maidenhead station improvements modelling report: proposed
TRANSCRIPT
Maidenhead Station Improvements
Modelling Report:
Proposed at-grade crossing improvements
Date: October 2017
Created by
Jessica Cecchinell i [email protected]
© Project Centre Proposed at-grade crossing improvements 1
CONTENTS PAGE PAGE NO.
1. INTRODUCTION 2.
2. EXISTING SITUATION
2.1 Road Network
2.2 Traffic Volumes
2.3 Signal Timing and Timetable
3. BASE MODELLING 9
3.1 LinSig Structure
3.2 Saturation Flows
3.3 Signal Data
3.4 Demand Dependent Stages / Bonus Greens
3.5 Underutilised Green Times
3.5 Base model validation and conclusion
4. DESIGN AND MODELLING 19
4.1 Introduction
4.2 ‘MOVA Current Scenario’ & MOVA Proposed Scenarios
4.3 Proposed Design
4.4 Proposed Modelling
4.5 Traffic Reassignment
4.6 Proposed LinSig Structure
4.7 Signal Timings
4.8 Proposed Intergreen Periods
4.9 Saturation Flows
5. MODELLING RESULTS 31
6. CONCLUSIONS & RECOMMENDATIONS 42
APPENDIX A – BASE LINSIG MODEL RESULTS
APPENDIX B - PROPOSED LINSIG MODEL RESULTS
APPENDIX C – GENERAL ARRANGEMENTS
INFORMATION AVAILABLE ON REQUEST
MCC AND QL SURVEY DATA
EMAIL CORRESPONDENCE & RAW SIGNAL DATA
SATURATION FLOW DATA
ANALYSED SIGNAL DATA
OBSERVED DEGREE OF SATURATION DATA
QUALITY
© Project Centre Proposed at-grade crossing improvements 2
1. INTRODUCTION
This report supports work undertaken to develop a business case for the
Maidenhead Station Access scheme.
Improvement proposals involve enhancements to pedestrian and cycling
facilities and improvements to the public realm that will notably enhance the
accessibility and functionality of the Station, reacting to planned growth in
passenger numbers and significant development activity within the Town centre
area.
One of the key outcomes of the scheme will be an improvement in crossing
facilities at the station. Current at-grade signalised road crossings that link the
town centre to the station are convoluted and there is limited public realm
space for large groups of pedestrians to wait.
Options have been developed to improve the at-grade crossings and
accommodate future growth in pedestrians, cyclists and motor vehicle traffic
associated with passenger growth at Maidenhead Station.
LinSig computer software has been used to simulate base (existing) traffic
conditions and predict how the junctions would operate with proposed layout
options in place.
This technical report describes the modelling, validation and option assessment
process and presents associated conclusions and recommendations.
© Project Centre Proposed at-grade crossing improvements 3
2. EXISTING SITUATION
2.1 Road Network
The road network within the study area comprises of three signal controlled
junctions, which are listed below:
Grenfell Place / Grenfell Road;
Grenfell Road / Queen Street / King Street; and
King Street / Braywick Road / Shoppenhangers Road.
Figure 2.1 illustrates the extent of the study area (highlighted in red) and the
location of the signalised junctions within the network (highlighted with blue
circles / arrows) that this technical report provides information.
Figure 2.1 – Location Plan
© Project Centre Proposed at-grade crossing improvements 4
Grenfell Place / Grenfell Road
The Grenfell Place / Grenfell Road junction is a signalised three-arm junction.
The junction, at the time of the traffic surveys, was running on CLF plans and the
signal stage sequence for the junction is shown in Figure 2.2.
Figure 2.2 – Signal Stage Sequence (Grenfell Place / Grenfell Road junction)
Grenfell Road / Queen Street / King Street
The Grenfell Road / Queen Street / King Street junction is a signalised six-arm
junction. The junction, at the time of the traffic surveys, was running on CLF
plans. The existing traffic signals operate a two stage sequence (in order of
stages 1, 3). The first stage is for traffic on Grenfell Road, King Street and Keys
Place and pedestrian movement across the westbound and southbound Queen
Street arms. Stage 3 is dedicated to traffic on the westbound and southbound
Queen Street approaching lanes together with pedestrian crossing movements
across Grenfell Road, King Street and Keys Place.
Figure 2.3 – Signal Stage Sequence (Grenfell Road / Queen Street / King Street junction)
King Street / Braywick Road / Shoppenhangers Road
The King Street / Braywick Road / Shoppenhangers Road junction is a signal
controlled three-arm junction. The junction, at the time of the traffic surveys,
© Project Centre Proposed at-grade crossing improvements 5
was running on CLF plans and the traffic signals operate in three stages (in order
of stages 1, 2, 3). The first stage is for traffic on Braywick Road and King S treet
(ahead traffic flow only), and pedestrian movements across Shoppenhangers
Road (Phase I) and King Street Road right turn arm (Phase J). Stage 2 provides
an extended green to the ahead traffic flow on King Street (early cut -off to the
northbound approach) and allows the simultaneous discharge of the left turning
traffic flow on Shoppenhangers road and the right turning traffic fl ow from King
Street into Shoppenhangers Road. Pedestrians on Braywick Road approaching
lanes are also allowed to cross within this stage.
Figure 2.4 –
Signal
Stage
Sequence
(King
Street /
Braywick
Road /
Shoppenhangers Road junction)
2.2 Traffic Volume
Traffic surveys were required to review the volume, speed and mix of traffic on
the network between Grenfell Place / Grenfell Road and King Street / Braywick
Road / Shoppenhangers Road junctions.
Fully classified (junction) turning counts (MCC) and queue length (QL) surveys
were carried out on Tuesday 29th August 2017 (weekday AM and PM peak
periods). The MCC data has been analysed by PCL to establish the peak hours
as follows:
Weekday morning peak hour (AM) – 08:00 - 09:00; and
Weekday evening peak hour (PM) – 17:00 - 18:00.
The traffic and signal data associated with these peak hours have been used to
develop the validated base LinSig models. The peak hour traffic flows, in
passenger car units (PCUs), are presented graphically in the traffic flow
diagrams (Figures 2.5 – 2.6) below. Comprehensive MCC survey and Queue
Length data is contained in Appendix A of this report.
© Project Centre Proposed at-grade crossing improvements 6
Figure 2.5 – AM Peak hour Traffic Flows (in PCUs)
© Project Centre Proposed at-grade crossing improvements 7
Figure 2.6 – PM Peak hour Traffic Flows (in PCUs)
© Project Centre Proposed at-grade crossing improvements 8
In addition, video surveys have been completed on the same day and time periods as
the classified junction turning counts and queue length surveys. The video surveys were
set to capture traffic signal heads and traffic discharge at stop lines on each approach
of the signalised junctions.
2.3 Signal Timing and Timetable
The CLF plans signal timing and timetables have been derived from the controller
specifications provided by RBWM.
The relevant signal information and the email correspondence with RBWM are
contained in Appendix B of this report.
© Project Centre Proposed at-grade crossing improvements 9
3. BASE MODELLING
3.1 LinSig Structure
Base LinSig modelling of the junctions has been undertaken, as agreed RBWM, for the
morning (AM) and evening (PM) peak periods on a neutral weekday.
