POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003

Upload: avis-hoover

Post on 13-Dec-2015

219 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003

POWERGRIDNORTHERN REGONAL LOAD DESPATCH CENTRE

SUBMISSION IN RESPECT OF

PETITION NO. 35/2003

DATED 30.09.2003

Page 2: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003
Page 3: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003

Period for which petition has been filed

• Total period referred in petition : 21st April 03 to 18th May 03

• Specific days when generation was affected due to tripping of

--400kV Uri-Wagoora D/C : 25th April,03 and 7th May,03

(No anomaly )

--220kV Kishenpur –Pampore ckt./ckts. : 26th April-4th May,03 and 11thMay-13th May,03

(Specific Problem : 220 kV K-P ckt.-I out due to jumper snapping)

Page 4: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003
Page 5: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003
Page 6: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003
Page 7: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003
Page 8: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003
Page 9: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003

Total collapse of power supply in valley on 26.04.2003:

Trippings Revivals 1422 hrs. 1451 hrs. 1458 hrs. 1520 hrs.

1914 hrs. 2127 hrs. 2148 hrs. 2258 hrs. 2329 hrs. 0616 hrs.(next day)

Page 10: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003

The clause referred to by the petitioner:

(CERC Notification 26th March 2001 Clause 3.13(xii))

In the event of bottleneck in evacuation of power due to any constraint, outage, failure or limitation in the transmission system, associated switchyard and substations owned by CTU (as certified by RLDC) necessitating reduction in generation, RLDC shall revise the schedules which become effective from 4th time block, counting the time block in which the bottleneck in evacuation of power has taken place to be the first one. Also during the first, second and third time blocks of such an event, the scheduled generation of the station shall be deemed to have been revised to be equal to the actual generation and also the scheduled drawals of the beneficiaries shall be deemed to have been revised to be equal to their actual drawals.

Page 11: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003
Page 12: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003
Page 13: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003
Page 14: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003
Page 15: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003
Page 16: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003
Page 17: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003

CERC Notification dated March 26th 2001 Clause 3.13.vi

Based on the requisitions given by the beneficiaries and taking into account technical limitations on varying the generation and also taking into account transmission system constraints, if any, RLDC shall prepare the economically optimal generation schedules and drawl schedules and communicate the same to generator and the beneficiaries.

RLDC shall also formulate the procedure for meeting contingencies both in the long run and in the short run (daily scheduling).

Page 18: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003
Page 19: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003
Page 20: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003
Page 21: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003
Page 22: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003
Page 23: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003
Page 24: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003
Page 25: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003

CERC Notification dated 26th March 2001 clause 3.13.xiii

In case of any grid disturbance, schedule generation of all the generating stations and schedule drawal of all the beneficiaries shall be deemed to have been revised to be equal to their actual generation/drawal for all the time blocks affected by the grid disturbance. Certification of grid disturbance and its duration shall be done by RLDC.

Page 26: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003
Page 27: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003
Page 28: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003
Page 29: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003
Page 30: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003
Page 31: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003

Chronology of Events

• RLDC’s instruction issued to Uri HEP formalizing

contingent operation mode (copy to NREB Sectt.) 29th April 2003

• SEM data with specific instructions to NREB Sectt. for

treatment of Uri generation during contingent condition 2nd May,2003

• NHPC Letter to NREB Sectt. 8th May,2003(Regarding above UI A/C)

• NREB Sectt. Reply to NHPC 14th May, 2003

• NRLDC Letter to NREB Sectt. 15th May, 2003(to amend UI accounts)

• UI Accounts issued by NREB Sectt. 7th May, 2003(for period 21st-27th April, 2003)

Page 32: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003

(Petitioner’s Rejoinder Para 11(v), Page-19)

Rightly Applicable Clause - IEGC Clause 7.5.13

On completion of the operating day, by 2400 hours, the schedule finally implemented during the day (taking into account all before-the-fact changes in dispatch schedule of generating stations and drawal schedule of the states) shall be issued by RLDC.

