i
February10
2012
El Paso Community College’s Annual Facilities Master Plan provides direction for facility acquisition, construction, remodeling, and maintenance.
ElPasoCommunityCollegeFacilitiesMasterPlan
Facilities Master Plan
Index……………………………………………………………………………..………..i
Chapter 1 Vision and Mission………………..…………….……………………..….1
Chapter 2 Description of Facilities…………………………..…………….………..3
Chapter 3 Guiding Principles for the Facilities Master Plan ….…………...…11
Chapter 4 Planning Assumptions: Managing for Change ….…………..……13
Chapter 5 Annual Facilities Plans ……………………………………..….………18
Appendix A – Space Utilization Study, Spring 2011
Appendix B – Facilities Condition – Assessment & Master Plan Summary
Appendix C – Administrative Services Center – Condition Assessment Report
Appendix D – Mission del Paso – Condition Assessment Report
Appendix E – Northwest – Condition Assessment Report
Appendix F – Rio Grande – Condition Assessment Report
Appendix G – Transmountain – Condition Assessment Report
Appendix H – Valle Verde – Condition Assessment Report
Appendix I – Career and Technical Center – Condition Assessment Report
Appendix J – Recent EPCC Board of Trustee actions regarding Facilities
Appendix K – Physical Plant and other Departments’ Area Effectiveness Plans
Appendix L – EPCC Physical Plant Manual
Facilities Master Plan Page 1 Spring 2012 Chapter 1
1.0 Vision and Mission 1.1. Vision
The El Paso County Community College District shall be the progressive leader in high-quality, innovative, educational opportunities in response to the border community. El Paso Community College (EPCC) has a District Facilities Master Plan in response to the Instructional and Student Support needs of the College and the District’s Strategic Plan. The plan recognizes the importance of a learner-centered education and the opportunities presented by alternative delivery systems. The evolution of technology expands the definition of the campus and college facilities beyond the traditional structural components. Cognizant of these possibilities and their impact on facilities, this plan addresses capital projects and facility maintenance for both short-term and long-term planning. 1.2. Mission “The mission of El Paso County Community College District is to provide educational opportunities and support services that prepare individuals to improve their personal quality of life and to contribute to their economically and culturally diverse community.” In order to accomplish this Mission, the College has eight Strategic District Goals.
Provide Quality Education Provide Quality Student Services Provide Personal Enrichment Promote Economic Development Initiatives Strengthen Institutional Resources Increase Technology Capacity Demonstrate Continuous Improvement Enhance the Image of the College
The Facilities Master Plan (the Plan) reflects the District’s Mission to provide educational opportunities and support services that meet the needs of the El Paso border community. The Plan is the first phase in planning and developing facility related projects and also considers the condition, use, and allocation of space in existing facilities throughout the District. The Plan also provides guidance for EPCC by including necessary facility descriptions and planning assumptions. The Plan includes a description and inventory of the District’s campuses, administrative facilities, and leased facilities.
Facilities Master Plan Page 2 Spring 2012 Chapter 1
2
The Plan outlines guiding principles relevant to all facility improvement programs and planning assumptions managing change. The plan also includes the annual schedule and timelines for major capital improvements. Finally, the Plan describes the process for updating and extending the plan on an annual basis. Key facilities parameters, including classroom space and laboratory space utilization and class section scheduling will be updated and reviewed on a regular basis. Those key facility utilization data, along with current enrollment and projections for area school districts and census data, will be used for facilities decision-making and complement the College’s overall strategic planning.
Facilities Master Plan Page 3 Spring 2012 Chapter 2
2.0. Description of Facilities 2.1. Facilities El Paso Community College’s (EPCC’s) first permanent facilities were located in a complex of buildings near downtown El Paso. The first building at this location was purchased in 1974. This complex of buildings became known as the Rio Grande Campus. Over the years, EPCC has constructed new facilities to meet expanding needs, including the Valle Verde Campus (1978), the Transmountain Campus (1979), the Northwest Campus (1994), and the Mission del Paso Campus (1998). In 1999, EPCC purchased a location along I-10 that would serve as the headquarters for several administrative offices. Throughout the years, EPCC has offered programming at a variety of off-campus sites, including high schools, businesses, and at Fort Bliss. EPCC has continually provided classes on Fort Bliss Military Base since 1971. EPCC also leases the Career Training Center and provides security, maintenance, and custodial services at this site. The physical facilities include the following:
2.1.1 Administrative Services Center
The Administrative Services Center (ASC) is located on a 22-acre site at 9050 Viscount, just north of Interstate 10 at Hawkins and Viscount. The facility opened in Spring 2002.
The ASC Building “A” houses College District administrative offices that include the College President’s Office, Budget and Financial Services, the Vice President of Instruction, the Vice President for Information Technology/CTO, Public Relations and Marketing, and Human Resources. The ASC Building “A” includes two large conference rooms: the Board of Trustees Boardroom and the
auditorium. Both of these rooms are available for community use. The second building of the ASC is the “B” Building, and that houses the Workforce Development Division, Distributional Services, Shipping and Receiving, Property Control Management, Culinary Arts, Cosmetology, Massage Therapy, GED programs, Travel and Tourism, Continuing Education courses and labs.
Facilities Master Plan Page 4 Spring 2012 Chapter 2
2.1.2 Mission del Paso Campus
EPCC opened the Mission del Paso Campus in East El Paso/Mission Valley area, in Spring 1998. It is located at 10700 Gateway East on a 100-acre site. The architectural design of the Mission del Paso Campus has the theme of the historic Mission Trail of the El Paso area. As one of the fastest growing campuses, this facility offers a full range of classes to the far east section of El Paso County. All student services are available including admissions, registration, financial aid, counseling, cafeteria, gym, bookstore, and a Distance Learning classroom. In 2000, EPCC opened a Law Enforcement Training Academy. Presently the total net square footage for this campus is 91,963 square feet. In 2006, an Early College High School was added to the Mission del Paso Campus.
2.1.3 Northwest Campus Opened in 1994, the Northwest Campus is located in West El Paso
County at 6701 S. Desert Blvd. at the intersection of I-10 and Transmountain Road. Large curved windows on the eastside of the campus maximize the view of the Franklin Mountains. A full range of academic, technical, and distance learning classes are offered and all student services are available on
Facilities Master Plan Page 5 Spring 2012 Chapter 2
the 84-acre campus. In Spring 2003, the District added a new library and a classroom/laboratory building. The additions provide the campus with four labs, eight classrooms, eight offices, and a library. The library has rooms for conferences, orientations and study space. The library was further expanded in 2012. In 2009, an Early College High School was added to the Northwest Campus.
2.1.4 Rio Grande Campus
In 1974-1975, the Rio Grande Campus on Rio Grande Street in downtown El Paso became the first permanent facility for EPCC. The addition of a five-story wing in 1980 enabled the College to expand its course offerings to include arts, sciences and other occupational education programs, as well as basic academic skills and credit courses in English as a Second Language. A full range of student services is available and include admissions, registration, financial aid, counseling, a bookstore, food services, campus police, and a Distance Learning classroom. Since1980, various adjoining buildings and property lots have been purchased to facilitate the expansion of the Rio Grande Campus. Renovation and expansion of the campus included the addition of classrooms, a new library and paved parking lots. In 2002, a parking garage was completed to provide an additional 400 parking spaces for students, staff and faculty use. The Health and Science Building opened in 2003 to accommodate the need for more classrooms and laboratory spaces for the rapidly growing Health Occupations programs. The net square footage for this building is 50,177 square feet. In 2010 and 2011, EPCC acquired and annexed three additional properties into the Rio Grande Campus. The properties are located at 1100 N. Stanton, 918 N. Oregon, and 1014 N. Stanton.
Facilities Master Plan Page 6 Spring 2012 Chapter 2
2.1.5 Transmountain Campus
Designed to complement the visual angles of the Franklin Mountains and blend its landscaping with the surrounding desert, the Transmountain Campus provides educational programs and services for northeast El Paso. The campus is located on 47 acres at 9570 Gateway Blvd. North at the Patriot Freeway and Diana Drive. All student services are available and include admissions, registration, financial aid, counseling, a full-service library, bookstore, food services, child care, and a Distance Learning classroom. It houses the College’s only performance/lecture/film facility. The Transmountain Campus also has 14 permanently installed portable buildings used as classrooms.
A wing was added in 1996 for classrooms, Reading and English as a Second Language laboratories and office space that increase the net square footage by 13,402 square feet.
In 2009, an Early
College High School was added to the Transmountain Campus. In 2011, a Math Emporium and a Math Lab were added to the Campus.
2.1.6 Valle Verde Campus
The largest facility in the College District is the Valle Verde Campus. The campus features multi-level buildings, patios, trees, and fountains. Valle Verde is located on 127 acres at 919 Hunter, just south of Interstate 10 at Hawkins and North Loop. This campus provides all student services and houses the largest District Library of 23,100 square feet. Other services include a bookstore, cafeteria, and childcare. The Advanced Technology Center, the Americana Language Program, the Intercollegiate Athletics Program, and the Physical Plant offices are located at this campus.
Facilities Master Plan Page 7 Spring 2012 Chapter 2
The Valle Verde Campus features a series of buildings. The newest instructional building on campus, Building B, built in 1997, has 24 classrooms, an open computer laboratory, foreign language, and English as Second Language laboratories, a Distance Learning classroom and space for noncredit classes.
New additions include an Early College High School in 2007 and a Math Emporium in 2012.
2.2 Leased Facilities
2.2.1 Career Training Center As part of the College’s Workforce Development Division, the Career Training Center (CTC) offers basic job skills training for displaced workers, single heads of household in need of education to support the family, and economically disadvantaged adults. The CTC is located at 215 Francis and includes 8,700 square feet with 3,600 sq. ft. of classrooms and laboratory facilities. The remaining 4,200 sq. ft. contain office, academic and general support facilities. The College leases this facility from the City of El Paso and provides maintenance, custodial and security services. 2.2.2 Construction Manager Continuing Education Program The Construction Manager Program is located at 1359 Lomaland on the East side of El Paso. Leased from the Greater El Paso Chamber of Commerce, the site offers training services through the Workforce/Economic Development and Continuing Education division. The Chamber of Commerce is responsible for building maintenance and support services.
Facilities Master Plan Page 8 Spring 2012 Chapter 2
2.3 Tenant Arrangement
2.3.1 Fort Bliss Military Base
EPCC has an agreement with Fort Bliss to offer classes on base. EPCC’s facilities are 10 classrooms located in Building 639, a part of a national historic landmark commemorating General John J. Pershing. The College’s educational area on Fort Bliss provides services in registration, testing, counseling, admissions, issuance of transcripts, and student identification. EPCC provides only janitorial services while the U.S. Army provides all other maintenance services. 2.3.2 Diesel Mechanics EPCC has an agreement with Mesilla Valley Training Institute, located in west El Paso County at 7440 Doniphan, Canutillo, Texas, 78935, to use facilities to provide training for the Credit Certificate in Diesel Mechanics and the Continuing Education Truck Driving Program. 2.3.3 Cotton Valley Early College High School EPCC has an agreement with Fabens Independent School District (ISD) offer Early College High School courses at 600 N.E. Fourth St., Fabens, Texas, 79838. 2.3.4 Dual Credit/High Schools
EPCC has agreements with Independent School Districts throughout the region to offer EPCC courses for dual credit at high school facilities. The School Districts are responsible for the maintenance and janitorial services for all high school facilities.
2.4. Completed Projects EPCC has completed several major renovation and new construction projects throughout the last decade to meet the educational and student support needs of the District. The projects exceeding the State approval limit require Board of Trustees’ approval. Appendix X includes Board actions regarding facilities since 2007. A summary of the major projects are listed below for easy reference.
Facilities Master Plan Page 9 Spring 2012 Chapter 2
2007-2011 Major Renovation and New Construction Projects
Year Project 2007 1. Valle Verde Campus High School Early College Campus – Modular
buildings installed and occupied. 2. ASC “B” Building – Major renovations from a warehouse to offices and classrooms for Workforce Development and Continuing Education Program for relocation from the Lomaland (off-site) location.
2008 1. ASC “C” building Auto Shop (building #6030) – New facility built for maintenance and repair of college vehicles. 2. Valle Verde Campus Physical Plant (building #2090) – Office area remodeling completed. 3. Transmountain Campus High School Early College Campus – Modular buildings installed and occupied. 4. Northwest Campus High School Early College Campus – Modular buildings installed and occupied.
2009 1. ASC “A” building (building #6010) room A621 – Built offices and classrooms for the Texas Tech University College of Architecture. 2. ASC “A” building (building #6010) A632 – Completed building the Culinary Arts Catering Kitchen. 3. ASC “A” building (building #6010) room A635 – Built Offices of the International Education Program. 4. ASC “B” building (building #6020) Culinary Arts area – Built classrooms, kitchen labs, offices, storage areas, and restaurant area. 5. Valle Verde Campus building ATC-4 – Built classroom and offices for the Fire Technology Program. 6. Valle Verde Campus Student Service Center (building #2018) rooms 100A, 100B – Remodeled to create rooms in support of Registration.
2010 1. Valle Verde Campus Grounds House (building #1) – Converted from grounds crew offices to carpentry workshop. 2. Northwest Campus – Education Services Center Region XIX completed and opened the Santiago Rodriguez Head Start & Early Start Center. 3. Northwest Campus – Remodeled cafeteria completed and opened. 4. Mission del Paso Campus – Remodeled cafeteria completed and opened. 5. District-wide – Re-lamping at all campuses as part of the Schools Conserving Resources Project (SCORES). 6. District-wide – HVAC Control modifications to make HVAC equipment at all campuses more efficient as part of SCORES Project. 7. District-wide – Water conservation project with installation of low-flow toilets at all campuses as part of SCORES Project.
2011 1. ASC “A” building (building #6010) room A157 – Remodeled to create new offices for the Associate Vice-President of Budget and Financial Services. 2. Mission del Paso (building #8020) room C119 – Remodeled room for Math Emporium. 3. Northwest Campus – Installed new cooling tower. 4. Rio Grande Campus – Installed new chiller and cooling tower. 5. Mission del Paso Campus – Installed new chiller.
Facilities Master Plan Page 10 Spring 2012 Chapter 2
6. Transmountain Campus – Installed new chiller. 7. Northwest Campus LRC (building #7020) – Addition being built to existing Library. 8. Rio Grande Campus (building #4090) – Existing building renovated to become the new Math Emporium. 9. Rio Grande Campus newly acquired building (building #4095) – Stanton Building at 1100 Stanton Street is currently being remodeled for occupancy later this year. 10. Transmountain Campus (building #3025) rooms 1136 – 1137A – Labs, offices, classroom and storage area built for Math Emporium. 11. Transmountain Campus (building #3050) – Remodeled Science Area classrooms, labs, and offices.
2012 1. Valle Verde Campus (building #2010) Administrative building – Student Union area with study and game areas being built within existing building. 2. Valle Verde Campus Addition – Math Emporium. 3. Valle Verde Campus – Advanced Technology Center – Building 1 – Installed solar panels to support the alternative energy continuing education courses.
Under construction or in Planning Stage
1. Valle Verde Campus Enrollment Services Building – Completion scheduled for 2013. 2. Renovation or new construction of a facility for the architecture program.
Routine maintenance and preventive maintenance for buildings, facilities, and grounds have been ongoing. The Executive Director of Physical Plant supervises the staff that performs regular inspections and duties. The staff provides feedback from the inspections so that the Executive Director may develop plans and establish schedules of maintenance. The programs include the following:
HVAC Preventive Maintenance Program Roof Maintenance Program Campus Zone Maintenance Program Grounds Weed Control Program Campus Weekly Inspections Campus Monthly Inspections Vehicle Maintenance Program Waste Disposal Management Grease Traps
The EPCC Physical Plant Procedure Manual directs day to day operations. The Executive Director of Physical Plant reviews and updates the manual on an annual basis to ensure currency and adequacy.
Facilities Master Plan Page 11 Spring 2012Chapter 3
3.0. Guiding Principles for the Facilities Master Plan 3. 1 Guiding Principles The Guiding Principles for the Facilities Master Plan should codify those precepts that best express both the philosophy of the El Paso County Community College District and its respect and understanding for the multi-cultural border community that it serves. These principles focus on the diverse audiences, including internal audience, served by the College and recognize the learner-centered nature of the modern community college system. EPCC will maintain a Facilities Master Plan to ensure thoughtful planning and execution of current and future facility needs.
a. The Plan shall make note of current facility conditions and projected planning for short-term and long-term maintenance of those facilities.
b. The Plan shall incorporate information from the Instructional Master Plan, Information Technology Plan, Needs Assessment Studies, and Space Utilization Studies when projecting future expansion and construction needs. The needs shall be prioritized and projected into short-term and long-term range timelines.
c. The Plan will include documentation of completed projects.
3. 2 Process for Review and Update of the Facilities Master Plan This Facilities Master Plan is a living document that is continually examined to ensure support of the instruction and other College services through considered facilities planning. It is to be used and modified on a regular basis to produce a timely Facilities Master Plan that will direct and guide physical plant operations. It will support the EPCCCD Strategic Plan and the District Strategic Goals. The Facilities Master Plan will follow the general guidelines of the Institutional Effectiveness Planning Process. To ensure that the Facilities Master Plan is developed and regularly reviewed, the Executive Director of Physical Plant, under the direction of the Vice President of Administrative and Financial Operations, will annually update Facilities Master Plan with the current facility square footage data, changes in facilities directed by the Board of Trustees, and capital projects completed and new ones planned. The Executive Director of Physical Plant will request enrollment data and trends and a space utilization study from Institutional Research. The Executive Director of Physical Plant will convene a meeting consisting of key stakeholders to include a representative of the Instructional Master Plan, a representative of the Information Technology Master Plan, the Campus Deans and other appropriate participants to review the document and may appropriate updates and revisions in the Facilities Master Plan. The participants should
Facilities Master Plan Page 12 Spring 2012Chapter 3
review proposals for facilities space needs and impact on existing space inventory and make recommendations based on:
a. Educational needs and demands of all District areas, including enrollment, space utilization, and potential for alternative delivery.
b. current priority renovations, repairs, and construction c. current college space inventory d. current space usage
Proposed changes will be forwarded to the President’s Cabinet for further review and comment. Approved modifications to the Facilities Master Plan will be incorporated and implemented by the Vice President of the Administration and Financial Operations. The President shall update the Board of Trustees as appropriate regarding the Facilities Master Plan.
Facilities Master Plan Page 13 Spring 2012Chapter 4
4.0 Planning Assumptions: Managing for Change To establish the basis for current and future planning for the El Paso Community College (EPCC) planning assumptions have been made and are being presented. These assumptions build on the set of assumptions used in the past Facilities Master Plans and incorporate the current data on space utilization, current enrollment statistics, demographic information based on the most recent census, and job market indicators for El Paso and the region. Each of these planning assumptions will be reviewed annually and updated accordingly. 4.1 Standards of efficiency and utilization
The ongoing application of nationally recognized facilities utilization standards is the acceptable form of measuring the efficient use of facilities. Taking a conservative approach, the facilities can be targeted for optimum levels of use which may exceed those standards. This allows for complete assurance to all stakeholders – students, faculty, staff, administrators, governance and regulatory agencies, and taxpayers.
4.2. Recognition of new technologies and distance learning The Facilities Master Plan (Plan) recognizes the increasing importance developing technology, delivery systems, and the emphasis on a learner-centered institution. This demands the integration of the Instructional Master Plan and Information Technology Master Plan into planning for the seamless construction of spaces that may use computer, video, and cyber technology. Information Technology includes the development of a networked infrastructure at each Campus and Administrative Services Center to include all instructional environments. Distance learning, including dual-credit courses, blended online/Internet courses combining new technology and traditional lectures, and other formats, require an examination of the open architecture that is beginning to define community college learning environments. Distance learning provides opportunities for unexplored enrollment growth away from traditional campus facilities. 4.3. Enrollments A basic component of facilities and capital outlay planning and budgeting are projections or estimates of enrollment. For projecting operating budgets, a one- or two-year projection of enrollment is typically applied; whereas, for capital outlay planning, enrollment projections of 10 years are applied. In the present planning effort, the EPCC examines and reviews specific data that can be defined by annual plans for a three-year period. Additionally, projects or tasks that fall beyond this timeline will be categorized as long term. The rationale for
Facilities Master Plan Page 14 Spring 2012Chapter 4
this relatively conservative approach for limiting timespan for short-term facilities planning includes:
Responsiveness of the EPCC Mission. With labor markets and enrollments subject to a variety of factors, the instructional objectives are often subject to change with short timeframes.
Program delivery. EPCC continues to expand its educational, technological, and community horizons. Each of these efforts may well require both planning and implementation within years rather than decades. These initiatives are exemplified by:
1. dual credit courses serving high school students throughout the service area;
2. Early College High School initiatives; 3. improving high speed connectivity to other secondary and
post-secondary institutions and agencies; 4. fast-tracking developmental education to encourage
students readiness for college; 5. identifying possible sites for future campus expansions.
Variable budget constraints that have unintended consequences on enrollment.
Recent census data indicates that El Paso County continues to grow. Moreover, there is every indication that significant growth will continue in those areas outside of the El Paso city limits. School districts in Vinton and Anthony in the far West of El Paso County and Socorro, San Elizario, and Clint , all located in the far East and lower valley areas of El Paso County experienced double digit enrollment growth in the two last decades. The percentage of off-campus enrollment is expected to continue to grow. This not only reflects new delivery modes including dual-credit courses, early college high schools, and blended courses but the continuing significant population growth of the outlying areas. The following table illustrates past and predicted enrollment trends at EPCC.
Facilities Master Plan Page 15 Spring 2012Chapter 4
CREDIT ENROLLMENT and FORECAST FOR EL PASO COMMUNITY COLLEGE 2005-2020
2005 2006 2007 2008 2009 2010 2015 2017 2020
34,637 35,286 34,818 33,986 34,783 38,138 63,248 73,031 80,788
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
90,000
2005 2006 2007 2008 2009 2010 2015 2017 2020
Enrollment/Forecast
Enrollment from EPCC Student Banner Files Forecast from Institute on Policy and Economic Development
4.3.1 Methodology for Estimating Enrollment
A participation rate model expresses enrollment as a proportion of the population base. The population base used should reflect the pool of individuals from which an institution of higher education can expect to draw the majority of its students. When participation rates are applied to the population base to project or estimate enrollment in each year of planning period, the resulting enrollment is directly related to projections of population within the service area. For example, if participation in the service area is assumed to remain constant, the projected enrollment growth will reflect the rate of population growth. If, however, there is reason to believe that participation will not remain constant, enrollment may grow or decline at a rate greater or lesser than projected population.
There are many reasons that may suggest a variance in the participation rate throughout a planning period. These reasons might include an historical trend in participation for a service area or known factors that are likely to influence individuals’ needs, or desires, to participate in higher education. Applying the participation rate concept in the challenging task of projecting or estimating enrollment essentially enables the behavior or character of a service area’s population for each individual year of a planning period to be predicted.
Facilities Master Plan Page 16 Spring 2012Chapter 4
4.3.2 Population Base
As mentioned above, application of the participation rate methodology requires substantial reliance on the population base projection in each year of the planning period. Population (ages 16 and over) projections are based on current census data, trends analysis and current data from The University of Texas at El Paso, City of El Paso and the Chamber of Commerce. The population base used includes the entire El Paso County.
The use of the El Paso County population base for the participation rate enrollment estimates appears to be quite reasonable. The strongest support for use of the County population base in the estimation enrollment is that historically there is a high correlation between growth in the County population and growth in EPCC enrollment. Secondly, the County contains the largest majority of individuals served by the College, and finally, there are no indicators of negative change in the behavior or attitude of individuals toward higher education who comprise the population.
4.4 Demographics.
Enrollment significantly correlates with population growth. Service area needs must account for indicators, sometimes conflicting, such as:
Significant growth of population in areas outside El Paso city. The percentage of off-campus enrollment is expected to
continue to grow. It includes evolving modes of distance learning such as dual-credit courses and hybrid courses.
Academic need as El Paso County, according to recent Census data, continues to rank near the bottom of higher educational attainment throughout the United States.
4.5 Economic indicators
When predicting enrollment trends and facility needs, EPCC considers current economic indicators. As annual revisions are made to the Plan and other College Master Plans, the current employment rates, workforce demands, and state/federal/national influences are considered. 4.6 Accessibility
Proximity is a critically significant factor contributing to enrollment and/or attendance. With the increasing technological advances, it is understood that the Instructional Master Plan and the Information Technology Master Plan offer guidance to short-term and long-term facility planning. Location of facilities will not be place bound and limited to major campuses but can be designed to serve
Facilities Master Plan Page 17 Spring 2012Chapter 4
many target markets through the use of Internet, video, hybrid, and dual credit models. This open architecture of the learner-centered institution should be based on a number of interrelated factors. These factors include:
Humanistic education. There must be the recognition that the needs of the learner may not always fit a tradition amalgam of bureaucratic or pedagogic solutions. Planning must allow for the expansion of thoughts, opportunities, and desires of the learners.
Responsiveness to all audiences. The role of the college is responsive when it identifies and meets the needs of underserved populations. This includes segmentation by population designations such as zip codes and also population characteristics such as high school students, high risk students, returning adults, veterans, and displaced workers.
Travel time. A desirable travel time from the point a student departs from work or home to the site where the program or services are offered may be critical in a student’s ability to attend community college classes.
Distance Education. EPCC’s distance education philosophy is to use technology to reach students by extending the campus to the students in a convenient and effective way.
Facilities Master Plan Page 18 Spring 2012 Chapter 5
5.0. Annual Facilities Plans Determining available space capacity is an essential starting point in the facilities planning process. Prior to determining future space capacity needs, there must be an assessment of current space holdings. Space in the current inventory for each campus is deducted from the total need generated in each type of space based on current enrollment which results in a net or assignable square feet (NSF) need or excess. In addition, a space utilization study and facility condition survey are needed to document current status. 5.1. Methodology The College program is delivered through a variety of existing facilities. Some are owned by the College; others are leased or temporarily borrowed for short periods of time. The majority of enrollment activity occurs on College-owned properties. This chapter assesses the existing facilities in terms of capacity, use, and condition. The space requirement parameters are delineated in the following sections.
5.2 Key Factors in Determining Facilities Requirements
5.2.1 Facilities Inventory.
EPCC maintains a “facility inventory” which identifies every room owned by the College. Planning processes inevitably produce far more successful results when beginning with an accurate inventory. The inventory of facilities is an important tool in planning and managing College campuses. Facilities inventories include descriptive data on buildings and rooms for each campus. A well-kept, well-monitored, and accurate facilities inventory is clearly in the best interest of a college.
Facility Square Feet Administrative Services Center 374,582 Career Training Center (Leased) 8,796 Mission Del Paso Campus 161,248 Northwest Campus 88,301 Rio Grande Campus 380,038 Transmountain Campus 207,502 Valle Verde Campus 511,848 TOTAL: 1,732,315
Facilities Master Plan Page 19 Spring 2012 Chapter 5
5.2.2 Space Utilization Study. The purpose of the Space Utilization Study is to measure the extent to which El Paso Community College (EPCC), an institution of higher education, is using instructional space productively. In particular, this study contains information as to how well the institution is using classrooms. The utilization of classrooms and laboratories is measured in a number of ways: (1) The average number of hours per week that the rooms are used. At EPCC the established guideline for the use of classrooms is an average of 40 hours per week. (2) The average proportion of stations or seats in classrooms that are filled when the rooms are in use. EPCC’s guideline for this measure states that we should fill an average of 60 percent of the stations/seats respectively in classrooms when they are in use. EPCC also annually conducts space utilization studies of instructional areas to assess and monitor capacity and predict future facility expansion needs. The Spring 2011 study documents space utilization at EPCC facilities. (See Appendix A) In summary the key findings in the 2011 study are as follow per site:
ASC’s average usage percentage over a 40-hour week is at 75%; MdP’s average usage percentage over a 40-hour week is at 77.5%; NW’s average usage percentage over a 40-hour week is at 57.5%; RG’s average usage percentage over a 40-hour week is at 72.5%; TM’s average usage percentage over a 40-hour week is at 62.5%; VV’s average usage percentage over a 40-hour week is at 82.5%.
On average EPCC’s instructional sites are used productively. Just as importantly, it is clear that when the model applies the 60 percent average fill as a guideline to denote that additional classroom space is needed, the college should begin the process for construction.
5.2.3 Consultant’s Findings in 2008. EPCC maintains an ongoing inventory of conditions of facilities and lists of needed repairs and upgrades. Safety concerns are the first priority when planning repairs and upgrades. Besides EPCC’s inventory, an outside consulting firm was contracted to conduct an inventory of facility conditions and projected short-term and long-term facility needs and improvements. The Summary of the consultant’s report is in Appendix B and individual site reports are in Appendices C to I.
Facilities Master Plan Page 20 Spring 2012 Chapter 5
5.2.4 EPCC’s Physical Plant Area Effectiveness Plans and Recent Projects. EPCC uses internal assessments including facility inspections, survey responses, Area Effectiveness Plans and Assessment Results, initiatives, and departmental budgets in concert with the consultant’s findings to develop short-term and long-term facility plans. Since the consultant’s report, EPCC has addressed some items and has developed plans and timelines for other items. Appendix J contains recent Board of Trustee actions regarding facilities. Appendix K contains Physical Plant and other Departments’ Area Effectiveness Plans regarding facilities.
5.3 Short-Term and Long-Term Projected Facility Plans and Priorities. EPCC uses internal and external data such as surveys, consultant findings, community input and need, Coordinating Board guidelines, Texas State laws, Federal Requirements, accreditation principles, current facility condition reports, grant funding, and the Instructional Master Plan to develop short-term and long-term facility plans.
Facilities Plan/Priorities for 2010 to 2035 Project current 5 years 10 years 15 years 20 years 25 years
Northwest Campus Library Expansion Northwest Campus Cafeteria Mission del Paso Campus Cafeteria Conduct a needs assessment and community survey regarding a Fine Arts Building the Valle Verde Campus
Remodel and/or construction of faculty/ staff offices to meet the needs of new faculty/staff
Develop an architecture plan for a Fine Arts Building
Conduct a needs assessment for a Center/Campus in far east El Paso County
Architecture Program’s building – remodel or construction
Fort Bliss Campus (establishing new campus)
Obtain architectural plans for a Center/Campus in far east El Paso County
Address Findings in the 2008 Consultant’s review of EPCC facilities
Plan and remodel open spaces in the Administrative Services Center as needed
Have an outside consultant review EPCC’s facilities
Incorporate energy saving and “green” technology into existing facilities
Facilities Master Plan Page 21 Spring 2012 Chapter 5
Build a Fine Arts Building on the Valle Verde Campus
Build a Center/Campus in far east El Paso County
Expansion of the Health and Fitness facilities across the District
Conduct a needs assessment for a College sports complex and aquatics center
Acquire suitable property around the Rio Grande Campus
Assessing facility needs based on the Instructional Master Plan
Fort Bliss Campus (if approved) expansion
Remodeling Existing Educational facilities in alignment with the Instructional Master Plan
Review Health Occupation Specialized Accreditation Requirements regarding facilities and respond with appropriate remodeling and construction
Construction of new facilities in accordance with the Instructional Master Plan and enrollment data
Address findings in the new consultant’s report on facilities
Address Early College High School maintenance and property issues
Address Preventative and Deferred Maintenance according to the Physical Plant Manual to ensure safety and facility preservation
Maintain Historical Buildings at the Rio Grande Campus according to rules and regulations
Respond to Facility condition issues highlighted in Student and Employee Surveys
Conduct an Annual Review of long and short-term facility needs
Conduct Student Service facility needs assessment across the District
Assess Information Technology needs in existing facilities, facilities to be remodeled and new construction facilities
Develop plans for Student Service facility needs identified by the needs assessment study
Implement the Information Technology assessment results in existing facilities and new construction
Construct/remodel facilities to meet the Student Service needs
Appendix A –
Space Utilization Study,
Spring 2011
Campus BLDG ROOMTotal Banner
StationsSeats
% Seats Filled (Seats/Total
Banner Stations)
Total LEC Hrs Rm Used
Total LAB Hrs Rm Used
Total Lab & LEC Hrs Rm Used
# Lec Hrs X % Seats
Filled
# Lab Hrs X % Seats
Filled
Weekly Hours of
Room Use
ASC 6010 A200 120 126 105.0% 6 6 6.3 0.0 6ASC 6020 B120 216 184 85.2% 40 40 34.1 0.0 34ASC 6020 B128 228 207 90.8% 53 53 48.1 0.0 48ASC 6020 B131 108 56 51.9% 15 15 7.8 0.0 8ASC 6020 B141 264 82 31.1% 63 63 19.6 0.0 20ASC 6020 B190 165 88 53.3% 12.5 0.75 13.25 6.7 0.4 7ASC 6020 B191 270 232 85.9% 20.5 20.5 17.6 0.0 18ASC 6020 B192 300 232 77.3% 13.5 9.5 23 10.4 7.3 18ASC 6020 B193 30 28 93.3% 3.5 3.5 3.3 0.0 3ASC 6020 B194 120 98 81.7% 6.5 1.5 8 5.3 1.2 7ASC 6020 B230 150 136 90.7% 5 16.5 21.5 4.5 15.0 19ASC 6020 B232 300 304 101.3% 7 17.5 24.5 7.1 17.7 25ASC 6020 B234 570 544 95.4% 16 31.5 47.5 15.3 30.1 45ASC 6020 B236 510 478 93.7% 12.5 35 47.5 11.7 32.8 45ASC 6020 B238 90 67 74.4% 17 17 12.7 0.0 13ASC 6020 B320 96 70 72.9% 6 6 4.4 0.0 4ASC 6020 B321 736 671 91.2% 44 44 40.1 0.0 40ASC 6020 B485 70 39 55.7% 18 18 10.0 0.0 10
4,343 3,642 83.9%241 202 83.9% 20 16 36 15 15 21
30
ASC AveragesASC Average Weekly Hours of Station Use
(Total Lab, Lec Hrs * % Seats Filled)
Space Utilization for EPCC, Spring 2011
ASC Total
1
Space Utilization for EPCC, Spring 2011
Campus BLDG ROOMTotal Banner
StationsSeats
% Seats Filled (Seats/Total
Banner Stations)
Total LEC Hrs Rm Used
Total LAB Hrs Rm Used
Total Lab & LEC Hrs Rm Used
# Lec Hrs X % Seats
Filled
# Lab Hrs X % Seats
Filled
Weekly Hours of
Room Use
MDP 8010 D103 156 136 87.2% 79.75 79.75 69.5 0.0 70MDP 8010 D115 120 45 37.5% 20 20 7.5 0.0 8MDP 8010 D116 1,394 946 67.9% 49.75 49.75 33.8 0.0 34MDP 8010 D117 1,520 993 65.3% 40.5 40.5 26.5 0.0 26MDP 8010 D118 1,368 1,051 76.8% 39 39 30.0 0.0 30MDP 8010 D135 360 264 73.3% 46 18 64 33.7 13.2 47MDP 8010 D136 630 472 74.9% 49.5 11 60.5 37.1 8.2 45MDP 8010 D138 120 44 36.7% 6 6 2.2 0.0 2MDP 8010 D145 1,312 965 73.6% 34 34 25.0 0.0 25MDP 8010 D146 1,394 984 70.6% 36.5 36.5 25.8 0.0 26MDP 8020 C114 160 118 73.8% 2.25 3.75 6 1.7 2.8 4MDP 8020 C115 285 257 90.2% 10.75 6 16.75 9.7 5.4 15MDP 8020 C119 408 380 93.1% 16.75 16.75 15.6 0.0 16MDP 8020 C120 576 555 96.4% 21.25 0.75 22 20.5 0.7 21MDP 8020 C122 520 490 94.2% 34.5 34.5 32.5 0.0 33MDP 8020 C144 350 274 78.3% 15.25 15.25 30.5 11.9 11.9 24MDP 8020 C147 840 807 96.1% 29 29 27.9 0.0 28MDP 8025 E112 1,960 1,439 73.4% 47 47 34.5 0.0 35MDP 8025 E113 1,617 1,315 81.3% 36.75 36.75 29.9 0.0 30MDP 8030 B102 1,122 879 78.3% 35.75 35.75 28.0 0.0 28MDP 8030 B107 1,024 859 83.9% 34 34 28.5 0.0 29MDP 8030 B108 952 727 76.4% 33.5 33.5 25.6 0.0 26MDP 8030 B109 1,015 785 77.3% 36.25 36.25 28.0 0.0 28MDP 8030 B110 960 764 79.6% 34 34 27.1 0.0 27MDP 8030 B111 900 857 95.2% 33 33 31.4 0.0 31MDP 8030 B112 840 692 82.4% 32 32 26.4 0.0 26MDP 8030 B113 690 505 73.2% 26.25 26.25 19.2 0.0 19MDP 8030 B114 660 518 78.5% 24.5 24.5 19.2 0.0 19MDP 8030 B115 672 682 101.5% 3.5 38 41.5 3.6 38.6 42MDP 8095 MECP14 60 46 76.7% 3.5 3.5 2.7 0.0 3MDP 8095 MECP19 60 52 86.7% 2.5 2.5 2.2 0.0 2MDP 8096 10 90 42 46.7% 4.5 4.5 2.1 0.0 2MDP 8096 17 150 55 36.7% 4.5 3 7.5 1.7 1.1 3
24,285 18,998 78.2%736 576 78.2% 28 12 40 22 10 24
31
MDP Total
MDP Average Weekly Hours of Station Use (Total Lab, Lec Hrs * % Seats Filled)
MDP Averages
2
Space Utilization for EPCC, Spring 2011
Campus BLDG ROOMTotal Banner
StationsSeats
% Seats Filled (Seats/Total
Banner Stations)
Total LEC Hrs Rm Used
Total LAB Hrs Rm Used
Total Lab & LEC Hrs Rm Used
# Lec Hrs X % Seats
Filled
# Lab Hrs X % Seats
Filled
Weekly Hours of
Room Use
NWC 7010 M45 1,536 833 54.2% 24 24 13.0 0.0 13NWC 7010 M48 1,400 1,092 78.0% 33.25 33.25 25.9 0.0 26NWC 7010 M49 960 836 87.1% 33.5 33.5 29.2 0.0 29NWC 7010 M50 570 576 101.1% 16.25 16.25 16.4 0.0 16NWC 7010 M56 1,150 710 61.7% 27.25 27.25 16.8 0.0 17NWC 7010 M57 1,850 1,112 60.1% 33.25 1.5 34.75 20.0 0.9 21NWC 7010 M61 900 656 72.9% 31.5 31.5 23.0 0.0 23NWC 7010 M66B 160 116 72.5% 9 9 6.5 0.0 7NWC 7010 M82 588 174 29.6% 14.25 1.5 15.75 4.2 0.4 5NWC 7010 M83 340 125 36.8% 8.75 6 14.75 3.2 2.2 5NWC 7010 M89 552 522 94.6% 24.25 24.25 22.9 0.0 23NWC 7010 M90 576 531 92.2% 24 24 22.1 0.0 22NWC 7010 M93 408 365 89.5% 18.25 18.25 16.3 0.0 16NWC 7010 M94 288 263 91.3% 12 12 11.0 0.0 11NWC 7010 M95 162 138 85.2% 8.25 8.25 7.0 0.0 7NWC 7030 C201 682 510 74.8% 24.5 24.5 18.3 0.0 18NWC 7030 C202 234 200 85.5% 17.75 17.75 15.2 0.0 15NWC 7030 C203 589 397 67.4% 16.25 16.25 11.0 0.0 11NWC 7030 C205 558 449 80.5% 16.5 16.5 13.3 0.0 13NWC 7030 C209 899 769 85.5% 41.75 41.75 35.7 0.0 36NWC 7030 C210 459 409 89.1% 19.75 19.75 17.6 0.0 18NWC 7030 C211 713 633 88.8% 24.25 24.25 21.5 0.0 22NWC 7030 C212 496 403 81.3% 14.5 2.5 17 11.8 2.0 14NWC 7030 C215 620 488 78.7% 25 25 19.7 0.0 20NWC 7030 C223 775 695 89.7% 14 31.25 45.25 12.6 28.0 41NWC 7030 C224 312 220 70.5% 11.25 11.5 22.75 7.9 8.1 16NWC 7030 C229 1,152 907 78.7% 14 38 52 11.0 29.9 41NWC 7095 P-1 300 160 53.3% 12 12 6.4 0.0 6NWC 7095 P-11 150 59 39.3% 6 6 2.4 0.0 2NWC 7095 P-13 60 50 83.3% 3 3 2.5 0.0 3NWC 7095 P-2 60 12 20.0% 3 3 0.6 0.0 1NWC 7095 P-21 300 188 62.7% 11.25 11.25 7.1 0.0 7NWC 7095 P-5 240 143 59.6% 9 9 5.4 0.0 5
20,039 14,741 73.6%607 447 73.6% 18 13 31 14 10 16
23
NWC TotalNWC Averages
NWC Average Weekly Hours of Station Use (Total Lab, Lec Hrs * % Seats Filled)
3
Space Utilization for EPCC, Spring 2011
Campus BLDG ROOMTotal Banner
StationsSeats
% Seats Filled (Seats/Total
Banner Stations)
Total LEC Hrs Rm Used
Total LAB Hrs Rm Used
Total Lab & LEC Hrs Rm Used
# Lec Hrs X % Seats
Filled
# Lab Hrs X % Seats
Filled
Weekly Hours of
Room Use
RG 4010 A002 1,435 875 61.0% 36.25 36.25 22.1 0.0 22RG 4010 A004 336 211 62.8% 27 12 39 17.0 7.5 24RG 4010 A112 600 354 59.0% 15 13.5 28.5 8.9 8.0 17RG 4010 A116 120 92 76.7% 10.5 7 17.5 8.1 5.4 13RG 4010 A117 252 112 44.4% 14.75 14.75 6.6 0.0 7RG 4010 A124 962 774 80.5% 35.75 35.75 28.8 0.0 29RG 4010 A126 1,488 1,184 79.6% 31.25 31.25 24.9 0.0 25RG 4010 A127 1,134 834 73.5% 30.25 30.25 22.2 0.0 22RG 4010 A228 952 809 85.0% 33 1.5 34.5 28.0 1.3 29RG 4010 A230 1,036 888 85.7% 44 44 37.7 0.0 38RG 4010 A232 1,120 1,024 91.4% 37.25 37.25 34.1 0.0 34RG 4010 A236 144 159 110.4% 43 43 47.5 0.0 47RG 4010 A239 1,770 1,126 63.6% 83.5 3.5 87 53.1 2.2 55RG 4010 A241 624 518 83.0% 45.5 45.5 37.8 0.0 38RG 4010 A243 180 157 87.2% 18.75 15.5 34.25 16.4 13.5 30RG 4010 A245 512 590 115.2% 53 53 61.1 0.0 61RG 4020 B202 1,080 861 79.7% 45 45 35.9 0.0 36RG 4020 B205 1,722 1,184 68.8% 49 49 33.7 0.0 34RG 4020 B210 1,806 1,301 72.0% 47.25 47.25 34.0 0.0 34RG 4020 B211 1,596 1,163 72.9% 42.5 42.5 31.0 0.0 31RG 4020 B217A 570 340 59.6% 38.5 6 44.5 23.0 3.6 27RG 4020 B217B 754 664 88.1% 26.5 7 33.5 23.3 6.2 30RG 4020 B300A 24 22 91.7% 0.75 1.25 2 0.7 1.1 2RG 4020 B300B 360 310 86.1% 17.75 11.75 29.5 15.3 10.1 25RG 4020 B303 216 131 60.6% 17 17 10.3 0.0 10RG 4020 B304 1,764 1,415 80.2% 43.5 43.5 34.9 0.0 35RG 4020 B307 162 66 40.7% 8 4.75 12.75 3.3 1.9 5RG 4020 B309 132 96 72.7% 16.25 2.25 18.5 11.8 1.6 13RG 4020 B400 442 365 82.6% 24.75 24.75 20.4 0.0 20RG 4020 B403 36 36 100.0% 2.5 2.5 2.5 0.0 3RG 4020 B408 416 392 94.2% 21 21 19.8 0.0 20RG 4020 B409 1,344 953 70.9% 40 40 28.4 0.0 28RG 4020 B412B 360 340 94.4% 14.25 14.25 13.5 0.0 13RG 4020 B509 240 220 91.7% 12.5 12.5 11.5 0.0 11RG 4020 B510 408 366 89.7% 17.25 17.25 15.5 0.0 15RG 4020 B516 330 251 76.1% 14.25 14.25 10.8 0.0 11RG 4020 B517 775 748 96.5% 31.25 31.25 30.2 0.0 30RG 4050 E111 38 16 42.1% 2.5 2.5 1.1 0.0 1RG 4050 E115 928 767 82.7% 27.75 27.75 22.9 0.0 23RG 4080 H014 444 212 47.7% 7 2 9 3.3 1.0 4RG 4080 H015 148 124 83.8% 2.5 2.5 2.1 0.0 2RG 4080 H118 160 86 53.8% 9.75 6.25 16 5.2 3.4 9RG 4080 H157 750 165 22.0% 13 36 49 2.9 7.9 11
4
Space Utilization for EPCC, Spring 2011
Campus BLDG ROOMTotal Banner
StationsSeats
% Seats Filled (Seats/Total
Banner Stations)
Total LEC Hrs Rm Used
Total LAB Hrs Rm Used
Total Lab & LEC Hrs Rm Used
# Lec Hrs X % Seats
Filled
# Lab Hrs X % Seats
Filled
Weekly Hours of
Room Use
RG 4080 H158 48 44 91.7% 7 7 6.4 0.0 6RG 4080 H206 200 71 35.5% 11 22.5 33.5 3.9 8.0 12RG 4080 H226 736 398 54.1% 11.75 16.5 28.25 6.4 8.9 15RG 4080 H233 240 220 91.7% 60 60 55.0 0.0 55RG 4080 H234 442 282 63.8% 27 6 33 17.2 3.8 21RG 4080 H238 600 538 89.7% 7.5 37.5 45 6.7 33.6 40RG 4080 H242 1,080 875 81.0% 23.25 28.25 51.5 18.8 22.9 42RG 4080 H248 780 615 78.8% 19.25 23.75 43 15.2 18.7 34RG 7010 M62 528 415 78.6% 29 2 31 22.8 1.6 24
34,324 25,759 75.0%660 495 75.0% 26 12 38 20 8 24
29
RG TotalRG Averages
RG Average Weekly Hours of Station Use (Total Lab, Lec Hrs * % Seats Filled)
5
Space Utilization for EPCC, Spring 2011
Campus BLDG ROOMTotal Banner
StationsSeats
% Seats Filled (Seats/Total
Banner Stations)
Total LEC Hrs Rm Used
Total LAB Hrs Rm Used
Total Lab & LEC Hrs Rm Used
# Lec Hrs X % Seats
Filled
# Lab Hrs X % Seats
Filled
Weekly Hours of
Room Use
TM 3020 1605 20 24 120.0% 2.5 2.5 3.0 0.0 3TM 3025 1123 1,152 769 66.8% 37 37 24.7 0.0 25TM 3025 1124 1,240 829 66.9% 46.25 46.25 30.9 0.0 31TM 3025 1125 1,400 851 60.8% 42.25 42.25 25.7 0.0 26TM 3025 1126 1,280 994 77.7% 35 35 27.2 0.0 27TM 3025 1127 1,160 815 70.3% 34.75 34.75 24.4 0.0 24TM 3025 1128 1,560 1,153 73.9% 40.25 40.25 29.7 0.0 30TM 3025 1130 171 136 79.5% 9.75 9.75 7.8 0.0 8TM 3025 1131 1,600 1,146 71.6% 44 44 31.5 0.0 32TM 3040 1700 1,320 1,011 76.6% 33.75 33.75 25.8 0.0 26TM 3040 1702 140 80 57.1% 9.5 7 16.5 5.4 4.0 9TM 3040 1703 72 38 52.8% 3.25 4.25 7.5 1.7 2.2 4TM 3040 1800 840 554 66.0% 18.75 18.75 12.4 0.0 12TM 3040 1801 1,240 700 56.5% 33.25 33.25 18.8 0.0 19TM 3040 1806 1,360 989 72.7% 41 41 29.8 0.0 30TM 3040 1807 120 33 27.5% 2.25 2.25 0.6 0.0 1TM 3040 1808 920 666 72.4% 21.25 21.25 15.4 0.0 15TM 3040 1809 1,160 807 69.6% 28.75 28.75 20.0 0.0 20TM 3040 1810 936 675 72.1% 29.5 29.5 21.3 0.0 21TM 3040 1811 460 323 70.2% 31.5 31.5 22.1 0.0 22TM 3040 1812 1,080 560 51.9% 38.25 38.25 19.8 0.0 20TM 3040 1813 1,080 763 70.6% 26.25 26.25 18.5 0.0 19TM 3050 1500 560 514 91.8% 19.75 29.25 49 18.1 26.8 45TM 3050 1505 896 513 57.3% 15 34 49 8.6 19.5 28TM 3050 1510 2,280 609 26.7% 59 53 112 15.8 14.2 30TM 3050 1515 440 257 58.4% 11.75 16.25 28 6.9 9.5 16TM 3050 1517 1,480 1,381 93.3% 41.75 41.75 39.0 0.0 39TM 3050 1544 144 109 75.7% 12.5 2.25 14.75 9.5 1.7 11TM 3060 1200 112 84 75.0% 7 7 14 5.3 5.3 11TM 3060 1206 104 68 65.4% 7.75 7.25 15 5.1 4.7 10TM 3060 1207 24 22 91.7% 1.25 1.25 1.1 0.0 1TM 3060 1210 475 399 84.0% 19.25 19.25 16.2 0.0 16TM 3060 1211 351 291 82.9% 11.75 11.75 9.7 0.0 10TM 3060 1213 552 404 73.2% 25 1.75 26.75 18.3 1.3 20TM 3060 1238 506 449 88.7% 30.25 30.25 26.8 0.0 27TM 3060 1239 315 307 97.5% 37.25 2.5 39.75 36.3 2.4 39TM 3064 1307 1,530 481 31.4% 50.25 50.25 15.8 0.0 16TM 3064 1308 160 193 120.6% 5 12.5 17.5 6.0 15.1 21TM 3064 1309 440 433 98.4% 24.5 24.5 24.1 0.0 24TM 3070 1404 300 54 18.0% 2.25 2.25 4.5 0.4 0.4 1TM 3070 1405 630 207 32.9% 18.25 18.25 6.0 0.0 6
31,610 20,691 65.5%771 505 65.5% 25 14 38 17 8 19TM Averages
TM Total
6
Space Utilization for EPCC, Spring 2011
25
TM Average Weekly Hours of Station Use (Total Lab, Lec Hrs* % Seats Filled)
7
Space Utilization for EPCC, Spring 2011
Campus BLDG ROOMTotal Banner
StationsSeats
% Seats Filled (Seats/Total
Banner Stations)
Total LEC Hrs Rm Used
Total LAB Hrs Rm Used
Total Lab & LEC Hrs Rm Used
# Lec Hrs X % Seats
Filled
# Lab Hrs X % Seats
Filled
Weekly Hours of
Room Use
VV 2019 101 270 110 40.7% 60 60 24.4 0.0 24VV 2019 102 24 5 20.8% 8 8 1.7 0.0 2VV 2019 103 2,352 84 3.6% 70 70 2.5 0.0 3VV 2019 105 551 314 57.0% 40 40 22.8 0.0 23VV 2019 106 32 14 43.8% 7 7 3.1 0.0 3VV 2019 118 270 170 63.0% 60 60 37.8 0.0 38VV 2019 119 180 70 38.9% 40 40 15.6 0.0 16VV 2019 121 1,860 375 20.2% 22 22 4.4 0.0 4VV 2019 206 170 60 35.3% 40 40 14.1 0.0 14VV 2019 207 200 88 44.0% 27.5 27.5 12.1 0.0 12VV 2019 208 220 112 50.9% 43.75 43.75 22.3 0.0 22VV 2019 216 700 245 35.0% 20 20 7.0 0.0 7VV 2019 219 900 405 45.0% 60 60 27.0 0.0 27VV 2019 220 675 325 48.1% 20 20 9.6 0.0 10VV 2019 314 196 135 68.9% 19.25 19.25 13.3 0.0 13VV 2019 317 224 203 90.6% 22 22 19.9 0.0 20VV 2019 318 252 209 82.9% 5.5 7.75 13.25 4.6 6.4 11VV 2019 321 28 20 71.4% 2 2 1.4 0.0 1VV 2019 408 448 346 77.2% 19 31 50 14.7 23.9 39VV 2020 C401 220 116 52.7% 20.25 20.25 10.7 0.0 11VV 2025 B100 1,870 1,510 80.7% 54.25 54.25 43.8 0.0 44VV 2025 B101 1,734 1,267 73.1% 53.75 1.5 55.25 39.3 1.1 40VV 2025 B102 1,632 1,169 71.6% 57.75 2.25 60 41.4 1.6 43VV 2025 B103 1,802 1,234 68.5% 65 0.75 65.75 44.5 0.5 45VV 2025 B104 1,666 1,120 67.2% 62 62 41.7 0.0 42VV 2025 B105 1,700 1,316 77.4% 60.5 60.5 46.8 0.0 47VV 2025 B106 1,692 1,313 77.6% 49.5 49.5 38.4 0.0 38VV 2025 B107 1,734 1,339 77.2% 52.5 52.5 40.5 0.0 41VV 2025 B108 1,512 1,115 73.7% 52 52 38.3 0.0 38VV 2025 B109 1,632 1,179 72.2% 64.5 1.5 66 46.6 1.1 48VV 2025 B110 1,088 803 73.8% 38.25 38.25 28.2 0.0 28VV 2025 B123 744 601 80.8% 37.25 37.25 30.1 0.0 30VV 2025 B124 864 666 77.1% 41.5 2.5 44 32.0 1.9 34VV 2025 B130 1,961 1,727 88.1% 58.75 58.75 51.7 0.0 52VV 2025 B131 1,776 1,605 90.4% 54 54 48.8 0.0 49VV 2025 B132 1,776 1,610 90.7% 52 52 47.1 0.0 47VV 2025 B133 1,628 1,135 69.7% 41.25 3 44.25 28.8 2.1 31VV 2025 B150 1,702 1,544 90.7% 57.75 57.75 52.4 0.0 52VV 2025 B151 216 90 41.7% 28 28 11.7 0.0 12VV 2025 B152 125 42 33.6% 12 12 4.0 0.0 4VV 2025 B153 192 95 49.5% 28 28 13.9 0.0 14VV 2025 B161 108 108 100.0% 4.5 4.5 4.5 0.0 5VV 2025 B162 36 30 83.3% 2.5 2.5 2.1 0.0 2
8
Space Utilization for EPCC, Spring 2011
Campus BLDG ROOMTotal Banner
StationsSeats
% Seats Filled (Seats/Total
Banner Stations)
Total LEC Hrs Rm Used
Total LAB Hrs Rm Used
Total Lab & LEC Hrs Rm Used
# Lec Hrs X % Seats
Filled
# Lab Hrs X % Seats
Filled
Weekly Hours of
Room Use
VV 2025 B163 782 656 83.9% 38.75 38.75 32.5 0.0 33VV 2025 B164 486 409 84.2% 18 9.75 27.75 15.1 8.2 23VV 2025 B170 1,386 1,161 83.8% 49.5 49.5 41.5 0.0 41VV 2025 B171 1,116 788 70.6% 43.75 43.75 30.9 0.0 31VV 2025 B180 1,435 1,034 72.1% 56 56 40.4 0.0 40VV 2025 B181 1,462 1,129 77.2% 49.5 0.75 50.25 38.2 0.6 39VV 2025 B182 1,260 980 77.8% 44.5 0.75 45.25 34.6 0.6 35VV 2025 B183 918 286 31.2% 57 57 17.8 0.0 18VV 2025 B184 23 20 87.0% 5 5 4.3 0.0 4VV 2025 B185 1,287 1,063 82.6% 38.25 38.25 31.6 0.0 32VV 2025 B186 1,254 1,005 80.1% 37 1.5 38.5 29.7 1.2 31VV 2025 B187 1,122 778 69.3% 46 46 31.9 0.0 32VV 2025 B188 1,088 907 83.4% 33.75 33.75 28.1 0.0 28VV 2025 B254 364 148 40.7% 13 11.75 24.75 5.3 4.8 10VV 2025 B256 640 286 44.7% 17.5 10.5 28 7.8 4.7 13VV 2030 11A 464 401 86.4% 46 46 39.8 0.0 40VV 2030 11B 608 424 69.7% 50 50 34.9 0.0 35VV 2030 13A 304 254 83.6% 60 60 50.1 0.0 50VV 2030 13B 544 438 80.5% 46 46 37.0 0.0 37VV 2030 14 1,596 835 52.3% 44 44 23.0 0.0 23VV 2030 15A 544 441 81.1% 50 50 40.5 0.0 41VV 2030 15B 400 310 77.5% 54 54 41.9 0.0 42VV 2030 16 1,176 595 50.6% 41.25 41.25 20.9 0.0 21VV 2030 17 1,470 864 58.8% 53.25 53.25 31.3 0.0 31VV 2030 18 1,092 548 50.2% 34 34 17.1 0.0 17VV 2030 19 672 318 47.3% 52.25 52.25 24.7 0.0 25VV 2030 20 840 715 85.1% 28.5 28.5 24.3 0.0 24VV 2030 21 1,050 550 52.4% 57.5 57.5 30.1 0.0 30VV 2030 22 1,050 540 51.4% 30 30 15.4 0.0 15VV 2030 24 756 178 23.5% 7 11 18 1.6 2.6 4VV 2030 25A 496 490 98.8% 34.25 34.25 33.8 0.0 34VV 2030 25B 400 305 76.3% 30 30 22.9 0.0 23VV 2030 28 1,344 828 61.6% 39.75 39.75 24.5 0.0 24VV 2030 29 1,260 698 55.4% 38 38 21.1 0.0 21VV 2030 30A 480 379 79.0% 43.5 43.5 34.3 0.0 34VV 2030 30B 80 76 95.0% 9 9 8.6 0.0 9VV 2030 31A 880 709 80.6% 44 44 35.5 0.0 35VV 2030 31B 496 411 82.9% 67.25 67.25 55.7 0.0 56VV 2030 5A 304 277 91.1% 19.25 19.25 17.5 0.0 18VV 2030 5B 224 215 96.0% 39.25 39.25 37.7 0.0 38VV 2030 7A 448 349 77.9% 35.75 1.75 37.5 27.8 1.4 29VV 2030 7B 176 172 97.7% 13.5 13.5 13.2 0.0 13VV 2030 9A 32 29 90.6% 6 6 5.4 0.0 5VV 2030 9B 496 407 82.1% 47.25 47.25 38.8 0.0 39
9
Space Utilization for EPCC, Spring 2011
Campus BLDG ROOMTotal Banner
StationsSeats
% Seats Filled (Seats/Total
Banner Stations)
Total LEC Hrs Rm Used
Total LAB Hrs Rm Used
Total Lab & LEC Hrs Rm Used
# Lec Hrs X % Seats
Filled
# Lab Hrs X % Seats
Filled
Weekly Hours of
Room Use
VV 2040 A1101 1,170 891 76.2% 43.5 1.75 45.25 33.1 1.3 34VV 2040 A1114 80 67 83.8% 8 10 18 6.7 8.4 15VV 2040 A1117 1,036 817 78.9% 36.25 1.5 37.75 28.6 1.2 30VV 2040 A1118 594 341 57.4% 12.25 12.25 7.0 0.0 7VV 2040 A1120 1,380 1,162 84.2% 50.75 0.75 51.5 42.7 0.6 43VV 2040 A1121 480 329 68.5% 24.5 5 29.5 16.8 3.4 20VV 2040 A1122 1,380 1,018 73.8% 48.5 48.5 35.8 0.0 36VV 2040 A1124 1,232 1,165 94.6% 48 48 45.4 0.0 45VV 2040 A1126 272 199 73.2% 14.5 9.75 24.25 10.6 7.1 18VV 2040 A1129 414 346 83.6% 26 12.25 38.25 21.7 10.2 32VV 2040 A1130 1,680 1,214 72.3% 37.25 37.25 26.9 0.0 27VV 2040 A1131 1,120 889 79.4% 37.5 37.5 29.8 0.0 30VV 2040 A1201 3,007 175 5.8% 7.5 47 54.5 0.4 2.7 3VV 2040 A1215 1,144 484 42.3% 43.25 20.75 64 18.3 8.8 27VV 2040 A1301 1,066 896 84.1% 44.75 44.75 37.6 0.0 38VV 2040 A1317 1,378 1,270 92.2% 55.75 55.75 51.4 0.0 51VV 2040 A1318 432 237 54.9% 43 43 23.6 0.0 24VV 2040 A1319 1,500 1,320 88.0% 59.5 59.5 52.4 0.0 52VV 2040 A1320 690 348 50.4% 54.25 54.25 27.4 0.0 27VV 2040 A1326 330 123 37.3% 30.5 30.5 11.4 0.0 11VV 2040 A1331 945 824 87.2% 39.25 39.25 34.2 0.0 34VV 2040 A1332 624 208 33.3% 12 31.5 43.5 4.0 10.5 15VV 2040 A1333 735 374 50.9% 31 18.5 49.5 15.8 9.4 25VV 2040 A2101 1,032 653 63.3% 49.75 2.5 52.25 31.5 1.6 33VV 2040 A2114 806 643 79.8% 34.5 0.75 35.25 27.5 0.6 28VV 2040 A2116 1,260 1,170 92.9% 46 46 42.7 0.0 43VV 2040 A2117 1,394 1,083 77.7% 42 2.75 44.75 32.6 2.1 35VV 2040 A2118 1,938 1,757 90.7% 60.25 60.25 54.6 0.0 55VV 2040 A2119 1,584 1,485 93.8% 53 53 49.7 0.0 50VV 2040 A2120 1,092 1,067 97.7% 38.25 38.25 37.4 0.0 37VV 2040 A2121 1,683 1,552 92.2% 60.25 60.25 55.6 0.0 56VV 2040 A2122 1,612 1,412 87.6% 65 65 56.9 0.0 57VV 2040 A2124 962 873 90.7% 39.75 39.75 36.1 0.0 36VV 2040 A2125 1,560 1,505 96.5% 59 59 56.9 0.0 57VV 2040 A2126 1,620 1,519 93.8% 81.75 81.75 76.7 0.0 77VV 2040 A2127 2,173 2,065 95.0% 61.75 61.75 58.7 0.0 59VV 2040 A2128 1,911 1,833 95.9% 59.75 59.75 57.3 0.0 57VV 2040 A2301 1,110 1,020 91.9% 41 41 37.7 0.0 38VV 2040 A2314 150 129 86.0% 9.5 9.5 8.2 0.0 8VV 2040 A2317 1,188 1,030 86.7% 47.75 47.75 41.4 0.0 41VV 2040 A2318 696 597 85.8% 31.75 31.75 27.2 0.0 27VV 2040 A2319 696 589 84.6% 25.75 4.75 30.5 21.8 4.0 26VV 2040 A2322 540 280 51.9% 18 2.5 20.5 9.3 1.3 11VV 2040 A2324 1,353 1,108 81.9% 53.75 53.75 44.0 0.0 44
10
Space Utilization for EPCC, Spring 2011
Campus BLDG ROOMTotal Banner
StationsSeats
% Seats Filled (Seats/Total
Banner Stations)
Total LEC Hrs Rm Used
Total LAB Hrs Rm Used
Total Lab & LEC Hrs Rm Used
# Lec Hrs X % Seats
Filled
# Lab Hrs X % Seats
Filled
Weekly Hours of
Room Use
VV 2040 A2325 680 309 45.4% 24.25 0.75 25 11.0 0.3 11VV 2040 A2326 648 515 79.5% 33 33 26.2 0.0 26VV 2050 A1509 255 82 32.2% 10 10.75 20.75 3.2 3.5 7VV 2050 A1510 1,968 1,462 74.3% 43.75 43.75 32.5 0.0 33VV 2050 A1511 465 205 44.1% 18.75 18.75 37.5 8.3 8.3 17VV 2050 A1512 465 236 50.8% 18 17.5 35.5 9.1 8.9 18VV 2050 A1515 500 389 77.8% 26 26 20.2 0.0 20VV 2050 A1517 315 321 101.9% 31 3.75 34.75 31.6 3.8 35VV 2050 A1518 456 241 52.9% 18 22 40 9.5 11.6 21VV 2050 A1523 256 250 97.7% 16.5 11.5 28 16.1 11.2 27VV 2050 A1607 264 158 59.8% 6 33.75 39.75 3.6 20.2 24VV 2050 A1701 264 157 59.5% 4 37.5 41.5 2.4 22.3 25VV 2050 A1702 210 188 89.5% 21 1.5 22.5 18.8 1.3 20VV 2050 A1711 672 601 89.4% 35 35 31.3 0.0 31VV 2050 A1712 1,225 682 55.7% 76.75 1.5 78.25 42.7 0.8 44VV 2050 A1713 775 381 49.2% 58.25 58.25 28.6 0.0 29VV 2050 A1722 242 190 78.5% 18.25 18.25 14.3 0.0 14VV 2050 A1723 270 251 93.0% 23 1.5 24.5 21.4 1.4 23VV 2050 A1724 546 395 72.3% 19.25 1.5 20.75 13.9 1.1 15VV 2050 A2509 720 595 82.6% 5 24 29 4.1 19.8 24VV 2050 A2511 1,056 782 74.1% 26.5 28.25 54.75 19.6 20.9 41VV 2050 A2513 864 780 90.3% 35.5 20.5 56 32.0 18.5 51VV 2050 A2515 896 690 77.0% 23.75 28.25 52 18.3 21.8 40VV 2050 A2518 3,036 2,581 85.0% 51.5 51.5 43.8 0.0 44VV 2050 A2519 132 64 48.5% 16.5 16.5 8.0 0.0 8VV 2050 A2704 408 245 60.0% 15 4.75 19.75 9.0 2.9 12VV 2050 A2707 192 90 46.9% 9.25 1.75 11 4.3 0.8 5VV 2050 A2708 168 71 42.3% 5.75 3.5 9.25 2.4 1.5 4VV 2050 A2721 1,044 890 85.2% 2.5 61.25 63.75 2.1 52.2 54VV 2070 G102 1,040 300 28.8% 27 27 7.8 0.0 8VV 2070 G103 306 180 58.8% 4.75 12 16.75 2.8 7.1 10VV 2070 G104 1,900 303 15.9% 9.75 9.5 19.25 1.6 1.5 3
144,554 102,081 70.6%887 626 70.6% 36 11 47 26 7 28
33
Source: Student Banner Files; Run Dates: October 24-November 4, 2011
VV Total
VV Average Weekly Hours of Station Use (Total Lab, Lec Hrs* % Seats Filled)
VV Averages
11
Appendix B –
Facilities Condition
Assessment and Master Plan Summary
Appendix C –
Administrative Services Center
Condition Assessment Report
Facilities Condition AssessmentAdministrative Services Center Condition Assessment
1Magellan Consulting, Inc.
Administrative Services Center Condition Assessment
6020 Building B 186,283 1956 $1,904,730 5.33% $10.22 $2,249
6030 KCOS 4,000 2007 $0 .00% $0.00 $0
6010 Building A 187,430 1956 $2,960,618 9.26% $15.80 $369,641
Site 0 0 $1,190,684 .00% $0.00 $0
Totals 377,713 $6,056,032 8.87% $16.03 $371,890
Facility Condition by Building
Number Building Name Gross Sq Ft Built DateFacility Condition
Cost FCICost Per
Square FootFuture Life Cycle
Cost (Yr 1-5)
The Administrative Services Center Facility located at 9050 Viscount Blvd. in El Paso, Texas, was built in 1956. It comprises approximately 377,713 gross square feet.
Summary of Findings
The total current deficiencies for this site, in 2008 construction cost dollars, are estimated at $6,056,032.
Cross Tab of Current Deficiencies
The following chart summarizes the current deficiencies for this site in a cross tab that shows the buildings systems down the left and the priority of the deficiency across the top. This listing includes current deficiencies including deferred maintenance, functional deficiencies, code compliance, Americans with Disabilities Act, and Life Cycle Capital Renewal categories.
Electrical - $78,677 $47,724 $166,181 - $292,581
Mechanical - $135,615 $398,130 - $19,570 $553,316
Interior - $9,393 $47,467 $883 $65,635 $123,378
Plumbing - - $103,465 - - $103,465
Conveyances - - - - - $0
Technology - - - - - $0
Fire and Life Safety - - - - - $0
Site - $51,528 - $1,267,885 $125,540 $1,444,953
Specialties - - - - - $0
Other - - - - - $0
Exterior - $61,673 $11,739 - $225,558 $298,970
Structural - - - - - $0
Roofing $3,232,078 $7,291 - - - $3,239,369
Total $3,232,078 $344,177 $608,526 $1,434,948 $436,303 $6,056,032
Facility Condition - System by PriorityPriority
System 1 2 3 4 5 Total
Facilities Condition AssessmentAdministrative Services Center Condition Assessment
2Magellan Consulting, Inc.
Portable Buildings - - - - - $0
New Construction - - - - - $0
Hazardous Material - - - - - $0
Functional Deficiency - $1,243 $6,985 $7,595 $52,589 $68,412
Energy Efficiency - $181,945 $398,130 $166,181 - $746,256
Educational Adequacy - - - - - $0
Deferred Maintenance - $56,522 $59,463 $20,892 $133,401 $270,277
Code Compliance - - - - $16,995 $16,995
Capital Renewal $3,232,078 $96,316 $40,482 $1,240,281 $223,733 $4,832,890
ADA Compliance - $8,150 $103,465 - $9,586 $121,201
Total $3,232,078 $344,177 $608,526 $1,434,948 $436,303 $6,056,032
Facility Condition - Category by PriorityPriority
Category 1 2 3 4 5 Total
All deficiencies have been further categorized according to the type of deficiency observed. Capital Renewal items include those that are included in the life cycle forecast and are items that have reached or exceeded their useful life. Americans with Disabilities Act deficiencies are associated with accessibility compliance concerns. Code Compliance includes items that are a building code related deficiency. Deferred Maintenance items are those items that have broken or are in need of repair prior to reaching the end of life term. A Functional Deficiency is one that is presently not in place, or is not functioning correctly, and should be added to the building.
Life Cycle Capital Renewal Forecast
As part of the assessment process, this facility was analyzed according to twelve major building systems. Each system has subsystems, and each subsystem is further distinguished by type. For each line item, the original year, or most recent replacement year if applicable, was identified. Then, the historical life was compared to a model of expected life for each subsystem type. The remaining year was then forecasted by subtracting the expected life from the life used, and further adjusted for the apparent maintenance quality of the subsystem. In some cases, the calculation was overridden if the assessor’s judgment suggested a shorter or longer than expected life expectancy.
Once each subsystem was analyzed, they were combined to provide a 10-year life cycle capital renewal forecast for the building. The following chart shows all deficiencies and the subsequent year’s capital renewal projections for all systems where a component is expected to reach the end of its useful life and require capital dollars for replacement.
The chart on the following page shows the forecast in thousands ($000s) for the next ten years.
Facilities Condition AssessmentAdministrative Services Center Condition Assessment
3Magellan Consulting, Inc.
Fire and Life Safety 0 0 0 0 0 199 0 0 0 0 199 $399 $1.19
Plumbing 103 0 0 0 0 0 0 0 21 0 0 $21 $0.06
Electrical 293 0 0 45 0 0 0 0 22 0 2 $70 $0.21
Technology 0 0 0 0 0 80 80 0 48 0 159 $367 $1.09
Other 0 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Specialties 0 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Conveyances 0 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Mechanical 553 0 0 0 0 0 0 0 6 0 478 $484 $1.44
Roofing 3,239 0 0 6 0 0 0 0 0 0 0 $6 $0.02
Site 1,445 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Structural 0 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Interior 123 0 0 0 0 2 438 0 104 15 1,053 $1,612 $4.80
Exterior 299 0 0 0 0 40 7 0 95 0 40 $182 $0.54
Total 6,056 0 0 51 0 321 525 0 296 15 1,933 $3,140 $9.36
Life Cycle Capital Renewal Projections ($000s)
SystemCurrent
DeficienciesYear 1 2008
Year 2 2009
Year 3 2010
Year 4 2011
Year 5 2012
Year 6 2013
Year 7 2014
Year 8 2015
Year 9 2016
Year 10 2017 Total $/GSF
Capital Renewal Forecast
Facilities Condition AssessmentAdministrative Services Center Condition Assessment
4Magellan Consulting, Inc.
Facility Condition Index (FCI)
The Facility Condition Index (FCI) is used throughout the facility condition assessment industry as a general indicator of a building’s health. The FCI is calculated by dividing the Facility Condition Cost plus five years of projected Life Cycle Capital Renewal Costs by the Replacement Value. Costs associated with new construction are not included in the FCI calculation. As a rule of thumb, an FCI below 10% is considered good. An FCI above 65% would suggest that the building is a candidate for replacement.
