BW0621-G Item Unit Quantity Rate Amount No BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed by the Employer as issued by the Federation Internationale des Ingenieurs-Conseils (FIDIC), 2010 Edition shall be the applicable contract for the execution of the Works The Model Preliminaries (1988 edition) as approved and recommended by the Namibian Institute of Quantity Surveyors and as published by the Association of South African Quantity Surveyors shall be taken to be incorporated herein Contractors are referred to the above-mentioned documents for the full intent and meaning of each clause thereof These clauses are hereinafter referred to by clause number only. Where standard clauses or alternatives are not applicable to the contract, such modifications / corrections as are necessary, are given under each relevant clause Items that are not relevant to this contract have been listed and are marked "N/A" (not applicable) The Model Preambles for Trades (2008 edition) as approved and recommended by the Namibian Institute of Quantity Surveyors and as published by the Association of South African Quantity Surveyors shall be deemed to be incorporated in these bills of quantities Supplementary preambles to the Model Preambles covering clauses of a general nature, clauses pertaining to specific materials and amendments to clauses in the Model Preambles are incorporated in these bills of quantities to satisfy the requirements of this project The contractor's prices for all items throughout these bills of quantities must take account of and include for all of the obligations, requirements and specifications given in the Model Preambles and Supplementary Preambles SECTION A - CONDITIONS OF CONTRACT FOR CONSTRUCTION Carried Forward N$ Bill No. 1 Preliminaries RSRC - GARAGE FOR MOBILE UNIT Millennium Challenge Account Namibia -1-

Upload: truongnguyet

Post on 20-May-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Item Unit Quantity Rate AmountNo

BILL NO 1

PRELIMINARIES

NOTES:

The Conditions of Contract for Construction for Building andEngineering Works Designed by the Employer as issued by theFederation Internationale des Ingenieurs-Conseils (FIDIC),2010 Edition shall be the applicable contract for the execution ofthe Works

The Model Preliminaries (1988 edition) as approved andrecommended by the Namibian Institute of Quantity Surveyorsand as published by the Association of South African QuantitySurveyors shall be taken to be incorporated herein

Contractors are referred to the above-mentioned documents for thefull intent and meaning of each clause thereof

These clauses are hereinafter referred to by clause number only.Where standard clauses or alternatives are not applicable to thecontract, such modifications / corrections as are necessary, aregiven under each relevant clause

Items that are not relevant to this contract have been listed and aremarked "N/A" (not applicable)

The Model Preambles for Trades (2008 edition) as approvedand recommended by the Namibian Institute of QuantitySurveyors and as published by the Association of South AfricanQuantity Surveyors shall be deemed to be incorporated in thesebills of quantities

Supplementary preambles to the Model Preambles coveringclauses of a general nature, clauses pertaining to specific materialsand amendments to clauses in the Model Preambles areincorporated in these bills of quantities to satisfy the requirementsof this project

The contractor's prices for all items throughout these bills ofquantities must take account of and include for all of theobligations, requirements and specifications given in the ModelPreambles and Supplementary Preambles

SECTION A - CONDITIONS OF CONTRACT FORCONSTRUCTION

Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 1 -

Page 2: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

CLAUSE 1 - GENERAL PROVISIONS

1 Clause 1.1 - Definitions Item

2 Clause 1.2 - Interpretation Item

3 Clause 1.3 - Communications Item

4 Clause 1.4 - Law and language Item

5 Clause 1.5 - Priority and documents Item

6 Clause 1.6 - Contract Agreement Item

7 Clause 1.7 - Assignment Item

8 Clause 1.8 - Care and supply of documents Item

9 Clause 1.9 - Delayed drawings or instructions Item

10 Clause 1.10 - Employer's use of Contractor's documents Item

11 Clause 1.11 - Contractor's use of Employer's documents Item

12 Clause 1.12 - Confidential details Item

13 Clause 1.13 - Compliance with laws Item

[a] Contractor to comply with the Namibia EnvironmentalManagement Act No. 7 of year 2007 as well as the EnvironmentalAssessment Policy of year 1995 by implementing theEnvironmental Management Plans (EMP) documented separatelyas part of this contract

Bidder's are compelled to price this Line Item in accordance withthe cost estimate required in Form: Environmental and SocialDocuments

[b] Contractor to comply with the Namibia Public Health andSafety Management Policy under Act No. 11 of year 2007 byimplementing the Public Health and Safety Awareness Plan(PHSAP) documented separately as part of this contract

Bidder's are compelled to price this Line Item in accordance withthe cost estimate required in Form: Health and Safety Documents

Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 2 -

Page 3: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

14 Clause 1.14 - Joint and several liability Item

CLAUSE 2 - THE EMPLOYER

15 Clause 2.1 - Right of access to the site Item

16 Clause 2.2 - Permits, Licences of Approvals Item

17 Clause 2.3 - Employer's personnel Item

18 Clause 2.4 - Employer's financial arrangement Item

CLAUSE 3 - THE ENGINEER

The Engineer will be deemed to be the Principal Agent, Architector any other person as appointed by the Client to fulfil such duties

