south deep gold mine
TRANSCRIPT
Overview of the South Deep ProjectSeptember 2011
Our Vision and Values
2
To be the global leader in sustainable gold mining
Locality – Wits Gold Fields
3
The Witwatersrand Gold Fields
� Historic production: > 1 600 000 000 oz of gold� 4.5bn tons of ore treated at an average grade of 9.0g/t
Locality – South Deep
4
Well established mining area
Tautona
Mponeng
Blyvooruitsicht
Kusasalethu
Ezulwini
Cooke
Overview
Outline
� Massive underground orebody
� 81.5 Moz Resource
� 34.5 Moz Reserve
� Fully mechanised mine
� Build-up to 750koz run-rate by end of 2014
� Life of Mine of 54 years
5
Capital Programme
Building a world class mine
2010 2011 2012 2013 2014 Status
Refrigeration Plant Complete
Twin Vent Shaft On-track
Tailings Storage Facility Commissioned
Plant Expansion On-track
New Mine Development On-track
0.0
0.5
1.0
1.5
2.0
2.5
0
200
400
600
800
2009 A 2010 A 2011 E 2012 E 2013 E 2014 E
Rbn(oz)
Production (lhs) Capex (rhs)
Production and Capex
History
� 1950: Prospecting in the area commenced
� 1961: Production at Western Areas Gold Mine (WAGM) commenced
� 1999: Placer Dome Western Areas (PDWA) Joint Venture (JV) formed
� 2000: Name changed to South Deep Gold Mine
� 2005: Twin Shaft Complex opened
� 2006: Gold Fields acquired Barrick’s 50% JV interest in the PDWA JV
� 2007: Gold Fields acquired all remaining WAL shares to own 100% of South Deep GoldMine WAL listing terminated
6
0.93
0 0.07 0.12 0.060
0.4
0.8
1.2
F2008 F2009 F2010 F2011 C2011
Safety
7
Safety Trends
LDIFR
21.29
5.782.8 2.4 1.82
0
5
10
15
20
25
F2008 F2009 F2010 F2011 C2011
SIFR
6.66
2.111.1 0.84 1.09
0
2
4
6
8
F2008 F2009 F2010 F2011 C2011
FIIFR
Our People
� Employ approximately 3,700 people on operation
� Diverse workforce
� Well trained and qualified personnel
� World class medical facilities
� Wellness programme
� “24 hours in the life of a miner”
� Organised labour
� 72% NUM, 15% UASA and 14% non affiliated
8
Sustainable Development
� Management of environmental aspects in line with latest legislative requirements
� Environmental Management Systems according to best practice international standards (ISO14001 certified)
� Water Management part of regional strategy
� International Cyanide Management Institute (ICMI) compliant
9
Environmental Management
Geology
10
General overview
Geology
11
Vertical slice through the orebody
The primary reef targets are the MB’s and the EC’s
Geology
� Surface exploration programme of R173 million
12
Exploration Programme
Surface
Pretoria Group
Black Reef
Chuniespoort
GroupBase at ±1800mbc
VCR
Klipriviersberg Group
Base at ±3000mbc
UpperElsburgsD7
D8
Orig.
D1D2
D3 D4D5
D6
Resources
Tonnes (Mt) Grade (g/t) Gold (‘000 oz)
Classification Dec 10 Jun 10 Jun 09 Dec 10 Jun 10 Jun 09 Dec 10 Jun 10 Jun 09
Underground
Measured 41.5 40.5 41.6 7.7 7.4 7.4 10,331 9,684 9,890
Indicated (AI) 250.5 125.7 125.9 6.6 8.7 8.7 53,523 35,016 35,038
Total Above
Infrastructure292.0 166.2 167.5 6.8 8.4 8.3 63,854 44,700 44,928
Indicated (BI) 42.3 92.6 92.6 7.0 6.3 6.3 9,568 18,898 18,898
Total Below
Infrastructure42.3 92.6 92.6 7.0 6.3 6.3 9,568 18,898 18,898
Grand Total 334.3 258.8 260.1 6.8 7.6 7.6 73,422 63,598 63,826
13
Measured & Indicated Resources
Resources
Tonnes (Mt) Grade (g/t) Gold (‘000 oz)
Classification Dec 10 Jun 10 Jun 09 Dec 10 Jun 10 Jun 09 Dec 10 Jun 10 Jun 09
Underground
Inferred AI 17.2 78.0 78.0 6.3 5.8 5.8 3,460 14,566 14,566
Inferred(BI) 21.8 - - 6.5 - - 4,572 - -
Grand Total 39.0 78.0 78.0 6.4 5.8 5.8 8,032 14,566 14,566
14
Tonnes (Mt) Grade (g/t) Gold (‘000 oz)
Grand Total 373.3 336.8 338.1 6.8 7.2 7.2 81,454 78,164 78,392
Inferred Resources
Total Measured, Indicated & Inferred Resources
Resources
0
40
80
120
160
200
240
280
Approximately one third of those of Gold Fields, AngloGold Ashanti and Barrick
Resources (Moz)
______________________Source: Goldval.com as at September 2010
Mining Philosophy
16
Mining a massive orebody at depth
Large backfilled
stope
MechanisationMechanisation
De-stress mining Backfilling
Mine Design and Scheduling
17
Reserving a great orebody
Trackless Drifts & Benches
Conventional Drifts & Drives
Longhole Stoping
Down Dip AccessedDestressing
Conventional Destress StopingApparent Dip Drifts & Drives with Benching
Conventional Composite Mining
Conventional Breast Mining
Bench access
Mining direction
Drift access
Bench mining Mining direction
Primary drift mining1
32
Mining Methods – Drift and Bench Mining
Bench access
