27 Feb 2017
Venue – Power Finance Corporation Ltd, New Delhi
1
URBANJYOTIABHIYAAN @URJA_India
INTEGRATED POWER DEVELOPMENT SCHEME (IPDS)
Review of SCADA /DMS Implementation
2
JAMMU
AMRITSAR JULUNDHUR
LUDHIANAUR
FARIDABADBIKANER
JODHPUR
AJMER
KOTA
DEHRADUN
SAHARANPURMEERUTGHAZIABAD
ALIGARH
MORADABAD
JHANSI
FIROZABAD
ALLAHBAD
GORAKHPUR
VARANASI
GWALIOR
JABALPURAHMEDABAD
BARODASURAT
INDORERAJKOTJAMNAGAR
BHAVNAGAR
G.MUMBAI BHIWANDI
PUNESOLAPUR
NASHIK
GULBARGA
KOCHI
KOZIKHODE
MADURAI
TIRNEVELI
TRICHIRAPAL
LI
SALEM
COIMBATORE
malegaon
SANGLI
KOLHAPURI
CC installed
CC to be installed
Completed
Targetted for commsng in FY
Targetted for completion in FY
• Set-up dedicated SCADA team for project implementationas well as Control centre operations and field activities.
• Expedite award /installation of SCADA enablers RMU,Sectionlizer, FPIs and keep Substation SCADA ready.Provide locational details of SCADA enablers.
• Do & expedite progressive end to end testing for RTU /FRTU and ensure timely and progressive payments as permilestones for proper cash flow.
• Facilitate GIS based DMS data to SIA. In case of problemin GIS data from ITIA, DMS network with single linediagram may be drawn & populated for DMS functions.
Common Advisories for DISCOM’s
• Get feeder and town-wise daily /monthly SAIFI/ SAIDIReports generated from SCADA.
• Ensure proper connectivity of network with NBSP
• Wherever 3G is not available, 2Gconnectivity for FRTUmay be considered till the time it is upgraded.
• Timely Outage for commissioning shall be provided
• Provide secured login to view SCADA from web-client linkfrom DISCOM website
• Functioning of SCADA of completed/ commissionedRTU/FRTU shall be by deployment of manpower (Statessuch as TN & Maharashtra have led the way).
Common Advisories for DISCOM’s
• DISCOMs requested for time extension of the project forcompletion from MoP have been given the same from timeto time. Accordingly, state utilities were advised to extendthe contract timeline with their respective SIA which shalldone immediately to keep project live
• DISCOMs shall also take pragmatic view processing ofrunning bills, keeping in view the cash-flow for theprojects. Utilities may retain provisional LD, based onappropriate rationales for the delay and final decision maybe taken at the time of contract-closure.
• Network security / Cyber security standard compliance
Advisories are without prejudice to terms and conditions and scope of Contract
between SIA and utility
Common Advisories for DISCOM’s
States Extension granted till for TPIEA-IT verification
AP Mar-17
Chhattisgarh Dec-17
Punjab Mar-17
Bihar Mar-17
Gujarat Dec-17
Maharashtra Mar-17
Tamilnadu Jun-17
Rajasthan Sep-17
MP Mar-18 (BPL GWL ). Jun-18 (JBP)
Kerala Sep-17 (ERN, KZK ) Nov-17(TVM)
SCADA CC Commissioning (Balance 3 - Achieved – 4)
• 2 Chattisgarh (Durg-Bhilai , Raipur)
• 1 Puducherry
Target by Mar 31,2017
34
SCADA CC Commissioning
Balance - Chattisgarh, Puducherry
Achieved- West Bengal, Kerala
(Achieved- 11, Near Ach- 9 , Balance- 7)
0 1 2 3 4 5 6 7
ASSAM