The Administrative Services Center facility has an overall FCI of 8.87%
Administrative Services Center Condition Assessment
Assessment Findings
The total current cost for all building deficiencies is $6,056,032. There are $1,190,684 in deficiencies at the site level that are included in the FCI calculation. The five year capital renewal cost was $371,890. The cost estimates were derived using a detailed listing of all noted deficiencies in the building. The cost to repair these deficiencies was then estimated using the cost data adjusted to El Paso, Texas (78% of national average).
The Replacement Value represents the estimated cost of replacing the current building with another building of like size, based on today’s estimated cost of construction in the El Paso, Texas area. The replacement cost for this facility is estimated to be $72,490,716.
The following pages provide a listing of all deficiencies and their associated cost for the site and building, followed by photos taken during the assessment.
Facilities Condition AssessmentAdministrative Services Center Condition Assessment
5Magellan Consulting, Inc.
The Power Service Is Inadequate And Should Be Upgraded 20607 900 Amps 3 $47,724 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 20605 36 Ea. 2 $35,095 Yes
The Electrical Circuit Capacity Is Inadequate 20608 168 EACH 4 $158,657 No
Sub Total for System 3 $241,476
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Roof Condenser Is Damaged And Requires Replacement 20603 20 TonAC 2 $44,594 No
The Large Diameter Exhausts/Hoods Are Missing/Damaged And Require Replacement 20602 18 Ea. 2 $30,645 No
Test And Balancing Required 23778 150,000 SF 3 $262,080 No
The Evaporative Cooling Unit Is Damaged And Requires Replacement 20604 15 Ea. 3 $136,051 No
Sub Total for System 4 $473,369
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Doors Require Replacement 20577 4 Door 3 $5,038 No
Interior Gypboard Walls Require Repair 20576 100 SF Wall 4 $883 No
Door is not equiped with Card Key Access 23779 10 Ea. 3 $6,985 No
The Interior Door Hardware is Damaged and Requires Replacement 20578 4 Ea. 2 $4,075 No
Directional / wayfinding signage missing or not accessible. 23757 75 Ea. 5 $9,460 No
The Acoustical Ceilings Tiles Are Damaged And Require Replacement 20575 40 SF 5 $249 No
Acoustical Wall Treatment is missing and is needed 23761 3,000 SF 5 $52,589 No
Sub Total for System 7 $79,279
Deficiency ID Qty UoM Priority Repair Cost WS&D
Interior
The Metal Exterior Door Is Damaged And Requires Replacement 20571 5 Door 2 $11,786 Yes
The Overhead Door Is Damaged And Requires Repair 20572 4 Door 2 $4,335 Yes
The Overhead Door Is Damaged And Requires Repair 20574 1 Door 2 $1,085 Yes
The Exterior Requires Painting 20570 74,799 SF Wall 5 $223,483 No
Exterior door hardware is damaged and should be replaced 20573 5 Door 2 $3,018 Yes
Sub Total for System 5 $243,707
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Pitch Pan Is Damaged And Should Be Replaced 20787 26 Ea. 2 $3,418 Yes
Pitch Pan Is Damaged And Should Be Replaced 20865 26 Ea. 2 $3,873 Yes
The Multi-Ply Bitumen Roof System Is Damaged And Requires Replacement 20600 150,430 SF 1 $1,812,030 No
Sub Total for System 3 $1,819,321
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 6010 - Building A
The Pole Lighting Is Damaged And Should Be Replaced 20651 1 Ea. 2 $8,993 Yes
The Pole Lighting Is Damaged And Should Be Replaced 20606 2 Ea. 2 $17,987 Yes
Sub Total for System 2 $26,980
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Bench is missing and is needed 23765 10 Ea. 4 $7,595 No
Fencing Is Damaged And Should Be Replaced (8' Chain Link Fence) 20565 585 LF 4 $19,461 No
Concrete Walks Are Damaged And Require Replacement 20568 1,000 SF 2 $13,741 Yes
Asphalt Paving Is Damaged And Requires Replacement 20566 407 CAR 4 $1,036,539 No
Site Drainage is Inadequate and Requires Regrading 20564 2,000 SF 4 $548 No
Trash Receptacles Are Damaged And Require Replacement 23763 6 Ea. 5 $6,170 No
Trash Receptacles Are Damaged And Require Replacement 20569 6 Ea. 5 $6,170 No
Paving Requires Restriping 20567 407 CAR 5 $73,481 No
Sub Total for System 8 $1,163,704
Deficiency ID Qty UoM Priority Repair Cost WS&D
Site
Sub Total for School and Site Level 10 $1,190,684
Site Level Deficiencies
Facilities Condition AssessmentAdministrative Services Center Condition Assessment
6Magellan Consulting, Inc.
6030 - KCOS
Buildings with no reported deficiencies
The GFCI Electrical Receptacles Are Inadequate And More Are Needed 20653 12 Ea. 2 $5,879 Yes
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20652 14 Ea. 4 $7,524 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 20650 11 Ea. 2 $10,723 Yes
Sub Total for System 3 $24,126
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Package Unit HVAC Component Is Damaged And Requires Replacement 20649 7 TonAC 2 $18,670 No
The Package Unit HVAC Component Is Damaged And Requires Replacement 20648 15 TonAC 2 $40,005 No
Duct Grill is Damaged And Should Be Replaced 20647 8 Ea. 5 $2,575 No
The Large Diameter Exhausts/Hoods Are Missing/Damaged And Require Replacement 20646 1 Ea. 2 $1,702 No
Exhaust Fan Ventilation Is Missing And Should Be Installed 23777 8 Ea. 5 $16,995 No
Sub Total for System 5 $79,947
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Handrail/Railing is missing and is needed 20879 10 LF 2 $1,243 Yes
The Carpet Flooring Is Damaged And Requires Replacement 20617 1,800 SF 3 $15,894 No
Interior Doors Require Replacement 20615 4 Door 3 $5,038 No
The Interior Door Hardware is Damaged and Requires Replacement 20616 4 Ea. 2 $4,075 No
Directional / wayfinding signage missing or not accessible. 23759 1 Ea. 5 $126 No
The Suspended Ceiling Grid is Damaged And Require Replacement 20613 1,800 SF 3 $14,513 No
Interior Walls Require Repainting 20614 1,200 SF 5 $3,210 No
Sub Total for System 7 $44,099
Deficiency ID Qty UoM Priority Repair Cost WS&D
Interior
The Metal Exterior Door Is Damaged And Requires Replacement 20610 14 Door 2 $33,002 Yes
Exterior door hardware is damaged and should be replaced 20611 14 Door 2 $8,447 Yes
The Exterior Requires Cleaning 18293 1,000 SF Wall 5 $2,075 No
The Brick Exterior Is Damaged And Requires Repair 20609 1,000 SF Wall 3 $11,739 No
Sub Total for System 4 $55,262
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Multi-Ply Bitumen Roof System Is Damaged And Requires Replacement 20644 186,283 SF 1 $1,420,048 No
Sub Total for System 1 $1,420,048
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Asphalt Paving Is Damaged And Requires Replacement 18290 80 CAR 4 $203,742 No
Concrete Walks Are Damaged And Require Replacement 18292 2,750 SF 2 $37,787 Yes
Paving Requires Restriping 18291 220 CAR 5 $39,720 No
Sub Total for System 3 $281,248
SiteDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 6020 - Building B 23 $1,904,730
Building: 6020 - Building B
The Restroom is Not ADA Compliant 23767 4 Ea. 3 $103,465 No
Sub Total for System 1 $103,465
Deficiency ID Qty UoM Priority Repair Cost WS&D
Plumbing
Sub Total for Building 6010 - Building A 23 $2,960,618
Total for Campus 56 $6,056,032
Facilities Condition AssessmentAdministrative Services Center Condition Assessment
7Magellan Consulting, Inc.
Supporting PhotosAdministrative Services Center Condition Assessment
6020 Building B (19) - Photo 6
6020 Building B (15) - Photo 2
6020 Building B (17) - Photo 4
6020 Building B (18) - Photo 5
6020 Building B (14) - Photo 1
6020 Building B (16) - Photo 3
Facilities Condition AssessmentAdministrative Services Center Condition Assessment
8Magellan Consulting, Inc.
6020 Building B (25) - Photo 12
6020 Building B (20) - Photo 8
6020 Building B (22) - Photo 10
6020 Building B (24) - Photo 11
6020 Building B (2) - Photo 7
6020 Building B (21) - Photo 9
Facilities Condition AssessmentAdministrative Services Center Condition Assessment
9Magellan Consulting, Inc.
6020 Building B (30) - Photo 18
6020 Building B (27) - Photo 14
6020 Building B (29) - Photo 16
6020 Building B (3) - Photo 17
6020 Building B (26) - Photo 13
6020 Building B (28) - Photo 15
Facilities Condition AssessmentAdministrative Services Center Condition Assessment
10Magellan Consulting, Inc.
6020 Building B (36) - Photo 24
6020 Building B (32) - Photo 20
6020 Building B (34) - Photo 22
6020 Building B (35) - Photo 23
6020 Building B (31) - Photo 19
6020 Building B (33) - Photo 21
Facilities Condition AssessmentAdministrative Services Center Condition Assessment
11Magellan Consulting, Inc.
6020 Building B (6) - Photo 30
6020 Building B (38) - Photo 26
6020 Building B (4) - Photo 28
6020 Building B (5) - Photo 29
6020 Building B (37) - Photo 25
6020 Building B (39) - Photo 27
Facilities Condition AssessmentAdministrative Services Center Condition Assessment
12Magellan Consulting, Inc.
6020 Building B (11) - Photo 36
6020 Building B (8) - Photo 32
6020 Building B (13) - Photo 34
6020 Building B (12) - Photo 35
6020 Building B (7) - Photo 31
6020 Building B (9) - Photo 33
Facilities Condition AssessmentAdministrative Services Center Condition Assessment
13Magellan Consulting, Inc.
6010 Bldg A (7) - Photo 42
6020 Building B (1) - Photo 38
6010 Bldg A (9) - Photo 40
6010 Bldg A (8) - Photo 41
6020 Building B (10) - Photo 37
6010 Front of A & C - Photo 39
Facilities Condition AssessmentAdministrative Services Center Condition Assessment
14Magellan Consulting, Inc.
6010 Bldg A (11) - Photo 48
6010 Bldg A (5) - Photo 44
6010 Bldg A (13) - Photo 46
6010 Bldg A (12) - Photo 47
6010 Bldg A (6) - Photo 43
6010 Bldg A (4) - Photo 45
Facilities Condition AssessmentAdministrative Services Center Condition Assessment
15Magellan Consulting, Inc.
6010 Bldg A - EVAP COOLER-2 - Photo 54
6010 Bldg A - SUPPY FAN - Photo 50
6010 Bldg A - EXHAUST FAN - Photo 52
6010 Bldg A - EVAP. COOLER - Photo 53
6010 Bldg A (10) - Photo 49
6010 Bldg A - EXHAUST FAN-2 - Photo 51
Facilities Condition AssessmentAdministrative Services Center Condition Assessment
16Magellan Consulting, Inc.
6020_03 Exterior Package Unit - Photo 60
6010 Bldg A (2) - Photo 56
6020_01 Exterior Package Unit - Photo 58
6020_02 Exterior Package Unit - Photo 59
6010 Bldg A - ACU ABANDONED - Photo 55
6010 Bldg A (1) - Photo 57
Facilities Condition AssessmentAdministrative Services Center Condition Assessment
17Magellan Consulting, Inc.
6030 Bldg A (2) - Photo 66
6020_07 Exterior Vent - Photo 64
6020_05 Exterior Package Unit - Photo 62
6030 Bldg A (1) - Photo 65
6020_04 Exterior Package Unit - Photo 61
6020_06 Exterior Package Unit - Photo 63
Facilities Condition AssessmentAdministrative Services Center Condition Assessment
18Magellan Consulting, Inc.
6030 Front of Building C - Photo 67
Appendix D –
Mission del Paso Campus
Condition Assessment Report
Facilities Condition AssessmentMission del Paso Campus Condition Assessment
1Magellan Consulting, Inc.
Mission del Paso Campus Condition Assessment
8070A Law Enforcement Portable A 1,536 2007 $13,890 10.24% $9.04 $16,282
8050 Physical Plant 1,686 1998 $533,537 170.54% $316.45 $18,298
8060 Mission Early College High School 15,399 1999 $161,039 7.37% $10.46 $56,752
8040 Student Services Center 8,720 1998 $276,920 24.48% $31.76 $132,807
8070C Law Enforcement Portable C 1,536 2007 $13,144 10.14% $8.56 $16,759
8070B Law Enforcement Portable B 1,536 2007 $13,603 7.91% $8.86 $9,730
8070 Law Enforcement Academy 23,389 1999 $231,291 8.98% $9.89 $171,720
8010 Health Building 22,945 1998 $697,286 22.43% $30.39 $290,301
Site 0 0 $1,133,511 .00% $0.00 $0
8020 Learning Resource Center 22,409 1998 $51,504 5.82% $2.30 $198,728
8030 Science Building 11,015 1998 $167,162 12.39% $15.18 $94,678
8025 Educational Resources Building 9,979 1998 $259,936 20.55% $26.05 $133,702
Totals 120,150 $3,552,822 20.35% $29.57 $1,139,755
Facility Condition by Building
Number Building Name Gross Sq Ft Built DateFacility Condition
Cost FCICost Per
Square FootFuture Life Cycle
Cost (Yr 1-5)
The Mission del Paso Campus Facility located at 10700 Gateway East in El Paso, Texas, was built in 1998. It comprises approximately 120,150 gross square feet.
Summary of Findings
The total current deficiencies for this site, in 2008 construction cost dollars, are estimated at $3,552,822.
Cross Tab of Current Deficiencies
The following chart summarizes the current deficiencies for this site in a cross tab that shows the buildings systems down the left and the priority of the deficiency across the top. This listing includes current deficiencies including deferred maintenance, functional deficiencies, code compliance, Americans with Disabilities Act, and Life Cycle Capital Renewal categories.
Electrical $1,532 $811,256 - $53,908 - $866,697
Mechanical - $568,342 $36,280 - $8,183 $612,805
Interior - - $610,423 $3,531 $108,399 $722,353
Plumbing - - $278,209 $27,948 $7,766 $313,923
Conveyances - - - - - $0
Technology - - - $3,210 - $3,210
Fire and Life Safety $36,551 $62,133 - - - $98,684
Site - - - $488,936 $62,650 $551,586
Specialties - - - $2,273 - $2,273
Other - - - - - $0
Exterior - $8,084 $173,490 $9,934 - $191,508
Structural - - - - - $0
Roofing $1,491 $110,288 $2,437 $75,568 - $189,784
Total $39,574 $1,560,104 $1,100,838 $665,308 $186,998 $3,552,822
Facility Condition - System by PriorityPriority
System 1 2 3 4 5 Total
Facilities Condition AssessmentMission del Paso Campus Condition Assessment
2Magellan Consulting, Inc.
Portable Buildings - - - - - $0
New Construction - - - - - $0
Hazardous Material - - - - - $0
Functional Deficiency - $144,690 $175,927 $83,605 - $404,222
Energy Efficiency - $1,174,795 $36,280 $53,908 - $1,264,984
Educational Adequacy - - - - - $0
Deferred Maintenance $746 $128,439 - $26,039 $168,763 $323,987
Code Compliance $33,610 $26,550 $272,159 - - $332,319
Capital Renewal $5,218 $85,629 $616,472 $501,756 $3,727 $1,212,802
ADA Compliance - - - - $14,507 $14,507
Total $39,574 $1,560,104 $1,100,838 $665,308 $186,998 $3,552,822
Facility Condition - Category by PriorityPriority
Category 1 2 3 4 5 Total
All deficiencies have been further categorized according to the type of deficiency observed. Capital Renewal items include those that are included in the life cycle forecast and are items that have reached or exceeded their useful life. Americans with Disabilities Act deficiencies are associated with accessibility compliance concerns. Code Compliance includes items that are a building code related deficiency. Deferred Maintenance items are those items that have broken or are in need of repair prior to reaching the end of life term. A Functional Deficiency is one that is presently not in place, or is not functioning correctly, and should be added to the building.
Life Cycle Capital Renewal Forecast
As part of the assessment process, this facility was analyzed according to twelve major building systems. Each system has subsystems, and each subsystem is further distinguished by type. For each line item, the original year, or most recent replacement year if applicable, was identified. Then, the historical life was compared to a model of expected life for each subsystem type. The remaining year was then forecasted by subtracting the expected life from the life used, and further adjusted for the apparent maintenance quality of the subsystem. In some cases, the calculation was overridden if the assessor’s judgment suggested a shorter or longer than expected life expectancy.
Once each subsystem was analyzed, they were combined to provide a 10-year life cycle capital renewal forecast for the building. The following chart shows all deficiencies and the subsequent year’s capital renewal projections for all systems where a component is expected to reach the end of its useful life and require capital dollars for replacement.
The chart on the following page shows the forecast in thousands ($000s) for the next ten years.
Facilities Condition AssessmentMission del Paso Campus Condition Assessment
3Magellan Consulting, Inc.
Fire and Life Safety 99 0 0 62 0 12 77 0 4 0 99 $253 $2.58
Plumbing 314 0 0 0 31 0 0 0 4 0 134 $169 $1.72
Electrical 867 0 0 14 5 2 10 0 152 0 612 $795 $8.12
Technology 3 0 0 38 0 0 51 12 0 0 86 $188 $1.92
Other 0 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Specialties 2 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Conveyances 0 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Mechanical 613 0 0 0 10 0 0 0 82 0 417 $510 $5.20
Roofing 190 0 0 217 653 0 0 0 8 0 0 $878 $8.96
Site 552 0 0 0 0 0 0 0 162 0 0 $162 $1.65
Structural 0 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Interior 722 5 0 4 23 63 310 0 98 1 161 $665 $6.79
Exterior 192 0 0 0 0 0 20 0 0 0 20 $40 $0.40
Total 3,553 5 0 335 722 77 468 12 509 1 1,528 $3,658 $37.34
Life Cycle Capital Renewal Projections ($000s)
SystemCurrent
DeficienciesYear 1 2008
Year 2 2009
Year 3 2010
Year 4 2011
Year 5 2012
Year 6 2013
Year 7 2014
Year 8 2015
Year 9 2016
Year 10 2017 Total $/GSF
Capital Renewal Forecast
Facilities Condition AssessmentMission del Paso Campus Condition Assessment
4Magellan Consulting, Inc.
Facility Condition Index (FCI)
The Facility Condition Index (FCI) is used throughout the facility condition assessment industry as a general indicator of a building’s health. The FCI is calculated by dividing the Facility Condition Cost plus five years of projected Life Cycle Capital Renewal Costs by the Replacement Value. Costs associated with new construction are not included in the FCI calculation. As a rule of thumb, an FCI below 10% is considered good. An FCI above 65% would suggest that the building is a candidate for replacement.
The Mission del Paso Campus facility has an overall FCI of 20.35%
Mission del Paso Campus Condition Assessment
Assessment Findings
The total current cost for all building deficiencies is $3,552,822. There are $1,133,511 in deficiencies at the site level that are included in the FCI calculation. The five year capital renewal cost was $1,139,755. The cost estimates were derived using a detailed listing of all noted deficiencies in the building. The cost to repair these deficiencies was then estimated using the cost data adjusted to El Paso, Texas (78% of national average).
The Replacement Value represents the estimated cost of replacing the current building with another building of like size, based on today’s estimated cost of construction in the El Paso, Texas area. The replacement cost for this facility is estimated to be $23,059,201.
The following pages provide a listing of all deficiencies and their associated cost for the site and building, followed by photos taken during the assessment.
Facilities Condition AssessmentMission del Paso Campus Condition Assessment
5Magellan Consulting, Inc.
The Suspended Ceiling Grid is Damaged And Require Replacement 23796 1,100 SF 3 $8,869 No
The Suspended Ceiling Grid is Damaged And Require Replacement 23676 1,200 SF 3 $9,675 No
The Carpet Flooring Is Damaged And Requires Replacement 18317 2,294 SF 3 $20,257 No
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Awning/Canopy is missing and is needed 20881 1 Ea. 3 $1,718 No
Awning/Canopy is missing and is needed 23797 100 Ea. 3 $171,772 No
Sub Total for System 2 $173,490
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Membrane Flashings At Equipment Curbs Are Damaged And Should Be Repaired 18300 12 LF 2 $187 Yes
Membrane Flashings At Penetration Are Damaged And Should Be Repaired 18303 3 Ea. 2 $313 Yes
Membrane Flashings At Drain Is Damaged And Should Be Repaired 18297 3 Ea. 2 $440 Yes
Lead Flashing Is Damaged And Should Be Repaired 18301 1 Ea. 2 $293 Yes
Membrane Flashing At Parapet (>2') Is Damaged And Should Be Repaired 18304 5 LF 2 $297 Yes
Metal Coping Is Damaged Or Loose And Should Be Repaired 18306 10 LF 2 $613 Yes
The Roof Requires Cleaning 18412 70 SF 2 $373 Yes
Tapered Insulation Is Required To Eliminate Ponding When Re-Roofing 18298 20 SF 3 $315 No
The Roof Drains Are Clogged 18296 1 Ea. 2 $116 Yes
Metal Umbrella At Penetration Or Pitch Pan Is Missing And Is Needed 18302 7 Ea. 2 $1,656 Yes
Missing Metal Closure Or Cement 18429 5 LF 2 $149 Yes
Built Up Roofing (Bur) Covering Has Blisters That Should Be Repaired 19006 20 Ea. 2 $2,561 Yes
The Clay Tile Roofing Roof Covering Is Damaged And Requires Replacement 18425 2 SF 1 $111 No
Counter Flashing Is Damaged Or Loose And Should Be Repaired 18305 30 LF 2 $610 Yes
Laps In Metal Cover At Hip/Ridge Require Resealing 18431 12 Ea. 2 $304 Yes
Flashings At Scupper Is Damaged And Should Be Repaired 18295 4 Ea. 2 $302 Yes
Sub Total for System 16 $8,641
Deficiency ID Qty UoM Priority Repair Cost WS&D
Roofing
Building: 8010 - Health Building
The Pole Lighting Is Damaged And Should Be Replaced 18471 4 Ea. 2 $35,972 Yes
The Pole Lighting Is Damaged And Should Be Replaced 18418 9 Ea. 2 $80,939 Yes
The Pole Lighting Is Damaged And Should Be Replaced 18436 5 Ea. 2 $44,965 Yes
The Ground Mounted Lighting Is Damaged And Should Be Replaced 18472 8 Ea. 2 $12,183 Yes
The Ground Mounted Lighting Is Damaged And Should Be Replaced 18493 2 Ea. 2 $3,047 Yes
The Ground Mounted Lighting Is Damaged And Should Be Replaced 18770 3 Ea. 2 $4,568 Yes
The Pole Lighting Is Damaged And Should Be Replaced 18492 11 Ea. 2 $98,924 Yes
The Pole Lighting Is Damaged And Should Be Replaced 18686 11 Ea. 2 $98,924 Yes
The Pole Lighting Is Damaged And Should Be Replaced 18769 8 Ea. 2 $71,945 Yes
The Pole Lighting Is Damaged And Should Be Replaced 18549 6 Ea. 2 $53,959 Yes
The Pole Lighting Is Damaged And Should Be Replaced 18597 9 Ea. 2 $80,939 Yes
Sub Total for System 11 $586,366
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Directional / wayfinding signage missing or not accessible. 23821 25 Ea. 5 $3,154 No
Sub Total for System 1 $3,154
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Paving Requires Restriping 18435 189 CAR 5 $34,123 No
Asphalt Paving Is Damaged And Requires Replacement 18434 189 CAR 4 $481,341 No
Paving Requires Restriping 18685 158 CAR 5 $28,527 No
Sub Total for System 3 $543,991
SiteDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for School and Site Level 15 $1,133,511
Site Level Deficiencies
Facilities Condition AssessmentMission del Paso Campus Condition Assessment
6Magellan Consulting, Inc.
The Canopy Lighting Is Damaged And Should Be Replaced 18444 2 Ea. 2 $3,527 Yes
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Directional / wayfinding signage missing or not accessible. 23816 25 Ea. 5 $3,154 No
Sub Total for System 1 $3,154
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Dryvit Exterior Is Damaged And Requires Repair 20677 15 SF Wall 2 $111 No
Sub Total for System 1 $111
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Laps In Metal Cover At Hip/Ridge Require Resealing 18448 30 Ea. 2 $322 Yes
Lead Flashing Is Missing And Is Needed 18443 1 Ea. 2 $129 Yes
Loose Metal Cover At Hip/Ridge Should Be Resecured 18449 50 LF 2 $530 Yes
Built Up Roofing (Bur) Covering Has Blisters That Should Be Repaired 18446 3 Ea. 2 $384 Yes
Counter Flashing Is Damaged Or Loose And Should Be Repaired 18441 150 LF 2 $1,889 Yes
Flashings At Scupper Is Damaged And Should Be Repaired 18438 1 Ea. 2 $293 Yes
Membrane Flashings At Drain Is Damaged And Should Be Repaired 18440 3 Ea. 2 $440 Yes
Thru-Wall Scuppers Are Clogged 18437 3 Ea. 2 $120 Yes
Tapered Insulation Is Required To Eliminate Ponding When Re-Roofing 18439 300 SF 3 $1,048 No
Metal Coping Is Damaged Or Loose And Should Be Repaired 18442 35 LF 2 $2,144 Yes
The Roof Requires Cleaning 18447 30 SF 2 $366 Yes
Sub Total for System 11 $7,666
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 8020 - Learning Resource Center
Security Alarm Motion Detector Is Missing And Needed 18321 11 Ea. 2 $12,698 No
Fire Alarm Horn/Strobe Is Missing And Is Needed 18322 3 Ea. 1 $1,951 Yes
Sub Total for System 2 $14,649
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Showers Plumbing Fixtures Are Damaged And Should Be Replaced 18324 6 Ea. 3 $5,185 No
The Showers Plumbing Fixtures Are Damaged And Should Be Replaced 18314 1 Ea. 3 $864 No
Install Fire Sprinklers 18325 21,000 SF 3 $160,864 No
The Class Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 18313 2 Ea. 4 $4,104 No
The Custodial Mop Or Service Sink Is Damaged And Should Be Replaced 18409 2 Ea. 4 $7,897 No
Sub Total for System 5 $178,915
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The Mounted Building Lighting Is Damaged And Should Be Replaced 18312 34 Ea. 2 $33,146 Yes
The Canopy Lighting Is Damaged And Should Be Replaced 18311 8 Ea. 2 $14,109 Yes
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 18320 27 Ea. 4 $9,533 No
Sub Total for System 3 $56,788
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Furnaces HVAC Component Is Damaged And Requires Replacement 23677 1,000 MBH 2 $3,049 No
The Air Handler HVAC Component Is Damaged And Requires Replacement 18419 9,000 CFM 2 $51,839 No
Sub Total for System 2 $54,888
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Doors Require Repainting 18316 54 Door 5 $2,874 No
Directional / wayfinding signage missing or not accessible. 23815 25 Ea. 5 $3,154 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 18318 18,356 SF 3 $138,333 No
Interior Walls Require Repainting 18315 10,000 SF 5 $26,754 No
Sub Total for System 7 $209,915
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 8010 - Health Building 37 $697,286
Facilities Condition AssessmentMission del Paso Campus Condition Assessment
7Magellan Consulting, Inc.
Flashings At Scupper Is Damaged And Should Be Repaired 18475 1 Ea. 2 $293 Yes
Membrane Flashings At Drain Is Damaged And Should Be Repaired 18477 3 Ea. 2 $440 Yes
Metal Coping Is Damaged Or Loose And Should Be Repaired 18479 8 LF 2 $490 Yes
Coping Termination At End Wall Is Damaged And Should Be Repaired 18480 2 Ea. 2 $204 Yes
Built Up Roofing (Bur) Covering Has Blisters That Should Be Repaired 19008 11 Ea. 2 $1,409 Yes
Built Up Roofing (Bur) Lap Seams Are Open Or Deteriorated 19010 10 LF 2 $495 Yes
Built Up Roofing (Bur) Membrane Has Holes That Should Be Repaired 19009 1 Ea. 2 $120 Yes
Penetration Boot Is Missing Or Damaged And Should Be Installed 18481 1 Ea. 2 $167 Yes
The Roof Requires Cleaning 18482 30 SF 2 $366 Yes
Thru-Wall Scuppers Are Clogged 18474 4 Ea. 2 $160 Yes
Tapered Insulation Is Required To Eliminate Ponding When Re-Roofing 18478 50 SF 3 $393 No
The Clay Tile Roofing Roof Covering Is Damaged And Requires Repair 19011 2 SF 2 $404 Yes
The Multi-Ply Bitumen Roof Coating Requires Repair 19029 50 SF 2 $437 Yes
The Roof Drains Are Clogged 18476 4 Ea. 2 $468 Yes
Sub Total for System 14 $5,846
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 8030 - Science Building
The Custodial Mop Or Service Sink Is Damaged And Should Be Replaced 18461 1 Ea. 4 $3,948 No
Install Fire Sprinklers 18462 9,979 SF 3 $76,442 No
Sub Total for System 2 $80,389
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The Canopy Lighting Is Damaged And Should Be Replaced 18457 1 Ea. 2 $1,764 Yes
Panelboard is not Labeled for Safety 18460 3 Amps 1 $786 Yes
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 18459 20 Ea. 4 $10,749 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 18458 25 Ea. 2 $24,372 Yes
Sub Total for System 4 $37,670
Deficiency ID Qty UoM Priority Repair Cost WS&D
Electrical
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 18470 1,991 SF 3 $15,004 No
The Ceramic Tile Flooring Is Damaged And Requires Replacement 20678 500 SF 3 $7,977 No
The Suspended Ceiling Grid is Damaged And Require Replacement 18467 9,979 SF 3 $80,457 No
Directional / wayfinding signage missing or not accessible. 23817 10 Ea. 5 $1,261 No
Interior Walls Require Repainting 18468 9,979 SF 5 $26,698 No
Interior Doors Require Repainting 18469 17 Door 5 $905 No
Sub Total for System 6 $132,301
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Flashings At Scupper Is Damaged And Should Be Repaired 18450 3 Ea. 2 $298 Yes
Laps In Metal Cover At Hip/Ridge Require Resealing 18465 10 Ea. 2 $302 Yes
Membrane Flashing At Parapet (>2') Is Damaged And Should Be Repaired 18452 55 LF 2 $348 Yes
Built Up Roofing (Bur) Covering Has Blisters That Should Be Repaired 19007 25 Ea. 2 $3,201 Yes
Damaged Metal Closure Or Cement 18464 2 LF 2 $302 Yes
Exhaust Fan Curbs are too Low and Should be Raised and Reflashed (<8") 18454 2 Ea. 2 $2,788 No
Membrane Flashings At Drain Is Damaged And Should Be Repaired 18451 3 Ea. 2 $440 Yes
Metal Umbrella At Penetration Or Pitch Pan Is Missing And Is Needed 18455 3 Ea. 2 $710 Yes
The Roof Requires Cleaning 18463 50 SF 2 $369 Yes
Membrane Flashings At Equipment Curbs Are Damaged And Should Be Repaired 18453 12 LF 2 $187 Yes
Membrane Flashings At Penetration Are Damaged And Should Be Repaired 18456 6 Ea. 2 $628 Yes
Sub Total for System 11 $9,575
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 8025 - Educational Resources Building 23 $259,936
Building: 8025 - Educational Resources Building
The Mounted Building Lighting Is Damaged And Should Be Replaced 18445 38 Ea. 2 $37,046 Yes
Sub Total for System 2 $40,573
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 8020 - Learning Resource Center 15 $51,504
Facilities Condition AssessmentMission del Paso Campus Condition Assessment
8Magellan Consulting, Inc.
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 18539 2,616 SF 3 $19,714 No
The Suspended Ceiling Grid is Damaged And Require Replacement 18535 6,104 SF 3 $49,215 No
The Carpet Flooring Is Damaged And Requires Replacement 18538 2,700 SF 3 $23,842 No
Directional / wayfinding signage missing or not accessible. 23819 10 Ea. 5 $1,261 No
Interior Doors Require Repainting 18537 27 Door 5 $1,436 No
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Laps In Metal Cover At Hip/Ridge Require Resealing 18532 10 Ea. 2 $302 Yes
Membrane Flashing At Parapet (>2') Is Damaged And Should Be Repaired 18512 20 LF 2 $311 Yes
Membrane Flashings At Drain Is Damaged And Should Be Repaired 18509 2 Ea. 2 $293 Yes
Flashings At Scupper Is Damaged And Should Be Repaired 18508 2 Ea. 2 $297 Yes
The Clay Tile Roofing Roof Covering Is Damaged And Requires Replacement 18530 5 SF 1 $277 No
Built Up Roofing (Bur) Covering Has Blisters That Should Be Repaired 19012 50 Ea. 2 $6,403 Yes
Built Up Roofing (Bur) Lap Seams Are Open Or Deteriorated 19013 25 LF 2 $1,238 Yes
The Roof Requires Cleaning 18518 50 SF 2 $369 Yes
Tapered Insulation Is Required To Eliminate Ponding When Re-Roofing 18511 10 SF 3 $288 No
Covered shade structure required 23799 1 Ea. 4 $72,800 No
Membrane Flashings At Equipment Curbs Are Damaged And Should Be Repaired 18514 36 LF 2 $561 Yes
Metal Coping Is Damaged Or Loose And Should Be Repaired 18513 25 LF 2 $1,532 Yes
Metal Umbrella At Penetration Or Pitch Pan Is Missing And Is Needed 18516 3 Ea. 2 $710 Yes
Sub Total for System 13 $85,380
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Bench is missing and is needed 23798 10 Ea. 4 $7,595 No
Sub Total for System 1 $7,595
Deficiency ID Qty UoM Priority Repair Cost WS&D
Site
Building: 8040 - Student Services Center
Fire Alarm Strobe Is Missing And Is Needed 18490 2 Ea. 1 $1,301 Yes
Fire Alarm Panel is Missing and is Needed 20579 1 Ea. 1 $3,727 Yes
Sub Total for System 2 $5,029
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Custodial Mop Or Service Sink Is Damaged And Should Be Replaced 18491 1 Ea. 4 $3,948 No
Sub Total for System 1 $3,948
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The Mounted Building Lighting Is Damaged And Should Be Replaced 18488 21 Ea. 2 $20,473 Yes
The Canopy Lighting Is Damaged And Should Be Replaced 18487 3 Ea. 2 $5,291 Yes
Sub Total for System 2 $25,764
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Large Diameter Exhausts/Hoods Are Missing/Damaged And Require Replacement 18486 6 Ea. 2 $10,216 No
Sub Total for System 1 $10,216
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Gypboard Walls Require Repair 18483 200 SF Wall 4 $1,765 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 20863 5,000 SF 3 $37,681 No
Directional / wayfinding signage missing or not accessible. 23818 10 Ea. 5 $1,261 No
The Carpet Flooring Is Damaged And Requires Replacement 18484 4,200 SF 3 $37,088 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 18485 5,020 SF 3 $37,831 No
Sub Total for System 5 $115,626
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Dryvit Exterior Is Damaged And Requires Repair 18473 100 SF Wall 2 $733 No
Sub Total for System 1 $733
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 8030 - Science Building 26 $167,162
Facilities Condition AssessmentMission del Paso Campus Condition Assessment
9Magellan Consulting, Inc.
The Exterior Cooling Tower Is Damaged And Requires Replacement 23822 350 TonAC 2 $85,629 No
The Chiller HVAC Component Is Damaged And Requires Replacement 18596 250 TonAC 2 $243,949 No
The Air Handler HVAC Component Is Damaged And Requires Replacement 18592 8,000 CFM 2 $30,281 No
Water cooled chiller required for redundancy 23730 1 Ea. 2 $143,380 No
Sub Total for System 4 $503,239
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Directional / wayfinding signage missing or not accessible. 23820 10 Ea. 5 $1,261 No
Interior Walls Require Repainting 18595 1,574 SF 5 $4,213 No
Concrete Flooring Epoxy Requires Replacement 20809 1,574 SF 5 $3,105 No
Sub Total for System 3 $8,579
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Membrane Flashings At Equipment Curbs Are Damaged And Should Be Repaired 18584 16 LF 2 $249 Yes
Membrane Flashings At Penetration Are Damaged And Should Be Repaired 18588 2 Ea. 2 $209 Yes
Membrane Flashings At Drain Is Damaged And Should Be Repaired 18579 2 Ea. 2 $293 Yes
Flashings At Scupper Is Damaged And Should Be Repaired 18578 2 Ea. 2 $297 Yes
Membrane Flashing At Parapet (>2') Is Damaged And Should Be Repaired 18580 25 LF 2 $317 Yes
Metal Coping Is Damaged Or Loose And Should Be Repaired 18583 20 LF 2 $1,225 Yes
Thru-Wall Flashing At Rise-Wall Should Be Raised And Reflashed 18581 1 LF 2 $300 No
HVAC Curbs are too Low and Should be Raised and Reflashed (<8") 18586 2 Ea. 4 $2,768 No
The Roof Requires Cleaning 18594 40 SF 2 $368 Yes
Metal Umbrella At Penetration Or Pitch Pan Is Missing And Is Needed 18587 2 Ea. 2 $473 Yes
The Multi-Ply Bitumen Roof Coating Requires Repair 19030 20 SF 2 $175 Yes
Exhaust Fan Curbs are too Low and Should be Raised and Reflashed (<8") 18585 2 Ea. 2 $2,788 No
Built Up Roofing (Bur) Covering Has Blisters That Should Be Repaired 19014 15 Ea. 2 $1,920 Yes
Awning Or Canopy Roof Coating is Rusted 20679 20 SF 2 $146 No
Built Up Roofing (Bur) Lap Seams Are Open Or Deteriorated 19016 20 LF 2 $990 Yes
Counter Flashing Is Damaged Or Loose And Should Be Repaired 18582 2 LF 2 $313 Yes
Built Up Roofing (Bur) Membrane Has Holes That Should Be Repaired 19015 5 Ea. 2 $604 Yes
Sub Total for System 17 $13,435
Deficiency ID Qty UoM Priority Repair Cost WS&D
Roofing
Building: 8050 - Physical Plant
Security Alarm Motion Detector Is Missing And Needed 18545 12 Ea. 2 $13,852 No
Sub Total for System 1 $13,852
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Custodial Mop Or Service Sink Is Damaged And Should Be Replaced 18547 1 Ea. 4 $3,948 No
The Class Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 18548 2 Ea. 4 $4,104 No
Sub Total for System 2 $8,052
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The Mounted Building Lighting Is Damaged And Should Be Replaced 18542 27 Ea. 2 $26,323 Yes
The Canopy Lighting Is Damaged And Should Be Replaced 18541 3 Ea. 2 $5,291 Yes
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 18544 10 Ea. 4 $5,374 No
Sub Total for System 3 $36,988
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Cleaning Required 18540 8,720 SF 5 $8,183 No
Sub Total for System 1 $8,183
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Walls Require Repainting 18536 8,000 SF 5 $21,403 No
Sub Total for System 6 $116,871
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 8040 - Student Services Center 27 $276,920
Facilities Condition AssessmentMission del Paso Campus Condition Assessment
10Magellan Consulting, Inc.
Metal Umbrella At Penetration Or Pitch Pan Is Missing And Is Needed 18688 2 Ea. 2 $473 Yes
Single-Ply Covering Has Blisters That Should Be Repaired 18696 6 Ea. 2 $653 Yes
Lead Flashing Is Missing And Is Needed 18687 6 Ea. 2 $779 Yes
Membrane Flashings At Penetration Are Damaged And Should Be Repaired 18689 7 Ea. 2 $732 Yes
Single-Ply Lap Seams Are Open Or Deteriorated 18698 15 LF 2 $319 Yes
The Single-Ply Membrane Roof Covering Requires Repair 20682 17,172 SF 2 $42,173 Yes
The Roof Requires Cleaning 18699 27 SF 2 $364 Yes
Single-Ply Membrane Has Holes That Should Be Repaired 18697 3 Ea. 2 $100 Yes
Sub Total for System 8 $45,593
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 8070 - Law Enforcement Academy
Install Fire Sprinklers 18627 4,550 SF 3 $34,853 No
The Custodial Mop Or Service Sink Is Missing And Should Be Installed 20680 1 Ea. 5 $7,766 No
Sub Total for System 2 $42,619
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The Mounted Building Lighting Is Damaged And Should Be Replaced 18624 25 Ea. 2 $24,372 Yes
The Canopy Lighting Is Damaged And Should Be Replaced 18623 3 Ea. 2 $5,291 Yes
Sub Total for System 2 $29,662
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 18646 3,000 SF 3 $22,608 No
The Suspended Ceiling Grid is Damaged And Require Replacement 18642 4,550 SF 3 $36,686 No
Interior Walls Require Repainting 18643 2,000 SF 5 $5,351 No
Interior Doors Require Repainting 18644 10 Door 5 $531 No
Sub Total for System 4 $65,176
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Concrete / CMU Exterior Is Damaged And Requires Replacement 18615 360 SF Wall 4 $9,934 No
Sub Total for System 1 $9,934
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Exhaust Fan Curbs are too Low and Should be Raised and Reflashed (<8") 18621 3 Ea. 2 $4,182 No
Expansion Joint Termination At End Wall Is Damaged And Should Be Repaired 20820 5 Ea. 2 $2,240 Yes
Damaged Metal Closure Or Cement 18636 10 LF 2 $349 Yes
The Clay Tile Roofing Roof Covering Is Damaged And Requires Replacement 18634 20 SF 1 $1,103 No
Counter Flashing Is Damaged Or Loose And Should Be Repaired 18620 30 LF 2 $610 Yes
Laps In Metal Cover At Hip/Ridge Require Resealing 18637 10 Ea. 2 $302 Yes
The Roof Requires Cleaning 18633 15 SF 2 $362 Yes
Tapered Insulation Is Required To Eliminate Ponding When Re-Roofing 18618 50 SF 3 $393 No
Membrane Flashings At Drain Is Damaged And Should Be Repaired 18617 2 Ea. 2 $293 Yes
Single-Ply Covering Has Blisters That Should Be Repaired 18631 35 Ea. 2 $3,813 Yes
Sub Total for System 10 $13,648
Deficiency ID Qty UoM Priority Repair Cost WS&D
Roofing
Sub Total for Building 8060 - Mission Early College High School 19 $161,039
Building: 8060 - Mission Early College High School
Security Alarm Contact Is Missing And Needed 18591 1 Ea. 2 $1,161 No
Emergency Exit Signage Is Missing And Needed 18590 1 Ea. 2 $783 Yes
Sub Total for System 2 $1,944
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Mounted Building Lighting Is Damaged And Should Be Replaced 18589 6 Ea. 2 $5,849 Yes
The GFCI Electrical Receptacles Are Inadequate And More Are Needed 18593 1 Ea. 2 $490 Yes
Sub Total for System 2 $6,339
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 8050 - Physical Plant 28 $533,537
Facilities Condition AssessmentMission del Paso Campus Condition Assessment
11Magellan Consulting, Inc.
The Data Ports Are Inadequate And More Are Needed 18766 4 Ea. 4 $1,070 No
Sub Total for System 1 $1,070
TechnologyDeficiency ID Qty UoM Priority Repair Cost WS&D
Emergency Lighting Is Inadequate Or Not Present And Should Be Installed 18762 1,690 SF 2 $2,523 Yes
Fire Alarm is Missing or Inadequate 18858 1,690 SF 1 $10,010 Yes
Sub Total for System 2 $12,533
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 8070B - Law Enforcement Portable B 3 $13,603
Building: 8070B - Law Enforcement Portable B
The Data Ports Are Inadequate And More Are Needed 18738 4 Ea. 4 $1,070 No
Sub Total for System 1 $1,070
TechnologyDeficiency ID Qty UoM Priority Repair Cost WS&D
Emergency Lighting Is Inadequate Or Not Present And Should Be Installed 18734 1,536 SF 2 $2,293 Yes
Fire Alarm is Missing or Inadequate 18857 1,536 SF 1 $9,781 Yes
Sub Total for System 2 $12,074
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Power Wiring to Building Should Be Repaired 23678 100 LF 1 $746 Yes
Sub Total for System 1 $746
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 8070A - Law Enforcement Portable A 4 $13,890
Building: 8070A - Law Enforcement Portable A
The Base Storage Cabinets Require Replacement 18703 8 LF 4 $2,273 No
Sub Total for System 1 $2,273
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 20580 24 Ea. 2 $12,804 Yes
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 18693 23,389 SF 2 $13,726 Yes
Sub Total for System 2 $26,530
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 18691 10 Ea. 4 $3,531 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 18690 18 Ea. 2 $17,548 Yes
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 18692 46 Ea. 4 $24,721 No
Sub Total for System 3 $45,800
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Evaporative Cooling Unit Is Damaged And Requires Replacement 20681 4 Ea. 3 $36,280 No
Sub Total for System 1 $36,280
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Gypboard Walls Require Repair 18701 200 SF Wall 4 $1,765 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 18702 8,650 SF 3 $65,187 No
The Acoustical Ceilings Tiles Are Damaged And Require Replacement 18700 100 SF 5 $622 No
Sub Total for System 3 $67,575
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Exterior door hardware is damaged and should be replaced 18727 12 Door 2 $7,240 Yes
Sub Total for System 1 $7,240
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 8070 - Law Enforcement Academy 19 $231,291
Facilities Condition AssessmentMission del Paso Campus Condition Assessment
12Magellan Consulting, Inc.
The Data Ports Are Inadequate And More Are Needed 18779 4 Ea. 4 $1,070 No
Sub Total for System 1 $1,070
TechnologyDeficiency ID Qty UoM Priority Repair Cost WS&D
Emergency Lighting Is Inadequate Or Not Present And Should Be Installed 18777 1,536 SF 2 $2,293 Yes
Fire Alarm is Missing or Inadequate 18859 1,536 SF 1 $9,781 Yes
Sub Total for System 2 $12,074
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 8070C - Law Enforcement Portable C 3 $13,144
Building: 8070C - Law Enforcement Portable C
Total for Campus 219 $3,552,822
Facilities Condition AssessmentMission del Paso Campus Condition Assessment
13Magellan Consulting, Inc.
Supporting PhotosMission del Paso Campus Condition Assessment
8010 Health Bldg - Interior Ceiling - Photo 6
8010 Health Bldg - Exterior Front 2 - Photo 2
8010 Health Bldg - Exterior Front 4 - Photo 4
8010 Health Bldg - Exterior Main Entrance - Photo 5
8010 Health Bldg - Exterior Front 1 - Photo 1
8010 Health Bldg - Exterior Front 3 - Photo 3
Facilities Condition AssessmentMission del Paso Campus Condition Assessment
14Magellan Consulting, Inc.
8020 LRC - Exterior Front - Photo 12
8010 Health Bldg - Roof - Photo 8
8010 Health Bldg - Room D134 - Photo 10
8020 LRC - Exhaust Fan - Photo 11
8010 Health Bldg - Interior - Photo 7
8010 Health Bldg - Room D134 2 - Photo 9
Facilities Condition AssessmentMission del Paso Campus Condition Assessment
15Magellan Consulting, Inc.
8020 LRC (5) - Photo 18
8020 LRC (10) - Photo 14
8020 LRC (3) - Photo 16
8020 LRC (4) - Photo 17
8020 LRC - Interior Piping - Photo 13
8020 LRC (2) - Photo 15
Facilities Condition AssessmentMission del Paso Campus Condition Assessment
16Magellan Consulting, Inc.
8025 Educational Resource - Electrical E105 (2) - Photo 24
8020 LRC (7) - Photo 20
8020 LRC (9) - Photo 22
8025 Educational Resource - Electrical E105 (1) - Photo 23
8020 LRC (6) - Photo 19
8020 LRC (8) - Photo 21
Facilities Condition AssessmentMission del Paso Campus Condition Assessment
17Magellan Consulting, Inc.
8025 Educational Resource (6) - Photo 30
8025 Educational Resource (2) - Photo 26
8025 Educational Resource (4) - Photo 28
8025 Educational Resource (5) - Photo 29
8025 Educational Resource (1) - Photo 25
8025 Educational Resource (3) - Photo 27
Facilities Condition AssessmentMission del Paso Campus Condition Assessment
18Magellan Consulting, Inc.
8030 Science Building (10) - Photo 36
8025 Educational Resource (9) - Photo 32
8030 Science Building - Exhaust Fans - Photo 34
8030 Science Building - Piping and Tank - Photo 35
8025 Educational Resource (8) - Photo 31
8030 Science Building - Bldg Signage - Photo 33
Facilities Condition AssessmentMission del Paso Campus Condition Assessment
19Magellan Consulting, Inc.
8030 Science Building (3) - Photo 42
8030 Science Building (12) - Photo 38
8030 Science Building (14) - Photo 40
8030 Science Building (2) - Photo 41
8030 Science Building (11) - Photo 37
8030 Science Building (13) - Photo 39
Facilities Condition AssessmentMission del Paso Campus Condition Assessment
20Magellan Consulting, Inc.
8030 Science Building (9) - Photo 48
8030 Science Building (5) - Photo 44
8030 Science Building (7) - Photo 46
8030 Science Building (8) - Photo 47
8030 Science Building (4) - Photo 43
8030 Science Building (6) - Photo 45
Facilities Condition AssessmentMission del Paso Campus Condition Assessment
21Magellan Consulting, Inc.
8060 Mission Early College (2) - Photo 54
8050 Physical Plant (2) - Photo 50
8050 Physical Plant (4) - Photo 52
8060 Mission Early College (1) - Photo 53
8040 Student Srvc Center (2) - Photo 49
8050 Physical Plant (3) - Photo 51
Facilities Condition AssessmentMission del Paso Campus Condition Assessment
22Magellan Consulting, Inc.
8070 Law Enforcement Academy (10) - Photo 60
8060 Mission Early College (5) - Photo 56
8060 Mission Early College (7) - Photo 58
8060 Mission Early College (8) - Photo 59
8060 Mission Early College (3) - Photo 55
8060 Mission Early College (6) - Photo 57
Facilities Condition AssessmentMission del Paso Campus Condition Assessment
23Magellan Consulting, Inc.
8070 Law Enforcement Academy (5) - Photo 66
8070 Law Enforcement Academy (12) - Photo 62
8070 Law Enforcement Academy (3) - Photo 64
8070 Law Enforcement Academy (4) - Photo 65
8070 Law Enforcement Academy (11) - Photo 61
8070 Law Enforcement Academy (2) - Photo 63
Facilities Condition AssessmentMission del Paso Campus Condition Assessment
24Magellan Consulting, Inc.
8070A Law Enforcement Portable A (1) - Photo 72
8070 Law Enforcement Academy (7) - Photo 68
8070 Law Enforcement Academy (9) - Photo 70
8070C Law Enforcement Portable C (1) - Photo 71
8070 Law Enforcement Academy (6) - Photo 67
8070 Law Enforcement Academy (8) - Photo 69
Facilities Condition AssessmentMission del Paso Campus Condition Assessment
25Magellan Consulting, Inc.
8070B Law Enforcement Portable B (1) - Photo 748070B Law Enforcement Portable B (2) - Photo 73
Appendix E –
Northwest Campus
Condition Assessment Report
Facilities Condition AssessmentNorthwest Campus Condition Assessment
1Magellan Consulting, Inc.
Northwest Campus Condition Assessment
7020 Library 26,625 2003 $18,959 1.30% $0.71 $47,350
7030 Classroom Building 15,509 2003 $32,787 2.29% $2.11 $35,340
7010 Main Building 36,768 1994 $2,013,812 39.06% $54.77 $742,805
Site 0 0 $1,752,851 .00% $0.00 $0
Totals 78,902 $3,818,409 30.67% $48.39 $825,495
Facility Condition by Building
Number Building Name Gross Sq Ft Built DateFacility Condition
Cost FCICost Per
Square FootFuture Life Cycle
Cost (Yr 1-5)
The Northwest Campus Facility located at 6701 South Desert Rd. in El Paso, Texas, was built in 1994. It comprises approximately 78,902 gross square feet.
Summary of Findings
The total current deficiencies for this site, in 2008 construction cost dollars, are estimated at $3,818,409.
Cross Tab of Current Deficiencies
The following chart summarizes the current deficiencies for this site in a cross tab that shows the buildings systems down the left and the priority of the deficiency across the top. This listing includes current deficiencies including deferred maintenance, functional deficiencies, code compliance, Americans with Disabilities Act, and Life Cycle Capital Renewal categories.
Electrical - $8,774 $49,482 $455,217 - $513,473
Mechanical - $434,925 $21,844 $190,647 $52,549 $699,965
Interior - - $506,433 $1,048 $129,642 $637,124
Plumbing - $2,315 $13,239 $51,464 - $67,018
Conveyances - - - - - $0
Technology - - - - - $0
Fire and Life Safety $6,417 $10,800 - - - $17,217
Site - - - $1,622,408 $124,137 $1,746,545
Specialties - - - $55,921 - $55,921
Other - - - - - $0
Exterior - $5,981 - $173 $5,105 $11,259
Structural - - - - - $0
Roofing - $54,251 $6,938 $8,494 $206 $69,888
Total $6,417 $517,046 $597,936 $2,385,372 $311,639 $3,818,409
Facility Condition - System by PriorityPriority
System 1 2 3 4 5 Total
Facilities Condition AssessmentNorthwest Campus Condition Assessment
2Magellan Consulting, Inc.
Portable Buildings - - - - - $0
New Construction - - - - - $0
Hazardous Material - - - - - $0
Functional Deficiency - $178,870 $6,938 $174,494 $206 $360,507
Energy Efficiency - $181,747 $1,758 $455,217 - $638,722
Educational Adequacy - - - - - $0
Deferred Maintenance - $63,609 $69,568 $29,924 $291,557 $454,658
Code Compliance $6,417 $9,235 - - - $15,652
Capital Renewal - $83,585 $519,672 $1,725,737 $955 $2,329,949
ADA Compliance - - - - $18,921 $18,921
Total $6,417 $517,046 $597,936 $2,385,372 $311,639 $3,818,409
Facility Condition - Category by PriorityPriority
Category 1 2 3 4 5 Total
All deficiencies have been further categorized according to the type of deficiency observed. Capital Renewal items include those that are included in the life cycle forecast and are items that have reached or exceeded their useful life. Americans with Disabilities Act deficiencies are associated with accessibility compliance concerns. Code Compliance includes items that are a building code related deficiency. Deferred Maintenance items are those items that have broken or are in need of repair prior to reaching the end of life term. A Functional Deficiency is one that is presently not in place, or is not functioning correctly, and should be added to the building.
Life Cycle Capital Renewal Forecast
As part of the assessment process, this facility was analyzed according to twelve major building systems. Each system has subsystems, and each subsystem is further distinguished by type. For each line item, the original year, or most recent replacement year if applicable, was identified. Then, the historical life was compared to a model of expected life for each subsystem type. The remaining year was then forecasted by subtracting the expected life from the life used, and further adjusted for the apparent maintenance quality of the subsystem. In some cases, the calculation was overridden if the assessor’s judgment suggested a shorter or longer than expected life expectancy.
Once each subsystem was analyzed, they were combined to provide a 10-year life cycle capital renewal forecast for the building. The following chart shows all deficiencies and the subsequent year’s capital renewal projections for all systems where a component is expected to reach the end of its useful life and require capital dollars for replacement.
The chart on the following page shows the forecast in thousands ($000s) for the next ten years.
Facilities Condition AssessmentNorthwest Campus Condition Assessment
3Magellan Consulting, Inc.
Fire and Life Safety 17 0 0 0 32 0 79 0 0 0 11 $123 $1.92
Plumbing 67 0 0 0 0 4 0 0 0 0 3 $6 $0.10
Electrical 513 0 0 17 106 0 13 81 0 0 0 $216 $3.38
Technology 0 0 0 0 0 0 48 14 0 0 40 $102 $1.60
Other 0 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Specialties 56 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Conveyances 0 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Mechanical 700 0 0 0 95 121 13 0 0 0 0 $229 $3.58
Roofing 70 0 368 0 0 0 0 0 305 0 0 $673 $10.52
Site 1,747 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Structural 0 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Interior 637 0 0 0 83 0 158 0 24 31 106 $402 $6.28
Exterior 11 0 0 0 0 0 0 0 64 0 10 $74 $1.16
Total 3,818 0 368 17 316 125 311 94 393 31 171 $1,826 $28.55
Life Cycle Capital Renewal Projections ($000s)
SystemCurrent
DeficienciesYear 1 2008
Year 2 2009
Year 3 2010
Year 4 2011
Year 5 2012
Year 6 2013
Year 7 2014
Year 8 2015
Year 9 2016
Year 10 2017 Total $/GSF
Capital Renewal Forecast
Facilities Condition AssessmentNorthwest Campus Condition Assessment
4Magellan Consulting, Inc.
Facility Condition Index (FCI)
The Facility Condition Index (FCI) is used throughout the facility condition assessment industry as a general indicator of a building’s health. The FCI is calculated by dividing the Facility Condition Cost plus five years of projected Life Cycle Capital Renewal Costs by the Replacement Value. Costs associated with new construction are not included in the FCI calculation. As a rule of thumb, an FCI below 10% is considered good. An FCI above 65% would suggest that the building is a candidate for replacement.
The Northwest Campus facility has an overall FCI of 30.67%
Northwest Campus Condition Assessment
Assessment Findings
The total current cost for all building deficiencies is $3,818,409. There are $1,752,851 in deficiencies at the site level that are included in the FCI calculation. The five year capital renewal cost was $825,495. The cost estimates were derived using a detailed listing of all noted deficiencies in the building. The cost to repair these deficiencies was then estimated using the cost data adjusted to El Paso, Texas (78% of national average).
The Replacement Value represents the estimated cost of replacing the current building with another building of like size, based on today’s estimated cost of construction in the El Paso, Texas area. The replacement cost for this facility is estimated to be $15,142,881.
The following pages provide a listing of all deficiencies and their associated cost for the site and building, followed by photos taken during the assessment.
Facilities Condition AssessmentNorthwest Campus Condition Assessment
5Magellan Consulting, Inc.
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 20353 23,899 SF 3 $180,105 No
Directional / wayfinding signage missing or not accessible. 23812 50 Ea. 5 $6,306 No
The Carpet Flooring Is Damaged And Requires Replacement 20352 9,192 SF 3 $81,168 No
The Suspended Ceiling Grid is Damaged And Require Replacement 20348 30,407 SF 3 $245,160 No
Interior Walls Require Repainting 20350 34,208 SF 5 $91,521 No
Interior Doors Require Repainting 20351 80 Door 5 $4,257 No
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Concrete / CMU Exterior Is Damaged And Requires Repair 20305 10 SF Wall 4 $173 No
The Storefront / Curtain Wall Is Damaged And Requires Repair 20806 60 SF Wall 2 $3,760 Yes
The Aluminum Window Is Damaged And Requires Replacement 20306 1 Ea. 2 $1,729 Yes
The Exterior Requires Painting 20304 320 SF Wall 5 $955 No
The Exterior Requires Cleaning 20303 2,000 SF Wall 5 $4,150 No
Sub Total for System 5 $10,767
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Roof Requires Cleaning 20346 200 SF 2 $757 Yes
The Roof Operable Hatch Is Damaged And Requires Repair 20308 2 Ea. 2 $1,138 Yes
Thru-Wall Flashing At Rise-Wall Should Be Raised And Reflashed 20311 15 LF 2 $439 No
HVAC Curbs are too Low and Should be Raised and Reflashed (<8") 20315 4 Ea. 4 $5,536 No
Curbs Have Been Abandoned And Should Be Removed 20316 6 Ea. 4 $2,958 No
Expansion Joint Laps Are Damaged And Should Be Repaired 20804 5 Ea. 2 $1,804 Yes
Exhaust Fan Curbs are too Low and Should be Raised and Reflashed (<8") 20314 9 Ea. 2 $12,549 No
Membrane Flashing At Parapet (>2') Is Damaged And Should Be Repaired 20310 600 LF 2 $1,491 Yes
Gas Line/Conduit On New Supports Is Unseated And Should Be Supported 20318 4 Ea. 2 $444 Yes
Built Up Roofing (Bur) Lap Seams Are Open Or Deteriorated 20344 100 LF 2 $4,954 Yes
Built Up Roofing (Bur) Covering Has Blisters That Should Be Repaired 20342 17 Ea. 2 $2,177 Yes
Counter Flashing Is Damaged Or Loose And Should Be Repaired 20313 100 LF 2 $1,356 Yes
Built Up Roofing (Bur) Membrane Has Holes That Should Be Repaired 20343 6 Ea. 2 $724 Yes
Membrane Flashings At Drain Is Damaged And Should Be Repaired 20309 12 Ea. 2 $1,762 Yes
Metal Umbrella At Penetration Or Pitch Pan Is Missing And Is Needed 20320 4 Ea. 2 $946 Yes
Metal Counter Flashing Is Loose Or Damaged And Should Be Replaced 20317 30 LF 2 $291 Yes
The Multi-Ply Bitumen Roof Coating Requires Repair 20345 1,300 SF 2 $11,351 Yes
Skylight Is Damaged And Should Be Repaired 20319 6 Ea. 2 $3,252 Yes
Membrane Flashings At Penetration Are Damaged And Should Be Repaired 20782 5 Ea. 2 $522 Yes
Membrane Flashings At Penetration Are Damaged And Should Be Repaired 20321 1 Ea. 2 $104 Yes
Metal Coping Lap Joints Have Lost Their Seal And Should Be Resealed 20312 28 Ea. 2 $319 Yes
Sub Total for System 21 $54,873
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 7010 - Main Building
Directional / wayfinding signage missing or not accessible. 23811 50 Ea. 5 $6,306 No
Sub Total for System 1 $6,306
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Paving Requires Restriping 20299 637 CAR 5 $115,006 No
Site Drainage is Inadequate and Requires Regrading 20356 400 SF 4 $109 No
Asphalt Paving Is Damaged And Requires Replacement 20298 637 CAR 4 $1,622,299 No
Trash Receptacles Are Damaged And Require Replacement 20300 4 Ea. 5 $4,113 No
Tree Replacement Required 20297 3 Ea. 5 $5,018 No
Sub Total for System 5 $1,746,545
Deficiency ID Qty UoM Priority Repair Cost WS&D
Site
Sub Total for School and Site Level 6 $1,752,851
Site Level Deficiencies
Facilities Condition AssessmentNorthwest Campus Condition Assessment
6Magellan Consulting, Inc.
Gas Line/Conduit On New Supports Is Unseated And Should Be Supported 20391 1 Ea. 2 $111 Yes
Membrane Flashings At Metal Edge Are Damaged And Should Be Repaired 20389 50 LF 2 $650 Yes
Single-Ply Lap Seams Are Open Or Deteriorated 20397 20 LF 2 $426 Yes
Counter Flashing Is Damaged Or Loose And Should Be Repaired 20390 50 LF 2 $823 Yes
Drains Are Clogged And Should Be Replaced 20805 2 Ea. 2 $748 Yes
Flashings At Scupper Is Damaged And Should Be Repaired 20807 4 Ea. 2 $302 Yes
Single-Ply Membrane Has Holes That Should Be Repaired 20396 20 Ea. 2 $672 Yes
Tapered Insulation Is Required To Eliminate Ponding When Re-Roofing 20387 30 SF 3 $340 No
Overflow Drain And Piping Is Missing And Is Needed 20388 5 Ea. 3 $6,257 No
The Roof Drains Are Clogged 20386 4 Ea. 2 $468 Yes
The Roof Requires Cleaning 20398 50 SF 2 $369 Yes
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 7020 - Library
The Base Storage Cabinets Require Replacement 20354 120 LF 4 $34,107 No
The Upper Storage Cabinets Require Replacement 20355 120 LF 4 $21,815 No
Sub Total for System 2 $55,921
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
The Custodial Mop Or Service Sink Is Damaged And Should Be Replaced 20337 1 Ea. 4 $3,948 No
The Class Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 20338 3 Ea. 4 $6,155 No
The Toilets Plumbing Fixtures Are Damaged And Should Be Replaced 20340 10 Ea. 3 $13,239 No
The Rest Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 20339 8 Ea. 4 $13,119 No
The Refrigerated Water Cooler is Damaged And Should Be Replaced 20341 6 Ea. 4 $26,192 No
Sub Total for System 5 $62,652
Deficiency ID Qty UoM Priority Repair Cost WS&D
Plumbing
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20330 32 Ea. 4 $11,299 No
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20786 14 Ea. 4 $4,943 No
The H.I.D. Lighting Is Damaged And Should Be Replaced 20332 3 Ea. 3 $1,758 No
The Power Service Is Inadequate And Should Be Upgraded 20334 900 Amps 3 $47,724 No
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20331 458 Ea. 4 $246,133 No
The Incandescent Lighting Is Damaged And Should Be Replaced 20785 5 Ea. 4 $1,818 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 20329 7 Ea. 2 $6,825 Yes
The Electrical Circuit Capacity Is Inadequate 20335 168 EACH 4 $158,657 No
The Incandescent Lighting Is Damaged And Should Be Replaced 20333 89 Ea. 4 $32,367 No
Sub Total for System 9 $511,524
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Roof Air Handler/Exhaust is Damaged And Requires Replacement 20325 12 TonAC 2 $60,404 No
Water cooled chiller required for redundancy 23728 1 Ea. 2 $86,596 No
Duct Damper is Damaged And Should Be Replaced 20784 100 Ea. 3 $16,587 No
The Large Diameter Exhausts/Hoods Are Missing/Damaged And Require Replacement 20322 3 Ea. 2 $5,107 No
Air cooled chiller required for redundancy 23727 1 Ea. 2 $92,274 No
The Chiller HVAC Component Is Damaged And Requires Replacement 23729 120 TonAC 2 $106,960 No
The Exterior Cooling Tower Is Damaged And Requires Replacement 23717 1 EACH 2 $83,585 No
The 2 X 4 Exhausts/Hoods Are Missing/Damaged And Require Replacement 20324 1 Ea. 3 $5,256 No
Duct Grill is Damaged And Should Be Replaced 20327 153 Ea. 5 $49,247 No
Duct Register is Damaged And Should Be Replaced 20783 4 Ea. 5 $3,301 No
The 2 X 2 Exhausts/Hoods Are Missing/Damaged And Require Replacement 20323 2 Ea. 4 $4,541 No
Computer room lacks independent AC. 23823 4 Ea. 4 $174,494 No
Exhaust Fan Ventilation Is Damaged And Should Be Replaced 20336 6 Ea. 4 $11,612 No
Sub Total for System 13 $699,965
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Gypboard Ceilings Are Damaged And Requires Repainting 20349 3,610 SF 5 $9,593 No
Sub Total for System 7 $618,110
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 7010 - Main Building 62 $2,013,812
Facilities Condition AssessmentNorthwest Campus Condition Assessment
7Magellan Consulting, Inc.
Fire Alarm Horn/Strobe Is Missing And Is Needed 20423 1 Ea. 1 $650 Yes
Fire Alarm Actuator Is Missing And Is Needed 20425 1 Ea. 1 $282 Yes
Emergency Exit Signage Is Missing And Needed 20421 1 Ea. 2 $783 Yes
Fire Alarm Strobe Is Missing And Is Needed 20424 7 Ea. 1 $4,554 Yes
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Water Heater Plumbing Fixtures Are Damaged And Should Be Replaced 20427 1 Ea. 2 $2,315 No
The Class Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 20426 1 Ea. 4 $2,051 No
Sub Total for System 2 $4,366
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
Portland Cement Plaster needs minor repairs 20872 50 SF 4 $524 No
Directional / wayfinding signage missing or not accessible. 23814 25 Ea. 5 $3,154 No
Interior Walls Require Repainting 20432 2,000 SF 5 $5,351 No
Sub Total for System 3 $9,029
Deficiency ID Qty UoM Priority Repair Cost WS&D
Interior
Mortar Joints in Stone Coping Requires Replacement 20873 20 LF 2 $246 No
Sub Total for System 1 $246
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Strainers Are Missing And Needed 20400 1 Ea. 2 $804 Yes
Single-Ply Membrane Has Holes That Should Be Repaired 20428 10 Ea. 2 $335 Yes
Metal Umbrella At Penetration Or Pitch Pan Is Missing And Is Needed 20405 1 Ea. 2 $237 Yes
Tapered Insulation Is Required To Eliminate Ponding When Re-Roofing 20401 30 SF 3 $340 No
The Roof Requires Cleaning 20429 50 SF 2 $369 Yes
The Roof Drains Are Clogged 20399 2 Ea. 2 $235 Yes
Membrane Flashings At Metal Edge Are Damaged And Should Be Repaired 20402 30 LF 2 $389 Yes
Counter Flashing Is Damaged Or Loose And Should Be Repaired 20403 50 LF 2 $823 Yes
Gas Line/Conduit On New Supports Is Unseated And Should Be Supported 20404 1 Ea. 2 $111 Yes
Sub Total for System 9 $3,644
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 7030 - Classroom Building
Fire Alarm Actuator Is Missing And Is Needed 20395 1 Ea. 1 $282 Yes
Fire Alarm Horn/Strobe Is Missing And Is Needed 20394 1 Ea. 1 $650 Yes
Emergency Exit Signage Is Missing And Needed 20393 1 Ea. 2 $783 Yes
Sub Total for System 3 $1,714
Deficiency ID Qty UoM Priority Repair Cost WS&D
Fire and Life Safety
The Mounted Building Lighting Is Damaged And Should Be Replaced 20392 2 Ea. 2 $1,949 Yes
Sub Total for System 1 $1,949
Deficiency ID Qty UoM Priority Repair Cost WS&D
Electrical
Portland Cement Plaster needs minor repairs 20874 50 SF 4 $524 No
Directional / wayfinding signage missing or not accessible. 23813 25 Ea. 5 $3,154 No
Sub Total for System 2 $3,678
Deficiency ID Qty UoM Priority Repair Cost WS&D
Interior
Mortar Joints in Stone Coping Requires Replacement 20875 20 LF 2 $246 No
Sub Total for System 1 $246
Deficiency ID Qty UoM Priority Repair Cost WS&D
Exterior
Splashblocks Are Missing Or Damaged And Are Needed 20385 2 Ea. 5 $206 No
Sub Total for System 12 $11,371
Deficiency ID Qty UoM Priority Repair Cost WS&D
Roofing
Sub Total for Building 7020 - Library 19 $18,959
Facilities Condition AssessmentNorthwest Campus Condition Assessment
8Magellan Consulting, Inc.
Security Alarm Motion Detector Is Missing And Needed 20422 8 Ea. 2 $9,235 No
Sub Total for System 5 $15,503
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 7030 - Classroom Building 20 $32,787
Total for Campus 107 $3,818,409
Facilities Condition AssessmentNorthwest Campus Condition Assessment
9Magellan Consulting, Inc.
Supporting PhotosNorthwest Campus Condition Assessment
7010 Main Bldg - EXHAUST FAN - Photo 6
7030 Classroom Addition (8) - Photo 2
7010 Main Bldg - AHU-1-OLD - Photo 4
7010 Main Bldg - AHU-2-OLD - Photo 5
7030 Classroom Addition (7) - Photo 1
7030 Classroom Addition (9) - Photo 3
Facilities Condition AssessmentNorthwest Campus Condition Assessment
10Magellan Consulting, Inc.
7010 Main Bldg (15) - Photo 12
7010 Main Bldg (11) - Photo 8
7010 Main Bldg (13) - Photo 10
7010 Main Bldg (14) - Photo 11
7010 Main Bldg (10) - Photo 7
7010 Main Bldg (12) - Photo 9
Facilities Condition AssessmentNorthwest Campus Condition Assessment
11Magellan Consulting, Inc.
7010 Main Bldg (4) - Photo 18
7010 Main Bldg (17) - Photo 14
7010 Main Bldg (2) - Photo 16
7010 Main Bldg (3) - Photo 17
7010 Main Bldg (16) - Photo 13
7010 Main Bldg (18) - Photo 15
Facilities Condition AssessmentNorthwest Campus Condition Assessment
12Magellan Consulting, Inc.
7020 Library - 01 Floor Drain - Photo 24
7010 Main Bldg (6) - Photo 20
7010 Main Bldg (8) - Photo 22
7010 Main Bldg (9) - Photo 23
7010 Main Bldg (5) - Photo 19
7010 Main Bldg (7) - Photo 21
Facilities Condition AssessmentNorthwest Campus Condition Assessment
13Magellan Consulting, Inc.
7030 Classroom Addition (1) - Photo 30
7020 Library (1) - Photo 26
7020 Library (3) - Photo 28
7020 Library (5) - Photo 29
7020 Library - 02 Floor Drain - Photo 25
7020 Library (2) - Photo 27
Facilities Condition AssessmentNorthwest Campus Condition Assessment
14Magellan Consulting, Inc.
7030 Classroom Addition (5) - Photo 34
7030 Classroom Addition (3) - Photo 32
7030 Classroom Addition (4) - Photo 33
7030 Classroom Addition (2) - Photo 31
Appendix F –
Rio Grande Campus
Condition Assessment Report
Facilities Condition AssessmentRio Grande Campus Condition Assessment
1Magellan Consulting, Inc.
