marsden park landfill proposed gas collection system and
TRANSCRIPT
The business of sustainability
www.erm.com
Blacktown Waste Services
June 2018
0430664_Final
Marsden Park Landfill Proposed Gas Collection System and Flare Unit
Statement of Environmental Effects
This disclaimer, together with any limitations specified in the report, apply to use of this report. This report was prepared in accordance with the contracted scope of services for the specific purpose stated and subject to the applicable cost, time and other constraints. In preparing this report, ERM relied on: (a) client/third party information which was not verified by ERM except to the extent required by the scope of services, and ERM does not accept responsibility for omissions or inaccuracies in the client/third party information; and (b) information taken at or under the particular times and conditions specified, and ERM does not accept responsibility for any subsequent changes. This report has been prepared solely for use by, and is confidential to, the client and ERM accepts no responsibility for its use by other persons. This report is subject to copyright protection and the copyright owner reserves its rights. This report does not constitute legal advice.
Prepared by: Matthew Errington
Position: Project Manager
Signed:
Date: 8 June 2018
Approved by: Paul Douglass
Position: Partner
Signed:
Date: 8 June 2018
Marsden Park Landfill
Proposed Gas Collection System and Flare
Unit
Statement of Environmental Effects
Blacktown Waste Services
June 2018
0340664 Final
www.erm.com
Document Control:
0430664 Marsden Park Landfill
Proposed Gas Collection System and Flare Unit
Version Revision Author
ERM Approval to Issue
Name Date
Draft 01 Matthew Errington Paul Douglass 28/11/17
Final 02 Matthew Errington Paul Douglass 12/06/18
CONTENTS
ABBREVIATIONS
EXECUTIVE SUMMARY
1 INTRODUCTION
1.1 OVERVIEW 1
1.2 BACKGROUND AND CONTEXT 1
1.3 LOCALITY AND SURROUNDING LAND USE 4
1.4 PROJECT AREA AND LAND OWNERSHIP 5
1.5 DA STATUS AND CONSULTATION FOR THE SOEE 6
2 PROJECT DESCRIPTION
2.1 SUMMARY OF PROPOSED WORKS 7
2.1.1 DRILLING GAS COLLECTION WELLS 8
2.1.2 FLOW LINES 8
2.1.3 REMEDIAL WORKS (TO SEAL LANDFILL CAP) 8
2.1.4 MANIFOLDS 10
2.1.5 CONDENSATE MANAGEMENT 10
2.1.6 INSTALLATION OF FLARE UNIT 10
2.2 WORKS PROGRAM 14
2.3 CONSTRUCTION WORKFORCE 14
2.4 CONSTRUCTION HOURS 14
2.5 SITE ACCESS AND EGRESS 14
2.6 CONSIDERATION OF ALTERNATIVES 14
2.6.1 PREFERRED OPTION 15
3 LEGISLATIVE AND POLICY CONSIDERATIONS
3.1 COMMONWEALTH LEGISLATION 16
3.1.1 ENVIRONMENTAL PROTECTION AND BIODIVERSITY
CONSERVATION ACT 1999 16
3.2 NSW LEGISLATION 16
3.2.1 ENVIRONMENTAL PLANNING AND ASSESSMENT ACT 1979 16
3.2.2 PROTECTION OF THE ENVIRONMENT OPERATION (CLEAN AIR)
REGULATION 2010 18
3.3 STATE ENVIRONMENTAL PLANNING POLICIES 20
3.3.1 STATE ENVIRONMENTAL PLANNING POLICY (SYDNEY REGION
GROWTH CENTRES) 2006 -MARSDEN PARK INDUSTRIAL PRECINCT
PLAN 2010 20
3.3.2 STATE ENVIRONMENTAL PLANNING POLICY NO 33— HAZARDOUS
AND OFFENSIVE DEVELOPMENT 20
3.4 LOCAL STATUTORY CONTEXT 21
3.4.1 BLACKTOWN LOCAL ENVIRONMENTAL PLAN 2015 21
3.5 DEVELOPMENT CONTROL PLANS 21
3.5.1 BLACKTOWN CITY COUNCIL GROWTH CENTRE PRECINCTS
DEVELOPMENT CONTROL PLAN 2014 (SCHEDULE 3 – MARSDEN
PARK INDUSTRIAL PRECINCT) 21
CONTENTS
4 ENVIRONMENTAL IMPACT ASSESSMENT AND
MANAGEMENT
4.1 FLORA AND FAUNA 22
4.1.1 EXISTING ENVIRONMENT 22
4.1.2 ASSESSMENT OF IMPACT 24
4.1.3 ENVIRONMENTAL MITIGATION 24
4.1.4 CONCLUSION 24
4.2 ABORIGINAL HERITAGE 24
4.2.1 EXISTING ENVIRONMENT 24
4.2.2 ASSESSMENT OF IMPACT 25
4.2.3 ENVIRONMENTAL MITIGATION 25
4.2.4 CONCLUSION 25
4.3 NON-ABORIGINAL HERITAGE 25
4.3.1 EXISTING ENVIRONMENT 25
4.3.2 ASSESSMENT OF IMPACT 25
4.3.3 ENVIRONMENTAL MITIGATION 26
4.3.4 CONCLUSION 26
4.4 GEOLOGY AND SOIL 26
4.4.1 EXISTING ENVIRONMENT 26
4.4.2 ASSESSMENT OF IMPACT 26
4.4.3 ENVIRONMENTAL MITIGATION 26
4.4.4 CONCLUSION 27
4.5 WATER QUALITY AND HYDROLOGY 27
4.5.1 EXISTING ENVIRONMENT 27
4.5.2 ASSESSMENT OF IMPACT 28
4.5.3 ENVIRONMENTAL MITIGATION MEASURES 28
4.5.4 CONCLUSION 29
4.6 AIR QUALITY AND GHG 29
4.6.1 EXISTING ENVIRONMENT 29
4.6.2 ASSESSMENT OF IMPACT 29
4.6.3 ENVIRONMENTAL MITIGATION 30
4.6.4 CONCLUSION 30
4.7 NOISE AND VIBRATION 31
4.7.1 POLICY SETTING 31
4.7.2 EXISTING ENVIRONMENT 31
4.7.3 NOISE MANAGEMENT LEVELS AND CRITERIA 33
4.7.4 ASSESSMENT OF IMPACT 36
4.7.5 ENVIRONMENTAL MITIGATION 38
4.7.6 CONCLUSION 39
4.8 TRAFFIC 39
4.8.1 EXISTING ENVIRONMENT 39
4.8.2 ASSESSMENT OF IMPACT 40
4.8.3 ENVIRONMENTAL MITIGATION 40
4.8.4 CONCLUSION 40
4.9 WASTE AND MATERIALS MANAGEMENT 40
4.9.1 BACKGROUND AND EXISTING ENVIRONMENT 40
4.9.2 ASSESSMENT OF IMPACT 41
CONTENTS
4.9.3 ENVIRONMENTAL MITIGATION MEASURES 41
4.9.4 CONCLUSION 41
4.10 VISUAL AMENITY 41
4.10.1 EXISTING ENVIRONMENT 41
4.10.2 ASSESSMENT OF IMPACT 43
4.10.3 ENVIRONMENTAL MITIGATION 45
4.10.4 CONCLUSION 46
4.11 HAZARD AND RISK 46
4.11.1 RISK MITIGATION 48
4.11.2 CONCLUSION 53
4.12 CUMULATIVE IMPACTS 54
5 SECTION 79C CONSIDERATIONS
6 CONCLUSION
7 REFERENCES
LIST OF PHOTOGRAPHS
PHOTOGRAPH 1.1 NEARBY COMMERCIAL FACILITIES SURROUNDING THE
MARSDEN PARK LANDFILL SITE.
5
PHOTOGRAPH 1.2 ENCLOSED GROUND FLARE UNIT FORMING PART OF THE
PROPOSED GCS.
10
PHOTOGRAPH 4.1 MARSDEN PARK LANDFILL SITE SHOWING INDICATIVE
GROUND FLARE UNIT LOCATION AND SITE OFFICE (RIGHT OF
PHOTOGRAPH).
41
PHOTOGRAPH 4.2 NEARBY SENSITIVE RECEIVERS NORTHEAST OF THE MARSDEN
PARK LANDFILL SITE.
42
PHOTOGRAPH 4.3 NEARBY SENSITIVE RECEIVERS SOUTHWEST OF THE MARSDEN
PARK LANDFILL SITE. 42
PHOTOGRAPH 4.4 SITE OFFICE AND EXISTING VEGETATION (TO THE RIGHT). 43
PHOTOGRAPH 4.5 VIEW TOWARDS LANDFILL SITE FROM THE CORNER OF
HAWTHORNE AVENUE AND DARLING STREET.
44
PHOTOGRAPH 4.6 NEARBY SENSITIVE RECEIVERS SOUTHWEST OF THE MARSDEN
PARK LANDFILL SITE (BEHIND VEGETATION BUFFER WITHIN
RED RECTANGLE).
45
CONTENTS
LIST OF FIGURES
FIGURE 1.1 SITE LOCALITY 3
FIGURE 1.2 LAND ZONING AND CADASTRAL BOUNDARIES (SOURCE: SEPP
2006) 4
LIST OF TABLES
TABLE 3.1 RELATIONSHIP BETWEEN PROPOSED WORKS AND MATTERS OF
NATIONAL ENVIRONMENTAL SIGNIFICANCE 16
TABLE 3.2 POLLUTANT DISCHARGE LIMITS (POEO REGULATION) 20
TABLE 4.1 THREATENED SPECIES (AND/OR THREATENED SPECIES HABITAT)
WITH POTENTIAL TO OCCUR WITHIN THE PROJECT AREA 23
TABLE 4.2 NSW OFFICE OF WATER REGISTERED BORES WITHIN PROJECT
VICINITY 28
TABLE 4.3 POLLUTANT DISCHARGE LIMITS 29
TABLE 4.4 RATING BACKGROUND NOISE LEVELS (RBL) 33
TABLE 4.5 CONSTRUCTION NOISE MANAGEMENT LEVELS (NML) - (LAEQ, 15
MINUTE) 34
TABLE 4.6 OPERATIONAL - PROJECT INTRUSIVENESS NOISE LEVEL - (LAEQ,
15 MINUTE) 34
TABLE 4.7 ROAD TRAFFIC NOISE CRITERIA 35
TABLE 4.8 SUMMARY OF PROJECT HAZARDS AND RISKS 47
TABLE 4.9 SUMMARY OF COMMISSIONING CHECKS 49
TABLE 5.1 SECTION 79C CONSIDERATIONS 55
ANNEX A FLARE EMISSION TESTING REPORT
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
I
ABBREVIATIONS
Abbreviation Description
AHIP Aboriginal Heritage Impact Permit
AHIMS Aboriginal Heritage Information Management System
BC Act Biodiversity Conservation Act 2016
BCC Blacktown City Council
Bgl Below ground level
CIV Capital investment value
DA Development Application
DCP Development Control Plan
DP&E NSW Department of Planning & Environment
DECC NSW Department of Environment and Climate Change
(now NSW Office of Environment and Heritage)
EEC Endangered Ecological Community
EPA NSW Environment Protection Authority
EP&A Act Environmental Planning and Assessment Act 1979
ERM Environmental Resources Management Australia Pty Ltd
FM Act Fisheries Management Act 1994
GCS Gas Collection System
HT High Temperature
ICNG NSW Interim Construction Noise Guideline
INP NSW Industrial Noise Policy
JHR John Holland Group Pty Ltd
ISEPP State Environmental Planning Policy (Infrastructure) 2007
JRPP Joint Regional Planning Panel
LEMP Landfill Environmental Management Plan
LEP Local Environmental Plan
LFG Landfill Gas
LGA Local government area
MPIP Marsden Park Industrial Precinct
NES National Environmental Significance
NML Noise Management Level
NPI Noise Policy for Industry
NP&W Act National Parks and Wildlife Act 1974
NPWS NSW National Parks and Wildlife Service
NSW New South Wales
NV Act Native Vegetation Act 2003
OEH NSW Office of Environment and Heritage
PA Project Area
RBL Rating Background Level
RMS Roads and Maritime Services
RNP NSW Road Noise Policy
SEPP State Environmental Planning Policy
SIS Species Impact Statement
SoEE Statement of Environmental Effects
SWLs Standard water levels
TEC Threatened Ecological Community
TSC Act Threatened Species Conservation Act 1995
WM Act Water Management Act 2000
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
II
EXECUTIVE SUMMARY
Environmental Resources Management Australia Pty Ltd (ERM) was engaged by
Blacktown Waste Services Pty Ltd (BWS) to prepare a Statement of Environmental
Effects (SoEE) to support a Development Application (DA) for the installation and
operation of an active gas collection system and enclosed ground flare unit.