19 Clause 3.1 - Engineer's duties and authority Item

20 Clause 3.2 - Delegation by the Engineer Item

21 Clause 3.3 - Instructions of the Engineer Item

22 Clause 3.4 - Replacement of the Engineer Item

23 Clause 3.5 - Determinations Item

CLAUSE 4 - THE CONTRACTOR

24 Clause 4.1 - Contractor's general obligations Item

25 Clause 4.2 - Performance security Item

26 Clause 4.3 - Contractor's security Item

27 Clause 4.4 - Sub-Contractors Item

28 Clause 4.5 - Assignment of benefit of Sub-contract Item

29 Clause 4.6 - Co-operation Item

30 Clause 4.7 - Setting out Item

31 Clause 4.8 - Safety procedures Item

32 Clause 4.9 - Quality assurance Item

Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 3 -

Page 4: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

33 Clause 4.10 - Site data Item

34 Clause 4.11 - Sufficiency of accepted Contract Amount Item

35 Clause 4.12 - Unforeseeable physical conditions Item

36 Clause 4.13 - Right of way and facilities Item

37 Clause 4.14 - Avoidance of interference Item

38 Clause 4.15 - Access route Item

39 Clause 4.16 - Transport of goods Item

40 Clause 4.17 - Contractor's equipment Item

41 Clause 4.18 - Protection of the environment Item

42 Clause 4.19 - Electricity, water and gas Item

43 Clause 4.20 - Employer's equipment and free-issue material Item

44 Clause 4.21 - Progress reports Item

45 Clause 4.22 - Security of the site Item

46 Clause 4.23 - Contractor's operations on site Item

47 Clause 4.24 - Fossils Item

CLAUSE 5 - NOMINATED SUB-CONTRACTORS

48 Clause 5.1 - Definition of "nominated Sub-Contractor" Item

49 Clause 5.2 - Objection to nomination Item

50 Clause 5.3 - Payments to nominated Sub-Contractors Item

51 Clause 5.4 - Evidence of payments Item

CLAUSE 6 - STAFF AND LABOUR

52 Clause 6.1 - Engagement of staff and labour Item

53 Clause 6.2 - Rates of wages and conditions of labour Item

Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 4 -

Page 5: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

54 Clause 6.3 - Persons in the service of the Employer Item

55 Clause 6.4 - Labour laws Item

56 Clause 6.5 - Working hours Item

57 Clause 6.6 - Facilities for staff and labour Item

58 Clause 6.7 - Health and safety Item

59 Clause 6.8 - Contractor's superintendence Item

60 Clause 6.9 - Contractor's personnel Item

61 Clause 6.10 - Records of Contractor's personnel and equipment Item

62 Clause 6.11 - Disorderly conduct Item

CLAUSE 7 - PLANT, MATERIALS AND WORKMANSHIP

63 Clause 7.1 - Manner of execution Item

64 Clause 7.2 - Samples Item

65 Clause 7.3 - Inspection Item

66 Clause 7.4 - Testing Item

67 Clause 7.5 - Rejection Item

68 Clause 7.6 - Remedial work Item

69 Clause 7.7 - Ownership of plant and material Item

70 Clause 7.8 - Royalties Item

CLAUSE 8 - COMMENCEMENT, DELAYS ANDSUSPENSION

71 Clause 8.1 - Commencement of works Item

72 Clause 8.2 - Time for completion Item

73 Clause 8.3 - Programme Item

74 Clause 8.4 - Extension of time for completion Item

Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 5 -

Page 6: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

75 Clause 8.5 - Delays caused by authorities Item

76 Clause 8.6 - Rate of progress Item

77 Clause 8.7 - Delay damages Item

78 Clause 8.8 - Suspension of work Item

79 Clause 8.9 - Consequences of suspension Item

80 Clause 8.10 - Payment for plant and materials in event ofsuspension Item

81 Clause 8.11 - Prolonged suspension Item

82 Clause 8.12 - Resumption of work Item

CLAUSE 9 - TESTS ON COMPLETION

83 Clause 9.1 - Contractor's obligation Item

84 Clause 9.2 - Delayed tests Item

85 Clause 9.3 - Retesting Item

86 Clause 9.4 - Failure to pass tests on completion Item

CLAUSE 10 - EMPLOYER'S TAKING OVER

87 Clause 10.1 - Taking over of the works and sections Item

88 Clause 10.2 - Taking over of parts of the works Item

89 Clause 10.3 - Interference with tests on completion Item

90 Clause 10.4 - Surfaces requiring reinstatement Item

CLAUSE 11 - DEFECTS LIABILITY

91 Clause 11.1 - Completion of outstanding work and remedyingdefects Item

92 Clause 11.2 - Cost of remedying defects Item

93 Clause 11.3 - Extension of defects notification period Item

Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 6 -

Page 7: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

94 Clause 11.4 - Failure to remedy defects Item

95 Clause 11.5 - Removal of defective work Item

96 Clause 11.6 - Further tests Item

97 Clause 11.7 - Right of access Item

98 Clause 11.8 - Contractor to search Item

99 Clause 11.9 - Performance certificate Item

100 Clause 11.10 - Unfulfilled obligations Item

101 Clause 11.11 - Clearance of site Item

CLAUSE 12 - MEASUREMENT AND EVALUATIONLIABILITY

102 Clause 12.1 - Works to be measured Item

103 Clause 12.2 - Method of measurement Item

104 Clause 12.3 - Evaluation Item

105 Clause 12.4 - Omissions Item

CLAUSE 13 - VARIATIONS AND ADJUSTMENTS

106 Clause 13.1 - Right to vary Item

107 Clause 13.2 - Value engineering Item

108 Clause 13.3 - Variation procedure Item

109 Clause 13.4 - Payment in applicable currencies Item

110 Clause 13.5 - Provisional sums Item

111 Clause 13.6 - Daywork Item

112 Clause 13.7 - Adjustments for changes in legislation Item

113 Clause 13.8 - Adjustments for changes in cost Item

Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 7 -

Page 8: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

CLAUSE 14 - CONTRACT PRICE AND PAYMENTS

114 Clause 14.1 - The Contract Price Item

115 Clause 14.2 - Advance payment Item

116 Clause 14.3 - Application for interim Payment Certificates Item

117 Clause 14.4 - Schedule of payments Item

118 Clause 14.5 - Plant and materials intended for the works Item

119 Clause 14.6 - Issue of interim Payment Certificates Item

120 Clause 14.7 - Payment Item

121 Clause 14.8 - Delayed payment Item

122 Clause 14.9 - Payment of retention money Item

123 Clause 14.10 - Statement at completion Item

124 Clause 14.11 - Application for Final Payment Certificate Item

125 Clause 14.12 - Discharge Item

126 Clause 14.13 - Issue of Final Payment Certificate Item

127 Clause 14.14 - Cessation of Employer's liability Item

128 Clause 14.15 - Currencies of payment Item

CLAUSE 15 - TERMINATION BY EMPLOYER

129 Clause 15.1 - Notice to correct Item

130 Clause 15.2 - Termination by Employer Item

131 Clause 15.3 - Valuation at date of termination Item

132 Clause 15.4 - Payment after termination Item

133 Clause 15.5 - Employer's entitlement to termination Item

Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 8 -

Page 9: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

CLAUSE 16 - SUSPENSION AND TERMINATION BYCONTRACTOR

134 Clause 16.1 - Contractor's entitlement to suspend work Item

135 Clause 16.2 - Termination by Contractor Item

136 Clause 16.3 - Cessasion of work and removal of Contractor'sequipment Item

137 Clause 16.4 - Payment and termination Item

CLAUSE 17 - RISK AND RESPONSIBILITY

138 Clause 17.1 - Indemnities Item

139 Clause 17.2 - Contractor's care of the works Item

140 Clause 17.3 - Employer's risks Item

141 Clause 17.4 - Consequences of Employer's risks Item

142 Clause 17.5 - Intellectual and industrial property rights Item

143 Clause 17.6 - Limitation of liability Item

CLAUSE 18 - INSURANCE

144 Clause 18.1 - General requirements for insurance Item

145 Clause 18.2 - Insurance for works and Contractor's equipment Item

146 Clause 18.3 - Insurance against injury to persons and damage toproperty Item

147 Clause 18.4 - Insurance for Contractor's personnel Item

CLAUSE 19 - FORCE MAJEURE

148 Clause 19.1 - Definition of Force Majeure Item

149 Clause 19.2 - Notice of Force Majeure Item

150 Clause 19.3 - Duty to minimise delay Item

151 Clause 19.4 - Consequences of Force Majeure Item

Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 9 -

