sms_element 2_swps-1. mechanical ctl. in lifting ops

Upload: mgmglatt

Post on 03-Jun-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 SMS_Element 2_SWPs-1. Mechanical Ctl. in Lifting Ops.

    1/20

    PRIME AIR HVAC (Pte) Ltd Ref No: PASMS2009-2

    SAFETY MANAGEMENT SYSTEM

    Section : 2

    Element : Safe Work Practices

    Appendix : Safe Work Procedure

    Description: Control of Mechanical Lifting Operations

    Issue Date: 1stSept.2009

    Document No. SWP-01

    Revision Date: 1stSept.2011

    Revision No: 01

    Authorised By: Executive Director

    Page No. Page 1 of 20

    Safe Work Procedure Master List

    SNDocument

    No.Rev

    LevelEffective

    DateDescription Page

    1. SWP-01 B 1 Nov 2008 Control of Mechanical Lifting Operations 2 -2. SWP-02 B 1 Nov 2008 Confined Spaces and dangerous

    atmospheres

    3. SWP-03 B 1 Nov 2008 Blasting and Painting

    4. SWP-04 B 1 Nov 2008 Scaffolding and Temporary WorkPlatforms

    5. SWP-05 B 1 Nov 2008 Ladders

    6. SWP-06 B 1 Nov 2008 Working at Heights

    7. SWP-07 B 1 Nov 2008 Welding & Heating Operations8. SWP-08 B 1 Nov 2008 Handling and Control of Gas Cylinders

    9. SWP-09 B 1 Nov 2008 Fabrication

    10. SWP-10 B 1 Nov 2008 Site Radiography

    11. SWP -11 B 1 Nov 2008 Radiation Safety

    12. SWP -12 B 1 Nov 2008 Control of Substances Hazardous toHealth

    13. SWP -13 B 1 Nov 2008 Personal Protection Equipment14. SWP -14 B 1 Nov 2008 Housekeeping

    15. SWP -15 B 1 Nov 2008 Fitting of Abrasive Discs

    16. SWP -16 B 1 Nov 2008 High Pressure Hydro testing

    17. SWP -17 B 1 Nov 2008 Allocation of work to Safeguard Safety

    18. SWP -18 B 1 Nov 2008 Fire Prevention and Control19. SWP -19 B 1 Nov 2008 Portable Electrical Tools

    20. SWP -20 B 1 Nov 2008 Air Receiver

    21. SWP -21 B 1 Nov 2008 Noise

    22. SWP -22 B 1 Nov 2008 Forklift Safety

    23. SWP -23 B 1 Nov 2008 Lockout / Tag Out24. SWP -24 B 1 Nov 2008 Manual Lifting

  • 8/12/2019 SMS_Element 2_SWPs-1. Mechanical Ctl. in Lifting Ops.

    2/20

  • 8/12/2019 SMS_Element 2_SWPs-1. Mechanical Ctl. in Lifting Ops.

    3/20

    PRIME AIR HVAC (Pte) Ltd Ref No: PASMS2009-2

    SAFETY MANAGEMENT SYSTEM

    Section : 2

    Element : Safe Work Practices

    Appendix : Safe Work Procedure

    Description: Control of Mechanical Lifting Operations

    Issue Date: 1stSept.2009

    Document No. SWP-01

    Revision Date: 1stSept.2011

    Revision No: 01

    Authorised By: Executive Director

    Page No. Page 3 of 20

    1.2 Hydraulic Access Platforms

    All work platforms such as scissors lifts, elevating platforms, cherry pickers shall be properly

    maintained and shall be tested and certified by a competent and Ministry authorised third party.

    Maintenance records and certification records shall be available for inspection at the

    Maintenance Dept.

    2. ATTACHMENT: WORK PROCEDURES FOR LIFTING OPERATION

    2.1 Lifting operationdone by cranes should comply with all relevant legislation, regulations, code

    of practices and any sub-legislation or amendments made there under to. The list included but

    not limited to:

    - Workplace Safety and Health Act

    - Workplace Safety and Health (Lifting Equipment) Regulations

    - SS 536 : 2008 Singapore Standard for Safe Use of Mobile Cranes

    2.2 Craneused for lifting shall possess a valid LM Certificate and such certificate must be displayed

    on the crane.

    2.3 The Load Capacity Chart (manufacturer or certified by Approved Person) shall be displayed on

    the crane.

    2.4 Craneshall be marked with its safe working load (maximum and minimum radius), and the LM

    number or other means of identification.