Rio Grande Campus Condition Assessment
4070 Community Center 4,084 1925 $1,432,049 183.64% $350.65 $7,353
4030 Queen Anne Building 5,156 1903 $215,211 30.29% $41.74 $84,501
4040 Student Services Building 29,173 1916 $2,535,398 47.80% $86.91 $140,920
4010B Building B 53,619 1980 $5,711,342 56.43% $106.52 $96,102
4060 Parking Garage 145,892 2002 $214,917 .92% $1.47 $43,468
4010A Building A 48,088 1955 $3,595,566 40.07% $74.77 $102,887
Site 0 0 $695,753 .00% $0.00 $81,620
4080 Allied Health Building 27,187 2003 $366,836 7.03% $13.49 $0
4050 Oregon Center 23,239 1981 $1,858,811 42.79% $79.99 $49,747
Totals 336,438 $16,625,883 26.69% $49.42 $606,598
Facility Condition by Building
Number Building Name Gross Sq Ft Built DateFacility Condition
Cost FCICost Per
Square FootFuture Life Cycle
Cost (Yr 1-5)
The Rio Grande Campus Facility located at 100 West Rio Grande Ave. in El Paso, Texas, was built in 1903. It comprises approximately 336,438 gross square feet.
Summary of Findings
The total current deficiencies for this site, in 2008 construction cost dollars, are estimated at $16,625,883.
Cross Tab of Current Deficiencies
The following chart summarizes the current deficiencies for this site in a cross tab that shows the buildings systems down the left and the priority of the deficiency across the top. This listing includes current deficiencies including deferred maintenance, functional deficiencies, code compliance, Americans with Disabilities Act, and Life Cycle Capital Renewal categories.
Electrical - $416,441 $358,414 $816,669 - $1,591,524
Mechanical - $3,795,472 $587,649 $176,101 $244,528 $4,803,750
Interior - $319,845 $4,333,929 $409,192 $601,206 $5,664,173
Plumbing $12,474 $9,002 $884,112 $133,091 - $1,038,679
Conveyances - $82,766 $255,894 $161,514 - $500,174
Technology - - - - - $0
Fire and Life Safety $424,803 $343,086 - - - $767,889
Site - $35,492 $1,077 $332,945 $110,043 $479,557
Specialties - $34,922 $3,940 $43,354 - $82,217
Other - - - - - $0
Exterior - $544,366 $224,371 $59,350 $136,220 $964,307
Structural - $30,940 - - - $30,940
Roofing $367,469 $312,600 $20,652 $923 $1,030 $702,673
Total $804,746 $5,924,932 $6,670,040 $2,133,140 $1,093,026 $16,625,883
Facility Condition - System by PriorityPriority
System 1 2 3 4 5 Total
Facilities Condition AssessmentRio Grande Campus Condition Assessment
2Magellan Consulting, Inc.
Portable Buildings - - - - - $0
New Construction - - - - - $0
Hazardous Material - - - - - $0
Functional Deficiency - $355,122 $4,343 $161,514 $40,297 $561,275
Energy Efficiency - $4,469,964 $630,730 $814,661 - $5,915,355
Educational Adequacy - - - - - $0
Deferred Maintenance $206,126 $318,707 $507,254 $406,115 $928,324 $2,366,526
Code Compliance $209,000 - $588,745 - $4,248 $801,992
Capital Renewal $389,620 $449,329 $4,711,450 $750,850 $36,151 $6,337,400
ADA Compliance - $331,810 $227,518 - $84,008 $643,335
Total $804,746 $5,924,932 $6,670,040 $2,133,140 $1,093,026 $16,625,883
Facility Condition - Category by PriorityPriority
Category 1 2 3 4 5 Total
All deficiencies have been further categorized according to the type of deficiency observed. Capital Renewal items include those that are included in the life cycle forecast and are items that have reached or exceeded their useful life. Americans with Disabilities Act deficiencies are associated with accessibility compliance concerns. Code Compliance includes items that are a building code related deficiency. Deferred Maintenance items are those items that have broken or are in need of repair prior to reaching the end of life term. A Functional Deficiency is one that is presently not in place, or is not functioning correctly, and should be added to the building.
Life Cycle Capital Renewal Forecast
As part of the assessment process, this facility was analyzed according to twelve major building systems. Each system has subsystems, and each subsystem is further distinguished by type. For each line item, the original year, or most recent replacement year if applicable, was identified. Then, the historical life was compared to a model of expected life for each subsystem type. The remaining year was then forecasted by subtracting the expected life from the life used, and further adjusted for the apparent maintenance quality of the subsystem. In some cases, the calculation was overridden if the assessor’s judgment suggested a shorter or longer than expected life expectancy.
Once each subsystem was analyzed, they were combined to provide a 10-year life cycle capital renewal forecast for the building. The following chart shows all deficiencies and the subsequent year’s capital renewal projections for all systems where a component is expected to reach the end of its useful life and require capital dollars for replacement.
The chart on the following page shows the forecast in thousands ($000s) for the next ten years.
Facilities Condition AssessmentRio Grande Campus Condition Assessment
3Magellan Consulting, Inc.
Fire and Life Safety 768 0 0 6 0 0 34 0 140 0 98 $278 $0.88
Plumbing 1,039 0 0 0 0 13 0 0 0 0 36 $48 $0.15
Electrical 1,592 0 0 1 3 86 116 0 440 27 11 $683 $2.17
Technology 0 0 0 82 0 160 68 0 0 0 4 $315 $1.00
Other 0 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Specialties 82 0 0 0 0 0 8 0 0 0 0 $8 $0.03
Conveyances 500 0 0 0 0 0 0 0 0 0 53 $53 $0.17
Mechanical 4,804 0 0 43 1 0 0 0 156 0 2 $202 $0.64
Roofing 703 0 0 10 1 36 594 0 0 0 0 $641 $2.03
Site 480 0 0 0 82 0 2 0 1,249 0 0 $1,332 $4.22
Structural 31 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Interior 5,664 0 7 0 3 53 389 0 479 1 100 $1,032 $3.27
Exterior 964 0 0 13 0 7 40 0 22 0 35 $117 $0.37
Total 16,626 0 7 155 89 356 1,251 0 2,485 28 339 $4,710 $14.93
Life Cycle Capital Renewal Projections ($000s)
SystemCurrent
DeficienciesYear 1 2008
Year 2 2009
Year 3 2010
Year 4 2011
Year 5 2012
Year 6 2013
Year 7 2014
Year 8 2015
Year 9 2016
Year 10 2017 Total $/GSF
Capital Renewal Forecast
Facilities Condition AssessmentRio Grande Campus Condition Assessment
4Magellan Consulting, Inc.
Facility Condition Index (FCI)
The Facility Condition Index (FCI) is used throughout the facility condition assessment industry as a general indicator of a building’s health. The FCI is calculated by dividing the Facility Condition Cost plus five years of projected Life Cycle Capital Renewal Costs by the Replacement Value. Costs associated with new construction are not included in the FCI calculation. As a rule of thumb, an FCI below 10% is considered good. An FCI above 65% would suggest that the building is a candidate for replacement.
The Rio Grande Campus facility has an overall FCI of 26.69%
Rio Grande Campus Condition Assessment
Assessment Findings
The total current cost for all building deficiencies is $16,625,883. There are $695,753 in deficiencies at the site level that are included in the FCI calculation. The five year capital renewal cost was $606,598. The cost estimates were derived using a detailed listing of all noted deficiencies in the building. The cost to repair these deficiencies was then estimated using the cost data adjusted to El Paso, Texas (78% of national average).
The Replacement Value represents the estimated cost of replacing the current building with another building of like size, based on today’s estimated cost of construction in the El Paso, Texas area. The replacement cost for this facility is estimated to be $64,569,216.
The following pages provide a listing of all deficiencies and their associated cost for the site and building, followed by photos taken during the assessment.
Facilities Condition AssessmentRio Grande Campus Condition Assessment
5Magellan Consulting, Inc.
Lead Flashing Is Damaged And Should Be Repaired 23432 2 Ea. 2 $588 Yes
HVAC Curbs are too Low and Should be Raised and Reflashed (<8") 23232 2 Ea. 2 $2,768 No
Flashings At Drain Is Damaged And Should Be Repaired 23528 1 Ea. 2 $75 Yes
Membrane Flashing At Parapet (>2') Is Damaged And Should Be Repaired 23418 100 LF 2 $393 Yes
Membrane Flashings At Penetration Are Damaged And Should Be Repaired 23379 2 Ea. 2 $209 Yes
Membrane Flashings At Equipment Curbs Are Damaged And Should Be Repaired 23224 18 LF 2 $280 Yes
Membrane Flashings At Drain Is Damaged And Should Be Repaired 23209 2 Ea. 2 $293 Yes
Counter Flashing Is Damaged Or Loose And Should Be Replaced 23423 200 LF 2 $2,561 Yes
Coping Termination At End Wall Is Damaged And Should Be Repaired 23424 8 Ea. 2 $817 Yes
Concealed Gutter Is Damaged And Should Be Repaired 23459 20 SF 2 $233 No
Damaged Metal Closure Or Cement 23263 200 LF 2 $1,463 Yes
Expansion Joint Termination At End Wall Is Damaged And Should Be Repaired 23427 11 Ea. 2 $4,930 Yes
Expansion Joint Laps Are Damaged And Should Be Repaired 23425 11 Ea. 2 $3,969 Yes
Expansion Joint Cover Is Missing Or Damaged And Should Be Replaced 23426 20 LF 2 $1,432 Yes
Metal Coping Is Damaged Or Loose And Should Be Replaced 23317 30 LF 2 $1,489 Yes
Overflow Drain And Piping Is Missing And Is Needed 23216 4 Ea. 2 $5,005 No
Metal Umbrella At Penetration Or Pitch Pan Is Missing And Is Needed 23366 2 Ea. 2 $473 Yes
Metal Coping Lap Joints Have Lost Their Seal And Should Be Resealed 23315 40 Ea. 2 $331 Yes
Rake Tile Is Damaged And Requires Replacement 23354 10 LF 2 $249 Yes
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Handrails missing or not compliant. 20831 5 LF 2 $369 Yes
Sub Total for System 1 $369
SiteDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 4010A - Building A
The Pole Lighting Is Damaged And Should Be Replaced 19610 3 Ea. 2 $26,980 Yes
The Pole Lighting Is Damaged And Should Be Replaced 20036 3 Ea. 2 $26,980 Yes
The Pole Lighting Is Damaged And Should Be Replaced 19257 6 Ea. 2 $53,959 Yes
The Pole Lighting Is Damaged And Should Be Replaced 19325 2 Ea. 2 $17,987 Yes
The Pole Lighting Is Damaged And Should Be Replaced 20750 4 Ea. 2 $35,972 Yes
The Incandescent Lighting Is Damaged And Should Be Replaced 20827 2 Ea. 4 $728 No
The Pole Lighting Is Damaged And Should Be Replaced 22928 6 Ea. 2 $53,959 Yes
Sub Total for System 7 $216,565
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Asphalt Paving Is Damaged And Requires Replacement 19601 78 CAR 4 $198,649 No
The Van Accessible Parking Spaces Do Not Meet ADA Requirements 23750 4 Ea. 3 $1,077 No
Fencing Is Damaged And Should Be Replaced (8' Chain Link Fence) 19600 56 LF 4 $1,864 No
Asphalt Paving Is Damaged And Requires Replacement 23692 52 CAR 4 $132,432 No
The Car Accessible Parking Spaces Do Not Meet ADA Requirements 23752 8 Ea. 2 $2,153 No
Concrete Paving Is Damaged And Requires Replacement 22752 13 CAR 2 $30,682 No
Bleachers Are Damaged And Require Replacement 19609 10 Seat 2 $1,037 No
Site Drainage system requires replacement 23085 30 LF 2 $632 No
Concrete Walks Are Damaged And Require Replacement 19603 45 SF 2 $619 Yes
Paving Requires Restriping 23093 4 CAR 5 $723 No
Trash Receptacles Are Damaged And Require Replacement 19605 8 Ea. 5 $8,226 No
Wheel Stops Are Damaged And Require Replacement 19607 35 Ea. 5 $5,092 No
Paving Requires Restriping 20001 367 CAR 5 $66,259 No
Bollards Are Damaged And Require Replacement 19604 8 Ea. 5 $10,243 No
Paving Requires Restriping 19256 30 CAR 5 $5,416 No
Paving Requires Restriping 19602 78 CAR 5 $14,083 No
Sub Total for System 16 $479,188
Deficiency ID Qty UoM Priority Repair Cost WS&D
Site
Sub Total for School and Site Level 23 $695,753
Site Level Deficiencies
Facilities Condition AssessmentRio Grande Campus Condition Assessment
6Magellan Consulting, Inc.
The Power Service Is Inadequate And Should Be Upgraded 23150 225 Amps 2 $11,930 No
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 23069 206 Ea. 3 $72,734 No
The Panelboard Is Damaged And Should Be Replaced 23083 2 Amps 2 $60 Yes
The Electrical Circuit Capacity Is Inadequate 23439 126 EACH 2 $118,992 No
The GFCI Electrical Receptacles Are Inadequate And More Are Needed 23149 3 Ea. 2 $1,471 Yes
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 23070 58 Ea. 3 $20,479 No
The Incandescent Lighting Is Damaged And Should Be Replaced 23084 7 Ea. 3 $2,546 No
The Power Service Is Inadequate And Should Be Replaced 22744 450 Amps 3 $18,622 No
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 22986 250 Ea. 3 $134,352 No
The Electrical Receptacles Are Inadequate And More Are Needed 23142 30 Ea. 3 $13,299 No
Sub Total for System 10 $394,485
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Cleaning Required 23018 48,088 SF 3 $45,129 No
Duct Grill is Damaged And Should Be Replaced 23605 96 Ea. 3 $30,900 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 23031 48,088 SF 3 $107,759 No
Complete HVAC Systemwide Replacement 23581 48,088 SF 2 $675,817 No
Water cooled chiller required for redundancy 23718 1 Ea. 2 $134,720 No
Duct Grill is Damaged And Should Be Replaced 23606 15 Ea. 3 $4,828 No
Test And Balancing Required 23173 48,088 SF 3 $84,018 No
Exhaust Fan Ventilation Is Damaged And Should Be Replaced 23753 2 Ea. 4 $3,871 No
Duct Grill is Damaged And Should Be Replaced 23607 6 Ea. 3 $1,931 No
Ductwork Is Damaged And Should Be Replaced 23197 480 LF 3 $9,131 No
Sub Total for System 10 $1,098,104
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Interior Door Hardware is Damaged and Requires Replacement 23403 80 Door 5 $81,485 No
Restrooms require complete renovation 23832 1 LS 3 $318,500 No
The Carpet Flooring Is Damaged And Requires Replacement 22895 12,000 SF 3 $105,964 No
The Concrete Flooring Is Damaged And Requires Replacement 22924 1,000 SF 3 $7,220 No
Interior Doors Require Repainting 22886 100 Door 3 $5,322 No
Interior Doors Require Replacement 22887 22 Door 3 $27,704 No
Interior Toilet Partition Require Repair Or Replacement 23101 6 SF 3 $14,522 No
The Suspended Ceiling Grid is Damaged And Require Replacement 23122 3,600 SF 4 $29,025 No
Acoustical Wall Treatment is missing and is needed 23764 2,240 SF 5 $39,267 No
Interior Ceramic Walls Require Repair Or Replacement 23102 300 SF Wall 3 $4,441 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 22910 30,000 SF 3 $226,082 No
Interior Walls Require Repainting 22864 44,000 SF 4 $117,718 No
The Exposed Ceilings Are Damaged And Requires Repainting 23458 1,000 SF 4 $2,162 No
Sub Total for System 13 $979,411
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Steel Window Is Damaged And Requires Replacement 20892 146 Ea. 2 $292,321 Yes
The Glass Pane Is Damaged In The Exterior Window: 23525 380 SQFT 2 $26,150 Yes
The Steel Window Is Damaged And Requires Replacement 22824 19 Ea. 2 $38,042 Yes
Sub Total for System 3 $356,512
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Skylight Is Damaged And Should Be Repaired 23217 6 Ea. 2 $3,252 Yes
Splashblocks Are Missing Or Damaged And Are Needed 23253 6 Ea. 2 $619 No
Sealant At Pitch Pan Is Damaged And Should Be Repaired 23365 6 Ea. 2 $610 Yes
Roof Curb To Match HVAC Unit Is Missing And Is Needed 23233 1 Ea. 2 $914 No
Sealant At Penetration Boot Is Damaged And Should Be Repaired 23383 6 Ea. 2 $306 Yes
The Roof Drains Are Clogged 23200 2 Ea. 2 $235 Yes
The Roof Requires Cleaning 23344 100 SF 2 $379 Yes
Strainers Are Missing And Needed 23208 3 Ea. 2 $2,415 Yes
The Multi-Ply Bitumen Roof System Is Damaged And Requires Replacement 23320 14,432 SF 2 $173,843 No
Sub Total for System 28 $210,132
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Facilities Condition AssessmentRio Grande Campus Condition Assessment
7Magellan Consulting, Inc.
The Carpet Flooring Is Damaged And Requires Replacement 20715 12,539 SF 3 $110,723 No
The Ceramic Tile Flooring Is Damaged And Requires Replacement 20717 4,000 SF 3 $63,811 No
Restrooms require complete renovation 23833 1 LS 3 $482,300 No
The Interior Door Hardware is Damaged and Requires Replacement 20714 169 Ea. 2 $172,137 No
Interior Doors Require Replacement 20713 169 Door 3 $212,811 No
The Suspended Ceiling Grid is Damaged And Require Replacement 20707 46,606 SF 3 $375,766 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 20716 26,631 SF 3 $200,693 No
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Metal Exterior Door Is Damaged And Requires Repair 22785 4 Door 2 $4,335 Yes
The Brick Exterior Is Damaged And Requires Repair 22773 3,500 SF Wall 3 $41,087 No
Exterior door hardware is damaged and should be replaced 23563 9 Door 2 $5,431 Yes
The Aluminum Storefront Exterior Door Is Damaged And Requires Repair 22794 5 Door 2 $5,420 Yes
The Exterior Requires Painting 22771 10,500 SF Wall 4 $31,371 No
The Exterior Soffit Is Damaged And Requires Repair 23094 2,500 SF 3 $9,839 No
The Concrete / CMU Exterior Is Damaged And Requires Repair 22774 10,000 SF Wall 3 $173,446 No
Sub Total for System 7 $270,929
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Metal Coping Is Damaged Or Loose And Should Be Repaired 20727 30 LF 2 $1,838 Yes
Metal Coping Lap Joints Have Lost Their Seal And Should Be Resealed 20725 6 Ea. 2 $297 Yes
Flashings At Scupper Is Damaged And Should Be Repaired 20724 1 Ea. 2 $293 Yes
Membrane Flashings At Penetration Are Damaged And Should Be Repaired 20730 11 Ea. 2 $1,150 Yes
Metal Umbrella At Penetration Or Pitch Pan Is Missing And Is Needed 20729 3 Ea. 2 $710 Yes
Tapered Insulation Is Required To Eliminate Ponding When Re-Roofing 20723 1,000 SF 3 $3,407 No
Awning Or Canopy Roofing Decking Is Damaged 20721 100 SF 4 $923 No
The Roof Operable Hatch Is Damaged And Requires Repair 20722 1 Ea. 2 $568 Yes
The Roof Requires Cleaning 20733 100 SF 2 $379 Yes
Built Up Roofing (Bur) Membrane Has Holes That Should Be Repaired 20731 7 Ea. 2 $844 Yes
The Multi-Ply Bitumen Roof System Is Damaged And Requires Replacement 20732 1,150 SF 1 $13,852 No
Expansion Joint Termination At End Wall Is Damaged And Should Be Repaired 20728 8 Ea. 2 $3,585 Yes
Counter Flashing Is Damaged Or Loose And Should Be Repaired 20726 62 LF 2 $952 Yes
Sub Total for System 13 $28,798
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 4010B - Building B
The Upper Storage Cabinets Require Replacement 23103 24 LF 4 $4,363 No
Lift for Physically Impaired is Missing and is Needed 23800 1 Ea. 2 $34,922 No
The Base Storage Cabinets Require Replacement 23072 24 LF 4 $6,821 No
Sub Total for System 3 $46,106
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 22722 48,088 SF 2 $28,223 Yes
Security Alarm Panel Should be Replaced 23409 48 Ea. 1 $206,126 No
Fire Alarm Panel Should Be Replaced 22988 1 Ea. 1 $9,677 Yes
Sub Total for System 3 $244,026
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Restroom is Not ADA Compliant 20829 4 Ea. 3 $103,465 No
The Restroom is Not ADA Compliant 20830 4 Ea. 3 $103,465 No
The Rest Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 23059 6 Ea. 3 $9,839 No
Gas Piping Is Damaged And Requires Replacement 23141 480 LF 1 $12,474 No
The Refrigerated Water Cooler is Damaged And Should Be Repaired 23134 4 Ea. 3 $4,335 No
The Class Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 23133 10 Ea. 4 $20,517 No
The Urinal Plumbing Fixtures Are Damaged And Should Be Replaced 20828 2 Ea. 3 $3,058 No
The Toilets Plumbing Fixtures Are Damaged And Should Be Replaced 23060 7 Ea. 3 $9,267 No
Sub Total for System 8 $266,421
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 4010A - Building A 79 $3,595,566
Facilities Condition AssessmentRio Grande Campus Condition Assessment
8Magellan Consulting, Inc.
The Base Storage Cabinets Require Replacement 20718 60 LF 4 $17,053 No
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Elevator Cab Is Damaged And Requires Replacement 20720 1 Ea. 3 $59,095 No
Elevator Electrical System Should Be Cleaned And Inspected 20766 10 Stop 2 $41,713 Yes
Sub Total for System 2 $100,808
ConveyancesDeficiency ID Qty UoM Priority Repair Cost WS&D
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 20760 53,619 SF 2 $31,468 Yes
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 20761 53 Ea. 2 $28,276 Yes
Fire Alarm is Missing or Inadequate 20764 53,619 SF 1 $93,539 Yes
Security Alarm is Missing or Inadequate 20763 53,619 SF 2 $96,771 No
Sub Total for System 4 $250,053
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
Install Fire Sprinklers 20749 53,619 SF 3 $410,730 No
The Toilets Plumbing Fixtures Are Damaged And Should Be Replaced 20746 24 Ea. 3 $31,772 No
The Rest Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 20745 13 Ea. 4 $21,318 No
The Water Heater Plumbing Fixtures Are Damaged And Should Be Replaced 20747 2 Ea. 2 $4,628 No
The Custodial Mop Or Service Sink Is Damaged And Should Be Replaced 20743 5 Ea. 4 $19,742 No
The Refrigerated Water Cooler is Damaged And Should Be Replaced 20748 10 Ea. 4 $43,653 No
The Urinal Plumbing Fixtures Are Damaged And Should Be Replaced 20826 18 Ea. 3 $27,518 No
The Class Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 20744 4 Ea. 4 $8,206 No
Sub Total for System 8 $567,567
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The Panelboard Is Damaged And Should Be Replaced 20758 450 Amps 2 $13,696 Yes
The Electrical Receptacles Are Inadequate And More Are Needed 20765 8 Ea. 3 $3,547 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 20752 4 Ea. 2 $3,900 Yes
The 2 X 2 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20754 1 Ea. 4 $366 No
The Canopy Lighting Is Damaged And Should Be Replaced 20751 4 Ea. 2 $7,054 Yes
The Power Service Is Inadequate And Should Be Upgraded 20757 900 Amps 3 $47,724 No
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20753 187 Ea. 4 $66,026 No
The Incandescent Lighting Is Damaged And Should Be Replaced 20756 11 Ea. 4 $4,000 No
The Electrical Circuit Capacity Is Inadequate 20759 168 EACH 4 $158,657 No
Ceiling Fan Is Damaged And Should Be Replaced 20762 2 Ea. 4 $2,007 No
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20755 452 Ea. 4 $242,910 No
Sub Total for System 11 $549,888
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Large Diameter Exhausts/Hoods Are Missing/Damaged And Require Replacement 20734 4 Ea. 2 $6,810 No
The Package Unit HVAC Component Is Damaged And Requires Replacement 20739 20 TonAC 2 $53,339 No
The Chiller HVAC Component Is Damaged And Requires Replacement 20741 640 TonAC 2 $381,427 No
The Air Handler HVAC Component Is Damaged And Requires Replacement 20740 225,000 CFM 2 $1,295,955 No
The Boiler HVAC Component Is Damaged And Requires Replacement 20742 5,500 MBH 2 $124,634 No
Duct Grill is Damaged And Should Be Replaced 20737 237 Ea. 5 $76,283 No
Duct Grill is Damaged And Should Be Replaced 20738 118 Ea. 5 $37,982 No
Ductwork Is Damaged And Should Be Replaced 20736 500 LF 3 $9,511 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 20735 53,619 SF 4 $120,155 No
Sub Total for System 9 $2,106,095
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Toilet Partition Require Repair Or Replacement 20711 10 Ea. 4 $24,202 No
Interior Gypboard Walls Require Repair 20710 500 SF Wall 4 $4,415 No
Interior Walls Require Repainting 20709 53,619 SF 5 $143,452 No
Interior Ceramic Walls Require Repair Or Replacement 20712 20 SF Wall 4 $297 No
The Gypboard Ceilings Are Damaged And Requires Repainting 20708 7,013 SF 5 $18,635 No
Sub Total for System 12 $1,809,244
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Facilities Condition AssessmentRio Grande Campus Condition Assessment
9Magellan Consulting, Inc.
Built Up Roofing (Bur) Lap Seams Are Open Or Deteriorated 20769 100 LF 2 $4,954 Yes
Built Up Roofing (Bur) Membrane Has Holes That Should Be Repaired 20768 20 Ea. 2 $2,413 Yes
The Multi-Ply Bitumen Roof System Is Damaged And Requires Replacement 19410 5,625 SF 1 $67,757 No
Built Up Roofing (Bur) Covering Has Blisters That Should Be Repaired 20767 10 Ea. 2 $1,281 Yes
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 4040 - Student Services Building
Emergency Exit Signage Is Missing And Needed 19311 4 Ea. 2 $3,130 Yes
Fire Alarm is Missing or Inadequate 19312 5,156 SF 1 $15,519 Yes
Emergency Lighting Is Inadequate Or Not Present And Should Be Installed 19309 5,156 SF 2 $7,697 Yes
Sub Total for System 3 $26,346
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Electrical Circuit Capacity Is Inadequate 23731 20 EACH 4 $18,888 No
Sub Total for System 1 $18,888
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Package HVAC unit required 23732 1 Ea. 2 $22,501 No
Sub Total for System 1 $22,501
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 19319 1,000 SF 3 $7,537 No
The Carpet Flooring Is Damaged And Requires Replacement 19317 2,600 SF 3 $22,959 No
The Wood Flooring Is Damaged And Requires Replacement 19320 1,500 SF 3 $35,495 No
Interior Walls Require Repainting 19316 4,185 SF 5 $11,197 No
Sub Total for System 4 $77,188
Deficiency ID Qty UoM Priority Repair Cost WS&D
Interior
The Stucco Exterior Is Damaged And Requires Replacement 20654 1,546 SF Wall 4 $27,979 No
The Exterior Requires Painting 19294 1,500 SF Wall 5 $4,481 No
Sub Total for System 2 $32,460
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Structure is Damaged and Requires Repairs 23719 2,000 SF 2 $30,940 No
Sub Total for System 1 $30,940
StructuralDeficiency ID Qty UoM Priority Repair Cost WS&D
Lead Flashing Is Missing And Is Needed 19303 4 Ea. 2 $519 Yes
Membrane Flashing At Parapet (>2') Is Damaged And Should Be Repaired 19299 50 LF 2 $342 Yes
Membrane Flashings At Equipment Curbs Are Damaged And Should Be Repaired 19302 12 LF 2 $187 Yes
The Single-Ply Membrane Roof Covering Is Damaged And Requires Replacement 23615 15 SF 1 $619 No
Counter Flashing Is Damaged Or Loose And Should Be Replaced 19301 50 LF 2 $786 Yes
Edge Metal Is Loose And Should Be Resecured 19295 5 LF 2 $151 Yes
Membrane Flashings At Metal Edge Are Damaged And Should Be Repaired 19297 30 LF 2 $389 Yes
The Wood Roof Subdeck Is Damaged And Requires Replacement 19314 10 SF 2 $109 No
Wood Decking requires replacement 20880 15 SF 3 $2,146 No
Metal Umbrella At Penetration Or Pitch Pan Is Missing And Is Needed 19305 4 Ea. 2 $946 Yes
Membrane Flashings At Penetration Are Damaged And Should Be Repaired 19306 4 Ea. 2 $419 Yes
Metal Edge Termination At Wall Is Damaged And Should Be Repaired 19298 4 Ea. 2 $275 Yes
Sub Total for System 12 $6,889
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 4030 - Queen Anne Building 24 $215,211
Building: 4030 - Queen Anne Building
The Upper Storage Cabinets Require Replacement 20719 60 LF 4 $10,907 No
Sub Total for System 2 $27,961
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 4010B - Building B 68 $5,711,342
Facilities Condition AssessmentRio Grande Campus Condition Assessment
10Magellan Consulting, Inc.
The Power Service Is Inadequate And Should Be Upgraded 19399 450 Amps 3 $23,862 No
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19395 7 Ea. 4 $2,472 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 19394 2 Ea. 2 $1,949 Yes
The Electrical Receptacles Are Inadequate And More Are Needed 19403 40 Ea. 3 $17,732 No
The GFCI Electrical Receptacles Are Inadequate And More Are Needed 19404 2 Ea. 2 $979 Yes
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Furnaces HVAC Component Is Damaged And Requires Replacement 20563 12,000 MBH 2 $36,573 No
The Roof Air Handler/Exhaust is Damaged And Requires Replacement 20773 45 TonAC 2 $39,878 No
VAV boxes require replacement 23704 65 Ea. 2 $134,305 No
The Air Handler HVAC Component Is Damaged And Requires Replacement 19392 18,000 CFM 2 $103,676 No
The Chiller HVAC Component Is Damaged And Requires Replacement 19393 120 TonAC 2 $147,649 No
The Fan Coil HVAC Component Is Damaged And Requires Replacement 20771 50 TonAC 2 $140,579 No
LC: The Mechanical / HVAC Piping / 2-Pipe Water System (Hot) system is beyond its useful life. 23614 27,289 SF 3 $157,441 No
Duct Grill is Damaged And Should Be Replaced 19391 4 Ea. 5 $1,287 No
Exhaust Fan Ventilation Is Missing And Should Be Installed 19405 2 Ea. 5 $4,248 No
Duct Grill is Damaged And Should Be Replaced 19390 45 Ea. 5 $14,484 No
Test And Balancing Required 19388 29,173 SF 3 $50,971 No
Duct Cleaning Required 19389 29,173 SF 5 $27,378 No
Sub Total for System 12 $858,468
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Concrete Flooring Is Damaged And Requires Replacement 19423 1,458 SF 4 $10,529 No
Interior Wood Walls Require Repair 19416 16,000 SF Wall 4 $208,208 No
Interior Doors Require Repainting 19418 72 Door 5 $3,831 No
The Gypboard Ceilings Are Damaged And Requires Repainting 19414 7,000 SF 5 $18,600 No
Interior Walls Require Repainting 19415 29,000 SF 5 $77,587 No
The Wood Flooring Is Damaged And Requires Replacement 19421 10,210 SF 3 $241,607 No
The Carpet Flooring Is Damaged And Requires Replacement 19419 8,751 SF 3 $77,274 No
Interior Doors Require Replacement 19417 6 Door 3 $7,555 No
The Interior Door Hardware is Damaged and Requires Replacement 23681 78 Ea. 2 $79,448 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 19420 2,917 SF 3 $21,982 No
The Suspended Ceiling Grid is Damaged And Require Replacement 19413 22,000 SF 3 $177,377 No
The Ceramic Tile Flooring Is Damaged And Requires Replacement 19422 5,834 SF 3 $93,068 No
Sub Total for System 12 $1,017,065
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Metal Exterior Door Is Damaged And Requires Replacement 19362 1 Door 2 $2,357 Yes
The Aluminum Storefront Exterior Door Is Damaged And Requires Replacement 19364 3 Door 2 $13,068 Yes
Exterior door hardware is damaged and should be replaced 19365 2 Door 2 $1,207 Yes
The Wood Exterior Door Is Damaged And Requires Replacement 20770 4 Door 2 $7,986 Yes
The Wood Window Is Damaged And Requires Replacement 19377 8 Ea. 2 $9,926 No
The Wood Window Is Damaged And Requires Replacement 19367 30 Ea. 2 $37,221 No
Sub Total for System 6 $71,764
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Lead Flashing Is Missing And Is Needed 19386 2 Ea. 2 $260 Yes
Membrane Flashing At Parapet (>2') Is Damaged And Should Be Repaired 19383 300 LF 2 $599 Yes
Membrane Flashings At Metal Edge Are Damaged And Should Be Repaired 19381 25 LF 2 $326 Yes
Edge Metal Is Loose And Should Be Resecured 19380 25 LF 2 $753 Yes
Exhaust Fan Curbs are too Low and Should be Raised and Reflashed (<8") 19385 1 Ea. 2 $1,394 No
Flashings At Scupper Is Damaged And Should Be Repaired 19379 2 Ea. 2 $297 Yes
Membrane Flashings At Penetration Are Damaged And Should Be Repaired 19387 8 Ea. 2 $835 Yes
Thru-Wall Flashing At Rise-Wall Should Be Raised And Reflashed 19384 320 LF 2 $4,494 No
Splashblocks Are Missing Or Damaged And Are Needed 19378 2 Ea. 5 $206 No
The Wood Roof Subdeck Is Damaged And Requires Replacement 19408 100 SF 2 $1,318 No
Metal Edge Termination At Wall Is Damaged And Should Be Repaired 19382 2 Ea. 2 $138 Yes
The Roof Requires Cleaning 19411 20 SF 2 $362 Yes
Sub Total for System 16 $87,387
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Facilities Condition AssessmentRio Grande Campus Condition Assessment
11Magellan Consulting, Inc.
Gutters Are Damaged 19670 20 LF 2 $306 No
Lead Flashing Is Missing And Is Needed 19686 2 Ea. 2 $260 Yes
Gutter Joints Require Repair 19671 15 Ea. 2 $484 No
Gutter Screens Are Missing And Needed 19669 200 LF 2 $1,008 No
Membrane Flashings At Drain Is Damaged And Should Be Repaired 19678 2 Ea. 2 $293 Yes
Membrane Flashings At Equipment Curbs Are Damaged And Should Be Repaired 19683 24 LF 2 $373 Yes
Membrane Flashing At Gutter Edge Is Damaged And Should Be Repaired 19672 16 LF 2 $124 Yes
Membrane Flashing At Parapet (>2') Is Damaged And Should Be Repaired 19679 30 LF 2 $322 Yes
Built Up Roofing (Bur) Lap Seams Are Open Or Deteriorated 19731 200 LF 2 $9,906 Yes
Built Up Roofing (Bur) Membrane Has Holes That Should Be Repaired 19730 13 Ea. 2 $1,569 Yes
The Multi-Ply Bitumen Roof System Is Damaged And Requires Replacement 19733 21,580 SF 1 $259,945 No
Built Up Roofing (Bur) Covering Has Blisters That Should Be Repaired 19729 5 Ea. 2 $641 Yes
Exhaust Fan Curbs are too Low and Should be Raised and Reflashed (<8") 19684 2 Ea. 2 $2,788 No
Flashings At Drain Is Damaged And Should Be Repaired 19675 2 Ea. 2 $151 Yes
Counter Flashing Is Damaged Or Loose And Should Be Repaired 19681 110 LF 2 $1,463 Yes
Debris In Gutters Should Be Removed 19668 140 LF 2 $359 Yes
Skylight Is Damaged And Should Be Repaired 19685 4 Ea. 2 $2,168 Yes
Roof System Requires Replacement 20777 130 SQFT 2 $1,001 No
Sealant At Pitch Pan Is Damaged And Should Be Repaired 19689 2 Ea. 2 $442 Yes
Metal Coping Lap Joints Have Lost Their Seal And Should Be Resealed 19680 3 Ea. 2 $295 Yes
Metal Roof Jack Is Missing And Is Needed 19687 1 Ea. 2 $224 Yes
Membrane Flashings At Penetration Are Damaged And Should Be Repaired 19691 6 Ea. 2 $628 Yes
Metal Coping Is Damaged Or Loose And Should Be Repaired 19682 10 LF 2 $613 Yes
Roof System Requires Replacement 20775 350 SQFT 2 $2,695 No
Roof System Requires Replacement 20776 150 SQFT 2 $1,156 No
Metal Umbrella At Penetration Or Pitch Pan Is Missing And Is Needed 19690 4 Ea. 2 $946 Yes
Pitch Pan Is Damaged And Should Be Replaced 19688 1 Ea. 2 $400 Yes
Deficiency ID Qty UoM Priority Repair Cost WS&D
Roofing
Building: 4050 - Oregon Center
The Fixed Shelving Storage Cabinets Require Replacement 19424 48 LF 4 $4,210 No
Charging Desk requires replacement 23793 1 Ea. 3 $3,940 No
Sub Total for System 2 $8,150
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Elevator Cab Is Damaged And Requires Replacement 19425 3 Ea. 3 $177,288 No
Sub Total for System 1 $177,288
ConveyancesDeficiency ID Qty UoM Priority Repair Cost WS&D
Security Alarm Camera Is Missing Or Damaged And Should Be Replaced 23791 3 Ea. 2 $11,015 No
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 20772 29 Ea. 2 $15,472 Yes
Fire Alarm is Missing or Inadequate 19402 29,173 SF 1 $53,923 Yes
Security Alarm is Missing or Inadequate 19401 29,173 SF 2 $52,651 No
Sub Total for System 4 $133,060
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Toilets Plumbing Fixtures Are Damaged And Should Be Replaced 19407 2 Ea. 3 $2,648 No
Sump Pump requires replacement 23720 1 Ea. 2 $2,058 No
The Rest Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 19406 4 Ea. 4 $6,559 No
Sub Total for System 3 $11,266
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The Electrical Circuit Capacity Is Inadequate 19400 84 EACH 4 $79,328 No
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19397 81 Ea. 4 $43,531 No
The 2 X 2 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19396 2 Ea. 4 $732 No
The Incandescent Lighting Is Damaged And Should Be Replaced 19398 1 Ea. 4 $364 No
Sub Total for System 9 $170,949
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 4040 - Student Services Building 65 $2,535,398
Facilities Condition AssessmentRio Grande Campus Condition Assessment
12Magellan Consulting, Inc.
Fire Alarm is Missing or Inadequate 19725 23,239 SF 1 $44,435 Yes
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 19723 23 Ea. 2 $12,270 Yes
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
Install Fire Sprinklers 19728 23,239 SF 3 $178,014 No
The Water Heater Plumbing Fixtures Are Damaged And Should Be Replaced 19726 1 Ea. 2 $2,315 No
The Refrigerated Water Cooler is Damaged And Should Be Replaced 19727 3 Ea. 4 $13,097 No
Sub Total for System 3 $193,426
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19718 257 Ea. 4 $90,742 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 19717 7 Ea. 2 $6,825 Yes
The Canopy Lighting Is Damaged And Should Be Replaced 19716 2 Ea. 2 $3,527 Yes
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19719 155 Ea. 4 $83,298 No
The Incandescent Lighting Is Damaged And Should Be Replaced 19721 44 Ea. 4 $16,001 No
The Incandescent Lighting Is Damaged And Should Be Replaced 19720 3 Ea. 4 $1,090 No
Sub Total for System 6 $201,483
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Roof Air Handler/Exhaust is Damaged And Requires Replacement 19697 30 TonAC 2 $93,584 No
Test And Balancing Required 19700 23,239 SF 3 $40,602 No
The Large Diameter Exhausts/Hoods Are Missing/Damaged And Require Replacement 19695 4 Ea. 2 $6,810 No
The Package Unit HVAC Component Is Damaged And Requires Replacement 23682 21 TonAC 2 $56,007 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 19701 23,239 SF 4 $52,076 No
Duct Grill is Damaged And Should Be Replaced 20778 19 Ea. 5 $6,115 No
Duct Register is Damaged And Should Be Replaced 19712 42 Ea. 5 $34,664 No
Duct Cleaning Required 19703 23,239 SF 5 $21,809 No
Duct Grill is Damaged And Should Be Replaced 19710 63 Ea. 5 $20,278 No
The Exterior Condenser Is Damaged And Requires Replacement 19694 100 TonAC 2 $73,725 No
The Boiler HVAC Component Is Damaged And Requires Replacement 19715 1,200 MBH 2 $27,193 No
The Chiller HVAC Component Is Damaged And Requires Replacement 19714 100 TonAC 2 $123,041 No
Sub Total for System 12 $555,904
Deficiency ID Qty UoM Priority Repair Cost WS&D
Mechanical
The Suspended Ceiling Grid is Damaged And Require Replacement 19736 7,800 SF 3 $62,888 No
The Interior Door Hardware is Damaged and Requires Replacement 19739 42 Ea. 2 $42,779 No
The Carpet Flooring Is Damaged And Requires Replacement 19740 13,943 SF 3 $123,121 No
Interior Walls Require Repainting 19737 17,650 SF 5 $47,222 No
Interior Doors Require Repainting 19738 42 Door 5 $2,235 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 19741 4,647 SF 3 $35,020 No
Sub Total for System 6 $313,266
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Metal Exterior Door Is Damaged And Requires Replacement 19664 4 Door 2 $9,429 Yes
The Aluminum Window Is Damaged And Requires Replacement 19667 6 Ea. 2 $10,372 Yes
The Aluminum Storefront Exterior Door Is Damaged And Requires Replacement 19665 5 Door 2 $21,778 Yes
Exterior door hardware is damaged and should be replaced 19666 9 Door 2 $5,431 Yes
The Exterior Soffit Is Damaged And Requires Repainting 20774 23,239 SF 5 $100,069 No
The Exterior Requires Painting 19663 10,600 SF Wall 5 $31,670 No
Sub Total for System 6 $178,749
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Strainers Are Missing And Needed 19677 1 Ea. 2 $804 Yes
The Roof Drains Are Clogged 19676 1 Ea. 2 $116 Yes
The Multi-Ply Bitumen Roof Coating Requires Replacement 19732 1,659 SF 2 $10,820 No
The Roof Requires Cleaning 19734 63 SF 2 $371 Yes
Splashblocks Are Missing Or Damaged And Are Needed 19674 3 Ea. 5 $309 No
The Metal Downspouts Are Damaged Or Missing And Requires Replacement 19673 15 LF 3 $713 No
Sub Total for System 33 $303,696
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Facilities Condition AssessmentRio Grande Campus Condition Assessment
13Magellan Consulting, Inc.
The Wood Window Is Damaged And Requires Replacement 20079 14 Ea. 2 $17,370 No
The Wood Window Is Damaged And Requires Replacement 20080 15 Ea. 2 $18,610 No
The Wood Window Is Damaged And Requires Replacement 20077 14 Ea. 2 $17,370 No
Sub Total for System 3 $53,350
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Damaged Hip/Ridge 20098 30 LF 2 $349 Yes
Flashings At Scupper Is Damaged And Should Be Repaired 20085 2 Ea. 2 $297 Yes
Membrane Flashing At Curb (<2') 20087 70 LF 2 $1,090 Yes
Curbs are Too Low and Require Reflashing 20088 15 LF 2 $1,096 Yes
The Multi-Ply Bitumen Roof System Is Damaged And Requires Replacement 20097 2,100 SF 1 $25,296 No
Built Up Roofing (Bur) Covering Has Blisters That Should Be Repaired 20095 10 Ea. 2 $1,281 Yes
Built Up Roofing (Bur) Membrane Has Holes That Should Be Repaired 20096 10 Ea. 2 $1,207 Yes
Membrane Flashings At Equipment Curbs Are Damaged And Should Be Repaired 20091 16 LF 2 $249 Yes
Overflow Scuppers Are Missing And Are Needed 20086 2 Ea. 3 $935 No
The Roof Operable Hatch Is Damaged And Requires Replacement 20083 2 Ea. 3 $13,450 No
Splashblocks Are Missing Or Damaged And Are Needed 20084 2 Ea. 5 $206 No
Metal Coping Is Damaged Or Loose And Should Be Replaced 20090 190 LF 2 $9,429 Yes
The Wood Roof Subdeck Is Damaged And Requires Replacement 20094 50 SF 2 $659 No
Thru-Wall Flashing At Rise-Wall Should Be Raised And Reflashed 20089 30 LF 2 $588 No
Sub Total for System 14 $56,132
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 4070 - Community Center (Little Temple)
Elevator Cab And Or Controls Are Damaged Or Missing And Require Repair 20035 1 Ea. 2 $24,368 Yes
Elevator Electrical System Should Be Cleaned And Inspected 20033 4 Stop 2 $16,686 Yes
Sub Total for System 2 $41,054
ConveyancesDeficiency ID Qty UoM Priority Repair Cost WS&D
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 20031 1 Ea. 2 $533 Yes
Sub Total for System 1 $533
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The H.I.D. Lighting Is Damaged And Should Be Replaced 20029 6 Ea. 3 $3,516 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 20027 5 Ea. 2 $4,874 Yes
Sub Total for System 2 $8,390
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Package Unit HVAC Component Is Damaged And Requires Replacement 20791 2 TonAC 2 $5,334 No
Sub Total for System 1 $5,334
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Walls Require Repainting 20034 58,000 SF 5 $155,173 No
Sub Total for System 1 $155,173
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Flashing At Termination Wall Is Damaged And Should Be Repaired 20790 50 Ea. 2 $3,689 Yes
Built Up Roofing (Bur) Lap Seams Are Open Or Deteriorated 20788 15 LF 2 $743 Yes
Sub Total for System 2 $4,432
Deficiency ID Qty UoM Priority Repair Cost WS&D
Roofing
Sub Total for Building 4060 - Parking Garage 9 $214,917
Building: 4060 - Parking Garage
Security Alarm is Missing or Inadequate 19724 23,239 SF 2 $41,942 No
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 19722 23,239 SF 2 $13,639 Yes
Sub Total for System 4 $112,287
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 4050 - Oregon Center 70 $1,858,811
Facilities Condition AssessmentRio Grande Campus Condition Assessment
14Magellan Consulting, Inc.
Stairs not accessible. 20792 60 Riser 3 $19,510 No
Deficiency ID Qty UoM Priority Repair Cost WS&D
Conveyances
The Mounted Building Lighting Is Damaged And Should Be Replaced 20112 26 Ea. 2 $25,347 Yes
Sub Total for System 1 $25,347
Deficiency ID Qty UoM Priority Repair Cost WS&D
Electrical
The Roof Cooling Tower Is Damaged And Requires Replacement 20110 300 TonAC 2 $83,807 No
Test And Balancing Required 23792 26,000 SF 3 $45,427 No
Sub Total for System 2 $129,235
Deficiency ID Qty UoM Priority Repair Cost WS&D
Mechanical
Safety bars are missing and need to be installed 23721 100 Sq 2 $25,480 No
Sub Total for System 1 $25,480
Deficiency ID Qty UoM Priority Repair Cost WS&D
Interior
The Wood Exterior Door Is Damaged And Requires Repair 20100 1 Door 2 $542 Yes
Sub Total for System 1 $542
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Sealant At Penetration Boot Is Damaged And Should Be Repaired 20109 3 Ea. 2 $298 Yes
Single-Ply Lap Seams Are Open Or Deteriorated 20115 10 LF 2 $213 Yes
Metal Umbrella At Penetration Or Pitch Pan Is Missing And Is Needed 20106 2 Ea. 2 $473 Yes
Penetration Boot Is Damaged And Should Be Replaced 20108 2 Ea. 2 $262 Yes
The Roof Requires Cleaning 20116 20 SF 2 $362 Yes
Splashblocks Are Missing Or Damaged And Are Needed 20101 3 Ea. 5 $309 No
Single-Ply Membrane Has Holes That Should Be Repaired 20114 3 Ea. 2 $100 Yes
Strainers Are Missing And Needed 20103 1 Ea. 2 $804 Yes
Membrane Flashing At Parapet (>2') Is Damaged And Should Be Repaired 20105 30 LF 2 $322 Yes
Flashings At Scupper Is Damaged And Should Be Repaired 20102 2 Ea. 2 $297 Yes
Membrane Flashings At Drain Is Damaged And Should Be Repaired 20104 3 Ea. 2 $440 Yes
Metal Decking Is Damaged And Requires Repair 20113 50 SF 2 $906 Yes
Membrane Flashings At Penetration Are Damaged And Should Be Repaired 20107 4 Ea. 2 $419 Yes
Sub Total for System 13 $5,207
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 4080 - Health Building
Fire Alarm Actuator Is Missing And Is Needed 20093 1 Ea. 1 $282 Yes
Fire Alarm Horn/Strobe Is Missing And Is Needed 20092 2 Ea. 1 $1,301 Yes
Sub Total for System 2 $1,583
Deficiency ID Qty UoM Priority Repair Cost WS&D
Fire and Life Safety
The Pendant Lighting Is Damaged And Should Be Replaced 20864 3 Ea. 4 $5,529 No
Sub Total for System 1 $5,529
Deficiency ID Qty UoM Priority Repair Cost WS&D
Electrical
Complete HVAC Systemwide Replacement 23801 2,000 SF 2 $28,108 No
Sub Total for System 1 $28,108
Deficiency ID Qty UoM Priority Repair Cost WS&D
Mechanical
Metal panel ceiling requires replacement 20885 2,000 SF 3 $23,660 No
Auditorium renvation required 23785 1 Job 3 $1,201,200 No
The Wood Flooring Is Damaged And Requires Replacement 20099 2,000 SF 3 $47,327 No
Directional / wayfinding signage missing or not accessible. 23788 20 Ea. 5 $2,523 No
The Gypboard Ceilings Are Damaged And Requires Repair 23684 4,084 SF 4 $12,636 No
Sub Total for System 5 $1,287,346
Deficiency ID Qty UoM Priority Repair Cost WS&D
Interior
Sub Total for Building 4070 - Community Center (Little Temple) 26 $1,432,049
Facilities Condition AssessmentRio Grande Campus Condition Assessment
15Magellan Consulting, Inc.
Elevator Is Missing And Needed 23787 3 FLOOR 4 $161,514 No
Sub Total for System 2 $181,024
ConveyancesDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 4080 - Health Building 20 $366,836
Total for Campus 384 $16,625,883
Facilities Condition AssessmentRio Grande Campus Condition Assessment
16Magellan Consulting, Inc.
Supporting PhotosRio Grande Campus Condition Assessment
4010A Building A (57) - Photo 6
4010A Building A (53) - Photo 2
4010A Building A (55) - Photo 4
4010A Building A (56) - Photo 5
4010A Building A (52) - Photo 1
4010A Building A (54) - Photo 3
Facilities Condition AssessmentRio Grande Campus Condition Assessment
17Magellan Consulting, Inc.
4010A Building A (62) - Photo 12
4010A Building A (59) - Photo 8
4010A Building A (60) - Photo 10
4010A Building A (61) - Photo 11
4010A Building A (58) - Photo 7
4010A Building A (6) - Photo 9
Facilities Condition AssessmentRio Grande Campus Condition Assessment
18Magellan Consulting, Inc.
4010A Building A (68) - Photo 18
4010A Building A (64) - Photo 14
4010A Building A (66) - Photo 16
4010A Building A (67) - Photo 17
4010A Building A (63) - Photo 13
4010A Building A (65) - Photo 15
Facilities Condition AssessmentRio Grande Campus Condition Assessment
19Magellan Consulting, Inc.
4010A Building A (73) - Photo 24
4010A Building A (7) - Photo 20
4010A Building A (71) - Photo 22
4010A Building A (72) - Photo 23
4010A Building A (69) - Photo 19
4010A Building A (70) - Photo 21
Facilities Condition AssessmentRio Grande Campus Condition Assessment
20Magellan Consulting, Inc.
4010A Building A (79) - Photo 30
4010A Building A (75) - Photo 26
4010A Building A (77) - Photo 28
4010A Building A (78) - Photo 29
4010A Building A (74) - Photo 25
4010A Building A (76) - Photo 27
Facilities Condition AssessmentRio Grande Campus Condition Assessment
21Magellan Consulting, Inc.
4010B Building B (1) - Photo 36
4010A Building A (80) - Photo 32
4010A Building A (82) - Photo 34
4010A Building A (9) - Photo 35
4010A Building A (8) - Photo 31
4010A Building A (81) - Photo 33
Facilities Condition AssessmentRio Grande Campus Condition Assessment
22Magellan Consulting, Inc.
4010B Building B (15) - Photo 42
4010B Building B (11) - Photo 38
4010B Building B (13) - Photo 40
4010B Building B (14) - Photo 41
4010B Building B (10) - Photo 37
4010B Building B (12) - Photo 39
Facilities Condition AssessmentRio Grande Campus Condition Assessment
23Magellan Consulting, Inc.
4010B Building B (20) - Photo 48
4010B Building B (17) - Photo 44
4010B Building B (19) - Photo 46
4010B Building B (2) - Photo 47
4010B Building B (16) - Photo 43
4010B Building B (18) - Photo 45
Facilities Condition AssessmentRio Grande Campus Condition Assessment
24Magellan Consulting, Inc.
4010B Building B (4) - Photo 54
4010B Building B (22) - Photo 50
4010B Building B (24) - Photo 52
4010B Building B (25) - Photo 53
4010B Building B (21) - Photo 49
4010B Building B (23) - Photo 51
Facilities Condition AssessmentRio Grande Campus Condition Assessment
25Magellan Consulting, Inc.
4030 Queen Anne House (10) - Photo 60
4010B Building B (7) - Photo 56
4010B Building B (9) - Photo 58
4030 Queen Anne House (1) - Photo 59
4010B Building B (5) - Photo 55
4010B Building B (8) - Photo 57
Facilities Condition AssessmentRio Grande Campus Condition Assessment
26Magellan Consulting, Inc.
4030 Queen Anne House (16) - Photo 66
4030 Queen Anne House (12) - Photo 62
4030 Queen Anne House (14) - Photo 64
4030 Queen Anne House (15) - Photo 65
4030 Queen Anne House (11) - Photo 61
4030 Queen Anne House (13) - Photo 63
Facilities Condition AssessmentRio Grande Campus Condition Assessment
27Magellan Consulting, Inc.
4030 Queen Anne House (21) - Photo 72
4030 Queen Anne House (18) - Photo 68
4030 Queen Anne House (2) - Photo 70
4030 Queen Anne House (20) - Photo 71
4030 Queen Anne House (17) - Photo 67
4030 Queen Anne House (19) - Photo 69
Facilities Condition AssessmentRio Grande Campus Condition Assessment
28Magellan Consulting, Inc.
4040 Student Srvc Center (47) - Photo 78
4040 Student Srvc Center (42) - Photo 74
4040 Student Srvc Center (44) - Photo 76
4040 Student Srvc Center (46) - Photo 77
4040 Student Srvc Center (41) - Photo 73
4040 Student Srvc Center (43) - Photo 75
Facilities Condition AssessmentRio Grande Campus Condition Assessment
29Magellan Consulting, Inc.
4040 Student Srvc Center (52) - Photo 84
4040 Student Srvc Center (49) - Photo 80
4040 Student Srvc Center (50) - Photo 82
4040 Student Srvc Center (51) - Photo 83
4040 Student Srvc Center (48) - Photo 79
4040 Student Srvc Center (5) - Photo 81
Facilities Condition AssessmentRio Grande Campus Condition Assessment
30Magellan Consulting, Inc.
4040 Student Srvc Center (58) - Photo 90
4040 Student Srvc Center (54) - Photo 86
4040 Student Srvc Center (56) - Photo 88
4040 Student Srvc Center (57) - Photo 89
4040 Student Srvc Center (53) - Photo 85
4040 Student Srvc Center (55) - Photo 87
Facilities Condition AssessmentRio Grande Campus Condition Assessment
31Magellan Consulting, Inc.
4040 Student Srvc Center (63) - Photo 96
4040 Student Srvc Center (6) - Photo 92
4040 Student Srvc Center (61) - Photo 94
4040 Student Srvc Center (62) - Photo 95
4040 Student Srvc Center (59) - Photo 91
4040 Student Srvc Center (60) - Photo 93
Facilities Condition AssessmentRio Grande Campus Condition Assessment
32Magellan Consulting, Inc.
4040 Student Srvc Center (69) - Photo 102
4040 Student Srvc Center (65) - Photo 98
4040 Student Srvc Center (67) - Photo 100
4040 Student Srvc Center (68) - Photo 101
4040 Student Srvc Center (64) - Photo 97
4040 Student Srvc Center (66) - Photo 99
Facilities Condition AssessmentRio Grande Campus Condition Assessment
33Magellan Consulting, Inc.
4040 Student Srvc Center (75) - Photo 108
4040 Student Srvc Center (70) - Photo 104
4040 Student Srvc Center (73) - Photo 106
4040 Student Srvc Center (74) - Photo 107
4040 Student Srvc Center (7) - Photo 103
4040 Student Srvc Center (71) - Photo 105
Facilities Condition AssessmentRio Grande Campus Condition Assessment
34Magellan Consulting, Inc.
4040 Student Srvc Center (82) - Photo 114
4040 Student Srvc Center (78) - Photo 110
4040 Student Srvc Center (8) - Photo 112
4040 Student Srvc Center (81) - Photo 113
4040 Student Srvc Center (77) - Photo 109
4040 Student Srvc Center (79) - Photo 111
Facilities Condition AssessmentRio Grande Campus Condition Assessment
35Magellan Consulting, Inc.
4040 Student Srvc Center (9) - Photo 120
4040 Student Srvc Center (86) - Photo 116
4040 Student Srvc Center (88) - Photo 118
4040 Student Srvc Center (89) - Photo 119
4040 Student Srvc Center (83) - Photo 115
4040 Student Srvc Center (87) - Photo 117
Facilities Condition AssessmentRio Grande Campus Condition Assessment
36Magellan Consulting, Inc.
4040 Student Srvc Center (95) - Photo 126
4040 Student Srvc Center (91) - Photo 122
4040 Student Srvc Center (93) - Photo 124
4040 Student Srvc Center (94) - Photo 125
4040 Student Srvc Center (90) - Photo 121
4040 Student Srvc Center (92) - Photo 123
Facilities Condition AssessmentRio Grande Campus Condition Assessment
37Magellan Consulting, Inc.
4050 Oregon Center (10) - Photo 132
4040 Student Srvc Center (97) - Photo 128
4040 Student Srvc Center (99) - Photo 130
4050 Oregon Center (1) - Photo 131
4040 Student Srvc Center (96) - Photo 127
4040 Student Srvc Center (98) - Photo 129
Facilities Condition AssessmentRio Grande Campus Condition Assessment
38Magellan Consulting, Inc.
4050 Oregon Center (5) - Photo 138
4050 Oregon Center (12) - Photo 134
4050 Oregon Center (3) - Photo 136
4050 Oregon Center (4) - Photo 137
4050 Oregon Center (11) - Photo 133
4050 Oregon Center (2) - Photo 135
Facilities Condition AssessmentRio Grande Campus Condition Assessment
39Magellan Consulting, Inc.
4080 Health and Science (13) - Photo 144
4050 Oregon Center (7) - Photo 140
4080 Health and Science (11) - Photo 142
4080 Health and Science (12) - Photo 143
4050 Oregon Center (6) - Photo 139
4080 Health and Science (10) - Photo 141
Facilities Condition AssessmentRio Grande Campus Condition Assessment
40Magellan Consulting, Inc.
4080 Health and Science (4) - Photo 150
4080 Health and Science (15) - Photo 146
4080 Health and Science (2) - Photo 148
4080 Health and Science (3) - Photo 149
4080 Health and Science (14) - Photo 145
4080 Health and Science (16) - Photo 147
Facilities Condition AssessmentRio Grande Campus Condition Assessment
41Magellan Consulting, Inc.
4030 Queen Anne House (22) - Photo 156
4080 Health and Science (6) - Photo 152
4080 Health and Science (8) - Photo 154
4080 Health and Science (9) - Photo 155
4080 Health and Science (5) - Photo 151
4080 Health and Science (7) - Photo 153
Facilities Condition AssessmentRio Grande Campus Condition Assessment
42Magellan Consulting, Inc.
4030 Queen Anne House (29) - Photo 162
4030 Queen Anne House (25) - Photo 158
4030 Queen Anne House (27) - Photo 160
4030 Queen Anne House (28) - Photo 161
4030 Queen Anne House (23) - Photo 157
4030 Queen Anne House (26) - Photo 159
Facilities Condition AssessmentRio Grande Campus Condition Assessment
43Magellan Consulting, Inc.
4030 Queen Anne House (5) - Photo 168
4030 Queen Anne House (30) - Photo 164
4030 Queen Anne House (32) - Photo 166
4030 Queen Anne House (4) - Photo 167
4030 Queen Anne House (3) - Photo 163
4030 Queen Anne House (31) - Photo 165
Facilities Condition AssessmentRio Grande Campus Condition Assessment
44Magellan Consulting, Inc.
4040 Student Srvc Center - Old Chiller Unit - Photo 174
4030 Queen Anne House (7) - Photo 170
4030 Queen Anne House (9) - Photo 172
4040 Student Srvc Center - Air Handler - Photo 173
4030 Queen Anne House (6) - Photo 169
4030 Queen Anne House (8) - Photo 171
Facilities Condition AssessmentRio Grande Campus Condition Assessment
45Magellan Consulting, Inc.
4040 Student Srvc Center (103) - Photo 180
4040 Student Srvc Center (10) - Photo 176
4040 Student Srvc Center (101) - Photo 178
4040 Student Srvc Center (102) - Photo 179
4040 Student Srvc Center (1) - Photo 175
4040 Student Srvc Center (100) - Photo 177
Facilities Condition AssessmentRio Grande Campus Condition Assessment
46Magellan Consulting, Inc.
4040 Student Srvc Center (109) - Photo 186
4040 Student Srvc Center (105) - Photo 182
4040 Student Srvc Center (107) - Photo 184
4040 Student Srvc Center (108) - Photo 185
4040 Student Srvc Center (104) - Photo 181
4040 Student Srvc Center (106) - Photo 183
Facilities Condition AssessmentRio Grande Campus Condition Assessment
47Magellan Consulting, Inc.
4040 Student Srvc Center (114) - Photo 192
4040 Student Srvc Center (110) - Photo 188
4040 Student Srvc Center (112) - Photo 190
4040 Student Srvc Center (113) - Photo 191
4040 Student Srvc Center (11) - Photo 187
4040 Student Srvc Center (111) - Photo 189
Facilities Condition AssessmentRio Grande Campus Condition Assessment
48Magellan Consulting, Inc.
4040 Student Srvc Center (14) - Photo 198
4040 Student Srvc Center (116) - Photo 194
4040 Student Srvc Center (12) - Photo 196
4040 Student Srvc Center (13) - Photo 197
4040 Student Srvc Center (115) - Photo 193
4040 Student Srvc Center (117) - Photo 195
Facilities Condition AssessmentRio Grande Campus Condition Assessment
49Magellan Consulting, Inc.
4040 Student Srvc Center (2) - Photo 204
4040 Student Srvc Center (16) - Photo 200
4040 Student Srvc Center (18) - Photo 202
4040 Student Srvc Center (19) - Photo 203
4040 Student Srvc Center (15) - Photo 199
4040 Student Srvc Center (17) - Photo 201
Facilities Condition AssessmentRio Grande Campus Condition Assessment
50Magellan Consulting, Inc.
4040 Student Srvc Center (25) - Photo 210
4040 Student Srvc Center (21) - Photo 206
4040 Student Srvc Center (23) - Photo 208
4040 Student Srvc Center (24) - Photo 209
4040 Student Srvc Center (20) - Photo 205
4040 Student Srvc Center (22) - Photo 207
Facilities Condition AssessmentRio Grande Campus Condition Assessment
51Magellan Consulting, Inc.
4040 Student Srvc Center (30) - Photo 216
4040 Student Srvc Center (27) - Photo 212
4040 Student Srvc Center (29) - Photo 214
4040 Student Srvc Center (3) - Photo 215
4040 Student Srvc Center (26) - Photo 211
4040 Student Srvc Center (28) - Photo 213
Facilities Condition AssessmentRio Grande Campus Condition Assessment
52Magellan Consulting, Inc.
4040 Student Srvc Center (36) - Photo 222
4040 Student Srvc Center (32) - Photo 218
4040 Student Srvc Center (34) - Photo 220
4040 Student Srvc Center (35) - Photo 221
4040 Student Srvc Center (31) - Photo 217
4040 Student Srvc Center (33) - Photo 219
Facilities Condition AssessmentRio Grande Campus Condition Assessment
53Magellan Consulting, Inc.
4050 Oregon Center (8) - Photo 228
4040 Student Srvc Center (38) - Photo 224
4040 Student Srvc Center (4) - Photo 226
4040 Student Srvc Center (40) - Photo 227
4040 Student Srvc Center (37) - Photo 223
4040 Student Srvc Center (39) - Photo 225
Facilities Condition AssessmentRio Grande Campus Condition Assessment
54Magellan Consulting, Inc.
4060 Parking Garage (13) - Photo 234
4060 Parking Garage (1) - Photo 230
4060 Parking Garage (11) - Photo 232
4060 Parking Garage (12) - Photo 233
4050 Oregon Center (9) - Photo 229
4060 Parking Garage (10) - Photo 231
Facilities Condition AssessmentRio Grande Campus Condition Assessment
55Magellan Consulting, Inc.
4060 Parking Garage (19) - Photo 240
4060 Parking Garage (15) - Photo 236
4060 Parking Garage (17) - Photo 238
4060 Parking Garage (18) - Photo 239
4060 Parking Garage (14) - Photo 235
4060 Parking Garage (16) - Photo 237
Facilities Condition AssessmentRio Grande Campus Condition Assessment
56Magellan Consulting, Inc.
4060 Parking Garage (24) - Photo 246
4060 Parking Garage (20) - Photo 242
4060 Parking Garage (22) - Photo 244
4060 Parking Garage (23) - Photo 245
4060 Parking Garage (2) - Photo 241
4060 Parking Garage (21) - Photo 243
Facilities Condition AssessmentRio Grande Campus Condition Assessment
57Magellan Consulting, Inc.
4060 Parking Garage (3) - Photo 252
4060 Parking Garage (26) - Photo 248
4060 Parking Garage (28) - Photo 250
4060 Parking Garage (29) - Photo 251
4060 Parking Garage (25) - Photo 247
4060 Parking Garage (27) - Photo 249
Facilities Condition AssessmentRio Grande Campus Condition Assessment
58Magellan Consulting, Inc.
4060 Parking Garage (36) - Photo 258
4060 Parking Garage (31) - Photo 254
4060 Parking Garage (34) - Photo 256
4060 Parking Garage (35) - Photo 257
4060 Parking Garage (30) - Photo 253
4060 Parking Garage (32) - Photo 255
Facilities Condition AssessmentRio Grande Campus Condition Assessment
59Magellan Consulting, Inc.
4060 Parking Garage (6) - Photo 264
4060 Parking Garage (39) - Photo 260
4060 Parking Garage (40) - Photo 262
4060 Parking Garage (5) - Photo 263
4060 Parking Garage (38) - Photo 259
4060 Parking Garage (4) - Photo 261
Facilities Condition AssessmentRio Grande Campus Condition Assessment
60Magellan Consulting, Inc.
4070 Community Center (11) - Photo 270
4060 Parking Garage (8) - Photo 266
4070 Community Center (1) - Photo 268
4070 Community Center (10) - Photo 269
4060 Parking Garage (7) - Photo 265
4060 Parking Garage (9) - Photo 267
Facilities Condition AssessmentRio Grande Campus Condition Assessment
61Magellan Consulting, Inc.
4070 Community Center (17) - Photo 276
4070 Community Center (13) - Photo 272
4070 Community Center (15) - Photo 274
4070 Community Center (16) - Photo 275
4070 Community Center (12) - Photo 271
4070 Community Center (14) - Photo 273
Facilities Condition AssessmentRio Grande Campus Condition Assessment
62Magellan Consulting, Inc.
4070 Community Center (27) - Photo 282
4070 Community Center (2) - Photo 278
4070 Community Center (21) - Photo 280
4070 Community Center (23) - Photo 281
4070 Community Center (18) - Photo 277
4070 Community Center (20) - Photo 279
Facilities Condition AssessmentRio Grande Campus Condition Assessment
63Magellan Consulting, Inc.
4070 Community Center (4) - Photo 288
4070 Community Center (29) - Photo 284
4070 Community Center (30) - Photo 286
4070 Community Center (31) - Photo 287
4070 Community Center (28) - Photo 283
4070 Community Center (3) - Photo 285
Facilities Condition AssessmentRio Grande Campus Condition Assessment
64Magellan Consulting, Inc.
4010A Building A - Air Handler 2 - Photo 294
4070 Community Center (6) - Photo 290
4070 Community Center (8) - Photo 292
4070 Community Center (9) - Photo 293
4070 Community Center (5) - Photo 289
4070 Community Center (7) - Photo 291
Facilities Condition AssessmentRio Grande Campus Condition Assessment
65Magellan Consulting, Inc.
4010A Building A - Ventilation Fan - Photo 300
4010A Building A - Building Signage - Photo 296
4010A Building A - Fire Sprinkler - Photo 298
4010A Building A - Interior Piping - Photo 299
4010A Building A - Air Handler - Photo 295
4010A Building A - Classroom AC Unit - Photo 297
Facilities Condition AssessmentRio Grande Campus Condition Assessment
66Magellan Consulting, Inc.
4010A Building A (14) - Photo 306
4010A Building A (10) - Photo 302
4010A Building A (12) - Photo 304
4010A Building A (13) - Photo 305
4010A Building A (1) - Photo 301
4010A Building A (11) - Photo 303
Facilities Condition AssessmentRio Grande Campus Condition Assessment
67Magellan Consulting, Inc.
4010A Building A (2) - Photo 312
4010A Building A (16) - Photo 308
4010A Building A (18) - Photo 310
4010A Building A (19) - Photo 311
4010A Building A (15) - Photo 307
4010A Building A (17) - Photo 309
Facilities Condition AssessmentRio Grande Campus Condition Assessment
68Magellan Consulting, Inc.
4010A Building A (26) - Photo 318
4010A Building A (21) - Photo 314
4010A Building A (23) - Photo 316
4010A Building A (25) - Photo 317
4010A Building A (20) - Photo 313
4010A Building A (22) - Photo 315
Facilities Condition AssessmentRio Grande Campus Condition Assessment
69Magellan Consulting, Inc.
4010A Building A (31) - Photo 324
4010A Building A (28) - Photo 320
4010A Building A (3) - Photo 322
4010A Building A (30) - Photo 323
4010A Building A (27) - Photo 319
4010A Building A (29) - Photo 321
Facilities Condition AssessmentRio Grande Campus Condition Assessment
70Magellan Consulting, Inc.
4010A Building A (37) - Photo 330
4010A Building A (33) - Photo 326
4010A Building A (35) - Photo 328
4010A Building A (36) - Photo 329
4010A Building A (32) - Photo 325
4010A Building A (34) - Photo 327
Facilities Condition AssessmentRio Grande Campus Condition Assessment
71Magellan Consulting, Inc.
4010A Building A (42) - Photo 336
4010A Building A (39) - Photo 332
4010A Building A (40) - Photo 334
4010A Building A (41) - Photo 335
4010A Building A (38) - Photo 331
4010A Building A (4) - Photo 333
Facilities Condition AssessmentRio Grande Campus Condition Assessment
72Magellan Consulting, Inc.
4010A Building A (48) - Photo 342
4010A Building A (44) - Photo 338
4010A Building A (46) - Photo 340
4010A Building A (47) - Photo 341
4010A Building A (43) - Photo 337
4010A Building A (45) - Photo 339
Facilities Condition AssessmentRio Grande Campus Condition Assessment
73Magellan Consulting, Inc.
4010A Building A (50) - Photo 344
4010A Building A (51) - Photo 345
4010A Building A (5) - Photo 343
Appendix G –
Transmountain Campus
Condition Assessment Report
Facilities Condition AssessmentTransmountain Campus Condition Assessment
1Magellan Consulting, Inc.