Page 10: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

152 Clause 19.5 - Force Majeure affecting Sub-Contractor Item

153 Clause 19.6 - Optimal termination, payment and release Item

154 Clause 19.7 - Release from performance under the law Item

CLAUSE 20 - CLAIMS, DISPUTES AND ARBITRATION

155 Clause 20.1 - Contractor's claim Item

156 Clause 20.2 - Appointment of the Dispute Adjudication Board Item

157 Clause 20.3 - Failure to agree to Dispute Adjudication Board Item

158 Clause 20.4 - Obtaining Dispute Adjudication Board's decision Item

159 Clause 20.5 - Amicable settlement Item

160 Clause 20.6 - Arbitration Item

161 Clause 20.7 - Failure to comply to Dispute Adjuducation Board'sdecision Item

162 Clause 20.8 - Expiry of Dispute Adjuducation Board'sappointment Item

SECTION B - PRELIMINARIES

B1: SUPPLEMENTARY DOCUMENTATION

163 B1.1: Bills of quantities Item

164 B1.2: Provisional bills of quantities N/A

165 B1.3: Availability of construction documentation for contractsbased on provisional bills of quantities N/A

B1.4: Name of Architect, Quantity Surveyor and otherconsultants:

Principal Agent : Se[arch] TeamArchitects : Nina Maritz ArchitectsQuantity Surveyors : De Leeuw NamibiaCivil/Struct Engineers : Bührmann & PartnersElectr/Mech Engineers : Emcon

Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 1 0 -

Page 11: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

166 B1.5: Lodging and scrutiny of priced bills of quantities Item

The priced Bills of Quantities, displaying unit rates, extended inblack ink and initialed on every page, will be submitted with thetender document

Failure to comply with this clause will result in thedisqualification of the tender

167 B1.6: Meaning of words Item

168 B1.6.1: Singular and plural Item

169 B1.6.2: Standard specifications Item

170 B1.6.3: Definition of "approved" etc Item

171 B1.7: Performance guarantee by the Contractor Item

Sub-clause 3. of this clause is not applicable. No interim paymentwill be certified before accepted guarantees have been received

The full security for the due fulfilment of all obligations under thiscontract is to remain in force for 60 (sixty) days after practicalcompletion or finalisation of the final account, whichever is thelater date

No guarantee containing any clause that allows the financialinstitution providing such guarantee to either withdraw from theirundertaking before 60 (sixty) days after practical completion, orthat stipulates an expiry date is acceptable

Notwithstanding the above, the guarantee will only be returned tothe contractor after receipt of satisfactory proof that thecontractor has met all his obligations under any and all selectedand nominated sub-contract agreements applicable to thiscontract

172 B1.8: Payment guarantee by Employer N/A

173 B1.9: Waiver of contractor's lien Item

174 B1.10: Signing powers Item

175 B1.11: Tenders Item

Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 1 1 -

Page 12: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

Notwithstanding anything contained in this clause tenders shallbe valid for a period of 90 (ninety) days from the closing date oftenders

The Employer reserves the right to correct any arithmetical orother errors in the extension of the rates and totals in the tenderand / or to adjust any rates that are considered by him to beimbalanced and unacceptable. Such adjustments will be donewithout affecting the Tender Sum

176 B1.12: Inspection of documents Item

The following drawings are issued with this bill

Drawing No: RP-01 Ground Floor Reference PlanDrawing No: SP-01 Site LayoutDrawing No: E-01 Site Elevations: NorthDrawing No: E-02 Site Elevations: SouthDrawing No: E-03 Ste Elevations: East & West

B.2: THE SITE

177 B2.1: Site and site boundaries Item

The site is the remainder of Farm Helao Nafidi, Settlement Areanumber 997, Ohangwena Region, Namibia

178 B2.2: Area of the works

The area of the works to be occupied by the contractor, anyrestriction to the area and access/exit limitations will be pointedout to the contractor by the Principal Agent during site handover Item

179 B2.3: Boundary beacons, setting out pegs and master datum

The contractor shall notify the Principal Agent if anyencroachments of adjoining foundations, buildings, structures,pavements, etc exist so that the necessary arrangements can bemade for the rectification of any such encroachments Item

180 B2.4: Site soil investigation Item

181 No site soil investigation report is available and the tenderer isadvised to inspect the site to ascertain the exact nature of theground Item

Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 1 2 -

Page 13: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

182 B2.5: Viewing of the site

No claim for extras arising from the contractor having failed tocomply with this Clause will be entertained Item

183 B2.6: Existing premises occupied N/A

184 B2.7: Dimensional accuracy of work executed under the previouscontract N/A

185 B2.8: Defects in work executed under the previous contract N/A

186 B2.9: Existing known services

Existing services and points of connection are shown on the siteplan or will be pointed out by the Principal Agent during sitehandover Item

187 B2.10: Unknown services Item

188 B2.11: Protection of trees, etc Item

Existing trees to be retained and protected will be identified bythe Principal Agent during site handover

189 B2.12: Articles of value Item

190 B2.13: Inspection of nearby properties, etc Item

B3: MANAGEMENT OF CONTRACT

191 B3.1: Management of works Item

192 B3.2: Programming of the works

The contract shall be programmed by the contractor inaccordance with alternative A Item

Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 1 3 -

Page 14: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

193 B3.3: Progress meetings

Progress meetings will be held once a month and will be attendedby the Contractor and his Foreman, Consultants andrepresentatives of the Employer

Should any of the Consultants or representatives of the Employerhave to make a separate trip for any reason which, in the opinionof the Principal Agent is due to the fault of the Contractor, thecost of such a trip shall be for the Contractors own account Item

194 B3.4: Technical meetings Item

B4: MATERIALS AND WORKMANSHIP

195 B4.1: Samples of materials Item

196 B4.2: Samples of workmanship and mockups Item

197 B4.3: Ordering of materials Item

B5: TEMPORARY WORKS AND PLANT

198 B5.1: Deposits and fees Item

199 B5.2: Enclosure of works Item

The contractor shall provide proper protection and provide anderect any temporary barriers, dust screens, etc that may benecessary during the progress of the works, all to the satisfactionof the principal agent, and remove when directed

200 B5.3: Pavement crossings and parking meters Item

201 B5.4: Advertising Item

202 B5.5: Plant and equipment Item

The contractor shall make available hoisting facilities and hoistinto position all sub-contractor's materials or manufacturedarticles for the works for the duration of the contract whilst suchhoisting facilities are in position for the works

Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 1 4 -

Page 15: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

203 B5.6: Special scaffolding

No special scaffolding is measured as these bills of quantities arebased on the sixth edition of the Standard System for MeasuringBuilding Work Item

204 B5.7: Contractor's offices and sheds Item

205 B5.8: Offices Item

206 B5.9: Office of the clerk of works N/A

207 B5.10: Main notice board Item

208 B5.11: Sub-Contractors' notice-board Item

B6: TEMPORARY SERVICES

209 B6.1: Water Item

Contractor shall provide water for the works in accordance withalternative A

210 B6.2: Electricity and lighting Item

Contractor shall provide electricity for the works in accordancewith alternative A

