soil nailing in germany

Upload: jose-martinez

Post on 04-Jun-2018

251 views

Category:

Documents


9 download

TRANSCRIPT

  • 8/13/2019 Soil Nailing in Germany

    1/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 1

    Soil Nailing in Germany: Development, Design, Execution

    [Eigene Dateien\Brasilia Powerpoint\Soil Nailing in Germany-63-Brasilia.ppt]

  • 8/13/2019 Soil Nailing in Germany

    2/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 2

    2. Design: Verification of stability of a nailed wall2.1 General design considerations

    2.2 Example: Verification of stability of a 10 m high wall

    1.1 Principle static analyses

    1.2 Model tests1.3 Field tests

    Summary and conclusions

    3. Execution: Several examples in soil and soft rock 3.1 Practical cases of nailed cuts near to the vertical3.2 Practical cases of nailed slopes3.3 Quality control and warnings

    Scope of Presentation

    Introduction

    1. Development: German research programme

  • 8/13/2019 Soil Nailing in Germany

    3/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 3

    Introduction

    Soil nailing: is a technique of reinforcing natural ground by the insertion of slender tension-carrying elements called nails.

    Applications: excavation pits, permanent retaining structures and (natural) slopes.

    Origin and idea of in situ reinforcing cuts or slopes:

    1972: First recorded case of a nailed wall in France:temporary stabilising of a 70 cut in cohesive sand(commercial project, no subsequent research! )

    1975 - 1981: Research and development projectSoil Nailing in Germany ( Univ. of Karlsruhein joint venture with the contractor BAUER)

    1979: First international publication on soil nailing by the Univ. of Karlsruhe and BAUER ( In this

    publication the termSoil nailing

    was created )

    1986 1990: National Research Project Clouterre in France

    1976 - 1981: Research and development project

    Lateral Earth Support System (Univ. of Cal.)Fig.: First test wall in history of soil

    nailing pushed to failure (1976)

  • 8/13/2019 Soil Nailing in Germany

    4/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 4

    Construction method

    (2) face stabilization using shotcrete(3) installation of nails and grouting

    The procedure is repeated untilthe required depth is reached.

    Three basic processes are involved insoil nailing:

    (1) excavation in steps

    h

    0.5-0.7 h

    (1)

    .

    ..

    .

    .

    (2)

    (3)

    (1)

    Fig. 1: Installed temporary nail of a testwall in sand (digged out after test)

    Fig. 2: Temporary nail after Germanapproval (System BAUER)

  • 8/13/2019 Soil Nailing in Germany

    5/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 5

    tension!

    slip surface

    displacementsmall

    STEEP CUTS:TENSION NAILS

    1

    t e n s i o n !

    d i s p l a c e m e

    n t

    s m a l l 2aTENSION NAILS

    2FLAT SLOPES

    bending!

    s l i p s u r

    f a c e

    d i s p l a

    c e m e n t

    l a r g e !

    w e a t h

    e r e d

    t o p l a y

    e r

    s o l i d

    g r o u n

    d

    2b

    DOWEL NAILS

    Principle mode of operation of soil nails

    Remark: Nails in case 1 and 2a act also as bending elements carrying shear forces at the slip line;but: These shear forces are of secondary order and are neglected in the following design example!

  • 8/13/2019 Soil Nailing in Germany

    6/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 6

    1. German research and development programmecomprised:

    4. Derivation of partial safety factors ona statistic-probabilistic basisandDevelopment of a practical designmethod2. Model tests in sand

    1. Static analyses on the basis of kinematicalfailure mechanisms of rigid earth blocks

    3. Field tests in sand and clay

  • 8/13/2019 Soil Nailing in Germany

    7/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 7

    Single wedge(may be chosen for low nailingdensities or rough calculations)

    Note: For given parameters (soil, load, nailing) the most unsafe failure mode is the one that, under vari-ation of the slip lines, requires the absolute maximum of the pull-out resistance per unit nail length T m,k !

    1.1 Static analyses on the basis of kinematical failure mechanisms of rigid earth blocks

    Several kinematic failure models for nailed walls were investigated.

