southern regional load despatch centre · southern regional load despatch centre 2005 – 06 29,...

93
SOUTHERN REGIONAL LOAD DESPATCH CENTRE WWW.SRLDC.ORG 2005 – 06 29, RACE COURSE CROSS ROAD, BANGALORE – 560 009

Upload: others

Post on 16-Jul-2020

8 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

E

29, R

SOUTHERN REGIONAL LOAD DESPATCH CENTR

WWW.SRLDC.ORG

2005 – 06

ACE COURSE CROSS ROAD, BANGALORE – 560 009

Page 2: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

Preface

Southern Regional Grid has passed another year with consistent growth and development and during the year the maximum and minimum demands have touched as high and low as 23,372 MW and 10,710 MW respectively. Even with such a large variation in the demand, the frequency could be maintained in the normal band for as much as 96.64% of time, which certainly gives a sense of accomplishment and achievement. With the continued augmentation of the generation and transmission network in the grid, the system grew further stronger and safer, contributing towards another disturbance-free year. During the year, the provisions of CERC orders for revised Terms and Conditions of Tariff and the revised STOA Regulations were implemented with all thrust and measures, resulting in easy transfer of power with the neighboring Regions. The 2000 MW HVDC Talcher-Kolar link which has become a life line for the SR grid was used to carry still higher quantum of power from ER to SR and it touched to a value of 1915 MW. Also, to take care of any eventuality of tripping of HVDC Talcher-Kolar link, the Special Protection Scheme (SPS) was also made fully operational by providing a load relief of 1600 MW in the event of bi-pole trip. The ULDC scheme which is the eyes and ears of the grid operators has continued to play an important role in grid operation and control. To further augment the usage of the ULDC system, a number of training programmes were conducted at SRLDC for enhancing the knowledge-base of the engineers of the constituents in the field of SCADA, EMS and other related functions. With the continued co-operation among the Grid Operators, the system voltages could be maintained well within the permissible limits of IEGC range and thereby minimizing the system losses and maximizing the generation availability. With the advancement in the IT field, several software utilities have also been developed in-house by RLDC for functions like shutdown coordination, outage data of transmission and generation elements and data base in respect of STOA transactions. Aiming towards paperless working and to achieve maximum possible transparency, SRLDC has taken steps to post all the scheduling and commercial data on its web site www.srldc.org along with the daily, weekly and monthly system operation reports. This document in the form of ‘Annual Report’ contains the highlights and progress the SR system made during the year as well as the details of power supply position and system parameters. Feed back on the report and/or suggestions for the further improvement is most welcome.

Page 3: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

2005-06 2004-05 2003-04

1 INSTALLED CAPACITY IN MW(At the end of the year) 36769 * 32734 30794

2 GENERATION CAPACITY ADDITION (MW) 871 1940 1606

3 PEAK DEMAND MET (MW)

- SOUTHERN REGION 23372 22364 21928

- ANDHRA PRADESH 8239 7613 7441

- KARNATAKA 5558 5612 5445

- KERALA 2578 2420 2426

- TAMILNADU 8209 7473 7401

4 AVERAGE DAILY ENERGY CONSUMPTION (MU)

- SOUTHERN REGION 417.43 406.50 395.01

- ANDHRA PRADESH 144.40 143.56 129.62

- KARNATAKA 93.54 91.52 85.19

- KERALA 36.73 34.41 33.62

- TAMILNADU & PONDICHERRY 142.75 137.01 146.57

5 AVERAGE DAILY REGIONAL GENERATION (MU) 459.47 428.22 394.05

6 AVERAGE ISGS GENERATION (MU) 138.21 117.20 99.19

7 AVERAGE GRID FREQUENCY(Hz) 49.84 49.85 49.69

8 AVERAGE FREQUENCY VARIATION INDEX 1.63 0.83 1.96

9 % TIME GRID FREQUENCY

- BELOW 49.0Hz 2.32 0.13 2.30

- BETWEEN 49.0Hz & 50.5Hz 96.64 99.7 97.26

- ABOVE 50.5Hz 1.04 0.17 0.44

10 AVERAGE OF DAILY MAXIMUM AND DAILY MINIMUM VOLTAGES (KV) MAX / MIN MAX / MIN MAX / MIN

- BANGALORE 411/388 410 / 391 405 / 385

- HYDERABAD 424/411 416 / 402 411 / 397

- CHENNAI 423/402 423 / 406 417 / 403

- TRISSUR 414/394 414 / 398 412 / 400

11 EXCHANGE THROUGH HVDC LINKS (MU)

- TALCHER-KOLAR BIPOLE (WITH ER)

IMPORT 11163 9330 6039

EXPORT 0 0 0

- GAZUWAKA HVDC BTB (WITH ER)

IMPORT 2096 2500 1926

EXPORT 3 1 0

- BHADRAVATI HVDC BTB (WITH WR)

IMPORT 220 147 298

EXPORT 2939 1761 543

* Includes Wind & Co-generation etc.

OPERATIONAL SUMMARY

Page 4: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

CONTENTS PAGE No. .

Section 1 Highlights During the Year 1 Section 2 Southern Regional Grid – An Overview 4 Section 3 New Generating Units/Lines/Sub-Stations commissioned during the year 9 Section 4 ULDC Scheme in Southern Region 12 Section 5 Generating Capacity 5.1 Summary of Installed Generating Capacity 27 5.2 Details of Installed Generating Capacity 28 5.3 Growth of Installed Generating Capacity during past decade 32 Section 6 Power Supply Position 6.1 Summary of 2004-05 Power Supply Position 33 6.2 Monthwise Power Supply Position (Energy & Peak MW) 34 6.3 Monthwise Maximum, Minimum Energy Consumption with corresponding dates 36 6.4 Monthwise Maximum and Minimum Demand met (MW) with corresponding dates 37 6.5 Demand met (MU/day and Peak MW) in Southern Region during past decade 38 6.6 Monthwise Schedule vs. Actual drawal by States from Central Sector Stations 39 6.7 Monthwise Inter-Regional Exchanges 40 6.8 Inter-Regional Exchange during past 5 years 41 6.9 Kadamparai Pumped Storage Plant Operational Details during past 5 years 42 Section 7 Generating Stations Performance 7.1 Summary of 2004-05 Regional Energy Generation 43 7.2 Performance of Generating Stations 44 7.3 Monthwise PLF of Thermal / Nuclear Generating Stations 51 7.4 Monthwise Schedule vs. Actual Generation by ISGSs 52 Section 8 Regional Load Curve Data 8.1 Generation vs. Load for the Maximum Demand Day 53 8.2 Generation vs. Load for the Minimum Demand Day 54 Section 9 Frequency, Voltage & Reservoir data 9.1 Monthwise Frequency Analysis 55 9.2 Monthwise Maximum / Minimum Voltage recorded at 400 KV Buses 56 9.3 Reservoir Data 57 9.4 Frequency Analysis during last 5 years 58 9.5 Voltage Analysis during last 5 years 59 Section 10 Miscellaneous 10.1 Under Frequency Relays Provision in Southern Region 60 10.2 Shunt Capacitors Installation in Southern Region 61 Graphs G-1 Break-up of effective Generating Capacity (source-wise) 62 G-2 Break-up of effective Generating Capacity (constituents-wise) 63 G-3 Source-wise contribution to Regional Energy during 2004-05 64 G-4 Source-wise contribution to Peak Met during 2004-05 65 G-5 Monthwise Frequency Spectrum 66 G-6 Annual Load Duration Curve 67 G-7 Annual Frequency Duration Curve 69 G-8 Load Curves for Maximum and Minimum Demand day 70 G-9 Reservoir Levels during last 3 years 72 Exhibits E-1 400 KV Network 76 E-2 Details of Reactors on Lines and Buses 77

Page 5: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009
Page 6: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

HIGHLIGHTS DURING THE YEAR

1.1 Power Supply Position

During the year 2005-06, the power supply position in the Region has been satisfactory and there was an addition of capacity generation to the tune of 875 MW. In order to have overall economy and efficiency, power was also exchanged with the neighboring Regions on opportunity basis. During the year the energy and peak MW availability in the grid also increased by 4% (daily average energy increased from 406.5 MU per day to 417.4 MU per day and peak MW increased from 22,364 MW to 23,372 MW).

Daily Consumption Plot Of SR For 2004-05 & 2005-06

280

330

380

430

480

530

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov Dec Jan

Feb

Mar

MONTHS ---->

CO

NSU

MPT

ION

(Mus

) ---

->

2005-06

2004-05

During the rainy season of the year, the region has got good inflows compared to last year and during different parts of the year most of the regional constituents have exported the power to neighboring regions through STOA transactions and UI. This year the region has witnessed a maximum consumption of energy 517.5 MU on 24th March 2006 and maximum peak demand of 23,372 MW on 29th March 2006. 1.2 Frequency Regime

During the year for 96.64% of the time, the frequency was within normal band i.e. between 49.0 to 50.5 Hz and the frequency profile was satisfactory. However during certain period of the year, particularly during the months of February-March 2006 the frequency sustained in the low range due to high demand coupled with low generation at some stations due to shortage of fuel etc.

Frequency Duration Curve (Last 4 Years)

47.0

47.5

48.0

48.5

49.0

49.5

50.0

50.5

51.0

5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95% OF TIME --->

FREQ

IN

HZ

--->

2002-03

2003-04

2004-052005-06

The frequency profile below 49 Hz. was for 2.32% of the time and in the higher

band, i.e above 50.5 Hz 1.04% of the time. 1

Page 7: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

1.3 Voltage Profile

During the year, the voltage profile remained within operating range with average daily minimum voltage of 388 KV at Bangalore. At times, during the lean demand period the voltage levels had increased and to contain the voltage all possible measures were taken including opening of some of the EHV lines.

Bangalore Voltage Comparision on a Typical Day (4th Mar 05 & 06)

360

370

380

390

400

410

420

00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23TIME IN HRS --->

VOLT

AG

E (K

V) --

>

2006

2005

Similarly on the neighbouring 400 KV buses also, there has been improvement of about 3-8kV in the voltage levels. The improvement in the voltage profile has been made possible due to judicious switching in and switching out of the VAR controlling devices (reactors and capacitors etc.), changing of transformer taps as well as participation by the generating units in VAR management. The month wise details of the maximum, minimum and average of daily minimum and maximum voltage of important 400 KV substations are given in Section 9.2

1.4 Short-term Open Access (STOA)

During this year a number of transactions under STOA were approved by SRLDC as nodal agency and simultaneously approval/consent was also accorded for wheeling of the power from ER/NER to WR/NR through SR. During the year 2005-06 , a total 865 number of cases were processed in Southern Region involving intra-region, inter-regional and wheeling transactions under STOA and a total energy quantum of 5604 MU was approved, leading to transfer of substantial power from surplus areas to deficit areas. The energy quantum transacted during the year is 80% more than compared to the last year, which was in the range of 3113 MU from 148 transactions. In view of the higher usage of transmission network due to open access, significant amount of relief to the SR constituents was also possible towards payment of annual transmission charges.

1.5 Inter – Regional Exchanges

Depending on the system conditions on opportunity basis, there has been a remarkably large UI exchange with neighboring regions. In the year 2005-06, SR has exported to WR, the energy to the tune of 403 MU and imported the energy to the tune of 348 MU. The figure shown below indicates the details of UI exported from SR to WR/ER on a typical day where the export under UI was to the extent of 8.57MU and during certain period exported quantity was as high as 718 MW to WR and 585 MW to ER. By exchanging UI with neighboring regions SR has gained to the tune of Rs.80 crores net during the year 2005-06. 2

Page 8: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

Typical Day UI Export From SR To ER/WR on 30-Aug-05

-400

-200

0

200

400

600

800

1000

1200

1400

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

HOURS --->

MW

---->

49.0

49.5

50.0

50.5

51.0

51.5

52.0

52.5

53.0

53.5

FREQ

(H

Z) -

--->

UI

CG Freq SR Freq

1.6 Up-To-Date Settlement of UI Pool Account

During the year 2005 – 06, the total turnover in SR in respect of UI is 3020 MU with disbursement amount of Rs. 644 Crores .This on an average comes out to be around 58 MU energy exchange per week with average disbursement of 12 Crores of Rupees. With the active co-operation of all the constituents, SRLDC has been able to maintain up-to-date settlement of UI transaction and no amount is outstanding amongst the constituents.

1.7 Safe and Secure Grid Operation

In view of the system strengthening and increase in the generation level as well as substantial operational efforts, the system parameters were maintained in normal range and security and safety of the grid was kept intact and no major disturbance occurred in the grid during the year 2005-06.

3

Page 9: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009
Page 10: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

SOUTHERN REGIONAL GRID - AN OVERVIEW

2.1 SOUTHERN REGIONAL GRID 2.1.1 SR Grid Constituents

Southern Regional (SR) grid is a large system comprising of 651000 sq. kms.of area encompassing 4 states system viz Andhra Pradesh, Karnataka, TamilNadu and kerala and Union Territory of Pondicherry and Central Sector, State sector and Independent Power Producing Generating stations. Different states are interconnected with each other through 400 KV grid network and some 200 KV inter-state lines.

ANDHRA PRADESH INSTALLED CAPACITY :-6823 MW KARNATAKA

INSTALLED CAPACITY :-4992 MW

PEAK DEMAND MET :-8239 MW

DAILY AVERAGE CONSUMPTION:-144 MU

PEAK DEMAND MET :-5558 MW

DAILY AVERAGE CONSUMPTION:- 94 MU

TAMILNADUINSTALLED CAPACITY :-5550 MW KERALA

INSTALLED CAPACITY :-2072 MW

PEAK DEMAND MET :-8209 MW

DAILY AVG CONSUMPTION:-139 MU

PEAK DEMAND MET :-2578 MW

DAILY AVERAGE CONSUMPTION:-37 MU

2.1.2 Effective Generation Capacity of SR • Effective generating capacity as on 31st March 2006 : 36769 MW • Regional peak demand met (2005-06) : 23372 MW • Average energy consumption(2005-06) : 417.4 MU/Day • Transmission systems (as on 31st March 2006)

+ 500 HVDC : 1370 ckt. kms. 400 kV A.C : 14300 ckt. kms.

220 kV A.C : 27600 ckt. kms.

4

Page 11: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

SOURCE-WISE EFFECTIVE GENERATING CAPACITY OF SOUTHERN REGION AS ON 31-MAR-06

HYDRO31%

THERMAL43%

GAS/NAPTHA/DIESEL12%

NUCLEAR2%

WIND12%

2.1.3 Salient features of the Southern Regional Grid

• 3rd largest geographical area amongst the five regions, covering apporx.19% of the area & approx.22% of India’s population and 29% of the Installed Capacity.

• Best Hydro thermal mix(31-69%) amongst all five regions giving, best operational flexibility

• 2600 MW Capacity Thermal Power Station of NTPC at Ramagundam which is the

largest capacity generating station in the country.

• Largest Pump storage schemes in the country at Srisailam (900MW), Andhra Pradesh and at Kadamparai (400MW), Tamil Nadu, bringing about economy in scale and operational flexibility.

• 2000 MW capacity Talchar-Kolar HVDC interconnection with the Eastern Region,

which is the largest capacity HVDC interconnection in the country.

• 3300 MW Wind Mill generating capacity (Approx.) which is highest amongst all the regions.

• 8000 MW capacity (Approx) from Independent Power Producers(IPP’s) generating

plants, which is also highest amongst all the regions.

5

Page 12: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

6

2.2 FUNCTIONS OF SRLDC As the ‘Apex Body’ for operation of the integrated Grid, the statutory functions of

SRLDC are:

• Optimum scheduling and despatch of electricity within the Region;

• Monitoring grid operation ;

• Keeping accounts of quantity of electricity transmitted through the Regional Grid;

• Exercising supervision and control over the Inter-State Transmission System

(ISTS);

• Responsible for Carrying out real time operations for grid control and despatch of electricity within the region through secure and economic operation of the regional grid in accordance with the Grid Standards and the Grid Code.

2.3 CHANGED FACE OF OPERATION OF SR GRID

• With the commissioning of Gazuwaka HVDC Pole II, power handling capacity increased to 1000MW. This is also helping in evacuation of Talcher – II power in case of any contingency on Talcher-Kolar HVDC link/ER system.

• Power handling capacity of Talcher-Kolar HVDC increased to 2000MW

with the successful commissioning of Special Protection Scheme at Talcher. • By commissioning of 400KV Madurai-Trivendrum D/C lines, inter-

connection between Kerala and Tamil Nadu is strengthened. • By commissioning of 400KV Kaiga-Narendra D/C lines, evacuation of

Kaiga generation made easy. This also helps in reducing the overloading problem of Kaiga-Guttur lines.

2.4 SPECIFIC ACHIEVEMENTS OF SRLDC

2.4.1 Grid Security and Safety

The SR grid security and safety has been enhanced remarkably in the recent

past following taking up of large number of measures as stated above and close co- ordination with the different Control centers/Utilities. As a testimony to this, it can be seen that no major grid disturbance in Southern Region has taken place in the last couple of years.

Page 13: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

7

2.4.2 Economic and Efficient System Operation In view of the strengthening of the network and various reactive control

measures like switching in/switching out of the Reactors, changing of Transformer Tap positions and operation of generating units in synchronous condenser mode etc.,, the voltage profile in SR grid has been improved consistently. As a result of the improvement in the voltage profile the overall system loss in the region is also being reduced, bringing about overall economy and efficiency.

ABT has infused a sense of commercial awareness amongst all the constituents of the region and has brought about a marked improvement in the system parameters and economy and efficiency in the Region. Open access in Power trading also helped the constituents to make best utilization of available resources which led to economy as well improvement in system parameters.

2.4.3 Metering and Settlement System under ABT Regime

SRLDC plays an important and a key role in metering and settlement system in Southern Regional grid. Over 300 Special Energy Meters (SEMs) of 0.2S accuracy class have been installed and commissioned covering 70 locations in the region in order to measure active as well as reactive energy exchanges at various inter utility exchange points of the States and ISGS. The data from these meters are read on weekly basis on every Monday and transferred electronically to SRLDC for processing and validation and for preparation of weekly Unscheduled Interchange (UI)/Reactive Energy (RE) accounts. SRLDC also operates and maintains Pool Account for UI and Reactive Energy Charges in the region. With the excellent support rendered by Constituents, No outstanding dues remain to be settled in pool accounts.

2.4.4 In-house development of operational utilities In view of transfer of REA responsibility to SRLDC from 1st April 2006,

requisite software utilities have been developed by SRLDC for the energy accounting calculations and successful mock accounts have been prepared for the months of Feb & March 2006.

2.4.5 Training for operators on ULDC scheme In order to enhance the skill of the system operators/development engineers at different control centers in the regions, SRLDC has conducted various training programmes including RTNA, NMS, RTU and XA-21 user level modules using in-house and external faculties. These training programmes have given a lot of confidence to the operators/development engineers, in order to utilise the facility provided under ULDC scheme in best possible manner. Training also provided to engineers on Grid Management & Open Access had helped to gain good knowledge for grid operation.

Page 14: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

8

2.4.6 SRLDC Website:

SRLDC website www.srldc.org has been designed to give the latest and relevant information in regard to grid operation and control. In order to update all the players and other agencies in and outside the grid, the various power supply position (psp) reports prepared at SRLDC on daily, weekly and monthly basis, and other relevant reports/documents are regularly uplinked to the website. The complete range of information related to daily schedules, bilateral contracts, un requisitioned surpluses, real time data, energy meter data and the pool account operation details etc. are also available on the website bringing about complete transparency in the entire process and leading to a zero dispute regime.

2.5 GRID SECURITY ENHANCEMENT USING SPECIAL PROTECTION SCHEME A specially designed protection scheme in order to safeguard the system in

the event of tripping of 2000 MW capacity HVDC Talcher-Kolar link has been designed and implemented in the SR Grid during the year. Under the phase-1 of the scheme which was already operational, automatic load shedding of the order of around 600 – 800MW used to be carried out in the event of tripping of HVDC link by transmitting inter-trip signals to distant sub-stations through PLCC Channels. During the year under phase 2, the scheme has been augmented further and from 28th March 2006 a total load relief of around 1500 MW from sub-stations of all the states is achieved by communicating trip signal through wide band communication network. The scheme has been of immense help in enhancing the SR grid safety and security in the event of tripping of HVDC Talcher-Kolar links.

