Amount Item No Quantity Rate Unit AT GLEBELANDS, UMLAZI 96 NEW COMMUNITY RESIDENTIAL UNITS 1H-48138 SECTION NO. 1 BILL NO. 1 PRELIMINARIES The JBCC Principal Building Agreement (Edition 6.2 - May 2018) prepared by the Joint Building Contracts Committee shall be the applicable building agreement, amended as hereinafter described BUILDING AGREEMENT AND PRELIMINARIES The JBCC Principal Building Agreement contract data form an integral part of this agreement The JBCC General Preliminaries (May 2018) published by the Joint Building Contracts Committee for use with the JBCC Principal Building Agreement (Edition 6.2 - May 2018) shall be deemed to be incorporated in these bills of quantities, amended as hereinafter described The contractor is deemed to have referred to the above mentioned documents for the full intent and meaning of each clause The clauses in the above mentioned documents are hereinafter referred to by clause number and heading only Where any item is not relevant to this agreement such item is marked N/A signifying "not applicable" Where standard clauses or alternatives are not entirely applicable to this agreement such amendments, modifications, corrections or supplements as will apply are given under each relevant clause heading and such amendments, modifications, corrections or supplements shall take precedence notwithstanding anything to the contrary contained in the above mentioned documents -72- PRELIMINARIES Bill No. 1 SECTION 1: PRELIMINARIES Section No. 1 Carried Forward R

Upload: others

Post on 18-Dec-2021

14 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity RateUnit

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 1

BILL NO. 1

PRELIMINARIES

The JBCC Principal Building Agreement (Edition 6.2 - May 2018) prepared by the Joint Building Contracts Committee shall be the applicable building agreement, amended as hereinafter described

BUILDING AGREEMENT AND PRELIMINARIES

The JBCC Principal Building Agreement contract data form an integral part of this agreement

The JBCC General Preliminaries (May 2018) published by the Joint Building Contracts Committee for use with the JBCC Principal Building Agreement (Edition 6.2 - May 2018) shall be deemed to be incorporated in these bills of quantities, amended as hereinafter described

The contractor is deemed to have referred to the above mentioned documents for the full intent and meaning of each clause

The clauses in the above mentioned documents are hereinafter referred to by clause number and heading only

Where any item is not relevant to this agreement such item is marked N/A signifying "not applicable"

Where standard clauses or alternatives are not entirely applicable to this agreement such amendments, modifications, corrections or supplements as will apply are given under each relevant clause heading and such amendments, modifications, corrections or supplements shall take precedence notwithstanding anything to the contrary contained in the above mentioned documents

-72-

PRELIMINARIESBill No. 1SECTION 1: PRELIMINARIESSection No. 1

Carried Forward R

Page 2: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

The General Preambles for Trades 2017 published by the Association of South African Quantity Surveyors shall be deemed to be incorporated in these bills of quantities and no claims arising from brevity of description of items fully described in the said General Preambles will be entertained

PREAMBLES FOR TRADES

Supplementary preambles and/or specifications are incorporated in these bills of quantities to satisfy the requirements of this project. Such supplementary preambles and/or specifications shall take precedence over the provisions of the General Preambles

The contractor's prices for all items throughout these bills of quantities shall take account of and include where applicable for all of the obligations, requirements and specifications given in the General Preambles and in any supplementary preambles and/or specifications

Section A: A recital of the headings of the individual clauses in the aforementioned JBCC Principal Building Agreement

STRUCTURE OF THIS PRELIMINARIES BILL

Section B: A recital of the headings of the individual clauses in the aforementioned JBCC General Preliminaries

Section C: Any special clauses to meet the particular circumstances of the project

Should the contractor select Option A in the contract data for the adjustment of preliminaries, the amounts entered against the relevant items in these preliminaries are to be divided into one or more of the three categories provided namely fixed (F), value related (V) and time related (T)

PRICING OF PRELIMINARIES

SECTION A: PRINCIPAL BUILDING AGREEMENT

-73-

PRELIMINARIESBill No. 1SECTION 1: PRELIMINARIESSection No. 1

Carried Forward R

Page 3: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Clause 1.0 - Definitions and interpretation

Pricing of bills of quantities

1

Interpretation (A1-A7)

The contractor is to allow opposite each item for all costs in connection therewith. All prices to include, unless otherwise stated, for all materials, fabrication, conveyance and delivery, unloading, storing, unpacking, hoisting, labour, setting, fitting and fixing in position, cutting and waste (except where to be measured in accordance with the standard system of measurement), patterns, models and templates, plant, temporary works, returning of packaging, duties, taxes (other than Value Added Tax), imposts, establishment charges, overheads, profit and all other obligations arising out of this agreement. Value Added Tax (VAT) is to be separately stated on the summary page of these bills of quantities

Items left unpriced will be deemed to be covered in prices against other items throughout these bills of quantities and no claim for any extras arising out of the contractor's omission to price any item will be entertained

2

Prices for all construction equipment, temporary works, services and other items shall include for the supply, maintenance, operating cost and subsequent removal and making good as necessary

3

Abbreviated descriptions

The items in these bills of quantities utilise abbreviated descriptions. It is the intention that the abbreviated descriptions be fully described when read with the applicable measuring system and the relevant preambles and/or specifications. However, should the full intent and meaning of any description not be clear, the contractor shall, before submission of his tender, call for a written directive from the Principal Agent, failing which it shall be assumed that the contractor has allowed in his pricing for materials and workmanship in terms of international best practice

4

-74-

PRELIMINARIESBill No. 1SECTION 1: PRELIMINARIESSection No. 1

Carried Forward R

Page 4: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Legal status of contractor

If the contractor constitutes a joint venture, consortium or other unincorporated grouping of two or more personsthen:

1. These persons are deemed to be jointly and severally liable to the employer for the performance of this agreement

2. These persons shall notify the employer of their leader who has assigned authority to bind the contractor and each of these persons

3. The contractor shall not alter its composition or legal status without the prior written consent of the employer

ItemF:........................ V:.........................T:.........................

Clause 2.0 - Law, regulations and notices5

ItemF:........................ V:.........................T:.........................

Clause 3.0 - Offer and acceptance6

ItemF:........................ V:.........................T:.........................

Clause 4.0 - Cession and assignment7

ItemF:........................ V:.........................T:.........................

Clause 5.0 - Documents8

ItemF:........................ V:.........................T:.........................

Clause 6.0 - Employer's agents9

ItemF:........................ V:.........................T:.........................

Clause 7.0 - Design responsibility10

ItemF:........................ V:.........................T:.........................

Clause 8.0 - Works risk11

Insurances and securities (A8-A11)

-75-

PRELIMINARIESBill No. 1SECTION 1: PRELIMINARIESSection No. 1

Carried Forward R

Page 5: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

ItemF:........................ V:.........................T:.........................

Clause 9.0 - Indemnities12

ItemF:........................ V:.........................T:.........................

Clause 10.0 - Insurances13

ItemF:........................ V:.........................T:.........................

Clause 11.0 - Securities14

Guarantee for payment

The Employer shall not provide to the contractor with a guarantee for payment

By virtue of the contractor submitting a tender offer, he is deemed to have waived his lien or right of continuing possession of the works [11.10]

Sub-clause 11.10 has been amended to read as follows:

"The contractor shall waive his lien or right of continuing possession of the works."

Clause 11.0 has been amended to include the following new sub-clauses:

Sub-clause 11.11

The guarantee provided by the contractor's Guarantor shall have an expiry date (if stated) no less than 3 months after the practical completion date and shall be extended accordingly should the practical completion date be extended. The cost for same shall be included on the contractor’s tender price as no claims for additional cost shall be entertained

Sub-clause 11.12

The contractor is required to provide the Employer with a variable construction guarantee with twenty-one (21) calendar days of acceptance of the contractors’ tender

-76-

PRELIMINARIESBill No. 1SECTION 1: PRELIMINARIESSection No. 1

Carried Forward R

Page 6: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Sub-clause 11.13

Extension of waiver of lien

The contractor shall ensure that a waiver of lien is included in all subcontracts and that the works executed on the site are kept free of all liens and other encumbrances at all times

ItemF:........................ V:.........................T:.........................

Clause 12.0 - Obligations of the parties15

Execution (A12 - A17)

Sub-clause 12.2.6 has been amended to include the following:

The programme for the works must be prepared and issued in Microsoft Project Programming Software

The contractor shall include a float of 15 working days within the contract period for project delays such as, but not limited to adverse weather conditions, etc., in the programme. Such provisions shall initially be included at the end of the contract period or proportionally allocate at the end of each section for contracts with sectional completion, and shall be monitored by the contractor and agreed with the Principal Agent as and when such delays takes place and shall be recorded in the programme based on actual stoppages when incurred. Revision of the date for Practical Completion shall only be considered once the 15 working days has been fully utilised

Sub-clause 12.2.10 has been amended to include the following:

The contractor shall be required to maintain, in addition to the approved programme, a comprehensive fortnightly bar-chart programme expanded to reflect anticipated daily activities for the ensuing fourteen (14) days

-77-

PRELIMINARIESBill No. 1SECTION 1: PRELIMINARIESSection No. 1

Carried Forward R

Page 7: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Sub-clause 12.2.18 has been amended to include the following:

Office accommodation

The contractor shall provide, maintain and remove on practical completion air conditioned office accommodation with suitable tables and chairs for meetings to be held on the site. Such offices shall be kept clean and fit for use at all times [12.2.18]

The contractor’s site camp shall be equipped with Wi-Fi internet connection which shall be utilised by the contractor’s staff, the client and members of professional team

Notice board

The contractor shall erect in a position approved by the principal agent, maintain and remove on practical completion a notice board recommended by the South African Institute of Architects and as approved by the Principal Agent listing the names and logos of the Employer, the contractor and the professional consultants. No subcontractor or supplier notice boards may be erected unless permission is granted by the principal agent for such notice boards to be erected [12.2.18]

ItemF:........................ V:.........................T:.........................

Clause 13.0 - Setting out16

ItemF:........................ V:.........................T:.........................

Clause 14.0 - Nominated subcontractors17

ItemF:........................ V:.........................T:.........................

Clause 15.0 - Selected subcontractors18

ItemF:........................ V:.........................T:.........................

Clause 16.0 - Direct contractors

Attendance on direct contractors

In respect of direct contractors the contractor shall:

19

-78-

PRELIMINARIESBill No. 1SECTION 1: PRELIMINARIESSection No. 1

Carried Forward R

Page 8: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

1. Designate an area for the direct contractor to

establish a temporary office and workshop and storage of equipment and materials

2. Allow the use of personnel welfare facilities, where

provided

3. Provide water, lighting and single phase electric

power to a position within 50m of the place where the direct contract work is to be carried out, other than fuel or power for commissioning of any installation

4. Permit the direct contractor to use erected

scaffolding, hoisting facilities, etc provided by the contractor, in common with others having the like right, while it remains erected on the site [16.1]

ItemF:........................ V:.........................T:.........................

Clause 17.0 - Contract instructions20

ItemF:........................ V:.........................T:.........................

Clause 18.0 - Interim completion21

Completion (A18 - A24)

ItemF:........................ V:.........................T:.........................

Clause 19.0 - Practical completion22

Practical Completion

In respect of practical completion:

1. The following certificates of compliance, as applicable shall be required (excluding others that may be required by the local/national authority, etc.) from the contractor to achieve practical completion

1.1 Certificates from the contractor that all aspects of the Construction Regulations of 2014 have been complied with

1.2 Certificates from the contractor that the National Building Regulations have been complied with

-79-

PRELIMINARIESBill No. 1SECTION 1: PRELIMINARIESSection No. 1

Carried Forward R

Page 9: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

1.3 Certificates of compliance with respect to plumbing and drainage installations

1.4 Certificates of compliance with respect to electrical and electronic installations

1.5 Certificates of compliance with respect to all glazing

1.6 Certificates of compliance with respect to structural and civil engineering

1.7 Certificates of compliance with respect to roof installation

1.8 Certificates of compliance with respect to mechanical installation

1.9 Certificate of compliance and fire clearance certificate from the contractor and fire chief respectively

1.10 Any other compliance documentation deemed necessary as instructed by the Principal Agent

1.11 Three complete sets of approved maintenance and operating manuals together with all workmanship and material warranties and guarantees (to be compiled and issued to the Principal Agent prior to achievement of practical completion for approval) and three complete copies of documents in electronic format

2. In order to achieve practical completion of the works and without deviating from the generality of the term practical completion, the contractor shall, as a minimum comply with the following basic criteria, as applicable. These criteria should not be regarded as comprehensive but as an expansion of the term practical completion

2.1 Electrical installation is to be completed and fully commissioned permanent power and lighting inclusive of all telephone and data installations

2.2 Plumbing installation it to be complete, commissioned permanent water supply and drainage tested. Pipe work to be pressured tested

3. Health and Safety file

-80-

PRELIMINARIESBill No. 1SECTION 1: PRELIMINARIESSection No. 1

Carried Forward R

Page 10: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Clause 19.0 has been amended to include the following new sub-clauses:

Sub-clause 19.2.3

The contractor shall within five (5) calender days ofreceipt of the list for practical completion issue aprogram indicating dates for completion for all listed items

Sub-clause 19.2.4

In the event that such inspection does not result in the work being accepted as Practically complete then the costs of such inspection and subsequent inspections shall be for the account of the contractor, at a rate of Ten Thousand Rand (R10 000.00) per man hour or part thereof, calculated by multiplying the total of the number of Employer’s agents and Employer’s staff present at each abortive practical completion inspection meeting, i.e. Where practical completion is not achieved, by the time taken for such an inspection until practical completion is achieved. In this regard, the Employer reserves the right to recover such costs in addition to any other remedies it may have in accordance with Clause 27

ItemF:........................ V:.........................T:.........................

Clause 20.0 - Completion in sections 23

N/AF:........................ V:.........................T:.........................24

Clause 21.0 - Defects liability period and final completion

25

-81-

PRELIMINARIESBill No. 1SECTION 1: PRELIMINARIESSection No. 1

Carried Forward R

Page 11: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Clause 21.0 has been amended to include the following new sub-clauses:

Sub-clause 21.13

In the event that the certificate of Final Completion is not issued due to the contractor’s work not being sufficiently complete then the costs of such inspection and subsequent inspections shall be for the account of the contractor, at a rate of Ten Thousand Rand (R10 000.00) per man hour or part thereof, calculated by multiplying the total of the number of Employer’s agents and Employer’s staff present at each abortive final completion inspection meeting, i.e. Where final completion is not achieved in terms of 21.6, by the time taken for such an inspection until final completion is achieved. In this regard, the Employer reserves the right to recover such costs in accordance with Clause 27

26

Sub-clause 21.14

Notwithstanding [21.2], where the contractor fails to rectify/attend to outstanding works or defects on the list for completion, list for final completion or latent defects that appear before the issue of certificate of final completion and where the contractor remains in default, the Employer may engage others to carry out said outstanding works or defects and recover expense and/or loss incurred [27]

27

ItemF:........................ V:.........................T:.........................

Clause 22.0 - Latent defects liability period28

ItemF:........................ V:.........................T:.........................

Clause 23.0 - Revision of the date for practical completion

Sub-clause 23.1 has been amended to include the following new sub-clause:

Sub-clause 23.1.7

Delayed possession of site [12.1.5]

29

-82-

PRELIMINARIESBill No. 1SECTION 1: PRELIMINARIESSection No. 1

Carried Forward R

Page 12: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Sub-clause 23.2 has been amended to omit the following sub-clause:

Sub-clause 23.2.1 Delayed possession of the site [12.1.5]

Clause 23.0 has been amended to include the following new sub-clauses:

Sub-clause 23.9

Notwithstanding, sub-clause(s) 23.1 to 23.8 a revision to the practical completion date will only be considered for work on the critical path of the contractual programme orthe revised contractual programme, as applicable

Any revised programme, in order to be considered as a contractual programme, must be approved by the Principal Agent in writing, prior to it becoming effective

ItemF:........................ V:.........................T:.........................

Clause 24.0 - Penalty for late or non-completion30

ItemF:........................ V:.........................T:.........................

Clause 25.0 - Payment31

Payment (A25 - A27)

Sub-clause 25.1 has been amended to include the following:

The contractor shall submit the following information on a monthly basis to the Principal Agent and Quantity Surveyor in order to assist with the processing of the payment certificate and the preparation of the empowerment report:

· A detailed breakdown of the work done. (The work breakdown must be referenced strictly in accordance with the Tender Document or the detailed Priced Bills of Quantities, as applicable.)

· A detailed breakdown of all variation order costs claimed (With specific reference to work done by the Principal Building Contractor) in the certificate concerned, together with copies of the relevant contract instructions

32

-83-

PRELIMINARIESBill No. 1SECTION 1: PRELIMINARIESSection No. 1

Carried Forward R

Page 13: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

· A detailed breakdown of the work done by each sub-contractor. (The work breakdown must be referenced strictly in accordance with the Tender Document or the detailed Priced Bills of Quantities, as applicable.)

· A detailed breakdown of all variation order costs claimed in the certificate concerned for sub-contract work, together with copies of the relevant contract instructions

· A written declaration authenticated by the contracts manager confirming, that the payment claims for work done by sub-contractors has been audited and amended by the contractor’s quantity surveyor, prior to it being forwarded to the Principal Agent and Quantity Surveyor for evaluation

· If applicable, a combined empowerment report which shall include reports on contractor and sub-contractor compliance, in accordance with the format required by the empowerment manager. In this regard, the combined, contractor and sub-contractor empowerment report must contain an affidavit certifying that all information contained the report as being true and correct and must be authenticated by the contractor and a commissioner of oaths. The combined reports must also state that the contractor has checked and verified that all information submitted by sub-contractors is true and correct

· Tax invoice: the contractor shall attach a tax invoice as prescribed in the Value Added Tax Legislation to each payment certificate when presenting the certificate to the employer for payment. Such tax invoices shall correctly reflect the prescribed information and the amounts shall match precisely the amounts included in the payment certificate. Should the contractor fail to comply with these requirements, the date of presentation of the certificate shall be deemed to be delayed at the contractor’s default until such time as the requirements are met

Should anyone or any combination of the above requirements not be complied with, the Principal Agent reserves the right to exclude any amounts that may have been due for certification from the payment certificate concerned and/ or delay the issue of payment

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

-84-

PRELIMINARIESBill No. 1SECTION 1: PRELIMINARIESSection No. 1

Carried Forward R

Page 14: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

certificate concerned and/ or delay the issue of payment certificates and/ or, revise the contractual payment date, as applicable, until such time compliance is achieved

Sub-clause 25.4 has been amended to include the following:

Where the Employer agrees to pay for materials on/off site, the contractor shall be required to provide the Principal Agent with the necessary forms for cession of ownership for such materials, with the necessary delivery notes and invoices (where applicable)

33

Sub-clause 25.10 has been amended as follows:

Replace the words “fourteen (14) calendar days” with “forty (40) calendar days”

ItemF:........................ V:.........................T:.........................

Clause 26.0 - Adjustment of the contract value and final account

34

Sub-clause 26.1 has been amended to include the following:

Contract Instructions

Instructions given by the Employer's agents in relation to the contract works, shall, irrespective of the format or wording of such instructions, not indicate that the work involved represents an extra or variation and shall not be deemed to be acceptance of any prices or quotations contained in any correspondence

It is recorded that only the quantity surveyor where appointed by the employer for quantity surveying services is empowered, to rule whether any instructions issued constitutes an extra or not and, to resolve cost aspects of any matter pertaining to this contract

35

ItemF:........................ V:.........................T:.........................

Clause 27.0 - Recovery of expense and/or loss36

ItemF:........................ V:.........................T:.........................

-85-

PRELIMINARIESBill No. 1SECTION 1: PRELIMINARIESSection No. 1

Carried Forward R

Page 15: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Clause 28.0 - Suspension by the contractor 37

Suspension and termination (A28 - A29)

ItemF:........................ V:.........................T:.........................

Clause 29.0 - Termination38

ItemF:........................ V:.........................T:.........................