Transmountain Campus Condition Assessment
3040-10 Humanities Bldg. 10 (1807) 800 1979 $70,445 52.69% $88.06 $10,454
3040-11 Humanities Bldg. 11 (1808) 800 1979 $71,790 53.25% $89.74 $9,973
3040-12 Humanities Bldg. 12 (1809) 800 1979 $71,264 55.12% $89.08 $13,370
3040-09 Humanities Bldg. 09 (1806) 800 1979 $73,472 56.43% $91.84 $13,171
3040-06 Humanities Bldg. 06(1803) 824 1979 $97,150 71.69% $117.90 $16,227
3040-07 Humanities Bldg. 07 (1804) 824 1979 $92,389 66.74% $112.12 $13,159
3040-08 Humanities Bldg. 08 (1805) 829 1979 $99,721 74.28% $120.29 $18,459
3040-17 Humanities Bldg. 17 (1814) 1,753 1979 $192,227 57.17% $109.66 $103
3062 Bookstore 7,506 1979 $916,672 64.56% $122.13 $13,356
3000 Interior Circulation 50,000 1979 $1,404,245 16.56% $28.08 $184,750
3040-16 Humanities Bldg. 16 (1813) 800 1979 $55,788 42.95% $69.74 $10,161
3040-13 Humanities Bldg. 13 (1810) 800 1979 $69,670 51.87% $87.09 $9,973
3040-14 Humanities Bldg. 14 (1811) 800 1979 $72,070 54.09% $90.09 $10,972
3040-15 Humanities Bldg. 15 (1812) 800 1979 $61,727 46.48% $77.16 $9,629
3040-05 Humanities Bldg. 05 (1802) 824 1979 $107,802 75.47% $130.83 $11,554
3040-01 Humanities Bldg. 1 (1700) 2,238 1979 $343,110 88.77% $153.31 $38,179
3050 Science and Technology 25,743 1979 $2,176,613 49.88% $84.55 $287,537
3060 Business Area 14,354 1979 $987,021 41.83% $68.76 $165,282
Site 0 0 $4,168,650 .00% $0.00 $0
3025 Liberal Arts Building 14,366 1997 $691,534 26.00% $48.14 $25,422
3030 Lecture Forum 11,517 1979 $1,862,111 92.40% $161.68 $180,309
3070 Gymnasium Building 9,171 1979 $866,555 56.03% $94.49 $119,547
3040-02 Humanities Bldg. 2 (1702) 2,637 1979 $168,193 41.60% $63.78 $42,358
3040-03 Humanities Bldg. 03 (1800) 800 1979 $91,710 66.02% $114.64 $9,655
3040-04 Humanities Bldg. 04 (1801) 800 1979 $81,059 60.43% $101.32 $11,728
3010 Administration 10,528 1979 $1,000,723 61.82% $95.05 $248,305
3091 Classroom Addition 14,363 1997 $0 .00% $0.00 $0
3020 Learning Resources Center 23,370 1979 $1,368,110 33.98% $58.54 $156,065
Totals 198,847 $17,261,820 49.50% $86.81 $1,629,696
Facility Condition by Building
Number Building Name Gross Sq Ft Built DateFacility Condition
Cost FCICost Per
Square FootFuture Life Cycle
Cost (Yr 1-5)
The Transmountain Campus Facility located at 9570 Gateway Blvd. North in El Paso, Texas, was built in 1979. It comprises approximately 198,847 gross square feet.
Summary of Findings
The total current deficiencies for this site, in 2008 construction cost dollars, are estimated at $17,261,820.
Cross Tab of Current Deficiencies
The following chart summarizes the current deficiencies for this site in a cross tab that shows the buildings systems down the left and the priority of the deficiency across the top. This listing includes current deficiencies including deferred maintenance, functional deficiencies, code compliance, Americans with Disabilities Act, and Life Cycle Capital Renewal categories.
Facilities Condition AssessmentTransmountain Campus Condition Assessment
2Magellan Consulting, Inc.
Electrical $2,619 $825,865 $85,755 $1,247,011 - $2,161,250
Mechanical - $3,009,601 $341,532 $307,345 $379,101 $4,037,579
Interior - $214,924 $2,240,653 $311,879 $495,903 $3,263,358
Plumbing - $32,027 $431,755 $161,618 - $625,399
Conveyances - - $59,095 - - $59,095
Technology $188,920 - - - - $188,920
Fire and Life Safety $318,183 $368,614 - - - $686,797
Site - $110,993 $13,887 $3,183,793 $438,118 $3,746,790
Specialties - - $4,486 $279,556 - $284,042
Other - - - - - $0
Exterior - $632,821 $26,978 $107,899 $201,578 $969,276
Structural - - - - - $0
Roofing $810,344 $346,914 $63,371 $15,288 $3,398 $1,239,314
Total $1,320,066 $5,541,758 $3,267,511 $5,614,389 $1,518,097 $17,261,820
Facility Condition - System by PriorityPriority
System 1 2 3 4 5 Total
Facilities Condition AssessmentTransmountain Campus Condition Assessment
3Magellan Consulting, Inc.
Portable Buildings - - - - - $0
New Construction - - - - - $0
Hazardous Material - - - - - $0
Functional Deficiency $188,920 $1,120,590 $10,319 $259,568 $79,126 $1,658,524
Energy Efficiency - $2,841,018 $346,228 $1,247,011 - $4,434,257
Educational Adequacy - - - - - $0
Deferred Maintenance $4,295 $490,559 $152,096 $623,284 $1,166,360 $2,436,594
Code Compliance $200,038 $16,163 $183,614 - - $399,816
Capital Renewal $926,813 $767,503 $2,471,789 $3,484,525 $272,611 $7,923,241
ADA Compliance - $305,924 $103,465 - - $409,389
Total $1,320,066 $5,541,758 $3,267,511 $5,614,389 $1,518,097 $17,261,820
Facility Condition - Category by PriorityPriority
Category 1 2 3 4 5 Total
All deficiencies have been further categorized according to the type of deficiency observed. Capital Renewal items include those that are included in the life cycle forecast and are items that have reached or exceeded their useful life. Americans with Disabilities Act deficiencies are associated with accessibility compliance concerns. Code Compliance includes items that are a building code related deficiency. Deferred Maintenance items are those items that have broken or are in need of repair prior to reaching the end of life term. A Functional Deficiency is one that is presently not in place, or is not functioning correctly, and should be added to the building.
Life Cycle Capital Renewal Forecast
As part of the assessment process, this facility was analyzed according to twelve major building systems. Each system has subsystems, and each subsystem is further distinguished by type. For each line item, the original year, or most recent replacement year if applicable, was identified. Then, the historical life was compared to a model of expected life for each subsystem type. The remaining year was then forecasted by subtracting the expected life from the life used, and further adjusted for the apparent maintenance quality of the subsystem. In some cases, the calculation was overridden if the assessor’s judgment suggested a shorter or longer than expected life expectancy.
Once each subsystem was analyzed, they were combined to provide a 10-year life cycle capital renewal forecast for the building. The following chart shows all deficiencies and the subsequent year’s capital renewal projections for all systems where a component is expected to reach the end of its useful life and require capital dollars for replacement.
The chart on the following page shows the forecast in thousands ($000s) for the next ten years.
Facilities Condition AssessmentTransmountain Campus Condition Assessment
4Magellan Consulting, Inc.
Fire and Life Safety 687 0 0 80 51 0 0 0 0 0 385 $516 $4.23
Plumbing 625 0 0 0 4 29 6 0 2 0 39 $80 $0.66
Electrical 2,161 0 0 25 18 0 5 4 1,982 0 3 $2,037 $16.71
Technology 189 0 0 72 0 137 102 0 0 0 15 $326 $2.68
Other 0 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Specialties 284 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Conveyances 59 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Mechanical 4,038 0 0 0 95 133 7 0 380 316 1,317 $2,247 $18.43
Roofing 1,239 0 0 619 193 10 0 0 0 0 15 $836 $6.86
Site 3,747 0 0 0 0 0 45 0 0 0 0 $45 $0.37
Structural 0 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Interior 3,263 0 7 5 91 38 476 0 16 0 94 $728 $5.97
Exterior 969 0 0 2 1 19 208 0 309 5 21 $565 $4.63
Total 17,262 0 7 803 454 366 848 4 2,689 321 1,888 $7,380 $60.53
Life Cycle Capital Renewal Projections ($000s)
SystemCurrent
DeficienciesYear 1 2008
Year 2 2009
Year 3 2010
Year 4 2011
Year 5 2012
Year 6 2013
Year 7 2014
Year 8 2015
Year 9 2016
Year 10 2017 Total $/GSF
Capital Renewal Forecast
Facilities Condition AssessmentTransmountain Campus Condition Assessment
5Magellan Consulting, Inc.
Facility Condition Index (FCI)
The Facility Condition Index (FCI) is used throughout the facility condition assessment industry as a general indicator of a building’s health. The FCI is calculated by dividing the Facility Condition Cost plus five years of projected Life Cycle Capital Renewal Costs by the Replacement Value. Costs associated with new construction are not included in the FCI calculation. As a rule of thumb, an FCI below 10% is considered good. An FCI above 65% would suggest that the building is a candidate for replacement.
The Transmountain Campus facility has an overall FCI of 49.50%
Transmountain Campus Condition Assessment
Assessment Findings
The total current cost for all building deficiencies is $17,261,820. There are $4,168,650 in deficiencies at the site level that are included in the FCI calculation. The five year capital renewal cost was $1,629,696. The cost estimates were derived using a detailed listing of all noted deficiencies in the building. The cost to repair these deficiencies was then estimated using the cost data adjusted to El Paso, Texas (78% of national average).
The Replacement Value represents the estimated cost of replacing the current building with another building of like size, based on today’s estimated cost of construction in the El Paso, Texas area. The replacement cost for this facility is estimated to be $38,162,737.
The following pages provide a listing of all deficiencies and their associated cost for the site and building, followed by photos taken during the assessment.
Facilities Condition AssessmentTransmountain Campus Condition Assessment
6Magellan Consulting, Inc.
The Pole Lighting Is Damaged And Should Be Replaced 19307 7 Ea. 2 $62,952 Yes
The Pole Lighting Is Damaged And Should Be Replaced 19184 8 Ea. 2 $71,945 Yes
The Pole Lighting Is Damaged And Should Be Replaced 18679 1 Ea. 2 $8,993 Yes
The Pole Lighting Is Damaged And Should Be Replaced 18370 1 Ea. 2 $8,993 Yes
The Pole Lighting Is Damaged And Should Be Replaced 19043 16 Ea. 2 $143,891 Yes
The Pole Lighting Is Damaged And Should Be Replaced 18761 6 Ea. 2 $53,959 Yes
The Ground Mounted Lighting Is Damaged And Should Be Replaced 19185 4 Ea. 2 $6,092 Yes
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Small Benches Are Damaged And Require Replacement 19742 1 Ea. 5 $2,086 No
Small Benches Are Damaged And Require Replacement 19833 1 Ea. 5 $2,086 No
Small Benches Are Damaged And Require Replacement 19906 1 Ea. 5 $2,086 No
Small Benches Are Damaged And Require Replacement 19556 2 Ea. 5 $4,171 No
Small Benches Are Damaged And Require Replacement 19254 2 Ea. 5 $4,171 No
Small Benches Are Damaged And Require Replacement 19433 1 Ea. 5 $2,086 No
Small Benches Are Damaged And Require Replacement 19498 3 Ea. 5 $6,257 No
Trash Receptacles Are Damaged And Require Replacement 19557 1 Ea. 5 $1,028 No
Tree Replacement Required 19431 3 Ea. 5 $5,018 No
Tree Replacement Required 19496 1 Ea. 5 $1,673 No
Trash Receptacles Are Damaged And Require Replacement 19333 4 Ea. 5 $4,113 No
Small Benches Are Damaged And Require Replacement 19949 1 Ea. 5 $2,086 No
Trash Receptacle is missing and is needed 23810 10 Ea. 5 $9,861 No
Trash Receptacles Are Damaged And Require Replacement 19097 2 Ea. 5 $2,057 No
Site Drainage system requires replacement 19329 110 LF 3 $2,315 No
Asphalt Paving Is Damaged And Requires Replacement 18704 34 CAR 4 $86,590 No
Site Drainage system requires replacement 18355 150 LF 3 $3,156 No
Site Drainage system requires replacement 18925 400 LF 3 $8,416 No
Asphalt Paving Is Damaged And Requires Replacement 19252 51 CAR 4 $129,886 No
Asphalt Paving Is Damaged And Requires Replacement 19331 263 CAR 4 $669,804 No
Asphalt Paving Is Damaged And Requires Replacement 18927 299 CAR 4 $761,488 No
Asphalt Paving Is Damaged And Requires Replacement 19092 490 CAR 4 $1,247,923 No
Concrete Walks Are Damaged And Require Replacement 19095 625 SF 2 $8,589 Yes
Concrete Walks Are Damaged And Require Replacement 19255 125 SF 2 $1,718 Yes
Concrete Walks Are Damaged And Require Replacement 18598 150 SF 2 $2,060 Yes
Concrete Walks Are Damaged And Require Replacement 18706 200 SF 2 $2,748 Yes
Concrete Walks Are Damaged And Require Replacement 20111 30 SF 2 $411 Yes
Exit pads and ramps required for egress 23809 1 Job 2 $91,000 No
Concrete Walks Are Damaged And Require Replacement 19432 125 SF 2 $1,718 Yes
Concrete Walks Are Damaged And Require Replacement 19497 200 SF 2 $2,748 Yes
Paving Requires Restriping 19094 490 CAR 5 $88,467 No
Paving Requires Restriping 19253 13 CAR 5 $2,348 No
Paving Requires Restriping 18705 78 CAR 5 $14,083 No
Paving Requires Restriping 18928 299 CAR 5 $53,983 No
Site Signage Is Damaged And Requires Replacement 19555 10 Ea. 5 $4,550 No
Small Benches Are Damaged And Require Replacement 19096 2 Ea. 5 $4,171 No
Paving Requires Restriping 19332 263 CAR 5 $47,484 No
School has insufficient football/soccer fields. 20800 1 Ea. 5 $65,868 No
Site Drainage is Inadequate and Requires Regrading 18926 10,000 SF 4 $2,737 No
Site Drainage is Inadequate and Requires Regrading 18294 6,000 SF 4 $1,643 No
Fencing Is Damaged And Should Be Repaired (Retaining Wall) 18924 25 LF 4 $19,498 No
Site Drainage is Inadequate and Requires Regrading 19330 12,000 SF 4 $3,285 No
LC: The Site / Rec/PE/Ath Fields / ES Playgrounds system is beyond its useful life. 20799 1 Ea. 5 $108,387 No
Wood exercise equipment requires replacement 20890 10 Ea. 4 $36,400 No
Site Marquee Is Damaged And Requires Replacement 19554 4 Ea. 4 $41,713 No
Sub Total for System 45 $3,563,964
SiteDeficiency ID Qty UoM Priority Repair Cost WS&D
Site Level Deficiencies
Facilities Condition AssessmentTransmountain Campus Condition Assessment
7Magellan Consulting, Inc.
Duct Grill is Damaged And Should Be Replaced 19655 6 Ea. 5 $1,931 No
Duct Grill is Damaged And Should Be Replaced 19656 6 Ea. 5 $1,931 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 23686 50,000 SF 4 $112,045 No
The Air Handler HVAC Component Is Damaged And Requires Replacement 23722 25,000 CFM 2 $139,170 No
Ductwork Is Damaged And Should Be Replaced 23687 5,000 LF 3 $95,104 No
Duct Grill is Damaged And Should Be Replaced 19657 2 Ea. 5 $644 No
Duct Grill is Damaged And Should Be Replaced 19661 1 Ea. 5 $322 No
Duct Grill is Damaged And Should Be Replaced 19662 2 Ea. 5 $644 No
Duct Grill is Damaged And Should Be Replaced 19659 12 Ea. 5 $3,862 No
Duct Grill is Damaged And Should Be Replaced 19660 7 Ea. 5 $2,253 No
Sub Total for System 10 $357,907
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 19635 30,000 SF 3 $226,082 No
The Suspended Ceiling Grid is Damaged And Require Replacement 19632 6,800 SF 3 $54,826 No
The Carpet Flooring Is Damaged And Requires Replacement 19634 8,000 SF 3 $70,641 No
Interior Walls Require Repainting 19633 30,000 SF 5 $80,262 No
The Gypboard Ceilings Are Damaged And Requires Repair 23685 43,000 SF 4 $133,042 No
Sub Total for System 5 $564,853
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Metal Roof-To-Curb Flashings Are Damaged And Should Be Resealed 19646 60 LF 2 $262 Yes
Metal Edge Termination At Wall Is Damaged And Should Be Repaired 19638 10 Ea. 2 $688 Yes
Metal Coping Lap Joints Have Lost Their Seal And Should Be Resealed 19640 20 Ea. 2 $311 Yes
Re-Seal Metal Roof-To-Wall Flashing At Wall 19643 160 LF 2 $329 Yes
Tapered Insulation Is Required To Eliminate Ponding When Re-Roofing 19636 20 SF 3 $315 No
The Roof Requires Cleaning 19654 20 SF 2 $362 Yes
Skylight Is Damaged And Should Be Repaired 19648 16 Ea. 2 $8,670 Yes
The Multi-Ply Bitumen Roof System Is Damaged And Requires Replacement 19653 4,000 SF 1 $48,183 No
Counter Flashing Is Damaged Or Loose And Should Be Replaced 19641 20 LF 2 $490 Yes
Built Up Roofing (Bur) Membrane Has Holes That Should Be Repaired 19650 10 Ea. 2 $1,207 Yes
Built Up Roofing (Bur) Covering Has Blisters That Should Be Repaired 19649 30 Ea. 2 $3,842 Yes
Built Up Roofing (Bur) Lap Seams Are Open Or Deteriorated 19651 80 LF 2 $3,962 Yes
Exhaust Fan Curbs are too Low and Should be Raised and Reflashed (<8") 19645 2 Ea. 2 $2,788 No
Membrane Flashings At Metal Edge Are Damaged And Should Be Repaired 19637 50 LF 2 $650 Yes
Metal Coping Is Damaged Or Loose And Should Be Replaced 19642 20 LF 2 $992 Yes
Membrane Flashings At Equipment Curbs Are Damaged And Should Be Repaired 19644 10 LF 2 $157 Yes
Gas Line/Conduit On New Supports Is Unseated And Should Be Supported 19647 1 Ea. 2 $111 Yes
Membrane Flashing At Curb (<2') 19639 200 LF 2 $3,116 Yes
Sub Total for System 18 $76,435
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 3000 - Interior Circulation
The Fire Hydrant Is Damaged And Requires Replacement 19167 1 Ea. 1 $2,568 Yes
Sub Total for System 1 $2,568
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Pole Lighting Is Damaged And Should Be Replaced 19616 4 Ea. 2 $35,972 Yes
The Pole Lighting Is Damaged And Should Be Replaced 19706 1 Ea. 2 $8,993 Yes
The Pole Lighting Is Damaged And Should Be Replaced 19765 1 Ea. 2 $8,993 Yes
The Pole Lighting Is Damaged And Should Be Replaced 19375 6 Ea. 2 $53,959 Yes
The Pole Lighting Is Damaged And Should Be Replaced 19484 2 Ea. 2 $17,987 Yes
The Pole Lighting Is Damaged And Should Be Replaced 19544 9 Ea. 2 $80,939 Yes
The Pole Lighting Is Damaged And Should Be Replaced 20024 1 Ea. 2 $8,993 Yes
The Pole Lighting Is Missing And Needed 19829 1 Ea. 2 $11,473 Yes
The Pole Lighting Is Damaged And Should Be Replaced 19794 1 Ea. 2 $8,993 Yes
The Pole Lighting Is Damaged And Should Be Replaced 19981 1 Ea. 2 $8,993 Yes
Sub Total for System 17 $602,118
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for School and Site Level 63 $4,168,650
Facilities Condition AssessmentTransmountain Campus Condition Assessment
8Magellan Consulting, Inc.
Membrane Flashing At Parapet (>2') Is Damaged And Should Be Repaired 19579 150 LF 2 $446 Yes
Lead Flashing Is Missing And Is Needed 19592 1 Ea. 2 $129 Yes
Gas Line/Conduit On New Supports Is Unseated And Should Be Supported 19590 8 Ea. 2 $888 Yes
Membrane Flashings At Metal Edge Are Damaged And Should Be Repaired 19577 60 LF 2 $779 Yes
Membrane Flashings At Equipment Curbs Are Damaged And Should Be Repaired 19587 80 LF 2 $1,247 Yes
Membrane Flashings At Drain Is Damaged And Should Be Repaired 19574 4 Ea. 2 $588 Yes
Expansion Joint Termination At End Wall Is Damaged And Should Be Repaired 19586 1 Ea. 2 $448 Yes
Edge Metal Is Damaged And Should Be Replaced 19576 25 LF 2 $852 Yes
Counter Flashing Is Damaged Or Loose And Should Be Repaired 19581 200 LF 2 $2,712 Yes
Coping Termination At End Wall Is Damaged And Should Be Repaired 19583 6 Ea. 2 $612 Yes
Expansion Joint Laps Are Damaged And Should Be Repaired 19584 3 Ea. 2 $1,083 Yes
Expansion Joint Cover Is Missing Or Damaged And Should Be Replaced 19585 22 LF 2 $1,574 Yes
Exhaust Fan Curbs are too Low and Should be Raised and Reflashed (<8") 19588 2 Ea. 2 $2,788 No
The Roof Drains Are Clogged 19572 5 Ea. 2 $586 Yes
Strainers Are Missing And Needed 19573 1 Ea. 2 $804 Yes
Skylight Is Damaged And Should Be Repaired 19591 4 Ea. 2 $2,168 Yes
Roof Curb To Match HVAC Unit Is Missing And Is Needed 19589 2 Ea. 4 $1,827 No
Tapered Insulation Is Required To Eliminate Ponding When Re-Roofing 19575 250 SF 3 $1,179 No
The Roof Requires Cleaning 19608 100 SF 2 $379 Yes
Sealant At Pitch Pan Is Damaged And Should Be Repaired 19593 3 Ea. 2 $484 Yes
Metal Edge Termination At Wall Is Damaged And Should Be Repaired 19578 4 Ea. 2 $275 Yes
Metal Coping Lap Joints Have Lost Their Seal And Should Be Resealed 19580 25 Ea. 2 $317 Yes
Metal Coping Is Damaged Or Loose And Should Be Replaced 19582 40 LF 2 $1,986 Yes
Sealant At Penetration Boot Is Damaged And Should Be Repaired 19596 2 Ea. 2 $297 Yes
Penetration Boot Is Damaged And Should Be Replaced 19595 2 Ea. 2 $262 Yes
Metal Umbrella At Penetration Or Pitch Pan Is Missing And Is Needed 19594 3 Ea. 2 $710 Yes
Built Up Roofing (Bur) Covering Has Blisters That Should Be Repaired 19597 150 Ea. 2 $19,208 Yes
The Multi-Ply Bitumen Roof System Is Damaged And Requires Replacement 19606 6,000 SF 1 $72,274 No
Built Up Roofing (Bur) Membrane Has Holes That Should Be Repaired 19598 2 Ea. 2 $242 Yes
Built Up Roofing (Bur) Lap Seams Are Open Or Deteriorated 19599 10 LF 2 $495 Yes
Sub Total for System 30 $117,638
Deficiency ID Qty UoM Priority Repair Cost WS&D
Roofing
Building: 3010 - Administration
Public Address Is Inadequate And Should Be Replaced 19708 50,000 SF 1 $96,582 Yes
Sub Total for System 1 $96,582
TechnologyDeficiency ID Qty UoM Priority Repair Cost WS&D
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 19707 50,000 SF 2 $29,344 Yes
Fire Alarm is Missing or Inadequate 19711 50,000 SF 1 $87,225 Yes
Security Alarm is Missing or Inadequate 19709 50,000 SF 2 $90,239 No
Sub Total for System 3 $206,808
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Refrigerated Water Cooler is Damaged And Should Be Replaced 19658 3 Ea. 4 $13,097 No
Sub Total for System 1 $13,097
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The Incandescent Lighting Is Damaged And Should Be Replaced 19704 1 Ea. 4 $364 No
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19693 86 Ea. 4 $46,217 No
The Incandescent Lighting Is Damaged And Should Be Replaced 19702 4 Ea. 4 $1,454 No
The 2 X 2 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19692 68 Ea. 4 $24,868 No
The Pendant Lighting Is Damaged And Should Be Replaced 19699 16 Ea. 4 $14,931 No
The Incandescent Lighting Is Damaged And Should Be Replaced 19705 2 Ea. 4 $728 No
Sub Total for System 6 $88,563
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 3000 - Interior Circulation 44 $1,404,245
Facilities Condition AssessmentTransmountain Campus Condition Assessment
9Magellan Consulting, Inc.
The Fixed Shelving Storage Cabinets Require Replacement 19571 16 LF 4 $1,403 No
Sub Total for System 1 $1,403
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 19624 10,528 SF 2 $6,179 Yes
Emergency Exit Signage Is Missing And Needed 19625 3 Ea. 2 $2,348 Yes
Fire Alarm Panel Should Be Replaced 19628 1 Ea. 1 $9,677 Yes
Security Alarm Motion Detector Is Missing Or Damaged And Should Be Replaced 19627 6 Ea. 2 $4,947 No
Security Alarm Motion Detector Is Missing And Needed 19626 6 Ea. 2 $6,927 No
Sub Total for System 5 $30,077
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
LC: The Plumbing / Domestic Water Piping System system is beyond its useful life. 23725 2,000 SF 3 $7,280 No
The Restroom is Not ADA Compliant 23766 4 Ea. 3 $103,465 No
Sub Total for System 2 $110,745
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The Electrical Receptacles Are Inadequate And More Are Needed 19629 30 Ea. 3 $13,299 No
The Power Service Is Inadequate And Should Be Upgraded 19622 450 Amps 3 $23,862 No
The GFCI Electrical Receptacles Are Inadequate And More Are Needed 19630 2 Ea. 2 $979 Yes
The Mounted Building Lighting Is Damaged And Should Be Replaced 19618 1 Ea. 2 $976 Yes
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19620 217 Ea. 4 $116,618 No
The Electrical Circuit Capacity Is Inadequate 19623 84 EACH 4 $79,328 No
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19619 12 Ea. 4 $4,237 No
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19621 2 Ea. 4 $706 No
The Canopy Lighting Is Damaged And Should Be Replaced 19617 17 Ea. 2 $29,981 Yes
Sub Total for System 9 $269,986
Deficiency ID Qty UoM Priority Repair Cost WS&D
Electrical
The Package Unit HVAC Component Is Damaged And Requires Replacement 19614 6 TonAC 2 $16,001 No
Additional air handlers required 23825 1 Ea. 2 $64,308 No
The Air Handler HVAC Component Is Damaged And Requires Replacement 23723 30,000 CFM 2 $167,005 No
Duct Grill is Damaged And Should Be Replaced 19613 26 Ea. 5 $8,368 No
Duct Cleaning Required 19612 10,528 SF 5 $9,881 No
The Roof Air Handler/Exhaust is Damaged And Requires Replacement 19611 10 TonAC 2 $31,195 No
Sub Total for System 6 $296,758
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Carpet Flooring Is Damaged And Requires Replacement 19568 64 SF 3 $566 No
The Suspended Ceiling Grid is Damaged And Require Replacement 19563 9,475 SF 3 $76,393 No
The Interior Door Hardware is Damaged and Requires Replacement 19567 3 Ea. 2 $3,056 No
Interior Doors Require Replacement 19565 3 Door 3 $3,778 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 19569 500 SF 3 $3,767 No
Interior Walls Require Repainting 19564 6,000 SF 5 $16,052 No
Interior Doors Require Repainting 19566 30 Door 5 $1,596 No
The Concrete Flooring Is Damaged And Requires Replacement 19570 500 SF 4 $3,611 No
Sub Total for System 8 $108,820
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Aluminum Storefront Exterior Door Is Damaged And Requires Replacement 19560 5 Door 2 $21,778 Yes
The Exterior Requires Cleaning 19558 8,000 SF Wall 5 $16,598 No
Exterior door hardware is damaged and should be replaced 19561 5 Door 2 $3,018 Yes
The Exterior Requires Painting 19559 8,000 SF Wall 5 $23,902 No
Sub Total for System 4 $65,296
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 3010 - Administration 65 $1,000,723
Facilities Condition AssessmentTransmountain Campus Condition Assessment
10Magellan Consulting, Inc.
Emergency Battery Pack Lighting Is Damaged And Should Be Replaced 19550 27 Ea. 2 $14,092 Yes
Fire Alarm Panel Should Be Replaced 19552 1 Ea. 1 $9,677 Yes
Fire Alarm Horn/Strobe Is Damaged And Should Be Replaced 23807 10 Ea. 1 $4,870 Yes
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Custodial Mop Or Service Sink Is Damaged And Should Be Replaced 19537 1 Ea. 4 $3,948 No
The Urinal Plumbing Fixtures Are Damaged And Should Be Replaced 20796 3 Ea. 3 $4,586 No
The Toilets Plumbing Fixtures Are Damaged And Should Be Replaced 19539 3 Ea. 3 $3,971 No
Install Fire Sprinklers 19541 23,370 SF 3 $179,019 No
The Rest Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 19538 4 Ea. 4 $6,559 No
The Refrigerated Water Cooler is Damaged And Should Be Replaced 19540 2 Ea. 4 $8,731 No
Sub Total for System 6 $206,814
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The Mounted Building Lighting Is Damaged And Should Be Replaced 19543 4 Ea. 2 $3,900 Yes
The H.I.D. Lighting Is Damaged And Should Be Replaced 19549 6 Ea. 3 $3,516 No
The Canopy Lighting Is Damaged And Should Be Replaced 19542 5 Ea. 2 $8,818 Yes
The GFCI Electrical Receptacles Are Inadequate And More Are Needed 19553 2 Ea. 2 $979 Yes
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19545 6 Ea. 4 $2,118 No
The Incandescent Lighting Is Damaged And Should Be Replaced 19548 5 Ea. 4 $1,818 No
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19547 279 Ea. 4 $149,937 No
The 2 X 2 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19546 5 Ea. 4 $1,829 No
Sub Total for System 8 $172,916
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Test And Balancing Required 19533 23,370 SF 3 $40,832 No
Duct Cleaning Required 19534 23,370 SF 5 $21,931 No
Duct Grill is Damaged And Should Be Replaced 19535 83 Ea. 5 $26,716 No
VAV boxes require replacement 23705 50 Ea. 2 $103,312 No
Additional air handlers required 23824 1 Ea. 2 $64,308 No
The Air Handler HVAC Component Is Damaged And Requires Replacement 19536 20,000 CFM 2 $115,195 No
The Large Diameter Exhausts/Hoods Are Missing/Damaged And Require Replacement 19532 5 Ea. 2 $8,512 No
Sub Total for System 7 $380,806
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Suspended Ceiling Grid is Damaged And Require Replacement 19503 1,900 SF 3 $15,319 No
Interior Ceramic Walls Require Repair Or Replacement 19507 880 SF Wall 4 $13,028 No
Interior Toilet Partition Require Repair Or Replacement 19506 2 Ea. 4 $4,841 No
The Interior Door Hardware is Damaged and Requires Replacement 19509 22 Ea. 2 $22,408 No
The Carpet Flooring Is Damaged And Requires Replacement 19510 21,550 SF 3 $190,292 No
The Ceramic Tile Flooring Is Damaged And Requires Replacement 19511 880 SF 3 $14,038 No
Interior Walls Require Repainting 19505 22,000 SF 5 $58,859 No
The Plaster Ceilings Are Damaged And Requires Repainting 19504 1,000 SF 5 $1,747 No
Interior Doors Require Repainting 19508 22 Door 5 $1,170 No
The Concrete Flooring Is Damaged And Requires Replacement 19512 960 SF 4 $6,932 No
Concrete Flooring Epoxy Requires Replacement 20808 960 SF 5 $1,882 No
Sub Total for System 11 $330,516
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Metal Exterior Door Is Damaged And Requires Replacement 19500 2 Door 2 $4,714 Yes
Exterior door hardware is damaged and should be replaced 19501 2 Door 2 $1,207 Yes
The Exterior Requires Painting 19499 12,000 SF Wall 5 $35,854 No
Sub Total for System 3 $41,774
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Multi-Ply Bitumen Roof System Is Damaged And Requires Replacement 19530 11,685 SF 1 $140,753 No
Sub Total for System 1 $140,753
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 3020 - Learning Resources Center
Facilities Condition AssessmentTransmountain Campus Condition Assessment
11Magellan Consulting, Inc.
Built Up Roofing (Bur) Covering Has Blisters That Should Be Repaired 19282 7 Ea. 2 $897 Yes
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 3030 - Lecture Forum
Security Alarm Panel Should be Replaced 19429 1 Ea. 1 $4,295 No
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 19428 14,366 SF 2 $8,432 Yes
Sub Total for System 2 $12,727
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
LC: The Plumbing / Domestic Water Piping System system is beyond its useful life. 23768 14,336 SF 3 $52,183 No
Sub Total for System 1 $52,183
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19376 189 Ea. 4 $101,571 No
Panelboard is not Labeled for Safety 19430 1,000 Amps 1 $2,619 Yes
The Incandescent Lighting Is Damaged And Should Be Replaced 19426 3 Ea. 4 $1,090 No
The Incandescent Lighting Is Damaged And Should Be Replaced 19427 6 Ea. 4 $2,182 No
Sub Total for System 4 $107,462
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Roof Air Handler/Exhaust is Damaged And Requires Replacement 19374 90 TonAC 2 $49,546 No
Sub Total for System 1 $49,546
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Gypboard Ceilings Are Damaged And Requires Repainting 19338 1,436 SF 5 $3,817 No
Interior Walls Require Repainting 19339 14,366 SF 5 $38,435 No
The Suspended Ceiling Grid is Damaged And Require Replacement 19337 10,000 SF 3 $80,626 No
The Ceramic Tile Flooring Is Damaged And Requires Replacement 19343 718 SF 3 $11,453 No
The Carpet Flooring Is Damaged And Requires Replacement 19341 5,746 SF 3 $50,738 No
Interior Doors Require Repainting 19340 52 Door 5 $2,766 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 19342 7,901 SF 3 $59,543 No
Sub Total for System 7 $247,378
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Exterior door hardware is damaged and should be replaced 19335 7 Door 2 $4,224 Yes
The Aluminum Storefront Exterior Door Is Damaged And Requires Repair 19334 7 Door 2 $7,588 Yes
Sub Total for System 2 $11,812
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Multi-Ply Bitumen Roof System Is Damaged And Requires Replacement 19371 17,469 SF 1 $210,427 No
Sub Total for System 1 $210,427
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 3025 - Liberal Arts Building 18 $691,534
Building: 3025 - Liberal Arts Building
Charging Desk requires replacement 23806 1 Ea. 3 $4,486 No
Sub Total for System 1 $4,486
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Elevator Cab Is Damaged And Requires Replacement 19513 1 Ea. 3 $59,095 No
Sub Total for System 1 $59,095
ConveyancesDeficiency ID Qty UoM Priority Repair Cost WS&D
Security Alarm Motion Detector Is Missing And Needed 19551 2 Ea. 2 $2,310 No
Sub Total for System 4 $30,949
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 3020 - Learning Resources Center 42 $1,368,110
Facilities Condition AssessmentTransmountain Campus Condition Assessment
12Magellan Consulting, Inc.
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19308 77 Ea. 4 $27,187 No
The GFCI Electrical Receptacles Are Inadequate And More Are Needed 19328 3 Ea. 2 $1,471 Yes
The Mounted Building Lighting Is Damaged And Should Be Replaced 19304 6 Ea. 2 $5,849 Yes
The Canopy Lighting Is Damaged And Should Be Replaced 19300 1 Ea. 2 $1,764 Yes
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Chiller HVAC Component Is Damaged And Requires Replacement 23689 300 TonAC 2 $390,203 No
HVAC ice storage tanks required 23739 9 Ea. 2 $109,746 No
The Radiant Heat HVAC Component Is Damaged And Requires Replacement 23690 2 Ea. 2 $4,636 No
The Large Diameter Exhausts/Hoods Are Missing/Damaged And Require Replacement 19284 2 Ea. 2 $3,405 No
HVAC ice machine required 23738 1 Ea. 2 $60,060 No
Additional pumping capacity required 23741 1 LS 2 $45,500 No
Additional air handlers required 23734 2 Ea. 2 $77,510 No
Heat exchanger, additional capacity required 23740 1 LS 2 $140,140 No
Air cooled chiller required for redundancy 23735 1 Ea. 2 $136,500 No
Duct Grill is Damaged And Should Be Replaced 19287 15 Ea. 5 $4,828 No
Exhaust Fan Ventilation Is Damaged And Should Be Replaced 19289 4 Ea. 4 $7,740 No
Duct Register is Damaged And Should Be Replaced 19286 1 Ea. 5 $824 No
Duct Grill is Damaged And Should Be Replaced 19288 15 Ea. 5 $4,828 No
Ductwork Is Damaged And Should Be Replaced 23688 1,000 LF 3 $19,021 No
VAV boxes require replacement 23706 40 Ea. 2 $82,650 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 19285 11,517 SF 4 $25,808 No
The Evaporative Cooling Unit Is Damaged And Requires Replacement 23691 2 Ea. 3 $18,140 No
Sub Total for System 17 $1,131,539
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Gypboard Ceilings Are Damaged And Requires Repainting 19265 10,100 SF 5 $26,838 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 19271 1,200 SF 3 $9,044 No
The Carpet Flooring Is Damaged And Requires Replacement 19270 6,500 SF 3 $57,397 No
The Interior Door Hardware is Damaged and Requires Replacement 19269 27 Ea. 2 $27,502 No
Interior Toilet Partition Require Repair Or Replacement 19267 4 Ea. 4 $9,681 No
Interior Walls Require Repainting 19266 11,517 SF 5 $30,813 No
Interior Doors Require Repainting 19268 27 Door 5 $1,436 No
Sub Total for System 7 $162,710
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Metal Exterior Door Is Damaged And Requires Replacement 19261 9 Door 2 $21,216 Yes
The Overhead Door Is Damaged And Requires Repair 19263 1 Door 2 $1,085 Yes
Exterior door hardware is damaged and should be replaced 19264 12 Door 2 $7,240 Yes
The Aluminum Storefront Exterior Door Is Damaged And Requires Replacement 19262 3 Door 2 $13,068 Yes
The Exterior Soffit Is Damaged And Requires Repainting 19259 200 SF 5 $861 No
The Exterior Requires Painting 19258 12,200 SF Wall 5 $36,451 No
The Stucco Exterior Is Damaged And Requires Repair 19260 40 SF Wall 2 $1,032 Yes
Sub Total for System 7 $80,952
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Expansion Joint Laps Are Damaged And Should Be Repaired 19277 20 Ea. 2 $7,218 Yes
Expansion Joint Termination At End Wall Is Damaged And Should Be Repaired 19279 5 Ea. 2 $2,240 Yes
Metal Coping Is Damaged Or Loose And Should Be Repaired 19276 300 LF 2 $18,384 Yes
Counter Flashing Is Damaged Or Loose And Should Be Replaced 19275 300 LF 2 $3,549 Yes
Exhaust Fan Curbs are too Low and Should be Raised and Reflashed (<8") 19280 5 Ea. 2 $6,972 No
Expansion Joint Cover Is Missing Or Damaged And Should Be Replaced 19278 160 LF 2 $11,453 Yes
Metal Coping Lap Joints Have Lost Their Seal And Should Be Resealed 19274 80 Ea. 2 $952 Yes
Tapered Insulation Is Required To Eliminate Ponding When Re-Roofing 19272 180 SF 3 $733 No
Splashblocks Are Missing Or Damaged And Are Needed 20891 3 Ea. 5 $309 No
Thru-Wall Flashing At Rise-Wall Should Be Raised And Reflashed 19273 1 LF 2 $300 No
Metal Umbrella At Penetration Or Pitch Pan Is Missing And Is Needed 19281 1 Ea. 2 $237 Yes
The Roof Requires Cleaning 19283 15 SF 2 $362 Yes
Sub Total for System 13 $53,608
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Facilities Condition AssessmentTransmountain Campus Condition Assessment
13Magellan Consulting, Inc.
The Aluminum Window Is Damaged And Requires Replacement 20120 5 Ea. 2 $8,643 Yes
The Aluminum Storefront Exterior Door Is Damaged And Requires Repair 20118 2 Door 2 $2,168 Yes
Exterior door hardware is damaged and should be replaced 20119 3 Door 2 $1,811 Yes
The Metal Exterior Door Is Damaged And Requires Replacement 20117 1 Door 2 $2,357 Yes
Sub Total for System 4 $14,979
Deficiency ID Qty UoM Priority Repair Cost WS&D
Exterior
Coping Termination At End Wall Is Damaged And Should Be Repaired 20143 2 Ea. 2 $204 Yes
Counter Flashing Is Damaged Or Loose And Should Be Repaired 20142 25 LF 2 $557 Yes
Exhaust Fan Curbs are too Low and Should be Raised and Reflashed (<8") 20145 1 Ea. 2 $1,394 No
The Roof Drains Are Clogged 20136 2 Ea. 2 $235 Yes
Built Up Roofing (Bur) Covering Has Blisters That Should Be Repaired 20149 10 Ea. 2 $1,281 Yes
Built Up Roofing (Bur) Membrane Has Holes That Should Be Repaired 20150 2 Ea. 2 $242 Yes
Expansion Joint Laps Are Damaged And Should Be Repaired 20144 5 Ea. 2 $1,804 Yes
Metal Umbrella At Penetration Or Pitch Pan Is Missing And Is Needed 20148 2 Ea. 2 $473 Yes
Sealant At Pitch Pan Is Damaged And Should Be Repaired 20147 2 Ea. 2 $442 Yes
Strainers Are Missing And Needed 20137 1 Ea. 2 $804 Yes
Gas Line/Conduit On New Supports Is Unseated And Should Be Supported 20146 4 Ea. 2 $444 Yes
Membrane Flashing At Curb (<2') 20140 20 LF 2 $311 Yes
Metal Coping Lap Joints Have Lost Their Seal And Should Be Resealed 20141 10 Ea. 2 $300 Yes
Overflow Drain And Piping Is Missing And Is Needed 20139 3 Ea. 3 $3,755 No
The Roof Requires Cleaning 20151 50 SF 2 $369 Yes
Tapered Insulation Is Required To Eliminate Ponding When Re-Roofing 20138 30 SF 3 $340 No
The Roof Operable Hatch Is Damaged And Requires Replacement 20135 1 Ea. 3 $6,725 No
Sub Total for System 17 $19,681
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 3040-01 - Humanities Area
Auditorium Seating is damaged or is missing 20797 490 Seat 4 $246,217 No
Sub Total for System 1 $246,217
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Public Address Is Inadequate And Should Be Replaced 19324 11,517 SF 1 $22,246 Yes
Sub Total for System 1 $22,246
Deficiency ID Qty UoM Priority Repair Cost WS&D
Technology
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 19322 11,517 SF 2 $6,759 Yes
Security Alarm is Missing or Inadequate 19326 11,517 SF 2 $20,786 No
Fire Alarm is Missing or Inadequate 19327 11,517 SF 1 $25,691 Yes
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 19323 11 Ea. 2 $5,870 Yes
Sub Total for System 4 $59,106
Deficiency ID Qty UoM Priority Repair Cost WS&D
Fire and Life Safety
The Refrigerated Water Cooler is Damaged And Should Be Replaced 19293 1 Ea. 4 $4,366 No
The Toilets Plumbing Fixtures Are Damaged And Should Be Replaced 19291 4 Ea. 3 $5,296 No
The Showers Plumbing Fixtures Are Damaged And Should Be Replaced 19292 2 Ea. 3 $1,729 No
Install Fire Sprinklers 19296 600 SF 3 $4,596 No
The Rest Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 19290 4 Ea. 4 $6,559 No
Sub Total for System 5 $22,546
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The Incandescent Lighting Is Damaged And Should Be Replaced 19315 97 Ea. 4 $35,277 No
The Incandescent Lighting Is Damaged And Should Be Replaced 19313 8 Ea. 4 $2,910 No
The Incandescent Lighting Is Damaged And Should Be Replaced 19310 20 Ea. 4 $7,273 No
The Incandescent Lighting Is Damaged And Should Be Replaced 19318 2 Ea. 4 $728 No
The Incandescent Lighting Is Damaged And Should Be Replaced 19321 2 Ea. 4 $728 No
Sub Total for System 9 $83,187
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 3030 - Lecture Forum 64 $1,862,111
Facilities Condition AssessmentTransmountain Campus Condition Assessment
14Magellan Consulting, Inc.
Public Address Is Inadequate And Should Be Replaced 20172 2,238 SF 1 $4,323 Yes
Sub Total for System 1 $4,323
TechnologyDeficiency ID Qty UoM Priority Repair Cost WS&D
Emergency Exit Signage Is Missing And Needed 20171 2 Ea. 2 $1,565 Yes
Fire Alarm is Missing or Inadequate 20174 2,238 SF 1 $3,904 Yes
Emergency Lighting Is Inadequate Or Not Present And Should Be Installed 20170 2,238 SF 2 $3,342 Yes
Security Alarm is Missing or Inadequate 20173 2,238 SF 2 $4,039 No
Sub Total for System 4 $12,849
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Class Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 20162 2 Ea. 4 $4,104 No
The Urinal Plumbing Fixtures Are Damaged And Should Be Replaced 20803 6 Ea. 3 $9,173 No
The Toilets Plumbing Fixtures Are Damaged And Should Be Replaced 20164 7 Ea. 3 $9,267 No
The Custodial Mop Or Service Sink Is Damaged And Should Be Replaced 20161 1 Ea. 4 $3,948 No
The Rest Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 20163 6 Ea. 4 $9,839 No
The Refrigerated Water Cooler is Damaged And Should Be Replaced 20165 1 Ea. 4 $4,366 No
Sub Total for System 6 $40,697
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The Mounted Building Lighting Is Damaged And Should Be Replaced 20167 3 Ea. 2 $2,925 Yes
The GFCI Electrical Receptacles Are Inadequate And More Are Needed 20175 2 Ea. 2 $979 Yes
The Canopy Lighting Is Damaged And Should Be Replaced 20166 2 Ea. 2 $3,527 Yes
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20169 16 Ea. 4 $8,598 No
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20168 12 Ea. 4 $4,237 No
Sub Total for System 5 $20,266
Deficiency ID Qty UoM Priority Repair Cost WS&D
Electrical
Ductwork Is Damaged And Should Be Replaced 20156 200 LF 3 $3,804 No
Test And Balancing Required 20153 2,238 SF 3 $3,909 No
Duct Damper is Damaged And Should Be Replaced 20159 3 Ea. 3 $497 No
Package HVAC unit required 23826 4 Ea. 2 $90,003 No
The Large Diameter Exhausts/Hoods Are Missing/Damaged And Require Replacement 20152 1 Ea. 2 $1,702 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 20154 2,238 SF 4 $5,016 No
Duct Grill is Damaged And Should Be Replaced 20158 3 Ea. 5 $966 No
Duct Register is Damaged And Should Be Replaced 20157 8 Ea. 5 $6,603 No
Exhaust Fan Ventilation Is Damaged And Should Be Replaced 20160 4 Ea. 4 $7,740 No
Duct Cleaning Required 20155 2,238 SF 5 $2,100 No
Sub Total for System 10 $122,340
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Suspended Ceiling Grid is Damaged And Require Replacement 20122 1,119 SF 3 $9,022 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 20133 900 SF 3 $6,783 No
Interior Ceramic Walls Require Repair Or Replacement 20128 1,280 SF Wall 4 $18,950 No
The Ceramic Tile Flooring Is Damaged And Requires Replacement 20134 900 SF 3 $14,358 No
The Interior Door Hardware is Damaged and Requires Replacement 20131 8 Ea. 2 $8,148 No
Interior Doors Require Replacement 20129 2 Door 3 $2,519 No
The Carpet Flooring Is Damaged And Requires Replacement 20132 350 SF 3 $3,090 No
Interior Doors Require Repainting 20130 6 Door 5 $319 No
Interior Walls Require Repainting 20124 2,238 SF 5 $5,988 No
The Gypboard Ceilings Are Damaged And Requires Repainting 20123 1,119 SF 5 $2,974 No
Interior Gypboard Walls Require Repair 20126 150 SF Wall 4 $1,325 No
Interior Toilet Partition Require Repair Or Replacement 20127 13 Ea. 4 $31,464 No
Interior Ceilings Requires Repainting 20125 1,200 SF 5 $3,036 No
Sub Total for System 13 $107,975
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 3040-01 - Humanities Area 60 $343,110
Facilities Condition AssessmentTransmountain Campus Condition Assessment
15Magellan Consulting, Inc.
Emergency Exit Signage Is Missing And Needed 20073 2 Ea. 2 $1,565 Yes
Fire Alarm Panel Should Be Replaced 20075 1 Ea. 1 $9,677 Yes
Emergency Lighting Is Inadequate Or Not Present And Should Be Installed 20072 2,637 SF 2 $3,937 Yes
Security Alarm Motion Detector Is Missing And Needed 20074 2 Ea. 2 $2,310 No
Sub Total for System 4 $17,488
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The GFCI Electrical Receptacles Are Inadequate And More Are Needed 20076 1 Ea. 2 $490 Yes
The Canopy Lighting Is Damaged And Should Be Replaced 20069 5 Ea. 2 $8,818 Yes
The Mounted Building Lighting Is Damaged And Should Be Replaced 20070 2 Ea. 2 $1,949 Yes
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20071 32 Ea. 4 $17,197 No
Sub Total for System 4 $28,454
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Cleaning Required 20067 2,637 SF 5 $2,475 No
Duct Grill is Damaged And Should Be Replaced 20068 16 Ea. 5 $5,151 No
The Large Diameter Exhausts/Hoods Are Missing/Damaged And Require Replacement 20066 2 Ea. 2 $3,405 No
Sub Total for System 3 $11,031
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Suspended Ceiling Grid is Damaged And Require Replacement 20042 2,360 SF 3 $19,028 No
The Carpet Flooring Is Damaged And Requires Replacement 20046 2,637 SF 3 $23,285 No
The Interior Door Hardware is Damaged and Requires Replacement 20045 4 Ea. 2 $4,075 No
Interior Walls Require Repainting 20043 2,637 SF 5 $7,054 No
Interior Doors Require Repainting 20044 2 Door 5 $106 No
Sub Total for System 5 $53,548
Deficiency ID Qty UoM Priority Repair Cost WS&D
Interior
The Aluminum Storefront Exterior Door Is Damaged And Requires Replacement 20039 2 Door 2 $8,711 Yes
Exterior door hardware is damaged and should be replaced 20040 3 Door 2 $1,811 Yes
The Metal Exterior Door Is Damaged And Requires Replacement 20038 3 Door 2 $7,073 Yes
The Exterior Requires Painting 20037 2,637 SF Wall 5 $7,879 No
Sub Total for System 4 $25,473
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Gas Line/Conduit On New Supports Is Unseated And Should Be Supported 20062 3 Ea. 2 $333 Yes
Expansion Joint Termination At End Wall Is Damaged And Should Be Repaired 20057 6 Ea. 2 $2,690 Yes
Membrane Flashing At Parapet (>2') Is Damaged And Should Be Repaired 20051 45 LF 2 $373 Yes
Membrane Flashings At Equipment Curbs Are Damaged And Should Be Repaired 20058 44 LF 2 $686 Yes
Membrane Flashings At Drain Is Damaged And Should Be Repaired 20048 2 Ea. 2 $293 Yes
Coping Termination At End Wall Is Damaged And Should Be Repaired 20055 2 Ea. 2 $204 Yes
Built Up Roofing (Bur) Covering Has Blisters That Should Be Repaired 20064 3 Ea. 2 $384 Yes
Counter Flashing Is Damaged Or Loose And Should Be Replaced 20053 165 LF 2 $2,215 Yes
Expansion Joint Laps Are Damaged And Should Be Repaired 20056 13 Ea. 2 $4,692 Yes
Exhaust Fan Curbs are too Low and Should be Raised and Reflashed (<8") 20059 2 Ea. 2 $2,788 No
Tapered Insulation Is Required To Eliminate Ponding When Re-Roofing 20049 18 SF 3 $309 No
Overflow Scuppers Are Missing And Are Needed 20050 2 Ea. 3 $935 No
Roof Curb To Match HVAC Unit Is Missing And Is Needed 20061 2 Ea. 4 $1,827 No
HVAC Curbs are too Low and Should be Raised and Reflashed (<8") 20060 2 Ea. 4 $2,768 No
The Roof Requires Cleaning 20065 50 SF 2 $369 Yes
Metal Coping Lap Joints Have Lost Their Seal And Should Be Resealed 20052 13 Ea. 2 $304 Yes
Metal Coping Is Damaged Or Loose And Should Be Replaced 20054 165 LF 2 $8,190 Yes
The Roof Drains Are Clogged 20047 2 Ea. 2 $235 Yes
Metal Umbrella At Penetration Or Pitch Pan Is Missing And Is Needed 20063 11 Ea. 2 $2,603 Yes
Sub Total for System 19 $32,199
Deficiency ID Qty UoM Priority Repair Cost WS&D
Roofing
Sub Total for Building 3040-02 - Humanities Bldg. 2 (1702) 39 $168,193
Building: 3040-02 - Humanities Bldg. 2 (1702)
Facilities Condition AssessmentTransmountain Campus Condition Assessment
16Magellan Consulting, Inc.
Emergency Lighting Is Inadequate Or Not Present And Should Be Installed 20026 800 SF 2 $1,194 Yes
Emergency Exit Signage Is Missing And Needed 20028 2 Ea. 2 $1,565 Yes
Fire Alarm is Missing or Inadequate 20032 800 SF 1 $1,396 Yes
Security Alarm is Missing or Inadequate 20030 800 SF 2 $1,443 No
Sub Total for System 4 $5,598
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20025 12 Ea. 4 $6,448 No
Sub Total for System 1 $6,448
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Register is Damaged And Should Be Replaced 20021 4 Ea. 5 $3,301 No
Duct Grill is Damaged And Should Be Replaced 20023 1 Ea. 5 $322 No
Ductwork Is Damaged And Should Be Replaced 20020 70 LF 3 $1,332 No
Duct Register is Damaged And Should Be Replaced 20022 2 Ea. 5 $1,651 No
Sub Total for System 4 $6,607
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Carpet Flooring Is Damaged And Requires Replacement 19997 800 SF 3 $7,063 No
Interior Doors Require Replacement 19996 1 Door 3 $1,259 No
The Interior Door Hardware is Damaged and Requires Replacement 19998 1 Ea. 2 $1,019 No
The Suspended Ceiling Grid is Damaged And Require Replacement 19993 800 SF 3 $6,450 No
Interior Walls Require Repainting 19994 800 SF 5 $2,140 No
Interior Wood Walls Require Repair 19995 800 SF Wall 4 $14,167 No
Sub Total for System 6 $32,099
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Metal Exterior Door Is Damaged And Requires Replacement 19988 2 Door 2 $4,714 Yes
The Aluminum Window Is Damaged And Requires Replacement 19990 8 Ea. 2 $13,830 Yes
Exterior door hardware is damaged and should be replaced 19989 2 Door 2 $1,207 Yes
The Exterior Soffit Is Damaged And Requires Replacement 19987 800 SF 4 $8,414 No
Sub Total for System 4 $28,164
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Gasketed Closure At Metal Edge Is Damaged And Should Be Replaced 20007 30 LF 2 $2,117 Yes
Edge Metal Is Missing 20013 15 LF 2 $289 Yes
Gutter Joints Require Repair 20003 8 Ea. 2 $258 No
Gutters Are Damaged 20002 60 LF 2 $915 No
Gutter Screens Are Missing And Needed 20000 60 LF 2 $395 No
Damaged Hip/Ridge 20017 30 LF 2 $349 Yes
Damaged Gasketed Closure 20018 20 LF 2 $220 Yes
Debris In Gutters Should Be Removed 19999 60 LF 2 $359 Yes
Edge Metal Is Loose And Should Be Resecured 20014 30 LF 2 $874 Yes
Edge Metal Is Damaged And Should Be Replaced 20006 15 LF 2 $511 Yes
Joint Between Rake Cover And Roof Panel Requires Re-Sealing 20016 10 LF 2 $753 Yes
The Roof Requires Cleaning 20010 75 SF 2 $373 Yes
Sealant At Penetration Boot Is Damaged And Should Be Repaired 20009 1 Ea. 2 $293 Yes
Splashblocks Are Missing Or Damaged And Are Needed 20005 4 Ea. 5 $413 No
The Metal Downspouts Are Damaged Or Missing And Requires Replacement 20004 60 LF 3 $2,852 No
Re-Seal Metal Roof-To-Wall Flashing At Wall 20008 8 LF 2 $293 Yes
Metal Rake Cover Is Missing And Should Be Installed 20015 5 LF 2 $380 Yes
Loose/Missing Exposed Panel Fasteners 20012 20 Ea. 2 $752 Yes
Re-Seal Metal Roof Panel Laps (Seams) Require Repair And Re-Seal 20011 15 LF 2 $224 Yes
Re-Seal Joint Between Metal Z Closure & Roof Panel Is Damaged And Requires Repair 20019 5 LF 2 $171 Yes
Sub Total for System 20 $12,793
Deficiency ID Qty UoM Priority Repair Cost WS&D
Roofing
Sub Total for Building 3040-03 - Humanities Bldg. 03 (1800) 39 $91,710
Building: 3040-03 - Humanities Bldg. 03 (1800)
Facilities Condition AssessmentTransmountain Campus Condition Assessment
17Magellan Consulting, Inc.
Debris In Gutters Should Be Removed 19883 15 LF 2 $359 Yes
Damaged Gasketed Closure 19896 30 LF 2 $329 Yes
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 3040-05 - Humanities Bldg. 05 (1802)
Emergency Exit Signage Is Missing And Needed 19984 1 Ea. 2 $783 Yes
Fire Alarm is Missing or Inadequate 19986 800 SF 1 $1,396 Yes
Emergency Lighting Is Inadequate Or Not Present And Should Be Installed 19983 800 SF 2 $1,194 Yes
Security Alarm is Missing or Inadequate 19985 800 SF 2 $1,443 No
Sub Total for System 4 $4,816
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19982 12 Ea. 4 $6,448 No
Sub Total for System 1 $6,448
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Grill is Damaged And Should Be Replaced 19980 1 Ea. 5 $322 No
Ductwork Is Damaged And Should Be Replaced 19977 70 LF 3 $1,332 No
Duct Register is Damaged And Should Be Replaced 19978 4 Ea. 5 $3,301 No
Duct Register is Damaged And Should Be Replaced 19979 2 Ea. 5 $1,651 No
Sub Total for System 4 $6,607
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 19959 800 SF 3 $6,030 No
The Suspended Ceiling Grid is Damaged And Require Replacement 19956 800 SF 3 $6,450 No
Interior Walls Require Repainting 19957 800 SF 5 $2,140 No
Interior Doors Require Repainting 19958 1 Door 5 $53 No
Sub Total for System 4 $14,673
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Aluminum Window Is Damaged And Requires Replacement 19953 8 Ea. 2 $13,830 Yes
The Metal Exterior Door Is Damaged And Requires Replacement 19951 2 Door 2 $4,714 Yes
Exterior door hardware is damaged and should be replaced 19952 2 Door 2 $1,207 Yes
The Exterior Soffit Is Damaged And Requires Replacement 19950 800 SF 4 $19,407 No
Sub Total for System 4 $39,157
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Joint Between Rake Cover And Roof Panel Requires Re-Sealing 19974 20 LF 2 $1,507 Yes
Gutter Screens Are Missing And Needed 19961 60 LF 2 $395 No
Loose/Missing Exposed Panel Fasteners 19972 20 Ea. 2 $752 Yes
Laps In Metal Cover At Hip/Ridge Require Resealing 19976 12 Ea. 2 $304 Yes
Gutter Joints Require Repair 19962 6 Ea. 2 $193 No
Debris In Gutters Should Be Removed 19960 15 LF 2 $359 Yes
Damaged Gasketed Closure 19975 25 LF 2 $275 Yes
Gasketed Closure At Metal Edge Is Missing And Is Needed 19965 20 LF 2 $189 Yes
Edge Metal Is Missing And Is Needed 19964 15 LF 2 $490 Yes
Sealant At Penetration Boot Is Damaged And Should Be Repaired 19969 1 Ea. 2 $293 Yes
Re-Seal Metal Roof-To-Wall Flashing At Wall 19967 10 LF 2 $293 Yes
The Metal Downspouts Are Damaged Or Missing And Requires Replacement 19963 45 LF 3 $2,139 No
The Roof Requires Cleaning 19970 50 SF 2 $369 Yes
Metal Rake Cover Is Missing And Should Be Installed 19973 15 LF 2 $1,141 Yes
Membrane Flashings At Metal Edge Are Damaged And Should Be Repaired 19966 15 LF 2 $195 Yes
Penetration Boot Is Missing Or Damaged And Should Be Installed 19968 1 Ea. 2 $167 Yes
Re-Seal Metal Roof Panel Laps (Seams) Require Repair And Re-Seal 19971 20 LF 2 $298 Yes
Sub Total for System 17 $9,358
Deficiency ID Qty UoM Priority Repair Cost WS&D
Roofing
Sub Total for Building 3040-04 - Humanities Bldg. 04 (1801) 34 $81,059
Building: 3040-04 - Humanities Bldg. 04 (1801)
Facilities Condition AssessmentTransmountain Campus Condition Assessment
18Magellan Consulting, Inc.
The Base Storage Cabinets Require Replacement 19882 5 LF 4 $1,421 No
Sub Total for System 1 $1,421
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Fire Alarm Panel Should Be Replaced 19905 1 Ea. 1 $9,677 Yes
Sub Total for System 1 $9,677
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Class Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 19901 1 Ea. 4 $2,051 No
The Refrigerated Water Cooler is Damaged And Should Be Replaced 19902 1 Ea. 4 $4,366 No
Sub Total for System 2 $6,417
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19904 12 Ea. 4 $6,448 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 19903 1 Ea. 2 $976 Yes
Sub Total for System 2 $7,424
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Cleaning Required 19899 824 SF 5 $774 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 19898 824 SF 4 $1,847 No
Duct Grill is Damaged And Should Be Replaced 19900 4 Ea. 5 $1,287 No
Sub Total for System 3 $3,908
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Walls Require Repainting 19876 824 SF 5 $2,204 No
Interior Doors Require Replacement 19879 3 Door 3 $3,778 No
Interior Doors Require Replacement 19878 4 Door 3 $5,038 No
The Interior Door Hardware is Damaged and Requires Replacement 19880 4 Ea. 2 $4,075 No
The Suspended Ceiling Grid is Damaged And Require Replacement 19875 824 SF 3 $6,643 No
Interior Toilet Partition Require Repair Or Replacement 19877 1 Ea. 4 $2,421 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 19881 824 SF 3 $6,210 No
Sub Total for System 7 $30,369
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Aluminum Window Is Damaged And Requires Replacement 19872 8 Ea. 2 $13,830 Yes
Exterior door hardware is damaged and should be replaced 19871 2 Door 2 $1,207 Yes
The Metal Exterior Door Is Damaged And Requires Replacement 19870 2 Door 2 $4,714 Yes
The Exterior Soffit Is Damaged And Requires Replacement 19869 824 SF 4 $19,989 No
Sub Total for System 4 $39,740
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Laps In Metal Cover At Hip/Ridge Require Resealing 19897 5 Ea. 2 $297 Yes
Loose/Missing Exposed Panel Fasteners 19893 20 Ea. 2 $752 Yes
Metal Rake Cover Is Damaged Or Loose 19894 20 LF 2 $344 Yes
Gutters Are Damaged 19885 30 LF 2 $457 No
Joint Between Rake Cover And Roof Panel Requires Re-Sealing 19895 20 LF 2 $1,507 Yes
Gutter Screens Are Missing And Needed 19884 60 LF 2 $395 No
Re-Seal Metal Roof Panel Laps (Seams) Require Repair And Re-Seal 19892 20 LF 2 $298 Yes
The Metal Downspouts Are Damaged Or Missing And Requires Replacement 19887 60 LF 3 $2,852 No
Splashblocks Are Missing Or Damaged And Are Needed 19888 2 Ea. 5 $206 No
Gutter Joints Require Repair 19886 3 Ea. 2 $96 No
Re-Seal Metal Roof-To-Wall Flashing At Wall 19889 20 LF 2 $297 Yes
Sealant At Penetration Boot Is Damaged And Should Be Repaired 19890 1 Ea. 2 $293 Yes
The Roof Requires Cleaning 19891 30 SF 2 $366 Yes
Sub Total for System 15 $8,847
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 3040-05 - Humanities Bldg. 05 (1802) 35 $107,802
Facilities Condition AssessmentTransmountain Campus Condition Assessment
19Magellan Consulting, Inc.
The Upper Storage Cabinets Require Replacement 19845 10 LF 4 $1,818 No
The Base Storage Cabinets Require Replacement 19844 10 LF 4 $2,843 No
Sub Total for System 2 $4,661
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Fire Alarm Panel Should Be Replaced 19868 1 Ea. 1 $9,677 Yes
Sub Total for System 1 $9,677
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Refrigerated Water Cooler is Damaged And Should Be Replaced 19865 1 Ea. 4 $4,366 No
The Class Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 19863 1 Ea. 4 $2,051 No
The Rest Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 19864 1 Ea. 4 $1,640 No
Sub Total for System 3 $8,057
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The Mounted Building Lighting Is Damaged And Should Be Replaced 19866 1 Ea. 2 $976 Yes
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19867 12 Ea. 4 $6,448 No
Sub Total for System 2 $7,424
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Cleaning Required 19861 824 SF 5 $774 No
Duct Grill is Damaged And Should Be Replaced 19862 4 Ea. 5 $1,287 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 19860 824 SF 4 $1,847 No
Sub Total for System 3 $3,908
Deficiency ID Qty UoM Priority Repair Cost WS&D
Mechanical
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 19843 824 SF 3 $6,210 No
The Suspended Ceiling Grid is Damaged And Require Replacement 19840 824 SF 3 $6,643 No
Interior Walls Require Repainting 19841 824 SF 5 $2,204 No
Interior Doors Require Repainting 19842 3 Door 5 $160 No
Sub Total for System 4 $15,217
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Aluminum Window Is Damaged And Requires Replacement 19837 8 Ea. 2 $13,830 Yes
Exterior door hardware is damaged and should be replaced 19836 2 Door 2 $1,207 Yes
The Metal Exterior Door Is Damaged And Requires Replacement 19835 2 Door 2 $4,714 Yes
The Exterior Soffit Is Damaged And Requires Replacement 19834 824 SF 4 $19,989 No
Sub Total for System 4 $39,740
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Gutters Are Damaged 19848 15 LF 2 $229 No
Joint Between Rake Cover And Roof Panel Requires Re-Sealing 19857 20 LF 2 $1,507 Yes
Laps In Metal Cover At Hip/Ridge Require Resealing 19859 10 Ea. 2 $302 Yes
Gutter Screens Are Missing And Needed 19847 60 LF 2 $395 No
Damaged Gasketed Closure 19858 30 LF 2 $329 Yes
Debris In Gutters Should Be Removed 19846 15 LF 2 $359 Yes
Gutter Joints Require Repair 19849 6 Ea. 2 $193 No
Loose/Missing Exposed Panel Fasteners 19855 25 Ea. 2 $939 Yes
Sealant At Penetration Boot Is Damaged And Should Be Repaired 19853 1 Ea. 2 $293 Yes
The Metal Downspouts Are Damaged Or Missing And Requires Replacement 19850 60 LF 3 $2,852 No
Splashblocks Are Missing Or Damaged And Are Needed 19851 2 Ea. 5 $206 No
Metal Rake Cover Is Damaged Or Loose 19856 20 LF 2 $344 Yes
Re-Seal Metal Roof Panel Laps (Seams) Require Repair And Re-Seal 19854 15 LF 2 $224 Yes
Re-Seal Metal Roof-To-Wall Flashing At Wall 19852 14 LF 2 $295 Yes
Sub Total for System 14 $8,467
Deficiency ID Qty UoM Priority Repair Cost WS&D
Roofing
Sub Total for Building 3040-06 - Humanities Bldg. 06 (1803) 33 $97,150
Building: 3040-06 - Humanities Bldg. 06 (1803)
Facilities Condition AssessmentTransmountain Campus Condition Assessment
20Magellan Consulting, Inc.
The Base Storage Cabinets Require Replacement 19918 5 LF 4 $1,421 No
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 19946 3 Ea. 2 $1,600 Yes
Fire Alarm is Missing or Inadequate 19948 824 SF 1 $1,438 Yes
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 19945 824 SF 2 $484 Yes
Security Alarm is Missing or Inadequate 19947 824 SF 2 $1,487 No
Sub Total for System 4 $5,009
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19944 10 Ea. 4 $5,374 No
Sub Total for System 1 $5,374
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Grill is Damaged And Should Be Replaced 19941 4 Ea. 5 $1,287 No
Ductwork Is Damaged And Should Be Replaced 19940 70 LF 3 $1,332 No
Duct Grill is Damaged And Should Be Replaced 19942 2 Ea. 5 $644 No
Duct Grill is Damaged And Should Be Replaced 19943 1 Ea. 5 $322 No
Sub Total for System 4 $3,585
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 19917 824 SF 3 $6,210 No
The Interior Door Hardware is Damaged and Requires Replacement 19916 3 Ea. 2 $3,056 No
The Suspended Ceiling Grid is Damaged And Require Replacement 19913 824 SF 3 $6,643 No
Interior Doors Require Repainting 19915 4 Door 5 $213 No
Interior Walls Require Repainting 19914 824 SF 5 $2,204 No
Sub Total for System 5 $18,326
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Exterior door hardware is damaged and should be replaced 19909 2 Door 2 $1,207 Yes
The Aluminum Window Is Damaged And Requires Replacement 19910 8 Ea. 2 $13,830 Yes
The Exterior Soffit Is Damaged And Requires Replacement 19907 824 SF 4 $19,989 No
The Metal Exterior Door Is Damaged And Requires Replacement 19908 2 Door 2 $4,714 Yes
Sub Total for System 4 $39,740
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Gasketed Closure At Metal Edge Is Damaged And Should Be Replaced 19927 30 LF 2 $7,142 Yes
Edge Metal Is Missing 19933 15 LF 2 $289 Yes
Gutter Joints Require Repair 19923 5 Ea. 2 $162 No
Gutters Are Damaged 19922 60 LF 2 $915 No
Gutter Screens Are Missing And Needed 19921 60 LF 2 $395 No
Damaged Hip/Ridge 19937 30 LF 2 $349 Yes
Damaged Gasketed Closure 19938 20 LF 2 $220 Yes
Debris In Gutters Should Be Removed 19920 60 LF 2 $359 Yes
Edge Metal Is Loose And Should Be Resecured 19934 30 LF 2 $874 Yes
Edge Metal Is Damaged And Should Be Replaced 19926 20 LF 2 $681 Yes
Joint Between Rake Cover And Roof Panel Requires Re-Sealing 19936 10 LF 2 $753 Yes
The Roof Requires Cleaning 19930 50 SF 2 $369 Yes
Sealant At Penetration Boot Is Damaged And Should Be Repaired 19929 1 Ea. 2 $293 Yes
Splashblocks Are Missing Or Damaged And Are Needed 19925 4 Ea. 5 $413 No
The Metal Downspouts Are Damaged Or Missing And Requires Replacement 19924 60 LF 3 $2,852 No
Re-Seal Metal Roof-To-Wall Flashing At Wall 19928 10 LF 2 $293 Yes
Metal Rake Cover Is Damaged Or Loose 19935 15 LF 2 $257 Yes
Loose/Missing Exposed Panel Fasteners 19932 25 Ea. 2 $939 Yes
Re-Seal Metal Roof Panel Laps (Seams) Require Repair And Re-Seal 19931 20 LF 2 $298 Yes
Re-Seal Joint Between Metal Z Closure & Roof Panel Is Damaged And Requires Repair 19939 5 LF 2 $171 Yes
Sub Total for System 20 $18,025
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 3040-07 - Humanities Bldg. 07 (1804)
Facilities Condition AssessmentTransmountain Campus Condition Assessment
21Magellan Consulting, Inc.
The Upper Storage Cabinets Require Replacement 19810 32 LF 4 $5,817 No
The Base Storage Cabinets Require Replacement 19809 32 LF 4 $9,095 No
Sub Total for System 2 $14,911
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Fire Alarm Panel Should Be Replaced 19832 1 Ea. 1 $9,677 Yes
Security Alarm Motion Detector Is Missing Or Damaged And Should Be Replaced 19831 1 Ea. 2 $824 No
Sub Total for System 2 $10,501
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19830 12 Ea. 4 $6,448 No
Sub Total for System 1 $6,448
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Cleaning Required 19827 829 SF 5 $777 No
Duct Grill is Damaged And Should Be Replaced 19828 4 Ea. 5 $1,287 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 19826 829 SF 4 $1,858 No
Sub Total for System 3 $3,922
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 19808 829 SF 3 $6,248 No
The Suspended Ceiling Grid is Damaged And Require Replacement 19805 829 SF 3 $6,683 No
Interior Doors Require Repainting 19807 3 Door 5 $160 No
Interior Walls Require Repainting 19806 829 SF 5 $2,219 No
Sub Total for System 4 $15,310
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Metal Exterior Door Is Damaged And Requires Replacement 19800 2 Door 2 $4,714 Yes
The Aluminum Window Is Damaged And Requires Replacement 19802 8 Ea. 2 $13,830 Yes
Exterior door hardware is damaged and should be replaced 19801 1 Door 2 $604 Yes
The Exterior Soffit Is Damaged And Requires Replacement 19799 829 SF 4 $20,111 No
Sub Total for System 4 $39,259
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Joint Between Rake Cover And Roof Panel Requires Re-Sealing 19823 20 LF 2 $1,507 Yes
Gutters Are Damaged 19813 30 LF 2 $457 No
Loose/Missing Exposed Panel Fasteners 19821 30 Ea. 2 $1,128 Yes
Laps In Metal Cover At Hip/Ridge Require Resealing 19825 10 Ea. 2 $302 Yes
Debris In Gutters Should Be Removed 19811 30 LF 2 $359 Yes
Damaged Gasketed Closure 19824 30 LF 2 $329 Yes
Gutter Screens Are Missing And Needed 19812 60 LF 2 $395 No
Gutter Joints Require Repair 19814 6 Ea. 2 $193 No
The Roof Requires Cleaning 19819 100 SF 2 $379 Yes
The Metal Downspouts Are Damaged Or Missing And Requires Replacement 19815 60 LF 3 $2,852 No
Splashblocks Are Missing Or Damaged And Are Needed 19816 2 Ea. 5 $206 No
Sealant At Penetration Boot Is Damaged And Should Be Repaired 19818 1 Ea. 2 $293 Yes
Metal Rake Cover Is Damaged Or Loose 19822 20 LF 2 $344 Yes
Re-Seal Metal Roof Panel Laps (Seams) Require Repair And Re-Seal 19820 22 LF 2 $329 Yes
Re-Seal Metal Roof-To-Wall Flashing At Wall 19817 20 LF 2 $297 Yes
Sub Total for System 15 $9,369
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 3040-08 - Humanities Bldg. 08 (1805) 31 $99,721
Building: 3040-08 - Humanities Bldg. 08 (1805)
The Upper Storage Cabinets Require Replacement 19919 5 LF 4 $908 No
Sub Total for System 2 $2,330
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 3040-07 - Humanities Bldg. 07 (1804) 40 $92,389
Facilities Condition AssessmentTransmountain Campus Condition Assessment
22Magellan Consulting, Inc.