    2.5 Craneshall be used in accordance with manufacturers operation instruction and / or the

    Approved Persons instructions.

    2.6 Craneshall be provided with:

    - An adequate braking mechanism;

    - A swing lock or swing brake capable of prevention of rotation;

    - A brake or other device adequate to bring the crane to a stop from any travel for which it isdesigned, together with a means of locking the crane so as to hold its stationary;

    - A load and / or radius indicator with warning alarm;

    - A load / radius table to be available in the crane cab of every variable radius jib-crane;

    - An automatic safe load indicator;

    - Crane hook with a safety latch to prevent displacement of the sling or load from the hook.

    2.7 Craneshall be examined by an Approved Personafter any major repair or any repair done on

    the hoisting or operating mechanism, boom / jib and after over loading incident.

    2.8 No craneshall be operated unless all measures are taken to prevent toppling or overturning or

    contact with overhead obstruction (such as structure, power line)

    2.9 When crane are reversing, an addition person shall be required to ensure that the path of travel is

    clear.

  • 8/12/2019 SMS_Element 2_SWPs-1. Mechanical Ctl. in Lifting Ops.

    4/20

    PRIME AIR HVAC (Pte) Ltd Ref No: PASMS2009-2

    SAFETY MANAGEMENT SYSTEM

    Section : 2

    Element : Safe Work Practices

    Appendix : Safe Work Procedure

    Description: Control of Mechanical Lifting Operations

    Issue Date: 1stSept.2009

    Document No. SWP-01

    Revision Date: 1stSept.2011

    Revision No: 01

    Authorised By: Executive Director

    Page No. Page 4 of 20

    2.10 Crane cabinshall lock when the operatoris not around. Unauthorised person shall not be

    permitted to enter in cab or operate the crane.

    2.11 Good housekeeping of the craneshall be exercised and maintained.

    2.12 Craneshall be maintained to ensure that all components of the lifting and operating mechanism

    are in good, safe and sound functioning condition.

    2.12 A maintenance programshall be required and implemented effectively for the crane, and the

    maintenance record shall be kept in the cabin.

    2.14 The operatorshall carry out daily inspection and testing of crane

    2.15 No lifting operationshall be performed when the load (stationary or otherwise) exceeds the safeworking load.

    2.16 The lifting supervisor must verify that the strength of lifting gearsand equipment are adequate

    and their certified SWL (Safe Working Load) are in line with the load they bear.

    2.17 The lifting operationarea and other areas with potential hazard / danger must be cordon off to

    prevent access for all unauthorized personnel. Only authorized personnel involved in the lifting

    shall be allowed in the lifting operation area.

    2.18 Safety measures shall be taken to address any potential hazards and / or danger that may arise out

    of the lifting operation.

    2.19 Weather forecasts shall be monitored before and during lifting work. No lifting shall beperformed during abnormal conditions like wind speed is too high, poor lighting, obscured view

    due to raining, etc.

    2.20 The operator shall be able to observe the load continually during lifting.

    2.21 The loads shall be raised vertically to avoid swinging during lifting.

    2.22 Whenever required the load shall be controlled by means of tag lines to prevent the load fromturning or swinging.

    2.23 Hoisting or lowering loose materials such as small brackets, cut pipes, etc, shall be done in

    covered containers or receptacles, and to be secured firmly.

    2.24 Only competent, trained and authorised person shall perform lifting and crane operation, rigging

    and signaling.

    2.25 Lifting Supervisors, riggersand signalersshall wear distinctively coloured safety helmets or

    other clearly identifiable clothing.

    2.26 Signals shall be specified. Two-way communications shall be arranged whenever required.

    2.27 Only authorised signalersshall be allowed to give signals and signs to the crane operator.

    2.28 All lifting gear must be identifiable and checked before and after use.

    2.29 When a load is suspended at two or more points with slings, the eyes of the lifting legs or the

    slings shall be shackled together and placed on the hook or shackled directly to the hoistinghook.

  • 8/12/2019 SMS_Element 2_SWPs-1. Mechanical Ctl. in Lifting Ops.

    5/20

    PRIME AIR HVAC (Pte) Ltd Ref No: PASMS2009-2

    SAFETY MANAGEMENT SYSTEM

    Section : 2

    Element : Safe Work Practices

    Appendix : Safe Work Procedure

    Description: Control of Mechanical Lifting Operations

    Issue Date: 1stSept.2009

    Document No. SWP-01

    Revision Date: 1stSept.2011

    Revision No: 01

    Authorised By: Executive Director

    Page No. Page 5 of 20

    2.30 Hoisting of personnel to height by crane is strictly prohibited, unless otherwise approval is given

    in writing by The Commissioner for Workplace Safety and Health (Ministry of Manpower).