2.6 THE ROAD AHEAD Indian Power Sector is witnessing major changes. Recognizing that electricity is one of the key drivers for rapid economic growth and poverty alleviation, the nation has set itself the target of providing access to all household by the end of the XI Plan, i.e. around end 2012. Further, the widely distributed and increasing demand of the Regions is required to be met in an optimum manner. Supply of reliable and quality power of specified standards in an efficient manner and at reasonable rates is another challenge ahead for all the Power Engineers. The enactment of Electricity Act 2003, its amendments and changes in Open Access Regulations in ISTS were already brought about in this direction. Revised IEGC 2006 norms help the operators to maintain the grid in safe and operable limits. The another important issue which required to be addressed in right earnest is harnessing large quantum of unutilized generation available with CPPs and IPPs within the States would not only help the grid meet its increased demand but also give assistance on STOA and opportunity basis to neighbouring Regions in crisis situations. Implementation of intra-state ABT in the State is also on the anvil and this would help in rationalization of tariff and scheduling process within the States for the generators and its distribution companies. It is of prime importance that States make all possible efforts to achieve this goal by optimizing their generation as well as by adopting best possible grid side management techniques through good load forecasting methods and other available means.

Page 15: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009
Page 16: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

3.1 GENERATING UNITS

SL.NO. STATION NAME CAPACITY (MW) TYPE OF FUEL DATE

1 GVK EXTENSION CCP (GT) 140 GAS 09-Oct-05

2 GVK EXTENSION CCP (ST) 80 GAS 11-Nov-05

3 VEMAGIRI CCPP 233 GAS 11-Nov-05

4 ALMATTI DAM POWER HOUSE U # 5 55 HYDRO 06-Jul-05

5 ALMATTI DAM POWER HOUSE U # 6 55 HYDRO 10-Aug-05

6 SABARIGIRI U # 6 ENHANCEMENT (50MW TO 60MW) 10 HYDRO 01-Jul-05

7 MALANKARA U # 1, 2 & 3 10.5 HYDRO 23-Oct-05

8 NERIAMANGALAM U# 2 ENHANCEMENT (15MW TO 17.5MW) 2.5 HYDRO 01-Dec-05

9 LOWER MEENMUTTY 1.5 HYDRO 25-Mar-06

10 ABAN POWER COMPANY (ST) 49.8 GAS 15-Jul-05

11 PYKARA ULTIMATE STAGE HEP U # 1& 2 100 HYDRO 11-Aug-05

12 PYKARA ULTIMATE STAGE HEP U # 3 50 HYDRO 06-Sep-05

13 ARKEY ENERGY (GT) 38 GAS 29-Oct-05

14 MAPP U # 1 UPGRADATION 50 NUCLEAR 18-Jan-06

TOTAL 875

3. NEW GENERATING UNITS/LINES/SUB-STATIONS COMMSSIONED DURING THE YEAR 2005-06

ANDHRA PRADESH

KARNATAKA

KERALA

TAMIL NADU

CENTRAL SECTOR

NPC

9

Page 17: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

3.2 TRANSMISSION LINES

SL.NO. NAME OF LINE CKT NO KV CKT KM DATEANDHRA PRADESH

1 KALPAKA(VIZAG)-VEMAGIRI I & II 400 316.0 10-Sep-05

2 VEMAGIRI-GMR I & II 400 4.0 11-Sep-05

3 VEMAGIRI-GVK(JPD) I & II 400 16.0 27-Sep-05

4 LILO OF N'SAGAR-RAICHUR AT MAHABOOBNAGAR I 400 1.0 17-Oct-05

5 MAHABOOBNAGAR-BOOTHPUR I & II 220 32.5 19-Oct-05

6 LILO OF SULURPET-NELLORE LINE AT 400KV NELLORE S/S 220 12.1 26-Dec-05

7 NUNNA-VEMAGIRI I & II 400 280.0 28-Dec-05

8 LILO OF 400KV CUDDAPAH-MADRAS AT CHITTOOR I 400 21.1 16-Feb-06

KARNATAKA

9 SHAHAPUR-GULBARGA I & II 220 8.3 17-May-05

10 KADUR-CHIKKAMAGALUR I & II 220 0.8 27-Jun-05

11 NARENDRA-HAVERI I & II 220 95.2 7-Jan-06

12 KUDACHI-MAHALINGAPUR I & II 220 72.0 23-Jan-06

13 TK HALLI-MADUVANAHALLI I & II 220 34.1 15-Mar-06

KERALA

14 POTHENCODE-400KV PG S/S AT TVM I, II, III & IV 220 15.0 25-Aug-05

15 LILO OF KAYAMKULAM-EDAMON AT KUNDARA II 220 46.5 5-Jan-06

TAMIL NADU

16 LILO OF NCTPS-THIRUVALAM AT ALMATHY I 230 3.1 24-Jul-05

17 LILO OF METTUR-HOSUR AT KARIMANGALAM I 230 49.0 4-Aug-05

18 230KV PUSHEP-ARASUR LINE I & II 230 116.5 4-Aug-05

19 SALEM 400KV S/S -INGUR 230KV S/S I 230 84.0 29-Aug-05

20 LILO OF EDAMON-KAYATHAR AT KODIKURICHI I 230 6.0 3-Oct-05

21 LILO OF UNJANAI-PUGALUR AT PUTHANSANTHAI I 230 35.7 29-Mar-06

POWERGRID

21 MADURAI-TRIVANDRUM I & II 400 432.0 1-Aug-05

22 KAIGA-GUTTUR (WAS CHARGED AT 220KV ) II 400 161.0 8-Aug-05

23 KAIGA-NARENDRA I & II 400 216.0 1-Nov-05

10

Page 18: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

3.3 SUB-STATIONS

SL.NO. SUB STATION MVA RATING KV LEVEL DATE

1 SHAMSHABAD 100 220/132 21-Jul-05

2 VEMAGIRI 2x315 400/220 11-Sep-05

3 MAHABOOBNAGAR 1x315 400/220 18-Oct-05

4 NELLORE 1x315 400/220 18-Dec-05

5 CHITTOOR 1x315 400/220 3-Mar-06

6 NELAMANGALA 3x 167 400/220 29-Jun-05

7 KADUR 2x100 220/110 8-Jul-05

8 MADUVANAHALLI 2x100 220/110 16-Mar-06

9 KUDACHI 2x100 220/110 27-Mar-06

10 GUTTUR 1x315 400/220 31-Mar-06

11 KUNDARA 1x100+3x12.5 220/110 14-Jan-06

12 MALUMICHAMPATTY 2x100 230/110 3-Apr-05

13 UDUMALPET 1x100 230/110 30-Jul-05

14 KARIMANGALAM 1x100 230/110 4-Aug-05

15 VEERANAM 1x50 230/33 28-Sep-05

16 KODIKURICHI 1x100 230/110 5-Oct-05

17 KILPAUK 1x50 230/110 27-Jan-06

NPC

18 KAIGA 1x500 400/220 4-Jun-05

19 TRIVANDRUM 2x315 400/220 1-Aug-05

20 NARENDRA 1x315 400/220 1-Nov-05

TAMIL NADU

POWERGRID

ANDHRA PRADESH

KARNATAKA

KERALA

11

Page 19: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009
Page 20: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

ULDC SCHEME IN SOUTHERN REGION

4.1 Overview The Unified Load Despatch Scheme (ULDC) in SR was commissioned in January 2002. The scheme envisaged installation and commissioning of Remote Terminal Units (RTUs), integration of existing RTUs in Karnataka, Tamil Nadu and Unit Territory of Pondicherry, installation and commissioning of dedicated communication system comprising of Fibre Optic, Microwave and PLCC system, installation and commissioning of Auxiliary Power supply system such as UPS, DG set, 48V D.C supply system and installation of EPABX system. Under this scheme the Regional System Coordination Centers (RSCC) & Central Project Coordination Centers (CPCC) were established at Bangalore whereas State Load Despatch Centres (SLDCs) were established at Mamidapally (Andhra Pradesh), Bangalore (Karnataka), Kalamassery (Kerala), Chennai (Tamil Nadu) along with system control center (SCC) at Pondicherry. Under each SLDC, Sub-LDCs were also established. The hierarchy of ULDC in Southern Region is given below:

RLDC,Bangalore

SCC, Pondy CPCC

Hyderabad Kalamassery Chennai Bangalore

Kerala Tamilnadu Andhra KarnatakaHYDERBAD

WARANGAL KALAMASSERY CHENNAI BANGALORE

CUDDAPAH KANNUR ERODE HUBLI

VIJAYAWADA TRIVANDRUM MADURAI LINGASUGUR

A list of RTUs integrated in ULDC scheme is enclosed as Annexure-I. Also, connectivity details of Workstations, Front-End Processors and Application Servers at RSCC and SLDCs are enclosed at Annexure-II 4.2 Specific Functions The SCADA-EMS system in ULDC is a suite of various Applications covering a broad spectrum of functions like Pre-Dispatch, Real-Time and Post-Dispatch functions. The details of these functions and their deployment in RSCC, SLDC’s and Sub-LDC’s are given in Annexure-III

12

Page 21: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

4.3 Communication Package A strong Communication Backbone is the key to the smooth functioning of the ULDC scheme. The Communication backbone is mainly on Fibre-Optic and Microwave links whereas the last mile connectivity is mostly on Power Line Carrier Communication (PLCC) links. The details of Fibre-Optic and Microwave Communication packages are given below. The Geographical map showing the details of Communication Backbone Network is enclosed at Annexure-IV

DETAILS OF FIBRE-OPTIC AND MICROWAVE PACKAGES FIBRE-OPTIC MICROWAVE S. NO. CONSTITUENTS TOTAL LENGTH

OF FIBRE OPTIC CABLE IN KMS

TO NO. OF HOPS

TOTAL NO. OF TOWERS

1 CENTRAL SECTOR 604 2 2 2 APTRANSCO 1037 7 7 3 KPTCL VSAT COMM LINKS PROVIDED BY KPTCL 4 KSEB 275 7 7 5 TNEB 396 16 16 6 UT OF PONDICHERRY NIL 3 3 TOTAL 2312 35 35

As the back up route to different SLDC’s was on the same physical route (through Optical Fibre Cable/Microwave), outage of the physical route was causing loss of data. In order to provide reliability & redundancy in data communication channel, an alternate physical route between SRLDC & SLDC’s has been established through a separate agency (i.e. BSNL) which has greatly improved the data availability/reliability. 4.4 Energy Management System Under this scheme various Energy Management System (EMS) modules have been implemented in the different control centers (RSCC/SLDCs). The power application functions under EMS package implemented in control centers support operational requirement of the SR grid and can be broadly grouped into Pre-dispatch, Real time dispatch and Post-dispatch functions. The Energy Management System (EMS) tools such as state estimation, contingent analysis, optimum power flow, load forecasting, resources scheduling and commitment has provided system operators greater flexibility in taking appropriate and judicious decisions during the course of operation. To supplement further, the following operational tools have been developed 4.4.1 Power Network Analysis (PNA) Module:

Due to complexity associated with the size of Power Network Analysis (PNA) module, the common network model was truncated control area-wise with view to develop different truncated model at the respective state and then to integrate the same to a common network model. All SR states have developed their PNA model separately. The models developed in Andhra Pradesh (AP) and RSCC have already been integrated at RSCC and is working satisfactorily. Similarly, models

13

Page 22: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

developed in Kerala (KSEB) & Tamil Nadu (TNEB) have also been integrated at Kerala & the same is also working satisfactorily. This has given an additional tool to system operator to do the contingent analysis more accurately. The integration process of integrated AP+RSCC model & TN +KER model has begun.

4.4.2 Disturbance Data Collection (DDC) Display:

Disturbance data collection (DDC) module has been fully configured to collect all telemetered parameters for a pre-configured interval before and after a disturbance. The ‘disturbance trigger’ can be a single event or a complex set of violation in the grid. During a grid disturbance or system occurrence the snap shot of the entire grid is stored in the system. Generally a pre-disturbance period of 5 minutes and a post disturbance period of 15 minutes information are available. DDC display is run to view the events that have taken place 5 minutes prior and 15 minutes after the disturbance. This tool has helped system operator in analyzing the grid occurrences more accurately to a large extent.

4.4.3 Data Extraction Tool (GET DATA)

A data extraction tool (GET DATA) has been developed which facilitates the system operator to extract data from the Temporal Data Base system and guides them to take appropriate decision during the system operation.

4.5 Monitoring Complexity Under this scheme, more than 30,000 Analog and Status points have been wired up covering more than 300 nodes across the Southern Region and the data from all these nodes are updated every 10-15 seconds. The complexities of the Southern Regional Grid in monitoring and control is as depicted below

Integrated Opn of Ten Power

Utilities Annual Inter-

Regional Generators –

Hydro, Energy Transfer Thermal,Gas/IPP

30,000 POINTS ≈10,000MU 422 nos. Active Power, Reactive

Power, Transmission Voltage, Frequency,

Transformer Installed Capacity Network

400/220kV Tap Position, Circuit Breaker Position, Isolator Position etc

≈32700 MW ≈ 40700 Ckm

Transformation Transformers Capacity ≈ (220kV and

above) 45000 MVA Dynamic Grid Conditions 480 nos.

14

Page 23: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

15

4.6 Training In order to enhance the skill of system operators/development engineers at various control centers/SRLDC has conducted various training program on various EMS related modules using expertise of internal as well as external faculties. The training programmes that have already been conducted in the past are as detailed below.

SL NAME OF THE TRAINING FROM TO Participants Man Days

1 CISCO ROUTER & NETWORKING 19-01-2004 24-01-2004 17 102

2 XA-21 USER LEVEL 23-02-2004 28-02-2004 10 60

3 RTNA WORKSHOP 29-03-2004 31-03-2004 14 42

4 AIX OPERATING SYSTEM 17-05-2004 22-05-2004 15 90

5 XA-21 USER LEVEL 21-06-2004 25-06-2004 6 30

6 SYBASE DATABASE ADMIN 22-11-2004 04-12-2004 19 228

7 XA-21 USER LEVEL 21-02-2005 23-02-2005 7 21

8 NMS TRAINING 13-06-2005 18-06-2005 14 84

9 RTU TRAINING 27-02-2006 03-03-2006 14 70

10 JAVA FOR SCADA ENVIRONMENT 24-04-2006 29-04-2006 16 96

4.7 Specific Benefits The benefits derived from the above schemes include:-

(1) Real time operation and monitoring of the system has improved. (2) Outages have been minimized. (3) Grid disturbances have been reduced/averted. (4) System reliability has been enhanced. (5) Losses in the system have come down. (6) Analysis of Grid occurrences has become simple and more visual.

Page 24: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

ANNEXURE - I

I. Central Sector RTUs commissioned and integrated under ULDC SchemeSL No. RTU Reporting CC

1 Chinakampally Central 2 Gazuwaka Central 3 Ghanapur Central 4 Gooty 400 Central 5 Hosur 400 Central 6 Kaiga APP Central 7 Kalpakkam (MAPP) Central 8 Kayamkulam TPS Central 9 Khammam Central

10 Local RTU Central 11 Madurai 400 Central 12 Munirabad Central 13 Nellore 400 Central 14 Neyveli TS-I Extn. Central 15 Neyveli TS-II Central 16 Ramagundam Central 17 Salem 400 Central 18 Somanahalli Central 19 Sriperumbudur Central 20 Tallapally Central 21 Trichur North Central 22 Trichy 400 Central 23 Udumalpet 400 Central 24 Vijayawada 400 Central 25 Kolar RCI Central 26 Trivandrum 400KV Central 27 Hiriyur 400KV Central

II. APTRANSCO

SL No. RTU Reporting CC1 A.P. Carbides Cuddapah 2 Ananthapur Cuddapah 3 Chinakampalli Cuddapah 4 Chitoor Cuddapah 5 Cuddapah 220 Cuddapah 6 Gooty 220 Cuddapah 7 Gooty SWS Cuddapah 8 Hampi PH Cuddapah 9 Hindupur Cuddapah

10 Kalikiri Cuddapah 11 Kurnool - B Cuddapah 12 Marakapur Cuddapah 13 Mydukur Cuddapah 14 Nandyal Cuddapah 15 Nellore 220 Cuddapah 16 NTS Cuddapah 17 Ongole Cuddapah 18 Podili Cuddapah 19 Rajampet Cuddapah 20 Renigunta Cuddapah 21 RTPP Cuddapah 22 Somayajulapalli Cuddapah 23 Srisailam LBPH Cuddapah

List of RTUs integrated under ULDC Scheme

A - RTUs commissioned and integrated under ULDC Scheme

22

Page 25: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

ANNEXURE - I

24 Srisailam PH Cuddapah 25 Sullurpet Cuddapah 26 Yerraguntla Cuddapah 27 CH Gutta Hyderabad 28 Chellakurthy Hyderabad 29 Erragada Hyderabad 30 Gachibowli Hyderabad 31 Ghanapur Hyderabad 32 Hyderbad 400 Hyderabad 33 Jubilee Hills Hyderabad 34 Kalwakurthy Hyderabad 35 Kalwakurthy SWS Hyderabad 36 Local RTU Hyderabad 37 Mahaboob Nagar Hyderabad 38 Malkaram Hyderabad 39 Tandur 220 KV Hyderabad 40 Medchal 220KV Hyderabad 41 Minpur Hyderabad 42 Moulali Hyderabad 43 N' Sagar LCPH Hyderabad 44 N' Sagar PH Hyderabad 45 N' Sagar RCPH Hyderabad 46 Narketpalli Hyderabad 47 R.C.Puram PH Hyderabad 48 Shapurnagar Hyderabad 49 ShivaramPalli Hyderabad 50 Siddipet Hyderabad 51 Tallapally Hyderabad 52 Yeddumailaram Hyderabad 53 Bhimadole Vijayawada 54 Bommur Vijayawada 55 Chilakallu Vijayawada 56 Garividi Vijayawada 57 Gazuwaka Vijayawada 58 Gunadala Vijayawada 59 Tadikonda 220KV Vijayawada 60 Kakinada Vijayawada 61 Kakinada GPS Vijayawada 62 Kalapakka Vijayawada 63 Kondapalli Vijayawada 64 Lower Sileru Vijayawada 65 Machkund Vijayawada 66 Nidadavolu - B Vijayawada 67 Peddapuram Vijayawada 68 Pendurthy Vijayawada 69 Rajahmundry GPS Vijayawada 70 Simhadhri Vijayawada 71 Upper Sileru Vijayawada 72 Vijaywada Vijayawada 73 Vijjeswaram Vijayawada 74 Visakhapatanam SWS Vijayawada 75 VTPS Vijayawada 76 Bhimgal Warangal 77 Bhongir Warangal 78 Durshed Warangal 79 Jagitial Warangal 80 Khammam - B Warangal 81 KTPS Warangal 82 KTPS Vth stage Warangal

23

Page 26: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

ANNEXURE - I

83 Manugur Warangal 84 Miryalaguda Warangal 85 Nirmal Warangal 86 Dichpally 220 Warangal 87 Ramagundam Warangal 88 RTS - B Warangal 89 Sitarampatnam Warangal 90 Wadekothapally Warangal 91 Warangal Warangal

B. APTRANSCO's own RTUs integrated under ULDC SchemeSL No. RTU Reporting CC

1 Kandi 132 KV Hyderabad 2 Kottur 132 KV Hyderabad 3 Bandlaguda 132 KV Hyderabad 4 Gunrock 132 KV Hyderabad 5 Raghunathpally Hyderabad 6 Kodur 220 KV Hyderabad 7 Ramagiri 220/33 KV Hyderabad 8 Nidadavolu 132 KV Hyderabad 9 Dairy Farm 220 KV Hyderabad

10 Rampachodavaram Hyderabad 11 Mahaboobnagar 400 KV (Velture) Hyderabad 12 LANCO Vijayawada 13 BSES Vijayawada 14 Vemagiri 400KV Vijayawada 15 Chittoor 400KV Cuddapah 16 Nelloor 400KV Cuddapah 17 Kurnool 499KV Cuddapah 18 Tadipatri 220KV Cuddapah

III. KPTCLA. RTUs commissioned and integrated under ULDC SchemeSL No. RTU Reporting CC

1 Alipur (Bellary) Bangalore 2 Ambewadi Bangalore 3 Antharasanahalli Bangalore 4 Basavana Bagewadi Bangalore 5 Chikkodi Bangalore 6 D. G. Plant (Yelahanka) Bangalore 7 Guttur (Davangere) Bangalore 8 Hassan Bangalore 9 Hebbal Bangalore