    An overview is given on the four different potential failure mechanisms that turned out to be critical.

    Note: the following failure modes were - theoretically investigated by stability analyses but also- verified in model tests and full scale tests

    Two-part wedge with circular slip lines(theoretically the least safe mechanism in case ofvery high surcharge in the rear or in case ofearthquake

    Two-part wedge withstraight slip lines(shall be chosen in

    non-cohesive soils)

    Slip circle(shall be chosen in cohesivesoils as well as in non-cohe-sive soils)

  • 8/13/2019 Soil Nailing in Germany

    8/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 8

    1.2. Model tests

    1.2.1 Simple wedge failure mechanism with a straight slip line

    Fig.: Model test in Sand with low nailing density

  • 8/13/2019 Soil Nailing in Germany

    9/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 9

    Fig. 1: Observed 2-part-wedge mechanism with straightslip lines in a model box filled with sand

    Fig. 2: Kinematics of earth block (1) and (2)

    1.2.2 The 2-part-wedge failure mechanism with straight slip lines

    This failure mode was observed in a model test, where the rigid facing of the nailed construction (h = 40cm) in dense sand was progressively moved to the air side.

  • 8/13/2019 Soil Nailing in Germany

    10/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 10

    a) Observed 2-part-block with circular slip linesin a model box filled with sand

    b) Kinematics of earth block (1) and (2) with centre points and radii of the three slip circles

    Fig.: Model test of a nailed wall in sand with a high load beyond the nailed zone

    1.2.3 The 2-part-wedge failure mechanism with curved slip lines

    This failure mode was observed in a model test, where a nailed wall (h = 40 cm) was progressivelysurcharged by a water pressure cushion beyond the nailed zone until failure occurred.

  • 8/13/2019 Soil Nailing in Germany

    11/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 11

    What is the explanation for this special failure mode?

    Answer: The high earth pressure force E of wedge (2) due to the high area load, acting upon the nailed block in its upper part, leads to an overturning moment

  • 8/13/2019 Soil Nailing in Germany

    12/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 12

    1.3 Field tests

    Fig.: Field tests in sand and clay

  • 8/13/2019 Soil Nailing in Germany

    13/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 13

    Fig. 1: Front view of the first test wall in history ofsoil nailng with measuring facilitiesHeight: 6.0 m; Nail lengths: 3.0 m to 4.0 mLoad: Strip load in the rear (hydraulic jackets)

    Fig. 2: Seperation of the proper test wall from thesurrounding ground by thin slurry walls toachieve 2-D conditions

    Test A: Strip load in the rear

  • 8/13/2019 Soil Nailing in Germany

    14/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 14

    Fig. 1: Cross-section of test wall A with inclino-meter boreholes to locate the slip lines

    Fig. 2: Cross-section of test wall A in moment of failure(Wall was weakened by further excavation andpulling-out of bottom nail row)

    Failure mode: Two-part wedge mechanism withstraight slip lines

    Test A: Measuring results

  • 8/13/2019 Soil Nailing in Germany

    15/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 15

    Test A

    Fig.: Field test A: Nailed wall after failure: total displacement ca. 20 cm(Movement of wall during failure parallel to itself is clearly to be seen)

  • 8/13/2019 Soil Nailing in Germany

    16/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 16

    Measurements: 1 Displacements using inclinometer and geodetic instruments

    2 Earth pressures using hydaulic cells3 Nail forces using electr. strain gauges

    Fig. 1: Cross-section of instrumented test wall B

    Test B: Strip load near the crest

    Fig. 2: Cross-section of wall B with horizontal defor-mation after completion (under dead weight)

    u = horizontal displacementh = height of the wall

    Non-cohesive soils u/h 2.5 - 3 (Cohesive soils u/h 3 - 5 )

  • 8/13/2019 Soil Nailing in Germany

    17/56

  • 8/13/2019 Soil Nailing in Germany

    18/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 18

    Test B: Strip load near the crest

    Fig. 6: View of test wall B after failure from theside (Movement of wall during failure inrotation clearly to be seen)