    2.31 No crane shall operate in such a position and / or location that any part of the crane, its load in

    any position, the jib boom, or its swing comes within 3 metres of a live power line unless

    otherwise the power is de-energised or the crane shall be effectively earthed.

    2.32 Underground cables and / or pipelines which are crossing / located under the crane access shall

    be adequately protected with mats or steel plates to prevent damages.

    2.33 Using plate clamps

    2.34.1 Areas of work must be kept clear during operation.2.34.2 Loads must not be lifted a mans height. However tag lines can be used to control lifting.

    All lifting clamps are subjected to annual inspections by Ministry of Manpowers (MOM)Approved Examiner.

  • 8/12/2019 SMS_Element 2_SWPs-1. Mechanical Ctl. in Lifting Ops.

    6/20

    PRIME AIR HVAC (Pte) Ltd Ref No: PASMS2009-2

    SAFETY MANAGEMENT SYSTEM

    Section : 2

    Element : Safe Work Practices

    Appendix : Safe Work Procedure

    Description: Control of Mechanical Lifting Operations

    Issue Date: 1stSept.2009

    Document No. SWP-01

    Revision Date: 1stSept.2011

    Revision No: 01

    Authorised By: Executive Director

    Page No. Page 6 of 20

    ANY CHANGESTHAT MIGHT

    AFFECT LIFTINGPLAN OR RA?

    EXECUTE OPERATION REQUIRED

    Note: RA = Risk Assessment

  • 8/12/2019 SMS_Element 2_SWPs-1. Mechanical Ctl. in Lifting Ops.

    7/20

    PRIME AIR HVAC (Pte) Ltd Ref No: PASMS2009-2

    SAFETY MANAGEMENT SYSTEM

    Section : 2

    Element : Safe Work Practices

    Appendix : Safe Work Procedure

    Description: Control of Mechanical Lifting Operations

    Issue Date: 1stSept.2009

    Document No. SWP-01

    Revision Date: 1stSept.2011

    Revision No: 01

    Authorised By: Executive Director

    Page No. Page 7 of 20

    LIFTING PLAN APPENDIX 2

    Factory Number S21859X001 Date of Lifting Operation

    Location of Lifting Operation

    Lifting Plan No.

    Risk Assessment No.

    Method Statement No.

    Description of Lifting Operation (Step by step Description)

    Type of Lifting Operation Routine Lift Non-routine Lift

    Weight of Load:

    List the personnel involved in the lifting operation

    Description of Lifting Equipment to be used:

    Attach the lift geometry diagram for the designated lifting points.

    Has the lifting operationconsidered items as listed in thepre-lifting operation checklist?Refer to Appendix 3)

    Radio Hand Signals Visual

    Prepared by

    Name: Signature: Date:

    Reviewed by

    Name: Signature: Date:

    Approved byName: Signature: Date:

  • 8/12/2019 SMS_Element 2_SWPs-1. Mechanical Ctl. in Lifting Ops.

    8/20

    PRIME AIR HVAC (Pte) Ltd Ref No: PASMS2009-2

    SAFETY MANAGEMENT SYSTEM

    Section : 2

    Element : Safe Work Practices

    Appendix : Safe Work Procedure

    Description: Control of Mechanical Lifting Operations

    Issue Date: 1stSept.2009

    Document No. SWP-01

    Revision Date: 1stSept.2011

    Revision No: 01

    Authorised By: Executive Director

    Page No. Page 8 of 20

    PRE-LIFTING OPERATION CHECKLIST APPENDIX 3

    S/N Description Y/N Remark

    1 Load

    . Has the actual weight of the load inclusive of the rigging accessories beenestablished

    . Is the established load within the safe working load of the lifting equipment?

    . Is the load rigged to its centre of gravity?

    . Is a tag line provided to control movement of the load?

    . Is the load being lifted in a level and stable manner?2 Lifting equipment

    . Is the selected lifting equipment fit for purpose and appropriate for thelifting operation?

    . Has the lifting equipment been examined at least once in the last 12 months(or 6 months for those lifting personnel) by an authorised examiner and does itpossess a valid lifting equipment certificate?

    . Has the lifting equipment been marked conspicuously with the maximumworking load which can safely carry?