AP-EPDCL
AP-SPDCL
GUJ- MGVCL
MAHARASTRA
PUNJAB
RAJASTHAN- JODHPUR
RAJASTHAN -AJMER
TAMILNADU
TELANGANA -NORTH
UTTARAKHAND
WEST BENGAL
4
7
1
1
1
2
2
2
1
2
1
1
1
1
Completion * Near Complerion * Balance tgt in FY
Target by Mar 31,2017
* SCADA functioning of completed /commissioned RTU/FRTU
SCADA compl/ functional with commiss’d RTU/FRTU
Operation Monitor for preventive maintenance
Equipment health monitoring for longevity
SAIFI /SAIDI report (Planned/Unplanned) & placement on SLD
Report of limit violations
Power Quality Analysis
Loss pocket analysis
Effective use of SCADA
Equipment health monitoring
Equipment health monitoring
STATE-WISE REVIEW
SANC DATE : October’2011, Completion by Mar 17 AWARD DATE : Sep. 2012 (Chemtrols)
One Town SANC Cost : Rs 21.82 Cr Disb : Rs 12.75 Released to SIA : Rs 6.19
Part-A (SCADA) town – Guwahati
ASSAM – Guwahati
13
0
5
10
15
20
25
30
35
40 36
3026
13
RTU Progress
S/S RTU Installed
Link Avalability RTU(E to E)
0
10
20
30
40
50
60
70 62
50 50
3
FRTU Progress
RMU+Sect FRTU Installed
Link Avalability FRTU(E to E)
8 S/S are functional
5 Sub-Stations not constructed
4 sites are having new panel issue
10 sites are compact substation where (ABB-2,Schneider-7 Travida -1 ) make equipmentswere installed which needs to be integratedwith RTU
In Big Bazaar S/s , FRTU will be installed inplace of RTU
50 FRTUs to be E-to E tested
ASSAM – Guwahati Issues
SANC DATE : October’2011, Completion Oct 16 AWARD DATE : February’2013 [Chemtrols]
3 Towns SANC Cost : Rs 32.94 Crs Disb : Rs 9.88 Crs, SIA payment : Rs 7.58 Cr
Part-A (SCADA) towns – 3 (Kolkata, Asansol, Siliguri)
West Bengal- Asansol
15
0
1
2
3
4
5
6
6
5 5
1
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
SANC DATE : October’2011, Completion Oct 16 AWARD DATE : February’2013 [Chemtrols]
3 Towns SANC Cost : Rs 32.94 Crs Disb : Rs 9.88 Crs, SIA payment : Rs 7.58 Cr
Part-A (SCADA) towns – 3 (Kolkata, Asansol, Siliguri)
West Bengal- Siliguri
16
0
1
2
3
4
5
6
7
8
8 8 8
6
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
SANC DATE : October’2011, Completion Oct 16 AWARD DATE : February’2013 [Chemtrols]
3 Towns SANC Cost : Rs 32.94 Crs Disb : Rs 9.88 Crs, SIA payment : Rs 7.58 Cr
Part-A (SCADA) towns – 3 (Kolkata, Asansol, Siliguri)
West Bengal- Kolkata
17
0
5
10
15
20
25
30
35
40
45
45
3740
0
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
10
20
30
40
50
60
70
69
43
69
0
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
Balance RTU of Siliguri & Asansol to be E toE Tested
SIA/ Utility Team to conduct concurrenttesting at sites and towns required
DCPS , Modem dispatch is in progress
West Bengal – Issues
SCADA IMPL UNDER APDRP–TSNPDCL , TELANGANA
SANC DATE : 27.09.2013
Completion by Sep 16 ( Requested upto 31 Mar 17 )
AWARD DATE : LOA Dt: 07-01-14,
Agt.Dt: 08-07-14 (Awarded to M/s.Chemtrols)
1 Town SANC Cost : Rs 9.75Cr :Award 10.04 Cr Disbursement : Rs 2.93 Cr, Released to SIA : Rs 5.57 Cr
Part-A (SCADA) towns – 1 (Visakhapatnam)
APEPDCL- Visakhapatnam
19
0
5
10
15
20
25
3028 28
63
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