Gutter Screens Are Missing And Needed 18400 60 LF 2 $395 No
Gutters Are Damaged 18401 60 LF 2 $915 No
Gutter Joints Require Repair 18402 8 Ea. 2 $258 No
Damaged Gasketed Closure 18413 60 LF 2 $659 Yes
Debris In Gutters Should Be Removed 18399 60 LF 2 $359 Yes
Joint Between Rake Cover And Roof Panel Requires Re-Sealing 18411 10 LF 2 $753 Yes
Laps In Metal Cover At Hip/Ridge Require Resealing 18414 8 Ea. 2 $298 Yes
Loose/Missing Exposed Panel Fasteners 18410 15 Ea. 2 $564 Yes
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 3040-10 - Humanities Bldg. 10 (1807)
Emergency Exit Signage Is Missing And Needed 18374 2 Ea. 2 $1,565 Yes
Fire Alarm Panel Should Be Replaced 18375 1 Ea. 1 $9,677 Yes
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 18373 800 SF 2 $470 Yes
Sub Total for System 3 $11,712
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Panelboard Is Damaged And Should Be Replaced 18372 100 Amps 2 $3,043 Yes
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 18371 12 Ea. 4 $6,448 No
Sub Total for System 2 $9,491
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Grill is Damaged And Should Be Replaced 18369 4 Ea. 5 $1,287 No
Duct Cleaning Required 18368 800 SF 5 $752 No
Sub Total for System 2 $2,038
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Carpet Flooring Is Damaged And Requires Replacement 18360 800 SF 3 $7,063 No
The Suspended Ceiling Grid is Damaged And Require Replacement 18357 800 SF 3 $6,450 No
Interior Walls Require Repainting 18358 800 SF 5 $2,140 No
The Interior Door Hardware is Damaged and Requires Replacement 18359 1 Ea. 2 $1,019 No
Sub Total for System 4 $16,673
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Metal Exterior Door Is Damaged And Requires Replacement 18383 2 Door 2 $4,714 Yes
The Aluminum Window Is Damaged And Requires Replacement 18385 8 Ea. 2 $13,830 Yes
Exterior door hardware is damaged and should be replaced 18384 2 Door 2 $1,207 Yes
The Exterior Soffit Is Damaged And Requires Repair 18382 600 SF 5 $2,362 No
The Exterior Requires Painting 18381 1,200 SF Wall 5 $3,585 No
Sub Total for System 5 $25,698
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Joint Between Rake Cover And Roof Panel Requires Re-Sealing 18378 10 LF 2 $753 Yes
Laps In Metal Cover At Hip/Ridge Require Resealing 18380 5 Ea. 2 $297 Yes
Loose/Missing Exposed Panel Fasteners 18376 30 Ea. 2 $1,128 Yes
Gutter Screens Are Missing And Needed 18362 60 LF 2 $395 No
Damaged Gasketed Closure 18379 30 LF 2 $329 Yes
Debris In Gutters Should Be Removed 18361 60 LF 2 $359 Yes
Gutter Joints Require Repair 18363 10 Ea. 2 $322 No
The Metal Downspouts Are Damaged Or Missing And Requires Replacement 18364 60 LF 3 $2,852 No
Splashblocks Are Missing Or Damaged And Are Needed 18365 2 Ea. 5 $206 No
The Roof Requires Cleaning 18367 160 SF 2 $750 Yes
Metal Rake Cover Is Damaged Or Loose 18377 10 LF 2 $171 Yes
Re-Seal Metal Roof-To-Wall Flashing At Wall 18366 24 LF 2 $297 Yes
Sub Total for System 12 $7,859
Deficiency ID Qty UoM Priority Repair Cost WS&D
Roofing
Sub Total for Building 3040-09 - Humanities Bldg. 09 (1806) 28 $73,472
Building: 3040-09 - Humanities Bldg. 09 (1806)
Facilities Condition AssessmentTransmountain Campus Condition Assessment
23Magellan Consulting, Inc.
Gutter Joints Require Repair 18506 8 Ea. 2 $258 No
Gutter Screens Are Missing And Needed 18504 60 LF 2 $395 No
Damaged Gasketed Closure 18522 30 LF 2 $329 Yes
Debris In Gutters Should Be Removed 18503 60 LF 2 $359 Yes
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 3040-11 - Humanities Bldg. 11 (1808)
Public Address Is Inadequate And Should Be Replaced 18427 800 SF 1 $1,545 Yes
Sub Total for System 1 $1,545
TechnologyDeficiency ID Qty UoM Priority Repair Cost WS&D
Emergency Exit Signage Is Missing And Needed 18426 1 Ea. 2 $783 Yes
Fire Alarm is Missing or Inadequate 18430 800 SF 1 $1,396 Yes
Emergency Lighting Is Inadequate Or Not Present And Should Be Installed 18424 800 SF 2 $1,194 Yes
Security Alarm is Missing or Inadequate 18428 800 SF 2 $1,443 No
Sub Total for System 4 $4,816
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Class Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 18421 1 Ea. 4 $2,051 No
Sub Total for System 1 $2,051
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 18422 12 Ea. 4 $6,448 No
The Electrical Circuit Capacity Is Inadequate 18423 4 EACH 4 $3,778 No
Sub Total for System 2 $10,227
Deficiency ID Qty UoM Priority Repair Cost WS&D
Electrical
Duct Grill is Damaged And Should Be Replaced 18417 2 Ea. 5 $644 No
Duct Grill is Damaged And Should Be Replaced 18416 4 Ea. 5 $1,287 No
Ductwork Is Damaged And Should Be Replaced 18415 70 LF 3 $1,332 No
Duct Register is Damaged And Should Be Replaced 18420 1 Ea. 5 $824 No
Sub Total for System 4 $4,088
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Suspended Ceiling Grid is Damaged And Require Replacement 18395 800 SF 3 $6,450 No
The Carpet Flooring Is Damaged And Requires Replacement 18398 800 SF 3 $7,063 No
The Interior Door Hardware is Damaged and Requires Replacement 18397 1 Ea. 2 $1,019 No
Interior Walls Require Repainting 18396 800 SF 5 $2,140 No
Sub Total for System 4 $16,673
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Aluminum Window Is Damaged And Requires Replacement 18393 8 Ea. 2 $13,830 Yes
Exterior door hardware is damaged and should be replaced 18392 2 Door 2 $1,207 Yes
The Metal Exterior Door Is Damaged And Requires Replacement 18391 2 Door 2 $4,714 Yes
The Exterior Soffit Is Damaged And Requires Repainting 18390 600 SF 5 $2,584 No
Sub Total for System 4 $22,335
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Sealant At Penetration Boot Is Damaged And Should Be Repaired 20818 10 Ea. 2 $317 Yes
The Roof Requires Cleaning 18408 70 SF 2 $373 Yes
Penetration Boot Is Missing Or Damaged And Should Be Installed 18407 1 Ea. 2 $167 Yes
Re-Seal Metal Roof-To-Wall Flashing At Wall 18406 7 LF 2 $293 Yes
Thru-Wall Flashing At Rise-Wall Should Be Raised And Reflashed 18405 1 LF 2 $300 No
Splashblocks Are Missing Or Damaged And Are Needed 18404 2 Ea. 5 $206 No
The Metal Downspouts Are Damaged Or Missing And Requires Replacement 18403 60 LF 3 $2,852 No
Sub Total for System 15 $8,711
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 3040-10 - Humanities Bldg. 10 (1807) 35 $70,445
Facilities Condition AssessmentTransmountain Campus Condition Assessment
24Magellan Consulting, Inc.
Gutter Screens Are Missing And Needed 18561 60 LF 2 $395 No
Gutters Are Damaged 18562 10 LF 2 $153 No
Joint Between Rake Cover And Roof Panel Requires Re-Sealing 18569 20 LF 2 $1,507 Yes
Damaged Gasketed Closure 18570 30 LF 2 $329 Yes
Debris In Gutters Should Be Removed 18560 35 LF 2 $359 Yes
Gutter Joints Require Repair 18563 12 Ea. 2 $388 No
Laps In Metal Cover At Hip/Ridge Require Resealing 18571 5 Ea. 2 $297 Yes
Loose/Missing Exposed Panel Fasteners 18568 35 Ea. 2 $1,316 Yes
Re-Seal Metal Roof-To-Wall Flashing At Wall 18566 12 LF 2 $293 Yes
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 3040-12 - Humanities Bldg. 12 (1809)
Emergency Exit Signage Is Missing And Needed 18533 2 Ea. 2 $1,565 Yes
Fire Alarm is Missing or Inadequate 18546 800 SF 1 $1,396 Yes
Emergency Lighting Is Inadequate Or Not Present And Should Be Installed 18531 800 SF 2 $1,194 Yes
Security Alarm is Missing or Inadequate 18543 800 SF 2 $1,443 No
Sub Total for System 4 $5,598
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 18529 12 Ea. 4 $6,448 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 18528 1 Ea. 2 $976 Yes
Sub Total for System 2 $7,424
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Register is Damaged And Should Be Replaced 18525 1 Ea. 5 $824 No
Duct Grill is Damaged And Should Be Replaced 18527 2 Ea. 5 $644 No
Ductwork Is Damaged And Should Be Replaced 18524 70 LF 3 $1,332 No
Duct Grill is Damaged And Should Be Replaced 18526 4 Ea. 5 $1,287 No
Sub Total for System 4 $4,088
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Carpet Flooring Is Damaged And Requires Replacement 18502 800 SF 3 $7,063 No
The Interior Door Hardware is Damaged and Requires Replacement 18501 4 Ea. 2 $4,075 No
The Suspended Ceiling Grid is Damaged And Require Replacement 18499 800 SF 3 $6,450 No
Interior Walls Require Repainting 18500 800 SF 5 $2,140 No
Sub Total for System 4 $19,729
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Metal Exterior Door Is Damaged And Requires Replacement 18495 2 Door 2 $4,714 Yes
The Aluminum Window Is Damaged And Requires Replacement 18497 8 Ea. 2 $13,830 Yes
Exterior door hardware is damaged and should be replaced 18496 2 Door 2 $1,207 Yes
The Exterior Requires Painting 18494 1,200 SF Wall 5 $3,585 No
The Exterior Soffit Is Damaged And Requires Repainting 23696 800 SF 5 $3,445 No
Sub Total for System 5 $26,781
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Loose/Missing Exposed Panel Fasteners 18519 30 Ea. 2 $1,128 Yes
Metal Rake Cover Is Damaged Or Loose 18520 10 LF 2 $171 Yes
Re-Seal Metal Roof-To-Wall Flashing At Wall 18515 10 LF 2 $293 Yes
Gutters Are Damaged 18505 30 LF 2 $457 No
Joint Between Rake Cover And Roof Panel Requires Re-Sealing 18521 10 LF 2 $753 Yes
Laps In Metal Cover At Hip/Ridge Require Resealing 18523 5 Ea. 2 $297 Yes
The Metal Downspouts Are Damaged Or Missing And Requires Replacement 18507 60 LF 3 $2,852 No
Splashblocks Are Missing Or Damaged And Are Needed 18510 2 Ea. 5 $206 No
Sealant At Penetration Boot Is Damaged And Should Be Repaired 20819 1 Ea. 2 $293 Yes
The Roof Requires Cleaning 18517 100 SF 2 $379 Yes
Sub Total for System 14 $8,170
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 3040-11 - Humanities Bldg. 11 (1808) 33 $71,790
Facilities Condition AssessmentTransmountain Campus Condition Assessment
25Magellan Consulting, Inc.
The Aluminum Window Is Damaged And Requires Replacement 18603 8 Ea. 2 $13,830 Yes
Exterior door hardware is damaged and should be replaced 18602 2 Door 2 $1,207 Yes
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Gutters Are Damaged 18611 10 LF 2 $153 No
Gutter Screens Are Missing And Needed 18610 60 LF 2 $395 No
Laps In Metal Cover At Hip/Ridge Require Resealing 18632 4 Ea. 2 $295 Yes
Joint Between Rake Cover And Roof Panel Requires Re-Sealing 18628 15 LF 2 $1,130 Yes
Damaged Hip/Ridge 18629 30 LF 2 $349 Yes
Damaged Gasketed Closure 18630 30 LF 2 $329 Yes
Gutter Joints Require Repair 18612 12 Ea. 2 $388 No
Debris In Gutters Should Be Removed 18609 40 LF 2 $359 Yes
Re-Seal Metal Roof-To-Wall Flashing At Wall 18616 25 LF 2 $297 Yes
The Metal Downspouts Are Damaged Or Missing And Requires Replacement 18613 60 LF 3 $2,852 No
Splashblocks Are Missing Or Damaged And Are Needed 18614 2 Ea. 5 $206 No
Repair Holes In Structural Metal Roof Panels 18625 1 Ea. 2 $399 Yes
Loose/Missing Exposed Panel Fasteners 18622 35 Ea. 2 $1,316 Yes
Metal Rake Cover Is Damaged Or Loose 18626 15 LF 2 $257 Yes
Penetration Boot Is Missing Or Damaged And Should Be Installed 18619 1 Ea. 2 $167 Yes
Sub Total for System 15 $8,891
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 3040-13 - Humanities Bldg. 13 (1810)
Emergency Exit Signage Is Missing And Needed 18576 2 Ea. 2 $1,565 Yes
Fire Alarm Panel Should Be Replaced 18577 1 Ea. 1 $9,677 Yes
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 18575 800 SF 2 $470 Yes
Sub Total for System 3 $11,712
Deficiency ID Qty UoM Priority Repair Cost WS&D
Fire and Life Safety
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 18574 12 Ea. 4 $6,448 No
Sub Total for System 1 $6,448
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Grill is Damaged And Should Be Replaced 18573 4 Ea. 5 $1,287 No
Duct Cleaning Required 18572 800 SF 5 $752 No
Sub Total for System 2 $2,038
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Suspended Ceiling Grid is Damaged And Require Replacement 18556 800 SF 3 $6,450 No
The Carpet Flooring Is Damaged And Requires Replacement 18559 800 SF 3 $7,063 No
The Interior Door Hardware is Damaged and Requires Replacement 18558 1 Ea. 2 $1,019 No
Interior Walls Require Repainting 18557 800 SF 5 $2,140 No
Sub Total for System 4 $16,673
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Metal Exterior Door Is Damaged And Requires Replacement 18552 2 Door 2 $4,714 Yes
The Aluminum Window Is Damaged And Requires Replacement 18554 8 Ea. 2 $13,830 Yes
Exterior door hardware is damaged and should be replaced 18553 2 Door 2 $1,207 Yes
The Exterior Requires Painting 18550 1,200 SF Wall 5 $3,585 No
The Exterior Soffit Is Damaged And Requires Repainting 18551 600 SF 5 $2,584 No
Sub Total for System 5 $25,920
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Splashblocks Are Missing Or Damaged And Are Needed 18565 2 Ea. 5 $206 No
The Metal Downspouts Are Damaged Or Missing And Requires Replacement 18564 60 LF 3 $2,852 No
The Roof Requires Cleaning 18567 100 SF 2 $379 Yes
Sub Total for System 12 $8,472
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 3040-12 - Humanities Bldg. 12 (1809) 27 $71,264
Facilities Condition AssessmentTransmountain Campus Condition Assessment
26Magellan Consulting, Inc.
The Metal Exterior Door Is Damaged And Requires Replacement 18655 2 Door 2 $4,714 Yes
The Aluminum Window Is Damaged And Requires Replacement 18657 8 Ea. 2 $13,830 Yes
Exterior door hardware is damaged and should be replaced 18656 2 Door 2 $1,207 Yes
The Stucco Exterior Is Damaged And Requires Repair 18654 6 SF Wall 2 $897 Yes
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Joint Between Rake Cover And Roof Panel Requires Re-Sealing 18674 15 LF 2 $1,130 Yes
Laps In Metal Cover At Hip/Ridge Require Resealing 18676 4 Ea. 2 $295 Yes
Loose/Missing Exposed Panel Fasteners 18672 35 Ea. 2 $1,316 Yes
Gutters Are Damaged 18665 20 LF 2 $306 No
Damaged Gasketed Closure 18675 30 LF 2 $329 Yes
Debris In Gutters Should Be Removed 18663 60 LF 2 $359 Yes
Gutter Screens Are Missing And Needed 18664 60 LF 2 $395 No
Metal Rake Cover Is Damaged Or Loose 18673 15 LF 2 $257 Yes
The Roof Requires Cleaning 18670 150 SF 2 $748 Yes
The Metal Downspouts Are Damaged Or Missing And Requires Replacement 18666 60 LF 3 $2,852 No
Splashblocks Are Missing Or Damaged And Are Needed 18667 2 Ea. 5 $206 No
Penetration Boot Is Missing Or Damaged And Should Be Installed 18669 1 Ea. 2 $167 Yes
Re-Seal Metal Roof Panel Laps (Seams) Require Repair And Re-Seal 18671 15 LF 2 $224 Yes
Re-Seal Metal Roof-To-Wall Flashing At Wall 18668 25 LF 2 $297 Yes
Sub Total for System 14 $8,880
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 3040-14 - Humanities Bldg. 14 (1811)
Emergency Lighting Is Inadequate Or Not Present And Should Be Installed 18648 800 SF 2 $1,194 Yes
Security Alarm is Missing or Inadequate 18650 800 SF 2 $1,443 No
Fire Alarm is Missing or Inadequate 18651 800 SF 1 $1,396 Yes
Emergency Exit Signage Is Missing And Needed 18649 2 Ea. 2 $1,565 Yes
Sub Total for System 4 $5,598
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Class Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 18645 1 Ea. 4 $2,051 No
Sub Total for System 1 $2,051
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 18647 12 Ea. 4 $6,448 No
Sub Total for System 1 $6,448
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Grill is Damaged And Should Be Replaced 18641 2 Ea. 5 $644 No
Duct Grill is Damaged And Should Be Replaced 18639 4 Ea. 5 $1,287 No
Ductwork Is Damaged And Should Be Replaced 18635 70 LF 3 $1,332 No
Duct Register is Damaged And Should Be Replaced 18638 1 Ea. 5 $824 No
Sub Total for System 4 $4,088
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Suspended Ceiling Grid is Damaged And Require Replacement 18605 800 SF 3 $6,450 No
The Carpet Flooring Is Damaged And Requires Replacement 18608 800 SF 3 $7,063 No
The Interior Door Hardware is Damaged and Requires Replacement 18607 1 Ea. 2 $1,019 No
Interior Walls Require Repainting 18606 800 SF 5 $2,140 No
Sub Total for System 4 $16,673
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Exterior Soffit Is Damaged And Requires Repainting 18600 600 SF 5 $2,584 No
The Exterior Requires Painting 18599 1,200 SF Wall 5 $3,585 No
The Metal Exterior Door Is Damaged And Requires Replacement 18601 2 Door 2 $4,714 Yes
Sub Total for System 5 $25,920
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 3040-13 - Humanities Bldg. 13 (1810) 34 $69,670
Facilities Condition AssessmentTransmountain Campus Condition Assessment
27Magellan Consulting, Inc.
The Suspended Ceiling Grid is Damaged And Require Replacement 19775 800 SF 3 $6,450 No
Interior Walls Require Repainting 19776 800 SF 5 $2,140 No
The Carpet Flooring Is Damaged And Requires Replacement 19777 800 SF 3 $7,063 No
Sub Total for System 3 $15,654
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Aluminum Window Is Damaged And Requires Replacement 19773 8 Ea. 2 $13,830 Yes
Exterior door hardware is damaged and should be replaced 19772 2 Door 2 $1,207 Yes
The Metal Exterior Door Is Damaged And Requires Replacement 19771 2 Door 2 $4,714 Yes
The Exterior Soffit Is Damaged And Requires Repainting 19770 600 SF 5 $2,584 No
Sub Total for System 4 $22,335
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Gutters Are Damaged 19780 15 LF 2 $229 No
Joint Between Rake Cover And Roof Panel Requires Re-Sealing 19788 15 LF 2 $1,130 Yes
Laps In Metal Cover At Hip/Ridge Require Resealing 19790 8 Ea. 2 $298 Yes
Debris In Gutters Should Be Removed 19778 60 LF 2 $359 Yes
Gutter Joints Require Repair 19781 8 Ea. 2 $258 No
Gutter Screens Are Missing And Needed 19779 60 LF 2 $395 No
The Roof Requires Cleaning 19785 40 SF 2 $368 Yes
The Metal Downspouts Are Damaged Or Missing And Requires Replacement 19782 60 LF 3 $2,852 No
Splashblocks Are Missing Or Damaged And Are Needed 19783 2 Ea. 5 $206 No
Loose/Missing Exposed Panel Fasteners 19786 25 Ea. 2 $939 Yes
Metal Rake Cover Is Damaged Or Loose 19787 12 LF 2 $206 Yes
Re-Seal Metal Roof-To-Wall Flashing At Wall 19784 10 LF 2 $293 Yes
Damaged Gasketed Closure 19789 15 LF 2 $164 Yes
Sub Total for System 13 $7,697
Deficiency ID Qty UoM Priority Repair Cost WS&D
Roofing
Building: 3040-15 - Humanities Bldg. 15 (1812)
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 18682 2 Ea. 2 $1,067 Yes
Fire Alarm Panel Should Be Replaced 18683 1 Ea. 1 $9,677 Yes
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 18681 800 SF 2 $470 Yes
Sub Total for System 3 $11,213
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 18680 12 Ea. 4 $6,448 No
Sub Total for System 1 $6,448
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Grill is Damaged And Should Be Replaced 18678 4 Ea. 5 $1,287 No
Duct Cleaning Required 18677 800 SF 5 $752 No
Sub Total for System 2 $2,038
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Suspended Ceiling Grid is Damaged And Require Replacement 18659 800 SF 3 $6,450 No
The Carpet Flooring Is Damaged And Requires Replacement 18662 800 SF 3 $7,063 No
The Interior Door Hardware is Damaged and Requires Replacement 18661 1 Ea. 2 $1,019 No
Interior Walls Require Repainting 18660 800 SF 5 $2,140 No
Sub Total for System 4 $16,673
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Exterior Soffit Is Damaged And Requires Repainting 18653 600 SF 5 $2,584 No
The Exterior Requires Painting 18652 1,200 SF Wall 5 $3,585 No
Sub Total for System 6 $26,818
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 3040-14 - Humanities Bldg. 14 (1811) 30 $72,070
Facilities Condition AssessmentTransmountain Campus Condition Assessment
28Magellan Consulting, Inc.
Emergency Exit Signage Is Missing And Needed 19768 2 Ea. 2 $1,565 Yes
Fire Alarm Panel is Missing and is Needed 19769 1 Ea. 1 $3,727 Yes
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19766 12 Ea. 4 $6,448 No
Sub Total for System 1 $6,448
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Controls Are Inadequate And Should Be Replaced With DDC Controls 19764 800 SF 4 $1,793 No
Sub Total for System 1 $1,793
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Walls Require Repainting 19749 80 SF 5 $215 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 19750 800 SF 3 $6,030 No
The Suspended Ceiling Grid is Damaged And Require Replacement 19748 800 SF 3 $6,450 No
Sub Total for System 3 $12,694
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Aluminum Window Is Damaged And Requires Replacement 19746 8 Ea. 2 $13,830 Yes
Exterior door hardware is damaged and should be replaced 19745 2 Door 2 $1,207 Yes
The Metal Exterior Door Is Damaged And Requires Replacement 19744 2 Door 2 $4,714 Yes
The Exterior Soffit Is Damaged And Requires Repainting 19743 240 SF 5 $1,034 No
Sub Total for System 4 $20,784
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Roof Requires Cleaning 19758 200 SF 2 $757 Yes
The Metal Downspouts Are Damaged Or Missing And Requires Replacement 19755 60 LF 3 $2,852 No
Splashblocks Are Missing Or Damaged And Are Needed 19756 2 Ea. 5 $206 No
Gutter Screens Are Missing And Needed 19752 60 LF 2 $395 No
Gutters Are Damaged 19753 10 LF 2 $153 No
Gutter Joints Require Repair 19754 8 Ea. 2 $258 No
Damaged Gasketed Closure 19762 20 LF 2 $220 Yes
Debris In Gutters Should Be Removed 19751 60 LF 2 $359 Yes
Joint Between Rake Cover And Roof Panel Requires Re-Sealing 19761 15 LF 2 $1,130 Yes
Metal Rake Cover Is Damaged Or Loose 19760 15 LF 2 $257 Yes
Re-Seal Metal Roof-To-Wall Flashing At Wall 19757 10 LF 2 $293 Yes
Loose/Missing Exposed Panel Fasteners 19759 30 Ea. 2 $1,128 Yes
Laps In Metal Cover At Hip/Ridge Require Resealing 19763 8 Ea. 2 $298 Yes
Sub Total for System 13 $8,306
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 3040-16 - Humanities Bldg. 16 (1813)
Emergency Exit Signage Is Missing And Needed 19797 2 Ea. 2 $1,565 Yes
Fire Alarm Panel is Missing and is Needed 19798 1 Ea. 1 $3,727 Yes
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 19796 800 SF 2 $470 Yes
Sub Total for System 3 $5,762
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19795 12 Ea. 4 $6,448 No
Sub Total for System 1 $6,448
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Grill is Damaged And Should Be Replaced 19793 4 Ea. 5 $1,287 No
Duct Cleaning Required 19792 800 SF 5 $752 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 19791 800 SF 4 $1,793 No
Sub Total for System 3 $3,831
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 3040-15 - Humanities Bldg. 15 (1812) 27 $61,727
Facilities Condition AssessmentTransmountain Campus Condition Assessment
29Magellan Consulting, Inc.
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 18351 2 Ea. 2 $1,067 Yes
Fire Alarm is Missing or Inadequate 18353 1,220 SF 1 $9,307 Yes
Emergency Lighting Is Inadequate Or Not Present And Should Be Installed 18350 1,220 SF 2 $1,822 Yes
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Power Service Is Inadequate And Should Be Replaced 18347 225 Amps 2 $9,311 No
The Electrical Receptacles Are Inadequate And More Are Needed 18354 2 Ea. 3 $886 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 18344 1 Ea. 2 $976 Yes
The Panelboard Is Damaged And Should Be Replaced 18348 225 Amps 2 $6,847 Yes
The Incandescent Lighting Is Damaged And Should Be Replaced 18346 1 Ea. 4 $364 No
The Electrical Circuit Capacity Is Inadequate 18349 42 EACH 4 $39,663 No
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 18345 9 Ea. 4 $3,178 No
Sub Total for System 7 $61,225
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Controls Are Inadequate And Should Be Replaced With DDC Controls 23699 1,220 SF 4 $2,734 No
Ductwork Is Damaged And Should Be Replaced 18341 100 LF 3 $1,902 No
Exhaust Fan Ventilation Is Damaged And Should Be Replaced 18343 1 Ea. 4 $1,935 No
Duct Register is Damaged And Should Be Replaced 18342 5 Ea. 5 $4,126 No
Sub Total for System 4 $10,696
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Interior Door Hardware is Damaged and Requires Replacement 18329 2 Ea. 2 $2,037 No
Interior Doors Require Replacement 18328 2 Door 3 $2,519 No
The Carpet Flooring Is Damaged And Requires Replacement 18330 1,220 SF 3 $10,773 No
Interior Walls Require Repainting 23698 1,220 SF 5 $3,263 No
The Gypboard Ceilings Are Damaged And Requires Repair 18327 1,220 SF 4 $3,775 No
Sub Total for System 5 $22,366
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Metal Panel Exterior Is Damaged And Requires Replacement 18308 2,000 SF Wall 3 $26,978 No
The Metal Exterior Door Is Damaged And Requires Replacement 18309 2 Door 2 $4,714 Yes
Exterior door hardware is damaged and should be replaced 18326 2 Door 2 $1,207 Yes
The Exterior Soffit Is Damaged And Requires Repainting 23697 1,220 SF 5 $5,254 No
The Exterior Requires Painting 18307 2,000 SF Wall 5 $5,975 No
Sub Total for System 5 $44,128
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Edge Metal Is Loose And Should Be Resecured 18333 120 LF 2 $3,616 Yes
Expansion Joint Cover Is Missing Or Damaged And Should Be Replaced 18335 35 LF 2 $2,506 Yes
Expansion Joint Laps Are Damaged And Should Be Repaired 18334 10 Ea. 2 $3,609 Yes
The Metal Roof Structural Roof Covering Is Damaged And Requires Replacement 18388 660 SF 1 $16,717 No
Edge Metal Is Damaged And Requires Replacement 18389 40 LF 2 $1,807 Yes
Edge Metal Is Damaged And Should Be Replaced 18332 120 LF 2 $4,090 Yes
Expansion Joint Termination At End Wall Is Damaged And Should Be Repaired 18336 2 Ea. 2 $897 Yes
Re-Seal Metal Roof Panel Laps (Seams) Require Repair And Re-Seal 18386 120 LF 2 $1,795 Yes
Curbs Have Been Abandoned And Should Be Removed 18337 2 Ea. 4 $986 No
Metal Roof-To-Curb Flashings Are Damaged And Should Be Resealed 18338 6 LF 2 $262 Yes
Loose/Missing Exposed Panel Fasteners 18387 30 Ea. 2 $1,128 Yes
Metal Roof Jack Is Damaged And Should Be Repaired 18339 2 Ea. 2 $295 Yes
Sub Total for System 12 $37,709
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 3040-17 - Humanities Bldg. 17 (1814)
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 19767 800 SF 2 $470 Yes
Sub Total for System 3 $5,762
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 3040-16 - Humanities Bldg. 16 (1813) 25 $55,788
Facilities Condition AssessmentTransmountain Campus Condition Assessment
30Magellan Consulting, Inc.
The Interior Door Hardware is Damaged and Requires Replacement 19131 72 Ea. 2 $73,337 No
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Aluminum Window Is Damaged And Requires Replacement 19121 32 Ea. 2 $55,317 Yes
The Aluminum Window Is Damaged And Requires Replacement 19122 3 Ea. 2 $5,185 Yes
Exterior door hardware is damaged and should be replaced 19120 9 Door 2 $5,431 Yes
The Aluminum Storefront Exterior Door Is Damaged And Requires Replacement 19119 4 Door 2 $17,423 Yes
The Metal Exterior Door Is Damaged And Requires Replacement 19118 5 Door 2 $11,786 Yes
The Exterior Soffit Is Damaged And Requires Repainting 19116 1,400 SF 5 $6,028 No
The Exterior Requires Painting 19115 1,596 SF Wall 5 $4,768 No
The Stucco Exterior Is Damaged And Requires Repair 19117 280 SF Wall 2 $1,982 Yes
Sub Total for System 8 $107,921
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Metal Umbrella At Penetration Or Pitch Pan Is Missing And Is Needed 19156 11 Ea. 2 $2,603 Yes
Pitch Pan Is Damaged And Should Be Replaced 19155 2 Ea. 2 $442 Yes
Strainers Are Missing And Needed 19139 2 Ea. 2 $1,611 Yes
Metal Coping Is Damaged Or Loose And Should Be Repaired 19145 57 LF 2 $3,493 Yes
Metal Coping Lap Joints Have Lost Their Seal And Should Be Resealed 19143 33 Ea. 2 $324 Yes
Metal Roof Jack Is Damaged And Should Be Repaired 19154 3 Ea. 2 $442 Yes
The Roof Drains Are Clogged 19138 7 Ea. 2 $819 Yes
Curbs Have Been Abandoned And Should Be Removed 19151 1 Ea. 4 $493 No
HVAC Curbs are too Low and Should be Raised and Reflashed (<8") 19149 3 Ea. 4 $4,151 No
Roof Curb To Match HVAC Unit Is Missing And Is Needed 19150 2 Ea. 4 $1,827 No
The Roof Requires Cleaning 19166 725 SF 2 $863 Yes
Thru-Wall Flashing At Rise-Wall Should Be Raised And Reflashed 19142 1 LF 2 $300 No
Tapered Insulation Is Required To Eliminate Ponding When Re-Roofing 19140 650 SF 3 $1,966 No
Coping Termination At End Wall Is Damaged And Should Be Repaired 19146 4 Ea. 2 $408 Yes
Counter Flashing Is Damaged Or Loose And Should Be Repaired 19144 555 LF 2 $6,783 Yes
Exhaust Fan Curbs are too Low and Should be Raised and Reflashed (<8") 19148 12 Ea. 2 $16,731 No
The Multi-Ply Bitumen Roof System Is Damaged And Requires Replacement 19165 400 SF 1 $4,818 No
Built Up Roofing (Bur) Covering Has Blisters That Should Be Repaired 19162 103 Ea. 2 $13,190 Yes
Built Up Roofing (Bur) Membrane Has Holes That Should Be Repaired 19163 2 Ea. 2 $242 Yes
Membrane Flashing At Parapet (>2') Is Damaged And Should Be Repaired 19141 200 LF 2 $788 Yes
Membrane Flashings At Equipment Curbs Are Damaged And Should Be Repaired 19147 24 LF 2 $373 Yes
Membrane Flashings At Penetration Are Damaged And Should Be Repaired 19158 2 Ea. 2 $209 Yes
Flashings At Scupper Is Damaged And Should Be Repaired 19137 5 Ea. 2 $304 Yes
Gas Line/Conduit On New Supports Is Unseated And Should Be Supported 19152 10 Ea. 2 $1,110 Yes
Lead Flashing Is Damaged And Should Be Repaired 19153 5 Ea. 2 $1,469 Yes
Sub Total for System 25 $65,758
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Fencing Is Damaged And Should Be Replaced (8' Chain Link Fence) 20867 80 LF 4 $2,661 No
Exterior Basketball Goals Are Damaged And Require Replacement 23623 4 Ea. 4 $22,792 No
Asphalt Paving Is Damaged And Requires Replacement 20882 55 CAR 4 $140,073 No
Volleyball standards are missing and are required 23625 2 Pr 4 $6,956 No
Tennis Nets And Equipment Are Damaged And Require Replacement 20866 4 Ea. 4 $10,345 No
Sub Total for System 5 $182,826
SiteDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 3050 - Science and Technology
The Base Storage Cabinets Require Replacement 18331 6 LF 4 $1,705 No
Sub Total for System 1 $1,705
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Security Alarm is Missing or Inadequate 18352 1,220 SF 2 $2,202 No
Sub Total for System 4 $14,398
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 3040-17 - Humanities Bldg. 17 (1814) 38 $192,227
Facilities Condition AssessmentTransmountain Campus Condition Assessment
31Magellan Consulting, Inc.
TechnologyDeficiency ID Qty UoM Priority Repair Cost WS&D
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 19193 25 Ea. 2 $13,339 Yes
Fire Alarm is Missing or Inadequate 19196 25,743 SF 1 $44,909 Yes
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 19192 25,743 SF 2 $15,108 Yes
Security Alarm is Missing or Inadequate 19195 25,743 SF 2 $46,461 No
Sub Total for System 4 $119,816
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Urinal Plumbing Fixtures Are Damaged And Should Be Replaced 20798 3 Ea. 3 $4,586 No
The Class Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 19179 3 Ea. 4 $6,155 No
The Water Heater Plumbing Fixtures Are Damaged And Should Be Replaced 19182 2 Ea. 2 $4,628 No
The Toilets Plumbing Fixtures Are Damaged And Should Be Replaced 19181 5 Ea. 3 $6,619 No
The Rest Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 19180 2 Ea. 4 $3,280 No
The Refrigerated Water Cooler is Damaged And Should Be Replaced 19183 2 Ea. 4 $8,731 No
The Custodial Mop Or Service Sink Is Damaged And Should Be Replaced 19178 1 Ea. 4 $3,948 No
Sub Total for System 7 $37,947
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The Mounted Building Lighting Is Damaged And Should Be Replaced 19187 8 Ea. 2 $7,799 Yes
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19188 67 Ea. 4 $23,656 No
The Canopy Lighting Is Damaged And Should Be Replaced 19186 13 Ea. 2 $22,927 Yes
The GFCI Electrical Receptacles Are Inadequate And More Are Needed 19197 4 Ea. 2 $1,960 Yes
The Incandescent Lighting Is Damaged And Should Be Replaced 19191 1 Ea. 4 $364 No
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19190 273 Ea. 4 $146,712 No
The 2 X 2 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19189 12 Ea. 4 $4,388 No
Sub Total for System 7 $207,806
Deficiency ID Qty UoM Priority Repair Cost WS&D
Electrical
VAV boxes require replacement 23707 60 Ea. 2 $123,973 No
The Roof Air Handler/Exhaust is Damaged And Requires Replacement 19170 8 TonAC 2 $100,076 No
Test And Balancing Required 19171 25,743 SF 3 $44,978 No
Ductwork Is Damaged And Should Be Replaced 19174 600 LF 3 $11,413 No
Exhaust hoods and fans require replacement 23831 1 LS 2 $100,100 No
Additional air handlers required 23736 3 Ea. 2 $172,907 No
The Large Diameter Exhausts/Hoods Are Missing/Damaged And Require Replacement 19168 3 Ea. 2 $5,107 No
The Boiler HVAC Component Is Damaged And Requires Replacement 20889 30 MBH 2 $681 No
Duct Cleaning Required 19173 25,443 SF 5 $23,877 No
Duct Grill is Damaged And Should Be Replaced 19176 60 Ea. 5 $19,312 No
Duct Register is Damaged And Should Be Replaced 19175 105 Ea. 5 $86,659 No
The 2 X 2 Exhausts/Hoods Are Missing/Damaged And Require Replacement 19169 10 Ea. 4 $22,710 No
The Evaporative Cooling Unit Is Damaged And Requires Replacement 20888 3 Ea. 3 $27,211 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 19172 25,743 SF 4 $57,687 No
Exhaust Fan Ventilation Is Damaged And Should Be Replaced 19177 13 Ea. 4 $25,158 No
Sub Total for System 15 $821,848
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Suspended Ceiling Grid is Damaged And Require Replacement 19124 19,700 SF 3 $158,833 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 19133 16,732 SF 3 $126,093 No
Interior Toilet Partition Require Repair Or Replacement 19128 14 Ea. 4 $33,885 No
Interior Doors Require Replacement 19129 4 Door 3 $5,038 No
The Carpet Flooring Is Damaged And Requires Replacement 19132 5,149 SF 3 $45,467 No
The Ceramic Tile Flooring Is Damaged And Requires Replacement 19134 1,287 SF 3 $20,531 No
Interior Walls Require Repainting 19127 25,743 SF 5 $68,872 No
The Gypboard Ceilings Are Damaged And Requires Repainting 19125 5,148 SF 5 $13,679 No
Interior Doors Require Repainting 19130 68 Door 5 $3,618 No
The Concrete Flooring Is Damaged And Requires Replacement 20887 2,574 SF 4 $18,586 No
Concrete Flooring Epoxy Requires Replacement 20868 4,500 SF 5 $8,818 No
Sub Total for System 12 $576,758
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Facilities Condition AssessmentTransmountain Campus Condition Assessment
32Magellan Consulting, Inc.
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The Electrical Receptacles Are Inadequate And More Are Needed 19494 10 Ea. 3 $4,434 No
The Power Service Is Inadequate And Should Be Upgraded 19489 225 Amps 3 $11,930 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 19483 4 Ea. 2 $3,900 Yes
The Canopy Lighting Is Damaged And Should Be Replaced 19482 6 Ea. 2 $10,581 Yes
The GFCI Electrical Receptacles Are Inadequate And More Are Needed 19495 1 Ea. 2 $490 Yes
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19485 6 Ea. 4 $2,118 No
The Electrical Circuit Capacity Is Inadequate 19490 1 EACH 4 $945 No
The Incandescent Lighting Is Damaged And Should Be Replaced 19488 2 Ea. 4 $728 No
The 2 X 2 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19486 1 Ea. 4 $366 No
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19487 196 Ea. 4 $105,333 No
Sub Total for System 10 $140,824
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
VAV boxes require replacement 23708 35 Ea. 2 $72,318 No
Duct Cleaning Required 19475 14,354 SF 5 $13,470 No
Additional air handlers required 23737 2 Ea. 2 $115,272 No
The Roof Air Handler/Exhaust is Damaged And Requires Replacement 19474 40 TonAC 2 $41,520 No
Duct Grill is Damaged And Should Be Replaced 19478 8 Ea. 5 $2,575 No
Duct Grill is Damaged And Should Be Replaced 19477 15 Ea. 5 $4,828 No
Duct Grill is Damaged And Should Be Replaced 19476 51 Ea. 5 $16,416 No
Sub Total for System 7 $266,399
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Doors Require Repainting 19443 35 Door 5 $1,862 No
Interior Walls Require Repainting 19439 13,000 SF 5 $34,780 No
The Ceramic Tile Flooring Is Damaged And Requires Replacement 19446 720 SF 3 $11,486 No
The Suspended Ceiling Grid is Damaged And Require Replacement 19438 12,000 SF 3 $96,751 No
Restrooms require complete renovation 23827 1 LS 3 $127,400 No
The Interior Door Hardware is Damaged and Requires Replacement 19444 38 Ea. 2 $38,706 No
Interior Doors Require Replacement 19442 3 Door 3 $3,778 No
The Concrete Flooring Is Damaged And Requires Replacement 19447 380 SF 4 $2,745 No
Interior Toilet Partition Require Repair Or Replacement 19440 2 Ea. 4 $4,841 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 19445 920 SF 3 $6,932 No
Interior Ceramic Walls Require Repair Or Replacement 19441 580 SF Wall 4 $8,587 No
Sub Total for System 11 $337,868
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Metal Exterior Door Is Damaged And Requires Replacement 19435 4 Door 2 $9,429 Yes
Exterior door hardware is damaged and should be replaced 19436 4 Door 2 $2,413 Yes
The Exterior Requires Painting 19434 4,800 SF Wall 5 $14,342 No
Sub Total for System 3 $26,184
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Multi-Ply Bitumen Roof System Is Damaged And Requires Replacement 19472 14,354 SF 1 $172,904 No
Sub Total for System 1 $172,904
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 3060 - Business Area
The Upper Storage Cabinets Require Replacement 19136 6 LF 4 $1,090 No
The Base Storage Cabinets Require Replacement 19135 18 LF 4 $5,116 No
Sub Total for System 2 $6,206
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Public Address Is Inadequate And Should Be Replaced 19194 25,743 SF 1 $49,726 Yes
Sub Total for System 1 $49,726
TechnologyDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 3050 - Science and Technology 86 $2,176,613
Facilities Condition AssessmentTransmountain Campus Condition Assessment
33Magellan Consulting, Inc.
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19044 17 Ea. 4 $6,002 No
The 2 X 2 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19045 2 Ea. 4 $732 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 19042 8 Ea. 2 $7,799 Yes
Mechanical system requires electrical retrofit 23748 1 LS 2 $49,868 No
The GFCI Electrical Receptacles Are Inadequate And More Are Needed 19056 2 Ea. 2 $979 Yes
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19046 140 Ea. 4 $75,237 No
The Incandescent Lighting Is Damaged And Should Be Replaced 19049 2 Ea. 4 $728 No
The Incandescent Lighting Is Damaged And Should Be Replaced 19047 6 Ea. 4 $2,182 No
The Incandescent Lighting Is Damaged And Should Be Replaced 19048 2 Ea. 4 $728 No
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Large Diameter Exhausts/Hoods Are Missing/Damaged And Require Replacement 19023 3 Ea. 2 $5,107 No
The 4 X 4 Exhausts/Hoods Are Missing/Damaged And Require Replacement 19024 1 Ea. 3 $5,354 No
Complete HVAC Systemwide Replacement 19032 7,506 SF 2 $105,487 No
The Air Handler HVAC Component Is Damaged And Requires Replacement 23829 20,000 CFM 2 $128,204 No
The 2 X 2 Exhausts/Hoods Are Missing/Damaged And Require Replacement 19025 4 Ea. 4 $9,084 No
Duct Register is Damaged And Should Be Replaced 19036 46 Ea. 5 $37,965 No
Duct Grill is Damaged And Should Be Replaced 19037 23 Ea. 5 $7,404 No
Duct Cleaning Required 19035 7,506 SF 5 $7,043 No
Sub Total for System 8 $305,649
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 18944 1,500 SF 3 $11,304 No
The Suspended Ceiling Grid is Damaged And Require Replacement 18934 3,500 SF 3 $28,219 No
Interior Doors Require Repainting 18941 11 Door 5 $586 No
The Gypboard Ceilings Are Damaged And Requires Repainting 18936 500 SF 5 $1,329 No
Interior Walls Require Repainting 18937 7,500 SF 5 $20,066 No
Interior Doors Require Replacement 18940 7 Door 3 $8,814 No
The Interior Door Hardware is Damaged and Requires Replacement 18942 18 Ea. 2 $18,335 No
The Carpet Flooring Is Damaged And Requires Replacement 18943 3,000 SF 3 $26,490 No
Restrooms require complete renovation 23828 1 LS 3 $127,400 No
Sub Total for System 9 $242,542
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Aluminum Storefront Exterior Door Is Damaged And Requires Replacement 18930 6 Door 2 $26,133 Yes
Exterior door hardware is damaged and should be replaced 18931 10 Door 2 $6,033 Yes
The Aluminum Window Is Damaged And Requires Replacement 18932 6 Ea. 2 $10,372 Yes
The Metal Exterior Door Is Damaged And Requires Replacement 18929 4 Door 2 $9,429 Yes
Sub Total for System 4 $51,968
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Multi-Ply Bitumen Roof System Is Damaged And Requires Replacement 19021 7,506 SF 1 $90,414 No
Sub Total for System 1 $90,414
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 3062 - Bookstore
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 19491 14,354 SF 2 $8,425 Yes
Fire Alarm Panel Should Be Replaced 19493 1 Ea. 1 $9,677 Yes
Security Alarm Motion Detector Is Missing And Needed 19492 4 Ea. 2 $4,617 No
Sub Total for System 3 $22,719
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Refrigerated Water Cooler is Damaged And Should Be Replaced 19481 2 Ea. 4 $8,731 No
The Custodial Mop Or Service Sink Is Damaged And Should Be Replaced 19479 1 Ea. 4 $3,948 No
Sanitary sewer piping requires replacement 23747 150 LF 3 $4,164 No
The Rest Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 19480 2 Ea. 4 $3,280 No
Sub Total for System 4 $20,122
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 3060 - Business Area 39 $987,021
Facilities Condition AssessmentTransmountain Campus Condition Assessment
34Magellan Consulting, Inc.
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Steel Window Is Damaged And Requires Replacement 18711 3 Ea. 2 $6,006 Yes
The Metal Exterior Door Is Damaged And Requires Replacement 18708 4 Door 2 $9,429 Yes
The Aluminum Storefront Exterior Door Is Damaged And Requires Replacement 18709 6 Door 2 $26,133 Yes
Exterior door hardware is damaged and should be replaced 18710 8 Door 2 $4,827 Yes
The Exterior Requires Painting 18707 2,000 SF Wall 5 $5,975 No
The Steel Window Is Damaged And Requires Replacement 18712 12 Ea. 2 $24,026 Yes
Sub Total for System 6 $76,396
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Metal Counter Flashing Is Loose Or Damaged And Should Be Repaired 18741 180 LF 2 $786 Yes
Metal Coping Lap Joints Have Lost Their Seal And Should Be Resealed 18730 20 Ea. 2 $602 Yes
Sealant At Pitch Pan Is Damaged And Should Be Repaired 18743 10 Ea. 2 $775 Yes
Metal Umbrella At Penetration Or Pitch Pan Is Missing And Is Needed 18744 10 Ea. 2 $2,366 Yes
Membrane Flashing At Parapet (>2') Is Damaged And Should Be Repaired 18729 10 LF 2 $302 Yes
Gas Line/Conduit On New Supports Is Unseated And Should Be Supported 18742 4 Ea. 2 $444 Yes
Metal Coping Is Damaged Or Loose And Should Be Repaired 18732 5 LF 2 $306 Yes
Membrane Flashings At Equipment Curbs Are Damaged And Should Be Repaired 18735 8 LF 2 $124 Yes
The Roof Operable Hatch Is Damaged And Requires Replacement 18722 1 Ea. 3 $6,725 No
Tapered Insulation Is Required To Eliminate Ponding When Re-Roofing 18728 200 SF 3 $786 No
Roof Curb To Match HVAC Unit Is Missing And Is Needed 18739 1 Ea. 4 $914 No
Curbs Have Been Abandoned And Should Be Removed 18740 1 Ea. 4 $493 No
The Roof Drains Are Clogged 18723 2 Ea. 2 $235 Yes
Strainers Are Missing And Needed 18724 1 Ea. 2 $804 Yes
Awning Or Canopy Roofing Decking Is Damaged 18721 5 SF 3 $388 No
The Roof Requires Cleaning 18748 2,000 SF 2 $1,478 Yes
Built Up Roofing (Bur) Membrane Has Holes That Should Be Repaired 18746 10 Ea. 2 $1,207 Yes
Built Up Roofing (Bur) Covering Has Blisters That Should Be Repaired 18745 70 Ea. 2 $8,964 Yes
The Multi-Ply Bitumen Roof System Is Damaged And Requires Replacement 18747 4,471 SF 1 $53,856 No
Exhaust Fan Curbs are too Low and Should be Raised and Reflashed (<8") 18737 4 Ea. 2 $5,576 No
Counter Flashing Is Damaged Or Loose And Should Be Repaired 18731 30 LF 2 $610 Yes
Coping Termination At End Wall Is Damaged And Should Be Repaired 18733 2 Ea. 2 $204 Yes
Sub Total for System 22 $87,944
Deficiency ID Qty UoM Priority Repair Cost WS&D
Roofing
Building: 3070 - Gymnasium Building
Public Address Is Inadequate And Should Be Replaced 19053 7,506 SF 1 $14,498 Yes
Sub Total for System 1 $14,498
TechnologyDeficiency ID Qty UoM Priority Repair Cost WS&D
Fire Alarm is Missing or Inadequate 19055 7,506 SF 1 $13,095 Yes
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 19051 7,506 SF 2 $4,404 Yes
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 19052 7 Ea. 2 $3,735 Yes
Security Alarm is Missing or Inadequate 19054 7,506 SF 2 $13,546 No
Sub Total for System 4 $34,780
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Custodial Mop Or Service Sink Is Damaged And Should Be Replaced 19038 1 Ea. 4 $3,948 No
The Class Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 19039 4 Ea. 4 $8,206 No
The Toilets Plumbing Fixtures Are Damaged And Should Be Replaced 19040 8 Ea. 3 $10,591 No
The Refrigerated Water Cooler is Damaged And Should Be Replaced 19041 2 Ea. 4 $8,731 No
Sub Total for System 4 $31,475
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The Incandescent Lighting Is Damaged And Should Be Replaced 19050 3 Ea. 4 $1,090 No
Sub Total for System 10 $145,345
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 3062 - Bookstore 41 $916,672
Facilities Condition AssessmentTransmountain Campus Condition Assessment
35Magellan Consulting, Inc.
3091 - Classroom Addition
Buildings with no reported deficiencies
The Fixed Shelving Storage Cabinets Require Replacement 18720 8 LF 4 $701 No
Sub Total for System 1 $701
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Fire Alarm Panel Should Be Replaced 18774 1 Ea. 1 $9,677 Yes
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 18773 9,171 SF 2 $5,382 Yes
Sub Total for System 2 $15,059
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Toilets Plumbing Fixtures Are Damaged And Should Be Replaced 18756 6 Ea. 3 $7,942 No
The Showers Plumbing Fixtures Are Damaged And Should Be Replaced 18757 20 Ea. 3 $17,286 No
Additional boiler required 23749 1 Ea. 2 $27,398 No
The Rest Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 18755 6 Ea. 4 $9,839 No
The Refrigerated Water Cooler is Damaged And Should Be Replaced 18758 2 Ea. 4 $8,731 No
Sub Total for System 5 $71,197
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The H.I.D. Lighting Is Damaged And Should Be Replaced 18768 12 Ea. 3 $7,031 No
The Power Service Is Inadequate And Should Be Upgraded 18771 225 Amps 3 $11,930 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 18760 6 Ea. 2 $5,849 Yes
The Electrical Receptacles Are Inadequate And More Are Needed 18775 20 Ea. 3 $8,867 No
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 18767 66 Ea. 4 $35,468 No
The Electrical Circuit Capacity Is Inadequate 18772 42 EACH 4 $39,663 No
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 18763 28 Ea. 4 $9,886 No
The 2 X 2 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 18765 1 Ea. 4 $366 No
The Canopy Lighting Is Damaged And Should Be Replaced 18759 8 Ea. 2 $14,109 Yes
The GFCI Electrical Receptacles Are Inadequate And More Are Needed 18776 2 Ea. 2 $979 Yes
Sub Total for System 10 $134,149
Deficiency ID Qty UoM Priority Repair Cost WS&D
Electrical
The Evaporative Cooling Unit Is Damaged And Requires Replacement 23695 5 Ea. 3 $45,351 No
The Large Diameter Exhausts/Hoods Are Missing/Damaged And Require Replacement 18726 8 Ea. 2 $13,619 No
The Roof Air Handler/Exhaust is Damaged And Requires Replacement 18749 112 TonAC 2 $121,219 No
Test And Balancing Required 18751 9,171 SF 3 $16,023 No
Duct Grill is Damaged And Should Be Replaced 18754 16 Ea. 5 $5,151 No
Duct Cleaning Required 18753 9,171 SF 5 $8,607 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 18752 9,171 SF 4 $20,551 No
Sub Total for System 7 $230,521
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Athletic Sport Flooring Is Damaged And Requires Replacement 20802 1,440 SF 3 $33,362 No
The Carpet Flooring Is Damaged And Requires Replacement 18718 480 SF 3 $4,239 No
Interior Doors Require Replacement 20886 20 Door 3 $25,185 No
Restrooms require complete renovation 23830 1 LS 3 $127,400 No
The Suspended Ceiling Grid is Damaged And Require Replacement 18715 4,000 SF 3 $32,250 No
Interior Walls Require Repainting 18716 9,171 SF 5 $24,535 No
Concrete Flooring Epoxy Requires Replacement 20801 230 SF 5 $451 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 18719 420 SF 3 $3,165 No
Sub Total for System 8 $250,589
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 3070 - Gymnasium Building 61 $866,555
Total for Campus 1,111 $17,261,820
Facilities Condition AssessmentTransmountain Campus Condition Assessment
36Magellan Consulting, Inc.
Supporting PhotosTransmountain Campus Condition Assessment
3010 - Exposed Wiring - Photo 6
3000 Interior Circulation (3) - Photo 2
3010 - Electrical Panel 2 - Photo 4
3010 - Exposed Wiring 2 - Photo 5
3000 Interior Circulation (2) - Photo 1
3010 - Air Handler Switch - Photo 3
Facilities Condition AssessmentTransmountain Campus Condition Assessment
37Magellan Consulting, Inc.
3010 Admin Area (3) - Photo 12
3010 Admin Area (10) - Photo 8
3010 Admin Area (13) - Photo 10
3010 Admin Area (2) - Photo 11
3010 Admin Area (1) - Photo 7
3010 Admin Area (12) - Photo 9
Facilities Condition AssessmentTransmountain Campus Condition Assessment
38Magellan Consulting, Inc.
3010 Admin Area (9) - Photo 18
3010 Admin Area (5) - Photo 14
3010 Admin Area (7) - Photo 16
3010 Admin Area (8) - Photo 17
3010 Admin Area (4) - Photo 13
3010 Admin Area (6) - Photo 15
Facilities Condition AssessmentTransmountain Campus Condition Assessment
39Magellan Consulting, Inc.
3020 LRC (16) - Photo 24
3020 LRC (11) - Photo 20
3020 LRC (14) - Photo 22
3020 LRC (15) - Photo 23
3020 LRC (1) - Photo 19
3020 LRC (13) - Photo 21
Facilities Condition AssessmentTransmountain Campus Condition Assessment
40Magellan Consulting, Inc.
3020 LRC (21) - Photo 30
3020 LRC (18) - Photo 26
3020 LRC (2) - Photo 28
3020 LRC (20) - Photo 29
3020 LRC (17) - Photo 25
3020 LRC (19) - Photo 27
Facilities Condition AssessmentTransmountain Campus Condition Assessment
41Magellan Consulting, Inc.
3020 LRC (3) - Photo 36
3020 LRC (23) - Photo 32
3020 LRC (25) - Photo 34
3020 LRC (26) - Photo 35
3020 LRC (22) - Photo 31
3020 LRC (24) - Photo 33
Facilities Condition AssessmentTransmountain Campus Condition Assessment
42Magellan Consulting, Inc.
3025 Liberal Arts Area (10) - Photo 42
3020 LRC (5) - Photo 38
3020 LRC (8) - Photo 40
3020 LRC (9) - Photo 41
3020 LRC (4) - Photo 37
3020 LRC (6) - Photo 39
Facilities Condition AssessmentTransmountain Campus Condition Assessment
43Magellan Consulting, Inc.
3025 Liberal Arts Area (3) - Photo 48
3025 Liberal Arts Area (12) - Photo 44
3025 Liberal Arts Area (14) - Photo 46
3025 Liberal Arts Area (2) - Photo 47
3025 Liberal Arts Area (11) - Photo 43
3025 Liberal Arts Area (13) - Photo 45
Facilities Condition AssessmentTransmountain Campus Condition Assessment
44Magellan Consulting, Inc.
3025 Liberal Arts Area (9) - Photo 54
3025 Liberal Arts Area (5) - Photo 50
3025 Liberal Arts Area (7) - Photo 52
3025 Liberal Arts Area (8) - Photo 53
3025 Liberal Arts Area (4) - Photo 49
3025 Liberal Arts Area (6) - Photo 51
Facilities Condition AssessmentTransmountain Campus Condition Assessment
45Magellan Consulting, Inc.
3030 Forum - Stage Lighting 3 - Photo 60
3030 Forum - Electrical Panel 2 - Photo 56
3030 Forum - Stage Lighting 1 - Photo 58
3030 Forum - Stage Lighting 2 - Photo 59
3030 Forum - Circuit Panel - Photo 55
3030 Forum - Electrical Panel - Photo 57
Facilities Condition AssessmentTransmountain Campus Condition Assessment
46Magellan Consulting, Inc.
3030 Forum (13) - Photo 66
3030 Forum - Stage Lighting 6 - Photo 62
3030 Forum (11) - Photo 64
3030 Forum (12) - Photo 65
3030 Forum - Stage Lighting 4 - Photo 61
3030 Forum (10) - Photo 63
Facilities Condition AssessmentTransmountain Campus Condition Assessment
47Magellan Consulting, Inc.
3030 Forum (19) - Photo 72
3030 Forum (15) - Photo 68
3030 Forum (17) - Photo 70
3030 Forum (18) - Photo 71
3030 Forum (14) - Photo 67
3030 Forum (16) - Photo 69
Facilities Condition AssessmentTransmountain Campus Condition Assessment
48Magellan Consulting, Inc.
3030 Forum (24) - Photo 78
3030 Forum (20) - Photo 74
3030 Forum (22) - Photo 76
3030 Forum (23) - Photo 77
3030 Forum (2) - Photo 73
3030 Forum (21) - Photo 75
Facilities Condition AssessmentTransmountain Campus Condition Assessment
49Magellan Consulting, Inc.
3030 Forum (7) - Photo 84
3030 Forum (26) - Photo 80
3030 Forum (5) - Photo 82
3030 Forum (6) - Photo 83
3030 Forum (25) - Photo 79
3030 Forum (4) - Photo 81
Facilities Condition AssessmentTransmountain Campus Condition Assessment
50Magellan Consulting, Inc.
3040 - 01 Humanities (4) - Photo 90
3030 Forum (9) - Photo 86
3040 - 01 Humanities (2) - Photo 88
3040 - 01 Humanities (3) - Photo 89
3030 Forum (8) - Photo 85
3040 - 01 Humanities (1) - Photo 87
Facilities Condition AssessmentTransmountain Campus Condition Assessment
51Magellan Consulting, Inc.
3040 - 02 Humanities (4) - Photo 96
3040 - 01 Humanities (7) - Photo 92
3040 - 02 Humanities (2) - Photo 94
3040 - 02 Humanities (3) - Photo 95
3040 - 01 Humanities (5) - Photo 91
3040 - 02 Humanities (1) - Photo 93
Facilities Condition AssessmentTransmountain Campus Condition Assessment
52Magellan Consulting, Inc.
3040 - 03 Humanities (11) - Photo 102
3040 - 02 Humanities (7) - Photo 98
3040 - 03 Humanities (1) - Photo 100
3040 - 03 Humanities (10) - Photo 101
3040 - 02 Humanities (6) - Photo 97
3040 - 02 Humanities (9) - Photo 99
Facilities Condition AssessmentTransmountain Campus Condition Assessment
53Magellan Consulting, Inc.
3040 - 03 Humanities (17) - Photo 108
3040 - 03 Humanities (13) - Photo 104
3040 - 03 Humanities (15) - Photo 106
3040 - 03 Humanities (16) - Photo 107
3040 - 03 Humanities (12) - Photo 103
3040 - 03 Humanities (14) - Photo 105
Facilities Condition AssessmentTransmountain Campus Condition Assessment
54Magellan Consulting, Inc.
3040 - 03 Humanities (22) - Photo 114
3040 - 03 Humanities (19) - Photo 110
3040 - 03 Humanities (20) - Photo 112
3040 - 03 Humanities (21) - Photo 113
3040 - 03 Humanities (18) - Photo 109
3040 - 03 Humanities (2) - Photo 111
Facilities Condition AssessmentTransmountain Campus Condition Assessment
55Magellan Consulting, Inc.
3040 - 03 Humanities (28) - Photo 120
3040 - 03 Humanities (24) - Photo 116
3040 - 03 Humanities (26) - Photo 118
3040 - 03 Humanities (27) - Photo 119
3040 - 03 Humanities (23) - Photo 115
3040 - 03 Humanities (25) - Photo 117
Facilities Condition AssessmentTransmountain Campus Condition Assessment
56Magellan Consulting, Inc.
3040 - 03 Humanities (33) - Photo 126
3040 - 03 Humanities (3) - Photo 122
3040 - 03 Humanities (31) - Photo 124
3040 - 03 Humanities (32) - Photo 125
3040 - 03 Humanities (29) - Photo 121
3040 - 03 Humanities (30) - Photo 123
Facilities Condition AssessmentTransmountain Campus Condition Assessment
57Magellan Consulting, Inc.
3040 - 03 Humanities (39) - Photo 132
3040 - 03 Humanities (35) - Photo 128
3040 - 03 Humanities (37) - Photo 130
3040 - 03 Humanities (38) - Photo 131
3040 - 03 Humanities (34) - Photo 127
3040 - 03 Humanities (36) - Photo 129
Facilities Condition AssessmentTransmountain Campus Condition Assessment
58Magellan Consulting, Inc.
3040 - 03 Humanities (44) - Photo 138
3040 - 03 Humanities (40) - Photo 134
3040 - 03 Humanities (42) - Photo 136
3040 - 03 Humanities (43) - Photo 137
3040 - 03 Humanities (4) - Photo 133
3040 - 03 Humanities (41) - Photo 135
Facilities Condition AssessmentTransmountain Campus Condition Assessment
59Magellan Consulting, Inc.
3040 - 03 Humanities (5) - Photo 144
3040 - 03 Humanities (46) - Photo 140
3040 - 03 Humanities (48) - Photo 142
3040 - 03 Humanities (49) - Photo 143
3040 - 03 Humanities (45) - Photo 139
3040 - 03 Humanities (47) - Photo 141
Facilities Condition AssessmentTransmountain Campus Condition Assessment
60Magellan Consulting, Inc.
3040 - 03 Humanities (55) - Photo 150
3040 - 03 Humanities (51) - Photo 146
3040 - 03 Humanities (53) - Photo 148
3040 - 03 Humanities (54) - Photo 149
3040 - 03 Humanities (50) - Photo 145
3040 - 03 Humanities (52) - Photo 147
Facilities Condition AssessmentTransmountain Campus Condition Assessment
61Magellan Consulting, Inc.
3040 - 04 Humanities (2) - Photo 156
3040 - 03 Humanities (7) - Photo 152
3040 - 03 Humanities (9) - Photo 154
3040 - 04 Humanities (1) - Photo 155
3040 - 03 Humanities (56) - Photo 151
3040 - 03 Humanities (8) - Photo 153
Facilities Condition AssessmentTransmountain Campus Condition Assessment
62Magellan Consulting, Inc.
3040 - 05 Humanities (6) - Photo 162
3040 - 04 Humanities (4) - Photo 158
3040 - 05 Humanities (4) - Photo 160
3040 - 05 Humanities (5) - Photo 161
3040 - 04 Humanities (3) - Photo 157
3040 - 05 Humanities (2) - Photo 159
Facilities Condition AssessmentTransmountain Campus Condition Assessment
63Magellan Consulting, Inc.
3040 - 08 Humanities (2) - Photo 168
3040 - 06 Humanities (2) - Photo 164
3040 - 06 Humanities (4) - Photo 166
3040 - 07 Humanities (1) - Photo 167
3040 - 05 Humanities (7) - Photo 163
3040 - 06 Humanities (3) - Photo 165
Facilities Condition AssessmentTransmountain Campus Condition Assessment
64Magellan Consulting, Inc.
3040 - 11 Humanities (2) - Photo 174
3040 - 09 Humanities (3) - Photo 170
3040 - 10 Humanities (2) - Photo 172
3040 - 10 Humanities (3) - Photo 173
3040 - 09 Humanities (2) - Photo 169
3040 - 09 Humanities (4) - Photo 171
Facilities Condition AssessmentTransmountain Campus Condition Assessment
65Magellan Consulting, Inc.
3040 - 15 Humanities (2) - Photo 180
3040 - 13 Humanities (2) - Photo 176
3040 - 13 Humanities (4) - Photo 178
3040 - 14 Humanities (2) - Photo 179
3040 - 12 Humanities (2) - Photo 175
3040 - 13 Humanities (3) - Photo 177
Facilities Condition AssessmentTransmountain Campus Condition Assessment
66Magellan Consulting, Inc.
3050 Science and Tech (1) - Photo 186
3040 - 17 Humanities (1) - Outlet on Roof - Photo 182
3040 - 17 Humanities (4) - Photo 184
3040 - 17 Humanities (5) - Photo 185
3040 - 16 Humanities (2) - Photo 181
3040 - 17 Humanities (2) - Circuit Board - Photo 183
Facilities Condition AssessmentTransmountain Campus Condition Assessment
67Magellan Consulting, Inc.
3050 Science and Tech (15) - Photo 192
3050 Science and Tech (11) - Photo 188
3050 Science and Tech (13) - Photo 190
3050 Science and Tech (14) - Photo 191
3050 Science and Tech (10) - Photo 187
3050 Science and Tech (12) - Photo 189
Facilities Condition AssessmentTransmountain Campus Condition Assessment
68Magellan Consulting, Inc.
3050 Science and Tech (20) - Photo 198
3050 Science and Tech (17) - Photo 194
3050 Science and Tech (19) - Photo 196
3050 Science and Tech (2) - Photo 197
3050 Science and Tech (16) - Photo 193
3050 Science and Tech (18) - Photo 195
Facilities Condition AssessmentTransmountain Campus Condition Assessment
69Magellan Consulting, Inc.
3050 Science and Tech (27) - Photo 204
3050 Science and Tech (22) - Photo 200
3050 Science and Tech (25) - Photo 202
3050 Science and Tech (26) - Photo 203
3050 Science and Tech (21) - Photo 199
3050 Science and Tech (24) - Photo 201
Facilities Condition AssessmentTransmountain Campus Condition Assessment
70Magellan Consulting, Inc.
3050 Science and Tech (32) - Photo 210
3050 Science and Tech (29) - Photo 206
3050 Science and Tech (30) - Photo 208
3050 Science and Tech (31) - Photo 209
3050 Science and Tech (28) - Photo 205
3050 Science and Tech (3) - Photo 207
Facilities Condition AssessmentTransmountain Campus Condition Assessment
71Magellan Consulting, Inc.
3050 Science and Tech (8) - Photo 216
3050 Science and Tech (4) - Photo 212
3050 Science and Tech (6) - Photo 214
3050 Science and Tech (7) - Photo 215
3050 Science and Tech (33) - Photo 211
3050 Science and Tech (5) - Photo 213
Facilities Condition AssessmentTransmountain Campus Condition Assessment
72Magellan Consulting, Inc.
3060 Business Area (13) - Photo 222
3060 Business Area (1) - Photo 218
3060 Business Area (11) - Photo 220
3060 Business Area (12) - Photo 221
3050 Science and Tech (9) - Photo 217
3060 Business Area (10) - Photo 219
Facilities Condition AssessmentTransmountain Campus Condition Assessment
73Magellan Consulting, Inc.
3060 Business Area (19) - Photo 228
3060 Business Area (15) - Photo 224
3060 Business Area (17) - Photo 226
3060 Business Area (18) - Photo 227
3060 Business Area (14) - Photo 223
3060 Business Area (16) - Photo 225
Facilities Condition AssessmentTransmountain Campus Condition Assessment
74Magellan Consulting, Inc.
3060 Business Area (25) - Photo 234
3060 Business Area (21) - Photo 230
3060 Business Area (23) - Photo 232
3060 Business Area (24) - Photo 233
3060 Business Area (2) - Photo 229
3060 Business Area (22) - Photo 231
Facilities Condition AssessmentTransmountain Campus Condition Assessment
75Magellan Consulting, Inc.
3060 Business Area (9) - Photo 240
3060 Business Area (4) - Photo 236
3060 Business Area (7) - Photo 238
3060 Business Area (8) - Photo 239
3060 Business Area (3) - Photo 235
3060 Business Area (6) - Photo 237
Facilities Condition AssessmentTransmountain Campus Condition Assessment
76Magellan Consulting, Inc.
3062 Bookstore Area (6) - Photo 246
3062 Bookstore Area (2) - Photo 242
3062 Bookstore Area (4) - Photo 244
3062 Bookstore Area (5) - Photo 245
3062 Bookstore Area (10) - Photo 241
3062 Bookstore Area (3) - Photo 243
Facilities Condition AssessmentTransmountain Campus Condition Assessment
77Magellan Consulting, Inc.
3070 Gymnasium (1) - Photo 252
3062 Bookstore Area (9) - Photo 248
3070 Gymnasium - Air Handlers & Evap Coolers 2 - Photo 250
3070 Gymnasium - Air Handlers & Evap Coolers - Photo 251
3062 Bookstore Area (7) - Photo 247
3066 I.S.C. - Photo 249
Facilities Condition AssessmentTransmountain Campus Condition Assessment
78Magellan Consulting, Inc.
3070 Gymnasium (3) - Photo 258
3070 Gymnasium (12) - Photo 254
3070 Gymnasium (14) - Photo 256
3070 Gymnasium (2) - Photo 257
3070 Gymnasium (10) - Photo 253
3070 Gymnasium (13) - Photo 255
Facilities Condition AssessmentTransmountain Campus Condition Assessment
79Magellan Consulting, Inc.
3070 Gymnasium (9) - Photo 264
3070 Gymnasium (7) - Photo 262
3070 Gymnasium (5) - Photo 260
3070 Gymnasium (8) - Photo 263
3070 Gymnasium (6) - Photo 261
3070 Gymnasium (4) - Photo 259
Appendix H –
Valle Verde Campus
Condition Assessment Report
Facilities Condition AssessmentValle Verde Campus Condition Assessment
1Magellan Consulting, Inc.