Clause 30.0 - Dispute resolution39

Dispute resolution (A30)

ItemF:........................ V:.........................T:.........................

Agreement

The required information of the parties and the amount of the contract sum shall be inserted in the agreement for signature of the agreement by the parties

40

ItemF:........................ V:.........................T:.........................

Contract data41

Tenderer's selections

Before submission of his Tender the contractor is to complete the Tenderer's selections in the contract data

ItemF:........................ V:.........................T:.........................

-86-

PRELIMINARIESBill No. 1SECTION 1: PRELIMINARIESSection No. 1

Carried Forward R

Page 16: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION B: GENERAL PRELIMINARIES

Clause 1.1 - Definitions42

Definitions and interpretation (B1)

ItemF:........................ V:.........................T:.........................

Clause 1.2 - Interpretation43

ItemF:........................ V:.........................T:.........................

Clause 2.1 - Checking of documents44

Documents (B2)

Sub-clause 2.1 refers – the following is to be added after the words “written directive”:

The items in these Bills of Quantities are to be read and priced in conjunction with, and the descriptions regarded as amplified by the General Preambles for Trades 2017 as recommended and published by the Association of South African Quantity Surveyors, 2017 edition, and no claim arising from brevity of description of items fully described in the said General Preambles for Trades 2017 and Supplementary documentation will be entertained. Notwithstanding the issue of the tender drawings, it will remain the responsibility of the Tenderer to study all available drawings at the offices of the Principal Agent during normal working hours in order to acquaint himself with all the cost implications of the design, programming, phasing, etc

ItemF:........................ V:.........................T:.........................

Clause 2.2 - Provisional bills of quantities45

ItemF:........................ V:.........................T:.........................

Clause 2.3 - Availability of construction information46

ItemF:........................ V:.........................T:.........................

Clause 2.4 - Ordering of materials and goods47

ItemF:........................ V:.........................T:.........................

-87-

PRELIMINARIESBill No. 1SECTION 1: PRELIMINARIESSection No. 1

Carried Forward R

Page 17: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Clause 3.1 - Previous work - dimensional accuracy48

Previous work and adjoining properties (B3)

ItemF:........................ V:.........................T:.........................

Clause 3.2 - Previous work - defects49

ItemF:........................ V:.........................T:.........................

Clause 3.3 - Inspection of adjoining properties50

ItemF:........................ V:.........................T:.........................

ItemClause 4.1 - Handover of site in stages51

The site (B4)

ItemF:........................ V:.........................T:.........................

Clause 4.2 - Enclosure of the works52

ItemF:........................ V:.........................T:.........................

Clause 4.3 - Geotechnical and other investigations53

ItemF:........................ V:.........................T:.........................

Clause 4.4 - Encroachments54

ItemF:........................ V:.........................T:.........................

Clause 4.5 - Existing premises occupied55

ItemF:........................ V:.........................T:.........................

Clause 4.6 - Services - known

The contractor shall consult the Principal Agent before disconnecting any services. The contractor shall take special care not to damage any existing services that could have been foreseen or what have been shown to him by the Principal Agent. Damage to this services shall be for the contractor’s account

56

ItemF:........................ V:.........................T:.........................

-88-

PRELIMINARIESBill No. 1SECTION 1: PRELIMINARIESSection No. 1

Carried Forward R

Page 18: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Clause 5.1 - Management of the works57

Management of contract (B5)

ItemF:........................ V:.........................T:.........................

Clause 5.2 - Progress meetings58

ItemF:........................ V:.........................T:.........................

Clause 5.3 - Technical meetings59

ItemF:........................ V:.........................T:.........................

Clause 5 has been amended to include the following new sub-clause:

Sub-clause 5.4 - Daily records

The contractor shall keep daily records of people and equipment employed as well as a site diary in respect of work performed on the site

At the end of each week the contractor shall provide the Principal Agent with a written record, in schedule form, reflecting the number and description of tradesmen and labourers employed by him and all sub-contractors on the works each day

At the end of each week the contractor shall provide the Principal Agent with a written record, in schedule form, reflecting the number, type and capacity of all plant, excluding hand tools, currently used on the works

60

ItemF:........................ V:.........................T:.........................

-89-

PRELIMINARIESBill No. 1SECTION 1: PRELIMINARIESSection No. 1

Carried Forward R

Page 19: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Clause 6.1 - Samples of materials

All material samples and colour samples must be submitted to the Principal Agent for selections and approval of the colour, shape and finish including mechanical, electrical and plumbing equipment that will be visible. The samples shall be provided in A4 size unless otherwise agreed. General samples shall be provided for Principal Agent/Employer to choose from each type of finish

The Principal Agent/Employer may reject all or part of the submitted samples and request for additional selections if the first submission are not acceptable

All samples must be kept in a sample room to be provided by the contractor for reference

Sample Board:

The contractor shall provide a board(s) of approved samples and make available one set at the site (sample room) and one for the Employer

61

Samples, shop drawings and manufacturer's instructions (B6)

ItemF:........................ V:.........................T:.........................

Clause 6.2 - Workmanship samples

Sub-clause 6.2 has been amended to include the following:

The contractor shall provide a mock-up of all finished surfaces prior to commencement of the relevant work. The contractor shall only be permitted to commence with the relevant scope of work, on approval of the mock-up by the Principal Agent or its designated representative

62

ItemF:........................ V:.........................T:.........................

Clause 6.3 - Shop drawings63

-90-

PRELIMINARIESBill No. 1SECTION 1: PRELIMINARIESSection No. 1

Carried Forward R

Page 20: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Sub-clause 6.3 refers – the following is to be added after the words 'and/or approval'

Shop drawings shall be submitted to the principal agents for approval at least ten (10) working days weeks prior to the date on which such approval is required in order to comply with the programme

All submissions shall be prepared in accordance with the contract drawings and specifications and/or any Principal Agents instructions and any deviation shall be specifically highlighted in writing, with a detailed explanation of the reason for such deviation, together with any cost and/or time implications. Delays in approval of shop drawings due to non compliance with drawings, specifications and/or Principal Agent’s instruction shall not constitute grounds for any claims for delay, extension of time and the like

The contractor shall be responsible for ensuring that all dimensions affecting shop drawings conform to the dimensions of built work

Should the contractor, sub-contractor, supplier or manufacturer be of the opinion that corrections to shop drawings made by the Principal Agent, constitute a change to the scope of work, then he shall immediately advise the Principal Agent in writing of this, together withthe cost and/or programme implications thereof, in order to obtain the Principal Agent's directive

64

Sub-clause 6.3.1 has been amended as follows:

Replace the words “two (2) copies” with “four (4) copies” under bullet point number 6

65

ItemF:........................ V:.........................T:.........................

Clause 6.4 - Compliance with manufacturer's instructions

66

ItemF:........................ V:.........................T:.........................

Clause 7.1 - Deposits and fees67

Deposits and fees (B7)

ItemF:........................ V:.........................T:.........................

-91-

PRELIMINARIESBill No. 1SECTION 1: PRELIMINARIESSection No. 1

Carried Forward R

Page 21: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Clause 8.1 - Water68

Temporary services (B8)

ItemF:........................ V:.........................T:.........................

Clause 8.2 - Electricity69

ItemF:........................ V:.........................T:.........................

Clause 8.3 - Ablution and welfare facilities70

ItemF:........................ V:.........................T:.........................

Clause 8.4 - Communication facilities71

ItemF:........................ V:.........................T:.........................

Clause 9.1 - Responsibility for prime cost amounts72

Prime cost amounts (B9)

ItemF:........................ V:.........................T:.........................

Clause 10.1 - General attendance73

Attendance on subcontractors (B10)

ItemF:........................ V:.........................T:.........................

Clause 10.2 - Special attendance

Sub-clause 10.2 has been amended to include the following:

The Tenderer shall examine all drawings and information pertaining to the works as a whole and shall provide all necessary special attendance resources required for the due and proper execution and completion of all sub-contract works

74

ItemF:........................ V:.........................T:.........................

Clause 11.1 - Protection of the works75

General (B11)

-92-

PRELIMINARIESBill No. 1SECTION 1: PRELIMINARIESSection No. 1

Carried Forward R

Page 22: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

ItemF:........................ V:.........................T:.........................

Clause 11.2 - Protection/isolation of existing works and works occupied in sections

76

ItemF:........................ V:.........................T:.........................

Clause 11.3 - Security of the works77

ItemF:........................ V:.........................T:.........................

Clause 11.4 - Notice before covering work78

ItemF:........................ V:.........................T:.........................

Clause 11.5 - Disturbance79

ItemF:........................ V:.........................T:.........................

Clause 11.6 - Environmental disturbance80

ItemF:........................ V:.........................T:.........................

Clause 11.7 - Works cleaning and clearing

Disposal of Waste Material, etc.

The contractor shall provide appropriate equipment (such as chutes, if required), etc., for the rapid removal of waste material, etc., at points as agreed with the Principal Agent in writing. In addition, the contractor is to provide for adequate waste skips for the disposal of such material to be located in positions as advised by the Principal Agent in writing

The contractor shall ensue that there is a maximum of a twenty four (24) hour turn-around time for the removal of all full waste skips from site. The contractor further acknowledges that the Employer reserves the right to appoint others to remove waste material and waste skips from site, should the contractor fail to meet the twenty four (24) hour turn-around time and that such costs shall be deducted from amounts due to the contractor

81

ItemF:........................ V:.........................T:.........................

-93-

PRELIMINARIESBill No. 1SECTION 1: PRELIMINARIESSection No. 1

Carried Forward R

Page 23: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Clause 11.8 - Vermin82

ItemF:........................ V:.........................T:.........................

Clause 11.9 - Overhand work83

ItemF:........................ V:.........................T:.........................

Clause 11.10 - Tenant installations84

ItemF:........................ V:.........................T:.........................

Clause 11.11 - Advertising85

ItemF:........................ V:.........................T:.........................

-94-

PRELIMINARIESBill No. 1SECTION 1: PRELIMINARIESSection No. 1

Carried Forward R

Page 24: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Item

Health and Safety

Without limiting the generality of the provisions of clause 2.0, the contractor's attention is drawn to the provisions of the Construction Regulations issued in terms of the Occupational Health and Safety Act, 1993 as amended. It is specifically stated that the employer shall prepare a documented health and safety specification for the works (annexed to these bills of quantities) and that the Employer shall ensure that the contractor has made provision for the cost of health and safety measures during the execution of the works. The contractor shall price opposite this item for compliance with the act and the regulations and the provisions of the aforementioned health and safety specification [2.1]

The contractor shall:

1. Comply with the health and safety specification for the works

2. Prepare and agree with the health and safety consultant the health and safety plan for the works

3. Cooperate with the health and safety consultant in all respects

4. Manage the compliance of all subcontractors with the regulations and with the health and safety plan and specification

5. Conform to the conditions contained in the Employer's health and safety specification

6. The contractor shall price section D of the preliminaries and allow opposite each item for all costs associated in connection with the health and safety specification

F:........................ V:.........................T:.........................

86

SECTION C: SPECIFIC PRELIMINARIES

-95-

PRELIMINARIESBill No. 1SECTION 1: PRELIMINARIESSection No. 1

Carried Forward R

Page 25: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Item

As Built Drawings

The contractor shall accurately record the details of the electrical, mechanical, security, fire installation, water reticulation details, construction breaks, etc., on drawings and issue same to the Principal Agent and the relevant agent for record purposes

F:........................ V:.........................T:.........................

87

Item

Personal Protective Equipment

The contractor shall provide and keep on site an adequate supply of clean safety helmets and reflective vests for the use of all professional personnel and all authorised visitors

F:........................ V:.........................T:.........................

88

Item

Site Access for and Management of Direct Contracts

The contractor shall allow direct contractors appointed by the Employer to access the site to execute work which does not form part of the Principal Building Agreement, concurrently with that of its (the principal building contractor), work. In this regard, the contractor shall provide any necessary assistance (e.g. ensuring placement of material orders, monitoring the manufacturing process, monitoring of raw materials availability, programming of works, etc.), to the principal agent in respect of management of any direct contracts.

In this regard, is shall be deemed that all allowances have been made in the contract amount to ensure compliance with this clause

F:........................ V:.........................T:.........................

89

-96-

PRELIMINARIESBill No. 1SECTION 1: PRELIMINARIESSection No. 1

Carried Forward R

Page 26: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Item

Pre contract Engagement

Contractors shall be engaged prior to issuance of site possession to facilitate all necessary pre contract work which shall include the construction work permit application, procurement of specialist sub-contractors, finalisation of contract and any design coordination between the contractor and the professional team. Contractors will be required to make the necessary allowances for such work during this period as no claims for additional preliminaries will be entertained

Contractor to allow for a period of 30 (thirty) working days for the above

F:........................ V:.........................T:.........................

90

300 000.00ItemProvide the sum of R 300 000.00 (Three Hundred Thousand Rand) for the Community Liaison Officer

91

Community Liaison Officer

ItemProfit92

ItemAttendance93

Item

Tender Data Schedule

F:........................ V:.........................T:.........................

94

Contract Provisions

Item

General Conditions of Contract

F:........................ V:.........................T:.........................

95

Item

Special Conditions of Contract

F:........................ V:.........................T:.........................

96

Item

Contract Data

F:........................ V:.........................T:.........................

97

-97-

PRELIMINARIESBill No. 1SECTION 1: PRELIMINARIESSection No. 1

Carried Forward R

Page 27: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Category : Fixed R........................................

Category : Value R........................................

Category : Time R........................................

SUMMARY OF CATEGORIES

-98-

PRELIMINARIESBill No. 1SECTION 1: PRELIMINARIESSection No. 1

Carried to Final Summary R

Page 28: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity Rate

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 2

BILL NO. 1

The Tenderer is referred to the relevant Clauses in the separate document General Preambles for Trades (2017 Edition)

EARTHWORKS (PROVISIONAL)

SUPPLEMENTARY PREAMBLES

A soils investigation has been carried out on the site by the engineer and the report is annexed to these bills of quantities. The soils report indicates that the ground varies between clayey, silty, and gravelly sand all of which will be deemed as "earth". Highly weathered, very "soft rock" was found at depth of 1300mm with possible interspersed moderately weathered medium "hard rock"

Nature of ground

No subterranean water is expected

Subterranean water

Descriptions of carting away of excavated material shall be deemed to include loading excavated material onto trucks directly from the excavations or, alternatively, from stock piles situated on the building site

Carting away of excavated material

References such as "G1", "G2", etc and "C1", "C2", etcin descriptions of filling and layer work materials refer tocorresponding references in the document "Guidelinesfor Road Construction Materials. TRH 14 : 1985"compiled by the Committee of State Road Authoritiesand the properties set out therein for each kind shall beapplicable to the respective materials describedhereinafter

Filling

-99-

EARTHWORKS (PROVISIONAL)Bill No. 1SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 29: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Prices for filling are to include for all necessary densityand other tests

Testing

EXCAVATION, FILLING, ETC OTHER THAN BULK

EXCAVATIONS, ETC

252m3To reduce levels under floors etc1

Excavation in earth not exceeding 2m deep

216m3Trenches2

252m3Holes including working around piles3

552m3Surplus material from excavations and/or stock piles on site, to a dumping site to be located by the contractor

4

Extra over all excavations for carting away

2 296m2Sides of bulk excavations not exceeding 1,5m deep5

Risk of collapse of excavations

ItemKeeping excavations free of all water other thansubterranean water

6

Keeping excavations free of water

FILLING, ETC

168m3Backfilling to trenches, holes, etc7

Earth filling obtained from the excavations and/or prescribed stock piles on site, compacted to 95% Mod AASHTO density

228m3Under floors, steps, pavings, etc8

Filling of G7 material supplied by the contractor, compacted to 98% Mod AASHTO density

-100-

EARTHWORKS (PROVISIONAL)Bill No. 1SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 30: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

1 488m2

Compaction of ground surface under floors etc including scarifying for a depth of 200mm, breaking down oversize material, adding suitable material where necessary and compacting to 95% Mod AASHTO density

9

Compaction of surfaces

WEED KILLERS, INSECTICIDES, ETC

1 488m2

Under floors etc including forming and poisoning shallow furrows against foundation walls etc, filling in furrows and ramming

10

Soil insecticide in accordance with SANS 5859

84m2To bottoms and sides of trenches etc11

TESTS

33No"Modified AASHTO Density" test12

Prescribed density tests on filling

-101-

EARTHWORKS (PROVISIONAL)Bill No. 1SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward to Summary of Section No. 2 R

Page 31: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity Rate

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 2

BILL NO. 2

The Tenderer is referred to the relevant Clauses in the separate document General Preambles for Trades (2017 Edition)

PILING (PROVISIONAL)

SUPPLEMENTARY PREAMBLES

The contractor shall take full responsibility for piling work and shall guarantee that piling work will support the calculated loads laid down by the engineer without injurious settlement. The actual lengths of piles shall be determined on site by the contractor in consultation with the engineer who will give all assistance possible. This does not in any way relieve the contractor of his responsibility or obligation to provide the specified guarantee.

Indemnity:

The contractor shall indemnify the employer against any injury to or death of any person and all loss or damage to all structures resulting from the failure of any pile. In the event of the failure of any pile the contractor shall make good such pile and all consequent damage at his own expense.

The contractor shall insure by means of a policy, approved by the principal agent, against risks arising out of the responsibilities, guarantee and indemnities specified. The contractor shall pay all premiums in respect of this insurance policy. The guarantee shall be for the amount and effective period as stated hereafter in this bill

-102-

PILING (PROVISIONAL)Bill No. 2SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 32: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

The responsibility for the design and performance of all piles shall lie with the Piling Contractor and the Piling Contractor shall supply a 'Piling Guarantee' or a 'Piling Liability Insurance Policy' in this regard. The 'Piling Guarantee' or a 'Piling Liability Insurance Policy' is to be in place for a minimum period of 3 years after the final pile has been installed. The Piling Contractor's Pile Design Engineer must submit a 'Certificate of Stability' to the Principal Structural Engineer on completion of the piling contract

The 'Piling Liability Insurance Policy' should have insurance cover for the following sections :

1.Public Liability Cover2.General Construction Liability Cover3.Foundation Failure Indemnity Cover4.Products and Defective Workmanship Liability Cover5.The 'Certificate of Insurance' is to be submitted to the Principal Structural Engineer for approval.

The work comprises the design and installation of 31piles per block. The contractor is referred to drawing No 007-S-CRU-PILE issued together with these bills of quantities in order to acquaint himself fully with the nature and scope of the work

Piles are to be installed subsequent to the site beingexcavated or filled to the correct levels

Scope of work

Drilling

"Hard rock" shall mean granite, quartzitic sandstone or other rock of similar hardness, the removal of which would normally require drilling, wedging and splitting or the use of explosives

Classification of material

"Earth" shall mean all ground other than that classified as "hard rock" and shall include made-up ground and loose stones or pieces of concrete not exceeding 0,03m3 in volume as well as hard material the removal of which would normally warrant the use of pneumatic tools and which includes hard shale, ferricite, compact ouklip and material of similar hardness

-103-

PILING (PROVISIONAL)Bill No. 2SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 33: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

All piling to be carried out in accordance with SABS 1200F

General

Concrete grout strength for all piles at 28 days is 30MPa. Concrete cube tests to be carried out on pile grout for every 20 piles installed. 6 cubes to be taken after every 20 piles installed (3 cubes to be tested at 7 days and 3 cubes to be tested at 28 days). Results of the cube tests to be submitted to the Principal Structural Engineer for approval

Pile type is 250mm Ø pressure grouted Continuous Flight Auger pile (in 'end bearing') with a maximum service load of 603 kN

Pile cut-off level to be 50mm above soffit of the concrete ground beam or as indicated on the piling layouts with 500mm pile rebar projection

Pile integrity testing is to be carried out on all piles by an independent Geotechnical Engineer. No 'in-house' integrity testing by the Piling Contractor will be accepted.

All pile setting out is to be carried out by the Piling Contractor and verified by the Main Contractor whom assumes full responsibility for the pile setting out.All pile positions are to be set out by the Piling Contractor's registered Engineering Surveyor.

