Acetylene Gas Production Facility, Gauteng Province TRAFFIC IMPACT REPORT June 2014 29 De Havilland Crescent Pro Park Building 1 Persequor Park 0200 Tel (012) 349 1664 Fax (012) 349 1665 e-mail: [email protected]

Upload: vokhanh

Post on 04-Jun-2018

225 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

 

Acetylene Gas Production Facility,

Gauteng Province

TRAFFIC IMPACT REPORT

June 2014

29 De Havilland Crescent Pro Park Building 1 Persequor Park 0200 Tel (012) 349 1664 Fax (012) 349 1665 e-mail: [email protected]

Page 2: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

Title: TRAFFIC IMPACT STUDY – PROPOSED

ACETYLENE GAS PRODUCTION FACILITY,

Client: AIR PRODUCTS SOUTH AFRICA (PTY) LTD

Project Team: Jaco Stolp

Henri Vorster

Siphiwe Ntuli

Lebogang Tsogang

Reviewed by Pieter Pretorius (Pr. Eng)

Project nr: ITS 3302

Date: June 2014

Report Status: Final

Page 3: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of
Page 4: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

i

TABLE OF CONTENTS

DECLARATION OF INDEPENDENCE ........................................................................ I

TABLE OF CONTENTS ............................................................................................... I

GLOSSARY OF TERMS ............................................................................................. II

APPLICABLE SOURCE DOCUMENTS ..................................................................... II

EXECUTIVE SUMMARY .............................................................................................. I

1 INTRODUCTION AND BACKGROUND ............................................................... 1

2 SCOPE OF STUDY ............................................................................................... 3

2.1 Study Objectives .......................................................................................... 3 2.2 Assessment Methodology ............................................................................ 3

2.2.1 Baseline Assessment ............................................................................... 3 2.2.2 Traffic Impact Assessment ....................................................................... 4 2.2.3 Identification of mitigations ....................................................................... 4

3 FINDINGS OF THE BASELINE ASSESSMENT .................................................. 5

3.1 Existing external road network ..................................................................... 5 3.2 Access to Proposed Plant.............................................................................5 3.3 Access to Proposed Plant ............................................................................ 6 3.4 Influence area............................................................................................... 6 3.5 Status quo traffic volumes ............................................................................ 7 3.6 Assessment variables .................................................................................. 9

3.6.1 Level of Service (LOS) ............................................................................. 9 3.6.2 Delay ........................................................................................................ 9

4 FINDINGS OF THE TRAFFIC IMPACT ASSESSMENT .................................... 10

4.1 Assessment scenarios ............................................................................... 10 4.2 Analysis Peak Hour .................................................................................... 11 4.3 Expected Trip Generation by Acetylene Gas prodution plant .................... 11

4.3.1 Assumptions ........................................................................................... 11 4.3.2 Plant Transport Requirements and Expected Trip generation ............... 12

4.4 Trip Distribution and Trip Assignment ........................................................ 14 4.5 Intersection Capacity Analysis ................................................................... 14

4.5.1 Road link capacity .................................................................................. 15

5 IMPACT RATING AND MITIGATING MEASURES............................................ 17

6 CONCLUSIONS .................................................................................................. 23

7 RECOMMENDATIONS ....................................................................................... 25

APPENDIX A – Figures APPENDIX B – Site Plan APPENDIX C – Gautrans Basic Planning APPENDIX D – Traffic Count Data

   

Page 5: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

ii

  GLOSSARY OF TERMS

EIA Environmental Impact Assessment LOS Level of Service

NDoT National Department of Transport p.a. Per annum TIA Traffic Impact Assessment v/c Volume/capacity ratio

GLA Gross Leasable Area

APPLICABLE SOURCE DOCUMENTS

Access Management Guidelines

Committee of Transportation Officials (COTO), 2002.National Guidelines for Road Access Management in South Africa.

Manual for Traffic Impact

Studies

National Department of Transport (NDOT), 1995. Manual for Traffic Impact Studies.

NGTC National Department of Transport, 1996. National Guidelines for Traffic Calming.

Trip Generation Guidelines

National Department of Transport, 1994. South African Trip Generation Rates, 2nd Edition.

UTG 1 National Department of Transport, 1986. National Urban Transport Guidelines: geometric Design of Urban Arterials.

SARTSM South African Road Traffic Signs Manual

Page 6: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

i

EXECUTIVE SUMMARY

A Traffic Impact Study was prepared as part of the consolidated environmental impact

assessment (EIA) and environmental management plan (EMP) for the proposed

Acetylene Gas Production Plant project for the EMP application and will include a gas

production plant and pipelines associated with the production facility and associated

entities.

The proposed Acetylene Gas Production Plant will be developed on Erf 88 and Erf 89

of the Farm Valley Agricultural Holdings, Witkopdorp (Daleside) south of

Johannesburg.

The site is located approximately 9km north of the Meyerton CBD and ±45km south of

the Johannesburg CBD in the Gauteng Province.

The proposed Acetylene Gas Production Plant on Erf 88 and Erf 89 will be developed

for the production of gas similar as existing gas production operations in South Africa.

The possible life span of the plant was estimated between 40 and 50 years. Fore the

purpose of this study a 20 year life was assumed to reach full design capacity of the

plant. The proposed Acetylene Gas Production Plant will have a staff complement of

±20 permanent job opportunities.

ITS (Pty) Ltd was appointed by Environmental Resources Management Southern

Africa (Pty) Ltd on behalf of Air Products South Africa (Pty) Ltd to carry out a Traffic

Impact Assessment for the proposed Acetylene Gas Production Plant development in

accordance with the Manual of Traffic Impact Studies published by the Department of

Transport, 1995.

The purpose of this report is to provide findings of the traffic investigation conducted to

assess the impact of the proposed Acetylene Gas Production Plant activity on the

existing external road networks surrounding the development area. Based on this

assessment, mitigation measures are recommended for the proponent to minimise the

potential impacts on the existing road network.

The following tasks have been carried out as part of the traffic impact investigation:

Collection of traffic information to determine the status quo of the existing road

network operations;

Determination of the trip generation due to the proposed Acetylene Gas

Production Plant development;

Assessing the impact of the trips generated by the proposed Acetylene Gas

Production Plant, on the road network (capacity analysis of the affected routes

including the intersection analysis);

Safety Statement: an assessment of the access position in terms of geometrical

standards (UTG 1 manual, site distance, stopping site distances etc.);

Public transport provision to accommodate the public transport users for the

proposed Acetylene Gas Production Plant employees;

A detailed proposal of site specific mitigations, if and where applicable. 

Page 7: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

ii

Assessment Methodology

The main phases of the project have been identified as follows: pre-construction phase

(2014 to 2015), construction phase (2015 to 2019), operational phase (2019 to 2030)

and closure and decommissioning phase (2030). The critical impact in terms of the

traffic generated is expected to be during the operational phase.

The following scenarios were considered for assessment:

2013 Existing Traffic Volumes,

Construction Phase: 2018 projected traffic demand,

Operational phase: 2038 projected traffic demand,

Decommissioning Phase: 2039 projected traffic demand.

Findings

The finding of this investigation can be summarised as follows:

The Tilliet Rd is a gravel road between the proposed Acetylene Gas Production

Plant site access point and Tilliet / Kalksteen Road intersection.

Kalksteen Road is a paved road and links Tilliet Road with the M61 (K89) Road.

The M61 (K89) Road located east of the proposed Acetylene Gas Production

Plant site is a future planned provincial K-route.

The future alignment of the K89 route will impact on Tilliet Road and access to

Tilliet Road would be provided from Kalksteen Road.

Both Tilliet / Kalksteen Road and Kalksteen / M61 Road intersections are priority

controlled intersections with priority on Kalksteen Road and the M61 Road

respectively.

Access to the proposed Acetylene Gas Production Plant site would be provided

from Tilliet Road.

It is expected that the access intersection would operate at an acceptable LOS

once the proposed development is fully operational.

The construction phase is anticipated to be the critical period in terms of additional

trips generation. The trips generation prediction for that period is in order of

± 96 vehicle trips during the AM and PM Peak Hours. The additional trips to be

generated will not pose a significant impact on the external road network.

The interaction (turning movements) between public transport and privates

vehicles might pose some safety hazard. It is therefore recommended that the

following measures be adopted to mitigate the impact:

Surfacing of Tilliet Road between the proposed Acetylene Gas Production

Plant access and the Tilliet / Kalksteen Road intersection.

Provision of road markings and road signage at the Tilliet / Kalksteen Road

and Kalksteen / M61 Road intersections according to the SARTSM “Road

Signs Manual” Volume 2.

Page 8: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

iii

Provision of lighting at sufficient standards at the Tilliet / Kalksteen Road

intersection; and

In terms of public transport provision as well as pedestrian safety:

No on-street pick up / drop off’s at the intersections of Tilliet Rd with the

access to the development should be allowed (drop-offs / pickup should be

done on site)

All of the above mitigation measures should be in place before the operational

phase commence, subject to the indicated timelines (some upgrades only required

by the year 2026).

Page 9: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

3302_Acetylene Gas Production Plant - TIA – June 2014 1

• A C E T Y L E N E G A S P R O D U C T I O N

P L A N T •

ACETYLENE GAS PRODUCTION PLANT

TRAFFIC IMPACT ASSESSMENT

1 INTRODUCTION AND BACKGROUND

ITS (Pty) Ltd was appointed by Environmental Resources Management Southern

Africa (Pty) Ltd on behalf of Air Products South Africa (Pty) Ltd to carry out a Traffic

Impact Assessment for the proposed Acetylene Gas Production Plant development in

accordance with the Manual of Traffic Impact Studies published by the Department of

Transport, 1995. In terms of the guideline, a fully fledged traffic impact analysis is

required to be carried out for the proposed development. This should include

conducting vehicle count surveys, conflicting turning movement analysis, intersection

performance analysis and road safety assessment if applicable. Measures such as

level of service, delay, and volume or capacity ratio can be used to quantify the

performance of an intersection or a roadway facility.

The proposed Acetylene Gas Production Plant on Erf 88 and Erf 89 will be developed

for the production of gas similar as existing gas production operations in South Africa.

The proposed Acetylene Gas Production Plant will be developed on Erf 88 and Erf 89

of the Farm Valley Agricultural Holdings, Witkopdorp (Daleside) south of

Johannesburg. The site area is approximately 4.4ha in extent. The extent of the

development will be approximately 16 000m² GLA, (Gross Leasable Area) industrial.

The site is located ±9km north of the Meyerton CBD and ±45km south of

Johannesburg CBD in the Gauteng Province. (Refer to the locality plan in Appendix

A: Figure 1).

The possible life span of the plant was estimated between 40 and 50 years. Fore the

purpose of this study a 20 year life was assumed to reach full design capacity of the

plant.