10 Humnabad Bangalore 11 Itagi (Hagari Bommanahalli) Bangalore 12 Kadakola Bangalore 13 Kadra Bangalore 14 Kibbanahalli Cross Bangalore 15 Kodasalli Bangalore 16 Kushtagi Bangalore 17 Lingasugur Bangalore 18 Local RTU Bangalore 19 Mahalingapur Bangalore 20 N.R.S. (Bangalore) Bangalore 21 Sedam Bangalore 22 T.K. Halli Bangalore 23 Sharavathy Bangalore 24 RTPS Bangalore

24

Page 27: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

ANNEXURE - I

25 Nagjhari Bangalore 26 Varahi Bangalore 27 Linganamakki LPH Bangalore 28 Gowribidanur 220 KV Bangalore 29 Hiriyur 220 KV Bangalore 30 Hoody 220/400 KV Bangalore 31 Hubli 220 KV Bangalore 32 Kavoor 220 KV Bangalore 33 Subramanyapura 220 KV Bangalore 34 Jog GS Bangalore 35 Supa GS Bangalore 36 Shimoga 220 Bangalore 37 Somanahalli 220 Bangalore 38 Shahabad 220 Bangalore 39 Peenya 220 Bangalore 40 Munirabad GS Bangalore 41 Hootagalli (Mysore) 220 KV Bangalore 42 Belgam 220 KV Bangalore 43 Davangere 220 KV Bangalore

B. KPTCL's own RTUs integrated under ULDC SchemeSL No. RTU Reporting CC

1 Anchepalya 220 Bangalore 2 Bidadi Bangalore 3 Doddaballapur Bangalore 4 Gadag Bangalore 5 Haveri 220 KV Bangalore 6 HSR Layout Bangalore 7 KEMAR 220 Bangalore 8 Kolar 220 Bangalore 9 Lingapur 220 Bangalore

10 Malur 220 Bangalore 11 Narendra 220 Bangalore 12 Raichur 220 Bangalore 13 Ranibennur 220 Bangalore 14 Yerandahalli 220 Bangalore 15 Bhadra Bangalore 16 Thaneerbhavi IPP Bangalore 17 Tata Power House IPP Bangalore 18 Rayalseema IPP Bangalore 19 Jindal IPP Bangalore 20 Nelamangala 400 KV Bangalore 21 Talaguppa 400 KV Bangalore

IV. KSEB A. RTUs commissioned and integrated under ULDC SchemeSL No. RTU Reporting CC

1 Chalakudy Kalamassery 2 Cochin Kalamassery 3 Idamalayar Kalamassery 4 Idukki Kalamassery 5 Kalamassery Kalamassery 6 Lower Periyar Kalamassery 7 Neriamangalam Kalamassery 8 Pallivasal Kalamassery 9 Pallom Kalamassery

10 Poringalkuttu Kalamassery 11 Sengulam Kalamassery

25

Page 28: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

ANNEXURE - I

12 Sholayar Kalamassery 13 Arikode (Kozhikode-B) Kozhikode (Kannur) 14 Kaniampetta Kozhikode (Kannur) 15 Kannur B Kozhikode (Kannur) 16 Kasargode-B Kozhikode (Kannur) 17 Kozhikode-A Kozhikode (Kannur) 18 Kuttiady Kozhikode (Kannur) 19 Manjeshwaram Kozhikode (Kannur) 20 Palakkad-B Kozhikode (Kannur) 21 Trichur North Kozhikode (Kannur) 22 Trikaripur Kozhikode (Kannur) 23 Edamon Trivandrum 24 Edappon Trivandrum 25 Kakkad Trivandrum 26 Kundara Trivandrum 27 Parasala Trivandrum 28 Sabarigiri Trivandrum 29 Trivandrum North Trivandrum 30 Punnapra Trivandrum

B. KSEB 's own RTUs integrated under ULDC SchemeSL No. RTU Reporting CC

1 Taliparamba 220 KV Kozhikode (Kannur)

V. Electricity Department, Pondy A. RTUs commissioned & integrated under ULDC SchemeSL No. RTU Reporting CC

1 Bahour 230 Pondicherry 2 Mahe Pondicherry 3 T.R.Pattanam Pondicherry 4 Vallianur Pondicherry 5 Yanam Pondicherry 6 Marapallam 110 KV Pondicherry 7 Kurumbapet Pondicherry 8 Sedarpet Pondicherry 9 Thethampakkam Pondicherry

10 Kalapet Pondicherry 11 Eripakkam Pondicherry 12 Thirubhuvani Pondicherry 13 Karaikal 110 Pondicherry 14 Bahour 110 Pondicherry

B. Elect Dept, Pondy's own RTUs integrated under ULDC SchemeSL No. RTU Reporting CC

1 Korkadu 110KV Pondicherry 2 Pillaitheruvasal 110/11KV Pondicherry

VI. TNEB

SL No. RTU Reporting CC1 Arni Chennai 2 Cuddalore Chennai 3 Gumidipoondi Chennai 4 Kadaperi Chennai 5 Koyambedu Chennai 6 Mosur Chennai 7 Mylapore Chennai

A - RTUs commissioned & integrated under ULDC Scheme

26

Page 29: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

ANNEXURE - I

8 SP Koil Chennai 9 Tondiarpet Chennai

10 Villupuram 230 Chennai 11 Vinnamangalam Chennai 12 Acharapakkam Chennai 13 Basin Bridge Chennai 14 Ennore TPS Chennai 15 Manali Chennai 16 Koratur Chennai 17 Neyveli TS I Chennai 18 NMTPS Chennai 19 Sriperumbudur Chennai 20 Thiruvalam Chennai 21 Taramani Chennai 22 Hosur Erode 23 TV Malai Erode 24 Singarapet Erode 25 Parsons' Valley Erode 26 Athur 230 (Deviakurchi) Erode 27 Gobichettypalayam Erode 28 Kadamparai PH Erode 29 Kundah PH 1 Erode 30 Kundah PH 4 Erode 31 Mettur Auto SS Erode 32 Mettur Dam PH Erode 33 Mettur Tunnel PH Erode 34 Moyar Erode 35 Sholayar PH 1 Erode 36 Thiruchengode Erode 37 Aliyar PH Erode 38 Arasur Erode 39 Ingur Erode 40 Kundah PH 2 Erode 41 Kundah PH 3 Erode 42 Lower Mettur PH3 Erode 43 Mettur TPS Erode 44 Pykara PH Erode 45 Salem 230 Erode 46 Salem 400 Erode 47 Thudiyalur Erode 48 Udumalpet 400 Erode 49 Udumalpet 230 Erode 50 Erode Erode 51 Echangodu Madurai 52 Karaikudi Madurai 53 Kodaiyar PH2 Madurai 54 Madurai North ( Alagarkoil) Madurai 55 Myladuthurai Madurai 56 Paramkudi Madurai 57 Perambulur Madurai 58 Pudukottai Madurai 59 S.R.Pudur Madurai 60 Samayapuram Madurai 61 Sathur (Anuppankulam) Madurai 62 Sembatty Madurai 63 Thanjore Madurai 64 Tuticorin Auto Madurai 65 Madurai 230 Madurai 66 Madurai 400 Madurai

27

Page 30: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

ANNEXURE - I

67 Periyar PH Madurai 68 Pugalur Madurai 69 Theni Madurai 70 Kayathar Madurai 71 Thiruvarur Madurai 72 Trichy 230 Madurai 73 Trichy 400 Madurai 74 Tuticorin TPS Madurai 75 SIPCOT Madurai

SL No. RTU Reporting CC1 STCMS IPP Chennai 2 GMR PCL IPP Chennai 3 TCPL IPP Chennai 4 Vyasarpadi 110 KV Chennai 5 Sembiyam 110 KV Chennai 6 SPCL IPP Erode 7 Kovilkalappal Madurai 8 Vazhuthur Madurai 9 PP Nallur IPP Madurai

10 MPCL IPP Madurai 11 Kuttalam Madurai 12 Aban Madurai 13 Arkay Madurai

B - TNEB own RTU's integrated under ULDC Scheme

28

Page 31: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

RSCC, BANGALORE CONTROL CENTREANNEXURE-II/1

FRONT END PROCESSORS

DUAL LAN

RAID

WS01 WS02 WS03 WS04 WS05

FEP-1 FEP-2

AP-01 AP-02 AP-04 AP-05 AP-06

SCADA AGC

DATA

SERVER

AP-03BACKUP

SERVER

PNA/ICCP

SERVER

COPS

SERVERBACKUP

SERVER

Switch

AP-07DTS

SERVER

AP-08DTS

SERVER

WS06 WS07

DTS SYSTEM

PNA:POWER NETWORK ANALYSIS

COPS: COMPREHENSIVE OPERATION PLANNING AND SCHEDULING

ICCP: INTER CONTROL CENTRE COMMUNICATION PROTOCOL

RAID:- REDUNDANT ARRAY OF INDEPENDENT DISKS

WORK

STATIONS

APPLICATION PROCESSOR

Page 32: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

ANNEXURE-II/2

SLDC, CONTROL CENTRE

FRONT END PROCESSOR

DUAL LAN

RAID

WS01 WS02 WS03 WS04

FEP-1 FEP-2

AP-01 AP-02 AP-03 AP-04 AP-05 AP-06

SCADA AGC

DATA

SERVER

BACKUP

SERVER

PNA/ICCP

SERVER

COPS

SERVERBACKUP

SERVER

WORK

STATIONS

APPLICATION SERVERS

Page 33: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

ANNEXURE-III

S

DEPLOYMENT OF POWER APPLICATION FUNCTIONS ACROSS VARIOUS CONTROL CENTRE

25

Page 34: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

ANNEXURE - IV

VIJAYAWADATALLAPALLI

GAJUWAKA

VIDYUTH SOUDHA

GOOTY

SALEM400

UDUMALPETTRICHUR NORTH

MADURAI

TRICHY

SRIPERUMBUDUR

NEYVELI

CHINAKAMPALLYDAVANAGERE

RAMAGUNDAM

PONDY

SOMANAHALLIP

N

PALLOMKAYANKULAM

RSCC (1)

CPCC (1)

SLDC (4)

SUB -LDC / SCC (14 )

FIBRE OPTIC LINK 110/132 kvFIBRE OPTIC LINK (220 kv)FIBRE OPTIC LINK (400 kv)FIBRE OPTIC LINK (SEB )

MICROWAVE LINK (35 LINKS)SATELLITE LINK (KEB)RTU LOCATIONS

SOUTHERN REGIONAL ULDC SCHEMETELECOM BACKBONE NETWORK

WARANGAL

PEDAPALLIDURSHED

JAMMIKUNTA

VTPS

VIZAG SWS

KAKINADA

BOMMUR

BHIMADOLEN’SAGAR PH

SRISAILAM PH

SRISAILAM LBPHKURNOOL

SOMAYAJULAPALLI

MUDDANOOR RTPP

ANANTHAPUR

SHAPURNAGAR

GHANAPUR

CH.GUTTAHYDERABAD 400

LEGEND LEGEND

CHALAKUDIKALAMASSERY

VIAKKAM

KUNDRA PARIPALLI

TRIVANDRUM NORTHVYDYUTHI BHAVANAM

KOZHIKODE

KANNUR-B

MADURAI400

CHENNAI

CHIDAMBARAM

MYLADUTURAI

SALEM230

ERODE

SIVAGANGA

KARAIKUDI

THIRUMAYAMPUDUKOTTAI

THIRUVARURORTHANADUKOVILVENNI

ADANIKOTTAI

INGUR

PONGALORE

PANRUTI

VILLIANUR

SP.KOVIL

BANGALORE

KUMBALGODI

:

LINGASUGUR

APTRANSCOGE RTUs:91OTHERS: 14

KPTCLGE RTUs:22OTHERS: 40RCI: 02

KSEBGE RTUs:30OTHERS: 1*

*(IN PROGRESS) TNEBGE RTUs:40OTHERS: 39

CENTRALGE RTUs:27RCI: 02

PONDYGE RTUs:5

OTHHERS: 10

HINDUPUR

64 Kbps BSNL DATA LINK

MAMIDAPALLI

26

Page 35: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009
Page 36: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

AGENCY HYDRO THERMAL GAS/DIESEL WIND/OTHERS NUCLEAR TOTAL

ANDHRA PRADESH 3586.36 2962.5 272 2 -- 6822.86 (18.6%)

KARNATAKA 3389.25 1470 127.8 4.55 -- 4991.6 (13.6%)

KERALA 1835.1 -- 234.6 2.025 -- 2071.725 (5.6%)

TAMILNADU 2137.35 2970 422.88 19.355 -- 5549.585 (15.1%)

PONDICHERRY -- -- 32.5 -- -- 32.5 (0.1%)

CENTRAL SECTOR -- 8090 359.58 -- 880 9329.58 (25.4%)

IPP 278.13 387.01 2997.46 4308.865 0 7971.465 (21.7%)

TOTAL 11226.19 (30.5%) 15879.51 (43.2%) 4446.82 (12.1%) 4336.795 (11.8%) 880 (2.4%) 36769.315 (100.0%)

Note:i). NTPC, 1000MW capacity at Simhadri, 359.58MW capacity at Kayamkulam and NLC's 600MW capacity at Neyveli Stage I which are fully dedicated to Andhra Pradesh, Kerala &Tamil Nadu respectively have also been included under the Central Sector.ii). The statewise bifurcation of IPP's is as follows:

5.1 SUMMARY OF EFFECTIVE INSTALLED CAPACITY IN MW IN SOUTHERN REGION AS ON 31.03.2006

5 GENERATING CAPACITY

AGENCY HYDRO THERMAL GAS/DIESEL WIND/OTHERS NUCLEAR TOTAL

ANDHRA PRADESH 91.4 73.51 1478.92 477.02 --- 2120.85

KARNATAKA 153.73 --- 435.9 598.47 --- 1188.1

KERALA 33 --- 178.93 --- --- 211.93

TAMILNADU --- 313.5 903.71 3233.375 --- 4450.585

TOTAL 278.13 387.01 2997.46 4308.865 0 7971.465

27

Page 37: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

ANDHRA PRADESH

SL.NO. STATION INSTALLED CAPACITY (MW) EFFECTIVE CAPACITY (MW)

HYDRO

1 MACHKUND 3x(23+17)x70% 84

2 T.B.DAM (8x9)x80% 57.6

3 UPPER SILERU 4x60 240

4 DONKARAYI 1x25 25

5 LOWER SILERU 4x115 460

6 SRISAILAM RBPH 7x110 770

7 SRISAILAM LBPH 6x150 900

8 N'SAGAR 1x110+7x100.8 815.6

9 NSR RT.CANAL.P.H 3x30 90

10 NSR LT.CANAL.P.H 2x30 60

11 NIZAMSAGAR 2x5 10

12 MINI HYDEL 12.16 12.16

13 POCHAMPAD 3x9 27

14 PENNA AHOBILAM 2x10 20

15 SINGUR 2x7.5 15

TOTAL 3586.36

THERMAL (COAL)

1 RAMAGUNDAM-B 1x62.5 62.5

2 KOTHAGUDEM-A 4x60 240

3 KOTHAGUDEM-B 2x120 240

4 KOTHAGUDEM-C 2x120 240

5 KOTHAGUDEM-D 2x250 500

6 VIJAYAWADA 6x210 1260

7 RAYALASEEMA 2x210 420

TOTAL 2962.5GAS/NAPTHA/DIESEL

1 VIJJESWARAM (GAS) 2x33+1x34 100

2 VIJJESWARAM (GAS) 1x112.5+1x59.5 172TOTAL 272

WIND MILL

1 WIND 2 2TOTAL 2

IPPHYDRO

1 MINI HYDRO 91.4 91.4COAL

2 MINI POWER PLANTS 73.51 73.51GAS/NAPTHA/DIESEL

3 LANCO (GAS) 2x115+1x125 355

4 JEGURUPADU (GAS) 2x45.8+1x48.9+1x75.5 216

5 SPECTRUM (GAS) 1x46.8+2x46.1+1x68.88 207.88

6 ISOLATED GAS WELL (GAS) 27.04 27.04

7 GVK EXTENSION(GAS) 1x140+1x80 220

8 RELIANCE ENERGY LTD. (GAS) 1x140+1x80 220

9 VEMAGIRI POWER GENERATION LTD. (GAS) 1x233 233WIND

10 WINDMILL 102.49 102.49OTHERS

11 CO-GENERATION (RCL) 41 41

12 BAGASSE 114.5 114.5

13 BIOMASS 197.93 197.93

14 WASTED BASED PP 21.1 21.1TOTAL 2120.85

TOTAL ANDHRA PRADESH 8943.71

Note: Simhadri (NTPC) of 1000 MW capacity Coal based plant, fully dedicated to Andhra Pradesh has been included under Central Sector.

5.2 DETAILS OF EFFECTIVE INSTALLED CAPACITY IN SOUTHERN REGION AS ON 31.03.2006

28

Page 38: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

KARNATAKA

SL.NO. STATION INSTALLED CAPACITY (MW) EFFECTIVE CAPACITY (MW)

HYDRO

1 SHARAVATHI 10x103.5 1035

2 LINGANAMAKKI.P.H. 2x27.5 55

3 JOG 4x18+4x12 120

4 NAGJHERI 3x135+3x150 855

5 SUPA 2x50 100

6 VARAHI 2x115 230

7 BHADRA POWER HOUSE 1x7+2x12.1+1x2+6 39.2

8 SIVANSAMUDRAM 6x3+4x6 42

9 SHIMSHA 2x8.6 17.2

10 MUNIRABAD 3x9 27

11 T.B.DAM SHARE (20 %) 8x9(20%) 14.4

12 GHATAPRABHA 2x16 32

13 MANI DAM.P.H. 2x4.5 9

14 MINI HYDRO 1.4+0.35+2.7 4.45

15 MALLAPUR 2x4.5 9

16 KODASALLI 3x40 120

17 SHARAVATHI TAIL RACE 4x60 240

18 KADRA 3x50 150

19 ALMATTI 1x15+5x55 290TOTAL 3389.25

THERMAL (COAL)

1 RAICHUR.T.PS. 7x210 1470TOTAL 1470

GAS/NAPTHA/DIESEL

1 YELEHANKA (DEISEL) 6x21.3 127.8TOTAL 127.8

WIND

1 KAPPATAGUDDA 4.55 4.55TOTAL 4.55

IPPHYDRO

1 MINI HYDEL 153.73 153.73GAS/NAPTHA/DIESEL

2 TANIR BHAVI (NAPTHA) 220 220

3 JINDAL (COREX GAS) 100 100

4 TATA ELECTRIC (DIESEL) 5x15.82 79.1

5 RAYAL SEEMA ALKALIES (DIESEL) 2x13.9 27.8

6 ITPL (DIESEL) 9 9WIND

7 WIND MILL 295.54 295.54OTHERS

8 CO-GENERATION 241.55 241.55

9 BIO-MASS 61.38 61.38TOTAL 1188.1

TOTAL KARNATAKA 6179.7

KERALA

SL.NO. STATION INSTALLED CAPACITY (MW) EFFECTIVE CAPACITY (MW)

HYDRO

1 KUTTIADI + KUTTIADI EXTENTION 3x25 + 1x50 125

2 SHOLAYAR 3x18 54

3 PORINGALKUTHU 4x8 32

4 PALLIVASAL 3x7.5+3x5 37.5

5 SENGULAM 4x12 48

6 PANNIAR 2x15 30

7 NERIAMANGALAM 1x18+1x15+1x17.5 50.5

8 SABARIGIRI 5x50+1x60 310

9 IDUKKI 3x130+3x130 780

10 IDAMALAYAR 2x37.5 75

29

Page 39: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06KERALA

HYDRO11 KALLADA 2x7.5 15

12 MADUPETTY 2 2

13 PEPPARA 3 3

14 L.PERIYAR 3x60 180

15 MALAMPUZHA 1x2.5 2.5

16 POR.L.BANK 16 16

17 KAKKAD 2x25 50

18 CHEMBUKADAVU 1x2.7+1x3.75 6.45

19 URUMI 1 x 3.75 + 1 x 2.4 6.15

20 MALANKARA 3 x 3.5 10.5

21 LOWER MEENMUTTY 1x 1.5 1.5TOTAL 1835.1

GAS/NAPTHA/DIESEL

1 BRAHMAPURAM DGPP (DIESEL) 5x21.32 106.6

2 KOZHIKODE DPP (DIESEL) 8x16 128TOTAL 234.6

WIND

1 WIND MILL 2.025 2.025TOTAL 2.025

IPPHYDRO

1 MANIYAR 3x4 12

2 KUTHUNGAL 3x7 21GAS/NAPTHA/DIESEL

3 BSES (NAPTHA) 3x40.5(GT)+1x35.5(ST) 157

4 KASARGODE (DIESEL) 3x7.31 21.93TOTAL 211.93

TOTAL KERALA 2283.655Note: RGCCPP, Kayamkulam (NTPC) of 359.58 MW capacity Naptha based plant, fully dedicated to Kerala has been included under Central Sector.

