Stellarator Program Update
Stellarator Team Meeting / 18 January 2012 / H. Neilson
Topics
2
• Recent developments. (M. Zarnstorff)
• FY-12 plans and status.
• Calendar
Stellarator Team Meeting / 18 January 2012 / H. Neilson
Milestones for FY-12 (1)
3
W7-X Trim Coils
Stellarator Team Meeting / 18 January 2012 / H. Neilson
Milestones for FY-12 (2)
4
W7-X Trim Coil Power Supplies
• PPPL work plan (WAF) review- Oct. 2011. ✓
• Conceptual Design Review. 5 January. ✓
• Choose technology (switching vs. rectifier bridge). 15 Feb.
• Preliminary Design Review, Final Design Review, Procurement / Fabrication
– Schedule to be updated after concept selection.
• Complete deliveries to IPP site.- 1 April 2014.
W7-X Physics Program: Research Preparations
• Define physics program and facilitate information transfer with W7-X (Gates)
• Arrange transfer of divertor and magnetic diagnostics info to PPPL (Gates, Lazerson)
• Benchmark HINT2-PIES against agreed upon W7-X equilibrium (Lazerson, Reiman)
• Modify PIES to allow non-stellarator symmetry (Lazerson, Reiman)
Stellarator Team Meeting / 18 January 2012 / H. Neilson
Milestones for FY-12 (3)
5
LHD Collaboration Program
• Analysis of the results from the XICS diagnostic (Pablant)
• Upgrade of XICS camera (need to develop schedule based on detector availability)
• Transition STELLOPT based reconstruction of LHD equilibria into a production mode (Lazerson)
• Expt. proposals for 2012 campaign due @LHD. – Jan. 2012
• Submit proposals in response to expected DOE Solicitation. (March?)
• Collaboration on dust dynamics (proposed)
Stellarator Optimization
• System code development (Zolfaghari)
• STELLOPT/COILOPT modification (Ku, Breslau)
• CTH eddy current analysis (Zolfaghari)
Stellarator Team Meeting / 18 January 2012 / H. Neilson
Milestones for FY-12 (4)
6
Reconstruction (Lazerson)
• MSE Diagnostic Benchmark - 2/12 (ISHW)
• Equilibrium with Flow paper - 3/12
• LHD Coil Current Optimization - 4/12 (EPS)
• Non-Stellarator Symmetric PIES - 7/12
• Shielding Currents in PIES - 9/12 (APS)
• PIES/HINT2 Benchmarking Effort –TBD
XICS (Pablant)
• RSI paper in progress.
• Paper on physics interpretation in progress
• New detector: delivery from Dectris by August.
• In-house work on detector housing needs to start in April.
Stellarator Team Meeting / 18 January 2012 / H. Neilson
Calendar
7
29 Jan. – 3 Feb. ISHW-18, Canberra, Australia
1 February Abstract Deadline for TOFE-2012
31 January Draft IAEA Synopses to Advanced Projects Office
JanuaryLHD experimental proposals due (see D. Gates & http://www.lhd.nifs.ac.jp/en/ for procedures.)
8 February IAEA synopses to U.S. selection committee.
16 February Stellarator team meeting
15 March Stellarator team meeting
March? DOE-FES International Solicitation issued.
27-31 August TOFE-2012 Symposium, Nashville, TN
7-12 October IAEA Fusion Energy Conference, San Diego
Stellarator Team Meeting / 18 January 2012 / H. Neilson
Agenda
8
1:30 Program Update, Recent developments, etc. - H. Neilson
1:50 Stellarator Physics Update- D. Gates
2:10 Recent Progress and FY-12 plans3.1 Eddy current modeling for CTH (J. Hanson, Auburn U.)3.2 Stellarator System Code Development (A. Zolfaghari)3.2 STELLOPT/COILOPT modifications for maintainable designs (J. Breslau)X.X Any other topics (Please let me know.)