20
40
60
80
100
120
140
160 145
115
0 0
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
FO switch installed at 6 S/S
NBSP , M/s Bharti Airtel has to extend theconnectivity for balance 22 locations . Notdone
Interim solution - using SIM instead of MPLSis being exercised till establishment
DCPS, Modem ,MFT AND 30 FRTUs to besupplied
APEPDCL – Visakhapatnam Issues
SANC DATE : 22.02.2011 Completion by Mar’17 AWARD DATE : 21.01.13 (CHEMTROLS LTD)
3 Towns SANC Cost : Rs 39.19 Crs Disb : Rs 11.76 Crs Released to SIA : Rs 15Cr
Part-A (SCADA) towns – 3 ( Vijayawada, Guntur & Nellore)
APSPDCL - Vijayawada
21
0
5
10
15
20
25 23 23
4
21
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
10
20
30
40
50
60
70
80
90
100
100
51
2 2
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
SCADA /DMS IMPLEMENTATION –
SANC DATE : 22.02.2011 Completion by Mar’17 AWARD DATE : 21.01.13 (CHEMTROLS LTD)
3 Towns SANC Cost : Rs 39.19 Crs Disb : Rs 11.76 Crs Released to SIA : Rs 15Cr
Part-A (SCADA) towns – 3 ( Vijayawada, Guntur & Nellore)
APSPDCL - Guntur
22
0
5
10
15
20
2521 21
24
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
10
20
30
40
50
60
70
80
90
100
100
51
2 2
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
SANC DATE : 22.02.2011 Completion by Mar’17 AWARD DATE : 21.01.13 (CHEMTROLS LTD)
3 Towns SANC Cost : Rs 39.19 Crs Disb : Rs 11.76 Crs Released to SIA : Rs 15Cr
Part-A (SCADA) towns – 3 ( Vijayawada, Guntur & Nellore)
APSPDCL - Nellore
23
0
2
4
6
8
10
12
1413 13
0 0
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
5
10
15
20
25
30
35
40
45
50
50
2 2 2
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
NBSP , M/s Bharti Airtel has to extend theconnectivity
Interim solution - using SIM instead of MPLSis being exercised till establishment
FAT of DCPS for FRTU to be done
DCPS FAT for RTU staged on 5 Feb 2017 to besupplied and commissioned .
APSPDCL- Issues
SCADA /DMS IMPLEMENTATION –
SCADA IMPL UNDER APDRP–TSNPDCL , TELANGANA
SANC DATE : 22.02.2011 Completion by Dec 16 AWARD DATE : 20.12.2012
1 Towns SANC Cost : Rs 12.47 Crs. Disb : Rs 3.74 Crs, SIA Payment :2.33 Cr
Part-A (SCADA) towns – 1 (Warangal)
Telangana- North - Warangal
25
0
2
4
6
8
10
12
14
16
18
18 18 18 18
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
0 0 0 0
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
FRTUs to be installed
SIM to be arranged and End to End test to beconducted
DCPS is yet to be delivered
Telangana- North – Warangal Issues
SANC DATE : 30.06.2011 Completion by Dec 16 AWARD DATE : 17.11.2012 (M/s. Chemtrols )
1 Town Sanction : Rs 65.15 Crs Disb : Rs 19.55 Crs, SIA Payment : 4.44 Cr
Part-A (SCADA) towns – 1 (Hyderabad UA)
Telangana- South - Hyderabad
27
0
50
100
150
200
250 228 225
7455
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
100
200
300
400
500
600
700
800
900
1000 917
0 0 0
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
FRTUs to be installedBalance RTU to be E to E testedSIM to be arranged and End to End test to
be conductedDCPS is yet to be delivered