211 B6.3: Telephones Item

212 B6.4: Toilets Item

Contractor shall provide toilets in accordance with alternative A

B7: PRIME COST AND PROVISIONAL AMOUNTS

213 B7.1: Cash discount Item

All prime cost and provisional sums are "NET" and do notinclude a cash discount, nor will the Contractor be allowed orentitled to a cash discount

214 B7.2: Taking delivery and fixing of prime cost items Item

215 B7.3: Nominated or selected sub-contract documents Item

Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 1 5 -

Page 16: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

216 B7.4: Attendance on nominated or selected sub-contractors Item

217 B7.5: Fuel, power and water for commissioning of mechanical andother specialised installations Item

B8: FINANCIAL ASPECTS

218 B8.1: Sales tax Item

Prices for items contained in these bills of quantities shall becalculated on the "NET" basis (ie excluding all components ofVAT). VAT will be added separately on the Summary page and allcertificate calculations

219 B8.2: Contract Price Adjustment Provisions Item

This contract amount will not be subject to contract priceadjustment provisions. Therefore the contractor must allow, if hedeems it necessary, for any price adjustment provisions under thisitem

220 B8.3: Payment of preliminaries Item

Payment of preliminaries will be calculated from the priced itemswithin the preliminaries in accordance with alternative B

221 B8.4: Adjustment of preliminaries Item

The adjustment of preliminaries will be on the basis of fixed price,value related and time related items in accordance with method 2

In addition to the exclusions mentioned in the third paragraph ofthis clause it shall be deemed that "day works" be added as afourth exclusion

222 B8.5: Certificate and payment projection Item

223 B8.6: Day works Item

Notwithstanding anything contained in this Clause, the signatureof the Principal Agent shall not indicate acceptance of quantum,value or method of valuation of work executed thereunder. Thequantum of these day works and the method of valuation will bedecided by the Quantity Surveyor

224 B8.7: Information supplied by contractor Item

Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 1 6 -

Page 17: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

B9: GENERAL

225 B9.1: Protection Item

226 B9.2: Protection of existing and/or partially occupied works Item

227 B9.3: Safety Item

The contractor and his work force will strictly comply with allhealth and safety regulations as stipulated in the latest NamibianMachinery and Occupational Safety Act as well as requirementsas set out in the Health and Safety Booklet as issued by theConstruction Industries Federation of Namibia

The principal agent retains the right to stop any work or requestany personnel to be removed from the site, should the contractoror his work-force fail to comply with the regulations as set out inabove-mentioned documents

All expenses / delays accrued due to the above will be for the costof the contractor

228 B9.4: Site security Item

229 B9.5: Notice before covering work Item

230 B9.6: Disturbance Item

231 B9.7: Clearing and cleaning Item

232 B9.8: Vermin Item

233 B9.9: Overhand work Item

234 B9.10: Jobbing Item

SECTION C - SPECIFIC PRELIMINARIES

235 Revenue stamps Item

The contractor must allow for and provide all necessary revenuestamps required in connection with the Agreement and Scheduleof Conditions of Building Contract and the PerformanceGuarantee in accordance with the Stamp Duty Act

236 As built drawings Item

Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 1 7 -

Page 18: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

The position of construction breaks and the extent of individualconcrete pours are to be recorded by the contractor on thestructural engineer's drawings and are to be submitted to thearchitect and the structural engineer for their records

The contractor shall furnish the Architect with a set of markeddrawings indicating the positions of all plumbing and drainagepipework as actually built

237 Site instructions Item

Site instructions issued on site are to be recorded in triplicate in asite instruction book which is to be maintained on site by the maincontractor

238 Labour record Item

At the end of each week the contractor shall provide the PrincipalAgent with a written record, in schedule form, showing thenumber and descriptions of tradesmen and labourers employed byhim and all sub-contractors on the works each day

239 Plant record Item

At the end of each week the contractor shall provide the PrincipalAgent with a written record, in schedule form, showing thenumber, type and capacity of all plant, excluding hand tools,currently used on the works

240 Guarantee Item

Where guarantees are called for, the Contractor shall obtain awritten guarantee, addressed to the Employer, from the firmsupplying the materials and/or doing the work and shall deliversame to the Architect on the certified completion of the contract.The guarantee shall state that workmanship, materials andinstallation are guaranteed for a specified period from the date ofcertified completion of the contract, and that any defects that mayarise during the specified period shall be made good at theexpense of the firm supplying the materials and/or doing thework, upon written notice from the Architect to do so. Thisguarantee will not be enforced if the work is damaged bystructural defects in the building in which case the responsibilityfor replacement shall rest entirely with the Contractor. TheArchitect shall be the sole judge of the cause responsible fordefects in the work and his ruling shall be final and binding

Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 1 8 -

Page 19: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

241 Inspection of the works at practical completion Item

The contractor is to ensure that the Principal Agent is not calledto the site for the practical completion inspection before the worksare complete. The cost, both in time and travel for anyunnecessary trips will be for the sole account of the contractor

242 Disconnection of existing services Item

Any water-supply pipes, sewer pipes, other piping and electricalcables that may be met with and found necessary to disconnect orcut, shall be effectively stopped-off and any new connections orre-routing that may be necessary shall be made with properfittings, to the satisfaction of the principal agent

243 Local community involvement Item

It is the express desire of the client that the local community beinvolved. The contractor is encouraged to employ labour fromthe area in which the project is situated. This applied equally tothe skilled and unskilled labour force. The successful contractormust be willing, during the course of this project to impart skillsto the members of the local community

244 Employment of Namibian People Item

It is an explicit condition of this contract that no unskilled labourmay be employed on these works unless he or she is a Namibian.Further, it is a condition of this contract that no skilled orsemi-skilled labour, being a non-Namibian person, be employedin this contract unless the contractor can prove that there is nosuitably trained Namibian available

245 Language and Law Item

The language to be used shall be English

The contract is subject to the law of the Republic of Namibia

246 Foreign Investment Item

Carried Forward N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 1 9 -

Page 20: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

The contractor may move construction plant and equipment intoNamibia for the purpose of this contract, and may remove samefrom Namibia after completion of the Contract subject to theprovisions of the Customs Act No 20 of 1998. After tax profits maybe taken out of Namibia to countries within the Rand monitoryarea without restriction by Namibia. The Foreign Investment ActNo 27 of 1990 and all amendments thereto will apply in thisregard

Carried to Summary N $ Bill No. 1PreliminariesRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 2 0 -

Page 21: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Item Quantity Rate AmountNo

BILL NO 2

EARTHWORKS (PROVISIONAL)

SUPPLEMENTARY PREAMBLES

Nature of ground

The nature of the ground is assumed to be imported sandy material,therefore "earth", but possibly interspersed with "hard rock" or "softrock".