The proposed Acetylene Gas Production Plant site however exclude wetlands, rivers,

registered servitudes, provincial and national roads and buildings or any other

structure or sensitive natural stature protected in terms of national and/or international

law.

Page 10: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

3302_Acetylene Gas Production Plant - TIA – June 2014 2

The method of producing gas at the proposed Acetylene Gas Production Plant will be by

using a rotating screw conveyor to feed calcium carbide granules (25mm – 50mm) into a

reaction chamber, which is filled with water. The acetylene gas bubbles to the surface and is

drawn off under low pressure. The gas is then compressed to a pressure of 2300kPa before

being filled into the cylinders, which are stored on site prior to distribution.

The proposed Acetylene Gas Production Plant will be similar to existing gas production

operations and will utilise the existing infrastructure and will include the provision of new or

upgrading of existing infrastructure, viz. access roads (M61 Road, Henley Drive or Randvaal

Road to access the R59 motorway), haul road, railway lines, water pipelines, etc.

Moreover, the proposed Acetylene Gas Production Plant is evaluating, based on

similar gas production operations, using rotating screw conveyers, reaction

chambers, cylinders, pipelines and distribution vehicles to distribute products to

varies markets in South Africa. The existing external infrastructure will be utilised for

this project with minor additions as identified will be used with a total new internal

infrastructure will be developed.

The purpose of this report is to provide findings of the traffic investigation conducted

to assess the impact of the proposed Acetylene Gas Production Plant on the

existing external road network surrounding the development site area. Based on this

assessment, mitigation measures are recommended for the proponent to minimise

the potential impacts on the existing road network.

Page 11: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

3302_Acetylene Gas Production Plant - TIA – June 2014 3

2 SCOPE OF STUDY

2.1 Study Objectives

The objective and scope of study for the traffic impact investigation entailed the following:

Collection of traffic information to determine proposed Acetylene Gas Production Plant

status quo;

Determination of the trip generation due to the proposed Acetylene Gas Production

operations activities;

Assessing the impact of the trips generated by the proposed Acetylene Gas Production

Plant, on the road network (capacity analysis of the affected routes including the intersection

analysis).

Safety Statement:

An assessment of the access position in terms of geometrical standards according to

the “UTG 1: geometric Design of Urban Arterials manual”.

Public transport provision for the proposed Acetylene Gas Production Plant

employees.

A detailed proposal of site specific mitigations, if and where applicable.

2.2 Assessment Methodology The assessment methodology entailed the baseline assessment, traffic impact assessment

and recommended mitigation measures (refer to Figure 2.1 below):

Figure 2.1: Traffic Impact Assessment Methodology

2.2.1 Baseline Assessment

The baseline assessment included the identification of the affected external roads; the

investigation and assessment of the status quo of external road networks including the

existing traffic volumes.

Page 12: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

3302_Acetylene Gas Production Plant - TIA – June 2014 4

2.2.2 Traffic Impact Assessment

The traffic impact assessment includes the capacity analysis of the existing road network

(surrounding roads) and the investigation and assessment of the existing and future

transport requirements (private and public transport) related to the proposed development.

Furthermore, road safety aspects will be assessed such as access positions.

2.2.3 Identification of mitigations

The potential impacts due to traffic generated by the proposed Acetylene Gas Production

Plant were identified and assessed in accordance with the methodology presented in

Section 2.1 of this report. Where applicable, mitigating measures were proposed to

attenuate the impact of the trips generated by the proposed Acetylene Gas Production Plant.

Page 13: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

3302_Acetylene Gas Production Plant - TIA – June 2014 5

3 FINDINGS OF THE BASELINE ASSESSMENT

This section of the report provides details and findings of the baseline assessment

conducted, as outlined below:

3.1 Existing external road network

The major routes in the study area are described in Table 3.1 below, and a schematic

representation of the road network is shown in Figure 1 - Appendix A of this report.

Table 3.1: Overview of the existing road network and jurisdiction

Road Link

Jurisdiction

Class of road

Function of the Road Road Surfacing Cross Section (Typical

Width of the road)

R59 Rd

(Sybrand van

Niekerk Freeway)

Gauteng Department of

Roads and Transport (GDRT)

C1

The road is a north-south, Provincial Class 1 road with a mobility function. The R59 Rd connects Vanderbijlpark with Johannesburg.

The road is paved and the surface condition is good*.

Single carriageway (4 lanes: two lanes per direction) with median and interchanges at

roads providing access to the R59 Rd

M61 Rd (K89)

Gauteng Department of

Roads and Transport (GDRT

R2

The road is a north-south, Provincial Class 2 rural road with a collector-distributor function. The M61 Rd connects Meyerton with Alberton.

The road is paved and the surface condition is fairly adequate**.

Single carriageway (2 lanes: one lane per

direction), unpaved shoulders

Kalksteen Rd

Midvaal Local Municipality

R5

The road is an east-west local municipality Class 5 rural road with a local access function. Kalksteen Road connects the M61 Rd with local roads in area.

The road is paved and the surface condition is fairly adequate**.

Single carriageway (2 lanes: one lane per direction), unpaved

shoulders

Tilliet Rd Midvaal Local Municipality

R5

The road is an north-south local municipality Class 5 rural road with a local access function. Tilliet Rd connects Kalksteen Rd with the access to the proposed plant site.

Gravel road. The future alignment Tilliet Rd will affected by the future K89 alignment, surfacing of Tilliet Rd would be required.

Local access street with a 16m road reserve

“good” = road maintenance standard, include surface of road, sight distance, road signs, road markings, driver

experience, etc.

“fairly adequate” = require road maintenance, improvement of road markings, road signs, surfacing, driver experience

less than freeway, etc.

The roads mentioned in Table 3.1 might be impacted by the new traffic generated by the

proposed Acetylene Gas Production Plant site and this will be evaluated further in the

present report.

Page 14: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

3302_Acetylene Gas Production Plant - TIA – June 2014 6

3.2 Existing Rail Network

Transnet has a major rail line located east of the M61 Road. This railway line is part of the

national major rail network between Johannesburg and the sub regions in South Africa. The

existing rail line is an important “branch line” but, with a main line standard. It serves the

industrial as well as the agricultural sector in the Gauteng and Vaal Triangle area.

The line feeds large volumes of bulk traffic into and through Gauteng. The nearest railway

station is Daleside station located north east of the proposed site. This station is mainly

designed for passenger use.

3.3 Access to Proposed Plant

The proposed Acetylene Gas Production Plant will have an access from Tilliet Road

currently a gravel road.

The access performance characteristics (from a traffic engineering point of view) are

discussed in Section 4 of this report.

The existing layout of the access point is shown in Appendix C – Site Layout Plan. The

existing access can accommodate the existing traffic and the future traffic demand (including

trucks to/from the Plant).

3.4 Influence area

As mentioned in Section 3.1 above, the following external link roads might be directly

affected by new traffic generated by the proposed Acetylene Gas Production Plant

development:

Tilliet Road;

Kalksteen Road; and

M61 Road.

The influence area for this study was determined by the locality of the site and based on the

proposed Acetylene Gas Production Plant transport needs (origins and destination).

The following intersections have been investigated as part of this Traffic Impact Assessment:

Intersection 1: M61 Road / Kalksteen Road;

Intersection 2: Tilliet Road / Kalksteen Road,

Intersection 3: Tilliet Road / Access to Acetylene Gas Plant; (refer to Figure 3 -

Appendix A)

Page 15: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

3302_Acetylene Gas Production Plant - TIA – June 2014 7

The additional capacity of the M61, Kalksteen and Tilliet routes and the intersections under

evaluation, to accommodate existing and future traffic demand, is discussed in Section 4 of

this report.

3.5 Status quo traffic volumes

A site visit and was traffic counts (traffic survey) were carried out on Thursday 13th

November 2013 as part of the scoping process. Traffic counts were carried out during the

morning and afternoon peak hours, typical between 06:00 – 09:00 and 16:00 – 18:00 at the

above mentioned intersections. The AM and PM Peak hour was determine based on the

highest traffic volumes registered during the morning and afternoon periods respectively.

The 2013 AM and PM traffic volumes can be seen in Figures 3 to 5 – Appendix A. The

existing intersections geometry and controls are indicted in Figure 2 - Appendix A.

Graph 3.1 and 3.2 below shows the total through and turning traffic volumes counted on the

M61 Road from 6:45am to 8:45am and 15:45pm to 17:30pm.

The existing traffic volume trends during a typical working day (when the traffic is expected

to be at the highest peak) are during 07:00 and 08:00 in the morning ad during 16:30 and

17:30 in the afternoon also revered to as the morning and afternoon peak hours are

summarised in Graph 3.1 and 3.2, below.

Graph 3.1: Existing AM peak hour traffic volumes Trends: North of Kalksteen Street

0

50

100

150

200

250

300

350

400

450

06:45

07:00

07:15

07:30

07:45

08:00

08:15

08:30

08:45

M61 Road North of Kalksteen St 

Total

Page 16: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

3302_Acetylene Gas Production Plant - TIA – June 2014 8

Graph 3.2: Existing PM peak hour traffic volumes Trends: North of Kalksteen Street

These graphs represent the existing traffic volumes during AM and Pm peak hour periods on

the M61 Rd from 6:45am to 8:45am and from 15:45pm to 17:30pm.

0

50

100

150

200

250

300

350

400

450

15:45

16:00

16:15

16:30

16:45

17:00

17:15

17:30

M61 Road North of Kalksteen St

Total

Page 17: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

3302_Acetylene Gas Production Plant - TIA – June 2014 9

3.6 Assessment variables

The following variables have been considered to assess the impact of the traffic generated

by the proposed development:

3.6.1 Level of Service (LOS)

A measure of intersection or roadway performance, determined based on delay for un-

signalised intersections. The LOS definitions in terms of delay are shown in Table 3.2,

below.

Table 3.2: LOS definitions based on vehicle delay

LEVEL-OF-SERVICE DEFINITIONS BASED ON VEHICLES DELAY

Level of Service

Control Delay per vehicle in seconds Level of Acceptability

A d≤14.5 Acceptable B 14.5 < d ≤ 28.5 Acceptable C 28.5 < d ≤ 42.5 Acceptable D 42.5 < d ≤ 56.5 Acceptable E 56.5 < d ≤ 70.5 Not Acceptable F 70.5 < d Not Acceptable

In most urban areas overall rating of A to D are normally considered acceptable. Levels of

service D or better are considered desirable and levels of service E and F are normally

undesirable. (Department of Transport,1995).

3.6.2 Delay

Delay is a measure of intersection or roadway performance which is measured based on the

driver discomfort, frustration, fuel consumption and lost travel time. Delay at intersections

depends on various factors such as type of signal control, volume of traffic and

volume/capacity ratio of each approach at an intersection (C A O’Flaherty, 1997). The

intersections performance has been rated based on the average delay, i.e. the LOS of the

intersections under investigation (including the access to the Plant) will be measured based

on the intersection average delay.