Telangana- South – Hyderabad Issues
SCADA IMPL UNDER APDRP–TSNPDCL , TELANGANA
SANC DATE : Dec 2010 Completion by DEC16 AWARD DATE : Feb-Apr2013 (Chemtrol)
6 Towns SANC Cost : Rs 138.51Crs Disb : Rs 41.55 Crs
Part-A (SCADA) towns – 6 (Ahmedabad, Baroda, Bhavnagar, Jamnagar, Rajkot, Surat)
Gujarat- MGVCL -Vadodara
29
0
2
4
6
8
10
12
14
16
18
18 18 18 18
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
100
200
300
400
500
600
700 614
304
0 0
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
3G SIM shall be available
FRTU End to End testing to be completed
Gujarat- MGVCL –Vadodara - Issues
SCADA IMPL UNDER APDRP–TSNPDCL , TELANGANA
SANC DATE : Dec 2010 Completion by DEC16 AWARD DATE : Feb-Apr2013 (Chemtrol)
6 Towns SANC Cost : Rs 138.51Crs Disb : Rs 41.55 Crs
Part-A (SCADA) towns – 6 (Ahmedabad, Baroda, Bhavnagar, Jamnagar, Rajkot, Surat)
Gujarat- UGVCL -Ahmedabad
31
0
2
4
6
8
10
12
14
16
18
2019 18
4 4
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
100
200
300
400
500
600
700 631
510 0
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
Utility to provide to provide shutdown forRTU/ FRTU
Permission for installation of tower fromGETCO not provided
Gujarat -UGVCL–Ahmedabad Issues
SCADA IMPL UNDER APDRP–TSNPDCL , TELANGANA
SANC DATE : Dec 2010 Completion by DEC16 AWARD DATE : Feb-Apr2013 (Chemtrol)
6 Towns SANC Cost : Rs 138.51Crs Disb : Rs 41.55 Crs
Part-A (SCADA) towns – 6 (Ahmedabad, Baroda, Bhavnagar, Jamnagar, Rajkot, Surat)
Gujarat- PGVCL - Rajkot
33
0
2
4
6
8
10
12
14
1615 15
21
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
100
200
300
400
500
600
584
0 0 0
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
SCADA IMPL UNDER APDRP–TSNPDCL , TELANGANA
SANC DATE : Dec 2010 Completion by DEC16 AWARD DATE : Feb-Apr2013 (Chemtrol)
6 Towns SANC Cost : Rs 138.51Crs Disb : Rs 41.55 Crs
Part-A (SCADA) towns – 6 (Ahmedabad, Baroda, Bhavnagar, Jamnagar, Rajkot, Surat)
Gujarat- PGVCL - Bhavnagar
34
0
1
2
3
4
5
6
7
8
9
9 9
10
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
50
100
150
200
250
300
350
400373
0
54
0
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
SCADA IMPL UNDER APDRP–TSNPDCL , TELANGANA
SANC DATE : Dec 2010 Completion by DEC16 AWARD DATE : Feb-Apr2013 (Chemtrol)
6 Towns SANC Cost : Rs 138.51Crs Disb : Rs 41.55 Crs
Part-A (SCADA) towns – 6 (Ahmedabad, Baroda, Bhavnagar, Jamnagar, Rajkot, Surat)
Gujarat- PGVCL - Jamnagar
35
0
1
2
3
4
5
6
7
8
87
10
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
50
100
150
200
250
300
350
343
0 0 0
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
Utility to provide to provide shutdown forRTU/ FRTU
Permission for installation of tower fromGETCO not provided
FRTU Installation is lagging
Gujarat- PGVCL - Issues
SCADA IMPL UNDER APDRP–TSNPDCL , TELANGANA
SANC DATE : Dec 2010 Completion by DEC16 AWARD DATE : Feb-Apr2013 (Chemtrol)
6 Towns SANC Cost : Rs 138.51Crs Disb : Rs 41.55 Crs
Part-A (SCADA) towns – 6 (Ahmedabad, Baroda, Bhavnagar, Jamnagar, Rajkot, Surat)
Gujarat- DGVCL - Surat
37
0
5
10
15
20
25
24 23
0 0
