industrialised building construction
TRANSCRIPT
![Page 1: INDUSTRIALISED BUILDING CONSTRUCTION](https://reader036.vdocuments.net/reader036/viewer/2022082920/554a21f7b4c9051b578b45b5/html5/thumbnails/1.jpg)
GREETINGS
I would like to thank to my beloved lecturer , En Shahrin bin Shafie, En Abdul Rahim bin Sarjan and Puan
Hadizah binti Mohamad Kassim. for their valuable supervision based on their
commitment at thesame time as they have given me full freedom in the research work. Duringthe research process I have benefited
from their experience and creativesuggestions.
![Page 2: INDUSTRIALISED BUILDING CONSTRUCTION](https://reader036.vdocuments.net/reader036/viewer/2022082920/554a21f7b4c9051b578b45b5/html5/thumbnails/2.jpg)
TABLE OF CONTENTS
GREETINGS INTRODUCTION TO INDUSTRIALISED
BUILDING SYSTEM TYPES OF INDUSTRIALISED BUILDING
SYSTEM ADVANTAGES AND DISADVANTAGES
(IBS) MMC PREFABRICATED BUILDING CONCLUSION
![Page 3: INDUSTRIALISED BUILDING CONSTRUCTION](https://reader036.vdocuments.net/reader036/viewer/2022082920/554a21f7b4c9051b578b45b5/html5/thumbnails/3.jpg)
INTRODUCTION
Since 2003, the government of Malaysia together with its agency, the Construction IndustryDevelopment Board has been aggressively pushing the construction industry to use of theIndustrialised Building System (IBS) method of construction. It is part of an integrated effort tofurther enhance the capacity, capability, efficiency and competitiveness of the industry and alsoto reduce the industry’s reliance on foreign workers. It is also an effort to promote cleaner, safer,simpler and efficient method of construction. Many considered it as novel effort but somesections of the industry are very concern of its impact on hundreds of small and medium sizedtraditional contractors, trade sub-contractors and material and component suppliers. Theiranxiety is well placed. As most of us already know, IBS is a construction system founded on theconception that “construction is also manufacturing” where by most of construction componentsand parts are manufactured (fabricated) in the factory and transported to site for assembly. Suchmethod of construction will most likely eliminate the role and function of the many of small andmedium sized general contractors as well as the traditional trade sub-contractors. The use oflarge pre-finished factory made components or parts will most likely diminish the need for smalltraditional trade sub-contractors whose business are in the sub-contract works such asconcreting, bar bending, bricklaying, plastering, tiling, carpentering, painting etc.
![Page 4: INDUSTRIALISED BUILDING CONSTRUCTION](https://reader036.vdocuments.net/reader036/viewer/2022082920/554a21f7b4c9051b578b45b5/html5/thumbnails/4.jpg)
WHAT IS INDUSTRIALISED BUILDING CONSTRUCTION?
Industrialised Building System (IBS) is a term used in Malaysia for a technique of construction where by components are manufactured in a controlled environment, either at site or off site, placed and assembled into construction works.[1] Worldwide, IBS is also known as
Pre-fabricated /Pre-fab Construction, Modern Method of Construction (MMC) and Off-site Construction.
CIDB Malaysia, through IBS Centre is promoting the usage of IBS to increase productivity and quality at construction sites [2] through various promotion programmes, training and incentives. The content of IBS (IBS Score) is determined based on the Construction Industry Standard
all building components such as :
wall,
floor slab, beam,
column and
staircase
are mass produced either in factory or at site under strict quality control and minimal on site activities (Rollet, 1986; Trikha, 1999).
![Page 5: INDUSTRIALISED BUILDING CONSTRUCTION](https://reader036.vdocuments.net/reader036/viewer/2022082920/554a21f7b4c9051b578b45b5/html5/thumbnails/5.jpg)
5 main IBS groups.
Pre-cast concrete frames, panels, columns etc
Formwork systems - tunnel forms, permanent steel formworks
Steel frame systems - portal frame, roof trusses
Prefabricated timber frames - i.e. for roof trusses
Block work systems - lightweight concrete blocks and so on...
![Page 6: INDUSTRIALISED BUILDING CONSTRUCTION](https://reader036.vdocuments.net/reader036/viewer/2022082920/554a21f7b4c9051b578b45b5/html5/thumbnails/6.jpg)
Types of IBS
1. Precast concrete - Proven Prestressed Concrete Half Slab
(considered as High End Product of precast concrete) which simplify
and expedite the construction of floor slab (is the critical activity in
the construction process), very adaptable to all other systems
(including conventional) which makes it a very popular IBS
component. It is highly demanded for all types of building
construction.