The final piling design is to be submitted by the Piling Contractor to the appointed Geotechnical Engineer for approval. The cost for this approval process is to be provided for by the Piling Contractor. The Piling Contractor can only commence with piling, pending the approval of the final pile design from the appointed Geotechnical Engineer and the approval from the Principal Structural Engineer.

The maximum permissible deviation of the pile positions shall be 50mm.

-104-

PILING (PROVISIONAL)Bill No. 2SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 34: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

All piles are to be neatly trimmed to pile cut-off level. The top surface of all trimmed piles is to be finished 'level and smooth'. An approved non-shrink leveling concrete grout must be allowed for by the Contractor to achieve the 'level and smooth' finish requirement, noted above.

Two copies of an 'As-Built' location drawing signed by the Piling Contractor showing the precise position of ever pile shall be supplied to the Principal Structural Engineer. Any pile outside the tolerance limits specified shall be clearly highlighted on the 'As-Built' layout

Item

Insurance policy against claims arising from the installation of piling up to a limit of R 1 000 000.00 (One Million Rand) per claim with no limit on the number of claims that may occur and effective for a period of 5 years from the date of completion of the contract

1

GUARANTEE AND INSURANCE

Item

Transporting to and establishment on site of necessary plant for the execution of the work and removal thereof on completion

2

ESTABLISHMENT

372NoSetting out of piles3

SETTING UP

372NoSetting up plant at pile position4

CONCRETE CAST IN SITU PILING

CONTINUOUS FLIGHT AUGER (CFA) PILES

3 720m250mm Diameter pile shafts5

Continuous flight auger drilling not exceeding 10m deep in earth below ground level

744m250mm Diameter pile shafts6

Continuous flight auger drilling exceeding 10m and not exceeding 15m deep in earth below ground level

-105-

PILING (PROVISIONAL)Bill No. 2SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 35: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

70m3Extra over continuous flight auger drilling in earth forcontinuous flight auger drilling in hard rock

7

Continuous flight auger drilling in strata of a moredifficult character

288m3Surplus material from pile shafts etc to a dumping site tobe located by the contractor

8

Extra over continuous flight auger drilling for carting away

4 464m250mm Diameter piles9

30MPa/19mm reinforced concrete to continuous flight auger piles

144NoMaking and testing 150 x 150 x 150mm concretestrength test cube (Provisional)

10

TEST CUBES

REINFORCEMENT (PROVISIONAL)

44tBars in various diameters11

High tensile steel reinforcement in continuous flight auger piles

372NoExposing pile for inspection including excavation 1m deep in earth and backfilling

12

EXPOSING PILES FOR INSPECTION

TRIMMING ETC

372No250mm Diameter pile13

Stripping back heads of concrete piles for a height not exceeding 1000mm to expose reinforcement including trimming to defined levels and bending reinforcement as necessary for casting into pile caps

-106-

PILING (PROVISIONAL)Bill No. 2SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 36: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Item

Transporting to and establishment on site of necessarytesting plant for the execution of the work and removalthereof on completion

14

TESTING

372NoTesting continuous flight auger (CFA) pile to a maximum load of 603kN

15

-107-

PILING (PROVISIONAL)Bill No. 2SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward to Summary of Section No. 2 R

Page 37: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity Rate

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 2

BILL NO. 3

The Tenderer is referred to the relevant Clauses in the separate document General Preambles for Trades (2017 Edition)

CONCRETE, FORMWORK AND REINFORCEMENT (PROVISIONAL)

SUPPLEMENTARY PREAMBLES

The costs of making, storing and testing of concrete test cubes as required under clause 7 "Tests" of SABS 1200 G shall include the cost of providing cube moulds necessary for the purpose, for testing costs and for submitting reports on the tests to the principal agent. The testing shall be undertaken by an independent firm or institution nominated by the contractor to the approval of the principal agent

Cost of tests

Descriptions of formwork shall be deemed to include use and waste only (except where described as "left in" or "permanent"), for fitting together in the required forms, wedging, plumbing and fixing to true angles and surfaces as necessary to ensure easy release during stripping and for reconditioning as necessary before re-use

Formwork

The vertical strutting shall be carried down to suchconstruction as is sufficiently strong to afford the required support without damage and shall remain in position until the newly constructed work is able to support itself

Formwork to soffits of slabs, beams, etc shall be deemed to be propped up exceeding 1,5m and not exceeding 3,5m high unless otherwise described

-108-

CONCRETE, FORMWORK AND REINFORCEMENT (PRBill No. 3SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 38: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Formwork to sides of bases, pile caps, ground beams, etc will only be measured where it is prescribed by the engineer for design reasons. Formwork necessitated by irregularity or collapse of excavated faces will not be measured and the cost thereof shall be deemed to be included in the allowance for taking the risk of collapse of the sides of the excavations, provision for which is made in "Earthworks"

UNREINFORCED CONCRETE CAST AGAINSTEXCAVATED SURFACES

36m3Surface blinding under footings and bases1

10MPa/19mm concrete

REINFORCED CONCRETE CAST AGAINSTEXCAVATED SURFACES

180m3Pile caps2

25MPa/19mm concrete

130m3Foundation beams3

REINFORCED CONCRETE CAST ON/INFORMWORK

1 032m3Slabs including beams and inverted beams4

25MPa/19mm concrete

132m3Stairs including landings, beams and inverted beams5

171m3Surface beds6

30MPa/19mm concrete

648NoMaking and testing 150 x 150 x 150mm concrete strength test cube (Provisional)

7

TEST CUBES

CONCRETE SUNDRIES

-109-

CONCRETE, FORMWORK AND REINFORCEMENT (PRBill No. 3SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 39: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

5 730m2Surface beds, slabs, etc8

Finishing top surfaces of concrete smooth with a wood float

48No255mm thick reinforced concrete slab, beam, wall, etc9

Sleeves exceeding 50mm and not exceeding 100mm diameter

24m2Bedding approximately 5mm thick above lintel 10

"Prostruct" or other equal and approved, 5 Star non-shrink grout

ROUGH FORMWORK (DEGREE OF ACCURACY II)

24m2Foundation beams (Provisional)11

Rough formwork to sides

3 186mEdges, risers, ends and reveals not exceeding 300mm high or wide

12

204mSloping and stepped outer edges of stairs 400mm highextreme

13

4 092m2Slabs propped up exceeding 1.5m and not exceeding 3.5m high

14

Rough formwork to soffits

180m2Landings15

96m2Stairs with sloping soffits16

180m2Stairs with sloping soffits propped of stairs below17

5 544m25 x 25mm Chamfers along top or bottom edges18

Boxing in smooth formwork to form

MOVEMENT JOINTS ETC

-110-

CONCRETE, FORMWORK AND REINFORCEMENT (PRBill No. 3SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 40: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

2 362mNot exceeding 300mm wide19

Two layers of 3 ply malthoid in slip joints between horizontal concrete and brick surfaces including cement mortar bed

1 428mNot exceeding 300mm high to edges of surface beds and slabs

20

Expansion joints with 10mm closed cell expandedpolyethylene between vertical concrete and bricksurfaces

150m3 x 30mm Saw-cut joints in top of concrete with the top 3mm increased to 8mm wide

21

Saw-cut joints

REINFORCEMENT

156tBars in various diameters22

High tensile steel reinforcement to structural concrete work

1 656m2Type 245 fabric reinforcement in concrete surface beds etc

23

Fabric reinforcement

-111-

CONCRETE, FORMWORK AND REINFORCEMENT (PRBill No. 3SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward to Summary of Section No. 2 R

Page 41: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity Rate

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 2

BILL NO. 4

The Tenderer is referred to the relevant Clauses in the separate document General Preambles for Trades (2017 Edition)

MASONRY (PROVISIONAL)

SUPPLEMENTARY PREAMBLES

BRICKWORK

Where sizes in descriptions are given in brick units, "onebrick" shall represent the length and "half brick" the width of a brick

Sizes in descriptions

Walls in two skins described as "bagged and sealed" shall be deemed to include having the outer face of the inner skin bagged with 1:6 cement and sand mixture and sealed with two coats bitumen emulsion waterproofing coating

Bagged and sealed walls

BRICKWORK

FOUNDATIONS

1 181m2One brick walls1

Brickwork of NFX bricks (14 MPa nominal compressive strength) in class II mortar

SUPERSTRUCTURE

8m3Mass brickwork2

Brickwork of NFX bricks (14 MPa nominal compressive strength) in class II mortar

2 396m2Half brick walls3

-112-

MASONRY (PROVISIONAL)Bill No. 4SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 42: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

178m2Half brick walls in beamfilling4

7 871m2One brick walls5

244m2One brick walls in beamfilling6

5 887m2On brick walls, piers, etc7

Cement wash of 1:3 liquid cement and sand mixture applied with a brush

1 195m210mm Expanded polystyrene built in vertically between brick skins

8

Joint forming material in movement joints

0.07t10mm Diameter high tensile steel bars built in horizontally

9

Steel bar reinforcement

13 001m75mm Wide reinforcement built in horizontally10

2,5mm Galvanised brick reinforcement

55 879m150mm Wide reinforcement built in horizontally11

2 554m110 x 75mm Lintels in lengths not exceeding 3m12

Prestressed fabricated concrete lintels including necessary temporary supports

504No30 x 1,6mm Roof tie 1,5m long with one end built intobrickwork and other end fixed to timber

13

Galvanised hoop iron cramps, ties, etc

384No229 x 152mm Clay vermin proof air brick14

Air bricks etc

384No233 x 175mm Foam plastic air vent15

FIBRE-CEMENT WINDOW SILLS

-113-

MASONRY (PROVISIONAL)Bill No. 4SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 43: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

714m15 x 150mm Wide sills set sloping and slightly projecting16

Natural grey sills in single lengths bedded in class I mortar including metal fixing lugs etc

-114-

MASONRY (PROVISIONAL)Bill No. 4SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward to Summary of Section No. 2 R

Page 44: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity Rate

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 2

BILL NO. 5

The Tenderer is referred to the relevant Clauses in the separate document General Preambles for Trades (2017 Edition)

WATERPROOFING (PROVISIONAL)

DAMPPROOFING OF WALLS AND FLOORS

872m2In walls1

One layer 375 micron embossed polyethylene dampproof course (SANS 952-1985 type B)

564m2Vertically between walls2

1 572m2Under surface beds3

One layer 250 micron green polyethylene waterproofsheeting (SANS 952-1985 type C) sealed at laps with PVC self-adhesive tape

5 887m2On bagged brick walls4

Two coats bitumen emulsion waterproof coating

WATERSTOPS, SEALING STRIPS, JOINTSEALANTS, ETC

156m8 x 13mm In saw cut joints in floors5

"Dow Corning 813C" or other equal and approved, silicone sealing compound including backing cord,bond breaker, primer, etc

1 428m10 x 10mm In expansion joints in floors including raking out expansion joint filler as necessary

6

370m10 x 10mm In expansion joints in walls etc including raking out expansion joint filler as necessary

7

1 783m10 x 10mm In expansion joints in soffits including rakingout expansion joint filler as necessary

8

-115-

WATERPROOFING (PROVISIONAL)Bill No. 5SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward to Summary of Section No. 2 R

Page 45: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity Rate

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 2

BILL NO. 6

The Tenderer is referred to the relevant Clauses in the separate document General Preambles for Trades (2017 Edition)

ROOF COVERINGS, CLADDINGS, ETC (PROVISIONAL)

SUPPLEMENTARY PREAMBLES

Roof sheeting systems are to be manufactured in strict accordance with the supplier's specifications.

Corrugated metal sheeting and accessories

Fixing of all roof sheeting is to be in accordance with the manufacturer's approved instruction book.

The manufacturer shall comply with ISO9002 Quality Management System.

PROFILED METAL SHEETING AND ACCESSORIES

1 976m2Roof covering with pitch not exceeding 25 degrees.1

"Global Roofing Solutions" or other equal and approved, 0.53mm thick 686mm cover IBR 686 profile Supergalum AZ150 spelter G550, Egret White finish top coat and standard backing coat to other side, fixed to timber purlins (elsewhere measured) and fixed strictly in accordance with the manufacturer's instructions

198m

Roll-top type ridge capping 550mm girth, includingdressing edges into corrugations of roof covering onboth sides

2

0,53mm AZ150 spelter supergalum steel sheet accessories to preceding roof covering

84mValley gutters 450mm girth3

-116-

ROOF COVERINGS, CLADDINGS, ETC. (PROVISIONABill No. 6SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 46: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

408mIBR pattern flute closers4

168mIBR pattern flute closers, raking at valleys or hips5

408mIBR pattern polyclosures to underside of ridge capping6

168mIBR pattern polyclosures to underside of rake at valleys or hips

7

ROOF AND WALL INSULATION

1 980m2

Insulation sheeting laid taut over purlins and fixed concurrent with roof covering with minimum 150mm stapled laps including galvanised steel straining wires at not exceeding 400mm centres and double-sided tape at edges where required

8

"Sisalation FR405" or other equal and approved multi-layered reinforced double-sided aluminium foil sheeting

1 980m2

Insulation blanket fixed to rafters (at approximately 750mm centres) with 150mm stapled laps including galvanised steel straining wires at not exceeding 400mmcentres and doublesided tape at edges where required

9

"Isover " or other equal and approved, 50mm Thick Factorylite non combustible light weight fibreglass glasswool thermal roof insulation

-117-

ROOF COVERINGS, CLADDINGS, ETC. (PROVISIONABill No. 6SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward to Summary of Section No. 2 R

Page 47: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity Rate

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 2

BILL NO. 7

The Tenderer is referred to the relevant Clauses in the separate document General Preambles for Trades (2017 Edition)

CARPENTRY AND JOINERY (PROVISIONAL)

SUPPLEMENTARY PREAMBLES

Items described as "nailed" shall be deemed to be fixed with hardened steel nails or pins, or to be shot pinned, to brickwork or concrete.

Fixing

Items described as "plugged" shall be deemed to include screwing to fibre, plastic or metal plugs at not exceeding 500mm centres, and where described as "bolted", the bolts have been given elsewhere.

Descriptions of frames shall be deemed to include frames, transoms, rails, etc.

Joinery

Descriptions of hardwood joinery shall be deemed to include sinking and pelleting heads and nuts of bolts.

The Structural Design of the prefabricated (nail plated) roof trusses must be carried out by an 'Approved Competent Person', who is professionally registered withECSA, in terms of the Engineering Profession Act, 2000, (Act No. 46 of 2000). The Structural Design of the prefabricated (nail plated) roof trusses must be carried out in accordance with the requirements of the following South African National Standards : SANS 10160, SANS 10163 and SANS 10243.

PREFABRICATED TIMBER ROOF TRUSS CONSTRUCTION, ETC

-118-

CARPENTRY AND JOINERY (PROVISIONAL)Bill No. 7SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 48: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

In accordance with the statutory requirements of the 'The South African National Building Regulations' - SANS 10400-A, Clause A19, the 'Approved Competent Person', who was responsible for the structural design ofthe prefabricated (nail plated) timber roof trusses, must submit a 'TR1 - Compliance and Completion Certificate' confirming the structural stability of the roof structure, to the Principle Structural Engineer (PSE), on completion of the roof truss installation.

The prefabricated (nail plated) timber roof trusses must be manufactured by an accredited ITC-SA fabricator.

A full set of 'Shop Drawings' (confirming all on-site dimensions, structural design information, truss tie down details, cross bracing details, etc), must be submitted by the Principle Building Contractor (PBC) to the Principle Structural Engineer (PSE) for review and approval, prior to any fabrication taking place.

The on-site Inspection of the installation of the prefabricated (nail plated) roof trusses must be carried out by an 'Approved Competent Person', who is professionally registered with ECSA, in terms of the Engineering Profession Act, 2000, (Act No. 46 of2000).

In accordance with the statutory requirements of the 'The South African National Building Regulations' - SANS 10400-A, Clause A19, the 'Approved Competent Person', who was responsible for the on-site Inspection of the installation of the prefabricated (nail plated) timber roof trusses, must submit a 'TR2 - Compliance and Completion Certificate' confirming that the fabrication, installation and erection of the entire prefabricated (nail plated) timber roof structure is structurally stable and has been completed in accordance with the approved structural design drawings, to the Principle Structural Engineer (PSE), on completion of the roof truss installation

Trusses are at maximum of 1200mm centres

Roof covering is 0.53mm IBR 686 roof sheeting on purlins

Ceiling is 9.5mm gypsum plasterboard with skimmed and taped joints on 38 x 38mm brandering

-119-

CARPENTRY AND JOINERY (PROVISIONAL)Bill No. 7SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 49: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

References given in descriptions refer to the respective types of trusses detailed on the architect's/engineer's drawings annexed to these bills of quantities for tender purposes

Dimensions in descriptions of trusses are nominal and actual measurements are to be obtained from the architect/ engineer and/ or taken on site before design or fabrication commences

12No

Roof construction to double pitched roof with three gable ends, 14.31 x 12.34m overall on plan x 1.35mm high overall, including trusses, jack rafters, permanent bracing and 75 x 50mm purlins at centres recommended for roof covering, splayed purlins at eaves and 38 x 114mm wall plates

1

Design, supply and install nailed roof truss system complete in accordance with the Standard Building Regulations including ring shank nails, hurricane clips at exposed sections and at ridges, temporary and permanent bracing, etc.

