's obligation Item
84 Clause 9.2 - Delayed tests Item
85 Clause 9.3 - Retesting Item
86 Clause 9.4 - Failure to pass tests on completion Item
CLAUSE 10 - EMPLOYER'S TAKING OVER
87 Clause 10.1 - Taking over of the works and sections Item
88 Clause 10.2 - Taking over of parts of the works Item
89 Clause 10.3 - Interference with tests on completion Item
90 Clause 10.4 - Surfaces requiring reinstatement Item
CLAUSE 11 - DEFECTS LIABILITY
91 Clause 11.1 - Completion of outstanding work and remedyingdefects Item
92 Clause 11.2 - Cost of remedying defects Item
93 Clause 11.3 - Extension of defects notification period Item
Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 6 -
BW0621-G
Brought Forward N $
94 Clause 11.4 - Failure to remedy defects Item
95 Clause 11.5 - Removal of defective work Item
96 Clause 11.6 - Further tests Item
97 Clause 11.7 - Right of access Item
98 Clause 11.8 - Contractor to search Item
99 Clause 11.9 - Performance certificate Item
100 Clause 11.10 - Unfulfilled obligations Item
101 Clause 11.11 - Clearance of site Item
CLAUSE 12 - MEASUREMENT AND EVALUATIONLIABILITY
102 Clause 12.1 - Works to be measured Item
103 Clause 12.2 - Method of measurement Item
104 Clause 12.3 - Evaluation Item
105 Clause 12.4 - Omissions Item
CLAUSE 13 - VARIATIONS AND ADJUSTMENTS
106 Clause 13.1 - Right to vary Item
107 Clause 13.2 - Value engineering Item
108 Clause 13.3 - Variation procedure Item
109 Clause 13.4 - Payment in applicable currencies Item
110 Clause 13.5 - Provisional sums Item
111 Clause 13.6 - Daywork Item
112 Clause 13.7 - Adjustments for changes in legislation Item
113 Clause 13.8 - Adjustments for changes in cost Item
Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 7 -
BW0621-G
Brought Forward N $
CLAUSE 14 - CONTRACT PRICE AND PAYMENTS
114 Clause 14.1 - The Contract Price Item
115 Clause 14.2 - Advance payment Item
116 Clause 14.3 - Application for interim Payment Certificates Item
117 Clause 14.4 - Schedule of payments Item
118 Clause 14.5 - Plant and materials intended for the works Item
119 Clause 14.6 - Issue of interim Payment Certificates Item
120 Clause 14.7 - Payment Item
121 Clause 14.8 - Delayed payment Item
122 Clause 14.9 - Payment of retention money Item
123 Clause 14.10 - Statement at completion Item
124 Clause 14.11 - Application for Final Payment Certificate Item
125 Clause 14.12 - Discharge Item
126 Clause 14.13 - Issue of Final Payment Certificate Item
127 Clause 14.14 - Cessation of Employer's liability Item
128 Clause 14.15 - Currencies of payment Item
CLAUSE 15 - TERMINATION BY EMPLOYER
129 Clause 15.1 - Notice to correct Item
130 Clause 15.2 - Termination by Employer Item
131 Clause 15.3 - Valuation at date of termination Item
132 Clause 15.4 - Payment after termination Item
133 Clause 15.5 - Employer's entitlement to termination Item
Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 8 -
BW0621-G
Brought Forward N $
CLAUSE 16 - SUSPENSION AND TERMINATION BYCONTRACTOR
134 Clause 16.1 - Contractor's entitlement to suspend work Item
135 Clause 16.2 - Termination by Contractor Item
136 Clause 16.3 - Cessasion of work and removal of Contractor'sequipment Item
137 Clause 16.4 - Payment and termination Item
CLAUSE 17 - RISK AND RESPONSIBILITY
138 Clause 17.1 - Indemnities Item
139 Clause 17.2 - Contractor's care of the works Item
140 Clause 17.3 - Employer's risks Item
141 Clause 17.4 - Consequences of Employer's risks Item
142 Clause 17.5 - Intellectual and industrial property rights Item
143 Clause 17.6 - Limitation of liability Item
CLAUSE 18 - INSURANCE
144 Clause 18.1 - General requirements for insurance Item
145 Clause 18.2 - Insurance for works and Contractor's equipment Item
146 Clause 18.3 - Insurance against injury to persons and damage toproperty Item
147 Clause 18.4 - Insurance for Contractor's personnel Item
CLAUSE 19 - FORCE MAJEURE
148 Clause 19.1 - Definition of Force Majeure Item
149 Clause 19.2 - Notice of Force Majeure Item
150 Clause 19.3 - Duty to minimise delay Item
151 Clause 19.4 - Consequences of Force Majeure Item
Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 9 -
BW0621-G
Brought Forward N $
152 Clause 19.5 - Force Majeure affecting Sub-Contractor Item
153 Clause 19.6 - Optimal termination, payment and release Item
154 Clause 19.7 - Release from performance under the law Item
CLAUSE 20 - CLAIMS, DISPUTES AND ARBITRATION
155 Clause 20.1 - Contractor's claim Item
156 Clause 20.2 - Appointment of the Dispute Adjudication Board Item
157 Clause 20.3 - Failure to agree to Dispute Adjudication Board Item
158 Clause 20.4 - Obtaining Dispute Adjudication Board's decision Item
159 Clause 20.5 - Amicable settlement Item
160 Clause 20.6 - Arbitration Item
161 Clause 20.7 - Failure to comply to Dispute Adjuducation Board'sdecision Item
162 Clause 20.8 - Expiry of Dispute Adjuducation Board'sappointment Item
SECTION B - PRELIMINARIES
B1: SUPPLEMENTARY DOCUMENTATION
163 B1.1: Bills of quantities Item
164 B1.2: Provisional bills of quantities N/A
165 B1.3: Availability of construction documentation for contractsbased on provisional bills of quantities N/A
B1.4: Name of Architect, Quantity Surveyor and otherconsultants:
Principal Agent : Se[arch] TeamArchitects : Nina Maritz ArchitectsQuantity Surveyors : De Leeuw NamibiaCivil/Struct Engineers : Bührmann & PartnersElectr/Mech Engineers : Emcon
Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 1 0 -
BW0621-G
Brought Forward N $
166 B1.5: Lodging and scrutiny of priced bills of quantities Item
The priced Bills of Quantities, displaying unit rates, extended inblack ink and initialed on every page, will be submitted with thetender document
Failure to comply with this clause will result in thedisqualification of the tender
167 B1.6: Meaning of words Item
168 B1.6.1: Singular and plural Item
169 B1.6.2: Standard specifications Item
170 B1.6.3: Definition of "approved" etc Item
171 B1.7: Performance guarantee by the Contractor Item
Sub-clause 3. of this clause is not applicable. No interim paymentwill be certified before accepted guarantees have been received
The full security for the due fulfilment of all obligations under thiscontract is to remain in force for 60 (sixty) days after practicalcompletion or finalisation of the final account, whichever is thelater date
No guarantee containing any clause that allows the financialinstitution providing such guarantee to either withdraw from theirundertaking before 60 (sixty) days after practical completion, orthat stipulates an expiry date is acceptable
