Discussion Items 06 November 2009 LARP CM13 Port Jefferson, NY Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator Research Program

Upload: jacob-henry

Post on 28-Dec-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

Discussion Items

06 November 2009

LARP CM13

Port Jefferson, NY

Tom Markiewicz/SLAC

BNL - FNAL- LBNL - SLAC

US LHC Accelerator Research Program

LARP CM13 - 04 Nov 2009 Accelerator Systems Plans - T. MarkiewiczSlide n° 2 / 24

LARP Publications

How to ensure that it be possible to collect a list of publications based on work partially funded by LARP?

Why?

Credit with the funding agency in same manner as any of the labs

Eric will ask Fermilab library staff to comb through SPIRES, etc. to search for existing documents

What can we do in the future to guarantee reference?

• DocDB?• Acknowledgements?• Other?

LARP CM13 - 04 Nov 2009 Accelerator Systems Plans - T. MarkiewiczSlide n° 3 / 24

LARP Apartment in Ferney

http://www.uslarp.org/misc/larp_apartment.html

Please email reservation requests to [email protected]

Soon to be implemented procedure:Get a Gmail account, send it to [email protected] will be allowed to book room through Google CalendarAccess to keys still under negotiationFor now one key at SLAC, 2 spares at the apartment

Two rooms available (Ryoichi permanent resident)

Bring your own sheets & towel (1 queen, 1 bed to-be-purchased)Clean up after yourself

More practical info on the web site

LARP CM13 - 04 Nov 2009 Accelerator Systems Plans - T. MarkiewiczSlide n° 4 / 24

LARP CM13 - 04 Nov 2009 Accelerator Systems Plans - T. MarkiewiczSlide n° 5 / 24

LARP CM13 - 04 Nov 2009 Accelerator Systems Plans - T. MarkiewiczSlide n° 6 / 24

Accelerator Systems Funding Profile

This as prelude to discussion Eric will lead during his talk

Dinged by DOE Review Committee in July

How to introduce placeholders to evidence ongoing rich program while not opening up “New Initiatives” process?

LARP CM13 - 04 Nov 2009 Accelerator Systems Plans - T. MarkiewiczSlide n° 7 / 24

Accelerator Systems

5 Year Spending Profile

$0k

$500k

$1,000k

$1,500k

$2,000k

$2,500k

$3,000k

$3,500k

$4,000k

$4,500k

$5,000k

FY09 FY10 FY11 FY12 FY13 FY14

Electron Lens as Collimation Scraper

Discretionary

Crab Cavities

PS2

SPS E-Cloud Study

E-lens for Beam-Beam Compensation

UA9 Crystal Collimation at SPS

T-980 Crystal Collimation at Tevatron

Rotatable Collimator Task

H- Development for Linac4

SLM Development and Studies

LLRF

AC Dipole

Tune & Chromaticity Feedback

Schottky

LUMI Monitor

Not too bad for 1st try!

LARP CM13 - 04 Nov 2009 Accelerator Systems Plans - T. MarkiewiczSlide n° 8 / 24

Committee on AS Funding Profile

Findings Out year funding appears to decline in planningNo precise activities in accelerator physics appear after 2012

Comments Does not appear to ensure return on investmentGives DoE a misleading indication of need for future high impact

LHC researchMany research thrusts are identified and examined each yearOne believes that at least a constant level of activity is likely

LHC commissioning will indicate specific pathsDo not squander opportunity to participate

Recommendation Do not be shy about funding requests

LARP has shown its worth

Put place-holder in lieu of specific projects in far-future funding plans