3.6.3 Volume / capacity ratio

Volume / capacity ratio (v/c) is a measure of intersection or roadway performance.

It is the ratio of number of vehicles on the road to the available capacity of the roadway. The

road link capacity in the study area was rated based on the volume/capacity ratio, i.e. the

LOS of the link roads will be measured based on the volume/capacity of the roads.

Page 18: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

3302_Acetylene Gas Production Plant - TIA – June 2014 10

4 FINDINGS OF THE TRAFFIC IMPACT ASSESSMENT

The impact assessment of the transportation aspects related to the proposed Acetylene Gas

Production Plant activities was determined based on the evaluation of the worst traffic

scenario during the construction, operation, closure and decommissioning phases. The

proposed Acetylene Gas Production Plant will be designed for 20 year life and will reach full

design capacity by 2038.

Year 3: This scenario refers to the year in which the gas production will commence. It was

assumed that Year 3 will be in 2017.

4.1 Assessment scenarios

Based on the information above, the following scenarios were considered critical for the

assessment:

2013 Existing AM and PM Peak Hour Traffic Volumes (Scenario 1a and 1b) - This

refers to the assessment of the existing traffic on the surrounding road network (refer

to Figures 3 and 4, Appendix A).

Construction Phase: 2017 projected traffic demand - This refers to the assessment

of the traffic demand during the construction phase of the proposed Acetylene Gas

Production Plant site.

Operational phase - 2018 projected AM Peak Hour traffic demand (Scenario 2a

and 2b): This scenario refers to the year in which the Acetylene Gas Production Plant

operations will commence. It was assumed that Year 5 will be in 2018 (refer to

Figures 5 and 6, Appendix A). A growth rate of 3% per annum was applied to the

2013 existing traffic (background traffic).

Scenario 3 (also refer to Table 4.5 and 4.6 below): 2018 projected AM Peak Hour

traffic demand without development traffic;

Scenario 4 (also refer to Table 4.5 and 4.6 below): 2018 projected AM Peak Hour

traffic demand with development traffic;

Decommissioning Phase: 2038 (Life of Plant=20 Years) projected traffic demand (Scenario 5). These refers to the assessment of the traffic demand during the decommissioning phase of the proposed plant site (refer to Figures 10, Appendix A).

Page 19: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

3302_Acetylene Gas Production Plant - TIA – June 2014 11

4.2 Analysis Peak Hour

The assessment of the impact will be done for the critical peak hour. The critical peak hours,

from a road capacity point of view occurs when the highest combination of existing road

traffic and traffic generated by the development occurs.

Based on the existing traffic counts, it was decided to consider the following peak hours for

analysis:

AM peak Hour: 7:30 to 8:30,

PM Peak hour 17:00 to 18:00.

4.3 Expected Trip Generation by Acetylene Gas Production Plant Activity

4.3.1 Assumptions

The expected trip generation during the AM and PM Peak hour was determined based on a

number of assumptions made from the data supplied to the Traffic Specialists. Table 4.1,

below refers.

Table 4.1: Trip Generation Calculation – Assumptions for Assessment of Traffic

Impact

Parameter

Assumptions

Source of information

5 years

Traffic Impact Assessment Only traffic volumes during construction will be

assigned to network as this will be the peak scenario

Air Products (Pty) Ltd schedule of phasing and mode of

distribution of Acetylene Gas Production Plant

Estimated number of employees at the Plant areas

±20 employees (skilled (50%), semi-skilled (25%) to unskilled people (25%) Air Products (Pty) Ltd 10 skilled employees

Number of working shifts 3 shifts (morning 05:00 to 13:00, Afternoon 13:00 to

21:00 and Night 21:00 to 05:00) Air Products (Pty) Ltd

Lifespan of the Plant >40 to 50 years Plant Layout Plan

Growth Rate (applied to project the background traffic

3% p.a Previous Studies conducted by

ITS Engineers

Transport Mode

rotating screw conveyers Pipe transport Private vehicles (mostly used by skilled

employees) and Buses (used by the majority of semi-skilled to

unskilled employees) Air Products (Pty) Ltd

Transport requirements Buses with a capacity of 60 passengers and taxi’s

with a capacity of 15 passengers will transport employees to and from the Plant

Private Vehicle Occupancy rate 1.8 people/car Previous Studies conducted by

ITS Engineers

Page 20: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

3302_Acetylene Gas Production Plant - TIA – June 2014 12

4.3.2 Plant Transport Requirements and Expected Trip generation

The Plant transport requirement will be as follows:

Construction Phase (2014 to 2019)

Transport of Material: Heavy vehicle trips are expected to be generated to transport

construction material to/from the Plant.

Commuter trips (private and public transport): Commuter trips are expected to be

generated daily by the skilled construction workers with approximately 90% using private

transport. It is assumed that the semi and unskilled works will be accommodated with

approximately 90% using public transport.

Operational Phase (2019 to 2039 for this study purposes) or 50 years estimated

Transportation of raw material: The facility will produce acetylene gas from mixing raw

calcium carbide raw material and will be transported from the various suppliers to the

Acetylene Gas Production Plant with heavy vehicles.

Transportation of final product: It is expected that the proposed Acetylene Gas Production

Plant will produce a maximum of 14 400m³ of acetylene gas per day. The acetylene gas will

be compressed to a pressure of 2 300kPa before being filled into cylinders and distributed.

Transportation of by-product: A by-product of the production process is a slurry of calcium

hydroxide (ie lime). Air Products South Africa (Pty) Ltd intension is to sell this by-product for

use in various markets including agricultural. Heavy vehicles will be used for the

transportation of the by-product.

Transport of Goods (deliveries): Trips are expected to be generated as a result of service

delivery as well as transportation of goods / products to / from the Plant. Initially 2 heavy

vehicles are estimated to be generated daily.

Commuter trips (private and public transport): Commuters trips are expected to be

generated daily from the origins surrounding the Plant. The commuter trips will be split into

private and public minibus taxi transport trips.

Decommissioning Phase (2040 for study purposes)

According to the estimated life span of the proposed Acetylene Gas Production Plant the

decommissioning and closure phase will be after 40 to 50 years. Traffic volumes during this

phase will be considerably lower than the operational phase.

Table 4.2 below summarises the typical peak hour expected transport requirements of the

proposed Acetylene Gas Production Plant.

Page 21: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

3302_Acetylene Gas Production Plant - TIA – June 2014 13

Table 4.2: Transport Requirements    

Peak Hour Transport Requirements for all Phases of the Proposed Plant

Analysis scenario Construction

Phase

Peak Operational

Phase Decommissioning

Phases

Private Vehicles >10 >10* 6

Trucks 2(during peak hours) 2* 3

Buses 0 0 0

Taxis 1 1* 2

Total number of vehicles 13 13 11 *Private vehicles: 5(90%)/1,8 = 5 + 3 (Supervision) =8

An estimated 13 vehicles are anticipated to be generated by the proposed Acetylene Gas

Production Plant during the AM and PM peak hours in the operational phase (most critical

hours for analysis). Table 4.3 and Table 4.4, below, shows the directional split (trips in and

out of the sites) during the AM and PM peak hours.

Table 4.3: Plant Area Expected trip generation (AM Peak Hour)

Expected AM Peak Hour Trip Generation

Analysis scenario Assumptions

Year 5 Plant Trips Year 6 Plant Trips

Total In Out Total In Out

Raw material transport (vph) >1% of total traffic 1 1 0 1 1 0

Suppliers (vph) 1% of total traffic 1 1 0 1 1 0

Private vehicle (vph) 3 shifts (60/40 split) 10 8 2 10 8 2

Public transport (vph) during peak hour 1 1 0 1 1 0 Total number of vehicles 13 11 2 13 11 2

Table 4.4: Plant Area Expected trip generation (PM Peak Hour)

Expected PM Peak Hour Trip Generation

Analysis scenario Assumptions

Year 5 Plant Trips Year 6 Plant Trips

Total In Out Total In Out

Raw material transport (vph) >1% of total traffic 1 0 1 1 0 1

Suppliers (vph) 1% of total traffic 1 0 1 1 0 1

Private vehicle (vph) 3 shifts (20/80 split) 10 2 8 10 2 8

Public transport (vph) during peak hour 1 2 1 1 0 1

Total number of vehicles 13 2 11 13 2 11

Notes: “vph” - Vehicles per hour, 3% growth rate

 

It is evident from Table 4.3 that during the operational phase (Year 5) the proposed Plant

will typically generate ± 13 additional vehicle trips during the AM and PM peak hours

respectively.

Page 22: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

3302_Acetylene Gas Production Plant - TIA – June 2014 14

4.4 Trip Distribution and Trip Assignment

The trip distribution of the additional traffic expected to be generated by the proposed

development was determined based on the expected origins and destinations of the

development traffic.

It is expected that most of the development traffic will use the M61 Road as well as

Randvaal Road and Henley Road to access the R59 (Sybrand van Niekerk) motorway. It is

expected that 60% of the development traffic would travel northbound towards Randvaal

Road via the M61 Road and 40% of the development traffic southbound towards Henley

Drive.

The additional vehicle trips that are expected to be generated by the Plant were assigned to

the adjacent road network. The assignment of the trips is based on the routes identified in

the baseline assessment.

Appendix A-Figure 7 shows the expected trip distribution, considering the different routes

to be taken by the different modes of transport available. Figures 8 indicate the assignment

of the trips generated by the proposed development.

4.5 Intersection Capacity Analysis

Capacity analysis of the intersections on the surrounding road network was conducted using

aaSIDRA analytical software. The performance characteristics and expected traffic demand

of every intersection were determined for the different traffic scenarios described in

Section 4.1. The traffic volumes used for the assessment and analysis results of the traffic

impact are indicated in the figures referred to in Section 4.1 of the report. The capacity

analysis results for the scenarios under evaluation are summarised in Table 4.5 and Table

4.6 below.