EAVES, VERGES, ETC

331m225 x 12mm Fascias including aluminium H-profile jointing strips

2

Medium density plain fibre-cement fascias and barge boards

322m200 x 80mm Barge boards, including aluminium H-profile jointing strips

3

DOORS, ETC

96No40mm Door 813 x 2032mm high4

Solid hardwood meranti timber door, hung to steel frames

288No40mm Door 813 x 2032mm high5

Semi-solid flush doors with 3,2mm plain hardboard covering on both sides, hung to steel frames

FITTINGS

-120-

CARPENTRY AND JOINERY (PROVISIONAL)Bill No. 7SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 50: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

CUPBOARDS TO KITCHENS, BEDROOMS, ETC

SUPPLEMENTARY PREAMBLES

The following cupboard fittings are given as complete units i.e. the components of the units have not been given separately. Descriptions of such units shall, therefore, be deemed to include all components, assembling, housing, notching, glueing, blocking, planting-on and screwing with countersunk screws, edge strips, thermosetting plastic laminate, glass, ironmongery, metalwork, paint or varnish finishes, etc

General

Prices are to include for all necessary filler pieces against walls etc

References given in descriptions refer to the respective types of fittings detailed on the architect's drawing numbered W501, annexed to these bills of quantities for tender purposes

References

96No

Sink cupboard complete 1825 x 625 x 900mm high with sides, bottom, divisions, shelf, drawers, back and double hinged doors including hinges and stainless steel barrel handles

6

Kitchen cupboards formed of 18mm Melawood panels (Colour: TBC) and 32mm thick Formica Life seal worktop (Colour: TBC). Doors, drawers andcupboard shelves with edging

-121-

CARPENTRY AND JOINERY (PROVISIONAL)Bill No. 7SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward to Summary of Section No. 2 R

Page 51: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity Rate

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 2

BILL NO. 8

The Tenderer is referred to the relevant Clauses in the separate document General Preambles for Trades (2017 Edition)

CEILINGS, PARTITIONS AND ACCESS FLOORING (PROVISIONAL)

SUPPLEMENTARY PREAMBLES

Items described as "nailed" shall be deemed to be fixed with hardened steel nails or pins, or to be shot-pinned, to brickwork or concrete

Fixing

Items described as "plugged" shall be deemed to include screwing to fibre, plastic or metal plugs at not exceeding 500mm centres, and where described as "bolted", the bolts have been given elsewhere

Unless otherwise described ceilings shall be deemed to be horizontal

Ceilings

All steel components for ceilings, partitions, etc are to begalvanised in accordance with SANS 121

Steel components

NAILED-UP CEILINGS

SUPPLEMENTARY PREAMBLES

Prices for openings for light fittings, ventilation grilles, airconditioning diffusers, etc are to include for anynecessary additional support, trimming around, etc

Openings

-122-

CEILINGS, PARTITIONS AND ACCESS FLOORING (PRBill No. 8SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 52: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

1 078m2

Ceilings including 38 x 38mm sawn softwood brandering at 400mm centres and cross brandering at 400mm centres

1

9,5mm Taper-edge gypsum plasterboard with taped and skimmed flush joints

24No

Extra over ceiling for 600 x 600mm thick white epoxy coated aluminium trap door, hinged to open 180 degrees onto ceiling in 38 x 25mm T-section steel frame

2

200m2

Ceilings including 38 x 38mm sawn softwood brandering at 400mm centres and cross brandering at 400mm centres

3

4,6mm Fibre-cement plain ceiling boards with H-profile galvanised steel jointing strips

1 483m75mm Coved cornices4

Gypsum plasterboard cornices

-123-

CEILINGS, PARTITIONS AND ACCESS FLOORING (PRBill No. 8SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward to Summary of Section No. 2 R

Page 53: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity RateUnit

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 2

BILL NO. 9

The Tenderer is referred to the relevant Clauses in the separate document General Preambles for Trades (2017 Edition)

IRONMONGERY (PROVISIONAL)

SUPPLEMENTARY PREAMBLES

Where applicable the manufacturers' names or product catalogue titles are given in sub-headings preceding the items

Proprietary items

Prices are to be based on the specific products/articles specified. If tenderers wish to offer alternative products/articles for certain items, these items are to be clearly marked and the alternative specification given with supporting brochures etc clarifying the features of the products/articles offered

On request returnable samples are to be provided to the principal agent for consideration

Where applicable finishes to ironmongery are indicated by suffixes in accordance with the following list:

Finishes to ironmongery

-124-

IRONMONGERY (PROVISIONAL)Bill No. 9SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 54: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

BS Satin bronze lacquered CH Chromium platedSC Satin chromium platedSE Silver enamelledGE Grey enamelledAN Anodised naturalAS Anodised silver AB Anodised bronzeAG Anodised goldBS Satin bronze lacquered CH Chromium platedSC Satin chromium platedSE Silver enamelledGE Grey enamelledAN Anodised naturalAS Anodised silver AB Anodised bronzeAG Anodised goldBS Satin bronze lacquered CH Chromium platedSC Satin chromium platedSE Silver enamelledGE Grey enamelledAN Anodised naturalAS Anodised silver AB Anodised bronzeAG Anodised goldABL Anodised blackPB Polished brass PL Polished and lacquered PT Epoxy coatedSD Sanded Anodised blackPB Polished brass PL Polished and lacquered PT Epoxy coatedSD Sanded Anodised blackPB Polished brass PL Polished and lacquered PT Epoxy coatedSD Sanded

LOCK SETS

288No

Gower 2 lever lock set with Chrome handle finish (Code: CZ682-24-95) including powder coated 2 lever lock with Zinc backplate

1

"ASSA ABLOY" or other equal and approved

-125-

IRONMONGERY (PROVISIONAL)Bill No. 9SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 55: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

96No

Gower 3 lever lock set with Chrome handle finish (Code: CZ682-24-52) including powder coated 3 lever lock with Zinc backplate.

2

LETTERS, NAMEPLATES, ETC

96No

150 x 50 x 5mm High perspex plate with engraved and painted letters or numerals "UNIT A1" fixed to timber door

3

Refer to the respective detail on the architect's drawing numbered W103, annexed to these bills of quantities for tender when pricing the items hereunder

PHOTOLUMINESCENT SIGNS

Signs are to comply with SANS 1186-1 to 5 and to be tothe approval of the local authority. Signs are to have anodised aluminium frames

SUPPLEMENTARY PREAMBLES

Prices are to include for fixing by approved methods.The use of double sided tape will not be permitted. Surface mounted signs are to be concealed fixed andceiling mounted signs are to be hung with 2mm diameter stainless steel cables

Samples, specifications, literature, etc of materials andfabricated articles the tenderer proposes to use shall besubmitted with the tender

A ten year guarantee on materials and workmanshipshall be submitted by the successful tenderer

References at the end of the item descriptions are to therelative items on drawings annexed to these bills of quantities

12No

SABS Arrow Left and Running Man photoluminescent (Glow in the dark) sign (Code: E2), size 380 x 190mm high

4

Wall mounted photoluminescent statutory signs in 190 x 190mm modules

-126-

IRONMONGERY (PROVISIONAL)Bill No. 9SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 56: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

36No

SABS Diagonal Arrow Down & Left Running Man photoluminescent (Glow in the dark) sign (Code: E14), size 380 x 190mm high

5

24No

SABS Arrow Down, Fire Hose Reel and Fire Extinguisher photoluminescent (Glow in the dark) sign (Code: F4), size 380 x 190mm high

6

SUNDRIES

384No38mm Black rubber door stop7

"DORMAKABA" or other equal and approved

BATHROOM FITTINGS

96NoFiorano chrome soap dish (Code: GIO-4369), fixed to wall

8

"La Gio Bella" or other equal and approved

96NoRieti chrome toilet roll holder (Code: GIO-3925), fixed to wall

9

96No

Demola double robe hooks chrome (Code: GIO-3323), fixed to wall

10

-127-

IRONMONGERY (PROVISIONAL)Bill No. 9SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward to Summary of Section No.2

R

Page 57: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity RateUnit

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 2

BILL NO. 10

The Tenderer is referred to the relevant Clauses in the separate document General Preambles for Trades (2017 Edition)

METALWORK (PROVISIONAL)

SUPPLEMENTARY PREAMBLES

Descriptions of bolts shall be deemed to include nuts and washers

Descriptions of expansion anchors and bolts and chemical anchors and bolts shall be deemed to include nuts, washers and mortices in brickwork or concrete

Items described as "holed for bolt(s)" shall be deemed to exclude the bolts unless otherwise described

Items described as "plugged" shall be deemed to include screwing to fibre, plastic or metal plugs at not exceeding 600mm centres

Descriptions of bolts, anchors, etc.

Doors and windows shall comply with AAAMSA designcriteria

Aluminium doors, windows, etc

Glazing shall comply with SAGGA regulations. Glass shall be 6mm thick toughened safety glass as shown on the window schedules/drawings appended to these bills of quantities. Glass thickness shall comply with SAGGA regulations irrespective of thicknesses shown on the schedules /drawings

Doors and windows shall be supplied with protective tape and plastic and shall be removed only once surrounding trades have been completed

For purpose made windows and doors, refer to drawingsannexed to these bills of quantities

-128-

METAL WORK (PROVISIONAL)Bill No. 10SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 58: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

The following certificates shall be provided prior tocommencement of site work:

1. A copy of the relevant AAAMSA Performance Test Certificate from the manufacturer/contractor supplying the architectural aluminium product

2. A Certificate of Conformance confirming that anodising or powder coating has been processed in accordance with SANS 999 and SANS 1796 respectively

3. A powder guarantee of not less than 15 years issued by the powder manufacturer. The specific conditions contained in this guarantee shall form part of the powder coating process

4. A Certificate of Conformance confirming that glazing has been installed in accordance with SANS 0137, ensuring that safety glazing materials have been installed in the mandatory areas and that each individual pane of safety glazing materials has been permanently marked

5. A warranty from the manufacturer of the laminated safety glass and/or hermetically sealed glazing units guaranteeing the products against delamination and colour degredation for a period of not less than five years

Rates shall include for the following:

1. All opening and fixed lights, coupling mullions and transoms, support steelwork, fittings, ironmongery, etc., as required and specified.

2. Complete glazing as described, with and including matching aluminium glazing beads and gaskets and glazed in accordance with the manufacturer's written instructions

3. Building in and fixing into preformed openings. Window opening sizes to be verified on site before windows can be manufactured. Shop drawings to be submitted for approval

-129-

METAL WORK (PROVISIONAL)Bill No. 10SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 59: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

4. Silicone pointing with a silicone sealant recommended by AAAMSA on all door / window and structure junctions

GALVANISED STEEL BALUSTRADING AND STAINLESS STEEL HAND RAILS

360m

Horizontal and raking balustrading 1100mm high, of 50mm external diameter x 1.5mm thick continuous pipe stainless steel handrail, 50 x 8mm flat section continuous top and bottom rails, 50 x 50 x 2mm square section posts with 12mm round bar handrail connection at approximately 1200mm centres with 150 x 150 x 8mm footplates bolted to concrete with M14 bolts and 12 x 12 x 1.6mm intermediate vertical balusters at 110mm centres between top and bottom rails. (Refer to Drawing No. W503)

1

Welded balustrading to walkways and stairs

GALVANISED PRESSED STEEL DOOR FRAMES

288NoFrame for door 813 x 2032mm high2

1,2mm Rebated frames suitable for half brick walls with two 100mm butt hinges

96NoFrame for door 813 x 2032mm high3

1,6mm Rebated frames suitable for one brick walls with two 100mm butt hinges

GALVANISED PRESSED STEEL TRANSFORMER ROOM DOORS AND FRAMES

12No

Hot dipped galvanised substation meter room door in single leaf (Type D1), size 900 x 2400mm high with 1,2mm solid steel slats, cabin hooks, earth strap, shooting bolt housing and 3 Point locking system for padlock, with perimeter framing plugged and screwed to face at maximum 300mm centres to concrete or brickwork using concealed rivets.

4

"Xpanda" or other equal and approved

-130-

METAL WORK (PROVISIONAL)Bill No. 10SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 60: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Refer to the respective details on the architect's drawing numbered W600, annexed to these bills of quantities for tender when pricing the items hereunder

ALUMINIUM WINDOWS

Glazing shall be in accordance with SANS 10160, SANS 10137, SANS 10400 (Part N of section 3) and SANS 1263 with clear glass. All complying with AAAMSA performance criteria A0.

96No

Window Type W-01 overall size 600mm wide x 600mm high extreme including all framing, glazing beads, glazing, and necessary glass fins, etc., complete

5

Powder coated casement window units colour: Matt charcoal (Code: ANP3055), complete with subframes, ironmongery, glass, sealing, etc and fixing to brickwork or concrete

96No

Window Type W-02 overall size 840mm wide x 900mm high extreme including all framing, glazing beads, glazing, and necessary glass fins, etc., complete

6

192No

Window Type W-03 overall size 1500mm wide x 900mm high extreme including all framing, glazing beads, glazing, and necessary glass fins, etc., complete

7

192No

Window Type W-04 overall size 1500mm wide x 900mm high extreme including all framing, glazing beads, glazing, and necessary glass fins, etc., complete

8

-131-

METAL WORK (PROVISIONAL)Bill No. 10SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward to Summary of Section No.2

R

Page 61: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity Rate

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 2

BILL NO. 11

The Tenderer is referred to the relevant Clauses in the separate document General Preambles for Trades (2017 Edition)

PLASTERING (PROVISIONAL)

SUPPLEMENTARY PREAMBLES

GRANOLITHIC

The method to be used shall be either the monolithicmethod or the bonded method

Method

For granolithic applied monolithically, the concrete floorshall be swept clean after bleeding of the concrete hasceased and the slab has begun to stiffen; any remainingbleed water shall be removed and the granolithic appliedimmediately thereafter. For granolithic to be bonded tothe floor slab after it has hardened, the slab surfaceshall be hacked (preferably by mechanical means) untilall laitance, dirt, oil, etc is dislodged and swept clean ofall loose matter. The slab shall then be wetted and keptdamp for at least six hours before applying thegranolithic

Preparation

Granolithic shall attain a compressive strength of at least 41MPa. The coarse aggregate shall comply with SANS 1083 and shall generally be capable of passing a 10mm mesh sieve. Where the thickness of the granolithic exceeds 25mm, the size of the coarse aggregate shall be increased to the maximum size compatible with the thickness of the granolithic

Mix

-132-

PLASTERING (PROVISIONAL)Bill No. 11SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 62: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Granolithic shall be laid in panels not exceeding 14m² for monolithic finishes, not exceeding 9,5m² for bonded finishes and not exceeding 6m² for all external granolithic. Wherever possible, panels shall be square but at no time should the length of the panel exceed 1,5 times its width

Panels

Where possible joints between panels shall be positioned over joints in the floor slab and shall be at least 3mm wide through the full thickness of the finish, separated by strips of wood or fibreboard and finished with V-joints

Monolithic granolithic shall be applied to the partially setslab and thoroughly compacted and lightly wood floatedto the required levels

Laying

Bonded granolithic shall be applied to the slab after applying a 1:1 sand-and-cement slurry brushed over thesurface and allowed to partially set before applying thegranolithic. The granolithic shall be throughly compactedand lightly wood floated to the required levels

After wood floating, the monolithic and bondedgranolithic shall remain undisturbed until bleeding hasceased and the surface has stiffened. Any remainingbleed water and laitance shall then be removed and thesurface steel trowelled or power floated

Granolithic shall be covered with clean hessian withwaterproof building foil over and kept wet for at leastseven days after laying

Curing, seasoning and protection

Coloured granolithic shall be tinted with an approvedcolouring pigment mixed into the granolithic in theappropriate proportions of pigment per pocket of cement, of uniform appearance and consistent colour throughout

Colour

SCREEDS

-133-

PLASTERING (PROVISIONAL)Bill No. 11SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 63: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

4 364m225mm Thick on floors and landings1

Screeds wood floated, on concrete

GRANOLITHIC

660m230mm Thick on floors and landings2

Tinted (Colour: TBC) granolithic, on concrete

312m230mm Thick on treads and risers of stairs3

INTERNAL PLASTER

14 304m2On walls4

Cement plaster steel trowelled, on brickwork

296m2On narrow widths5

84m2On walls6

Cement plaster steel trowelled, on concrete

55m2On narrow widths7

3 936m2On ceilings8

240m2On raking soffits of stairs9

EXTERNAL PLASTER

6 216m2On walls10

Cement plaster wood floated, on brickwork

336m2On narrow widths11

516m2On narrow widths12

Cement plaster wood floated, on concrete

-134-

PLASTERING (PROVISIONAL)Bill No. 11SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward to Summary of Section No. 2 R

Page 64: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity Rate

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 2

BILL NO. 12

The Tenderer is referred to the relevant Clauses in the separate document General Preambles for Trades (2017 Edition)

TILING (PROVISIONAL)

SUPPLEMENTARY PREAMBLES

Unless otherwise described, tiles shall be laid withcontinuous joints in both directions

Patterns

Unless described as "fixed with adhesive to plaster (plaster elsewhere)" descriptions of tiling on brick or concrete walls, columns, etc shall be deemed to include 1:4 cement plaster backing and descriptions of tiling on concrete floors etc shall be deemed to include 1:3 plaster bedding

Tiling described as "fixed with adhesive on power floated concrete" shall be deemed to include for approved tiling key-coat

Fixing

Ceramic, porcelain, marble and granite tiles are to be fixed and grouted with suitable adhesives and grouts from the "Tal Professional" range of products as recommended by the manufacturer of the tiles

Prime cost amounts are net. Prime cost amounts shall include for delivery to site of all articles concerned

Prime cost amounts

WALL TILING

312m2On walls1

150 x 150 x 5mm White glazed ceramic tiles fixed with adhesive to plaster (plaster elsewhere)

-135-

TILING (PROVISIONAL)Bill No. 12SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 65: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

FLOOR TILING

4 307m2On floors and landings 2

Ceramic floor tiles (P.C Sum of R100.00/m²) fixed with adhesive to screed (screed elsewhere) and flush pointed with tinted grouting

4 524mSkirting 100mm high3

96m

"Genesis" or other equal and approved, interior aluminium medium duty trim in Mill Aluminium (Code: EMA100.80), size 18 x 10mm x 2,5m long on ceramic tile surfaces, securely bedded in adhesive

4

SUNDRIES

947m

"Genesis" or other equal and approved, interior built-in PVC Trim Regular colour White (Code: ETR608.01), size 6mm on ceramic tiles including all necessary single corner pieces, bedded in mortar/tile adhesive

5

-136-

TILING (PROVISIONAL)Bill No. 12SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward to Summary of Section No. 2 R

Page 66: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity Rate

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 2

BILL NO. 13

The Tenderer is referred to the relevant Clauses in the separate document General Preambles for Trades (2017 Edition)

PLUMBING AND DRAINAGE (PROVISIONAL)

SUPPLEMENTARY PREAMBLES

Descriptions of gutter outlets etc shall be deemed to include wire balloon gratings

Wire gratings

Descriptions of channels shall be deemed to include necessary excavation, surface preparation, compaction, etc, and disposal of surplus material on site

Stormwater channels

Stainless steel for economy basins, domestic sinks andworktops shall be Type 430 (17/0)

Stainless steel basins, sinks, wash troughs, urinals, etc

Stainless steel for urinals, basins, quality sinks, washtroughs, institutional equipment, etc shall be Type 304(18/8)

Units shall have standard aprons on all exposed edgesand tiling keys against walls where applicable

Outer edges of sinks, basins, baths, urinals, etc are to be sealed against adjacent surfaces with approved silicone.

Sealing of edges

-137-

PLUMBING AND DRAINAGE (PROVISIONAL)Bill No. 13SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 67: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Sewer and drainage pipes and fittings shall be jointed and sealed with butyl rubber rings

Soil, waste and vent pipes and fittings shall be solvent weld jointed or sealed with butyl rubber rings

PVC-U pipes and fittings

Pipes of 50mm diameter and smaller shall be plain ended with solvent welded uPVC loose sockets and fittings

Pipes of 63mm diameter and greater shall have sockets and spigots with push-in type integral rubber ring joints. Bends shall be uPVC and all other fittings shall be cast iron, all with similar push-in type joints

PVC-U pressure pipes and fittings

Pipes shall be hard drawn and half hard "Maksal" pipes of the class described. Class 0 (thin walled hard drawn) pipes shall not be bent. Class 1 (thin walled half hard), Class 2 (half hard) and Class 3 (heavy walled half-hard) pipes shall only be bent with benders with inner and outer formers. Fittings to copper waste, vent and anti syphon pipes, capillary solder fittings and compression fittings shall be "Cobra Watertech" or other equally and approved type. Capillary solder fittings shall comply with ISO 2016.

Copper pipes

Copper pipes are to be installed in accordance with the latest revision of the Code of Practice for Copper Plumbing soldering techniques. Flux, solder, etc to be strictly in accordance with the manufacturer's requirements with special attention to copper flux composition.

Where fittings have reducing ends or branches they are described as "reducing" and only the largest end or branch size is given.

Reducing fittings

-138-

PLUMBING AND DRAINAGE (PROVISIONAL)Bill No. 13SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 68: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Unless specifically otherwise stated, descriptions of pipes shall be deemed to include fixing to walls, etc, casting in, building in or suspending not exceeding 1m below suspension level.

Fixing of pipes

Pipes chased into brickwork must be wrapped with two layers of stout brown paper tied with wire. Rates are to include for wrapping around joints and fittings

Paper wrapping to pipes

Water pipework is to be disinfected at completion in accordance with SABS 1200L (provision for disinfection elsewhere)

Disinfection of water pipework

Pipes to be taped shall be coated with the appropriateprimer and the tape shall be applied in the appropriatewidths and with 55% overlaps

"Densyl" petrolatum anti-corrosion tape as manufactured by Denso SA (Pty) Ltd.