    3 Lifting Operation

    . Is the lifting plan available for the operation?

    . Has risk assessment been conducted to ensure that all possible hazards areeliminate and risks are reduced?

    . Has the identified control measured(s) been implemented?

    . Is the area lifting the load and the lifting path been cleared of obstructionand personnel?

    . Has the designated area for placing the load been cleared or properly preparedprior to the lifting operation?

    . Is the load likely to clash with other structures or equipment along itslifting path?

    . Has a safe means of access or egress been provided for personnel to attach orrecover the rigging of the load?

    . Has the means of communication during the lift been established anf confirmed?

    . Has the lifting zone been barricaded to prevent access by unauthorised

    personnel

    4 Personnel involved in lifting operation, such as equipmentoperator, signalman, rigger and lifting supervisor

    . Have trained and competent lifting personnel been identified for the liftingoperation?

    . Have all lifting personnel such as operator, lifting supervisor, signalman andrigger been briefed at a tool box pre-lift meeting?

  • 8/12/2019 SMS_Element 2_SWPs-1. Mechanical Ctl. in Lifting Ops.

    9/20

    PRIME AIR HVAC (Pte) Ltd Ref No: PASMS2009-2

    SAFETY MANAGEMENT SYSTEM

    Section : 2

    Element : Safe Work Practices

    Appendix : Safe Work Procedure

    Description: Control of Mechanical Lifting Operations

    Issue Date: 1stSept.2009

    Document No. SWP-01

    Revision Date: 1stSept.2011

    Revision No: 01

    Authorised By: Executive Director

    Page No. Page 9 of 20

    Yes No

    1. Are you appointed as a lifting supervisor to co-ordinate lifting activities in your yard?

    2. Have you successfully completed the safety instruction course for lifting supervisors?

    3. Have you made an assessment of the lifting operation in the following areas?3.1 Selection of cranes (Types and capacities)?--------------------------------------------------------------------

    3.2 Selection of lifting gears (Types and capacities)?

    3.3 Selection of lifting appliances (Types and capacities)?

    4. Have you ensured that :

    4.1 The lifting equipment is properly maintained and has a valid report of

    examination issued by an Approved Person?

    4.2 The lifting gears are inspected and maintained?

    4.3 The crane operator is trained?

    4.4 (Where applicable) A load chart is made available to the crane operators?

    5. Have you briefed your workers involved in the lifting operation on safety measures

    to be taken?

    6. Have you checked the load and riggings to ensure that the load can be safely lifted

    and moved?

    7. Have you ensure that outriggers of a mobile crane are used when the crane is

    involved in the Lifting operation?

    8. Have you ensured that pads are made available where wire ropes have to bend

    sharp edges?

    9. For loads such as pipelines and containers, have you taken the weight of the

    residual contents into consideration?

    10. Have you ensured that attachments to the load are properly secured?

    11. Have you ensured that the ground condition is safe for any lifting operation to be

    performed?

    12. Have you ensured that properly trained signalers are assigned to the lifting

    operation?

    13. Have you ensured that the load is placed on stable ground and rested properly

    to prevent toppling?

    Note: Do not start work unless the above questions are answered YES. If in doubt, please check with your supervisors.

    SAFETY CHECKLISTFOR

    LIFTING SUPERVISOR

    SAFETY FIRST

  • 8/12/2019 SMS_Element 2_SWPs-1. Mechanical Ctl. in Lifting Ops.

    10/20

    PRIME AIR HVAC (Pte) Ltd Ref No: PASMS2009-2

    SAFETY MANAGEMENT SYSTEM

    Section : 2

    Element : Safe Work Practices

    Appendix : Safe Work Procedure

    Description: Control of Mechanical Lifting Operations

    Issue Date: 1stSept.2009

    Document No. SWP-01

    Revision Date: 1stSept.2011

    Revision No: 01

    Authorised By: Executive Director

    Page No. Page 10 of 20

    INSPECTION NO. MONTH / YEAR LM NO.YARDS /CONTRACTORS /SUPPLIERS

    CRANE OPERATOR

    KEY: !Satisfactory/Yes X Poor/No O Not Applicable

    S/N.