Development consent for the proposed works is being sought from Blacktown Council
under Part 4 of the Environmental Planning and Assessment Act 1979 (EP&A Act).
This SoEE has been developed to describe the proposed gas collection system
installation and operational activities, assesses the associated potential environmental
impacts and recommends management and mitigation measures.
The SoEE provides a review all relevant legislation and policy and finds that the
primary issues to consider in determining the DA are potential noise and air quality
impacts to nearby sensitive receptors.
The main noise source is associated with the operation of the flare unit which is not
anticipated to generate high noise levels. In order to attenuate anticipated noise
emissions, the flare unit will be fitted with an acoustic enclosure and strategically
located behind existing site infrastructure and vegetation to obscure the direct line of
sight towards potentially affected receivers. Regular maintenance, testing and
monitoring will be undertaken to ensure regulatory compliance. The Project is not
anticipated to have adverse noise impacts on nearby sensitive receptors.
With regards to potential air quality impacts, the flare unit will utilise the latest
technology to meet present and near future emissions standards. Pollutant emission
limits required by the Protection of the Environment Operations (Clean Air
Regulation) 2010 will not be exceeded during operation of the flare unit. Emission
compliance testing and monitoring will be undertaken by a NATA accredited
Contractor. The reduction in GHG emissions (in particular, methane) as a result of
the Project will have a beneficial environmental outcome and positive impact. The
Project will also reduce the potential for odorous landfill gases to dissipate to
surrounding receivers.
It is in the public interest to install and operate the GCS and flare unit, as it will assist
in the:
Reduction of GHG emissions reducing the effects of global warming
Reduction of the potential for dispersion of odorous and potentially harmful
landfill gases to nearby sensitive receivers; and
Achievement of the final land use goal of ‘low density industrial use’, which will
help stimulate economic growth within the local community by providing jobs to
community members.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
III
The SoEE has given consideration to all relevant legislation and policies, and has
conducted an assessment of potential environmental impacts. It concludes that the
Project and its associated potential environmental impacts are unlikely to have a
significant negative impact on the environment and all identified minor risks and
impacts can be effectively managed through the implementation of mitigation
measures during the proposed works and during the long-term operation of the
project.
Additionally, the reduction in GHG emissions as a result of the operation of Project
means the overall environmental impact is considered positive, and such works are
considered viable for the Emissions Reduction Fund (subject to approval by the Clean
Energy Regulator). Other positive benefits include the significantly reduced risk of
sub-surface migration of landfill gas and potential for airborne odour at surrounding
receivers.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
1
1 INTRODUCTION
1.1 OVERVIEW
Environmental Resources Management Australia Pty Ltd (ERM) was engaged
by Blacktown Waste Services (BWS) to prepare a Statement of Environmental
Effects (SoEE) to support a Development Application (DA) for the proposed
construction and operation of an active landfill Gas Collection System (GCS)
and enclosed high temperature ground flare unit at Marsden Park Landfill,
Blacktown, NSW (hereinafter referred to as the Project).
1.2 BACKGROUND AND CONTEXT
The Marsden Park Landfill is located on Richmond Road, Marsden Park,
NSW, approximately 9 km northwest of Blacktown City Centre, and is wholly
contained within the Blacktown City Council (BCC) local government area
(LGA). The location of the Marsden Park Landfill is shown in Figure 1.1.
The Marsden Park Landfill site is located in a predominantly industrial/
commercial area, with surroundings land uses including vacant lots,
warehouses, distribution centres and retail facilities. Marsden Park Industrial
Precinct (MPIP) surrounds the Project site and the IKEA Distribution Centre is
adjacent to the western site boundary. Residential areas are located to the
south and north-east.
Blacktown Waste Services (BWS) propose to construct and operate an active
gas extraction system and high temperature fully enclosed ground flare to
assist in the management of landfill gases associated with the operation of the
landfill site. The Project involves the installation of a series of vertical pipes
(collection wells) in the landfill waste mass. Piping will be connected to the
wells and reticulated by a blower fan installed on the flare unit. A vacuum
will be created and landfill gas containing methane is sent to a combustion
flare. The flare burns the methane at very high destruction rates to generate
carbon dioxide.
The flare unit will utilise the latest technology to meet present and near future
emissions standards. The resulting reduction of global warming potential
means the Project is eligible under the Emissions Reduction Fund (ERF),
enabling the offsetting of fossil fuel. Further information on the specifications
and design of the GCS and flare unit is provided in Section 2.
BWS has operated the Marsden Park Landfill site as a solid waste class 2
landfill since 2000, in accordance with Environmental Protection Licence (EPL)
11497. A Landfill Environmental Management Plan (LEMP) has been
developed and recently updated in 2015 (by MRA Consulting) for the landfill
component of operations. The updates to the LEMP addressed changes to site
boundaries and locations of environmental monitoring points.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
2
A similar GCS and enclosed ground flare unit was recently approved at the
Horsley Park Landfill by the NSW Environment Protection Authority (EPA).
It is expected that, similar to the system at Horsley Park Landfill, the Project’s
potential adverse environmental impacts will be negligible. The reduction in
greenhouse gas (GHG) emissions (in particular, methane) as a result of the
Project will have a beneficial environmental outcome and positive impact.
An assessment of potential environmental impacts is provided in Section 4 of
this report.
!(
24/11/20170430664b_SOEE_G001_R5.mxd
A4
This figure may be based on third party data or data which has notbeen verified by ERM and it may not be to scale. Unless expresslyagreed otherwise, this figure is intended as a guide only and ERM doesnot warrant its accuracy.
Client:Drawn By:
Drawing No:Date: Drawing Size:
Reviewed By:
Marsden Park Landfill Statement of EnvironmentalEffects
Blacktown Waste Services (BWS)JLT TBCoordinate System: GDA 1994 MGA Zone 56
Site Locality F.1
0 100 200m [N
!(
LegendCadastreProposed gas collection system
!( Indicative flare unit location
Project Site
SITE OFFICE
Source:Imagery - Nearmap (image date 7/09/2017)Cadastre - NSW Department of Finance,Services & Innovation 2017
IKEA DISTRIBUTION CENTRE
Ric
hm
ond R
oad
Hawthorne Avenue
Fulton Road
So
uth
Str
ee
t
South Street
Darling Street
Harris
Avenue
Hollinsworth Road
Darling Stre
et
Harris
Avenue
Darlin
g S
treet
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
4
1.3 LOCALITY AND SURROUNDING LAND USE
The Marsden Park Landfill site is located at 920 Richmond Road, Marsden
Park (Lot 102 DP 1188147 and Lot 313 DP 1213756).
Under the State Environmental Planning Policy (Sydney Region Growth
Centres) 2006 (SEPP 2006), the following land use zoning applies to the site –
‘IN1’ General Industrial (refer to Figure 1.2):
Figure 1.2 Land Zoning and Cadastral Boundaries (Source: SEPP 2006)
Site Surroundings
The Project site is located within the MPIP, which comprises approximately
551 hectares of land, under various ownerships. The MPIP is bounded by
South Street to the north and west, the easement for the proposed Castlereagh
Freeway to the south, and Bells Creek to the east. The core development area
of the MPIP is roughly rectangular and is approximately 2.5 km from east to
west and approximately 2 km from north to south.
The MPIP currently contains the landfill itself, a number of commercial and
industrial properties including Bunnings, Home Consortium, McDonalds,
IKEA, some commercial/industrial uses located on Richmond Road, and the
Town and Country Estate, located approximately 890 m south west of the site.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
5
Photograph 1.1 Nearby commercial facilities to the south-east of Marsden Park Landfill
site.
Potentially Sensitive Receptors
Potentially sensitive receptors include residential premises, schools, hospitals,
places of worship, parks and wilderness areas. The nearest residential areas to
the Marsden Park Landfill are located on Richmond Road and South Street,
which form the eastern and northern boundaries of the MPIP, and consist of a
mixture of low and medium-density residential zoning (refer to Section 4.7.2
for further details).
The Ahmadiyya Muslim Association Mosque is located near the southern
edge of the MPIP and is considered a sensitive receptor, however it is not
expected to be impacted by the Project.
1.4 PROJECT AREA AND LAND OWNERSHIP
The Project area is limited to the Marden Park Landfill site, which is owned
and operated by BWS. The Project area comprises the GCS located in the
landfill mass itself and the flare unit located near the site office.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
6
1.5 DA STATUS AND CONSULTATION FOR THE SOEE
ERM understands that Ganian Pty Ltd was granted development consent (DA
98/2962) on 7 September 2000 by the Land and Environment Court of NSW to
operate a joint quarry and landfill at 920 Richmond Road, Marsden Park. The
Development Consent (DA 98/2962) covers quarrying, landfilling and
associated activities. However, under condition No. 54, separate planning
approvals must be obtained for any gas extraction facility. To fulfil this
requirement, ERM has prepared an SoEE for the Project to support a DA
under Part 4 of the Environmental Planning and Assessment Act 1979 (EP&A
Act).
A Pre-Application Meeting was undertaken on 21 September 2017 between
BWS and BCC representatives to discuss the outline Project scope, proposed
planning approval pathway and key issues for consideration and assessment.
A site visit and second meeting with BCC representatives was held on 20
October 2017 to inform the impact assessment process. The purpose of the site
visit and meeting was to:
discuss the detailed Project scope;
inspect the Project area and surrounding areas for potential sensitive
receptors and environmentally sensitive areas; and
discuss and agree on the scope of the SoEE, potential impacts and
mitigation and management measures.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
7
2 PROJECT DESCRIPTION
2.1 SUMMARY OF PROPOSED WORKS
The GCS is comprised of wells and pipe lying beneath the surface of the site,
which is connected to a high temperature enclosed flare. The GCS will utilise
the natural gradient of the site to dewater condensate from the gas flow lines.
In summary, the Project includes the following scope of works:
Installation of approximately 40 gas collection wells in the waste mass;
Installation of 90 mm flow lines to reticulate landfill gas from extraction
wells to the 250 mm header line;
Remedial works to re-seal compacted clay cap over pipe trenching;
Manifolds to contain approximately 4-8 wells per manifold;
Each well will have individual control and measurement of gas flow,
pressure and composition;
Manifolds connected to main header line via a length of 125 mm pipe;
In-line barometric condensate traps installed to remove any condensate
build up within the main header line close to flare;
Installation of a 1000 m3/hr capacity high temperature enclosed ground
flare powered by on-site three phase power supply;
The flare will have automatic shutdown and restart with remote dial in
telemetry;
Commissioning and pressure testing of the GCS and flare to ensure they
meet performance requirements;
Fencing enclosing the flare for security purposes;
Construction Quality Assurance reporting;
Operations and maintenance; and
Monthly reporting.
Further details of the various Project components are provided below.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
8
Note: Landfill closure planning is currently underway and BWS will seek to vary the existing landfill DA 98/2962, which is expected to involve updating the LEMP with the final agreed landfill level. The Project will need to consider the final landfill level and the wells, collection pipework, manifolds, etc. will not be able to be installed until the level is approved by BCC through the existing DA variation process. Once the final landfill level is agreed, the Project design will be updated, if required.
2.1.1 Drilling gas collection wells
Large diameter gas collection wells will be installed within the waste mass
using a TR100 Drilling rig. Wells will be drilled with a 500 mm diameter auger
and installed with a 160 mm diameter well screen. Extraction from these wells
will reduce the positive pressure build-up of landfill gas in the waste mass
and therefore reduce the potential for landfill gas to migrate laterally or
through the cap. The deep wells are installed to provide a uniform
overlapping radius of influence and low vacuum in the sub-surface to control
landfill gas. With 12 m deep collection wells spaced at 30 m, an effective zone
of vacuum will be exerted in the waste mass and soils surrounding the site.
Figure 2.1 provides an indicate layout of the GCS.
Well installation will be undertaken in accordance with the Environmental
Guidelines – Solid Waste Landfills (NSW EPA, 2016, 2nd Edition). The following
international guidelines will also be referred to:
UK Environment Agency Guidance on Pumping Trials to Determine Whether
Installation of Gas Flaring Systems at Landfill Sites Can Be Justified (2005);
UK Environmental Agency Guidance on Landfill Gas Management (2004);
UK Environmental Agency Guidance on Landfill Gas Flaring (2002);
Waste Management Industry Drilling into landfill waste, Industry Code of
Practice (2006); and
Industry Guidance Code Practice Perimeter Soil Gas Emission Criteria and
Associated Management (2011).
2.1.2 Flow Lines
Flow of landfill gas from the gas collection wells will be conveyed to the flare
via a 250 mm header line. The 90 mm diameter flow lines will be laid so that
condensate can fall back to the wells or to a condensate trap. The length of the
lines will be minimised to reduce the likelihood of introducing low points,
friction loss and build-up of condensate.