Valle Verde Campus Condition Assessment
2030-20 Americana Lang. Vill. - Bldg. 20 768 1989 $61,944 43.95% $80.66 $2,832
2030-19 Americana Lang. Vill. - Bldg. 19 768 1989 $55,040 48.10% $71.67 $15,859
2030-18 Americana Lang. Vill. - Bldg. 18 768 1989 $60,755 44.79% $79.11 $5,259
2030-23 Americana Lang. Vill. - Bldg. 23 1,886 1989 $126,399 37.37% $67.02 $8,874
2030-22 Americana Lang. Vill. - Bldg. 22 768 1989 $61,574 43.85% $80.17 $3,062
2030-21 Americana Lang. Vill. - Bldg. 21 768 1989 $62,137 44.79% $80.91 $3,876
2030-14 Americana Lang. Vill. - Bldg. 14 768 1989 $66,213 46.69% $86.22 $2,603
2030-13 Americana Lang. Vill. - Bldg. 13 758 1989 $58,458 41.95% $77.12 $2,569
2030-12 Americana Lang. Vill. - Bldg. 12 758 1989 $55,175 38.48% $72.79 $803
2030-17 Americana Lang. Vill. - Bldg. 17 768 1989 $68,070 46.18% $88.63 $0
2030-16 Americana Lang. Vill. - Bldg. 16 768 1989 $61,440 43.45% $80.00 $2,603
2030-15 Americana Lang. Vill. - Bldg. 15 758 1989 $55,277 38.00% $72.92 $0
2030-25 Americana Lang. Vill. - Bldg. 25 758 1989 $50,227 38.85% $66.26 $6,289
2030-24 Americana Lang. Vill. - Bldg. 24 730 1989 $57,528 43.79% $78.81 $3,821
2050 Math and Science Building 72,948 1978 $3,484,836 25.63% $47.77 $102,977
2040 Humanities Building 87,477 1978 $5,156,793 32.14% $58.95 $239,471
2070 Gymnasium 22,799 1978 $2,302,855 55.65% $101.01 $132,167
2019-02 ATC Complex 2 21,437 1991 $684,891 18.86% $31.95 $91,090
2018 Student Services Center 44,437 1990 $3,001,755 41.45% $67.55 $533,109
2030-01 Americana Lang. Vill. - Bldg. 1 768 1989 $64,963 44.07% $84.59 $0
2010 Administration Building 18,232 1976 $2,961,613 87.61% $162.44 $103,930
2019-01 ATC Complex 1 31,130 1991 $2,565,767 45.51% $82.42 $153,440
2025 Building B 61,317 1997 $1,203,235 14.89% $19.62 $548,836
2020 Learning Resource Center 91,294 1978 $6,076,436 36.38% $66.56 $297,329
2019-03 ATC Complex 3 4,608 1991 $0 .00% $0.00 $0
2030-07 Americana Lang. Vill. - Bldg. 7 758 1989 $59,498 40.90% $78.49 $0
2030-06 Americana Lang. Vill. - Bldg. 6 1,526 1989 $119,827 41.47% $78.52 $1,618
2030-09 Americana Lang. Vill. - Bldg. 9 758 1989 $61,769 44.36% $81.49 $2,767
2030-11 Americana Lang. Vill. - Bldg. 11 758 1989 $59,168 40.67% $78.06 $0
2030-10 Americana Lang. Vill. - Bldg. 10 762 1989 $52,074 36.16% $68.34 $808
2030-05 Americana Lang. Vill. - Bldg. 5 758 1989 $52,068 36.34% $68.69 $803
2019-04B ATC Athletic Portable B 768 1989 $24,794 16.82% $32.28 $0
2019-04A ATC Athletic Portable A 768 1989 $37,685 25.57% $49.07 $0
2030-02 Americana Lang. Vill. - Bldg. 2 758 1989 $59,510 43.03% $78.51 $3,091
2030-04 Americana Lang. Vill. - Bldg. 4 768 1989 $73,470 50.40% $95.66 $814
2030-03 Americana Lang. Vill. - Bldg. 3 768 1989 $66,745 45.84% $86.91 $814
Facility Condition by Building
Number Building Name Gross Sq Ft Built DateFacility Condition
Cost FCICost Per
Square FootFuture Life Cycle
Cost (Yr 1-5)
The Valle Verde Campus Facility located at 919 Hunter in El Paso, Texas, was built in 1948. It comprises approximately 503,444 gross square feet.
Summary of Findings
The total current deficiencies for this site, in 2008 construction cost dollars, are estimated at $35,214,036.
Facilities Condition AssessmentValle Verde Campus Condition Assessment
2Magellan Consulting, Inc.
2090 Physical Plant 10,892 1978 $1,818,446 96.05% $166.95 $189,479
2060 Day Care Center 6,857 1948 $552,295 45.81% $80.54 $50,580
2030-32 Americana Lang. Vill. - Bldg. 32 768 1989 $59,576 56.99% $77.57 $24,430
2080-03 ATC Fire Tech. Portable 3 1,536 2006 $24,574 15.53% $16.00 $21,200
2080-02 ATC Fire Tech. Portable 2 1,536 2006 $23,966 15.87% $15.60 $22,828
2080-01 ATC Fire Tech. Portable 1 1,536 2006 $36,578 20.15% $23.81 $22,828
2030-28 Americana Lang. Vill. - Bldg. 28 768 1989 $57,112 41.38% $74.36 $3,876
Site 0 0 $3,424,701 .00% $0.00 $106,000
2030-29 Americana Lang. Vill. - Bldg. 29 724 1989 $57,685 43.06% $79.68 $2,151
2030-31 Americana Lang. Vill. - Bldg. 31 720 1989 $46,146 36.17% $64.09 $3,835
2030-30 Americana Lang. Vill. - Bldg. 30 718 1989 $42,968 31.78% $59.84 $822
Totals 503,444 $35,214,036 39.26% $69.95 $2,719,546
Facility Condition by Building
Number Building Name Gross Sq Ft Built DateFacility Condition
Cost FCICost Per
Square FootFuture Life Cycle
Cost (Yr 1-5)
Cross Tab of Current Deficiencies
The following chart summarizes the current deficiencies for this site in a cross tab that shows the buildings systems down the left and the priority of the deficiency across the top. This listing includes current deficiencies including deferred maintenance, functional deficiencies, code compliance, Americans with Disabilities Act, and Life Cycle Capital Renewal categories.
Electrical $524 $4,185,558 $1,007,506 $2,758,952 - $7,952,541
Mechanical - $4,179,766 $1,707,293 $800,997 $760,196 $7,448,251
Interior - $147,691 $5,589,344 $1,388,862 $1,146,433 $8,272,329
Plumbing $882,727 $28,288 $1,464,743 $373,906 - $2,749,665
Conveyances - $32,711 $10,865 $484,544 - $528,120
Technology $60,131 - - - - $60,131
Fire and Life Safety $989,818 $716,006 - - - $1,705,824
Site - $1,161,406 $16,653 $777,504 $91,841 $2,047,403
Specialties - - - $278,309 - $278,309
Other - - - - - $0
Exterior - $1,129,474 $220,986 $24,909 $15,155 $1,390,524
Structural - $27,300 - - - $27,300
Roofing $1,398,386 $1,257,440 $20,895 $76,813 $104 $2,753,638
Total $3,331,586 $12,865,639 $10,038,286 $6,964,796 $2,013,728 $35,214,036
Facility Condition - System by PriorityPriority
System 1 2 3 4 5 Total
Facilities Condition AssessmentValle Verde Campus Condition Assessment
3Magellan Consulting, Inc.
Portable Buildings - - - - - $0
New Construction - - - - - $0
Hazardous Material - - - - - $0
Functional Deficiency $60,131 $539,810 $261,654 $674,650 $105,982 $1,642,228
Energy Efficiency $11,129 $8,217,145 $1,676,617 $2,758,952 - $12,663,843
Educational Adequacy - - - - - $0
Deferred Maintenance $21,476 $967,770 $971,152 $732,539 $1,492,713 $4,185,650
Code Compliance $1,686,432 $2,308 $22,981 - $58,848 $1,770,569
Capital Renewal $1,552,418 $2,990,178 $6,182,860 $2,798,654 $160,466 $13,684,576
ADA Compliance - $148,428 $923,022 - $195,719 $1,267,169
Total $3,331,586 $12,865,639 $10,038,286 $6,964,796 $2,013,728 $35,214,036
Facility Condition - Category by PriorityPriority
Category 1 2 3 4 5 Total
All deficiencies have been further categorized according to the type of deficiency observed. Capital Renewal items include those that are included in the life cycle forecast and are items that have reached or exceeded their useful life. Americans with Disabilities Act deficiencies are associated with accessibility compliance concerns. Code Compliance includes items that are a building code related deficiency. Deferred Maintenance items are those items that have broken or are in need of repair prior to reaching the end of life term. A Functional Deficiency is one that is presently not in place, or is not functioning correctly, and should be added to the building.
Life Cycle Capital Renewal Forecast
As part of the assessment process, this facility was analyzed according to twelve major building systems. Each system has subsystems, and each subsystem is further distinguished by type. For each line item, the original year, or most recent replacement year if applicable, was identified. Then, the historical life was compared to a model of expected life for each subsystem type. The remaining year was then forecasted by subtracting the expected life from the life used, and further adjusted for the apparent maintenance quality of the subsystem. In some cases, the calculation was overridden if the assessor’s judgment suggested a shorter or longer than expected life expectancy.
Once each subsystem was analyzed, they were combined to provide a 10-year life cycle capital renewal forecast for the building. The following chart shows all deficiencies and the subsequent year’s capital renewal projections for all systems where a component is expected to reach the end of its useful life and require capital dollars for replacement.
The chart on the following page shows the forecast in thousands ($000s) for the next ten years.
Facilities Condition AssessmentValle Verde Campus Condition Assessment
4Magellan Consulting, Inc.
Fire and Life Safety 1,706 0 0 68 80 0 127 0 3 24 770 $1,071 $2.52
Plumbing 2,750 0 0 0 2 73 3 0 8 0 9 $96 $0.22
Electrical 7,953 0 0 30 6 64 45 0 2,017 0 540 $2,702 $6.35
Technology 60 0 0 54 0 428 241 0 0 4 66 $793 $1.86
Other 0 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Specialties 278 0 37 0 0 5 0 0 0 0 0 $42 $0.10
Conveyances 528 0 0 80 0 0 0 0 0 0 0 $80 $0.19
Mechanical 7,448 0 0 0 0 511 11 0 2,438 0 353 $3,312 $7.78
Roofing 2,754 0 0 243 726 0 0 0 602 0 0 $1,571 $3.69
Site 2,047 0 0 0 106 0 2 6 99 0 0 $213 $0.50
Structural 27 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Interior 8,272 0 45 0 27 31 1,168 36 137 270 463 $2,177 $5.12
Exterior 1,391 11 1 4 42 46 133 3 0 7 42 $289 $0.68
Total 35,214 11 84 479 988 1,158 1,730 44 5,304 305 2,242 $12,346 $29.01
Life Cycle Capital Renewal Projections ($000s)
SystemCurrent
DeficienciesYear 1 2008
Year 2 2009
Year 3 2010
Year 4 2011
Year 5 2012
Year 6 2013
Year 7 2014
Year 8 2015
Year 9 2016
Year 10 2017 Total $/GSF
Capital Renewal Forecast
Facilities Condition AssessmentValle Verde Campus Condition Assessment
5Magellan Consulting, Inc.
Facility Condition Index (FCI)
The Facility Condition Index (FCI) is used throughout the facility condition assessment industry as a general indicator of a building’s health. The FCI is calculated by dividing the Facility Condition Cost plus five years of projected Life Cycle Capital Renewal Costs by the Replacement Value. Costs associated with new construction are not included in the FCI calculation. As a rule of thumb, an FCI below 10% is considered good. An FCI above 65% would suggest that the building is a candidate for replacement.
The Valle Verde Campus facility has an overall FCI of 39.26%
Valle Verde Campus Condition Assessment
Assessment Findings
The total current cost for all building deficiencies is $35,214,036. There are $3,424,701 in deficiencies at the site level that are included in the FCI calculation. The five year capital renewal cost was $2,719,546. The cost estimates were derived using a detailed listing of all noted deficiencies in the building. The cost to repair these deficiencies was then estimated using the cost data adjusted to El Paso, Texas (78% of national average).
The Replacement Value represents the estimated cost of replacing the current building with another building of like size, based on today’s estimated cost of construction in the El Paso, Texas area. The replacement cost for this facility is estimated to be $96,621,027.
The following pages provide a listing of all deficiencies and their associated cost for the site and building, followed by photos taken during the assessment.
Facilities Condition AssessmentValle Verde Campus Condition Assessment
6Magellan Consulting, Inc.
The Pole Lighting Is Damaged And Should Be Replaced 19164 31 Ea. 2 $278,788 Yes
The Pole Lighting Is Damaged And Should Be Replaced 18999 15 Ea. 2 $134,898 Yes
The Pole Lighting Is Damaged And Should Be Replaced 18901 8 Ea. 2 $71,945 Yes
The Ground Mounted Lighting Is Damaged And Should Be Replaced 22937 3 Ea. 2 $4,568 Yes
The Ground Mounted Lighting Is Damaged And Should Be Replaced 22936 1 Ea. 2 $1,523 Yes
The Pole Lighting Is Damaged And Should Be Replaced 18860 4 Ea. 2 $35,972 Yes
The Pole Lighting Is Damaged And Should Be Replaced 18780 25 Ea. 2 $224,830 Yes
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Concrete Flooring Is Damaged And Requires Replacement 23786 50 SF 4 $246 No
Sub Total for System 1 $246
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Covered shade structure required 23770 1 Ea. 4 $72,800 No
Sub Total for System 1 $72,800
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Paving Requires Restriping 23092 74 CAR 5 $13,361 No
Paving Requires Restriping 23091 25 CAR 5 $4,514 No
Site Signage Is Damaged And Requires Replacement 20301 1 Ea. 5 $455 No
Site Signage Is Damaged And Requires Replacement 20511 4 Ea. 5 $1,820 No
Site Signage Is Damaged And Requires Replacement 20406 2 Ea. 5 $910 No
Paving Requires Restriping 23090 26 CAR 5 $4,694 No
Fencing Is Damaged And Should Be Replaced (Ornamental Fence) 22747 285 LF 2 $28,703 Yes
Concrete Walks Are Damaged And Require Replacement 22756 30 SF 2 $411 Yes
Concrete Walks Are Damaged And Require Replacement 22755 980 SF 2 $13,466 Yes
Handrails missing or not compliant. 23660 10 LF 2 $737 Yes
Site Drainage is Inadequate and Requires Regrading 22709 600 SF 2 $164 No
Site Drainage is Inadequate and Requires Regrading 22708 10,000 SF 2 $2,737 No
Site Drainage is Inadequate and Requires Regrading 22707 10,000 SF 2 $2,737 No
Concrete Walks Are Damaged And Require Replacement 22754 15 SF 2 $206 Yes
Asphalt Paving Is Damaged And Requires Replacement 22750 23 CAR 2 $58,577 No
Asphalt Paving Is Damaged And Requires Replacement 22749 400 CAR 2 $1,018,712 No
Asphalt Paving Is Damaged And Requires Replacement 22748 7 CAR 2 $17,827 No
Concrete Walks Are Damaged And Require Replacement 19114 600 SF 2 $8,245 Yes
Concrete Walks Are Damaged And Require Replacement 22753 200 SF 2 $2,748 Yes
Concrete Walks Are Damaged And Require Replacement 20512 50 SF 2 $686 Yes
Concrete Walks Are Damaged And Require Replacement 20407 75 SF 2 $1,030 Yes
Site Drainage system requires replacement 23086 210 LF 2 $4,419 No
Dumpsters Are Damaged And Require Replacement 19161 4 Ea. 5 $46,951 No
Site Signage Is Damaged And Requires Replacement 22758 3 Ea. 4 $1,365 No
Site Signage Is Damaged And Requires Replacement 22757 5 Ea. 4 $2,275 No
Paving Requires Restriping 19160 20 CAR 5 $3,611 No
Paving Requires Restriping 23089 35 CAR 5 $6,319 No
Paving Requires Restriping 23088 35 CAR 5 $6,319 No
Paving Requires Restriping 23087 16 CAR 5 $2,888 No
Asphalt Paving Is Damaged And Requires Replacement 18998 125 CAR 4 $318,347 No
Asphalt Paving Is Damaged And Requires Replacement 19159 20 CAR 4 $50,936 No
Fencing Is Damaged And Should Be Replaced (8' Chain Link Fence) 22746 400 LF 3 $13,308 No
Tree Replacement Required 22745 2 Ea. 3 $3,345 No
Site Drainage is Inadequate and Requires Regrading 19157 1,780 SF 4 $488 No
Site Drainage is Inadequate and Requires Regrading 20302 600 SF 4 $164 No
Bench is missing and is needed 23769 10 Ea. 4 $7,595 No
Sub Total for System 36 $1,651,069
SiteDeficiency ID Qty UoM Priority Repair Cost WS&D
Site Level Deficiencies
Facilities Condition AssessmentValle Verde Campus Condition Assessment
7Magellan Consulting, Inc.
The Ceramic Tile Flooring Is Damaged And Requires Replacement 22921 3,200 SF 3 $51,049 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 22900 400 SF 3 $3,014 No
The Carpet Flooring Is Damaged And Requires Replacement 22889 14,632 SF 3 $129,205 No
Interior Doors Require Repainting 22881 49 Door 3 $2,608 No
Interior Doors Require Replacement 22888 20 Door 3 $25,185 No
Interior Toilet Partition Require Repair Or Replacement 23693 16 Ea. 4 $38,724 No
Directional / wayfinding signage missing or not accessible. 23780 75 Ea. 5 $9,460 No
Interior Walls Require Repainting 22873 9,000 SF 4 $24,079 No
The Suspended Ceiling Grid is Damaged And Require Replacement 23109 18,232 SF 4 $146,998 No
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Aluminum Storefront Exterior Door Is Damaged And Requires Replacement 22801 4 Door 2 $17,423 Yes
Exterior door hardware is damaged and should be replaced 23564 4 Door 2 $2,413 Yes
The Steel Window Is Damaged And Requires Replacement 22826 36 Ea. 2 $72,079 Yes
The Steel Window Is Damaged And Requires Replacement 22827 40 Ea. 2 $80,087 Yes
Sub Total for System 4 $172,003
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Minor Structural Condition Exists 23808 1 Job 2 $27,300 No
Sub Total for System 1 $27,300
StructuralDeficiency ID Qty UoM Priority Repair Cost WS&D
Sealant At Penetration Boot Is Damaged And Should Be Repaired 23384 1 Ea. 2 $293 Yes
Overflow Drain And Piping Is Missing And Is Needed 23214 4 Ea. 2 $5,005 No
Tapered Insulation Is Required To Eliminate Ponding When Re-Roofing 23393 100 SF 2 $524 No
The Roof Requires Cleaning 23332 200 SF 2 $1,065 Yes
The Multi-Ply Bitumen Roof Coating Requires Repair 22712 200 SF 2 $1,747 Yes
HVAC Curbs are too Low and Should be Raised and Reflashed (<8") 23231 1 Ea. 2 $1,383 No
Built Up Roofing (Bur) Lap Seams Are Open Or Deteriorated 23331 25 LF 2 $1,238 Yes
Built Up Roofing (Bur) Covering Has Blisters That Should Be Repaired 23324 12 Ea. 2 $1,536 Yes
Membrane Flashing At Parapet (>2') Is Damaged And Should Be Repaired 23416 100 LF 2 $393 Yes
Membrane Flashings At Penetration Are Damaged And Should Be Repaired 23374 1 Ea. 2 $104 Yes
Metal Umbrella At Penetration Or Pitch Pan Is Missing And Is Needed 23370 1 Ea. 2 $237 Yes
Membrane Flashings At Drain Is Damaged And Should Be Repaired 23211 4 Ea. 2 $588 Yes
Sub Total for System 12 $14,112
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2010 - Administration Building
Exterior Signage is missing and is needed 23784 30 Ea. 4 $3,784 No
Sub Total for System 1 $3,784
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
The Pole Lighting Is Damaged And Should Be Replaced 22927 10 Ea. 2 $89,932 Yes
The Pole Lighting Is Damaged And Should Be Replaced 22929 3 Ea. 2 $26,980 Yes
The Pole Lighting Is Damaged And Should Be Replaced 22930 7 Ea. 2 $62,952 Yes
The Pole Lighting Is Damaged And Should Be Replaced 22926 10 Ea. 2 $89,932 Yes
The Pole Lighting Is Damaged And Should Be Replaced 20470 1 Ea. 2 $8,993 Yes
The Pole Lighting Is Damaged And Should Be Replaced 20530 1 Ea. 2 $8,993 Yes
The Pole Lighting Is Damaged And Should Be Replaced 22925 1 Ea. 2 $8,993 Yes
The Pole Lighting Is Damaged And Should Be Replaced 22935 11 Ea. 2 $98,924 Yes
The Pole Lighting Is Damaged And Should Be Replaced 20377 1 Ea. 2 $8,993 Yes
The Pole Lighting Is Damaged And Should Be Replaced 20291 1 Ea. 2 $8,993 Yes
The Pole Lighting Is Damaged And Should Be Replaced 22934 1 Ea. 2 $8,993 Yes
The Pole Lighting Is Damaged And Should Be Replaced 22931 4 Ea. 2 $35,972 Yes
The Pole Lighting Is Damaged And Should Be Replaced 22932 14 Ea. 2 $125,904 Yes
The Pole Lighting Is Damaged And Should Be Replaced 22933 40 Ea. 2 $359,727 Yes
Sub Total for System 21 $1,696,802
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for School and Site Level 60 $3,424,701
Facilities Condition AssessmentValle Verde Campus Condition Assessment
8Magellan Consulting, Inc.
The Base Storage Cabinets Require Replacement 23077 72 LF 4 $20,464 No
Sub Total for System 1 $20,464
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Elevator Electrical System Should Be Cleaned And Inspected 22996 2 Stop 2 $8,343 Yes
Elevator Cab And Or Controls Are Damaged Or Missing And Require Repair 22742 1 Ea. 2 $24,368 Yes
Elevator Control/Relay Is Damaged And Should Be Replaced 22997 2 Stop 3 $10,865 No
Elevator Is Missing And Needed 23771 4 FLOOR 4 $215,353 No
Sub Total for System 4 $258,930
ConveyancesDeficiency ID Qty UoM Priority Repair Cost WS&D
Fire Alarm Panel Should Be Replaced 22993 2 Ea. 1 $19,354 Yes
Fire Alarm Horn/Strobe Is Damaged And Should Be Replaced 22732 18 Ea. 1 $8,765 Yes
Fire Alarm Heat Detector Is Damaged And Should Be Replaced 23543 18 Ea. 1 $8,347 Yes
Fire Alarm Smoke Detector Is Damaged And Should Be Replaced 23546 18 Ea. 1 $8,905 Yes
Fire Alarm Actuator Is Damaged And Should Be Replaced 23536 18 Ea. 1 $3,771 Yes
Emergency Lighting Is Inadequate Or Not Present And Should Be Installed 23609 18,232 SF 2 $27,216 Yes
Fire Alarm Strobe Is Damaged And Should Be Replaced 22741 18 Ea. 1 $11,768 Yes
Sub Total for System 7 $88,126
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
Sanitary sewer piping requires replacement 23711 17,902 SF 3 $97,745 No
Floor drain requires replacement 23802 2 Ea. 3 $2,541 No
Install Fire Sprinklers 23447 18,232 SF 1 $139,660 No
The Restroom is Not ADA Compliant 23756 8 Ea. 3 $206,929 No
The Class Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 23132 3 Ea. 4 $6,155 No
The Restroom is Not ADA Compliant 23790 4 Ea. 3 $103,465 No
Sub Total for System 6 $556,494
Deficiency ID Qty UoM Priority Repair Cost WS&D
Plumbing
The GFCI Electrical Receptacles Are Inadequate And More Are Needed 23148 10 Ea. 2 $4,899 Yes
The Panelboard Is Damaged And Should Be Replaced 23078 4 Amps 2 $122 Yes
The Electrical Circuit Capacity Is Inadequate 23446 168 EACH 2 $158,657 No
The Electrical Transformer Is Damaged And Should Be Replaced 23710 220 KVA 2 $39,723 No
The Power Service Is Inadequate And Should Be Upgraded 23151 1,000 Amps 2 $43,047 No
The Electrical Receptacles Are Inadequate And More Are Needed 23709 140 Ea. 3 $62,064 No
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 22968 200 Ea. 3 $107,482 No
The 2 X 2 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 22961 80 Ea. 3 $29,257 No
Sub Total for System 8 $445,250
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Grill is Damaged And Should Be Replaced 23595 50 Ea. 3 $16,094 No
Duct Grill is Damaged And Should Be Replaced 23596 50 Ea. 3 $16,094 No
Duct Register is Damaged And Should Be Replaced 23024 60 Ea. 3 $49,520 No
Duct Cleaning Required 23007 18,232 SF 3 $17,110 No
Exhaust hoods and fans require replacement 23841 1 LS 2 $500,500 No
The Package Unit HVAC Component Is Damaged And Requires Replacement 23838 30 TonAC 2 $63,878 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 23046 18,232 SF 3 $40,855 No
Computer room lacks independent AC. 23839 2 Ea. 4 $21,840 No
Computer room lacks independent AC. 23840 2 Ea. 4 $41,860 No
Exhaust Fan Ventilation Is Missing And Should Be Installed 23842 1 Ea. 5 $54,600 No
Exhaust Fan Ventilation Is Damaged And Should Be Replaced 23129 8 Ea. 3 $15,483 No
Test And Balancing Required 23167 18,232 SF 3 $31,855 No
The Air Handler HVAC Component Is Damaged And Requires Replacement 23054 1,500 CFM 3 $8,640 No
Sub Total for System 13 $878,330
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Interior Door Hardware is Damaged and Requires Replacement 23399 69 Door 5 $70,281 No
Sub Total for System 10 $500,604
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Facilities Condition AssessmentValle Verde Campus Condition Assessment
9Magellan Consulting, Inc.
The GFCI Electrical Receptacles Are Inadequate And More Are Needed 23146 4 Ea. 2 $1,960 Yes
The Mounted Building Lighting Is Damaged And Should Be Replaced 22944 8 Ea. 2 $7,799 Yes
The Electrical Transformer Is Damaged And Should Be Replaced 23713 100 KVA 2 $17,454 No
The Canopy Lighting Is Damaged And Should Be Replaced 22939 6 Ea. 2 $10,581 Yes
The Electrical Circuit Capacity Is Inadequate 23440 20 EACH 2 $18,888 No
The Panelboard Is Damaged And Should Be Replaced 23080 8 Amps 2 $244 Yes
The 2 X 2 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 22962 12 Ea. 3 $4,388 No
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 22967 495 Ea. 3 $266,019 No
The Panelboard Is Damaged And Should Be Replaced 23081 3 Amps 2 $91 Yes
The Power Service Is Inadequate And Should Be Upgraded 23153 450 Amps 2 $23,862 No
Sub Total for System 10 $351,285
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Cleaning Required 23015 44,437 SF 3 $41,702 No
Duct Grill is Damaged And Should Be Replaced 23593 224 Ea. 3 $72,099 No
The Large Diameter Exhausts/Hoods Are Missing/Damaged And Require Replacement 22999 1 Ea. 2 $1,702 No
Complete HVAC Systemwide Replacement 23572 44,437 SF 2 $824,708 No
Mechanical Room too small 23843 1 LS 2 $100,100 No
Duct Grill is Damaged And Should Be Replaced 23594 44 Ea. 3 $14,163 No
Water Chiller - Air Reciprocating 100 Ton is missing and is needed 23712 1 Ea. 3 $227,136 No
Computer room lacks independent AC. 23844 1 Ea. 4 $31,794 No
Exhaust Fan Ventilation Is Damaged And Should Be Replaced 23131 1 Ea. 3 $1,935 No
Test And Balancing Required 23163 44,437 SF 3 $77,641 No
Sub Total for System 10 $1,392,979
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Walls Require Repainting 22868 44,437 SF 4 $118,886 No
The Suspended Ceiling Grid is Damaged And Require Replacement 23105 20,000 SF 4 $161,252 No
Interior Doors Require Repainting 22882 24 Door 3 $1,278 No
The Carpet Flooring Is Damaged And Requires Replacement 22894 23,000 SF 3 $203,097 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 22906 500 SF 3 $3,767 No
Sub Total for System 5 $488,281
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Exterior door hardware is damaged and should be replaced 23571 3 Door 2 $1,811 Yes
The Metal Exterior Door Is Damaged And Requires Replacement 22799 3 Door 2 $7,073 Yes
Sub Total for System 2 $8,883
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Membrane Flashing At Curb (<2') 23312 40 LF 2 $622 Yes
Flashings At Scupper Is Damaged And Should Be Repaired 23386 3 Ea. 2 $298 Yes
Membrane Flashings At Equipment Curbs Are Damaged And Should Be Repaired 23222 50 LF 2 $779 Yes
Membrane Flashings At Drain Is Damaged And Should Be Repaired 23213 2 Ea. 2 $293 Yes
Built Up Roofing (Bur) Lap Seams Are Open Or Deteriorated 23329 10 LF 2 $495 Yes
Built Up Roofing (Bur) Covering Has Blisters That Should Be Repaired 23322 15 Ea. 2 $1,920 Yes
Counter Flashing Is Damaged Or Loose And Should Be Repaired 23420 5 LF 2 $344 Yes
Built Up Roofing (Bur) Membrane Has Holes That Should Be Repaired 23326 15 Ea. 2 $1,811 Yes
Membrane Flashings At Penetration Are Damaged And Should Be Repaired 23378 6 Ea. 2 $628 Yes
The Multi-Ply Bitumen Roof Coating Requires Repair 22711 100 SF 2 $874 Yes
The Roof Drains Are Clogged 23204 3 Ea. 2 $351 Yes
The Roof Requires Cleaning 23340 250 SF 2 $768 Yes
Tapered Insulation Is Required To Eliminate Ponding When Re-Roofing 23396 250 SF 2 $917 No
Sealant At Pitch Pan Is Damaged And Should Be Repaired 23364 1 Ea. 2 $400 Yes
Skylight Is Damaged And Should Be Repaired 23218 9 Ea. 2 $4,878 Yes
Strainers Are Missing And Needed 23205 1 Ea. 2 $804 Yes
Sub Total for System 16 $16,183
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2018 - Student Services CenterSub Total for Building 2010 - Administration Building 66 $2,961,613
Facilities Condition AssessmentValle Verde Campus Condition Assessment
10Magellan Consulting, Inc.
The Furnaces HVAC Component Is Damaged And Requires Replacement 23694 60,000 MBH 2 $182,861 No
The 4 X 4 Exhausts/Hoods Are Missing/Damaged And Require Replacement 23001 2 Ea. 2 $10,707 No
The 2 X 4 Exhausts/Hoods Are Missing/Damaged And Require Replacement 23000 1 Ea. 2 $5,256 No
The Large Diameter Exhausts/Hoods Are Missing/Damaged And Require Replacement 22998 12 Ea. 2 $20,430 No
The Package Unit HVAC Component Is Damaged And Requires Replacement 23192 200 TonAC 2 $533,393 No
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 22908 4,500 SF 3 $33,912 No
Interior Walls Require Repainting 22865 17,150 SF 4 $45,884 No
The Carpet Flooring Is Damaged And Requires Replacement 22892 1,200 SF 3 $10,596 No
Interior Doors Require Repainting 22885 56 Door 3 $2,979 No
Interior Toilet Partition Require Repair Or Replacement 23098 2 SF 3 $4,841 No
The Exposed Ceilings Are Damaged And Requires Repainting 23456 16,500 SF 4 $35,681 No
The Gypboard Ceilings Are Damaged And Requires Repainting 23097 700 SF 5 $1,860 No
The Interior Door Hardware is Damaged and Requires Replacement 23402 48 Door 5 $48,891 No
The Suspended Ceiling Grid is Damaged And Require Replacement 23106 13,196 SF 4 $106,394 No
Concrete Flooring Epoxy Requires Replacement 20835 16,500 SF 5 $32,334 No
Sub Total for System 10 $323,372
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Concrete / CMU Exterior Is Damaged And Requires Repair 22776 10 SF Wall 3 $173 No
Exterior Metal Door Requires Repainting 20859 9 Door 3 $6,193 No
Sub Total for System 2 $6,366
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Multi-Ply Bitumen Roof System Is Damaged And Requires Replacement 23319 30,888 SF 2 $372,066 No
The Roof Drains Are Clogged 23202 1 Ea. 2 $116 Yes
The Roof Requires Cleaning 23343 700 SF 2 $1,218 Yes
Strainers Are Missing And Needed 23206 1 Ea. 2 $804 Yes
Metal Umbrella At Penetration Or Pitch Pan Is Missing And Is Needed 23368 7 Ea. 2 $1,656 Yes
Overflow Scuppers Are Missing And Are Needed 23488 6 Ea. 2 $2,805 No
Metal Decking Is Damaged And Requires Repair 23388 50 SF 2 $906 Yes
Counter Flashing Is Damaged Or Loose And Should Be Repaired 23422 3 LF 2 $322 Yes
Membrane Flashings At Equipment Curbs Are Damaged And Should Be Repaired 23220 20 LF 2 $311 Yes
Skylight Is Damaged And Should Be Repaired 23219 3 Ea. 2 $1,625 Yes
Splashblocks Are Missing Or Damaged And Are Needed 23252 2 Ea. 2 $206 No
Roof System Requires Replacement 23587 1,683 SQFT 2 $12,957 No
Penetration Boot Is Missing Or Damaged And Should Be Installed 23381 5 Ea. 2 $841 Yes
Sub Total for System 13 $395,834
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2019-01 - Advanced Technology Center
The Base Storage Cabinets Require Replacement 23075 110 LF 4 $31,264 No
Sub Total for System 1 $31,264
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Fire Alarm Panel Should Be Replaced 22994 1 Ea. 1 $9,677 Yes
Sub Total for System 1 $9,677
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Water Heater Plumbing Fixtures Are Damaged And Should Be Replaced 23067 2 Ea. 3 $4,628 No
The Restroom is Not ADA Compliant 23774 4 Ea. 3 $300,025 No
The Rest Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 23058 20 Ea. 3 $32,796 No
Install Fire Sprinklers 23450 44,437 SF 1 $340,395 No
The Refrigerated Water Cooler is Damaged And Should Be Replaced 23138 4 Ea. 3 $17,461 No
The Custodial Mop Or Service Sink Is Damaged And Should Be Replaced 23531 2 Ea. 4 $7,897 No
Sub Total for System 6 $703,202
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2018 - Student Services Center 51 $3,001,755
Facilities Condition AssessmentValle Verde Campus Condition Assessment
11Magellan Consulting, Inc.
Exhaust Fan Curbs are too Low and Should be Raised and Reflashed (<8") 23227 2 Ea. 2 $2,788 No
Membrane Flashings At Drain Is Damaged And Should Be Repaired 23212 2 Ea. 2 $293 Yes
Membrane Flashings At Equipment Curbs Are Damaged And Should Be Repaired 23221 10 LF 2 $157 Yes
Counter Flashing Is Damaged Or Loose And Should Be Repaired 23421 20 LF 2 $504 Yes
Built Up Roofing (Bur) Covering Has Blisters That Should Be Repaired 23321 50 Ea. 2 $6,403 Yes
Built Up Roofing (Bur) Lap Seams Are Open Or Deteriorated 23328 20 LF 2 $990 Yes
Built Up Roofing (Bur) Membrane Has Holes That Should Be Repaired 23327 10 Ea. 2 $1,207 Yes
Membrane Flashings At Penetration Are Damaged And Should Be Repaired 23375 4 Ea. 2 $419 Yes
Metal Coping Lap Joints Have Lost Their Seal And Should Be Resealed 23313 2 Ea. 2 $293 Yes
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2019-02 - ATC Complex 2
The Base Storage Cabinets Require Replacement 23074 12 LF 4 $3,411 No
Sub Total for System 1 $3,411
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Public Address Is Inadequate And Should Be Replaced 23156 31,130 SF 1 $60,131 Yes
Sub Total for System 1 $60,131
TechnologyDeficiency ID Qty UoM Priority Repair Cost WS&D
Fire Alarm is Missing or Inadequate 23702 31,130 SF 1 $54,307 Yes
Emergency Lighting Is Inadequate Or Not Present And Should Be Installed 23613 31,130 SF 2 $46,470 Yes
Sub Total for System 2 $100,777
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Custodial Mop Or Service Sink Is Damaged And Should Be Replaced 23533 1 Ea. 4 $3,948 No
The Water Heater Plumbing Fixtures Are Damaged And Should Be Replaced 23066 1 Ea. 3 $2,315 No
The Refrigerated Water Cooler is Damaged And Should Be Replaced 23139 3 Ea. 3 $13,097 No
Roof Top Unit Condensate Drain Is Damaged And Should Be Repaired 23160 4 Ea. 2 $1,436 No
Install Fire Sprinklers 23448 31,130 SF 1 $238,462 No
The Toilets Plumbing Fixtures Are Damaged And Should Be Replaced 23062 6 Ea. 3 $7,942 No
The Rest Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 23056 5 Ea. 3 $8,199 No
Sub Total for System 7 $275,399
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The Panelboard Is Damaged And Should Be Replaced 23082 450 Amps 2 $13,696 Yes
The Power Service Is Inadequate And Should Be Upgraded 23154 450 Amps 2 $23,862 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 22941 13 Ea. 2 $12,673 Yes
The Canopy Lighting Is Damaged And Should Be Replaced 22940 3 Ea. 2 $5,291 Yes
The Electrical Circuit Capacity Is Inadequate 23441 84 EACH 2 $79,328 No
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 23068 150 Ea. 3 $52,962 No
The Electrical Receptacles Are Inadequate And More Are Needed 23143 84 Ea. 3 $37,239 No
The H.I.D. Lighting Is Damaged And Should Be Replaced 23144 25 Ea. 4 $14,647 No
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 22965 150 Ea. 3 $80,611 No
The 2 X 2 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 22964 3 Ea. 3 $1,097 No
Sub Total for System 10 $321,407
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Grill is Damaged And Should Be Replaced 23588 59 Ea. 3 $18,990 No
Duct Grill is Damaged And Should Be Replaced 23589 28 Ea. 3 $9,013 No
Duct Cleaning Required 23013 31,130 SF 3 $29,215 No
VAV boxes require replacement 23703 100 Ea. 2 $154,968 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 23052 10,000 SF 3 $22,410 No
The Boiler HVAC Component Is Damaged And Requires Replacement 23053 2,400 MBH 3 $54,385 No
Test And Balancing Required 23161 10,000 SF 3 $17,472 No
Ductwork Is Damaged And Should Be Replaced 23194 1,050 LF 3 $19,973 No
Sub Total for System 13 $1,079,071
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2019-01 - Advanced Technology Center 59 $2,565,767
Facilities Condition AssessmentValle Verde Campus Condition Assessment
12Magellan Consulting, Inc.
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Fire Alarm Horn/Strobe Is Missing And Is Needed 23486 10 Ea. 1 $6,507 Yes
Fire Alarm Actuator Is Missing And Is Needed 23460 5 Ea. 1 $1,407 Yes
Security Alarm Motion Detector Is Missing And Needed 23504 3 Ea. 1 $3,463 No
Sub Total for System 3 $11,377
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Rest Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 23057 4 Ea. 3 $6,559 No
The Refrigerated Water Cooler is Damaged And Should Be Replaced 23140 2 Ea. 3 $8,731 No
Install Fire Sprinklers 23449 21,437 SF 1 $164,211 No
The Toilets Plumbing Fixtures Are Damaged And Should Be Replaced 23061 6 Ea. 3 $7,942 No
The Custodial Mop Or Service Sink Is Damaged And Should Be Replaced 23532 1 Ea. 4 $3,948 No
The Urinal Plumbing Fixtures Are Damaged And Should Be Replaced 23794 2 Ea. 3 $3,058 No
Sub Total for System 6 $194,449
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The Mounted Building Lighting Is Damaged And Should Be Replaced 22943 9 Ea. 2 $8,774 Yes
The GFCI Electrical Receptacles Are Inadequate And More Are Needed 23145 8 Ea. 2 $3,918 Yes
The 2 X 2 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 22963 11 Ea. 3 $4,022 No
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 22966 58 Ea. 3 $31,169 No
Sub Total for System 4 $47,884
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Exhaust Fan Ventilation Is Damaged And Should Be Replaced 23130 2 Ea. 3 $3,871 No
Test And Balancing Required 23162 21,437 SF 3 $37,456 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 23050 21,437 SF 3 $48,037 No
Duct Cleaning Required 23014 21,437 SF 3 $20,118 No
Complete HVAC Systemwide Replacement 23714 11,000 SF 2 $154,591 No
The Package Unit HVAC Component Is Damaged And Requires Replacement 23189 15 TonAC 2 $40,005 No
Duct Grill is Damaged And Should Be Replaced 23591 48 Ea. 3 $15,450 No
Duct Grill is Damaged And Should Be Replaced 23592 3 Ea. 3 $966 No
Duct Grill is Damaged And Should Be Replaced 23590 17 Ea. 3 $5,473 No
Sub Total for System 9 $325,967
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Concrete Flooring Is Damaged And Requires Replacement 22923 1,200 SF 3 $8,665 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 22909 500 SF 3 $3,767 No
Interior Doors Require Repainting 22884 16 Door 3 $852 No
Interior Toilet Partition Require Repair Or Replacement 23099 1 SF 3 $2,421 No
Interior Walls Require Repainting 22866 500 SF 4 $1,338 No
The Interior Door Hardware is Damaged and Requires Replacement 23401 32 Door 5 $32,594 No
The Suspended Ceiling Grid is Damaged And Require Replacement 23107 3,300 SF 4 $26,607 No
The Concrete Flooring Is Damaged And Requires Replacement 23805 400 SF 4 $2,888 No
Sub Total for System 8 $79,132
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Concrete / CMU Exterior Is Damaged And Requires Repair 22775 30 SF Wall 3 $521 No
Sub Total for System 1 $521
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Multi-Ply Bitumen Roof Coating Requires Repair 22710 100 SF 2 $874 Yes
Splashblocks Are Missing Or Damaged And Are Needed 23251 2 Ea. 2 $206 No
Tapered Insulation Is Required To Eliminate Ponding When Re-Roofing 23395 100 SF 2 $524 No
Metal Umbrella At Penetration Or Pitch Pan Is Missing And Is Needed 23369 8 Ea. 2 $1,893 Yes
The Roof Requires Cleaning 23341 50 SF 2 $369 Yes
The Roof Drains Are Clogged 23203 1 Ea. 2 $116 Yes
Sub Total for System 15 $17,035
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Facilities Condition AssessmentValle Verde Campus Condition Assessment
13Magellan Consulting, Inc.
Fire Alarm Heat Detector Is Missing And Is Needed 23466 1 Ea. 1 $586 Yes
Fire Alarm Horn/Strobe Is Missing And Is Needed 23484 1 Ea. 1 $650 Yes
Emergency Exit Signage Is Missing And Needed 23157 2 Ea. 1 $1,565 Yes
Fire Alarm Actuator Is Missing And Is Needed 23465 1 Ea. 1 $282 Yes
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Package Unit HVAC Component Is Damaged And Requires Replacement 23191 2 TonAC 2 $5,334 No
Sub Total for System 1 $5,334
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2019-04B - ATC Athletic Portable B
Fire Alarm Panel is Missing and is Needed 23473 1 Ea. 1 $3,727 Yes
Fire Alarm Smoke Detector Is Missing And Is Needed 23479 1 Ea. 1 $406 Yes
Fire Alarm Strobe Is Missing And Is Needed 23518 1 Ea. 1 $650 Yes
Fire Alarm Actuator Is Missing And Is Needed 23464 1 Ea. 1 $282 Yes
Fire Alarm Heat Detector Is Missing And Is Needed 23467 1 Ea. 1 $586 Yes
Fire Alarm Horn/Strobe Is Missing And Is Needed 23487 1 Ea. 1 $650 Yes
Security Alarm Camera Is Missing And Needed 23491 1 Ea. 2 $3,793 No
Security Alarm Contact Is Missing And Needed 23453 1 Ea. 2 $1,161 No
Emergency Exit Signage Is Missing And Needed 23158 2 Ea. 1 $1,565 Yes
Security Alarm Horn Is Missing And Needed 23496 1 Ea. 1 $1,190 No
Security Alarm Motion Detector Is Missing And Needed 23501 1 Ea. 1 $1,154 No
Security Alarm Panel Should be Replaced 23413 1 Ea. 1 $4,295 No
Sub Total for System 12 $19,459
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
Roof Top Unit Condensate Drain Is Missing And Needed 23159 1 EACH 2 $486 No
Sub Total for System 1 $486
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The Mounted Building Lighting Is Damaged And Should Be Replaced 22942 3 Ea. 2 $2,925 Yes
Sub Total for System 1 $2,925
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Controls Are Inadequate And Should Be Replaced With DDC Controls 23051 768 SF 3 $1,722 No
The Package Unit HVAC Component Is Damaged And Requires Replacement 23190 2 TonAC 2 $5,334 No
Sub Total for System 2 $7,056
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Suspended Ceiling Grid is Damaged And Require Replacement 23108 768 SF 4 $6,192 No
Sub Total for System 1 $6,192
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Exterior door hardware is damaged and should be replaced 23569 2 Door 2 $1,207 Yes
Sub Total for System 1 $1,207
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Roof Requires Cleaning 23342 10 SF 2 $360 Yes
Sub Total for System 1 $360
Deficiency ID Qty UoM Priority Repair Cost WS&D
Roofing
Sub Total for Building 2019-04A - ATC Athletic Portable A 19 $37,685
Building: 2019-04A - ATC Athletic Portable A
The Base Storage Cabinets Require Replacement 23073 30 LF 4 $8,527 No
Sub Total for System 1 $8,527
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2019-02 - ATC Complex 2 47 $684,891
Facilities Condition AssessmentValle Verde Campus Condition Assessment
14Magellan Consulting, Inc.
The Aluminum Window Is Damaged And Requires Replacement 18789 56 Ea. 2 $96,806 Yes
The Aluminum Storefront Exterior Door Is Damaged And Requires Replacement 18784 2 Door 2 $8,711 Yes
The Aluminum Window Is Damaged And Requires Replacement 18788 28 Ea. 2 $48,403 Yes
Exterior door hardware is damaged and should be replaced 18787 4 Door 2 $2,413 Yes
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Skylight Is Damaged And Should Be Repaired 18813 5 Ea. 2 $2,710 Yes
Metal Umbrella At Penetration Or Pitch Pan Is Missing And Is Needed 18815 2 Ea. 2 $473 Yes
Strainers Are Missing And Needed 18797 1 Ea. 2 $804 Yes
The Multi-Ply Bitumen Roof Coating Requires Repair 19026 30,000 SF 2 $261,964 Yes
The Clay Tile Roofing Roof Covering Is Damaged And Requires Repair 19017 20 SF 2 $4,046 Yes
Metal Coping Lap Joints Have Lost Their Seal And Should Be Resealed 18804 4 Ea. 2 $295 Yes
Membrane Flashings At Drain Is Damaged And Should Be Repaired 18798 6 Ea. 2 $881 Yes
Membrane Flashing At Parapet (>2') Is Damaged And Should Be Repaired 18802 100 LF 2 $393 Yes
Membrane Flashings At Equipment Curbs Are Damaged And Should Be Repaired 18809 60 LF 2 $935 Yes
Metal Coping Is Damaged Or Loose And Should Be Repaired 18805 2 LF 2 $122 Yes
Membrane Flashings At Penetration Are Damaged And Should Be Repaired 18816 6 Ea. 2 $628 Yes
The Metal Downspouts Are Damaged Or Missing And Requires Replacement 18794 4 LF 3 $189 No
Tapered Insulation Is Required To Eliminate Ponding When Re-Roofing 18800 2,000 SF 3 $6,290 No
Awning Or Canopy Roofing Cracked Or Spauld 20656 9 SF 4 $138 No
Splashblocks Are Missing Or Damaged And Are Needed 18795 1 Ea. 5 $104 No
HVAC Curbs are too Low and Should be Raised and Reflashed (<8") 18811 2 Ea. 4 $2,768 No
Drains And Piping Are Needed To Eliminate Ponding 18799 4 Ea. 3 $8,925 No
The Roof Operable Hatch Is Damaged And Requires Repair 18790 1 Ea. 2 $568 Yes
The Roof Drains Are Clogged 18796 2 Ea. 2 $235 Yes
The Roof Requires Cleaning 18844 1,000 SF 2 $1,278 Yes
Awning Or Canopy Concrete Roofing System Requires Replacement 20657 10 SF 3 $490 No
Awning Or Canopy Composition Shingle Roofing System Requires Replacement 20655 20 SF 3 $284 No
Debris In Gutters Should Be Removed 18791 25 LF 2 $359 Yes
Curbs are Too Low and Require Reflashing 18803 50 LF 2 $3,655 Yes
Edge Metal Is Loose And Should Be Resecured 18923 12 LF 2 $349 Yes
Edge Metal Is Loose And Should Be Resecured 18801 30 LF 2 $905 Yes
Concrete Decking Is Damaged And Requires Repair 18842 10 SF 2 $100 Yes
Built Up Roofing (Bur) Covering Has Blisters That Should Be Repaired 18956 7 Ea. 2 $897 Yes
The Multi-Ply Bitumen Roof System Is Damaged And Requires Replacement 18843 3,000 SF 1 $36,138 No
Built Up Roofing (Bur) Membrane Has Holes That Should Be Repaired 18957 2 Ea. 2 $242 Yes
Built Up Roofing (Bur) Lap Seams Are Open Or Deteriorated 18958 30 LF 2 $1,485 Yes
Gas Line/Conduit On New Supports Is Unseated And Should Be Supported 18812 3 Ea. 2 $333 Yes
Flashing At Termination Wall Is Damaged And Should Be Repaired 18793 2 Ea. 2 $147 Yes
Lead Flashing Is Missing And Is Needed 18814 2 Ea. 2 $260 Yes
Gutter Joints Require Repair 18792 2 Ea. 2 $297 No
Expansion Joint Termination At End Wall Is Damaged And Should Be Repaired 18808 2 Ea. 2 $897 Yes
Exhaust Fan Curbs are too Low and Should be Raised and Reflashed (<8") 18810 4 Ea. 2 $5,576 No
Edge Metal Is Missing 18845 10 LF 2 $193 Yes
Expansion Joint Laps Are Damaged And Should Be Repaired 18806 3 Ea. 2 $1,083 Yes
Expansion Joint Cover Is Missing Or Damaged And Should Be Replaced 18807 15 LF 2 $1,074 Yes
Sub Total for System 40 $348,510
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2020 - Learning Resource Center
Security Alarm Motion Detector Is Missing And Needed 23500 1 Ea. 1 $1,154 No
Security Alarm Panel Should be Replaced 23414 1 Ea. 1 $4,295 No
Fire Alarm Strobe Is Missing And Is Needed 23519 1 Ea. 1 $650 Yes
Security Alarm Horn Is Missing And Needed 23497 1 Ea. 1 $1,190 No
Fire Alarm Smoke Detector Is Missing And Is Needed 23478 1 Ea. 1 $406 Yes
Fire Alarm Panel is Missing and is Needed 23474 1 Ea. 1 $3,727 Yes
Security Alarm Camera Is Missing And Needed 23490 1 Ea. 2 $3,793 No
Security Alarm Contact Is Missing And Needed 23452 1 Ea. 2 $1,161 No
Sub Total for System 12 $19,459
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2019-04B - ATC Athletic Portable B 13 $24,794
Facilities Condition AssessmentValle Verde Campus Condition Assessment
15Magellan Consulting, Inc.
The Class Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 18838 16 Ea. 4 $32,826 No
The Urinal Plumbing Fixtures Are Damaged And Should Be Replaced 20816 15 Ea. 3 $22,932 No
The Toilets Plumbing Fixtures Are Damaged And Should Be Replaced 18840 51 Ea. 3 $67,515 No
The Custodial Mop Or Service Sink Is Damaged And Should Be Replaced 18837 7 Ea. 4 $27,637 No
The Restroom is Not ADA Compliant 23773 4 Ea. 3 $103,465 No
The Rest Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 18839 29 Ea. 4 $47,555 No
The Refrigerated Water Cooler is Damaged And Should Be Replaced 18841 11 Ea. 4 $48,019 No
Sub Total for System 7 $349,948
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The Electrical Receptacles Are Inadequate And More Are Needed 18836 20 Ea. 3 $8,867 No
The Power Service Is Inadequate And Should Be Upgraded 18827 2,250 Amps 3 $119,308 No
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 18823 60 Ea. 4 $21,185 No
The Canopy Lighting Is Damaged And Should Be Replaced 18821 140 Ea. 2 $246,896 Yes
The Mounted Building Lighting Is Damaged And Should Be Replaced 18822 24 Ea. 2 $23,398 Yes
The Panelboard Is Damaged And Should Be Replaced 18828 900 Amps 2 $27,391 Yes
The 2 X 2 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 18824 1,290 Ea. 4 $471,768 No
The Incandescent Lighting Is Damaged And Should Be Replaced 20536 206 Ea. 4 $74,917 No
The Pendant Lighting Is Damaged And Should Be Replaced 18826 3 Ea. 4 $2,799 No
The Incandescent Lighting Is Damaged And Should Be Replaced 20535 7 Ea. 4 $2,546 No
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 18825 810 Ea. 4 $435,302 No
The Electrical Circuit Capacity Is Inadequate 18829 336 EACH 4 $317,312 No
Sub Total for System 12 $1,751,688
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Register is Damaged And Should Be Replaced 20660 176 Ea. 5 $145,258 No
Test And Balancing Required 18818 91,294 SF 3 $159,508 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 18819 91,294 SF 4 $204,579 No
The Large Diameter Exhausts/Hoods Are Missing/Damaged And Require Replacement 18817 5 Ea. 2 $8,512 No
Duct Damper is Damaged And Should Be Replaced 20662 58 Ea. 3 $9,621 No
Duct Grill is Damaged And Should Be Replaced 20661 24 Ea. 5 $7,724 No
Duct Cleaning Required 18820 91,294 SF 5 $85,677 No
Exhaust Fan Ventilation Is Damaged And Should Be Replaced 20659 13 Ea. 4 $25,158 No
Sub Total for System 8 $646,036
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Ceramic Tile Flooring Is Damaged And Requires Replacement 18854 2,000 SF 3 $31,905 No
The Suspended Ceiling Grid is Damaged And Require Replacement 18847 48,928 SF 3 $394,487 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 18853 8,062 SF 3 $60,755 No
The Carpet Flooring Is Damaged And Requires Replacement 18852 60,549 SF 3 $534,665 No
The Interior Door Hardware is Damaged and Requires Replacement 18935 123 Ea. 2 $125,283 No
Interior Doors Require Replacement 18850 2 Door 3 $2,519 No
Restrooms require complete renovation 23845 1 LS 3 $364,000 No
Interior Toilet Partition Require Repair Or Replacement 19004 20 Ea. 4 $48,407 No
Interior Doors Require Repainting 18851 101 Door 5 $5,374 No
Interior Doors Require Repair 18938 4 Door 5 $1,820 No
Interior Walls Require Repainting 18848 73,035 SF 5 $195,397 No
The Stone/Quarry Flooring Is Damaged And Requires Replacement 20658 13,694 SF 4 $273,830 No
Concrete Flooring Epoxy Requires Replacement 20811 1,723 SF 5 $3,376 No
Directional / wayfinding signage missing or not accessible. 23781 75 Ea. 5 $9,460 No
Sub Total for System 14 $2,051,278
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Overhead Door Is Damaged And Requires Repair 18786 2 Door 2 $2,168 Yes
The Metal Exterior Door Is Damaged And Requires Repair 18785 4 Door 2 $4,335 Yes
The Brick Exterior Is Damaged And Requires Repair 18781 100 SF Wall 3 $1,174 No
The Concrete / CMU Exterior Is Damaged And Requires Repair 18782 50 SF Wall 4 $868 No
Sub Total for System 8 $164,877
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Facilities Condition AssessmentValle Verde Campus Condition Assessment
16Magellan Consulting, Inc.
The Concrete Flooring Is Damaged And Requires Replacement 22922 1,000 SF 3 $7,220 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 22897 46,300 SF 3 $348,921 No
The Carpet Tiles Requires Replacement 22896 1,550 SF 3 $11,035 No
Interior Doors Require Repainting 22880 60 Door 3 $3,192 No
The Carpet Flooring Is Damaged And Requires Replacement 22890 10,000 SF 3 $88,303 No
The Exposed Ceilings Are Damaged And Requires Repainting 23457 1,000 SF 4 $2,162 No
The Interior Door Hardware is Damaged and Requires Replacement 23400 6 Door 5 $6,112 No
Interior Ceilings Requires Repainting 22879 15,000 SF 4 $37,938 No
Interior Walls Require Repainting 22870 46,500 SF 4 $124,406 No
Sub Total for System 9 $629,289
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Metal Coping Is Damaged Or Loose And Should Be Repaired 23316 12 LF 2 $735 Yes
Membrane Flashings At Penetration Are Damaged And Should Be Repaired 23372 4 Ea. 2 $419 Yes
Metal Umbrella At Penetration Or Pitch Pan Is Missing And Is Needed 23371 2 Ea. 2 $473 Yes
Metal Coping Lap Joints Have Lost Their Seal And Should Be Resealed 23314 3 Ea. 2 $295 Yes
Membrane Flashing At Curb (<2') 23311 20 LF 2 $311 Yes
HVAC Curbs are too Low and Should be Raised and Reflashed (<8") 23230 2 Ea. 2 $2,768 No
Membrane Flashings At Drain Is Damaged And Should Be Repaired 23210 3 Ea. 2 $440 Yes
Membrane Flashing At Parapet (>2') Is Damaged And Should Be Repaired 23417 50 LF 2 $342 Yes
The Roof Drains Are Clogged 23201 6 Ea. 2 $703 Yes
The Multi-Ply Bitumen Roof Coating Requires Replacement 23318 40,000 SF 2 $260,893 No
The Roof Requires Cleaning 23334 4,000 SF 2 $2,595 Yes
The Roof Operable Hatch Is Damaged And Requires Repair 22828 3 Ea. 2 $1,705 Yes
Re-Seal Metal Roof-To-Wall Flashing At Wall 23429 20 LF 2 $297 Yes
Overflow Drain And Piping Is Missing And Is Needed 23215 2 Ea. 2 $2,503 No
Tapered Insulation Is Required To Eliminate Ponding When Re-Roofing 23394 6,000 SF 2 $17,295 No
Strainers Are Missing And Needed 23207 3 Ea. 2 $2,415 Yes
Counter Flashing Is Damaged Or Loose And Should Be Repaired 23419 15 LF 2 $451 Yes
Curbs Have Been Abandoned And Should Be Removed 23234 1 Ea. 2 $493 No
Debris In Gutters Should Be Removed 23250 100 LF 2 $359 Yes
Built Up Roofing (Bur) Covering Has Blisters That Should Be Repaired 23323 7 Ea. 2 $897 Yes
Built Up Roofing (Bur) Lap Seams Are Open Or Deteriorated 23330 10 LF 2 $495 Yes
Built Up Roofing (Bur) Membrane Has Holes That Should Be Repaired 23325 3 Ea. 2 $362 Yes
Edge Metal At Gutter Is Missing And Needed 23258 3 Ea. 2 $866 Yes
Flashings At Drain Is Damaged And Should Be Repaired 23529 7 Ea. 2 $528 Yes
Flashings At Scupper Is Damaged And Should Be Repaired 23387 4 Ea. 2 $302 Yes
Gutter Joints Require Repair 23257 7 Ea. 2 $226 No
Edge Metal Is Missing And Is Needed 23355 75 LF 2 $2,444 Yes
Expansion Joint Termination At End Wall Is Damaged And Should Be Repaired 23428 3 Ea. 2 $1,345 Yes
Flashing At Termination Wall Is Damaged And Should Be Repaired 23261 4 Ea. 2 $295 Yes
Sub Total for System 29 $303,254
Deficiency ID Qty UoM Priority Repair Cost WS&D
Roofing
Building: 2025 - Building B
The Base Storage Cabinets Require Replacement 18855 240 LF 4 $68,214 No
Sub Total for System 1 $68,214
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Elevator Is Missing And Needed 18856 5 FLOOR 4 $269,191 No
Sub Total for System 1 $269,191
ConveyancesDeficiency ID Qty UoM Priority Repair Cost WS&D
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 18830 91,294 SF 2 $53,579 Yes
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 20537 92 Ea. 2 $49,084 Yes
Fire Alarm is Missing or Inadequate 18835 91,294 SF 1 $159,265 Yes
Security Alarm is Missing or Inadequate 18834 91,294 SF 2 $164,766 No
Sub Total for System 4 $426,694
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2020 - Learning Resource Center 95 $6,076,436
Facilities Condition AssessmentValle Verde Campus Condition Assessment
17Magellan Consulting, Inc.
The Toilets Plumbing Fixtures Are Damaged And Should Be Replaced 20554 7 Ea. 3 $9,267 No
The Water Heater Plumbing Fixtures Are Damaged And Should Be Replaced 20555 1 Ea. 2 $2,315 No
The Refrigerated Water Cooler is Damaged And Should Be Replaced 20556 1 Ea. 4 $4,366 No
The Rest Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 20553 5 Ea. 4 $8,199 No
Sub Total for System 4 $24,148
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20558 2 Ea. 4 $706 No
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20559 15 Ea. 4 $8,061 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 20557 3 Ea. 2 $2,925 Yes
Sub Total for System 3 $11,692
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Grill is Damaged And Should Be Replaced 20551 5 Ea. 5 $1,609 No
Duct Register is Damaged And Should Be Replaced 20550 2 Ea. 5 $1,651 No
Sub Total for System 2 $3,260
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Toilet Partition Require Repair Or Replacement 20545 2 Ea. 4 $4,841 No
The Suspended Ceiling Grid is Damaged And Require Replacement 20543 768 SF 3 $6,192 No
The Interior Door Hardware is Damaged and Requires Replacement 20547 2 Ea. 2 $2,037 No
Interior Walls Require Repainting 20544 768 SF 5 $2,055 No
Interior Doors Require Repainting 20546 2 Door 5 $106 No
Sub Total for System 5 $15,230
Deficiency ID Qty UoM Priority Repair Cost WS&D
Interior
Exterior door hardware is damaged and should be replaced 20538 1 Door 2 $604 Yes
The Aluminum Window Is Damaged And Requires Replacement 20541 4 Ea. 2 $6,914 Yes
Exterior Metal Door Requires Repainting 20836 4 Door 3 $2,754 No
Sub Total for System 3 $10,272
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Roof Requires Cleaning 20548 12 SF 2 $362 Yes
Sub Total for System 1 $362
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2030-01 - Americana Language Village 18 $64,963
Building: 2030-01 - Americana Language Village
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 22731 3 Ea. 1 $1,600 Yes
Sub Total for System 1 $1,600
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Refrigerated Water Cooler is Damaged And Should Be Replaced 23137 2 Ea. 3 $8,731 No
The Toilets Plumbing Fixtures Are Damaged And Should Be Replaced 23064 12 Ea. 3 $15,887 No
Sub Total for System 2 $24,617
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The Mounted Building Lighting Is Damaged And Should Be Replaced 22950 35 Ea. 2 $34,121 Yes
The Electrical Circuit Capacity Is Inadequate 23445 84 EACH 2 $79,328 No
The Panelboard Is Damaged And Should Be Replaced 23079 1 Amps 2 $31 Yes
The Power Service Is Inadequate And Should Be Upgraded 23152 450 Amps 2 $23,862 No
Sub Total for System 4 $137,343
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Test And Balancing Required 23754 61,317 SF 3 $107,133 No
Sub Total for System 1 $107,132
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2025 - Building B 46 $1,203,235
Facilities Condition AssessmentValle Verde Campus Condition Assessment
18Magellan Consulting, Inc.
The Carpet Flooring Is Damaged And Requires Replacement 20482 200 SF 3 $1,765 No
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Aluminum Window Is Damaged And Requires Replacement 20477 8 Ea. 2 $13,830 Yes
Exterior door hardware is damaged and should be replaced 20476 2 Door 2 $1,207 Yes
Exterior Metal Door Requires Repainting 20838 2 Door 3 $1,376 No
Sub Total for System 3 $16,413
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Edge Metal Is Missing And Is Needed 20485 8 LF 2 $260 Yes
Debris In Gutters Should Be Removed 20484 56 LF 2 $359 Yes
Metal Counter Flashing Is Loose Or Damaged And Should Be Repaired 20486 8 LF 2 $262 Yes
The Roof Requires Cleaning 20487 100 SF 2 $379 Yes
Sub Total for System 4 $1,259
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2030-03 - Americana Lang. Vill. - Bldg. 3
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 20532 2 Ea. 2 $1,067 Yes
Fire Alarm is Missing or Inadequate 20534 758 SF 1 $8,834 Yes
Security Alarm is Missing or Inadequate 20533 758 SF 2 $1,369 No
Sub Total for System 3 $11,269
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20531 12 Ea. 4 $6,448 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 20529 2 Ea. 2 $1,949 Yes
Sub Total for System 2 $8,397
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Controls Are Inadequate And Should Be Replaced With DDC Controls 20525 758 SF 4 $1,698 No
Test And Balancing Required 20524 758 SF 3 $1,325 No
Duct Grill is Damaged And Should Be Replaced 20528 1 Ea. 5 $322 No
Ductwork Is Damaged And Should Be Replaced 20526 60 LF 3 $1,141 No
Duct Register is Damaged And Should Be Replaced 20527 2 Ea. 5 $1,651 No
Sub Total for System 5 $6,137
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Room Signage Is Not ADA Compliant With Raised Letters And Braille 23627 2 Ea. 3 $184 No
The Suspended Ceiling Grid is Damaged And Require Replacement 20517 758 SF 3 $6,112 No
The Interior Door Hardware is Damaged and Requires Replacement 20520 2 Ea. 2 $2,037 No
The Carpet Flooring Is Damaged And Requires Replacement 20521 380 SF 3 $3,356 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 20522 380 SF 3 $2,863 No
Interior Walls Require Repainting 20518 758 SF 5 $2,027 No
Interior Doors Require Repainting 20519 2 Door 5 $106 No
Sub Total for System 7 $16,684
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Metal Panel Exterior Is Damaged And Requires Repair 20513 2 SF Wall 2 $238 Yes
The Aluminum Window Is Damaged And Requires Replacement 20515 8 Ea. 2 $13,830 Yes
Exterior door hardware is damaged and should be replaced 20514 2 Door 2 $1,207 Yes
Exterior Metal Door Requires Repainting 20837 2 Door 3 $1,376 No
Sub Total for System 4 $16,651
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Roof Requires Cleaning 20523 60 SF 2 $371 Yes
Sub Total for System 1 $371
Deficiency ID Qty UoM Priority Repair Cost WS&D
Roofing
Sub Total for Building 2030-02 - Americana Lang. Vill. - Bldg. 2 22 $59,510
Building: 2030-02 - Americana Lang. Vill. - Bldg. 2
Facilities Condition AssessmentValle Verde Campus Condition Assessment
19Magellan Consulting, Inc.
The Mounted Building Lighting Is Damaged And Should Be Replaced 20469 2 Ea. 2 $1,949 Yes
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20471 12 Ea. 4 $6,448 No
Sub Total for System 2 $8,397
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Test And Balancing Required 20463 768 SF 3 $1,341 No
Ductwork Is Damaged And Should Be Replaced 20465 60 LF 3 $1,141 No
The Package Unit HVAC Component Is Damaged And Requires Replacement 20468 4 TonAC 2 $10,667 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 20464 768 SF 4 $1,722 No
Duct Register is Damaged And Should Be Replaced 20499 8 Ea. 5 $6,603 No
Duct Grill is Damaged And Should Be Replaced 20500 2 Ea. 5 $644 No
Sub Total for System 6 $22,118
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Suspended Ceiling Grid is Damaged And Require Replacement 20458 758 SF 3 $6,112 No
The Room Signage Is Not ADA Compliant With Raised Letters And Braille 23629 2 Ea. 3 $184 No
The Carpet Flooring Is Damaged And Requires Replacement 20461 300 SF 3 $2,650 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 20462 458 SF 3 $3,451 No
Interior Walls Require Repainting 20459 758 SF 5 $2,027 No
Interior Doors Require Repainting 20460 7 Door 5 $373 No
Sub Total for System 6 $14,797
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Aluminum Window Is Damaged And Requires Replacement 20456 8 Ea. 2 $13,830 Yes
Exterior door hardware is damaged and should be replaced 20455 2 Door 2 $1,207 Yes
Exterior Metal Door Requires Repainting 20840 2 Door 3 $1,376 No
Sub Total for System 3 $16,413
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2030-04 - Americana Lang. Vill. - Bldg. 4
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 20495 768 SF 2 $451 Yes
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 20496 2 Ea. 2 $1,067 Yes
Fire Alarm is Missing or Inadequate 20498 768 SF 1 $8,840 Yes
Security Alarm is Missing or Inadequate 20497 768 SF 2 $1,387 No
Sub Total for System 4 $11,744
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20494 11 Ea. 4 $5,911 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 20493 2 Ea. 2 $1,949 Yes
Sub Total for System 2 $7,861
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Controls Are Inadequate And Should Be Replaced With DDC Controls 20488 768 SF 4 $1,722 No
Ductwork Is Damaged And Should Be Replaced 20489 60 LF 3 $1,141 No
The Package Unit HVAC Component Is Damaged And Requires Replacement 20492 2 TonAC 2 $5,334 No
Duct Grill is Damaged And Should Be Replaced 20491 2 Ea. 5 $644 No
Duct Register is Damaged And Should Be Replaced 20490 7 Ea. 5 $5,777 No
Sub Total for System 5 $14,618
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 20483 568 SF 3 $4,281 No
The Suspended Ceiling Grid is Damaged And Require Replacement 20479 768 SF 3 $6,192 No
The Room Signage Is Not ADA Compliant With Raised Letters And Braille 23628 2 Ea. 3 $184 No
Interior Doors Require Repainting 20481 7 Door 5 $373 No
Interior Walls Require Repainting 20480 768 SF 5 $2,055 No
Sub Total for System 6 $14,849
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2030-03 - Americana Lang. Vill. - Bldg. 3 24 $66,745
Facilities Condition AssessmentValle Verde Campus Condition Assessment
20Magellan Consulting, Inc.
The Suspended Ceiling Grid is Damaged And Require Replacement 20360 1,526 SF 3 $12,303 No
The Room Signage Is Not ADA Compliant With Raised Letters And Braille 20878 1 Ea. 3 $93 No
Interior Doors Require Repainting 20362 10 Door 5 $531 No
The Carpet Flooring Is Damaged And Requires Replacement 20363 1,320 SF 3 $11,655 No
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Aluminum Window Is Damaged And Requires Replacement 20358 15 Ea. 2 $25,930 Yes
Exterior Metal Door Requires Repainting 20842 1 Door 3 $688 No
Exterior door hardware is damaged and should be replaced 20357 1 Door 2 $604 Yes
Sub Total for System 3 $27,222
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Membrane Flashings At Penetration Are Damaged And Should Be Repaired 20366 2 Ea. 2 $209 Yes
The Roof Requires Cleaning 20367 100 SF 2 $379 Yes
Gutters Are Damaged 20365 15 LF 2 $229 No
Sub Total for System 3 $817
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2030-06 - Americana Lang. Vill. - Bldg. 6
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 20452 2 Ea. 2 $1,067 Yes
Fire Alarm is Missing or Inadequate 20454 758 SF 1 $8,834 Yes
Emergency Lighting Is Inadequate Or Not Present And Should Be Installed 20451 758 SF 2 $1,132 Yes
Security Alarm is Missing or Inadequate 20453 758 SF 2 $1,369 No
Sub Total for System 4 $12,401
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20450 12 Ea. 4 $6,448 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 20449 2 Ea. 2 $1,949 Yes
Sub Total for System 2 $8,397
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Suspended Ceiling Grid is Damaged And Require Replacement 20444 758 SF 3 $6,112 No
The Room Signage Is Not ADA Compliant With Raised Letters And Braille 23630 2 Ea. 3 $184 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 20446 758 SF 3 $5,713 No
Interior Walls Require Repainting 20445 758 SF 5 $2,027 No
Sub Total for System 4 $14,036
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Exterior Metal Door Requires Repainting 20841 2 Door 3 $1,376 No
The Aluminum Window Is Damaged And Requires Replacement 20442 8 Ea. 2 $13,830 Yes
Exterior door hardware is damaged and should be replaced 20441 2 Door 2 $1,207 Yes
Sub Total for System 3 $16,413
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Roof Requires Cleaning 20448 25 SF 2 $364 Yes
Gutters Are Damaged 20447 30 LF 2 $457 No
Sub Total for System 2 $821
Deficiency ID Qty UoM Priority Repair Cost WS&D
Roofing
Sub Total for Building 2030-05 - Americana Lang. Vill. - Bldg. 5 15 $52,068
Building: 2030-05 - Americana Lang. Vill. - Bldg. 5
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 20472 768 SF 2 $451 Yes
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 20473 2 Ea. 2 $1,067 Yes
Fire Alarm is Missing or Inadequate 20475 768 SF 1 $8,840 Yes
Security Alarm is Missing or Inadequate 20474 768 SF 2 $1,387 No
Sub Total for System 4 $11,744
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2030-04 - Americana Lang. Vill. - Bldg. 4 21 $73,470
Facilities Condition AssessmentValle Verde Campus Condition Assessment
21Magellan Consulting, Inc.