The base LinSig models were built using information from the OS map, site visit and
traffic behaviour observed from the video survey footage.
The LinSig structure has been developed to represent the layout of the junctions within
the study area, taking into account all allowed movements at each junction. Figure 3.1
below shows the LinSig link structure that has been developed and used to model the
junctions within the study area between Grenfell Place / Grenfell Road and King
Street / Braywick Road / Shoppenhangers Road junctions.
Figure 3.1 – Link Structure for Base Model
© Project Centre Proposed at-grade crossing improvements 10
As can be seen from Figure 3.1, the offside southbound King Street approach to the
Shoppenhangers Road / King Street / Braywick Road junction which is a lane
dedicated to the right turning traffic, has been modelled as a long lane instead of a
flare. The video observations have revealed that there are times in which the traffic
queue extends from the upstream junction. More so, the modelling of the offside lane
as flare in LinSig means that there is a mutual interaction between traffic in the middle
lane and offside flare whilst the video footage has confirmed that the operation of this
lane does not affect the traffic queue and discharge of the middle one.
In addition, the southbound offside Queen Street lane (right traffic flow) has been
modelled as long lane due to the traffic and queuing conditions which makes this lane
largely used during the peak hours. However, the southbound offside Queen Street lane
(middle lane) in which it has been observed a lower traffic flow, has not been modelled
as a flare due to LinSig limitations.
3.2 Saturation Flows
Link saturation flows were measured using video recordings where possible. The
saturation flow for each lane has been derived as an average of 5 measurements.
During the saturation flow measurements, it was observed that some lanes experience
exit blocking which inhibits free flow conditions whilst other lanes have low traffic
demand. For these lanes, the RR67 formula (based on lane geometry) was used to
estimate the saturation flows.
A summary of the saturation flows used in the base models are listed in Table 3.1 below.
The full saturation flow data is provided in Appendix C.
© Project Centre Proposed at-grade crossing improvements 11
Table 3.1 – Measured / Calculated Saturation Flows
Link Saturation Flow Measured or
Calculated
Grenfell Road / Green Place
Grenfell Place SB Approach- N/S 2003 Measured
Grenfell Place SB Approach- O/S 2016 Measured
Grenfell Road EB Approach- N/S 2049 Measured
Grenfell Road WB Approach- N/S 1992 Measured
Grenfell Road WB Approach- O/S 2009 Measured
Grenfell Road / Queen Street / King Street / Keys Place
Grenfell Road EB Approach- N/S 1999 Measured
Grenfell Road EB Approach- O/S 1920 Measured
King Street NB Approach- N/S 1968 Measured
King Street NB Approach- O/S 1968 Measured
Queen Street SB Approach- N/S 2003 Measured
Queen Street SB Approach- O/S (middle lane) 2015 Calculated
Queen Street SB Approach- O/S (RT) 1995 Measured
Queen Street WB Approach- N/S 1944 Measured
Queen Street WB Approach- O/S 1903 Measured
Keys Place SB Approach- N/S 2065 Calculated
King Street / Braywick Road / Shoppenhangers Road
Braywick Road NB Approach- N/S 1872 Measured
Braywick Road NB Approach- O/S 1982 Measured
King Street SB Approach- N/S 1981 Measured
King Street SB Approach- O/S (middle lane) 2015 Measured
King Street SB Approach- O/S (LT) 1944 Measured
Shoppenhangers Road EB Approach- N/S 1937 Measured
© Project Centre Proposed at-grade crossing improvements 12
3.3 Signal Data
The signalised junctions, at the time of survey were running on CLF plans. The controller
specifications provided by RBWM have been analysed to obtain the stage durations
and cycle times for each junction during the assessed peak hours. However, the video
footage analysis has evidenced that the cycle time values on the Grenfell Road /
Grenfell Place and Grenfell Road / Queen Street / King Street junctions are lower than
the CTs indicated in the CLF plans (90s in the AM peak and 86s in the PM peak).
Therefore, further video analysis has been carried out to determine the green time
allocated to each lane and the accurate cycle times at these two junctions. Table 3.2
shows a summary of the cycle times and stage durations for each junction during the
peak periods.
Table 3.2 – Stage Durations and Cycle Time, seconds (s)
Stage AM Peak PM Peak
Grenfell Road / Green Place
1 60 59
2 20 18
Cycle Time 80 77
Grenfell Road / Queen Street / King Street / Keys Place
1 50 45
3 24 34
Cycle Time 74 79
King Street / Braywick Road / Shoppenhangers Road
1 46 46
2 30 26
3 14 14
Cycle Time 90 86
3.4 Demand Dependent Stages / Bonus Greens
The controller specifications indicates that Stage 2 of the Grenfell Road / Grenfell Place
junction and Stages 2 and 3 of the King Street / Braywick Road / Shoppenhangers Road
junction are demand dependent and can be called in if there is demand for traffic
phase. The video analysis has confirmed that these stages are called in all the times
during the assessed peak hours. Therefore, no bonus greens have been accounted for
in the modelling.
© Project Centre Proposed at-grade crossing improvements 13
3.5 Underutilised Green Times
The video survey footage has been analysed to determine the parameters for
calculating the observed degrees of saturation (DoS) on all approach lanes to the
junctions during the peak hours.
The analysis of the observed DoS established that there is currently underutilised green
time (UGT) on some of the approach lanes to the junctions. The UGT was observed to
be as a result of exit blocking and slow moving vehicles (high HGV proportion, at times).
Figure 3.2 below shows examples of issues causing UGT occurrences at the junctions.
Figure 3.2 – Exit blocking on King Street NB and Braywick Road NB; AM peak
As can be seen in Figures 3.2, exit blocking occurs during the AM peak period on
Braywick Road and King Street approaches heading northbound from the King Street /
Braywick Road / Shoppenhangers Road junction due to traffic queues extending from
the Grenfell Place / Grenfell Road signalised junction.
Table 3.3 below shows all the UGT included in the base modelling for all approach lanes
to the junction.
© Project Centre Proposed at-grade crossing improvements 14
Table 3.3 – UGT included in Base Model, seconds (s)
3.6 Base model validation and conclusion
The video survey footage has been analysed to derive the observed Degree of
Saturation (DoS) for each of the lane approaches of the junctions. The DoS has been
obtained for all of the modelled peak hours.
