  • LXB RP (Gloucester) Ltd

    Construction Management Strategy

    Railway Triangle Site Metz Way Gloucester

  • Metz Way, Gloucester MLM Consulting Engineers Ltd Construction Management Strategy

    X:\MLM Ashford\614462_Dev_Gloucester\Docs\reports\12_08_03 CMS_Gloucester_463C.doc

    Project Revision Sheet Revision No Date Status Changes Author Approved

    0 February 2012 Draft n/a Jonathan Rodger Les Brown

    A February 2012 Final Minor changes

    Jonathan Rodger Les Brown

    B May 2012 Final Minor changes

    Jonathan Rodger Les Brown

    C August 2012 Final Minor changes

    Jonathan Rodger Les Brown

  • Metz Way, Gloucester MLM Consulting Engineers Ltd Construction Management Strategy

    X:\MLM Ashford\614462_Dev_Gloucester\Docs\reports\12_08_03 CMS_Gloucester_463C.doc

    Contents Page 1 Introduction 1

    2 Existing Highway Network 2

    3 Construction Strategy 4

    4 Public Consultation 6

    5 Summary and Conclusions 7

    Appendices Appendix 1: Local Road Network Appendix 2: Routeing Strategy

  • Metz Way, Gloucester MLM Consulting Engineers Ltd Construction Management Strategy

    X:\MLM Ashford\614462_Dev_Gloucester\Docs\reports\12_08_03 CMS_Gloucester_463C.doc 1

    1 Introduction 1.1 MLM Consulting Engineers have been instructed to provide a Construction

    Management Strateg y associated with a planning application (11/00902/OUT) for the development at the Railway Triangle at Metz Way in Gloucester. The site has approval for a hybrid planning application for:

    1.2 Detailed planning permission for:

    Retail food store for 6,800sqm Petrol filling station Associated parking and means of access from Metz Way Outline planning permission for: Office, Storage and distribution for 15,264sqm Car showroom for 1,024sqm Additional retail uses of 571sqm

    1.3 This Cons truction Ma nagement St rategy will review the access required

    for the enabling works only. The enabling works are the creation of a new access from the site to Metz Way and required site work. This includes the erection of perimeter h ording, Heras fencing to the si te compound which will include the site storage, parking areas and welfare facilities.

    1.4 After the n ew access on to Metz Way is constru cted t he si te wil l be

    accessed solely from Metz Way and Bl inkhorns Bridge will cease to be used. All co nstruction work following the enabling work ( including phase 1) will be subject to a separate Construction Mana gement Strategy utilising M etz Way . Smit hs ( Gloucester) w ill be respon sible f or undertaking the wor ks and have appointed a Si te Manager to super vise. The Site Manager is Matt Bennett, his contact details are as follows:-

    1.5 Section 2 reviews the local network and local constraints, section 3

    reviews the proposal t o obtain sui table access to the si te to enabl e the access ramp to be construction from Metz Way. Section 4 provides a strategy for communicating with the public and Section 5 summarises and concludes this review.

  • Metz Way, Gloucester MLM Consulting Engineers Ltd Construction Management Strategy

    X:\MLM Ashford\614462_Dev_Gloucester\Docs\reports\12_08_03 CMS_Gloucester_463C.doc 2

    2 Existing Highway Network 2.1 The site is bound by Metz Way to the south and railway lines to north and

    east. Access to the cur rent site is vi a Blinkhorns Bridge Lane which leads to the north under the railway line to the local residential area. Blinkhorns Bridge Lane joins Armscroft Road wh ich leads to Barnwood Road (A38). The local road network can be reviewed in Appendix 1.

    2.2 Blinkhorns Bridge Lane comprises of a narro w l ane whi ch passes under

    the nort hern rai lway li ne. Thi s provi des wi dth an d hei ght restri ctions allowing access for small and med ium sized vehicles (i.e. cars and transit vans).

    2.3 Within the housing area towards t he nort hern end o f Bl inkhorns Bri dge

    Lane and Armscroft Road the streets comprise of a typical layout with un-restricted parking for residents. Within close pr oximity t o th e junct ion with Barnwood Road double yellow lines are present. Some of the local streets have dwellings that have off road parking however Armscroft Road is mainly terraced properties with parking mainly on street.

