of a bespoke passive dewatering system which used deep
TRANSCRIPT
Background The Crag End Landslip project comprises the reconstruction of a 300m section of road near
Rothbury, for Northumberland County Council (NCC). The B6344 was closed in December
2012 following multiple landslips, causing dramatic socio-economic impacts and a major
inconvenience to residents.
This project follows a history of slope stability problems spanning several decades, with the
most recent failure triggered by one of the wettest periods on record. The 2012 landslips
caused part of an existing 90m length anchored sheet pile retaining wall to fail, initiating
significant cracking along the carriageway and distortion of the wall capping beam. In addition,
other sections of the road collapsed and slipped down slope over the 300m stretch.
NCC’s key requirements were to:
Open the road at the earliest opportunity: the road closure has had a dramatic social and economic effect on Rothbury.
Provide a robust solution within the available funding and requiring minimal maintenance: NCC requires a high quality structure.
Enhance the SSSI: the River Coquet is at the toe of the slope and the majority of the site is within a SSSI.
In order to achieve these aims and to solve such a complex geotechnical problem it was
essential that a multidiscipline team was mobilised that could work in together from start to
finish of the project.
NCC appointed VBA (a joint venture comprising VolkerStevin, Boskalis Westminster and
Atkins) was appointed as ECI contractor and subsequently for the construction phase of works.
The VBA team also included the design team of geologists, hydro geologists, geotechnical and
structural and highway engineers all essential for this project. Keller were appointed as the
specialist foundation contractors who were involved early in the ECI process to ensure
constructability. Other team members included ecologists, GI contractors and dewatering
contractors.
Geotechnical investigation and back analysis at ECI revealed a complex geological stratigraphy
and slope instability within shallow superficial deposits and that artesian groundwater in the
underlying Fell Sandstone was a key driving mechanism. Following an extensive value
engineering process involving the full project teams, the proposed solution was a combination
of a bespoke passive dewatering system which used deep wells to lower artesian
pressures and a new anchored bored pile retaining wall, a section of which has been
constructed behind the existing wall, to support the road in the event of potential slips
downslope of the road.
Technical engineering excellence and ingenuity
On site testing and extensive modelling to produce an efficient and reliable
design: During ECI, to gain an understanding of the local geology and hydrology,
downhole CCTV and geophysical testing as well as substantial field work was
planned by the geotechnical team and undertaken to produce 3D models which
were the basis of our design. Groundwater was identified as the major cause of
instability and extensive hydrogeological modelling was undertaken to understand
the groundwater regime and to predict its response to the proposed dewatering
scheme. Results from pumping trials were used for calibration. Sensitivity models
and studies were performed to assess the impact of varying permeability and
rainfall intensities.
Developing an innovative passive dewatering system to reduce groundwater
pressure: The initial slope drainage proposal was for an extensive counterfort system
which would have significant ecological, cost and programme implications. Following
extensive modelling and VE between the design teams de-watering was achieved
using a system of deep wells supplemented with minor modifications to existing
surface water features. The deep well solution required minimal import and export of
materials compared to counterfort drains and minimised impacts on the protected
SSSI environment. The wells work under gravity without a requirement for pumps,
minimising on-going maintenance - an important issue for NCC.
Innovative Ground Investigation (left) – managing the artesian water pressure and avoiding unplanned discharge into the river required forward planning using 4m of elevated borehole casing.
Passive dewatering system – two rows of dewatering well installed on the slope.
Crag End Land Slip Award Submission
British Geotechnical Association Fleming Award 2016
Buildability assessments: Due to restricted access constructability had a huge influence on
the wall design and due to unfavorable conditions; i.e. potential loss of ground on the passive
side, and the high active pressures associated with unstable sloping ground, the anchored
retaining wall required to withstand high bending moments.
Usually, large diameter piles would be needed to accommodate the steel required to resist
the high bending moments, however using the heavy plant could have potentially triggered
further landslides. Following meetings with the VBA construction and design team and Keller,
it was proposed to adopt small diameter (450mm) piles, reinforced with recycled high strength
circular hollow section tubes (API tubes) to provide the required moment resistance and
facilitate the use of 10 tonne piling rigs and a specialist overburden drilling system.
Klemm 709-2 (case and auger)
The requirement to construct part of the new wall close to the rear of the existing failed wall
added further complexity. To avoid existing ground anchors, the new piles could not be
constructed in the usual contiguous arrangement. Since the exact alignment of the anchor
tendons below ground was unknown, the anchors were exposed close to the capping beam
to get an indication of their alignment and thus determine a safe zone for piling. Generally a
series of triangular groups fitted into each safe zone was used but was modified to suit the
actual conditions. Owing to this pile configuration, additional retaining wall analysis
techniques were adopted and the wall also assessed using first-principles engineering analysis,
considering the provision of moment restraint at pile head to determine the worst case
combination of the newly induced axial loads and bending stresses.