2. Formwork - Proven Plastech Formwork (using material of high
strength plastic as formwork) is a green building material (unlike
metal formwork). It is very light and require less capacity crane for
handling. The insitu concrete does not stick to the surface of the
formwork which makes the end product of the surface which makes
the end product of the concrete wall, very smooth and ensure good
quality for the sebsequent finishes work.
5. Blockwork - PGC produce Proven Interlocking Engineering Block
and Brick. The Proven Interlocking Engineering Block is designed as
load bearing wall system. It can easily be installed (like lego
system) and transferred into Do It Yourself Concept (DIY). The
proven Interlocking Bricks can be utilised as a load bearing wall
system, as well as infill. Both products are installer friendly, fast and
easily laid vertically, resulting in quality wall finishes.
6. Hybrid/Innovative - PGC had implemented successfully by
combining all the above IBS Systems (1+2+5) formultilevel
buildings higher than five storeys. We name these combination as
Proven IBS Hybrid System.
![Page 7: INDUSTRIALISED BUILDING CONSTRUCTION](https://reader036.vdocuments.net/reader036/viewer/2022082920/554a21f7b4c9051b578b45b5/html5/thumbnails/7.jpg)
ADVANTAGES DISADVANTAGESSpeed
2 times faster than conventional
method
Conventional method of making the
floor is about 14 days. With our Pre-
Stressed Half Slabs, it will take
only 2 days.
Reduces workers
Reduces the need for skilled
workers, carpenters and bar-
benders
Systematic way
Wall: M&E piping & conduits can be
placed with no hacking required
Floor: Slabs can just be arranged
like planks speedily
Both products are made by moulds,
which creates size consistency
No formwork required
With our wall, no formwork is
required as it will all be
incorporated into the blocks.
Environmental-friendly
Less formworks and less wastages
Air gap feature helps heat and
sound insulation
Smooth surface finishes
Wall: Smooth and straight due to
the tongue and groove feature
Floor: smooth surface which will
lead to savings in finishes
Savings
high initial capital costs for the contractors –
lack of aesthetics value - buildings tend to be very boxy and square-y, which may not look as impressive
bad workmanship while using pre-fabricated panels.
result in problems in the joints - resulting in water leakages.
pre-cast elements is that these components are considered to be inflexible,
heavy,
not insulated
not attractive
INCREASED TRANSPORTATION LOGISTICS REQUIREMENTS
LIMITED NUMBER OF PROVIDERS EARLY COMMITMENT
TO ENGINEERING ANDDESIGN WORK
![Page 8: INDUSTRIALISED BUILDING CONSTRUCTION](https://reader036.vdocuments.net/reader036/viewer/2022082920/554a21f7b4c9051b578b45b5/html5/thumbnails/8.jpg)
TIME : 50% faster than conventional
STEEL: save 50% usage as less steel needed for the wall and slabs
FOUNDATION: our system is lighter than conventional, so can save on foundation
FINISHES: smooth surfaces means less work on finishes (plastering and skimcoat)
WORKERS: less dependency on plumbing, M&E, carpenters, bar-benders and skilled general workers
working environment in a factory is easier to control. Simple erection with developed jointing methods on site to obtainhigher productivity at the site.
![Page 9: INDUSTRIALISED BUILDING CONSTRUCTION](https://reader036.vdocuments.net/reader036/viewer/2022082920/554a21f7b4c9051b578b45b5/html5/thumbnails/9.jpg)
MODERN METHOD CONSTRUCTION (MMC)
Modular construction involves the manufacture and fitout of steel framed building modules within a factory controlled environment, whilst ground works and foundations are prepared on site. The modular units are then delivered to site and craned into position to form the building.
Precast Flat Panel SystemFloor and wall units are produced off-site in a factory and erected on-site to form robust structures, Panels can include :
services,
windows,
doors
finishes.
3D Volumetric Construction
involves the production of three-dimensional units in controlled factory conditions
prior to transportation to site.
Modules can be brought to site in a variety of forms, ranging from a basic structure
to one with all internal and external finishes and services installed,
inherent benefits of concrete, :such as
thermal mass ,
sound
fire resistance,
as well as offering factory quality and accuracy, together with speed of
erection on-site.
