DSN 103: Project Management. Clifford A. Keenan, PMP, MAS, MSS. Course review. Agenda. Chapters 1-13 review. What is a Project?. Temp endeavor to create a unique product, service, or result Can also last for centuries (monuments, ie. Sitting Bull, etc…) - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: DSN 103: Project Management

DSN 103: PROJECT MANAGEMENT

Clifford A. Keenan, PMP, MAS, MSS

COURSE REVIEW

Page 2: DSN 103: Project Management

Agenda

Chapters 1-13 review

Page 3: DSN 103: Project Management

What is a Project? Temp endeavor to create a unique

product, service, or result Can also last for centuries (monuments, ie.

Sitting Bull, etc…) Unique in location, function (office buildings…)

Does end when objectives are reached or project termination

Termination reasons: Objectives cannot be met Project does not exist Sponsor closes it

Page 4: DSN 103: Project Management

Relationships: PTS, PgMs, Proj

Portfolio: Collection of projects, programs, subportfolios and operations managed as a group to achieve strategic goals

Program: Projects, subprograms, managed in a coordinated manner to support the portfolio

Project: Usually single goal

Page 5: DSN 103: Project Management

What is Project Management?

“…the application of knowledge, skills, tools, and techniques to protect activities to meet the project requirements.” (PMBOK)

47 logically grouped PM processes Five process groups:

Initiating Planning Executing Monitoring and Controlling Closing

Page 6: DSN 103: Project Management

What is Project Management?

Factors change? Others will follow… Ie. Crashing

The heart: PM Plan Iterative Progressively elaborated throughout project’s

life cycle “…continuously improving a plan (detailing) as

more detailed info (estimates) become available.”

Page 7: DSN 103: Project Management

Project Management Office (PMO)

Three types: Supportive: consults with templates, lessons

learned (Org process assets). (Project repository)

Controlling: (Moderate) Directive: Directly managing projects. (High)

PMO projects may not be related (SPAWAR)

Acts as integral stakeholder/key decision maker

Can deploy resources

Page 8: DSN 103: Project Management

PM, Ops Mgmt, Org Strategy Operations Management: Day-to-day

business operations Production Manufacturing Accounting Software support Maintenance

Projects can change business strategies Projects need PM knowledge Ops need business knowledge

Page 9: DSN 103: Project Management

Project Manager responsibilities/competencies

Responsibilities: Satisfy needs of Task, Team, and Individuals Link between team and strategy

Competencies: Knowledge – PM Performance – What is able to be

accomplished Personal – behavior, attitudes, character,

leadership

Page 10: DSN 103: Project Management

Project Manager Interpersonal Skills

Leadership Team Building Motivation Communication Influencing Decision Making Cultural Awareness Trust Conflict Management

Page 11: DSN 103: Project Management

DSN 103: PROJECT MANAGEMENT

Clifford A. Keenan, PMP, MAS, MSSCHAPTER 2:

ORGANIZATIONAL INFLUENCES AND PROJECT LIFE CYCLE

Page 12: DSN 103: Project Management

Organizational Structures

Page 13: DSN 103: Project Management

Project Lifecycle

• Different from Product life cycle• Project dependent

Page 14: DSN 103: Project Management

Project Lifecycle

• Change at the start is easiest/cheapest• Risk is greatest at the start

Page 15: DSN 103: Project Management

DSN 103: PROJECT MANAGEMENT

Clifford A. Keenan, PMP, MAS, MSSCHAPTER 3:

PROJECT MANAGEMENT PROCESSES

Page 16: DSN 103: Project Management

PM Process Interaction

Page 17: DSN 103: Project Management

Knowledge Areas

Page 18: DSN 103: Project Management

DSN 103: PROJECT MANAGEMENT

Clifford A. Keenan, PMP, MAS, MSSCHAPTER 4:

PROJECT INTEGRATION MANAGEMENT

Page 19: DSN 103: Project Management

Develop Project Charter

Page 20: DSN 103: Project Management

Develop

Project Charter

Page 21: DSN 103: Project Management

Develop Project Management Plan

”…process of defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive project management plan.”