    REPORT OF CHECKING

    1. Crane is operated by a qualified operator

    2. Daily checking of a crane is carried out by crane operator with reports available.

    3. Load that is being lifted is not exceeding the safe working load of the crane/sling.

    4. Area of crane operation cleared of other workers not connected with the operation.

    5. The load is kept as low as possible.

    6. Tag lines are provided to restrict swinging of load.

    7. The slew lock is set when crane is travelling.

    8. A capacity chart is provided for the crane.

    9. Outriggers are fully extended on firm footing and wheels are off the ground.

    10. Ground condition is safe for lifting operation and confirmed by crane operators.

    (a) Laying of hardcore.

    (b) Compaction of subgrade.

    (c) Laying of steel plates.

    (d) Stability

    (e) Barriers next ground depression or excavated area.

    11. Brakes are activated, control set to neutral position and starter key removed?

    NAME OF LIFTING SUPERVISOR: SIGNATURE:

    N.B. 1. To be filled up by the Lifting Supervisor whenever commence operation.2. Do not start work unless the above questions are answered.

    REMARKS(IF ANY) WITH DATE :________________________________________________________________

    ____________________________________________________________________________

    INSPECTION DATE / TIME

    ITEM

    SAFETY FIRST

    CHECKLIST FOR LIFTING OPERATIONS BY LIFTING SUPERVISOR

  • 8/12/2019 SMS_Element 2_SWPs-1. Mechanical Ctl. in Lifting Ops.

    11/20

    PRIME AIR HVAC (Pte) Ltd Ref No: PASMS2009-2

    SAFETY MANAGEMENT SYSTEM

    Section : 2

    Element : Safe Work Practices

    Appendix : Safe Work Procedure

    Description: Control of Mechanical Lifting Operations

    Issue Date: 1stSept.2009

    Document No. SWP-01

    Revision Date: 1stSept.2011

    Revision No: 01

    Authorised By: Executive Director

    Page No. Page 11 of 20

    PROJECT : __________________________________ YARD / CONTRACTOR : ________________________________

    SITE : __________________________________ TRADE : ________________________________

    INSPECTION NO. LM NO.

    YARDS / CONTRACTORS / SUPPLIERS CRANE OPERATORNAME

    SIGNATURE

    ! Satisfactory / Yes X Poor / No O Not Applicable

    S/NO.

    REPORT OF CHECKING

    REMARKS

    1. ENGINE

    Water level in radiator and reserve tank

    Oil level and condition

    Oil, water and fuel leakage

    Fan belt tension

    Air cleaner2. HYDRAULIC SYSTEM

    Hydraulic oil level and condition

    Control lever and valve working condition

    Pump working condition

    Motor working condition

    Hydraulic pump, motors and cylinders oil leakage

    Control valve, rotating joint and piping oil leakage

    3. ELECTRICITY SYSTEM

    Fluid level in battery

    Instruments working condition

    4. SAFETY DEVICES

    Anti-two block, boom over-hoist limiting and moment limiter, etc.

    5. ATTACHEMENT

    Appearance

    Crank and deformation

    Wire rope

    6. TRAVEL WARNING DEVICE

    7. LOAD/RADIUS AND AUTOMATIC SAFE LOAD/INDICATORS

    8. MOTION LIMIT SWITCHES

    9. THE CRANE BOOM

    10. BALLAST

    11. WINDING DRUM FOR POWER CABLE

    12. RAIL CLAMPS13. RAIL TRACKS

    14. WHEELS AND AXLES OF RAIL MOUNTED CRANE

    CHECKLIST- DAILY CHECKING BY CRANE OPERATOR

    INSPECTION DATE / TIME

    ITEM

    Key:

    SAFETY FIRST

  • 8/12/2019 SMS_Element 2_SWPs-1. Mechanical Ctl. in Lifting Ops.

    12/20

    PRIME AIR HVAC (Pte) Ltd Ref No: PASMS2009-2

    SAFETY MANAGEMENT SYSTEM

    Section : 2

    Element : Safe Work Practices

    Appendix : Safe Work Procedure

    Description: Control of Mechanical Lifting Operations

    Issue Date: 1stSept.2009

    Document No. SWP-01

    Revision Date: 1stSept.2011

    Revision No: 01

    Authorised By: Executive Director

    Page No. Page 12 of 20

    Note: 1. Inspection of lifting gears, that is, chain blocks, lever blocks, chain slings, wire slings, fibresling, shackles, plate clamps to be carried out in weekly or daily if frequent lifting operation.

    2. Lifting Gears colour coding to be change and painted at the suitable location once in every 4

    months for inspection identification.

    3. After inspection and record of lifting gears, copies to be retained by the Lifting Supervisor and

    copies to be submitted to the Safety Office.