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
50
100
150
200
250
300 276
0 0 0
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
Utility to provide to provide shutdown forRTU/ FRTU
Permission for installation of tower fromGETCO not provided
RTU/FRTU installation to be expedited
Gujarat- DGVCL – Surat Issues
SANC DATE : June-2011 -8 towns
Completion by Dec 2016 (Mar’17 requested )
AWARD DATE : DEC -2011 (SIEMENS)
8 Towns SANC Cost : Rs 116.57Crs Disb : Rs 48.48 CrsPart-A (SCADA) towns – 8 (Amravati, Solapur, Sangli, Malegaon, Greater Mumbai, Pune, Nashik and Kolhapur)
Maharashtra - Nashik
39
0
5
10
15
20
25
30
35
34
28
22
0
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
SANC DATE : June-2011 -8 towns
Completion by Dec 2016 (Mar’17 requested )
AWARD DATE : DEC -2011 (SIEMENS)
8 Towns SANC Cost : Rs 116.57Crs Disb : Rs 48.48 CrsPart-A (SCADA) towns – 8 (Amravati, Solapur, Sangli, Malegaon, Greater Mumbai, Pune, Nashik and Kolhapur)
Maharashtra - Kolhapur
40
0
2
4
6
8
10
12
14
16
16 16
6 6
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
SANC DATE : June-2011 -8 towns
Completion by Dec 2016 (Mar’17 requested )
AWARD DATE : DEC -2011 (SIEMENS)
8 Towns SANC Cost : Rs 116.57Crs Disb : Rs 48.48 CrsPart-A (SCADA) towns – 8 (Amravati, Solapur, Sangli, Malegaon, Greater Mumbai, Pune, Nashik and Kolhapur)
Maharashtra – Greater Mumbai
41
0
10
20
30
40
50
60
70
80
8071
6
17
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
200
400
600
800
1000
1200 1025919
435 435
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
SANC DATE : June-2011 -8 towns
Completion by Dec 2016 (Mar’17 requested )
AWARD DATE : DEC -2011 (SIEMENS)
8 Towns SANC Cost : Rs 116.57Crs Disb : Rs 48.48 CrsPart-A (SCADA) towns – 8 (Amravati, Solapur, Sangli, Malegaon, Greater Mumbai, Pune, Nashik and Kolhapur)
Maharashtra - Pune
42
0
10
20
30
40
50
60
70
80
9083
64
2 0
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
SANC DATE : June-2011 -8 towns
Completion by Dec 2016 (Mar’17 requested )
AWARD DATE : DEC -2011 (SIEMENS)
8 Towns SANC Cost : Rs 116.57Crs Disb : Rs 48.48 CrsPart-A (SCADA) towns – 8 (Amravati, Solapur, Sangli, Malegaon, Greater Mumbai, Pune, Nashik and Kolhapur)
Maharashtra - Sangli
43
0
2
4
6
8
10
12
14
16
18
18 1816
13
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
20
40
60
80
100
120
140
160153 152 152 152
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
R-COMM /BSNL to deliver links
Completion for functioning of commissionedRTU/FRTU is to be given for Kolhapur andNashik
Maharashtra - Issues
SCADA IMPL UNDER APDRP–TSNPDCL , TELANGANA
SANC DATE : JAN 12 Completion by JAN 17 AWARD DATE : DEC 14
1 Towns SANC Cost : Rs 16.55 Crs. Disb : Rs 8.25 Crs SIA Payment : Rs 4.07 Cr
Part-A (SCADA) towns – 1 (DEHRADUN)
Uttarakhand - Dehradun
45
0
5
10
15
20
25 23
13
9 8
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
50
100
150
200
250
300
350
400 364
160194
80
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
Delay in installation of RTU/ FRTUinstallation
MPLS Connectivity issue in some sites to beresolved
