lean improvement case study 3
DESCRIPTION
Lean Case Study summarising savings made for an SME over an 8 month period.TRANSCRIPT
21-Aug-09Vative - Truly Innovative 1
ChangeChangeChangeChange
Without it, at best we remain the same,
with it, comes the opportunity to improve!!
2
Previous Findings
Findings of VSM/VSD start 2009 :
Implement KANBAN for internal production processes feeding main line (Implemented)
Controlled FIFO between processes (Implemented)
Finished Goods supermarket may be able to reduce in size with the introduction of a new level planning system (Implemented)
Investigate supermarket feasibility by 80/20 analysis (Completed)
Reduce or eliminate batch building and move to single piece flow to reduce overall inventory (Implemented)
Improve final testing cell utilization and procedure
Optimize layout to group together logical work cell (Implemented)
Reduce compressor defect rate
The current process has an excellent Kanban system for store materials
3
Action Plans - Production
Approved by
Vative - Steven FarrugiaResponsible person
16/03/2009 to 12/08/2009 (5 months)Timing for implementation
1. Implement 5S, conduct time studies and develop Standard Operating Procedures for main processes
2. Improved production material flow and consolidate logical process steps to form balanced work cells
3. Implement KANBAN for production area. Work towards single piece flow systems with FIFO between stations
other4. Implement Lean metrics, OEE monitoring and establish KPIs.
Understand customer demands, set targets & monitor5. Implement continuous improvement program and empower teams
to improve without management6. Provide vision planning and goals for business
Improvement idea
1. Standardisation and consolidation of processes2. Process orientation improvements to flow within work cells3. Pull System implementation through productionOther4. Transparency of processes5. Continuous Improvement circles6. Associate involvement and empowerment
Opportunity
ProductionFunctional Area
14th January 2009Audit Date
LBHC link
4
Project details
Project commencement date: 16/03/2009
•80/20 analysis
•Time studies and labour planning for all main production
•CAD Layout of plant and layout planning for optimisation
•Grouping of logical work cells and labour balancing
•Implementation of SOPs throughout production main processes
•Analysis of production Kanban system requirements
•Training and implementation of complete Kanban System including 2 bin systems in production
5
Lean Business Health Check
Areas assessed were – Production and Associate Involvement
Overall Audit Results
0%
20%
40%
60%
80%
100%Process Orientation
Pull System
Perfect Quality
Flexibility
Standardization
Transparent Processes
Continuous
Improvement
Associate Involvement
and Empowerment
Current
Last Audit
6
Health Check findings
1. Business processes are extremely flexible
2. Well established pull systems
3. Great process orientation
4. Some establish quality systems
Further overall opportunities are:
• Standardisation and consolidation of processes
• Transparency of processes
• Continuous Improvement circles
• Associate involvement and empowerment
LBHC link
7
Total Project Savings
Total project savings:
• Reduced process time by 30.1% reduction (Target 10% reduction)
• Reduction in Work In Progress by 83% 576 to 98 pieces (target 80% reduction)
• Reduce lead time through production process by 92% from 31.2 days to 2.5 days (target 85% reduction)
8
Project Teams
The following teams implemented specific projects:
Team 1A Production
Team 1B Final Packaging
Team 2A Stores
9
Team 1A
Production Colour Coded Kanban System
Production/Assembly
10
Project Scope and Objectives
Opportunity Statement:
Setup permanent work stations for each area
Introduce a color code system for each work station
Reduce Work In Progress inventory
Reduce process times
Reduce chance of missing tools
Project helps (Quality, Cost & Delivery):
Waiting times, Defects, Motion, Inventory & Space
11
Project Steps
Implementation Steps:
1. Plan layout of production work stations considering process flow
2. Remove all unwanted items from work areas using white tags
3. Arrange all work stations using color coding system
4. Work out what tools were needed for each station and order tools
5. Set up shadow boards for tools and color code tools to match stations
6. Assist in setting up 2 bin system for materials at each station
12
Project Outcomes
Planned Improvements:
1. Reduced process time by 10% (actual 30.1% reduction)
2. Reduction in Work In Progress by 50% (actual 83% reduction)
13
Project Outcomes
Before After
14
Project Outcomes
Before After
15
Project Outcomes
Before After
16
Project Outcomes
Before After
17
Project Outcomes
Before After
18
Some Other Improvements
Vacuum pump saving
Mobile Gluing Unit
Innovation of shop floor to combine heat cell and cold tank assembly station utilizing existing vacuum pump and eliminating the need to buy a second vacuum pump.
Saving = approx. $1500
Innovation of shop floor to make the hot glue machine mobile to allow for flexibility and storage under workstation. This makes the unit easily accessible when it requires refilling.
19
Team 1B
Improved process layout
Final Assembly & Packaging Area
20
Project Scope and Objectives
Opportunity Statement:
Reduce packaging time
Optimise packing flow and efficiency
Optimise inventory qantities, locations and layout
Project helps (Quality, Cost & Delivery):
Waiting times, Motion, Inventory & Space
21
Project Steps
Implementation Steps:
1. Plan new layout
2. Relocate shelf and table
3. Optimise layout to support single piece flow
4. Shelf setup
5. Container dispense for systematic supply of parts
6. Container labelling and relocation
7. Floor marking and min/max levels
8. Implement 2 bin systems
9. Final modifications, measure savings and presentation
22
Project Outcomes
Planned Improvements:
1. Reduced process time by 39% (actual 58% reduction 13 to 6 min)
2. Reduction in travel disctance 15% (actual 75% reduction 53m to 13m)
3. Reduced time to restock supplies (Savings including in above)
23
Project Outcomes
Before After
24
Project Outcomes
Before After
25
Team 2A
Implement 2 Bin Production Supply System
Stores
26
Project Scope and Objectives
Opportunity Statement:
Reduce inventory in production areas
Reduce lead time to supply parts
Create milkrun replenishment system to eliminate waiting time for materials
Project helps (Cost & Delivery):
Waiting times, Overproduction, Motion, Inventory, transport & Space
27
Project Steps
Implementation Steps:
1. 80/20 analysis of parts supply from stores to production
2. Establish Bill Of Materials for each station and calculate replenishment qty for each part type for each station
3. According to calculations select appropriate bin sizes and determine color coding for each station, then purchase materialsas required
4. Design trolley for empty bin holding location and train all staff how to use new system
5. Setup and label all bins with part no., qty, location and station number and then fill with correct qty of parts
6. Setup and train involved people about milkrun
7. Measure project savings and present to management
28
Project Outcomes
Planned Improvements:
1. Reduced Work In Progress 80% (actual 83% reduction 576 to 98 pieces)
2. Reduction in lead time to replenish parts 50% (actual 63% reduction 2 hours to 44 minutes)
3. Reduced space used by excess WIP and materials by 20% (actual 20% savings from 15 work stations to 12 work stations)
4. Cleaner and tidier work stations (See pictures)