Main-access-drive
2.2m
Recently filled stoping drive
Stoping-drive
1 Stoping-drive mining
3 Stoping-drive completion2 Advance stope-access-drive
Mining Methods – Destress Mining
1 2
•
Longhole stope access Slot development
Slot raise
3 4 5Slot development Stoping Stoping
Completed slot
Slot access
••Mining Methods – Longhole stoping
Development towards the Wrench fault (105 & 105 levels)
Build-up in Phase-1 NoW
105 Development of intake and conveyer infrastructure
Current to October 2015
Mine Design and Scheduling
Current to Jan 2019
Destress mining accessed from 105 Level South of the Wrench fault
Continuation of the Phase-1 NoW at ~220Kt/m
105 SoW commence Jan 2013
110 Level Decline to SoW commence in October 2012
Mine Design and Scheduling
Infrastructure development on 95 and 93 levels to access the
Eastern portion of Phase-1 SoW (Block-A)
Start date Jan 2023
Current to Jan 2035
Stoping on the four corridors South of Wrench (West Block-B)
110 Level mining reaching SoW in 2020
Mine Design and Scheduling
Stoping in the Eastern portion of
Phase-1 SoW (Block-A)
Stoping in Phase-2
VCR mining
Current to Jan 2050
Mine Design and Scheduling
Completion of Phase-2
Current to Dec 2067
Completion of Phase-1 SoW (Block – A)
Mine Design and Scheduling
Final Extraction (April 2064)
VCR Pillar extraction
Retreat mining in original access areas
Mine Design and Scheduling
Reserves
Tonnes (Mt) Grade (g/t) Gold (‘000 oz)
Classification Dec 2010
June 2010
June 2009
Dec 2010
June 2010
June 2009
Dec 2010
June2010
June 2009
CM – Proved 14.9 14.1 15.2 6.5 5.9 5.9 3,113 2,700 2,906
CM – Probable 1.8 3.7 3.7 5.5 4.2 4.2 308 505 505
NOW - Probable 56.2 42.5 42.6 6.6 6.6 6.6 11,968 8,991 9,014
SOW – Probable 83.3 17.5 17.5 5.0 6.6 6.6 13,378 3,703 3,703
OM – Probable 0 3.8 3.8 0 8.7 8.7 0 1,044 1,044
Total AI 156.1 81.6 82.8 5.7 6.5 6.5 28,766 16,943 17,171
Probable (BI) –
Phase 236.5 66.6 66.6 4.9 5.8 5.8 5,767 12,315 12,315
Total 192.6 148.2 149.4 5.6 6.1 6.1 34,533 29,258 29,486
27
Mineral Reserves at a gold price of R265,000/kg
0
40
80
120
160
ReservesApproximately one third of those of Gold Fields, AngloGold Ashanti
Reserves (Moz)
______________________Source: Goldval.com as at September 2010
Existing Mine Infrastructure
29
Station Station
33 Lvl
48 Lvl
49 Lvl
50 Lvl
53 Lvl
56 Lvl
58 Lvl
60 Lvl
63 Lvl
65 Lvl
68 Lvl
70 Lvl
70a Lvl
71 Lvl
72 Lvl
75 Lvl
78 Lvl
80 Lvl
83 Lvl
85 Lvl
87 Lvl
90 Lvl 90 Lvl
93 Lvl 93 Lvl
94 Lvl
95 Lvl 95 Lvl
100 Lvl 100 Lvl
105 Lvl 105 Lvl
110 Lvl 110 Lvl
110a Lvl
Colour Coding: Red Up Cast.Green Down CastGold Rock Handling Capacity
Rock Capacity 120ktpm Rock Capacity 175ktpmRock Capacity 195ktpm
94 Level Refrigeration
SV 1
50 Level Plugs
Shaft damaged
South Shaft
SV 3
80 Level Pumps & Refrigeration
Plants
83 Level Backfill Plant
95a Level Pump Station
Intermediate Pump Stations
Twins Ventilation Shaft
Twins Main Shaft
51 Level Pump Station
84 Level Pump Station
Metallurgical Plant
SV 2
Deepened Section
110a Pump
Challenge is the limited Storage from 95 Level to
95a Level
1.4km
30
Headgear A-Frame early lift strategyCompleted in May 2011
Rock winder installation progressing to plan – all major components manufactured and delivered to the mine
Planned Mine Infrastructure – Vent Shaft Deepening
105 level
100 level
110 level
95 level
Main Shaft Ventilation Shaft
Reef silo’s 105 to 110 level
110A level
100A level
Reef silo’s 110 to 110A level
Settlers & dams 105 to 110 level
31
Reef silo’s 100 to 105 level
Main Shaft Ventilation ShaftPlanned Mine Infrastructure – Mine Development
32
Full Plant Tailings – Backfill plant under construction at South Shaft
Planned Mine Infrastructure – Backfill Infrastructure
33
Completed Silt Trap and Neutralisation Plant
TSF – tailings deposition to cover the toe drains is in progress
Penstock - returning water to fill the return water dam
No.1
No.2
Planned Mine Infrastructure – Tailings Storage Facility
Return Water Dam – lining complete and both return dams being filled
330ktpm milling capacity
450ktpm downstream processing capacity
34
Leach extension earthworks
Planned Mine Infrastructure – Plant Expansion
Leach extension earthworks
Thickener earthworks
Leach Extension Civils
Thickener Civilsand Earthworks
Ball Mill 2 Civilsand Earthworks
Thickener Civilsand Earthworks
35
Eskom new 132KV overhead supply line
40MVA transformer No.5
Substation extension
Planned Mine Infrastructure – Electrical Infrastructure
Enjoy your visit to South Deep