![Page 10: INDUSTRIALISED BUILDING CONSTRUCTION](https://reader036.vdocuments.net/reader036/viewer/2022082920/554a21f7b4c9051b578b45b5/html5/thumbnails/10.jpg)
Tunnel FormTunnel form is a formwork system that allows the contractor to build monolithic walls and slabs in one operation on a daily cycle. It combines the speed, quality and accuracy of factory/offsite produced ready-mix concrete and formwork with the flexibility and economy of cast in-situ construction.
Flat SlabsFlat slabs are built quickly due to modern formwork being simplified and minimised. Rapid turnaround is achieved using a combination of early striking and flying formwork systems.
Thin Joint MasonryThin Joint Masonry allows the depth of the mortar to be reduced from 10mm to just 3mm or less, resulting in faster laying and improved productivity, particularly on long runs of walling. Construction speed can be further increased by some 13.5 per cent using large-format concrete blocks
Insulating Concrete FormworkInsulating Concrete Formwork (ICF) systems consist of twin-walled, expanded polystyrene panels or blocks that are quickly built up to create formwork for the walls of a building.
Precast Foundations
Precast concrete systems can be used to rapidly construct foundations. The elements are usually to a bespoke design and cast in a factory environment, giving assured quality for the finished product. The foundations are often supported by concrete piles and connected together.
improve productivity
Superstructure Components
– _Volumetric or modular construction.Factory produced three-dimensional units that are thentransported to site and bolted together. The frames willnormally be steel, timber or concrete and can be suppliedwith all external and internal finishes (including servicessuch as electrics and plumbing), or solely the basicstructure.
– _Pods.Factory produced three-dimensional elements that areincorporated into the superstructure of a building. Theseare ready made rooms which can be pieced together tomake complete premises when set within a light steelframework.
– _Panellized.actory produced flat panel units transported to site for
![Page 11: INDUSTRIALISED BUILDING CONSTRUCTION](https://reader036.vdocuments.net/reader036/viewer/2022082920/554a21f7b4c9051b578b45b5/html5/thumbnails/11.jpg)
assembly. Typically these would form the exterior walls ofthe building – they can be load-bearing (ie. providingstructural support) or non-load-bearing. They can bemade of timber, light gauge steel, structurally insulatedpanels (SIPs), concrete or non-structural in-fill walling usedto create the whole building.
– _Hybrid.These structures combine both volumetric and panellisedapproaches within the same building and are also knownas semi-volumetric.
– _Timber framed.Timber framed buildings have been around for hundredsof years, however, the concept is now being used tocreate some much larger and more innovative structures
– _On-site manufacture.
Site based assembly methods include the use of traditionalcomponents but in innovative designs including theestablishment of manufacturing facilities at construction
SITES.
LIGHTWEIGHT CLADDING SYSTEMS
Brick slipsIndividual brick slices that are fixed vertically by adhesive.Normally brick slips will be glued to plastic wall facingsheet though they are also available in larger panels thatare hung onto the superstructure.Rain screenThese are weatherproof external coverings that are easilyfixed to factory produced framework attached to thebuilding and can be made from metals, ceramics, granite,terracotta, vitreous enamel, laminates and timber.Insulation material may be present behind the cladding.Render systemsRender is an external covering applied to the outside of abuilding, usually directly on to bricks, blockwork, boardsor insulation. It is normally made from limestone, cementand polymers and can be produced in a wide variety ofcolours and finishes. The actual render is non-combustible,but the covered material to which it is applied can oftenbe combustible (eg. foam plastic insulation).Timber claddingAlthough a traditional building material the use of timbercladding has become increasingly common in recent yearsalongside the desire for increased use of sustainablebuilding materials. For new commercial buildings it iscommonly used in combination with other claddingsystems, although it can form the majority of the externalarea of the building.External Insulated Finish Systems (EIFS)
![Page 12: INDUSTRIALISED BUILDING CONSTRUCTION](https://reader036.vdocuments.net/reader036/viewer/2022082920/554a21f7b4c9051b578b45b5/html5/thumbnails/12.jpg)
These systems involve attaching insulation material directlyto an external wall that is then covered with a render orother type of finish such as tiles, metal or brick. There areventilated and non-ventilated systems, the former havingan air gap between the insulation and the exteriorcovering. The insulation used is very often a foam plasticmaterial (eg. expanded polystyrene) which is highlycombustible when exposed to fire.Lightweight cladding systemsAs many of these method and forms of construction arenew there is a level of uncertainty how they will performover time and the impact that might arise on thefrequency and size of loss. Issues which need to beconsidered in relation to MMC buildings include:• The use of lightweight and combustible materialsmay allow a greater degree of fire spread leadingto increased claims costs. Similarly the use ofcombustible materials externally may increasepotential for damage from external fires whetherdeliberate (arson) or accidental.• Where component parts are fixed together (notablymodules and
![Page 13: INDUSTRIALISED BUILDING CONSTRUCTION](https://reader036.vdocuments.net/reader036/viewer/2022082920/554a21f7b4c9051b578b45b5/html5/thumbnails/13.jpg)
PREFABRICATION
conventional method of building a house is to transport bricks, timber, cement, sand,steel and construction aggregate, etc. to the site, and to construct the house on site from these materials.