Approach Link
UGT applied (s)
AM PM
Grenfell Road / Green Place
Grenfell Place SB Approach- N/S J1: 1/1 -4 -11
Grenfell Place SB Approach- O/S J1:1/2 -1 -1
Grenfell Road EB Approach- N/S J1:2/1 -1 –
Grenfell Road WB Approach- N/S J1:8/1 -5 -3
Grenfell Road WB Approach- O/S J1:8/2 -4 -2
Grenfell Road / Queen Street / King Street / Keys Place
Grenfell Road EB Approach- N/S J2:2/1 -1 -3
Grenfell Road EB Approach- O/S J2:2/2 -1 -2
King Street NB Approach- N/S J2:3/1 -10 -6
King Street NB Approach- O/S J2:3/2 -2 -5
Queen Street SB Approach- N/S J2:1/1 – -1
Queen Street SB Approach- O/S (middle
lane) J2:1/2 – –
Queen Street SB Approach- O/S (RT) J2:1/3 – -3
Queen Street WB Approach- N/S J2:4/1 – -4
Queen Street WB Approach- O/S J2:4/2 – -2
Keys Place SB Approach- N/S J2:5/1 – -3
King Street / Braywick Road / Shoppenhangers Road
Braywick Road NB Approach- N/S J3:3/2 -11 -10
Braywick Road NB Approach- O/S J3:3/3 -6 -6
King Street SB Approach- N/S J3:1/1 – -6
King Street SB Approach- O/S (middle lane) J3:1/2 -1 -3
King Street SB Approach- O/S (LT) J3:1/3 – -2
Shoppenhangers Road EB Approach- N/S J3:4/1 -6 -2
© Project Centre Proposed at-grade crossing improvements 15
The observed values and base model results for the DoS at all approaches, during all
peak periods, are summarised in Table 3.5. Appendix E provides the base LinSig models
and results and Appendix F has a comprehensive observed DoS data.
Table 3.4 - Comparison of Observed and Modelled Degrees of Saturation (DoS)
Degree of Saturation (%)
AM PM
Observed Modelled Diff Observed Modelled Diff
Grenfell Road / Green Place
Grenfell Place SB Approach- N/S 39% 38% 1% 44% 44% 0%
Grenfell Place SB Approach- O/S 37% 33% 4% 31% 32% -1%
Grenfell Road EB Approach- N/S 80% 77% 3% 87% 87% 0%
Grenfell Road WB Approach- N/S 60% 62% -2% 62% 66% -4%
Grenfell Road WB Approach- O/S 66% 66% 0% 56% 55% 1%
Cycle Time 80 77
Grenfell Road / Queen Street / King Street / Keys Place
Grenfell Road EB Approach- N/S 42% 42% 0% 70% 72% -2%
Grenfell Road EB Approach- O/S 54% 54% 0% 55% 52% 3%
King Street NB Approach- N/S 88% 91% -3% 82% 82% 0%
King Street NB Approach- O/S 82% 78% 4% 79% 80% -1%
Queen Street SB Approach- N/S 35% 34% 1% 63% 64% -1%
Queen Street SB Approach- O/S (middle
lane) 15% 13% 2% 18% 13% 5%
Queen Street SB Approach- O/S (RT) 34% 29% 5% 60% 55% 5%
Queen Street WB Approach- N/S 40% 37% 4% 68% 64% 4%
Queen Street WB Approach- O/S 37% 39% -2% 71% 70% 1%
Keys Place SB Approach- N/S 9% 8% 1% 26% 22% 4%
Cycle Time 74 79
King Street / Braywick Road / Shoppenhangers Road
Braywick Road NB Approach- N/S 79% 83% -4% 69% 66% 3%
Braywick Road NB Approach- O/S 60% 56% 4% 43% 40% 3%
King Street SB Approach- N/S 38% 37% 1% 60% 61% -1%
King Street SB Approach- O/S (middle 34% 29% 5% 41% 38% 3%
© Project Centre Proposed at-grade crossing improvements 16
Table 3.5 - Comparison of Observed and Modelled Mean Maximum Queue (MMQ)
lane)
King Street SB Approach- O/S (LT) 35% 39% -4% 86% 84% 2%
Shoppenhangers Road EB Approach- N/S 89% 93% -4% 76% 73% 3%
Cycle Time 90 86
Mean Maximum Queue (PCUs)
AM PM
Observed Modelled Diff Observed Modelled Diff
Grenfell Road / Green Place
Grenfell Place SB Approach- N/S 3 6 -3 5 7 -2
Grenfell Place SB Approach- O/S 2 5 -3 5 4 1
Grenfell Road EB Approach- N/S 6 7 -1 6 9 -3
Grenfell Road WB Approach- N/S 5 11 -6 7 12 -5
Grenfell Road WB Approach- O/S 7 13 -6 6 9 -3
Cycle Time 80 77
Grenfell Road / Queen Street / King Street / Keys Place
Grenfell Road EB Approach- N/S 5 6 -1 7 13 -6
Grenfell Road EB Approach- O/S 5 8 -3 7 8 -1
King Street NB Approach- N/S 10 19 -9 13 14 -1
King Street NB Approach- O/S 11 15 -4 10 14 -4
Queen Street SB Approach- N/S 2 1 1 3 11 -8
Queen Street SB Approach- O/S (middle
lane) 1 1 0 2 0 2
Queen Street SB Approach- O/S (RT) 1 1 0 3 3 0
Queen Street WB Approach- N/S 3 3 0 7 8 -1
Queen Street WB Approach- O/S 3 3 0 0 9 -9
Keys Place SB Approach- N/S 2 1 1 3 3 0
Cycle Time 74 79
King Street / Braywick Road / Shoppenhangers Road
Braywick Road NB Approach- N/S 7 18 -11 8 12 -4
Braywick Road NB Approach- O/S 6 10 -4 5 6 -1
King Street SB Approach- N/S 3 5 -2 3 11 -8
© Project Centre Proposed at-grade crossing improvements 17
As shown in Tables 3.5 and 3.6, the base LinSig model results compare reasonably well
with the observed values (DoS and MMQ), which suggest an accurate simulation of the
existing traffic conditions. In Table 3.5, the difference between the observed DoS and
modelled values for each link is +/-5% or less.
All arms of the Grenfell Road / Grenfell Place junction operate significantly below the
maximum desired practical capacity of 90% DoS during the observed peak hours. The
highest DoS (of 87% for the observed and modelled) were experienced on Grenfell
Road (eastbound) during the PM peak period.
The King Street northbound approach (nearside lane) is operating slightly over the
desired maximum practical capacity of 90% DoS during the AM peak hour. The lane
also operates at high capacity, close to but less than 90%, during the PM peak hours.
This is evident in both the modelled and the observed DoS values in Table 3.5. This is
observed to be caused by the high volume of traffic and the occurrence of exit
blocking on this approach.
Similarly, Shoppenhangers Road (eastbound) approach of the King Street / Braywick
Road / Shoppenhangers Road junction is currently operating at high capacity during
the AM peak period with modelled value of 93% (slightly above than 90%) but
operating below the desired maximum practical capacity of 90% during the PM peak
hour.
All other approach lanes operate below the desired maximum practical capacity of
90% during all peak hours.
The modelled MMQ compares very well with the observed MMQ on all the approach
lanes of the junction (during all peak hours). The capacity issues identified through the
DoS values are reflected very well in the MMQ of those approaches.
The base LinSig model is found to be robust and representative of the existing traffic
conditions during the time of the surveys at the signalised junction for the assessed peak
hours. It is therefore concluded that the validated base model can be used to assess
the impact of proposed schemes in terms of lane capacities and queue lengths.