    Left: Armscroft Road Right: Blinkhorns Bridge Lane

    2.4 The geomet ry is t ypical f or res idential st reets an d t ypical carr iageway

    widths as per Manual for Streets are:

    Blinkhorns Bridge Lane

  • Metz Way, Gloucester MLM Consulting Engineers Ltd Construction Management Strategy

    X:\MLM Ashford\614462_Dev_Gloucester\Docs\reports\12_08_03 CMS_Gloucester_463C.doc 3

    2.5 The width of Armscroft Road is a pproximate 6.1m wide and therefore even with on street parking the ro ad should be sufficient for larger vehicles. H owever based on in itial researc h park ing occurs in close proximity t o t he jun ctions which may resu lt in a redu ction in manoeuvrability space for larger vehicles at the junctions.

    2.6 It should also be n oted that the local area p rovides turning facilities for

    typical vehicles (refuse vehicles) whi ch would be requi red to serve the residential properties and therefore based on the above this route is not suitable for larger vehicles.

    2.7 Barnwood Road (A38) comprises of a 4 lane carriageway with parking

    restrictions along its enti re length which acts as a bypass for the central area of Gloucester a nd provides access to the M5 via the A417. Approximately 300 m t o the east of the Armscroft Road the road passes under the railway line which has a height restriction of 16 feet.

    2.8 Metz Way (A4302) is approximately 6m higher than the site at the site

    boundary. Metz Way provides a 10m wide single carriageway with central hatching carriageway markings to restrict overtaking manoeuvres.

    2.9 Metz Way comprises of a 40 mph speed lim it w ith all ot her local r oads

    subject to a 30 mph limit.

  • Metz Way, Gloucester MLM Consulting Engineers Ltd Construction Management Strategy

    X:\MLM Ashford\614462_Dev_Gloucester\Docs\reports\12_08_03 CMS_Gloucester_463C.doc 4

    3 Construction Strategy

    3.1 The construction of the site will be undertaken in two stages: Enabling works via access from Blinkhorns Bridge Lane All other construc tion works vi a a ne w acc ess from M etz Way i n

    accordance with the planning permi ssion for th e site and subject to a separate Construction Management Strategy

    Access Requirements

    3.2 The fi rst task wi ll be to construct the access road from the site to Metz Way. During t his st age all t raffic w ill h ave t o pass under Bl inkhorns Bridge ( and comply w ith th e rest rictions) an d t ravel t hrough the loca l residential area.

    3.3 It is therefore import ant that this stage be undertake n with minimal

    impact u pon local res idents, an d t hat local residents will be advised accordingly.

    3.4 All vehi cles l arger than a tra nsit type van (and l ess t han the t unnel

    restriction) wi ll be brought to si te wi thin the fi rst two day s of construction. The equi pment requ ired for the construc tion of the ac cess road will consist of a tracked excavator and four dumper trucks.

    3.5 This w ill re quire t he del ivery of t he abov e veh icles by f lat bed t railers,

    which are unabl e to pass under Blinkhorns Bridge. These vehicles will have to unl oad before Blinkhorns Bridge Lane as the current layout may not provi de su fficient area for l arger vehi cles to turn and l eave vi a the same route, as highlighted within Section 2.

    3.6 It is propos ed that the flat bed trai lers will unload on Armscroft Place on

    the wider section of the road next to the green. This will reduce the impact on residents.

    3.7 Due to the potential hazards of l arger vehicles entering A rmscroft Road,

    depending on the delivery of site plant, advance signage may be advisable to reduce the risk. In a ddition photographs of the surrounding area wi ll be taken pri or to the construction pl ant a nd vehicles being delivered to site at commencement of the project.

    3.8 Following t he in itial d elivery of l arge plan t, access t o t he sit e wil l be

    restricted to vehi cles similar to a transi t van as all the plant requi red for the construction of the access road w ill be a ll on site. Subsequent traffic will be primaril y for site personne l and no more than 12 transit sized vans, or smaller, per day.

    3.9 It is en visaged that the access ramp w ill be completed within six weeks

    after the d elivery of t he i nitial plant to si te. Therefore by t he sev enth week all tr affic will us e the new a ccess via Metz Way and cease to use Blinkhorns Bridge Lane.

    3.10 All constru ction traffi c and con struction works will be restricted to

    weekdays and between the hours of 07:30 and 18:00, a summary of the above can be reviewed in Appendix 2.

  • Metz Way, Gloucester MLM Consulting Engineers Ltd Construction Management Strategy

    X:\MLM Ashford\614462_Dev_Gloucester\Docs\reports\12_08_03 CMS_Gloucester_463C.doc 5

    Site Requirements and Management 3.11 To allow t he con struction of the access road a sit e compou nd will be

    established. This will p rovide a secure area f or staff and v isitor parking, storage and welfare areas.

    3.12 Signing in procedures will be implemen ted for the si te. This wi ll aid si te

    safety and will also monitor the number of vehicle trips to and from the site within the first 6 weeks.

    3.13 To