Notwithstanding the above, the guarantee will only be returned tothe contractor after receipt of satisfactory proof that thecontractor has met all his obligations under any and all selectedand nominated sub-contract agreements applicable to thiscontract
172 B1.8: Payment guarantee by Employer N/A
173 B1.9: Waiver of contractor's lien Item
174 B1.10: Signing powers Item
175 B1.11: Tenders Item
Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 1 1 -
BW0621-G
Brought Forward N $
Notwithstanding anything contained in this clause tenders shallbe valid for a period of 90 (ninety) days from the closing date oftenders
The Employer reserves the right to correct any arithmetical orother errors in the extension of the rates and totals in the tenderand / or to adjust any rates that are considered by him to beimbalanced and unacceptable. Such adjustments will be donewithout affecting the Tender Sum
176 B1.12: Inspection of documents Item
The following drawings are issued with this bill
Drawing No: RP-01 Ground Floor Reference PlanDrawing No: SP-01 Site LayoutDrawing No: E-01 Site Elevations: NorthDrawing No: E-02 Site Elevations: SouthDrawing No: E-03 Ste Elevations: East & West
B.2: THE SITE
177 B2.1: Site and site boundaries Item
The site is the remainder of Farm Helao Nafidi, Settlement Areanumber 997, Ohangwena Region, Namibia
178 B2.2: Area of the works
The area of the works to be occupied by the contractor, anyrestriction to the area and access/exit limitations will be pointedout to the contractor by the Principal Agent during site handover Item
179 B2.3: Boundary beacons, setting out pegs and master datum
The contractor shall notify the Principal Agent if anyencroachments of adjoining foundations, buildings, structures,pavements, etc exist so that the necessary arrangements can bemade for the rectification of any such encroachments Item
180 B2.4: Site soil investigation Item
181 No site soil investigation report is available and the tenderer isadvised to inspect the site to ascertain the exact nature of theground Item
Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 1 2 -
BW0621-G
Brought Forward N $
182 B2.5: Viewing of the site
No claim for extras arising from the contractor having failed tocomply with this Clause will be entertained Item
183 B2.6: Existing premises occupied N/A
184 B2.7: Dimensional accuracy of work executed under the previouscontract N/A
185 B2.8: Defects in work executed under the previous contract N/A
186 B2.9: Existing known services
Existing services and points of connection are shown on the siteplan or will be pointed out by the Principal Agent during sitehandover Item
187 B2.10: Unknown services Item
188 B2.11: Protection of trees, etc Item
Existing trees to be retained and protected will be identified bythe Principal Agent during site handover
189 B2.12: Articles of value Item
190 B2.13: Inspection of nearby properties, etc Item
B3: MANAGEMENT OF CONTRACT
191 B3.1: Management of works Item
192 B3.2: Programming of the works
The contract shall be programmed by the contractor inaccordance with alternative A Item
Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 1 3 -
BW0621-G
Brought Forward N $
193 B3.3: Progress meetings
Progress meetings will be held once a month and will be attendedby the Contractor and his Foreman, Consultants andrepresentatives of the Employer
Should any of the Consultants or representatives of the Employerhave to make a separate trip for any reason which, in the opinionof the Principal Agent is due to the fault of the Contractor, thecost of such a trip shall be for the Contractors own account Item
194 B3.4: Technical meetings Item
B4: MATERIALS AND WORKMANSHIP
195 B4.1: Samples of materials Item
196 B4.2: Samples of workmanship and mockups Item
197 B4.3: Ordering of materials Item
B5: TEMPORARY WORKS AND PLANT
198 B5.1: Deposits and fees Item
199 B5.2: Enclosure of works Item
The contractor shall provide proper protection and provide anderect any temporary barriers, dust screens, etc that may benecessary during the progress of the works, all to the satisfactionof the principal agent, and remove when directed
200 B5.3: Pavement crossings and parking meters Item
201 B5.4: Advertising Item
202 B5.5: Plant and equipment Item
The contractor shall make available hoisting facilities and hoistinto position all sub-contractor's materials or manufacturedarticles for the works for the duration of the contract whilst suchhoisting facilities are in position for the works
Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 1 4 -
BW0621-G
Brought Forward N $
203 B5.6: Special scaffolding
No special scaffolding is measured as these bills of quantities arebased on the sixth edition of the Standard System for MeasuringBuilding Work Item
204 B5.7: Contractor's offices and sheds Item
205 B5.8: Offices Item
206 B5.9: Office of the clerk of works N/A
207 B5.10: Main notice board Item
208 B5.11: Sub-Contractors' notice-board Item
B6: TEMPORARY SERVICES
209 B6.1: Water Item
Contractor shall provide water for the works in accordance withalternative A
210 B6.2: Electricity and lighting Item
Contractor shall provide electricity for the works in accordancewith alternative A
211 B6.3: Telephones Item
212 B6.4: Toilets Item
Contractor shall provide toilets in accordance with alternative A
B7: PRIME COST AND PROVISIONAL AMOUNTS
213 B7.1: Cash discount Item
All prime cost and provisional sums are "NET" and do notinclude a cash discount, nor will the Contractor be allowed orentitled to a cash discount
214 B7.2: Taking delivery and fixing of prime cost items Item
215 B7.3: Nominated or selected sub-contract documents Item
Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 1 5 -
BW0621-G
Brought Forward N $
216 B7.4: Attendance on nominated or selected sub-contractors Item
217 B7.5: Fuel, power and water for commissioning of mechanical andother specialised installations Item
B8: FINANCIAL ASPECTS
218 B8.1: Sales tax Item
Prices for items contained in these bills of quantities shall becalculated on the "NET" basis (ie excluding all components ofVAT). VAT will be added separately on the Summary page and allcertificate calculations
219 B8.2: Contract Price Adjustment Provisions Item
This contract amount will not be subject to contract priceadjustment provisions. Therefore the contractor must allow, if hedeems it necessary, for any price adjustment provisions under thisitem
220 B8.3: Payment of preliminaries Item
Payment of preliminaries will be calculated from the priced itemswithin the preliminaries in accordance with alternative B
221 B8.4: Adjustment of preliminaries Item
The adjustment of preliminaries will be on the basis of fixed price,value related and time related items in accordance with method 2