    Fig. 5: Test B: Cross-section with ruptureline located in the inclinometerboreholes after failure

  • 8/13/2019 Soil Nailing in Germany

    19/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 19

    Fig.: Cross-section of test wall B with axial nail forcesafter completion and during loading until failure

    Test B

  • 8/13/2019 Soil Nailing in Germany

    20/56

  • 8/13/2019 Soil Nailing in Germany

    21/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 21

    Test G in clay

    Fig.: View at test wall G in slightly overconsolidated clay with loading equipment

  • 8/13/2019 Soil Nailing in Germany

    22/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 22

    Test G

    B1, B2, B3 .... Boreholes for inclinometer measurements (horiz. & vertical deformations)

    Fig.: Test G in overconsolidated clay: Measured horizontal and vertical deformations of facingand nailed soil after completion (i. e. under dead weight)

  • 8/13/2019 Soil Nailing in Germany

    23/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 23

    2.1 Presenting the design example: cross-section and soil parameters

    2.2 Preconsiderations on the type of design approach

    2.3 Derivation of design values

    2.4 Identification of the unsafest failure mechanism2.5 Determination of the required characteristic nail resistance

    2.6 Further stability checks for the total structure

    2. Design: Verification of stability of a nailed wall with shotcrete facing

    Scope:

  • 8/13/2019 Soil Nailing in Germany

    24/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010

    2.1 Design example: Permanent nailed wall in sand with a transient surface load

    Given geometric data:Height of the wall: h = 10 m;Horizontal nail length at the bottom: l = 6.0 mWall inclination (to the vertical): = 10;

    Nail inclination: = 10Vertical nail spacing: s v = 1.10 m

    Horizontal nail spacing: s h = 1.25 m

    Acting characteristic parameters:Transient surface load: q k = 23 kN/mUnit weight of soil: k = 18 kN/m

    Resisting characteristic parameters:Friction angle of soil: k = 35; cohesion: c k = 0Lowest value in a series of pulling-out tests of nails in-situ:

    F P = 160 kN (Index P denotes P roof load)

    Bonded length of all test nails: l b = 5.0 mHence: the ultimate pull-out resistance per unit nail lengthis yielded by: T Pm,k = F P lb = 160 / 5.0 = 32 kN/m

    Question: Is this nailed wall safe after EC-7 and DIN 1054?

  • 8/13/2019 Soil Nailing in Germany

    25/56

  • 8/13/2019 Soil Nailing in Germany

    26/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 26

    2.4 Identification of the unsafest failure mechanism for the given example

    As shown above, the stability proof of a nailed wall with conditions as given in the example can be based on

    - the two-part wedge mechanism with straight slip lines,

    or as well as on - the slip circle

    NOTE: As the two-part wedge failure mechanism is more comprehensible for a presentation,

    it will be used in the following design procedure!

  • 8/13/2019 Soil Nailing in Germany

    27/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 27

    h' = 5,8 m

    (1) = 35

    qd

    1st Variation (1) = 35

    Actions or driving forces:

    Wd

    Wd = 694 kN/m

    K a : active earth pressure coefficient

    K a = 0,308

    Pd = q d b = 30 4.2 = 126 kN/m

    Pd b = 4.2 m

    Ea,d = h ( h + 2q d) K a (d)d = 29

    Ea,d

    Ea,d = 5.8 (18 5.8 + 2 30) 0.308 = 147 kN/m

    ?

    ?

    ?

    ?