SIM errors in AIRTEL SIMs to be resolved
SCADA enabler work to expedited tocomplete project in Jan’17
Uttarakhand - Issues
SANC DATE : November 2011 Completion by Aug.16 AWARD DATE : Feb. 2015 (Siemens)
3 Towns SANC Cost : Rs 52.36 Crs Disb : Rs .15.71 Crs
Part-A (SCADA) towns – 3 (Amritsar, Jalandhar & Ludhiana)
Punjab - Jalandhar
47
0
2
4
6
8
10
12
14
16
18
20
20
10
53
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
5
10
15
20
25
30
30
0 0 0
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
SANC DATE : November 2011 Completion by Aug.16 AWARD DATE : Feb. 2015 (Siemens)
3 Towns SANC Cost : Rs 52.36 Crs Disb : Rs .15.71 Crs
Part-A (SCADA) towns – 3 (Amritsar, Jalandhar & Ludhiana)
Punjab - Amritsar
48
0
2
4
6
8
10
12
14
16
18
20
20
42 1
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
5
10
15
20
25
30
30
0 0 0
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
SANC DATE : November 2011 Completion by Aug.16 AWARD DATE : Feb. 2015 (Siemens)
3 Towns SANC Cost : Rs 52.36 Crs Disb : Rs .15.71 Crs
Part-A (SCADA) towns – 3 (Amritsar, Jalandhar & Ludhiana)
Punjab - Ludhiana
49
0
5
10
15
20
25
30
35
40
40
117 6
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
1
2
3
4
5
6
7
8
9
9
0 0 0
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
• RTU and FRTU installation /End to End to bespeeded up
• Link availability to be ensured
Punjab - Issues
SCADA IMPL UNDER APDRP–TSNPDCL , TELANGANA
SANC DATE : MAR 10( 3) & JUN 10 (2)
Completion Dec 16 - Jan 17
AWARD DATE : AUG 2012 (DONGFANG)
5 Towns SANC Cost : Rs 151Crs Disb : Rs 45 Crs
Part-A (SCADA) towns – 5 (Jaipur, Kota , Ajmer, Jodhpur, Bikaner)
Rajasthan – JdVVNL - Jodhpur
51
44
45
46
47
48
49
50
51
52
53
53
49 49
47
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
20
40
60
80
100
120
140
160148
3 0 0
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
SCADA IMPL UNDER APDRP–TSNPDCL , TELANGANA
SANC DATE : MAR 10( 3) & JUN 10 (2)
Completion Dec 16 - Jan 17
AWARD DATE : AUG 2012 (DONGFANG)
5 Towns SANC Cost : Rs 151Crs Disb : Rs 45 Crs
Part-A (SCADA) towns – 5 (Jaipur, Kota , Ajmer, Jodhpur, Bikaner)
Rajasthan – JdVVNL - Bikaner
52
0
5
10
15
20
25
30
35
40 36 35 35 35
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
20
40
60
80
100
120
116
0 0 0
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
SCADA IMPL UNDER APDRP–TSNPDCL , TELANGANA
SANC DATE : MAR 10( 3) & JUN 10 (2)
Completion Dec 16 - Jan 17
AWARD DATE : AUG 2012 (DONGFANG)
5 Towns SANC Cost : Rs 151Crs Disb : Rs 45 Crs
Part-A (SCADA) towns – 5 (Jaipur, Kota , Ajmer, Jodhpur, Bikaner)
Rajasthan – AVVNL - Ajmer
53
0
5
10
15
20
2521 20 20
16
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
20
40
60
80
100
120
118
0 0 0
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
SCADA IMPL UNDER APDRP–TSNPDCL , TELANGANA
SANC DATE : MAR 10( 3) & JUN 10 (2)
Completion Dec 16 - Jan 17
AWARD DATE : AUG 2012 (DONGFANG)
5 Towns SANC Cost : Rs 151Crs Disb : Rs 45 Crs
Part-A (SCADA) towns – 5 (Jaipur, Kota , Ajmer, Jodhpur, Bikaner)
Rajasthan – JVVNL - Jaipur