In addition to the exclusions mentioned in the third paragraph ofthis clause it shall be deemed that "day works" be added as afourth exclusion
222 B8.5: Certificate and payment projection Item
223 B8.6: Day works Item
Notwithstanding anything contained in this Clause, the signatureof the Principal Agent shall not indicate acceptance of quantum,value or method of valuation of work executed thereunder. Thequantum of these day works and the method of valuation will bedecided by the Quantity Surveyor
224 B8.7: Information supplied by contractor Item
Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 1 6 -
BW0621-G
Brought Forward N $
B9: GENERAL
225 B9.1: Protection Item
226 B9.2: Protection of existing and/or partially occupied works Item
227 B9.3: Safety Item
The contractor and his work force will strictly comply with allhealth and safety regulations as stipulated in the latest NamibianMachinery and Occupational Safety Act as well as requirementsas set out in the Health and Safety Booklet as issued by theConstruction Industries Federation of Namibia
The principal agent retains the right to stop any work or requestany personnel to be removed from the site, should the contractoror his work-force fail to comply with the regulations as set out inabove-mentioned documents
All expenses / delays accrued due to the above will be for the costof the contractor
228 B9.4: Site security Item
229 B9.5: Notice before covering work Item
230 B9.6: Disturbance Item
231 B9.7: Clearing and cleaning Item
232 B9.8: Vermin Item
233 B9.9: Overhand work Item
234 B9.10: Jobbing Item
SECTION C - SPECIFIC PRELIMINARIES
235 Revenue stamps Item
The contractor must allow for and provide all necessary revenuestamps required in connection with the Agreement and Scheduleof Conditions of Building Contract and the PerformanceGuarantee in accordance with the Stamp Duty Act
236 As built drawings Item
Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 1 7 -
BW0621-G
Brought Forward N $
The position of construction breaks and the extent of individualconcrete pours are to be recorded by the contractor on thestructural engineer's drawings and are to be submitted to thearchitect and the structural engineer for their records
The contractor shall furnish the Architect with a set of markeddrawings indicating the positions of all plumbing and drainagepipework as actually built
237 Site instructions Item
Site instructions issued on site are to be recorded in triplicate in asite instruction book which is to be maintained on site by the maincontractor
238 Labour record Item
At the end of each week the contractor shall provide the PrincipalAgent with a written record, in schedule form, showing thenumber and descriptions of tradesmen and labourers employed byhim and all sub-contractors on the works each day
239 Plant record Item
At the end of each week the contractor shall provide the PrincipalAgent with a written record, in schedule form, showing thenumber, type and capacity of all plant, excluding hand tools,currently used on the works
240 Guarantee Item
Where guarantees are called for, the Contractor shall obtain awritten guarantee, addressed to the Employer, from the firmsupplying the materials and/or doing the work and shall deliversame to the Architect on the certified completion of the contract.The guarantee shall state that workmanship, materials andinstallation are guaranteed for a specified period from the date ofcertified completion of the contract, and that any defects that mayarise during the specified period shall be made good at theexpense of the firm supplying the materials and/or doing thework, upon written notice from the Architect to do so. Thisguarantee will not be enforced if the work is damaged bystructural defects in the building in which case the responsibilityfor replacement shall rest entirely with the Contractor. TheArchitect shall be the sole judge of the cause responsible fordefects in the work and his ruling shall be final and binding
Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 1 8 -
BW0621-G
Brought Forward N $
241 Inspection of the works at practical completion Item
The contractor is to ensure that the Principal Agent is not calledto the site for the practical completion inspection before the worksare complete. The cost, both in time and travel for anyunnecessary trips will be for the sole account of the contractor
242 Disconnection of existing services Item
Any water-supply pipes, sewer pipes, other piping and electricalcables that may be met with and found necessary to disconnect orcut, shall be effectively stopped-off and any new connections orre-routing that may be necessary shall be made with properfittings, to the satisfaction of the principal agent
243 Local community involvement Item
It is the express desire of the client that the local community beinvolved. The contractor is encouraged to employ labour fromthe area in which the project is situated. This applied equally tothe skilled and unskilled labour force. The successful contractormust be willing, during the course of this project to impart skillsto the members of the local community
244 Employment of Namibian People Item
It is an explicit condition of this contract that no unskilled labourmay be employed on these works unless he or she is a Namibian.Further, it is a condition of this contract that no skilled orsemi-skilled labour, being a non-Namibian person, be employedin this contract unless the contractor can prove that there is nosuitably trained Namibian available
245 Language and Law Item
The language to be used shall be English
The contract is subject to the law of the Republic of Namibia
246 Foreign Investment Item
Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 1 9 -
BW0621-G
Brought Forward N $
The contractor may move construction plant and equipment intoNamibia for the purpose of this contract, and may remove samefrom Namibia after completion of the Contract subject to theprovisions of the Customs Act No 20 of 1998. After tax profits maybe taken out of Namibia to countries within the Rand monitoryarea without restriction by Namibia. The Foreign Investment ActNo 27 of 1990 and all amendments thereto will apply in thisregard
Carried to Summary N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 2 0 -
BW0621-G
Item Quantity Rate AmountNo
BILL NO 2
EARTHWORKS (PROVISIONAL)
SUPPLEMENTARY PREAMBLES
Nature of ground
The nature of the ground is assumed to be imported sandy material,therefore "earth", but possibly interspersed with "hard rock" or "softrock".