King Street SB Approach- O/S (middle
lane) 3 4 -1 3 5 -2
King Street SB Approach- O/S (LT) 4 4 0 8 10 -2
Shoppenhangers Road EB Approach- N/S 13 14 -1 10 8 2
Cycle Time 90 86
© Project Centre Proposed at-grade crossing improvements 18
4. DESIGN AND MODELLING
4.1 Introduction
Two options have been developed for improving the existing at-grade crossings at
Grenfell Road / Queen Street / King Street signalised junction. Outcomes of the
modelling work undertaken are described below.
4.2 ‘MOVA Current Scenario’ & MOVA Proposed Scenario
The linked Microprocessor Optimised Vehicle Actuation (MOVA) system is
proposed to be implemented at Grenfell Road / Queen Street / King Street,
Grenfell Road / Green Place and King Street / Braywick Road / Shoppenhangers
Road junctions.
As mentioned previously, the traffic control strategy MOVA will be implemented in the
proposed network to maximise the operational efficiency of the junctions. The process
of MOVA is based on two modes of operation which depend on the road conditions –
congested and uncongested (free flowing). In free flowing mode the aim of MOVA is to
disperse any queues which have built up on a red signal, it then assesses the traffic
flows approaching on each arm of the junction and calculates if extending the current
green would be beneficial. If it is beneficial then the current green is extended and the
calculation is repeated.
When the network is congested MOVA operates in capacity maximising mode. This
assesses which approaches are overloaded and how efficiently the green is being used
and seeks to determine a set of signal timings which will maximise the throughput of the
junction under the current conditions.
As described in paragraph 3.3, the modelled network was operating on CLF plans at
the time of the traffic surveys. Therefore, the proposed MOVA timing data have been
applied to the validated base for comparison with the proposed options. In order to
replicate the operation of this traffic control system in LinSig software, the signal timings
of each junction have been optimised and higher cycle time values have been used in
the models ensuring the entire network running within capacity.
The analogous methodology has been applied in the modelling of the proposed
options.
4.3 Proposed Design
PCL has developed two at-grade crossing options. These proposed designs involve
some changes to the existing layout of the Grenfell road / Queen Street / King Street
junction which are briefly described below and shown in Appendix H:
© Project Centre Proposed at-grade crossing improvements 19
Option 1
Removal of right turn from Queen Street to A308 to provide wider pavements
and new public space;
Footways would be re-paved in area to create consistent and legible route
between town centre and Station; and
Two-stage crossing over A308.
Option 2
Queen Street amended to join A308 at new junction;
Footways re-paved to create consistent and legible route between town
centre and Station;
Pedestrian / cycle route amended to east side of A308; and
Two-stage crossing over A308.
Appendix H contains the General Arrangement (GA) of the proposed designs
described above.
4.4 Proposed Modelling
The models for the two proposed options have been modelled from the calibrated /
validated base LinSig models with changes made to the base models described below:
Option 1
The proposed option has been modelled with the cycle times used in the
‘MOVA current scenario’ (96s and 72s in the AM and PM peak hours
respectively) and higher cycle time values (104s and 88s in the AM and PM
peaks);
Intergreen re-measured (calculated to TfL SQA-645 standard);
Method of Control (MoC) has not been altered; and
Reassignment of traffic flow due to closure of right turning traffic on Queen
Street.
Option 2
The proposed option has been modelled with the cycle times used in the
‘MOVA current scenario’ (96s and 72s in the AM and PM peak hours
© Project Centre Proposed at-grade crossing improvements 20
respectively) and higher cycle time values (104s and 120s in the AM and PM
peaks);
Intergreen re-measured (calculated to TfL SQA-645 standard); and
Method of Control amended to include pedestrian stream for the pedestrian
crossing across the southbound A308 exit lane.
4.5 Traffic Reassignment
The closure of Queen Street right turning traffic to A308 has involved the diversion of the
traffic exiting town centre through the entire network. However, to reduce the diversion
route length, there is potential to make a section of Broadway two-way between
Nicholson’s and A308. Therefore, two different scenarios have been modelled for
Option 1.
The peak hours re-assigned traffic flow used in the proposed Option 1 are shown
graphically, in passenger car units (PCUs), in the traffic flow diagrams (Figure 4.1– 4.2)
below.
© Project Centre Proposed at-grade crossing improvements 21
Figure 4.1 a) – AM Peak hour - Reassigned Traffic Flows (in PCUs) through the network
© Project Centre Proposed at-grade crossing improvements 22
Figure 4.1 b) – PM Peak hour - Reassigned Traffic Flows (in PCUs) through the network
© Project Centre Proposed at-grade crossing improvements 23
Figure 4.2 a) – AM Peak hour - Reassigned Traffic Flows (in PCUs) through Broadway
© Project Centre Proposed at-grade crossing improvements 24
Figure 4.2 b) – PM Peak hour - Reassigned Traffic Flows (in PCUs) through Broadway
A
4.6 Proposed LinSig Structure
As can be seen in Figure 4.3, the LinSig structure for Option 1 has remained the same as
the base model with the exception of the southbound Queen Street right turn
approach to the Grenfell Road / Queen Street / King Street junction which has been
removed. In addition the pedestrian crossing facility across this lane has been also
removed.
Figure 4.3 – Link Structure for Proposed Model – Option 1
B
Figure 4.4 shows the LinSig structure used for Option 2. The southbound Queen Street
arm has been amended and two internal links of 1 PCU length have been provided on
the southbound A308.
Figure 4.4 – Link Structure for Proposed Model – Option 2
C
4.7 Signal Timings
The proposed methods of control for the two modelled options are shown below in
Figure 4.5 – 4.6.
Figure 4.5 – Proposed Method of Control – Option 1
The signal stage sequence for the Grenfell Road / Queen Street / King Street junction
will continue to operate a two stage sequence.
Figure 4.6 – Proposed Method of Control – Option 2
The proposed junction is proposed to operate a two stage signal sequence and will
largely be unchanged, with the exception of a separate stream for the pedestrian
D
crossing across the southbound A308 exit lane. This stream (Stream 2) is necessary to
control southbound traffic leaving the junction and the signalised pedestrian crossing
facility.
4.8 Proposed Intergreen Periods
Proposed Option 1
The proposed intergreens for the proposed Option 1 are illustrated in Figure 4.7 below.
Figure 4.7– Proposed Intergreen periods (seconds) – Option 1
A B C D E F G H I J K L
A - - - - 6 - - - - 5 3
B - 5 - - - 6 - - - 8 3
C - 5 - - - - 6 - - - 3
D - - - 5 - - - 6 - 5 3
E - - - 5 - - - - 6 - 3
F 9 - - - - - - - - - 3
G - 8 - - - - - - - - 3
H - - 9 - - - - - - - 3
I - - - 9 - - - - - - 3
J - - - - 8 - - - - 6 3
K - - - - - - - - - - -
L 2 2 2 2 2 2 2 2 2 2 -
Proposed Option 2
The LinSig model of the proposed option 2 has been prepared to include new phase /
stage intergreens illustrated in Figure 4.8. The intergreen values have been obtained to
TfL specifications using the method prescribed in TAL 01/06 and referenced in the SQA-
0645.