Couplings and fittings to pipes shall be taped in strictaccordance with the manufacturer's instructions including mastic, tape, "Layflat" sheeting, securing of same, etc

Prices for wrapping of pipes shall include for all work asdescribed to couplings in the length

Pipes shall be laid and bedded in accordance withmanufacturers' instructions and trenches shall be carefully backfilled

Laying, backfilling, bedding, etc of pipes

Where no manufacturers' instructions exist, pipes shall be laid in accordance with Clauses 5.1 and 5.2 of each of the following:SABS 1200L : Medium-pressure pipelinesSABS 1200LD: SewersSABS 1200LE: Stormwater drainage

-139-

PLUMBING AND DRAINAGE (PROVISIONAL)Bill No. 13SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 69: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Descriptions of overflow pipes where measured in number, shall be deemed to include joints to cisterns and splay cut ends

General

Descriptions of service pipes and flexible connecting pipes shall be deemed to include connections to taps, cisterns, etc and to steel pipes (adaptors for connectionsto copper pipes, etc are given separately)

Descriptions of WC pans, slop hoppers, etc shall bedeemed to include for joints to soil pipes (pan connectors are separately measured)

Where required, the contractor shall prepare an updatedset of as-built drawings. At completion of the contractthe contractor shall hand these drawings to the principalagent for reproducing onto the originals for handing overto the employer (provision for allowance of as-builtdrawings elsewhere)

As-built drawings

RAINWATER DISPOSAL

331m125mm Half-round roof gutters with beaded front edge1

PVC-U gutters and rainwater pipes

840m75mm Diameter rainwater pipes2

96NoExtra over gutter for stopped end3

24NoExtra over gutter for angle4

72NoExtra over gutter for outlet for 75mm pipe5

72NoExtra over rainwater pipe for eaves or plinth offset6

72NoExtra over rainwater pipe for shoe7

SANITARY FITTINGS

-140-

PLUMBING AND DRAINAGE (PROVISIONAL)Bill No. 13SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 70: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

96No

Grade 304 18/10 polished stainless steel inset sink, overall size 800 x 460mm with one 340 x 370 x140mm deep bowl (Model: PLN611, Code: 1990030), fitted onto cupboard (cupboard elsewhere specified).

8

"Franke Projectline" or other equal and approved

96No

Amaro II vitreous china lavatory basin, colour white, (Code: 037119), overall size 500 x 410mm with one taphole including integrated overflow and chainstay hole, bolted to wall with M10 x 120mm bolts (Code: 035678) and sealed with silicone sealant where basin meets wall

9

"Plumline" or other equal and approved

96No

Amaro II T/F C/C 90° outlet low level box set pan and cistern, colour White, (Code: 0348661) including wooden toilet seat with nylon hinge, colour white, (Code: 024454)

10

96NoAmaro II contract bath with handles 1700 x 700mm, colour white (Code: 036517)

11

WASTE UNIONS ETC

96No

Chrome plated slotted basin waste, size 32mm (Code: 030700) with 62mm diameter flange, 80mm long shank and plug

12

"Plumline" or other equal and approved

96No

Chrome plated slotted basin waste, size 40mm (Code: 030701) with 62mm diameter flange, 80mm long shank and plug

13

96NoFlexi Rubber P-trap size 40 x 40mm (Code: 000413)14

TRAPS ETC

96NoFlexi rubber plain bath trap and overflow size 40 x 40mm (Code: 000401)

15

96NoStandard chrome plated bottle trap, size 32mm (Code: 035583) including tailpipe and bung

16

"Plumline" or other equal and approved

-141-

PLUMBING AND DRAINAGE (PROVISIONAL)Bill No. 13SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 71: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

TAPS, VALVES, ETC

672No15mm chromium plated angle regulating valve and connection pipe (Code: 832-10)

17

"Cobra Watertech" or other equal and approved

192No15mm chrome plated stella washing machine tap (Code: 3309ST-15)

18

96No15mm brass fullway isolating ball valve with lever handle19

"Tekflo valves" or other equal and approved

12No42mm brass fullway isolating ball valve with lever handle20

12No42mm brass in-line strainer21

12No42mm brass pressure control valve (adjustable)22

12No42mm brass non-return valve23

96No15mm chrome plated Hydrus sink mixer (Code: 031461)24

"Plumline" or other equal and approved

192No15mm Hydrus chromium plated pillar tap (Code: 031465)

25

96NoAramo 10930002 MW2 dual top flush mechanism (Code: 031459)

26

"Wirquin" or other equal and approved

96No15mm Polymer volumetric rotary piston water meter27

"Precision Meters" or other equal and approved

SANITARY PLUMBING

576m50mm Pipes fixed to wall28

PVC-U soil and vent pipes

552m63mm Pipes fixed to wall29

-142-

PLUMBING AND DRAINAGE (PROVISIONAL)Bill No. 13SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 72: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

552m110mm Pipes fixed to wall30

408No50mm Bend31

Extra over PVC-U soil and vent pipes for fittings

96No50mm Rodding eye32

96No50mm Junction33

216No63mm Bend34

24No63mm Vent cowel35

72No63mm Reducing junction36

204No110mm Bend37

96No110mm Access bend38

96No110mm Pan connector39

96No110mm Vent valve (GI two way)40

12No110mm Vent cowel41

144No110mm Double junction42

192No110mm Reducing junction43

36NoWire balloon grating in top of pipe not exceeding 100mmdiameter

44

Sundries

ItemTesting waste pipe system45

Testing

WATER SUPPLIES

6 624m15mm Pipes46

Class 1 copper pipes with capillary couplings

96m42mm Pipes47

-143-

PLUMBING AND DRAINAGE (PROVISIONAL)Bill No. 13SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 73: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

2 016No15mm Elbow48

Extra over Class 1 copper pipes for capillary fittings

672No15mm Tee49

60No42mm Elbow50

96No42mm Reducing tee51

672No300mm Long flexi braided hose 52

Flexible service pipes

ItemDisinfecting water pipe and tank system53

Disinfecting

ItemTesting water pipe system54

Testing

ELECTRIC WATER HEATERS

96No

Kwikot Kwiksol direct close coupled thermosyphon solar water heating system with one 2000 x 1000 x 80mm high flat solar panel collector (Code: SOL PANEL 2B), system to include 150 Litre SOL-150-DIR round solar water heater complying with SANS 1307:2007, overall size 538mm diameter x 1035mm long with 22mm copper pipe and operating at 400kPa with 400kPa Kwikot Multi pressure control and expansion relief valve (Code: KHN3.214), 20mm draincock and 22mm insulated pipe work including two Kwikot vacuum breakers (Code: KHN4.200CX) installed on hot and cold water supply, including all necessary brackets, lagging, thermostatic mixing valve and 7 day digital geyser timer. Geyser to be positioned horizontally on roof at least 300mm higher than the Kwikot solar collector panel, all in accordance with SANS 10254:2004 and SANS 10106:2006, connected to single phase electrical power supply with isolator 1m away from connection on geyser

55

"Kwikot" or other equal and approved

-144-

PLUMBING AND DRAINAGE (PROVISIONAL)Bill No. 13SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 74: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

24No

SABS approved hose reel with 30m rubber hose, chromium plated stopcock, shut-off nozzle, gylcerine gauge and wall bracket

56

FIRE APPLIANCES ETC

24No4.5kg Carbon dioxide fire extinguisher57

WATER SUPPLIES TO FIRE APPLIANCES

120No25mm Pipes58

Black mild steel pipes

72No25mm Fittings59

Extra over black mild pipes for steel fittings

ItemTesting fire water pipe system60

Testing

PIPE INSULATION

3 600mInsulation to 15mm internal diameter pipes including couplings and fittings

61

"K-flex" or other equal and approved pipe insulation over hot water piping, including all necessary accessories as specified, with a minimum R value of 0.80 (M_2 K/W), lagged with 0.5mm

ItemProvision of as-built drawings62

AS-BUILT DRAWINGS

-145-

PLUMBING AND DRAINAGE (PROVISIONAL)Bill No. 13SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward to Summary of Section No. 2 R

Page 75: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity Rate

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 2

BILL NO. 14

NOTE: Tenderers are advised to study the specification before pricing the bill.

ELECTRICAL WORK (PROVISIONAL)

CONDUITING AND ACCESSORIES AS SPECIFIED

Conduit placed into position for casting into concrete or screed, for building or chased into concrete or brickwork and for surface mounted in ceiling, roof space, including bending, threading, jointing, short lengths, draw boxes, couplings, bends, tees and saddles, including 1.5mm² drawwire

Including all couplings, bends, t-and end -pieces, (spacer) saddles, nails etc.

Where cavity walls are encountered tenderers must allow to install deep back to back open ended or one end closed wall boxes

9 360mSupply1

20 mm diameter PVC

9 360mInstall2

1 124mSupply3

32 mm diameter PVC

1 124mInstall4

3 435mSupply5

Round conduit box as specified, placed in position for casting into concrete, building or chased into brickwork or surface mounted including locknuts and bushes 60 mm dia conduit boxes (irrespective of no. of entries)

-146-

ELECTRICAL WORK (PROVISIONAL)Bill No. 14SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 76: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

3 435mInstall6

384NoSupply7

100 x 50 x 50 mm Wall boxes as specified, placed in position for casting into concrete, building or chased into brickwork or surface mounted including locknuts and bushes

384NoInstall8

864NoSupply9

100 x 100 x 50 mm Wall boxes as specified, placed in position for casting into concrete, building or chased into brickwork or surface mounted including locknuts and bushes

864NoInstall10

CONDUCTORS

Supply and install PVC insulated copper conductors drawn into conduits, trunking or wiremesh cable trays

600/1000 V grade PVC insulated stranded copper conductors drawn in conduit

11 751mSupply11

1.5 mm2

11 751mInstall12

11 060NoSupply13

2.5 mm2

11 060NoInstall14

3 111mSupply 15

6 mm2

3 111mInstall16

-147-

ELECTRICAL WORK (PROVISIONAL)Bill No. 14SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 77: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

APPLIANCES

Appliances complete with cover plates fixed in flush/recessed boxes (included)

Dedicated Single socket Outlet 4x4

192NoSupply17

Single switched socket outlet, flush mounted in wall at 300/1200 mm AFFL, complete with 100 x 100 x 50 mm conduit box, yoke assembly & cover plate, including all PVC wiring up to distribution panel or other outlet, ECC, PVC conduit. & other consumables.

192NoInstall18

Double socket Outlet 4x4

384NoSupply19

Double switched socket outlet, flush mounted in wall at 300/1200 mm AFFL, complete with 100 x 100 x 50 mm conduit box, yoke assembly & cover plate, including all PVC wiring up to distribution panel or other outlet, ECC, PVC conduit. & other consumables.

384NoInstall20

Light Switches

16 Amp light switch (1-way), flush mounted in wall at 1200 mm AFFL, complete with 100 x 50 x 50 mm conduit box, yoke assembly & cover plate, including all PVC wiring up to distribution panel or other outlet, ECC, PVC conduit. & other consumables.

384NoSupply21

16 Ampere 250 V grade single lever one way

384NoInstall22

Isolators

-148-

ELECTRICAL WORK (PROVISIONAL)Bill No. 14SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 78: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Supply, install and connect isolator switches complete with flush mounted conduit box, conduit termination, coverplates, isolator housing /enclosure, label, final connection to equipment, complete as required & specified. Includes termination and final connection of supply cable including suitably sized cable glands onto equipment as specified.

96NoSupply23

40 Amp double pole isolator complete with coverplate & neon indicator mounted in 100 x 50 x 50 wall box on cable tray

96NoInstall24

LV DISTRIBUTION BOARDS

Supply, delivery, installation, circuit breakers, LCR units, connection and commissioning of new distribution boards complete including all metalwork, frames, sub-frames, fixtures and doors, switch-and-control gear, meters, internal outlets, internal busbars and conductors, q-bars, backboards , conduit terminations, conductor terminations (incl cable terminations), supports, labels, cable labels, legends, etc. complete as specified and required ;

96NoSupply25

U-DB (POWER)

96NoInstall26

U-DB-TELKOM

Supply, deliver and installation of the following Telkom / Data distribution boards with wooden backboards and lockable doors , complete as required including all metalwork , wiring trays , conduit and sleeve terminations , labels internal switched socket outlets , etc. as specified.

-149-

ELECTRICAL WORK (PROVISIONAL)Bill No. 14SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 79: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

96NoSupply27

Telkom / Data Distribution Board (flush) 600 x 600 x 150 with softboard inner and lockable door

96NoInstall28

96NoSupply29

Single Telkom (RJ11) outlet, flush mounted in wall at 300/1200 mm AFFL, complete with 100 x 100 x 50 mm conduit box, yoke assembly & cover plate, including steel draw wire, PVC conduit. & other consumables.

96NoInstall30

96NoSupply31

Double data (RJ45) outlet, flush mounted in wall at 300/1200 mm AFFL, complete with 100 x 100 x 50 mm conduit box, yoke assembly & cover plate, including steel draw wire, PVC conduit. & other consumables.

96NoInstall32

LUMINARES

Supply, off-load, install and connect the following approved luminaries and equipment complete with lamps, connections, jointing/butting of luminaries where required, etc. The fittings shall be installed complete with lamps, control gear, 5A plug tops and connection cables, etc.(Refer to Electrical Schedule of Luminaries)

480NoSupply33

Type A-Interior lighting

480NoInstall34

96NoSupply35

Type A-Interior lighting Emergency

-150-

ELECTRICAL WORK (PROVISIONAL)Bill No. 14SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 80: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

96NoInstall36

96NoSupply37

5A plugs - luminaires

96NoInstall38

FIRE DETECTION & ALARM INSTALLATION

12No

Addressable Fire Alarm panel with four (4) loops, complete with battery backup and capacity for 127 devices per loop and 20% spare capacity for future coverage

39

Addressable Fire Alarm Panel

Supply and installation of galvanised steel conduit using threadless fittings. No distinction made between vertical or horizontal installation. Rates to include for bending, threading, jointing, short lengths, draw boxes, couplings, bends, tees, saddles, cutting, reaming, setting, fixing, wastage, cleaning, expansion boxes etc.

Galvanised Conduits and Accessories

5 400No25mm Diameter conduit40

1 500No25mm Galvanised Sprague Complete with end box41

Galvanised steel outlet boxes complete with coverplates, including terminations etc to suit any number, size or type of entries and rates to include for fixing, recessing in brickwork or cast into concrete

Galvanised Conduit boxes

12No150 x 150 x 75mm (Fire Panel Tray)42

144No100 x 100 x 50mm with lid43

240No60mm dia round box with lid44

-151-

ELECTRICAL WORK (PROVISIONAL)Bill No. 14SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 81: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Supply and install galvanised wiremesh cable tray complete with hangers, brackets, risers, droppers, tees, bends, joints, elbows, supports, cantilever arms, unistrut channels and sections, threaded rods, bolts, fasteners (springnuts & washers) etc. required for the complete installation of the cable trays

Wireways

65m200x200x75mm Medium Duty Wiremesh Cable Tray45

4 200mDrawn into conduit (1,5mm)46

Drawwire and Fire Retardant Cabling

7 800mPH30 fire resistant cable 1,0m2 x 2-core47

48NoAddressable Manual Call point( Breakglass unit) with flap

48

Fire Detection Devices

288NoAddressable Optical detector49

96NoAddressable Heat detector (fixed)50

96NoAddressable Audible alarm51

96NoAddressable Siren/Strobe combo fire alarm52

384NoAddressable Bases for detectors53

12NoAddressable sounder base54

48NoFire Panel Batteries 12 V 12 Ah - 5LA55

Equipment

12NoNetwork card for ZP2 fire panel56

12NoProgramming of Fire panel57

12NoFire Panel Signage - Photo luminance " Fire Panel"58

12NoLogbook, logbook holder and laminated instructions59

-152-

ELECTRICAL WORK (PROVISIONAL)Bill No. 14SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 82: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

24NoFire/smoke detector interface Unit in protective wall box60

48NoLine Relays61

96NoLabelling of Audible Alarm Devices62

12NoLabelling of Overdoor Indicators63

12NoLabelling of Fire Panel Isolator64

24No24V Power Supply Units65

ItemElectrical work required for fire panel installation (isolator, wiring & circuit breaker in local DB)

66

Sundry Items

ItemTraining of Staff67

Item3 Sets of Operation & Maintenance Manuals, drawings hardcopy and one set soft copy

68

Item12 Month Maintenance Contract 69

-153-

ELECTRICAL WORK (PROVISIONAL)Bill No. 14SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward to Summary of Section No. 2 R

Page 83: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity Rate

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 2

BILL NO. 15

The Tenderer is referred to the relevant Clauses in the separate document General Preambles for Trades (2017 Edition)

PAINTWORK (PROVISIONAL)

"Plascon" or other equal and approved

PAINTWORK ETC. TO NEW WORK

ON INTERNAL FLOATED PLASTER SURFACES

14 604m2Walls1

One coat plaster primer and two coats "Double Velvet" paint

ON EXTERNAL FLOATED PLASTER SURFACES

6 552m2Walls2

One coat plaster primer and two coats "Wall and All" paint

ON SMOOTH CONCRETE SURFACES

144m2Walls3

One coat primer and two coats low odour "Cashmere" paint

4 176m2Ceilings and beams4

ON PLASTERBOARD SURFACES

1 080m2Ceilings and cornices5

One coat primer and two coats "Super Acrylic Polvin" paint

ON FIBRE-CEMENT BOARD SURFACES

-154-

PAINTWORK (PROVISIONAL)Bill No. 15SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward R

Page 84: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

204m2Ceilings and cornices, including priming metal coverstrips and nailheads

6

One coat plaster primer and two coats "Wall and All" paint

660mFascias and barge boards not exceeding 300mm girth, including priming metal jointing strips

7

720mSills, thresholds, etc not exceeding 300mm girth8

ON METAL SURFACES

1 044m2Doors and door frames, etc9

One coat alkyd based zinc phosphate primer and two coats "Cashmere" paint, on steel. Colour: to match matt charcoal (code: ANP 3055)

792m2Gates, grilles, burglar screens, balustrades, etc (bothsides measured over the full flat area)

10

ON WOOD SURFACES

1 344m2Doors and door frames, etc11

Three coats superior quality clear gloss varnish

SIGNWRITING

60NoCalibri numeral or letter 200mm high12

Primer and two coats suitable paint on plaster, metal, wood or glass

12NoCalibri numeral or letter 920mm high13

-155-

PAINTWORK (PROVISIONAL)Bill No. 15SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried Forward to Summary of Section No. 2 R

Page 85: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION SUMMARY - SECTION 2: COMMUNITY RESIDENTIAL UNITS

BillNo

PageNo

Amount

101EARTHWORKS (PROVISIONAL)1

107PILING (PROVISIONAL)2

111CONCRETE, FORMWORK AND REINFORCEMENT (PROVISIONAL)

3

114MASONRY (PROVISIONAL)4

115WATERPROOFING (PROVISIONAL)5

117ROOF COVERINGS, CLADDINGS, ETC. (PROVISIONAL)

6

121CARPENTRY AND JOINERY (PROVISIONAL)7

123CEILINGS, PARTITIONS AND ACCESS FLOORING (PROVISIONAL)

8

127IRONMONGERY (PROVISIONAL)9

131METAL WORK (PROVISIONAL)10

134PLASTERING (PROVISIONAL)11

136TILING (PROVISIONAL)12

145PLUMBING AND DRAINAGE (PROVISIONAL)13

153ELECTRICAL WORK (PROVISIONAL)14

155PAINTWORK (PROVISIONAL)15

-156-

SECTION 2: COMMUNITY RESIDENTIAL UNITSSection No. 2

Carried to Final Summary R

Page 86: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity Rate

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 3

BILL NO. 1

The Tenderer is referred to the relevant Clauses in the separate document General Preambles for Trades (2017 Edition)

EARTHWORKS (PROVISIONAL)

SUPPLEMENTARY PREAMBLES

A soils investigation has been carried out on the site by the engineer and the report is annexed to these bills of quantities. The soils report indicates that the ground varies between clayey, silty, and gravelly sand all of which will be deemed as "earth". Highly weathered, very "soft rock" was found at depth of 1300mm with possible interspersed moderately weathered medium "hard rock"

Nature of ground

No subterranean water is expected

Subterranean water

Descriptions of carting away of excavated material shall be deemed to include loading excavated material onto trucks directly from the excavations or, alternatively, from stock piles situated on the building site

Carting away of excavated material

References such as "G1", "G2", etc and "C1", "C2", etcin descriptions of filling and layer work materials refer tocorresponding references in the document "Guidelinesfor Road Construction Materials. TRH 14 : 1985"compiled by the Committee of State Road Authoritiesand the properties set out therein for each kind shall beapplicable to the respective materials describedhereinafter

