  • 8/2/2019 Subhadeep Notes

    1/18

    CVISN Planning Workshop

    The Johns Hopkins University Applied Physics Laboratory

    Day 0, P2 Work Breakdown Structure Review & Prep!

    3/19/2012 8:37 AM P2 - 1

    Session Outline

    What is a WBS and where is it useful? What is successive decomposition?

    How is the WBS used on a program?

    How can I tell if I have a good WBS?

    Numbering notation.

    Examples.

    Common errors.

    Outline

  • 8/2/2019 Subhadeep Notes

    2/18

    CVISN Planning Workshop

    The Johns Hopkins University Applied Physics Laboratory

    Day 0, P2 Work Breakdown Structure Review & Prep!

    3/19/2012 8:37 AM P2 - 2

    Where is WBS Useful?

    Rocket Science?

    Brain Surgery?

    CVISN?

  • 8/2/2019 Subhadeep Notes

    3/18

    CVISN Planning Workshop

    The Johns Hopkins University Applied Physics Laboratory

    Day 0, P2 Work Breakdown Structure Review & Prep!

    3/19/2012 8:37 AM P2 - 3

    The Work Breakdown Structure Is...

    Product-oriented hierarchy of goods and services.

    Form: inverted tree; or indented list.

    Visualizing the entire project.

    Common framework for planning and control.

    Vehicle to divide work into tasks that are:

    Manageable

    Independent

    Measurable

    Integratable

    Graphically displays entire project. Clear definition of all effort.

    Top Assembly Drawing of the project.

    Product Breakdown Structure or Project Breakdown Structure moreapt name! Or perhaps Work Buildup Structure.

    WBS Definition

  • 8/2/2019 Subhadeep Notes

    4/18

    CVISN Planning Workshop

    The Johns Hopkins University Applied Physics Laboratory

    Day 0, P2 Work Breakdown Structure Review & Prep!

    3/19/2012 8:37 AM P2 - 4

    and so on, while it makes sense

    more decomposition

    more decomposition

    Create a WBS via RecursiveProduct-Oriented Decomposition

    (Call This Level 1)

    Principal Product Associated SupportProduct Level 2

    Associated SupportService Level 2

    Principal Product

    Sub-Product Associated SupportProduct Level 3

    Associated SupportService Level 3

    Sub-Product

    Sub-Sub-Product(s)

    Associated SupportProduct Level 4

    Associated SupportService Level 4

    WBS Construction 2000-01-26

  • 8/2/2019 Subhadeep Notes

    5/18

    CVISN Planning Workshop

    The Johns Hopkins University Applied Physics Laboratory

    Day 0, P2 Work Breakdown Structure Review & Prep!

    3/19/2012 8:37 AM P2 - 5

    Example: Break Down 100% (1 of 2)

    100%

    Decomposition Summation

    2000-01-26

  • 8/2/2019 Subhadeep Notes

    6/18

    CVISN Planning Workshop

    The Johns Hopkins University Applied Physics Laboratory

    Day 0, P2 Work Breakdown Structure Review & Prep!

    3/19/2012 8:37 AM P2 - 6

    Example: Break Down 100% (2 of 2)

    and so on, while it makes sense

    more decomposition

    more decomposition

    20% 10%10% 60%

    25% 10%5% 20%

    20% 3%2%

    100%

    Summation 2000-01-26

  • 8/2/2019 Subhadeep Notes

    7/18

    CVISN Planning Workshop

    The Johns Hopkins University Applied Physics Laboratory

    Day 0, P2 Work Breakdown Structure Review & Prep!

    3/19/2012 8:37 AM P2 - 7

    Program IntegrationActivity Plan

    Project Integration Plan

    Product Activity Plan

    CVISNProgram

    CI

    Credentialing

    Product Activity Plan

    Project Integration PlanSafety

    CVIEW

    Product Activity Plan

    IRP

    Program

    Project

    Product

    MoreDecomposition MoreDecompositionMoreDecomposition

    More

    Decomposition

    More

    Decomposition

    More

    Decomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    Principal Product(s) Associated SupportProducts Level 2

    Associated SupportServices Level 2

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    (Call This Level 1)

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    MoreDecomposition

    By decomposing, eventually.....

    .....you get to activities thatcan be assigned and

    scheduled.