TAMILNADU

SL.NO. STATION INSTALLED CAPACITY (MW) EFFECTIVE CAPACITY (MW)

HYDRO

1 PYKARA 3x6.65+1x11+2x14 59

2 PYKARA MICRO 1x2 2

3 PYKARA ULTIMATE 3x50 150

4 MOYAR 3x12 36

5 MARAVAKANDI 1x0.7 0.7

6 KUNDAH-I 3x20 60

7 KUNDAH-II 5x35 175

8 KUNDAH-III 3x60 180

9 KUNDAH-IV 2x50 100

10 KUNDAH-V 2x20 40

11 KUNDAH-VI 1x30 30

12 SURULIYAR 1x35 35

13 KADAMPARAI 4x100 400

14 ALIYAR 1x60 60

15 POONACHI 1x2 2

16 METTUR DAM 4x10 40

17 METTUR TUNNEL 4x50 200

18 LOWER METTUR 8x15 120

19 BHAVANISAGAR 4x2 8

20 PERIYAR 4x35 140

21 VAIGAI 2x3 6

22 PAPANASAM 4x7 28

23 SERVALAR 1x20 20

24 SARKARAPATHY 1x30 30

25 SHOLAYAR 2x35+25 95

26 LOWER BHAVANI 8 8

27 KODAYAR 1x60+1x40 100

28 SATHANUR DAM PH 1x7.5 7.5

29 MICRO TOTAL 5.15 5.15TOTAL 2137.35

SL.NO. STATION INSTALLED CAPACITY (MW) EFFECTIVE CAPACITY (MW)

30

Page 40: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06TAMILNADU

SL.NO. STATION INSTALLED CAPACITY (MW) EFFECTIVE CAPACITY (MW)

THERMAL (COAL)

1 ENNORE.T.P.S 2x60+3x110 4502 TUTUCORIN.T.P.S 5x210 10503 METTUR.T.P.S 4x210 8404 NORTH MADRAS.T.P.S 3x210 630

TOTAL 2970GAS/NAPTHA/DIESEL

1 BASIN BRIDGE (NAPTHA) 4x30 1202 KOVIL KALAPPAL (GAS) 1x70+1x37.88 107.883 VALATHUR (GAS) 1x60+1x34 944 KUTTALAM (GAS) 1x64+1x37 101

TOTAL 422.88WIND

1 TNEB WIND MILL 19.355 19.355

TOTAL 19.355IPPCOAL

1 TCPL 63.5 63.5LIGNITE

2 ST - CMS 250 250GAS/NAPTHA/DIESEL

3 P P NALLUR (NAPTHA) 330.5 330.54 ABAN POWER (GAS) 74.41+38.81 113.215 HI-TECH (GAS) 15 156 MADURAI POWER CL (DIESEL) 106 1067 SAMALPATTY (DIESEL) 7x15 1058 ARKEY ENERGY(GAS) 1x38 389 GMR POWER (DIESEL) 4x49 196

WIND

10 WIND MILL 2878.425OTHERS

11 CO-GENERATION 314.612 BIO-MASS 40.35

TOTAL 4450.585

TOTAL TAMIL NADU 10000.17Note: Neyveli-I (NLC) of 600 MW capacity Lignite based plant, fully dedicated to Tamil Nadu has been included under Central Sector.

PONDICHERRY

SL.NO. STATION INSTALLED CAPACITY (MW) EFFECTIVE CAPACITY (MW)

GAS/NAPTHA/DIESEL

1 KARIAKAL POWER PLANT (GAS) 1x32.5 32.5

TOTAL 32.5

TOTAL PONDICHERRY 32.5

CENTRAL SECTOR

SL.NO. STATION INSTALLED CAPACITY (MW) EFFECTIVE CAPACITY (MW)

THERMAL

COAL1 RAMAGUNDAM T.P.S (ISGS) - NTPC 3x200+4x500 26002 TALCHER STAGE II (ISGS) - NTPC 4x500 20003 SIMHADRI (AP) - NTPC 2x500 1000

LIGNITE4 NEYVELI-I (TN) - NLC 6x50+3x100 6005 NEYVELI-II (ISGS) - NLC 7x210 14706 NEYVELI TPS-I (Expansion) (ISGS) - NLC 2x210 420

TOTAL 8090GAS/NAPTHA/DIESEL

7 RGCCPP,KAYAMKULAM (KSEB) - NTPC 2x116.6(GT)+1x126.38(ST) 359.58TOTAL 359.58

NUCLEAR1 M.A.P.S KALPAKAM (ISGS) - NPC 2x220 4402 KAIGA A.P.S (ISGS) - NPC 2x220 440

TOTAL 880TOTAL CENTRAL SECTOR 9329.58

GRAND TOTAL 36769.315

31

Page 41: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

YEAR HYDRO THERMAL GAS/NAPTHA/ DIESEL NUCLEAR WIND TOTAL

1996-97 8666.50 10670.44 703.30 340.00 76.40 20456.64

1997-98 8907.75 10941.45 1033.92 340.00 78.11 21301.23

1998-99 9141.00 11186.25 1485.92 340.00 84.11 22237.28

1999-00 9665.70 11450.56 1897.40 560.00 110.36 23684.02

2000-01 9424.30 12064.76 2545.58 780.00 114.10 24928.74

2001-02 9932.41 13290.25 2480.41 780.00 127.21 26610.27

2002-03 10469.86 14825.39 2963.42 780.00 149.36 29188.03

2003-04 10721.58 15515.84 3463.69 830.00 263.12 30794.23

2004-05 10938.99 15909.51 3955.82 830.00 1099.42 32733.74

2005-06 11222.19 15879.51 4446.82 880.00 4009.12 36769.32

INCLUDES WIND AND OTHER NCERP

5.3 GROWTH OF INSTALLED CAPACITY OF SOUTHERN REGION DURING PAST DECADE

32

Page 42: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009
Page 43: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

A.. AVERAGE ENERGY PER DAY

DEMAND MET REQUIREMENT SHORTAGE

MU/Day MU/Day %

ANDHRA PRADESH 144.4 146.2 1.1

KARNATAKA 93.5 94.2 0.6

KERALA 36.7 37.0 0.7

TAMIL NADU 138.6 139.5 0.6

PONDICHERRY 4.1 4.2 0.7

SOUTHERN REGION 417.4 421.1 0.8

B.. PEAK DEMAND MW

MAX DEMAND MET MAX REQUIREMENT SHORTAGE

MW MW %

ANDHRA PRADESH 8239 8361 1.5

KARNATAKA 5558 5659 1.8

KERALA 2578 2617 1.5

TAMIL NADU 8209 8400 2.3

PONDICHERRY 251 256 2.0

SOUTHERN REGION 23372 23737 1.5

Note: The Values of Shortages and Requirement indicated above and in subsequent sheets are tentative and approximate based on the intial information collected from the respective control rooms on the day of operation.

STATE / UT

STATE / UT

6.1 SUMMARY OF POWER SUPPLY POSITION IN SOUTHERN REGION

6 POWER SUPPLY POSITION

DURING 2005-06

33

Page 44: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

STATE-->

Month Demand met (MU/Day)

Requirement (MU/Day) Shortage (%) Demand met

(MU/Day)Requirement

(MU/Day) Shortage (%) Demand met (MU/Day)

Requirement (MU/Day) Shortage (%)

Apr-05 150.9 152.1 0.8 95.3 96.1 0.7 36.4 36.7 0.9May-05 141.7 148.1 4.3 93.7 95.5 1.8 38.5 39.3 2.1Jun-05 139.2 145.3 4.2 81.1 82.5 1.8 34.6 35.3 2.0Jul-05 132.8 133.8 0.7 75.5 76.0 0.7 33.1 33.3 0.8Aug-05 149.3 148.7 -0.4 81.4 81.0 -0.4 35.5 35.4 -0.5Sep-05 142.4 140.9 -1.1 83.1 82.2 -1.1 35.7 35.3 -1.2Oct-05 138.5 137.1 -1.0 81.7 80.9 -1.0 37.1 36.7 -1.0Nov-05 125.3 124.6 -0.6 86.2 85.8 -0.5 36.4 36.2 -0.6Dec-05 138.0 138.4 0.3 100.0 100.3 0.2 36.8 36.9 0.3Jan-06 151.1 152.2 0.7 110.5 111.1 0.6 37.5 37.7 0.8Feb-06 161.9 167.7 3.4 118.6 120.7 1.7 38.8 39.6 2.2Mar-06 161.6 165.3 2.2 115.3 118.7 2.8 40.5 41.5 2.32005-06 144.4 146.2 1.1 93.5 94.2 0.6 36.7 37.0 0.7

STATE-->

Month Demand met (MU/Day)

Requirement (MU/Day) Shortage (%) Demand met

(MU/Day)Requirement

(MU/Day) Shortage (%) Demand met (MU/Day)

Requirement (MU/Day) Shortage (%)

Apr-05 141.4 142.4 0.8 4.1 4.1 1.2 428.1 431.5 0.8May-05 143.2 145.8 1.8 4.2 4.4 3.0 421.4 433.0 2.7Jun-05 145.5 147.7 1.5 4.6 4.7 2.1 404.9 415.5 2.5Jul-05 140.8 141.6 0.6 4.4 4.5 0.7 386.6 389.2 0.7Aug-05 139.5 138.9 -0.4 4.2 4.2 -0.8 409.9 408.2 -0.4Sep-05 132.8 131.4 -1.0 4.3 4.2 -1.6 398.3 394.0 -1.1Oct-05 131.3 130.1 -0.9 4.1 4.1 -1.6 392.7 388.9 -1.0Nov-05 120.3 119.7 -0.5 3.5 3.5 -1.0 371.7 369.8 -0.5Dec-05 124.1 124.4 0.3 3.6 3.6 0.0 402.6 403.6 0.3Jan-06 133.2 134.1 0.7 3.9 3.9 0.8 436.1 439.0 0.7Feb-06 151.9 154.7 1.8 4.3 4.4 2.4 475.5 487.1 2.4Mar-06 159.4 163.5 2.5 4.5 4.6 2.8 481.3 493.5 2.52005-06 138.6 139.5 0.6 4.1 4.2 0.7 417.4 421.1 0.8

TAMILNADU PONDICHERRY SOUTHERN REGION

6.2 (A) MONTHWISE POWER SUPPLY POSITION(Average Energy in MU/Day) IN SOUTHERN REGION DURING 2005-06

ANDHRA PRADESH KARNATAKA KERALA

34

Page 45: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

STATE-->

Month Demand met (MW)

Requirement (MW)

Shortage (%)

Demand met (MW)

Requirement (MW)

Shortage (%)

Demand met (MW)

Requirement (MW)

Shortage (%)

Apr-05 7130 7122 -0.1 5442 5570 2.3 2355 2370 0.6May-05 6680 6849 2.5 5073 5252 3.4 2439 2496 2.3Jun-05 6264 6373 1.7 4561 4704 3.0 2336 2393 2.4Jul-05 6276 6245 -0.5 4499 4526 0.6 2218 2236 0.8Aug-05 7275 7244 0.0 4442 4477 0.8 2360 2368 0.3Sep-05 7067 6942 -1.8 4735 4773 0.8 2346 2331 -0.6Oct-05 7359 7323 -0.5 4562 4538 -0.5 2394 2388 -0.3Nov-05 6336 6388 0.8 4732 4779 1.0 2370 2360 -0.4Dec-05 7065 7114 0.7 5037 5073 0.7 2519 2555 1.4Jan-06 7868 7969 1.3 5393 5428 0.6 2468 2504 1.4Feb-06 8210 8363 1.8 5478 5559 1.5 2490 2499 0.4Mar-06 8239 8361 1.5 5558 5659 1.8 2578 2617 1.52005-06 8239 8361 1.5 5558 5659 1.8 2578 2617 1.5

STATE-->

Month Demand met (MW)

Requirement (MW)

Shortage (%)

Demand met (MW)

Requirement (MW)

Shortage (%)

Demand met (MW)

Requirement (MW)

Shortage (%)

Apr-05 7511 7558 0.6 218 224 2.7 21756 22364 2.7May-05 7522 7826 3.9 235 244 3.7 21646 22111 2.1Jun-05 7708 7773 0.8 249 257 3.1 20758 21058 1.4Jul-05 7583 7628 0.6 245 249 1.6 20847 20947 0.5Aug-05 7719 7744 0.3 213 214 0.5 21134 21298 0.8Sep-05 7592 7581 -0.1 223 223 0.0 21112 20890 -1.1Oct-05 7557 7510 0.0 239 237 -0.8 21268 21154 -0.5Nov-05 7249 7281 0.4 244 246 0.8 20736 20836 0.5Dec-05 7064 7118 0.8 215 216 0.5 21174 21467 1.4Jan-06 7356 7388 0.4 229 234 2.1 21915 21915 0.0Feb-06 7902 8132 2.8 241 246 2.0 23164 23765 2.5Mar-06 8209 8400 2.3 251 256 2.0 23372 23737 1.52005-06 8209 8400 2.3 251 256 2.0 23372 23737 1.5

TAMILNADU PONDICHERRY SOUTHERN REGION

6.2 (B) MONTHWISE POWER SUPPLY POSITION(Peak MW) IN SOUTHERN REGION DURING 2005-06

ANDHRA PRADESH KARNATAKA KERALA

35

Page 46: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

MAX. DATE MIN. DATE MAX. DATE MIN. DATE MAX. DATE MIN. DATE

Apr-05 159.65 02-04-05 142.55 30-04-05 113.78 02-04-05 82.63 27-04-05 39.98 29-04-05 33.39 03-04-05

May-05 148.69 20-05-05 129.89 03-05-05 109.22 19-05-05 72.32 29-05-05 41.11 20-05-05 32.47 27-05-05

Jun-05 145.91 23-06-05 128.03 28-06-05 88.34 16-06-05 75.38 05-06-05 37.68 08-06-05 29.09 19-06-05

Jul-05 141.90 07-07-05 113.44 24-07-05 93.83 13-07-05 59.83 26-07-05 35.37 14-07-05 29.33 31-07-05

Aug-05 159.00 27-08-05 135.73 01-08-05 93.61 23-08-05 65.43 01-08-05 38.19 26-08-05 31.20 01-08-05

Sep-05 159.94 01-09-05 111.02 20-09-05 102.45 27-09-05 64.25 04-09-05 38.12 23-09-05 32.12 15-09-05

Oct-05 165.75 07-10-05 104.93 30-10-05 94.68 07-10-05 70.73 14-10-05 39.03 18-10-05 33.86 23-10-05

Nov-05 136.96 19-11-05 110.01 02-11-05 99.07 19-11-05 74.70 02-11-05 38.05 10-11-05 33.59 06-11-05

Dec-05 146.44 31-12-05 126.07 04-12-05 107.71 22-12-05 83.59 04-12-05 38.88 21-12-05 33.53 04-12-05

Jan-06 159.50 23-01-06 140.09 15-01-06 115.67 23-01-06 98.24 01-01-06 39.74 18-01-06 33.47 01-01-06

Feb-06 170.18 25-02-06 152.04 05-02-06 123.74 28-02-06 109.91 05-02-06 40.83 28-02-06 35.40 12-02-06

Mar-06 173.83 28-03-06 134.05 11-03-06 125.76 30-03-06 92.77 10-03-06 43.81 29-03-06 36.54 05-03-06

2005-06 173.83 28-03-06 104.93 30-10-05 125.76 30-03-06 59.83 26-07-05 43.81 29-03-06 29.09 19-06-05

MAX. DATE MIN. DATE MAX. DATE MIN. DATE MAX. DATE MIN. DATE

Apr-05 157.34 02-04-05 114.62 10-04-05 4.57 27-04-05 3.59 04-04-05 474.97 02-04-05 399.94 10-04-05

May-05 159.60 20-05-05 125.85 29-05-05 4.57 13-05-05 3.62 02-05-05 461.71 20-05-05 371.68 29-05-05

Jun-05 156.43 29-06-05 136.68 12-06-05 5.02 18-06-05 4.17 12-06-05 416.93 07-06-05 388.58 26-06-05

Jul-05 155.04 13-07-05 118.41 17-07-05 4.79 20-07-05 3.81 07-07-05 426.54 13-07-05 331.26 24-07-06

Aug-05 157.96 22-08-05 120.82 15-08-05 4.66 03-08-05 3.45 15-08-05 445.75 22-08-05 373.12 01-08-05

Sep-05 150.16 22-09-05 112.67 04-09-05 4.80 20-09-05 3.83 04-09-05 441.74 28-09-05 349.45 11-09-05

Oct-05 157.26 06-10-05 100.83 27-10-05 4.58 08-10-05 3.70 11-10-05 460.37 07-10-05 332.58 30-10-05

Nov-05 140.11 18-11-05 98.05 01-11-05 3.95 17-11-05 2.88 01-11-05 416.07 19-11-05 322.51 01-11-05

Dec-05 137.38 30-12-05 103.29 11-12-05 3.98 31-12-05 3.22 04-12-05 430.00 22-12-05 351.87 04-12-05

Jan-06 145.72 23-01-06 107.12 15-01-06 4.20 24-01-06 3.30 15-01-06 462.86 23-01-06 388.98 15-01-06

Feb-06 161.43 23-02-06 134.69 05-02-06 4.72 28-02-06 3.23 14-02-06 502.10 28-02-06 436.63 05-02-06

Mar-06 172.41 24-03-06 133.99 12-03-06 4.82 24-03-06 3.31 27-03-06 517.52 24-03-06 409.18 12-03-06

2005-06 172.41 24-03-06 98.05 01-11-05 5.02 18-06-05 2.88 01-11-05 517.52 24-03-06 322.51 01-11-05

6.3 MONTHWISE MAXIMUM AND MINIMUM ENERGY CONSUMPTION WITH CORRESPONDING DATES (MU/Day)

PONDICHERRY SOUTHERN REGION

ANDHRA PRADESH KARNATAKA KERALA

TAMIL NADU

36

Page 47: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

MAX. DATE MIN. DATE MAX. DATE MIN. DATE MAX. DATE MIN. DATE

Apr-05 7130 09-04-05 4758 21-04-05 5442 02-04-05 2556 14-04-05 2355 29-04-05 1012 04-04-05

May-05 6680 25-05-05 4338 01-05-05 5073 19-05-05 2241 29-05-05 2439 20-05-05 687 27-05-05

Jun-05 6264 03-06-05 3791 26-06-05 4561 16-06-05 2237 01-06-05 2336 07-06-05 948 20-06-05

Jul-05 6276 30-07-05 3776 26-07-05 4499 08-07-05 1611 26-06-05 2218 09-07-05 919 30-06-05

Aug-05 7275 27-08-05 4254 15-08-05 4422 22-08-05 1902 02-08-05 2360 23-08-05 917 01-08-05

Sep-05 7067 18-09-05 3371 21-09-05 4735 27-09-05 1617 05-09-05 2346 19-09-05 1017 05-09-05

Oct-05 7359 07-10-05 3651 29-10-05 4562 07-10-05 1849 15-10-05 2394 03-10-05 1131 23-10-05

Nov-05 6336 19-11-05 3672 17-11-05 4732 18-11-05 2077 02-11-05 2370 10-11-05 1059 25-11-05

Dec-05 7065 30-12-05 3574 08-12-05 5037 27-12-05 2240 31-12-05 2519 21-12-05 1094 30-12-05

Jan-06 7868 24-01-06 2595 02-01-06 5393 27-01-06 1952 16-01-06 2468 23-01-06 1105 02-01-06