Table 4.5: Capacity Analysis Results (AM Peak Hour)

Nr Intersection

AM Peak Hour

Scenario 1: Existing Traffic Volumes

Scenario 3: Background projected

traffic demand and Plant traffic

Scenario 4: Background projected

traffic demand and Plant traffic in 2018

2013 Background 2018 Future Traffic

Volumes

2018 Future Traffic Volumes plus

Development Traffic

v/c Delay LOS v/c Delay LOS v/c Delay LOS

1 Tilliet Rd / Access Rd 0.01 1.2 A 0.01 1.3 A 0.05 2.8 A

2 Tilliet Rd / Kalksteen Rd 0.01 1.7 A 0.01 1.8 A 0.06 6.9 A

3 Kalksteen Rd / M61 Rd 0.12 1.3 A 0.17 3.0 A 0.70 11.9 B

Page 23: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

3302_Acetylene Gas Production Plant - TIA – June 2014 15

Table 4.6: Capacity Analysis Results (PM Peak Hour)

Nr Intersection

PM Peak Hour

Scenario 1: Existing Traffic Volumes

Scenario 3: Background projected

traffic demand and Plant traffic

Scenario 4: Background projected

traffic demand and Plant traffic in 2018

2013 Background 2018 Future Traffic

Volumes

2018 Future Traffic Volumes plus

Development Traffic

v/c Delay LOS v/c Delay LOS v/c Delay LOS

1 Tilliet Rd / Access Rd 0.01 1.1 A 0.01 1.2 A 0.06 4.7 A

A Tilliet Rd / Kalksteen Rd 0.01 1.9 A 0.07 7.8 A 0.08 6.8 A

3 Kalksteen Rd / M61 Rd 0.13 1.2 A 0.14 1.3 A 0.83 11.6 B

 Legend:        Background: projected traffic without development, Future: projected traffic with development  Volume to capacity ratio (v/c)      Delay (in seconds)       

Level of service (LOS)   A,B,C,D   acceptable LOS       E and F   unacceptable LOS 

 

All the intersections within the influence area operate at acceptable LOS. The analysis

indicated that all the intersections analysed will continue to operate in the future 2019

scenario at acceptable LOS. With the development traffic volumes added during the most

critical phase (construction phase), the surrounding road capacity analysis shows that the

intersections would operated at acceptable levels of service. In other words, congestion

levels will be at an acceptable level during the most critical phase of the Acetylene Gas

Production plant development (the operational phase).

4.5.1 Road link capacity

The analysis results for the assessment of the road link capacity (within the area of

influence) per direction are summarised in Table 4.7 below. For the purposes of this

assessment only the critical phase was considered (the construction phase).

Page 24: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

3302_Acetylene Gas Production Plant - TIA – June 2014 16

Table 4.7: Typical Weekday AM Peak (critical peak) link volumes and lane capacity

From Table 4.7 it is evident that the M61 Road and Kalksteen routes is expected to

accommodate the existing and future traffic demand (up to the decommissioning phase)

without requiring additional road upgrades. The M61 Road and Kalksteen routes have an

average of 91% spare capacity per lane to accommodate the future demand during the

critical peak hours.

4.5.2 M61 Road (K68 route)

The basic planning of the future K68 route is indicated in Appendix D. A portion of Tilliet Street will be closed to accommodate the future K68 route road reserve.

The future K68 route planning will not be impacted by the proposed Acetylene Gas Production Plant development.

Ro

ad

Section of the road

Direction and Lane

Requirements

Construction Phase: 2014 Background

Traffic + Development

Traffic

Existing nr. of

lanes per direction

Utilisation (v/c ratio) during horizon year

(2019 Traffic + Development Traffic)

Available spare

capacity per lane

M6

1 R

oad

North of Kalksteen Street

Northbound 222 1.0 0.15 0.85

Southbound 202 1.0 0.13 0.87

South of Kalksteen Street

Northbound 211 1.0 0.14 0.86

Southbound 198 1.0 0.13 0.87

Ka

lkst

ee

n

Str

eet

West of the M61 Rd

Eastbound 22 1.0 0.01 0.99

Westbound 15 1.0 0.01 0.99

Note 1: Lanes required to accommodate the demand on all the roads, based on a lane capacity of (vph): 1 500

Page 25: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

3302_Acetylene Gas Production Plant - TIA – June 2014 17

5 IMPACT RATING AND MITIGATING MEASURES

This section of the report identifies the potential impacts associated with the trips generated

by the proposed development and the mitigation measures. The significance (quantification)

of traffic impacts was identified during the assessments and these were determined using a

ranking scale, based on the following terminology:

Magnitude (M) refers to the degree or magnitude to which the impact alters the functioning

of an element of the environment, the magnitude can either be positive or negative.

Duration (D) refers to the timeframe over which the impact is expected to occur, measured

relative to the lifetime of the proposed development. The Extent / scale (S) of the impact

refers to the extent at which the impact will affect the national, regional or local environment,

or only that of the site. The Probability describes the likelihood of the impact actually

occurring. Each of these factors has been assessed each for the current and potential

impacts using the following ranking scale values.

Page 26: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

3302_AcetylenePlant - TIA Report – June 2014 18

Table 5.1: Pre-Construction Phase (Activity 1)

Table 5.2: Construction Phase (Activity 1 to Activity 4)

PRE-CONSTRUCTION PHASE: ACTIVITIES REQUIRING MANAGEMENT MEASURES

M D S P

TO

TA

L

STA

TU

S

SP M D S P

TO

TA

L

STA

TU

S

SP

Traffic volumes - no impact 2 4 2 3 24 - L No recommendations 2 4 2 3 24 - L Design and planning Once-off Specialists Once-off, fixed ammount

Traffic safety - no impact 2 4 2 3 24 - L No recommendations 2 4 2 3 24 - L Design and planning Once-off Specialists Once-off, fixed ammount

PRE-CONSTRUCTION PHASE: ACTIVITIES REQUIRING MANAGEMENT MEASURES

Issues related to TRAFFIC

POTENTIAL ENVIRONMENTAL IMPACT ACTIVITY FREQUENCY RESPONSIBLE PERSON ANNUAL MANAGEMENT COSTRECOMMENDED MITIGATION MEASURES ACTION PLAN

ENVIRONMENTAL SIGNIFICANCE

BEFORE MITIGATION

ENVIRONMENTAL SIGNIFICANCE

AFTER MITIGATION

CONSTRUCTION PHASE ACTIVITY 1: RECRUITMENT, PROCUREMENT AND EMPLOYMENT

M D S P

TO

TA

L

STA

TU

S

SP M D S P

TO

TA

L

STA

TU

S

SP

Recruitment, procurement and employment 2 2 2 4 24 - L No Recommendation - No Impact 2 2 2 4 24 - L No Action plan During start of mining process Mine management To be determined

FREQUENCY RESPONSIBLE PERSON ANNUAL MANAGEMENT COST

CONSTRUCTION PHASE ACTIVITY 1: RECRUITMENT, PROCUREMENT AND EMPLOYMENT

Issues related to TRAFFIC

POTENTIAL ENVIRONMENTAL IMPACT ACTIVITY

ENVIRONMENTAL SIGNIFICANCE

BEFORE MITIGATION

RECOMMENDED MITIGATION MEASURES

ENVIRONMENTAL SIGNIFICANCE

AFTER MITIGATION

ACTION PLAN

CONSTRUCTION PHASE ACTIVITY 2: SITE CLEARANCE AND ROAD ESTABLISHMENT

M D S P

TO

TAL

STA

TUS

SP M D S P

TO

TAL

STA

TUS

SP

1) Tilliet Road (surfacing approximately 450m) 8 5 2 4 60 - M Geometry and surfacing of access road 2 4 3 2 18 - L Construct road and surfacing Once plus maintenance Plant management R100 000 - R4 000 000 every 5 - 10 years

2) M61 Rd / Kalksteen Rd & Kalksteen Rd / Tilliet Rd: Road

signs, markings 8 5 2 4 60 - M Geometry and surfacing 2 4 2 2 16 - L Construct access Once plus maintenance Plant management R10 000 - R1 000 000 every 5 - 10 years

3) Public transport facility 2 4 2 3 24 - L Provision of public transport facility 2 4 2 2 16 - L Construction of public transport facility Once plus maintenance Plant management R10 000 - R1 000 000 every 5 - 10 years

4) Street lights at M61 Kalksteen Rd & Kalksteen / Tilliet

Rd intersections2 4 2 3 24 - L Provision of Street lights 2 4 2 2 16 - L Provision of Street lights Once plus maintenance Plant management R10 000 - R500 000 every 10 - 15 years

0 - L 0 - L

FREQUENCY RESPONSIBLE PERSON ANNUAL MANAGEMENT COST

CONSTRUCTION PHASE ACTIVITY 2: SITE CLEARANCE AND ROAD ESTABLISHMENT

Issues related to TRAFFIC

POTENTIAL ENVIRONMENTAL IMPACT ACTIVITY

ENVIRONMENTAL SIGNIFICANCE

BEFORE MITIGATION

RECOMMENDED MITIGATION MEASURES

ENVIRONMENTAL SIGNIFICANCE

AFTER MITIGATION

ACTION PLAN

CONSTRUCTION PHASE ACTIVITY 3: PLANT AREA DEVELOPMENT

M D S P

TO

TA

L

STA

TU

S

SP M D S P

TO

TA

L

STA

TU

S

SP

1) Site clearance 2 2 1 4 20 - L No Impact 2 2 1 4 20 - L No Action Plan As and When required Plant management To be detemined at time of requirement

2) Construction of Plant 2 2 1 4 20 - L No Impact 2 2 1 4 20 - L No Action Plan As and When required Plant management To be detemined at time of requirement

3) Construction of Access Roads 2 2 1 4 20 - L No Impact 2 2 1 4 20 - L No Action Plan As and When required Plant management To be detemined at time of requirement

FREQUENCY RESPONSIBLE PERSON ANNUAL MANAGEMENT COST

CONSTRUCTION PHASE ACTIVITY 3: PLANT AREA DEVELOPMENT

Issues related to TRAFFIC

POTENTIAL ENVIRONMENTAL IMPACT ACTIVITY

ENVIRONMENTAL SIGNIFICANCE

BEFORE MITIGATION

RECOMMENDED MITIGATION MEASURES

ENVIRONMENTAL SIGNIFICANCE

AFTER MITIGATION

ACTION PLAN

CONSTRUCTION PHASE ACTIVITY 4: WATER MANAGEMENT ACTIVITIES

M D S P

TO

TA

L

STA

TU

S

SP M D S P

TO

TA

L

STA

TU

S

SP

1) Stormwater 2 2 2 4 24 - L No Impact 2 2 2 4 24 - L No action plan As and When required Plant management To be detemined at time of requirement

2) Construction of attenuation dams 2 2 2 4 24 - L No Impact 2 2 2 4 24 - L No action plan As and When required Plant management To be detemined at time of requirement

3) Construction of clear water system 2 2 2 4 24 - L No Impact 2 2 2 4 24 - L No action plan As and When required Plant management To be detemined at time of requirement

4) Construction of sewerage system 2 2 2 4 24 - L No Impact 2 2 2 4 24 - L No action plan As and When required Plant management To be detemined at time of requirement