Earth

All material as spesified above as well as all material which ispickable or which can be excavated by means of a backactor(complete with all equipment and accessories and in good condition,producing not less than 57kw (gross) at the flywheel and with a baretractor mass of not less than 7900kg, equipped with 600mm widebucket with matching teeth) will be classified as "earth". All bouldersnot exceeding 0,3m3 in volume will also be classified as "earth"

Soft rock

All material which can not be removed as described above, but theremoval of which necessitates the use of jack hammers with moilpoints, will be classified as "soft rock"

Hard rock

All very hard material which can not be removed as described above,but the removal of which necessitates the use of explosives or heavyduty hydraulic percussion hammers (peckers), will be classified as"hard rock"

Carried Forward N $ Bill No. 2EarthworksRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 2 1 -

Page 22: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

Carting away of excavated material

Descriptions of carting away of excavated material shall be deemed toinclude loading excavated material onto trucks directly from theexcavations or, alternatively, from stock piles situated on the buildingsite

Filling

Notwithstanding the reference to prescribed multiple handling inclause 1 page 6 of the Standard System of Measuring Building Work,prices for filling and backfilling shall include for all selection and anymultiple handling of material

REMOVAL OF EXISTING WORK

Taking out and setting aside for re-use (re-installing elsewhere)

1 80mm Interlock paving m2 50

2 Pre-cast concrete road kerbs including cleaning of mortar andpreparing for re-use m 5

EXCAVATION, FILLING, ETC OTHER THAN BULK

Excavation in soil raft not exceeding 2m deep

3 Reduce levels under paving, etc m3 38

4 Trenches m3 28

Extra over all excavations for carting away

5 Surplus material from excavations and/or stock piles on site to adumping site to be located by the contractor m3 38

Risk of collapse of excavations

6 Sides of trench and hole excavations not exceeding 1,5m deep m2 70

Keeping excavations free of water

7 Keeping excavations free of water Item

Carried Forward N $ Bill No. 2EarthworksRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 2 2 -

Page 23: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

Earth filling of G6 material obtained from the excavations and/orprescribed stock piles on site compacted to 95% Mod AASHTOdensity

8 Under floors, steps, pavings, etc m3 19

9 Backfilling to trenches, holes, etc m3 14

Earth filling supplied by the contractor

10 G6 material under floors, steps, pavings, etc compacted to 95% ModAASHTO density m3 59

Compaction of surfaces

11 Compaction of ground surface in trench excavations etc to 95% ModAASHTO density m2 30

12 Compaction of ground surface under floors, paving, etc includingscarifying for a depth of 150mm, breaking down oversize material,adding suitable material where necessary and compacting to 93%Mod AASHTO density m2 270

Approved clean sand filling supplied by the contractor

13 25mm Thick under floors, etc m3 2

Prescribed density tests on filling

14 "Modified AASHTO Density" test No 8

SOIL POISONING

"Premise 200SC" weedkiller mixed with water and applied at arate of 5 litre/m2

15 Under floors, etc including forming and poisoning shallow furrowsagainst foundation walls, etc filling in furrows and ramming m2 270

16 To bottoms and sides of trenches, etc m2 100

Carried to Summary N $ Bill No. 2EarthworksRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 2 3 -

Page 24: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Item Quantity Rate AmountNo

BILL NO 3

CONCRETE, FORMWORKAND REINFORCEMENT

SUPPLEMENTARY PREAMBLES

Soilcrete

Soilcrete shall be mixed in a suitable mixer to ratios by mass. In situmaterial must be approved and have a maximum PI of 4

Water content to be adjusted to obtain 80-100mm slump

All trench bottom material disturbed during excavation must becompacted to 90% Mod AASHTO density. Trenches shall bebackfilled with soilcrete to the founding level on which the stripfooting or column base shall be cast, allowing 24 hours betweencasting of soilcrete and casting of concrete

The soilcrete shall be placed with a mechanical vibrator in a singleoperation

Cost of tests

The costs of making, storing and testing of concrete test cubes asrequired under clause 7 "Tests" of SABS 1200 G shall include thecost of providing cube moulds necessary for the purpose, for testingcosts and for submitting reports on the tests to the architect. Thetesting shall be undertaken by an independent firm or institutionnominated by the contractor and to the approval of the architect.(Test cubes are measured separately)

Formwork

Descriptions of formwork shall be deemed to include use and wasteonly (except where described as "left in" or "permanent"), for fittingtogether in the required forms, wedging, plumbing and fixing to trueangles and surfaces as necessary to ensure easy release duringstripping and for reconditioning as necessary before re-use. Thevertical strutting shall be carried down to such construction as issufficiently strong to afford the required support without damage andshall remain in position until the newly constructed work is able tosupport itself.

Carried Forward N $ Bill No. 3Concrete, formwork & reinforcementRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 2 4 -

Page 25: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

Formwork to soffits of (solid) slabs etc shall be deemed to be to slabsnot exceeding 250mm thick unless otherwise described

Formwork to soffits of slabs, beams etc shall be deemed to be to slabspropped up exceeding 1,5 but not exceeding 3,5m high unlessotherwise described

Formwork to sides of bases, pile caps, ground beams, etc will only bemeasured where it is prescribed by the engineer for design reasons.Formwork necessitated by irregularity or collapse of excavated faceswill not be measured and the cost thereof shall be deemed to beincluded in the allowance for taking the risk of collapse of the sides ofthe excavations, provision for which is made in "Earthworks"

High quality cement-based surface treatment

Surface treatment is to be executed by an approved applicator and aguarantee for the product as well as application thereof to besubmitted to Principal Agent before the issuing of the practicalcompletion certificate

UNREINFORCED CONCRETE CAST AGAINSTEXCAVATED SURFACES

15MPa Soilcrete of in-situ material in 150mm layers compactedto 100% Mod Aashto density

1 Under strip footings, bases, etc m3 9

25MPa/19mm concrete

2 Surface blinding under footings and bases m3 1

REINFORCED CONCRETE

30MPa/19mm Concrete

3 Strip footings m3 9

4 Surface beds on waterproofing m3 11

5 Beams m3 3

6 Columns m3 0.3

Carried Forward N $ Bill No. 3Concrete, formwork & reinforcementRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 2 5 -

Page 26: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

TEST CUBES

7 Making and testing 150 x 150 x 150mm concrete strength test cubes(Provisional) No 6

CONCRETE SUNDRIES

Finishing top surfaces of concrete smooth with a steel trowel

8 Floors, etc m2 73

ROUGH FORMWORK (DEGREE OF ACCURACY II)

Rough formwork to soffits

9 Vanity slabs, cupboard slabs, cover slabs, etc propped up notexceeding 1,5m high m2 3

SMOOTH FORMWORK (DEGREE OF ACCURACY I)

