EUCalc
EU Calcu lato r: trad e -o ffs an d p ath way s to ward s
su stain able an d lo w-carbo n Eu ro p ean so cie tie s
Detaile d wo rk p lan fo r first s ix m o n th s
––––––––– ––––
D11.1
February/2017
Ref. Ares(2017)644400 - 06/02/2017
EUCalc D11.1 Detailed work plan for the first six months
- 1 -
This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 730459.
EUCalc D11.1 Detailed work plan for the first six months
- 2 -
Project Acronym and Name
EUCalc EU Calculator: trade-offs and pathways towards sustainable and low-carbon European Societies
Grant Agreement Number
730459
Document Type Report
Document version & WP No.
V. 02 WP11
Document Title Detailed work plan for the first six months
Main authors Jürgen Kropp (PIK), Luis Costa (PIK), Katja Firus (T6)
Partner in charge PIK
Contributing partners T6
Release date 4 February 2017
The publication reflects the author’s views. The European Commission is not liable for any use that may be made of the information contained therein.
Document Control Page
Short Description
This report describes project planning issues for the first six months of the EUCalc project. The aim is to efficiently start project activities from the very beginning. Therefore a detailed work plan for the first six months is presented which was partly developed during the kick-off meeting in December 2016 in Potsdam and partly shortly afterwards, with clearly assigned tasks to all involved partners.
Review status Action Person Date
Quality Check Coordination Team
Internal Review Partners involved
Distribution Public
Statement of originality:
This deliverable contains original unpublished work except where clearly indicated otherwise. Acknowledgement of previously published material and of the work of others has been made through appropriate citation, quotation or both.
EUCalc D11.1 Detailed work plan for the first six months
- 3 -
Table of Contents
Table of Contents
1 Executive Summary ........................................................................................ - 5 -
2 Gantt chart of the first EUCalc year (M1-12) ................................................. - 5 -
3 Deliverables and milestones of M1-6 ................................................................ 8
4 Detailed work plan for the first six months....................................................... 8
5 Monitoring and follow-up ................................................................................. 20
6 References ........................................................................................................ 20
List of Tables TABLE 1 - GANTT CHART FOR THE EUCALC PROJECT BETWEEN MONTH 1 AND 12. ....................................... 6 TABLE 2: LIST OF DELIVERABLES EUCALC – M1-6 .................................................................................. 8 TABLE 3: LIST OF MILESTONES EUCALC – M1-6 ..................................................................................... 8 TABLE 4: DETAILED WORK PLAN FOR THE MONTHS 1 – 8 (NOVEMBER 2016 – JUNE 2017) ......................... 19
EUCalc D11.1 Detailed work plan for the first six months
- 4 -
List of abbreviations DoA Description of the action
M Month
WP Work package
EUCalc D11.1 Detailed work plan for the first six months
- 5 -
1 Executive Summary Good governance and an aligned team of partners are crucial for a successful project implementation. The planning for the various activities needs continuous monitoring of the progress towards the achievement of the defined research objectives. International projects may suffer from a slow start of activities in the first few months, as sometimes experienced by project partners in other projects.
In EUCalc, we mitigate this risk with a detailed work plan for the first 6 months of project activities. During the kick-off meeting in December 2016 the consortium discussed a detailed work plan for the first six months until the next face-to-face project meeting. Moreover, general understanding of some key questions was discussed in order to guarantee a coherent start of the research. Responsibilities of each partner and interdependencies of work were highlighted. The planned detailed activities in each work package will be implemented by the responsible work package leaders.
2 Gantt chart of the first EUCalc year (M1-12) An overview is given on planned activities for the first project year, covering the period November 2016 to October 2017.Activities of the second half were reviewed to make sure that the deliverables and tasks carried out during the first six months (Q1-Q2) are completed on time and fulfil requirements for the subsequent activities to be performed during Months 7 - 12.
EUCalc D11.1 Detailed work plan for the first six months
6
Table 1 - Gantt chart for the EUcalc project between month 1 and 12.
EUCalc D11.1 Detailed work plan for the first six months
7
EUCalc D11.1 Detailed work plan for the first six months
8
3 Deliverables and milestones of M1-6 According to the DoA, the following deliverables should be submitted and the following milestones should be reached in the first six months of the EUCalc project:
No Deliverable name WP Lead Type Disseminati
on level Delivery month
10.1 EUCalc Factsheet for European Commission
10 PIK R PU 1
10.2 EUCalc Dissemination and exploitation strategy
10 CMF R PU 6
10.3 EUCalc Project website 10 PIK DEM PU 6
11.1 Detailed work plan for first six months
11 PIK R PU 1
11.2 Data management plan 11 PIK R PU 6
11.3 Advisory Board final list and Terms of reference
11 PIK O Confidential 6
12.1 H - Requirement No. 1 12 PIK Ethics Confidential 2
12.2 POPD – Requirement No. 4 12 PIK Ethics Confidential 6
Table 2: List of Deliverables EUCalc – M1-6
No Milestone name WP Month Means of verification
MS1 Demand analysis workshop 9 1 Summarised demands in minutes
MS2 Realisation of EUCalc branding 10 3 Identity Handbook
MS3 Definition of levers, ambition level and metrics for parameters
1-6 3 The definitions will be provided for the following sectors/indicators:
Demographic development, economic growth, life style patterns
Land, Land use, Biomass (Bioenergy), Food, Water, Raw Materials, Minerals, Climate
Electricity and oil refinery, fossil fuels,
Transport and travel
Buildings Successful integration of lever definitions in alpha model for the preparation of the operating model
Table 3: List of Milestones EUCalc – M1-6
4 Detailed work plan for the first six months The following work plan was partly discussed during the EUCalc kick-off meeting in December 2016 in Potsdam, and further developed by the single work package leaders.
As the kick-off meeting took place in Month 2 of the project, the work plan partly covers also Months beyond Month 6.
EUCalc D11.1 Detailed work plan for the first six months
9
EUCalc D11.1 Detailed work plan for the first six months
10
EUCalc D11.1 Detailed work plan for the first six months
11
EUCalc D11.1 Detailed work plan for the first six months
12
EUCalc D11.1 Detailed work plan for the first six months
13
EUCalc D11.1 Detailed work plan for the first six months
14
EUCalc D11.1 Detailed work plan for the first six months
15
EUCalc D11.1 Detailed work plan for the first six months
16
EUCalc D11.1 Detailed work plan for the first six months
17
EUCalc D11.1 Detailed work plan for the first six months
18
EUCalc D11.1 Detailed work plan for the first six months
19
Table 4: Detailed work plan for the Months 1 – 8 (November 2016 – June 2017)
EUCalc D11.1 Detailed work plan for the first six months
20
5 Monitoring and follow-up As written above, the presented work plan shall support the consortium members to implement project activities from the very start of the project. The discussion on detailed activities within the work package groups during the kick-off meeting (and during the preparation of the meeting) served also to support the elaboration of the plan presented. The implementation of activities will be monitored during monthly conference calls that have been set to take place during the second Thursday of each month. Potential delays and ongoing status of the workplan will be discussed there, including consequences for further activities in the near future and for the project as a whole.
6 References EUCalc Grant Agreement, Annex I (part A)