Savings through value engineering of piling and design solutions: The construction and
design team worked closely together day to day on site in order to provide rapid value
engineering solutions to the ever changing site and ground conditions. For example the
retaining wall design required all piles to have a 3m socket into sandstone bedrock. Since the
exact rock-head level was not known and varied significantly, this was verified on site by the
designer and piling contractor during pile installation and fed back into the analysis. This was
essential owing to the risk of encountering large boulders within the superficial deposits and
the potentially serious consequences of founding a section of wall within a boulder rather than
in bedrock. In some areas this led to both piles and anchor free lengths being shortened, saving
NCC money and accelerating the construction programme while maintaining a robust design.
Sustainability and environmental merits
The presence of the SSSI over much of the site required careful management of
environmental and ecological issues: VBA worked closely with Natural England,
National Trust, Environment Agency and NCC’s ecological consultant (EcoNorth)
throughout design and construction to ensure minimal impact on the SSSI. High
environmental standards were maintained throughout the works for example by using
a Siltbuster® water treatment unit and Terra Firma Dura- base © matting to provide
safe access across the lower slopes. In total, 11 bird boxes, an owl box, an otter holt
and two bat boxes have been installed to encourage wildlife to the area.
Incorporating minimum maintenance and encouraging natural regeneration: The
passive dewatering system was designed to require no long term energy usage once
operational and to discharge to the natural wetlands by the river. Care was taken to
ensure the lower slope can be returned to its original use as wood pasture for example
by providing cattle crossing locations across drainage channels and reinstating
grasslands through natural regeneration and using a wild, local provenance seed mix,
as well as Oak tree planting to replace/enhance the sites veteran trees that have died
or are in very poor condition due to waterlogging.
Approach to safety
No reportable accidents with over 88,000 hours worked: Safety challenges
overcome included difficult topographic and ground conditions, restricted working
areas and complex site logistics. Well organised plant and people zones were created
during ECI, by designing an innovative and bespoke temporary scaffolding walkway
along the 350m length of the site to allow safe access for our operatives. This solution
eliminated the risk of plant/people interface and enabled the safe operation of up to
seven piling rigs working simultaneously along the narrow road. Piling operations
were safely completed one month ahead of schedule. Weekly safety meetings and
toolbox talks took place for all site staff, outlining safe use of plant and equipment.
Environmental tool box talks for all site staff were given by ecologists provide by
EcoNorth, to educate the team on the sensitive nature of the site and to promote
environmental awareness. Hazard spotting cards to promote a safety culture were
available and actively encouraged to be completed to improve safety and encourage
continuous improvement.
Adherence to programme and budget The project was completed within budget and prior to the agreed contract completion
date of April 2016: This is a significant accomplishment considering the technical
challenges, environmental constraints, pile layout design changes and increases in
work scope. It is a result of collaboration between team members, strong project
management and a resolute commitment to get the road re-open as early as possible.
Innovative and bespoke temporary scaffolding walkway along the 350m length of the site to allow safe access for our operatives.
Installing rock anchors (20-30m length) –fixed length socketed into Fell Sandstone
To achieve the programme extensive resources were deployed: This demanded careful time
and spatial management to plan around the relatively small working area and congested site.
The installation of 436 piles was an integral part of the stabilisation process and was
completed ahead of schedule, highlighting our team’s strength in managing the challenging
conditions faced.
Community benefit
Proactive engagement with the community: The B6344 is a key route to Rothbury and the
project has been of high public interest. Despite the inconvenience of the road closure, an
excellent relationship has maintained with the local community through attending
consultation events and working collaboratively with NCC to keep the project website
updated. It was important to keep the public informed of progression and the site team has
been upfront and honest about any issues.
VBA engaged with the local community prior to work commencing and also gave an
exhibition following completion of construction works.
Generating socio-economic benefits by engaging local people: Fifteen local workers were
employed and trained on site including four within our VBA site management team, general
operatives, plant operatives and joiners. Local companies were also utilised to undertake tree
surgery, supply aggregates, remove spoil and for specialist plant.
Sharing lessons and best practice with the civil engineering and local community:
VBA’s involvement with The Crag End Landslip has been shared amongst the
engineering community through a presentation at Leeds University, at the annual
Ground Engineering Slopes Conference in London, and evening lectures presented to
the Northern Geotechnical Group of the ICE and Geological Society North West
regional group.
Collaborative Working
Excellent team relationship: The key to the success of the project was fundamentally
down to the close working relationship between VBA construction and design team,
Keller, Dewatering Services Ltd and Northumberland County Council. During the
initial ECI phase of work VBA discussions took place with all the contractors as the
design was developed. By having this early liaison it meant that decisions could be
taken as an early stage and the client was able to have a better understanding of
anticipated costs.