    WBS Construction

  • 8/2/2019 Subhadeep Notes

    8/18

    CVISN Planning Workshop

    The Johns Hopkins University Applied Physics Laboratory

    Day 0, P2 Work Breakdown Structure Review & Prep!

    3/19/2012 8:37 AM P2 - 8

    Example Extended WBS for a Complex Program

    Note the different orientationsfrom top to bottom.

    WBS unfolds and evolves as

    scope and design become known.

    WBS Definition

    The Work to

    be Done!

  • 8/2/2019 Subhadeep Notes

    9/18

    CVISN Planning Workshop

    The Johns Hopkins University Applied Physics Laboratory

    Day 0, P2 Work Breakdown Structure Review & Prep!

    3/19/2012 8:37 AM P2 - 9

    History

    Clinical Exam

    Imaging

    Blood &Tissue Tests

    Likely Diagnosis

    Risk Assessment

    Education of Patient

    Alternative Analysis& Trade-Offs

    Treatment Plan

    1.0 Diagnosis

    Communications AmongTeam

    Patient & TeamPositioning

    (for neurosurgery)

    Acquisition of NeededInstruments & Equipment

    Scheduling of NeededSpecialists

    Practice Run-Throughs

    2.0 Plan forOperation

    Verify Patient Can HandleStress of Surgery

    Stop Drugs that WouldInterfere with Surgery

    3.0 PreoperativePatient Care

    Verify Patient Identity &Location of Surgery

    Anesthesia

    Patient Underthe Knife

    Vital Signs &Fluid-Loss Monitoring

    NeurophysiologicalMonitoring

    (during neurosurgery)

    Maintain Neat & CleanOperative Field

    Wrap-up: VerifySmall Part Count

    (sponge, needle, cottonoid, Michel clips)

    Operative Notes &Chart Updates

    4.0 Execution ofOperation

    Written Care Orders

    Briefing of Recovery Staffby Surgeon

    Vital Signs &Fluid-Loss Monitoring

    NeurophysiologicalMonitoring

    5.0 PostoperativePatient Care

    Follow-up Clinical Visits

    Physical Therapy

    6.0 Long-TermPatient Care

    Surgical TreatmentProject

    WBS for Brain Surgery (tree format)

    Sources:1.Bailey & Lovess Short Practice of Surgery, 22nd Edition, edited by Charles V. Mann, R.C.G.Russell, and Norman S. Williams. Chapman & Hall Medical, 1995. ISBN 0-412-49490-6.

    2. Brain Surgery Complication Avoidance and Management, by Michael L. J. Apuzzo, M.D.Churchill Livingstone, Inc., 1993. ISBN 0-443-08709-1. See Chapter 1, Preoperative and SurgicalPlanning for Avoiding Complications by Robert G. Grossman.

  • 8/2/2019 Subhadeep Notes

    10/18

    CVISN Planning Workshop

    The Johns Hopkins University Applied Physics Laboratory

    Day 0, P2 Work Breakdown Structure Review & Prep!

    3/19/2012 8:37 AM P2 - 10

    Surgical Treatment Project

    1.0 DiagnosisHistory

    General Medical ConditionSpecific ComplaintClerking?? (for elective surgery??)

    Clinical ExamImaging

    Ultrasonography

    Plain Radiography (X-Ray)Computed Tomography (CAT Scan)Magnetic Resonance Imaging (MRI)

    Blood and Tissue TestsLikely DiagnosisRisk AssessmentEducation of Patient (e.g. anatomy)Alternative Analysis & Trade-OffsTreatment Plan

    2.0 Planning of the OperationCommunications Among TeamPatient and Team Positioning (for neurosurgery)Acquisition of Needed Instruments & EquipmentScheduling of Needed SpecialistsPractice Run-Throughs

    3. 0 Preoperative Patient Care

    Verify Patient can Handle Stress of SurgeryStop Drugs that Would Interfere with Surgery

    4.0 Execution of the Operation (Actual Surgery)Verify Patient Identity and Location of SurgeryAnesthesiaPatient Under the Knife

    Real-time Diagnostic BiopsiesTherapeutic Surgery

    Vital Signs and Fluid-Loss MonitoringNeurophysiological monitoring (during neurosurgery)Maintain Neat and Clean Operative FieldWrap-up: Verify Small Part Count (sponge,

    needle, cottonoid, Michel clips)Operative Notes and Chart Updates

    5.0 Postoperative CareWritten Care Orders

    Briefing of Recovery Staff by SurgeonVital Signs and Fluid-Loss MonitoringNeurophysiological Monitoring

    6.0 Long-Term Patient CareFollow-up Clinical VisitsPhysical Therapy

    WBS for Brain Surgery (indented list)

  • 8/2/2019 Subhadeep Notes

    11/18

    CVISN Planning Workshop

    The Johns Hopkins University Applied Physics Laboratory

    Day 0, P2 Work Breakdown Structure Review & Prep!