2.1.3 Remedial Works (to seal landfill cap)
Remedial works will be required by the Civil Contractor after excavation of
the landfill cap, in order to compact the clay liner back to its previous state.
44.00
44.50
45.00
45.00
45.50
46.00
51.00
51.00
51.00
ROAD No. 04
310.5
m468.3m
170.4
m
266.4m
108.3m
125.4m
CELL 2
CELL 1
GM10
GM11
GM9
GW12
GM8
GM2
GM7
GM4
GM6
GM5GM3
GM1
G2
G1
LEACHATE WELL
CELL 3
BLACKTOWN WASTE920 RICHMOND ROADMARSDEN PARK
DLA ENVIRONMENTAL3/38 LEIGHTON PLACEHORNSBY
920 RICHMOND ROAD
GAS WELL LOCATIONS
DRAFT
24/07/2017 SB AJM
4115 1 B
HISTORICAL VENT PIPE
INSTALLED GAS WELL
LFG MONITORING WELL
LEACHATE WELL
PROPOSED 125mm DIA15m DEEP PRODUCTION WELLPROPOSED 90mm DIAMIGRATION CONTROL WELL
KNOCK OUT POT
FLARE
250mm MAIN LINE
125mm MAIN LINE63mm FLOW LINEMANIFOLD
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
10
2.1.4 Manifolds
Each well will have individual control and measurement of gas flow, pressure
and composition. The tops of the wells will be constructed to enable ease of
removal for dipping, inspection and swapping between passive venting and
active extraction modes.
2.1.5 Condensate Management
Condensate refers to the moisture or liquid that is formed when collected
landfill gas cools. Many factors affect the quantity of condensate generated in
a collection system, including the gas temperature and flow rate. Condensate
will be removed passively at low points using barometric ‘traps’.
2.1.6 Installation of flare unit
A 1,000 m3/hr high temperature, fully enclosed ground flare unit will be
installed on site and connected to an existing three phase power source. This
eliminates the need to use diesel fuel in a portable generator and the use of
non-compliant elevated flares (non-high temperature).
The flare unit will be approximately 7 m high and located approximately 100
m south-west of the site office (refer to Figure 1.1). Figure 2.2 provides a
general arrangement for a similar flare unit and Photograph 2.1 shows an
example of a similar flare unit.
A bobcat excavator and small crane will be used to construct the concrete base
slab and install the flare unit. The works are minor in nature and will take
approximately 3 days to complete. The proposed design will assist with the
installation of the flare unit and make it easier and faster to construct. The
flare unit will be skid mounted and connected to ancillary equipment. By skid
mounting the unit and carrying out final assembly on site, it is possible to
carry out pre-delivery tests in the factory.
The flare unit provides industry best practice control over combustion air to
facilitate elevated temperatures, whilst ensuring complete combustion. All
flaring equipment on site will be compliant with the relevant Australian and
international standards, including:
AS 1375-Industrial Fuel Fired Appliances Code;
AS 3814/AG 501-Industrial and Commercial Gas-fired Appliances;
AS 5601/AG 601-Gas Installations;
Dangerous Substances and Explosive Atmospheres Regulations 2002
(DSEAR);
Implementing the Chemical Agents Directive 98/24/EC (CAD); and
The Explosive Atmospheres Directive 99/92/EC (ATEX 137).
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
12
Photograph 2.1 Enclosed ground flare unit
Key features of the flare unit are summarised below:
The flare unit will meet current NSW, Australian and European emissions
standards and is fully ATEX compliant.
The flare unit will have a demonstrable 98 to 99 % destruction efficiency.
A stainless steel condensate knockout pot located prior to the entry of the
gas booster ensures that no airborne liquids can pass into the gas booster.
An electric motor, with a direct-drive arrangement to a gas booster, will be
capable of delivering 1,000 m3/hr.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
13
A booster motor will be fitted with an inverter drive for variable speed
control and reduced energy costs. By installing an inverter drive, the
booster speed can be set to control the gas flow and save around 50% of the
energy costs.
The flare unit with automatic flame temperature will burn with a
combustion chamber temperature of 1,200 0C when methane concentration
is above 35%. Minimum residence time will be 0.6 seconds.
The height from ground level to the top of the shroud will be between 6.5
and 7.5 m. The chimney will be fitted with two off-gas sampling ports for
emissions monitoring and a stainless steel sample line at 1 m above ground
for sampling.
A gas analyser will be calibrated to read methane, carbon dioxide, oxygen
in %v/v, hydrogen sulphide and carbon monoxide in parts per million. The
gas analyser will have double measuring cells so that incoming gas and
exhaust gas exiting from the chimney can be measured simultaneously.
When this is combined with volumetric flow rate and temperature a mass
balance can be calculated continuously. Hence, a running ‘real-time’
measurement of destruction efficiency can be transmitted on line via the
telemetry unit.
Actual flow in m3/hr and total (cumulative) flow in m3 will be displayed
and recorded.
Temperature gauges will be fitted on the inlet and outlet to the gas booster.
The fixing of the flare stack to the concrete base will comply with relevant
Australian Standards.
The radiation levels at ground level will be within acceptable levels.
All pipework will be manufactured from stainless steel.
A control panel will be weather-proofed and fitted with a 24 hr / 7-day
timer.
2.4 m palisade security fencing will be installed around the flare unit.
The flare will be monitored remotely with alarm set points on gas quality. The
temperature and other variables are recorded by the loggers and transmitted
to a database.
Following installation of the wells and pipework, the system will be pressure
tested and validated prior to the system ‘going live’. The flare will be
monitored so that the critical parameters can be trended to assess the current
conditions on the gas field. The system will be balanced so that the maximum
number of wells can be extracted upon at the maximum rate of flow.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
14
2.2 WORKS PROGRAM
Subject to final staging and any weather delays, it is anticipated that
installation works will be completed over a period of approximately three
weeks, which is expected to include mobilisation and demobilisation at
commencement and completion respectively. Operation of the GCS is not
considered part of the works program.
As noted in Section 2.1, installation works will not commence until the final
landfill level is approved by BCC through the existing DA variation process.
2.3 CONSTRUCTION WORKFORCE
It is anticipated that the workforce will consist of approximately five
personnel on site at any one time.
2.4 CONSTRUCTION HOURS
It is anticipated that construction of the Project will be undertaken in general
accordance with the Interim Construction Noise Guideline (DECC, 2009), with
the standard hours of work being:
Monday to Friday: 7.00am-6.00pm;
Saturday: 8.00am-1.00pm; and
no works on Sunday or public holidays.
Construction works outside the standard construction hours may be undertaken in the following unlikely circumstances:
for the delivery of materials required outside the standard construction
hours by the NSW Police Force or other authorities for safety reasons; or
where it is required in an emergency to avoid the loss of lives, property
and/or to prevent environmental harm.
2.5 SITE ACCESS AND EGRESS
The proposed installation works will utilize Quarry Road via Richmond Road
for access to and egress from the Project area.
2.6 CONSIDERATION OF ALTERNATIVES
The following Project alternatives have been investigated as part of this SoEE
and are described below:
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
15
Do Nothing or Passive Approach (leave the landfill in its current state) –
This approach could result in:
Increased risk of sub-surface migration of landfill gas and other
contaminants in the event of failure of the system;
Increased emissions of un-oxidised methane direct to atmosphere acting
as a GHG; and
Increased risk of odours from organic compounds present in landfill gas.
Active Approach – This is the proposed installation of the GCS and flare
unit described above.
2.6.1 Preferred Option
The preferred option is to install the GCS and flare unit and this is the subject
of this application. Justification for the proposed works is provided below:
Removal of potentially hazardous landfill gases resulting in reduced health
and safety risks to nearby residents and community;
The removal of methane during gas collection and flaring will reduce GHG
emissions from the site, which makes the Project eligible under the ERF
enabling the offsetting of fossil fuel, which in turn results in a beneficial
environmental outcome and positive impact; and
The Project will contribute to the future rehabilitation and redevelopment
of the landfill site. The Project will assist in achieving the final land use goal
of ‘low density industrial use’, which will support the local community by
providing jobs and services, and in turn increasing cash flow throughout
the community.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
16
3 LEGISLATIVE AND POLICY CONSIDERATIONS
3.1 COMMONWEALTH LEGISLATION
3.1.1 Environmental Protection and Biodiversity Conservation Act 1999
The Environment Protection and Biodiversity Conservation Act 1999 (EPBC
Act) streamlines the national environmental assessment and approvals
process, protects Australian biodiversity and integrates management of
important natural and cultural places. Referral under the EPBC Act is
required for actions that are likely to have a significant impact on any
matter protected by the EPBC Act, including Matters of National
Environmental Significance (NES) as listed under the Act.
Table 3.1 Relationship between proposed works and Matters of National
Environmental Significance
Matters of National
Environmental Significance Application to the proposed works
Relevant
Sections
World heritage properties Not identified within the Project area. Not applicable
National heritage places Not identified within the Project area. Not applicable
Ramsar wetlands of international
importance
Not identified within the Project area. Not applicable
Listed threatened species and
communities
Potential habitat of threatened species
may occur within surrounding areas
of the Project area.
No Threatened Ecological
Communities (TEC) are present
within the Project area, however may
be present within areas surrounding
the Project area.
Not applicable
Internationally protected migratory
species
Migratory species identified as
potentially occurring within areas
surrounding the Project area.
Not applicable
Commonwealth marine areas Not identified within the Project area. Not applicable
The Great Barrier Reef Marine Park Not identified within the Project area. Not applicable
Nuclear actions Not identified within the Project area. Not applicable
A water resource, in relation to coal
seam gas development and large
coal mining development
Not identified within the Project area. Not applicable
3.2 NSW LEGISLATION
3.2.1 Environmental Planning and Assessment Act 1979
The Environmental Planning and Assessment Act 1979 (EP&A Act) is the
principal planning legislation for NSW. Section 79C of the EP&A Act
requires the consent authority to take into consideration a range of matters
when undertaking an assessment of a DA. These matters are address in
Section 5.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
17
‘Designated development’ refers to developments that are high-impact
developments (e.g. likely to generate pollution) or are located in or near an
environmentally sensitive area (e.g. a wetland). There are two ways a
development can be categorised as designated development:
1. the class of development can be listed in Schedule 3 of the
Environmental Planning and Assessment Regulation 2000 (EP&A
Regulation) as being designated development, or
2. a LEP or SEPP can declare certain types of development to be
designated.
For designated development an environmental impact statement is
required and third parties must be notified and can appeal against a
decision to grant consent.
Under the EP&A Regulation, Schedule 3, Clause 4, Part 1 lists the
following as designated development:
32 Waste management facilities or works (1) Waste management facilities or works that store, treat, purify or dispose of waste or sort, process, recycle, recover, use or reuse material from waste and:
(a) that dispose (by landfilling, incinerating, storing, placing or other means) of solid or liquid waste: (i) that includes any substance classified in the Australian Dangerous Goods Code or medical, cytotoxic or quarantine waste, or (ii) that comprises more than 100,000 tonnes of “clean fill” (such as soil, sand, gravel, bricks or other excavated or hard material) in a manner that, in the opinion of the consent authority, is likely to cause significant impacts on drainage or flooding, or (iii) that comprises more than 1,000 tonnes per year of sludge or effluent, or (iv) that comprises more than 200 tonnes per year of other waste material
The Project does not meet this definition of designated development in the
EP&A Regulation. There are also no LEPs or SEPPs which declare the
Project as designated development.
Schedule 4A of the EP&A Act identifies development for which Joint
Regional Planning Panels (JRPPs) may be authorised to exercise consent
authority functions of councils. The relevant provisions of Schedule 4A
applicable to the Project include:
‘general development’ that has a capital investment value of more than $20
million;
The Project has a capital investment value of approximately $495,000,
therefore this provision does not apply.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
18
Private infrastructure and community facility development that has a capital
investment value of over $5 million for any of the following purposes: air
transport facilities, electricity generating works, port facilities, rail
infrastructure facilities, road infrastructure facilities, sewerage systems,
telecommunications facilities, waste or resource management facilities, water
supply systems, or wharf or boating facilities
The Project is less than $5 million and is not consistent with any of
those purposes, therefore this provision does not apply.
As none of the provisions above apply to the Project, the consent authority is
BCC and a DA with an accompanying SoEE will be lodged for determination
under Part 4 of the EP&A Act.
Part 4 of the EP&A Act identifies integrated development, where approval
must also be obtained from other public authorities before consent can be
granted. Integrated development applications require a permit listed in
Section 91 of the EP&A Act. For the Project to operate, an EPL is required
under Protection of the Environment Operations Act 1997. BWS will submit a
variation request to the NSW EPA to modify their existing EPL (11497) to
include the proposed works. A similar process was recently undertaken for
the Horsley Park Landfill.