FREQUENCY RESPONSIBLE PERSON ANNUAL MANAGEMENT COST

CONSTRUCTION PHASE ACTIVITY 4: WATER MANAGEMENT ACTIVITIES

Issues related to TRAFFIC

POTENTIAL ENVIRONMENTAL IMPACT ACTIVITY

ENVIRONMENTAL SIGNIFICANCE

BEFORE MITIGATION

RECOMMENDED MITIGATION MEASURES

ENVIRONMENTAL SIGNIFICANCE

AFTER MITIGATION

ACTION PLAN

Page 27: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

3302_AcetylenePlant - TIA Report – June 2014 19

Table 5.3: Operational Phase (Activity 5 to Activity 13)

CONSTRUCTION PHASE ACTIVITY 5: CALCIUM CARBIDE MANAGEMENT ACTIVITIES

M D S P

TO

TA

L

STA

TU

S

SP M D S P

TO

TA

L

STA

TU

S

SP

1) Development of a Calcium Carbide storage and

dispensing area2 2 2 4 24 - L No Impact 2 2 2 4 24 - L No action plan As and When required Plant management To be detemined at time of requirement

2) Development of a Calcium Hydroxide (lime) storage and

dispensing area2 2 2 4 24 - L No Impact 2 2 2 4 24 - L No action plan As and When required Plant management To be detemined at time of requirement

FREQUENCY RESPONSIBLE PERSON ANNUAL MANAGEMENT COST

CONSTRUCTION PHASE ACTIVITY 5: CALCIUM CALBIDE MANAGEMENT ACTIVITIES

Issues related to TRAFFIC

POTENTIAL ENVIRONMENTAL IMPACT ACTIVITY

ENVIRONMENTAL SIGNIFICANCE

BEFORE MITIGATION

RECOMMENDED MITIGATION MEASURES

ENVIRONMENTAL SIGNIFICANCE

AFTER MITIGATION

ACTION PLAN

CONSTRUCTION PHASE ACTIVITY 6: WASTE MANAGEMENT ACTIVITIES

M D S P

TO

TA

L

STA

TU

S

SP M D S P

TO

TA

L

STA

TU

S

SP

1) Development of a temporary waste sorting and storage

area2 2 2 4 24 - L No Impact 2 2 2 4 24 - L No action plan As and When required Plant management To be detemined at time of requirement

FREQUENCY RESPONSIBLE PERSON ANNUAL MANAGEMENT COST

CONSTRUCTION PHASE ACTIVITY 6: WASTE MANAGEMENT ACTIVITIES

Issues related to TRAFFIC

POTENTIAL ENVIRONMENTAL IMPACT ACTIVITY

ENVIRONMENTAL SIGNIFICANCE

BEFORE MITIGATION

RECOMMENDED MITIGATION MEASURES

ENVIRONMENTAL SIGNIFICANCE

AFTER MITIGATION

ACTION PLAN

CONSTRUCTION PHASE ACTIVITY 2: ESTABLISHMENT OF INFRASTRUCTURE

M D S P

TO

TA

L

STA

TU

S

SP M D S P

TO

TA

L

STA

TU

S

SP

1) Surfacing of Tilliet St 4 4 2 3 30 - M Surfacing 2 4 3 2 18 - L Change Geometry Once plus maintenance Development R10 000 - R1 000 000 every 5 - 10 years

2) M61 Rd / Kalksteen St intersection upgrades 4 4 2 3 30 - M Road signs and road markings 3 4 2 2 18 - L Change Geometry Once plus maintenance Development R10 000 - R1 000 000 every 5 - 10 years

3) Kalksteen St / Tilliet St intersection upgrades 2 4 2 3 24 - L Road signs and road markings 3 4 2 2 18 - L Construction of public transport facility Once plus maintenance Development R10 000 - R500 000 every 20 - 30 years

4) Street Lights at intersection 2 4 2 3 24 - L Provision of Street lights 2 2 2 3 18 - L Provision of Street lights Once plus maintenance Development R10 000 - R500 000 every 20 - 30 years

FREQUENCY RESPONSIBLE PERSON ANNUAL MANAGEMENT COST

CONSTRUCTION PHASE ACTIVITY 2: ESTABLISHMENT OF INFRASTRUCTURE

Issues related to TRAFFIC

POTENTIAL ENVIRONMENTAL IMPACT ACTIVITY

ENVIRONMENTAL SIGNIFICANCE

BEFORE MITIGATION

RECOMMENDED MITIGATION MEASURES

ENVIRONMENTAL SIGNIFICANCE

AFTER MITIGATION

ACTION PLAN

CONSTRUCTION PHASE ACTIVITY 3: PLANT CONSTRUCTION

M D S P

TO

TA

L

STA

TU

S

SP M D S P

TO

TA

L

STA

TU

S

SP

Traffic volumes 2 4 2 3 24 - L No recommendations 2 4 2 3 24 - L Maintain road Once plus maintenance Plant management R100 000 - R4 000 000 every 5 - 10 years

Traffic safety 2 4 2 3 24 - L No recommendations 2 4 2 3 24 - L Maintain road signs Once plus maintenance Plant management R10 000 - R250 000 every 5 - 10 years

FREQUENCY RESPONSIBLE PERSON ANNUAL MANAGEMENT COST

CONSTRUCTION PHASE ACTIVITY 3: PLANT CONSTRUCTION

Issues related to TRAFFIC

POTENTIAL ENVIRONMENTAL IMPACT ACTIVITY

ENVIRONMENTAL SIGNIFICANCE

BEFORE MITIGATION

RECOMMENDED MITIGATION MEASURES

ENVIRONMENTAL SIGNIFICANCE

AFTER MITIGATION

ACTION PLAN

CONSTRUCTION PHASE ACTIVITY 4: WASTE HANDLING

M D S P

TO

TA

L

STA

TU

S

SP M D S P

TO

TA

L

STA

TU

S

SP

Traffic volumes 2 4 2 3 24 - L No recommendations 2 4 2 3 24 - L No action plan No frequency Plant management Annual Operational budget

Traffic safety 2 4 2 3 24 - L No recommendations 2 4 2 3 24 - L No action plan No frequency Plant management Annual Operational budget

FREQUENCY RESPONSIBLE PERSON ANNUAL MANAGEMENT COST

CONSTRUCTION PHASE ACTIVITY 4: WASTE HANDLING

Issues related to TRAFFIC

POTENTIAL ENVIRONMENTAL IMPACT ACTIVITY

ENVIRONMENTAL SIGNIFICANCE

BEFORE MITIGATION

RECOMMENDED MITIGATION MEASURES

ENVIRONMENTAL SIGNIFICANCE

AFTER MITIGATION

ACTION PLAN

OPERATIONAL PHASE ACTIVITY 5: STOCKPILING

M D S P

TO

TA

L

STA

TU

S

SP M D S P

TO

TA

L

STA

TU

S

SP

Calcium Carbide stockpile - No Impact 2 4 1 4 28 - L No Recommendation 2 4 1 4 28 - L Conveyer Long-term Plant Manager No annual cost

Calcium Hydroxide stockpile - No Impact 2 4 1 4 28 - L No Recommendation 2 4 1 4 28 - L Conveyer Long-term Plant Manager No annual cost

FREQUENCY RESPONSIBLE PERSON ANNUAL MANAGEMENT COST

OPERATIONAL PHASE ACTIVITY 2: STOCKPILING

Issues related to TRAFFIC

POTENTIAL ENVIRONMENTAL IMPACT ACTIVITY

ENVIRONMENTAL SIGNIFICANCE

BEFORE MITIGATION

RECOMMENDED MITIGATION MEASURES

ENVIRONMENTAL SIGNIFICANCE

AFTER MITIGATION

ACTION PLAN

Page 28: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

3302_AcetylenePlant - TIA Report – June 2014 20

OPERATIONAL PHASE ACTIVITY 6: PLANT

M D S P

TO

TA

L

STA

TU

S

SP M D S P

TO

TA

L

STA

TU

S

SP

Traffic volumes - No Impact 0 4 1 4 20 - L No Recommendation 0 4 1 4 20 - L No Action plan Long-term Plant Manager No annual cost

Traffic safety - No Impact 0 4 1 4 20 - L No Recommendation 0 4 1 4 20 - L No Action plan Long-term Plant Manager No annual cost

FREQUENCY RESPONSIBLE PERSON ANNUAL MANAGEMENT COST

OPERATIONAL PHASE ACTIVITY 6: PLANT

Issues related to TRAFFIC

POTENTIAL ENVIRONMENTAL IMPACT ACTIVITY

ENVIRONMENTAL SIGNIFICANCE

BEFORE MITIGATION

RECOMMENDED MITIGATION MEASURES

ENVIRONMENTAL SIGNIFICANCE

AFTER MITIGATION

ACTION PLAN

OPERATIONAL PHASE ACTIVITY 7: PLANT PRODUCTION ACTIVITY

M D S P

TO

TA

L

STA

TU

S

SP M D S P

TO

TA

L

STA

TU

S

SP

1. Deliverable of Calcium Carbide 0 4 2 3 18 - L No Impact 0 4 2 3 18 - L On site storage Long-term Plant Manager Annual cost to be determined

2. Calcium Carbide stockpiling 0 4 2 3 18 - L No Impact 0 4 2 3 18 - L On site storage Long-term Plant Manager Annual cost to be determined

3. Production process 0 4 2 3 18 - L No Impact 0 4 2 3 18 - L On site Long-term Plant Manager Annual cost to be determined

4. Calcium Hydroxide (lime) stockpile 0 4 2 3 18 - L No Impact 0 4 2 3 18 - L On site storage Long-term Plant Manager Annual cost to be determined

0 - L 0 - L Long-term Plant Manager Annual cost to be determined

FREQUENCY RESPONSIBLE PERSON ANNUAL MANAGEMENT COST

OPERATIONAL PHASE ACTIVITY 7: PLANT PRODUCTION ACTIVITY

Issues related to TRAFFIC

POTENTIAL ENVIRONMENTAL IMPACT ACTIVITY

ENVIRONMENTAL SIGNIFICANCE

BEFORE MITIGATION

RECOMMENDED MITIGATION MEASURES

ENVIRONMENTAL SIGNIFICANCE

AFTER MITIGATION

ACTION PLAN

OPERATIONAL PHASE ACTIVITY 8: PROCESS ACTIVITY

M D S P

TO

TA

L

STA

TU

S

SP M D S P

TO

TA

L

STA

TU

S

SP

1. Calcium Carbide granules feed to reaction chamber 0 4 1 4 20 - L No Impact 0 4 1 4 20 - L Heavy vehicle transport Long-term Plant Manager Annual cost to be determined

2. Operation of plant 0 4 1 4 20 - L No Impact 0 4 1 4 20 - L Screw Conveyer and pipe system Long-term Plant Manager Annual cost to be determined

3. Stockpiles and export stockpiles (Calcium Hydroxide) 0 4 1 4 20 - L No Impact 0 4 2 4 24 - L Screw Conveyer and pipe system Long-term Plant Manager Annual cost to be determined

