mikhail kubantsev - kansas state university 1 assembly of a large area microstrip silicon tracker...
TRANSCRIPT
Mikhail Kubantsev - Kansas State University
1
Assembly of a Large Area
Microstrip Silicon Tracker
Assembly of a Large Area
Microstrip Silicon Tracker
Some Experience of Construction of D0 SMT
H-disk Silicon Detectors March 16 2000
Mikhail Kubantsev - Kansas State University
2
OutlineOutline
Introduction: Overall Design Detectors Mechanical Tolerances Electronics Thermal Conditions
Mechanical assembly of modules (half wedges)
Testing and diagnostics of modules
Construction of full wedges and disks
Perspectives and conclusion
Mikhail Kubantsev - Kansas State University
3
Experiment D0 Experiment D0
Silicon MicrostripTracker
Scintillating fiber tracker
Mikhail Kubantsev - Kansas State University
4
SMT made of Barrels and Disks
Ladders make up Barrels
Wedges make up Disks
SMT made of Barrels and Disks
Ladders make up Barrels
Wedges make up Disks
F-DISKS
H-DISKS
BARRELS
Mikhail Kubantsev - Kansas State University
5
Silicon SensorsSilicon Sensors
Double and single sided detectors for barrels Double sided for F-disks Single sided for H-disks glued back to back Total of 147,000 readout channels on 1.26
square meters of silicon detectors are to be assembled as H-disks
Mikhail Kubantsev - Kansas State University
6
SMT ReadoutSMT Readout
Basic element is a SVX-IIE chip with 128 channels of 8-bit ADC, sparsification, , buffers, and output drivers
The SVX chips are installed on the High Density Interconnect (HDI) flex circuit laminated on the berullium substrate
Digital information is passed to readout sequencers and via optical links to VRB’s and to computers
Mikhail Kubantsev - Kansas State University
7
Temperature Control
Temperature Control
The readout generate a substantial amount of heat ( about 3.8 watts/HDI) or 185 watts for one H-disk
The cooling channels made of beryllium will support the structure and provide cooling
Temperature of silicon detectors should be close to 0oC so they have to be in dry atmosphere (nitrogen gas)
Mixture of water and ethylene glycol is used as a coolant at temperature of -10oC
Mikhail Kubantsev - Kansas State University
8
Track Measurements
by H-disks
Track Measurements
by H-disks H-disk subsystem is a tracking device
and not a vertex detector measuring tracks in rapidity interval 2.2 -3.0. Particle momentum is measured in r- plane (magnetic field is normal to the disk) .
Detector position accuracy of 10 - 15 is expected
The track momentum is measured by combination of barrel ladders (vertex position), F-disks and H-disks.
Mikhail Kubantsev - Kansas State University
9
H-disk TolerancesH-disk Tolerances
Numerical estimations and detailed Monte-Carlo studies showed that tolerances in r- plane should be better then 25 and few hundreds along the beam direction.
Intrinsic H-disk precision:
Mikhail Kubantsev - Kansas State University
10
Structure of the H-diskStructure of the H-disk
H-disk shroud
Beryllium cooling channel
Scintillating fiber tracker
barrel
24 wedges installed on the cooling channel
Mikhail Kubantsev - Kansas State University
11
Half Wedge -Basic Module of
the H-disk
Half Wedge -Basic Module of
the H-disk
Outer silicon sensor
(under Be substrateand HDI)
Inner silicon sensor
Be substrate
HDI
65 cm2 areaof silicon
Mikhail Kubantsev - Kansas State University
12
H-disk Production Team
H-disk Production Team
Kansas State - Moscow State - Fermilab team: M.Kubantsev(team leader) KSU E.Shabalina MoSU M.Merkin MoSU D.Karmanov MoSU G.Derylo Fermilab G.Sellberg Fermilab S.Jakubovski Fermilab N.Ronzhina Fermilab
Mikhail Kubantsev - Kansas State University
13
H-disk Design and Production Philosophy
H-disk Design and Production Philosophy
Vigilance on production since silicon is not permissive: clean room environment
With alignment at when two half wedges are stuck together
With alignment at when 24 wedges are put on the large cooling ring
Puts problems:
- Use single-sided sensors- Define required precision of assembly.- Develop assembly procedures - Make a pre-production batch of modules- Full scale production of modules- Make two half wedges and stick them together -Put 24 wedges on the cooling ring with high precision
Mikhail Kubantsev - Kansas State University
14
Major Production
Steps
Major Production
Steps Obtain and test sensors HDI fabrication: flex by
Compunetics,lamination by Fermilab, stuffing by Promex/Silitronics, testing by CSUF/KSU/KU/Fermilab
Here is our starting point:
silicon, beryllium,flex circuit
Mikhail Kubantsev - Kansas State University
15
Major Production Steps
(Continue)
Major Production Steps
(Continue) Half wedge assembly Half wedge testing Full wedge assembly Ring Assembly Wedges mounted on Rings Over test of the rings Installation and commission at
the D0 detector
Mikhail Kubantsev - Kansas State University
16
H-disk Si SensorsH-disk Si Sensors
H-Wedges have inner and outer sensors that are made by ELMA(Russian) and Moscow State University with 4” technology.
Silicon detectors have 40 pitch, 80 readout pitch
About 500 are here, tested and more than a half assembled in the (half)wedges but we will need 60 detectors more to be delivered late spring.
Outer silicon detector control measurement on the coordinate measuring machine
Mikhail Kubantsev - Kansas State University
17
HDI-Beryllium Lamination
HDI-Beryllium Lamination
Set up 2 sandwiches of parts on the special fixture: the bare HDI, epoxy glue film, Be substrate, conductive
epoxy glue
Mikhail Kubantsev - Kansas State University
18
Lamination (continue) Lamination (continue)
Put the sandwiches in the oven and bake them with a special compressed air press (shown below) using accurately determined temperature and pressure cycles (it took two months to determine it!)
Can make 4 HDI laminations per day
Mikhail Kubantsev - Kansas State University
19
HDI Stuffing HDI Stuffing
Insufficient parts throughput
Bubbling in surface mount stage at Promex
Wire bonding pull strength problems
Low efficiency of production
Find more then one vendor
Bake out to remove moisture from kapton
Plasma cleaning after parts surface mount
Work with company on testing
Problem Resolution
Product - a stuffed HDI:Present yield - 80%
Mikhail Kubantsev - Kansas State University
20
Module - Half Wedge Assembly
Module - Half Wedge Assembly
The fully tested HDI on Be substrate is glued with an outer silicon sensor and a supporting beryllium plate
3M adhesive film is used to reduce mechanical stress on silicon to speed up production from 24 hours to 2-3 hours to make one glue joint
Working on gluing procedure
Mikhail Kubantsev - Kansas State University
21
Assembly of Half Wedge
(Continue)
Assembly of Half Wedge
(Continue) The assembly is made on precision
fixtures with accuracy of 50 The inner detector is attached to
the outer detector with high accuracy 2-5 with special fixture using CMM OMIS.
Mikhail Kubantsev - Kansas State University
22
Wire Bonding of the Half WedgesWire Bonding of the Half Wedges
Wire bonding on the hybrid flex circuits is made by vendors (Promex, Silitronics)
Bonding of the SVX chips to pitch adapter,pitch adapter to outer detector and outer to inner detector is made on high speed bonding machines 8090.
Over 2000 bonds per half wedge are made in less than 30 minutes
SVX chip wire bonding to the flex circuit
Mikhail Kubantsev - Kansas State University
23
Encapsulation of Wire Bonds
Encapsulation of Wire Bonds
Encapsulation of wire bonds on the fully tested half wedges is made
with the computer controlled motorized table watched by two
TV cameras .
Mikhail Kubantsev - Kansas State University
24
Encapsulation (continue)
Encapsulation (continue)
Special combination of 2 materials with different viscosity is used to encapsulate dense wire bonds on the detector-pitch adapter connection.
Encapsulation is cured with ultra violet
light lamp
TV image of encapsulation process:
top and side(insert) views
Mikhail Kubantsev - Kansas State University
25
HDI/Wedge Testing:
Functional Test
HDI/Wedge Testing:
Functional Test HDI and Wedge/Ladder functional tests
are made with 4 available two-channel test stands.
The test is done after every step of assembly and includes: pedestal and noise measurements calibration charge inject silicon detector dark current
Mikhail Kubantsev - Kansas State University
26
HDI/Wedge Testing: Burn-
in Test
HDI/Wedge Testing: Burn-
in Test HDI, ladders and wedges burn-in is done
with 2 16-channel test stands. The devices are tested at low temperature (about 5oC) for up to 72 hours.
SVX gains, noise, pedestals, sparse mode and silicon detector dark current are
tested.
Mikhail Kubantsev - Kansas State University
27
Wedge Testing: Laser Test
Wedge Testing: Laser Test
HCB-126 Active Region 3/14/00
-20
0
20
40
60
80
100
120
140
160
0 128 256 384 512 640 768
Channel
Am
pli
tud
e -
Baseli
ne
0.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
Std
ev
Avg, w/o Ped
Stdev
2 infrared laser stands are used for final certification of the devices. Over 10 units per day
can be tested. Number of dead channels, detector depletion voltage, noise level are determined
Mikhail Kubantsev - Kansas State University
28
Test stands (continue)Test stands (continue)
10% system test stand is used for final system evaluation (cosmic ray test, barrel/disk tests)
Mikhail Kubantsev - Kansas State University
29
Diagnostics and Repair
Diagnostics and Repair
Diagnosis of problems with HDIs and detector assemblies is a major concern. Several microscopes, probe stations and logic analyzers are in use
Repairs of found faults: SVX chip replacement, wire bonding and pulling, flex circuits traces defects are made by a team of skilled technicians.
Mikhail Kubantsev - Kansas State University
30
Assembly of Full Wedge
Assembly of Full Wedge
Full wedge is made of two half wedges glued together. It is a double sided device with a stereo angle of 15 degrees.
Assembly made on a bi-facial machine with two microscopes.Typical accuracy 5 -10 . Up two wedges per day can be made.
Upper microscope
Lower Microscope
Assembled wedge
Mikhail Kubantsev - Kansas State University
31
Scheme of By-Facial Machine
Scheme of By-Facial Machine
Upper camera
Lower Camera
Accurate alignment of two cameras in angle and X-Y positions required
Mikhail Kubantsev - Kansas State University
32
Full wedge assembly
Full wedge assembly
Assembled full wedge on the flipping fixture ready for control measurements
Mikhail Kubantsev - Kansas State University
33
Ring AssemblyRing Assembly
This a prototype ring with mockup wedges and carbon fiber shroud
ring to hold HDIs tails and connectors with cables
Mikhail Kubantsev - Kansas State University
34
Ring Assembly (continued)
Ring Assembly (continued)
H-DISK beryllium cooling channels are assembled and leak tested
Mikhail Kubantsev - Kansas State University
35
H-disk AssemblyH-disk Assembly
Wedges are assembled on the cooling channel with a Coordinate-Measuring Machine (CMM) Zeiss-500. Thermal grease is applied for good contact between the cooling channel and wedges. Assembly accuracy is better that 10 .
Mikhail Kubantsev - Kansas State University
36
Production YieldsProduction Yields
Step Made Accepted Percent Silicon detectors1200 480 40 HDI assembly 210 157 75
Module assembly 150 120 80 Disk assembly 90 ?
Initial silicon/final device 100/30
Initial flex/final device 100/50
Mikhail Kubantsev - Kansas State University
37
H-disk Assembly Status:
H-disk Assembly Status:
125 grade A (<3% dead channels) and 17 grade B (3-10% dead channels ) devices (half wedges) are produced ( 75%) Note: average D0 SMT module production is about 50%.
Yield of grade A devices made during production period started in October 99 is about 90%
Full wedges are under assembly and 11 devices are ready
Disk assembly has started, first one is due in April
Goal: finish H-disk construction by fall 2000
Mikhail Kubantsev - Kansas State University
38
H Disk Status(in detail)H Disk Status(in detail)
Sensors OK except order of 15% (60 sensors) should be delivered before June
HDIs (192 needed) 218 laminated 162 stuffed (80%
yield) Half-Wedges (192 needed)
156 built including 11 mechanical grade ones 145 electrical grade wedges assembled: 84 were tested: 67(80%) graded as grade A (less then 3% of bad channels) 17(20%) grated as grade B
Full-Wedge(96 needed) 8 electrical and 4 mechanical built
Beryllium cooling rings (4 needed) all four fully manufactured, tested and ready for assembly
Assembly of the first mechanical H-disk ring has started with mechanical wedges
Mikhail Kubantsev - Kansas State University
39
HDI (High Density Interconnect) - Hybrid circuit Fabrication and Testing
HDI (High Density Interconnect) - Hybrid circuit Fabrication and Testing
Order bare flex circuit boards and probe them for shorts and discontinues (CSUF) - DONE
Lamination on beryllium substrates (FNAL) - 75% DONE
Surface Mount, die attach, wire bond chips to HDI substrate (Promex,Silitronics) - 65% DONE
Functional Tests Run (CSUF, KU, KSU, FNAL)- 65% DONE
Burn-in Tests(FNAL) - 65% DONE Repair and Rework - CAN BE FINISHED
AS THE DETECTOR COMPLETED!
Mikhail Kubantsev - Kansas State University
40
Production MilestonesProduction Milestones
10/15/99 - H- half wedge fab 20% complete - DONE
2/23/00 - H- half wedge fab 80% complete - DONE
4/10/00 -first H-disk assembled
10/2/00- H-disks ready to be installed
These are only production milestones,
we have to have working detector.
Mikhail Kubantsev - Kansas State University
41
Characteristics of Assembled
Devices
Characteristics of Assembled
DevicesDistribution of number of dead channels for H-disk half wedges after bond pulling and tests.
0
2
4
6
8
10
12
14
16
18
20
3 6 9 12 15 18 21 24 27 30 33 40 50
Number of dead channels
Qu
ant.
Of
HW
edg
es
3 HWs52 HWs
A-grade(Nd<3%)B-grade(3<Nd<6%)
Mikhail Kubantsev - Kansas State University
42
H-disk Production Yields
H-disk Production Yields
HW production and testing summary:(except results of production and testing before October 99.)
Status HEA HEB HCA HCB Total Total were
assembled
Grade A 15 7 18 19 59Grade B 2 1 3 1 7 C@M 1 0 2 0 3
1/4Ws 0 0 0 0 0HWs fun-test 0 0 0 0 0HW burn-in 9 16 14 11 50HWs repair 0 0 0 0 0HWs laser 1 4 3 3 11
All: A@notest 25 27 35 33 120Yield:(A + 0.95*notest)/all 0.88 0.93 0.85 0.95 0.90 130
Mikhail Kubantsev - Kansas State University
43
Conclusions and Perspectives
Conclusions and Perspectives
The H-disk construction is on track.
The assembly, installation and commissioning at D0 will be completed in the end of the year.
The developed techniques can be used for the proposed D0 upgrade (Layer 1,2) to assemble two singe sided radiation hard silicon sensors
Acquired experience will be useful for future work on large area silicon trackers for B-TEV and CMS.
Mikhail Kubantsev - Kansas State University
44
Perspectives:Perspectives:
use new type of adhesive (re-workable, thermo- ( if needed electrical-) conductive 3M film for large area detector assembly
use bi-facial machine to make double sided silicon assembly with single sided detectors with high precision
use high depletion voltage devices with over depletion up to 150 volts at low temperature below 0o C)