In prefabricated construction, only the foundations are constructed in this way, while sections of walls, floors and roof are prefabricated (assembled) in a factory (possibly with window and door frames included), transported to the site, lifted into place by a crane and bolted together.
Prefabrication is used in the manufacture of ships, aircraft and all kinds of vehicles and machines where sections previously assembled at the final point of manufacture are assembled elsewhere instead, before being delivered for final assembly.
the structure is composed of repeating units or forms, or where multiple copies of the same basic structure are being constructed. Prefabrication avoids the need to transport so many skilled workers to the construction site, and other restricting conditions such as a lack of power, lack of water, exposure to harsh weather or a hazardous environment are avoided. Against these advantages must be weighed the cost of transporting prefabricated sections and lifting them into position as they will usually be larger, more fragile and more difficult to handle than the materials and components of which they are made.
EXAMPLE OF THE BUILDING
Tesco modular store in Zub ř í , Czech
![Page 15: INDUSTRIALISED BUILDING CONSTRUCTION](https://reader036.vdocuments.net/reader036/viewer/2022082920/554a21f7b4c9051b578b45b5/html5/thumbnails/15.jpg)
REFERENCES
[1]- (CIDB 2005-a), Construction Industry Development Board (CIDB) Malaysia, “Precast Concrete Construction”, IBS Digest January – March 2005 Issue, 2005, pp 11-14.
[2]- (CIDB 2007-a), Construction Industry Development Board (CIDB) Malaysia, “The First Industrialized Building System (IBS) Timber House (TH) in Malaysia”, Contributor: Ar. Zulkifli Hj Ismail (UIAM), IBS Digest 01-2007 Issue, 2007, pp 8.
[3]- (CIDB 2005-b), Construction Industry Development Board (CIDB) Malaysia, “IBS a Short History”, IBS Digest July-September 2005 Issue, 2005, pp 11, 12.
Wikipedia Eric;s yong blog Book Charles, T. M and Louis, F. S. (1995). Making A Difference: Measuring the
Impact of Information on Development. Canada: The International Development Research Centre. Cox, A., and Townsend, M. (1998). Strategic procurement in construction.
Thomas Telford, London. Magazine CIDB. (2008). Construction and IBS Industry – At a Glance (2008). IBS
Digest, 01, 1 Industrialised Building System – A Brief Background. IBS Modular Buletin
(February, 2008)
![Page 16: INDUSTRIALISED BUILDING CONSTRUCTION](https://reader036.vdocuments.net/reader036/viewer/2022082920/554a21f7b4c9051b578b45b5/html5/thumbnails/16.jpg)
CONCLUSION
As highlighted earlier in this paper, in 2003, the government has embarked on the program topromote the greater use of IBS in the country by announcing that all public projects must contain70% of IBS components. Although it is a welcoming initiative, several quarters, such as micro,small and medium companies and suppliers are worry that the move may force them to closedown their business or they have to move their businesses somewhere else. Their concerns haveground because Figure 1, 2, 3 and 4 suggested that the use of IBS will likely eliminate many ofthe traditional processes. Consequently, it will eliminate the need many of the traditional tradecontractors and suppliers. By comparing Figure 1 and 2, it can be seen that the traditional processof bricklaying, bar-bending, plastering will be gone. By comparing Figure 3 and 4, the traditionalwork of concreter, bar-bender and carpenter will also not be needed when IBS is used.
![Page 17: INDUSTRIALISED BUILDING CONSTRUCTION](https://reader036.vdocuments.net/reader036/viewer/2022082920/554a21f7b4c9051b578b45b5/html5/thumbnails/17.jpg)
As a conclusion, it can be suggested that considerable numbers of construction related businessin the form of trade contractors may not be able to continue their business when the industry ismoving towards greater use of IBS. Therefore, it is very apt to carry out a more detailed study onthe implication of greater use of IBS on construction business community.