    PERIOD COLOUR CODE

    JAN TO APRIL YELLOW

    MAY TO AUG GREEN

    SEP TO DEC WHITE

    SAFETY FIRST

    COLOUR CODING SYSTEMOF LIFTING GEARS

  • 8/12/2019 SMS_Element 2_SWPs-1. Mechanical Ctl. in Lifting Ops.

    13/20

    PRIME AIR HVAC (Pte) Ltd Ref No: PASMS2009-2

    SAFETY MANAGEMENT SYSTEM

    Section : 2

    Element : Safe Work Practices

    Appendix : Safe Work Procedure

    Description: Control of Mechanical Lifting Operations

    Issue Date: 1stSept.2009

    Document No. SWP-01

    Revision Date: 1stSept.2011

    Revision No: 01

    Authorised By: Executive Director

    Page No. Page 13 of 20

    No.Type ofCheck

    Parts tocheck

    Condition of PartsMaintenance

    of partsType of Action

    Taken1. Visual &

    ListeningFunction ofchain block

    a) Chain entangle duringpulling and releasing.

    - Jumps during pulling andreleasing.

    - Make excessivenoise, etc

    a) Clean and lubricate. a) Maintenance is noteffective, replace newone.

    2. Visual Fasteningparts, that isbolts, nuts,rivets, etc.

    a) Defective- Missing- Loosen

    a) Fasten loose parts a) Replace new fasteningparts

    - Discard the chain block /lever block

    3. Visual - Seeappearance

    Top & bottomhook assembly

    a) Safety latch openingup at hooks.

    - Safety latch does notreturn after pushing.

    b) Hooks deformation.

    c) Hook swivel worn out.

    d) Hook swivel did not

    move freely.

    a) N.A.

    b) N.A.

    c) N.A.

    d) Clean and lubricate.

    a) Replace new safety latch.

    b) Replace the hooks.

    c) Replace the hooks.

    d) Clean and lubricate.

    4. Visual - Seeappearance

    Load Chain a) Weld Crack- Deformation- Indentation on edgeor surface

    - Excessive wear- Corrosion.

    b) Not lubricated.

    c) Kinked or twisted.- Welds are not in a row.

    d) Kinked due to kinkedtackle block.

    - Welds are not in a row.

    a) Beyond repair

    b) Clean & lubricate

    c) N.A.

    d) N.A.

    a) Competence person torenew load chain.

    b) Clean & lubricate.

    c) Straighten the chain andset to normal position.

    d) Straighten by turningback

    the tackle block.

    5. Visual - Seeappearance

    Hand Chain a) Kinked or twisted.

    b) Deformed or damagedand does not comecorrectly to chain wheel.

    a) N.A.

    b) Beyond repair.

    a) Straighten the chain andset to normal position.

    b) Exchange new handchain.

    6. Visual IdentificationTag, that is LGNo.; Distinctiveno.: S.W.L.:expiry date

    a) Missing, came off. a) Replace tag a) Renew identification tagimmediately.

    LIFTING GEARS (CHAIN BLOCK & LEVERBLOCK CHECKLIST

    SAFETY FIRST

  • 8/12/2019 SMS_Element 2_SWPs-1. Mechanical Ctl. in Lifting Ops.

    14/20

    PRIME AIR HVAC (Pte) Ltd Ref No: PASMS2009-2

    SAFETY MANAGEMENT SYSTEM

    Section : 2

    Element : Safe Work Practices

    Appendix : Safe Work Procedure

    Description: Control of Mechanical Lifting Operations

    Issue Date: 1stSept.2009

    Document No. SWP-01

    Revision Date: 1stSept.2011

    Revision No: 01

    Authorised By: Executive Director

    Page No. Page 14 of 20

    Note: Storage Slings and attachments to be stored correctly

    No.Type ofCheck

    Item tocheck

    Condition of PartsMaintenance

    of partsType of Action

    Taken1. Visual Chain

    Sling

    Wear or Mechanical abuse

    Cracks

    Twisted or bent links

    Links elongated and stretched

    Links or attachment distorted ordamaged (Check both master andcoupling links

    Tag or label is missing

    *Check for Safe Working Load.

    Replace damaged parts1. Replace of damaged parts

    by competent person

    2. Replace new one.

    2. Visual ChainHook

    Signs of opening up at safety latchSigns of distortion or crackingSigns of damaged threadSigns of damage to swivel andbearings.Spread in the hook throat openingless than 15%

    *Check for Safe Working Load.