The Suspended Ceiling Grid is Damaged And Require Replacement 20413 758 SF 3 $6,112 No
The Room Signage Is Not ADA Compliant With Raised Letters And Braille 23631 2 Ea. 3 $184 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 20415 758 SF 3 $5,713 No
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Metal Exterior Door Is Damaged And Requires Repair 20408 1 Door 2 $1,085 Yes
The Aluminum Window Is Damaged And Requires Replacement 20410 8 Ea. 2 $13,830 Yes
Exterior door hardware is damaged and should be replaced 20409 2 Door 2 $1,207 Yes
The Exterior Soffit Is Damaged And Requires Repair 20411 50 SF 5 $197 No
Sub Total for System 4 $16,318
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Edge Metal Is Loose And Should Be Resecured 20419 17 LF 2 $511 Yes
Edge Metal Is Damaged And Should Be Replaced 20418 10 LF 2 $340 Yes
Debris In Gutters Should Be Removed 20416 54 LF 2 $359 Yes
The Roof Requires Cleaning 20420 379 SF 2 $794 Yes
Gutter Screens Are Missing And Needed 20417 4 LF 2 $244 No
Sub Total for System 5 $2,248
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2030-07 - Americana Lang. Vill. - Bldg. 7
The Base Storage Cabinets Require Replacement 20364 10 LF 4 $2,843 No
Sub Total for System 1 $2,843
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Fire Alarm is Missing or Inadequate 20384 1,526 SF 1 $9,766 Yes
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 20382 3 Ea. 2 $1,600 Yes
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 20381 1,526 SF 2 $895 Yes
Security Alarm is Missing or Inadequate 20383 1,526 SF 2 $2,754 No
Sub Total for System 4 $15,015
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Toilets Plumbing Fixtures Are Damaged And Should Be Replaced 20374 2 Ea. 3 $2,648 No
The Water Heater Plumbing Fixtures Are Damaged And Should Be Replaced 20375 1 Ea. 2 $2,315 No
The Rest Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 20373 2 Ea. 4 $3,280 No
Sub Total for System 3 $8,243
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The Electrical Circuit Capacity Is Inadequate 20380 4 EACH 4 $3,778 No
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20378 24 Ea. 4 $12,898 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 20376 2 Ea. 2 $1,949 Yes
The Pendant Lighting Is Damaged And Should Be Replaced 20379 1 Ea. 4 $934 No
Sub Total for System 4 $19,560
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Exhaust Fan Ventilation Is Damaged And Should Be Replaced 20372 2 Ea. 4 $3,871 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 20368 1,526 SF 4 $3,420 No
Ductwork Is Damaged And Should Be Replaced 20369 120 LF 3 $2,282 No
Duct Grill is Damaged And Should Be Replaced 20504 4 Ea. 5 $1,287 No
Duct Register is Damaged And Should Be Replaced 20503 8 Ea. 5 $6,603 No
Sub Total for System 5 $17,463
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Walls Require Repainting 20361 1,526 SF 5 $4,082 No
Sub Total for System 5 $28,665
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2030-06 - Americana Lang. Vill. - Bldg. 6 28 $119,827
Facilities Condition AssessmentValle Verde Campus Condition Assessment
22Magellan Consulting, Inc.
Fire Alarm is Missing or Inadequate 20296 758 SF 1 $8,834 Yes
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20292 12 Ea. 4 $6,448 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 20290 2 Ea. 2 $1,949 Yes
Sub Total for System 2 $8,397
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Grill is Damaged And Should Be Replaced 20506 2 Ea. 5 $644 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 20286 758 SF 4 $1,698 No
Ductwork Is Damaged And Should Be Replaced 20287 60 LF 3 $1,141 No
Duct Register is Damaged And Should Be Replaced 20505 4 Ea. 5 $3,301 No
Sub Total for System 4 $6,785
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 20282 758 SF 3 $5,713 No
The Suspended Ceiling Grid is Damaged And Require Replacement 20280 758 SF 3 $6,112 No
The Room Signage Is Not ADA Compliant With Raised Letters And Braille 20877 2 Ea. 3 $184 No
Interior Walls Require Repainting 20281 758 SF 5 $2,027 No
Sub Total for System 4 $14,036
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Metal Exterior Door Is Damaged And Requires Replacement 20277 2 Door 2 $4,714 Yes
Exterior Metal Door Requires Repainting 20843 1 Door 3 $688 No
The Aluminum Window Is Damaged And Requires Replacement 20278 8 Ea. 2 $13,830 Yes
Sub Total for System 3 $19,232
Deficiency ID Qty UoM Priority Repair Cost WS&D
Exterior
Gutters Are Damaged 20284 30 LF 2 $457 No
The Roof Requires Cleaning 20285 360 SF 2 $790 Yes
Debris In Gutters Should Be Removed 20283 50 LF 2 $359 Yes
Sub Total for System 3 $1,605
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2030-09 - Americana Lang. Vill. - Bldg. 9
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 20437 758 SF 2 $444 Yes
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 20438 2 Ea. 2 $1,067 Yes
Fire Alarm is Missing or Inadequate 20440 758 SF 1 $8,834 Yes
Security Alarm is Missing or Inadequate 20439 758 SF 2 $1,369 No
Sub Total for System 4 $11,714
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20436 12 Ea. 4 $6,448 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 20435 2 Ea. 2 $1,949 Yes
Sub Total for System 2 $8,397
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Grill is Damaged And Should Be Replaced 20502 2 Ea. 5 $644 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 20430 758 SF 4 $1,698 No
Ductwork Is Damaged And Should Be Replaced 20431 60 LF 3 $1,141 No
Duct Register is Damaged And Should Be Replaced 20501 4 Ea. 5 $3,301 No
Sub Total for System 4 $6,785
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Walls Require Repainting 20414 758 SF 5 $2,027 No
Sub Total for System 4 $14,036
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2030-07 - Americana Lang. Vill. - Bldg. 7 23 $59,498
Facilities Condition AssessmentValle Verde Campus Condition Assessment
23Magellan Consulting, Inc.
The Aluminum Window Is Damaged And Requires Replacement 20221 8 Ea. 2 $13,830 Yes
Exterior door hardware is damaged and should be replaced 20220 2 Door 2 $1,207 Yes
Exterior Metal Door Requires Repainting 20845 2 Door 3 $1,376 No
Sub Total for System 3 $16,413
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Gutter Screens Are Missing And Needed 20230 5 LF 2 $246 No
Edge Metal Is Missing And Is Needed 20231 6 LF 2 $195 Yes
Debris In Gutters Should Be Removed 20229 50 LF 2 $359 Yes
The Roof Requires Cleaning 20232 350 SF 2 $788 Yes
Loose/Missing Exposed Panel Fasteners 20233 5 Ea. 2 $420 Yes
Sub Total for System 5 $2,007
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2030-11 - Americana Lang. Vill. - Bldg. 11
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 20188 2 Ea. 2 $1,067 Yes
Fire Alarm is Missing or Inadequate 20190 762 SF 1 $8,836 Yes
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 20187 762 SF 2 $448 Yes
Security Alarm is Missing or Inadequate 20189 762 SF 2 $1,376 No
Sub Total for System 4 $11,726
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Mounted Building Lighting Is Damaged And Should Be Replaced 20185 2 Ea. 2 $1,949 Yes
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20186 13 Ea. 4 $6,987 No
Sub Total for System 2 $8,936
Deficiency ID Qty UoM Priority Repair Cost WS&D
Electrical
Controls Are Inadequate And Should Be Replaced With DDC Controls 20181 762 SF 4 $1,707 No
Ductwork Is Damaged And Should Be Replaced 20182 60 LF 3 $1,141 No
Duct Grill is Damaged And Should Be Replaced 20510 4 Ea. 5 $1,287 No
Duct Register is Damaged And Should Be Replaced 20509 6 Ea. 5 $4,952 No
Sub Total for System 4 $9,087
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Suspended Ceiling Grid is Damaged And Require Replacement 20178 762 SF 3 $6,144 No
The Room Signage Is Not ADA Compliant With Raised Letters And Braille 20876 1 Ea. 3 $93 No
Sub Total for System 2 $6,237
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Exterior Metal Door Requires Repainting 20844 2 Door 3 $1,376 No
The Aluminum Window Is Damaged And Requires Replacement 20176 8 Ea. 2 $13,830 Yes
Sub Total for System 2 $15,206
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Roof Requires Cleaning 20180 300 SF 2 $777 Yes
Membrane Flashings At Penetration Are Damaged And Should Be Repaired 20179 1 Ea. 2 $104 Yes
Sub Total for System 2 $881
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2030-10 - Americana Lang. Vill. - Bldg. 10 16 $52,074
Building: 2030-10 - Americana Lang. Vill. - Bldg. 10
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 20293 758 SF 2 $444 Yes
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 20294 2 Ea. 2 $1,067 Yes
Security Alarm is Missing or Inadequate 20295 758 SF 2 $1,369 No
Sub Total for System 4 $11,714
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2030-09 - Americana Lang. Vill. - Bldg. 9 20 $61,769
Facilities Condition AssessmentValle Verde Campus Condition Assessment
24Magellan Consulting, Inc.
Duct Grill is Damaged And Should Be Replaced 23601 4 Ea. 3 $1,287 No
Duct Damper is Damaged And Should Be Replaced 23025 2 Ea. 3 $331 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 23043 758 SF 3 $1,698 No
Test And Balancing Required 23170 758 SF 3 $1,325 No
Ductwork Is Damaged And Should Be Replaced 23195 60 LF 3 $1,141 No
Sub Total for System 5 $5,782
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Walls Require Repainting 22876 758 SF 4 $2,027 No
The Room Signage Is Not ADA Compliant With Raised Letters And Braille 23437 2 Ea. 3 $184 No
The Suspended Ceiling Grid is Damaged And Require Replacement 23115 758 SF 4 $6,112 No
Sub Total for System 3 $8,323
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Exterior Metal Door Requires Repainting 20850 2 Door 3 $1,376 No
The Aluminum Window Is Damaged And Requires Replacement 22809 8 Ea. 2 $13,830 Yes
Exterior door hardware is damaged and should be replaced 23568 2 Door 2 $1,207 Yes
Exterior Metal Door Requires Repainting 23665 2 Door 3 $1,376 No
The Exterior Requires Cleaning 23664 1,000 SF Wall 5 $2,075 No
The Metal Panel Exterior Is Damaged And Requires Replacement 23398 6 SF Wall 3 $80 No
Sub Total for System 6 $19,944
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Re-Seal Joint Between Metal Z Closure & Roof Panel Is Damaged And Requires Repair 23273 7 LF 2 $193 Yes
The Roof Requires Cleaning 23338 10 SF 2 $360 Yes
Membrane Flashings At Penetration Are Damaged And Should Be Repaired 23373 1 Ea. 2 $104 Yes
Debris In Gutters Should Be Removed 23249 5 LF 2 $359 Yes
Sub Total for System 4 $1,016
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2030-12 - Americana Lang. Vill. - Bldg. 12
Security Alarm is Missing or Inadequate 20254 758 SF 2 $1,369 No
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 20251 758 SF 2 $444 Yes
Fire Alarm is Missing or Inadequate 20255 758 SF 1 $8,834 Yes
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 20252 2 Ea. 2 $1,067 Yes
Sub Total for System 4 $11,714
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20248 12 Ea. 4 $6,448 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 20245 2 Ea. 2 $1,949 Yes
Sub Total for System 2 $8,397
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Grill is Damaged And Should Be Replaced 20508 2 Ea. 5 $644 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 20235 758 SF 4 $1,698 No
Ductwork Is Damaged And Should Be Replaced 20238 60 LF 3 $1,141 No
Duct Register is Damaged And Should Be Replaced 20507 4 Ea. 5 $3,301 No
Sub Total for System 4 $6,785
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Walls Require Repainting 20226 758 SF 5 $2,027 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 20228 758 SF 3 $5,713 No
The Suspended Ceiling Grid is Damaged And Require Replacement 20224 758 SF 3 $6,112 No
Sub Total for System 3 $13,852
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2030-11 - Americana Lang. Vill. - Bldg. 11 21 $59,168
Facilities Condition AssessmentValle Verde Campus Condition Assessment
25Magellan Consulting, Inc.
The Roof Requires Cleaning 23350 15 SF 2 $362 Yes
Sub Total for System 1 $362
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2030-14 - Americana Lang. Vill. - Bldg. 14
Fire Alarm is Missing or Inadequate 23668 758 SF 1 $8,834 Yes
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 22729 2 Ea. 1 $1,067 Yes
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 22719 758 SF 2 $444 Yes
Security Alarm is Missing or Inadequate 23669 758 SF 2 $1,369 No
Sub Total for System 4 $11,714
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Mounted Building Lighting Is Damaged And Should Be Replaced 22958 2 Ea. 2 $1,949 Yes
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 22979 12 Ea. 3 $6,448 No
Sub Total for System 2 $8,397
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Register is Damaged And Should Be Replaced 23022 4 Ea. 3 $3,301 No
Duct Grill is Damaged And Should Be Replaced 23602 2 Ea. 3 $644 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 23038 758 SF 3 $1,698 No
Test And Balancing Required 23178 758 SF 3 $1,325 No
Ductwork Is Damaged And Should Be Replaced 23198 60 LF 3 $1,141 No
Sub Total for System 5 $8,110
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Walls Require Repainting 22861 758 SF 4 $2,027 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 22914 758 SF 3 $5,713 No
The Room Signage Is Not ADA Compliant With Raised Letters And Braille 23438 2 Ea. 3 $184 No
The Suspended Ceiling Grid is Damaged And Require Replacement 23126 758 SF 4 $6,112 No
Sub Total for System 4 $14,036
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Exterior Requires Cleaning 23670 768 SF Wall 5 $1,594 No
The Aluminum Window Is Damaged And Requires Replacement 22819 8 Ea. 2 $13,830 Yes
Sub Total for System 2 $15,424
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Roof Requires Cleaning 23351 300 SF 2 $777 Yes
Sub Total for System 1 $777
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2030-13 - Americana Lang. Vill. - Bldg. 13 18 $58,458
Building: 2030-13 - Americana Lang. Vill. - Bldg. 13
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 22728 2 Ea. 1 $1,067 Yes
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 22720 758 SF 2 $444 Yes
Fire Alarm is Missing or Inadequate 23667 758 SF 1 $8,834 Yes
Security Alarm is Missing or Inadequate 23666 758 SF 2 $1,369 No
Sub Total for System 4 $11,714
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 22973 12 Ea. 3 $6,448 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 22947 2 Ea. 2 $1,949 Yes
Sub Total for System 2 $8,397
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2030-12 - Americana Lang. Vill. - Bldg. 12 24 $55,175
Facilities Condition AssessmentValle Verde Campus Condition Assessment
26Magellan Consulting, Inc.
Duct Damper is Damaged And Should Be Replaced 23027 4 Ea. 3 $664 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 23030 758 SF 3 $1,698 No
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 22911 758 SF 3 $5,713 No
The Room Signage Is Not ADA Compliant With Raised Letters And Braille 23434 2 Ea. 3 $184 No
Interior Walls Require Repainting 22863 758 SF 4 $2,027 No
The Suspended Ceiling Grid is Damaged And Require Replacement 23123 758 SF 4 $6,112 No
Sub Total for System 4 $14,036
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Aluminum Window Is Damaged And Requires Replacement 22820 8 Ea. 2 $13,830 Yes
Exterior Metal Door Requires Repainting 20848 2 Door 3 $1,376 No
Exterior door hardware is damaged and should be replaced 23560 2 Door 2 $1,207 Yes
Sub Total for System 3 $16,413
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Roof Requires Cleaning 23347 10 SF 2 $360 Yes
Membrane Flashings At Penetration Are Damaged And Should Be Repaired 23380 2 Ea. 2 $209 Yes
Sub Total for System 2 $570
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2030-15 - Americana Lang. Vill. - Bldg. 15
Fire Alarm is Missing or Inadequate 23675 768 SF 1 $8,840 Yes
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 22730 2 Ea. 1 $1,067 Yes
Security Alarm is Missing or Inadequate 23674 768 SF 2 $1,387 No
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 22718 768 SF 2 $451 Yes
Sub Total for System 4 $11,744
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Mounted Building Lighting Is Damaged And Should Be Replaced 22957 2 Ea. 2 $1,949 Yes
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 22980 12 Ea. 3 $6,448 No
Sub Total for System 2 $8,397
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Grill is Damaged And Should Be Replaced 23603 2 Ea. 3 $644 No
Duct Register is Damaged And Should Be Replaced 23023 4 Ea. 3 $3,301 No
The Package Unit HVAC Component Is Damaged And Requires Replacement 23673 2 TonAC 2 $5,334 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 23037 768 SF 3 $1,722 No
Test And Balancing Required 23177 768 SF 3 $1,341 No
Ductwork Is Damaged And Should Be Replaced 23199 60 LF 3 $1,141 No
Sub Total for System 6 $13,484
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Walls Require Repainting 22860 768 SF 4 $2,055 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 22915 768 SF 3 $5,788 No
The Room Signage Is Not ADA Compliant With Raised Letters And Braille 23436 2 Ea. 3 $184 No
The Suspended Ceiling Grid is Damaged And Require Replacement 23127 768 SF 4 $6,192 No
Sub Total for System 4 $14,218
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Exterior Requires Cleaning 23671 768 SF Wall 5 $1,594 No
Exterior Metal Door Requires Repainting 23672 2 Door 3 $1,376 No
Exterior door hardware is damaged and should be replaced 23559 2 Door 2 $1,207 Yes
The Aluminum Window Is Damaged And Requires Replacement 22818 8 Ea. 2 $13,830 Yes
Sub Total for System 4 $18,007
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2030-14 - Americana Lang. Vill. - Bldg. 14 21 $66,213
Facilities Condition AssessmentValle Verde Campus Condition Assessment
27Magellan Consulting, Inc.
The Roof Requires Cleaning 23348 20 SF 2 $362 Yes
Sub Total for System 1 $362
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2030-17 - Americana Lang. Vill. - Bldg. 17
Fire Alarm is Missing or Inadequate 23659 768 SF 1 $8,840 Yes
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 22726 2 Ea. 1 $1,067 Yes
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 22723 768 SF 2 $451 Yes
Security Alarm is Missing or Inadequate 23658 768 SF 2 $1,387 No
Sub Total for System 4 $11,744
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 22984 12 Ea. 3 $6,448 No
Sub Total for System 1 $6,448
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Ductwork Is Damaged And Should Be Replaced 23196 40 LF 3 $761 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 23034 768 SF 3 $1,722 No
The Package Unit HVAC Component Is Damaged And Requires Replacement 23183 2 TonAC 2 $5,334 No
Test And Balancing Required 23175 768 SF 3 $1,341 No
Duct Register is Damaged And Should Be Replaced 23656 2 Ea. 5 $1,651 No
Duct Grill is Damaged And Should Be Replaced 23657 1 Ea. 5 $322 No
Sub Total for System 6 $11,131
Deficiency ID Qty UoM Priority Repair Cost WS&D
Mechanical
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 22916 768 SF 3 $5,788 No
Interior Walls Require Repainting 22857 768 SF 4 $2,055 No
The Suspended Ceiling Grid is Damaged And Require Replacement 23118 768 SF 4 $6,192 No
Sub Total for System 3 $14,034
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Aluminum Window Is Damaged And Requires Replacement 22815 8 Ea. 2 $13,830 Yes
Exterior door hardware is damaged and should be replaced 23561 2 Door 2 $1,207 Yes
The Metal Exterior Door Is Damaged And Requires Replacement 22795 1 Door 2 $2,357 Yes
Exterior Metal Door Requires Repainting 20853 1 Door 3 $688 No
Sub Total for System 4 $18,082
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2030-16 - Americana Lang. Vill. - Bldg. 16 18 $61,440
Building: 2030-16 - Americana Lang. Vill. - Bldg. 16
Fire Alarm is Missing or Inadequate 23663 758 SF 1 $8,834 Yes
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 22727 2 Ea. 1 $1,067 Yes
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 22721 758 SF 2 $444 Yes
Security Alarm is Missing or Inadequate 23662 758 SF 2 $1,369 No
Sub Total for System 4 $11,714
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 22987 12 Ea. 3 $6,448 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 22954 2 Ea. 2 $1,949 Yes
Sub Total for System 2 $8,397
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Ductwork Is Damaged And Should Be Replaced 23661 60 LF 3 $1,141 No
Duct Grill is Damaged And Should Be Replaced 23604 2 Ea. 3 $644 No
Sub Total for System 4 $4,148
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2030-15 - Americana Lang. Vill. - Bldg. 15 19 $55,277
Facilities Condition AssessmentValle Verde Campus Condition Assessment
28Magellan Consulting, Inc.
Interior Walls Require Repainting 22858 768 SF 4 $2,055 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 22919 768 SF 3 $5,788 No
The Suspended Ceiling Grid is Damaged And Require Replacement 23121 768 SF 4 $6,192 No
Sub Total for System 3 $14,034
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Exterior Metal Door Requires Repainting 20851 2 Door 3 $1,376 No
The Exterior Requires Cleaning 22766 768 SF Wall 4 $1,594 No
The Aluminum Window Is Damaged And Requires Replacement 22816 8 Ea. 2 $13,830 Yes
Sub Total for System 3 $16,800
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Metal Roof-To-Curb Flashings Are Damaged And Should Be Resealed 23243 4 LF 2 $262 Yes
Loose/Missing Exposed Panel Fasteners 23302 20 Ea. 2 $752 Yes
Laps In Metal Cover At Hip/Ridge Require Resealing 23285 3 Ea. 2 $295 Yes
Re-Seal Joint Between Metal Z Closure & Roof Panel Is Damaged And Requires Repair 23265 25 LF 2 $420 Yes
The Roof Requires Cleaning 23346 50 SF 2 $369 Yes
Re-Seal Metal Roof Panel Laps (Seams) Require Repair And Re-Seal 23295 30 LF 2 $450 Yes
Sub Total for System 6 $2,548
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2030-18 - Americana Lang. Vill. - Bldg. 18
Fire Alarm is Missing or Inadequate 23655 768 SF 1 $8,840 Yes
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 22725 2 Ea. 1 $1,067 Yes
Security Alarm is Missing or Inadequate 23654 768 SF 2 $1,387 No
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 22724 768 SF 2 $451 Yes
Sub Total for System 4 $11,744
Deficiency ID Qty UoM Priority Repair Cost WS&D
Fire and Life Safety
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 22985 12 Ea. 3 $6,448 No
The Canopy Lighting Is Damaged And Should Be Replaced 22938 1 Ea. 2 $1,764 Yes
The Mounted Building Lighting Is Damaged And Should Be Replaced 22951 2 Ea. 2 $1,949 Yes
The Exterior telephone call-box is rusted and requires replacement 23803 1 Ea. 3 $2,626 No
Sub Total for System 4 $12,787
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Damper is Damaged And Should Be Replaced 23028 1 Ea. 3 $166 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 23032 768 SF 3 $1,722 No
The Package Unit HVAC Component Is Damaged And Requires Replacement 23181 2 TonAC 2 $5,334 No
Duct Grill is Damaged And Should Be Replaced 23608 2 Ea. 3 $644 No
Test And Balancing Required 23174 768 SF 3 $1,341 No
Sub Total for System 5 $9,207
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Walls Require Repainting 22856 768 SF 4 $2,055 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 22917 768 SF 3 $5,788 No
The Room Signage Is Not ADA Compliant With Raised Letters And Braille 23435 2 Ea. 3 $184 No
The Suspended Ceiling Grid is Damaged And Require Replacement 23119 768 SF 4 $6,192 No
Sub Total for System 4 $14,218
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Metal Exterior Door Is Damaged And Requires Replacement 22796 2 Door 2 $4,714 Yes
The Aluminum Window Is Damaged And Requires Replacement 22814 8 Ea. 2 $13,830 Yes
Exterior door hardware is damaged and should be replaced 23562 2 Door 2 $1,207 Yes
Sub Total for System 3 $19,751
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2030-17 - Americana Lang. Vill. - Bldg. 17 21 $68,070
Facilities Condition AssessmentValle Verde Campus Condition Assessment
29Magellan Consulting, Inc.
Fire Alarm Panel Should Be Replaced 23651 1 Ea. 1 $9,677 Yes
Security Alarm Motion Detector Is Missing And Needed 23514 1 Ea. 1 $1,154 No
Sub Total for System 2 $10,831
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 22977 12 Ea. 3 $6,448 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 22960 2 Ea. 2 $1,949 Yes
Sub Total for System 2 $8,397
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Controls Are Inadequate And Should Be Replaced With DDC Controls 23039 768 SF 3 $1,722 No
Duct Cleaning Required 23021 768 SF 3 $721 No
Sub Total for System 2 $2,442
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Walls Require Repainting 22859 768 SF 4 $2,055 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 22918 768 SF 3 $5,788 No
The Suspended Ceiling Grid is Damaged And Require Replacement 23120 768 SF 4 $6,192 No
Sub Total for System 3 $14,034
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Aluminum Window Is Damaged And Requires Replacement 22817 8 Ea. 2 $13,830 Yes
Exterior Metal Door Requires Repainting 20852 2 Door 3 $1,376 No
The Exterior Requires Cleaning 22767 768 SF Wall 4 $1,594 No
Sub Total for System 3 $16,800
Deficiency ID Qty UoM Priority Repair Cost WS&D
Exterior
Metal Roof-To-Curb Flashings Are Damaged And Should Be Resealed 23242 4 LF 2 $262 Yes
Laps In Metal Cover At Hip/Ridge Require Resealing 23286 3 Ea. 2 $295 Yes
Loose/Missing Exposed Panel Fasteners 23303 20 Ea. 2 $752 Yes
Re-Seal Joint Between Metal Z Closure & Roof Panel Is Damaged And Requires Repair 23264 20 LF 2 $337 Yes
The Roof Requires Cleaning 23345 30 SF 2 $366 Yes
Re-Seal Metal Roof Panel Laps (Seams) Require Repair And Re-Seal 23294 35 LF 2 $524 Yes
Sub Total for System 6 $2,535
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2030-19 - Americana Lang. Vill. - Bldg. 19 18 $55,040
Building: 2030-19 - Americana Lang. Vill. - Bldg. 19
Fire Alarm Panel Should Be Replaced 23653 1 Ea. 1 $9,677 Yes
Security Alarm Motion Detector Is Missing And Needed 23511 1 Ea. 1 $1,154 No
Sub Total for System 2 $10,831
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 22983 12 Ea. 3 $6,448 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 23652 1 Ea. 2 $976 Yes
Sub Total for System 2 $7,424
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Cleaning Required 23019 768 SF 3 $721 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 23029 768 SF 3 $1,722 No
The Package Unit HVAC Component Is Damaged And Requires Replacement 23182 2 TonAC 2 $5,334 No
Test And Balancing Required 23176 768 SF 3 $1,341 No
Sub Total for System 4 $9,118
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2030-18 - Americana Lang. Vill. - Bldg. 18 20 $60,755
Facilities Condition AssessmentValle Verde Campus Condition Assessment
30Magellan Consulting, Inc.
Exterior Metal Door Requires Repainting 20839 2 Door 3 $1,376 No
The Aluminum Window Is Damaged And Requires Replacement 20685 8 Ea. 2 $13,830 Yes
Exterior Metal Door Requires Repainting 23649 2 Door 3 $1,376 No
The Exterior Requires Cleaning 20683 768 SF Wall 5 $1,594 No
Sub Total for System 4 $18,176
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Metal Roof-To-Curb Flashings Are Damaged And Should Be Resealed 20691 15 LF 2 $262 Yes
Loose/Missing Exposed Panel Fasteners 20694 20 Ea. 2 $752 Yes
Laps In Metal Cover At Hip/Ridge Require Resealing 20696 3 Ea. 2 $295 Yes
Re-Seal Joint Between Metal Z Closure & Roof Panel Is Damaged And Requires Repair 20695 15 LF 2 $280 Yes
The Roof Requires Cleaning 20692 100 SF 2 $379 Yes
Re-Seal Metal Roof Panel Laps (Seams) Require Repair And Re-Seal 20693 30 LF 2 $450 Yes
Sub Total for System 6 $2,417
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2030-21 - Americana Lang. Vill. - Bldg. 21
Fire Alarm Panel Should Be Replaced 23650 1 Ea. 1 $9,677 Yes
Security Alarm Motion Detector Is Missing And Needed 23513 1 Ea. 1 $1,154 No
Sub Total for System 2 $10,831
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 22978 12 Ea. 3 $6,448 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 22959 2 Ea. 2 $1,949 Yes
Sub Total for System 2 $8,397
Deficiency ID Qty UoM Priority Repair Cost WS&D
Electrical
Controls Are Inadequate And Should Be Replaced With DDC Controls 23040 768 SF 3 $1,722 No
The Package Unit HVAC Component Is Damaged And Requires Replacement 23180 2 TonAC 2 $5,334 No
Duct Cleaning Required 23020 768 SF 3 $721 No
Test And Balancing Required 23179 768 SF 3 $1,341 No
Sub Total for System 4 $9,118
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Suspended Ceiling Grid is Damaged And Require Replacement 23128 768 SF 4 $6,192 No
Interior Walls Require Repainting 22855 768 SF 4 $2,055 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 22920 768 SF 3 $5,788 No
Sub Total for System 3 $14,034
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Exterior Requires Cleaning 22770 768 SF Wall 4 $1,594 No
Exterior Metal Door Requires Repainting 20854 2 Door 3 $1,376 No
The Aluminum Window Is Damaged And Requires Replacement 22823 8 Ea. 2 $13,830 Yes
Sub Total for System 3 $16,800
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Metal Roof-To-Curb Flashings Are Damaged And Should Be Resealed 23246 4 LF 2 $262 Yes
Re-Seal Joint Between Metal Z Closure & Roof Panel Is Damaged And Requires Repair 23268 20 LF 2 $337 Yes
Laps In Metal Cover At Hip/Ridge Require Resealing 23282 3 Ea. 2 $295 Yes
Loose/Missing Exposed Panel Fasteners 23299 20 Ea. 2 $752 Yes
The Roof Requires Cleaning 23352 50 SF 2 $369 Yes
Re-Seal Metal Roof Panel Laps (Seams) Require Repair And Re-Seal 23298 50 LF 2 $748 Yes
Sub Total for System 6 $2,763
Deficiency ID Qty UoM Priority Repair Cost WS&D
Roofing
Sub Total for Building 2030-20 - Americana Lang. Vill. - Bldg. 20 20 $61,944
Building: 2030-20 - Americana Lang. Vill. - Bldg. 20
Facilities Condition AssessmentValle Verde Campus Condition Assessment
31Magellan Consulting, Inc.
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 22970 12 Ea. 3 $6,448 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 23644 2 Ea. 2 $1,949 Yes
Sub Total for System 2 $8,397
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Cleaning Required 23005 768 SF 3 $721 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 23049 768 SF 3 $1,722 No
The Package Unit HVAC Component Is Damaged And Requires Replacement 23187 2 TonAC 2 $5,334 No
Test And Balancing Required 23168 768 SF 3 $1,341 No
Sub Total for System 4 $9,118
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Walls Require Repainting 22872 768 SF 4 $2,055 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 22901 768 SF 3 $5,788 No
The Suspended Ceiling Grid is Damaged And Require Replacement 23110 768 SF 4 $6,192 No
Sub Total for System 3 $14,034
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Aluminum Window Is Damaged And Requires Replacement 22802 8 Ea. 2 $13,830 Yes
Exterior Metal Door Requires Repainting 20847 2 Door 3 $1,376 No
The Exterior Requires Cleaning 22759 768 SF Wall 4 $1,594 No
Sub Total for System 3 $16,800
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Loose/Missing Exposed Panel Fasteners 23309 20 Ea. 2 $752 Yes
Laps In Metal Cover At Hip/Ridge Require Resealing 23281 3 Ea. 2 $295 Yes
Re-Seal Metal Roof Panel Laps (Seams) Require Repair And Re-Seal 23288 50 LF 2 $748 Yes
Metal Roof-To-Curb Flashings Are Damaged And Should Be Resealed 23643 4 LF 2 $262 Yes
Re-Seal Joint Between Metal Z Closure & Roof Panel Is Damaged And Requires Repair 23269 20 LF 2 $337 Yes
Sub Total for System 5 $2,393
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2030-22 - Americana Lang. Vill. - Bldg. 22
Security Alarm Motion Detector Is Missing And Needed 20704 1 Ea. 2 $1,154 No
Fire Alarm is Missing or Inadequate 20705 768 SF 1 $8,840 Yes
Sub Total for System 2 $9,994
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20703 12 Ea. 4 $6,448 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 20702 2 Ea. 2 $1,949 Yes
Sub Total for System 2 $8,397
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Cleaning Required 20700 768 SF 5 $721 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 20699 768 SF 4 $1,722 No
The Package Unit HVAC Component Is Damaged And Requires Replacement 20701 2 TonAC 2 $5,334 No
Test And Balancing Required 20698 768 SF 3 $1,341 No
Sub Total for System 4 $9,118
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Walls Require Repainting 20689 768 SF 5 $2,055 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 20690 768 SF 3 $5,788 No
The Suspended Ceiling Grid is Damaged And Require Replacement 20688 768 SF 3 $6,192 No
Sub Total for System 3 $14,034
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2030-21 - Americana Lang. Vill. - Bldg. 21 21 $62,137
Facilities Condition AssessmentValle Verde Campus Condition Assessment
32Magellan Consulting, Inc.
Metal Roof-To-Curb Flashings Are Damaged And Should Be Resealed 23240 4 LF 2 $262 Yes
Loose/Missing Exposed Panel Fasteners 23307 26 Ea. 2 $977 Yes
Re-Seal Joint Between Metal Z Closure & Roof Panel Is Damaged And Requires Repair 23271 18 LF 2 $315 Yes
Laps In Metal Cover At Hip/Ridge Require Resealing 23279 3 Ea. 2 $295 Yes
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2030-24 - Americana Lang. Vill. - Bldg. 24
The Fixed Shelving Storage Cabinets Require Replacement 22713 10 LF 4 $877 No
Sub Total for System 1 $877
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Fire Alarm Panel Should Be Replaced 22992 1 Ea. 1 $9,677 Yes
Security Alarm Motion Detector Is Missing And Needed 23509 2 Ea. 1 $2,310 No
Sub Total for System 2 $11,987
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Mounted Building Lighting Is Damaged And Should Be Replaced 23642 2 Ea. 2 $1,949 Yes
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 22969 32 Ea. 3 $17,197 No
Panelboard is not Labeled for Safety 23155 200 Amps 1 $524 Yes
Sub Total for System 3 $19,671
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Cleaning Required 23006 1,886 SF 3 $1,769 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 23047 1,886 SF 3 $4,226 No
Test And Balancing Required 23164 1,886 SF 3 $3,296 No
Sub Total for System 3 $9,291
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Walls Require Repainting 22871 1,886 SF 4 $5,045 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 22899 1,214 SF 3 $9,149 No
The Carpet Flooring Is Damaged And Requires Replacement 22891 672 SF 3 $5,933 No
The Suspended Ceiling Grid is Damaged And Require Replacement 23112 1,886 SF 4 $15,206 No
Sub Total for System 4 $35,333
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Exterior Metal Door Requires Repainting 20855 3 Door 3 $2,064 No
The Aluminum Window Is Damaged And Requires Replacement 22804 22 Ea. 2 $38,031 Yes
The Exterior Requires Cleaning 22761 1,886 SF Wall 4 $3,913 No
Sub Total for System 3 $44,008
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Loose/Missing Exposed Panel Fasteners 23308 50 Ea. 2 $1,880 Yes
Metal Roof-To-Curb Flashings Are Damaged And Should Be Resealed 23241 12 LF 2 $262 Yes
Edge Metal Is Loose And Should Be Resecured 23358 6 LF 2 $180 Yes
Laps In Metal Cover At Hip/Ridge Require Resealing 23280 7 Ea. 2 $298 Yes
The Roof Requires Cleaning 23333 20 SF 2 $362 Yes
Re-Seal Metal Roof Panel Laps (Seams) Require Repair And Re-Seal 23289 100 LF 2 $1,496 Yes
Re-Seal Joint Between Metal Z Closure & Roof Panel Is Damaged And Requires Repair 23270 58 LF 2 $753 Yes
Sub Total for System 7 $5,232
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2030-23 - Americana Lang. Vill. - Bldg. 23 23 $126,399
Building: 2030-23 - Americana Lang. Vill. - Bldg. 23
Security Alarm Motion Detector Is Missing And Needed 23510 1 Ea. 1 $1,154 No
Fire Alarm Panel Should Be Replaced 23645 1 Ea. 1 $9,677 Yes
Sub Total for System 2 $10,831
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2030-22 - Americana Lang. Vill. - Bldg. 22 19 $61,574
Facilities Condition AssessmentValle Verde Campus Condition Assessment
33Magellan Consulting, Inc.
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Walls Require Repainting 22878 758 SF 4 $2,027 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 22902 758 SF 3 $5,713 No
The Suspended Ceiling Grid is Damaged And Require Replacement 23117 758 SF 4 $6,112 No
Sub Total for System 3 $13,852
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Exterior Metal Door Requires Repainting 20857 2 Door 3 $1,376 No
The Exterior Requires Cleaning 22764 758 SF Wall 4 $1,572 No
The Aluminum Window Is Damaged And Requires Replacement 22806 8 Ea. 2 $13,830 Yes
Sub Total for System 3 $16,779
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Metal Roof-To-Curb Flashings Are Damaged And Should Be Resealed 23236 8 LF 2 $262 Yes
Loose/Missing Exposed Panel Fasteners 23306 26 Ea. 2 $977 Yes
Laps In Metal Cover At Hip/Ridge Require Resealing 23278 3 Ea. 2 $295 Yes
Re-Seal Joint Between Metal Z Closure & Roof Panel Is Damaged And Requires Repair 23272 23 LF 2 $386 Yes
The Roof Requires Cleaning 23335 25 SF 2 $364 Yes
Re-Seal Metal Roof Panel Laps (Seams) Require Repair And Re-Seal 23291 20 LF 2 $298 Yes
Sub Total for System 6 $2,583
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2030-25 - Americana Lang. Vill. - Bldg. 25
Security Alarm Motion Detector Is Missing And Needed 23508 1 Ea. 1 $1,154 No
Fire Alarm Panel is Missing and is Needed 23641 1 Ea. 1 $3,727 Yes
Sub Total for System 2 $4,881
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 22976 12 Ea. 3 $6,448 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 23640 2 Ea. 2 $1,949 Yes
Sub Total for System 2 $8,397
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Test And Balancing Required 23165 730 SF 3 $1,276 No
Duct Cleaning Required 23008 730 SF 3 $684 No
The Package Unit HVAC Component Is Damaged And Requires Replacement 23184 2 TonAC 2 $5,334 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 23048 730 SF 3 $1,636 No
Sub Total for System 4 $8,931
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Walls Require Repainting 22869 730 SF 4 $1,953 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 22898 730 SF 3 $5,502 No
The Suspended Ceiling Grid is Damaged And Require Replacement 23111 730 SF 4 $5,886 No
Sub Total for System 3 $13,341
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Metal Exterior Door Is Damaged And Requires Repair 22783 2 Door 2 $2,168 Yes
The Metal Exterior Door Is Damaged And Requires Repair 20856 2 Door 2 $2,168 Yes
The Aluminum Window Is Damaged And Requires Replacement 22803 8 Ea. 2 $13,830 Yes
The Exterior Requires Cleaning 22760 730 SF Wall 4 $1,514 No
Sub Total for System 4 $19,680
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Re-Seal Metal Roof Panel Laps (Seams) Require Repair And Re-Seal 23290 30 LF 2 $450 Yes
Sub Total for System 5 $2,299
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2030-24 - Americana Lang. Vill. - Bldg. 24 20 $57,528
Facilities Condition AssessmentValle Verde Campus Condition Assessment
34Magellan Consulting, Inc.
Fire Alarm Panel is Missing and is Needed 23648 1 Ea. 1 $3,727 Yes
Security Alarm Motion Detector Is Missing And Needed 23507 1 Ea. 1 $1,154 No
Sub Total for System 2 $4,881
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 22974 12 Ea. 3 $6,448 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 23647 2 Ea. 2 $1,949 Yes
Sub Total for System 2 $8,397
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Cleaning Required 23010 768 SF 3 $721 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 23042 768 SF 3 $1,722 No
The Package Unit HVAC Component Is Damaged And Requires Replacement 23185 2 TonAC 2 $5,334 No
Duct Grill is Damaged And Should Be Replaced 23598 2 Ea. 3 $644 No
Duct Grill is Damaged And Should Be Replaced 23646 1 Ea. 5 $322 No
Test And Balancing Required 23171 768 SF 3 $1,341 No
Sub Total for System 6 $10,085
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Walls Require Repainting 22877 768 SF 4 $2,055 No
The Suspended Ceiling Grid is Damaged And Require Replacement 23116 768 SF 4 $6,192 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 22903 768 SF 3 $5,788 No
Sub Total for System 3 $14,034
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Metal Exterior Door Is Damaged And Requires Replacement 22798 1 Door 2 $2,357 Yes
The Aluminum Window Is Damaged And Requires Replacement 22805 8 Ea. 2 $13,830 Yes
Exterior Metal Door Requires Repainting 20858 1 Door 3 $688 No
Exterior door hardware is damaged and should be replaced 23565 1 Door 2 $604 Yes
The Exterior Requires Cleaning 22765 768 SF Wall 4 $1,594 No
Sub Total for System 5 $19,074
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Roof Requires Cleaning 23336 100 SF 2 $379 Yes
Metal Roof-To-Curb Flashings Are Damaged And Should Be Resealed 23237 4 LF 2 $262 Yes
Sub Total for System 2 $641
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2030-28 - Americana Lang. Vill. - Bldg. 28 20 $57,112
Building: 2030-28 - Americana Lang. Vill. - Bldg. 28
Security Alarm Motion Detector Is Missing And Needed 23638 1 Ea. 2 $1,154 No
Fire Alarm Panel is Missing and is Needed 23639 1 Ea. 1 $3,727 Yes
Sub Total for System 2 $4,881
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 22975 12 Ea. 3 $6,448 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 23637 2 Ea. 2 $1,949 Yes
Sub Total for System 2 $8,397
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Cleaning Required 23009 758 SF 3 $712 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 23041 758 SF 3 $1,698 No
Test And Balancing Required 23172 758 SF 3 $1,325 No
Sub Total for System 3 $3,735
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2030-25 - Americana Lang. Vill. - Bldg. 25 19 $50,227
Facilities Condition AssessmentValle Verde Campus Condition Assessment
35Magellan Consulting, Inc.
The Metal Exterior Door Is Damaged And Requires Replacement 23635 1 Door 2 $2,357 Yes
The Aluminum Window Is Damaged And Requires Replacement 22808 4 Ea. 2 $6,914 Yes
Exterior door hardware is damaged and should be replaced 23567 1 Door 2 $604 Yes
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Metal Roof-To-Curb Flashings Are Damaged And Should Be Resealed 23238 8 LF 2 $262 Yes
Loose/Missing Exposed Panel Fasteners 23305 19 Ea. 2 $713 Yes
Laps In Metal Cover At Hip/Ridge Require Resealing 23277 3 Ea. 2 $295 Yes
Re-Seal Joint Between Metal Z Closure & Roof Panel Is Damaged And Requires Repair 23274 10 LF 2 $226 Yes
The Roof Requires Cleaning 23337 100 SF 2 $379 Yes
Re-Seal Metal Roof Panel Laps (Seams) Require Repair And Re-Seal 23292 24 LF 2 $359 Yes
Sub Total for System 6 $2,233
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2030-30 - Americana Lang. Vill. - Bldg. 30
Fire Alarm Panel is Missing and is Needed 23476 1 Ea. 1 $3,727 Yes
Security Alarm Motion Detector Is Missing And Needed 23506 1 Ea. 1 $1,154 No
Sub Total for System 2 $4,881
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Mounted Building Lighting Is Damaged And Should Be Replaced 22949 2 Ea. 2 $1,949 Yes
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 22971 12 Ea. 3 $6,448 No
Sub Total for System 2 $8,397
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Grill is Damaged And Should Be Replaced 23600 1 Ea. 3 $322 No
Test And Balancing Required 23169 724 SF 3 $1,265 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 23045 724 SF 3 $1,622 No
The Package Unit HVAC Component Is Damaged And Requires Replacement 23186 2 TonAC 2 $5,334 No
Duct Cleaning Required 23012 724 SF 3 $679 No
Duct Grill is Damaged And Should Be Replaced 23599 2 Ea. 3 $644 No
Sub Total for System 6 $9,866
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Walls Require Repainting 22874 724 SF 4 $1,936 No
The Suspended Ceiling Grid is Damaged And Require Replacement 23113 724 SF 4 $5,837 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 22905 724 SF 3 $5,456 No
Sub Total for System 3 $13,230
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Metal Exterior Door Is Damaged And Requires Repair 22780 1 Door 2 $1,085 Yes
The Aluminum Window Is Damaged And Requires Replacement 22807 8 Ea. 2 $13,830 Yes
Exterior door hardware is damaged and should be replaced 23566 1 Door 2 $604 Yes
The Metal Exterior Door Is Damaged And Requires Replacement 22797 1 Door 2 $2,357 Yes
The Exterior Requires Cleaning 22762 724 SF Wall 4 $1,502 No
Sub Total for System 5 $19,378
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Metal Roof-To-Curb Flashings Are Damaged And Should Be Resealed 23239 4 LF 2 $262 Yes
Re-Seal Joint Between Metal Z Closure & Roof Panel Is Damaged And Requires Repair 23275 10 LF 2 $226 Yes
Laps In Metal Cover At Hip/Ridge Require Resealing 23276 3 Ea. 2 $295 Yes
Loose/Missing Exposed Panel Fasteners 23304 15 Ea. 2 $564 Yes
The Roof Requires Cleaning 23339 20 SF 2 $362 Yes
Re-Seal Metal Roof Panel Laps (Seams) Require Repair And Re-Seal 23293 15 LF 2 $224 Yes
Sub Total for System 6 $1,933
Deficiency ID Qty UoM Priority Repair Cost WS&D
Roofing
Sub Total for Building 2030-29 - Americana Lang. Vill. - Bldg. 29 24 $57,685
Building: 2030-29 - Americana Lang. Vill. - Bldg. 29
Facilities Condition AssessmentValle Verde Campus Condition Assessment
36Magellan Consulting, Inc.
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 22981 12 Ea. 3 $6,448 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 22956 2 Ea. 2 $1,949 Yes
Sub Total for System 2 $8,397
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Cleaning Required 23017 720 SF 3 $675 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 23036 720 SF 3 $1,614 No
Sub Total for System 2 $2,290
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Suspended Ceiling Grid is Damaged And Require Replacement 23125 720 SF 4 $5,806 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 22913 720 SF 3 $5,425 No
Sub Total for System 2 $11,231
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Exterior Metal Door Requires Repainting 20833 2 Door 3 $1,376 No
The Aluminum Window Is Damaged And Requires Replacement 22821 8 Ea. 2 $13,830 Yes
The Exterior Requires Cleaning 22768 720 SF Wall 4 $1,494 No
Sub Total for System 3 $16,700
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Loose/Missing Exposed Panel Fasteners 23301 20 Ea. 2 $752 Yes
Laps In Metal Cover At Hip/Ridge Require Resealing 23284 3 Ea. 2 $295 Yes
Metal Roof-To-Curb Flashings Are Damaged And Should Be Resealed 23245 8 LF 2 $262 Yes
Re-Seal Metal Roof Panel Laps (Seams) Require Repair And Re-Seal 23296 20 LF 2 $298 Yes
Re-Seal Joint Between Metal Z Closure & Roof Panel Is Damaged And Requires Repair 23266 10 LF 2 $226 Yes
Joint Between Rake Cover And Roof Panel Requires Re-Sealing 23634 10 LF 2 $753 Yes
Edge Metal Is Loose And Should Be Resecured 23359 2 LF 2 $60 Yes
Sub Total for System 7 $2,646
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2030-31 - Americana Lang. Vill. - Bldg. 31
Security Alarm Motion Detector Is Missing And Needed 23505 1 Ea. 1 $1,154 No
Fire Alarm Panel is Missing and is Needed 23636 1 Ea. 1 $3,727 Yes
Sub Total for System 2 $4,881
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 22972 12 Ea. 3 $6,448 No
The Mounted Building Lighting Is Damaged And Should Be Replaced 22948 2 Ea. 2 $1,949 Yes
Sub Total for System 2 $8,397
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Cleaning Required 23011 718 SF 3 $673 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 23044 718 SF 3 $1,609 No
Sub Total for System 2 $2,282
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Walls Require Repainting 22875 718 SF 4 $1,920 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 22904 718 SF 3 $5,411 No
The Suspended Ceiling Grid is Damaged And Require Replacement 23114 718 SF 4 $5,789 No
Sub Total for System 3 $13,120
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Exterior Requires Cleaning 22763 718 SF Wall 4 $1,491 No
Exterior Metal Door Requires Repainting 20832 1 Door 3 $688 No
Sub Total for System 5 $12,054
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2030-30 - Americana Lang. Vill. - Bldg. 30 20 $42,968
Facilities Condition AssessmentValle Verde Campus Condition Assessment
37Magellan Consulting, Inc.
Built Up Roofing (Bur) Lap Seams Are Open Or Deteriorated 18961 20 LF 2 $990 Yes
Built Up Roofing (Bur) Membrane Has Holes That Should Be Repaired 18960 10 Ea. 2 $1,207 Yes
The Multi-Ply Bitumen Roof System Is Damaged And Requires Replacement 18892 44,000 SF 1 $530,009 No
Built Up Roofing (Bur) Covering Has Blisters That Should Be Repaired 18959 50 Ea. 2 $6,403 Yes
Counter Flashing Is Damaged Or Loose And Should Be Repaired 18876 100 LF 2 $1,356 Yes
Debris In Gutters Should Be Removed 18868 10 LF 2 $359 Yes
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2040 - Humanities Building
Fire Alarm Panel Should Be Replaced 23632 1 Ea. 1 $9,677 Yes
Sub Total for System 1 $9,677
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Refrigerated Water Cooler is Damaged And Should Be Replaced 23135 1 Ea. 3 $4,366 No
The Urinal Plumbing Fixtures Are Damaged And Should Be Replaced 23795 4 Ea. 3 $6,115 No
Sub Total for System 2 $10,481
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 23071 3 Ea. 3 $1,059 No
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 22982 14 Ea. 3 $7,524 No
Sub Total for System 2 $8,583
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Duct Cleaning Required 23016 768 SF 3 $721 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 23035 768 SF 3 $1,722 No
Sub Total for System 2 $2,442
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Interior Walls Require Repainting 22862 768 SF 4 $2,055 No
The Suspended Ceiling Grid is Damaged And Require Replacement 23124 768 SF 4 $6,192 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 22912 768 SF 3 $5,788 No
Sub Total for System 3 $14,034
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Exterior Metal Door Requires Repainting 20834 4 Door 3 $2,754 No
The Aluminum Window Is Damaged And Requires Replacement 22822 4 Ea. 2 $6,914 Yes
The Exterior Requires Cleaning 22769 768 SF Wall 4 $1,594 No
Sub Total for System 3 $11,262
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Membrane Flashings At Equipment Curbs Are Damaged And Should Be Repaired 23225 4 LF 2 $62 Yes
Metal Roof-To-Curb Flashings Are Damaged And Should Be Resealed 23244 4 LF 2 $262 Yes
Laps In Metal Cover At Hip/Ridge Require Resealing 23283 3 Ea. 2 $295 Yes
Loose/Missing Exposed Panel Fasteners 23300 23 Ea. 2 $864 Yes
Penetration Boot Is Damaged And Should Be Replaced 23382 2 Ea. 2 $262 Yes
The Roof Requires Cleaning 23349 20 SF 2 $362 Yes
Re-Seal Metal Roof Panel Laps (Seams) Require Repair And Re-Seal 23297 38 LF 2 $568 Yes
Re-Seal Joint Between Metal Z Closure & Roof Panel Is Damaged And Requires Repair 23267 25 LF 2 $420 Yes
Sub Total for System 8 $3,096
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2030-32 - Americana Lang. Vill. - Bldg. 32 21 $59,576
Building: 2030-32 - Americana Lang. Vill. - Bldg. 32
Security Alarm Motion Detector Is Missing And Needed 23512 1 Ea. 1 $1,154 No
Fire Alarm Panel is Missing and is Needed 23633 1 Ea. 1 $3,727 Yes
Sub Total for System 2 $4,881
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2030-31 - Americana Lang. Vill. - Bldg. 31 18 $46,146
Facilities Condition AssessmentValle Verde Campus Condition Assessment
38Magellan Consulting, Inc.
The Restroom is Not ADA Compliant 23775 4 Ea. 3 $103,465 No
Restroom vent lines, water lines and sewer lines require replacement 23726 12 Fixture 2 $4,368 No
The Custodial Mop Or Service Sink Is Damaged And Should Be Replaced 18890 4 Ea. 4 $15,792 No
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20822 6 Ea. 4 $2,118 No
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20823 5 Ea. 4 $1,765 No
Total electrical upgrage required 23715 65,693 SF 2 $1,195,613 No
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 18884 14 Ea. 4 $4,943 No
The Incandescent Lighting Is Damaged And Should Be Replaced 20821 34 Ea. 4 $12,365 No
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 18886 964 Ea. 4 $518,063 No
The 2 X 2 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 18885 91 Ea. 4 $33,281 No
Sub Total for System 7 $1,768,148
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Exhaust Fan Ventilation Is Damaged And Should Be Replaced 20664 1 Ea. 4 $1,935 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 18882 87,477 SF 4 $196,025 No
Test And Balancing Required 23755 87,477 SF 3 $152,840 No
Duct Cleaning Required 18883 87,477 SF 5 $82,093 No
Exhaust Fan Ventilation Is Missing And Should Be Installed 20663 2 Ea. 5 $4,248 No
Duct Grill is Damaged And Should Be Replaced 18889 226 Ea. 5 $72,744 No
Sub Total for System 6 $509,884
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Directional / wayfinding signage missing or not accessible. 23782 75 Ea. 5 $9,460 No
Interior Doors Require Repainting 18897 138 Door 5 $7,344 No
Interior Walls Require Repainting 18896 60,000 SF 5 $160,524 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 18899 64,400 SF 3 $485,325 No
Restrooms require complete renovation 23834 1 LS 3 $236,600 No
The Interior Door Hardware is Damaged and Requires Replacement 18939 6 Ea. 2 $6,112 No
The Suspended Ceiling Grid is Damaged And Require Replacement 18895 87,477 SF 3 $705,292 No
The Carpet Flooring Is Damaged And Requires Replacement 18898 12,500 SF 3 $110,379 No
Sub Total for System 8 $1,721,036
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Metal Exterior Door Is Damaged And Requires Replacement 18861 4 Door 2 $9,429 Yes
The Aluminum Storefront Exterior Door Is Damaged And Requires Replacement 18862 16 Door 2 $69,690 Yes
Exterior door hardware is damaged and should be replaced 18863 6 Door 2 $3,620 Yes
The Steel Window Is Damaged And Requires Replacement 18865 16 Ea. 2 $32,036 Yes
The Steel Window Is Damaged And Requires Replacement 18864 24 Ea. 2 $48,053 Yes
Sub Total for System 5 $162,828
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Gutter Screens Are Missing And Needed 18869 10 LF 2 $260 No
Gutter Joints Require Repair 18870 5 Ea. 2 $162 No
Membrane Flashing At Curb (<2') 18875 100 LF 2 $1,558 Yes
Lead Flashing Is Damaged And Should Be Repaired 18881 2 Ea. 2 $588 Yes
Expansion Joint Cover Is Missing Or Damaged And Should Be Replaced 18878 120 LF 2 $8,590 Yes
Exhaust Fan Curbs are too Low and Should be Raised and Reflashed (<8") 18880 4 Ea. 2 $5,576 No
Expansion Joint Termination At End Wall Is Damaged And Should Be Repaired 18879 2 Ea. 2 $897 Yes
Expansion Joint Laps Are Damaged And Should Be Repaired 18877 20 Ea. 2 $7,218 Yes
The Roof Requires Cleaning 18893 100 SF 2 $379 Yes
Tapered Insulation Is Required To Eliminate Ponding When Re-Roofing 18873 50 SF 3 $393 No
Awning Or Canopy Roofing Decking Is Damaged 20669 30 SF 4 $277 No
The Roof Drains Are Clogged 18871 3 Ea. 2 $351 Yes
Membrane Flashings At Drain Is Damaged And Should Be Repaired 18872 4 Ea. 2 $588 Yes
Membrane Flashings At Metal Edge Are Damaged And Should Be Repaired 18874 100 LF 2 $1,299 Yes
The Multi-Ply Bitumen Roof Coating Requires Repair 19027 2,500 SF 2 $21,831 Yes
Sub Total for System 21 $590,291
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Facilities Condition AssessmentValle Verde Campus Condition Assessment
39Magellan Consulting, Inc.
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Suspended Ceiling Grid is Damaged And Require Replacement 18985 43,800 SF 3 $353,142 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 18994 29,000 SF 3 $218,547 No
Interior Toilet Partition Require Repair Or Replacement 19005 3 Ea. 4 $7,260 No
The Ceramic Tile Flooring Is Damaged And Requires Replacement 18995 80 SF 3 $1,276 No
The Interior Door Hardware is Damaged and Requires Replacement 18992 12 Ea. 2 $12,223 No
Interior Doors Require Replacement 18990 4 Door 3 $5,038 No
The Carpet Flooring Is Damaged And Requires Replacement 18993 14,600 SF 3 $128,922 No
Interior Doors Require Repair 18989 6 Door 5 $2,730 No
Interior Walls Require Repainting 18987 65,000 SF 5 $173,901 No
The Exposed Ceilings Are Damaged And Requires Repainting 18986 29,200 SF 5 $63,145 No
Concrete Flooring Epoxy Requires Replacement 20812 29,000 SF 5 $56,830 No
Directional / wayfinding signage missing or not accessible. 23783 75 Ea. 5 $9,460 No
Interior Doors Require Repainting 18991 67 Door 5 $3,565 No
Sub Total for System 13 $1,036,039
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Aluminum Window Is Damaged And Requires Replacement 18906 18 Ea. 2 $31,117 Yes
The Aluminum Storefront Exterior Door Is Damaged And Requires Replacement 18903 2 Door 2 $8,711 Yes
Exterior door hardware is damaged and should be replaced 18905 9 Door 2 $5,431 Yes
The Overhead Door Is Damaged And Requires Replacement 18904 5 Door 2 $17,121 Yes
The Metal Exterior Door Is Damaged And Requires Repair 18902 4 Door 2 $4,335 Yes
Sub Total for System 5 $66,714
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Awning Or Canopy Roofing Decking Is Damaged 20668 50 SF 4 $462 No
Edge Metal Is Missing And Is Needed 18910 50 LF 2 $1,629 Yes
Exhaust Fan Curbs are too Low and Should be Raised and Reflashed (<8") 18914 3 Ea. 2 $4,182 No
Expansion Joint Cover Is Missing Or Damaged And Should Be Replaced 18912 160 LF 2 $11,453 Yes
Concrete Decking Is Damaged And Requires Repair 18979 40 SF 2 $402 Yes
The Multi-Ply Bitumen Roof System Is Damaged And Requires Replacement 18983 36,000 SF 1 $433,644 No
Built Up Roofing (Bur) Covering Has Blisters That Should Be Repaired 18980 3 Ea. 2 $384 Yes
Built Up Roofing (Bur) Membrane Has Holes That Should Be Repaired 18981 7 Ea. 2 $844 Yes
The Roof Operable Hatch Is Damaged And Requires Repair 18907 1 Ea. 2 $568 Yes
The Roof Requires Cleaning 18982 100 SF 2 $379 Yes
Tapered Insulation Is Required To Eliminate Ponding When Re-Roofing 18909 1,500 SF 3 $4,324 No
Expansion Joint Laps Are Damaged And Should Be Repaired 18911 20 Ea. 2 $7,218 Yes
Expansion Joint Termination At End Wall Is Damaged And Should Be Repaired 18913 2 Ea. 2 $897 Yes
Membrane Flashings At Drain Is Damaged And Should Be Repaired 18908 4 Ea. 2 $588 Yes
Sub Total for System 14 $466,976
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2050 - Math and Science Building
The Base Storage Cabinets Require Replacement 18900 100 LF 4 $28,423 No
Sub Total for System 1 $28,423
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 18887 87,477 SF 2 $51,339 Yes
Fire Alarm Panel is Missing and is Needed 20825 1 Ea. 1 $3,727 Yes
Fire Alarm is Missing or Inadequate 18888 87,477 SF 1 $161,984 Yes
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 20824 1,000 SF 2 $586 Yes
Sub Total for System 4 $217,636
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Refrigerated Water Cooler is Damaged And Should Be Replaced 18891 8 Ea. 4 $34,922 No
Sub Total for System 4 $158,547
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2040 - Humanities Building 56 $5,156,793
Facilities Condition AssessmentValle Verde Campus Condition Assessment
40Magellan Consulting, Inc.
Curbs Have Been Abandoned And Should Be Removed 23235 1 Ea. 2 $493 No
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2060 - Day Care Center
The Base Storage Cabinets Require Replacement 18996 96 LF 4 $27,285 No
The Upper Storage Cabinets Require Replacement 18997 96 LF 4 $17,452 No
Sub Total for System 2 $44,737
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 20552 73 Ea. 2 $38,946 Yes
Fire Alarm is Missing or Inadequate 18972 72,948 SF 1 $147,211 Yes
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 18969 72,948 SF 2 $42,812 Yes
Security Alarm is Missing or Inadequate 18971 72,948 SF 2 $131,657 No
Sub Total for System 4 $360,626
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Toilets Plumbing Fixtures Are Damaged And Should Be Replaced 18976 3 Ea. 3 $3,971 No
The Urinal Plumbing Fixtures Are Damaged And Should Be Replaced 20869 1 Ea. 3 $1,529 No
The Showers Plumbing Fixtures Are Damaged And Should Be Replaced 18977 1 Ea. 3 $864 No
Laboratory/art sinks are damaged and should be replaced 20871 1 Ea. 3 $9,475 No
The Restroom is Not ADA Compliant 23776 4 Ea. 3 $103,465 No
The Refrigerated Water Cooler is Damaged And Should Be Replaced 18978 5 Ea. 4 $21,827 No
The Rest Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 18975 3 Ea. 4 $4,919 No
The Custodial Mop Or Service Sink Is Damaged And Should Be Replaced 18973 2 Ea. 4 $7,897 No
Trench drain requires cleaning 20884 8 Ea. 3 $6,359 No
The Class Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 18974 2 Ea. 4 $4,104 No
Floor drain requires cleaning 20883 9 Ea. 3 $5,686 No
Restroom vent lines, water lines and sewer lines require replacement 23742 35 Fixture 2 $12,740 No
Sub Total for System 12 $182,837
Deficiency ID Qty UoM Priority Repair Cost WS&D
Plumbing
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 18962 40 Ea. 4 $14,123 No
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20671 84 Ea. 4 $29,659 No
The Canopy Lighting Is Damaged And Should Be Replaced 18921 3 Ea. 2 $5,291 Yes
The Mounted Building Lighting Is Damaged And Should Be Replaced 18922 4 Ea. 2 $3,900 Yes
The Panelboard Is Damaged And Should Be Replaced 18967 450 Amps 2 $13,696 Yes
The Power Service Is Inadequate And Should Be Upgraded 18966 900 Amps 3 $47,724 No
The Electrical Circuit Capacity Is Inadequate 20813 5 EACH 4 $4,721 No
The Incandescent Lighting Is Damaged And Should Be Replaced 20549 2 Ea. 4 $728 No
The Pendant Lighting Is Damaged And Should Be Replaced 18965 4 Ea. 4 $3,733 No
The 2 X 2 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 18963 345 Ea. 4 $126,170 No
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 18964 589 Ea. 4 $316,534 No
The Electrical Circuit Capacity Is Inadequate 18968 168 EACH 4 $158,657 No
Sub Total for System 12 $724,935
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Abandoned equipment left in place 20814 6 Ea. 4 $22,943 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 18917 72,948 SF 4 $163,467 No
Exhaust Fan Ventilation Is Damaged And Should Be Replaced 23760 6 Ea. 4 $11,612 No
Small HVAC Circulating Pump requies Replacement 20815 6 Ea. 2 $45,689 Yes
The Large Diameter Exhausts/Hoods Are Missing/Damaged And Require Replacement 18915 3 Ea. 2 $5,107 No
Test And Balancing Required 18916 72,948 SF 3 $127,455 No
Duct Register is Damaged And Should Be Replaced 18919 154 Ea. 5 $127,100 No
Duct Register is Damaged And Should Be Replaced 20670 10 Ea. 5 $8,254 No
Duct Grill is Damaged And Should Be Replaced 18920 68 Ea. 5 $21,887 No
Duct Cleaning Required 18918 72,948 SF 5 $68,459 No
Sub Total for System 10 $601,972
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2050 - Math and Science Building 72 $3,484,836
Facilities Condition AssessmentValle Verde Campus Condition Assessment
41Magellan Consulting, Inc.
Duct Grill is Damaged And Should Be Replaced 23597 24 Ea. 3 $7,724 No
Test And Balancing Required 23166 6,857 SF 3 $11,981 No
The Package Unit HVAC Component Is Damaged And Requires Replacement 23188 9 TonAC 2 $24,002 No
Duct Cleaning Required 23004 6,857 SF 3 $6,436 No
The Roof Compressor Is Damaged And Requires Replacement 23003 9 TonAC 3 $26,192 No
The Evaporative Cooling Unit Is Damaged And Requires Replacement 23700 1 Ea. 3 $9,071 No
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Plaster Ceilings Are Damaged And Requires Repainting 23096 500 SF 3 $874 No
The Carpet Flooring Is Damaged And Requires Replacement 22893 420 SF 3 $3,709 No
Interior Doors Require Repainting 22883 43 Door 3 $2,288 No
Interior Walls Require Repainting 22867 6,857 SF 4 $18,346 No
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 22907 6,300 SF 3 $47,477 No
Sub Total for System 5 $72,693
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Aluminum Window Is Damaged And Requires Replacement 22811 2 Ea. 2 $3,458 Yes
The Aluminum Window Is Damaged And Requires Replacement 22812 3 Ea. 2 $5,185 Yes
The Aluminum Window Is Damaged And Requires Replacement 22810 1 Ea. 2 $1,729 Yes
Exterior door hardware is damaged and should be replaced 23570 4 Door 2 $2,413 Yes
The Aluminum Storefront Exterior Door Is Damaged And Requires Replacement 22800 4 Door 2 $17,423 Yes
The Aluminum Window Is Damaged And Requires Replacement 22813 2 Ea. 2 $3,458 Yes
The Wood Exterior Is Damaged And Requires Replacement 23397 800 SF Wall 3 $10,725 No
The Exterior Requires Painting 22772 1,000 SF Wall 4 $2,988 No
The Steel Window Is Damaged And Requires Replacement 22825 2 Ea. 2 $4,004 Yes
The Exterior Soffit Is Damaged And Requires Replacement 22743 6,857 SF 3 $166,343 No
Sub Total for System 10 $217,727
Deficiency ID Qty UoM Priority Repair Cost WS&D
Exterior
Gutter Joints Require Repair 23256 20 Ea. 2 $644 No
Gas Line/Conduit On New Supports Is Unseated And Should Be Supported 23247 3 Ea. 2 $333 Yes
Flashing At Termination Wall Is Damaged And Should Be Repaired 23260 5 Ea. 2 $369 Yes
Gutter Screens Are Missing And Needed 23254 20 LF 2 $288 No
Lead Flashing Is Damaged And Should Be Repaired 23430 15 Ea. 2 $4,404 Yes
HVAC Curbs are too Low and Should be Raised and Reflashed (<8") 23229 4 Ea. 2 $5,536 No
Gutters Are Damaged 23255 20 LF 2 $306 No
Field-Wrap Flashing At Penetration Is Damaged And Should Be Repaired 23385 2 Ea. 2 $206 Yes
Edge Metal At Gutter Is Damaged And Should Be Replaced 23534 20 Ea. 2 $198 Yes
Debris In Gutters Should Be Removed 23248 20 LF 2 $359 Yes
Damaged Hip/Ridge 23262 50 LF 2 $582 Yes
Edge Metal Is Damaged And Should Be Replaced 23356 35 LF 2 $1,192 Yes
Exhaust Fan Curbs are too Low and Should be Raised and Reflashed (<8") 23226 4 Ea. 2 $5,576 No
Edge Metal Is Loose And Should Be Resecured 23357 20 LF 2 $602 Yes
Edge Metal Is Loose And Should Be Resecured 23353 20 LF 2 $582 Yes
Pitch Pan Is Damaged And Should Be Replaced 23362 5 Ea. 2 $568 Yes
Open Metal Valley Is Damaged And Should Be Replaced 23390 10 LF 2 $157 Yes
Metal Umbrella At Penetration Or Pitch Pan Is Missing And Is Needed 23367 5 Ea. 2 $1,183 Yes
Re-Seal Laps In Open Valley 23391 5 Ea. 2 $1,456 Yes
Shingle Roof Requires Replacement 23389 6,857 SF 2 $40,843 No
Sealant At Pitch Pan Is Damaged And Should Be Repaired 23363 5 Ea. 2 $568 Yes
Re-Work/Re-Place "Dead Valley" 23392 4 Ea. 2 $2,550 Yes
Membrane Flashings At Equipment Curbs Are Damaged And Should Be Repaired 23223 15 LF 2 $233 Yes
Membrane Flashing At Gutter Edge Is Damaged And Should Be Repaired 23259 20 LF 2 $157 Yes
Membrane Flashing At Curb (<2') 23310 40 LF 2 $622 Yes
Membrane Flashings At Metal Edge Are Damaged And Should Be Repaired 23360 50 LF 2 $650 Yes
Metal Roof Jack Is Damaged And Should Be Repaired 23433 5 Ea. 2 $737 Yes
Metal Edge Termination At Wall Is Damaged And Should Be Repaired 23361 5 Ea. 2 $344 Yes
Membrane Flashings At Penetration Are Damaged And Should Be Repaired 23377 15 Ea. 2 $1,567 Yes
Sub Total for System 30 $73,306
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Facilities Condition AssessmentValle Verde Campus Condition Assessment
42Magellan Consulting, Inc.
The Ceramic Tile Flooring Is Damaged And Requires Replacement 19112 4,600 SF 3 $73,382 No
The Suspended Ceiling Grid is Damaged And Require Replacement 19107 7,700 SF 3 $62,082 No
Restrooms require complete renovation 23835 1 LS 3 $400,400 No
The Carpet Flooring Is Damaged And Requires Replacement 19111 844 SF 3 $7,453 No
Acoustical Wall Treatment is missing and is needed 23762 6,040 SF 5 $105,879 No
Interior Walls Require Repainting 19109 21,799 SF 5 $58,322 No
Interior Doors Require Repainting 19110 29 Door 5 $1,543 No
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Metal Exterior Door Is Damaged And Requires Replacement 19000 8 Door 2 $18,859 Yes
Exterior door hardware is damaged and should be replaced 19001 5 Door 2 $3,018 Yes
The Steel Window Is Damaged And Requires Replacement 19002 8 Ea. 2 $16,018 Yes
Sub Total for System 3 $37,894
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Multi-Ply Bitumen Roof System Is Damaged And Requires Replacement 19087 9,648 SF 1 $116,216 No
Damaged Hip/Ridge 19093 15 LF 2 $175 Yes
Slate Roof Requires Replacement 23616 5,400 SF 1 $141,480 No
The Clay Tile Roofing Roof Covering Is Damaged And Requires Replacement 19090 50 SF 1 $2,759 No
Rake Tile Is Damaged And Requires Replacement 19091 15 LF 2 $375 Yes
Awning Or Canopy Roofing Decking Is Damaged 20673 20 SF 4 $184 No
Awning Or Canopy Roofing Decking Is Damaged 20672 20 SF 4 $184 No
Repair Holes In Structural Metal Roof Panels 19089 5 Ea. 2 $561 Yes
Sub Total for System 8 $261,933
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Volleyball standards are missing and are required 23626 3 Pr 4 $10,434 No
Asphalt Paving Is Damaged And Requires Replacement 23680 10 CAR 4 $25,467 No
Asphalt Paving Is Damaged And Requires Replacement 23620 27 CAR 4 $68,763 No
Asphalt Paving Is Damaged And Requires Replacement 23619 55 CAR 4 $140,073 No
Concrete Paving Is Damaged And Requires Replacement 23679 48 CAR 4 $113,288 No
Tennis Nets And Equipment Are Damaged And Require Replacement 23618 6 Ea. 4 $15,517 No
Exterior Basketball Goals Are Damaged And Require Replacement 23624 4 Ea. 4 $22,792 No
Sub Total for System 7 $396,334
SiteDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2070 - Gymnasium
The Fixed Shelving Storage Cabinets Require Replacement 22714 50 LF 4 $4,384 No
The Base Storage Cabinets Require Replacement 23076 100 LF 4 $28,423 No
The Upper Storage Cabinets Require Replacement 23104 100 LF 4 $18,178 No
Sub Total for System 3 $50,985
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
The Water Heater Plumbing Fixtures Are Damaged And Should Be Replaced 23065 1 Ea. 3 $2,315 No
The Refrigerated Water Cooler is Damaged And Should Be Replaced 23136 2 Ea. 3 $8,731 No
The Custodial Mop Or Service Sink Is Damaged And Should Be Replaced 23530 2 Ea. 4 $7,897 No
Sub Total for System 3 $18,943
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The Mounted Building Lighting Is Damaged And Should Be Replaced 22945 4 Ea. 2 $3,900 Yes
The GFCI Electrical Receptacles Are Inadequate And More Are Needed 23147 3 Ea. 2 $1,471 Yes
The Mounted Building Lighting Is Damaged And Should Be Replaced 22946 8 Ea. 2 $7,799 Yes
Sub Total for System 3 $13,170
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Roof Condenser Is Damaged And Requires Replacement 23002 9 TonAC 3 $20,067 No
Sub Total for System 7 $105,473
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2060 - Day Care Center 61 $552,295
Facilities Condition AssessmentValle Verde Campus Condition Assessment
43Magellan Consulting, Inc.