Feb-06 8210 17-02-06 4507 01-02-06 5478 17-02-06 3448 06-02-06 2490 01-02-06 1184 23-02-06

Mar-06 8239 25-03-06 4464 12-03-06 5558 23-03-06 2726 10-03-06 2578 20-03-06 1172 10-03-06

2005-06 8239 25-03-06 2595 5558 1611 2578 687

MAX. DATE MIN. DATE MAX. DATE MIN. DATE MAX. DATE MIN. DATE

Apr-05 7511 26-04-05 3791 07-04-05 218 19-04-05 122 04-04-05 21756 02-04-05 14575 21-04-05

May-05 7522 20-05-05 4230 30-05-05 235 27-05-05 86 02-05-05 21646 25-05-05 13207 30-05-05

Jun-05 7708 30-06-05 4230 01-06-05 249 21-06-05 159 02-06-05 20758 03-06-05 13175 01-06-05

Jul-05 7583 08-07-05 4390 18-07-05 245 23-07-05 47 06-07-05 20847 07-07-05 12048 25-07-05

Aug-05 7719 05-08-05 4601 29-08-05 213 24-08-05 122 25-08-05 21134 22-08-05 13418 16-08-05

Sep-05 7592 22-09-05 4408 11-09-05 223 22-09-05 127 28-09-05 21112 30-09-05 12617 08-09-05

Oct-05 7557 06-10-05 3329 28-10-05 239 09-10-05 130 09-10-05 21268 07-10-05 11262 28-10-05

Nov-05 7249 19-11-05 3054 02-11-05 244 25-11-05 61 02-11-05 20736 19-11-05 10710 02-11-05

Dec-05 7064 30-12-05 3451 05-12-05 215 27-12-05 111 04-12-05 21174 22-12-05 11901 05-12-05

Jan-06 7356 31-01-06 3344 16-01-06 229 24-01-06 123 31-01-06 21915 27-01-06 12595 02-01-06

Feb-06 7902 28-02-06 4683 03-02-06 241 17-02-06 68 14-02-06 23164 28-02-06 15613 12-02-06

Mar-06 8209 28-03-06 4736 12-03-06 251 24-03-06 113 12-03-06 23372 29-03-06 15388 04-03-06

2005-06 8209 3054 251 47 23372 10710

6.4 MONTHWISE MAXIMUM AND MINIMUM DEMAND MET WITH CORRESPONDING DATES (MW)

PONDICHERRY SOUTHERN REGION

ANDHRA PRADESH KARNATAKA KERALA

TAMIL NADU

37

Page 48: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

YEAR ANDHRA PRADESH KARNATAKA KERALA TAMIL NADU SOUTHERN REGION1996-97 92.21 51.43 18.62 97.87 260.13

1997-98 104.58 59.60 25.82 101.68 291.68

1998-99 111.25 62.71 30.04 104.55 308.56

1999-00 125.00 72.00 32.00 114.00 343.00

2000-01 128.00 76.00 34.00 123.00 361.00

2001-02 129.00 80.00 35.00 130.00 374.00

2002-03 131.00 81.00 34.00 139.00 385.00

2003-04 130.00 85.00 36.00 147.00 398.00

2004-05 144.00 92.00 34.00 137.00 407.00

2005-06 144.40 93.54 36.73 138.60 417.43

YEAR ANDHRA PRADESH KARNATAKA KERALA TAMIL NADU SOUTHERN REGION1996-97 5022 3126 1572 4875 14296

1997-98 5742 3527 1786 4918 15682

1998-99 6480 3820 1896 5196 17180

1999-00 6684 4066 2177 5580 18535

2000-01 7143 4464 2316 6290 19428

2001-02 7029 4644 2333 6686 20063

2002-03 6895 4805 2347 6957 20428

2003-04 7441 5445 2426 7401 21928

2004-05 7613 5612 2420 7473 223642005-06 8239 5558 2578 8209 23372

6.5 AVERAGE ENERGY CONSUMPTION OF SOUTHERN REGION DURING PAST DECADE ( MU/DAY)

PEAK DEMAND MET OF SOUTHERN REGION DURING PAST DECADE (MW)

38

Page 49: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

ENTITLEMENT SCHEDULE ACTUAL DRAWAL ENTITLEMENT SCHEDULE ACTUAL

DRAWAL ENTITLEMENT SCHEDULE ACTUAL DRAWAL

Apr-05 971.23 905.28 707.99 932.92 910.82 1024.73 663.82 594.13 611.79May-05 960.24 843.00 898.76 915.97 893.56 1033.15 658.98 572.41 508.36Jun-05 875.79 817.63 797.14 837.83 821.12 926.17 598.31 440.49 429.99Jul-05 948.72 884.31 806.27 890.90 825.59 902.85 643.05 606.83 496.04Aug-05 899.10 476.34 338.86 866.78 779.47 831.87 624.18 523.68 489.55Sep-05 898.38 364.14 305.49 882.28 699.79 823.69 639.21 358.35 205.80Oct-05 953.14 417.51 388.53 942.24 679.40 791.48 687.43 383.68 283.42Nov-05 886.77 685.80 681.78 828.62 457.02 539.21 680.41 511.45 438.91Dec-05 909.19 609.09 643.52 833.93 627.21 692.88 647.39 551.06 530.81Jan-06 1008.44 754.75 751.94 941.65 819.00 887.35 735.26 587.85 565.70Feb-06 943.88 881.63 914.78 867.31 749.63 819.97 680.58 537.75 456.22Mar-06 1000.68 1022.72 1156.90 898.66 756.56 820.65 707.98 477.32 368.91TOTAL 11255.57 8662.19 8391.97 10639.08 9019.17 10093.99 7966.62 6144.99 5385.48

ENTITLEMENT SCHEDULE ACTUAL DRAWAL ENTITLEMENT SCHEDULE ACTUAL

DRAWAL ENTITLEMENT SCHEDULE ACTUAL DRAWAL

Apr-05 1458.67 1430.76 1482.46 167.03 160.64 131.01 49.09 44.78 38.78May-05 1444.37 1450.56 1437.65 165.36 159.03 139.96 51.47 44.89 36.88Jun-05 1308.33 1302.08 1422.87 149.94 144.73 144.90 49.21 45.69 30.89Jul-05 1372.20 1313.16 1489.35 158.54 152.57 145.49 44.45 41.11 32.14Aug-05 1379.28 1282.96 1401.30 151.33 145.02 139.57 41.64 37.60 33.83Sep-05 1401.30 1217.62 1257.74 159.46 144.75 137.96 41.44 38.28 34.91Oct-05 1475.43 1247.70 1305.86 168.49 142.37 137.01 39.38 36.40 38.51Nov-05 1319.19 1021.68 1069.54 158.86 140.78 114.45 39.01 35.85 34.85Dec-05 1335.54 1036.02 1053.78 141.49 135.16 123.00 47.74 43.96 42.40Jan-06 1510.72 1284.46 1330.03 168.81 162.53 129.47 49.80 45.77 41.57Feb-06 1416.10 1305.96 1349.83 154.09 148.04 128.89 57.69 53.29 49.49Mar-06 1489.51 1494.86 1554.83 153.40 146.63 147.81 70.18 63.90 46.45TOTAL 16910.64 15387.80 16155.23 1896.79 1782.23 1619.52 581.12 531.52 460.69

MONTHS

MONTHS

6.6 MONTHWISE ENTITLEMENT, SCHEDULE Vs ACTUAL DRAWAL BY STATES FROM THE GRID (MU)

ANDHARA PRADESH KARNATAKA KERALA

TAMIL NADU PONDICHERRY GOA

39

Page 50: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

IMPORT(MU) EXPORT(MU) IMPORT(MU) EXPORT(MU) IMPORT(MU) EXPORT(MU)

APRIL 4.40 123.54 146.46 - 877.68 -

MAY 20.51 97.77 229.89 - 698.08 -

JUNE 119.49 68.93 139.19 - 692.78 -

JULY 27.85 80.57 165.32 - 1254.32 -

AUGUST 1.76 224.53 153.20 - 859.03 -

SEPTEMBER - 362.38 155.80 - 731.64 -

OCTOBER 0.09 399.88 174.88 - 891.92 -

NOVEMBER - 367.08 103.24 1.08 1000.55 -

DECEMBER 1.02 441.55 114.56 - 885.17 -

JANUARY - 380.31 159.43 - 1095.83 -

FEBRUARY - 244.12 264.13 - 1046.12 -

MARCH 44.86 147.91 290.28 1.42 1129.61 -

2005-06 219.98 2938.57 2096.38 2.50 11162.73 0.00

BTB - Back to Back

6.7 INTER-REGIONAL EXCHANGES (PHYSICAL) OF SR WITH WR AND ER DURING 2005-06BHADRAWATI BTB GAZUWAKA BTB TALCHER-KOLAR BI-POLE

40

Page 51: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

IMPORT (MU) EXPORT (MU)2001-02 788 54

2002-03 173 456

2003-04 298 543

2004-05 147 1761

2005-06 220 2939

IMPORT (MU) EXPORT (MU)2001-02 3666 0 43802002-03 3016 3 43802003-04 1926 0 43922004-05 2500 1

2005-06 2096 3 4752

IMPORT (MU) EXPORT (MU)2001-02 - -

2002-03 1458 0 36482003-04 6039 0 175682004-05 9330 0

2005-06 11163 0 17520

6.8 INTER-REGIONAL EXCHANGE (PHYSICAL) OF SR WITH WR AND ER DURING LAST 5 YEARS

YEAR TALCHER - KOLAR BI-POLE

YEAR BHADRAWATI BACK TO BACK

YEAR GAZUWAKA BACK TO BACK

41

Page 52: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

2001-02 2002-03GENERATOR

MODEGENERATOR

MODEGENERATOR

MODEPUMP MODE

GENERATOR MODE

PUMP MODE

GENERATOR MODE

PUMP MODE

APRIL 0.1 3.9 35.0 40.0 26.0 35.0 0.0 2.6

MAY 0.0 1.4 37.0 43.0 41.0 48.0 29.6 45.7

JUNE 1.0 6.4 29.0 45.0 55.0 35.0 45.3 51.2

JULY 27.5 6.9 47.0 49.0 50.0 49.0 79.0 62.3

AUGUST 21.4 8.8 54.0 55.0 55.0 41.0 49.5 25.0

SEPTEMBER 11.0 8.6 36.0 48.0 30.0 25.0 40.8 15.2

OCTOBER 19.5 18.5 26.0 15.0 0.0 0.0 46.9 45.1

NOVEMBER 17.9 16.7 23.0 24.0 0.0 0.0 64.1 59.2

DECEMBER 20.3 20.5 49.0 53.0 0.0 0.0 70.0 62.5

JANUARY 18.4 39.0 44.0 58.0 0.0 0.0 72.0 92.9

FEBRUARY 14.0 39.0 21.0 21.0 0.0 0.0 53.3 55.6

MARCH 5.7 32.0 6.0 18.0 0.0 0.0 30.9 37.9

TOTAL 156.7 201.8 407.0 469.0 257.0 233.0 581.4 555.3

Note: The plant was under shutdown from 16th Sep 2004 to 28th April 05 for dam maintenance works.

6.9 SRISAILAM LB ENERGY GENERATED/PUMPED DURING THE YEAR (MU)

GENERATOR MODE PUMP MODE

APRIL 21.2 -

MAY 56.0 -

JUNE 5.3 -

JULY 11.7 -

AUGUST 571.5 -

SEPTEMBER 514.6 -

OCTOBER 335.1 -

NOVEMBER 110.5 -

DECEMBER 122.5 12.5

JANUARY 180.0 102.6

FEBRUARY 148.8 49.0

MARCH 166.6 88.1

TOTAL 2243.8 252.1

Note: The plant started pump mode operation from 07th December 2005.

MONTHS2005-06

2005-06

6.9 KADAMPARAI ENERGY GENERATED/PUMPED DURING LAST 5 YEARS (MU)

MONTHS2003-04 2004-05 *

42

Page 53: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009
Page 54: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

(Figures in Gross Mus.)

AGENCY HYDRO THERMAL GAS/DIESEL WIND/OTHERS NUCLEAR TOTAL

ANDHRA PRADESH 8033.90 20842.89 1840.51 0.66 -- 30717.97

KARNATAKA 11421.86 9182.27 96.74 5.06 -- 20705.93

KERALA 7449.56 -- 148.98 2.05 -- 7600.60

TAMILNADU 6136.93 18794.90 1984.68 14.67 -- 26931.19

PONDICHERRY -- -- 258.39 -- -- 258.39

CENTRAL SECTOR -- 57035.76 355.20 -- 4711.80 62102.75

IPP 256.40 2555.42 9822.73 6775.63 0.00 19410.18

TOTAL 33298.66 108411.24 14507.23 6798.08 4711.80 167727.01

7.1 SUMMARY OF REGIONAL ENERGY GENERATION OF SOUTHERN REGION DURING 2005-06

7 GENERATING STATIONS PERFORMANCE

43

Page 55: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

ANDHRA PRADESH (Figures in Gross Mus.)

SL.NO. STATION EFFECTIVE CAPACITY (MW) Apr-05 May-05 Jun-05 Jul-05 Aug-05 Sep-05 Oct-05 Nov-05 Dec-05 Jan-06 Feb-06 Mar-06 TOTAL

HYDRO

1 MACHKUND 84 42.9 37.6 33.5 19.5 26.1 28.3 33.0 31.8 47.6 34.2 30.1 29.2 393.8

2 T.B.DAM 57.6 0.0 0.0 0.0 4.4 24.9 25.5 21.9 17.4 16.8 20.6 17.7 13.0 162.2

3 UPPER SILERU 240 41.2 38.5 39.0 37.8 19.3 20.7 13.6 26.8 36.2 60.2 65.6 75.0 473.9

4 DONKARAYI 25 10.2 11.0 11.8 9.1 4.7 1.5 0.0 8.2 15.1 13.9 14.2 15.6 115.2

5 LOWER SILERU 460 91.1 96.2 108.0 84.9 52.8 24.8 0.1 66.3 127.3 134.6 120.2 132.0 1038.2

6 SRISAILAM RBPH 770 6.3 5.0 0.0 6.5 435.7 384.8 235.3 65.5 68.7 135.6 95.4 57.1 1496.0

7 SRISAILAM LBPH 900 21.2 56.0 5.3 11.7 571.5 514.6 335.1 110.5 122.5 180.0 148.8 166.6 2243.8

8 N'SAGAR 815.6 10.1 14.2 1.2 60.1 464.5 396.0 302.1 128.6 35.6 83.9 46.8 21.5 1564.5

9 NSR RT.CANAL.P.H 90 0.0 0.0 0.0 0.0 24.4 46.0 49.4 42.4 38.2 32.0 24.5 16.7 273.6

10 NSR LT.CANAL.P.H 60 0.0 0.0 0.0 0.0 19.6 21.5 20.5 23.7 12.3 14.5 7.7 1.8 121.7

NIZAMSAGAR 10 0.0 0.0 0.0 0.0 0.0 0.0 0.3 0.0 0.0 3.7 3.5 2.3 9.8

12 MINI HYDEL 12.16 0.6 0.5 0.1 0.4 0.5 2.5 4.7 0.1 0.1 0.5 0.5 1.0 11.4

13 POCHAMPAD 27 0.0 0.0 0.0 0.4 19.1 20.1 16.2 19.5 9.4 10.6 9.1 6.8 111.1

14 PENNA AHOBILAM 20 0.0 0.0 0.0 0.0 2.4 1.3 2.3 1.6 1.9 0.0 0.0 0.0 9.5

15 SINGUR 15 0.0 0.0 0.0 0.0 0.0 0.5 3.9 0.1 0.3 0.5 0.9 2.7 9.0

TOTAL 3586.36 223.6 259.0 198.9 234.8 1665.4 1488.1 1038.4 542.5 532.0 724.8 585.1 541.3 8033.9THERMAL

COAL

1 RAMAGUNDAM-B 62.5 35.1 38.9 9.6 32.6 33.8 31.7 31.3 31.6 37.9 41.2 38.2 37.4 399.3

2 KOTHAGUDEM-A 240 159.6 139.5 146.8 149.2 95.2 85.7 105.1 145.3 144.7 126.3 129.1 169.5 1595.9

3 KOTHAGUDEM-B 240 169.1 133.3 153.8 161.5 69.3 80.1 101.1 134.2 140.9 167.1 144.2 155.5 1610.0

4 KOTHAGUDEM-C 240 148.7 107.6 147.0 123.0 69.8 62.8 105.1 140.0 157.2 173.7 156.1 165.0 1556.0

5 KOTHAGUDEM-D 500 360.8 213.8 214.4 363.0 297.8 226.4 280.6 217.0 348.2 296.6 320.6 368.2 3507.4

6 VIJAYAWADA 1260 889.5 912.9 898.4 860.1 620.6 590.8 692.7 725.1 883.2 929.4 846.4 955.3 9804.4

7 RAYALASEEMA 420 234.0 152.9 202.4 120.0 121.5 142.3 259.6 130.4 143.4 297.7 272.4 293.3 2369.9

TOTAL 2962.5 1996.8 1698.9 1772.4 1809.3 1307.9 1219.8 1575.5 1523.6 1855.5 2032.0 1906.9 2144.2 20842.9GAS/NAPTHA/DIESEL

1 VIJJESWARAM (GAS) 100 60.6 57.7 55.1 57.9 103.5 55.4 61.9 49.2 58.6 37.5 85.6 32.4 715.5

2 VIJJESWARAM (GAS) 172 114.0 101.4 98.0 102.5 58.9 97.7 110.8 92.2 95.3 109.2 34.9 110.2 1125.1TOTAL 272 174.6 159.1 153.1 160.3 162.4 153.1 172.7 141.4 153.9 146.7 120.6 142.6 1840.5

7.2 PERFORMANCE OF POWER STATIONS DURING THE YEAR 2005-06

44

Page 56: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

ANDHRA PRADESH (Figures in Gross Mus.)

SL.NO. STATION EFFECTIVE CAPACITY (MW) Apr-05 May-05 Jun-05 Jul-05 Aug-05 Sep-05 Oct-05 Nov-05 Dec-05 Jan-06 Feb-06 Mar-06 TOTAL

WIND MILL

1 WIND 2 0.0 0.0 0.1 0.3 0.2 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.7TOTAL 2 0.0 0.0 0.1 0.3 0.2 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.7

IPPHYDRO

1 MINI HYDRO 91.4 0.0 4.5 3.2 0.9 16.3 21.2 20.0 25.0 25.0 21.0 12.3 18.0 167.3COAL

2 MINI POWER PLANTS 73.51 71.0 68.3 148.0 52.1 109.6 51.9 38.6 48.9 60.1 76.1 0.0 0.0 724.6GAS/NAPTHA/DIESEL

3 LANCO (GAS) 355 182.7 187.7 173.6 183.9 168.4 175.6 181.9 165.9 181.3 179.6 152.5 182.2 2115.2

4 JEGURUPADU (GAS) 216 135.4 110.6 108.5 106.6 66.8 106.0 134.0 124.5 107.6 93.3 102.5 106.5 1302.3

5 SPECTRUM (GAS) 207.88 118.2 110.4 110.1 110.6 112.6 110.6 118.3 100.9 109.2 114.3 94.7 105.5 1315.4

6 ISOLATED GAS WELL (GAS) 27.04 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

7 GVK EXTENSION (GAS) 220 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 28.8 0.0 0.0 28.8

8 RELIANCE ENERGY LTD. (GAS) 220 111.7 73.9 74.9 73.9 81.8 62.1 1.5 68.2 74.8 76.1 72.0 71.5 842.5

9 VEMAGIRI POWER GENERATION LTD. (GAS) 233 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 2.2 2.2WIND

10 WINDMILL 102.49 2.7 5.8 12.3 23.5 19.2 10.0 1.5 1.9 1.2 1.6 2.5 1.6 83.8OTHERS

11 COGENERATION (RCL) 41 22.6 23.9 23.2 24.1 24.0 23.2 24.6 20.8 22.3 25.6 22.6 8.7 265.6

12 BAGASSE 114.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0

13 BIOMASS 197.93 0.0 0.0 0.0 116.9 154.1 67.1 338.1

14 WASTED BASED PP 21.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0TOTAL 2120.85 644.3 585.1 653.8 692.6 598.6 560.6 520.4 556.1 581.3 616.4 613.1 563.3 7185.7

TOTAL AP 8943.71 3039.3 2702.1 2778.3 2897.4 3734.6 3421.6 3307.0 2763.6 3122.8 3519.9 3225.7 3391.4 37903.6

KARNATAKAHYDRO

1 SHARAVATHI 1035 360.0 415.7 211.8 206.9 472.3 400.2 333.1 406.2 480.1 528.1 511.6 539.7 4865.6

2 LINGANAMAKKI.P.H. 55 13.9 12.5 3.7 4.7 30.2 27.6 24.0 29.4 33.6 35.2 31.2 29.2 275.2

3 JOG 120 15.5 15.5 15.5 24.0 26.1 22.1 18.2 17.7 20.1 21.0 19.9 21.8 237.3

4 NAGJHERI 855 125.9 231.1 39.3 121.6 138.3 103.3 49.5 150.5 255.3 290.2 296.2 360.7 2162.0

5 SUPA 100 16.8 32.8 2.3 3.9 1.8 3.2 3.8 36.7 59.6 74.2 62.8 59.6 357.6

6 VARAHI 230 72.0 88.0 61.4 86.7 129.4 53.3 43.9 67.4 81.4 96.4 95.6 96.4 971.9

45

Page 57: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

KARNATAKA (Figures in Gross Mus.)