  • 8/13/2019 Soil Nailing in Germany

    28/56

  • 8/13/2019 Soil Nailing in Germany

    29/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 29

    (2) = 40 Z d Q

    d

    Zd = T m,d (0.8 + 2.0 + 3.2 + 4.3 + 5.6)

    Zd = T m,d li9

    5

    275 = T m,d 15.9

    Tm,d = 275 15.9 = 17.3 kN/m/m

    fr (2) = 40

    Z d = 2 7 5 k N / m

    Q

    Wd =649 kN/m

    Pd =126

    d

    Ea,d = 115 kN/m

    l 9 = 5 .6 m

    l 6 = 2 .0 m

    l 8 = 4 .3 m

    l 7 = 3.2 m

    l 5 = 0 .8 m

    Wd

    Pd

    d = 29

    Ea,d

    h = 5.0 m

    2nd Variation (2) = 40

    = 5

  • 8/13/2019 Soil Nailing in Germany

    30/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010

    (3) = 45 Z d

    Q

    d

    Z d = 30 0 k N / m

    Q

    Wd

    Pd

    Ea,d

    l 9 = 5 .6 m

    l 6 = 2 .6 m

    l 8 = 4 .6 m

    l 7 = 3.6 m

    l 5 = 1.6 m

    Wd

    Pd

    Ea,d

    h = 4.0 m

    3rd Variation (3) = 45

    l 4 = 0 .6 m

    16.118.630045

    17.3 = MAX!15.927540

    16.913.623035

    [kN/m/m][m][kN/m][]

    Tm,d = Zd / li liZd

    design pull-out resistance: T m,d,max = 17.3 kN/m/m

    characteristic pull-out resistance:with partial safetyfactor (DIN 1054,Table 3)

    N = Tm,k

    Tm,d

    Tm,k,max = N Tm,dTm,k,max = 1.40 17.3T m, k,max = 24.2 kN/m/m

  • 8/13/2019 Soil Nailing in Germany

    31/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 31

    Remember: established horizontal spacing was: s h = 1.25 mThus, the required characteristic pull-out resistance per unit nail length of the physical

    nail is yielded by:T m,k = 24.2 1.25 = 30.25 kN/m

    Remember: ultimate pull-out resistance, verified in a series of load tests was:

    Result of slip line variation:Tm,k,max = 24.2 kN/m/m (i.e. per unit length of a virtual nail per unit width of the wall)

    T Pm, k = 32 kN/m (P indicates: P roof load)It can be seen: T m, k,max < T Pm,k which is OK!

    The maximum ultimate pull-out resistance per unit nail length in the design is less than ultimate

    pull-out resistance per unit nail length in the load test in-situ.Conclusion: 1. The design is safe!

    2. The design is also economic, as

    the utilisation factor for the nails: T m,k / T Pm, k = 30.25 / 32 = 0.95 or 95%

    2.5 Determination of the required characteristic nail resistance

  • 8/13/2019 Soil Nailing in Germany

    32/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010

    (a) Groundfailure

    (a) Groundfailure

    (c) Overall (or external) stability

    (c) Embankmentfailure

    M

    (b) Failure against horizontal sliding (often involved in varia-ion of slip staight lines)

    (b) Horizontal sliding

    2.6 Further stability checks for the nailed wall

    After DIN 1054, sec. 12.4.4 (2) the nailed (or reinforced) part ofthe soil has to be considered as a solid block or gravity wall.

    If in doubt, the following stability checks have to be made:

    NOTE: Verification of nails and facing cannot be presented here (please, see publications!)

    DC N il

  • 8/13/2019 Soil Nailing in Germany

    33/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 33

    DC-Nailwww.dc-software.comMunich/ Germany

    Fig.: Checking internal stability by two-wedge failure mechanisms with straight slip lines andexternal stability by slip circles using German computer program DC-Nail

    Anlisis de Suelos EnclavadosProgram DC-Nail

    Anlisis de suelos enclavados de acuerdo aDIN 1054:2005 (basado en EUROCODE 7),DIN 1054:1976

    Diseo de revestimiento de hormignlanzado de acuerdo a DIN 1045, DIN 1045-1

    Anlisis con factores de seguridad parcial ocon seguridad global

    Versiones del programa en Alemn, Ingls,Francs, Italiano, Espaol

    Anlisis de acuerdo con el mtodo general dedeslizamiento de bloques

    Determinacin de la estabilidad interior yexterior

    3 E i S l l i il d f k h d k

  • 8/13/2019 Soil Nailing in Germany

    34/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 34

    3. Execution: Several examples in soil and soft rock or weatherd rock

    3.1 Practical cases of nailed cuts near to the vertical

    a) Auger drilling for the nails b) Pull-out test of a nail

    Fig. 1: One of the first permanent nailed walls near to the vertical in sand/ gravel,executed by the German contractor BAUER near Stuttgart, 1985