3.2.2 Protection of the Environment Operation (Clean Air) Regulation 2010
Regulatory requirements for the combustion of landfill gas by the use of an
active GCS and flare unit is detailed within the New South Wales
Environmental Protection Agency (NSW EPA) Environmental Guidelines: Solid
Waste Landfills (2016) and Protection of the Environment Operations (Clean Air)
Regulation 2010 (POEO Regulation).
The key air pollutants of concern from the combustion of LFG include oxides
of nitrogen and sulphur, and un-combusted volatile organic compounds. The
POEO Regulation requires Group 6 Treatment Plants to comply with the
following conditions:
Condition 49:
a) any flare operated for the treatment of air impurities is operated in such a way
that a flame is present at all times while air impurities are required to be
treated, and
b) either or both of the following requirements relating to the operation of any
such plant are complied with:
i. the requirements in clauses 50 and 51,
ii. the requirements in clause 52.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
19
Condition 50:
(2) An enclosed ground-level flare for the treatment of landfill gas must be operated
in such a way that the time between landfill gas entering and exiting the flare is
more than 0.6 seconds.
(3) For the purposes of this clause, the time elapsing between an air impurity
(including landfill gas) entering and exiting an afterburner or flare is to be
calculated:
a) using the volumetric flow rate for the air impurity, as determined in
accordance with TM-2 or CEM-6, and
b) using a 1 hour rolling averaging period.
Condition 51:
(2) An enclosed ground-level flare for the treatment of landfill gas must be operated
in such a way that the temperature for the combustion of landfill gas by the flare is
more than 760°C.
Condition 52:
(2) An enclosed ground-level flare for the treatment of landfill gas must be operated
in such a way that the destruction efficiency of the flare, in relation to landfill gas
entering the flare, is more than 98%.
Any liquid condensed from the landfill gas shall be handled in the same manner
as leachate. Because of the low pH and the potential odour it shall not be spray-
irrigated.
The discharge point(s) from any landfill gas combustion source should be
designed to promote good dispersion (i.e. by means of such factors as stack
height, diameter and discharge velocity) and ensure that the ground level
concentration criteria are not exceeded.
Additionally, Schedule 2 Clause 38 also requires that gas treatment discharge
limits which are to be complied with during operations (Table 3.2).
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
20
Table 3.2 Pollutant discharge limits (POEO Regulation)
Pollutant Standard of concentration
(mg/m3 )
Hydrogen sulphide (H2S) 5
Nitrogen dioxide (NO2) or nitric oxide (NO) or
both, as NO2 equivalent 350 (flare)
Sulfuric acid mist (H2SO4) or sulphur trioxide
(SO3) or both, as SO3 equivalent 100
Volatile organic compounds as n-propane
equivalent 40
Smoke (as a Group 6 category Treatment Plant)
No visible emission other than
for a total period of no more than
5 minutes in any 2 hours
Implications for the Project
The pollutant discharge limits set out in the POEO Regulation will not be
exceeded during operation of the Project. A similar flare unit was recently
approved by the NSW EPA at the Horsley Park Landfill Site, which contained
results from previous emissions tests, which demonstrated compliance with
these discharge limits. Refer to Section 4.6 for further details.
3.3 STATE ENVIRONMENTAL PLANNING POLICIES
3.3.1 State Environmental Planning Policy (Sydney Region Growth Centres) 2006 -
Marsden Park Industrial Precinct Plan 2010
The Marsden Park Landfill falls within the MPIP, which in itself contains a
plan within Appendix 5 of this SEPP (i.e. Marsden Park Industrial Precinct
Plan 2010). The site is zoned ‘IN1’ General Industrial, which permits
development of the following with consent:
Animal boarding or training establishments; Depots; Drainage; Earthworks;
Freight transport facilities; Light industries; Neighbourhood shops; Recreation
facilities (major); Registered clubs; Roads; Take away food and drink premises;
Warehouse or distribution centres; Waste or resource management facilities; Any
other development not specified in item 2 or 4
The Project does not fall into any of the developments listed above, or into any
of the prohibited developments listed in Item 4, as it is not ‘Waste or resource
management facilities’ or ‘Waste disposal facilities’. Therefore the Project is
permitted with development consent from BCC.
3.3.2 State Environmental Planning Policy No 33— Hazardous and Offensive
Development
In accordance with State Environmental Planning Policy 33 – Hazardous and
Offensive Development (SEPP 33), consideration has been made as to whether
the Project should be considered a hazardous or potentially hazardous
industry using the Applying SEPP 33 – Hazardous and Offensive Development
Application Guidelines (SEPP 33 Guidelines).
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
21
The Project will not involve the storage of hazardous materials within the site
or the transportation of hazardous materials to/from the site. In addition,
Appendix 3 of the SEPP 33 Guidelines provides a schedule of potentially
hazardous industries that may fall within SEPP 33. The proposed works are
not included in the schedule.
The Project is not deemed hazardous or potentially hazardous under SEPP 33
and therefore it is not considered applicable. Nevertheless, a high-level risk
assessment has been undertaken for the Project and is summarised in Section
4.11 of this report.
3.4 LOCAL STATUTORY CONTEXT
3.4.1 Blacktown Local Environmental Plan 2015
The Marsden Park Landfill site exists within the SEPP (Sydney Region Growth
Centres) 2006 zoning within the Blacktown LEP 2015. The site therefore is
assessed under the conditions of the SEPP, which takes preference over the
LEP.
3.5 DEVELOPMENT CONTROL PLANS
3.5.1 Blacktown City Council Growth Centre Precincts Development Control Plan
2014 (Schedule 3 – Marsden Park Industrial Precinct)
BCC has a consolidated Development Control Plan (DCP) for development
within the Blacktown LGA, being the BCC Growth Centre Precincts DCP 2014.
Site-specific controls for the MPIP support the controls in the DCP under
Schedule 3 – Marsden Park Industrial Precinct of the DCP. The DCP has been
prepared to provide guidance to applicants proposing to undertake
development in the BCC Growth Centre precincts in respect of the planning,
design and environmental objectives and controls.
There are no specific controls relating to the proposed works outlined in the
plan. The general development objectives and controls outlined in the Plan
have been considered in the preparation of the SoEE, as relevant to the Project
and its potential impacts, and included in the management and mitigation
measures.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
22
4 ENVIRONMENTAL IMPACT ASSESSMENT AND MANAGEMENT
4.1 FLORA AND FAUNA
4.1.1 Existing Environment
A site inspection was undertaken at the Marsden Park Landfill on 20 October
2017 to inspect the site and surrounding areas for potential sensitive receptors
and other potential areas of impact to the surrounding environment.
Additional inspection was undertaken to observe any remnant vegetation or
signs of biodiversity value, to assist in the determination of the suitability of
the site as habitat for flora and fauna.
The findings from the site inspection indicated a lack of suitable habitat for
fauna within the Project area due to the degree of disturbance from the landfill
operation, and the lack of suitable vegetation necessary for foraging and
protection. The only vegetation within the Project area was a small stand of
mature gum tress located around the site office.
An EPBC Protected Matters Search was also undertaken on 31 October 2017 to
determine whether Matters of National Environmental Significance or other
matters protected by the Environment Protection and Biodiversity Conservation
Act 1999 were likely to occur within the area of interest. The search included a
1 km buffer around the Project area in all directions.
Threatened Ecological Communities
The results of the search indicated that four Threatened Ecological
Communities (TEC’s) have potential to exist within the area and surrounding
areas, including Castlereagh Scribbly Gum and Agnes Banks Woodlands of
the Sydney Basin Bioregion, the Cooks River/Castlereagh Ironbark Forest of
the Sydney Basin Bioregion, the Cumberland Plain Shale Woodlands and
Shale-Gravel Transition Forest and the Western Sydney Dry Rainforest and
Moist Woodland on Shale threatened ecological communities.
There is scarce remnant vegetation throughout the Project area, however due
to ongoing disturbance as a result of existing landfill operations, such
vegetation is not considered optimal for habitat for native fauna.
Threatened Flora and Fauna Species
No threatened species were observed within the Project area during the site
inspection. The results of the Protected Matters Search Tool identified 29
threatened species which have the potential occur based on the presence of
suitable habitat and records within the locality. Table 4.1 below provides
information on the listed threatened species with potential to exist within and
in areas surrounding the Project area.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
23
Table 4.1 Threatened species (and/or threatened species habitat) with potential to occur
within the Project area
Value Type Scientific Name Common Name Conservation Status
BC Act EPBC
Birds Anthochaera Phrygia Regent Honeyeater CE CE
Birds Numenius
madagascariensis
Eastern Curlew, Far
Eastern Curlew
- CE
Birds Calidris ferruginea Curlew Sandpiper E CE
Birds Lathamus discolour Swift Parrot E CE
Birds Botaurus poiciloptilus Australasian Bittern E E
Birds Rostratula australis Australian Painted
Snipe
E E
Birds Grantiella picta Painted Honeyeater V V
Fish Macquaria australasica Macquarie Perch E E
Fish Prototroctes maraena Australian Grayling E V
Frogs Heleioporus australiacus Giant Burrowing Frog V V
Frogs Litoria aurea Green and Golden Bell
Frog
E V
Mammals Dasyurus maculatus
maculatus (SE mainland
population)
Spot-tailed Quoll,
Spotted-tail Quoll,
Tiger Quoll
(south-eastern
mainland population)
V E
Mammals Chalinolobus dwyeri Large-eared Pied Bat,
Large Pied Bat V V
Mammals Petauroides Volans Great Glider - V
Mammals Pseudomys novaehollandiae New Holland Mouse,
Pookila V V
Mammals Phascolarctos cinereus Koala V V
Mammals Pteropus poliocephalus Grey-headed Flying-
fox V V
Plants Allocasuarina glareicola - E E
Plants Genoplesium bauera Yellow Gnat-orchid E E
Plants Pimelea spicata Spiked Rice-flower E E
Plants Pterostylis saxicola Sydney Plains
Greenhood E E
Plants Acacia bynoeana Bynoe’s Wattle, Tiny
Wattle E V
Plants Acacia pubescens Downy Wattle, Hairy
Stemmed Wattle V V
Plants Haloragis exalata subsp.
exalata
Wingless Raspwort,
Square Raspwort V V
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
24
Value Type Scientific Name Common Name Conservation Status
BC Act EPBC
Plants Micromyrtus minutiflora - E V
Plants Pimelea curviflora var.
curviflora
- V V
Plants Pultenaea parviflora - E V
Plants Syzygium paniculatum Magenta Lilly Pilly,
Magenta Cherry,
Daguba, Scrub Cherry,
Creek Lilly Pilly, Brush
Cherry
E V
Plants Thesium austral Austral Toadflax,
Toadflax V V
CE = Critically Endangered, E = Endangered, V – Vulnerable
4.1.2 Assessment of Impact
No vegetation will be required to be cleared and the small stand of mature
gum tress located around the site office will not be impacted. Due to the
minimal environmental disturbance associated with the proposed works, it is
considered highly unlikely that any significant impacts to flora and fauna
would arise from the installation and operation of the GCS and flare unit.
4.1.3 Environmental Mitigation
Given the limited potential for any ecological impacts to occur, no
recommendations for mitigation and management measures are warranted or
provided in this SoEE.
4.1.4 Conclusion
The Project is not likely to result in a significant impact on any threatened
species or threatened ecological community listed under the BC Act or the
EPBC Act. The Project is not anticipated to have any significant impact upon
ecological values of the area and the environmental risk is considered to be
negligible.
4.2 ABORIGINAL HERITAGE
4.2.1 Existing Environment
ERM undertook a targeted Aboriginal Heritage Information Management
systems (AHIMS) search on 9 November 2017, which revealed that four
Aboriginal sites had been previously recorded within the proximity of the
Project area. No artefacts or items of significance were declared within the
Project area.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
25
It is expected that the existing Project area is of relatively low Aboriginal
archaeological significance and sensitivity, due to the highly disturbed and
modified landscape in which the landfill currently exists, and the limited
identified items (or areas) of significance within and surrounding the Project
area.
4.2.2 Assessment of Impact
Due to the highly modified existing environment throughout and surrounding
the Project area and the results of the AHIMS search, it is considered unlikely
that any impacts to areas of Aboriginal or archaeological significance will
occur during the proposed works.
4.2.3 Environmental Mitigation
Given the limited potential for any Aboriginal heritage impacts to occur, no
recommendations for mitigation and management measures are warranted or
provided in this SoEE.
4.2.4 Conclusion
Due to the current lack of declared Aboriginal heritage areas within and
surrounding the Project area, the Project is not anticipated to have any
significant impact upon Aboriginal heritage and the overall environmental
risk is considered to be negligible.
4.3 NON-ABORIGINAL HERITAGE
4.3.1 Existing Environment
ERM undertook a search of relevant databases, inventories and registers,
including the NSW State Heritage Register, the NSW State Heritage Inventory,
the EPBC Act listings, Australian Heritage Register and the Blacktown LEP
2015 to determine if any items of non-Aboriginal Heritage (also referred to as
historic heritage) significance were found previously on or in the vicinity of
the Project area.