Earth
All material as spesified above as well as all material which ispickable or which can be excavated by means of a backactor(complete with all equipment and accessories and in good condition,producing not less than 57kw (gross) at the flywheel and with a baretractor mass of not less than 7900kg, equipped with 600mm widebucket with matching teeth) will be classified as "earth". All bouldersnot exceeding 0,3m3 in volume will also be classified as "earth"
Soft rock
All material which can not be removed as described above, but theremoval of which necessitates the use of jack hammers with moilpoints, will be classified as "soft rock"
Hard rock
All very hard material which can not be removed as described above,but the removal of which necessitates the use of explosives or heavyduty hydraulic percussion hammers (peckers), will be classified as"hard rock"
Carried Forward N $ Bill No. 2EarthworksRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 2 1 -
BW0621-G
Brought Forward N $
Carting away of excavated material
Descriptions of carting away of excavated material shall be deemed toinclude loading excavated material onto trucks directly from theexcavations or, alternatively, from stock piles situated on the buildingsite
Filling
Notwithstanding the reference to prescribed multiple handling inclause 1 page 6 of the Standard System of Measuring Building Work,prices for filling and backfilling shall include for all selection and anymultiple handling of material
REMOVAL OF EXISTING WORK
Taking out and setting aside for re-use (re-installing elsewhere)
1 80mm Interlock paving m2 50
2 Pre-cast concrete road kerbs including cleaning of mortar andpreparing for re-use m 5
EXCAVATION, FILLING, ETC OTHER THAN BULK
Excavation in soil raft not exceeding 2m deep
3 Reduce levels under paving, etc m3 38
4 Trenches m3 28
Extra over all excavations for carting away
5 Surplus material from excavations and/or stock piles on site to adumping site to be located by the contractor m3 38
Risk of collapse of excavations
6 Sides of trench and hole excavations not exceeding 1,5m deep m2 70
Keeping excavations free of water
7 Keeping excavations free of water Item
Carried Forward N $ Bill No. 2EarthworksRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 2 2 -
BW0621-G
Brought Forward N $
Earth filling of G6 material obtained from the excavations and/orprescribed stock piles on site compacted to 95% Mod AASHTOdensity
8 Under floors, steps, pavings, etc m3 19
9 Backfilling to trenches, holes, etc m3 14
Earth filling supplied by the contractor
10 G6 material under floors, steps, pavings, etc compacted to 95% ModAASHTO density m3 59
Compaction of surfaces
11 Compaction of ground surface in trench excavations etc to 95% ModAASHTO density m2 30
12 Compaction of ground surface under floors, paving, etc includingscarifying for a depth of 150mm, breaking down oversize material,adding suitable material where necessary and compacting to 93%Mod AASHTO density m2 270
Approved clean sand filling supplied by the contractor
13 25mm Thick under floors, etc m3 2
Prescribed density tests on filling
14 "Modified AASHTO Density" test No 8
SOIL POISONING
"Premise 200SC" weedkiller mixed with water and applied at arate of 5 litre/m2
15 Under floors, etc including forming and poisoning shallow furrowsagainst foundation walls, etc filling in furrows and ramming m2 270
16 To bottoms and sides of trenches, etc m2 100
Carried to Summary N $ Bill No. 2EarthworksRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 2 3 -
BW0621-G
Item Quantity Rate AmountNo
BILL NO 3
CONCRETE, FORMWORKAND REINFORCEMENT
SUPPLEMENTARY PREAMBLES
Soilcrete
Soilcrete shall be mixed in a suitable mixer to ratios by mass. In situmaterial must be approved and have a maximum PI of 4
Water content to be adjusted to obtain 80-100mm slump
All trench bottom material disturbed during excavation must becompacted to 90% Mod AASHTO density. Trenches shall bebackfilled with soilcrete to the founding level on which the stripfooting or column base shall be cast, allowing 24 hours betweencasting of soilcrete and casting of concrete
The soilcrete shall be placed with a mechanical vibrator in a singleoperation
Cost of tests
The costs of making, storing and testing of concrete test cubes asrequired under clause 7 "Tests" of SABS 1200 G shall include thecost of providing cube moulds necessary for the purpose, for testingcosts and for submitting reports on the tests to the architect. Thetesting shall be undertaken by an independent firm or institutionnominated by the contractor and to the approval of the architect.(Test cubes are measured separately)
Formwork
Descriptions of formwork shall be deemed to include use and wasteonly (except where described as "left in" or "permanent"), for fittingtogether in the required forms, wedging, plumbing and fixing to trueangles and surfaces as necessary to ensure easy release duringstripping and for reconditioning as necessary before re-use. Thevertical strutting shall be carried down to such construction as issufficiently strong to afford the required support without damage andshall remain in position until the newly constructed work is able tosupport itself.