Figure 4.8– Proposed Intergreen periods (seconds) – Option 2
A B C D E F G H I J K L M
A - - - - 6 - - - - 5 3 -
E
B - 6 - - - - - - - 8 3 -
C - 5 - - - - 6 - - - 3 -
D - - - 5 - - - 6 - - 3 -
E - - - 5 - - - - 6 - 3 -
F 9 - - - - - - - - - 3 -
G - - - - - - - - - - - 8
H - - 10 - - - - - - - 3 -
I - - - 9 - - - - - - 3 -
J - - - - 8 - - - - 6 3 -
K - - - - - - - - - - - -
L 2 2 2 2 2 2 - 2 2 2 - -
M - - - - - - 6 - - - - -
4.9 Saturation Flows
As the proposed design of the Grenfell Road / Queen Street / King Street junction alters
the existing geometry, in particular the lane widths and radii, the existing saturation
flows would change and cannot be use for the proposed modelling. Hence, the
saturation flows at Queen Street approaching lanes used in the proposed models have
been calculated using the RR67.
F
5. PROPOSED MODELLING RESULTS
To assess the impact of the proposed schemes on traffic conditions at the modelled
network, the proposed modelling results have been compared with base model results
with the implementation of MOVA traffic control system. The traffic impacts on the
operation of the junctions due to the implementation of the proposed schemes are
assessed through two fundamental parameters, the Degree of Saturation (DoS) and
Mean Maximum Queue (MMQ).
Proposed Option 1 - TRAFFIC FLOW DIVERTED THROUGH THE NETWORK
Table 5.1a) – Comparison of MOVA base and Proposed Modelled Degrees of Saturation (DoS) –
Option 1 (96s AM & 72s PM)
ink Description
Degree of Saturation (%)
AM PM
Base (MOVA)
Option1 Diff Base
(MOVA) Option1 Diff
Grenfell Road / Green Place
Grenfell Place SB Approach- N/S 37% 38% -1% 50% 50% 0%
Grenfell Place SB Approach- O/S 32% 32% -1% 35% 35% 0%
Grenfell Road EB Approach- N/S 71% 67% 4% 70% 70% 0%
Grenfell Road WB Approach- N/S 60% 56% 4% 72% 63% 8%
Grenfell Road WB Approach- O/S 66% 68% -2% 59% 62% -3%
Grenfell Road / Queen Street / King Street / Keys Place
Grenfell Road EB Approach- N/S 34% 33% 1% 70% 59% 11%
Grenfell Road EB Approach- O/S 44% 43% 1% 51% 43% 8%
King Street NB Approach- N/S 65% 70% -4% 81% 89% -8%
King Street NB Approach- O/S 63% 68% -5% 78% 86% -8%
Queen Street SB Approach- N/S 52% 49% 3% 70% 79% -
10%
Queen Street SB Approach- O/S (middle
lane) 20%
60% 14%
85%
Queen Street SB Approach- O/S (RT) 43% 60%
Queen Street WB Approach- N/S 58% 45% 13% 75% 75% 0%
Queen Street WB Approach- O/S 61% 47% 14% 80% 80% 0%
Keys Place SB Approach- N/S 7% 7% 0% 21% 20% 2%
King Street / Braywick Road / Shoppenhangers Road
Braywick Road NB Approach- N/S 85% 87% -2% 78% 93% -
G
15%
Braywick Road NB Approach- O/S 57% 61% -3% 46% 60% -
14%
King Street SB Approach- N/S 45% 42% 4% 66% 66% 0%
King Street SB Approach- O/S (middle
lane) 36% 33% 3% 40% 70%
-
30%
King Street SB Approach- O/S (LT) 35% 40% -4% 74% 90% -
16%
Shoppenhangers Road EB Approach- N/S 81% 85% -4% 65% 69% -4%
Cycle Time 96 72
Table 5.1 b) - Comparison of MOVA base and Proposed Mean Maximum Queue (MMQ) – Option
1 (96s AM & 72s PM)
Link Description
Mean Maximum Queue (PCUs)
AM PM
Base
(MOVA) Option1 Diff
Base
(MOVA) Option1 Diff
Grenfell Road / Green Place
Grenfell Place SB Approach- N/S 6 7 0 7 7 0
Grenfell Place SB Approach- O/S 5 5 0 5 5 0
Grenfell Road EB Approach- N/S 8 7 6 6
Grenfell Road WB Approach- N/S 4 1 3 7 1 6
Grenfell Road WB Approach- O/S 3 1 2 3 1 2
Grenfell Road / Queen Street / King Street / Keys Place
Grenfell Road EB Approach- N/S 1 1 0 11 9 2
Grenfell Road EB Approach- O/S 6 6 0 8 7 1
King Street NB Approach- N/S 6 6 0 12 19 -6
King Street NB Approach- O/S 7 9 -2 11 17 -5
Queen Street SB Approach- N/S 1 1 0 10 11 -1
Queen Street SB Approach- O/S (middle
lane) 1
7
0
10
-10
Queen Street SB Approach- O/S (RT) 2 3 3
Queen Street WB Approach- N/S 5 4 0 8 8 0
H
As can be seen in Table 5.1a), the proposed modelling results suggest that Option1 (with
banned right turn traffic assumed to divert through the network), with the cycle times of 96s
in the AM and 72s in the PM peak hours, would not be feasible for the PM peak period. The
King Street / Braywick Road / Shoppenhangers Road junction is predicted to operate above
the maximum desired capacity (90%) with the highest DoS value of 93% predicted on the
nearside Braywick Road (northbound) during the evening peak.
