technical specifications of roads

Upload: citizenkaneg

Post on 03-Jun-2018

264 views

Category:

Documents


2 download

TRANSCRIPT

  • 8/12/2019 Technical Specifications of Roads

    1/97

    TECHNICAL SPECIFICATIONS OF ROADS

    September 2010

    i

  • 8/12/2019 Technical Specifications of Roads

    2/97

    Table of Contents

    1 ................................................................................................ 1-1SUMMARY OF WORK

    2 ................................................................................ 2-1DEMOLITION AND REMOVAL2.1 ................................................................................................................... 2-1General2.2 ......................................................................................................... 2-1Requirements2.3 .............................................................................................................. 2-3Submittals2.4 ............................................................................................................... 2-4Inspection2.5 ............................................................................................................. 2-4Preparation2.6 ............................................................................................................. 2-5Demolition2.7 ......................................................................................... 2-7Disposition of materials2.8 ................................................................................................. 2-7Cleanup and repair

    3 ........................................... 3-1GENERAL EARTHWORK AND SITE PREPARATION3.1 ................................................................................................................... 3-1General3.2 ......................................................................................................... 3-1Requirements3.3 .............................................................................................................. 3-3Submittals3.4 ....................................................................................................... 3-4Quality control3.5 .............................................................................. 3-6Delivery, storage and handling3.6 .................................................................................................... 3-7Site investigation3.7 ................................................................................................................. 3-9Products

    3.7.1 .............................................................................................. 3-9Existing ground3.7.2 .................................................................................................... 3-9Fill material3.7.3 ............................................................................................................ 3-10Water

    3.8 ............................................................................................................. 3-10Execution3.8.1 ..................................................................................................... 3-10Protection3.8.2 ........................................................................................................ 3-10Clearing3.8.3 ......................................................................... 3-12Existing ground preparation3.8.4 ............................................................................. 3-13Placement of fill material

    4 ........................................................................................ 4-1ROADS AND FOOTPATHS

    4.1 ............................................................................................................. 4-1Definitions4.2 ............................................................................................ 4-2General Requirements4.3 .............................................................................................................. 4-3Submittals

    4.3.1 .......................................................................................................... 4-3Samples4.3.2 .......................................................................................... 4-3Method Statement4.3.3 ............................................................................................... 4-4Shop Drawings4.3.4 ......................................................................................................... 4-5Mock-up

    4.4 ...................................................................................................... 4-6Quality Control4.5 ............................................................................. 4-8Delivery, Storage and Handling4.6 ................................................................................................................. 4-9Products

    4.6.1 ........................................................................................................ 4-9Subgrade4.6.2 ......................................................................................................... 4-9Rock fill4.6.3 ............................................................................... 4-10Pre-cast Concrete Curbs4.6.4 ................................................................................... 4-12In-situ concrete curbs4.6.5 ........................................................................... 4-13Interlocking paving blocks

    ii

  • 8/12/2019 Technical Specifications of Roads

    3/97

    iii

    4.6.6 ....................................................................................... 4-14Granular Sub Base4.6.7 ................................................................................... 4-16Aggregate Road Base4.6.8 .................................................................... 4-18Materials for Asphalt Concrete4.6.9 .......................................................................................... 4-21Asphalt Concrete4.6.10 ................................................................................... 4-29Prime and Tack coats

    4.6.11 ............................................................................... 4-29Road marking materials4.6.12 ................................................................................................. 4-30Traffic signs

    4.7 ............................................................................................................. 4-35Execution4.7.1 ........................................................................................... 4-35Placement of fill4.7.2 ................................................................................... 4-38Subgrade preparation4.7.3 .................................................................................................. 4-39Compaction4.7.4 ........................................................... 4-41Installation of precast concrete curbs4.7.5 ......................................................................... 4-43In-situ concrete curb laying4.7.6 ........................................................................................ 4-43Granular sub-base4.7.7 .................................................................................... 4-44Aggregate road-base4.7.8 ............................................................. 4-47Placement of asphalt paving course4.7.9 ........................................................ 4-67Application of road marking materials4.7.10 .......................................................................................... 4-68Erection of signs4.7.11 ...................................................................................................... 4-69Footpaths4.7.12 ......................................................... 4-69Installation of concrete paving blocks4.7.13 ................................................. 4-71Lifting and relaying concrete block paving

  • 8/12/2019 Technical Specifications of Roads

    4/97

    1 SUMMARY OF WORKThe project includes the upgrades of existing road network as a part of the upgrading of

    existing sanitary and storm sewers in a city. The contractor shall supply all supervision,

    labors, materials, temporary works, plant, machinery, equipment, parts, tools, supplies,transportation, testing and handling over the infrastructure works and facilities in perfect

    working condition.