Carried Forward N $ Bill No. 3Concrete, formwork & reinforcementRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 2 4 -
BW0621-G
Brought Forward N $
Formwork to soffits of (solid) slabs etc shall be deemed to be to slabsnot exceeding 250mm thick unless otherwise described
Formwork to soffits of slabs, beams etc shall be deemed to be to slabspropped up exceeding 1,5 but not exceeding 3,5m high unlessotherwise described
Formwork to sides of bases, pile caps, ground beams, etc will only bemeasured where it is prescribed by the engineer for design reasons.Formwork necessitated by irregularity or collapse of excavated faceswill not be measured and the cost thereof shall be deemed to beincluded in the allowance for taking the risk of collapse of the sides ofthe excavations, provision for which is made in "Earthworks"
High quality cement-based surface treatment
Surface treatment is to be executed by an approved applicator and aguarantee for the product as well as application thereof to besubmitted to Principal Agent before the issuing of the practicalcompletion certificate
UNREINFORCED CONCRETE CAST AGAINSTEXCAVATED SURFACES
15MPa Soilcrete of in-situ material in 150mm layers compactedto 100% Mod Aashto density
1 Under strip footings, bases, etc m3 9
25MPa/19mm concrete
2 Surface blinding under footings and bases m3 1
REINFORCED CONCRETE
30MPa/19mm Concrete
3 Strip footings m3 9
4 Surface beds on waterproofing m3 11
5 Beams m3 3
6 Columns m3 0.3
Carried Forward N $ Bill No. 3Concrete, formwork & reinforcementRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 2 5 -
BW0621-G
Brought Forward N $
TEST CUBES
7 Making and testing 150 x 150 x 150mm concrete strength test cubes(Provisional) No 6
CONCRETE SUNDRIES
Finishing top surfaces of concrete smooth with a steel trowel
8 Floors, etc m2 73
ROUGH FORMWORK (DEGREE OF ACCURACY II)
Rough formwork to soffits
9 Vanity slabs, cupboard slabs, cover slabs, etc propped up notexceeding 1,5m high m2 3
SMOOTH FORMWORK (DEGREE OF ACCURACY I)
Smooth formwork to sides
10 Rectangular columns m2 5
11 Wall beams m2 25
12 Edges, risers, ends and reveals not exceeding 300mm high or wide m 36
Smooth formwork to soffits
13 Wall beams over openings m2 1
Boxing in smooth formwork to form
14 10 x 10mm Chamfer along top or bottom edge m 8
MOVEMENT JOINTS, ETC
Two layers of "DPC" in slip joints between horizontal concreteand brick surfaces, including cement mortar bed
15 Not exceeding 300mm wide m 33
Carried Forward N $ Bill No. 3Concrete, formwork & reinforcementRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 2 6 -
BW0621-G
Brought Forward N $
Saw cut joints
16 3 x 40mm Saw cut joints in top of concrete with the top 20mmincreased to 6mm wide m 24
REINFORCEMENT (PROVISIONAL)
Steel reinforcement to structural concrete work
17 Bars t 0.28
Fabric reinforcement
18 Type 245 fabric reinforcement in floors, ramps, aprons, etc m2 150
Carried to Summary N $ Bill No. 3Concrete, formwork & reinforcementRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 2 7 -
BW0621-G
Item Quantity Rate AmountNo
BILL NO 4
PRECAST CONCRETE
SUPPLEMENTARY PREAMBLES
Sizes:
Blocks, sills, etc measured linear shall be made in suitable lengths.Large size setting out drawings shall be prepared where necessary andsubmitted to the architect for approval before moulds are made
General:
Where kerbstones, blocks, etc are laid in ground descriptions shall bedeemed to include necessary excavation, filling in and ramming
PRECAST CONCRETE
Precast concrete block and clay brick road surfacing
Paving is to be laid in accordance with SABS 1200 MJ, SABS 1058and the Concrete Masonry Association's specifications
Paving is to be laid on 25mm (thickness after final compaction) cleanriver sand (preparation of ground or filling elsewhere)
Clean sand is to be swept into joints between paving blocks
Pre-cast paving and kerbs removed elsewhere
1 Relay paving to parking areas, roadways, etc including joining withexisting m2 50
2 Re-lay kerb on new 25MPa concrete bedding including jointing andpointing
m 5
35MPa x 60mmThick interlocking paving blocks
3 Paving to parking areas, roadways, etc m2 195
Precast concrete finished smooth on exposed surfaces including25MPa concrete bedding, jointing and pointing
4 Barrier kerb 125 x 250mm high set on concrete surface beds withgrout bedding and infill m 31
Carried Forward N $ Bill No. 4Precast ConcreteRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 2 8 -
BW0621-G
Brought Forward N $
5 Barrier kerb 125 x 250mm high set on 150mm thick unreinforcedconcrete bed m 38
6 Mountable kerb 250 x 150mm high set on 150mm thick unreinforcedconcrete bed m 71
Carried to Summary N $ Bill No. 4Precast ConcreteRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 2 9 -
BW0621-G
Item Quantity Rate AmountNo
BILL NO 5
MASONRY
SUPPLEMENTARY PREAMBLES
BRICKWORK
Sizes in descriptions
Where sizes in descriptions are given in brick units, "one brick" shallrepresent the length and "half brick" the width of a brick
Pointing
Descriptions of recessed pointing to fair face brickwork and facebrickwork shall be deemed to include square recessed, hollowrecessed, weathered pointing, etc
Samples
Samples of all masonry building units, shall consist of a minimum of6 units