Smooth formwork to sides

10 Rectangular columns m2 5

11 Wall beams m2 25

12 Edges, risers, ends and reveals not exceeding 300mm high or wide m 36

Smooth formwork to soffits

13 Wall beams over openings m2 1

Boxing in smooth formwork to form

14 10 x 10mm Chamfer along top or bottom edge m 8

MOVEMENT JOINTS, ETC

Two layers of "DPC" in slip joints between horizontal concreteand brick surfaces, including cement mortar bed

15 Not exceeding 300mm wide m 33

Carried Forward N $ Bill No. 3Concrete, formwork & reinforcementRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 2 6 -

Page 27: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

Saw cut joints

16 3 x 40mm Saw cut joints in top of concrete with the top 20mmincreased to 6mm wide m 24

REINFORCEMENT (PROVISIONAL)

Steel reinforcement to structural concrete work

17 Bars t 0.28

Fabric reinforcement

18 Type 245 fabric reinforcement in floors, ramps, aprons, etc m2 150

Carried to Summary N $ Bill No. 3Concrete, formwork & reinforcementRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 2 7 -

Page 28: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Item Quantity Rate AmountNo

BILL NO 4

PRECAST CONCRETE

SUPPLEMENTARY PREAMBLES

Sizes:

Blocks, sills, etc measured linear shall be made in suitable lengths.Large size setting out drawings shall be prepared where necessary andsubmitted to the architect for approval before moulds are made

General:

Where kerbstones, blocks, etc are laid in ground descriptions shall bedeemed to include necessary excavation, filling in and ramming

PRECAST CONCRETE

Precast concrete block and clay brick road surfacing

Paving is to be laid in accordance with SABS 1200 MJ, SABS 1058and the Concrete Masonry Association's specifications

Paving is to be laid on 25mm (thickness after final compaction) cleanriver sand (preparation of ground or filling elsewhere)

Clean sand is to be swept into joints between paving blocks

Pre-cast paving and kerbs removed elsewhere

1 Relay paving to parking areas, roadways, etc including joining withexisting m2 50

2 Re-lay kerb on new 25MPa concrete bedding including jointing andpointing

m 5

35MPa x 60mmThick interlocking paving blocks

3 Paving to parking areas, roadways, etc m2 195

Precast concrete finished smooth on exposed surfaces including25MPa concrete bedding, jointing and pointing

4 Barrier kerb 125 x 250mm high set on concrete surface beds withgrout bedding and infill m 31

Carried Forward N $ Bill No. 4Precast ConcreteRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 2 8 -

Page 29: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

5 Barrier kerb 125 x 250mm high set on 150mm thick unreinforcedconcrete bed m 38

6 Mountable kerb 250 x 150mm high set on 150mm thick unreinforcedconcrete bed m 71

Carried to Summary N $ Bill No. 4Precast ConcreteRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 2 9 -

Page 30: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Item Quantity Rate AmountNo

BILL NO 5

MASONRY

SUPPLEMENTARY PREAMBLES

BRICKWORK

Sizes in descriptions

Where sizes in descriptions are given in brick units, "one brick" shallrepresent the length and "half brick" the width of a brick

Pointing

Descriptions of recessed pointing to fair face brickwork and facebrickwork shall be deemed to include square recessed, hollowrecessed, weathered pointing, etc

Samples

Samples of all masonry building units, shall consist of a minimum of6 units

FOUNDATIONS (PROVISIONAL)

14MPa Brickwork of "Uis" clay bricks in class I mortar

1 One brick walls m2 22

SUPERSTRUCTURE

7MPa Brickwork of "Uis" clay bricks in class II mortar

2 One brick walls m2 169

3 One brick walls in beamfilling m2 6

BRICKWORK SUNDRIES

Fair face to brickwork in horizontal stretcher bond with flushhorizontal and vertical joints

4 Extra for fair face m2 152

5 Extra for fair face in foundations (Provisional) m2 18

Carried Forward N $ Bill No. 5MasonryRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 3 0 -

Page 31: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

Brick-on-edge header course copings, sills, etc of "Uis" claybricks with flush joints on all exposed faces

6 Extra over brickwork for brick-on-edge soldier course lintel m 1

Pre-stressed fabricated lintels

7 110 x 75mm Lintels in lengths not exceeding 3m m 1

Brickwork reinforcement

8 150mm Wide reinforcement built in horizontally in foundations(Provisional) m 260

9 150mm Wide reinforcement built in horizontally m 499

Turning pieces

10 220mm Wide turning piece to lintels, etc m 1

Carried to Summary N $ Bill No. 5MasonryRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 3 1 -

Page 32: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Item Quantity Rate AmountNo

BILL NO 6

WATERPROOFING

SUPPLEMENTARY PREAMBLES

Waterproofing

Waterproofing are to be executed by an approved applicator and a tenyear guarantee for the product as well as application thereof to besubmitted to principal agent before the issuing of the practicalcompletion certificate.

Waterproofing to roofs are to be applied strictly according to themanufacturers specification and shall be laid to even falls to outlets,etc with necessary ridges, hips and valleys. Descriptions of sheet ormembrane waterproofing shall be deemed to include additional labourto turn-ups and turn-downs

DAMPPROOFING OF WALLS AND FLOORS

One layer of 375 micron "Consol Plastics Brikgrip DPC"embossed damp proof course

1 In walls m2 8

One layer of 375micron "Consol Plastics Gunplas USB Orange"waterproof sheeting sealed at laps with "Gunplas PressureSensitive Tape"

2 Under surface beds, ramps, etc m2 75

3 Under pavers, etc m2 19

JOINT SEALANTS, ETC

"Fosroc Thioflex 600" two-part polysulphide sealing compoundincluding backing cord, bond breaker, primer, etc

4 6 x 10mm In saw cut joints in floors m 24

Carried to Summary N $ Bill No. 6WaterproofingRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 3 2 -

Page 33: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Item Quantity Rate AmountNo

BILL NO 7

ROOF COVERINGS, ETC

SUPPLEMENTARY PREAMBLES

Straight cutting

Descriptions of all roof coverings are deemed to include for allstraight cutting

PROFILED METAL SHEETING AND ACCESSORIES

0,5mm "Klip-Lock 700" galvanized troughed sheet steel in singlelengths fixed to steel purlins or rails and 0,5mm galvanized sheetsteel accessories

1 Roof coverings with pitches not exceeding 25 degrees m2 104

ROOF AND WALL INSULATION

"Sisalation FR430" heavy duty industrial grade aluminium foilbonded insulation

2 Insulation laid taut over purlins (at approximately 1250mm centres)and fixed concurrent with roof covering, including galvanised steelstraining wires m2 80

Carried to Summary N $ Bill No. 7Roof coveringRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 3 3 -

Page 34: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Item Quantity Rate AmountNo