    3 1 P ti l f il d t t th ti l (1 st ti ti )

  • 8/13/2019 Soil Nailing in Germany

    35/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 35

    3.1 Practical cases of nailed cuts near to the vertical (1 st continuation)

    a) Shotcreting b) Drainage provided by drainmats (System ENKA)

    Fig. 2: Permanent nailed wall near to the vertical in sand/ gravel as before(Nails coverd by shotcrete to prevent corrosion)

  • 8/13/2019 Soil Nailing in Germany

    36/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 36

    a) Permanent soil nail with corrugated plastic sheath

    for complete corrosion protection

    Fig. 2: Permanent nail (System BAUER, Germany) b) Permanent nail on site

    Permanent nailed wall with revetment wall

  • 8/13/2019 Soil Nailing in Germany

    37/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 37

    a) b)Fig. 2: Cross-section of the nailed cut (a) after completion,

    (b) in final state with a revetment wall to be greened

    Fig. 1: Permanent nailed cut in mountaineous areain Southern Germany (Nails heads coveredby shotcrete, only weep hole pipes to be seen)(National Road widening scheme project)

    Permanent nailed wall with revetment wall

    Permanent nailed wall with revetment wall

  • 8/13/2019 Soil Nailing in Germany

    38/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 38

    Fig. 3: Wall shortly after completion: Greening yet to comeFig. 1: Mounting of the prefabricated concrete

    elements by a crane

    Permanent nailed wall with revetment wall

    Fig. 2: Fixing of concrete elementsat the top

  • 8/13/2019 Soil Nailing in Germany

    39/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 39

    Fig.: Permanent cutting slope in Keuper marl (South-West Germany) for a new National Road;due to significant creeping property of marl: nail lengths 23 m; calculation by slip circles

  • 8/13/2019 Soil Nailing in Germany

    40/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 40

    Fig 1: Permanent nails without plastic sheath; corrosion protectiononly by in-situ grouting; diameter of GEWI tendon: 50 mm(Degradation due to corrosion incorporated in the design)

    Fig. 2: Permanent facing with double reinforce-ment layers (earth-sided and air-sided)

    3 2 Practical cases of nailed slopes

  • 8/13/2019 Soil Nailing in Germany

    41/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010

    Landslide is a nightmare for every geotechnical engineer!

    3.2 Practical cases of nailed slopes

    F ig.: Landslide due to fossil slip surfaces reactivated in a cutting (Marlstone)

  • 8/13/2019 Soil Nailing in Germany

    42/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 42

    F ig.: Reinforcing a 30 cut in marlstone to prevent sliding on potential geologic slipsurfaces possibly reactivated by excavation in front of a tunnel portal of theGerman high speed railway line Mannheim - Stuttgart

  • 8/13/2019 Soil Nailing in Germany

    43/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 43

    INCLINOMETREBOREHOLE

    SOIL-NAILS

    2 0 m

    1 5 m

    2 4 m

    GEOLOGIC-SLIP-

    SURFACES

    10

    DRAIN TUBES

    EXTENSO-

    METRE (GREENED)(GREENED)

    NATURAL GROUND LEVEL

    FREE SURFACE

    1 : 1 ,7 5

    1 : 1, 1 5

    NATURAL GROUND LEVEL

    FREE SURFACE

    1 : 1 ,7 5

    1 : 1, 1 5

    1 : 1, 1 5

    F ig.: Cross-section of the 30 cut (i.e. 1:1.75) in marlstone to prevent sliding on potentialgeologic slip surfaces reactivated by excavation

    (Slip surfaces were not localized but expected due to the experienced landslide shown before)

  • 8/13/2019 Soil Nailing in Germany

    44/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 44

    F ig.: View at geologic slip surface found in reality during excavation process: Nailing absolutely necessary for reasons of safety!