Filling

-157-

EARTHWORKS (PROVISIONAL)Bill No. 1SECTION 3: BIN AREASection No. 3

Carried Forward R

Page 87: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Prices for filling are to include for all necessary densityand other tests

Testing

EXCAVATION, FILLING, ETC OTHER THAN BULK

EXCAVATIONS, ETC

16m3Trenches1

Excavation in earth not exceeding 2m deep

5m3Surplus material from excavations and/or stock piles on site, to a dumping site to be located by the contractor

2

Extra over all excavations for carting away

44m2Sides of bulk excavations not exceeding 1,5m deep3

Risk of collapse of excavations

ItemKeeping excavations free of all water other thansubterranean water

4

Keeping excavations free of water

FILLING, ETC

11m3Backfilling to trenches, holes, etc5

Earth filling obtained from the excavations and/or prescribed stock piles on site, compacted to 95% Mod AASHTO density

-158-

EARTHWORKS (PROVISIONAL)Bill No. 1SECTION 3: BIN AREASection No. 3

Carried Forward to Summary of Section No. 3 R

Page 88: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity Rate

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 3

BILL NO. 2

The Tenderer is referred to the relevant Clauses in the separate document General Preambles for Trades (2017 Edition)

CONCRETE, FORMWORK AND REINFORCEMENT (PROVISIONAL)

SUPPLEMENTARY PREAMBLES

The costs of making, storing and testing of concrete test cubes as required under clause 7 "Tests" of SABS 1200 G shall include the cost of providing cube moulds necessary for the purpose, for testing costs and for submitting reports on the tests to the principal agent. The testing shall be undertaken by an independent firm or institution nominated by the contractor to the approval of the principal agent

Cost of tests

Descriptions of formwork shall be deemed to include use and waste only (except where described as "left in" or "permanent"), for fitting together in the required forms, wedging, plumbing and fixing to true angles and surfaces as necessary to ensure easy release during stripping and for reconditioning as necessary before re-use

Formwork

The vertical strutting shall be carried down to suchconstruction as is sufficiently strong to afford the required support without damage and shall remain in position until the newly constructed work is able to support itself

Formwork to soffits of slabs, beams, etc shall be deemed to be propped up exceeding 1,5m and not exceeding 3,5m high unless otherwise described

-159-

CONCRETE, FORMWORK AND REINFORCEMENT (PRBill No. 2SECTION 3: BIN AREASection No. 3

Carried Forward R

Page 89: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Formwork to sides of bases, pile caps, ground beams, etc will only be measured where it is prescribed by the engineer for design reasons. Formwork necessitated by irregularity or collapse of excavated faces will not be measured and the cost thereof shall be deemed to be included in the allowance for taking the risk of collapse of the sides of the excavations, provision for which is made in "Earthworks"

UNREINFORCED CONCRETE CAST AGAINSTEXCAVATED SURFACES

1m3Surface blinding under footings and bases1

10MPa/19mm concrete

REINFORCED CONCRETE CAST AGAINSTEXCAVATED SURFACES

5m3Strip footings2

25MPa/19mm concrete

6NoMaking and testing 150 x 150 x 150mm concrete strength test cube (Provisional)

3

TEST CUBES

REINFORCEMENT

1tBars in various diameters4

High tensile steel reinforcement to structural concrete work

-160-

CONCRETE, FORMWORK AND REINFORCEMENT (PRBill No. 2SECTION 3: BIN AREASection No. 3

Carried Forward to Summary of Section No. 3 R

Page 90: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity Rate

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 3

BILL NO. 3

The Tenderer is referred to the relevant Clauses in the separate document General Preambles for Trades (2017 Edition)

MASONRY (PROVISIONAL)

SUPPLEMENTARY PREAMBLES

BRICKWORK

Where sizes in descriptions are given in brick units, "onebrick" shall represent the length and "half brick" the width of a brick

Sizes in descriptions

Walls in two skins described as "bagged and sealed" shall be deemed to include having the outer face of the inner skin bagged with 1:6 cement and sand mixture and sealed with two coats bitumen emulsion waterproofing coating

Bagged and sealed walls

Blocks shall be of approved manufacture, sound, wellburnt or cured and uniform and true in size, shape andcolour

DECORATIVE BLOCKS

BRICKWORK

FOUNDATIONS

25m2One brick walls1

Brickwork of NFX bricks (14 MPa nominal compressive strength) in class II mortar

SUPERSTRUCTURE

-161-

MASONRY (PROVISIONAL)Bill No. 3SECTION 3: BIN AREASection No. 3

Carried Forward R

Page 91: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

5m2Half brick walls in beamfilling2

Brickwork of NFX bricks (14 MPa nominal compressive strength) in class II mortar

63m2One brick walls3

5m2One brick walls in beamfilling4

68m2On brick walls, piers, etc5

Cement wash of 1:3 liquid cement and sand mixture applied with a brush

23m75mm Wide reinforcement built in horizontally6

2,5mm Galvanised brick reinforcement

636m150mm Wide reinforcement built in horizontally7

24No30 x 1,6mm Roof tie 1,5m long with one end built intobrickwork and other end fixed to timber

8

Galvanised hoop iron cramps, ties, etc

DECORATIVE SCREEN WALLS AND GRILLES

2m2230mm Walls pointed on both sides9

Screen walls of 150 x 150 x 115mm grille blocks with vermin proof mesh internally, bedded and jointed in class II mortar, with continuous joints in both directions and pointed with flush horizontal and vertical joints

-162-

MASONRY (PROVISIONAL)Bill No. 3SECTION 3: BIN AREASection No. 3

Carried Forward to Summary of Section No. 3 R

Page 92: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity Rate

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 3

BILL NO. 4

The Tenderer is referred to the relevant Clauses in the separate document General Preambles for Trades (2017 Edition)

WATERPROOFING (PROVISIONAL)

DAMPPROOFING OF WALLS AND FLOORS

6m2In walls1

One layer 375 micron embossed polyethylene dampproof course (SANS 952-1985 type B)

68m2On bagged brick walls2

Two coats bitumen emulsion waterproof coating

-163-

WATERPROOFING (PROVISIONAL)Bill No. 4SECTION 3: BIN AREASection No. 3

Carried Forward to Summary of Section No. 3 R

Page 93: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity Rate

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 3

BILL NO. 5

The Tenderer is referred to the relevant Clauses in the separate document General Preambles for Trades (2017 Edition)

ROOF COVERINGS, CLADDINGS, ETC (PROVISIONAL)

SUPPLEMENTARY PREAMBLES

Roof sheeting systems are to be manufactured in strict accordance with the supplier's specifications.

Corrugated metal sheeting and accessories

Fixing of all roof sheeting is to be in accordance with the manufacturer's approved instruction book.

The manufacturer shall comply with ISO9002 Quality Management System.

PROFILED METAL SHEETING AND ACCESSORIES

48m2Roof covering with pitch not exceeding 25 degrees.1

"Global Roofing Solutions" or other equal and approved, 0.53mm thick 686mm cover IBR 686 profile Supergalum AZ150 spelter G550, Egret White finish top coat and standard backing coat to other side, fixed to timber purlins (elsewhere measured) and fixed strictly in accordance with the manufacturer's instructions

-164-

ROOF COVERINGS, CLADDINGS, ETC. (PROVISIONABill No. 5SECTION 3: BIN AREASection No. 3

Carried Forward to Summary of Section No. 3 R

Page 94: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity Rate

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 3

BILL NO. 6

The Tenderer is referred to the relevant Clauses in the separate document General Preambles for Trades (2017 Edition)

CARPENTRY AND JOINERY (PROVISIONAL)

SUPPLEMENTARY PREAMBLES

Items described as "nailed" shall be deemed to be fixed with hardened steel nails or pins, or to be shot pinned, to brickwork or concrete.

Fixing

Items described as "plugged" shall be deemed to include screwing to fibre, plastic or metal plugs at not exceeding 500mm centres, and where described as "bolted", the bolts have been given elsewhere.

Descriptions of frames shall be deemed to include frames, transoms, rails, etc.

Joinery

Descriptions of hardwood joinery shall be deemed to include sinking and pelleting heads and nuts of bolts.

The Structural Design of the prefabricated (nail plated) roof trusses must be carried out by an 'Approved Competent Person', who is professionally registered withECSA, in terms of the Engineering Profession Act, 2000, (Act No. 46 of 2000). The Structural Design of the prefabricated (nail plated) roof trusses must be carried out in accordance with the requirements of the following South African National Standards : SANS 10160, SANS 10163 and SANS 10243.

PREFABRICATED TIMBER ROOF TRUSS CONSTRUCTION, ETC

-165-

CARPENTRY AND JOINERY (PROVISIONAL)Bill No. 6SECTION 3: BIN AREASection No. 3

Carried Forward R

Page 95: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

In accordance with the statutory requirements of the 'The South African National Building Regulations' - SANS 10400-A, Clause A19, the 'Approved Competent Person', who was responsible for the structural design ofthe prefabricated (nail plated) timber roof trusses, must submit a 'TR1 - Compliance and Completion Certificate' confirming the structural stability of the roof structure, to the Principle Structural Engineer (PSE), on completion of the roof truss installation.

The prefabricated (nail plated) timber roof trusses must be manufactured by an accredited ITC-SA fabricator.

A full set of 'Shop Drawings' (confirming all on-site dimensions, structural design information, truss tie down details, cross bracing details, etc), must be submitted by the Principle Building Contractor (PBC) to the Principle Structural Engineer (PSE) for review and approval, prior to any fabrication taking place.

The on-site Inspection of the installation of the prefabricated (nail plated) roof trusses must be carried out by an 'Approved Competent Person', who is professionally registered with ECSA, in terms of the Engineering Profession Act, 2000, (Act No. 46 of2000).

In accordance with the statutory requirements of the 'The South African National Building Regulations' - SANS 10400-A, Clause A19, the 'Approved Competent Person', who was responsible for the on-site Inspection of the installation of the prefabricated (nail plated) timber roof trusses, must submit a 'TR2 - Compliance and Completion Certificate' confirming the that the fabrication, installation and erection of the entire prefabricated (nail plated) timber roof structure is structurally stable and has been completed in accordance with the approved structural design drawings, to the Principle Structural Engineer (PSE), on completion of the roof truss installation

Trusses are at maximum of 1200mm centres

Roof covering is 0.53mm IBR 686 roof sheeting on purlins

-166-

CARPENTRY AND JOINERY (PROVISIONAL)Bill No. 6SECTION 3: BIN AREASection No. 3

Carried Forward R

Page 96: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

References given in descriptions refer to the respective types of trusses detailed on the architect's/engineer's drawings annexed to these bills of quantities for tender purposes

Dimensions in descriptions of trusses are nominal and actual measurements are to be obtained from the architect/ engineer and/ or taken on site before design or fabrication commences

1No

Roof construction to single pitched roof, 8.35 x 5.70m overall on plan, including trusses, jack rafters, permanent bracing and 75 x 50mm purlins at centres recommended for roof covering, splayed purlins at eaves and 38 x 114mm wall plates

1

Design, supply and install nailed roof truss system complete in accordance with the Standard Building Regulations including ring shank nails, hurricane clips at exposed sections and at ridges, temporary and permanent bracing, etc.

EAVES, VERGES, ETC

9m225 x 12mm Fascias including aluminium H-profile jointing strips

2

Medium density plain fibre-cement fascias and barge boards

20m200 x 80mm Barge boards, including aluminium H-profile jointing strips

3

-167-

CARPENTRY AND JOINERY (PROVISIONAL)Bill No. 6SECTION 3: BIN AREASection No. 3

Carried Forward to Summary of Section No. 3 R

Page 97: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity RateUnit

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 3

BILL NO. 7

The Tenderer is referred to the relevant Clauses in the separate document General Preambles for Trades (2017 Edition)

METALWORK (PROVISIONAL)

SUPPLEMENTARY PREAMBLES

Descriptions of bolts shall be deemed to include nuts and washers

Descriptions of expansion anchors and bolts and chemical anchors and bolts shall be deemed to include nuts, washers and mortices in brickwork or concrete

Items described as "holed for bolt(s)" shall be deemed to exclude the bolts unless otherwise described

Items described as "plugged" shall be deemed to include screwing to fibre, plastic or metal plugs at not exceeding 600mm centres

Descriptions of bolts, anchors, etc.

GALVANISED STEEL GATES, SCREENS, ETC

1No

Single gate 1000 x 2100mm high of 38 x 38 x 3mm hollow section frame, 2 No. x 38 x 38 x 3mm hollow section horizontal middle rails, with 40 x 40 x 3mm angle section welded vertically to frame at 84mm centres and fitted with a pair of bullet hinges welded to 50 x 50 x 3mm hollow section steel frame bolted to wall including ears for padlock and lock box. Gate to be covered with vermin proof mesh with 10mm apertures welded to back of gate frame. (Refer to Drawing No. W502)

1

Welded screens and gates fixed to brickwork

-168-

METAL WORK (PROVISIONAL)Bill No. 7SECTION 3: BIN AREASection No. 3

Carried Forward to Summary of Section No.3

R

Page 98: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity Rate

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 3

BILL NO. 8

The Tenderer is referred to the relevant Clauses in the separate document General Preambles for Trades (2017 Edition)

PLASTERING (PROVISIONAL)

INTERNAL PLASTER

62m2On walls1

Cement plaster steel trowelled, on brickwork

2m2On narrow widths2

EXTERNAL PLASTER

77m2On walls3

Cement plaster wood floated, on brickwork

2m2On narrow widths4

-169-

PLASTERING (PROVISIONAL)Bill No. 8SECTION 3: BIN AREASection No. 3

Carried Forward to Summary of Section No. 3 R

Page 99: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity Rate

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 3

BILL NO. 9

The Tenderer is referred to the relevant Clauses in the separate document General Preambles for Trades (2017 Edition)

PLUMBING AND DRAINAGE (PROVISIONAL)

SUPPLEMENTARY PREAMBLES

Descriptions of gutter outlets etc shall be deemed to include wire balloon gratings

Wire gratings

Sewer and drainage pipes and fittings shall be jointed and sealed with butyl rubber rings

Soil, waste and vent pipes and fittings shall be solvent weld jointed or sealed with butyl rubber rings

PVC-U pipes and fittings

Pipes of 50mm diameter and smaller shall be plain ended with solvent welded uPVC loose sockets and fittings

Pipes of 63mm diameter and greater shall have sockets and spigots with push-in type integral rubber ring joints. Bends shall be uPVC and all other fittings shall be cast iron, all with similar push-in type joints

PVC-U pressure pipes and fittings

-170-

PLUMBING AND DRAINAGE (PROVISIONAL)Bill No. 9SECTION 3: BIN AREASection No. 3

Carried Forward R

Page 100: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Pipes shall be hard drawn and half hard "Maksal" pipes of the class described. Class 0 (thin walled hard drawn) pipes shall not be bent. Class 1 (thin walled half hard), Class 2 (half hard) and Class 3 (heavy walled half-hard) pipes shall only be bent with benders with inner and outer formers. Fittings to copper waste, vent and anti syphon pipes, capillary solder fittings and compression fittings shall be "Cobra Watertech" or other equally and approved type. Capillary solder fittings shall comply with ISO 2016.

Copper pipes

Copper pipes are to be installed in accordance with the latest revision of the Code of Practice for Copper Plumbing soldering techniques. Flux, solder, etc to be strictly in accordance with the manufacturer's requirements with special attention to copper flux composition.

Where fittings have reducing ends or branches they are described as "reducing" and only the largest end or branch size is given.

Reducing fittings

Unless specifically otherwise stated, descriptions of pipes shall be deemed to include fixing to walls, etc, casting in, building in or suspending not exceeding 1m below suspension level.

Fixing of pipes

Pipes chased into brickwork must be wrapped with two layers of stout brown paper tied with wire. Rates are to include for wrapping around joints and fittings

Paper wrapping to pipes

Water pipework is to be disinfected at completion in accordance with SABS 1200L (provision for disinfection elsewhere)

Disinfection of water pipework

-171-

PLUMBING AND DRAINAGE (PROVISIONAL)Bill No. 9SECTION 3: BIN AREASection No. 3

Carried Forward R

Page 101: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Pipes to be taped shall be coated with the appropriateprimer and the tape shall be applied in the appropriatewidths and with 55% overlaps

"Densyl" petrolatum anti-corrosion tape as manufactured by Denso SA (Pty) Ltd.

Couplings and fittings to pipes shall be taped in strictaccordance with the manufacturer's instructions including mastic, tape, "Layflat" sheeting, securing of same, etc

Prices for wrapping of pipes shall include for all work asdescribed to couplings in the length

Pipes shall be laid and bedded in accordance withmanufacturers' instructions and trenches shall be carefully backfilled

Laying, backfilling, bedding, etc of pipes

Where no manufacturers' instructions exist, pipes shall be laid in accordance with Clauses 5.1 and 5.2 of each of the following:SABS 1200L : Medium-pressure pipelinesSABS 1200LD: SewersSABS 1200LE: Stormwater drainage

Where required, the contractor shall prepare an updatedset of as-built drawings. At completion of the contractthe contractor shall hand these drawings to the principalagent for reproducing onto the originals for handing overto the employer (provision for allowance of as-builtdrawings elsewhere)

As-built drawings

RAINWATER DISPOSAL

9m125mm Half-round roof gutters with beaded front edge1

PVC-U gutters and rainwater pipes

4m75mm Diameter rainwater pipes2

2NoExtra over gutter for stopped end3

-172-

PLUMBING AND DRAINAGE (PROVISIONAL)Bill No. 9SECTION 3: BIN AREASection No. 3

Carried Forward R

Page 102: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

1NoExtra over gutter for outlet for 75mm pipe4

1NoExtra over rainwater pipe for eaves or plinth offset5

1NoExtra over rainwater pipe for shoe6

SANITARY FITTINGS

TAPS, VALVES, ETC

1No15mm chrome plated stella washing machine tap (Code: 3309ST-15)

7

"Cobra Watertech" or other equal and approved

1No15mm brass fullway isolating ball valve with lever handle8

"Tekflo valves" or other equal and approved

1No15mm Polymer volumetric rotary piston water meter9

"Precision Meters" or other equal and approved

WATER SUPPLIES

5m15mm Pipes10

Class 1 copper pipes with capillary couplings

3No15mm Elbow11

Extra over Class 1 copper pipes for capillary fittings

ItemDisinfecting water pipe and tank system12

Disinfecting

ItemTesting water pipe system13

Testing

ItemProvision of as-built drawings14

AS-BUILT DRAWINGS

-173-

PLUMBING AND DRAINAGE (PROVISIONAL)Bill No. 9SECTION 3: BIN AREASection No. 3

Carried Forward to Summary of Section No. 3 R

Page 103: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity Rate

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 3

BILL NO. 10

NOTE: Tenderers are advised to study the specification before pricing the bill.

ELECTRICAL WORK (PROVISIONAL)

CONDUITING AND ACCESSORIES AS SPECIFIED

Conduit placed into position for casting into concrete or screed, for building or chased into concrete or brickwork and for surface mounted in ceiling, roofspace, including bending, threading, jointing, short lengths, draw boxes, couplings, bends, tees and saddles, including 1.5mm² drawwire

Including all couplings, bends, t-and end -pieces, (spacer) saddles, nails etc.