BILL NO 8

CARPENTRY AND JOINERY

SUPPLEMENTARY PREAMBLES

Joinery

Descriptions of frames shall be deemed to include frames, transomes,mullions, rails, etc

Descriptions of hardwood joinery shall be deemed to include pelletingof bolt holes

Fixing

Items described as "nailed" shall be deemed to be fixed with hardenedsteel nails or shot pins to brickwork or concrete

Decorative laminate finish

Laminate finish shall be glued under pressure. Edge strips shall bebutt jointed at junctions with adjacent similar finish

DOORS, ETC

44mm Wrought meranti framed, ledged and braced batten doorsof 44 x 107mm top rail, middle ledge and stiles, 16 x 107mmbraces and 22 x 219mm bottom ledge

1 Door 813 x 2032mm high filled in with 22mm V-jointed boarding toone side and other side covered with 6mm plywood with veneer tomatch door with and including 44 x 50mm rebated, splayed andgrooved weather board set into groove in door No 1

JOINERY SUNDRIES

Wrought prosopis

2 169 x 800 x 32mm Thick fire extinguisher backing board withrounded edges and corners, plugged No 1

Carried to Summary N $ Bill No. 8Carpentry & joineryRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 3 4 -

Page 35: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Item Quantity Rate AmountNo

BILL NO 9

IRONMONGERY

SUPPLEMENTARY PREAMBLES

Finishes to ironmongery

Where applicable finishes to ironmongery are indicated by suffixes inaccordance with the following list: BS Satin bronze lacquered CH Chromium plated SC Satin chromium plated SE Silver enamelled GE Grey enamelled AS Anodized silver AB Anodized bronze AG Anodized gold ABL Anodized black PB Polished brass PL Polished and lacquered PT Epoxy coated SD Sanded

LOCKS

"Union"

1 50mm UN335000000010 PB Padlock No 1

2 "Teal" code CB6T45-05SC/L-22315-76/2X810 euro profile doublecylinder lockset No 1

SUNDRIES

"Union"

3 "87001SS" Door stop No 1

"Chubb"

4 4,5kg Dry chemical powder fire extinguisher No 1

Carried to Summary N $ Bill No. 9IronmongeryRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 3 5 -

Page 36: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Item Quantity Rate AmountNo

BILL NO 10

STRUCTURAL STEELWORK

SUPPLEMENTARY PREAMBLES

Descriptions

Descriptions of bolts shall be deemed to include nuts and washers

Descriptions of L-shaped and U-shaped anchor bolts shall be deemedto include bending, threading, nuts and washers and embedding inconcrete

Descriptions of expansion anchors and bolts and chemical anchorsand bolts shall be deemed to include nuts, washers and mortices inbrickwork or concrete

STEEL COLUMNS, BEAMS AND RAFTERS

Welded beams and rafters in single lengths with angle sectioncleats and flat section bearer and connection plates, bolted toconcrete or brickwork

1 IPE160 x 16kg/m I-section rafters t 0.67

Bolts to columns, beams, etc

2 220 x 220 x 6mm Base plate with and including two lugs 1200mmgirth, cast into top of concrete columns No 10

Architectural features to rafter ends

3 Splayed cutting to IPE160-sections m 4

PURLINS, GIRTS, BRACING, ETC

Purlins and girts bolted to steel

4 Lipped channel section purlins t 0.28

Purlins and girts welded to steel

5 Lipped channel section purlins t 0.05

Carried to Summary N $ Bill No. 10Structural steelworkRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 3 6 -

Page 37: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Item Quantity Rate AmountNo

BILL NO 11

METALWORK

STEEL WELDED SCREENS, GATES, ETC

Gates

1 40 x 40 x 4mm Angle section frame with stiles and lintol for 813 x2032mm gate, welded into mild steel door frame and fitted with 30 x30 x 5mm padlock lug (door frame and hinges elsewhere) No 1

2 Single gate 813 x 2032mm high overall, formed of 20 x 30 x 4mmhollow section frame around and two horizontal middle rails, top andbottom panes filled in with 10 x 10mm solid vertical bars at 90mmcenters and fitted with two 100mm weld-on hinges, barrol bolt, 55 x50 x 5mm padlock lug with slotted hole and 20 x 5mm flat sectionstricker plate, 2032mm high, welded to stile No 1

SUNDRY STEELWORK

Corner protectors

3 70 x 70 x 6mm Angle section corner protectors in varying lengthswith 20 x 5mm lugs, 70mm long at 300mm centres cast into floor m 57

Ventilation grids

4 "Flatex 344/VEM 6320C" expanded metal mesh welded to sub-frame m2 0.5

5 10 x 10mm Square solid section sub-frame welded into metal frames kg 4

6 Extra over 10 x 10mm square solid section frame for mitredL-intersection No 16

7 20 x 30 x 4mm Rectangular hollow section frames m 5

8 Extra over 20 x 30mm hollow section frame for mitred L-intersection No 8

9 Extra over 20 x 30mm hollow section frame for T-intersection No 4

10 50 x 50 x 5mm Flat section anchor plate, once holed and welded on No 8

11 8mm Anchor bolt to concrete or brickwork No 8

PRESSED STEEL DOOR FRAMES

Carried Forward N $ Bill No. 11MetalworkRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 3 7 -

Page 38: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

1,6mm Double rebated frames suitable for one brick walls

12 Frame for door 813 x 2032mm high No 1

STEEL ROLLER SHUTTERS, ETC

"Serranda" 1,0mm thick galvanized slatted metal roller shutterswith "Chromadeck" finish fixed to brickwork or concrete

13 Chain operated slatted roller shutter for 4000 x 4500mm high openingcomplete with locking bars, lock, handles, etc No 1

FENCING, ETC

Galvanized security fencing, gates, etc including two coatsaluminium paint on metal stays, framing, etc

14 Security fencing 2,1m high formed of 2,7m x 50mm diameter x2,5mm thick pipe standards with cap and sole plate in and including300 x 300 x 650mm deep 20MPa concrete bases at maximum 4,0mcentres, four 2,5 x 4,0mm oval high strain galvanised straining wiresand three galvanised razor wires tied to standards, posts and eye bolts,etc with 1,8m height covered with 2,5 x 50mm galvanised steel razorwire mesh fixed at 450mm centres to each straining wire and 150 x250mm deep 20MPa concrete ground beam including excavations,risk of collapse, etc m 127

15 50mm Diameter x 2,5mm thick galvanised horizontal stay 1900mmlong with each end flattened, holed and bolted to posts No 10

16 50mm Diameter x 2,5mm thick galvanised inclined stay 2950mm longwith one end flattened, holed and bolted to post and other end withsole plate in and including 600 x 300 x 500mm 20MPa concrete base No 12

17 100mm Diameter x 2,5mm thick corner or straining post 2700mmhigh with cap and sole plate in and including 400 x 400 x 800mm20MPa concrete base No 7