4. Transport of calcium hydroxide (lime) product off site 0 4 1 4 20 - L No Impact 0 4 2 4 24 - L Heavy vehicle transport Long-term Plant Manager Annual cost to be determined

FREQUENCY RESPONSIBLE PERSON ANNUAL MANAGEMENT COST

OPERATIONAL PHASE ACTIVITY 8: PROCESS ACTIVITY

Issues related to TRAFFIC

POTENTIAL ENVIRONMENTAL IMPACT ACTIVITY

ENVIRONMENTAL SIGNIFICANCE

BEFORE MITIGATION

RECOMMENDED MITIGATION MEASURES

ENVIRONMENTAL SIGNIFICANCE

AFTER MITIGATION

ACTION PLAN

OPERATIONAL PHASE ACTIVITY 9: CALCIUM CARBIDE MANAGEMENT ACTIVITIES

M D S P

TO

TA

L

STA

TU

S

SP M D S P

TO

TA

L

STA

TU

S

SP

1. Calcium Carbide storage and dispensing 0 4 1 4 20 - L No Impact 0 4 1 4 20 - L Cover material Long-term Plant Manager No annual cost

FREQUENCY RESPONSIBLE PERSON ANNUAL MANAGEMENT COST

OPERATIONAL PHASE ACTIVITY 9: CALCIUM CARBIDE MANAGEMENT ACTIVITIES

Issues related to TRAFFIC

POTENTIAL ENVIRONMENTAL IMPACT ACTIVITY

ENVIRONMENTAL SIGNIFICANCE

BEFORE MITIGATION

RECOMMENDED MITIGATION MEASURES

ENVIRONMENTAL SIGNIFICANCE

AFTER MITIGATION

ACTION PLAN

OPERATIONAL PHASE ACTIVITY 10: WATER MANAGEMENT ACTIVITIES

M D S P

TO

TA

L

STA

TU

S

SP M D S P

TO

TA

L

STA

TU

S

SP

1. Use and maintenance of storm water management

systems0 4 1 4 20 - L No Recommendation 0 4 1 4 20 - L Pipe system Long-term Plant Manager No annual cost

2. Use and operation of clean water systems 0 4 1 4 20 - L No Recommendation 0 4 1 4 20 - L Pipe system Long-term Plant Manager No annual cost

4. Operation of sewerage systems 0 4 1 4 20 - L No Recommendation 0 4 1 4 20 - L Pipe system Long-term Plant Manager No annual cost

FREQUENCY RESPONSIBLE PERSON ANNUAL MANAGEMENT COST

OPERATIONAL PHASE ACTIVITY 10: WATER MANAGEMENT ACTIVITIES

Issues related to TRAFFIC

POTENTIAL ENVIRONMENTAL IMPACT ACTIVITY

ENVIRONMENTAL SIGNIFICANCE

BEFORE MITIGATION

RECOMMENDED MITIGATION MEASURES

ENVIRONMENTAL SIGNIFICANCE

AFTER MITIGATION

ACTION PLAN

OPERATIONAL PHASE ACTIVITY 11: TREATMENT OF SEWAGE EFFLUENT

M D S P

TO

TA

L

STA

TU

S

SP M D S P

TO

TA

L

STA

TU

S

SP

Traffic volumes - No Impact 0 4 1 4 20 - L No Recommendation 0 4 1 4 20 - L Sewer & wast water plant Long-term Plant Manager No annual cost

Traffic safety - No Impact 0 4 1 4 20 - L No Recommendation 0 4 1 4 20 - L Sewer & wast water plant Long-term Plant Manager No annual cost

FREQUENCY RESPONSIBLE PERSON ANNUAL MANAGEMENT COST

OPERATIONAL PHASE ACTIVITY 8: TREATMENT OF SEWAGE EFFLUENT

Issues related to TRAFFIC

POTENTIAL ENVIRONMENTAL IMPACT ACTIVITY

ENVIRONMENTAL SIGNIFICANCE

BEFORE MITIGATION

RECOMMENDED MITIGATION MEASURES

ENVIRONMENTAL SIGNIFICANCE

AFTER MITIGATION

ACTION PLAN

Page 29: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

3302_AcetylenePlant - TIA Report – June 2014 21

Table 5.4: Closure and Decommissioning Phase (Activity 14 to Activity 16)

Table 5.5: Cumulative Impacts

OPERATIONAL PHASE ACTIVITY 12: WASTE MANAGEMENT ACTIVITIES

M D S P

TO

TA

L

STA

TU

S

SP M D S P

TO

TA

L

STA

TU

S

SP

1. Collection and separation of waste 0 4 1 4 20 - L No Recommendation 0 4 1 4 20 - L Skip bins Long-term Plant Manager No annual cost

2. Management of waste storage area 0 4 1 4 20 - L No Recommendation 0 4 1 4 20 - L Skip bins Long-term Plant Manager No annual cost

FREQUENCY RESPONSIBLE PERSON ANNUAL MANAGEMENT COST

OPERATIONAL PHASE ACTIVITY 11: WASTE MANAGEMENT ACTIVITIES

Issues related to TRAFFIC

POTENTIAL ENVIRONMENTAL IMPACT ACTIVITY

ENVIRONMENTAL SIGNIFICANCE

BEFORE MITIGATION

RECOMMENDED MITIGATION MEASURES

ENVIRONMENTAL SIGNIFICANCE

AFTER MITIGATION

ACTION PLAN

OPERATIONAL PHASE ACTIVITY 13: REHABILITATION AND MAINTENANCE OF PLANT

M D S P

TO

TA

L

STA

TU

S

SP M D S P

TO

TA

L

STA

TU

S

SP

1. Rehabilitation and Maintenance of Plant 0 4 1 4 20 - L No Impact 0 4 1 4 20 - L Internal process Long-term Plant Manager No annual cost

FREQUENCY RESPONSIBLE PERSON ANNUAL MANAGEMENT COST

OPERATIONAL PHASE ACTIVITY 12: REHABILITATION AND MAINTENANCE OF PLANT

Issues related to TRAFFIC

POTENTIAL ENVIRONMENTAL IMPACT ACTIVITY

ENVIRONMENTAL SIGNIFICANCE

BEFORE MITIGATION

RECOMMENDED MITIGATION MEASURES

ENVIRONMENTAL SIGNIFICANCE

AFTER MITIGATION

ACTION PLAN

CLOSURE AND DECOMMISSIONING PHASE ACTIVITY 14: REHABILITATION ACTIVITIES

M D S P

TO

TA

L

STA

TU

S

SP M D S P

TO

TA

L

STA

TU

S

SP

1. Removal of all infrastructure 2 2 1 4 20 - L No recommendations 2 2 1 4 20 - L No action Short-term Plant Manager No annual cost

FREQUENCY RESPONSIBLE PERSON ANNUAL MANAGEMENT COST

CLOSURE AND DECOMMISSIONING PHASE ACTIVITY 14: REHABILITATION ACTIVITIES

Issues related to TRAFFIC

POTENTIAL ENVIRONMENTAL IMPACT ACTIVITY

ENVIRONMENTAL SIGNIFICANCE

BEFORE MITIGATION

RECOMMENDED MITIGATION MEASURES

ENVIRONMENTAL SIGNIFICANCE

AFTER MITIGATION

ACTION PLAN

CLOSURE AND DECOMMISSIONING PHASE ACTIVITY 15: ENVIRONMENTAL MONITORING OF DECOMMISSIONING ACTIVITIES

M D S P

TO

TA

L

STA

TU

S

SP M D S P

TO

TA

L

STA

TU

S

SP

1. Environmental monitoring of decommissioning 0 4 1 4 20 - L No recommendations 0 4 1 4 20 - L No action Short-term Plant Manager No annual cost

FREQUENCY RESPONSIBLE PERSON ANNUAL MANAGEMENT COST

CLOSURE AND DECOMMISSIONING PHASE ACTIVITY 15: ENVIRONMENTAL MONITORING OF DECOMMISSIONING ACTIVITIES

Issues related to TRAFFIC

POTENTIAL ENVIRONMENTAL IMPACT ACTIVITY

ENVIRONMENTAL SIGNIFICANCE

BEFORE MITIGATION

RECOMMENDED MITIGATION MEASURES

ENVIRONMENTAL SIGNIFICANCE

AFTER MITIGATION

ACTION PLAN

POST-CLOSURE PHASE ACTIVITY 16: POST-CLOSURE MONITORING AND REHABILITATION ACTIVITIES

M D S P

TO

TA

L

STA

TU

S

SP M D S P

TO

TA

L

STA

TU

S

SP

1. Post-closure monitoring and rehabilitation 0 4 1 4 20 - L No recommendations 0 4 1 4 20 - L No action Short-term Plant Manager No annual cost

FREQUENCY RESPONSIBLE PERSON ANNUAL MANAGEMENT COST

CLOSURE AND DECOMMISSIONING PHASE ACTIVITY 16: POST-CLOSURE MONITORING AND REHABILITATION ACTIVITIES

Issues related to TRAFFIC

POTENTIAL ENVIRONMENTAL IMPACT ACTIVITY

ENVIRONMENTAL SIGNIFICANCE

BEFORE MITIGATION

RECOMMENDED MITIGATION MEASURES

ENVIRONMENTAL SIGNIFICANCE

AFTER MITIGATION

ACTION PLAN

CUMULATIVE IMPACT ASSESSMENT

M D S P

TO

TA

L

STA

TU

S

SP M D S P

TO

TA

L

STA

TU

S

SP

Traffic volumes 6 4 3 3 39 - M Monitor and mitigate frequently 4 4 3 2 22 - L Setup monitor and action plan Monthly Plant Manager Annual Capilal and Operational cost

Traffic safety 6 4 3 3 39 - M Monitor and mitigate frequently 4 4 3 2 22 - L Setup monitor and action plan Monthly Plant Manager Annual Capilal and Operational cost

FREQUENCY RESPONSIBLE PERSON ANNUAL MANAGEMENT COST

CUMULATIVE IMPACT ASSESSMENT

Issues related to TRAFFIC

POTENTIAL ENVIRONMENTAL IMPACT ACTIVITY

ENVIRONMENTAL SIGNIFICANCE

BEFORE MITIGATION

RECOMMENDED MITIGATION MEASURES

ENVIRONMENTAL SIGNIFICANCE

AFTER MITIGATION

ACTION PLAN

Page 30: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

3302_AcetylenePlant - TIA Report – June 2014 22

Based on the impact rating in Table 5.5 above, it is evident that the existing and development

traffic volumes would have a small impact on the existing M61 / Kalksteen Road and Tilliet Road

/ Access Road intersections and no upgrades would be required to accommodate the additional

traffic volumes. It is recommended that Tilliet Road be surfaced and that the M61 Road /

Kalksteen Road and Kalksteen Road / Tilliet Road intersections be upgraded by

provision of road signs and road markings according to SARTSM requirements.