54
0
20
40
60
80
100
120 105
51
83
51
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
200
400
600
800
1000
1200
1400
16001517
5 5 5
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
SCADA IMPL UNDER APDRP–TSNPDCL , TELANGANA
SANC DATE : MAR 10( 3) & JUN 10 (2)
Completion Dec 16 - Jan 17
AWARD DATE : AUG 2012 (DONGFANG)
5 Towns SANC Cost : Rs 151Crs Disb : Rs 45 Crs
Part-A (SCADA) towns – 5 (Jaipur, Kota , Ajmer, Jodhpur, Bikaner)
Rajasthan – JVVNL - Kota
55
0
5
10
15
20
25
30
29
1215
12
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
100
200
300
400
500
600
700
700
0 0 0
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
Despite project completion extended byMoP/PFC in Jan’17 ,Rajasthan DISCOMs areyet to extend contract with SIA
FRTU installation to be expedited by SIA andSIMs to be provided
DISCOM to make progressive milestonepayment for end to end test
Rajasthan – Issues
SCADA IMPL UNDER APDRP–TSNPDCL , TELANGANA
SANC DATE : December 2010 Completion by Dec 16
7 Towns SANC Cost : Rs 182.17 Crores
Part-A (SCADA) towns – 7 ( Chennai, Trichy, Madurai, Tirunelvelli, Salem, Tiruppur, Coimbatore)
TamilNadu - Chennai
57
0
20
40
60
80
100
120
140
160
180
200 183
156 156
125
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
200
400
600
800
1000
1200
1400
1600
1800
20001905
17171717
1410
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
SCADA IMPL UNDER APDRP–TSNPDCL , TELANGANA
SANC DATE : December 2010 Completion by Dec 16
7 Towns SANC Cost : Rs 182.17 Crores
Part-A (SCADA) towns – 7 ( Chennai, Trichy, Madurai, Tirunelvelli, Salem, Tiruppur, Coimbatore)
TamilNadu - Salem
58
0
1
2
3
4
5
6
6 6 6 6
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
50
100
150
200
250
300
350334
194
334
124
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
SCADA IMPL UNDER APDRP–TSNPDCL , TELANGANA
SANC DATE : December 2010 Completion by Dec 16
7 Towns SANC Cost : Rs 182.17 Crores
Part-A (SCADA) towns – 7 ( Chennai, Trichy, Madurai, Tirunelveli, Salem, Tiruppur, Coimbatore)
TamilNadu - Tirupur
59
0
2
4
6
8
10
12
12 12 12 12
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
50
100
150
200
250
300
350
400369
255
119
2
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
SCADA IMPL UNDER APDRP–TSNPDCL , TELANGANA
SANC DATE : December 2010 Completion by Dec 16
7 Towns SANC Cost : Rs 182.17 Crores
Part-A (SCADA) towns – 7 ( Chennai, Trichy, Madurai, Tirunelvelli, Salem, Tiruppur, Coimbatore)
TamilNadu - Coimbatore
60
0
5
10
15
20
25 23 23 23 23
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
100
200
300
400
500
600
700
800
799
518
799
338
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
Balance FRTU Commissioning to be expedited
TamilNadu - Issues
SCADA IMPL UNDER APDRP–TSNPDCL , TELANGANA
SANC DATE : MAR & JUN 2011 AWARD DATE : Dec’2011 (DONGFANG)
5 Towns SANC Cost : Rs 103Crs Disb : Rs 31 Crs
Part-A (SCADA) towns – 5 (Bhopal, Gwalior, Jabalpur, Indore & Ujjain)
Madhya Pradesh – Bhopal
62
0
10
20
30
40
50
60
70 63 63
3731
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
