technical specifications of roads
TRANSCRIPT
-
8/12/2019 Technical Specifications of Roads
1/97
TECHNICAL SPECIFICATIONS OF ROADS
September 2010
i
-
8/12/2019 Technical Specifications of Roads
2/97
Table of Contents
1 ................................................................................................ 1-1SUMMARY OF WORK
2 ................................................................................ 2-1DEMOLITION AND REMOVAL2.1 ................................................................................................................... 2-1General2.2 ......................................................................................................... 2-1Requirements2.3 .............................................................................................................. 2-3Submittals2.4 ............................................................................................................... 2-4Inspection2.5 ............................................................................................................. 2-4Preparation2.6 ............................................................................................................. 2-5Demolition2.7 ......................................................................................... 2-7Disposition of materials2.8 ................................................................................................. 2-7Cleanup and repair
3 ........................................... 3-1GENERAL EARTHWORK AND SITE PREPARATION3.1 ................................................................................................................... 3-1General3.2 ......................................................................................................... 3-1Requirements3.3 .............................................................................................................. 3-3Submittals3.4 ....................................................................................................... 3-4Quality control3.5 .............................................................................. 3-6Delivery, storage and handling3.6 .................................................................................................... 3-7Site investigation3.7 ................................................................................................................. 3-9Products
3.7.1 .............................................................................................. 3-9Existing ground3.7.2 .................................................................................................... 3-9Fill material3.7.3 ............................................................................................................ 3-10Water
3.8 ............................................................................................................. 3-10Execution3.8.1 ..................................................................................................... 3-10Protection3.8.2 ........................................................................................................ 3-10Clearing3.8.3 ......................................................................... 3-12Existing ground preparation3.8.4 ............................................................................. 3-13Placement of fill material
4 ........................................................................................ 4-1ROADS AND FOOTPATHS
4.1 ............................................................................................................. 4-1Definitions4.2 ............................................................................................ 4-2General Requirements4.3 .............................................................................................................. 4-3Submittals
4.3.1 .......................................................................................................... 4-3Samples4.3.2 .......................................................................................... 4-3Method Statement4.3.3 ............................................................................................... 4-4Shop Drawings4.3.4 ......................................................................................................... 4-5Mock-up
4.4 ...................................................................................................... 4-6Quality Control4.5 ............................................................................. 4-8Delivery, Storage and Handling4.6 ................................................................................................................. 4-9Products
4.6.1 ........................................................................................................ 4-9Subgrade4.6.2 ......................................................................................................... 4-9Rock fill4.6.3 ............................................................................... 4-10Pre-cast Concrete Curbs4.6.4 ................................................................................... 4-12In-situ concrete curbs4.6.5 ........................................................................... 4-13Interlocking paving blocks
ii
-
8/12/2019 Technical Specifications of Roads
3/97
iii
4.6.6 ....................................................................................... 4-14Granular Sub Base4.6.7 ................................................................................... 4-16Aggregate Road Base4.6.8 .................................................................... 4-18Materials for Asphalt Concrete4.6.9 .......................................................................................... 4-21Asphalt Concrete4.6.10 ................................................................................... 4-29Prime and Tack coats
4.6.11 ............................................................................... 4-29Road marking materials4.6.12 ................................................................................................. 4-30Traffic signs
4.7 ............................................................................................................. 4-35Execution4.7.1 ........................................................................................... 4-35Placement of fill4.7.2 ................................................................................... 4-38Subgrade preparation4.7.3 .................................................................................................. 4-39Compaction4.7.4 ........................................................... 4-41Installation of precast concrete curbs4.7.5 ......................................................................... 4-43In-situ concrete curb laying4.7.6 ........................................................................................ 4-43Granular sub-base4.7.7 .................................................................................... 4-44Aggregate road-base4.7.8 ............................................................. 4-47Placement of asphalt paving course4.7.9 ........................................................ 4-67Application of road marking materials4.7.10 .......................................................................................... 4-68Erection of signs4.7.11 ...................................................................................................... 4-69Footpaths4.7.12 ......................................................... 4-69Installation of concrete paving blocks4.7.13 ................................................. 4-71Lifting and relaying concrete block paving
-
8/12/2019 Technical Specifications of Roads
4/97
1 SUMMARY OF WORKThe project includes the upgrades of existing road network as a part of the upgrading of
existing sanitary and storm sewers in a city. The contractor shall supply all supervision,
labors, materials, temporary works, plant, machinery, equipment, parts, tools, supplies,transportation, testing and handling over the infrastructure works and facilities in perfect
working condition.
The contractor should note that there might be other contractors working in the same vicinity
during the contract period. The contractor must consider this and coordinate his work to
minimize any disruptions to others working in the area. Access to the work sites shall be
maintained by the contractor at all times and he shall take all necessary steps to ensure thesafety of persons on the sites. All construction operations and site-established facilities shall
be confined to within the site boundaries as shown on the drawings, unless otherwise
approved by the engineer and the relevant authorities. Following such approvals, all such
areas shall also be designated and treated as included within the site. The contractor shall be
responsible for safeguarding all structures, plant or property near the site and shall provide all
shoring, or supports as may be necessary to preserve their stability.
1-1
-
8/12/2019 Technical Specifications of Roads
5/97
2 DEMOLITION AND REMOVAL
2.1 General
This Section specifies requirements for demolition and removal of structures and includes,
but is not limited to, the following:
1. Complete demolition of designated existing buildings and/or
structures.
2. Removal of existing underground tanks, manholes and pipes
3. Cutting into existing structures to make connections to new and
existing work.
4. Removal of existing protective coatings from concrete surfaces to
permit resurfacing, patching and recoating of surfaces.
5. Arrangement with relevant utility owners for renewal and/or
relocation of their existing services.
6. Removal or salvage of designated mechanical, electrical or other
equipment.
7. Removal from site and disposal of trash, debris, demolished
materials and salvable materials.
8. Removal and disposal of any hazardous material relating to or
associated with demolition or new work.
2.2 Requirements
1. Demolition shall include removal of all below grade structures
foundations, piles and pipes cables, etc and restoration to original
conditions unless otherwise approved by the Engineer.
2. The Contract Drawings are prepared using existing record
drawings and they may not show all items to be removed. The
Contractor shall therefore visit the site as necessary prior to
2-1
-
8/12/2019 Technical Specifications of Roads
6/97
3. Use of explosives shall not be permitted.
4.
Comply with all applicable safety precautions.5. Conform to applicable codes for demolition work, safety of
structures, dust and noise control.
6. Notify affected utility companies, pipeline owners and relevant
authorities before starting work and comply with their
requirements.
7. Obtain required permits from the governing authorities and pay for
all associated licenses, permits and inspections required by these
authorities.
8. Conform to applicable procedures when discovering hazardous or
contaminated materials.
9. Occupancy and use of facilities Client may continue to use process piping, equipment, and treatment
facilities near and adjacent to the areas designated for selective
demolition.
Conduct selective demolition work in a manner that will not interfere
with normal plant operations. This may require temporary facilities to
be constructed as necessary, at no cost to the Client, to comply with
this provision.
Provide at least 72 hours advance notice to the Engineer and Client for
those activities, which affect normal plant operations. No demolition
can be started without prior approval of Engineer and Client.
10. Conditions of facilities requiring demolition All facilities shall be handed over to the Contractor in an as is
condition.
Any preliminary work necessary to permit the main works to start shall
be at the Contractors expense. This may include, but not be limited to,
removal of tanks, pipelines or other structures containing raw or
2-2
-
8/12/2019 Technical Specifications of Roads
7/97
Conditions existing at the beginning of the project will be maintained
by the Client so far as practical; however, the Client makes noguarantee that conditions will be the same when demolition is
performed.
All facilities will continue to be used for their intended purpose until
turned over to the Contractor for rehabilitation.
2.3 Submittals
The Contractor is to prepare a method statement, which shall detail all aspects of the
proposed demolition and associated work. The method statement shall be approved by the
Engineer before any demolition work commences. The method statement shall incorporate at
least the following items:
1. Detailed description of the methods and equipment to be used for each
operation as well as proposed sequence of demolition operations.
2. Safety precautions required to ensure the safety of the workers,
members of the public, and users of adjacent facilities or properties.
3. The controlled demolition, removal and disposal of hazardous
materials.
4. The removal, protection and transportation of salvable materials.
5. Coordination of the demolition work with other work in progress, and
with any existing facility operations.
6. Shut down schedule of equipment and disconnection sequence of the
utilities involved.