    3/19/2012 8:37 AM P2 - 11

    WBS is The Basis For......

    Cost estimates and budgets.

    Milestones & schedules.

    Responsibility assignment.

    Allocation of resources.

    Schedule horizontal and vertical traceability.

    Risk analysis.

    Concurrence of participants.

    Integrating the total project effort.

    Summarizing costs, schedules, performance.

    Forcing the Project Manager to think through all elementsof the project.

    WBS Definition

  • 8/2/2019 Subhadeep Notes

    12/18

    CVISN Planning Workshop

    The Johns Hopkins University Applied Physics Laboratory

    Day 0, P2 Work Breakdown Structure Review & Prep!

    3/19/2012 8:37 AM P2 - 12

    Tests for a Good WBS:

    Product-oriented hierarchy of goods and services.

    Top level may be dictated by contract.

    Basis for cost estimating, project organization, assigning responsibility,task scheduling, and status reporting.

    Basis for understanding and communication.

    Each element should be manageable.

    Based on System Engineering: interfaces are minimized; units are

    stand-alone testable. Eliminating one product element will delete the associated costs.

    Segregate recurring from non-recurring costs.

    Identifies and defines all effort to be expended: correlation of lowerlevels to specification tree, contract line items, data items, and work

    statement tasks. Useful! Reflects the way the work is managed and performed.

    Sufficiently low level to establish adequate visibility and confidence forcost estimating, project planning, and project control.

    Technical/cost/schedule can be integrated at every level for each

    element. WBS Definition

  • 8/2/2019 Subhadeep Notes

    13/18

    CVISN Planning Workshop

    The Johns Hopkins University Applied Physics Laboratory

    Day 0, P2 Work Breakdown Structure Review & Prep!

    3/19/2012 8:37 AM P2 - 13

    WBS Levels & Numbering Notation

    1. Project Management

    2.1 Magnetometer

    2.2 Spectrograph

    2. Science Instruments

    3.1 Propulsion Subsystem

    3.2 Attitude Control Subsystem

    3.3.1.1 Processor Card

    3.3.1.2 Memory Card

    3.3.1 C&DH Hardware

    3.3.2 C&DH Software

    3.3.3 Subsystem Integration

    3.3 Command & Data Handling Subsystem

    3. Spacecraft Bus 4. Ground Support Equipment

    Satellite Mission Project

    Satellite Mission Project1. Project Management2. Science Instruments

    2.1 Magnetometer

    2.2 Spectrograph

    3. Spacecraft Bus

    3.1 Propulsion Subsystem3.2 Attitude Control Subsystem

    3.3 Command & Data Handling Subsystem

    3.3.1 C&DH Hardware3.3.1.1 Processor Card3.3.1.2 Memory Card

    3.3.2 C&DH Software

    3.3.3 Subsystem Integration

    4. Ground Support Equipment WBS Definition

    Level 1

    (Level 1)

    Level 2

    (Level 2)

    Level 3

    (Level 3)

    Level 4

    (Level 4)

    Level 5

    (Level 5)

  • 8/2/2019 Subhadeep Notes

    14/18

    CVISN Planning Workshop

    The Johns Hopkins University Applied Physics Laboratory

    Day 0, P2 Work Breakdown Structure Review & Prep!

    3/19/2012 8:37 AM P2 - 14

    Exercise

    Scenario Exercise

    Imagine you are working at the

    Atlantic Pacific Sea VisionFountain Pen Manufacturing Company

    Lets develop a WBS for our proposedmechanical pencil project.

    Motto: Yesterdays Technology Solving

    Todays Problems Tomorrow

  • 8/2/2019 Subhadeep Notes

    15/18

    CVISN Planning Workshop

    The Johns Hopkins University Applied Physics Laboratory

    Day 0, P2 Work Breakdown Structure Review & Prep!

