glast large area telescope wbs 4.1.b instrument science operations center monthly status review

17
GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005 1 GLAST Large Area Telescope GLAST Large Area Telescope WBS 4.1.B Instrument Science Operations Center Monthly Status Review 1 September 2005 Rob Cameron [email protected] 650-926-2989 Gamma-ray Large Gamma-ray Large Area Space Area Space Telescope Telescope

Upload: clodia

Post on 26-Jan-2016

30 views

Category:

Documents


0 download

DESCRIPTION

Gamma-ray Large Area Space Telescope. GLAST Large Area Telescope WBS 4.1.B Instrument Science Operations Center Monthly Status Review 1 September 2005 Rob Cameron [email protected] 650-926-2989. ISOC Management. ISOC Operations Facility - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: GLAST Large Area Telescope WBS 4.1.B Instrument Science Operations Center  Monthly Status Review

GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005

1

GLAST Large Area TelescopeGLAST Large Area Telescope

WBS 4.1.BInstrument Science Operations Center Monthly Status Review1 September 2005

Rob [email protected]

Gamma-ray Large Gamma-ray Large Area Space Area Space TelescopeTelescope

Page 2: GLAST Large Area Telescope WBS 4.1.B Instrument Science Operations Center  Monthly Status Review

GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005

2

ISOC ManagementISOC Management

ISOC Operations Facility– Met with SLAC management to review plans for Ops facility in

Building 84, near existing Dataflow Lab– Preparing SLAC infrastructure proposal for construction of

operations facility– ISOC staff will be relocated to Building 84, coincident with

KIPAC move to new building– To be completed in 2006

Coordination activities– GLAST/SCCS meetings

• Managing ITAR-controlled data and computers• Offline processing – GLAST/BaBar resource sharing

– Increasing I&T coordination • Fastcopy data transport to SLAC during NRL, SASS tests• LAT Configuration tracking and control

– Operations Planning meetings• User review of FSW

Page 3: GLAST Large Area Telescope WBS 4.1.B Instrument Science Operations Center  Monthly Status Review

GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005

3

ISOC Ground Test PreparationsISOC Ground Test Preparations

Continued Ground Readiness Test Team (GRTT) participation with GSFC and other ground elements

– Preliminary test objectives and procedures agreed to for GRT3 and GRT4

– Dates of GRT3 and GRT4 swapped to give more time to prepare for GRT3 (a much larger test for ground elements)

Next GRT - GRT4 on 25 Oct 05

– Regression test for ISOC - no new functionality

– New SW release (# 1.1) to be made ~ 4 wks before test

• No new functions to be tested, but incorporate several improvements since GRT2

• Will verify before test that functions needed for GRT4 still work in release 1.1

Page 4: GLAST Large Area Telescope WBS 4.1.B Instrument Science Operations Center  Monthly Status Review

GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005

4

ISOC Ground Test Preparations –ISOC Ground Test Preparations –GRT 3 on 6 Dec 05GRT 3 on 6 Dec 05

New ISOC functions in GRT3– Ingest new data products from MOC into ISOC database

• New orbital data products• Integrated Science Timeline

– Trending data ingest and display/plot– Logging

• Log receipt/transmission of data products• Limit exceeded messages• Operator comments• Includes database and web interface

– Science Data Processing• Ingest L0 Process into L1 data

Package into ICD-compliant L1 product Send to GSSC• Provided small sample of L0 data to PSS• Still need to create large L0 sample to use in GRT3

– Cover typical pass size (~ 2GByte/pass)– With overlap between passes– Needed at least 1 month before test (by early Nov)

SW release 1.2 to be completed 9 Nov 05 (~4 weeks before GRT3)– New functions to be acceptance tested locally before release– Began acceptance test preparations for release 1.2

• Enhanced requirements database to support new tests• Identifying requirements to include in 1.2

Page 5: GLAST Large Area Telescope WBS 4.1.B Instrument Science Operations Center  Monthly Status Review

GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005

5

ISOC Ground Test Preparations –ISOC Ground Test Preparations –Ground System Discrepancy Review BoardGround System Discrepancy Review Board

GSDRB began in August– Includes all ground elements– Primary focus is ground system problems identified in

GRTs, ETEs, Mission Sims– All problems addressed by GSDRB tracked via SOARS

(GSFC discrepancy reporting tool)– Met twice in August

• Agreed on roles and procedures of GSDRB• Dispositioned all pending SOARS reports

– Generally to meet once/month or more often as needed– Next meeting 12 Sept 05

Page 6: GLAST Large Area Telescope WBS 4.1.B Instrument Science Operations Center  Monthly Status Review

GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005

6

Software DevelopmentSoftware Development

Next release planned for 22 September 2005– Interim release to bring production installation up to head

of development tree (release # 1.1)– Adds retrieval of CCSDS packet groups from raw archive –

required for science data processing in GRT3. Began integrating ISOC code modules into LICOS framework

for I&T support.– CCSDS packet archive file object used for recording

telemetry data from the VSC.– ISOC raw-archive implementation used for data-storage

organization and retrieval.– Flight-like packaging of data and use of FASTCopy for

transfers from I&T equipment to SLAC Central Unix.

Page 7: GLAST Large Area Telescope WBS 4.1.B Instrument Science Operations Center  Monthly Status Review

GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005

7

Software Development (cont’d.)Software Development (cont’d.)

I&T support (cont’d)– Modified FASTCopy-automation software and database to

operate on non-Oracle RDBMS (PostgreSQL) for use on I&T mobile rack.

– Packaged ISOC software and required external packages for automated installation on mobile rack.

Page 8: GLAST Large Area Telescope WBS 4.1.B Instrument Science Operations Center  Monthly Status Review

GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005

8

GOWG/GIMGOM ActivityGOWG/GIMGOM Activity

Ops Data Products ICD issues– Handling of priority and normal command requests by

GSSC– Change to project database delivery to ISOC - will be

delivered as a directory of “tarred” files, which is then “tarred” with a manifest

– Reviewed and approved new Science Timeline format– Deleted Spacecraft Timeline because information is

provided to ISOC through other means and the timeline itself is not used by the MOC

– Discussed revising As-Flown Timeline to ensure it contains useful information

Finalized agenda for the Sept Ops TIM

Page 9: GLAST Large Area Telescope WBS 4.1.B Instrument Science Operations Center  Monthly Status Review

GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005

9

GOWG/GIMGOM Activity (cont.)GOWG/GIMGOM Activity (cont.)

Aura Mission Planning tool (used on Aura project) – MOC evaluating use of tool (with modifications) during

L&EO and on-orbit ops– Pass plan used for routine operations with ISOC

command requests handled through change requests – would still have GSSC approval of requests

Relative Time Sequence (RTS) allocation - 35 slots with 29 for S/C and 6 allocated for use by LAT and GBM

Operation Agreements - interface information between the ground elements that does not belong in ICD

Confirmation of PROC requests by GSSC– GSSC confirms PROC requests (real time command

requests) from ISOC are valid but does not validate PROC contents

– List of PROC requests to be added to ICD – Use of rejection messages will be described in MOA

Page 10: GLAST Large Area Telescope WBS 4.1.B Instrument Science Operations Center  Monthly Status Review

GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005

10

ISOC Database ActivitiesISOC Database Activities

LAT Command and Telemetry database– Updating LAT T&C DB for housekeeping trending, as

updates occur in conjunction with FSW releases– Working with I&T on control of telemetry limits and cal

curves to be shared between LICOS for (SLAC and NRL testing) and dbx files (for SASS testing and flight ops).