REGARDING PETITIONER’S (MISPLACED) STATEMENT ABOUT RLDC’S RESPONSIBILITY

Page 33: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003

Attempts To Resolve the Issue

•Matter was discussed in NREB Board Meeting on 14th June, 2003

• It was agreed to resolve the issue by mutual discussions between NREB Sectt., NRLDC, PDD J&K and NHPC

• NHPC however did not attend the meeting held in NREB on 16th June, 2003.

Page 34: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003
Page 35: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003

REAL ISSUES

•Transmission constraints of specific and special kind.

• Solution as agreed between NRLDC, PDD J & K and Uri HEP was

formalized with a copy to NREB Sectt.

- to avoid spillage

- to maximize generation even under contingency

- to maintain secure power supply in Kashmir valley.

• The above mechanism worked satisfactorily and in a failsafe manner.

- no element of protest from any corner.

Page 36: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003

REAL ISSUES (contd.)

• Treatment of weekly energy accounting was done by NREB Sectt.

in contrast to NRLDC memo.

- No reference or discussion made by NREB Sectt. with NRLDC.

• Petitioner now appears to be longing for undeserved UI earning and has

filed a misdirected petition.

- any concession or let up would lead to possible spillage at the station and also earning of undeserved UI: leading to national

loss and bad practices in the sector.

• The special mechanism was repeated by NRLDC in the weekly

transmittal of SEM energy data to NREB Sectt.

- aim was to avoid imposition of an undue UI.

Page 37: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003

THANK YOU

Page 38: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003

EXTRACTS FROM REJOINDER BY NHPC CONTAINING MISDIRECTED WORDS

Para 1, Page 5 :AT THE OUTSET IT IS SUBMITTED THAT THE RESPONDENT NO. 2 HAS FAILED TO COME WITH CLEAN HANDS BEFORE THIS HON’BLE COMMISSION.

 Para 2 (iv), Page 6 :

THAT THE FAILURE ON THE PART OF RESPONDENT NO. 2 TO REVISE THE SCHEDULE AND TO SUBMIT DATA TO THE NREB ACCORDING TO THE REVISED SCHEDULE, WAS DELIBERATE AND WILLFUL.

Page 39: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003

EXTRACTS FROM REJOINDER BY NHPC CONTAINING MISDIRECTED WORDS

Para 2 (v), Page 6-7 CONSEQUENT TO THE WILLFUL, DELIBERATE DISREGARD OF THE ORDERS OF THIS HON’BLE COMMISSION AND DISREGARD OF STATUTORY OBLIGATIONS, UI CHARGES HAVE BEEN WRONGLY AND ILLEGITIMATELY IMPOSED ON THE PETITIONER AS A RESULT OF THE LAPSES ON THE PART OF THE RESPONDENT NOS. 1 & 2, FOR WHICH THE PETITIONER MUST BE RESTITUTED.

 

Para 3, Page 7:IT IS RESPECTFULLY SUBMITTED THAT THE WILLFUL, DELIBERATE AND CONTUMACIOUS DEFIANCE AND DISREGARD AND VIOLATION OF THE ORDERS PASSED BY THIS HON’BLE COMMISSION MUST NOT BE ALLOWED TO GO UNHEEDED. …………..THE PRESENT PETITION ALSO RAISES A MUCH LARGER ISSUE NAMELY, THE BLATANT AND REPEATED DISREGARD OF STATUTORY AND PUBLIC OBLIGTIONS BY A MONOPOLISTIC PUBLIC UTILITY.

Page 40: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003
Page 41: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003

Wrong Interpretation of clauses by NHPC regarding

Post-Facto revision of schedule Extracts from Rejoinder from NHPC, Page-19,

Para 11(V):

NRLDC HAS WILLFULLY NOT REPLACED THE SCHEDULE OF URI POWER STATION DURING THE PERIOD OF TRANSMISSION CONSTRAINT BY THE ACTUAL AGENERATION AS RECORDED BY THE SEMs, THOUGH THE SAME HAS BEEN MENTIONED IN THE STATUS REPORT BY NRLDC.