Table 5.2 a) – Comparison of MOVA base and Proposed Modelled Degrees of Saturation (DoS) –
Option 1 (104s AM & 88s PM)
Link Description
Degree of Saturation (%)
AM PM
Base
(MOVA) Option1 Diff
Base
(MOVA) Option1 Diff
Grenfell Road / Green Place
Grenfell Place SB Approach- N/S 37% 36% 1% 45% 46% -1%
Grenfell Place SB Approach- O/S 32% 32% 0% 34% 34% -1%
Grenfell Road EB Approach- N/S 65% 68% -3% 67% 63% 4%
Grenfell Road WB Approach- N/S 60% 55% 5% 69% 63% 6%
Grenfell Road WB Approach- O/S 66% 66% 0% 57% 61% -4%
Grenfell Road / Queen Street / King Street / Keys Place
Grenfell Road EB Approach- N/S 33% 32% 2% 49% 57% -8%
Grenfell Road EB Approach- O/S 44% 41% 2% 67% 42% 25%
Queen Street WB Approach- O/S 5 4 1 10 10 0
Keys Place SB Approach- N/S 1 1 0 3 2 0
King Street / Braywick Road / Shoppenhangers Road
Braywick Road NB Approach- N/S 20 23 -3 12 21 -9
Braywick Road NB Approach- O/S 11 13 -1 6 9 -3
King Street SB Approach- N/S 9 3 7 10 10 0
King Street SB Approach- O/S (middle
lane) 8 5 3 4 16 -13
King Street SB Approach- O/S (LT) 6 6 0 8 11 -3
Shoppenhangers Road EB Approach- N/S 11 12 -1 6 7 0
Cycle Time 96 72
I
King Street NB Approach- N/S 64% 66% -2% 74% 84% -9%
King Street NB Approach- O/S 62% 66% -3% 73% 82% -9%
Queen Street SB Approach- N/S 51% 53% -3% 67% 76% -
10%
Queen Street SB Approach- O/S (middle
lane) 20%
65%
13%
81%
Queen Street SB Approach- O/S (RT) 42% 57%
Queen Street WB Approach- N/S 55% 48% 6% 66% 69% -3%
Queen Street WB Approach- O/S 58% 51% 6% 73% 75% -3%
Keys Place SB Approach- N/S 7% 7% 0% 21% 19% 2%
King Street / Braywick Road / Shoppenhangers Road
Braywick Road NB Approach- N/S 81% 84% -3% 74% 85% -
11%
Braywick Road NB Approach- O/S 56% 59% -3% 45% 56% -
11%
King Street SB Approach- N/S 35% 49% -
13% 60% 60% 0%
King Street SB Approach- O/S (middle
lane) 28% 39%
-
11% 37% 64%
-
28%
King Street SB Approach- O/S (LT) 36% 40% -4% 64% 86% -
22%
Shoppenhangers Road EB Approach-
N/S 81% 84% -3% 56% 68%
-
11%
Cycle Time 104 88
Table 5.2 b) - Comparison of MOVA base and Proposed Mean Maximum Queue (MMQ) – Option
1 (104s AM & 88s PM)
Link Description
Mean Maximum Queue (PCUs)
AM PM
Base
(MOVA) Option1 Diff
Base
(MOVA) Option1 Diff
Grenfell Road / Green Place
Grenfell Place SB Approach- N/S 7 7 0 8 8 0
Grenfell Place SB Approach- O/S 6 5 0 5 5 0
Grenfell Road EB Approach- N/S 8 8 7 7
J
The results reveal the benefit of considering higher cycle times (104s in the AM and 88s
in the PM) with all the predicted capacities below 90%. Increasing the cycle time (to
88s) in the PM peak hour improves the operating capacities of the nearside Braywick
Road (northbound) and the offside King Street (southbound) with DoS values of 85%
and 86% respectively.
Proposed Option 1 - TRAFFIC FLOW DIVERTED THROUGH BROADWAY
Table 5.3 a) – Comparison of MOVA base and Proposed Modelled Degrees of Saturation (DoS) –
Option 1 (96s AM & 72s PM)
Grenfell Road WB Approach- N/S 5 1 4 8 1 7
Grenfell Road WB Approach- O/S 3 2 1 4 1 3
Grenfell Road / Queen Street / King Street / Keys Place
Grenfell Road EB Approach- N/S 1 1 0 13 10 3
Grenfell Road EB Approach- O/S 6 6 0 9 6 3
King Street NB Approach- N/S 6 6 0 9 13 -5
King Street NB Approach- O/S 10 9 1 14 12 2
Queen Street SB Approach- N/S 1 2 0 12 13 -1
Queen Street SB Approach- O/S (middle
lane) 1
8
0
13
Queen Street SB Approach- O/S (RT) 2 4
Queen Street WB Approach- N/S 5 5 0 9 9 0
Queen Street WB Approach- O/S 5 5 0 11 11 0
Keys Place SB Approach- N/S 1 1 0 3 3 0
King Street / Braywick Road / Shoppenhangers Road
Braywick Road NB Approach- N/S 20 23 -3 14 20 -6
Braywick Road NB Approach- O/S 12 13 -1 7 10 -3
King Street SB Approach- N/S 1 11 -10 12 5 7
King Street SB Approach- O/S (middle
lane) 6 6 -1 3 17 -14
King Street SB Approach- O/S (LT) 6 6 0 9 11 -2
Shoppenhangers Road EB Approach- N/S 12 12 -1 7 8 -1
Cycle Time 104 88
K
Link Description
Degree of Saturation (%)
AM PM
Base
(MOVA) Option1 Diff
Base
(MOVA) Option1 Diff
Grenfell Road / Green Place
Grenfell Place SB Approach- N/S 37% 38% -1% 50% 55% -5%
Grenfell Place SB Approach- O/S 32% 32% -1% 35% 38% -3%
Grenfell Road EB Approach- N/S 71% 67% 4% 70% 58% 12%
Grenfell Road WB Approach- N/S 60% 51% 9% 72% 51% 21%
Grenfell Road WB Approach- O/S 66% 61% 5% 59% 49% 10%
Grenfell Road / Queen Street / King Street / Keys Place
Grenfell Road EB Approach- N/S 34% 31% 2% 70% 57% 13%
Grenfell Road EB Approach- O/S 44% 41% 3% 51% 42% 9%
King Street NB Approach- N/S 65% 60% 5% 81% 64% 16%
King Street NB Approach- O/S 63% 59% 5% 78% 63% 15%
Queen Street SB Approach- N/S 52% 49% 3% 70% 37% 33%
Queen Street SB Approach- O/S (middle
lane) 20%
31%
14%
65%
Queen Street SB Approach- O/S (RT) 43% 60%
Queen Street WB Approach- N/S 58% 54% 4% 75% 47% 28%
Queen Street WB Approach- O/S 61% 14% 47% 80% 50% 31%
Keys Place SB Approach- N/S 7% 4% 3% 21% 11% 10%
King Street / Braywick Road / Shoppenhangers Road
Braywick Road NB Approach- N/S 85% 76% 9% 78% 78% 0%
Braywick Road NB Approach- O/S 57% 52% 5% 46% 46% 0%
King Street SB Approach- N/S 45% 36% 10% 66% 66% 0%
King Street SB Approach- O/S (middle
lane) 36% 29% 8% 40% 40% 0%
King Street SB Approach- O/S (LT) 35% 43% -8% 74% 74% 0%
Shoppenhangers Road EB Approach- N/S 81% 78% 3% 65% 65% 0%
Cycle Time 96 72
L
Table 5.3 b) - Comparison of MOVA base and Proposed Mean Maximum Queue (MMQ) – Option
1 (96s AM & 72s PM)
Link Description
Mean Maximum Queue (PCUs)
AM PM
Base
(MOVA) Option1 Diff
Base
(MOVA) Option1 Diff
Grenfell Road / Green Place
Grenfell Place SB Approach- N/S 6 7 0 7 8 -1
Grenfell Place SB Approach- O/S 5 5 0 5 5 -1
Grenfell Road EB Approach- N/S 8 7 6 6
Grenfell Road WB Approach- N/S 4 1 3 7 1 6
Grenfell Road WB Approach- O/S 3 2 2 3 1 3
Grenfell Road / Queen Street / King Street / Keys Place
Grenfell Road EB Approach- N/S 1 1 0 11 9 2
Grenfell Road EB Approach- O/S 6 5 0 8 5 3
King Street NB Approach- N/S 6 5 0 12 5 7
King Street NB Approach- O/S 7 7 0 11 5 6
Queen Street SB Approach- N/S 1 1 1 10 0 10
Queen Street SB Approach- O/S (middle
lane) 1
3
0
8
-8
Queen Street SB Approach- O/S (RT) 2 3 3
Queen Street WB Approach- N/S 5 5 0 8 4 4
Queen Street WB Approach- O/S 5 1 4 10 5 5
Keys Place SB Approach- N/S 1 0 0 3 1 1
King Street / Braywick Road / Shoppenhangers Road
Braywick Road NB Approach- N/S 20 17 3 12 12 0
Braywick Road NB Approach- O/S 11 10 1 6 6 0
King Street SB Approach- N/S 9 1 8 10 6 4
King Street SB Approach- O/S (middle
lane) 8 3 5 4 5 -1
King Street SB Approach- O/S (LT) 6 6 0 8 8 0
Shoppenhangers Road EB Approach- N/S 11 11 1 6 6 0
M
Table 5.3 a) above suggest that Option 1 (with banned right turn traffic assumed to
divert through Broadway) with cycle time of 96s and 72s in the AM and PM peak
periods respectively, would run more efficiently during the assessed peak hours with all
approaches well below 90% of the modelled network.
As expected, the queues on the approaching lanes are predicted to reduce in the
proposed modelling results. The decreases in MMQs are shown to be consistent with
their respective DoS on the approaching lanes.
Proposed Option 2
Table 5.4 a) – Comparison of MOVA base and Proposed Modelled Degrees of Saturation (DoS) –
Option 2 (96s AM & 72s PM)
Link Description
Degree of Saturation (%)
AM PM
Base
(MOVA) Option1 Diff
Base
(MOVA) Option1 Diff
Grenfell Road / Green Place
Grenfell Place SB Approach- N/S 37% 38% -1% 50% 52% -2%
Grenfell Place SB Approach- O/S 32% 33% -1% 35% 36% -1%
Grenfell Road EB Approach- N/S 71% 63% 8% 70% 65% 5%
Grenfell Road WB Approach- N/S 60% 60% 0% 72% 70% 2%
Grenfell Road WB Approach- O/S 66% 66% 0% 59% 58% 1%
Grenfell Road / Queen Street / King Street / Keys Place
Grenfell Road EB Approach- N/S 34% 35% -1% 70% 66% 4%
Grenfell Road EB Approach- O/S 44% 45% -1% 51% 49% 2%
King Street NB Approach- N/S 65% 73% -8% 81% 94% -
13%
King Street NB Approach- O/S 63% 70% -7% 78% 90% -
13%
Queen Street SB Approach- N/S 52% 78% -
26% 70% 96%
-
26%
Queen Street SB Approach- O/S (middle 20% 43% 14% 59%
Cycle Time 96 72
N
lane)
Queen Street SB Approach- O/S (RT) 43% 60%
Queen Street WB Approach- N/S 58% 34% 24% 75% 52% 23%
Queen Street WB Approach- O/S 61% 36% 25% 80% 57% 23%
Keys Place SB Approach- N/S 7% 8% -1% 21% 24% -3%
King Street / Braywick Road / Shoppenhangers Road
Braywick Road NB Approach- N/S 85% 81% 4% 78% 78% 0%
Braywick Road NB Approach- O/S 57% 55% 2% 46% 46% 0%
King Street SB Approach- N/S 45% 36% 9% 66% 64% 2%
King Street SB Approach- O/S (middle
lane) 36% 29% 8% 40% 39% 1%
King Street SB Approach- O/S (LT) 35% 37% -1% 74% 70% 4%
Shoppenhangers Road EB Approach-
N/S 81% 78% 3% 65% 55% 10%
Cycle Time 96 72
Table 5.4 b) - Comparison of MOVA base and Proposed Mean Maximum Queue (MMQ) – Option
2 (96s AM & 72s PM)
Link Description
Mean Maximum Queue (PCUs)
AM PM
Base
(MOVA) Option1 Diff
Base
(MOVA) Option1 Diff
Grenfell Road / Green Place
Grenfell Place SB Approach- N/S 6 7 0 7 7 0
Grenfell Place SB Approach- O/S 5 5 0 5 5 0
Grenfell Road EB Approach- N/S 8 7 6 6
Grenfell Road WB Approach- N/S 4 4 0 7 7 0
Grenfell Road WB Approach- O/S 3 3 0 3 3 0
Grenfell Road / Queen Street / King Street / Keys Place
Grenfell Road EB Approach- N/S 1 1 0 11 9 2
Grenfell Road EB Approach- O/S 6 6 0 8 8 0
King Street NB Approach- N/S 6 13 -7 12 17 -5
King Street NB Approach- O/S 7 19 11 16
O
The results from Table 5.4a) indicate a significant increase in DoS on the northbound
King Street and the nearside Queen Street (southbound) approaching lanes during the
evening peak following the implementation of the proposed scheme (Option 2). The
highest DoS is predicted on the southbound Queen Street approach (96%) during the
PM peak hour.
Proposed Option 2
Table 5.5 a) – Comparison of MOVA base and Proposed Modelled Degrees of Saturation (DoS) –
Option 2 (104s AM & 120s PM)
Queen Street SB Approach- N/S 1 9 10 19
Queen Street SB Approach- O/S (middle
lane) 1
5
0
8
-8
Queen Street SB Approach- O/S (RT) 2 3 3
Queen Street WB Approach- N/S 5 4 1 8 6 2
Queen Street WB Approach- O/S 5 4 1 10 7 2
Keys Place SB Approach- N/S 1 1 0 3 3 0
King Street / Braywick Road / Shoppenhangers Road
Braywick Road NB Approach- N/S 20 19 1 12 12 0
Braywick Road NB Approach- O/S 11 11 1 6 6 0
King Street SB Approach- N/S 9 8 2 10 9 2
King Street SB Approach- O/S (middle
lane) 8 2 6 4 4 0
King Street SB Approach- O/S (LT) 6 6 0 8 8 0
Shoppenhangers Road EB Approach- N/S 11 11 1 6 6 1
Cycle Time 96 72
P
Link Description
Degree of Saturation (%)
AM PM
Base
(MOVA) Option1 Diff
Base
(MOVA) Option1 Diff
Grenfell Road / Green Place
Grenfell Place SB Approach- N/S 37% 37% 0% 45% 40% 6%
Grenfell Place SB Approach- O/S 32% 32% 0% 34% 32% 2%
Grenfell Road EB Approach- N/S 65% 65% 0% 67% 65% 1%
Grenfell Road WB Approach- N/S 60% 59% 2% 69% 64% 5%
Grenfell Road WB Approach- O/S 66% 64% 2% 57% 53% 4%
Grenfell Road / Queen Street / King Street / Keys Place
Grenfell Road EB Approach- N/S 33% 34% -1% 49% 60% -
12%
Grenfell Road EB Approach- O/S 44% 45% -1% 67% 45% 22%
King Street NB Approach- N/S 64% 71% -7% 74% 72% 2%
King Street NB Approach- O/S 62% 68% -6% 73% 71% 2%
Queen Street SB Approach- N/S 51% 76% -
26% 67% 89%
-
22%
Queen Street SB Approach- O/S (middle
lane) 20%
42%
13%
55%
Queen Street SB Approach- O/S (RT) 42% 57%
Queen Street WB Approach- N/S 55% 34% 21% 66% 49% 17%
Queen Street WB Approach- O/S 58% 36% 22% 73% 56% 17%
Keys Place SB Approach- N/S 7% 8% -1% 21% 21% 0%
King Street / Braywick Road / Shoppenhangers Road
Braywick Road NB Approach- N/S 81% 78% 3% 74% 68% 6%
Braywick Road NB Approach- O/S 56% 54% 2% 45% 42% 3%
King Street SB Approach- N/S 35% 35% 0% 60% 54% 6%
King Street SB Approach- O/S (middle
lane) 28% 28% 0% 37% 34% 3%
King Street SB Approach- O/S (LT) 36% 37% -1% 64% 57% 7%
Shoppenhangers Road EB Approach-
N/S 81% 78% 3% 56% 47% 9%
Cycle Time 104 120
Q
Table 5.5 b) - Comparison of MOVA base and Proposed Mean Maximum Queue (MMQ) – Option
2 (104s AM & 120s PM)
Link Description
Mean Maximum Queue (PCUs)
AM PM
Base
(MOVA) Option1 Diff
Base
(MOVA) Option1 Diff
Grenfell Road / Green Place
Grenfell Place SB Approach- N/S 7 7 0 8 9 -1
Grenfell Place SB Approach- O/S 6 6 0 5 6 -1
Grenfell Road EB Approach- N/S 8 8 7 9
Grenfell Road WB Approach- N/S 5 4 1 8 10 -2
Grenfell Road WB Approach- O/S 3 3 1 4 5 -1
Grenfell Road / Queen Street / King Street / Keys Place
Grenfell Road EB Approach- N/S 1 1 0 13 15 -3
Grenfell Road EB Approach- O/S 6 6 0 9 12 -3
King Street NB Approach- N/S 6 14 -8 9 18 -10
King Street NB Approach- O/S 10 20 -11 14 17 -3
Queen Street SB Approach- N/S 1 9 -8 12 23 -11
Queen Street SB Approach- O/S (middle
lane) 1
5
0
12
Queen Street SB Approach- O/S (RT) 2 4
Queen Street WB Approach- N/S 5 4 1 9 10 -1
Queen Street WB Approach- O/S 5 4 1 11 12 -1
Keys Place SB Approach- N/S 1 1 0 3 4 -1
King Street / Braywick Road / Shoppenhangers Road
Braywick Road NB Approach- N/S 20 19 1 14 17 -3
Braywick Road NB Approach- O/S 12 11 1 7 9 -2
R
With increased cycle times (104s in the AM and 120s in the PM), the model results
suggest that the junction would operate better with the predicted capacities on all
approaching lanes below 90% DoS during the AM and PM peak hours.
King Street SB Approach- N/S 1 8 -7 12 2 10
King Street SB Approach- O/S (middle
lane) 6 2 4 3 0 3
King Street SB Approach- O/S (LT) 6 6 0 9 11 -2
Shoppenhangers Road EB Approach- N/S 12 11 0 7 8 -2
Cycle Time 104 120
S
6. CONCLUSION
6.1.1 Base LinSig models have been developed and validated to simulate
existing traffic conditions for weekday morning peaks (AM) and evening
(PM) peak hours.
6.1.2 Base modelling indicates that the network currently operates within
capacity during peak hours, except for the northbound A308 movement
past the station, and the Shoppenhangers Road traffic signal approach.
Both movements exceed 90% capacity during peak hours.
6.1.3 Two at-grade crossing options at the Grenfell Road / Queen Street / King
Street junction have been developed for assessment.
6.1.4 Option1 involves removal of right turning traffic from Queen Street to A308 .
Right turners may either continue to travel to A308 south and then pass
around Stafferton Way roundabout to continue north, or potentially be
diverted from Nicholson’s car park via a two-way Broadway, thereby
avoiding the junction altogether. The latter option may not be taken
forward, therefore both scenarios have been tested.
6.1.5 Option 2 involves amendments to Queen Street arm (southbound) with a
two-stage crossing over A308. Right turning movements would be retained
in this scenario.
6.1.6 MOVA traffic control is being implemented at these signals. therefore, a
‘MOVA Current Scenario’ has been developed from the calibrated and
validate base model for option assessment purposes.
6.1.7 Option1, with banned right turn traffic assumed to divert via Stafferton
Way, would require cycle times to be amended to 104s in the AM peak
and 88s in the PM peak hours. With these amended cycle times, the
degree of saturation predicted on all approach lanes would be below
90%, leading to an improvement in conditions.
6.1.8 Option 1 with right turn traffic diverted away from the junction via
Broadway would be able to operate on cycle times of 96s and 72s in the
AM and PM peak periods respectively. This option is predictably shown to
operate more efficiently during the peak hours as it removes traffic from
the network.
T
6.1.9 Option 2 modelling has indicated that the layout proposed would cause
significant queuing on A308 approach lanes, and on Queen Street. The
signal operation is not optimum and would not be practical in this
location.
6.1.10 Option 1 with Broadway two-way would provide an optimum solution.
However, if this change did not occur and current right turners were
diverted through the network via Stafferton Way roundabout, the network
would still see operational improvements, albeit with a need to increase
cycle times to better reflect peak flow demands.
6.1.11 It is noted that the Stafferton Way diversion assumes that all current right
turners would divert via Stafferton Way, but the numbers would be
significantly less as there are alternative routes that could be used by
traffic leaving the town centre area. The approach taken is therefore
robust and “worst case”.
6.1.12 It is recommended to progress with Option 1 with banned right turn traffic
from Queen Street.
U
Document Control
Project: Maidenhead Station Business Case Job No: 1000004054
Subject: LinSig Modelling Issue: 01
Prepared by: J. Cecchinelli Date: 25/09/2017
Approved by: Paul Chandler Date: 02/10/2017
V
Quality
It is the policy of Project Centre to supply Services that meet or exceed our clients’
expectations of Quality and Service. To this end, the Company's Quality
Management System (QMS) has been structured to encompass all aspects of the
Company's activities including such areas as Sales, Design and Client Service.
By adopting our QMS on all aspects of the Company, Project Centre aims to achieve
the following objectives:
Ensure a clear understanding of customer requirements;
Ensure projects are completed to programme and within budget;
Improve productivity by having consistent procedures;
Increase flexibility of staff and systems through the adoption of a common
approach to staff appraisal and training;
Continually improve the standard of service we provide internally and
externally;
Achieve continuous and appropriate improvement in all aspects of the
company;
Our Quality Management Manual is supported by detailed operational
documentation. These relate to codes of practice, technical specifications, work
instructions, Key Performance Indicators, and other relevant documentation to form
a working set of documents governing the required work practices throughout the
Company.
All employees are trained to understand and discharge their individual responsibilities
to ensure the effective operation of the Quality Management System.
W
Appendix A – BASE LINSIG MODELS AND RESULTS
X
Appendix B – PROPOSED LINSIG MODEL AND RESULTS
Y
Appendix C – GENERAL ARRANGEMENTS (GA)
Z