    3/19/2012 8:37 AM P2 - 16

    Where Does the Work Get Done?!!

    Satellite Mission Project1. Project Management2. Science Instruments3. Spacecraft Bus

    3.1 Propulsion Subsystem3.2 Attitude Control Subsystem3.3 Command & Data Handling Subsystem

    3.3.1 C&DH Hardware3.3.1.1 Processor Card

    3.3.1.1.1 Engineering Design3.3.1.1.2 Layout & Package Design3.3.1.1.3 Fabrication3.3.1.1.4 Assembly & Test

    3.3.2 C&DH Software3.3.2.1 Command Parsing Module

    3.3.2.1.1 Architectural Design

    3.3.2.1.2 Detailed Design3.3.2.1.3 Coding3.3.2.1.4 Unit Test

    3.3.3 Subsystem Integration3.3.3.1 Integration Plan3.3.3.1 Integrate Instruments with Bus

    4. Ground Support Equipment WBS Definition

    Product-Oriented

    Nouns

    Process-Oriented

    Here is real work!

    Verbs

  • 8/2/2019 Subhadeep Notes

    16/18

    CVISN Planning Workshop

    The Johns Hopkins University Applied Physics Laboratory

    Day 0, P2 Work Breakdown Structure Review & Prep!

    3/19/2012 8:37 AM P2 - 17

    Typical WBS for a State CVISN Program

    WBS Sample

    1.1 Planning &Coordination

    1.2 CarrierCoordination

    1.3 Showcases

    & Outreach

    1.4 RegionalCoordination

    1.5 O & M Planning

    1.6 Training

    1.7 Policy

    1.8 Subcontract &Procurement Mgt

    1. ProgramManagement

    2.1 SystemRequirements

    Definition

    2.2 SystemDesign

    2.3 Architecture

    Conformance

    2.4 SystemIntegrationand Test

    2.5 InteroperabilityTesting

    2. SystemEngineering &

    Integration

    3.1 Proj Mgt

    3.2 Sys Engr &Integration

    3.3 Subcontract &

    Procurement Mgt

    3.4 CV InformationExchange

    Window (CVIEW)

    3.5 ASPEN

    3.6 SAFETYNET

    3.7 Builds 1...n

    3. SafetyProject

    4.1 Proj Mgt

    4.2 Sys Engr &

    4.3 Subcontract &

    Procurement Mgt

    4.4 InternationalRegistrationPlan (IRP)

    4.5 InternationalFuel Tax

    Agreement (IFTA)

    4.6 CredentialingInterface

    4.7 Motor CarrierHome Page &

    Web Credentialing

    4.8 Carrier CredSystems

    (CAT or module)

    4.9 Intra-StateRegistration

    4.10 Builds 1...n

    4. CredentialsProject

    5.1 Proj Mgt

    5.2 Sys Engr &Integration

    5.3 Subcontract &

    Procurement Mgt

    5.4 RoadsideOperations

    5.5 Screening

    5.6 Site Mods

    5.7 CarrierE-ScreeningEnrollment

    5.8 Builds 1...n

    5. E-ScreeningProject

    6.1 Self-Evaluation

    6.2 National Evaluation(Funded Separately)

    6. Evaluation

    StateCVISN Program

    2001-06-14

    Level 1

    Level 2

    Level 3

  • 8/2/2019 Subhadeep Notes

    17/18

    CVISN Planning Workshop

    The Johns Hopkins University Applied Physics Laboratory

    Day 0, P2 Work Breakdown Structure Review & Prep!

    3/19/2012 8:37 AM P2 - 18

    Elements Not to Include in WBS

    Do not use the structure of the contractors organization as the basis

    of a WBS. At the top levels do not begin by decomposing into the functions or

    cost categories associated with developing those products.

    Adapted fromDepartment of Defense HandbookWork Breakdown Structure, MIL-HDBK-881.Available at:http://www.acq.osd.mil/pm/newpolicy/wbs/wbs.html.

    Includes examples from the defense industry.

    Program

    Design Build Test

    Hardware Software

    What not to do!

    Do not use generic names -- use actual system names andnomenclature.

    No disembodied software -- software developed to reside on specificequipment must be identified as a subset of that equipment.

    WBS Definition

  • 8/2/2019 Subhadeep Notes

    18/18