Where cavity walls are encountered tenderers must allow to install deep back to back open ended or one end closed wall boxes

59mSupply1

20 mm diameter PVC

59mInstall2

12mSupply3

Round conduit box as specified, placed in position for casting into concrete, building or chased into brickwork or surface mounted including locknuts and bushes 60mm diameter conduit boxes (irrespective of no. of entries)

12mInstall4

CONDUCTORS

-174-

ELECTRICAL WORK (PROVISIONAL)Bill No. 10SECTION 3: BIN AREASection No. 3

Carried Forward R

Page 104: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Supply and install PVC insulated copper conductors drawn into conduits, trunking or wire mesh cable trays

600/1000 V grade PVC insulated stranded copper conductors drawn in conduit

162mSupply5

1.5 mm2

162mInstall6

LUMINARIES

Supply, off-load, install and connect the following approved luminaries and equipment complete with lamps, connections , jointing/butting of luminaries where required , etc. The fittings shall be installed complete with lamps, control gear, 5A plug tops and connection cables , etc.(Refer to Electrical Schedule of Luminaries)

2NoSupply7

Type B-Exterior lighting

2NoInstall8

2NoSupply9

5A plugs - luminaries

2NoInstall10

-175-

ELECTRICAL WORK (PROVISIONAL)Bill No. 10SECTION 3: BIN AREASection No. 3

Carried Forward to Summary of Section No. 3 R

Page 105: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity Rate

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 3

BILL NO. 11

The Tenderer is referred to the relevant Clauses in the separate document General Preambles for Trades (2017 Edition)

PAINTWORK (PROVISIONAL)

"Plascon" or other equal and approved

PAINTWORK ETC. TO NEW WORK

ON INTERNAL FLOATED PLASTER SURFACES

64m2Walls1

One coat plaster primer and two coats "Double Velvet" paint

ON EXTERNAL FLOATED PLASTER SURFACES

79m2Walls2

One coat plaster primer and two coats "Wall and All" paint

ON FIBRE-CEMENT BOARD SURFACES

29mFascias and barge boards not exceeding 300mm girth, including priming metal jointing strips

3

One coat plaster primer and two coats "Wall and All" paint

ON METAL SURFACES

4m2Gates, grilles, burglar screens, balustrades, etc (bothsides measured over the full flat area)

4

One coat alkyd based zinc phosphate primer and two coats "Cashmere" paint, on steel. Colour: to match matt charcoal (code: ANP 3055)

-176-

PAINTWORK (PROVISIONAL)Bill No. 11SECTION 3: BIN AREASection No. 3

Carried Forward to Summary of Section No. 3 R

Page 106: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity Rate

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 3

BILL NO. 12

The Tenderer is referred to the relevant Clauses in the separate document General Preambles for Trades (2017 Edition)

EXTERNAL WORK (PROVISIONAL)

ROADWORK, PARKING AREAS AND PAVING

Descriptions of earth filling, compaction, etc shall be deemed to include for all necessary testing required inaccordance with the SABS 1200 series

Testing of material and filling

9m3To reduce levels under floors etc1

Excavation in earth

9m3Surplus material from excavations and/or stock piles on site, to a dumping site to be located by the contractor

2

Extra over all excavations for carting away

ItemKeeping excavations free of all water other thansubterranean water

3

Keeping excavations free of water

32m2

Compaction of ground surfaces under pavings etc, including scarifying for a depth of 150mm, breaking down oversize material, adding suitable material where necessary and compacting to 95% Mod AASHTO density

4

Compaction of surfaces

5m3Subbase course of G4 material, compacted to 97% Mod AASHTO density

5

Filling supplied by the contractor under parking areas, roadways, etc

-177-

EXTERNAL WORK (PROVISIONAL)Bill No. 12SECTION 3: BIN AREASection No. 3

Carried Forward R

Page 107: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

5m3Subbase course of G5 material, compacted to 95% Mod AASHTO density

6

3No"Modified AASHTO Density" test7

Prescribed density tests on filling

32m2

Under floors etc including forming and poisoning shallow furrows against foundation walls etc, filling in furrows and ramming

8

Soil insecticide in accordance with SANS 5859

32m225mm Thick paving to parking areas, roadways, etc including bitumen spray to base course

9

Bituminous premix road surfacing

-178-

EXTERNAL WORK (PROVISIONAL)Bill No. 12SECTION 3: BIN AREASection No. 3

Carried Forward to Summary of Section No. 3 R

Page 108: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION SUMMARY - SECTION 3: BIN AREA

BillNo

PageNo

Amount

158EARTHWORKS (PROVISIONAL)1

160

CONCRETE, FORMWORK AND REINFORCEMENT (PROVISIONAL)

2

162MASONRY (PROVISIONAL)3

163WATERPROOFING (PROVISIONAL)4

164

ROOF COVERINGS, CLADDINGS, ETC. (PROVISIONAL)

5

167CARPENTRY AND JOINERY (PROVISIONAL)6

168METAL WORK (PROVISIONAL)7

169PLASTERING (PROVISIONAL)8

173PLUMBING AND DRAINAGE (PROVISIONAL)9

175ELECTRICAL WORK (PROVISIONAL)10

176PAINTWORK (PROVISIONAL)11

178EXTERNAL WORK (PROVISIONAL)12

-179-

SECTION 3: BIN AREASection No. 3

Carried to Final Summary R

Page 109: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity Rate

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 4

BILL NO. 1

The Tenderer is referred to the relevant Clauses in the separate document General Preambles for Trades (2017 Edition)

EARTHWORKS (PROVISIONAL)

SUPPLEMENTARY PREAMBLES

A soils investigation has been carried out on the site by the engineer and the report is annexed to these bills of quantities. The soils report indicates that the ground varies between clayey, silty, and gravelly sand all of which will be deemed as "earth". Highly weathered, very "soft rock" was found at depth of 1300mm with possible interspersed moderately weathered medium "hard rock"

Nature of ground

No subterranean water is expected

Subterranean water

Descriptions of carting away of excavated material shall be deemed to include loading excavated material onto trucks directly from the excavations or, alternatively, from stock piles situated on the building site

Carting away of excavated material

References such as "G1", "G2", etc and "C1", "C2", etcin descriptions of filling and layer work materials refer tocorresponding references in the document "Guidelinesfor Road Construction Materials. TRH 14 : 1985"compiled by the Committee of State Road Authoritiesand the properties set out therein for each kind shall beapplicable to the respective materials describedhereinafter

Filling

-180-

EARTHWORKS (PROVISIONAL)Bill No. 1SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward R

Page 110: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Prices for filling are to include for all necessary densityand other tests

Testing

SITE CLEARANCE

8 670m2

Digging up and removing rubbish, debris, vegetation, hedges, shrubs, bush, etc and trees not exceeding 200mm girth

1

Site clearance

REMOVAL OF TREES ETC

1NoTree stump not exceeding 1m high, exceeding 200mmand not exceeding 500mm girth

2

Cutting down and removing, grubbing up roots andfilling in holes

BULK EXCAVATION, FILLING, ETC

EXCAVATIONS, ETC

675m3Digging up topsoil to an average depth of 150mm andpreserving for use as filling

3

Digging up topsoil

271m3Open face excavation4

Open face excavation in earth over sloping site

452m2100mm Thick reinforced concrete surface beds, paving, etc

5

Extra over bulk excavations in earth for breaking up and removing

5NoManhole overall size 3200 x 1400mm not exceeding 2m deep, including brickwork, concrete base, cover slab

6

150m

Galvanised steel / PVC / Cast iron, Clay piping exceeding 100mm and not exceeding 150mm external diameter

7

-181-

EARTHWORKS (PROVISIONAL)Bill No. 1SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward R

Page 111: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

675m3Surplus material from excavations and/or stock piles on site, to a dumping site to be located by the contractor

8

Extra over all excavations for carting away

ItemKeeping excavations free of all water other thansubterranean water

9

Keeping excavations free of water

FILLING, ETC

271m3Over site to form platforms10

Earth filling obtained from the excavations and/orprescribed stock piles on site, compacted to 95% Mod AASHTO density

1 667m3Over site to form platforms11

Filling of G7 material supplied by the contractor, compacted to 95% Mod AASHTO density

TESTS

173No"Modified AASHTO Density" test12

Prescribed density tests on filling

-182-

EARTHWORKS (PROVISIONAL)Bill No. 1SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward to Summary of Section No. 4 R

Page 112: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity RateUnit

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 4

BILL NO. 2

The Tenderer is referred to the relevant Clauses in the separate document General Preambles for Trades (2017 Edition)

METALWORK (PROVISIONAL)

SUPPLEMENTARY PREAMBLES

Descriptions of bolts shall be deemed to include nuts and washers

Descriptions of expansion anchors and bolts and chemical anchors and bolts shall be deemed to include nuts, washers and mortices in brickwork or concrete

Items described as "holed for bolt(s)" shall be deemed to exclude the bolts unless otherwise described

Items described as "plugged" shall be deemed to include screwing to fibre, plastic or metal plugs at not exceeding 600mm centres

Descriptions of bolts, anchors, etc.

GALVANISED STEEL GALVANISED STEEL BALUSTRADING AND STAINLESS STEEL HAND RAILS, ETC AND STAINLESS STEEL HAND RAILS, ETC

128m

Horizontal balustrading 1100mm high, of 50mm external diameter x 1.5mm thick continuous pipe stainless steel handrail, 50 x 8mm flat section continuous top and bottom rails, 50 x 50 x 2mm square section posts with 12mm round bar handrail connection at approximately 1200mm centres with 150 x 150 x 8mm footplates bolted to concrete with M14 bolts and 12 x 12 x 1.6mm intermediate vertical balusters at 110mm centres between top and bottom rails. (Refer to Drawing No. W503)

1

Welded balustrading to walkways

-183-

METAL WORK (PROVISIONAL)Bill No. 2SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward R

Page 113: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

282m2Gates, grilles, burglar screens, balustrades, etc (bothsides measured over the full flat area)

2

One coat alkyd based zinc phosphate primer and two coats "Cashmere" paint, on steel.

GALVANISED STEEL MINOR WORK

72No

65mm Diameter x 2.5mm x 2635mm Long galvanised mild steel hollow section drying T-Pole, formed by 65mm Diameter x 2.5mm x 800mm hollow section with ends sealed, welded centrally onto vertical post, encased in 300 x 300 x 600mm 25MPa/19mm concrete base, including 3 x 8mm diameter U-Piece eyes, 35 mm long, welded on T-Piece section (Nylon lines elsewhere measured) (Refer to Drawing No. W504)

3

Hot-dipped galvanised drying T-Pole

108No5mm Diameter x 3000mm nylon washing lines tied taut between wash lines post

4

Nylon washing lines

-184-

METAL WORK (PROVISIONAL)Bill No. 2SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward to Summary of Section No.4

R

Page 114: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity Rate

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 4

BILL NO. 3

The Tenderer is referred to the relevant Clauses in the separate document General Preambles for Trades (2017 Edition)

PLUMBING AND DRAINAGE (PROVISIONAL)

SUPPLEMENTARY PREAMBLES

Sewer and drainage pipes and fittings shall be jointed and sealed with butyl rubber rings

Soil, waste and vent pipes and fittings shall be solvent weld jointed or sealed with butyl rubber rings

PVC-U pipes and fittings

Pipes of 50mm diameter and smaller shall be plain ended with solvent welded PVC-U loose sockets and fittings

Pipes of 63mm diameter and greater shall have sockets and spigots with push-in type integral rubber ring joints. Bends shall be PVC-U and all other fittings shall be cast iron, all with similar push-in type joints

PVC-U pressure pipes and fittings

Pipes shall be type IV and of the class specified with compression fittings

High density polyethylene (HDPe) pipes and fittings

Where fittings have reducing ends or branches they are described as "reducing" and only the largest end or branch size is given. Should the contractor wish to use other fittings and bushes or reducers he may do so on the understanding that no claim in this regard will be entertained

Reducing fittings

-185-

PLUMBING AND DRAINAGE (PROVISIONAL)Bill No. 3SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward R

Page 115: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Unless specifically otherwise stated, descriptions of pipes shall be deemed to include fixing to walls, etc, casting in, building in or suspending not exceeding 1m below suspension level

Fixing of pipes

Pipes shall be laid and bedded in accordance withmanufacturers' instructions and trenches shall becarefully backfilled

Laying, backfilling, bedding, etc of pipes

Where no manufacturers' instructions exist, pipes shallbe laid in accordance with the relevant section of SANS 2001

Descriptions of pipes laid in and including trenches andof inspection chambers, catchpits, etc shall be deemed to include excavation, bedding, backfilling, compaction to a minimum of 90% Mod AASHTO density and disposal of surplus material on site

General

Where required, the contractor shall prepare an updated set of as built drawings. At completion of the contract the contractor shall hand these drawings to the Principal Agent for reproducing onto the originals for handing over to the employer (provision for allowance of as-built drawings elsewhere).

As built drawings

470m3Excavation in earth not exceeding 1m deep for pipe trenches

1

STORMWATER DRAINAGE

358m3Excavation in earth exceeding 1m and not exceeding 2m deep for pipe trenches

2

382m3

Extra over pipe excavations for carting away of surplus material from excavations and/or stock piles on site, to a dumping site to be located by the contractor

3

-186-

PLUMBING AND DRAINAGE (PROVISIONAL)Bill No. 3SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward R

Page 116: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

446m3

Backfilling to pipe trenches with earth filling obtained from the excavations and/or prescribed stock piles on site, compacted to 90% Mod AASHTO density

4

382m3

Selected imported G7 earth filling supplied by the Contractor under and filling around pipes, compacted to 90% Mod AASHTO density

5

52m450mm Diameter pipes laid in trenches6

Class 75D concrete pipes with spigot and socket joints with rubber rings (excavations, backfilling, bedding, etc. elsewhere measured)

401m110mm Diameter pipes laid in trenches7

Heavy duty (Class 34) PVC-U stormwater pipes (excavations, backfilling, bedding, etc. elsewhere measured)

285m160mm Diameter pipes laid in trenches8

137m300mm Diameter pipes laid in trenches9

17No110mm Bend10

Extra over heavy duty (Class 34) PVC-U stormwater pipes for fittings

49No110mm Junction11

16No110mm Double junction12

15No110mm Rodding eye13

24No160mm Reducing junction14

4No300mm Reducing junction15

84No

Excavate for and construct brick rainwater sump size 400 x 400mm internally not exceeding 1m deep to invert level, as detailed on drawing no. 007-C-SW-DET-1, attached to these Bills of Quantities

16

Sumps, catchpits, inspection chambers, etc including concrete kerbs or precast concrete cover slabs (covers, gratings, etc. separately measured)

-187-

PLUMBING AND DRAINAGE (PROVISIONAL)Bill No. 3SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward R

Page 117: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

14No

Excavate for and construct brick inspection chamber size 600 x 600mm internally not exceeding 1m deep to invert level, formed of one brick walls plastered internally set on 150mm thick concrete base graded to falls including concrete benching, as detailed on drawing no. 007-C-SW-DET-1, attached to these Bills of Quantities

17

1No

Excavate for and construct brick inspection chamber size 600 x 600mm internally exceeding 1m and not exceeding 2m deep to invert level, formed of one brick walls plastered internally set on 150mm thick concrete base graded to falls including concrete benching, as detailed on drawing no. 007-C-SW-DET-1, attached to these Bills of Quantities

18

1No

Excavate for and construct brick inspection chamber size 600 x 600mm internally not exceeding 1m deep to invert level, formed of one brick walls plastered internally, the lower portion increased to 1000 x 1000mm internally formed of one brick walls as before, with a 150mm thick reinforced concrete reducer slab, set on 150mm thick concrete base graded to falls including concrete benching, as detailed on drawing no. 007-C-SW-DET-1, attached to these Bills of Quantities

19

2No

Excavate for and construct brick inspection chamber size 600 x 600mm internally exceeding 1m and not exceeding 2m deep to invert level, formed of one brick walls plastered internally, the lower portion increased to 1000 x 1000mm internally formed of one brick walls as before, with a 150mm thick reinforced concrete reducer slab, set on 150mm thick concrete base graded to falls including concrete benching, as detailed on drawing no. 007-C-SW-DET-1, attached to these Bills of Quantities

20

Cast iron gratings, covers, etc.

84No450 x 450mm x 65kg Light duty cast iron square dish grating and frame (Code: 16035 and 16036)

21

"Saint Gobain" or other equal and approved

4No450 x 600mm x 102kg Heavy duty cast iron stormwater grating and frame (Code: 16059 and 16060)

22

11No600 x 600mm x 52kg Medium duty square single seal cast iron cover and frame (Code: 15874 and 15875)

23

-188-

PLUMBING AND DRAINAGE (PROVISIONAL)Bill No. 3SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward R

Page 118: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

3No

550mm Diameter x 33kg Type 4A medium duty cast iron single seal manhole cover and frame (Code: 15905 and 15906)

24

1NoLifting-key for manhole cover (handed to employer)25

Item

Allow for testing the whole of the stormwater drainage installation to the satisfaction of the Principal Agent and Local Authorities. All defective work is to be taken out and replaced at the Contractor's expense and the whole re-tested until found satisfactory.

26

Testing

Item

Cutting into side of existing inspection chamber for and connecting new stormwater 450mm diameter concrete pipe including making good concrete benching

27

Connection

341m3Excavation in earth not exceeding 1m deep for pipe trenches

28

SOIL DRAINAGE

278m3Excavation in earth exceeding 1m and not exceeding 2m deep for pipe trenches

29

262m3

Extra over pipe excavations for carting away of surplus material from excavations and/or stock piles on site, to a dumping site to be located by the contractor

30

362m3

Backfilling to pipe trenches with earth filling obtained from the excavations and/or prescribed stock piles on site, compacted to 90% Mod AASHTO density

31

262m3

Selected imported G7 earth filling supplied by the Contractor under and filling around pipes, compacted to 90% Mod AASHTO density

32

186m110mm pipe laid in trenches 33

Heavy Duty (Class 34) uPVC sewer pipes in "Class B" bedding (excavations, backfilling, bedding, etc. elsewhere measured)

452m160mm pipe laid in trenches34

-189-

PLUMBING AND DRAINAGE (PROVISIONAL)Bill No. 3SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward R

Page 119: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

48No110mm Reducing junction35

Extra over Heavy Duty (Class 34) uPVC pipe for fittings

3No160mm Bends36

7No160mm Junction37

44No160mm Reducing junction38

17No

160mm rodding eyes set in 500 x 500 x 300mm thick 25MPa/19 unreinforced concrete surround, finished smooth on exposed surfaces with rounded angles (Refer to Drawing No. 007-C-SEW)

39

Rodding eyes

24No110mm Gulley not exceeding 500mm deep including precast concrete surround

40

uPVC gulleys

12No

Excavate for and construct precast concrete circular inspection chamber size 750mm diameter internally not exceeding 1m deep to invert level, formed of precast concrete rings, the lower portion increased to 1000mm diameter internally formed of precast concrete rings as before, including HDPE steps at 300mm centres, with a 150mm thick reinforced concrete reducer slab, set on 150mm thick concrete base graded to falls including concrete benching (Refer to Drawing No. 007-C-SEW)

41

Precast concrete circular inspection chambers including precast concrete cover slabs (covers and frames elsewhere) and channels in benching

-190-

PLUMBING AND DRAINAGE (PROVISIONAL)Bill No. 3SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward R

Page 120: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

5No

Excavate for and construct precast concrete circular inspection chamber size 750mm diameter internally exceeding 1m and not exceeding 2m deep to invert level, formed of precast concrete rings, the lower portion increased to 1000mm diameter internally formed of precast concrete rings as before, including HDPE steps at 300mm centres, with a 150mm thick reinforced concrete reducer slab, set on 150mm thick concrete base graded to falls including concrete benching (Refer to Drawing No. 007-C-SEW)

42

19No

600mm diameter x 42kg Type 4A heavy duty cast iron single seal manhole cover and frame (Refer to Drawing No. 007-C-SEW)

43

Covers and frames, etc.

Item

Allow for testing the whole of the soil drainage installation to the satisfaction of the Principal Agent and Local Authorities. All defective work is to be taken out and replaced at the Contractor's expense and the whole re-tested until found satisfactory.

44

Testing

Item

Cutting into side of existing inspection chamber for and connecting new sewer pipe including making good concrete benching

45

Connection

WATER SUPPLIES

684m3Excavation not exceeding 2m deep for pipe trenches46

Earthworks

126m3

Extra over excavation for pipe trenches, etc. for carting away surplus material to a dumping site to be located by the Contractor

47

503m3

Backfilling to pipe trenches with selected material to pipe trenches around pipes compacted to 90% Mod. AASHTO density

48

-191-

PLUMBING AND DRAINAGE (PROVISIONAL)Bill No. 3SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward R

Page 121: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

126m3''Class C'' bedding supplied by the Contractor in bedding under pipes

49

55m15mm Pipes laid in trenches50

Class 16 HDPE pipes

309m32mm Pipes laid in trenches51

321m75mm Pipes laid in trenches52

4No15mm Elbow53

Extra over HDPE for fittings

5No15mm Tee54

12No32mm Elbow55

12No32mm Reducing tee56

12No75mm Elbow57

4No75mm End cap58

6No75mm Tee59

12No75mm Reducing tee60

3No75mm Gate valve to S.A.B.S 56461

Taps, valves, etc.