Carried Forward N $ Bill No. 11MetalworkRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 3 8 -

Page 39: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

18 Double gate 5,2 x 2,1m high overall, each leaf of 50mm diameter x2,5mm thick frame with two 30 x 5mm mild steel flat diagonal braces,both stiles extended at top to form top panel to suit the securityfencing and the bottom 1,8m high covered with 2,5 x 50mmgalvanised steel razor wire mesh fixed to framing and cross brace andtop section provided with three galvanised razor wires tied to stiles,including two square 100 x 100mm round bar handguards, heavy dutyhinges, chain, 50mm "Union" padlock and two 10mm diameter450mm long barrel bolts with two 100mm long keeps in and including300 x 300 x 300mm 20MPa concrete anchor blocks No 1

Carried to Summary N $ Bill No. 11MetalworkRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 3 9 -

Page 40: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Item Quantity Rate AmountNo

BILL NO 12

PLASTERING

SUPPLEMENTARY PREAMBLES

GRANOLITHIC

Method

The method to be used shall be either the monolithic or bondedmethod

Preparation

For granolithic applied monolithically, the concrete floor shall beswept clean after bleeding of the concrete has ceased and the slab hasbegun to stiffen; any remaining bleed water shall be removed and thegranolithic shall then be applied immediately afterwards. Forgranolithic to be bonded to the floor slab after it has hardened, theslab surface shall be hacked (preferably by mechanical means) untilall laitance, dirt, oil, etc is dislodged and swept clean of all loosematter. The slab shall then be wetted and kept damp for at least sixhours before applying the finish

Mix

Granolithic shall attain a compressive strength of at least 41MPa. Thecoarse aggregate shall comply with SABS 1083 and be capable ofpassing a 10mm mesh sieve. Where the thickness of the granolithicexceeds 25mm, the size of the coarse aggregate shall be increased tothe maximum size compatible with the thickness of the granolithic

Laying

Monolithic granolithic shall be applied to the partially set slab andthoroughly compacted and lightly wood floated to the required levels

Bonded granolithic shall be applied to the slab after applying a 1:1sand and cement slurry brushed over the surface and allowed topartially set before applying the granolithic, thoroughly compactedand lightly wood floated to the required levels

After wood floating, the monolithic and bonded granolithic shallremain undisturbed until bleeding has ceased and the surface hasstiffened, any remaining bleed water and laitance shall then beremoved and the surface steel trowelled or power floated

Carried Forward N $ Bill No. 12PlasteringRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 4 0 -

Page 41: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

Curing, seasoning and protection

Granolithic shall be covered with clean hessian with waterproofbuilding foil over and kept wet for at least seven days after laying

Colour

Coloured granolithic shall be tinted with an approved colouringpigment mixed into a true and even colour

GRANOLITHIC

Untinted granolithic on concrete

1 35mm Thick on treads and risers of stairs including reedings m2 0.2

INTERNAL PLASTER

Cement plaster on brickwork

2 On walls m2 184

3 On narrow widths m2 0.4

EXTERNAL PLASTER

Cement plaster on brickwork

4 On walls m2 30

5 On narrow widths m2 0.4

Carried to Summary N $ Bill No. 12PlasteringRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 4 1 -

Page 42: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Item Quantity Rate AmountNo

BILL NO 13

PAINTWORK

SUPPLEMENTARY PREAMBLES

DESCRIPTIONS

Descriptions of paintwork shall be deemed to include for all cutting in

ISO Pine polystyrene insulated roof liner

Visible dents, defects , etc to be filled with "ISO Pine" adhesive andpolyfiller mix and sand down smoothly before application of paint

PAINTWORK, ETC TO NEW WORK ON

FLOATED PLASTER SURFACES WITH

One coat "Pera Aquaprime (CE-1)" primer, stopped with"Polycell Mendall 90" and two coats "Pera-Acrylon EAG"acrylic paint on

1 Internal walls m2 184

2 External walls m2 30

ON CLAY BRICKS

Two coats "Siliseal Waterproofing A101" sealant, using a lowpressure spray, on

3 Walls m2 170

SMOOTH CONCRETE

Scrub down and wash with sugar soap and three coats "Cobra"clear wax polish on

4 Floors, etc m2 72

METAL SURFACES WITH

Carried Forward N $ Bill No. 13PaintworkRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 4 2 -

Page 43: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Brought Forward N $

Clean with "Pera-XC" metal cleaner, spot priming defects inpre-primed surfaces with zinc chromate metal primer, one coat"Pera ANTIRUST CWP-1" undercoat and two coats"Pera-Acrylon EAG" acrylic paint on

5 Door frames m2 2

6 Members of roof trusses and structural steel m2 119

7 Gates, grilles, balustrades, etc (both sides measured on flat) m2 6

8 Rails, bars, pipes, etc not exceeding 300mm girth m 8

WOOD SURFACES WITH

Two coats "AECI Paints (Pty) Ltd Woodguard Timbasheen"sealant on

9 Doors m2 4

Carried to Summary N $ Bill No. 13PaintworkRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 4 3 -

Page 44: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

Item Quantity Rate AmountNo

BILL NO 14

PROVISIONAL AMOUNTS

SPECIALIST WORK

Electrical installation

1 Allow the amount of N$35 000.00 (thirty five thousand Namibiadollars) for the electrical installation Item 35 000 00

2 Add for profit on above if required Item

3 Allow for attendance Item

Electrical connection fee

4 Allow the amount of N$50 000.00 (fifty thousand Namibia dollars)for electrical connection fee Item 50 000 00

5 Add for profit on above if required Item

6 Allow for attendance Item

CONTINGENCIES

Construction contingencies

7 Allow the amount of N$ 35 000,00 (thirty five thousand Namibiadollars) for contingencies to be used as directed by the engineer anddeducted in whole or in part if not required Item 35 000 00

Carried to Summary N $ Bill No. 14Provisional amountsRSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia

- 4 4 -

Page 45: BILL NO 1 PRELIMINARIES - MCA Namibia Oshakati RSRC Garages.pdf · BILL NO 1 PRELIMINARIES NOTES: The Conditions of Contract for Construction for Building and Engineering Works Designed

BW0621-G

FINAL SUMMARY

Bill Page AmountNo No

1 -20-Preliminaries

2 -23-Earthworks

3 -27-Concrete, formwork & reinforcement

4 -29-Precast Concrete

5 -31-Masonry

6 -32-Waterproofing

7 -33-Roof covering

8 -34-Carpentry & joinery

9 -35-Ironmongery

10 -36-Structural steelwork

11 -39-Metalwork

12 -41-Plastering

13 -43-Paintwork

14 -44-Provisional amounts

Net Amount N $

Add: Value Added Tax at 15% N $

Carried to Form of Tender N $ RSRC - GARAGE FOR MOBILE UNITMillennium Challenge Account Namibia