SL.NO. STATION EFFECTIVE CAPACITY (MW) Apr-05 May-05 Jun-05 Jul-05 Aug-05 Sep-05 Oct-05 Nov-05 Dec-05 Jan-06 Feb-06 Mar-06 TOTAL

HYDRO

7 BHADRA POWER HOUSE 39.2 0.5 0.0 0.0 0.3 13.7 12.6 13.4 7.7 0.0 7.5 10.3 10.1 76.1

8 SIVANSAMUDRAM 42 11.3 3.2 0.0 19.1 30.6 30.4 30.6 29.9 31.2 28.9 18.4 27.4 260.9

9 SHIMSHA 17.2 5.2 8.5 9.6 9.4 5.1 9.3 10.6 10.0 10.8 7.8 2.7 4.4 93.4

10 MUNIRABAD 27 0.0 0.0 0.0 1.3 10.2 17.3 15.0 11.2 8.7 11.0 6.4 2.2 83.3

11 T.B.DAM SHARE (20 %) 14.4 0.0 0.0 0.0 1.1 9.4 8.2 6.2 4.6 4.2 5.0 3.6 3.1 45.5

12 GHATAPRABHA 32 1.5 0.0 0.0 0.2 25.1 19.2 10.1 15.2 19.4 16.5 12.1 3.2 122.5

13 MANI DAM.P.H. 9 1.3 0.7 0.0 0.0 0.0 0.0 0.8 3.2 3.8 3.7 3.9 3.2 20.6

14 MINI HYDRO 4.45 0.0 0.0 0.0 1.1 1.2 1.2 1.1 1.1 1.1 1.1 1.1 1.1 10.1

15 MALLAPUR 9 0.0 0.0 0.0 2.8 2.8 2.8 2.8 2.8 2.8 2.8 2.8 2.8 25.2

16 KODASALLI 120 14.7 24.2 10.5 37.8 48.6 22.2 11.6 13.3 26.9 29.8 30.5 42.9 312.9

17 SHARAVATHI TAIL RACE 240 38.4 42.1 25.7 42.3 69.2 47.0 35.2 42.7 50.9 54.9 53.3 55.2 557.0

18 KADRA 150 13.0 21.9 15.2 59.3 71.8 32.6 13.1 12.6 21.7 25.0 22.9 36.7 345.9

19 ALMATTI 290 1.2 0.0 0.0 79.1 150.6 177.5 63.9 25.0 31.4 29.0 21.5 19.8 599.0

TOTAL 3389.25 691.2 896.2 395.0 701.6 1236.5 990.0 686.9 887.2 1143.0 1268.1 1206.6 1319.5 11421.9THERMAL

COAL

1 RAICHUR.T.PS. 1470 968.9 712.1 913.7 537.4 195.2 315.9 712.1 890.4 976.0 999.6 962.4 998.6 9182.3TOTAL 1470 968.9 712.1 913.7 537.4 195.2 315.9 712.1 890.4 976.0 999.6 962.4 998.6 9182.3

GAS/DIESEL/NAPTHA

1 YELEHANKA (DIESEL) 127.8 35.8 14.5 0.0 0.0 0.0 1.6 5.7 0.0 0.0 0.0 1.1 38.0 96.7TOTAL 127.8 35.8 14.5 0.0 0.0 0.0 1.6 5.7 0.0 0.0 0.0 1.1 38.0 96.7

WIND

1 KAPPATAGUDDA 4.55 0.0 0.0 2.2 0.0 2.1 0.0 0.0 0.0 0.0 0.0 0.8 0.0 5.1TOTAL 4.55 0.0 0.0 2.2 0.0 2.1 0.0 0.0 0.0 0.0 0.0 0.8 0.0 5.1

IPPHYDRO

1 MINI HYDEL 153.73 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0GAS/NAPTHA/DIESEL

2 TANIR BHAVI (NAPTHA) 220 8.6 51.1 35.5 0.0 0.0 0.0 0.0 0.0 0.0 4.7 50.2 91.3 241.4

3 JINDAL (COREX GAS) 100 88.2 115.9 114.4 80.6 16.2 95.2 84.6 129.0 0.0 112.0 124.6 139.0 1099.7

46

Page 58: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

KARNATAKA (Figures in Gross Mus.)

SL.NO. STATION EFFECTIVE CAPACITY (MW) Apr-05 May-05 Jun-05 Jul-05 Aug-05 Sep-05 Oct-05 Nov-05 Dec-05 Jan-06 Feb-06 Mar-06 TOTAL

GAS/DIESEL/NAPTHA

4 TATA ELECTRIC (DIESEL) 79.1 7.5 32.5 19.1 0.0 0.0 0.0 0.0 0.0 4.1 10.4 25.7 33.8 133.1

5 RAYAL SEEMA ALKALIES (DIESEL) 27.8 0.6 0.9 0.3 0.0 0.0 0.0 0.0 0.0 0.0 0.1 4.6 10.6 17.1

6 ITPL (DIESEL) 9WIND

7 WIND MILL 295.54OTHERS

8 CO-GENERATION 241.559 BIO-MASS 61.38

TOTAL 1188.1 226.3 324.4 289.3 265.7 284.5 398.0 403.6 355.4 239.5 367.3 418.2 510.6 4082.8TOTAL KAR 6179.7 1922.2 1947.2 1600.2 1504.7 1718.3 1705.5 1808.3 2133.0 2358.5 2635.0 2589.2 2866.7 24788.7

KERALAHYDRO

1 KUTTIADI + KUTTIADI EXTENTION 125 2.8 0.9 24.4 84.7 82.4 70.9 76.2 68.8 46.9 12.5 13.2 31.7 515.52 SHOLAYAR 54 24.3 28.4 15.9 1.5 25.4 25.7 26.5 25.5 35.2 23.2 26.5 32.1 290.23 PORINGALKUTHU 32 10.8 8.8 14.3 23.4 32.1 20.6 23.2 11.3 10.8 6.8 13.6 8.4 184.04 PALLIVASAL 37.5 19.5 20.5 21.0 21.5 20.9 20.3 21.3 19.7 18.2 21.2 17.2 17.2 238.55 SENGULAM 48 12.8 14.1 14.8 20.7 20.2 19.3 19.4 18.3 17.4 11.6 9.7 10.6 188.86 PANNIAR 30 4.0 7.5 3.5 15.1 23.8 23.0 14.5 12.0 21.9 12.9 10.0 11.5 159.77 NERIAMANGALAM 50.5 12.2 15.7 17.5 24.1 22.4 23.3 24.0 23.4 31.6 18.8 15.0 17.1 245.18 SABARIGIRI 310 90.6 130.5 71.8 73.0 124.8 162.0 179.4 140.7 126.6 135.2 99.1 134.9 1468.59 IDUKKI 780 192.5 241.9 169.1 97.8 85.0 281.2 294.8 167.4 175.4 271.4 344.3 378.0 2698.7

10 IDAMALAYAR 75 21.6 27.9 16.7 6.6 26.3 51.1 52.0 43.3 31.3 17.8 40.2 40.8 375.611 KALLADA 15 3.8 2.5 0.6 0.6 5.4 7.6 10.3 7.5 5.4 7.4 4.0 9.0 64.112 MADUPETTY 2 0.7 0.8 0.2 0.0 0.0 0.5 1.6 1.9 2.1 1.2 0.7 0.8 10.513 PEPPARA 3 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.3 0.0 0.314 L.PERIYAR 180 13.6 16.5 35.7 111.0 99.6 105.1 71.6 70.1 51.2 22.4 15.7 18.9 631.415 MALAMPUZHA 2.5 0.0 0.0 0.0 0.0 0.0 0.7 0.0 0.0 0.0 0.0 0.0 0.0 0.716 POR.L.BANK 16 0.0 7.3 8.7 11.8 0.0 11.0 11.5 8.9 9.5 8.7 0.0 8.5 85.917 KAKKAD 50 15.8 21.8 16.1 21.4 21.8 26.8 27.1 22.6 19.7 20.1 15.3 20.1 248.518 CHEMBUKADAVU 6.45 0.0 0.0 1.3 2.8 2.1 2.6 1.5 0.3 0.0 0.0 0.0 0.0 10.619 URUMI 6.15 0.0 0.0 1.1 2.6 2.5 2.9 1.9 1.5 0.3 0.0 0.0 0.0 12.920 MALANKARA 10.5 0.0 0.0 0.0 0.4 2.1 3.0 3.1 2.5 2.5 2.4 2.0 2.2 20.221 LOWER MEENMUTTY 1.15 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

TOTAL 1834.75 425.0 545.1 432.7 519.0 596.6 857.6 859.9 645.7 606.0 593.6 626.5 741.8 7449.6GAS/DIESEL/NAPTHA

1 BRAHMAPURAM DGPP (DIESEL) 106.6 3.6 17.8 10.2 0.0 3.4 0.0 0.0 0.0 0.5 0.0 3.7 16.6 55.7

2 KOZHIKODE DPP (DIESEL) 128 11.7 25.8 16.9 2.1 4.0 0.1 0.3 1.0 1.0 5.5 6.0 18.9 93.3TOTAL 234.6 15.3 43.6 27.1 2.1 7.3 0.1 0.3 1.0 1.5 5.5 9.6 35.5 149.0

121.4 124.0 120.0 185.1 268.4 302.8 319.0 226.4 235.4 240.1 213.0 235.9 2591.4

47

Page 59: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

KERALA (Figures in Gross Mus.)

SL.NO. STATION EFFECTIVE CAPACITY (MW) Apr-05 May-05 Jun-05 Jul-05 Aug-05 Sep-05 Oct-05 Nov-05 Dec-05 Jan-06 Feb-06 Mar-06 TOTAL

WIND

1 WIND MILL 2.025 0.1 0.2 0.3 0.3 0.2 0.2 0.1 0.1 0.1 0.2 0.1 0.1 2.1TOTAL 2.025 0.1 0.2 0.3 0.3 0.2 0.2 0.1 0.1 0.1 0.2 0.1 0.1 2.1

IPPHYDRO

1 MANIYAR 12 1.8 2.9 4.8 5.6 3.9 4.7 4.9 4.4 3.1 1.7 1.0 1.9 40.7

2 KUTHUNGAL 21 0.4 2.0 0.8 5.6 5.8 7.1 4.8 7.8 6.4 2.0 0.5 5.2 48.4GAS/NAPTHA/DIESEL

3 BSES (NAPTHA) 157 0.0 28.1 5.3 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 3.8 37.2

4 KASARGODE (DIESEL) 21.93 0.7 5.2 1.1 0.0 0.7 0.0 0.0 0.0 0.2 0.0 0.0 0.1 8.0TOTAL 211.93 2.9 38.2 12.0 11.2 10.4 11.8 9.7 12.2 9.7 3.7 1.5 11.0 134.3

TOTAL KER 2283.305 443.3 627.1 472.1 532.6 614.6 869.7 870.0 659.0 617.3 603.0 637.8 788.4 7734.9

TAMILNADUHYDRO

SL.NO. STATION EFFECTIVE CAPACITY (MW) Apr-05 May-05 Jun-05 Jul-05 Aug-05 Sep-05 Oct-05 Nov-05 Dec-05 Jan-06 Feb-06 Mar-06 TOTAL

1 PYKARA 59 30.2 27.1 29.0 29.0 21.9 18.1 12.8 17.2 18.0 16.6 14.0 22.3 256.2

2 PYKARA MICRO 2 0.9 0.7 0.4 1.2 1.3 1.2 1.1 1.0 0.8 0.8 0.8 0.6 10.9

3 PYKARA ULTIMATE 150 0.0 0.0 0.0 20.1 42.3 28.1 30.0 21.7 10.8 13.7 22.8 189.4

4 MOYAR 36 12.8 11.1 13.4 20.1 22.0 19.5 16.0 14.6 11.0 11.9 13.8 8.6 174.9

5 MARAVAKANDI 0.7 0.2 0.1 0.2 0.3 0.9 0.2 0.2 0.2 0.1 0.1 0.1 0.1 2.6

6 KUNDAH-I 60 41.6 31.3 11.4 27.3 35.6 23.5 16.9 24.9 24.1 28.8 27.1 34.4 326.9

7 KUNDAH-II 175 99.1 76.1 57.0 77.6 94.9 65.7 55.6 63.9 58.2 66.0 62.5 79.1 855.7

8 KUNDAH-III 180 57.9 44.1 35.9 44.8 56.3 41.4 39.1 40.7 35.3 38.6 37.2 45.3 516.6

9 KUNDAH-IV 100 9.3 13.1 39.8 28.6 26.5 16.6 17.4 10.9 6.4 6.2 6.4 7.1 188.2

10 KUNDAH-V 40 8.2 1.9 5.1 13.0 11.2 5.3 3.2 5.9 3.3 6.6 18.2 11.3 93.3

11 KUNDAH-VI 30 6.8 0.0 13.5 7.4 2.3 3.5 3.2 4.3 5.4 3.0 0.0 6.0 55.4

12 SURULIYAR 35 0.0 0.9 6.8 18.4 19.8 18.2 15.5 20.7 3.1 6.8 5.1 2.3 117.6

13 KADAMPARAI 400 29.6 45.3 79.0 49.5 40.8 46.9 64.0 70.1 72.0 53.3 30.9 0.0 581.4

14 ALIYAR 60 0.1 0.5 28.8 30.1 34.9 16.5 22.9 34.2 9.8 11.6 7.9 4.7 202.0

15 POONACHI 2 0.0 0.3 1.1 0.9 0.9 0.5 0.5 0.7 0.3 0.1 0.0 0.0 5.3

16 METTUR DAM 40 4.3 2.8 1.0 14.6 17.8 16.4 10.8 9.9 11.6 0.0 0.5 1.2 90.9

17 METTUR TUNNEL 200 0.0 1.6 14.9 115.7 140.1 115.8 116.7 78.5 36.7 6.4 11.2 3.1 640.7

18 LOWER METTUR 120 3.0 3.7 13.0 66.1 54.2 49.2 54.1 52.4 31.8 4.2 6.5 4.0 342.2

19 BHAVANISAGAR 8 1.0 3.0 4.7 5.1 2.0 1.3 3.0 4.2 4.6 4.8 2.4 3.9 40.0

20 PERIYAR 140 0.0 14.6 38.3 80.0 72.7 60.5 53.5 31.4 36.3 32.8 21.0 0.5 441.6

48

Page 60: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

TAMILNADUHYDRO (Figures in Gross Mus.)

SL.NO. STATION EFFECTIVE CAPACITY (MW) Apr-05 May-05 Jun-05 Jul-05 Aug-05 Sep-05 Oct-05 Nov-05 Dec-05 Jan-06 Feb-06 Mar-06 TOTAL

21 VAIGAI 6 0.1 0.0 0.0 0.0 2.1 4.0 1.7 1.6 3.4 2.1 1.0 2.2 18.2

22 PAPANASAM 28 1.8 8.2 10.1 12.9 16.2 15.0 10.6 10.0 13.7 14.1 13.0 4.2 129.7

23 SERVALAR 20 0.0 1.9 5.3 5.1 6.8 6.3 3.6 3.7 6.9 7.0 5.9 1.4 53.9

24 SARKARAPATHY 30 6.4 0.0 0.0 0.0 14.1 17.2 15.8 11.7 5.0 15.4 13.3 16.1 115.0

25 SHOLAYAR 95 9.4 5.6 25.8 60.8 56.8 60.1 45.7 26.2 28.6 42.0 5.1 12.9 379.0

26 LOWER BHAVANI 8 0.5 0.0 0.0 0.0 4.8 3.4 1.9 3.9 3.6 2.7 3.2 1.1 25.1

27 KODAYAR 100 27.4 32.8 32.4 35.1 3.4 6.0 3.5 9.1 9.4 33.0 25.1 27.3 244.5

28 SATHANUR DAM PH 7.5 1.7 0.0 0.0 0.0 0.0 0.7 1.3 5.0 5.7 2.4 3.0 3.5 23.3

29 MICRO TOTAL 5.15 0.6 0.3 0.2 0.6 1.5 2.2 1.5 1.6 1.8 2.5 2.1 1.3 16.2TOTAL 2137.35 352.9 327.0 467.1 764.4 804.3 663.3 622.1 580.2 457.6 433.5 360.1 304.5 6136.9

THERMALCOAL

1 ENNORE.T.P.S 450 103.2 49.4 65.9 36.5 47.8 49.1 42.0 47.5 44.5 40.4 41.2 33.0 600.5

2 TUTUCORIN.T.P.S 1050 699.6 706.1 716.8 717.8 606.0 510.9 609.0 547.7 579.4 635.4 580.2 765.3 7674.3

3 METTUR.T.P.S 840 596.1 602.2 556.1 594.1 498.1 416.4 549.6 478.0 605.6 470.4 526.5 625.8 6518.9

4 NORTH MADRAS.T.P.S 630 291.6 305.5 300.5 303.5 360.9 317.2 299.1 288.7 297.6 364.3 405.5 466.8 4001.2TOTAL 2970 1690.5 1663.2 1639.3 1651.9 1512.8 1293.6 1499.7 1361.9 1527.2 1510.5 1553.4 1890.9 18794.9

GAS/NAPTHA/DIESEL

1 BASIN BRIDGE (NAPTHA) 120 2.8 6.5 8.6 4.6 0.6 0.9 0.7 1.1 1.7 2.3 6.2 3.9 39.9

2 KOVIL KALAPPAL (GAS) 107.88 16.6 45.3 57.4 57.6 61.6 57.9 59.7 39.3 42.1 43.5 46.8 45.1 572.9

3 VALATHUR (GAS) 94 59.7 55.8 60.1 58.1 55.0 52.3 64.0 61.7 45.2 60.5 61.0 64.2 697.6

4 KUTTALAM (GAS) 101 66.2 58.3 53.9 30.5 12.4 64.6 67.3 62.4 83.1 59.0 57.8 58.7 674.2

TOTAL 422.88 145.3 165.9 180.0 150.8 129.7 175.7 191.7 164.5 172.0 165.3 171.9 171.9 1984.7WIND

1 TNEB WIND MILL 19.355 0.3 0.8 2.9 3.1 2.6 2.5 0.7 0.5 0.1 0.5 0.6 0.1 14.7

TOTAL 19.355 0.3 0.8 2.9 3.1 2.6 2.5 0.7 0.5 0.1 0.5 0.6 0.1 14.7IPPCOAL

1 TCPL 63.5 42.0 41.8 39.4 42.7 43.1 41.6 42.5 37.5 28.7 43.2 39.0 41.9 483.3LIGNITE

2 ST - CMS 250 131.1 162.3 138.2 72.6 58.3 20.7 61.1 78.4 147.0 156.4 151.7 169.7 1347.5GAS/NAPTHA/DIESEL

3 P P NALLUR (NAPTHA) 330.5 0.0 112.9 94.4 36.0 0.0 -0.3 -0.2 -0.1 0.0 0.0 37.3 147.4 427.4

4 ABAN POWER (GAS) 113.21 11.4 32.7 36.1 36.2 64.9 70.3 59.5 68.0 72.5 74.0 68.0 75.0 668.5

5 HI-TECH (GAS) 15 7.0 6.5 6.8 6.9 6.4 6.2 6.6 6.6 6.9 6.4 6.0 6.7 79.0

49

Page 61: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

TAMILNADUIPPGAS/NAPTHA/DIESEL (Figures in Gross Mus.)