  • 8/13/2019 Soil Nailing in Germany

    45/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010

    Fig.: Special drilling rig for 18 m long nails constructed by BAUER

    Nail setting

  • 8/13/2019 Soil Nailing in Germany

    46/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 46

    Fig. 3

    Fig. 2

    Fig. 5

    Fig. 1

    Fig. 4

  • 8/13/2019 Soil Nailing in Germany

    47/56

  • 8/13/2019 Soil Nailing in Germany

    48/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 48

    Fig. 2: Setting of instrumented nail for pulling-outtest to verify the assumptions of design

    Fig. 1: Analysis for the worst case: Geologic slip surface assumed at thebottom of the slope (assumed failure: two-part wedge mechanism)

    Question: Assumption of mean pull-out resistance per unit nail length T m (kN/m) correct?

  • 8/13/2019 Soil Nailing in Germany

    49/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 49

    Fig. 2: Test loading facilitiesFig. 1: Axial force distribution along the instrumented test nailfor different loads (soil: weathered Keuper Marl)

  • 8/13/2019 Soil Nailing in Germany

    50/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010

    F ig.: Completed nailed slope with hidden nails under green surface(Picture taken few months before opening to traffic, 1991)

    Quality control:

  • 8/13/2019 Soil Nailing in Germany

    51/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 51

    - Work: according to the plans?

    - Excavation steps: following theadmissible depth and the time sequence?

    - Free standing of boreholes?(if not: casing!)

    - Nails: Length correct?Diameter of the steel

    tendon correct?

    - Soil conditions: according to geotechnical report?

    Put the following questions on the site:

    Missing quality control:Nails too short! Facing too thin! =>

    Quality control:P h f ll i i h i

  • 8/13/2019 Soil Nailing in Germany

    52/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 52

    - Work: according to the plans?

    - Excavation steps: following theadmissible depth and the time sequence?

    - Free standing of boreholes?(if not: casing!)

    - Nails: Length correct?Diameter of the steel tendon correct?

    - Grouting water-cement-factor correct?

    - Shotcrete: thickness?

    - Mounting of mats: sufficient overlapping?

    - Soil conditions: according to geotechnical report?

    Put the following questions on the site:

    - Pull-out tests of nails: performance correct?results according to the design?

    Benefits of Soil Nailing:

  • 8/13/2019 Soil Nailing in Germany

    53/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010 53

    g

    - Economic advantage

    - Construction flexibility

    - Small construction equipment

    - Special solutions: Remedial work

    Fig.: Restoring and stabilizing historicmasonry walls using soil nails

  • 8/13/2019 Soil Nailing in Germany

    54/56

    Summary and Conclusions:

  • 8/13/2019 Soil Nailing in Germany

    55/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010

    2. The ultimate limit state design of nailed walls and slopes is based on kinematic

    failure mechanisms proved in model and field tests of the research programme.

    1. The research and development programme in Germany (1976 1981) yielded

    numerous results on the bearing behaviour and the stability of nailed walls.

    3. The application of the principles of new European Standard EC 7-1 GeotechnicalDesign combined with the detailed rules in German Standard DIN 1054

    provides a safe and practicable limit state design of soil nail constructions.

    4. Execution of soil nailed constructions needs experience and good knowledge of the

    ground conditions.

    5. Soil nailing involves numerous benefits but also some limitations.

    6. Today soil nailing is a well established construction method in many contries allover the world.

    There is a wide field for its application in Brazil, too!

    Last but very important conclusion:S il ili d i d i !

  • 8/13/2019 Soil Nailing in Germany

    56/56

    University of Applied Sciences Munich / Germany Prof. Dr.-Ing. G. Gssler Department of Civil Engineering Presentation at Universidade de Braslia 03/2010

    Not guys doing it like that:

    Soil nailing needs experienced engineers !

    Thank you very much for your attention!

    Cartoon by courtesy of Sddeutsche Zeitung,

    Germany