Searches of the abovementioned databases confirmed that no items of non-
Aboriginal significance exist within the Project area, with the closest item
being approximately 2.2 km north of the site.
4.3.2 Assessment of Impact
Minimal disturbance to areas of non-Aboriginal heritage are expected during
the proposed works due to the distance from the closest item of significance
and the minor disruptive activities associated with the proposed works.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
26
4.3.3 Environmental Mitigation
Given the limited potential for any non-Aboriginal heritage impacts to occur, no recommendations for mitigation and management measures are warranted or provided in this SoEE.
4.3.4 Conclusion
The Project is not expected to impact upon any listed items of non-Aboriginal
heritage significance and the environmental risk is considered to be negligible.
4.4 GEOLOGY AND SOIL
A desktop study of the landform, soils and geology along the Project area was
undertaken using the Soil Landscapes of the Penrith 1:100 000 sheet report
prepared by the Department of Land and Water Conservation, Sydney (Banks,
2001).
4.4.1 Existing Environment
The Marsden Park Landfill exists within the Blacktown Soil Landscape, which
is comprised of:
Low hills and rises on Wianamatta Group Shale (shale, sandstone-lithic and
sandstone-quartz) in the Cumberland Plain, Hornsby Plateau and Picton
Hills. Local relief 10-50 m; altitude 10-202 m; slopes 0-9%; rock outcrop nil.
Extensively cleared woodland.
The landfill is located in a relatively anthropogenic environment (cleared vegetation and pre-existing disturbance from landfill operations) with minimal interaction with the soil. The landfill has a Flexible Membrane Liner.
4.4.2 Assessment of Impact
Installation and operation of the GCS and flare unit is not expected to cause
any activities that may give rise to potential soil impacts. Only minor
excavation works will be required in the landfill mass itself and near the site
office for the installation of the concrete base slab. Futures settlement of the
landfill mass will not affect the operation of the GCS or flare unit.
Site personnel vehicles, heavy vehicles and plant and equipment will use
existing paved and sealed areas, which will not be disturbed by the works.
4.4.3 Environmental Mitigation
Due to the highly disturbed and industrial nature of the Project area, impacts
to soil and geographic landscape are expected to be minimal, however
mitigation measures will be in place to ensure that any potential impacts are
managed where practicable.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
27
Sediment and erosion control devices will be established before any ground
disturbance begins and maintained as necessary until affected ground surfaces
have been adequately stabilised. The following general principles and
mitigation and management measures will be implemented during the
proposed works:
establishment and maintenance of sediment and erosion control devices
will be consistent with the Landcom Managing Urban Stormwater: Soils and
Construction (New South Wales Government, 2004), commonly referred to
as the ‘Blue Book’;
if the presence of contaminated soils is identified, removal will take place in
accordance with NSW EPA (2014) Waste Classification Guidelines;
appropriate PPE will be utilized during proposed works;
where practicable, maintenance of natural buffer zones between disturbed
areas and drainage lines will be implemented.
stockpiles of soil/landfill waste will be appropriately located away from
waterways and drainage lines; and
where areas have been disturbed and ongoing use of disturbed areas is not
required for operations, reinstatement of the natural ground level and
revegetation of disturbed areas will be undertaken.
4.4.4 Conclusion
By implementing the aforementioned mitigation measures, the Project is not
anticipated to have significant adverse impacts on local soils and the
environmental risk is considered to be negligible.
4.5 WATER QUALITY AND HYDROLOGY
4.5.1 Existing Environment
The Project area is located within the Hawksbury-Nepean Catchment and
approximately 1.2 km west of Bells Creek. The creek generally flows
north/north-east until it reaches its confluence with Eastern Creek. Bells
Creek will be not be affected by the proposed works. A minor tributary of
South Creek is located to the west of the Project area, which will also be
avoided during the proposed activities.
A search of the NSW groundwater data resource All Water Data (DPI, Office
of Water) identified groundwater bores registered within 1 km of the Project
area. Three monitoring bores are located in the vicinity of the site, however
the Standing Water Level data was unavailable and has not been reproduced
within Table 4.3 below.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
28
Table 4.2 NSW Office of Water Registered Bores Within Project Vicinity
Bore Number Co-ordinates Standing Water
Level (m bgl)
Final Depth
(m)
Use of Well
GW104308 N: 6268327.0
E: 298650.0
- 14 Monitoring
Bore
GW104310 N: 6268471.0
E: 299111.0
- 9 Monitoring
Bore
GW104311 N: 6268327.0
E: 299016.0
- 17 Monitoring
Bore
The nearest bore is located approximately 875 m to the north of the Project
area and will not be affected by the proposed works.
4.5.2 Assessment of Impact
Potential water related impacts associated with the proposed activities
include:
erosion of any waste stockpiles (landfill waste, etc.);
water collected within the Project area following rainfall events may have
high sediment content and if not managed appropriately, could
contaminate surface waters;
potential accidental hydrocarbon spills from plant and equipment (burst
hoses, mechanical failures, leaking machinery, etc.); and
contamination of waterways from hazardous substances due to incorrect
storage (including drums and containers and spent oil filters, etc.).
4.5.3 Environmental Mitigation Measures
The following mitigation and management measures will be implemented
during the proposed works:
avoid and/or cover existing drainage infrastructure during proposed
works to reduce potential for contamination;
landfill waste will only be temporarily stockpiled and reinstated as soon as
practicable post installation of the GCS;
spill response plans/procedures will be prepared for the Project prior to
commencement of proposed works; and
spill kits will be made available in locations used for chemical storage,
where refuelling is undertaken, and in other sensitive work sites where
potential for spills from plant or equipment are in use.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
29
4.5.4 Conclusion
By implementing the aforementioned mitigation measures, the Project is not
anticipated to have significant adverse impacts on water quality and
hydrology and the environmental risk is considered to be negligible.
4.6 AIR QUALITY AND GHG
4.6.1 Existing Environment
Based on the surrounding land use, it is expected that existing air quality in
the locality is influenced by nearby industrial and commercial facilities, along
with the existing operations undertaken at the landfill site, including the
movement of vehicles to and from the site. During unfavourable (high wind)
weather conditions, it is possible that the landfill site impacts local air quality
due to the mobilisation of airborne odour particulates, and air quality
pollutants being emitted from vehicular movements associated with the
operation of the site (e.g. trucks delivering waste to the landfill site).
4.6.2 Assessment of Impact
During the installation of the GCS in the landfill mass, there is the potential
for localised, short-term odour impacts from the drilling waste. The waste
will be taken to the active tip face and filled immediately.
The combustion of the landfill gas by the flare unit will result in the emission
of air pollutants. The key air pollutants of concern from the combustion of
landfill gas include oxides of nitrogen, sulphur and un-combusted volatile
organic compounds (VOCs). As such, discharge limits are applied to the
above pollutants under the Protection of the Environment Operations (Clean Air)
Regulation 2010 (Schedule 2), which will be adhered to during operation of the
flare unit (refer to Table 4.3).
Table 4.3 Pollutant discharge limits
Pollutant Standard of concentration
(mg/m3 )
Hydrogen sulphide (H2S) 5
Nitrogen dioxide (NO2) or nitric oxide (NO) or both,
as NO2 equivalent 350 (flare)
Sulfuric acid mist (H2SO4) or sulphur trioxide (SO3)
or both, as SO3 equivalent 100
Volatile organic compounds as n-propane
equivalent 40
Smoke (as a Group 6 category Treatment Plant)
No visible emission other than
for a total period of no more
than 5 minutes in any 2 hours
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
30
These pollutant discharge limits will not be exceeded during operation of the
flare unit, due to rigorous compliance testing which must be undertaken and
documented prior to installation. A similar flare unit was recently approved
by the NSW EPA at the Horsley Park Landfill Site, which contained results
from previous emissions tests, which demonstrated compliance with these
discharge limits. A typical flare emission testing report is provided in
AnnexA.
Following on-site commissioning of the GCS and flare unit, a National
Association of Testing Authorities (NATA) accredited Contractor will
undertake the compliance emission monitoring. The NATA contractor will be
independent of BWS and will meet the following requirements:
Testing procedures are NATA accredited in accordance with ISO/IEC
17025 and AS4323.1;
NATA accreditation number recorded; and
Principal and senior level technicians accredited under The American
Source Evaluation Society’s QSTI program.
The initial program of testing will be undertaken annually subject to passing
all compliance tests.
4.6.3 Environmental Mitigation
The following mitigation and management measures will be implemented
during the proposed works:
during installation, significant dust generating activities (if any) will be
avoided during unfavourable (high wind) weather conditions;
dust suppression may be used during installation, if required;
undertake regular operational compliance monitoring and maintenance of
the GCS and flare unit as described in Section 4.11 below;
4.6.4 Conclusion
The flare unit will utilise the latest technology to meet present and near future
emissions standards. By implementing the aforementioned mitigation
measures, the Project is not anticipated to have adverse impacts on air quality
and the environmental risk is considered to be negligible The reduction in
GHG emissions (in particular, methane) as a result of the Project will have a
beneficial environmental outcome and positive impact. The Project will also
reduce the potential for odorous landfill gases to dissipate to surrounding
receivers.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
31
4.7 NOISE AND VIBRATION
Nuisance, or an unacceptable level of noise amenity, may arise from
construction or operational activities associated with new or existing
developments. This section addresses potential issues associated with noise
and vibration generated by the Project and provides recommendations for
mitigation and management measures. These measures are based on the
likely magnitude and extent of potential impacts, they are designed to reduce
noise and vibration levels as far as practicable and to assist achieve an
acceptable amenity for residential (dwelling) occupants and other sensitive
receptors surrounding the site.
The key noise issues potentially associated proposed works are mainly
operational noise emissions attributable to the operation of the GCS and flare
unit, with minor noise expected during installation activities. Potential noise
issues associated with road traffic from Project vehicles on public roads and
potential vibration issues associated with the proposed works are also
considered here but impacts are unlikely to occur, if at all.
4.7.1 Policy Setting
This noise and vibration assessment has been conducted with due regard to
and in accordance with the following key policy and guidelines. Other local
and international acoustical standards have been adopted where relevant to
the assessment.
NSW Environmental Protection Authority (EPA) – Noise Policy for Industry
(NPI), October 2017 (which supersedes the NSW Industrial Noise Policy
(INP), January 2000);
NSW Department of Environment and Climate Change – NSW Interim
Construction Noise Guideline (ICNG), July 2009;
NSW Department of Environment, Climate Change and Water – NSW Road
Noise Policy (RNP), March 2011; and
NSW Department of Environment and Conservation - Assessing Vibration:
A Technical Guideline (NSW Vibration Guideline), February 2006.
The key noise and vibration guideline applicable to this assessment is the NPI
and is associated with the proposed operation of the GCS and flare unit.
4.7.2 Existing Environment
A key element in assessing environmental noise impacts is an understanding
of the existing noise conditions at areas surrounding, or in proximity to, a site.
In particular, the ambient and background noise levels at or in the vicinity of
the closest and/or potentially most affected receptors situated within the
potential area of influence of a project.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
32
This is of particular importance (and a formal assessment requirement for
projects developed in NSW) as it assists to directly evaluate potential noise
impacts and prevents an incremental increase in background noise levels, the
result of which may both generate nuisance, or an unacceptable level of noise
amenity.
Existing vibration levels are not required to be measured as vibration criteria
are fixed values that do not depend on the existing conditions. Hence, this
section focuses on the existing noise environment.
Existing Noise Conditions
The existing environment in the vicinity of the Project is described as
‘suburban’. Although being in an area zoned ‘industrial’ within the State
Environmental Planning Policy (Sydney Region Growth Centres) 2006, the
area is consistent with the characteristics identified for suburban residential
receiver category outlined in the NPI.
The existing noise generating activities within the vicinity of the Project
include:
noise generated from nearby facilities, warehouses and commercial
premises;
noise generated by the activities undertaken on site in regards to the
operation of the landfill; and
road traffic noise from the roadways adjacent to the Project area, including
Richmond Road.
No other significant noise generating activities or sources have been identified
to occur in the area.
Potentially Sensitive Receptors
The NPI and the ICNG identify a number of sensitive receptor types that
should be considered when assessing noise and vibration impacts. These
receptor types include residential premises, schools, hospitals, places of
worship, recreational areas as well as commercial and industrial premises.