    Replace damaged parts

    1. Replace of damaged partsby competent person

    2. Replace new one.

    3. Visual WireSling

    Damage due to severe loadingExternal wear caused by draggingLocal abrasion caused by movementover sharp edgesBroken Wires

    Any fatigue (clean break in wire)Any kinks in the slingFerrule in good condition*Check for Safe Working Load.

    Replace new one Replace new one

    4. Visual FibreSling

    Damage due to severe loadingExternal wear caused by draggingLocal abrasion caused by movementover sharp edgesLubrication dried out

    Any broken or cut fibresAny torn or frayed materialAny broken stitchingAny kinksAny worn or distorted fittingsSplices in good condition

    Replace new one Replace new one

    5. Visual ShacklesWear and or deformation

    Cracks

    Nicks

    Gouges

    Corrosion

    Damage to thread

    *Check for Safe Working Load

    Replace new one Replace new one

    LIFTING GEARS CHECKLISTSAFETY FIRST

  • 8/12/2019 SMS_Element 2_SWPs-1. Mechanical Ctl. in Lifting Ops.

    15/20

  • 8/12/2019 SMS_Element 2_SWPs-1. Mechanical Ctl. in Lifting Ops.

    16/20

    PRIME AIR HVAC (Pte) Ltd Ref No: PASMS2009-2

    SAFETY MANAGEMENT SYSTEM

    Section : 2

    Element : Safe Work Practices

    Appendix : Safe Work Procedure

    Description: Control of Mechanical Lifting Operations

    Issue Date: 1stSept.2009

    Document No. SWP-01

    Revision Date: 1stSept.2011

    Revision No: 01

    Authorised By: Executive Director

    Page No. Page 16 of 20

    WEEKLY INSPECTION OF LIFTING GEARS

    TYPE OF LIFTING GEARS:____________________________________

    PERIOD & COLOUR CODE: ___________________________________

    Registration

    No.

    Distinctive

    No.

    Date & Remarks of Visual Inspection(Refer to the LIFTING GEARS CHECKLIST)

    Remarks

    Inspected by LiftingSupervisors Name:

    Signature:

    SAFETY FIRST

  • 8/12/2019 SMS_Element 2_SWPs-1. Mechanical Ctl. in Lifting Ops.

    17/20

    PRIME AIR HVAC (Pte) Ltd Ref No: PASMS2009-2

    SAFETY MANAGEMENT SYSTEM

    Section : 2

    Element : Safe Work Practices

    Appendix : Safe Work Procedure

    Description: Control of Mechanical Lifting Operations

    Issue Date: 1stSept.2009

    Document No. SWP-01

    Revision Date: 1stSept.2011

    Revision No: 01

    Authorised By: Executive Director

    Page No. Page 17 of 20

    1. OBJECTIVE

    1.1. To establish Safe Work Practices (SWPs) for known hazardous activities, so that suchworks are carried out safely.

    2. DESCRIPTION

    2.1. Safe work practices can minimise, if not eliminate the risk of an accident. This elementcontains well-defined procedures and instructions to carry out specific works, tasks andequipment operations safely.

    3. SCOPE OF APPLICATION

    3.1. Safe work Practices shall be established for other hazardous work or work processes asand when required. The SWPs serve as a guide. The list of SWP shall include but not

    be limited to the following:-

    3.1.1. Control of Mechanical Lifting Operations3.1.2. Confined Space and Dangerous Atmospheres3.1.3. Blasting and Painting3.1.4. Ladders3.1.5. Working at Heights3.1.6. Welding and Heating operations3.1.7. Handling and Control of gas cylinders3.1.8. Fabrication3.1.9. Site Radiography3.1.10. Radiation Safety3.1.11. Control of substances hazardous to health

    3.1.12. Personal Protective Equipment3.1.13. Housekeeping3.1.14. Fitting of Abrasive Discs3.1.15. High Pressure Hydro-testing3.1.16. Allocation of work to safeguard safety3.1.17. Fire Prevention & Control3.1.18. Portable Electrical Tools3.1.19. Air Receiver3.1.20. Noise3.1.21. Forklift Safety3.1.22. Lockout / Tag-out3.1.23. Manual Lifting

  • 8/12/2019 SMS_Element 2_SWPs-1. Mechanical Ctl. in Lifting Ops.

