15 May 98 Worldwide CNS/ATM Conference Rio de Janeiro, Brazil Successful CNS/ATM Project Implementation: Human Resource and Training Needs Dr. Frank T. Ruggiero Project Director FANS Stakeholders’ Group IATA Headquarters, Montreal, Quebec [email protected]

Upload: phylicia-fauna

Post on 01-Jan-2016

65 views

Category:

Documents


0 download

DESCRIPTION

Successful CNS/ATM Project Implementation: Human Resource and Training Needs Dr. Frank T. Ruggiero Project Director FANS Stakeholders’ Group IATA Headquarters, Montreal, Quebec [email protected]. Work Systems. Training. Human Factors. Work Systems. Operations. CNS/ATM Success Factors. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: CNS/ATM Success Factors

15 May 98 Worldwide CNS/ATM Conference Rio de Janeiro, Brazil

Successful CNS/ATM Project Implementation: Human Resource and Training Needs

Dr. Frank T. Ruggiero

Project DirectorFANS Stakeholders’ Group

IATA Headquarters, Montreal, Quebec [email protected]

Successful CNS/ATM Project Implementation: Human Resource and Training Needs

Dr. Frank T. Ruggiero

Project DirectorFANS Stakeholders’ Group

IATA Headquarters, Montreal, Quebec [email protected]

Page 2: CNS/ATM Success Factors

15 May 98 Worldwide CNS/ATM Conference Rio de Janeiro, Brazil

CNS/ATM Success FactorsCNS/ATM Success Factors

Plann ing Project O pe ration sDevelopm ent

Approval

M anagem ent

National Im plem entationGlobal

Regional

ANPp

Transition

M aintenance

ANPp

Page 3: CNS/ATM Success Factors

15 May 98 Worldwide CNS/ATM Conference Rio de Janeiro, Brazil

Satisfying Regional Differences while Maintaining Interoperability with Global Approach

Cost-benefit & Business Case for adopting FANS, CNS/ATM elements for all stakeholders’

Need for “implementation orientated” regional coalitions for achieving real progress

Team-Centered, Human Resources Management, Planning & Training

Plan and manage full system life-cycle solution

Planning for Success: Lessons from 5 Years of ProjectsPlanning for Success: Lessons from 5 Years of Projects

Page 4: CNS/ATM Success Factors

15 May 98 Worldwide CNS/ATM Conference Rio de Janeiro, Brazil

Focus on Technical System Component DesignFocus on Technical System Component Design

Page 5: CNS/ATM Success Factors

15 May 98 Worldwide CNS/ATM Conference Rio de Janeiro, Brazil

(RNP 5) Basic RNAV ‘98 / 8.33 kHz VHF ‘99 / (RNP 1) Data Link Comm ‘01

(RNP 10) ‘98/

ADS-A, RNP-4 CPDLC ‘03

(RNP 10) ‘98/

ADS-A, RNP-4 CPDLC ‘03

Reduced Vertical Separation Minimums (RVSM) ‘98

Focus on Technical System Component DesignFocus on Technical System Component Design

Page 6: CNS/ATM Success Factors

15 May 98 Worldwide CNS/ATM Conference Rio de Janeiro, Brazil

Rqmt PlanningDocuments

TechnicalDocuments

CarriageDocuments

PotentialSolutions

Dates/ Confidence

8.33 kHzVHF

ICAO COM/DIV-Apr 95MNC Statement

SARPs Annex 10EUROCAE MOPS ED23BRTCA MOPS, DO-186A

Eurocontrol 8.33Implementation Plan,8.33 kHz User GuideAIC IFR 6/96 (Ger)

See Radio SlideUHF alternative

Eur - Jan 99(High)

VHF DLACARS,Mode 2(AVPAC),Mode 3(TDMA)

ICAO COM/DIV-Apr 95NAS Arch Plan

Draft VDL SARPsARINC 716-9, 750-1TDMA draft MASPsMode 2 draft MOPS

CONUS TDMA -2004-2010(Low)Europe Mode 2~2005 (Low)

HFDL ICAO AMCP/4Mar 96

Draft SARPs, to be completedlate 97ARINC 753, 635, 634Draft MASPs and MOPS, to becompleted late 97

ARC-190/CP2024B Pacific 2003-2005(Med-High)NAT >2000(Low-Med)

SATCOM ATS SR&OIPACG/9FAA/JCABStrategic OceanicPlan

AMSS SARPs, Annex 10ARINC Char 741RTCA DO-210C,215A,222FAA Notice N8110.58

ICAO Annex 11proposal

Aero-HAero-IUHF SATCOM (?)Iridium (?)

Pacific 2003-2005(Med-High)NAT >2000(Low-Med)

CMU All ADS/CPDLCPlans

ARINC Char 758ARINC Report 660

Allied SignalCollins CMU-900

Typical CNS/ATM Transition Table

Focus on Technical System Component DesignFocus on Technical System Component Design

Page 7: CNS/ATM Success Factors

15 May 98 Worldwide CNS/ATM Conference Rio de Janeiro, Brazil

Airport Analysis Lacks Work Systems Airport Analysis Lacks Work Systems

Page 8: CNS/ATM Success Factors

15 May 98 Worldwide CNS/ATM Conference Rio de Janeiro, Brazil

Work Task/Systems AnalysisWork Task/Systems Analysis

Page 9: CNS/ATM Success Factors

15 May 98 Worldwide CNS/ATM Conference Rio de Janeiro, Brazil

Large System DevelopmentLarge System Development

Page 10: CNS/ATM Success Factors

15 May 98 Worldwide CNS/ATM Conference Rio de Janeiro, Brazil

Full Life-cycle Project Planning ProcessFull Life-cycle Project Planning Process

Plann ing Project OperationsDevelopm ent

Approval

M anagem ent

National Im plem entationGlobal

Regional

ANPp

Transition

M aintenance

ANPp

Page 11: CNS/ATM Success Factors

15 May 98 Worldwide CNS/ATM Conference Rio de Janeiro, Brazil

ConclusionsConclusions

Page 12: CNS/ATM Success Factors

15 May 98 Worldwide CNS/ATM Conference Rio de Janeiro, Brazil

Develop a new accredited job skill

“Bridge” between Planning and Operations

Modular training approach

Would not replace consultants, but improve their effectiveness and reduce risk

CNS/ATM Implementation SpecialistCNS/ATM Implementation SpecialistCNS/ATM Implementation SpecialistCNS/ATM Implementation Specialist

Plann ing Project OperationsDevelopm ent

Approval

M anagem ent

National Im plem entationGlobal

Regional

ANPp

Transition

M aintenance

ANPp

CNS/ATM Implementation SpecialistCNS/ATM Implementation Specialist

CNS/ATM Implementation SpecialistCNS/ATM Implementation Specialist

Page 13: CNS/ATM Success Factors

15 May 98 Worldwide CNS/ATM Conference Rio de Janeiro, Brazil

[email protected]