SL.NO. STATION EFFECTIVE CAPACITY (MW) Apr-05 May-05 Jun-05 Jul-05 Aug-05 Sep-05 Oct-05 Nov-05 Dec-05 Jan-06 Feb-06 Mar-06 TOTAL

6 MADURAI POWER CL (DIESEL) 106 28.2 40.4 44.5 24.2 11.6 10.8 11.9 15.2 21.2 31.7 45.1 43.6 328.3

7 SAMALPATTY (DIESEL) 105 29.5 43.5 43.7 23.1 12.0 13.2 12.1 15.2 21.0 29.7 46.4 43.3 332.6

8 ARKEY ENERGY (GAS) 38 0.0 0.0 0.0 0.0 0.0 0.0 0.3 19.4 22.3 22.1 17.9 16.3 98.3

9 GMR POWER (DIESEL) 196 61.8 79.6 92.3 66.6 40.2 37.9 40.7 38.4 50.1 63.9 87.1 87.1 745.6WIND/OTHERS

10 WIND 2763.7 113.9 137.1 417.4 561.8 589.4 510.2 380.7 172.3 59.2 148.5 253.3 88.0 3431.8

11 CO-GENERATION 142 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 65.0 65.0

TOTAL 4122.91 424.9 656.8 912.8 870.1 825.9 710.6 615.2 450.9 428.7 575.9 751.7 784.0 8007.5

TOTAL TN 9672.495 2613.9 2813.7 3202.1 3440.3 3275.2 2845.7 2929.4 2558.0 2585.5 2685.7 2837.7 3151.4 34938.7

PONDICHERRYGAS/NAPTHA/DIESEL

1 KARIAKAL POWER PLANT (GAS) 32.5 21.5 24.0 22.3 23.6 22.9 22.7 24.3 23.0 22.7 19.9 9.6 21.9 258.4

TOTAL 32.5 21.5 24.0 22.3 23.6 22.9 22.7 24.3 23.0 22.7 19.9 9.6 21.9 258.4

TOTAL PONDY 32.5 21.5 24.0 22.3 23.6 22.9 22.7 24.3 23.0 22.7 19.9 9.6 21.9 258.4

CENTRAL SECTORTHERMAL

COAL

1 RAMAGUNDAM T.P.S (ISGS) - NTPC 2600 1836.4 1927.8 1772.4 1534.2 1424.3 1243.1 1274.3 1363.4 1753.1 1846.7 1760.8 1955.1 19691.5

2 TALCHER STAGE II (ISGS) - NTPC 2000 997.0 837.9 786.0 1348.1 987.5 988.8 1264.6 1338.1 1171.6 1416.3 1313.5 1337.6 13787.0

3 SIMHADRI (AP) - NTPC 1000 691.3 724.9 605.4 481.4 577.1 506.7 595.2 429.0 666.2 675.1 644.4 714.0 7310.7

LIGNITE

4 NEYVELI-I (TN) - NLC 600 372.2 381.4 365.9 363.5 356.3 306.4 286.8 206.8 241.6 324.7 380.5 404.1 3990.1

5 NEYVELI-II (ISGS) - NLC 1470 1023.1 1020.2 881.5 883.3 789.8 726.6 755.1 610.1 560.8 724.2 637.0 562.5 9174.1

6 NEYVELI TPS-I (Expansion) (ISGS) - NLC 420 248.4 310.9 290.8 212.4 246.5 257.0 258.4 180.4 260.5 306.3 263.7 247.0 3082.3TOTAL 8090 5168.4 5203.1 4702.0 4822.9 4381.5 4028.6 4434.4 4127.8 4653.7 5293.3 4999.8 5220.3 57035.8

GAS/NAPTHA/DIESEL

4 RGCCPP,KAYAMKULAM (KSEB) - NTPC 359.58 44.9 61.5 140.3 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 108.5 355.2TOTAL 359.58 44.9 61.5 140.3 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 108.5 355.2

NUCLEAR

1 M.A.P.S KALPAKAM (ISGS) - NPC 440 152.8 158.0 101.2 137.9 154.5 149.9 123.3 135.5 116.2 167.4 199.3 256.4 1852.4

2 KAIGA A.P.S (ISGS) - NPC 440 301.2 260.2 255.8 170.5 240.6 249.3 256.3 224.8 231.9 230.9 207.7 230.2 2859.4TOTAL 880 454.0 418.2 357.0 308.4 395.1 399.2 379.6 360.3 348.1 398.3 407.0 486.6 4711.8

TOTAL C.S 9329.58 5667.3 5682.8 5199.3 5131.3 4776.5 4427.8 4814.0 4488.1 5001.8 5691.6 5406.8 5815.4 62102.8GRAND TOTAL 36441.29 13707.5 13796.9 13274.3 13530.0 14142.0 13293.0 13753.0 12624.7 13708.5 15155.1 14706.8 16035.3 167727.0

50

Page 62: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

MONTHS Apr-05 May-05 Jun-05 Jul-05 Aug-05 Sep-05 Oct-05 Nov-05 Dec-05 Jan-06 Feb-06 Mar-06 AVERAGE

ANDHRA PRADESH

VIJAYAWADA TS 98.05 97.38 99.03 91.75 66.20 65.12 73.89 79.93 94.22 99.14 99.96 101.91 88.83

KOTHAGUDAM TS 95.42 65.46 75.36 87.77 58.62 51.80 65.21 72.46 87.14 84.14 91.47 94.55 77.38

RAYALASEEMA TPS 77.38 48.93 66.93 38.41 38.87 47.06 83.08 43.12 45.90 95.27 96.50 93.86 64.41

KARNATAKARAICHUR TPS 91.54 65.11 86.33 49.14 17.85 29.85 65.11 84.13 89.24 91.40 97.43 91.31 71.31

TAMIL NADUENNORE TS 31.85 14.76 20.34 10.90 14.28 15.15 12.54 14.66 13.29 12.07 13.62 9.86 15.23

NORTH CHENNAI TPS 64.29 65.18 66.25 64.75 77.00 69.93 63.81 63.65 63.50 77.72 95.78 99.59 72.50

METTUR TPS 98.56 96.36 91.95 95.06 79.69 68.85 87.94 79.03 96.90 75.27 93.27 100.13 88.59

TUTUCORIN TPS 92.54 90.39 94.81 91.88 77.58 67.58 77.96 72.45 74.17 81.34 82.23 97.96 83.43

NTPCRAMAGUNDAM STPS 98.10 99.66 94.68 79.31 73.63 66.40 65.88 72.83 90.63 95.47 100.78 101.07 86.46

SIMHADRI STPS 96.01 97.43 84.08 64.70 77.57 70.38 80.00 59.58 89.54 90.74 95.89 95.97 83.46

NLCNEYVELI - II 96.66 93.28 83.29 80.76 72.21 68.65 69.04 57.64 51.27 66.22 64.49 51.43 71.24

NEYVELI TPS I (Exp) 82.14 99.49 96.16 67.97 78.87 84.99 82.69 59.66 83.37 98.02 93.43 79.05 83.78

NEYVELI - I 86.16 85.44 84.70 81.43 79.82 70.93 64.25 47.87 54.12 72.74 94.36 90.52 75.92

NPCMADRAS APS 54.42 54.45 36.04 47.53 53.24 53.38 42.49 48.25 40.05 57.69 76.04 88.37 54.22

KAIGA GS 95.08 79.48 80.74 52.08 73.49 78.69 78.29 70.96 70.84 70.53 70.26 70.32 74.19

7.3 MONTH-WISE PLANT LOAD FACTOR (%) OF MAJOR THERMAL UNITS DURING 2005 - 06

51

Page 63: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

DC SCHEDULE ACTUAL INJECTION DC SCHEDULE ACTUAL

INJECTION DC SCHEDULE ACTUAL INJECTION DC SCHEDULE ACTUAL

INJECTIONApr-05 1375.39 1373.09 1390.32 326.45 325.55 330.24 936.30 934.32 944.49 390.36 388.24 392.96May-05 1441.83 1440.68 1456.77 347.29 347.29 351.23 777.20 777.11 785.50 386.70 383.59 389.68Jun-05 1378.11 1378.07 1390.44 271.31 271.31 271.62 703.20 703.01 714.35 334.02 332.87 336.92Jul-05 1245.06 1223.75 1232.36 209.16 199.41 200.00 1018.50 1016.14 1027.83 324.19 322.07 325.36Aug-05 1166.58 1049.38 1057.32 333.49 248.72 265.33 1020.78 973.49 987.54 302.95 290.42 291.13Sep-05 1161.11 897.72 910.45 311.70 230.92 236.71 1074.59 893.92 930.36 374.08 328.82 329.84Oct-05 1103.32 892.55 906.39 344.81 266.40 272.50 1344.15 1165.51 1201.59 366.33 328.38 328.69Nov-05 1092.50 948.69 969.00 336.48 291.19 298.20 1343.27 1251.00 1273.35 292.07 278.56 278.54Dec-05 1337.43 1294.12 1315.42 348.59 323.01 332.90 1112.92 1103.43 1115.18 156.02 152.48 151.73Jan-06 1394.59 1393.82 1407.15 337.14 330.83 335.05 1347.23 1347.05 1355.35 273.01 267.33 322.78Feb-06 1344.08 1344.08 1357.09 301.21 301.96 303.97 1247.55 1247.55 1257.57 226.79 226.51 228.58Mar-06 1474.26 1474.26 1487.81 350.84 350.96 353.43 1269.71 1272.35 1282.20 154.42 154.42 155.68TOTAL 15514.26 14710.21 14880.53 3818.47 3487.56 3551.19 13195.39 12684.87 12875.31 3580.92 3453.70 3531.90

DC SCHEDULE ACTUAL INJECTION DC SCHEDULE ACTUAL

INJECTION DC SCHEDULE ACTUAL INJECTION DC SCHEDULE ACTUAL

INJECTIONApr-05 536.39 507.44 536.18 224.52 223.42 225.67 127.33 127.33 128.96 270.00 270.00 273.65May-05 532.35 525.40 535.73 281.35 281.35 284.07 131.09 131.09 132.65 233.38 233.38 233.91Jun-05 458.21 456.96 461.55 263.60 263.60 265.12 84.68 84.68 81.22 227.80 227.80 228.76Jul-05 480.42 456.90 473.68 196.98 191.32 192.35 115.63 115.63 114.71 151.11 151.11 150.52Aug-05 466.04 396.90 420.42 238.88 219.73 222.75 129.36 129.36 130.16 212.04 212.04 213.83Sep-05 392.47 315.85 323.12 262.39 231.34 232.18 126.10 126.10 126.42 221.28 221.28 223.10Oct-05 398.53 342.42 350.03 266.92 233.87 233.80 101.78 101.78 100.67 223.58 223.58 228.34Nov-05 282.65 264.08 267.81 177.18 162.00 162.60 112.95 112.95 113.67 195.05 195.05 198.49Dec-05 352.45 343.66 348.99 245.09 235.14 237.08 94.37 94.37 94.22 201.24 201.24 204.01Jan-06 386.59 379.41 384.00 281.14 278.24 280.26 139.68 139.68 138.74 200.88 200.88 203.00Feb-06 343.34 343.02 346.21 239.96 239.99 241.40 174.43 174.43 171.69 181.80 181.80 183.61Mar-06 347.86 347.86 350.89 223.84 223.84 225.00 223.75 223.75 223.09 201.23 201.23 203.58TOTAL 4977.31 4679.89 4798.60 2901.85 2783.84 2802.29 1561.16 1561.16 1556.21 2519.37 2519.37 2544.81

NEYVELI TPS I (Exp)

7.4 MONTHWISE DECLARED CAPABILITY, DESPATCH SCHEDULE Vs ACTUAL INJECTION BY ISGS TO THE GRID (Mus)

MONTHS

MONTHS

NTPC, RAMAGUNDAM U # 7NTPC, RAMAGUNDAM U # 1 - 6 NTPC, TALCHER STAGE II NEYVELI TPS II STAGE I

NEYVELI TPS II STAGE II MADRAS APS KAIGA GS

52

Page 64: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009
Page 65: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

HYDRO THERMAL NUCLEAR OTHERSMW MW MW MW MW MW MW

1 4365 11813 584 2419 19181 1407 205882 4112 11900 588 2393 18993 1571 205643 4220 11906 584 2340 19050 1572 206224 4338 11898 588 2541 19364 1571 209365 5102 11937 585 2742 20366 1293 216596 5881 11905 584 2583 20953 1291 222437 5594 11867 586 2805 20853 1351 222038 4851 11817 596 2881 20144 1682 218279 4775 11737 594 2847 19953 1869 2182210 5314 11768 585 2901 20567 1931 2249811 5456 11698 590 2753 20498 1958 2245612 5465 11713 590 2236 20003 2125 2212813 5018 11669 594 3038 20320 2150 2247014 5127 11672 592 2905 20296 2147 2244315 5410 11694 584 3263 20951 2092 2304316 4849 11656 586 3082 20173 2043 2221617 3766 11800 582 2893 19041 1955 2099618 3215 11950 590 2837 18592 2027 2061919 6055 12095 588 2875 21613 1759 2337220 6246 12089 589 1804 20729 1757 2248621 5964 12129 418 2737 21248 1760 2300722 5739 12047 394 2656 20836 1757 2259323 5135 12018 391 2612 20156 1846 2200224 4464 11938 393 2600 19394 1856 21250

8 REGIONAL LOAD CURVE DATA

TOTAL DEMAND MET

8.1 HOURLY GENERATION/LOAD FOR THE REGIONAL PEAK DEMAND DAY DURING 2005-06

HOURS

GENERATION INTER REGIONAL EXCHNAGES

IMPORT(+)/EXPORT(-)TOTAL

(29th Mar 2006)

53

Page 66: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

HYDRO THERMAL NUCLEAR OTHERSMW MW MW MW MW MW MW

1 1572 6924 459 1526 10482 485 109662 1519 6819 465 1287 10090 621 107103 1384 6811 463 1654 10313 620 109334 1670 6842 463 1314 10289 620 109105 2096 6893 463 1648 11100 621 117226 2910 6923 461 1590 11884 570 124547 3527 7079 464 1593 12662 621 132838 4192 7134 464 1491 13280 672 139529 4244 7170 465 1675 13553 691 1424410 4264 7208 459 1649 13579 777 1435611 3872 7242 463 1722 13298 795 1409312 3906 7230 462 1786 13384 798 1418313 4098 7395 465 1700 13657 656 1431314 3850 7500 462 1771 13584 654 1423815 4006 7380 465 1806 13658 653 1431116 3980 7358 463 1466 13266 654 1392017 4213 7307 463 1633 13616 610 1422618 6100 7619 462 1956 16137 869 1700619 7550 7760 466 1579 17355 860 1821520 6933 7779 465 1624 16801 935 1773621 6665 7598 466 1368 16096 757 1685322 4543 7586 470 1734 14333 503 1483623 3432 7504 466 1817 13219 489 1370724 2751 7315 467 1783 12316 597 12913

TOTAL DEMAND MET

8.2 HOURLY GENERATION/LOAD FOR THE REGIONAL LEAN DEMAND DAY DURING 2005-06

HOURS

GENERATION INTER REGIONAL EXCHNAGES

IMPORT(+)/EXPORT(-)TOTAL

(02nd Nov 2005)

54

Page 67: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009
Page 68: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

MAXIMUM MINIMUM AVERAGE < 48.5 HZ 48.5 TO 49.0 HZ

49.0 TO 49.5 HZ

49.5 TO 50.0 HZ

50.0 TO 50.5 HZ > 50.5 HZ

Apr-05 50.67 48.86 49.8 0 0.01 7.8 78.92 13.2 0.07 0.77 0.16

May-05 50.76 48.42 49.52 0.01 6.36 39.2 49.52 4.89 0.02 3.46 0.24

Jun-05 50.62 48.54 49.59 0 1.91 35.2 54.22 8.64 0.03 2.52 0.23

Jul-05 50.79 48.69 49.85 0 0.28 8.77 60.77 28.82 1.36 1.00 0.21

Aug-05 50.89 48.53 50.1 0 0.06 0.32 22.57 76.14 0.91 0.42 0.14

Sep-05 50.83 48.92 50.25 0 0 0.11 5.67 88.60 5.62 0.88 0.13

Oct-05 51.02 49.4 50.22 0 0 0.03 3.93 93.51 2.53 0.67 0.11

Nov-05 50.96 48.54 50.11 0 0.12 1.46 19.82 76.96 1.64 0.55 0.17

Dec-05 50.74 48.58 49.94 0 0.2 3.49 48.92 47.34 0.05 0.55 0.19

Jan-06 50.87 48.84 49.83 0 0.08 5.39 68.48 26 0.05 0.77 0.20

Feb-06 50.87 48.53 49.49 0 8.55 33.41 55.67 2.31 0.06 3.58 0.19

Mar-06 50.71 48.47 49.42 0 10.24 46.55 39.29 3.84 0.08 4.39 0.20

AVERAGE 49.84 0.00 2.32 15.14 42.31 39.19 1.04 1.63 0.18

Maximum frequency during the year = 51.02 Hz on 28.10.2005

Minimum frequency during the year = 48.42 Hz on 11.05.2005

Minimum FVI during the year = 0.12 on 01.09.2005

Maximum FVI during the year = 10.82 on 02.03.2006

Minimum St. Dev during the year = 0.08 on 30.09.2005

Maximum St. Dev during the year = 0.44 on 18.07.2005

9 FREQUENCY, VOLTAGE & RESERVOIR DATA

FREQUENCY (Hz) % OF TIME WHEN FREQUECY WAS BETWEEN

9.1 FREQUENCY PROFILE OF SOUTHERN REGION 2005 - 06

MONTH AVERAGE FVI

AVERAGE STD

DEVIATION

55

Page 69: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

MAX MIN AVG DAILY MAX

AVG DAILY MIN MAX MIN AVG DAILY

MAXAVG DAILY

MIN MAX MIN AVG DAILY MAX

AVG DAILY MIN

Apr-05 415 400 412 403 426 400 422 407 423 393 419 398May-05 416 403 412 405 425 393 421 408 423 394 418 398Jun-05 420 400 414 406 430 403 422 409 425 390 416 397Jul-05 419 403 416 409 429 408 425 414 428 393 419 401Aug-05 420 402 416 406 428 406 425 411 426 394 421 401Sep-05 418 401 415 406 431 405 426 412 429 399 423 402Oct-05 418 399 414 404 429 406 425 412 432 399 424 405Nov-05 419 403 416 406 430 409 428 414 432 401 427 407Dec-05 419 402 415 405 429 409 427 412 430 393 426 406Jan-06 418 403 415 405 430 409 427 413 426 395 421 402Feb-06 416 401 413 404 426 402 422 410 423 386 419 398Mar-06 415 401 411 404 430 396 417 406 422 390 418 398

AVERAGE 414 405 424 411 421 401MAX/MIN 420 399 431 393 432 386

MAX MIN AVG DAILY MAX

AVG DAILY MIN MAX MIN AVG DAILY

MAXAVG DAILY

MIN MAX MIN AVG DAILY MAX

AVG DAILY MIN

Apr-05 420 384 412 390 432 396 425 403 425 376 409 389May-05 422 377 411 388 427 392 421 400 421 385 409 393Jun-05 413 383 408 388 423 387 415 395 415 386 409 394Jul-05 419 382 408 388 428 385 417 396 425 384 413 393Aug-05 416 384 412 388 425 390 421 398 426 384 417 394Sep-05 421 384 414 389 429 390 422 399 426 386 421 393Oct-05 421 385 415 391 441 395 426 402 426 381 420 393Nov-05 422 385 415 390 435 397 431 407 426 376 419 390Dec-05 419 385 413 389 431 400 427 410 423 385 419 396Jan-06 414 379 408 386 430 405 426 410 422 388 414 399Feb-06 420 383 411 388 428 395 425 404 418 377 413 396Mar-06 420 376 411 387 428 390 421 398 421 388 411 395