Key: Central document defining the basis of all project work

Page 22: DSN 103: Project Management

Develop Project Management Plan

Page 23: DSN 103: Project Management

Direct and Manage Project Work Leading and performing work

defined in the _______________ and implementing approved changes

KEY: Overall project management

Page 24: DSN 103: Project Management

Direct and Manage Project Work

Page 25: DSN 103: Project Management

Direct and Manage Project Work

Impact of changes: Corrective action: Intentional action to

bring it back to center Preventive action: Ensures future

performance is assured Defect repair: Modifying a nonconforming

product or component

Page 26: DSN 103: Project Management

Monitor and Control Project Work

Page 27: DSN 103: Project Management

Monitor and

Control Project Work

Data Flow

Page 28: DSN 103: Project Management

Perform Integrated Change Control

Perform Integrated Change Control “process of reviewing all change requests;

approving changes and managing changes to deliverables, organizational process assets, project documents, and the project management plan; and communicating their disposition”

Page 29: DSN 103: Project Management

Perform Integrated Change Control

Page 30: DSN 103: Project Management

Close Project or Phase

Finalizing all activities from all PM processes to formally complete project or phase

Key: Lessons learned, work ends, org assets released

Page 31: DSN 103: Project Management

Close Project or Phase

Page 32: DSN 103: Project Management

DSN 103: PROJECT MANAGEMENT

Clifford A. Keenan, PMP, MAS, MSS

CHAPTER 5:PROJECT SCOPE MANAGEMENT

Page 33: DSN 103: Project Management

Project Scope Management

Page 34: DSN 103: Project Management

Project Scope Management

Page 35: DSN 103: Project Management

Collect Requirements

“…process of determining, documenting, managing stakeholder needs and requirements to meet project objectives.”

Key: Basis for defining and managing the project scope which is includes the product scope

Page 36: DSN 103: Project Management

Collect Requirements

Page 37: DSN 103: Project Management

Define Scope

“…process of developing a detail description of the project and product.”

Key: Describes product, services, boundaries by defining which requirements are included/excluded from project scope.

Page 38: DSN 103: Project Management

Define Scope

Page 39: DSN 103: Project Management

Create WBS

“…process of subdividing project deliverables and project work into smaller, more manageable components.”

Key: structured vision of deliverables

Page 40: DSN 103: Project Management

Create WBS

Page 41: DSN 103: Project Management

Validate Scope

“…formalizing acceptance of the completed project deliverables.”

Key: Brings objectivity to acceptance process Customer conducts this Differs from QC in that this is the process NOT the

product – can be performed in parallel with QC

Page 42: DSN 103: Project Management

Validate Scope

Page 43: DSN 103: Project Management

Control Scope

“…process of monitoring the status of the project and product scope and managing changes to the scope baseline.”

Key: Maintaining Scope

Page 44: DSN 103: Project Management

Control Scope

Page 45: DSN 103: Project Management

DSN 103: PROJECT MANAGEMENT

Clifford A. Keenan, PMP, MAS, MSS

CHAPTER 6:PROJECT TIME MANAGEMENT

Page 46: DSN 103: Project Management

Plan Schedule Management

“…process of establishing the policies, procedures, and documentation for planning, managing, executing, and controlling the project schedule.”

Key: guidance/direction of managing schedule

Page 47: DSN 103: Project Management

Plan Schedule Management

Page 48: DSN 103: Project Management

Define Activities

“identifying and documenting the specific actions to be performed to produce to project deliverables.”

Key: Decomposition work into lowest work packages

Page 49: DSN 103: Project Management

Define Activities

Page 50: DSN 103: Project Management

Sequence Activities

Relationships Key: logical work sequence Each should have predecessor/successor

except first and last Finish to start or start to start relationship Sequencing automatic or manual

Page 51: DSN 103: Project Management

Sequence Activities

Page 52: DSN 103: Project Management

Sequence Activities

Page 53: DSN 103: Project Management

Estimate Activity Resources

Schedule Mgmt Plan: level of accuracy/units of measure

Resource calendar: Length of Days/Shifts resources are available Skill level, location, availability are

considered

Page 54: DSN 103: Project Management

Estimate Activity Resources

Page 55: DSN 103: Project Management

Estimate Activity Durations

Est. work periods to complete ind. Activates with est. resources

Key: Activity time required feeds Develop Schedule process

Page 56: DSN 103: Project Management

Estimate Activity Durations

Page 57: DSN 103: Project Management

Develop Schedule

Analyze activity sequences, durations, resource rqmts, schedule constraints

Key: Info into scheduling tool generates schedule model with planned completion dates