The traffic volumes generated by the proposed Acetylene Gas Production Plant development

does not have a significant impact on the external road network. In terms of the intersection and

road link capacity, no further improvements are recommended since the intersections under

investigation are expected to operate at acceptable level of service with the proposed upgrades

in place. The interaction (turning movements) between public transport and privates vehicles

might impose some safety hazardous to the vehicles drivers.

It is therefore recommended that the following measures be adopted to mitigate the impact:

Surfacing of Tilliet Road between Kalksteen Road / Tilliet Road intersection and the

access to the Acetylene Gas Production Plant approximately 450m.

Upgrade of the existing M61 Road / Kalksteen Road and Kalksteen Road / Tilliet Road

intersections by providing road sign and road markings according to the SARTSM

requirements.

Provision of lighting at sufficient standards at the intersections of the Kalksteen Road /

Tilliet Road.

No on-street pick up/drop off’s at the intersections of the Tilliet Road and the access to the

development should be allowed (drop-offs / pickup should be done on site).

 

 

Page 31: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

3302_AcetylenePlant - TIA Report – June 2014 23

6 CONCLUSIONS

The following conclusions are drawn based on the findings of the traffic impact

assessment conducted for proposed Acetylene Gas Production Plant.

The proposed development will have a life span of approximately more than 20

years. From year 1 to year 3 of operation the production rates are expected to rise

reaching a steady curve thereof. The critical impact in terms of the traffic generated

is expected to be around Year 5 of construction. According to the development

implementation plan the following scenarios were considered for assessment:

o Scenario 1: 2014 Existing Traffic Volumes;

o Scenario 2: 2019 Background projected traffic demand;

o Scenario 3: 2039 Background projected traffic demand and Plant Traffic Demand; and

o Scenario 4: 2040 Background projected traffic demand and Plant Traffic Demand.

Currently the M61 Road / Kalksteen Road and the Kalksteen Road / Tilliet Road

intersections within the influence area of the proposed Acetylene Gas Production

Plant, operate at acceptable LOS. No upgrades would be required to accommodate

the existing traffic volumes.

In scenario 3 (2019 projected volumes and proposed development traffic) all

intersections under assessment are expected to operate at an acceptable level.

The M61 (K68) Road located east of the proposed Acetylene Gas Production Plant

site is a future planned K-route.

The future K68 route planning will not be impacted by the proposed future K68road.

The future alignment of the K68 route will impact on Tilliet Road and a portion of

Tilliet Road will be closed to accommodate the alignment of the K68 route. Access

to Tilliet Road would be provided from Kalksteen Road.

Surfacing of Tilliet Road between Kalksteen Road / Tilliet Road intersection and the

access to the Acetylene Gas Production Plant approximately 450m.

The M61 Road / Kalksteen Road and Kalksteen Road / Tilliet Road intersections

must be upgraded by the provision of road signs and road markings according to

the SARTSM requirements.

Page 32: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

3302_AcetylenePlant - TIA Report – June 2014 24

It must be noted that the proposed road improvement is recommended to be implemented at the start of the Acetylene Gas Production activities (Year 1 of operations).

It is recommended to improve the safety at the Kalksteen Road / Tilliet Road and

M61 Road / Kalksteen Road intersections be providing the intersections with street

lights.

In terms of public transport provision as well as pedestrian safety no on-street pick

up / drop offs at the intersection of Tilliet Road and the access to the Plant, should

be allowed (drop-offs / pickup should be done on site).

Page 33: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

3302_AcetylenePlant - TIA Report – June 2014 25

7 RECOMMENDATIONS

The findings of the traffic impact assessment for proposed Acetylene Gas Production

Plant conclude that the proposed development will not have a negative impact on the

existing road networks within the project area. However, certain mitigation measures

have been recommended to accommodate the background traffic demand and the

proposed development traffic in year 2019 and beyond (for the duration of the Plant life

span).

Based on the conclusions of this assessment, it is recommended that the proposed

development should be favourably considered from a traffic engineering point of view

by the relevant authorities.

Page 34: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

APPENDIX A: FIGURES

Page 35: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

ACETYLENE

PLANT

1

2

3

4

R

5

9

R

5

9

WITKOPDORP

(DALESIDE)

K

A

L

K

S

T

E

E

N

R

D

G

R

A

N

IE

T

R

D

L

A

W

A

R

D

T

IL

L

IE

T

R

D

M

6

1

M

6

1

LOCALITY PLAN 1

FIGURE: NUMBER:PROJECT:

3302\Fig 1.dwg

LEGEND

Site

Provincial Roads

Local Roads

ACETYLENE PLANT

Page 36: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

EXISTING GEOMETRY AND CONTROLACETYLENE PLANT 2

FIGURE: NUMBER:PROJECT:

3302\Fig 2.dwg

LEGEND

STOP CONTROL

LEFT LANE

THROUGH LANE

RIGHT LANE

SHARED LANE

TRAFFIC SIGNAL

SHARED LANE

SHARED LANE

1

2 3

4

PROPOSED

SITE

LA

WA

RD

GR

AN

IE

T R

D

TIL

LIE

T R

D

M6

1

KALKSTEEN RDKALKSTEEN RD

M6

1M

61

Page 37: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

ACETYLENE PLANT 3

FIGURE: NUMBER:PROJECT:

3302\Fig 3.dwg

SCENARIO 1a: 2013 AM PEAK HOUR EXISTINGTRAFFIC

VOLUMES AND CAPACITY ANALYSIS RESULTS

1

2 3

4

PROPOSED

SITE

LA

WA

RD

GR

AN

IE

T R

D

TIL

LIE

T R

D

M6

1

KALKSTEEN RDKALKSTEEN RD

M6

1M

61

LOS=C

Del=17.1

V/C=0.05

1 22

81

111

1

2

1 7

7

1

LOS=A

Del=1.7

V/C=0.01

1 2

12

1 3

17

LOS=A

Del=1.3

V/C=0.12

7 20

41

948

18

4

LOS=A

Del=0.6

V/C=0.12

1 21

01

971

1

2

LEGEND

TURNING VOLUMES (vph)

LEVEL OF SERVICE

DELAY (SECONDS/VEHICLE)

VOLUME / CAPACITY RATIO

PROPOSED SITE

V/C

Del

LOS

10

10

10

Page 38: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

4

FIGURE: NUMBER:PROJECT:

3302\Fig 4.dwg

1

2 3

4

PROPOSED

SITE

LA

WA

RD

GR

AN

IE

T R

D

TIL

LIE

T R

D

M6

1

KALKSTEEN RDKALKSTEEN RD

M6

1M

61

LOS=C

Del=17.4

V/C=0.04

1 12

61

201

1

6

1 5

5

2

LOS=A

Del=1.9

V/C=0.01

1 1

13

1 4

12

LOS=A

Del=0.6

V/C=0.13

16

18

22

221

13

2

LOS=A

Del=1.2

V/C=0.13

4 18

62

10

14

20

4

ACETYLENE PLANT

SCENARIO 1b: 2013 PM PEAK HOUR EXISTING TRAFFIC

VOLUMES AND CAPACITY ANALYSIS RESULTS

LEGEND

TURNING VOLUMES (vph)

LEVEL OF SERVICE

DELAY (SECONDS/VEHICLE)

VOLUME / CAPACITY RATIO

PROPOSED SITE

V/C

Del

LOS

10

10

10

Page 39: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

ACETYLENE PLANT 5

FIGURE: NUMBER:PROJECT:

3302\Fig 5.dwg

SCENARIO 2a: 2018 AM PEAK HOUR BACKGROUND TRAFFIC

VOLUMES AND CAPACITY ANALYSIS RESULTS

1

2 3

4

PROPOSED

SITE

LA

WA

RD

GR

AN

IE

T R

D

TIL

LIE

T R

D

M6

1

KALKSTEEN RDKALKSTEEN RD

M6

1M

61

LOS=C

Del=17.1

V/C=0.06

1 26

91

131

1

2

1 8

8

1

LOS=A

Del=1.5

V/C=0.01

1 2

15

1 3

19

LOS=A

Del=1.5

V/C=0.13

8 23

62

259

21

5

LOS=A

Del=1.5

V/C=0.13

1 24

32

281

1

2

LEGEND

TURNING VOLUMES (vph)

LEVEL OF SERVICE

DELAY (SECONDS/VEHICLE)

VOLUME / CAPACITY RATIO

PROPOSED SITE

V/C

Del

LOS

10

10

10

Page 40: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

6

FIGURE: NUMBER:PROJECT:

3302\Fig 6.dwg

1

2 3

4

PROPOSED

SITE

LA

WA

RD

GR

AN

IE

T R

D

TIL

LIE

T R

D

M6

1

KALKSTEEN RDKALKSTEEN RD

M6

1M

61

LOS=C

Del=17.4

V/C=0.04

1 14

71

231

1

7

1 6

6

2

LOS=A

Del=1.8

V/C=0.01

1 1

14

1 5

15

LOS=A

Del=1.3

V/C=0.14

19

21

12

571

15

2

LOS=A

Del=1.6

V/C=0.16

5 21

62

43

16

23

5

ACETYLENE PLANT

SCENARIO 2b: 2018 PM PEAK HOUR BACKGROUND TRAFFIC

VOLUMES AND CAPACITY ANALYSIS RESULTS

LEGEND

TURNING VOLUMES (vph)

LEVEL OF SERVICE

DELAY (SECONDS/VEHICLE)

VOLUME / CAPACITY RATIO

PROPOSED SITE

V/C

Del

LOS

10

10

10

Page 41: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

7

FIGURE: NUMBER:PROJECT:

3302\Fig 7.dwg

OUTBOUND TRAFFIC IN PERCENTAGE

INBOUND TRAFFIC IN PERCENTAGE

PROPOSED SITE

10%

(10%)

PROPOSED ROAD

LEGEND

EXPECTED TRIP DISTRIBUTION

1

2 3

LA

WA

RD

GR

AN

IE

T R

D

TIL

LIE

T R

D

M6

1

KALKSTEEN RDKALKSTEEN RD

M6

1M

61

100%

(1

00

%)

5

10

0%

(100%)

PROPOSED

SITE

50

%

(50%)

50

%

(50%)

50

%(5

0%

)

ACETYLENE PLANT

Page 42: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

8

FIGURE: NUMBER:PROJECT:

3302\Fig 8.dwg

TRIP ASSIGNMENT (AM PEAK HOUR)

OUTBOUND TRAFFIC IN PERCENTAGE

PROPOSED SITE

PROPOSED ROAD

10

10

10

LEGEND

1

2 3

LA

WA

RD

GR

AN

IE

T R

D

TIL

LIE

T R

D

M6

1

KALKSTEEN RDKALKSTEEN RD

M6

1M

61

76

20

5

76

20

PROPOSED

SITE

38

10

38

10

38

10

ACETYLENE PLANT

Page 43: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of
Page 44: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of
Page 45: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