The Acoustical Ceilings Tiles Are Damaged And Require Replacement 22842 10 SF 4 $62 No
Sub Total for System 1 $62
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Lead Flashing Is Damaged And Should Be Repaired 23431 1 Ea. 2 $293 Yes
Exhaust Fan Curbs are too Low and Should be Raised and Reflashed (<8") 23228 3 Ea. 2 $4,182 No
Membrane Flashings At Penetration Are Damaged And Should Be Repaired 23376 3 Ea. 2 $313 Yes
Sub Total for System 3 $4,788
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2080-01 - ATC Fire Tech. Portable 1
The Base Storage Cabinets Require Replacement 19113 46 LF 4 $13,075 No
Sub Total for System 1 $13,075
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 19079 8 Ea. 2 $4,268 Yes
Fire Alarm is Missing or Inadequate 19080 22,799 SF 1 $43,731 Yes
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 19078 22,799 SF 2 $13,381 Yes
Sub Total for System 3 $61,379
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Refrigerated Water Cooler is Damaged And Should Be Replaced 19104 5 Ea. 4 $21,827 No
The Refrigerated Water Cooler is Damaged And Should Be Replaced 19105 5 Ea. 4 $21,827 No
The Rest Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 19100 14 Ea. 4 $22,957 No
The Toilets Plumbing Fixtures Are Damaged And Should Be Replaced 19101 17 Ea. 3 $22,504 No
The Showers Plumbing Fixtures Are Damaged And Should Be Replaced 19102 37 Ea. 3 $31,979 No
The Water Heater Plumbing Fixtures Are Damaged And Should Be Replaced 19103 2 Ea. 2 $4,628 No
The Class Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 19099 2 Ea. 4 $4,104 No
The Urinal Plumbing Fixtures Are Damaged And Should Be Replaced 20810 8 Ea. 3 $12,230 No
The Custodial Mop Or Service Sink Is Damaged And Should Be Replaced 19098 1 Ea. 4 $3,948 No
Sub Total for System 9 $146,006
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The GFCI Electrical Receptacles Are Inadequate And More Are Needed 19082 1 Ea. 2 $490 Yes
The Mounted Building Lighting Is Damaged And Should Be Replaced 19072 15 Ea. 2 $14,624 Yes
The Canopy Lighting Is Damaged And Should Be Replaced 19071 86 Ea. 2 $151,664 Yes
The Canopy Lighting Is Damaged And Should Be Replaced 19073 19 Ea. 2 $33,508 Yes
The H.I.D. Lighting Is Damaged And Should Be Replaced 19077 36 Ea. 3 $21,092 No
The 2 X 2 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19075 13 Ea. 4 $4,754 No
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19076 9 Ea. 4 $4,838 No
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19074 109 Ea. 4 $38,486 No
Sub Total for System 8 $269,455
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Controls Are Inadequate And Should Be Replaced With DDC Controls 19058 22,799 SF 4 $51,089 No
Exhaust Fan Ventilation Is Damaged And Should Be Replaced 20674 4 Ea. 4 $7,740 No
The Air Handler HVAC Component Is Damaged And Requires Replacement 19061 60,000 CFM 2 $252,077 No
Test And Balancing Required 19057 22,799 SF 3 $39,834 No
Duct Grill is Damaged And Should Be Replaced 19060 40 Ea. 5 $12,875 No
Duct Cleaning Required 19059 22,799 SF 5 $21,396 No
Sub Total for System 6 $385,012
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Plaster Ceilings Are Damaged And Requires Repainting 19108 12,996 SF 5 $22,706 No
Sub Total for System 8 $731,767
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2070 - Gymnasium 53 $2,302,855
Facilities Condition AssessmentValle Verde Campus Condition Assessment
44Magellan Consulting, Inc.
The Electrical Circuit Capacity Is Inadequate 23442 4 EACH 2 $3,778 No
Sub Total for System 1 $3,778
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Acoustical Ceilings Tiles Are Damaged And Require Replacement 22843 8 SF 4 $291 No
Sub Total for System 1 $291
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Loose Metal Cover At Hip/Ridge Should Be Resecured 23287 30 LF 2 $317 Yes
Sub Total for System 1 $317
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2080-03 - ATC Fire Tech. Portable 3
Fire Alarm Panel is Missing and is Needed 23472 1 Ea. 1 $3,727 Yes
Fire Alarm Smoke Detector Is Missing And Is Needed 23480 1 Ea. 1 $406 Yes
Fire Alarm Strobe Is Missing And Is Needed 23517 1 Ea. 1 $650 Yes
Fire Alarm Actuator Is Missing And Is Needed 23463 1 Ea. 1 $282 Yes
Fire Alarm Heat Detector Is Missing And Is Needed 23468 1 Ea. 1 $586 Yes
Fire Alarm Horn/Strobe Is Missing And Is Needed 23483 1 Ea. 1 $650 Yes
Emergency Lighting Is Inadequate Or Not Present And Should Be Installed 23612 1,536 SF 2 $2,293 Yes
Security Alarm Camera Is Missing And Needed 23493 1 Ea. 2 $3,793 No
Security Alarm Contact Is Missing And Needed 23454 1 Ea. 2 $1,161 No
Security Alarm Horn Is Missing And Needed 23494 1 Ea. 1 $1,190 No
Security Alarm Motion Detector Is Missing And Needed 23502 1 Ea. 1 $1,154 No
Security Alarm Panel Should be Replaced 23411 1 Ea. 1 $4,295 No
Sub Total for System 12 $20,187
Deficiency ID Qty UoM Priority Repair Cost WS&D
Fire and Life Safety
The Electrical Circuit Capacity Is Inadequate 23444 4 EACH 2 $3,778 No
Sub Total for System 1 $3,778
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2080-02 - ATC Fire Tech. Portable 2 13 $23,966
Building: 2080-02 - ATC Fire Tech. Portable 2
Fire Alarm Strobe Is Missing And Is Needed 23516 1 Ea. 1 $650 Yes
Security Alarm Motion Detector Is Missing And Needed 23499 1 Ea. 1 $1,154 No
Security Alarm Horn Is Missing And Needed 23498 1 Ea. 1 $1,190 No
Fire Alarm Heat Detector Is Missing And Is Needed 23469 1 Ea. 1 $586 Yes
Fire Alarm Actuator Is Missing And Is Needed 23462 1 Ea. 1 $282 Yes
Fire Alarm Horn/Strobe Is Missing And Is Needed 23485 1 Ea. 1 $650 Yes
Fire Alarm Smoke Detector Is Missing And Is Needed 23477 1 Ea. 1 $406 Yes
Fire Alarm Panel is Missing and is Needed 23475 1 Ea. 1 $3,727 Yes
Security Alarm Contact Is Missing And Needed 23451 1 Ea. 2 $1,161 No
The Fire Hydrant Is Damaged And Requires Replacement 23585 1 Ea. 2 $2,568 Yes
The Fire Hydrant Is Damaged And Requires Replacement 23586 1 Ea. 2 $2,568 Yes
Security Alarm Panel Should be Replaced 23415 1 Ea. 1 $4,295 No
Emergency Lighting Is Inadequate Or Not Present And Should Be Installed 23610 1,536 SF 2 $2,293 Yes
Security Alarm Camera Is Missing And Needed 23489 1 Ea. 2 $3,793 No
Sub Total for System 14 $25,323
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Exterior telephone call-box is rusted and requires replacement 23804 1 Ea. 3 $2,626 No
The Electrical Circuit Capacity Is Inadequate 23443 4 EACH 2 $3,778 No
Sub Total for System 2 $6,405
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2080-01 - ATC Fire Tech. Portable 1 20 $36,578
Facilities Condition AssessmentValle Verde Campus Condition Assessment
45Magellan Consulting, Inc.
The Mounted Building Lighting Is Damaged And Should Be Replaced 19223 10 Ea. 2 $9,750 Yes
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19224 16 Ea. 4 $5,649 No
Electrical filters required for mechanical equipment 23837 1 LS 2 $64,974 No
The Canopy Lighting Is Damaged And Should Be Replaced 19222 2 Ea. 2 $3,527 Yes
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19226 29 Ea. 4 $15,585 No
The 2 X 2 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 19225 9 Ea. 4 $3,291 No
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20676 98 Ea. 4 $34,602 No
Sub Total for System 7 $137,377
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Boiler HVAC Component Is Damaged And Requires Replacement 23743 18,000 MBH 2 $538,116 No
40 HP variable frequency drive in AHU requires replacement 23745 20 Ea. 2 $280,087 No
The Exterior Cooling Tower Is Damaged And Requires Replacement 23744 3 Ea. 2 $236,829 No
The Fan Coil HVAC Component Is Damaged And Requires Replacement 19221 500 TonAC 2 $116,234 No
Sub Total for System 4 $1,171,266
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Suspended Ceiling Grid is Damaged And Require Replacement 19246 1,400 SF 3 $11,288 No
The Carpet Flooring Is Damaged And Requires Replacement 19250 4,626 SF 3 $40,848 No
Restrooms require complete renovation 23836 1 LS 3 $120,120 No
Interior Doors Require Repainting 19249 6 Door 5 $319 No
The Plaster Ceilings Are Damaged And Requires Repainting 19247 4,525 SF 5 $7,906 No
Interior Walls Require Repainting 19248 8,200 SF 5 $21,938 No
Sub Total for System 6 $202,419
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Exterior Requires Cleaning 19198 1,600 SF Wall 5 $3,320 No
The Exterior Requires Painting 19199 1,600 SF Wall 5 $4,781 No
Exterior door hardware is damaged and should be replaced 19201 7 Door 2 $4,224 Yes
The Metal Exterior Door Is Damaged And Requires Replacement 19200 7 Door 2 $16,500 Yes
The Steel Window Is Damaged And Requires Repair 19202 1 Ea. 2 $195 Yes
Sub Total for System 5 $29,020
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
Loose/Missing Exposed Panel Fasteners 19242 10 Ea. 2 $377 Yes
Joint Between Rake Cover And Roof Panel Requires Re-Sealing 19243 20 LF 2 $1,507 Yes
The Multi-Ply Bitumen Roof System Is Damaged And Requires Replacement 19239 11,468 SF 1 $138,140 No
Metal Coping Is Damaged Or Loose And Should Be Repaired 20675 10 LF 2 $613 Yes
Re-Seal Metal Roof Panel Laps (Seams) Require Repair And Re-Seal 19241 20 LF 2 $298 Yes
Re-Seal Joint Between Metal Z Closure & Roof Panel Is Damaged And Requires Repair 19244 10 LF 2 $226 Yes
Sub Total for System 6 $141,161
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 2090 - Physical Plant
Fire Alarm Smoke Detector Is Missing And Is Needed 23481 1 Ea. 1 $406 Yes
Fire Alarm Strobe Is Missing And Is Needed 23515 1 Ea. 1 $650 Yes
Security Alarm Horn Is Missing And Needed 23495 1 Ea. 1 $1,190 No
Fire Alarm Panel is Missing and is Needed 23471 1 Ea. 1 $3,727 Yes
Fire Alarm Actuator Is Missing And Is Needed 23461 1 Ea. 1 $282 Yes
Fire Alarm Heat Detector Is Missing And Is Needed 23470 1 Ea. 1 $586 Yes
Fire Alarm Horn/Strobe Is Missing And Is Needed 23482 1 Ea. 1 $650 Yes
Security Alarm Camera Is Missing And Needed 23492 1 Ea. 2 $3,793 No
Security Alarm Contact Is Missing And Needed 23455 1 Ea. 2 $1,161 No
Emergency Lighting Is Inadequate Or Not Present And Should Be Installed 23611 1,536 SF 2 $2,293 Yes
Security Alarm Motion Detector Is Missing And Needed 23503 1 Ea. 1 $1,154 No
Security Alarm Panel Should be Replaced 23412 1 Ea. 1 $4,295 No
Sub Total for System 12 $20,187
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2080-03 - ATC Fire Tech. Portable 3 15 $24,574
Facilities Condition AssessmentValle Verde Campus Condition Assessment
46Magellan Consulting, Inc.
2019-03 - ATC Complex 3
Buildings with no reported deficiencies
The Base Storage Cabinets Require Replacement 19251 6 LF 4 $1,705 No
Sub Total for System 1 $1,705
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 19227 11,938 SF 2 $7,007 Yes
Emergency Exit Signage Is Missing And Needed 19228 8 Ea. 2 $6,261 Yes
Fire Alarm is Missing or Inadequate 19229 11,938 SF 1 $26,365 Yes
Sub Total for System 3 $39,632
Deficiency ID Qty UoM Priority Repair Cost WS&D
Fire and Life Safety
Group - Fixtures & Finish - Replace - The Group Restroom infrastructure, fixtures/finishes are beyond their useful life
23746 237 SF 3 $56,074 No
Install Fire Sprinklers 23701 3,000 SF 3 $22,981 No
The Class Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 19230 1 Ea. 4 $2,051 No
The Toilets Plumbing Fixtures Are Damaged And Should Be Replaced 19232 4 Ea. 3 $5,296 No
The Showers Plumbing Fixtures Are Damaged And Should Be Replaced 19233 4 Ea. 3 $3,458 No
The Rest Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 19231 3 Ea. 4 $4,919 No
The Refrigerated Water Cooler is Damaged And Should Be Repaired 19234 1 Ea. 4 $1,085 No
Sub Total for System 7 $95,865
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 2090 - Physical Plant 39 $1,818,446
Total for Campus 1,377 $35,214,036
Facilities Condition AssessmentValle Verde Campus Condition Assessment
47Magellan Consulting, Inc.
Supporting PhotosValle Verde Campus Condition Assessment
2030 Americana Village (135) - Photo 6
2030 Americana Village (129) - Photo 2
2030 Americana Village (133) - Photo 4
2030 Americana Village (134) - Photo 5
2030 Americana Village (11) - Photo 1
2030 Americana Village (132) - Photo 3
Facilities Condition AssessmentValle Verde Campus Condition Assessment
48Magellan Consulting, Inc.
2030 Americana Village (81) - Photo 12
2030 Americana Village (137) - Photo 8
2030 Americana Village (3) - Photo 10
2030 Americana Village (80) - Photo 11
2030 Americana Village (136) - Photo 7
2030 Americana Village (2) - Photo 9
Facilities Condition AssessmentValle Verde Campus Condition Assessment
49Magellan Consulting, Inc.
2000 Building A (4) - Photo 18
2030 FOUNTAIN-2 - Photo 14
2000 Building A (2) - Photo 16
2000 Building A (3) - Photo 17
2030 FOUNTAIN-1 - Photo 13
2000 Building A (1) - Photo 15
Facilities Condition AssessmentValle Verde Campus Condition Assessment
50Magellan Consulting, Inc.
2010 Photo (3) - Photo 24
2000 Building A (6) - Photo 20
2010 Photo (1) - Photo 22
2010 Photo (2) - Photo 23
2000 Building A (5) - Photo 19
2010 Interior Wall - Photo 21
Facilities Condition AssessmentValle Verde Campus Condition Assessment
51Magellan Consulting, Inc.
2018 Student Service Center (4) - Photo 30
2010 Power Outlet - Photo 26
2018 Student Service Center (2) - Photo 28
2018 Student Service Center (3) - Photo 29
2010 Photo (4) - Photo 25
2010 Surge Protector - Photo 27
Facilities Condition AssessmentValle Verde Campus Condition Assessment
52Magellan Consulting, Inc.
2019-01 ATC Complex 1 (10) - Photo 36
2018 Student Service Center (6) - Photo 32
2018 Student Service Center (8) - Photo 34
2018 Student Service Center (9) - Photo 35
2018 Student Service Center (5) - Photo 31
2018 Student Service Center (7) - Photo 33
Facilities Condition AssessmentValle Verde Campus Condition Assessment
53Magellan Consulting, Inc.
2019-01 ATC Complex 1 (16) - Photo 42
2019-01 ATC Complex 1 (12) - Photo 38
2019-01 ATC Complex 1 (14) - Photo 40
2019-01 ATC Complex 1 (15) - Photo 41
2019-01 ATC Complex 1 (11) - Photo 37
2019-01 ATC Complex 1 (13) - Photo 39
Facilities Condition AssessmentValle Verde Campus Condition Assessment
54Magellan Consulting, Inc.
2019-01 ATC Complex 1 (6) - Photo 48
2019-01 ATC Complex 1 (2) - Photo 44
2019-01 ATC Complex 1 (4) - Photo 46
2019-01 ATC Complex 1 (5) - Photo 47
2019-01 ATC Complex 1 (17) - Photo 43
2019-01 ATC Complex 1 (3) - Photo 45
Facilities Condition AssessmentValle Verde Campus Condition Assessment
55Magellan Consulting, Inc.
2019-02 ATC Complex 2 (1) - Photo 54
2019-01 ATC Complex 1 (9) - Photo 50
2019-02 ATC Complex 2 - Exterior Piping - Photo 52
2019-02 ATC Complex 2 - Roof Outlet - Photo 53
2019-01 ATC Complex 1 (8) - Photo 49
2019-02 ATC Complex 2 - Exit Signage & Battery Backup - Photo 51
Facilities Condition AssessmentValle Verde Campus Condition Assessment
56Magellan Consulting, Inc.
2019-02 ATC Complex 2 (4) - Photo 60
2019-02 ATC Complex 2 (12) - Photo 56
2019-02 ATC Complex 2 (2) - Photo 58
2019-02 ATC Complex 2 (3) - Photo 59
2019-02 ATC Complex 2 (10) - Photo 55
2019-02 ATC Complex 2 (13) - Photo 57
Facilities Condition AssessmentValle Verde Campus Condition Assessment
57Magellan Consulting, Inc.
2019-03 ATC Complex 3 (1) - Photo 66
2019-02 ATC Complex 2 (6) - Photo 62
2019-02 ATC Complex 2 (8) - Photo 64
2019-02 ATC Complex 2 (9) - Photo 65
2019-02 ATC Complex 2 (5) - Photo 61
2019-02 ATC Complex 2 (7) - Photo 63
Facilities Condition AssessmentValle Verde Campus Condition Assessment
58Magellan Consulting, Inc.
2020 LRC (12) - Photo 72
2019-04B ATC Athletic Portable B - Exterior AC Unit - Photo 68
2020 LRC (10) - Photo 70
2020 LRC (11) - Photo 71
2019-04A ATC Athletic Portable - Exterior AC Unit - Photo 67
2020 LRC (1) - Photo 69
Facilities Condition AssessmentValle Verde Campus Condition Assessment
59Magellan Consulting, Inc.
2020 LRC (18) - Photo 78
2020 LRC (14) - Photo 74
2020 LRC (16) - Photo 76
2020 LRC (17) - Photo 77
2020 LRC (13) - Photo 73
2020 LRC (15) - Photo 75
Facilities Condition AssessmentValle Verde Campus Condition Assessment
60Magellan Consulting, Inc.
2020 LRC (3) - Photo 84
2020 LRC (2) - Photo 80
2020 LRC (21) - Photo 82
2020 LRC (22) - Photo 83
2020 LRC (19) - Photo 79
2020 LRC (20) - Photo 81
Facilities Condition AssessmentValle Verde Campus Condition Assessment
61Magellan Consulting, Inc.
2025 Building B (1) - Photo 90
2020 LRC (5) - Photo 86
2020 LRC (7) - Photo 88
2020 LRC (9) - Photo 89
2020 LRC (4) - Photo 85
2020 LRC (6) - Photo 87
Facilities Condition AssessmentValle Verde Campus Condition Assessment
62Magellan Consulting, Inc.
2025 Building B (15) - Photo 96
2025 Building B (11) - Photo 92
2025 Building B (13) - Photo 94
2025 Building B (14) - Photo 95
2025 Building B (10) - Photo 91
2025 Building B (12) - Photo 93
Facilities Condition AssessmentValle Verde Campus Condition Assessment
63Magellan Consulting, Inc.
2025 Building B (6) - Photo 102
2025 Building B (2) - Photo 98
2025 Building B (4) - Photo 100
2025 Building B (5) - Photo 101
2025 Building B (16) - Photo 97
2025 Building B (3) - Photo 99
Facilities Condition AssessmentValle Verde Campus Condition Assessment
64Magellan Consulting, Inc.
2030 - 02 Americana Village (7) - Photo 108
2025 Building B (8) - Photo 104
2030 - 01 Ceiling Tiles - Photo 106
2030 - 02 Americana Village (10) - Photo 107
2025 Building B (7) - Photo 103
2025 Building B (9) - Photo 105
Facilities Condition AssessmentValle Verde Campus Condition Assessment
65Magellan Consulting, Inc.
2030 - 03 Exposed Smoke Detector - Photo 114
2030 - 02 Americana Village (9) - Photo 110
2030 - 03 Americana Village (12) - Photo 112
2030 - 03 Americana Village (13) - Photo 113
2030 - 02 Americana Village (8) - Photo 109
2030 - 02 Electrical Panels and Wiring - Photo 111
Facilities Condition AssessmentValle Verde Campus Condition Assessment
66Magellan Consulting, Inc.
2030 - 04 Bowed Ceiling Tiles - Photo 120
2030 - 04 Americana Village (18) - Photo 116
2030 - 04 Americana Village (20) - Photo 118
2030 - 04 Americana Village (21) - Photo 119
2030 - 04 Americana Village (122) - Photo 115
2030 - 04 Americana Village (19) - Photo 117
Facilities Condition AssessmentValle Verde Campus Condition Assessment
67Magellan Consulting, Inc.
2030 - 06 Americana Village (23) - Photo 126
2030 - 05 Americana Village (15) - Photo 122
2030 - 06 Americana Village (126) - Photo 124
2030 - 06 Americana Village (22) - Photo 125
2030 - 05 Americana Village (124) - Photo 121
2030 - 05 Americana Village (16) - Photo 123
Facilities Condition AssessmentValle Verde Campus Condition Assessment
68Magellan Consulting, Inc.
2030 - 07 Americana Village (130) - Photo 132
2030 - 06 Americana Village (25) - Photo 128
2030 - 06B - Photo 130
2030 - 07 Americana Village (128) - Photo 131
2030 - 06 Americana Village (24) - Photo 127
2030 - 06A - Photo 129
Facilities Condition AssessmentValle Verde Campus Condition Assessment
69Magellan Consulting, Inc.
2030 - 07b Americana Village (29) - Photo 138
2030 - 07b Americana Village (30) - Photo 134
2030 - 07b Americana Village (27) - Photo 136
2030 - 07b Americana Village (28) - Photo 137
2030 - 07 Americana Village (131) - Photo 133
2030 - 07b Americana Village (26) - Photo 135
Facilities Condition AssessmentValle Verde Campus Condition Assessment
70Magellan Consulting, Inc.
2030 - 09 Americana Village (35) - Photo 144
2030 - 09 Americana Village (34) - Photo 140
2030 - 09 Americana Village (38) - Photo 142
2030 - 09 Americana Village (33) - Photo 143
2030 - 07b Americana Village (31) - Photo 139
2030 - 09 Americana Village (36) - Photo 141
Facilities Condition AssessmentValle Verde Campus Condition Assessment
71Magellan Consulting, Inc.
2030 - 10 Americana Village (41) - Photo 150
2030 - 09B - Photo 146
2030 - 10 Americana Village (40) - Photo 148
2030 - 10 Americana Village (39) - Photo 149
2030 - 09 Americana Village (37) - Photo 145
2030 - 09C - Photo 147
Facilities Condition AssessmentValle Verde Campus Condition Assessment
72Magellan Consulting, Inc.
2030 - 11 Americana Village (46) - Photo 156
2030 - 10 - Photo 152
2030 - 11 Americana Village (44) - Photo 154
2030 - 11 Americana Village (45) - Photo 155
2030 - 10 Americana Village (42) - Photo 151
2030 - 10A - Photo 153
Facilities Condition AssessmentValle Verde Campus Condition Assessment
73Magellan Consulting, Inc.
2030 - 12 Americana Village (51) - Photo 162
2030 - 11A - Photo 158
2030 - 12 Americana Village (49) - Photo 160
2030 - 12 Americana Village (50) - Photo 161
2030 - 11 Americana Village (47) - Photo 157
2030 - 11B - Photo 159
Facilities Condition AssessmentValle Verde Campus Condition Assessment
74Magellan Consulting, Inc.
2030 - 13 Americana Village (57) - Photo 168
2030 - 12 Americana Village (53) - Photo 164
2030 - 12B - Photo 166
2030 - 13 Americana Village (56) - Photo 167
2030 - 12 Americana Village (52) - Photo 163
2030 - 12 Americana Village (54) - Photo 165
Facilities Condition AssessmentValle Verde Campus Condition Assessment
75Magellan Consulting, Inc.
2030 - 14 Americana Village (61) - Photo 174
2030 - 13 Americana Village (59) - Photo 170
2030 - 14 Americana Village (4) - Photo 172
2030 - 14 Americana Village (5) - Photo 173
2030 - 13 Americana Village (58) - Photo 169
2030 - 13B - Photo 171
Facilities Condition AssessmentValle Verde Campus Condition Assessment
76Magellan Consulting, Inc.
2030 - 15 Americana Village (68) - Photo 180
2030 - 14 Americana Village (63) - Photo 176
2030 - 14A - Photo 178
2030 - 14B - Photo 179
2030 - 14 Americana Village (62) - Photo 175
2030 - 14 Americana Village (64) - Photo 177
Facilities Condition AssessmentValle Verde Campus Condition Assessment
77Magellan Consulting, Inc.
2030 - 16 Americana Village (72) - Photo 186
2030 - 15 Americana Village (67) - Photo 182
2030 - 16 Americana Village (74) - Photo 184
2030 - 16 Americana Village (71) - Photo 185
2030 - 15 Americana Village (66) - Photo 181
2030 - 15 Americana Village (69) - Photo 183
Facilities Condition AssessmentValle Verde Campus Condition Assessment
78Magellan Consulting, Inc.
2030 - 20 Americana Village (113) - Photo 192
2030 - 17 Americana Village (78) - Photo 188
2030 - 17 Americana Village (77) - Photo 190
2030 - 17 Americana Village (79) - Photo 191
2030 - 16 Americana Village (73) - Photo 187
2030 - 17 Americana Village (76) - Photo 189
Facilities Condition AssessmentValle Verde Campus Condition Assessment
79Magellan Consulting, Inc.
2030 - 23 Americana Village (106) - Photo 198
2030 - 21 Americana Village (104) - Photo 194
2030 - 22 Americana Village (111) - Photo 196
2030 - 22 Americana Village (6) - Photo 197
2030 - 21 Americana Village (103) - Photo 193
2030 - 22 Americana Village (110) - Photo 195
Facilities Condition AssessmentValle Verde Campus Condition Assessment
80Magellan Consulting, Inc.
2030 - 25 Americana Village (96) - Photo 204
2030 - 23 Americana Village (108) - Photo 200
2030 - 24 Americana Village (101) - Photo 202
2030 - 25 Americana Village (95) - Photo 203
2030 - 23 Americana Village (107) - Photo 199
2030 - 24 Americana Village (100) - Photo 201
Facilities Condition AssessmentValle Verde Campus Condition Assessment
81Magellan Consulting, Inc.
2030 - 29 Americana Village (90) - Photo 210
2030 - 25 Americana Village (98) - Photo 206
2030 - 28 Americana Village (93) - Photo 208
2030 - 29 Americana Village (89) - Photo 209
2030 - 25 Americana Village (97) - Photo 205
2030 - 28 Americana Village (92) - Photo 207
Facilities Condition AssessmentValle Verde Campus Condition Assessment
82Magellan Consulting, Inc.
2030 - 32 Americana Village (119) - Photo 216
2030 - 30 Americana Village (87) - Photo 212
2030 - 31 Americana Village (84) - Photo 214
2030 - 32 Americana Village (117) - Photo 215
2030 - 30 Americana Village (86) - Photo 211
2030 - 31 Americana Village (83) - Photo 213
Facilities Condition AssessmentValle Verde Campus Condition Assessment
83Magellan Consulting, Inc.
2040 Humanities (12) - Photo 222
2030 RR'S-1 - Photo 218
2040 Humanities (1) - Photo 220
2040 Humanities (11) - Photo 221
2030 - 32 Americana Village (120) - Photo 217
2030 RR'S-2 - Photo 219
Facilities Condition AssessmentValle Verde Campus Condition Assessment
84Magellan Consulting, Inc.
2040 Humanities (3) - Photo 228
2040 Humanities (14) - Photo 224
2040 Humanities (16) - Photo 226
2040 Humanities (2) - Photo 227
2040 Humanities (13) - Photo 223
2040 Humanities (15) - Photo 225
Facilities Condition AssessmentValle Verde Campus Condition Assessment
85Magellan Consulting, Inc.
2050 Math and Science (2) - Photo 234
2040 Humanities (6) - Photo 230
2040 Humanities (8) - Photo 232
2040 Humanities (9) - Photo 233
2040 Humanities (5) - Photo 229
2040 Humanities (7) - Photo 231
Facilities Condition AssessmentValle Verde Campus Condition Assessment
86Magellan Consulting, Inc.
2060 Day Care Center - Exterior AC Units - Photo 240
2050 Math and Science (4) - Photo 236
2050 Math and Science (6) - Photo 238
2060 Day Care Center - Boiler - Photo 239
2050 Math and Science (3) - Photo 235
2050 Math and Science (5) - Photo 237
Facilities Condition AssessmentValle Verde Campus Condition Assessment
87Magellan Consulting, Inc.
2060 Day Care Center- Roof AC Unit - Photo 246
2060 Day Care Center - Mechanical Closet - Photo 242
2060 Day Care Center - Old Boiler Units - Photo 244
2060 Day Care Center - Old Coil Unit - Photo 245
2060 Day Care Center - Mechanical 1 Room - Photo 241
2060 Day Care Center - Mechanical - Photo 243
Facilities Condition AssessmentValle Verde Campus Condition Assessment
88Magellan Consulting, Inc.
2060 Day Care Center (15) - Photo 252
2060 Day Care Center (10) - Photo 248
2060 Day Care Center (13) - Photo 250
2060 Day Care Center (14) - Photo 251
2060 Day Care Center (1) - Photo 247
2060 Day Care Center (11) - Photo 249
Facilities Condition AssessmentValle Verde Campus Condition Assessment
89Magellan Consulting, Inc.
2060 Day Care Center (5) - Photo 258
2060 Day Care Center (17) - Photo 254
2060 Day Care Center (3) - Photo 256
2060 Day Care Center (4) - Photo 257
2060 Day Care Center (16) - Photo 253
2060 Day Care Center (2) - Photo 255
Facilities Condition AssessmentValle Verde Campus Condition Assessment
90Magellan Consulting, Inc.
2070 Gymnasium (1) - Photo 264
2060 Day Care Center (7) - Photo 260
2060 Day Care Center (9) - Photo 262
2070 Gym Added Section - Photo 263
2060 Day Care Center (6) - Photo 259
2060 Day Care Center (8) - Photo 261
Facilities Condition AssessmentValle Verde Campus Condition Assessment
91Magellan Consulting, Inc.
2070 Gymnasium (15) - Photo 270
2070 Gymnasium (11) - Photo 266
2070 Gymnasium (13) - Photo 268
2070 Gymnasium (14) - Photo 269
2070 Gymnasium (10) - Photo 265
2070 Gymnasium (12) - Photo 267
Facilities Condition AssessmentValle Verde Campus Condition Assessment
92Magellan Consulting, Inc.
2070 Gymnasium (8) - Photo 276
2070 Gymnasium (3) - Photo 272
2070 Gymnasium (5) - Photo 274
2070 Gymnasium (6) - Photo 275
2070 Gymnasium (2) - Photo 271
2070 Gymnasium (4) - Photo 273
Facilities Condition AssessmentValle Verde Campus Condition Assessment
93Magellan Consulting, Inc.
2090 Physical Plant (13) - Photo 282
2090 Physical Plant (1) - Photo 278
2090 Physical Plant (11) - Photo 280
2090 Physical Plant (12) - Photo 281
2070 Gymnasium (9) - Photo 277
2090 Physical Plant (10) - Photo 279
Facilities Condition AssessmentValle Verde Campus Condition Assessment
94Magellan Consulting, Inc.
2090 Physical Plant (2) - Photo 288
2090 Physical Plant (16) - Photo 284
2090 Physical Plant (18) - Photo 286
2090 Physical Plant (19) - Photo 287
2090 Physical Plant (14) - Photo 283
2090 Physical Plant (17) - Photo 285
Facilities Condition AssessmentValle Verde Campus Condition Assessment
95Magellan Consulting, Inc.
2090 Physical Plant (3) - Photo 294
2090 Physical Plant (21) - Photo 290
2090 Physical Plant (23) - Photo 292
2090 Physical Plant (24) - Photo 293
2090 Physical Plant (20) - Photo 289
2090 Physical Plant (22) - Photo 291
Facilities Condition AssessmentValle Verde Campus Condition Assessment
96Magellan Consulting, Inc.
2090 Physical Plant (7) - Photo 298
2090 Physical Plant (5) - Photo 296
2090 Physical Plant (8) - Photo 299
2090 Physical Plant (6) - Photo 297
2090 Physical Plant (4) - Photo 295
Appendix I –
Career and Technical Center
Condition Assessment Report
Facilities Condition AssessmentCareer Training Center Condition Assessment
1Magellan Consulting, Inc.
Career Training Center Condition Assessment
5010 Career Training Center 8,840 1974 $923,415 55.43% $104.46 $16,927
Site 0 0 $115,226 .00% $0.00 $0
Totals 8,840 $1,038,641 62.22% $117.49 $16,927
Facility Condition by Building
Number Building Name Gross Sq Ft Built DateFacility Condition
Cost FCICost Per
Square FootFuture Life Cycle
Cost (Yr 1-5)
The Career Training Center Facility located at 215 Francis in El Paso, Texas, was built in 1974. It comprises approximately 8,840 gross square feet.
Summary of Findings
The total current deficiencies for this site, in 2008 construction cost dollars, are estimated at $1,038,641.
Cross Tab of Current Deficiencies
The following chart summarizes the current deficiencies for this site in a cross tab that shows the buildings systems down the left and the priority of the deficiency across the top. This listing includes current deficiencies including deferred maintenance, functional deficiencies, code compliance, Americans with Disabilities Act, and Life Cycle Capital Renewal categories.
Electrical - $28,232 $11,930 $113,158 - $153,320
Mechanical - $123,720 $91,160 $26,718 $18,731 $260,329
Interior - $41,762 $171,653 - $27,972 $241,387
Plumbing - $4,628 $15,887 $18,706 - $39,221
Conveyances - - - - - $0
Technology - - - - - $0
Fire and Life Safety $21,410 $25,944 - - - $47,355
Site - - - $90,489 $6,750 $97,239
Specialties - - - $9,320 - $9,320
Other - - - - - $0
Exterior - $81,867 - - - $81,867
Structural - - - - - $0
Roofing $102,015 $6,588 - - - $108,603
Total $123,425 $312,742 $290,630 $258,391 $53,453 $1,038,641
Facility Condition - System by PriorityPriority
System 1 2 3 4 5 Total
Facilities Condition AssessmentCareer Training Center Condition Assessment
2Magellan Consulting, Inc.
Portable Buildings - - - - - $0
New Construction - - - - - $0
Hazardous Material - - - - - $0
Functional Deficiency - $15,954 - - - $15,954
Energy Efficiency - $223,825 $91,160 $113,158 - $428,144
Educational Adequacy - - - - - $0
Deferred Maintenance - $26,845 $11,930 $35,960 $53,453 $128,188
Code Compliance $21,410 - - - - $21,410
Capital Renewal $102,015 $4,355 $187,540 $109,273 - $403,183
ADA Compliance - $41,762 - - - $41,762
Total $123,425 $312,742 $290,630 $258,391 $53,453 $1,038,641
Facility Condition - Category by PriorityPriority
Category 1 2 3 4 5 Total
All deficiencies have been further categorized according to the type of deficiency observed. Capital Renewal items include those that are included in the life cycle forecast and are items that have reached or exceeded their useful life. Americans with Disabilities Act deficiencies are associated with accessibility compliance concerns. Code Compliance includes items that are a building code related deficiency. Deferred Maintenance items are those items that have broken or are in need of repair prior to reaching the end of life term. A Functional Deficiency is one that is presently not in place, or is not functioning correctly, and should be added to the building.
Life Cycle Capital Renewal Forecast
As part of the assessment process, this facility was analyzed according to twelve major building systems. Each system has subsystems, and each subsystem is further distinguished by type. For each line item, the original year, or most recent replacement year if applicable, was identified. Then, the historical life was compared to a model of expected life for each subsystem type. The remaining year was then forecasted by subtracting the expected life from the life used, and further adjusted for the apparent maintenance quality of the subsystem. In some cases, the calculation was overridden if the assessor’s judgment suggested a shorter or longer than expected life expectancy.
Once each subsystem was analyzed, they were combined to provide a 10-year life cycle capital renewal forecast for the building. The following chart shows all deficiencies and the subsequent year’s capital renewal projections for all systems where a component is expected to reach the end of its useful life and require capital dollars for replacement.
The chart on the following page shows the forecast in thousands ($000s) for the next ten years.
Facilities Condition AssessmentCareer Training Center Condition Assessment
3Magellan Consulting, Inc.
Fire and Life Safety 47 0 0 0 0 0 0 0 0 0 22 $22 $2.54
Plumbing 39 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Electrical 153 0 0 0 8 0 0 0 0 0 0 $8 $0.94
Technology 0 0 0 0 0 9 4 0 0 0 0 $13 $1.59
Other 0 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Specialties 9 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Conveyances 0 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Mechanical 260 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Roofing 109 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Site 97 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Structural 0 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Interior 241 0 0 0 0 0 6 0 2 0 0 $8 $0.92
Exterior 82 0 0 0 0 0 0 0 0 0 0 $0 $0.00
Total 1,039 0 0 0 8 9 10 0 2 0 22 $51 $5.99
Life Cycle Capital Renewal Projections ($000s)
SystemCurrent
DeficienciesYear 1 2008
Year 2 2009
Year 3 2010
Year 4 2011
Year 5 2012
Year 6 2013
Year 7 2014
Year 8 2015
Year 9 2016
Year 10 2017 Total $/GSF
Capital Renewal Forecast
Facilities Condition AssessmentCareer Training Center Condition Assessment
4Magellan Consulting, Inc.
Facility Condition Index (FCI)
The Facility Condition Index (FCI) is used throughout the facility condition assessment industry as a general indicator of a building’s health. The FCI is calculated by dividing the Facility Condition Cost plus five years of projected Life Cycle Capital Renewal Costs by the Replacement Value. Costs associated with new construction are not included in the FCI calculation. As a rule of thumb, an FCI below 10% is considered good. An FCI above 65% would suggest that the building is a candidate for replacement.
The Career Training Center facility has an overall FCI of 62.22%
Career Training Center Condition Assessment
Assessment Findings
The total current cost for all building deficiencies is $1,038,641. There are $115,226 in deficiencies at the site level that are included in the FCI calculation. The five year capital renewal cost was $16,927. The cost estimates were derived using a detailed listing of all noted deficiencies in the building. The cost to repair these deficiencies was then estimated using the cost data adjusted to El Paso, Texas (78% of national average).
The Replacement Value represents the estimated cost of replacing the current building with another building of like size, based on today’s estimated cost of construction in the El Paso, Texas area. The replacement cost for this facility is estimated to be $1,696,574.
The following pages provide a listing of all deficiencies and their associated cost for the site and building, followed by photos taken during the assessment.
Facilities Condition AssessmentCareer Training Center Condition Assessment
5Magellan Consulting, Inc.
Test And Balancing Required 20213 8,469 SF 3 $14,797 No
Ductwork Is Damaged And Should Be Replaced 20216 200 LF 3 $3,804 No
The Evaporative Cooling Unit Is Damaged And Requires Replacement 20793 4 Ea. 3 $36,280 No
The Evaporative Cooling Unit Is Damaged And Requires Replacement 20779 4 Ea. 3 $36,280 No
The Large Diameter Exhausts/Hoods Are Missing/Damaged And Require Replacement 20211 8 Ea. 2 $13,619 No
The Furnaces HVAC Component Is Damaged And Requires Replacement 20223 30,000 MBH 2 $91,431 No
The Package Unit HVAC Component Is Damaged And Requires Replacement 20794 5 TonAC 2 $13,335 No
The Package Unit HVAC Component Is Damaged And Requires Replacement 20780 2 TonAC 2 $5,334 No
Controls Are Inadequate And Should Be Replaced With DDC Controls 20214 8,469 SF 4 $18,977 No
Duct Grill is Damaged And Should Be Replaced 20219 1 Ea. 5 $322 No
Duct Grill is Damaged And Should Be Replaced 20225 1 Ea. 5 $322 No
Duct Grill is Damaged And Should Be Replaced 20227 1 Ea. 5 $322 No
Duct Grill is Damaged And Should Be Replaced 20218 4 Ea. 5 $1,287 No
Exhaust Fan Ventilation Is Damaged And Should Be Replaced 20256 4 Ea. 4 $7,740 No
Duct Cleaning Required 20215 7,269 SF 5 $6,821 No
Duct Grill is Damaged And Should Be Replaced 20217 30 Ea. 5 $9,657 No
Sub Total for System 16 $260,329
MechanicalDeficiency ID Qty UoM Priority Repair Cost WS&D
The Vinyl Composition Tile Flooring Is Damaged And Requires Replacement 20273 7,700 SF 3 $58,027 No
Interior Walls Require Repainting 20270 8,469 SF 5 $22,657 No
The Gypboard Ceilings Are Damaged And Requires Repainting 20269 2,000 SF 5 $5,314 No
Interior Doors Require Replacement 20271 41 Door 3 $51,628 No
The Interior Door Hardware is Damaged and Requires Replacement 20272 41 Ea. 2 $41,762 No
The Suspended Ceiling Grid is Damaged And Require Replacement 20268 6,000 SF 3 $48,376 No
The Ceramic Tile Flooring Is Damaged And Requires Replacement 20274 854 SF 3 $13,623 No
Sub Total for System 7 $241,387
InteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Aluminum Window Is Damaged And Requires Replacement 20199 38 Ea. 2 $65,689 Yes
The Aluminum Storefront Exterior Door Is Damaged And Requires Replacement 20197 1 Door 2 $4,355 Yes
Exterior door hardware is damaged and should be replaced 20198 11 Door 2 $6,638 Yes
The Aluminum Window Is Damaged And Requires Replacement 20200 3 Ea. 2 $5,185 Yes
Sub Total for System 4 $81,867
ExteriorDeficiency ID Qty UoM Priority Repair Cost WS&D
The Multi-Ply Bitumen Roof System Is Damaged And Requires Replacement 20265 8,469 SF 1 $102,015 No
The Wood Roof Subdeck Is Damaged And Requires Replacement 20260 500 SF 2 $6,588 No
Sub Total for System 2 $108,603
RoofingDeficiency ID Qty UoM Priority Repair Cost WS&D
Building: 5010 - Career Training Center
The Pole Lighting Is Damaged And Should Be Replaced 20196 2 Ea. 2 $17,987 Yes
Sub Total for System 1 $17,987
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Gate Is Damaged And Requires Replacement 20192 1 Ea. 4 $5,975 No
Fencing Is Damaged And Should Be Replaced (8' Chain Link Fence) 20191 550 LF 4 $18,296 No
Asphalt Paving Is Damaged And Requires Replacement 20193 26 CAR 4 $66,217 No
Paving Requires Restriping 20194 26 CAR 5 $4,694 No
Trash Receptacles Are Damaged And Require Replacement 20195 2 Ea. 5 $2,057 No
Sub Total for System 5 $97,239
Deficiency ID Qty UoM Priority Repair Cost WS&D
Site
Sub Total for School and Site Level 6 $115,226
Site Level Deficiencies
Facilities Condition AssessmentCareer Training Center Condition Assessment
6Magellan Consulting, Inc.
The Base Storage Cabinets Require Replacement 20275 20 LF 4 $5,684 No
The Upper Storage Cabinets Require Replacement 20276 20 LF 4 $3,636 No
Sub Total for System 2 $9,320
SpecialtiesDeficiency ID Qty UoM Priority Repair Cost WS&D
Emergency Exit Signage Is Damaged Or Missing And Should Be Replaced 20247 9 Ea. 2 $4,801 Yes
Fire Alarm is Missing or Inadequate 20250 8,840 SF 1 $21,410 Yes
Emergency Lighting System Is Damaged Or Missing And Should Be Replaced 20246 8,840 SF 2 $5,189 Yes
Security Alarm is Missing or Inadequate 20249 8,840 SF 2 $15,954 No
Sub Total for System 4 $47,355
Fire and Life SafetyDeficiency ID Qty UoM Priority Repair Cost WS&D
The Custodial Mop Or Service Sink Is Damaged And Should Be Replaced 20257 1 Ea. 4 $3,948 No
The Rest Room Lavatories Plumbing Fixtures Are Damaged And Should Be Replaced 20258 9 Ea. 4 $14,758 No
The Toilets Plumbing Fixtures Are Damaged And Should Be Replaced 20259 12 Ea. 3 $15,887 No
The Water Heater Plumbing Fixtures Are Damaged And Should Be Replaced 20795 2 Ea. 2 $4,628 No
Sub Total for System 4 $39,221
PlumbingDeficiency ID Qty UoM Priority Repair Cost WS&D
The Power Service Is Inadequate And Should Be Upgraded 20243 225 Amps 3 $11,930 No
The 1 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20236 38 Ea. 4 $13,417 No
The GFCI Electrical Receptacles Are Inadequate And More Are Needed 20253 3 Ea. 2 $1,471 Yes
The Mounted Building Lighting Is Damaged And Should Be Replaced 20234 9 Ea. 2 $8,774 Yes
The 2 X 2 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20237 7 Ea. 4 $2,561 No
The Incandescent Lighting Is Damaged And Should Be Replaced 20240 3 Ea. 4 $1,090 No
The Electrical Circuit Capacity Is Inadequate 20244 42 EACH 4 $39,663 No
The 2 X 4 Interior Fluorescent Lighting Is Damaged And Should Be Replaced 20239 105 Ea. 4 $56,427 No
Sub Total for System 8 $135,333
ElectricalDeficiency ID Qty UoM Priority Repair Cost WS&D
Sub Total for Building 5010 - Career Training Center 47 $923,415
Total for Campus 53 $1,038,641
Facilities Condition AssessmentCareer Training Center Condition Assessment
7Magellan Consulting, Inc.
Supporting PhotosCareer Training Center Condition Assessment
5010 Career Training Center - Mop Sink - Photo 6
5010 Career Training Center - Exterior Evap Cooler - Photo 2
5010 Career Training Center - Interior Furnace 2 - Photo 4
5010 Career Training Center - Interior Furnace - Photo 5
5010 Career Training Center - Electric Water Heater - Photo 1
5010 Career Training Center - Exterior Pole Lighting - Photo 3
Facilities Condition AssessmentCareer Training Center Condition Assessment
8Magellan Consulting, Inc.
5010 Career Training Center (15) - Photo 12
5010 Career Training Center (11) - Photo 8
5010 Career Training Center (13) - Photo 10
5010 Career Training Center (14) - Photo 11
5010 Career Training Center (10) - Photo 7
5010 Career Training Center (12) - Photo 9
Facilities Condition AssessmentCareer Training Center Condition Assessment
9Magellan Consulting, Inc.
5010 Career Training Center (20) - Photo 18
5010 Career Training Center (17) - Photo 14
5010 Career Training Center (19) - Photo 16
5010 Career Training Center (2) - Photo 17
5010 Career Training Center (16) - Photo 13
5010 Career Training Center (18) - Photo 15
Facilities Condition AssessmentCareer Training Center Condition Assessment
10Magellan Consulting, Inc.
5010 Career Training Center (7) - Photo 24
5010 Career Training Center (3) - Photo 20
5010 Career Training Center (5) - Photo 22
5010 Career Training Center (6) - Photo 23
5010 Career Training Center (21) - Photo 19
5010 Career Training Center (4) - Photo 21
Facilities Condition AssessmentCareer Training Center Condition Assessment
11Magellan Consulting, Inc.
5010 Career Training Center (9) - Photo 265010 Career Training Center (8) - Photo 25
Appendix J –
Recent EPCC Board of Trustee actions regarding Facilities
Appendix K –
Physical Plant and other Departments’ Area Effectiveness Plans regarding Facilities
Appendix L –
EPCC Physical Plant Manual
Area Effectiveness Plan/Assessment Report - Four Column
El Paso Community CollegePlanning - Physical Plant
ObjectivesMeasures & Baselines and Standards /Strategies
Results Action & Follow-Up
Planning - Physical Plant - Electricity (2009-2010) - Increase utility budget because ofnew square footage and anticipated 5% rateincrease.Planning Year(s):2009 - 2010
Actual Completion Date:03/03/2009Objective Status:NewBudget Account Number:11000-76008Person(s) Responsible:Richard Lobato
Measure:New facilities expected to come on-line:Culinary Arts (29,000 sq. ft), SSC (25,600sq. ft.), Cafeteria expansion - MdP (3,800sq. ft.), Cafeteria expansion - NW (2,170 sq.ft.) and Math Lab at TM (5,000 sq. ft.)Data Source for Measure:Department/Area ReportBaseline and Standard:Request additional funding due to increasesquare footage and anticipated utility rateincrease. Baseline: Increased consumptionand rate increase.
11/24/2010 - Utility did not increaseProgress:SatisfactoryAction Plan Status:3 - Follow-Up Documented
Strategy:Electricity EfficiencyStrategy Description:Electricity efficiency.Budget Impact:Additional/New Funding RequiredProjected Cost:192000.0000
Planning - Physical Plant - Gas (2009-2010)- Increase utility budget because of newsquare footage being added.Planning Year(s):2009 - 2010
Actual Completion Date:03/03/2009Objective Status:NewBudget Account Number:11000-76009Person(s) Responsible:Richard Lobato
Measure:New facilities expected to come on-line:Culinary Arts (29,000 sq. ft), SSC (25,600sq. ft.), Cafeteria expansion - MdP (3,800sq. ft.), Cafeteria expansion - NW (2,170 sq.ft.) and Math Lab at TM (5,000 sq. ft.)Data Source for Measure:Department/Area ReportBaseline and Standard:Request additional funding due to increasesquare footage. Baseline: Increaseconsumption.
11/24/2010 - Utility did not increaseProgress:SatisfactoryAction Plan Status:3 - Follow-Up Documented
01/17/2012 2:57 PM Generated by TracDat a product of Nuventive. Page 1 of 14
ObjectivesMeasures & Baselines and Standards /Strategies
Results Action & Follow-Up
Strategy:Gas EfficiencyStrategy Description:Gas efficiency.Budget Impact:Additional/New Funding RequiredProjected Cost:10000.0000
Planning - Physical Plant - Water/Sewage(2009-2010) - Increase utility budgetbecause of new square footage andanticipated 4% increase.Planning Year(s):2009 - 2010
Actual Completion Date:03/03/2009Objective Status:NewBudget Account Number:11000-76010Person(s) Responsible:Richard Lobato
Measure:New facilities expected to come on-line:Culinary Arts (29,000 sq. ft), SSC (25,600sq. ft.), Cafeteria expansion - MdP (3,800sq. ft.), Cafeterial expansion - NW (2,170 sq.ft.) and Math Lab at TM (5,000 sq. ft.)Data Source for Measure:Department/Area ReportBaseline and Standard:Request additional funding due to increasesquare footage. Baseline: Increaseconsumption.
11/24/2010 - Utility did not increaseProgress:SatisfactoryAction Plan Status:3 - Follow-Up Documented
Strategy:Water EfficiencyStrategy Description:Water efficiency.Budget Impact:Additional/New Funding RequiredProjected Cost:20000.0000
Planning - Physical Plant - Automotive FleetMaintenance (2009-2010) - Increaseexisting budget to be capable of providingbasic maintenance to the current fleet of140 vehicles and Physical Plant equipment.Planning Year(s):2009 - 2010
Actual Completion Date:03/03/2009
Measure:The current budget is not adequate toprovide the basic maintenance for the EPCCfleet/grounds equipment without using fundsintended for facility maintenance.Data Source for Measure:Department/Area ReportBaseline and Standard:An increase in this budget will insure basic
11/24/2010 - No funding providedProgress:UnsatisfactoryAction Plan Status:0 - No Action Plan Necessary
01/17/2012 2:57 PM Generated by TracDat a product of Nuventive. Page 2 of 14
ObjectivesMeasures & Baselines and Standards /Strategies
Results Action & Follow-Up
Objective Status:NewBudget Account Number:11000-76012Person(s) Responsible:Richard Lobato
maintenance to the vehicle fleet withoutsacrificing infrastructure maintenance.Baseline: Extremely figures reflect amaintenance (material) cost of $197 pervehicle/year. Current figures indicate that amore realistic number is $500 pervehicle/year.
Strategy:Required Maintenance for Automotive ShopStrategy Description:The requested increase will allow theAutomotive shop to provide the requiredmaintenance for EPCC vehicles to operatesafely.Budget Impact:Additional/New Funding RequiredProjected Cost:50000.0000
Planning - Physical Plant - HazardousWaste Disposal (2009-2010) - To dispose ofhazardous waste at EPCC.Planning Year(s):2009 - 2010
Actual Completion Date:03/03/2009Objective Status:NewBudget Account Number:11000-72009Person(s) Responsible:Richard Lobato
Measure:Requirement for medical waste disposal.Data Source for Measure:Department/Area ReportBaseline and Standard:Increase budget to cover waste disposalexpenses. Baseline: Continue disposal ofhazardous waste.
11/24/2010 - No funding providedProgress:UnsatisfactoryAction Plan Status:0 - No Action Plan Necessary
Strategy:Medical Waste DisposalStrategy Description:Conform to medical waste disposalregulations.Budget Impact:Additional/New Funding RequiredProjected Cost:5000.0000
Planning - Physical Plant - Operation andMaintenance (2009-2010) - Maintain
Measure:Keeping EPCC Grounds appearance in
11/24/2010 - No funding provided
01/17/2012 2:57 PM Generated by TracDat a product of Nuventive. Page 3 of 14
ObjectivesMeasures & Baselines and Standards /Strategies
Results Action & Follow-Up
minimum staffing requirements for Groundsmaintenance at all EPCC campuses.Planning Year(s):2009 - 2010
Actual Completion Date:03/03/2009Objective Status:NewBudget Account Number:11000-76003Person(s) Responsible:Richard Lobato
good order.Data Source for Measure:Department/Area ReportBaseline and Standard:The EPCC Grounds maintenance will bemaintained at its current level. Baseline:Continue maintaining the Grounds with itstidy and neat appearance throughout all thecampuses.
Progress:UnsatisfactoryAction Plan Status:3 - Follow-Up Documented
Strategy:The Grounds MaintenanceStrategy Description:The Grounds maintenance will continue at itscurrent level, maintaining the tidy and neatappearance throughout all EPCC campuses.Budget Impact:Additional/New Funding RequiredProjected Cost:140000.0000
Planning - Physical Plant - Custodial (2009-2010) - Increase to custodial contract due toincreases in CPA adjustments, minimumwage increase and additional space.Planning Year(s):2009 - 2010
Actual Completion Date:03/03/2009Objective Status:NewBudget Account Number:11000-76005Person(s) Responsible:Richard Lobato
Measure:Expand janitorial services for students,faculty and staff in the expansion of facilities.Data Source for Measure:Department/Area ReportBaseline and Standard:Funding will ensure continuance of qualityand timely services. No Baseline.
11/24/2010 - Funding providedProgress:SatisfactoryAction Plan Status:0 - No Action Plan Necessary
Strategy:Funding for Janitorial ServicesStrategy Description:Obtain additional funding for janitorialservices.Budget Impact:Additional/New Funding RequiredProjected Cost:225685.0000
01/17/2012 2:57 PM Generated by TracDat a product of Nuventive. Page 4 of 14
ObjectivesMeasures & Baselines and Standards /Strategies
Results Action & Follow-Up
Planning - Physical Plant - Director,Physical Plant (2010-2011) - Convert PTClerk position II to FT.Planning Year(s):2010 - 2011
Actual Completion Date:03/04/2010Objective Status:NewBudget Account Number:11000-76000-61605Person(s) Responsible:Rick Lobato
Measure:Provide support to office staff.Data Source for Measure:Department/Area ReportBaseline and Standard:Increase in workload/Responsibilities toAdmin. Associate. Baseline: Convert PTposition to FT and obtain increase to budget.
10/11/2011 - No progress because of hiringfreeze. Work try to fill position in the future.Progress:UnsatisfactoryAction Plan Status:0 - No Action Plan Necessary
Strategy:Payment to VendorsStrategy Description:Continue in processing requisitions andpayment to vendors in a timely manner.Budget Impact:Additional/New Funding RequiredProjected Cost:18447.0000
Planning - Physical Plant - HazardousWaste Materials (2010-2011) - Providecontinued disposal of hazardous materials.Planning Year(s):2010 - 2011
Actual Completion Date:03/04/2010Objective Status:NewBudget Account Number:11000-72009-71100Person(s) Responsible:Rick Lobato
Measure:Continue to secure students safety andwelfare.Data Source for Measure:Department/Area ReportBaseline and Standard:This is due to the increased student loadwhich results in a generation of morehazardous materials. Baseline: Obtain anincrease to current budget.
10/11/2011 - Additional funding secured.Progress:SatisfactoryAction Plan Status:0 - No Action Plan Necessary
Strategy:Disposal of Hazardous WasteStrategy Description:Required to safely disposal of hazardouswaste to all campuses.Budget Impact:Additional/New Funding RequiredProjected Cost:17000.0000
01/17/2012 2:57 PM Generated by TracDat a product of Nuventive. Page 5 of 14
ObjectivesMeasures & Baselines and Standards /Strategies
Results Action & Follow-Up
Planning - Physical Plant - Director,Physical Plant-2 (2010-2011) - Continuemaintenance of facilities DW.Planning Year(s):2010 - 2011
Actual Completion Date:03/04/2010Objective Status:NewBudget Account Number:11000-76000-71100Person(s) Responsible:Rick Lobato
Measure:Continue to provide a secure environment.Data Source for Measure:Department/Area ReportBaseline and Standard:Campus infrastructure is aging, not tomention the fact that it continues togrow(addition of 17,000 sq. ft.), this growthcoupled with aging facilities require morefunds to keep the campus in safe operatingorder. Baseline: Increase to supply pool.
10/11/2011 - Funding was not received due tocurrent budget constraints. Continue to request inthe future.Progress:UnsatisfactoryAction Plan Status:0 - No Action Plan Necessary
Strategy:Maintenance MaterialsStrategy Description:Provide maintenance materials to continueproviding a safe environment.Budget Impact:Additional/New Funding RequiredProjected Cost:100000.0000
Planning - Physical Plant - Director,Physical Plant-3 (2010-2011) - Training topersonnel.Planning Year(s):2010 - 2011
Actual Completion Date:03/04/2010Objective Status:NewBudget Account Number:11000-76000-72099Person(s) Responsible:Rick Lobato
Measure:Sent Personnel to seminars or workshops.Data Source for Measure:Department/Area ReportBaseline and Standard:Training for the development of aprofessional management staff. Baseline:Obtain increase to travel budget.
10/11/2011 - No additional funding received. Willcontinue to absorb in budget.Progress:UnsatisfactoryAction Plan Status:0 - No Action Plan Necessary
Strategy:Personnel TrainingStrategy Description:No additional funds received. Will continueto absorb in budget.Budget Impact:Rollover/Maintain Current Funding
01/17/2012 2:57 PM Generated by TracDat a product of Nuventive. Page 6 of 14
ObjectivesMeasures & Baselines and Standards /Strategies
Results Action & Follow-Up
Strategy:Travel and TrainingStrategy Description:Provide travel and training to managementstaff.Budget Impact:Additional/New Funding RequiredProjected Cost:2517.0000
Planning - Physical Plant - FacilitiesConstruction (2010-2011) - Constructionstaff required to work after regular workschedule.Planning Year(s):2010 - 2011
Actual Completion Date:03/04/2010Objective Status:NewBudget Account Number:11000-76002-61900Person(s) Responsible:Rick Lobato
Measure:Provide adequate overtime budget.Data Source for Measure:Department/Area ReportBaseline and Standard:Complete construction projects in a timelymanner. Baseline: Obtain an increase tobudget.
10/11/2011 - No additional funding received. Tryand minimize overtime, only hen absolutelyrequired.Progress:UnsatisfactoryAction Plan Status:0 - No Action Plan Necessary
Strategy:Meet NeedsStrategy Description:Meet necessary needs of the college.Budget Impact:Additional/New Funding RequiredProjected Cost:30000.0000
Planning - Physical Plant - FacilitiesConstruction-2 (2010-2011) - Constructionsupport.Planning Year(s):2010 - 2011
Actual Completion Date:03/04/2010Objective Status:NewBudget Account Number:11000-76000-71100Person(s) Responsible:
Measure:Provide adequate construction materialsbudget.Data Source for Measure:Department/Area ReportBaseline and Standard:Provide construction support to allcampuses. Baseline: Obtain an increase tobudget.
10/11/2011 - No additional funding received.Absorbed into existing budget.Progress:UnsatisfactoryAction Plan Status:0 - No Action Plan Necessary
Strategy:Construction
01/17/2012 2:57 PM Generated by TracDat a product of Nuventive. Page 7 of 14
ObjectivesMeasures & Baselines and Standards /Strategies
Results Action & Follow-Up
Rick LobatoStrategy Description:Continue with construction support in aprofessional manner to the EPCC facilities.Budget Impact:Additional/New Funding RequiredProjected Cost:30000.0000
Planning - Physical Plant - FacilitiesConstruciton-3 (2010-2011) - Training forconstruction personnel.Planning Year(s):2010 - 2011
Actual Completion Date:03/04/2010Objective Status:NewBudget Account Number:11000-76002-72099Person(s) Responsible:Rick Lobato
Measure:Sent personnel to seminars or workshopsfor additional training.Data Source for Measure:Department/Area ReportBaseline and Standard:Training for the development of aprofessional construction staff. Baseline:Obtain increase to travel budget.
10/10/2011 - No additional funding received. Willcontinue to absorb in existing budget.Progress:UnsatisfactoryAction Plan Status:0 - No Action Plan Necessary
Strategy:Travel and TrainingStrategy Description:Provide travel and training to theconstruction staff.Budget Impact:Additional/New Funding RequiredProjected Cost:4988.0000
Planning - Physical Plant - CollegeOperations (2010-2011) - Training foroperations and maintenance personnel.Planning Year(s):2010 - 2011
Actual Completion Date:03/04/2010Objective Status:NewBudget Account Number:11000-76003-72099Person(s) Responsible:
Measure:Send personnel to seminars or workshops.Data Source for Measure:Department/Area ReportBaseline and Standard:Training for the development of aprofessional operations and maintenancestaff. Baseline: Obtain increase to travelbudget.
10/11/2011 - No additional funding received. Willcontinue to absorb in existing budget.Progress:UnsatisfactoryAction Plan Status:0 - No Action Plan Necessary
Strategy:Travel and Training
01/17/2012 2:57 PM Generated by TracDat a product of Nuventive. Page 8 of 14
ObjectivesMeasures & Baselines and Standards /Strategies
Results Action & Follow-Up
Rick LobatoStrategy Description:Provide travel and training to theconstruction staff.Budget Impact:Additional/New Funding RequiredProjected Cost:4800.0000
Planning - Physical Plant - VV & ASCRecycling Program (2010-2011) - Expandrecycling program to all EPCC campuses.Planning Year(s):2010 - 2011
Actual Completion Date:03/04/2010Objective Status:NewBudget Account Number:11000-76004-71100Person(s) Responsible:Rick Lobato
Measure:Recycling program expanded to allcampuses.Data Source for Measure:Department/Area ReportBaseline and Standard:Become compliance with state mandate thatall Gov't Federal Colleges recycle. Baselin:Obtain increase to recycling program.
10/11/2011 - Completed recycling program is nowat all campuses. Recycling program will continueduring the year.Progress:SatisfactoryAction Plan Status:0 - No Action Plan Necessary
Strategy:Expand Recycling ProgramStrategy Description:Expand Recycling Program to include allEPCC campuses.Budget Impact:Additional/New Funding RequiredProjected Cost:40000.0000
Planning - Physical Plant - Custodial (2010-2011) - Increase Custodial budget by$97,131 for paper goods for restrooms to beprovided by GCA. Also need to increase thebase contract amount by 3% for CPIincome.Planning Year(s):2010 - 2011
Actual Completion Date:03/04/2010Objective Status:New
Measure:Ensure continuance of quality and timelyservices.Data Source for Measure:Department/Area ReportBaseline and Standard:Provide better services to EPCC personnel.Baseline: Obtain increase to budget.
10/11/2011 - Funding secure.Progress:SatisfactoryAction Plan Status:0 - No Action Plan Necessary
Strategy:PuchaseStrategy Description:
01/17/2012 2:57 PM Generated by TracDat a product of Nuventive. Page 9 of 14
ObjectivesMeasures & Baselines and Standards /Strategies
Results Action & Follow-Up
Budget Account Number:11000-76005-71100Person(s) Responsible:Rick Lobato
By allowing GCA to purchase and provide allpaper goods. We hope to achieve a higherstandard of service.Budget Impact:Additional/New Funding RequiredProjected Cost:97131.0000
Planning - Physical Plant - OperatingGrounds (2010-2011) - Provide minimumservices and materials to maintain basiclandscaping and maintenance of facilitiesDW.Planning Year(s):2010 - 2011
Actual Completion Date:03/04/2010Objective Status:NewBudget Account Number:11000-76007-71100Person(s) Responsible:Rick Lobato
Measure:Maintaining attractive EPCC landscape at allcampuses and improvement to facilities.Data Source for Measure:Department/Area ReportBaseline and Standard:EPCC landscaping and facilities will bebrought to a minimum standard. Baseline:Obtain increase to budget.
10/11/2011 - Not accomplished due to currentbudget constraints. Hope to obtain funding in thefuture.Progress:UnsatisfactoryAction Plan Status:0 - No Action Plan Necessary
Strategy:Increase LandscapingStrategy Description:Increase landscaping effort at all campuses.Remove dead materials and replace withcolorful live material. Continue to maintainfacilities in running condition.Budget Impact:Additional/New Funding RequiredProjected Cost:100000.0000
Planning - Physical Plant - Automotive FleetMgmt. (2010-2011) - Hire an AutomotiveFleet Manager.Planning Year(s):2010 - 2011
Actual Completion Date:03/04/2010Objective Status:NewBudget Account Number:
Measure:No Measure.Data Source for Measure:Department/Area ReportBaseline and Standard:The college requires a manager to provide acomprehensive strategy in the managementof all college vehicles. Baseline: Providebetter service and vehicles to all who are inneed of them through EPCC.
10/11/2011 - Not accomplished due to budgetconstraints and hiring freeze. Absorbedresponsiblities by Physical Plant employees.Progress:UnsatisfactoryAction Plan Status:0 - No Action Plan Necessary
01/17/2012 2:57 PM Generated by TracDat a product of Nuventive. Page 10 of 14
ObjectivesMeasures & Baselines and Standards /Strategies
Results Action & Follow-Up
11000-76012-61605Person(s) Responsible:Rick Lobato
Strategy:Service and PurchaseStrategy Description:Provide a service and purchase stategy forEPCC in the fleet management of ourvehicles.Budget Impact:Additional/New Funding RequiredProjected Cost:35000.0000
Planning - Physical Plant - Automotive FleetMgmt (2010-2011) - Increase presentbudget due to increase of college vehicles.Planning Year(s):2010 - 2011
Actual Completion Date:03/04/2010Objective Status:NewBudget Account Number:11000-76012-71100Person(s) Responsible:Rick Lobato
Measure:By the performance of college vehicles.Data Source for Measure:Department/Area ReportBaseline and Standard:On-going process. Baseline: Automotivedepartment is providing oil changes and tirechanges and continue to maintain allvehicles to include motorcycles.
10/11/2011 - Not accomplished due to budgetconstraints. Will continue to request in the future.Progress:UnsatisfactoryAction Plan Status:0 - No Action Plan Necessary
Strategy:Increase BudgetStrategy Description:By increasing this budget it will not benecessary to pay invoices using theDirector's nor the Operations budgets.Budget Impact:Additional/New Funding RequiredProjected Cost:50000.0000
Planning - Physical Plant - Vehicle FleetManagement (2011-12) - Develop an up todate fleet management program for EPCC.Planning Year(s):2011 - 2012
Expected Completion Date:08/31/2012
Objective Status:
Measure:Reduction in older vehicles that should betaken off the road.Data Source for Measure:Department/Area ReportBaseline and Standard:Have modern reliable vehicles for EPCCemployees.
01/17/2012 2:57 PM Generated by TracDat a product of Nuventive. Page 11 of 14
ObjectivesMeasures & Baselines and Standards /Strategies
Results Action & Follow-Up
NewBudget Account Number:13000-76012Person(s) Responsible:Rick Lobato
Currently there is no plan in place.
Strategy:Review existing vehicle inventoryStrategy Description:To review existing vehicle inventory anddispose of unserviceable vehicles. ObtainGPS system to assist in maintenance andoperations.Budget Impact:Additional/New Funding RequiredProjected Cost:90000.0000Funding Justification:Provide a fleet management system.
Planning - Physical Plant - Work OrderSystem (2011-12) - Develop a data base fortrouble and repairs calls district wide.Planning Year(s):2011 - 2012
Expected Completion Date:08/31/2012
Objective Status:NewBudget Account Number:13000-76000Person(s) Responsible:Rick Lobato
Measure:The ability to track trouble and repairs callsthroughout the distict.Data Source for Measure:Department/Area ReportBaseline and Standard:Overall reduction in trouble and repair calls.Quicker response time and feedback fromcustomers. Existing data is cumbersomeand does not provide data required.
Strategy:Select work order program and purchaseStrategy Description:Team with IT to select data basemanagment system that will meet thedepartment's requirements to obtain allinformation required.Budget Impact:Rollover/Maintain Current FundingProjected Cost:50000.0000
Planning - Physical Plant - PreventiveMaintenance Plan (2011-12) - Develop a
Measure:Reduction in trouble calls throughout the
01/17/2012 2:57 PM Generated by TracDat a product of Nuventive. Page 12 of 14
ObjectivesMeasures & Baselines and Standards /Strategies
Results Action & Follow-Up
detail preventive maintenance plan that willprovide history of maintenance to facilitiesequipment throughout the district.Planning Year(s):2011 - 2012
Expected Completion Date:08/31/2012
Objective Status:NewBudget Account Number:13000-76000Person(s) Responsible:Rick Lobato
district.
Data Source for Measure:Department/Area ReportBaseline and Standard:Switch from the reactive maintenace topreventive maintenance. Currently PhysicalPlant works on reactive maintenancephilosoiphy.
Strategy:Develop and implement PreventiveMaintenance PlanStrategy Description:Perform equipment inventory, developwritten maintenance plan for all equipment.Incorporate all information into data basethat will automatically submit work ordersprior to maintenance required.Budget Impact:No Funding Needed
Planning - Physical Plant - Ft. Bliss CampusDesign (2011-12) - Design and constructnew campus at Ft Bliss.Planning Year(s):2011 - 2012
Expected Completion Date:08/31/2013
Objective Status:NewBudget Account Number:91357-M91357Person(s) Responsible:Rick Lobato
Measure:Development of architectural design andspecifications.Data Source for Measure:Committee RecommendationBaseline and Standard:Complete design documents. Awaiting landlease.
Strategy:Hiring of architect.Strategy Description:Director and Construction Engineer willspend 50% of their time in the developmentand construction phase until the campus iscompleted.Budget Impact:
01/17/2012 2:57 PM Generated by TracDat a product of Nuventive. Page 13 of 14
ObjectivesMeasures & Baselines and Standards /Strategies
Results Action & Follow-Up
No Funding Needed
01/17/2012 2:57 PM Generated by TracDat a product of Nuventive. Page 14 of 14