Objective ATC 12

ESSIP Plan 2014

Luca DELL’ORTODSS/EIPR

19.09.2014

Page 2: Objective ATC 12 ESSIP Plan 2014 Luca DELL’ORTO DSS/EIPR 19.09.2014

2

Comprehensive Explanation (1/2)

Implementation of Medium Term Conflict Detection (MTCD) and MONitoring Aids (MONA) functionalities. MTCD is an ATC tool which checks the system trajectories (Flight plan

enhanced with surveillance data) and identifies the potential conflict. This function requires an appropriate presentation of detected conflict to the planning/tactical controller.

MONA is a conformance monitoring functionality including lateral, longitudinal and vertical conformance as well as progress monitoring.

Some functions, like longitudinal and lateral conformance plus progress monitoring, are widely implemented in ECAC area.

Additional flight conformance monitoring functions as: vertical conformance, CFL conformance, potential co-ordination failure, SSR code conformance, potential level bust are implemented by a limited number of ATM systems.

Automatic reminders (i.e. those that include controller reminders for next sector transfer, co-ordination reminders and maneuvering clearance) are not widely implemented.

ESSIP Plan 2014 / Objective ATC12

Page 3: Objective ATC 12 ESSIP Plan 2014 Luca DELL’ORTO DSS/EIPR 19.09.2014

3

Comprehensive Explanation (2/2)

Scope: ECAC Applicability Area: in en-route airspace of AL / AM / AT / AZ / BA / BE / BG / CH /

CY / CZ / DE / DK / EE / ES / FI / FR / GE / GR / HR / HU / IE / IT / LT / LU / LV / MAS / MD / ME / MK / MT / NL / NO / PL / PT / RO / RS / SE / SI / SK / TR / UA / UK

Requirement: Implement and make operational use of ground based automated ATC support tool for conflict detection and conformance monitoring.

ESSIP Plan 2014 / Objective ATC12

Page 4: Objective ATC 12 ESSIP Plan 2014 Luca DELL’ORTO DSS/EIPR 19.09.2014

4

What is new or has changed for ESSIP Plan ed. 2014

SLoA REG01 on safety oversight removed (general action across all ESSIP objectives in the ESSIP Plan ed. 2014);

‘Supporting material’ list extended (see full list in the last slide)

ESSIP Plan 2014 / Objective ATC12

Page 5: Objective ATC 12 ESSIP Plan 2014 Luca DELL’ORTO DSS/EIPR 19.09.2014

5

Link to European ATM Master Plan and/or Interim Deployment Programme (IDP)

Eur. ATM Master Plan: [CM-0202] - Automated Assistance to ATC Planning for Preventing

Conflicts in En Route Airspace [CM-0203] - Automated Flight Conformance Monitoring

IDP: None

ESSIP Plan 2014 / Objective ATC12

Page 6: Objective ATC 12 ESSIP Plan 2014 Luca DELL’ORTO DSS/EIPR 19.09.2014

6

Most important SLoA(s)

ASP01 – ‘Implement MTCD function’ ASP03 – ‘Develop safety assessment for the changes’

ESSIP Plan 2014 / Objective ATC12

Page 7: Objective ATC 12 ESSIP Plan 2014 Luca DELL’ORTO DSS/EIPR 19.09.2014

7

Finalisation Criteria and Closed Questions

ASP01 – MTCD and conformance monitoring are implemented, documented and in operational use.

ASP03 – The Safety assessment report including safety arguments for the changes has been delivered to the NSA and a notification of acceptance was received. MTCD and MONA implemented? Safety assessment done and accepted by NSA? Notification of acceptance received from NSA?

ESSIP Plan 2014 / Objective ATC12

Page 8: Objective ATC 12 ESSIP Plan 2014 Luca DELL’ORTO DSS/EIPR 19.09.2014

8

Supporting Material

EUROCONTROL Specification for Medium-Term Conflict Detection, Ed 1.0 of 15/07/2010; EUROCONTROL-SPEC- 0139

EUROCONTROL Specification for Monitoring Aids, Ed 1.0 of 15/07/2010; EUROCONTROL-SPEC-0142

EUROCONTROL Specification for Trajectory Prediction, Ed 1.0 of 15/07/2010; EUROCONTROL-SPEC-0143

EUROCONTROL: Completing the FASTI Safety Case: Guidance for Service Providers-Edition 1.0-11/2008

EUROCONTROL - Good Practice Guidelines for First ATC Support Tools Implementation (FASTI) with a Focus on Human Factors and Managing the Transition - Edition 1.0 / 06/2007 

EUROCONTROL: FASTI Operational Performance Requirements Analysis for the Conflict Detection Tool  2nd Edition 2012

EUROCONTROL: FASTI ATC Manual - Guidelines for FASTI Tools Implementation 2009 

EUROCONTROL : FASTI Specific Human Factors Guidelines for MTCD, MONA and SYSCO 2007

ESSIP Plan 2014 / Objective ATC12

Page 9: Objective ATC 12 ESSIP Plan 2014 Luca DELL’ORTO DSS/EIPR 19.09.2014

9

ESSIP Report 2013

Progress mostly on schedule. 16 States have declared it Completed, another 5 as Partially

Completed and 16 with plans for completion by FOC date (12/2016) at the latest.

ESSIP Plan 2014 / Objective ATC12

Page 10: Objective ATC 12 ESSIP Plan 2014 Luca DELL’ORTO DSS/EIPR 19.09.2014

10

Links and contacts

Objective Coordinator: Dell’Orto Luca, +32 2 729 3325

[email protected]

EUROCONTROL Objective Expert:

Predrag Terzioski, +32 2 729 3347

[email protected]

ESSIP Plan 2014 / Objective ATC12