7. Accurate record of disconnected services and utilities
8. Videotape of existing conditions prior to demolition.
2-3
-
8/12/2019 Technical Specifications of Roads
8/97
2.4 Inspection
The Contractor shall inspect each area prior to performing any demolition work and record
on videotape existing conditions as well as the condition of surrounding areas, clearly
marking the location, date, time taken and the items which are to be demolished. Theoriginal film and a copy of it must be submitted to the Engineer prior to starting any
demolition works. The Contractor shall ascertain that the property to be demolished lies
within the project area as shown on the drawings and is the lawful property of the Client.
2.5 Preparation
1.
Provide interior and exterior shoring, bracing and support as necessaryto prevent movement, settlement or collapse of both, facilities to be
demolished and adjacent facilities, which are designated to remain.
Stop all demolition work and notify the engineer immediately, if the
stability of the facilities, which are to remain, appears to be in danger.
If required, extra support shall be provided by the Contractor as
deemed necessary by the Engineer.
2.
Temporary barricades and other forms of protection shall be providedto safeguard personnel and the facilities, which are to remain.
3. Ensure free and safe access for Clients personnel to move to and from
occupied portions of the facility.
4. Prevent the migration of dust and dirt to occupied areas by
constructing temporary partitions.
5. Remaining facilities must be protected in the interval between
completion of demolition and the beginning of the new construction.
6. Cover and protect equipment, fixtures, surface finishes and floors
remaining in the demolition area to prevent soiling or damage.
7. Remove protective measures when work is completed
8. Maintain and protect utilities, which are to remain, against damage
during demolition.
9. Provide bypass connections where necessary to serve occupied
portions of facilities.
10. Do not shut down any utilities without prior approval of Engineer.
2-4
-
8/12/2019 Technical Specifications of Roads
9/97
11. Do not interrupt existing utilities serving occupied facilities, unless
authorized in writing by the Engineer.
2.6 Demolition
A. General
Support or reinforce existing construction that is weakened by
demolition in order not to over load structural elements.
Completely backfill voids and below grade areas resulting from
demolition work.
Dust spread must be kept to a minimum by sprinkling anyrubbish with water twice daily.
Maintain adequate fire protection, including extinguishers and
operative water-hose lines during demolition of flammable
materials.
B. Traffic Control
Demolition work and debris removal operations are to be
carried out in such a manner that shall minimize interference
with roads, streets, walks and/or other adjacent facilities.
Provide alternative routes around closed or obstructed traffic
ways as directed by the Engineer.
Do not close, block or otherwise obstruct roads or facilities
without written permission from the Client.
C. Concrete and Masonry
Demolish concrete and masonry in small sections. Saw cut concrete along straight lines to a depth of not less than
50 mm, unless otherwise indicated on the Drawings.
Make cuts in walls perpendicular to the face and aligned with
the cut in the opposite wall face, and break out the remainder of
the concrete.
2-5
-
8/12/2019 Technical Specifications of Roads
10/97
Use removal methods, which will not crack or structurally
disturb the concrete, which will remain.
Distribute demolition equipment throughout structure and
promptly remove debris to avoid overloading supporting walls,slabs, and framing.
Seal all wall and floor openings as directed by the Engineer.
D. Pipes, Utilities and Conduits
All pipelines to be connected shall be cleaned and purged as
necessary to assure a safe environment before any cutting
activities.
The appropriate locations of pipes and conduits are generally
shown on the Drawings. Where the cutting location is not
shown, the pipe or conduit shall be removed back to the first
joint or valve, or to a location approved in advance by the
Engineer. Seal all remaining pipe ends as directed by the
Engineer.
Contractor shall inform the Engineer 72 hours prior to the
cutting of any pipes or conduits leading to or from a structure
to be demolished or to be relocated. These operations shall be
coordinated with the relevant Department/Authority to assure
that no interruptions are caused.
All pipes or conduits which are encountered and which are not
shown on the Drawings shall be brought to the attention of the
Engineer.
Utility lines not specifically noted for disposition, but which
are encountered in the Work shall be capped, extended,
protected or reworked as necessary for completion of the work
as directed by the Engineer.
E. Record of all disconnected services and utilities
The Contractor shall keep on site, an accurate, up to date record
of all disconnected services and utilities. Upon completion of
2-6
-
8/12/2019 Technical Specifications of Roads
11/97
2-7
2.7 Disposition of materials
1. All materials resulting from the demolition work, except those
specifically identified to be salvaged, shall become the
contractors property.
2. Remove debris, rubbish, dust, fluids and other demolition
materials not intended for salvage from the project site bytransporting and legally disposing of the materials off site to a
dumping site, which is approved by all relevant authorities.
The Contractor is responsible to pay all costs associated with
transport and disposal.
3. If any hazardous materials are encountered during demolition
operations, the contractor must comply with all applicable
regulations, laws and ordinances concerning removal, handling
and protection against exposure or environmental pollution.
4. Burning of removed materials shall not be permitted on the
project site.
2.8 Cleanup and repair
1. Remove tools, equipment, demolished materials and protective
devices from the site upon completion of demolition work, and
leave all areas clean to the satisfaction of the Engineer.
2. Restore all remaining structures, surfaces and facilities, which
may have been damaged during demolition work to their
original condition as required by the Engineer.
-
8/12/2019 Technical Specifications of Roads
12/97
3 GENERAL EARTHWORK AND SITE PREPARATION
3.1 General
This Section specifies general requirements for earthworks and site preparation and includes, but is not limited to, the following:
General Requirements Submittals and samples Quality Control Site Investigation
Suitable fill material Clearing Preparation of existing ground Placement of fill materials
3.2 Requirements
Earthwork shall comply with the following requirements, unless otherwise approved by theEngineer.
1. No trees or shrubs shall be disturbed, unless approved by
the Engineer in writing.
2. Blasting is not permitted.
3. All excavation and backfilling shall be performed in dry
conditions.
4. Earthwork shall be constructed to the lines, grades,elevations, slopes, and cross sections indicated on the
Drawings. Allowance shall be made as required for the
thickness of any pavement, blinding concrete, lining and
riprap.
5. Levels to be recorded: Benchmarks and baselines are to be agreed with Engineer.
3-1
-
8/12/2019 Technical Specifications of Roads
13/97
Before the surface of any part of the Site is disturbed, the
Contractor shall take and record levels on 10 m grids, unless
otherwise agreed with the Engineer.
Two working days notice is to be given to the Engineer so that therecording of levels can be performed in the presence of the
Engineer.
6. Slopes shall be smooth and uniform upon completion of
the work.
7. All excavated materials shall be utilized for the
construction of embankment, shoulders and other such
places as directed by the Engineer, unless the material is
found to be unsuitable. If not immediately re-used, the
excavated material shall be stockpiled in an area
designated by the Engineer. Before excavating any
material, the Contractor shall test to existing material to
determine if it is suitable to the requirements of fill or
subgrade material as specified. Suitable and unsuitable
materials shall be stockpiled separately.
8. The Contractor shall not waste or otherwise dispose of
suitable excavated materials without written permission of
the Engineer.
9. Any excavated material not required or not suitable for use
as filling material shall become the property of the
Contractor and the Contractor shall be entirely responsible
for its removal from the Site and for its appropriate
disposal.
10. If unsuitable materials are encountered in fill areas, such
unsuitable materials shall be removed as instructed by the
Engineer. Cross-sections shall be taken before and after
cutting.
11. Contractor at his own expense shall remove from the Site
all material resulting from excess excavations below that
required for the foundation, lining or bedding and shall
3-2
-
8/12/2019 Technical Specifications of Roads
14/97
12. If the bottom of any trench or structure excavation, while
acceptable to the Engineer at the time of his inspection,may subsequently become unacceptable due to exposure to
weather conditions, equipment traffic, flooding or other
conditions encountered during the progress of the works,
the Contractor shall remove such damaged, softened or
loosened material as directed by the Engineer. The cost
of the extra excavation and of the additional foundation
materials required will be the Contractors responsibility if
necessitated by his negligence.
3.3 Submittals
1. The contractor shall submit sufficient information to the
Engineer, prior to purchase, in order to verify compliance
with the specifications. Such information shall include at
least the following: manufacturers name, suppliers name,
product description, manufacturers technical data sheet,
storage instructions, and application instructions.
2. Samples shall be supplied for at least the following
products or as requested by the Engineer.
Borrow pit material (50 kgs) Excavated material (50 kgs) Water for soil compaction (1.5 l) Geotextile (30cm x 30cm)
3. The Contractor shall provide separate method statements
for at least the following activities or as requested by the
Engineer.
General excavation, backfill and compaction.