    18/20

    PRIME AIR HVAC (Pte) Ltd Ref No: PASMS2009-2

    SAFETY MANAGEMENT SYSTEM

    Section : 2

    Element : Safe Work Practices

    Appendix : Safe Work Procedure

    Description: Control of Mechanical Lifting Operations

    Issue Date: 1stSept.2009

    Document No. SWP-01

    Revision Date: 1stSept.2011

    Revision No: 01

    Authorised By: Executive Director

    Page No. Page 18 of 20

    4. PROCEDURE

    4.1. For current methods of work

    4.1.1. Persons In-charge of respective tasks are to ensure that all workingpersonnel follow all prescribed safe work practices as required under the

    local code of practices and mandatory requirements.

    4.2. For new methods of work and those works without SWPs

    4.2.1. For new work or equipment to be used, Person In-charge (PIC) is to submita Work Method Statement or procedures for review by the Safety

    Department and Safety Committee, prior to commencement of the work.

    The procedure for submission of new method of statement is:-

    4.2.1.1. PIC to submit Risk Assessment (RA) & Work Method Statement(WMS) at least 1 week prior to commencement of work;

    4.2.1.2. Safety Department to review the RA & WMS;

    4.2.1.3. Related parties to discuss or meet to go through the safe work

    practice for better understanding and input;

    4.2.1.4. PIC to disseminate the SWP and safety measures to be taken toconcerned staff/ contractor;

    4.2.1.5. Concerned parties to commence work only after complying withthe safety requirements in the SWP;

    4.2.1.6. Safety Department to incorporate the SWP into this SMS;

    4.2.1.7. Safety Supervisor shall supervise for compliance to safe workpractices (SWPs);

    4.2.1.8. Safety Department shall inspect periodically for adherence toSWPs.

    4.3. Hazard Analysis

    4.3.1. As a precursor to development of SWPs, Risk Assessment and Job SafetyAnalysis may be carried out to identity the hazards related to the job

  • 8/12/2019 SMS_Element 2_SWPs-1. Mechanical Ctl. in Lifting Ops.

    19/20

    PRIME AIR HVAC (Pte) Ltd Ref No: PASMS2009-2

    SAFETY MANAGEMENT SYSTEM

    Section : 2

    Element : Safe Work Practices

    Appendix : Safe Work Procedure

    Description: Control of Mechanical Lifting Operations

    Issue Date: 1stSept.2009

    Document No. SWP-01

    Revision Date: 1stSept.2011

    Revision No: 01

    Authorised By: Executive Director

    Page No. Page 19 of 20

    activity, so that the development of new SWP is systematic. For details,

    refer to the element on hazard Analysis.

    5. RESPONSIBILITY

    5.1. Department Managers

    5.1.1. Ensure that safe work practices are established for existing and newhazardous works in the premises;

    5.1.2. Review safe work practices prior to submission to Safety Department;

    5.1.3. Monitor the compliance of staff and contractor in adhering to the prescribedsafe work procedure.

    5.2. Superintendents & Supervisors

    5.2.1. Obtain a copy of SWPs prior to commencement of hazardous work;

    5.2.2. Communicate the contents to the parties involved in the work;

    5.2.3. Ensure compliance to safe work practices.

    5.3. Safety Department

    5.3.1. Review Risk Assessment, Work Method Statements submitted byDepartment & Contractors;

    5.3.2. Incorporate safety provision in the Work Method Statement, as necessary;

    5.3.3. Request for additional information or details if Work Method Statementsubmitted contains insufficient information;

    5.3.4. Meet, discuss and present the safe work practices to relevant staff/contractors;

    5.3.5. Conduct periodic inspection of staff and contractors on compliance to safework practices.

    5.3.6. Incorporate newly established SWP into this SMS.

    5.3.7. Review established SWPs, amend and update as and when necessary.

  • 8/12/2019 SMS_Element 2_SWPs-1. Mechanical Ctl. in Lifting Ops.

    20/20

    PRIME AIR HVAC (Pte) Ltd Ref No: PASMS2009-2

    SAFETY MANAGEMENT SYSTEM

    Section : 2

    Element : Safe Work Practices

    Appendix : Safe Work Procedure

    Description: Control of Mechanical Lifting Operations

    Issue Date: 1stSept.2009

    Document No. SWP-01

    Revision Date: 1stSept.2011

    Revision No: 01

    Authorised By: Executive Director

    Page No. Page 20 of 20

    6. SAFE WORK PROCEDURES

    6.1. Safe Work Procedures and Master list are as attached in Appendix.

    6.2. Amendments required for safety improvement of the SWPs, are to be brought up to theSafety Department for discussion and then to adopt as recommended by the Safety

    Committee.