FOUNDATIONS (PROVISIONAL)
14MPa Brickwork of "Uis" clay bricks in class I mortar
1 One brick walls m2 22
SUPERSTRUCTURE
7MPa Brickwork of "Uis" clay bricks in class II mortar
2 One brick walls m2 169
3 One brick walls in beamfilling m2 6
BRICKWORK SUNDRIES
Fair face to brickwork in horizontal stretcher bond with flushhorizontal and vertical joints
4 Extra for fair face m2 152
5 Extra for fair face in foundations (Provisional) m2 18
Carried Forward N $ Bill No. 5MasonryRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 3 0 -
BW0621-G
Brought Forward N $
Brick-on-edge header course copings, sills, etc of "Uis" claybricks with flush joints on all exposed faces
6 Extra over brickwork for brick-on-edge soldier course lintel m 1
Pre-stressed fabricated lintels
7 110 x 75mm Lintels in lengths not exceeding 3m m 1
Brickwork reinforcement
8 150mm Wide reinforcement built in horizontally in foundations(Provisional) m 260
9 150mm Wide reinforcement built in horizontally m 499
Turning pieces
10 220mm Wide turning piece to lintels, etc m 1
Carried to Summary N $ Bill No. 5MasonryRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 3 1 -
BW0621-G
Item Quantity Rate AmountNo
BILL NO 6
WATERPROOFING
SUPPLEMENTARY PREAMBLES
Waterproofing
Waterproofing are to be executed by an approved applicator and a tenyear guarantee for the product as well as application thereof to besubmitted to principal agent before the issuing of the practicalcompletion certificate.
Waterproofing to roofs are to be applied strictly according to themanufacturers specification and shall be laid to even falls to outlets,etc with necessary ridges, hips and valleys. Descriptions of sheet ormembrane waterproofing shall be deemed to include additional labourto turn-ups and turn-downs
DAMPPROOFING OF WALLS AND FLOORS
One layer of 375 micron "Consol Plastics Brikgrip DPC"embossed damp proof course
1 In walls m2 8
One layer of 375micron "Consol Plastics Gunplas USB Orange"waterproof sheeting sealed at laps with "Gunplas PressureSensitive Tape"
2 Under surface beds, ramps, etc m2 75
3 Under pavers, etc m2 19
JOINT SEALANTS, ETC
"Fosroc Thioflex 600" two-part polysulphide sealing compoundincluding backing cord, bond breaker, primer, etc
4 6 x 10mm In saw cut joints in floors m 24
Carried to Summary N $ Bill No. 6WaterproofingRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 3 2 -
BW0621-G
Item Quantity Rate AmountNo
BILL NO 7
ROOF COVERINGS, ETC
SUPPLEMENTARY PREAMBLES
Straight cutting
Descriptions of all roof coverings are deemed to include for allstraight cutting
PROFILED METAL SHEETING AND ACCESSORIES
0,5mm "Klip-Lock 700" galvanized troughed sheet steel in singlelengths fixed to steel purlins or rails and 0,5mm galvanized sheetsteel accessories
1 Roof coverings with pitches not exceeding 25 degrees m2 104
ROOF AND WALL INSULATION
"Sisalation FR430" heavy duty industrial grade aluminium foilbonded insulation
2 Insulation laid taut over purlins (at approximately 1250mm centres)and fixed concurrent with roof covering, including galvanised steelstraining wires m2 80
Carried to Summary N $ Bill No. 7Roof coveringRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 3 3 -
BW0621-G
Item Quantity Rate AmountNo
BILL NO 8
CARPENTRY AND JOINERY
SUPPLEMENTARY PREAMBLES
Joinery
Descriptions of frames shall be deemed to include frames, transomes,mullions, rails, etc
Descriptions of hardwood joinery shall be deemed to include pelletingof bolt holes
Fixing
Items described as "nailed" shall be deemed to be fixed with hardenedsteel nails or shot pins to brickwork or concrete
Decorative laminate finish
Laminate finish shall be glued under pressure. Edge strips shall bebutt jointed at junctions with adjacent similar finish
DOORS, ETC
44mm Wrought meranti framed, ledged and braced batten doorsof 44 x 107mm top rail, middle ledge and stiles, 16 x 107mmbraces and 22 x 219mm bottom ledge
1 Door 813 x 2032mm high filled in with 22mm V-jointed boarding toone side and other side covered with 6mm plywood with veneer tomatch door with and including 44 x 50mm rebated, splayed andgrooved weather board set into groove in door No 1
JOINERY SUNDRIES
Wrought prosopis
2 169 x 800 x 32mm Thick fire extinguisher backing board withrounded edges and corners, plugged No 1
Carried to Summary N $ Bill No. 8Carpentry & joineryRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 3 4 -
BW0621-G
Item Quantity Rate AmountNo
BILL NO 9
IRONMONGERY
SUPPLEMENTARY PREAMBLES
Finishes to ironmongery
Where applicable finishes to ironmongery are indicated by suffixes inaccordance with the following list: BS Satin bronze lacquered CH Chromium plated SC Satin chromium plated SE Silver enamelled GE Grey enamelled AS Anodized silver AB Anodized bronze AG Anodized gold ABL Anodized black PB Polished brass PL Polished and lacquered PT Epoxy coated SD Sanded
LOCKS
"Union"
1 50mm UN335000000010 PB Padlock No 1
2 "Teal" code CB6T45-05SC/L-22315-76/2X810 euro profile doublecylinder lockset No 1
SUNDRIES
"Union"
3 "87001SS" Door stop No 1
"Chubb"
4 4,5kg Dry chemical powder fire extinguisher No 1
Carried to Summary N $ Bill No. 9IronmongeryRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 3 5 -
BW0621-G
Item Quantity Rate AmountNo
BILL NO 10
STRUCTURAL STEELWORK