AVERAGE 411 388 423 402 414 394MAX/MIN 422 376 441 385 426 376

9.2 400kV VOLTAGE PROFILE OF IMPORTANT STATIONS : 2005-06 (KV)

MONTHSRAMAGUNDAM HYDERABAD CUDDAPAH

MONTHSBANGALORE MADRAS TRISSUR

56

Page 70: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

SRISAILAM N'SAGARLEVEL ENERGY INFLOW LEVEL LEVEL LEVEL ENERGY INFLOW LEVEL ENERGY INFLOW

Mts MU MU Mts Mts Mts MU MU Mts MU MUApr-05 825.40 129 39 247.86 154.26 537.00 991 13 524.00 585 0May-05 820.89 63 26 242.26 153.68 533.42 547 3 517.70 380 0Jun-05 818.42 31 53 231.71 155.72 536.08 793 555 520.90 479 147Jul-05 819.06 45 45 262.65 154.05 548.37 2811 2313 541.40 1423 961Aug-05 825.79 136 133 269.66 179.71 553.67 4300 1818 554.20 2303 740Sep-05 834.79 396 315 269.60 179.69 554.39 4532 655 559.80 2772 430Oct-05 837.10 479 161 269.69 179.77 554.20 4478 295 560.82 2869 101Nov-05 837.61 504 132 268.93 170.08 553.09 4118 83 559.63 2757 24Dec-05 836.74 462 57 267.61 173.49 551.49 3641 65 557.18 2555 7Jan-06 835.53 414 52 264.57 170.84 549.33 3056 41 553.73 2273 0Feb-06 834.07 355 36 261.31 168.19 547.21 2544 54 550.66 2028 0Mar-06 832.50 304 58 258.93 164.62 544.51 1989 45 547.16 1790 0

Total Inflow in Mus 1107 5940 2410Full Reservoir Level in Mts 838.4 270.7 179.9 554.5 564Energy In Mus at FRL 495 4547 3152MDDL IN Mts 818.39 243.84 149.3 522.73 495

LEVEL ENERGY INFLOW LEVEL ENERGY INFLOW ENERGY INFLOWMts MU MU Mts MU MU MU MU

Apr-05 706.38 457 41 949.12 204 20 760 50May-05 701.84 254 37 933.10 78 15 534 44Jun-05 702.83 301 228 936.27 101 118 463 168Jul-05 718.58 1120 1014 967.10 505 531 1249 1186Aug-05 725.95 1624 496 974.55 670 235 1484 533Sep-05 730.64 1998 640 980.80 873 361 1491 327Oct-05 729.33 1924 225 979.52 827 136 1471 206Nov-05 729.52 1948 194 979.55 828 143 147 176Dec-05 728.52 1866 88 978.80 801 96 1343 106Jan-06 725.28 1604 30 975.40 695 35 1206 45Feb-06 720.80 1291 30 972.23 607 15 1050 17Mar-06 715.32 946 35 967.42 486 23 869 19

Total Inflow in Mus 3058 1728 2877Full Reservoir Level in Mts 732.43 981.45Energy In Mus at FRL 2148 856 1504MDDL IN Mts 694.94 908.3

End Of The Month

9.3 MAJOR RESERVOIR PARTICULARS DURING 2005 - 06

End Of The Month

IDUKKI KAKKI NILIGIRIS

JALAPUT LINGANAMAKKI SUPA

57

Page 71: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

MAXIMUM MINIMUM AVERAGE < 48.5 HZ 48.5 TO 49.0 HZ

49.0 TO 49.5 HZ

49.5 TO 50.0 HZ

50.0 TO 50.5 HZ > 50.5 HZ

2001 - 02 51.44 47.72 48.52 68.08 9.96 6.48 8.51 2.88 4.10 29.71

2002 - 03 51.37 47.69 48.95 39.31 10.17 14.48 23.93 10.10 2.01 18.86

2003 - 04 51.17 48.18 49.69 0.10 2.20 22.03 63.00 12.23 0.44 1.95

2004 - 05 50.90 48.62 49.85 0.00 0.13 8.49 63.81 27.40 0.17 0.83

2005 - 06 51.02 48.42 49.84 0.00 2.32 15.14 42.31 39.19 1.04 1.63

9.4 FREQUENCY SPECTRUM OF SOUTHERN REGION FOR PAST FIVE YEARS

MONTH AVERAGE FVI

FREQUENCY (Hz) % OF TIME WHEN FREQUECY WAS BETWEEN

58

Page 72: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

AVG DAILY MAX

AVG DAILY MIN

AVG DAILY MAX

AVG DAILY MIN

AVG DAILY MAX

AVG DAILY MIN

AVG DAILY MAX

AVG DAILY MIN

AVG DAILY MAX

AVG DAILY MIN

AVG DAILY MAX

AVG DAILY MIN

AVG DAILY MAX

AVG DAILY MIN

2000 - 01 397 385 396 377 396 361 379 333 386 354 400 363 392 374

2001 - 02 405 394 409 388 404 366 396 345 399 369 406 369 400 382

2002 - 03 407 399 412 397 403 377 403 367 398 376 407 385 403 391

2003 - 04 409 402 411 397 415 398 405 385 417 403 412 400 414 406

2004 - 05 411 403 416 402 415 398 410 391 423 406 414 398 418 409

2005 - 06 414 405 424 411 421 401 411 388 423 402 414 394 419 409

9.5 VOLTAGE PROFILE OF SOUTHERN REGION FOR PAST SIX YEARS

YEAR TRISSUR NEYVELI IIRAMAGUNDAM HYDERABAD CUDDAPHA BANGALORE MADRAS

59

Page 73: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009
Page 74: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

10 MISCELLANEOUS

10.1 DEFENCE MECHANISMS IN SOUTHERN REGION

48.5Hz Inst. 48.2Hz Inst 48.0Hz Inst

ANDHRA PRADESH 516 409 975

453 - 857 369 - 841 332 - 732

Off peak -Peak Off peak -Peak Off peak -Peak

100 - 180 83 - 125 317 - 494

Off peak -Peak Off peak -Peak Off peak -Peak

TAMIL NADU 504 484 757

TOTAL 1573 -2057 1345 - 1859 2381 - 2958

FOR ALARM : 49.5Hz WITH RATE OF FALL OF 0.3HZ/Sec.FOR TRIP : 49.0Hz WITH RATE OF FALL OF 0.3HZ/Sec.Instantaneous

CONSTITUENT LOAD RELIEF (MW )

ANDHRA PRADESH 1472

485 - 1036Off peak -Peak

98 - 168Off peak -Peak

TAMIL NADU 509

KERALA

KERALA

I) PROVISION FOR UNDER FREQUENCY LOAD SHEDDING THROUGH FLAT UF RELAY

KARNATAKA

LOAD RELIEF IN MW AT CONSTITUENT

KARNATAKA

II) PROVISION FOR UNDER FREQUENCY LOAD SHEDDING THROUGH DF/DT UF RELAY

60

Page 75: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

10.2 SHUNT CAPACITORS INSTALLED DURING 2005 - 06

CONSTITUENTS INSTALLED AS ON 31.03.2005

INSTALLED DURING 2005 - 06

CAPACITOR INSTALLED AS ON 31.03.2006

REQUIREMENT FOR 2005 - 06

SHORTFALL DURING 2005 - 06

APTRANSCO 6413.4 10 6423.4 200 190

KPTCL 4031.7 105.8 4137.5 72.9 -32.9

KSEB 865 140 1005 140 0

TNEB 3762.7 129.6 3892.3 213.6 84

SOUTHERN REGION 15072.8 385.4 15458.2 626.5 241.1

61

Page 76: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009
Page 77: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

GRAPH G1

62

SOURCE-WISE EFFECTIVE GENERATING CAPACITY OF SOUTHERN REGION AS ON 31-MAR-06

HYDRO31%

THERMAL43%

GAS/NAPTHA/DIESEL12%

NUCLEAR2%

WIND12%

SOURCE IN MW IN %HYDRO 11226 31

THERMAL 15880 43GAS/NAPTHA/DIESEL 4447 12

NUCLEAR 880 2WIND 4336 12TOTAL 36769 100

Page 78: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

GRAPH G2

63

AGENCY-WISE EFFECTIVE GENERATING CAPACITY OF SOUTHERN REGION AS ON 31-MAR-06

IPP22%

CENTRAL SECTOR25%

PONDY0.1%

TAMIL NADU15%

KERALA6%

KARNATAKA14%

ANDHRA PRADESH19%

AGENCY IN MW IN %ANDHRA PRADESH 6823 19

KARNATAKA 4992 14KERALA 2072 6

TAMILNADU 5550 15PONDICHERRY 33 0

CENTRAL SECTOR 9330 25IPP 7971 22

TOTAL 36769 100

Page 79: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

GRAPH G3

64

SOURCE-WISE CONTRIBUTION TO ENERGY GENERATED DURING 2005-06

HYDRO20%

THERMAL65%

GAS/NAPTHA/DIESEL8%

NUCLEAR3%

WIND4%

SOURCE IN Mus IN %HYDRO 33299 20

THERMAL 108411 65GAS/NAPTHA/DIESEL 14507 8

NUCLEAR 4712 3WIND 6798 4TOTAL 167727 100

Page 80: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

GRAPH G4

65

SOURCE-WISE CONTRIBUTION(MW) TO REGIONAL PEAK MET DURING 2005-06(29TH MARCH 2006)

HYDRO26%

THERMAL52%

NUCLEAR2%

OTHERS12%

IMPORTS8%

SOURCE IN MW IN %HYDRO 6055 26

THERMAL 12095 52NUCLEAR 588 2OTHERS 2875 12IMPORTS 1759 8

TOTAL 23372 100

Page 81: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

GRAPH G5

66

0.01

99.9

2

0.07

6.37

93.6

1

0.02 1.

9198

.06

0.03 0.

2898

.36

1.36 0.06

99.0

3

0.91

0.00

94.3

8

5.62

0.00

97.4

7

2.53

0.12

98.2

4

1.64

0.20

99.7

5

0.05

0.08

99.8

7

0.05

8.55

91.3

9

0.06

10.2

489

.68

0.08

0.00

10.00

20.00

30.00

40.00

50.00

60.00

70.00

80.00

90.00

100.00

IN %

--->

Apr-05 May-05 Jun-05 Jul-05 Aug-05 Sep-05 Oct-05 Nov-05 Dec-05 Jan-06 Feb-06 Mar-06MONTHS --->

FREQUENCY SPECTRUM FOR 2005 - 06

< 49 HZ 49 - 50.5 HZ > 50.5 HZ

Page 82: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

GRAPH-G6/1

67

LOAD DURATION CURVE OF SOUTHERN REGION 2005 - 2006

11500

12500

13500

14500

15500

16500

17500

18500

19500

20500

21500

22500

23500

0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100

% OF TIME --->

DEM

AN

D M

ET IN

MW

--->

40

45

50

55

60

65

70

75

80

85

90

95

100

IN %

--->

Page 83: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

GRAPH-G6/2LOAD DURATION CURVE 2005 - 2006

ANDHRA PRADESH

3500390043004700510055005900630067007100750079008300

0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100

% OF TIME --->

DEM

AN

D M

ET IN

MW

--->

404550556065707580859095100

IN %

--->

KARNATAKA

1200

1600

2000

2400

2800

3200

3600

4000

4400

4800

5200

5600

0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100

% OF TIME --->

DEM

AN

D M

ET IN

MW

--->

34

40

46

52

58

64

70

76

82

88

94

100

IN %

--->

KERALA

700

900

1100

1300

1500

1700

1900

2100

2300

2500

2700

0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100

% OF TIME --->

DEM

AN

D M

ET IN

MW

--->

30

37

44

51

58

65

72

79

86

93

100

IN %

--->

TAMIL NADU

32003600400044004800520056006000640068007200760080008400

0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100

% OF TIME --->

DEM

AN

D M

ET IN

MW

--->

35404550556065707580859095100

IN %

--->

68

Page 84: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

GRAPH G7

69

FREQUENCY DURATION CURVE 2005-06

48.00

48.50

49.00

49.50

50.00

50.50

51.00

0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95

% OF TIME --->

FREQ

UEN

CY

IN H

Z ---

>

Page 85: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

GRAPH G8/1

70

LOAD CURVE FOR MAXIMUM DEMAND DAY 2005-06(29-MAR-2006)

20000

20500

21000

21500

22000

22500

23000

23500

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

HOUR ---->

DEM

AN

D IN

MW

--->

Page 86: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

GRAPH G8/2

71

LOAD CURVE FOR MINIMUM DEMAND DAY 2005-06 (02-NOV-2005)

10000

11000

12000

13000

14000

15000

16000

17000

18000

19000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

HOUR ---->

DEM

AN

D IN

MW

--->

Page 87: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

GRAPH G9/1

RESERVOIR GRAPHS OF ANDHRA PRADESH DURING 2002-03, 2003-04, 2004-05 & 2005-06

ENERGY STORED AT JALAPUT RESERVOIR

0

100

200

300

400

500

600

APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR

MONTHS --->

ENER

GY

IN M

Us

--->

2002-03 2003-04 2004-05 2005-06

LEVELS RECORDED AT JALAPUT RESERVOIR

815

820

825

830

835

840

APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR

MONTHS --->

LEVE

L IN

MET

ERS

--->

2002-03 2003-04

2004-05 2005-06

Full Reservoir Level Minimum Draw Down Level

LEVELS RECORDED AT SRISAILAM RESERVOIR

210

220

230

240

250

260

270

280

APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR

MONTHS --->

LEVE

L IN

MET

ERS

--->

2002-03 2003-04

2004-05 2005-06

Full Reservoir Level Minimum Draw Down Level

LEVELS RECORDED AT N'SAGAR RESERVOIR

140145150155160165170175180185

APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR

MONTHS --->

LEVE

L IN

MET

ERS

--->

2002-03 2003-04

2004-05 2005-06

Full Reservoir Level Minimum Draw Down Level

72

Page 88: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

GRAPH G9/2

RESERVOIR GRAPHS OF KARNATAKA DURING 2002-03, 2003-04 , 2004-05 & 2005-06

LEVELS RECORDED AT LINGANAMAKKI RESERVOIR

510515520525530535540545550555560

APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR

MONTHS --->

LEVE

L IN

MET

ERS

--->

2002-03 2003-04

2004-05 2005-06

Full Reservoir Level Minimum Draw Down Level

ENERGY STORED AT LINGANAMAKKI RESERVOIR

0

500

1000

1500

2000

2500

3000

3500

4000

4500

5000

APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR

MONTHS --->

ENER

GY

IN M

Us

--->

2002-03 2003-04 2004-05 2005-06

LEVELS RECORDED AT SUPA RESERVOIR

480490500510520530540550560570

APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR

MONTHS --->

LEVE

L IN

MET

ERS

--->

2002-03 2003-04

2004-05 2005-06

Full Reservoir Level Minimum Draw Down Level

ENERGY STORED AT SUPA RESERVOIR

0

500

1000

1500

2000

2500

3000

APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR

MONTHS --->

ENER

GY

IN M

Us

--->

2002-03 2003-04 2004-05 2005-06

73

Page 89: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2004-05

GRAPH G9/3

RESERVOIR GRAPHS OF KERALA DURING 2002-03, 2003-04 , 2004-05 & 2005-06

LEVELS RECORDED AT IDDUKKI RESERVOIR

680690700710720730740750760770780

APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR

MONTHS --->

LEVE

L IN

MET

ERS

--->

2002-03 2003-04

2004-05 2005-06

Full Reservoir Level Minimum Draw Down Level

ENERGY STORED AT IDDUKKI RESERVOIR

100

300

500

700

900

1100

1300

1500

1700

1900

2100

APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR

MONTHS --->

ENER

GY

IN M

Us

--->

2002-03 2003-04 2004-05 2005-06

LEVELS RECORDED AT KAKKI RESERVOIR

880

900

920

940

960

980

1000

APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR

MONTHS --->

LEVE

L IN

MET

ERS

--->

2002-03 2003-04

2004-05 2005-06

Full Reservoir Level Minimum Draw Down Level

ENERGY STORED AT KAKKI RESERVOIR

0

100

200

300

400

500

600

700

800

900

APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR

MONTHS --->

ENER

GY

IN M

Us

--->

2002-03 2003-04 2004-05 2005-06

74

Page 90: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

GRAPH G9/4

75

RESERVOIR GRAPHS OF TAMIL NADU DURING 2002-03, 2003-04 , 2004-05 & 2005-06

ENERGY STORED AT NILGIRIS RESERVOIR

0

200

400

600

800

1000

1200

1400

1600

APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR

MONTHS --->

ENER

GY

IN M

Us

--->

2002-03 2003-04 2004-05 2005-06

Page 91: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009
Page 92: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

EXHIBIT – E 1

NUCLEAR STATION

NARENDRA

MAHABOOB NAGAR

CHITTOOR

VEMAGIRI

GVKGMR

VIJAYAWADA

GAZUWAKA

HYDERABAD

RAICHUR

GOOTY

BANGALORE

SALEM

UDUMALPET

TRICHUR

MADURAI

TRICHY

MADRAS

NEYVELI

GUTTUR

KAIGA

RSTPP

BHADRAVATI

MUNIRABAD

P

P

P

P

P

KOLAR

TALCHER

JEYPORE

HOSUR

SSLMM

MMDP

TRIVANDRUM

NELLORE

NELAMANGALA

KALPAKKA

SIMHADRI

HIRIYUR

TALGUPPA

KADAPA

1000 MW HVDC BACK TO BACK LINK

2000 MW HVDC BIPOLE

500 KV HVDC LINE

400 KV LINE POWERGRID

400 KV LINE APTRANSCO

400 KV LINE KPTCL

400 KV LINE OPERATED AT 220 KV

THERMAL GENERATING STATION

NEYVELI TPS – 1 (EXP)

400KV SUB-STATION

MAPS

HOODY

KURNOOL

KHAMMAM

N’SAGAR

76

Page 93: SOUTHERN REGIONAL LOAD DESPATCH CENTRE · southern regional load despatch centre  2005 – 06 29, race course cross road, bangalore – 560 009

SRLDC ANNUAL GRID REPORT 2005-06

RAMAGUNDAM

HYDERABAD

N'SAGAR

KHAMMAM

NUNNA

CUDDAPAH

GOOTY

RAICHUR

HOODY

MADRAS

BANGALORE

NEYVELI

SALEM

MUNIRABAD

UDUMALPET

TRICHY

MADURAI

THRISSUR

MMD'PALLI

KURNOOL

80 80

63

63

63

63

63

63

63 63(AP)

TO JEYPORE

NELMANGALA

GUTTUR

KALPAKA

CH’PUR

~

~ ~

~

SRISAILAM

NELLORE

KOLAR

HOSUR

63

6363

63

TALAGUPPA

NEYVELI TS-I (Exp)

HIRIYUR

63

63

63 50

63

50

50

50

50

5050

50 50

5050

50

50

5050

50

63

5050

50 5050

50

50

50

50

50

50

50

5050

50

5050

50 50

50

50

50

50 50

- LINE REACTOR

- LINE REACTOR CONVERTABLE INTO BUS REACTOR

- BUS REACTOR

50

5050

50

TRIVANDRUM

MB’NAGARNARENDRA

KAIGA

5050

SIMHADRI

VEMAGIRI

(178)

(178)

(201)

(195

) (12)

(187

)

(267

)

(197)(197)

(147)(147)

(201)

(227)

(108

)

(161)

(110

)

(201)

(73)

(348

)

(201)

(12)GAZUWAKA

(8)

(21)

(140)

(115)

(155)

(158)

(145)

(223)

(341)

(341)

(103)

(84)

(151

)

(108

)

(173

)

(69)

(51)

(206)

(107)(1

27)

(175)(164)

(7)

(138

)

(162)

(130

)

(130

)

(127)

(216)

(267

) (189)

(220)

(364)

(317)

(315)

(315)

(277)

(279)

(190)

(190)

(74)(184)

(308

)(3

05)

(256

)

(172

)

(300

)

(145

)

(106)

(98)

(181)

(182

)

(179)

(151

)

(130

)

(130

) - FIXED SERIES COMPENSATOR

400KV NETWORK IN SR WITH LINES AND BUS REACTORS

CHITTOOR

(158)

(216)

GVK

(7)

GMR

(2)

- SWITCHABLE LINE REACTOR

EXHIBIT – E 2

77