project progress ppt
Embed Size (px)
DESCRIPTION
Presentation for progress of a construction project at Bandra,MumbaiTRANSCRIPT
-
D MONTE PARK SITE,BANDRA WEST.DHEERAJ HOUSING PVT. LTD.
-
RESIDENTIAL BUILDING
3 BASEMENTS+ STILT FLOOR+
PODIUM FLOOR+13 STORIES PROJECT
-
PROGRESS
-
3 Double Height Basements completed ahead of schedule. (18,900 Sq. Ft.) Podium with Swimming pool completed.Transfer Slab at 5.2m height, 1.2m depth expected completion 7 days ahead of schedule.Over all project: 30+ days ahead of schedule.
-
WORK STATUS: SIX MONTHS AGO
-
WORK STATUS: 6 MONTHS INTO THE PROJECT( 3 BASEMENTS+ PLINTH+ PODIUMS+ TRANSFER SLAB
-
Organization Chart
Mr. Nitin Agresar Sr. VP & Head Projects Mr. Amesh Dharmale Sr. Project Manager Mr. Shivram Desai Sr. Site Engr. Mr. Sachin Mangutkar Storekeeper
-
Execution DepartmentBackbone of the project ResponsibilitiesAssure timely completion of the project.Assure Best possible qualityAssure safe and clean workplace
Support System:Design DepartmentStores DepartmentPurchase DepartmentContracts DepartmentMEP & Services
-
QUALITY
-
TEMPRATURE METER
-
HIGH SPEED MEN + MATERIAL 1.5 TON HOIST
-
HOUSEKEEPING AND SAFETY
-
HOUSEKEEPING AND SAFETYPreparation of project specific HSE Plan ,HIRA Register for siteInduction Training to All workers & staff .Sub contractor foreman refresher TrainingSafety Committee & its meeting.Safety Inspection of mechanical equipment Power Tools & Hand tools safety.
-
SAFETY EQUIPMENTFollowing of SOPs Electrical safety Provision of Earthing, ELCB,Hot Work safety Inspection of Temporary structures Peripheral & lift duct barricadingFall Protection - Safety net Provision.
-
Nomenclature of Structure
-
TECHNOLOGY
-
Shuttering from World Class RMD KWICKFORM used for speed and qualityBest in class machinery from German Wacker Neuson ,Bosh & DeWault used for the project.
-
Thank You
-
DescriptionArea in SQFTWork StatusPlot Area13944.96Total Construction area90000Basement -33500Completed Basement-27500 CompletedGround Floor7500CompletedPodium Floor7500CompletedTransfer Floor550060% completed, balance work in ProgressTypical Floor3600