APPENDIX B: SITE PLAN

Page 46: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of
Page 47: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

APPENDIX C: GAUTRANS BASIC PLANNING

Page 48: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of
Page 49: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

APPENDIX D: TRAFFIC COUNT DATA

Page 50: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

TRAFFIC COUNT: AcetylenePlant

INTERSECTION: Tillet Rd_M61

PEAK PERIOD: AM

DATE:

Cumulative Volumes Per Hour

15 min PHF

START END 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 Total Highest Intersection

06:00 06:15 0 34 14 0 0 0

06:15 06:30 0 88 53 0 0 0

06:30 06:45 0 138 82 0 0 0

06:45 07:00 0 197 126 0 0 0 0 197 0 0 0 0 0 126 0 0 0 0 323 103 0.78

07:00 07:15 0 248 185 0 0 1 0 214 0 0 0 0 0 171 0 0 0 1 386 111 0.87

07:15 07:30 0 300 230 0 0 1 0 212 0 0 0 0 0 177 0 0 0 1 390 111 0.88

07:30 07:45 0 348 279 1 0 2 0 210 0 0 0 0 0 197 1 0 0 2 410 111 0.92

07:45 08:00 0 388 316 1 0 2 0 191 0 0 0 0 0 190 1 0 0 2 384 111 0.86

08:00 08:15 0 418 341 1 0 2 0 170 0 0 0 0 0 156 1 0 0 1 328 99 0.83

08:15 08:30 0 440 369 1 0 2 0 140 0 0 0 0 0 139 1 0 0 1 281 99 0.71

08:30 08:45 1 470 406 1 0 2 1 122 0 0 0 0 0 127 0 0 0 0 250 77 0.81

08:45 09:00 4 501 438 1 0 3 4 113 0 0 0 0 0 122 0 0 0 1 240 68 0.88

Northbound Westbound Southbound EastboundEastboundSouthboundTIME

13/11/2013

Northbound Westbound

TRAFFIC COUNT: AcetylenePlant

INTERSECTION: Tillet Rd_M61

PEAK PERIOD: PM

DATE:

Cumulative Volumes Per Hour

15 min PHF

START END 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 Total Highest Intersection

15:00 15:15 0 39 20 1 2 2

15:15 15:30 0 57 61 4 4 3

15:30 15:45 1 93 88 6 8 3

15:45 16:00 3 124 126 7 8 3 3 124 0 0 0 0 0 126 7 8 0 3 271 72 0.94

16:00 16:15 3 156 156 8 12 3 3 117 0 0 0 0 0 136 7 10 0 1 274 72 0.95

16:15 16:30 4 198 204 11 17 3 4 141 0 0 0 0 0 143 7 13 0 0 308 99 0.78

16:30 16:45 4 249 261 16 21 4 3 156 0 0 0 0 0 173 10 13 0 1 356 118 0.75

16:45 17:00 6 290 321 20 24 5 3 166 0 0 0 0 0 195 13 16 0 2 395 118 0.84

17:00 17:15 7 322 361 22 32 7 4 166 0 0 0 0 0 205 14 20 0 4 413 118 0.88

17:15 17:30 8 354 415 24 33 7 4 156 0 0 0 0 0 211 13 16 0 4 404 118 0.86

17:30 17:45 9 380 495 26 43 8 5 131 0 0 0 0 0 234 10 22 0 4 406 120 0.85

13/11/2013

EastboundTIME Northbound Westbound Southbound Southbound EastboundNorthbound Westbound

Intersection 1: Tilliet St_M61 INTERSECTION: Kalksteen Rd_Graniet St

PEAK PERIOD: AM

Cumulative Volumes Per Hour

15 min PHF

START END 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 Total Highest Intersection

06:00 06:15 0 2 0 2 0 0 0 3 0 1 0 0

06:15 06:30 0 3 5 3 1 0 0 8 0 1 1 0

06:30 06:45 0 9 5 6 2 0 0 11 0 1 2 0

06:45 07:00 0 11 6 8 4 0 0 12 0 1 2 0 0 11 6 8 4 0 0 12 0 1 2 0 44 14 0.79

07:00 07:15 1 19 7 10 5 1 0 12 0 2 2 0 1 17 7 8 5 1 0 9 0 1 2 0 51 15 0.85

07:15 07:30 1 25 8 12 8 1 0 15 0 2 2 0 1 22 3 9 7 1 0 7 0 1 1 0 52 15 0.87

07:30 07:45 1 31 13 13 9 1 0 22 0 2 4 0 1 22 8 7 7 1 0 11 0 1 2 0 60 22 0.68

07:45 08:00 1 36 15 14 11 2 0 22 0 2 6 0 1 25 9 6 7 2 0 10 0 1 4 0 65 22 0.74

08:00 08:15 1 39 16 14 11 2 0 23 0 2 6 0 0 20 9 4 6 1 0 11 0 0 4 0 55 22 0.63

08:15 08:30 1 44 16 16 12 2 0 24 0 3 6 0 0 19 8 4 4 1 0 9 0 1 4 0 50 22 0.57

08:30 08:45 2 47 16 16 13 2 0 26 0 3 10 0 1 16 3 3 4 1 0 4 0 1 6 0 39 13 0.75

08:45 09:00 2 49 17 18 14 2 0 30 0 4 10 0 1 13 2 4 3 0 0 8 0 2 4 0 37 11 0.84

EastboundTIME Northbound Westbound Southbound Northbound Westbound Southbound Eastbound

INTERSECTION: Kalksteen Rd_Graniet St

PEAK PERIOD: PM

DATE:

Cumulative Volumes Per Hour

15 min PHF

START END 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 Total Highest Intersection

15:00 15:15 0 2 2 0 2 0 2 4 3 0 0 0

15:15 15:30 0 2 2 1 2 0 2 4 3 0 0 0

15:30 15:45 0 7 2 1 2 1 2 7 3 0 3 0

15:45 16:00 0 8 2 3 4 2 3 10 5 1 3 0 0 8 2 3 4 2 3 10 5 1 3 0 41 15 0.68

16:00 16:15 0 13 6 4 4 2 4 12 6 2 4 0 0 11 4 4 2 2 2 8 3 2 4 0 42 16 0.66

16:15 16:30 0 15 10 4 6 2 4 13 6 2 5 0 0 13 8 3 4 2 2 9 3 2 5 0 51 16 0.80

16:30 16:45 0 20 10 4 6 3 4 24 6 2 7 0 0 13 8 3 4 2 2 17 3 2 4 0 58 19 0.76

16:45 17:00 0 22 11 8 7 3 4 28 6 2 7 0 0 14 9 5 3 1 1 18 1 1 4 0 57 19 0.75

17:00 17:15 0 25 12 9 9 4 5 32 6 2 10 0 0 12 6 5 5 2 1 20 0 0 6 0 57 19 0.75

17:15 17:30 0 28 14 12 9 4 5 34 6 2 11 0 0 13 4 8 3 2 1 21 0 0 6 0 58 19 0.76

17:30 17:45 2 30 16 13 10 4 7 37 6 3 12 0 2 10 6 9 4 1 3 13 0 1 5 0 54 16 0.84

EastboundEastboundSouthbound Northbound Westbound SouthboundTIME Northbound Westbound

13/11/2013

Intersection 2: Kalksteen St_Graniet St

Page 51: Acetylene Gas Production Facility, Gauteng Province - …€¦ · Acetylene Gas Production Facility, Gauteng Province ... similar gas production operations, ... geometric Design of

INTERSECTION: Kalksteen Rd_M61

PEAK PERIOD: AM

Cumulative Volumes Per Hour

15 min PHF

START END 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 Total Highest Intersection

06:00 06:15 0 40 16 1 2 1

06:15 06:30 0 87 43 2 6 2

06:30 06:45 1 140 70 4 12 2

06:45 07:00 5 191 105 7 15 4 5 191 0 0 0 0 0 105 7 15 0 4 327 98 0.83

07:00 07:15 6 238 152 9 20 5 6 198 0 0 0 0 0 136 8 18 0 4 370 103 0.90

07:15 07:30 7 296 195 10 22 6 7 209 0 0 0 0 0 152 8 16 0 4 396 106 0.93

07:30 07:45 8 346 238 12 30 6 7 206 0 0 0 0 0 168 8 18 0 4 411 106 0.97

07:45 08:00 8 384 265 13 33 7 3 193 0 0 0 0 0 160 6 18 0 3 383 106 0.90

08:00 08:15 8 414 293 15 34 7 2 176 0 0 0 0 0 141 6 14 0 2 341 106 0.80

08:15 08:30 9 434 321 15 34 7 2 138 0 0 0 0 0 126 5 12 0 1 284 104 0.68

08:30 08:45 11 457 346 16 37 7 3 111 0 0 0 0 0 108 4 7 0 1 234 70 0.84

08:45 09:00 12 484 373 19 39 7 4 100 0 0 0 0 0 108 6 6 0 0 224 61 0.92

EastboundNorthbound Westbound SouthboundTIME Northbound Westbound Southbound Eastbound

TRAFFIC COUNT: AcetylenePlant

INTERSECTION: Kalksteen Rd_M61

PEAK PERIOD: PM

DATE:

Cumulative Volumes Per Hour

15 min PHF

START END 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 Total Highest Intersection

15:00 15:15 0 40 40 1 0 1

15:15 15:30 0 56 82 1 0 5

15:30 15:45 0 93 109 1 0 5

15:45 16:00 0 118 149 1 0 5 0 118 0 0 0 0 0 149 1 0 0 5 273 82 0.83

16:00 16:15 0 155 183 1 0 5 0 115 0 0 0 0 0 143 0 0 0 4 262 71 0.92

16:15 16:30 1 190 233 1 0 5 1 134 0 0 0 0 0 151 0 0 0 0 286 86 0.83

16:30 16:45 1 236 298 1 0 5 1 143 0 0 0 0 0 189 0 0 0 0 333 111 0.75

16:45 17:00 2 289 353 1 0 7 2 171 0 0 0 0 0 204 0 0 0 2 379 111 0.85

17:00 17:15 4 321 405 1 0 7 4 166 0 0 0 0 0 222 0 0 0 2 394 111 0.89

17:15 17:30 4 354 462 1 0 7 3 164 0 0 0 0 0 229 0 0 0 2 398 111 0.90

17:30 17:45 4 387 482 1 0 7 3 151 0 0 0 0 0 184 0 0 0 2 340 111 0.77

TIME Northbound Westbound Southbound Eastbound

13/11/2013

Westbound Southbound EastboundNorthbound

Intersection 3: Kalksteen St_M61 Rd