3-3
-
8/12/2019 Technical Specifications of Roads
15/97
Dewatering activities
4. The Contractor shall submit drawings for at least cross
sections for cut and fill areas.
3.4 Quality control
1. Inspection Requests shall be submitted to the Engineer
during the on site installation work prior to proceeding
with at least the following activities. Minimum
notification time shall be 24 hours. Start of excavation Start of backfilling Sampling and testing
2. Testing of all fill materials shall be carried out by a
suitably equipped laboratory. The proposed laboratory
shall be submitted to the Engineer for his review and
approval at least 30 days before commencing earthwork.
3. During the course of the work, tests shall be carried out
under the supervision of the Engineer, to :
Identify materials, and determine suitability. Determine compaction characteristics. Determine moisture content, and field
density.
4. Test Methods Maximum dry density of all soils shall be
determined by BS 1377: Part 4: Method
3.5/3.6.
3-4
-
8/12/2019 Technical Specifications of Roads
16/97
In situ field density of compacted soils shall
be determined by BS 1377: Part 9 method
2.1 or 2.2 (Sand Replacement Method).
Other tests (C.B.R., Sieve analysis,Atterberg limits, etc.) shall be determined
by relevant BS, AASHTO & ASTM
methods as directed by the Engineer.
5. Testing Density tests shall be made prior to removal
of dewatering systems.
Contractor shall adjust his operations to
permit time to make tests and shall excavate
and fill such holes as may be required for
sampling and testing.
A subsequent layer cannot be placed until
the density of the proceeding layer has been
tested and the area is approved by the
Engineer.
The minimum number of field density tests
to be performed shall be one for every 1000
m2 per layer of compacted existing ground
or fill, unless otherwise approved by the
Engineer.
The minimum number of compaction tests to
determine the maximum dry density (MDD)
of the soil shall be at least one for every 30
consecutive field density tests conducted or
as directed by the Engineer due to changes
in the soil.
All other specified tests shall be carried out
on every 2500m3 of fill material or as
directed by the Engineer due to changes in
materials.
3-5
-
8/12/2019 Technical Specifications of Roads
17/97
The Contractor shall maintain a daily log of
all tests carried out for the Engineers
review.
6. Allowable Tolerances Finished surfaces: + 25 mm from specified
level, unless otherwise approved by the
Engineer.
3.5 Delivery, storage and handling
Delivery, stockpiling, storage and handling shall be according to the method statement or
manufacturers recommendations along with the following provisions:
Transportation, handling and storage shall at all
times be performed in a manner to avoid product
damage.
Do not store products directly on ground, unless
approved by the Engineer. Ensure adequate timber
blocking is utilized to provide sufficient support.
If stored outside, cover products as recommended
by the manufacturer.
All excavated or borrow materials shall be stock
piled at least one meter away from the edge of the
trenches.
Stockpiling of the materials shall be in such a
manner that segregation shall be kept to a minimum.
The Contractor shall visually inspect all products
upon delivery and report any damage to the
Engineer. Any products damaged during delivery,
storage or installation shall be marked by the
Contractor and set aside. Any damaged products
deemed unsuitable for repair by the Engineer shall
3-6
-
8/12/2019 Technical Specifications of Roads
18/97
3.6 Site investigation
1. A soil investigation report may be provided
by the Client or Engineer. Such reports are
for information only and without any
warranty as to the correctness of the
information contained therein. Availability
of this report to the Contractor does notrelieve him of his:
a. Obligation to thoroughly investigate for himself the nature of the Site and
the sub-soil conditions therein.
b. Obligations and responsibilities under the terms and conditions of the
Contract.
2. Contractor shall be deemed to have visited
the Site prior to submitting his Tender and
made all necessary inspections and
investigations and allowed for the following
in his Tender:
a. Means of access and working space.
b. Nature of the ground and sub-soils.
c. Presence of existing foundations or other hidden obstructions.
d. Level of the water table.
e. Extent of rock.
f. Support to neighboring properties and structures.
g. All factors affecting the Work.
3. Any information made available to the
Contractor, either in these documents or by
any other source, will not relieve the
3-7
-
8/12/2019 Technical Specifications of Roads
19/97
4. Contractor shall be deemed to have
contacted the relevant authorities to establish
the existence of any existing, live or
redundant services adjacent to or passing
through the area of work and shall be
deemed to have allowed in his Tender for
their location, diversion, demolition or
removal.
5. Boring logs and related information depict
subsurface conditions only at the specific
locations and at the particular time
designated on the logs.
a. Soil conditions at other locations may differ from conditions occurring at
the boring locations.
b. Passage of time may result in a change of the subsurface conditions or
water levels at the boring locations.
c. Client does not guarantee any statements, opinions, or conclusions
contained in the report.
d. Contractor shall assume all responsibility for:
Deductions and conclusions made by him
regarding the nature of the materials to be
excavated;
Maintaining the required excavations; Carrying out the work affected by the subsurface
conditions at the site of the works.
e. Neither the Client nor the Engineer shall be liable for any loss sustained, if
the actual conditions encountered during progress of the work differs from
the borings, samples, tests, and/or reports provided.
3-8
-
8/12/2019 Technical Specifications of Roads
20/97
3.7 Products
3.7.1
Existing groundAfter site clearing, the top compacted 200mm of the existing ground shall be comprised of
material having the minimum qualities of suitable fill and shall be compacted to 95% of the
MDD, unless otherwise directed by the Engineer.
3.7.2 Fill material
1. Suitable fill material shall consist of
excavated or borrow material free fromrubbish, vegetation, perishable matter, tree
and plant stumps and other objectionable
matter.
2. Suitable fill material shall comply with the
following requirements, unless otherwise
approved by the Engineer.
For Embankments with maximum height 2m, fill materials
should comply with "AASHTO" classifications A-1, A-2-4
or A-2-5 materials with min. C.B.R. Soaked value of 10%
at 95% of M.D.D., Materials classified as A-3 may only be
utilized in areas approved by the Engineer. Generally,
materials classified as A-5,A-6, A-7 shall never be used to
construct any Embankment height .
For Embankment higher than 2m, the top 2m shall comply
with the previous requirement. The remaining height (lower
part of Embankment) should comply with the same req.
except if A-2-6, A-2-7 or A-4 have been improved and
accepted by the Engineer to comply with the following:
Min.C.B.R. soaked value = 3% at 95% of M.D.D. Max. swelling of C.B.R. test 3%
3-9
-
8/12/2019 Technical Specifications of Roads
21/97
Rock fill may be utilized except for the top 2m of
Embankment only as directed by the Engineer and
specified later.
3.
When sufficient quantities of suitable fillmaterials cannot be obtained from site
excavations, additional material meeting the
requirements of Fill Materials shall be
obtained from approved borrow areas.
4. The Contractor shall be responsible for the
arrangement and payment for all borrow
material.
3.7.3 Water
Water used for compacting fill shall be clean and free from oil, grease, organic matter,
suspended fine sediment or deleterious materials, unless otherwise approved by the Engineer.
3.8 Execution
3.8.1 Protection
Protect benchmarks and other permanent structures in the Site area from damage or
displacement.
3.8.2 Clearing
A. General
1. Contractor shall clear the Site area of
all vegetation, rubbish, debris and
other objectionable materials. Soils
suitable for landscaping or
agricultural purposes shall be
stockpiled separately for replacement
if directed by the Engineer.
3-10
-
8/12/2019 Technical Specifications of Roads
22/97
2. Contractor shall also clear the access
routes to the Site and any other areas
deemed necessary by the Engineer to
facilitate the construction of theWorks.
3. When clearing vegetation, the
Contractor shall ensure that the roots
of the trees, bushes, shrubs, etc. are
fully removed. Holes left by stumps
or roots shall be filed with suitable
material to the satisfaction of the
Engineer.
4. Contractor shall dispose of all
cleared vegetation, rubbish, debris
and other objectionable materials in a
controlled manner to a location
approved by the relevant authorities.
5. Contractor shall be responsible for
the proper upkeep and maintenance
of the Site and the Works and shall
remove from the Site, rubbish and
other waste as it accumulates.
6. Existing roads, improvements,
facilities, adjacent property etc. shall
be protected to the satisfaction of the
Engineer.
B. Existing services
1. Contractor shall check with the
relevant authorities to determine
what existing underground services
are present in the Site area.
3-11
-
8/12/2019 Technical Specifications of Roads
23/97
2. Contractor shall locate and
effectively seal off drain ends.
3. When necessary, the Contractor shall
divert services still in use and provide all temporary works
necessary to maintain such services
in full functional order. Such
services shall be reinstated to the
approval of the relevant authorities at
the earliest opportunity when
carrying out such work. The
contractor must comply with
regulations and obtain necessary
permits and No Objection
Certificates.
3.8.3 Existing ground preparation
1. After site clearing, the existing ground surfaces shall be graded to
remove surface irregularities.
2. In cut areas, excavation shall extend for the full-designated width
down to the bottom of the excavation.
3. The ground surface shall be scarified and loosened to a minimum
depth of 200 mm (except where the material is classified as rock).
If unsuitable materials are encountered, they shall be
excavated to a depth as directed by the Engineer.
The scarified material shall watered as necessary to
achieve uniform moisture content suitable for
compaction.
The scarified material shall then be compacted to at least
95% MDD below structures, roadways or parking areas
and at least 90% below landscaped or open areas.
3-12
-
8/12/2019 Technical Specifications of Roads
24/97
4. Surface materials of the existing ground shall be compacted and
bonded with the first layer of earth fill as specified for subsequent
layers of earth fill.
5.
Rock Foundations All rock foundation and abutment surfaces shall be
cleared of all loose materials by hand or other effective
means and shall be free of standing water when fill is
placed.
Fill placed immediately adjacent to such rock foundations
or where not accessible with large compaction equipment
shall be compacted to the specified density by means of
manually directed power tampers or plate vibrators.
6. Benching Where slope of existing soils to receive fill exceeds
1H:3V, horizontal benches shall be cut to key the new fill
material to the existing soils.
At least 600 mm of existing soil normal to the original
slope shall be removed and re-compacted as the new fill
is brought up in layers.
3.8.4 Placement of fill material
1. Placement of fill materials shall comply with the following
requirements:
Distribution of materials throughout each layer shall be
essentially uniform.
Fill shall be free from lenses, pockets, streaks, or layers of
material differing substantially in texture or gradation from the
surrounding material.
If the surface of any layer becomes too hard and/or smooth for
proper bond with the succeeding layer, it shall be scarified
parallel to the axis of the fill to a depth not less than 75 mm
before the next layer is placed.
3-13
-
8/12/2019 Technical Specifications of Roads
25/97
3-14
Top surface of each layer of fill shall be approximately level
during construction. The final surface of fill shall be finished
with a 2 percent crown or cross-slope as suitable for site
drainage, unless shown otherwise on the drawings.2. Field Compaction
Fill material in landscaped or open areas shall be compacted in
loose lifts up to 250mm thick to at least than 90% MDD.
Fill material below structures and paved areas shall be
compacted to at least 95% MDD in 200mm maximum loose
lifts, unless otherwise directed by the Engineer.
All fill shall be moistened or aerated to control the moisture
content to within a range of 3% of the optimum moisture
content when compacted.
Uniform moisture distribution shall be obtained by any
approved method prior to the compaction of the layer.
If the top surface of the preceding layer of compacted fill or
foundation becomes too dry or wet to permit suitable bond, it
shall be scarified and moistened by sprinkling or aerated to
acceptable moisture content prior to the placement of the next
layer.
-
8/12/2019 Technical Specifications of Roads
26/97
4 ROADS AND FOOTPATHS
This section covers all road works and footpaths and includes, but is not limited to, the
following: Geo-textile Fabric Pre-cast Concrete Curbs Interlocking Paving Blocks Free draining materials Stabilizing rock fill Rock fill
Subgrade Granular Sub Base Granular Road Base Bituminous Paving Courses Road Markings Traffic Signs Trench Excavation and Reinstatement in Roads
4.1 Definitions
The following definitions shall pertain to words or phrases as utilized in this Section:
Embankment shall mean any fill placed above the existing
ground or cut.
Fill shall mean suitable material utilized to raise an embankment
up to the bottom of subgrade. Subgrade shall mean the compacted top surface (150 to 300mm)
of the existing ground (or in some cases fill) below the formation
level.
Formation level shall mean top of subgrade after final
compaction.
Formation shall mean the top surface of the subgrade after
preparation for subsequent layers of material.
4-1
-
8/12/2019 Technical Specifications of Roads
27/97
Wearing course shall mean the top layer of asphalt concrete
directly supporting the traffic.
Asphalt concrete shall mean a hot mixture of asphalt cement and
well-graded, high quality aggregate, thoroughly compacted into auniform dense mass.
Borrow material shall mean suitable fill material taken from an
approved source.
OMC shall mean optimum moisture content. MDD shall mean maximum dry density. CBR shall mean California bearing ratio. Prime Coat shall mean a thin film of liquid asphalt applied on a
previously prepared untreated soil.
Tack Coat shall mean a thin film of liquid asphalt applied on a
previously prepared bituminous course or to an existing bituminous
surface.
Foot Path shall mean a passage paved by interlocking blocks for
pedestrian traffic.
Coarse aggregate shall mean that material retained on a 4.75 mm
sieve.
Fine aggregate shall mean that material passing a 4.75 mm sieve.
4.2 General Requirements
Product manufacturer, testing and installation shall comply with the following requirements,
unless otherwise approved by the Engineer.
Paving shall conform to the lines and levels on the drawings unless
otherwise approved by the Engineer.
All materials for use in construction shall be obtained only from
sources approved by the Engineer.
The specific source of materials shall not be changed without prior
written approval of the Engineer.
If the grading and quality of material delivered to the site does not
conform to the grading and quality as previously inspected and
4-2
-
8/12/2019 Technical Specifications of Roads
28/97
Sufficient materials must be stored in stockpiles to allow for testing
and approval of such materials prior to use in works.
4.3 Submittals
The contractor shall submit sufficient information to the Engineer, prior to purchase, in order
to verify compliance with the specifications. Such information shall include at least thefollowing, unless otherwise required by the Engineer.
Manufacturers name. Suppliers name. Product name and description. Manufacturers technical data. Storage instructions. Relevant test results of all materials specified. Application or installation instructions. Details of asphalt plant, location and calibration results
4.3.1 Samples
Samples shall be supplied for at least the products included in Table 4-1 or as requested by
the Engineer. All sampling shall be witnessed by the Engineer, unless agreed otherwise.
4.3.2 Method Statement
The Contractor shall provide separate method statements for at least the following activities
or as requested by the Engineer.
Site clearing and earthwork. Dewatering activities (if necessary).
4-3
-
8/12/2019 Technical Specifications of Roads
29/97
Method of mixing and laying for sub-base, road base
and wet-mix.
Method of surface preparations and application of prime
and tack coat. Method of mixing, laying and compaction of bitumen
mixtures.
Asphalt plant calibration.
4.3.3 Shop Drawings
The Contractor shall submit shop drawings for at least the proposed roadway Sections.
Table 4-1. Sampling Schedule
Item Sample
Geo-textile Fabric: 20cm x 20cm sample of each proposed fabric.
Pre-cast Concrete Curbs If requested, three sample of each size.
Concrete Paving Blocks Fifteen sample of each size and color and as required for
testing.
Aggregates 100 kgs of each size and type.
Fill Material 100 kgs from each source.
Existing Material 100 kgs from each source.
Free Draining Material 50 kgs from each source.
Subgrade Material 100 kgs from each source.
Rock fill Material 500kgs from each source.
Granular sub-base Material 100kgs from each source.
Road Base Material 100kgs from each source.Bedding Sand 25kgs from each source.
Bituminous Mixes 50kgs from each source.
Prime Coat 3 liters from each source.
Tack Coat 3 liters from each source.
Bitumen 3 liters from each source.
Road Marking Materials Applied samples and or as requested by the Engineer.
Signs Prepared samples as requested by the Engineer.
4-4
-
8/12/2019 Technical Specifications of Roads
30/97
4.3.4 Mock-up
The Contractor shall prepare a mock-up for at least the following installations or as requested
by the Engineer.1. Concrete Paving Blocks
Provide mockup of paving layout where directed by the
Engineer.
Size: 15 - 20 m 2. Laying of bedding course, installation of paving blocks and
accessories to indicated pattern shall be included.
Show range of shades, color, and texture of pavers. Accepted mockup may become part of the work.
2. Rock Fill Provide mock-up of laying trial as directed by the Engineer. Length 100 m, width 4 m.
3. Sub-Base Provide mock-up of laying trial as directed by the Engineer. Length 30 m, width 4 m.
4. Road Base Provide mock-up of laying trial as directed by the Engineer. Length 30 m, width 4 m.
5. Binder Course Provide mock-up of laying trial as directed by the Engineer. Length 30 m, width 4 m.
6. Asphalt Wearing Course Provide laying trial as directed by the Engineer. Length 30 m, width 4 m.
4-5
-
8/12/2019 Technical Specifications of Roads
31/97
4.4 Quality Control
1. Prior to dispatch from the factory, the
Contractor shall notify the Engineer, insufficient time to allow the Engineer or his
representatives to inspect and test the products,
if so desired. All notifications shall be made by
written Inspection Requests. An advance
copy may be faxed to the Engineers office, but
the original must arrive before the scheduled day
of inspection.2. Inspection Requests shall be submitted to the
Engineer during the on site installation work
prior to proceeding with at least the following
activities. Minimum notification time shall be
24 hours.
Start of excavation Start of backfilling Start of free draining material Start of stabilizing material Start of rock fill Start of subgrade Start of sub-base and road base and wet mix mixing and laying. Start of prime coat and tack coat application. Start of bituminous paving mixtures. Sampling and testing.
3. Testing of all materials shall be carried out by a
suitably equipped site laboratory or in an
approved independent laboratory.
Routine materials testing and site testing shall always be
conducted in the site laboratory, unless otherwise agreed by the
Engineer.
4-6
-
8/12/2019 Technical Specifications of Roads
32/97
All sampling shall be witnessed by the Engineer, unless
otherwise directed by the Engineer.
During the course of the work, all required tests shall be carried
out under the supervision of the Engineer, to ascertain thesuitability of materials according to this speciation.
The Contractor shall maintain a daily log of all tests carried out
for the Engineers review.
4. Test Methods Compaction tests to establish maximum dry density for
all soils shall be determined by BS 1377: Part 4:
Method 3.5/3.6 as appropriate.
In situ density of compacted soils shall be determined
by BS 1377: Part 9 Method 2.1 or 2.2 (as appropriate).
Cone penetration test: TRL Method or BS 1377 as
directed by the Engineer.
Density tests shall be made prior to removal of
dewatering systems.
Contractor shall adjust his operations to permit time to
make tests and shall excavate and fill such holes as may
be required for sampling and testing.
A subsequent layer cannot be placed until the density of
the proceeding layer has been tested and the area
approved.
At least one field density test shall be conducted for
each layer at each structure (or every 200m2), unless
otherwise directed by the Engineer.
At least one compaction test (MDD/OMC) shall be
conducted for every 30 field. Density tests conducted or
as directed by the Engineer due to changes in the soil.
At least one complete soil analysis shall be carried on
each type of material as specified in relevant Clauses or
as directed by the Engineer due to changes in the soil.
4-7
-
8/12/2019 Technical Specifications of Roads
33/97
The allowable soil-bearing load shall be verified by
dynamic cone penetration test if directed by the
Engineer.
4.5 Delivery, Storage and Handling
Delivery, storage and handling shall be according to the manufacturers recommendations
along with the following provisions:
Transportation, handling and storage shall at all times be
performed in a manner to avoid product damage.
Only nylon slings shall be allowed for lifting products.Steel chains, clamps or cables shall not be allowed for
lifting purposes, unless approved by the Engineer. Steel
chains or cables may be allowed for securing products
during transport or storage provided protective padding or
timber blocking is utilized.
Do not store products directly on ground, unless approved
by the Engineer. Ensure adequate timber blocking is
utilized to provide sufficient support.
Where product manufacturer recommends storage under
controlled temperatures, the Contractor must provide an
enclosed, insulated, cool store maintained at the proper
temperature 24 hours a day.
If stored outside, cover products to prevent UV degradation
as recommended by the manufacturer.
The Contractor shall visually inspect all products upon
delivery and report any damage to the Engineer.
a. Any products damaged during delivery, storage or
installation shall be marked by the Contractor and set aside.
b. Proposals for repair of any damaged products shall be
submitted in writing to the Engineer for approval.
c. No repairs to damaged products shall be attempted without
the Engineers approval.
4-8
-
8/12/2019 Technical Specifications of Roads
34/97
d. Any damaged products deemed unsuitable for repair by the
Engineer shall be removed from site and replaced at the
Contractors expense.
4.6 Products
4.6.1 Subgrade
1. Suitable subgrade materials shall be a minim. 30
cm thick after compaction in both Embankment
and cut areas using materials of the followingrequirements:
Materials classified by "AASHTO" as A-1-a(0) , A-1-b(0) and A-
2-4(0).
Materials having a min. soaked C.B.R. of 15% at 98% of M.D.D. Materials being reasonably well graded with sufficient fines to
permit compaction and compaction testing.
Materials with max. size 75mm. Materials free from organic matter, shale and other deleterious
material
2. Minimum test frequency One sample shall be tested to confirm the above properties for
every 1500m (or part there of) placed or compacted.
Two in-situ density tests shall be made every 800m2 of subgrade
laid.
4.6.2 Rock fill
1. Rock fill used as stabilizing materials where Embankment
foundation is found unstable:
Shall be 100% hard durable crushed rock of suitable size. Free from organic matter, shale and other deleterious material.
4-9
-
8/12/2019 Technical Specifications of Roads
35/97
Shall bind readily to form a stable mass with sound, smooth, well-
knit upper surface free from loose material.
2.
Rock fill used to construct high Embankments: Materials consisting predominantly of rock fragments of such a
size that it cannot be placed in layers of the thickness allowed
without crushing , or further breaking down, may be placed in high
Embankment in layers not exceeding twice the average size of the
larger fragments. However, no layer of rock fill shall exceed 80 cm
loose thickness.
Top surface voids should be completely filled with smaller
fragments sand or gravel.
Materials should be approved by the Engineer.
4.6.3 Pre-cast Concrete Curbs
1. A company specializing in curbstone manufacturing with at
least three (3) years experience, unless otherwise agreed by the
Engineer.
2. Pre-cast curbs shall conform to BS 7263: Part 1: 1994 except as
modified in this Section.
3. This Section covers non-mountable curbs, dropped curbs, heel
curbs, quadrants, flush curbs, curb ramps, noses, channel
blocks and edgings.
4. Materials for precast curbs Cement
a. Portland cement, conforming to BS 4027 or ASTM C 150, Type V.
b. Minimum cement content shall be 300 kg/m 3.
Aggregates
a. Combined gradation shall be as follows, unless otherwise agreed by the
Engineer. Sieve analysis shall be according to BS 812: Part 103.
Table 4-2. Aggregate gradation for precast curbs
4-10
-
8/12/2019 Technical Specifications of Roads
36/97
ASTM Sieve Size(mm)
% By WeightPassing
20.0 95 -10014.0 80 - 100
10.0 60 - 855.0 40 - 652.36 22 - 421.18 12 - 32
0.600 7-230.300 4 - 150.150 2 - 100.075 0 - 2
5. Manufacturer: Elements shall be manufactured to the
designated dimensions as shown on the Contract Drawings,
unless otherwise directed by the Engineer. Precast curbs shall
be formed by elements 900 mm long where required to be laid
in straight lines, unless otherwise approved by the Engineer.
May be reduced to 200 mm long where required to be laid to
curves depending on the radii of the curves. Pre-cast
curbstones shall be hydraulically pressed precast products
manufactured in a fully automatic batching plant and
complying with the requirements of BS 7263: Part 1 except as
modified hereunder.
a. They shall be uniform in color free from cracks, flaws of other
defects and shall have well defined arises.
b. If required by the Engineer 100mm diameter cores shall be
taken from the pre-cast elements to ascertain that the concrete
strength is not less than specified value.
Cores shall be tested to BS 1881: Part 120 A sample of 3 products shall be taken from a
consignment of not more than 1000 products.
Two cores shall be cut form each of three samples. Mean compression strength of two cores shall
reported as the compressive strength of that
product.
4-11
-
8/12/2019 Technical Specifications of Roads
37/97
Average compressive strength of 3 products shall
not be less than 250kg/cm 2.
Mean water absorption of cubes when tested in
accordance with B7263: Part 1 shall not be greaterthan 3.0%.
Cure units by either: low-pressure steam, steam
vapor, or other similar process as approved by the
Engineer.
c. Finishes Ensure exposed-to-view finish surfaces of pre-cast
concrete members are fair faced, uniform in color
and appearance.
Cure members under identical conditions to
develop required quality. Minimize appearance
blemishes such as non-uniformity, staining, or
surface cracking.
Small surfaces holes, normal form joint marks,
and minor chips are acceptable, if approved by the
Engineer. Major or unsightly imperfections,
honeycombs, or structural defects are not
acceptable.
d. Tolerances: Tolerances of manufacture shall be 3 mm in any
one dimension and end faces shall be truly perpendicular to the
base.
e. Testing Frequency: As directed by the Engineer.
4.6.4 In-situ concrete curbs
1. A. Cast in-situ curbs shall comply with the following except as
modified by the Engineer.
Min. compressive strength of cubes after 28 days, 250
kg/cm2.
4-12
-
8/12/2019 Technical Specifications of Roads
38/97
Cement used shall conform BS4027 or ASTM C150 Type
V.
Use of additives may be allowed if approved by the
Engineer.
4.6.5 Interlocking paving blocks
1. Concrete Paving Blocks Manufacturer: A company specializing in exterior
concrete paving block manufacturing with three (3) years
experience unless otherwise agreed by the Engineer.
Installer: A company specializing in installing exterior
pavers with three (3) years experience, unless otherwise
agreed by the Engineer.
2. Materials and Manufacture Portland cement conforming to BS 4027 or ASTM, C150
Type V.
Thickness shall be 60mm or 80mm on footpaths, unless
otherwise shown on the Drawings or instructed by the
Engineer.
Color and pattern of the blocks shall be as noted on the
drawings or as directed by the Engineer.
Pigment (inorganic) shall comply with BS 1014.
Minimum pigment content shall be 5% by weight of
cement, unless otherwise approved by the Engineer.
Compressive Strength.
a. 350 kg/cm 2 for roads (8 cm thickness).
b. Strength 250 kg/cm 2 for footpath (6 cm thickness).
Water Absorption
a. Average of 3 specimens tested in accordance with ASTM C140 shall not
be greater than 5%.
4-13
-
8/12/2019 Technical Specifications of Roads
39/97
b. No individual result shall be greater than 7%.
Sulphate and Chlorides
a. The total sulphate content shall not be more than 4.0% by weight of thecement in the mix.
b. The total chloride content shall not be more than 0.15% weight of mix.
Bedding Sand Shall consist of non-plastic sand meeting the following
properties, unless otherwise approved by the Engineer.
Table 4-3. Properties of bedding sand
Sieve Size (mm) Percent Passing by Wet Sieving
10 1005.0 95 100
2.36 80 1001.18 50 85
0.300 10 300.150 5 15
0.075 0 3Test Standard Limit
Clay, silt and dust content BS 812: Part 103.1 3.0% Max
Sulphates (SO 3) BSI 377: Part 3 Method 5 0.3% Max
Chlorides (Cl) BSI 3777: Part 3 Method 7 0.5% Max
4.6.6 Granular Sub Base
1. Hard, durable gravel and/or crushed gravel or crushed stone
with sand and silt.
2. Free of clay balls or other deleterious substances.
3. If required approved binding material shall be added to the
coarse gravel to improve the binding property of sub-base
material but in no case, the percentage of binding material
added shall not be more than 20% of the sub-base.
4-14
-
8/12/2019 Technical Specifications of Roads
40/97
4. Grading shall be one of the following classes when tested in
accordance with BS 1377: Part 2: Method 9.2. Selected class
shall be as directed by the Engineer
Table 4-4. Gradation of Granular Sub Base
% By Weight PassingSieve Size / No.
Class A Class B Class C
3" 100 100 100
2" 90 - 100 90-100 90-100
No. 4 35 - 70 40-90 50-100
No. 200 0 - 20 0-20 0-30
5. Materials shall conform with the following requirements:
Table 4-5. Requirements of Granular Sub Base
Test Standard Limit
Liquid Limit BS 1377: Part 2 : Method 4.5 max 30%Plasticity Index BS 1377 : Part 2 : Method 5 max 8%
% water absorption after 24 hours
submerged in waterLocal codes max 10%
Clay lumps and friable particles in
aggregatesLocal codes-T 113 max 10%
Los Angeles Abrasion ASTM C131/C535 max 50%
Compaction Test (MDD) BS 1377: Part 4: Method 3.6 2.1 Mg/m Min
In-situ Density Test BS 1377: Part 9: Method 2.2 min 98%
CBR at 98% MDD (96 hour soaked) BS 1377: Part 4 Method 7 min 25%
Swelling of soaked C.B.R. moulds No swelling
6. Minimum Test Frequency
4-15
-
8/12/2019 Technical Specifications of Roads
41/97
One sample every 1000m shall be tested for
complete analysis unless otherwise approved by
the Engineer.
Three in-situ density tests shall be made every1000m of granular sub base laid, unless
otherwise approved by the Engineer.
One in-situ density shall be carried out for every
150 linear meter of shoulder or footpath, unless
otherwise approved the Engineer.
4.6.7 Aggregate Road Base
1. Hard, durable crushed gravel or crushed stone. The amount of
crushing shall be such that at least 80% (by weight) of the
pieces retained on 4.75mm sieve shall have at least one
mechanically fractured face. Material shall consist of uniform
mixtures of gravel and or crushed gravel with sand, silt and
clay conforming to the following gradation limits.
2. Free of organic matter or other deleterious substances.
3. Grading shall be one of the following classes when tested in
accordance with BS 1377: Part 2: Method 9.2. Selected class
shall be as directed by the Engineer
Table 4-6. Gradation of Aggregate Road Base
% by Weight PassingSieve Size
/No. Class A Class B Class C
2" 100
1.5" 70 -100 100
1" 55 - 85 70-100 100
3/4" 50 - 80 60-90 70-100
3/8" 40 - 70 45-75 50-80
No.4 30 - 60 30-60 35-65
4-16
-
8/12/2019 Technical Specifications of Roads
42/97
No.10 20 - 50 20-50 25-50
No.40 10 - 30 10-30 15-30
N0.200 5 - 15 5-15 5-15
4. Material shall conform with the following requirements:
Table 4-7. Requirements of Aggregate Road Base
Test Standard Limit
Liquid Limit BS 1377: Part 2: Method 4.5 max 30%
Plasticity Index BS 1377: Part 2: Method 5 max 8%
Linear shrinkage BS 1377: Part 2: Method 6.5 Max 7%
Organic Impurities BS 1377: Part 3: Method 3 Max 0.2%
% absorption submerged in water for 24
hours.
Local codes max 10%
Clay lumps and friable particles Local codes T-113 max 5%
Los Angeles Abrasion ASTM C131/C535 max 50%
Thin and Elongated particles Local codes Max 10%
Compaction Test (MDD) BS 1377: Part 4: Method 3.6 min 2.2
Mg/m
In-situ Density Test BS 1377: Part 9: Method 2.2 100%
CBR at 100% MDD (96 hr. soaked) BS 1377: Part 4: Method 7 min 80%
Swelling of soaked C.B.R. moulds No swelling
5. Minimum Test Frequency
One sample every 1000 m 3 shall be tested. Two in-situ density tests shall be made every 500 m 2 of
aggregate road base laid.
4-17
-
8/12/2019 Technical Specifications of Roads
43/97
4.6.8 Materials for Asphalt Concrete
1. Mineral aggregates for bituminous paving course shall consist
of coarse aggregates, fine aggregates and filler material all
complying with the following requirements.2. Prior to the production of aggregates or delivery of aggregates
the Contractor shall notify the Engineer of the source of
aggregates for inspection of the borrow or quarry area. All
sources of aggregates shall be approved by the Engineer prior
to the processing of material.
3. The properties of aggregates specified in this section shall be
for aggregates from individual sources or individual stockpiles.
4. If the grading and other specified properties of the material
delivered to the site does not conform to the same properties of
originally approved samples or does not comply with the
specification, the Engineer reserves the right to reject such
materials at the site of the work. If required by the Engineer
the Contractor shall submit to the Engineer the original
invoices for any delivery of mineral aggregates including filler.
5. Coarse Aggregates (those retained on a 4.75mm sieve) Shall consist of crushed rock or crushed gravel. Shall be clean, hard, tough, durable and sound. Shall be of uniform quality and free from decomposed
stone, shale, clay lumps and other deleterious substances.
Mineralogical tests shall be carried out on the aggregates,
if requested by the Engineer
Crushed gravel. Consists of products obtained by
crushing material that has first been screened in such a
manner that not less than 90% of the material to be
crushed is retained on an ASTM 9.5 mm sieve.
100% (by weight) of each stockpile of aggregate retained
on 2.36mm sieve shall have at least one crushed face.
4-18
-
8/12/2019 Technical Specifications of Roads
44/97
At least 85% (by weight) of each separate stockpile of
aggregate retained on 2.36m sieve shall have all faces
crushed, unless otherwise approved by the Engineer.
Coarse aggregate in each individual stock pile shall have
properties which comply with the following values:
Table 4-8. Requirements of Materials for Asphalt Concrete
Test Standard Binder Course Wearing Course
Los Angeles Abrasion ASTM C131/C535 max 40% max 40%
Thin & Elongated particles Local codes max 10% max 10%
Clay lumps and friable particlesLocal codes 0%* 0%*
% water absorption Local codes max 5% max 5%
Organic Impurities BS 1377 Max 0.05% Max 0.05%
6. Fine aggregate shall be obtained from 100% crushed gravel or
crushed rock, unless otherwise approved by the Engineer.
If approved by the Engineer, a maximum of 25%
(by weight) of fine aggregate may be uncrushed if it
is separately fed into the plant.
Use of dune sand shall not be permitted. Fine aggregates shall be Non-Plastic when tested for
Plasticity Index:
7. Filler Material When the combined grading of the coarse and fine
aggregates is deficient in material passing the
ASTM No. 200 sieve, external mineral filler shall
be added as approved by the Engineer at the
Contractors expense.
Mineral filler shall consist of finely ground non-
plastic particles of limestone or cement.
4-19
-
8/12/2019 Technical Specifications of Roads
45/97
Mineral filler shall be thoroughly dry and free from
organic substances and clay.
Test frequency is as directed by the Engineer.
8. Bitumen Binder Shall be penetration grade 40/50 or 60/70 as
directed by the Engineer.
Bitumen shall be prepared by refining crude
petroleum.
Shall be homogeneous and free from water. Shall not foam when heated to 175C. Shall conform to the following requirements, unless
otherwise accepted by the Engineer.
Bitumen heated 100C above the maximum
temperature obtained form viscosity temperature
relationship shall be considered over-heated and
shall be removed from site and disposed of by the
Contractor at his own expense. Bitumen shall be
heated only in approved boilers or bulk storage
containers equipped with adequate and accurate
thermometers.
When filling the bitumen from distributors boilers
or bulk containers, the bitumen shall be passed
through a filter of fine wire gauge.
The Contractor shall take every reasonable pre-
cautions to avoid fire or heath hazards.
A sample of bitumen that the Contractor propose to
use in the work together with a statement as to its
source and properties shall be submitted to and
approved by the Engineer at least 45 days before
Construction begins.
4-20
-
8/12/2019 Technical Specifications of Roads
46/97
The properties of bitumen shall be as specified by
the Local code unless otherwise approved by the
Engineer.
Only the bitumen represented by the approvedsample shall be used by the Contractor.
Blending of bitumen from different refineries will
not be permitted.
Test Frequency. One full analysis shall be carried
out on a sample from every 80ton.
4.6.9 Asphalt Concrete
1. When tested according to ASTM C117 and ASTM C136, the combined
aggregates shall conform to the following grading having a smooth curve
to the appropriate limits and shall not vary from the low limit on one sieve
to the high limit on the adjacent or vice-versa.
Table 4-9. Gradation of aggregate to used in asphalt concrete
Sieve size/No. % By Weight Passing
Binder Course Wearing Course
1" 100 100
3/4" 75-100 80-100
1/2" NA NA
3/8" 45-70 60-80
No 4 30-50 48-65
No 8 20-35 35-50
No 30 5-20 19-36
No 50 3-12 13-23
No 80 2-8 7-15
No 200 0-4 3-8
2.
Combined mineral aggregate shall be non-plastic.
4-21
-
8/12/2019 Technical Specifications of Roads
47/97
3. Coarse aggregate, shall show no detrimental amount of stripping when
tested in accordance with ASTM D 1664. The area coated shall be
evaluated not only at 25C but also after the aggregate has been soaked
in water at 40C and 60C. Minimum value of non-stripped area shall be 95%. If stripping occurs, the aggregate shall be rejected
unless:
a. An approved method of treatment shall be carried out as specified to
change the material from a hydrophilic to a hydrophobic state.
b. Only approved additives shall be used with the bituminous binder.
4. When necessary to change the hydrophilic character of aggregates to
hydrophobic, additives of approved type will be added to the
bituminous material in such percentage as required to obtain
satisfactory results from the test performed in accordance with ASTM
D1664. Approved additive will be used in accordance with Technical
Specifications issued by the manufacturer and approved by the
Engineer after appropriate testing. No extra payment will be made for
required anti-stripping additives.
5. Design Criteria: The following table summarizes the design criteria of
asphalt concrete. However, the exact percentage of bitumen to be used
shall be fixed by the Engineer based on the laboratory mix and full-
scale plant trial mix results.
Table 4-10. Design Criteria of Asphalt Concrete
PropertiesBinder
course
Wearing
course
Bitumen Content (% of total mix) Marshall Specimens: 3 - 6 4 - 7.5
Number of Compaction blow at each end of specimen. 75 75
Air voids in total mix (VIM %) 3 - 8 3 - 5
Voids in mineral aggregate (VMA %) Min. 14 Min. 15
Stability (kg) Min. 700 Min. 900
4-22
-
8/12/2019 Technical Specifications of Roads
48/97
Flow (mm) 2 - 4 2 - 4
6.
Job mix for Bituminous Paving Courses: field trials with the followingrecommendations shall be taken into account.
Combined aggregate gradation should be
adjusted within the allowable limits to achieve
maximum stability whilst not going below the
minimum requirement for void content.
Minimum bitumen binder content should be
used according to the results of the Marshall
Method of Mix Design, if it will still satisfy all
the specified requirements.
Final job mix must display all characteristics as
specified for Asphalt Concrete mixes.
After receiving approval of the aggregates and
bitumen from the Engineer, the Contractor shall
make a written request for the approval of the
job-mix formula from the Engineer at least
thirty, (30) days prior to the date he intends to
begin production of plant-mix Bituminous
Paving Course Mixes. Formula will be
prepared by the Contractor under the
supervision of the Engineer in the Laboratory.
The laboratory job mix formula shall define:
a. Percentage of aggregate passing each required sieve size.
b. Percentage of bitumen binder to be added to the aggregate.
c. Temperature at which the mix is to be emptied from the mixer.
d. Temperature at which the mix is to be delivered to the works site.
Before the start of the permanent work, mock-
ups or trial areas having lengths of at least 30
m shall be laid to the specified layer thickness
4-23
-
8/12/2019 Technical Specifications of Roads
49/97
a. Materials used in the trials shall be those
approved for use in the bituminous paving courses.
b. Equipment used shall be that according
to the Contractors approved method
statement and the program of work.
c. The object of these trials is to determine
adequacy of the Contractors equipment,
loose depth measurements necessary to
result in the specified compacted layer
depths, and relationship between the
number of compaction passes and the
resulting density of the material.
d. Additionally at least two samples of non-
compacted material and two cores of
specified diameter shall be taken from
the trial area in accordance with
AASHTO T-168 and analyzed in the
presence of the Engineer to determine
aggregate grading, binder content,
stability, flow, bulk density, and voids.
Results shall be submitted to the
Engineer for approval before further
mixing and laying are carried out.
If the laboratory job mix formula fails to
produce a satisfactory trial, the mix proportions
may be modified by agreement with the
Engineer, within the applicable specification
requirements to produce a mix of satisfactory
workability and acceptable surface finish.
4-24
-
8/12/2019 Technical Specifications of Roads
50/97
All mixes produced shall conform to the
properties of Job Standard Mix approved by the
Engineer, within the ranges of tolerance
specified in Table 22. Should a change in a material be encountered or
should a change in a source of material be made,
a new Job-Standard Mix shall be submitted by
the Contractor and approved by the Engineer
before the mix containing the new materials is
delivered. Job materials will be rejected if they
do not possess the same characteristics of the
approved Job Standard Mix.
Table 4-11. Job Mix Tolerance
Aggregate retained on 4.75 mm sieve or larger + 5%
Aggregate passing 4.75 mm sieve and retained on 0.075mm sieve
+ 4%
Aggregate passing 0.075 mm sieve + 2%Bitumen Binder + 0.25%
Temperature for mixing and placing 10C
7. Samples of Bituminous paving course mixes shall be taken from the
mixing plant and/or behind the paver prior to compaction, as decided
by the Engineer, to check compliance with the approved job mix
requirements. Density of the compacted mixes shall be related to the
job standard density or the daily Marshall Density at the option of the
Engineer, which shall be determined by making four Standard
Marshall specimens from samples of the mix taken from the mixing
plant or paver.
Density of each sample shall be determined and
compared with the mean value.
Any individual result, which varies from the
mean by more than 0.015 g/cc, shall be rejected.
4-25
-
8/12/2019 Technical Specifications of Roads
51/97
Marshall tests shall be repeated on a daily basis
to establish the daily Marshal Density for that
particular days production.
Daily Marshall Density shall not vary from theJob Mix Design Density by more than + 1%.
8. Assistance of the Engineer in the preparation of the job standard mix
shall in no way relieve the Contractor of his responsibility for
producing a bituminous mix meeting the requirements of the
Specifications.
9. Preparation of Bitumen Binder Temperature of the bitumen binder for mixing
and compacting shall be in accordance with
ASTM D1559. The Contractor shall submit a
temperature / viscosity chart for each grade of
bitumen to be used.
10. Preparation of Mineral Aggregate for Bituminous Mix Coarse and fine aggregate shall be stored at the
asphalt plant in such a manner that separate
stockpiles will not become intermixed.
a. Stockpiles shall be of sufficient size to provide a minimum quantity of one
weeks continuous production of asphalt mix.
b. Aggregates brought to the asphalt plant to supplement stocks should be
tested and approved prior to placing in the existing approved stockpiles.
Cold bins shall be calibrated with the materials
to be used and the settings shall be such as to
produce a combined gradation in accordance
with the job mix formula.
a. Proportioning shall be such that surpluses and shortages
in the hot bins will not occur.
b. Neither the dryer nor the screens shall be overloaded.
4-26
-
8/12/2019 Technical Specifications of Roads
52/97
c. All the above shall be as approved by the Engineer.
Materials shall be thoroughly dried and heated
so that their temperature is within 8C of the
temperature needed to satisfy the viscosityrequirements of the asphalt cement.
a. Moisture content of the heated and dried materials shall not exceed 0.5%.
b. Quantity of materials fed through the drier shall in all cases be held to an
amount, which can be thoroughly dried and heated within the limits
specified.
Immediately after heating, the aggregates shall
be screened into at least five sizes and conveyed
into separate bins ready for batching and mixing
with bituminous materials. When the aggregates
supplied are of such size and grading that
separating into five bins is impractical, the
number of required separations may be reduced
to four or to three with the approval of the
Engineer.
Efficiency of the screening operations shall be
sufficient to produce (at plant operating
capacity) gradations (in all sizes of heated and
dried aggregates) which are reasonably uniform
and result in the production of a mix complying
with the limits specified for the aggregate
gradation.
11. Preparation of Bituminous Mix Asphalt concrete shall be prepared in a central
mixing plant conforming to the requirements of
ASTM D995.
a. The plant shall be equipped with an efficient mechanical dust extraction
system and storage silos.
4-27
-
8/12/2019 Technical Specifications of Roads
53/97
b. Its design shall be provided for the controlled return of some of the filler to
the mix, when necessary, by means of filler weighing bin discharging in to
the pugmil.
c. The dust collection system shall be powerful enough to keep the mineralfiller contents the in hot sand bin below 2%.
d. The plant settings once established shall not be changed without the
approval of the Engineer.
e. The minimum mixing time shall not be less than that recommended by the
manufacturer. The mixing time may be increased by the Engineer if
additional time is necessary to obtain a homogeneous mix and satisfactory
coating.
f. Bitumen binder shall be introduced into the mix in the proportion specified
by the job-mix formula.
Initial mixing time will be designated by the
Engineer. Mixing time may be increased by the
Engineer if additional time is necessary to obtain
a homogeneous mix and satisfactory coating.
Timing at the batch plant for mixing shall begin
at the start of the introduction of the bitumen
into the pugmill.
Temperature of the aggregate immediately prior
to mixing shall be within + 8 C of the
temperature of the bitumen binder.
a. Temperature of the aggregate and asphalt prior to mixing shall be
approximately that of the completed mix as defined in the job mix formula
approved by the Engineer.
b. Mix temperature shall be within the limits set out in the job mix formula
when emptied from the mixer.
12. Minimum test requirements for bituminous courses Bitumen material: One sample shall be tested for
penetration and Ring ball test for every 80 tons
or part thereof, unless otherwise agreed by the
Engineer.
4-28
-
8/12/2019 Technical Specifications of Roads
54/97
Aggregate: One sample for each stockpile or
every 1,000 m. Perform all the required tests.
Bituminous mix: one sample of mix shall be
obtained from at least every 200 tons. Performall the required tests.
4.6.10 Prime and Tack coats
1. Prime coat shall be a medium curing cut back
asphalt (MC-70) .
Sampling shall be in accordance with ASTM D140. Frequency of the testing shall be as directed by the
Engineer.
2. Tack Coat shall be Rapid Curing cut back asphalt (
RC-250 ).
Sampling shall be in accordance with ASTM D140. Frequency of the testing shall be as required by the
Engineer.
3. Depending on the possibilities of obtaining
Bituminous materials, the Engineer may modify the
type and gradation of the materials for the prime
coat and tack coat.
4.6.11 Road marking materials
1. Thermoplastic Materials shall comply with
BS3262 hot-applied thermoplastic road
marking materials and shall be suitable for
road surface temperature of up to 80C,
unless otherwise approved by the
Engineer. Proportions, testing
requirements and type of materials used
shall be as mentioned in the Contractors
approved method statement.
2. Road marking paint shall be either
chlorinated rubber, one pack epoxy or
4-29
-
8/12/2019 Technical Specifications of Roads
55/97
4.6.12 Traffic signs
1. Permanent traffic signs shall be
reflector and shall comply with the
following requirements except as
modified here under or as directed by
the Engineer.
2. Sign plates shall be manufactured
from sheet aluminum with a
minimum thickness of 3mm, unless
otherwise approved by the Engineer.
3. Information on signs shall be
constructed in extruded aluminum
plank sections, which will either be
self-locking or rear fixing, and the
aluminum shall be BS EN 485, or BS
1490 or other approved equivalent
International Standard.
4. All sign plates shall have clean,
smooth edges cut to the required
shape of the sign and shall be etched
4-30
-
8/12/2019 Technical Specifications of Roads
56/97
5.
Sign shall be covered with HighIntensity reflective sheeting.
Sheeting must have
the manufacturers
guarantee for a period
of not less than 5
years for Engineering
Grade and 7 years for
High Intensity.
Rear faces shall be
non-reflective grey
and should give a
similar life span to the
sign face.
Reflective sheeting
shall be fixed to the
sign plate either with
a heat activated
adhesive using
vacuum applicator or
with a pressure
sensitive adhesive
using a pressure roller
in accordance with the
sheeting
manufacturers
instructions.
Sign faces shall be
formed from a single
piece of reflective
4-31
-
8/12/2019 Technical Specifications of Roads
57/97
Sheeting, after
application to the sign
base, will not come
off at the edges nor
shall it peel off or
warp. Surface shall
be smooth, flat and
free from any bubbles,
pimples, edge
chipping or edge
shattering. Surface
4-32
-
8/12/2019 Technical Specifications of Roads
58/97
Corners of all
direction signs shall be rounded to a radius
of 75 mm.
6. Stiffening and Framing All stiffening and
framing shall be of hot
dipped galvanized
steel.
Signs constructed of
aluminum sheet shall,
when recommended
by the Traffic Sign
Manual, be framed on
all edges using hot
dipped galvanized
steel angle.
Stiffening to signs
constructed of
aluminum sheet,
having an area
exceeding 0.10 sq.m.
shall be confined to
horizontal lengths at
the top and bottom
edges of the sign
plate.
7. All rivets or other devices fixing sign
plates to their framework shall be of
non-staining steel or other materials
approved by the Engineer and shall
4-33
-
8/12/2019 Technical Specifications of Roads
59/97
All rivet and boltholes
shall be edge-sealed
with clear lacquer
after the application of
the plastics sheeting.
Rivets shall be spaced
at not more than 150
mm apart, around the
outside edge of the
sign plate and on
cross braces the
spacing shall be not
more than 300 mm.
Any rivet brought
through the sign face
shall be colored to
match the sign face.
Any rivet or other
device fixing sign
plates to their
framework shall have
protective washer of
nylon or other
approved insulating
material inserted
where they would be
in contact.
8. All materials shall be supplied in
new and unused condition except in
4-34
-
8/12/2019 Technical Specifications of Roads
60/97
4.7
ExecutionAll operations shall be performed in accordance with the specification, and in conformity
with the lines, grades, thickness and typical cross Section shown on the plans or established
by the Engineer. Only approved material shall be used in the construction. The embankment
and sub grade in fill shall be constructed utilizing only suitable material obtained from
roadway excavation or imported fill material from sources previously approved by the
competent authority.
4.7.1 Placement of fill
1. Prior to the placement of any fill
materials, the Contractor shall
conduct trial compaction tests as
directed by the Engineer.
Fill material used in the trials shall be with the proposed borrow or
excav