  THE ABOVE ACTION CONFIRMS THAT THE RESPONDENT HAS WILLFULLY NOT IMPLEMENTED THE VARIOUS PROVISIONS OF THE ORDERS OF THE HON’BLE COMMISSION AND PROVISIONS OF IEGC, WHICH NRLDC SHOULD HAVE DONE EX-POST FACTO OR WHEN THE SAME CAME INTO ITS KNOWLEDGE AS PER THE PROVISIONS MENTIONED IN PARA–10 (B)(iv) AND PARA-10(C)(ii) OF THE PETITION.

NON-REVISION OF THE SCHEDULE BY THE RESPONDENT HAS RESULTED INTO WRONG IMPOSITION OF UI AMOUNT ON THE PETITIONER.

Page 42: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003

Wrong Interpretation of clauses by NHPC regarding Post-Facto revision of schedule(contd..)

 Para 10B(iv) of petition ( para 3.13(xvii) of CERC Notification):

FOR ANY REVISION OF SCHEDULED GENERATION, INCLUDING POST FACTO DEEMED REVISION, THERE SHALL BE A CORRESPONDING REVISION OF SCHEDULED DRAWALS OF THE BENEFICIARIES.

 Para 10C(ii) of petition ( IEGC clause 7.5 (15) on scheduling):

THE PROCEDURE FOR SCHEDULING AND THE FINAL SCHEDULES ISSUED BY RLDC SHALL BE OPEN TO ALL CONSTITUENTS FOR ANY CHECKING / VERIFICATION, FOR A PERIOD OF 20 DAYS. IN CASE ANY MISTAKE / OMISSION IS DELECTED, THE RLDC SHALL FORTHWITH MAKE A COMPLETE CHECK AND RECTIFY THE SAME.

Page 43: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003

SCHEDULE VIS-À-VIS ACTUAL GENERATION AT URI

Date Schedule Actual Date Schedule Actual

21.04.2003 115.20 115.2201.05.2003 115.20 66.7722.04.2003 115.20 115.2802.05.2003 115.20 44.5923.04.2003 115.20 115.2903.05.2003 115.20 96.9824.04.2003 115.20 115.2704.05.2003 114.90 84.2725.04.2003 110.62 110.4905.05.2003 115.20 115.5726.04.2003 108.91 83.8906.05.2003 115.20 115.3627.04.2003 115.20 41.6707.05.2003 112.47 112.8028.04.2003 115.20 99.8508.05.2003 112.47 112.8029.04.2003 115.20 96.5309.05.2003 115.20 115.69 30.04.2003 115.20 92.1310.05.2003 115.20 115.48

11.05.2003 112.33 100.9312.05.2003 115.30 93.04 13.05.2003 112.40 88.4815.05.2003 115.20 115.68 16.05.2003 115.20 115.56 17.05.2003 115.20 115.63 18.05.2003 115.20 115.52

Page 44: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003

STATE’S SCHEDULE vs DRAWAL

Page 45: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003

STATE’S SCHEDULE vs DRAWAL (contd.)

Page 46: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003

Transmission system of Uri & Dulhasti

• Original schedule of Dulhasti HEP : July 1994

• Transfer of transmission works from : 1992 NHPC to POWERGRID

• Approval of contingency evacuation : Dec 1992 for Dulhasti (400 kV Wagoora-Kishenpur D/C line deferred temporarily)

Dulhasti generation project gets delayed indefinitely warranting review of contingency transmission system.

Page 47: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003

Transmission system of Uri & Dulhasti (contd/-)

• Commissioning of Uri HEP and its : April-May 1997 transmission system

• Fresh feasibility report for Dulhasti : August 1996 transmission system submitted to CEA

• Techno-Economic Clearance received : April 2000

• Investment approval received : July 2002

• Commissioning schedule : July 2006

Page 48: POWERGRID NORTHERN REGONAL LOAD DESPATCH CENTRE SUBMISSION IN RESPECT OF PETITION NO. 35/2003 DATED 30.09.2003