Page 11: GLAST Large Area Telescope WBS 4.1.B Instrument Science Operations Center  Monthly Status Review

GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005

11

LAT Configuration Control and TrackingLAT Configuration Control and Tracking

Second TIM held on 15 August

– Operations concept review

– LAT configuration data flow through existing and proposed tools

– MOOT/MOOD (config management tools and database) design progress

– LICOS interfaces

– Instrument turn-on sequence

– Agenda: http://confluence.slac.stanford.edu/display/ISOC/TIM%2C+15+Aug+2005

First draft of all MOOD database tables nearing completion

– Next: make test database to operate with FSW tools

Page 12: GLAST Large Area Telescope WBS 4.1.B Instrument Science Operations Center  Monthly Status Review

GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005

12

Issues and ConcernsIssues and Concerns

Handling ITAR-restricted data– Spacecraft telemetry (which contains 96 LAT analog

telemetry points + bilevel telemetry)– Optional approaches

• ITAR-compliant restricted network for GLAST data, firewalled from SCCS servers, filesystems and databases

• Use ITOS capabilities at MOC to extract and deliver LAT-specific telemetry as sequential prints. ICD change required.

Page 13: GLAST Large Area Telescope WBS 4.1.B Instrument Science Operations Center  Monthly Status Review

GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005

13

Future ActivitiesFuture Activities

Ops TIM – 14-15 September 2005 GRT4 – 25 October 2005 GRT3 – 6 December 2005 MOR – 15-16 March 2006

Page 14: GLAST Large Area Telescope WBS 4.1.B Instrument Science Operations Center  Monthly Status Review

GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005

14

Level 3 Milestone CountLevel 3 Milestone Count

0

1

2

DE

C05

JAN

05

FE

B05

MA

R05

AP

R05

JUN

05

JUL0

5

Plan

Actual

Forecast

Page 15: GLAST Large Area Telescope WBS 4.1.B Instrument Science Operations Center  Monthly Status Review

GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005

15

Level 3 Milestone ListLevel 3 Milestone List

WPNO ActivityDescription

BaselineFinish

-2mVar

-1mVar

DeltaBslnVar

EarlyFinish

4.1.B ISOC

Ground System Interface Test start 06/15/05* -9 -9 -9 06/28/05A

Mission Operations Review 01/17/06* 0 0 0 01/17/06*

2005 2006FEBMARAPRMAYJUNJULAUGSEPOCTNOVDECJANFEBMARAPRMAYJUNJUL

© Primavera Systems, Inc.

Run Date 08/19/05 08:47

Data Date 08/01/05

GLAST LAT PROJECTLevel 3 Milestones

Baseline Variance (Organized by Subsystem)

LT-DZ: Baseline VarianceFL-D4: AV: Level 3 Milestones

Report #10Sheet 12

Page 16: GLAST Large Area Telescope WBS 4.1.B Instrument Science Operations Center  Monthly Status Review

GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005

16

Milestone Variance ExplanationMilestone Variance Explanation

Schedule Impact Cost Impact Corrective Action

– None Required

Page 17: GLAST Large Area Telescope WBS 4.1.B Instrument Science Operations Center  Monthly Status Review

GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005

17

Cost ReportCost Report

Reporting Cost Incurred Estimated Cost Estimated Final UnfilledCategory Cost Orders

During Month Cum. to Date Detail Balance of Contractor Contract OutstandingActual Planned Actual Planned AUG05 SEP05 Contract Estimate Value

4.1.B LAT INSTRUMENT SCIENCE OPERATIONS CENTER4.1.B.1 PROJECT MANAGEMENT 2 5 171 181 5 2 9 188 188 04.1.B.2 PERFORMANCE ASSURANCE 0 0 0 6 0 0 6 6 6 04.1.B.3 MISSION & OPERATIONS PLANNING 0 0 101 101 0 0 0 101 101 04.1.B.4 LAT OPERATIONS FACILITY 0 0 16 16 0 0 0 16 16 04.1.B.5 IOC TEST 0 0 0 0 0 0 0 0 04.1.B.6 LAT PERFORMANCE VERIFICATION 0 0 24 24 0 0 0 24 24 0CAPW[3]Totals: 2 5 312 327 5 2 15 334 334 0