SCADA IMPL UNDER APDRP–TSNPDCL , TELANGANA
SANC DATE : MAR & JUN 2011 AWARD DATE : Dec’2011 (DONGFANG)
5 Towns SANC Cost : Rs 103Crs Disb : Rs 31 Crs
Part-A (SCADA) towns – 5 (Bhopal, Gwalior, Jabalpur, Indore & Ujjain)
Madhya Pradesh – Gwalior
63
0
5
10
15
20
25
30
35
40
45
50 4643
40
3
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
SCADA IMPL UNDER APDRP–TSNPDCL , TELANGANA
SANC DATE : MAR & JUN 2011 AWARD DATE : Dec’2011 (DONGFANG)
5 Towns SANC Cost : Rs 103Crs Disb : Rs 31 Crs
Part-A (SCADA) towns – 5 (Bhopal, Gwalior, Jabalpur, Indore & Ujjain)
Madhya Pradesh – Indore
64
0
10
20
30
40
50
60
70
80 72 72 72 72
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
SCADA IMPL UNDER APDRP–TSNPDCL , TELANGANA
SANC DATE : MAR & JUN 2011 AWARD DATE : Dec’2011 (DONGFANG)
5 Towns SANC Cost : Rs 103Crs Disb : Rs 31 Crs
Part-A (SCADA) towns – 5 (Bhopal, Gwalior, Jabalpur, Indore & Ujjain)
Madhya Pradesh – Ujjain
65
0
5
10
15
20
2521 21 21 21
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
SCADA IMPL UNDER APDRP–TSNPDCL , TELANGANA
SANC DATE : MAR & JUN 2011 AWARD DATE : Dec’2011 (DONGFANG)
5 Towns SANC Cost : Rs 103Crs Disb : Rs 31 Crs
Part-A (SCADA) towns – 5 (Bhopal, Gwalior, Jabalpur, Indore & Ujjain)
Madhya Pradesh – Jabalpur
66
0
5
10
15
20
25
30
35
40
3936
31 31
RTU Progress
Link Feasibility
RTU Installed
Link Feasibility2
RTU(E to E)
Acute Delay in installation of enablers(Actual Sanction incld Enablers)
DMS data and locational details to beprovided
Madhya Pradesh – Issues
SCADA IMPL UNDER APDRP–TSNPDCL , TELANGANA
SANC DATE : Aug 2012 Completion by Sept 16 AWARD DATE : DEC 2012 (M/s. SCHNEIDER)
1 Town SANC Cost : Rs 22.02 Crs Disb : Rs 6.61Crs
Part-A (SCADA) towns – 1 (Patna)
Bihar– Patna
68
0
10
20
30
40
50
60 5146
10
0
RTU Progress
S/S RTU Installed
Link Feasibility RTU(E to E)
0
50
100
150
200
250
300
350 305 289 305
0
FRTU Progress
RMU+Sect FRTU Installed
Link Feasibility FRTU(E to E)
RTU /FRTU End to End test to be expedited
GIS integration to be done
Bihar– Patna - Issues
Chattisgarh –
Both CC to be commissioned - Pending
UPS PO placed on 23 Feb
FRTU order placed on 21 Feb
Temporary arrangement with 2 nos 10KVA UPS to power up CC
is being made till ordered UPS is delivered
Hardware and software installation/ commission to be expedited
Kerala –
CC commissioned in Feb 17
RTU/FRTU installation and End to End test to be expedited
Puducherry –
CC to be commissioned
Chhattisgarh,Kerala, Puducherry
o/c
E/F
MFT
0 0 0 0 0 0
Operation Monitor
o/c
E/F
MFT
1 0 0 0 0 0
Operation Monitor
R-APDRP RT-DAS
Real Time Feeder DAS at Substation Level
o/c
E/F
MFT
1 0 0 0 0 0
o/c
E/F
MFT
2 0 0 0 0 0
Operation Monitor
o/c
E/F
MFT
2 0 0 1 0 0
Operation Monitor
Operation Monitor
o/c
E/F
MFT
23 1 1 13 0 7
After month or year
SAIDI P U T
5.5 2.0 7.5 Hr
SAIFI P U T
19 4 23
SAIDI P U T
2 0 2 Hr
SAIFI P U T
1 0 1
SAIDI P U T
0 3 3 Hr
SAIFI P U T
0 1 1
SAIDI P U T
2 13 15 Hr
SAIFI P U T
2 10 23
SAIDI P U T
0 0 0 Hr
SAIFI P U T
0 0 0
SAIDI P U T
7 0 7. Hr
SAIFI P U T
7 0 7
URBANJYOTIABHIYAAN
@URJA_India