SUPPLEMENTARY PREAMBLES
Descriptions
Descriptions of bolts shall be deemed to include nuts and washers
Descriptions of L-shaped and U-shaped anchor bolts shall be deemedto include bending, threading, nuts and washers and embedding inconcrete
Descriptions of expansion anchors and bolts and chemical anchorsand bolts shall be deemed to include nuts, washers and mortices inbrickwork or concrete
STEEL COLUMNS, BEAMS AND RAFTERS
Welded beams and rafters in single lengths with angle sectioncleats and flat section bearer and connection plates, bolted toconcrete or brickwork
1 IPE160 x 16kg/m I-section rafters t 0.67
Bolts to columns, beams, etc
2 220 x 220 x 6mm Base plate with and including two lugs 1200mmgirth, cast into top of concrete columns No 10
Architectural features to rafter ends
3 Splayed cutting to IPE160-sections m 4
PURLINS, GIRTS, BRACING, ETC
Purlins and girts bolted to steel
4 Lipped channel section purlins t 0.28
Purlins and girts welded to steel
5 Lipped channel section purlins t 0.05
Carried to Summary N $ Bill No. 10Structural steelworkRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 3 6 -
BW0621-G
Item Quantity Rate AmountNo
BILL NO 11
METALWORK
STEEL WELDED SCREENS, GATES, ETC
Gates
1 40 x 40 x 4mm Angle section frame with stiles and lintol for 813 x2032mm gate, welded into mild steel door frame and fitted with 30 x30 x 5mm padlock lug (door frame and hinges elsewhere) No 1
2 Single gate 813 x 2032mm high overall, formed of 20 x 30 x 4mmhollow section frame around and two horizontal middle rails, top andbottom panes filled in with 10 x 10mm solid vertical bars at 90mmcenters and fitted with two 100mm weld-on hinges, barrol bolt, 55 x50 x 5mm padlock lug with slotted hole and 20 x 5mm flat sectionstricker plate, 2032mm high, welded to stile No 1
SUNDRY STEELWORK
Corner protectors
3 70 x 70 x 6mm Angle section corner protectors in varying lengthswith 20 x 5mm lugs, 70mm long at 300mm centres cast into floor m 57
Ventilation grids
4 "Flatex 344/VEM 6320C" expanded metal mesh welded to sub-frame m2 0.5
5 10 x 10mm Square solid section sub-frame welded into metal frames kg 4
6 Extra over 10 x 10mm square solid section frame for mitredL-intersection No 16
7 20 x 30 x 4mm Rectangular hollow section frames m 5
8 Extra over 20 x 30mm hollow section frame for mitred L-intersection No 8
9 Extra over 20 x 30mm hollow section frame for T-intersection No 4
10 50 x 50 x 5mm Flat section anchor plate, once holed and welded on No 8
11 8mm Anchor bolt to concrete or brickwork No 8
PRESSED STEEL DOOR FRAMES
Carried Forward N $ Bill No. 11MetalworkRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 3 7 -
BW0621-G
Brought Forward N $
1,6mm Double rebated frames suitable for one brick walls
12 Frame for door 813 x 2032mm high No 1
STEEL ROLLER SHUTTERS, ETC
"Serranda" 1,0mm thick galvanized slatted metal roller shutterswith "Chromadeck" finish fixed to brickwork or concrete
13 Chain operated slatted roller shutter for 4000 x 4500mm high openingcomplete with locking bars, lock, handles, etc No 1
FENCING, ETC
Galvanized security fencing, gates, etc including two coatsaluminium paint on metal stays, framing, etc
14 Security fencing 2,1m high formed of 2,7m x 50mm diameter x2,5mm thick pipe standards with cap and sole plate in and including300 x 300 x 650mm deep 20MPa concrete bases at maximum 4,0mcentres, four 2,5 x 4,0mm oval high strain galvanised straining wiresand three galvanised razor wires tied to standards, posts and eye bolts,etc with 1,8m height covered with 2,5 x 50mm galvanised steel razorwire mesh fixed at 450mm centres to each straining wire and 150 x250mm deep 20MPa concrete ground beam including excavations,risk of collapse, etc m 127
15 50mm Diameter x 2,5mm thick galvanised horizontal stay 1900mmlong with each end flattened, holed and bolted to posts No 10
16 50mm Diameter x 2,5mm thick galvanised inclined stay 2950mm longwith one end flattened, holed and bolted to post and other end withsole plate in and including 600 x 300 x 500mm 20MPa concrete base No 12
17 100mm Diameter x 2,5mm thick corner or straining post 2700mmhigh with cap and sole plate in and including 400 x 400 x 800mm20MPa concrete base No 7
Carried Forward N $ Bill No. 11MetalworkRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 3 8 -
BW0621-G
Brought Forward N $
18 Double gate 5,2 x 2,1m high overall, each leaf of 50mm diameter x2,5mm thick frame with two 30 x 5mm mild steel flat diagonal braces,both stiles extended at top to form top panel to suit the securityfencing and the bottom 1,8m high covered with 2,5 x 50mmgalvanised steel razor wire mesh fixed to framing and cross brace andtop section provided with three galvanised razor wires tied to stiles,including two square 100 x 100mm round bar handguards, heavy dutyhinges, chain, 50mm "Union" padlock and two 10mm diameter450mm long barrel bolts with two 100mm long keeps in and including300 x 300 x 300mm 20MPa concrete anchor blocks No 1
Carried to Summary N $ Bill No. 11MetalworkRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 3 9 -
BW0621-G
Item Quantity Rate AmountNo
BILL NO 12
PLASTERING
SUPPLEMENTARY PREAMBLES
GRANOLITHIC
Method
The method to be used shall be either the monolithic or bondedmethod