The nearest schools, hospitals and places of worship are all between
approximately 2 to 6 km away from the Project area. Residential properties
have been identified based on a review of aerial photography, and are located
approximately 750 m south, approximately 500 m to the north and
approximately 850 m northeast from the Project area. The nearest commercial
and industrial receptors are located approximately 400 m from the Project
area.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
33
Estimated Background Noise Levels
In the absence of measured ambient and background noise level data for the
site and surrounding area, representative values have been estimated for the
purpose of this assessment. The ‘Rating Background Level’ (RBL) has been
established following a review of aerial photography and knowledge of
existing background noise levels for similar acoustical environments and a
review of the existing EPL (11497).
In accordance with the NPI the RBL is defined as the overall single figure
background level representing each assessment period; daytime, evening, and
night time. The RBL values considered in this assessment are presented in
Table 4.4 for each assessment period separated by northern and southern
receptors.
Table 4.4 Rating Background Noise Levels (RBL)
RBL (dBA)
Day Evening Night
Northern
Receptors 40 35 30
Southern
Receptors 35 30 30
1. In accordance with the NPI the assessment periods are defined as follows:
a) Day – the period from 7 am to 6 pm Monday to Saturday or 8 am to 6 pm on Sundays
and public holidays
b) Evening – the period from 6 pm to 10 pm
c) Night – the remaining periods.
4.7.3 Noise Management Levels and Criteria
All Project-specific Noise Management Levels (NML) and criteria have been
established in accordance with the NPI, ICNG and RNP as applicable to the
factor being addressed. For residential receptors these levels have been based
on the estimated RBL values presented in Table 4.4. NMLs and criteria for
other sensitive receptors are fixed values and do not rely on RBL.
For the purposes of the assessment the LAeq, 15 minute parameter has been
adopted for all receptors (including other sensitive receptors) assuming that
emissions will generally occur throughout the total duration of any given
assessment period. LAeq is an A-weighted noise level representing the
equivalent or average noise energy during a measurement period. The LAeq,
15minute noise descriptor simply refers to the LAeq noise level calculated over a
15 minute period. For road traffic noise, the LAeq parameter also applies with
assessment periods of one hour, nine hours or 15 hours depending on the type
of road and time of day.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
34
Construction Noise
For construction noise, the NML values have been determined with due
regard to the ICNG utilising the RBLs described in Section 4.7.2. During
construction, the Highly Noise Affected Management Level (HNML) also
applies to residential receptors during standard daytime hours and is a fixed
value of LAeq, 15 minute 75 dB (dB or decibels is the unit used to measure sound
pressure levels. For A-weighted decibels, dBA may be used. A-weighting is an
adjustment made to sound-level measurement to approximate the response of
the human ear). Construction NMLs are presented in Table 4.5 below.
Table 4.5 Construction Noise Management Levels (NML) - (LAeq, 15 minute)
Receptor Type
NML (dBA)
Standard Hours Non-Standard Hours
Day Day Evening Night
Northern Residential 50 45 40 35
Southern Residential 45 40 35 35
Commercial Premises 70 70 70 70-
Industrial Premises 75 75 75 75
1. In accordance with the ICNG the recommended standard hours of construction are
Monday to Friday 7 am to 6 pm, Saturday 8 am to 1 pm and no work on Sundays or
public holidays.
In accordance with the ICNG, NML values for other sensitive receptors (i.e.
places of worship, commercial and industrial premises, schools or recreational
areas) are fixed levels based on usage. They are not derived from measured
ambient and background noise levels.
Operational Noise
All Project-specific operational noise management levels (project intrusiveness
noise level) are presented in Table 4.6. These values have been determined
with due regard to the NPI utilising the RBLs described above.
Table 4.6 Operational - Project Intrusiveness Noise Level - (LAeq, 15 minute)
Receptor Type RBL (dBA)
Day1 Evening2 Night3
Northern Residential 45 40 35
Southern Residential 40 35 35
1. Day – the period from 7 am to 6 pm Monday to Saturday or 8 am to 6 pm on Sundays
and public holidays
2. Evening – the period from 6 pm to 10 pm
3. Night – the remaining periods.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
35
In accordance with the NPI, intrusiveness noise levels are only applied to
residential (dwelling) receptors. For other receptor types identified, only the
amenity levels outlined in the NPI apply.
Intrusiveness noise levels and amenity noise levels are not used directly as
regulatory limits. They are used in combination to assess the potential impact
of noise, assess reasonable and feasible mitigation options, and subsequently
determine achievable noise requirements.
Road Traffic Noise Criteria
The NPI and ICNG do not include any criteria to assess off-site traffic noise
associated with operation and construction. Criteria for off-site road traffic
noise applicable to ‘existing residences affected by additional traffic on
existing roads generated by land use developments’ are specified in the RNP.
Whilst these criteria do not specifically apply to construction/operational
traffic movements, they have been conservatively adopted for this assessment.
In accordance with the RNP, criteria values for residential receptors are fixed
levels. They are not derived from measured ambient and background noise
levels.
The project-specific road traffic noise criteria are presented in Table 4.7 below.
Table 4.7 Road Traffic Noise Criteria
Road Category Assessment Criteria - dBA
Day
(7 am - 10 pm)
Night
(10 pm - 7 am)
Freeway / Arterial / sub-
arterial roads 60 LAeq, 15 hour (external) 1 55 LAeq, 9 hour (external) 1
Local roads 55 LAeq, 1 hour (external) 2 50 LAeq, 1 hour (external) 2
1. Existing residences affected by additional traffic on existing freeways/arterial/sub-arterial
roads generated by land use developments; and
2. Existing residences affected by additional traffic on existing local roads generated by land
use developments.
Where existing traffic noise levels are above the noise assessment criteria, the
primary objective is to reduce these through feasible and reasonable measures
to meet the assessment criteria. A secondary objective is to protect against
excessive decreases in amenity as the result of a project by applying the
relative increase criteria outlined in the Section 2.4 of the RNP.
In assessing feasible and reasonable mitigation measures, an increase of up to
2 dBA represents a minor impact that is considered barely perceptible to the
average person. A relative increase of 12 dBA (as per the relative increase
criteria) represents slightly more than an approximate doubling of perceived
loudness (RNP, 2011) and is likely to trigger community reaction, particularly
in environments where there is a low existing level of traffic noise.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
36
Vibration Criteria and Safe Limits
The effects of vibration in buildings can be divided into three main categories:
human comfort (annoyance); cosmetic damage; and structural damage. An
overview of the applicable standards and guidelines is provided below.
Human Comfort (Annoyance): the NSW Vibration Guideline provides
guidance for assessing human exposure (comfort or annoyance issues) to
vibration. The publication is based on British Standard (BS 6472–1992) –
Evaluation of Human Exposure to Vibration in Buildings (1 Hz to 80 Hz), dated
1992.
Cosmetic and Structural Damage: there is currently no Australian policy,
standards or guidelines for assessing the potential for building damage
(cosmetic and structural) from vibration. It is common practice however to
derive safe limit values for assessment purposes from international standards,
such as British Standard BS7385: Part 2-1993 (BS 7385) - Evaluation and
Measurement for Vibration in Buildings — Part 2 – Guide to Damage Levels from
Ground-borne Vibration, dated 1993 and German Standard DIN4150 Part 3-1999
(DIN4150-3) – Structural Vibration - Effects of Vibration on Structures, dated
1999.
The NSW Vibration Guideline, BS 7385 and DIN 4150 vary based on vibration
type, receptor type and are dependent on the component frequency of the
vibration event. To avoid presenting an exhaustive list of criterion values and
as vibration impacts are not expected (refer Section 4.7.4 below), the criteria
values from the NSW Vibration Guideline, BS 7385 and DIN 4150 were
considered in the assessment of potential impacts but are not reproduced here.
4.7.4 Assessment of Impact
A quantitative assessment of potential noise and vibration impacts associated
with the installation and operation of the GCS and flare unit (including road
traffic) has not been undertaken. Instead, a qualitative assessment is provided
below.
Construction Noise
The construction and installation of the GSC would be completed over
approximately three weeks. These activities would be undertaken during the
daytime between recommended ICNG standard hours for construction.
Based on the type of works, activities and equipment that would be
undertaken or in use and proximity to the nearest sensitive receptors, it is not
expected that construction noise levels from the Project will exceed the
construction NMLs or the HNML for the duration of the Project.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
37
Where receptors are situated at a greater distance from the Project works,
noise levels and associated impact will be reduced by comparison to works
and activities conducted in close proximity to receptors.
The ICNG focuses on minimising construction noise impacts, rather than only
on achieving numeric noise levels. Best practice noise mitigation and
management measures will be required to reduce noise levels as far as
practicable. In accordance with the intent of the ICNG, suitable
recommendations for noise mitigation and management measures are
provided in Section 4.7.5.
Operational Noise
The main noise emission source is associated with the 24 hour operation of the
flare unit. In order to attenuate the anticipated noise emissions, the flare unit
will be fitted with an acoustic enclosure and situated in a strategic location in
which existing site infrastructure and vegetation will obscure the direct line of
sight towards potentially affected receivers. In accordance with the NPI, this
qualitative assessment has considered modifying factors for annoying
characteristics and sleep disturbance.
Based on the information provided and the implementation of an acoustic
enclosure, the operation of the flare unit is not expected to exceed the
operational criteria at the nearby sensitive receptors identified in this
assessment. The predicted noise level associated with the new flare unit is 23
dBA LAeq, 15 minute at the closest and/or the potentially most affected
residential (dwelling) receptor (situated approximately 500 m north of the site
on South Street) near the site. Based on this, the introduction of the new
equipment to the Marsden Park Landfill site is not expected to significantly
increase the site’s noise level contribution or change its existing compliance
status with regards to EPL 11497. Given that the surrounding area is best
described as a suburban acoustic environment, it is expected that the new
equipment will be inaudible for the majority of the time and any impacts to
the adjacent community are expected to be minor.
Road Traffic Noise
Apart from delivery of pipe and materials at the start of the Project, any
impacts from Project-related traffic on public roads will be minimal, if any at
all. Furthermore, the vehicle movements (to and from the site) associated with
the Project works are insignificant when compared to that of the existing road
network. As such, it is expected that road traffic noise generated by the
Project would comply with the requirements of the RNP at the majority of
receptors and any temporary change in overall road traffic noise would be
barely perceptible to the average person.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
38
Road traffic noise from the Project may be audible at times, but with the
implementation of the traffic management measures outlined in Section 4.8.3
below, any adverse effects would be maintained at acceptable levels.
Therefore, no further recommendations for road traffic noise mitigation and
management measures are warranted or provided in this SoEE.
Vibration
Based on the equipment and activities identified for the Project, potential
sources of vibration are limited and would only occur during the installation
works. This feature combined with the ≥ 400 m distance offset (vibration
dissipates rapidly with distance) to the closest receptor or buildings identifies
that vibration impacts are not anticipated as a result of the Project. It is
expected that vibration generated by the Project works would comply with the
requirements of the NSW Vibration Guideline, BS 7385 and DIN 4150.
Given the limited potential for any vibration impacts to occur, no further
recommendations for vibration mitigation and management measures are
warranted or provided in this SoEE.
4.7.5 Environmental Mitigation
To ensure noise emissions associated with Project construction works are kept
to acceptable levels, the following mitigation and management measures are
recommended:
install GSC in accordance with the construction quality assurance (CQA)
program and undertake commissioning checks and regular operational
maintenance, testing and monitoring as outlined in Section 4.11 below;
locate noisy equipment (in this case, the flare unit) behind structures that
act as barriers, or at the greatest distance from the noise-sensitive areas;
work and activities should be carried out during the ICNG recommended
standard hours (i.e. 7am to 6pm Monday to Friday and 8am to 1pm
Saturdays), with no work on Sundays or public holidays;
choose appropriate machines for each task and adopt efficient work
practices to minimise the total construction period and the number of noise
sources on the site;
ensure all machines used on the site are in good condition, with particular
emphasis on exhaust silencers, covers on engines and transmissions and
squeaking or rattling components;
all plant, equipment and vehicles movements should be optimised in a
forward direction to avoid triggering motion alarms that are typically
required when these items are used in reverse; and
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
39
if any noise complaints are received, attempts will be made to discuss with
the complainant how works can be adjusted to alleviate their concerns. If
this is not successful then operator attended noise measurements will be
undertaken to measure and compare the site noise level contributions
(LAeq, 15 minute) to the NMLs presented in this report. All site noise levels
would be measured in the absence of any influential source not associated
with the site. If the measured site noise levels comply with the NMLs
presented in this report, no further mitigation or management measures are
required. If the measured site noise levels are above those presented in this
report, further mitigation and/or management measures would be
implemented.
No further recommendations for mitigation and management to those
established by the findings of this qualitative assessment, and documented in
this SoEE report, are provided or warranted. BWS should however remain
aware of the potential for nuisance, or an unacceptable level of amenity, to
occur due to Project noise and continue to plan for and then manage Project
works accordingly.