Construction collaboration: VBA provided site support during construction and by
taking a proactive approach to producing detailed ground condition long-sections,
substantial cost savings to the client was achieved through revisions to pile lengths
and or rock anchor lengths. Weekly and sometimes daily progress meetings with
Keller took place to review production. As a result of challenging ground conditions
Keller needed to utilise additional rigs and drilling techniques in order to meet the
required construction programme. This required liaison with the design team and fast
track temporary and permanent works design checks.
Throughout the ECI design phase and construction phase VBA developed a good
relationship with AECOM who were appointed as Northumberland County Councils
Geotechnical advisors. Atkins geotechnical and hydrogeological project team
organised regular meetings with AECOM as the design progressed to present the
design. This worked well as AECOM was able to feed back to the client which gave the
client further confidence in the technically challenging design.
Rothbury Connected again!
Road reopened April 2016.
Regular media updates were given during the duration of the project.
Rothbury Exhibition – VBA and NCC met with residents of the local community and received excellent feedback.
Ground conditions cross section updated throughout piling – Value engineering
90.60
90.61
90.61
90.5990.57
90.52
90.4590.4090.35
90.34
90.34
90.41
90.51
90.57
90.6690.84
91.20
91.45
91.70
91.94
92.08
90.54
90.60
90.63
90.63
90.60
90.60
90.5
5
90.52
90.4590.48
90.49
90.48
90.45
90.40
90.38
90.39
90.41
90.43
90.4190.4590.48
90.5290.58
90.63
9
0
.6
7
9
0
.8
0
9
1
.1
1
9
1
.4
3
9
1
.5
5
90.53
90.51
90.47
90.49
90.51
90.5390.51
90.53
90.56
90.5990.63
90.66
9
0
.7
0
9
0
.8
3
9
1
.1
9
9
1
.5
3
9
1
.6
0
90.58
90.4
4
90.4290.41
90.3990.37
90.40
90.50
90.62
90.7690.99
91.35
91.61
91.7691.89
92.04
9
1
.
7
2
91.83
91.76
91.94
Tarmac
Tarmac
Tarmac
Tarmac
Concrete R
TW
Concrete RTW
Concrete RTW
SOP3
SOP4
T
P
4
A85 A86A87 A88 A89 A90 A91
A92 A93 A94 A95 A96 A97 A98 A99 A100 A101 A102 A103 A104 A105 A106 A107 A108 A109 A110 A111 A112 A113 A114 A115 A116A117 A118 A119 A120
A121 A122 A123 A124 A125 A126 A127 A128 A129 A130 A131 A132 A133 A134 A135 A136 A137
A139 A140A141 A142 A143 A144
T
P
4
A
0.75m
13.382m BEAM 1714.474m BEAM 18
12.831m BEAM 19 10.809m BEAM 2010.756m BEAM 21
10.688m BEAM 22 11.693m BEAM 23
13m BEAM 16
2m
2m
0.82m
12.96m BEAM 15
W
E
L
L
1
9
1
.4
1
4
9
1
.0
7
3
W
E
L
L
1
A
9
0
.7
3
8
W
E
L
L
2
9
0
.6
1
4
9
1
.8
8
9W
E
L
L
3
W
E
L
L
2
A
P252
P253
P254
P255
P256
P257
P258
P259
P260
P261
P262
P263
P264
P265
P266
P267
P268
P269
P270
P271
P272
P273
P274
P275
P276
P277
P278
P279
P280
P281
P282
P283
P284
P285
P286
P287
P288
P289
P290
P291
P292
P293
P294
P295
P296
P297
P298
P299
P300
P301
P302
P303
P304
P305
P306
P307
P308
P309
P310
P311
P312
P313
P314
P315
P316
P317
P318
P319
P320
P321
P322
P323
P324
P325
P326
P327
P328
P329
P330
P331
P332
P333
P334
P335
P336
P337
P338
P339
P340
P341
P342
P343
P344
P345
P346
P347
P348
P349
P350
P351
P352
P353
P354
P355
P356
P357
P358
P359
P360
P361
P362
P363
P364
P365
P366
P367
P368
P369
P370
P371
P372
P373
P374
P375
P376
P377
P378
P379
P380
P381
P382
P383
P384
P385
P386
P387
P388
P389
P390
P391
P392
P393
P394
P395
P396
P397
P398
P399
P400
P401
P402
P403
P404
P405
P406
P407
P408
P409
P410
P411
P412
P413
P414
P415
P416
P417
P418
P419
P420
P421
P422
P423
P424
P425
P426
P427
P428
P429
P430
P431
P432
P433
P434
P435
P436
A138
0.14
0.150.20
0.200.20
0.320.23
CONCRETE CAPPING BEAM
(ASSUME 110Kg/m²)
3000
(M
IN
IM
UM
R
OC
K S
OC
KE
T)
CONCRETE
TOP OF
FINISHED R.L
ASSUMED ROCK
HEAD PROFILE
APPROXIMATELY ≈ 3000 TO 4000 DEPTH TO EXISTING ANCHOR
VARIES, MINIMUM 1500
EXISTING
ANCHOR
4
2
.