2No75mm Non-return valve to HDPE pipes62

12No

42mm Polymer volumetric rotary piston water meter (Code: ASM LXHS) and joint to HDPE pipe with and including necessary adaptors

63

"Precision Meters" or other equal and approved

3NoValve chamber 1,0m diameter and not exceeding 1,0m deep internally including heavy duty cover and frame

64

Valve chambers, etc.

-192-

PLUMBING AND DRAINAGE (PROVISIONAL)Bill No. 3SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward R

Page 122: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

3m3Extra over backfilling to chambers, etc. for earth backfilling supplied by the Contractor

65

4m3Unreinforced concrete in thrust blocks at bends, tees, etc. including necessary extra excavation, formwork, etc

66

Sundries

ItemDisinfecting water pipe and tank system67

Disinfecting

25 000.00ItemProvide the sum of R 25 000.00 (Twenty Five Thousand Rand) for municipal connection

68

Municipal connection

ItemProfit69

ItemTesting water pipe system70

Testing

WATER SUPPLIES TO FIRE APPLIANCES

6No

Standard hydrant with steel fittings including 102mm riser, 102mm Duckfoot bend on 300 x 300 x 100mm concrete bed, etc. complete. Refer to Engineers drawing 007-C-HYDRANT

71

Fire hydrant

Water supply to fire appliances

349m3Excavation not exceeding 2m deep for pipe trenches72

Earthworks

70m3

Extra over excavation for pipe trenches, etc. for carting away surplus material to a dumping site to be located by the Contractor

73

202m3Backfilling to pipe trenches with selected material compacted to 90% Mod. AASHTO density

74

70m3''Class C'' bedding supplied by the Contractor in bedding under pipes

75

-193-

PLUMBING AND DRAINAGE (PROVISIONAL)Bill No. 3SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward R

Page 123: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

349m50mm Pipes laid in trenches 76

Class 16 HDPE pipes

4No50mm Elbow77

Extra over HDPE pipes for fittings

3No50mm Double tee78

2No50mm Gate valve to S.A.B.S 56479

Taps, valves, etc.

2m50mm Non-return Valve80

6No

Unreinforced concrete 25Mpa/19mm stone hydrant pedestal 1200mm high cast around 76mm diameter vertical pipe with bottom 300mm below ground level, 300 x 300mm square at base and tapering to octagonal shaped top 200 x 200mm overall including excavation, formwork, etc and two coats of approved paint on exposed surfaces

81

Sundries

2m3Unreinforced concrete in thrust blocks at bends, tees, etc. including necessary extra excavation, formwork, etc

82

12No500 x 500 x 700mm Anchor block, concrete hydrant pedestal painted, etc

83

6NoMarker posts 1350mm high as detailed84

25 000.00ItemProvide the sum of R 25 000.00 (Twenty Five Thousand Rand) for municipal connection

85

Municipal connection

ItemProfit86

ItemTesting fire water pipe system87

Testing

-194-

PLUMBING AND DRAINAGE (PROVISIONAL)Bill No. 3SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward to Summary of Section No. 4 R

Page 124: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity Rate

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 4

BILL NO. 4

NOTE: Tenderers are advised to study the specification before pricing the bill.

ELECTRICAL WORK (PROVISIONAL)

400 000.00ItemProvide the sum of R 400 000.00 (Four Hundred Thousand Rand) for municipal connection

1

MUNICIPAL CONNECTION

ItemProfit2

CONDUCTORS

Deliver and install 600/1000V PVC SWA PVC cables with stranded copper conductors

1 590mSupply3

10 mm2 2 C ECC

1 590mInstall4

252mSupply5

16 mm2 4 C ECC

252mInstall6

CABLE TERMINATIONS

For ECC / PVC / SWA / PVC cables, including armour glands, shrouds, lugs, connections, insulation tape, cadmium plated bolts, nuts, springwashers, etc including connections and commissioning

600/1000 V grade PVC insulated stranded copper conductors drawn in conduit

-195-

ELECTRICAL WORK (PROVISIONAL)Bill No. 4SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward R

Page 125: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

12mSupply7

10 mm² 2-core

12mInstall8

1NoSupply9

16 mm² 2-core

1NoInstall10

LV DISTRIBUTION BOARDS

13NoSupply11

Supply, delivery, installation, connection and commissioning of new distribution boards complete including all metalwork, frames, sub-frames, fixtures and doors, switch-and-control gear, meters, internal outlets, internal busbars and conductors, q-bars, backboards, conduit terminations, conductor terminations (incl cable terminations), supports, labels, cable labels, legends, etc. complete as specified and required

13NoInstall12

Distribution Kiosks

1NoSupply13

Supply, delivery, installation, connection and commissioning of new distribution kiosk complete including all metalwork, frames, sub-frames, fixtures and doors, switch-and-control gear, meters, internal outlets, internal busbars and conductors, q-bars, backboards, conduit terminations, conductor terminations (incl cable terminations), supports, labels, cable labels, legends, etc. complete as specified and required

1NoInstall14

Telecom Distribution Board

-196-

ELECTRICAL WORK (PROVISIONAL)Bill No. 4SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward R

Page 126: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

13NoSupply15

Supply, delivery, installation, connection and commissioning of new telecoms distribution board. complete including all metalwork, frames, sub-frames, fixtures and doors, switch-and-control gear, meters, internal outlets, internal busbars and conductors, q-bars, backboards, conduit terminations, conductor terminations (incl cable terminations), supports, labels, cable labels, legends, etc. complete as specified and required

13NoInstall16

Bulk Services

1NoSupply17

400V LV Isolation point box (complete)

1NoInstall18

EARTHING INSTALLATION

ItemSpecification and drawings19

Supply and install main earthing installation complete with all necessary equipment e.g. earth meats, electrodes, copper conductors, cadweld connections, drawboxes, terminations on main earth bar etc, to comply with Supply Authority requirements,

ItemBonding of taps, hand wash basins and HWC20

ItemBonding of gutters and downpipes21

ItemEarthing continuity tests22

Item

Testing and commissioning of Main Earthing Installation to the satisfaction of the Supply Authority (including earth resistance tests)

23

ItemSupply and Install Lightning Protection (Design by specialist)

24

-197-

ELECTRICAL WORK (PROVISIONAL)Bill No. 4SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward R

Page 127: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Item

This installation includes for the carrying out of the required soil survey on site, the issuing of the test report, the design of the required system (if required) in accordance with SABS, the supply and installation of the design for system.

25

Telkom / Data Distribution Board (flush) 600 x 600 x 150 with softboard inner and lockable door

All prices below includes the excavation of trenches and holes, seperating of stones and soil, rocks, etc. levelling of trench beds, back-filling, compacting and reparation of all surfaces to the original finish.

EXCAVATIONS

Excavate for cable and sleeve trench including temporary support of sides, keeping excavations dry, backfilling and compacting to the Engineer's specification and includes PVC warning tape

Trenching shall be calculated using the formula below

(0.75 mm deep x 0.45 mm wide x length of trench)

147m3Excavate in soft ground, backfill and compact to MOD AASHTO 95%

26

8m3Excavate in soft rock, backfill and compact to MOD AASHTO 95%

27

8m3Excavate in hard rock, backfill and compact to MOD AASHTO 95%

28

110NoSupply29

Concrete cable markers complete with properly secured inscription plate with inspection as indicated by the Engineer

110NoInstall30

490m50MPA concrete screed over L.V. cable in trenches (antitheft)

31

Sleeves

-198-

ELECTRICAL WORK (PROVISIONAL)Bill No. 4SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward R

Page 128: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

PVC cable sleeves to be installed at road crossings and entrance to DB's in buildings and as per drawings

1 440NoSupply32

110mm PVC Sleeve+fittings

1 440NoInstall33

2 621NoSupply34

50mm PVC Sleeves+fittings

2 621NoInstall35

CONDUITING AND ACCESSORIES AS SPECIFIED

Conduit placed into position for casting into concrete or screed, for building or chased into concrete or brickwork and for surface mounted in ceiling, roofspace, including bending, threading, jointing, short lengths, draw boxes, couplings, bends, tees and saddles, including 1.5mm² drawwire

Including all couplings,bends, t-and end -pieces, (spacer) saddles, nails etc.

1 463mSupply36

20 mm diameter PVC

1 463mInstall37

488mSupply38

Round conduit box as specified, placed in position for casting into concrete, building or chased into brickwork or surface mounted including locknuts and bushes 60mm diameter conduit boxes (irrespective of the no. of entries)

488mInstall39

CONDUCTORS

-199-

ELECTRICAL WORK (PROVISIONAL)Bill No. 4SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward R

Page 129: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

Supply and install PVC insulated copper conductors drawn into conduits, trunking or wire mesh cable trays

600/1000 V grade PVC insulated stranded copper conductors drawn in conduit

3 834mSupply40

1.5 mm2

3 834mInstall41

144NoSupply42

2.5 mm2

144NoInstall43

Airdac Cable to units from MDB of Block

2 184mSupply44

10 mm2

2 184mInstall45

LUMINARIES

Supply, off-load, install and connect the following approved luminaries and equipment complete with lamps, connections, jointing/butting of luminaries where required, etc. The fittings shall be installed complete with lamps, control gear, 5A plug tops and connection cables, etc.(Refer to Electrical Schedule of Luminaries)

12NoSupply46

Type B-Exterior Emergency lighting

12NoInstall47

16NoSupply48

Type C-LED Flood lighting (Parking)

-200-

ELECTRICAL WORK (PROVISIONAL)Bill No. 4SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward R

Page 130: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

16NoInstall49

28NoSupply50

5A plugs - luminaries

28mInstall51

13NoSupply52

Weatherproof Photocell

13NoInstall53

-201-

ELECTRICAL WORK (PROVISIONAL)Bill No. 4SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward to Summary of Section No. 4 R

Page 131: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AmountItemNo

Quantity Rate

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION NO. 4

BILL NO. 5

The Tenderer is referred to the relevant Clauses in the separate document Model Preambles for Trades (2008 Edition)

EXTERNAL WORKS (PROVISIONAL)

RETAINING STRUCTURES

120m3To embankment behind retaining blocks including trimming to slope

1

Open face excavation in earth

90m3Trenches2

Excavation in earth not exceeding 2m deep

40m3Surplus material from excavations and/or stock piles on site to a dumping site to be located by the Contractor.

3

Extra over all excavations for carting away

240m2Sides of trench and hole excavations not exceeding 1,5m deep

4

Risk of collapse of excavations

ItemKeeping excavations free of all water other than subterranean water.

5

Keeping excavations free of water

120m3Backfilling behind retaining walls6

Earth filling obtained from the excavations and/or prescribed stock piles on site compacted to 90% Mod AASHTO density

50m3Backfilling behind retaining walls7

Filling of G7 material supplied by the contractor, compacted to 95% Mod AASHTO density

-202-

EXTERNAL WORK (PROVISIONAL)Bill No. 5SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward R

Page 132: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

420m2To bottoms and sides of trenches, etc.8

Soil insecticide

227m2Type "U24 Kaymat" filter blanket vertically behind retaining structures

9

Filter fabric

54m3Strip footings (bottom only cast against excavated surfaces)

10

25MPa/19mm concrete

30NoMaking and testing 150 x 150 x 150mm concrete strength test cube.

11

Test Blocks

227m2

Retaining structures with stepped face and curves as required to suit slopes, of 490 x 470 x 180mm high type "Terrace Block TB 490" interlocking blocks laid with horizontal bed joints to 75 degree slope, including average 150mm thick compacted earth filling behind the blocks

12

"Loffelstein" precast concrete interlocking blocks finished smooth on exposed surfaces

240m

110mm ''Cordrain'' slotted agricultural pipes behind retaining wall including 19mm crushed stone encasing size 300 x 300mm and ''Bidum U 14'' geofabric filter blanket wrapped around encasing with 150mm side and 150mm end laps including stitching

13

Sub-soil drainage

30NoExtra for 110mm capped end14

12NoExtra for 110mm bend15

ROADWORK, PARKING AREAS AND PAVING

-203-

EXTERNAL WORK (PROVISIONAL)Bill No. 5SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward R

Page 133: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

1 423m3To reduce levels and dispose in prescribed stock piles on site

16

Excavation in earth not exceeding 2m below reduced level

1 423m3Surplus material from excavations and/or stock piles onsite to a dumping site to be located by the contractor

17

Extra over all excavations for carting away

ItemKeeping excavations free of water other thansubterranean water

18

Keeping excavations free of water

2 372m2

Compaction of ground surfaces under floors etc including scarifying for a depth of 150mm, breaking down oversize material, adding suitable material where necessary and compacting to 95% Mod. AASHTO density

19

Compaction of surfaces

2 372m2

Under floors, etc. including forming and poisoning shallow furrows against foundation walls, etc., filling in furrows and ramming

20

Soil insecticide in accordance with SANS 5859

Layerworks

356m3150mm High imported G2 material compacted to 100% Mod. AASHTO density

21

Filling supplied by the contractor under parking areas, roadways, etc

356m3150mm High imported G5 material compacted to 95% Mod. AASHTO density

22

356m3150mm high imported G7 material, compacted to 93% Mod AASHTO density

23

356m3150mm High imported G9 material compacted to 93% Mod. AASHTO density

24

-204-

EXTERNAL WORK (PROVISIONAL)Bill No. 5SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward R

Page 134: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

50No"Modified AASHTO Density" test25

Prescribed density tests on filling

273m2

30mm Thick ashphalt surfacing continuously graded 5.5% 40/50 penetration bitumen compacted to 96% Marshal Density to parking and delivery areas, etc.

26

Bituminous premix road surfacing

2 099m2To parking areas, etc27

340 x 400 x 95m thick Grass blocks laid to falls on and including 25mm thick sand layer with joints filled in with sand, compacted with a vibration compactor

415m

120 x 230mm High kerbs (Figure 6) laid on 20mm mortar with 150 x 150 x 300mm unreinforced concrete haunching at back of each joint, including excavation, backfilling, etc

28

Precast concrete finished smooth on exposed surfaces, including bedding, jointing and pointing

FENCING

400m

Design, supply and install security palisade fence comprising of 102 x 44 x 3mm steel post 2725mm high, 40 x 40 x 4mm horizontal top and bottom rail and 40 x 40 x 3mm pointed and angle sections at 260mm centres. Post to be embedded 625mm in 450 x 450mm 25 MPa concrete base, all in accordance with manufactures recommendations

29

Galvanised steel palisade fence with posts, gates, etc including galvanised steel post clamps, fishplates, bolts, nuts, etc,

1No

Single gate 1000 x 2100mm high of 38 x 38 x 3mm hollow section frame, 2 No. x 38 x 38 x 3mm hollow section horizontal middle rails, with 40 x 40 x 3mm angle section welded vertically to frame at 84mm centres and fitted with ears for padlock and pair of bullet hinges welded to 50 x 50 x 3mm hollow section steel post with welded end plates encased in 300 x 300 x 600mm 25MPa/19mm concrete base. (Refer to Drawing No. W502)

30

-205-

EXTERNAL WORK (PROVISIONAL)Bill No. 5SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward R

Page 135: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

1No

Double gate 6000 x 2100mm high, each leaf of 75 x 75 x 3mm hollow section top and side rails, 75 x 100 x 3mm bottom rail, 2No. x 75 x 75 x 3mm hollow section horizontal middle rails, with 40 x 40 x 3mm angle sectionwelded vertically to frame at 84mm centres and fitted with ears for padlock in lock box and drop bolt welded on each leaf with keep in concrete. Gates to be fitted with a pair of suitable bullet hinges welded to 200 x 200 x 4.5mm hollow section steel post with welded end plate encased in 600 x 600 x 600mm 25MPa/19mm concrete base.(Refer to Drawing No. W502)

31

284m2Gates, grilles, burglar screens, balustrades, etc (bothsides measured over the full flat area)

32

One coat alkyd based zinc phosphate primer and two coats "Cashmere" paint, on steel.

APRONS, V-DRAINS, ETC

13m3

Not exceeding 2m deep over site between buildings, retaining walls, etc to reduce levels and dispose inprescribed stock piles on site

33

Excavation in earth

13m3Surplus material from excavations and/or stock piles on site, to a dumping site to be located by the contractor

34

Extra over all excavations for carting away

ItemKeeping excavations free of all water other thansubterranean water

35

Keeping excavations free of water

84m2

Compaction of ground surface under floors etc including scarifying for a depth of 200mm, breaking down oversize material, adding suitable material where necessary and compacting to 95% Mod AASHTO density

36

Compaction of surfaces

-206-

EXTERNAL WORK (PROVISIONAL)Bill No. 5SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward R

Page 136: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

84m2

Under floors etc including forming and poisoning shallow furrows against foundation walls etc, filling in furrows and ramming

37

Soil insecticide in accordance with SANS 5859

2No"Modified AASHTO Density" test38

Prescribed density tests on filling

13m3Surface beds cast in panels39

25MPa/19mm concrete

6NoMaking and testing 150 x 150 x 150mm concrete strength test cube (Provisional)

40

Test cubes

84m2Surface beds, slabs, etc41

Finishing top surfaces of concrete smooth with a wood float

119mEdges, risers, ends and reveals not exceeding 300mm high or wide

42

Rough formwork to sides

79m25 x 25mm Chamfers along top or bottom edges43

Boxing in smooth formwork to form

78mNot exceeding 300mm high to edges of surface beds44

Expansion joints with 10mm closed cell expandedpolyethylene between vertical concrete and bricksurfaces

98m2Type 193 fabric reinforcement in concrete surface beds etc

45

Fabric reinforcement

-207-

EXTERNAL WORK (PROVISIONAL)Bill No. 5SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward R

Page 137: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

Brought Forward R

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

108m2Under surface beds46

One layer 250 micron green polyethylene waterproofsheeting (SANS 952-1985 type C) sealed at laps with PVC self-adhesive tape

78m10 x 10mm In expansion joints in floors including raking out expansion joint filler as necessary

47

"Dow Corning 813C" or other equal and approved, silicone sealing compound including backing cord,bond breaker, primer, etc

-208-

EXTERNAL WORK (PROVISIONAL)Bill No. 5SECTION 4: EXTERNAL WORKSSection No. 4

Carried Forward to Summary of Section No. 4 R

Page 138: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

SECTION SUMMARY - SECTION 4: EXTERNAL WORKS

BillNo

PageNo

Amount

182EARTHWORKS (PROVISIONAL)1

184METAL WORK (PROVISIONAL)2

194PLUMBING AND DRAINAGE (PROVISIONAL)3

201ELECTRICAL WORK (PROVISIONAL)4

208EXTERNAL WORK (PROVISIONAL)5

-209-

SECTION 4: EXTERNAL WORKSSection No. 4

Carried to Final Summary R

Page 139: SECTION NO. 1 BILL NO. 1 PRELIMINARIES

AT GLEBELANDS, UMLAZI

96 NEW COMMUNITY RESIDENTIAL UNITS

1H-48138

PageNo

FINAL SUMMARY

SectionNo

Amount

98SECTION 1: PRELIMINARIES1

156SECTION 2: COMMUNITY RESIDENTIAL UNITS2

179SECTION 3: BIN AREA3

209SECTION 4: EXTERNAL WORKS4

RSUB-TOTAL

2 000 000.00ItemADD: CONTINGENCY TO THE SUB-TOTAL ABOVE

RSUB-TOTAL

RADD: VAT @ 15% OF THE SUB-TOTAL ABOVE

-210-

Carried to Form of Offer and Acceptance R