Preparation
For granolithic applied monolithically, the concrete floor shall beswept clean after bleeding of the concrete has ceased and the slab hasbegun to stiffen; any remaining bleed water shall be removed and thegranolithic shall then be applied immediately afterwards. Forgranolithic to be bonded to the floor slab after it has hardened, theslab surface shall be hacked (preferably by mechanical means) untilall laitance, dirt, oil, etc is dislodged and swept clean of all loosematter. The slab shall then be wetted and kept damp for at least sixhours before applying the finish
Mix
Granolithic shall attain a compressive strength of at least 41MPa. Thecoarse aggregate shall comply with SABS 1083 and be capable ofpassing a 10mm mesh sieve. Where the thickness of the granolithicexceeds 25mm, the size of the coarse aggregate shall be increased tothe maximum size compatible with the thickness of the granolithic
Laying
Monolithic granolithic shall be applied to the partially set slab andthoroughly compacted and lightly wood floated to the required levels
Bonded granolithic shall be applied to the slab after applying a 1:1sand and cement slurry brushed over the surface and allowed topartially set before applying the granolithic, thoroughly compactedand lightly wood floated to the required levels
After wood floating, the monolithic and bonded granolithic shallremain undisturbed until bleeding has ceased and the surface hasstiffened, any remaining bleed water and laitance shall then beremoved and the surface steel trowelled or power floated
Carried Forward N $ Bill No. 12PlasteringRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 4 0 -
BW0621-G
Brought Forward N $
Curing, seasoning and protection
Granolithic shall be covered with clean hessian with waterproofbuilding foil over and kept wet for at least seven days after laying
Colour
Coloured granolithic shall be tinted with an approved colouringpigment mixed into a true and even colour
GRANOLITHIC
Untinted granolithic on concrete
1 35mm Thick on treads and risers of stairs including reedings m2 0.2
INTERNAL PLASTER
Cement plaster on brickwork
2 On walls m2 184
3 On narrow widths m2 0.4
EXTERNAL PLASTER
Cement plaster on brickwork
4 On walls m2 30
5 On narrow widths m2 0.4
Carried to Summary N $ Bill No. 12PlasteringRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 4 1 -
BW0621-G
Item Quantity Rate AmountNo
BILL NO 13
PAINTWORK
SUPPLEMENTARY PREAMBLES
DESCRIPTIONS
Descriptions of paintwork shall be deemed to include for all cutting in
ISO Pine polystyrene insulated roof liner
Visible dents, defects , etc to be filled with "ISO Pine" adhesive andpolyfiller mix and sand down smoothly before application of paint
PAINTWORK, ETC TO NEW WORK ON
FLOATED PLASTER SURFACES WITH
One coat "Pera Aquaprime (CE-1)" primer, stopped with"Polycell Mendall 90" and two coats "Pera-Acrylon EAG"acrylic paint on
1 Internal walls m2 184
2 External walls m2 30
ON CLAY BRICKS
Two coats "Siliseal Waterproofing A101" sealant, using a lowpressure spray, on
3 Walls m2 170
SMOOTH CONCRETE
Scrub down and wash with sugar soap and three coats "Cobra"clear wax polish on
4 Floors, etc m2 72
METAL SURFACES WITH
Carried Forward N $ Bill No. 13PaintworkRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 4 2 -
BW0621-G
Brought Forward N $
Clean with "Pera-XC" metal cleaner, spot priming defects inpre-primed surfaces with zinc chromate metal primer, one coat"Pera ANTIRUST CWP-1" undercoat and two coats"Pera-Acrylon EAG" acrylic paint on
5 Door frames m2 2
6 Members of roof trusses and structural steel m2 119
7 Gates, grilles, balustrades, etc (both sides measured on flat) m2 6
8 Rails, bars, pipes, etc not exceeding 300mm girth m 8
WOOD SURFACES WITH
Two coats "AECI Paints (Pty) Ltd Woodguard Timbasheen"sealant on
9 Doors m2 4
Carried to Summary N $ Bill No. 13PaintworkRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 4 3 -
BW0621-G
Item Quantity Rate AmountNo
BILL NO 14
PROVISIONAL AMOUNTS
SPECIALIST WORK
Electrical installation
1 Allow the amount of N$35 000.00 (thirty five thousand Namibiadollars) for the electrical installation Item 35 000 00
2 Add for profit on above if required Item
3 Allow for attendance Item
Electrical connection fee
4 Allow the amount of N$50 000.00 (fifty thousand Namibia dollars)for electrical connection fee Item 50 000 00
5 Add for profit on above if required Item
6 Allow for attendance Item
CONTINGENCIES
Construction contingencies
7 Allow the amount of N$ 35 000,00 (thirty five thousand Namibiadollars) for contingencies to be used as directed by the engineer anddeducted in whole or in part if not required Item 35 000 00
Carried to Summary N $ Bill No. 14Provisional amountsRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia
- 4 4 -
BW0621-G
FINAL SUMMARY
Bill Page AmountNo No
1 -20-Preliminaries
2 -23-Earthworks
3 -27-Concrete, formwork & reinforcement
4 -29-Precast Concrete
5 -31-Masonry
6 -32-Waterproofing
7 -33-Roof covering
8 -34-Carpentry & joinery
9 -35-Ironmongery
10 -36-Structural steelwork
11 -39-Metalwork
12 -41-Plastering
13 -43-Paintwork
14 -44-Provisional amounts
Net Amount N $
Add: Value Added Tax at 15% N $
Carried to Form of Tender N $ RSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia