design and construction guideline for soil nail wall
Embed Size (px)
TRANSCRIPT
-
7/25/2019 Design and Construction Guideline for soil nail wall
1/27
DESIGN & CONSTRUCTION GUIDELINES
FOR A
SOIL NAIL WALL SYSTEM
GEOTECHNICAL ENGINEERING MANUAL
GEM-21
Revision #4
AUGUST 2015
-
7/25/2019 Design and Construction Guideline for soil nail wall
2/27
-
7/25/2019 Design and Construction Guideline for soil nail wall
3/27
EB 15-025 Page 1 of 13
GEOTECHNICAL ENGINEERING MANUAL:
DESIGN & CONSTRUCTION GUIDELINES FOR A SOIL NAIL WALL SYSTEM
GEM-21
Revision #4
STATE OF NEW YORK
DEPARTMENT OF TRANSPORTATION
GEOTECHNICAL ENGINEERING BUREAU
AUGUST 2015
-
7/25/2019 Design and Construction Guideline for soil nail wall
4/27
EB 15-025 Page 2 of 13
TABLE OF CONTENTS
I. DESIGN ....................................................................................................................................3
A. Consultation .................................................................................................3
1. Temporary or Permanent Soil Nail Walls ....................................................3B. Feasibility Analysis ......................................................................................3
C. General Layout .............................................................................................4
II. CONSTRUCTION ..................................................................................................................6
A. Consultation .................................................................................................6
B. Design Submittals ........................................................................................6
C. Materials ......................................................................................................6
D. Monitoring Nail Installation.........................................................................7
1. Excavation....................................................................................................7
2. Drilling .........................................................................................................8
3. Nail Installation ............................................................................................8
4. Grouting .......................................................................................................8
E. Supervising Nail Stressing & Testing ..........................................................9
F. Temporary Shotcrete Construction Facing & Drainage Examination .......11
G. Documentation ...........................................................................................11
REFERENCES ..............................................................................................................................12
APPENDICES ...............................................................................................................................13
A. Soil Nail Installation Forms (US Customary Units) ............................... A-1
B. Soil Nail Installation Forms (International System of Units) .................. B-1
-
7/25/2019 Design and Construction Guideline for soil nail wall
5/27
EB 15-025 Page 3 of 13
I. DESIGN
A. Consultation
The Designer shall consult with the Regional Geotechnical Engineer (RGE) as early as possible
in the design phase to ensure adequate subsurface explorations are progressed to verify thefeasibility of installing the soil nail wall system. Subsurface explorations must also provide
enough information to define the engineering characteristics of the soil for design purposes.
When considering the use of a soil nail wall system, it is recommended that the Designer contact
the RGE for the determination of the appropriate subsurface exploration locations and
subsequent analysis of the soil for its suitability for soil nailing. The Designer and the RGE shall
also discuss the groundwater elevation and its effect on the proposed soil nail wall system and
the anticipated construction sequencing with regard to the work zone traffic control to determine
if additional subsurface explorations are required.
1. Temporary or Permanent Soil Nail Walls:
A structure with a service life of 18 months or less qualifies as temporary. A structure
with a service life longer than 18 months qualifies as permanent. If a structure is initially
intended as temporary (e.g. temporary support of an excavation) but the results of the
discussions between the Designer and RGE indicate that substantial construction delays
are expected which dictate the excavation remain open much longer than 18 months, the
soil nail wall should be characterized as permanent.
B. Feasibility Analysis
Although the details of the soil nail wall system will be designed by the Contractors consultant,
a feasibility analysis is recommended. The Designer and the RGE shall request the Geotechnical
Engineering Bureau (GEB) for a feasibility analysis. This analysis shall include:
1. Investigation of the site to determine if the subsoils are appropriate for soil nailing. Some
limitations to soil nails are:
A. Excavation support: To construct a soil nail wall, the first step is to make a near
vertical excavation approximately 3 ft. to 6 ft. (1 m to 2 m) high. Therefore, the
soil must be able to stand unsupported for a certain period of time, depending on
nail installation progress and the length of the excavated row (length of wall).
This would require the soil to have a sufficient degree of cohesion, cementing, orapparent cohesion from moisture. In addition, the anticipated construction
sequencing with regard to the work zone traffic control should be reviewed to
determine the offset to traffic.
B. Seepage: If the groundwater exists within the cut face, the unreinforced soil may
slump locally upon excavation, or the shotcrete to soil bond may be reduced.
C. Soft Clays: The low frictional resistance of soft clay would require a very high
density, of considerable length, of nails. In addition, soil nails in these soils are
susceptible to creep and permanent wall systems may not be practical.
-
7/25/2019 Design and Construction Guideline for soil nail wall
6/27
-
7/25/2019 Design and Construction Guideline for soil nail wall
7/27
EB 15-025 Page 5 of 13
8. Table identifying the soil parameters used for the design:
SOIL NAIL WALL DESIGN PARAMETERS
Location Elevation
(feet (meters))
Unit
Weight
(pcf (kN/m))
Friction
Angle
(degrees)
Notes: a. Groundwater is assumed at elevation ______.
b. A surcharge load of _____psf (kPa) is to be assumed at the top
of wall.
c. The Contractors attention is directed to the subsurface
conditions at elevation ______ which indicates (choices: rock,
boulders, loose material, obstructions, perched water).d. Any other pertinent information.
If the soil nailed wall is associated with a structure for which a Foundation Design
Report (FDR) has been prepared, the FDR will provide this information. If,
however, an FDR has not been prepared or the soil nailed wall is not in the
vicinity of a structure, this information is to be provided by the GEB or the RGE
for inclusion on the plans.
9. The location of the preproduction verification test nail is to be shown on the
Plans. The specification requires a minimum of 2 verification tests in each
different soil/rock unit and for each different drilling/grouting method proposed tobe used, at each wall location. Verification test nails will be sacrificial and not
incorporated as production nails. The preproduction verification test nail location
will identify the first nail (sacrificial) to be tested to confirm the assumptions of
the Contractors Consultant.
The facing details for permanent soil nail walls are left to the Designer. All appropriate item
numbers should be identified for the permanent facing components as they are not included under
the Basis of Payment in the soil nail specification. The details should include:
1. Connection of the permanent facing to the construction face of the soil nailed wall
system.
2. Required reinforcement (if necessary).
3. Extension of internal and external drainage systems.
4. All appropriate item numbers and details pertinent to the chosen facing (barriers,
coping, color, finishes, etc.).
-
7/25/2019 Design and Construction Guideline for soil nail wall
8/27
-
7/25/2019 Design and Construction Guideline for soil nail wall
9/27
EB 15-025 Page 7 of 13
The nail tendons will be inspected for rust just prior to installation. Loose,
powdery rust should be rubbed off, but not sanded. Nail tendons with nicks or pits
are to be rejected.
The nail tendon is encapsulated or specified corrosion protection is applied, ifrequired by the contract documents. Bare spots are unacceptable, as even the
smallest pinholes can result in severe corrosion in aggressive soils.
The nail tendons shall be covered and stored off the ground, out of the way of
construction equipment. Encapsulated or epoxy coated corrosion protected nail tendons
shall be stacked with care to prevent damage to the coating or encapsulation.
The Inspector will confirm the mix design of the soil nail grout and facing shotcrete for
compliance with the specification. When required, take grout cubes and/or shotcrete test
panel and core samples for testing.
The Inspector will verify that the geocomposite drainage materials conform to the
requirements of the specification and appear on the Departments Approved List.
D. Monitoring Nail Installation
1. Excavation:
Prior to the start of the wall construction, the Inspector will check for any
variations between the actual ground elevation along the wall line and
those shown on the Approved Shop Drawings.
The Inspector will monitor the excavation operation, frequently scanning
the walls construction site to ensure the Contractor is maintaining overall
stability and no ground deformations have occurred. The Inspector will
check the wall neat line excavation and verify that the Contractor is not
overexcavating into the next lift.
Typically, tension cracks form in the ground surface located immediately
behind the top of the soil nail wall excavation. These cracks should be
located and the Contactor and designer notified of their presence. TheInspector will monitor the cracks and provide displacement data to the
Contractor and designer. Water should not be allowed to enter tension
cracks.
-
7/25/2019 Design and Construction Guideline for soil nail wall
10/27
EB 15-025 Page 8 of 13
2. Drilling:
The Inspector will record all appropriate information for each soil nail
installation on a copy of the Soil Nail Installation and Summary Forms
included in this manual. The Inspector will log the soil and rock cuttings
brought up by the drilling operation.
The Inspector will verify the nail hole location. During drilling, the
Inspector will check that the Contractor is utilizing a drill bit that will
produce the proper hole diameter and verify that the nail declination angle
is the same as shown on the Approved Shop Drawings.
The Inspector will continue monitoring to ensure no ground deformations
have occurred or that there is no interconnection between drillholes.
3. Nail Installation:
The Inspector will inspect uncased holes with a mirror or flashlight forcaving or loose debris. The hole shall be open and clean.
The Inspector will check the bonded and temporary unbonded lengths of
the test nails.
The Inspector will ensure that the nail tendon is handled carefully to
prevent damage. The temperature of the nail tendons must be above 32 F
(0 C) to prevent the grout from freezing on contact.
The Inspector will verify that the nails are inserted to the minimum length
shown on the Approved Drawings. If the Contractor is unable to insert the
nail tendon to the minimum length, this unacceptable condition points to a
caving/sloughing hole and/or insufficient drilled length. Never allow the
nail tendon to be driven or pushed beyond the drilled length, or cut off.
4. Grouting:
The Inspector will verify that the grout is batched in accordance with the
approved mix design. The grouting equipment shall be equipped with a
working pressure gauge. The Inspector will monitor and record the groutpressure used. The Contractor shall clean the grout pressure gauge at least
daily to prevent clogging.
-
7/25/2019 Design and Construction Guideline for soil nail wall
11/27
-
7/25/2019 Design and Construction Guideline for soil nail wall
12/27
EB 15-025 Page 10 of 13
P= load (maximum applied test load, kips (kN)).
L= original length (temporary unbonded length: length from back of reference plate to the
top of the bond length, inches (millimeters).
A= cross sectional area of steel (square inches (square millimeters))
= Youngs modulus of elasticity (typically 29,000 ksi (200 GPa) for steel)
The measured movement of the soil nail head should exceed 80% of the theoretical
elastic movement. This ensures that load is transferred from the soil nail tendon to the
soil only in the bonded length and that additional load transfer is not occurring in the
temporary unbonded length.
The Inspector will verify that the nail length is sufficient to accommodate all test
equipment (or use a coupler if allowed). The dial gauges shall be in proper working order
and have an appropriate travel length (2 in. (50 mm) recommended minimum). The jack
shall be in proper working order and the jack and pressure gauge shall be calibrated as a
set. The calibration curves for the jack and pressure gauge and the load cell shall be
obtained from the Contractor. The jack or pump shall have a bleed-off valve.
The Inspector will check that the load cell and jack are aligned concentrically with one
another and with the soil nail tendon. The dial gauge shall be aligned with the axis line of
the anchor and independent of the nail and testing apparatus. Do not allow the jack to
drop onto or lay on the anchor.
The Inspector will ensure that the load in the anchor does not drop below the alignment
load (AL) identified in the testing criteria. During a creep test, the load shall be held
constant. The load shall be held within 2% of the intended load by use of a load cell.
The creep movement in the verification test is set such that the total movement is less
than 0.08 in. (2 mm) between the 6 minute and 60 minute readings. During a proof test,
the creep portion may be terminated if less than 0.04 in. (1 mm) of movement has
occurred between the 1 minute and 10 minute readings. This criterion has been set to
ensure that the nail design loads can be safely carried throughout the structures service
life.
The Inspector will continue monitoring the testing equipment to ensure that interference
between the jacking set-up and the nail tendon has not occurred due to misalignment.
The Inspector will record all readings and other pertinent information during testing on a
copy of the Soil Nail Test Data Sheet, Elastic Movement, and Test Nail Creep Movement
included in this manual.
At the completion of testing for all test nails, including sacrificial nails, the Inspector will
verify that the unbonded test length has been properly filled with grout. No voids shall be
left in the ground.
-
7/25/2019 Design and Construction Guideline for soil nail wall
13/27
EB 15-025 Page 11 of 13
F. Temporary Shotcrete Construction Facing and Drainage Examination:
The Inspector will check that the geocomposite drainage strips, along with all elements of
the wall drainage network, are installed as shown on the Approved Shop Drawings and
are interconnected, providing continuous drainage paths. Maintenance of drainage
continuity and capacity is critical to the overall stability of the soil nail wall system.
The Inspector will verify that the welded wire fabric has been installed at the locations
and to the dimensions shown on the Approved Shop Drawings.
The Inspector will verify that the reinforcing steel has been installed at the locations and
to the dimensions shown on the Approved Shop Drawings.
The Inspector will verify that the shotcrete is batched in accordance with the approved
mix design.
G. Documentation:
The Inspector will make copies of all appropriate forms for nail tendon installation and
testing. Record and log each nail tendon installation which includes: drilling, subsurface
conditions encountered, nail tendon installation, and grouting. Record and plot test results
for each nail tendon.
All forms and calculations shall be complete, accurate and up to date. Log dates, times,and weather conditions on all records. Keep a photographic record along with the written
documentation.
-
7/25/2019 Design and Construction Guideline for soil nail wall
14/27
EB 15-025 Page 12 of 13
REFERENCES
Further information on soil nails may be found in such sources as: US Department of
Transportation, Federal Highway Administration, Publications - Geotechnical Engineering -
FHWA
Publication No. FHWA-IF-03-017: Geotechnical Engineering Circular No. 7 Soil Nail Walls,March 2003 and Publication No. FHWA-SA-93-068: Soil Nailing Field Inspectors Manual, Soil
Nail Walls-Demonstration Project 103, April, 1994.
http://www.fhwa.dot.gov/engineering/geotech/library_listing.cfmhttp://www.fhwa.dot.gov/engineering/geotech/library_listing.cfmhttp://www.fhwa.dot.gov/engineering/geotech/library_listing.cfmhttp://www.fhwa.dot.gov/engineering/geotech/library_listing.cfmhttp://www.fhwa.dot.gov/engineering/geotech/library_listing.cfm -
7/25/2019 Design and Construction Guideline for soil nail wall
15/27
EB 15-025 Page 13 of 13
APPENDICIES
FORMS:
The following forms were reproduced from:
US Department of Transportation, Federal Highway Administration, Publication No. FHWA-
SA-93-068: Soil Nailing Field Inspectors Manual, Soil Nail Walls-Demonstration Project 103,
Appendix A, April, 1994.
-
7/25/2019 Design and Construction Guideline for soil nail wall
16/27
-
7/25/2019 Design and Construction Guideline for soil nail wall
17/27
Soil Nail Installation and Summary Forms (US Customary Uni ts)
EB 15-025 A-1 of A-5
-
7/25/2019 Design and Construction Guideline for soil nail wall
18/27
-
7/25/2019 Design and Construction Guideline for soil nail wall
19/27
Soil Nail Installation and Summary Forms (US Customary Uni ts)
EB 15-025 A-3 of A-5
-
7/25/2019 Design and Construction Guideline for soil nail wall
20/27
Soil Nail Installation and Summary Forms (US Customary Uni ts)
EB 15-025 A-4 of A-5
-
7/25/2019 Design and Construction Guideline for soil nail wall
21/27
Soil Nail Installation and Summary Forms (US Customary Uni ts)
EB 15-025 A-5 of A-5
-
7/25/2019 Design and Construction Guideline for soil nail wall
22/27
-
7/25/2019 Design and Construction Guideline for soil nail wall
23/27
Soil Nail Installation and Summary Forms (I nternational System of Uni ts)
EB 15-025 B-1 of B-5
-
7/25/2019 Design and Construction Guideline for soil nail wall
24/27
Soil Nail Installation and Summary Forms ( I nternational System of Uni ts)
EB 15-025 B-2 of B-5
-
7/25/2019 Design and Construction Guideline for soil nail wall
25/27
Soil Nail Installation and Summary Forms (I nternational System of Uni ts)
EB 15-025 B-3 of B-5
-
7/25/2019 Design and Construction Guideline for soil nail wall
26/27
Soil Nail Installation and Summary Forms (I nternational System of Uni ts)
EB 15-025 B-4 of B-5
-
7/25/2019 Design and Construction Guideline for soil nail wall
27/27