5
°
EXISTING
SHEET
PILE WALL
EXISTING
CAPPING
BEAM
EGL
508mm DIA. BORED
PILES @ 600mm C/C
MINIMUM ANCHOR FREE LENGTH MUST
BE TO ROCK HEAD. THE ANTICIPATED
ANCHOR FREE LENGTH TO ROCK HEAD
AT EACH ANCHOR LOCATION WILL BE
AGREED WITH THE CONTRACTOR &
VBA AND VERIFIED DURING ANCHOR
INSTALLATION.
2000
VARIES, MINIMUM 2000
100
STAGGERED ANCHOR
ANGLE 27.5° & 32.5°
SINGLE FINE
GRAVEL 10-20
150Ø SLOTTED PVC
PIPE (DEPTH TO BE
CONFIRMED)
300 Min.
75
LEVEL
GROUND
300
1435
3000
(M
IN
IM
UM
R
OC
K S
OC
KE
T)
1000
1700
75
200
260mmØ RESERVATION
TUBE
NOTE:
REFER TO DRAWINGS
5129596-DRG-801 TO 811
FOR R.C. DETAILS
CAPPING BEAM RECESS
WIDTH 321 (32.5°) OR
291 (27.5°)
HEIGHT OF RECESS
504 (32.5°) OR
558 (27.5°)
Date
DesignedScale
Drawing Title
Project Title
Drawing Status
DO NOT SCALE
Date Date Date
Drawn Checked Authorised
Millim
etre
s
10
01
00
Client
Copyright C
VBA Joint Venture Limited (2013)
Original Size
Suitability
Tel:
Fax:
Drawing Number Revision
+44 (0)1524 599400
+44 (0)1524 599401
Whitegate
White Lund Trading Estate
Morecambe
Lancashire
LA3 3BY
Rev. Date
Description By
Chk'd
App'd
A1
PROPOSED ROCK ANCHOR POSITION AT VARIED CENTRES
PROPOSED ROCK ANCHOR LOCATIONS AT 1800mm CENTRES
LOCATION OF DEEP DE WATERING WELLS
EXISTING CONCRETE RETAINING WALL CAPPING BEAM
ASSUMED LOCATION OF EXISTING ANCHORS TENSION PILE
WITH CONSTRUCTION TOLERANCES APPLIED
} SURVEYED ANCHOR TENSION PILE
PILE
}
KEY
TEST PILE LOCATION
INSTALLING GROUND ANCHORS (OCT. 2015) WITH SCAFFOLD WALKWAY
PROVIDING SAFE ACCESS
CAPPING BEAM AND GROUND ANCHORS FOR
TRIANGULAR PILE ARRANGEMENT
SECTION A-A
TRIANGULAR PILE ARRANGEMENT TO REDUCE CONFLICT WITH EXISTING ANCHORS
LIVE RISK MITIGATION TOOL ADOPTED ON SITE TO ASSESS GROUND CONDITIONS ENCOUNTERED DURING PILING AND VALIDATE DESIGN - RESULTING IN SAVINGS IN PILE LENGTH IN SOME AREAS AND INCREASED PILE
LENGTH WHERE REQUIRED RESPONSE TO GROUND CONDITIONS
EXISTING GROUND ANCHORS EXPOSED AND
ALIGNMENT PROJECTED BACK TO PILE LOCATIONS
TO IDENTIFY SAFE ZONES FOR PILING
PILE ALIGNMENT MOVED FORWARD TO
MAXIMISE SPACE FOR PILING. CAPPING
BEAM WIDENED TO ACCOMMODATE
TRIANGULAR PILE ARRANGEMENT
PREPARED FOR SUBMISSION TO ICE
ROBERT STEPHENSON AWARD 2016
EXISTING ANCHORED SHEET
PILE WALL FAILED IN DEC. 2012
A
A
STANDARD CONTIGUOUS
PILE ARRANGEMENT
PILES RECONFIGURED TO TRIANGULAR ARRANGEMENT TO AVOID CONFLICT WITH EXISTING
ANCHORS - REQUIRING ADVANCED FIRST PRINCIPLES ANALYSIS TO VERIFY DESIGN
STANDARD CONTIGUOUS
PILE ARRANGEMENT
PILE INSTALLATION - MULTIPLE RIGS ON A CONSTRAINED SITE REQUIRED CAREFUL PLANNING
TO ENSURE SAFE WORKING
CONSTRUCTION OF CAPPING BEAM