Page 58: DSN 103: Project Management

Develop Schedule

Page 59: DSN 103: Project Management

Critical Path

Page 60: DSN 103: Project Management

Control Schedule

Monitoring project activities status and schedule baseline

Key: Recognize deviation requiring corrective/preventive actions minimizing risk

Page 61: DSN 103: Project Management

Control Schedule

Page 62: DSN 103: Project Management

DSN 103: PROJECT MANAGEMENT

Clifford A. Keenan, PMP, MAS, MSS

CHAPTER 7:PROJECT COST MANAGEMENT

Page 63: DSN 103: Project Management

Plan Cost Management

Policies and procedures for planning, managing, controlling project costs

Key: Guidance/direction

Page 64: DSN 103: Project Management

Plan Cost Management

Page 65: DSN 103: Project Management

Estimate Costs

Approx. monetary resources required to complete activities

Key: Cost to complete project work

Page 66: DSN 103: Project Management

Estimate Costs

Page 67: DSN 103: Project Management

Determine Budget

Aggregating all costs into baseline Key: Cost baseline established –

performance measured

Page 68: DSN 103: Project Management

Determine Budget All funds

reqd Excludes

mgmt reserves

Page 69: DSN 103: Project Management

Control Costs

Monitoring status, managing changes to cost baseline

Key: Means to recognize variance: act & minimize risk

Page 70: DSN 103: Project Management

Control Costs

Page 71: DSN 103: Project Management

DSN 103: PROJECT MANAGEMENT

Clifford A. Keenan, PMP, MAS, MSS

CHAPTER 8:PROJECT QUALITY MANAGEMENT

Page 72: DSN 103: Project Management

Plan Quality Management

ID quality requirements of deliverables Key: Guidance of how quality is managed

and validated in project

Page 73: DSN 103: Project Management

Plan Quality Management

Page 74: DSN 103: Project Management

7 basic quality tools (7QC) Tools

Cause and Effect Diagrams Flowcharts Check Sheets Pareto Diagrams Histograms Control Charts Scatter Diagrams

Page 75: DSN 103: Project Management

Cost of Quality

Page 76: DSN 103: Project Management

Perform Quality Assurance

“…auditing the quality requirements and the results from quality control measurements to ensure that appropriate quality standards and operational definitions are used.”

Key: Improving quality processes, not the product

Page 77: DSN 103: Project Management

Perform Quality Assurance

Process Maps Steps and branches Activities Points Branches

Page 78: DSN 103: Project Management

Control Quality

QC: Operational techniques - control QA: planning/execution - prevention

Page 79: DSN 103: Project Management

Control Quality

Page 80: DSN 103: Project Management

DSN 103: PROJECT MANAGEMENT

Clifford A. Keenan, PMP, MAS, MSSCHAPTER 9:

PROJECT HUMAN RESOURCE MANAGEMENT

Page 81: DSN 103: Project Management

Plan Human Resource Management

Identifying project roles, responsibilities, required skills, relationships, creating a staffing plan

Key: Est. project roles/responsibilities Org. charts, staff management plan and timetable

Page 82: DSN 103: Project Management

Plan Human Resource Management

Page 83: DSN 103: Project Management

Acquire Project Team

Confirming HR availability Key: Outlining and guiding team

selection Responsibility assigned

Page 84: DSN 103: Project Management

Acquire Project Team

Page 85: DSN 103: Project Management

Develop Project Team

Improve competencies Team member interaction Environment Key: Improved teamwork, skills, motivated

employees reduced turnover rates, improved performance

Page 86: DSN 103: Project Management

Develop Project Team

Page 87: DSN 103: Project Management

Manage Project Team

Tracking team performance Providing feedback Resolving issues Managing team changes

Page 88: DSN 103: Project Management

Manage Project Team

Page 89: DSN 103: Project Management

DSN 103: PROJECT MANAGEMENT

Clifford A. Keenan, PMP, MAS, MSSCHAPTER 10:

PROJECT COMMUNICATIONS MANAGEMENT

Page 90: DSN 103: Project Management

Plan Communications Management

Planning an approach for project comms Key: Identifies and documents most

effective and efficient ways to push/pull info

Page 91: DSN 103: Project Management

Plan Communications Management

Page 92: DSN 103: Project Management

Manage Communications

Create, retrieve, store, distribute info Key: Enables effective and efficient info to

pass

Page 93: DSN 103: Project Management

Manage Communications

Page 94: DSN 103: Project Management

Control Communications

Monitoring and Controlling comms Key: Optimal info flows to stakeholders and all

participation participants

Page 95: DSN 103: Project Management

Control Communications

Page 96: DSN 103: Project Management

DSN 103: PROJECT MANAGEMENT

Clifford A. Keenan, PMP, MAS, MSSCHAPTER 11:

PROJECT RISK MANAGEMENT

Page 97: DSN 103: Project Management

Plan Risk Management

Objective: Increase positive, decrease negative events from occurring

Risks are uncertain events which cause the above

Page 98: DSN 103: Project Management

Plan Risk Management

Page 99: DSN 103: Project Management

Identify Risks

Page 100: DSN 103: Project Management

Identify Risk

Page 101: DSN 103: Project Management

Perform Qualitative Risk Analysis

“Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact.”

Key: PMs decrease level of uncertainty

Page 102: DSN 103: Project Management

Perform Qualitative Risk Analysis

Page 103: DSN 103: Project Management

Perform Qualitative Risk Analysis

RM Plan: roles/responsibilities, budget, activities, categories, definitions of risks, P/I matrix, risk tolerances

If not available, then might be with the Quantitative Risk process

Page 104: DSN 103: Project Management

Perform Quantitative Risk Analysis

Numerical analyzing of risk Key: Info supports decision-making reasoning “Potentially and substantially impacting the project’s

competing demands.” Total effect of Risks checked!

Page 105: DSN 103: Project Management

Perform Quantitative Risk Analysis

Page 106: DSN 103: Project Management

Plan Risk Responses

Option development countering risks (threats) and capitalize on opportunities

Key: Risks mitigated

Page 107: DSN 103: Project Management

Plan Risk Responses

Page 108: DSN 103: Project Management

Control Risks

Implementing Risk response plans, tracking/monitoring risks, ID new risks, evaluate risk process effectiveness

Key: Efficiency improves, risk minimized

Page 109: DSN 103: Project Management

Control Risks

Page 110: DSN 103: Project Management

DSN 103: PROJECT MANAGEMENT

Clifford A. Keenan, PMP, MAS, MSS

CHAPTER 12:PROJECT PROCUREMENT MANAGEMENT

Page 111: DSN 103: Project Management

Plan Procurement Management

Documenting decisions, determining approach, and ID potential sellers

Key: Determines outside support – if required – what, when, how, how much support

Page 112: DSN 103: Project Management

Plan Procurement Management

Page 113: DSN 103: Project Management

Conduct Procurements

Obtain seller responses, seller selection, contract award

Key: Alignment of stakeholder expectation through established agreements

Page 114: DSN 103: Project Management

Conduct Procurements

Page 115: DSN 103: Project Management

Control Procurements

“Managing procurement relationships, monitoring contract performance, and making changes and corrections to contract as appropriate.”

Key: Seller/Buyer performance meet contractual requirements

Page 116: DSN 103: Project Management

Control Procurements

Page 117: DSN 103: Project Management

Close Procurements

Process of completing each procurement Key: Agreements documented as reference

Page 118: DSN 103: Project Management

Close Procurements

Page 119: DSN 103: Project Management

DSN 103: PROJECT MANAGEMENT

Clifford A. Keenan, PMP, MAS, MSS

CHAPTER 13:PROJECT STAKEHOLDER MANAGEMENT

Page 120: DSN 103: Project Management

ID Stakeholders

Key: PM can ID the correct focus for each stakeholder

Page 121: DSN 103: Project Management

ID Stakeholders

Page 122: DSN 103: Project Management

Plan Stakeholder Management

Mgmt strategy: Iterative process Key: Clear, actionable plan to interact

with stakeholders

Page 123: DSN 103: Project Management

Plan Stakeholder Management

Page 124: DSN 103: Project Management

Manage Stakeholder Engagement

Meeting stakeholders expectations, address issues: Comm heavy!

Key: PM can increase support and min resistance: thus increasing projects success

Page 125: DSN 103: Project Management

Manage Stakeholder Engagement

Page 126: DSN 103: Project Management

Control Stakeholder Engagement

Monitoring and adjusting stakeholder strategy

Key: Keep or increase effective/efficient stakeholder engagement activities

Page 127: DSN 103: Project Management

Control Stakeholder Engagement

Page 128: DSN 103: Project Management

Questions?