4.7.6 Conclusion
Potential impacts associated with all construction and operational noise and
vibration aspects of the Project were qualitatively assessed. No impacts are
anticipated; however it is recommended that the acoustic enclosure is
implemented for operation of the flare unit as per the detailed design and
standard best practice mitigation and management measures outlined in
Section 4.7.5 are implemented to reduce noise and vibration levels associated
with construction as far as practicable.
The Project is therefore not anticipated to have significant adverse noise or
vibration impacts on nearby sensitive receptors and the environmental risk is
considered to be negligible.
4.8 TRAFFIC
4.8.1 Existing Environment
The existing local road network within the locality of the landfill site includes
Richmond Road which is a major road allowing passage to and from
Blacktown and is approximately 800 m directly east of the site. Richmond
Road and South Street form part of the arterial road network of the proposed
MPIP precinct and are predicted to have future (2036) traffic flows in the
range 40,000 - 90,000 vehicles per day.
Existing traffic sources include heavy vehicles delivering landfill material to
the site on a daily basis, and light and heavy vehicles accessing the nearby
commercial and industrial facilities.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
40
4.8.2 Assessment of Impact
The Project is only expected to generate approximately five heavy vehicle
movements for the delivery of the materials required for the installation of the
GCS and flare unit. During construction, there will be approximately two light
vehicles used by site personnel travelling to and from site daily. No vehicles
will be required for the operation of the Project, expect for any unplanned
maintenance activities.
It is anticipated that the minor traffic generated by the Project will be easily accommodated by the existing road network and will not result in any significant impacts to road users.
4.8.3 Environmental Mitigation
Given the limited potential for any traffic impacts to occur, no
recommendations for mitigation and management measures are warranted or
provided in this SoEE.
4.8.4 Conclusion
The Project may result in a minor increase in traffic during construction and
installation, however any local traffic impacts will be temporary. The Project is
therefore not anticipated to have significant adverse impacts on traffic and the
environmental risk is considered to be negligible.
4.9 WASTE AND MATERIALS MANAGEMENT
4.9.1 Background and Existing Environment
NSW OEH is responsible for initiating waste avoidance and resource recovery
strategies as a method of ensuring ecological sustainability.
The objectives of these schemes are to:
Minimise the consumption of natural resources;
Encourage resource recovery, including reuse, recycling and energy
recovery;
Provide for continual reduction in waste generation; and
Minimise the final disposal of waste.
The NSW Waste Management hierarchy will be incorporated into the waste
reduction and resource recovery strategies for the Project. The hierarchy is
formed on the principles: avoid, reuse, recycle/reprocess, and dispose.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
41
4.9.2 Assessment of Impact
Minimal waste is expected to be generated during the proposed works.
Existing waste contained within the landfill site is expected to be repositioned
during installation of the GCS, however no additional waste is expected to be
generated. Drilling waste will be taken to the active tip face and filled
immediately.
4.9.3 Environmental Mitigation Measures
Given the limited potential for waste generation, no recommendations for
mitigation and management measures are warranted or provided in this
SoEE.
4.9.4 Conclusion
Given the short-term nature of the proposed works and that limited quantities
of waste are anticipated to be generated, through the implementation of the
mitigation measures outlined in this assessment, the overall environmental
risk is considered to be negligible.
4.10 VISUAL AMENITY
4.10.1 Existing Environment
The existing visual environment at Marsden Park Landfill site can be
described as cleared and anthropogenic, with remnant patches of vegetation
located around the site office and small warehouse/storage shed, as shown in
Photograph 4.1, 4.2 and 4.3 below.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
42
Photograph 4.1 Site office and existing vegetation (to the right).
Photograph 4.2 Warehouse/storage shed
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
43
Photograph 4.3 View west towards the landfill mass from beside the warehouse/storage
shed
4.10.2 Assessment of Impact
The proposed installation and operation of the GCS and flare unit is not
expected to impact the visual amenity of any nearby potentially sensitive
receivers. The flare unit will be approximately 7 m high and located
approximately 100 m south-west of the site office, near the warehouse/storage
shed.
Photograph 4.4 was taken from the landfill site boundary near the site office
looking towards nearby residential properties, which exist approximately 850
m north-east of the flare unit. Photograph 4.5 was taken from the corner of
Hawthorne Avenue and Darling Street (close to the residential properties),
looking towards the landfill site.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
44
Photograph 4.4 View towards sensitive receivers north-east of the Marsden Park Landfill
site.
Photograph 4.5 View towards landfill site from the corner of Hawthorne Avenue and
Darling Street.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
45
The existing vegetation located at the site office and the warehouse/storage
shed, which will obscure views towards the flare unit, coupled with the lay of
the land and distance of nearby receivers, means no impacts to visual amenity
are anticipated. From some public viewpoints closer to the landfill site, such as
roads, the top of the flare unit may be visible, however it will blend in with the
existing working landfill site infrastructure and not impact visual amenity.
The top of the flare will be at approximately the same height as the
warehouse/storage shed. Given that the flare unit is enclosed, no flame will
be visible during daytime or night time operations.
Photograph 4.6 is taken in the direction of receivers which exist approximately
750 m southwest. Due to the extensive vegetative buffer completely obscuring
vision towards the landfill site (and in particular, the flare unit) and the
overall distance from the site, it is expected that impacts to visual amenity at
this location will also be negligible.
Photograph 4.6 Nearby sensitive receivers southwest of the Marsden Park Landfill site
(behind vegetation buffer within red rectangle).
4.10.3 Environmental Mitigation
Given the limited potential for any visual amenity impacts to occur, no
recommendations for mitigation and management measures are warranted or
provided in this SoEE.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
46
4.10.4 Conclusion
The Project is not anticipated to have significant adverse impacts on visual
amenity and the environmental risk is considered to be negligible.
4.11 HAZARD AND RISK
Hazards and risks are evident throughout all projects, and identifying them is
crucial in ensuring the health and safety of the community and the
surrounding environment. This section of the report identifies potential
hazards and risks associated with the proposed works and provides strategies
to assist in their reduction through effective post-construction monitoring and
maintenance activities.
Table 4.8 below outlines the expected hazards and risks associated with the
proposed works, and the potential controls which may be adapted in order to
overcome and manage them.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
47
Table 4.8 Summary of Project Hazards and Risks
Risk Potential Controls
Exposure to asbestos fibres
during construction, in
particular during excavation of
waste or drilling of wells.
Prepare and implement appropriate monitoring and
management procedures during construction.
Refer to site asbestos management plan provided in the
LEMP.
Exposure to chemicals such as
heavy metals, TPH, BTEX, PCBs
etc.
Develop plan to avoid exposure to chemicals.
Wear appropriate PPE.
Cover excavated material.
Landfill gas: fire or explosion
during construction.
Prepare and implement appropriate monitoring and
management procedures during construction, including
explosive limit monitoring.
Hot working permits to be implemented as required.
Prohibit smoking on site.
Landfill gas: fire, explosion or
exposure to landfill gas post-
construction.
Routine surface and subsurface gas monitoring.
Appropriate warning labels on all structures, such as head
walls, pipe outlets and leachate collection wells.
Hot working permits to be implemented as required.
Explosive limit monitoring.
A marker layer will be placed above buried pipes.
Interaction of construction
vehicles with other vehicles on
site (stockpiling and any other
works concurrently carried out
at the site).
Develop Traffic Management Plan.
Collapse of excavations and/or
vehicles sliding into excavation.
Excavation in waste always to be battered at no steeper than
2H:1V. Backfill excavations as soon as possible. Use fencing
where excavations have to remain open.
Striking services Contractor to do service search.
LDS to decommission services prior to construction.
Pipe welding: burns, landfill gas
fire.
PPE, landfill has monitoring.
Security of flare from
community during operations.
Flare to be fenced off. Final location will consider the risk
profile as a result of landscape layout and proximity to
community access.
Importing materials; road
accidents
Traffic management to consider the safest transport route.
Falls or accidents as a result of
working on steep slopes
Contractor to be made aware and to develop appropriate
work methodologies.
Slips, trips or falls during
operation and maintenance.
Vehicle accidents as part of
maintenance works.
Provide safe access to all locations requiring monitoring or
maintenance by staff.
Exposure of public to landfill
gas
Prevent access to landfill gas wells, valves and condensate
pumps by fencing or enclosure. Prevent access of public to
gas flare by fencing and co-locating flare within leachate
plant compound.
Securely lock landfill gas monitoring points.
Prepare management plan and communicate management
plan to future site users.
Differential settlement Annual survey of the top of cap levels to assess that
minimum gas pipe grades are met to ensure the drainage of
the collection network. Regular inspection of gas wellheads.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
48
Risk Potential Controls
Lateral migration of landfill gas
and accumulation in subsurface
service trenches, pits or
buildings.
Regular monitoring of perimeter landfill gas monitoring
wells to detect lateral subsurface gas migration from the
landfill.
Condensate accumulation and
pipe blockage.
The system is designed so that defective sections of the GCS
may be isolated. Additional pumping at condensate sumps
can be used to clear the system.
Striking of GCS system
pipework in post-construction
excavations.
Pipework below marker layer in capping system. Header
pipes covered with a pea-gravel layer.
Prepare management plan and communicate management
plan to future users.
Flare shutdown leading to
uncontrolled methane emissions
Slam shut and failsafe valves fitted throughout. Flare is
remotely monitored using telemetry and checked by a
qualified Technician at least once every two weeks. Gas
system pipework is air tight and rigorously pressure tested
at commissioning stage. Therefore will not leak methane
when shutdown.
4.11.1 Risk Mitigation
GCS Construction Quality Assurance
Construction will employ proven techniques to ensure a well-built system,
and a construction quality assurance (CQA) program shall be implemented to
make sure that the system is built in accordance with the required design
considerations (such as pipe slopes and well depths). Field engineering
decisions will need to be made in some instances to account for unforeseen
conditions at the time of construction.
Before construction begins, a professional surveyor shall stake out each well
and collection piping routes. The surveyed elevations and well identification
numbers shall be recorded (and assigned) and written on stakes positioned at
each well location.
A qualified CQA engineer/scientist shall be present during construction to
provide CQA to monitor and document the techniques used. Typically, the
first step in construction of a GCS is drilling the vertical wells. As the driller
gets set to drill each well, the designated CQA engineer/scientist shall verify
the elevation and depth of the well to avoid drilling through the base of the
landfill.
The CQA engineer/scientist shall keep accurate records of the pipe depth,
pipe location, and the location of special fittings such as tees that mark where
a lateral pipe is joined to the header. Other important structures such as
condensate traps or condensate sumps shall be documented on the as-built
drawings to include any deviations from the design plan.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
49
The flare supplier and CQA engineer/scientist will carry out operational
checks (refer to Table 4.9 below) prior to the Air Emission Contractor taking
samples (see following section).
Table 4.9 Summary of commissioning checks
Item Factors Involved Checks Comments
Flare
operational
Requirements
Flame/combustion
process
Yes Temperature, excess air and
retention time
Maintenance record Yes Available for inspection
Operations manual Yes Available for use
Operator training Yes Competent personnel on-call
General condition Yes Is the system fully operational?
Extraction
System
Well balancing Yes Effective balancing will be evident
from gas quality and site records.
Well balancing must be carried out
by technically competent and
trained staff
Oxygen content O2 at
acceptable
concentration
High O2 implies a leaking system or
over-extraction.
General condition Yes Is the system fully operational?
Liquid in gas
collection pipework
No Condensate blockages
characterised by a “sloshing”
sound and indicated by rapid
fluctuations in gas flow rate,
temperature and increasing
negative pressure
Site operational
requirements
Is the well
installation
programme
designed to control
migration
effectively?
Yes
Do the extraction
system and its
operation meet the
requirements of site
licence?
Yes Insufficient or poorly installed
wells may meet the letter, but not
the intention, of a licence
Are the operating
instructions
available for use by
the operators?
Yes
Is the emission
standard being
achieved
Yes Instrumental monitoring for
verification
Environmental
Compliance
Are there odours? No
Monitoring records
of inlet and outlet
gas quality
Available for inspection and up-to-
date, complete with regular written
reviews
Is the surrounding
radiative heat
excessive?
No
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
50
Item Factors Involved Checks Comments
Does the flame
temperature match
the specification?
Yes
Can the residence
time be ascertained?
No
Are there low-
temperature spots
within the
chamber?
Within the section designated as
meeting the design requirement
Is casual access by
the public
prevented?
Yes
Health and
Safety
Are clear
instructions on how
to stop and isolate
the unit readily
available?
Yes
Are emissions
monitoring
requirements being
complied with?
Yes
Is the type and
design of flare
suitable for the
location?
Yes
Are emergency
procedures in place
and effectively
disseminated and
understood?
Yes
Post-construction monitoring
The GCS and flare unit will operate on a continuous basis. Site conditions are
expected to change overtime and the rate of landfill collection will vary
temporally and across locations within the waste mass.
These changes will require periodic monitoring and adjustment of the vacuum
applied to each gas collection well to:
Maintain or increase collection efficiency;
Prevent excessive vacuum application;
Minimize the potential migration of landfill gas; and
Optimise flare combustion and potential shut-downs.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
51
Monitoring will detect undesirable subsurface combustion that can result if
excessive vacuum is applied to the wellfield (introducing oxygen into the
waste mass). Monitoring will be conducted at sufficient frequency to promote
optimal system operation and to allow for effective system maintenance.
System monitoring will involve examining landfill gas conditions at the
wellheads and the waste mass surface. Wellhead monitoring parameters shall
include:
Volumetric flow rate and vacuum
Methane, carbon dioxide oxygen, balance gas concentration (%v/v), carbon
monoxide and hydrogen sulphide.
Measurements of carbon monoxide and hydrogen sulphide will be recorded
to provide information about the potential for subsurface fires as well as the
corrosive potential of the landfill gas to subsurface materials.
Effective system operation will generally be expected to fall within the
following approximate monitored ranges:
Methane: 20 to 60 %v/v
Oxygen: up to 10 %v/v (depending on extraction effort)
Carbon monoxide and hydrogen sulphide: less than 100 ppm
Gas temperature: 30 to 60 degrees Celsius.
The blower will be continuously monitored for unusual noise, temperature or
excessive vibration. For sustained operation, the flare must receive landfill gas
flow of sufficient methane content before steady-state operation can be
attained.
Maintenance
Detailed documentation of scheduled maintenance and GCS management will
be included within the GCS Maintenance and Management Plan, and will
include a maintenance history of equipment and contain trouble shooting of
potential problems. The GCS operation will depend on effective maintenance,
which generally falls into the following categories:
Planned – Maintenance scheduled at periodic frequencies such as daily,
monthly, annual and multiyear as appropriate to prevent system failure,
ensure reliability of meters and optimize operation.
Routine – Maintenance occurring in the normal course of operation or
during regular monitoring efforts.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
52
Unplanned / Emergency – Not all maintenance is planned. Some
maintenance may be required by component failure or in emergencies. The
Site GCS Maintenance and Management Plan shall proactively consider
failures that will result in emergencies, plan maintenance to enact in these
events, and post signage to avoid compounding hazards resulting from
system failures. System or equipment failures shall be investigated to
determine causes and identify future preventative measures.
Planned maintenance of the flare system includes scheduled inspections of all
relevant components of the system to ensure safe, efficient and reliable
operation. Maintenance includes:
Visual inspection of the flare tips and flare stack for damage or
deterioration
Inspection of the exterior surface for indications of heat degradation, such
as paint discoloration
Monthly assessment of the overall integrity of the internal insulation. Tears
or wear of the insulation will be repaired if necessary
Removal of the flare tip for cleaning if an obstruction is suspected. This
includes measurement of the pressure differential between the flare inlet
flange and the flare tip exit, and cleaning of tips if necessary
Inspection of all thermocouple assemblies and replacement at least yearly
Quarterly inspection of the pilot assembly, ignition rod, electrode, and
insulators for damage, with repair or replacement if necessary
Verification of pilot gas supply pressure and pilot ignition
Inspection of the flame detection components and cleaning relevant
components
Verification of proper operation of the air damper louvers and lubrication if
necessary
Semi-annual removal and cleaning of the flame arrester element.
Measurement of the pressure differential across the element and cleaning, if
necessary
Monthly inspection of the condensate injection nozzles, including
confirmation of proper atomization and regular cleaning of nozzles.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
53
The maintenance technician is responsible for daily operations and
maintenance, and scheduled maintenance, such as greasing blowers. The
technician will have a copy of the flare operations manual and plans for
scheduled se vicing and maintenance, and will follow those instructions as
specified and required.
The flare unit is to be inspected regularly, as per the manufacturer’s
recommendations, to ensure that proper service and maintenance is
performed in order to maximize optimum performance. Spare parts are to be
kept on-site and made available should they be required. The manufacturer is
also available as a contingency measure for additional resources or
troubleshooting should they be required.
The GCS is subject to a variety of stresses from the site environment such as
system collapse caused by waste settlement, corrosion or aging of materials
(including ultraviolet degradation), and damage as a result of heavy
equipment coming into contact with the wells and piping. GCS maintenance
activities may include:
Repair or replacement of damaged wells and valves
Removal of leachate and condensate blockages
Re-grading or replacement of pipe affected by settlement of the waste mass
Replacement of components that have failed as a result of aging or fatigue.
Major repairs may require the temporary shutdown of the blower and flare
system. Blowers are subject to vibration, belt wear, bearing deterioration and
seal damage. Wear necessitates regular routine and scheduled maintenance as
well as particular attention to sounds during system start-up and shutdowns.
Flares are subject to thermal stress that can be exacerbated if the flare is
operated at temperatures or flows above manufacturer recommendations.
Maintenance generally involves inspecting the flare for heat damage,
maintaining pilot fuel and igniters, preventing condensate build-up and
checking the general mechanical condition.
4.11.2 Conclusion
There are a number of hazards and risks associated with the proposed works,
however with the correct implementation of the proposed management
measures and effective monitoring and maintenance, the overall risk is
considered negligible.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
54
4.12 CUMULATIVE IMPACTS
Cumulative impacts are an additional way in which a specific environmental
aspect may be affected by a new project or another development. Cumulative
impacts have two key characteristics:
they occur over a geographical area; and
they occur over time.
Potential cumulative traffic generation impacts associated with nearby
facilities, warehouses and commercial premises are unlikely, as the
cumulative traffic will be accommodated by the existing road network and an
appropriate level of service maintained.
The Project is anticipated to span over approximately three weeks and will
only involve the installation and operation of the GCS and flare unit. Due to
the short duration and negligible anticipated environmental impacts, it is
considered unlikely that the Project will result in any significant cumulative
impacts.
Additionally, due to the reduction in the emission of GHG as a result of the
Project, the overall environmental impact is expected to be positive.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
55
5 SECTION 79C CONSIDERATIONS
Section 79C of the EP&A Act requires the consent authority to take into
consideration a range of matters when undertaking an assessment of a DA.
These are detailed in Table 5.1
Table 5.1 Section 79C Considerations
Section 79C Requirements Comment
(a)(i) any environmental planning
instrument
The Project is consistent with the requirements of
relevant environmental planning instruments as
detailed in Section 3.
(a)(ii) any proposed instrument that is or
has been the subject of public consultation
under this Act and that has been notified
to the consent authority (unless the
Secretary has notified the consent
authority that the making of the proposed
instrument has been deferred indefinitely
or has not been approved)
N/A
(a)(iii) any development control plan The Project is consistent with the general
development objectives and controls of the
Blacktown City Council Development Control
Plan 2016.
(a)(iv) any planning agreement that has
been entered into under section 93F, or any
draft planning agreement that a developer
has offered to enter into under section 93F,
N/A
(a)(v) the regulations (to the extent that
they prescribe matters for the purposes of
this paragraph)
N/A
(a)(vi) any coastal zone management plan N/A
(b) the likely impacts of that development,
including environmental impacts on both
the natural and built environments, and
social and economic impacts in the locality
The likely impacts of the development have been
assessed in Section 4.
(c) the suitability of the site for the
development
The Project is permissible with development
consent under State Environmental Planning
Policy (Sydney Region Growth Centres) 2006 -
Marsden Park Industrial Precinct Plan 2010 and
will not impact on the surrounding
industrial/commercial facilities.
(d) any submissions made in accordance
with this Act or the regulations,
Council is to take into consideration any
submission required as part of the notification
process.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA 0430664/FINAL/12 JUNE 2018
56
Section 79C Requirements Comment
(e) the public interest The proposed works will provide the following
benefits:
Removal of potentially hazardous landfill
gases resulting in reduced health and safety
risks to nearby residents and community;
The removal of methane during gas collection
and flaring will reduce GHG emissions from
the site, which makes the Project eligible
under the ERF enabling the offsetting of fossil
fuel, which in turn results in a beneficial
environmental outcome and positive impact;
and
The Project will contribute to the future
rehabilitation and redevelopment of the
landfill site. The Project will assist in
achieving the final land use goal of ‘low
density industrial use’, which will support the
local community by providing jobs and
services, and in turn increasing cash flow
throughout the community.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA PTY LTD 0430664/FINAL/12 JUNE 2018
57
6 CONCLUSION
This SoEE has been prepared to assess the environmental impacts associated
with proposed installation and operation of an active GCS and enclosed
ground flare unit. The SoEE provides a review all relevant legislation and
policy and finds that the fundamental issues to consider in determining the
DA are potential noise and air quality impacts.
The main noise source is associated with the operation of the flare unit which
is not anticipated to generate high noise levels. In order to attenuate
anticipated noise emissions, the flare unit will be fitted with an acoustic
enclosure and strategically located behind existing site infrastructure and
vegetation to obscure the direct line of sight towards potentially affected
receivers. Regular maintenance, testing and monitoring will be undertaken to
ensure regulatory compliance. The Project is not anticipated to have adverse
noise impacts on nearby sensitive receptors.
With regards to potential air quality impacts, the flare unit will utilise the
latest technology to meet present and near future emissions standards.
Pollutant emission limits required by the Protection of the Environment
Operations (Clean Air Regulation) 2010 will not be exceeded during operation of
the flare unit. Emission compliance testing and monitoring will be undertaken
by a NATA accredited Contractor.
It is in the public interest to install and operate the GCS and flare unit, as it
will assist in the:
Reduction of GHG emissions reducing the effects of global warming
Reduction of the potential for dispersion of odorous and potentially
harmful landfill gases to nearby sensitive receivers; and
Achievement of the final land use goal of ‘low density industrial use’,
which will help stimulate economic growth within the local community by
providing jobs to community members.
The SoEE has given consideration to all relevant legislation and policies, and
has conducted an assessment of potential environmental impacts. It concludes
that the Project and its associated potential environmental impacts are
unlikely to have a negative impact on the environment and all minor risks and
impacts can be effectively managed through the implementation of mitigation
measures during proposed works and during the long-term operation of the
project.
Additionally, the reduction in GHG emissions as a result of the operation of
Project means the overall environmental impact is considered positive, and
such works are considered viable for the Emissions Reduction Fund (subject to
approval by the Clean Energy Regulator). Other positive benefits include the
significantly reduced risk of sub-surface migration of landfill gas and potential
for airborne odour at surrounding receivers.
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA PTY LTD 0430664/FINAL/12 JUNE 2018
58
7 REFERENCES
British Standard (1992). BS 6472–1992) – Evaluation of Human Exposure to
Vibration in Buildings (1 Hz to 80 Hz).
British Standard (1993). BS7385: Part 2-1993 (BS 7385) - Evaluation and
Measurement for Vibration in Buildings — Part 2 – Guide to Damage Levels from
Ground-borne Vibration.
Clean Energy Regulator (2017) – Participate in the Emissions Reduction Fund
Commonwealth Department of the Environment and Energy (2013). Protected
Matters Search Tool - Environment Protection and Biodiversity Conservation Act
1999.
Department of Land and Water Conservation (2001) Soil Landscapes of the
Penrith 1:100 000 Sheet.
Department of Primary Industries (DPI) (undated) Key Fish Habitat in the
Blacktown LGA.
Department of the Environment and Energy (2017). Emissions Reduction Fund
Information Page.
http://www.environment.gov.au/climate-change/government/emissions-reduction-
fund/about
German Standard (1999). DIN4150 Part 3-1999 (DIN4150-3) – Structural
Vibration - Effects of Vibration on Structures.
Landcom (2004) Managing Urban Stormwater: Soils and Construction – Volume 1.
NSW Department of Environment and Climate Change (DECC) (2006).
Assessing Vibration: A Technical Guideline.
NSW DECC (2009) NSW Interim Construction Noise Guideline (ICNG).
NSW DECCW (2011) NSW Road Noise Policy.
NSW Environment Protection Authority (EPA) (2017). NSW Environmental
Noise Management – Noise Policy for Industry and relevant application notes.
NSW EPA (2014) Waste Classification Guidelines.
Annex A
Flare Emission Testing Report
ATTACHMENT 3: FLARE EMISSION TESTING REPORT
ERM has over 100 officesacross the followingcountries worldwide
Australia
Argentina
Belgium
Brazil
China
France
Germany
Hong Kong
Hungary
India
Indonesia
Ireland
Italy
Japan
Korea
Malaysia
Mexico
Netherlands
New Zealand
Peru
Poland
Portugal
Puerto Rico
Singapore
Spain
Sri Lanka
Sweden
Taiwan
Thailand
UK
USA
Venezuela
Vietnam
Environmental Resources Management
Level 15 309 Kent StreetSydney NSW 2000Locked Bag3012,
Australia Square NSW 1215
T: 61 2 8584 8888F: 61 2 8584 8800www.erm.com