    The contractor should note that there might be other contractors working in the same vicinity

    during the contract period. The contractor must consider this and coordinate his work to

    minimize any disruptions to others working in the area. Access to the work sites shall be

    maintained by the contractor at all times and he shall take all necessary steps to ensure thesafety of persons on the sites. All construction operations and site-established facilities shall

    be confined to within the site boundaries as shown on the drawings, unless otherwise

    approved by the engineer and the relevant authorities. Following such approvals, all such

    areas shall also be designated and treated as included within the site. The contractor shall be

    responsible for safeguarding all structures, plant or property near the site and shall provide all

    shoring, or supports as may be necessary to preserve their stability.

    1-1

  • 8/12/2019 Technical Specifications of Roads

    5/97

    2 DEMOLITION AND REMOVAL

    2.1 General

    This Section specifies requirements for demolition and removal of structures and includes,

    but is not limited to, the following:

    1. Complete demolition of designated existing buildings and/or

    structures.

    2. Removal of existing underground tanks, manholes and pipes

    3. Cutting into existing structures to make connections to new and

    existing work.

    4. Removal of existing protective coatings from concrete surfaces to

    permit resurfacing, patching and recoating of surfaces.

    5. Arrangement with relevant utility owners for renewal and/or

    relocation of their existing services.

    6. Removal or salvage of designated mechanical, electrical or other

    equipment.

    7. Removal from site and disposal of trash, debris, demolished

    materials and salvable materials.

    8. Removal and disposal of any hazardous material relating to or

    associated with demolition or new work.

    2.2 Requirements

    1. Demolition shall include removal of all below grade structures

    foundations, piles and pipes cables, etc and restoration to original

    conditions unless otherwise approved by the Engineer.

    2. The Contract Drawings are prepared using existing record

    drawings and they may not show all items to be removed. The

    Contractor shall therefore visit the site as necessary prior to

    2-1

  • 8/12/2019 Technical Specifications of Roads

    6/97

    3. Use of explosives shall not be permitted.

    4.

    Comply with all applicable safety precautions.5. Conform to applicable codes for demolition work, safety of

    structures, dust and noise control.

    6. Notify affected utility companies, pipeline owners and relevant

    authorities before starting work and comply with their

    requirements.

    7. Obtain required permits from the governing authorities and pay for

    all associated licenses, permits and inspections required by these

    authorities.

    8. Conform to applicable procedures when discovering hazardous or

    contaminated materials.

    9. Occupancy and use of facilities Client may continue to use process piping, equipment, and treatment

    facilities near and adjacent to the areas designated for selective

    demolition.

    Conduct selective demolition work in a manner that will not interfere

    with normal plant operations. This may require temporary facilities to

    be constructed as necessary, at no cost to the Client, to comply with

    this provision.

    Provide at least 72 hours advance notice to the Engineer and Client for

    those activities, which affect normal plant operations. No demolition

    can be started without prior approval of Engineer and Client.

    10. Conditions of facilities requiring demolition All facilities shall be handed over to the Contractor in an as is

    condition.

    Any preliminary work necessary to permit the main works to start shall

    be at the Contractors expense. This may include, but not be limited to,

    removal of tanks, pipelines or other structures containing raw or

    2-2

  • 8/12/2019 Technical Specifications of Roads

    7/97

    Conditions existing at the beginning of the project will be maintained

    by the Client so far as practical; however, the Client makes noguarantee that conditions will be the same when demolition is

    performed.

    All facilities will continue to be used for their intended purpose until

    turned over to the Contractor for rehabilitation.

    2.3 Submittals

    The Contractor is to prepare a method statement, which shall detail all aspects of the

    proposed demolition and associated work. The method statement shall be approved by the

    Engineer before any demolition work commences. The method statement shall incorporate at

    least the following items:

    1. Detailed description of the methods and equipment to be used for each

    operation as well as proposed sequence of demolition operations.

    2. Safety precautions required to ensure the safety of the workers,

    members of the public, and users of adjacent facilities or properties.

    3. The controlled demolition, removal and disposal of hazardous

    materials.

    4. The removal, protection and transportation of salvable materials.

    5. Coordination of the demolition work with other work in progress, and

    with any existing facility operations.

    6. Shut down schedule of equipment and disconnection sequence of the

    utilities involved.

    7. Accurate record of disconnected services and utilities

    8. Videotape of existing conditions prior to demolition.

    2-3

  • 8/12/2019 Technical Specifications of Roads

    8/97

    2.4 Inspection

    The Contractor shall inspect each area prior to performing any demolition work and record

    on videotape existing conditions as well as the condition of surrounding areas, clearly

    marking the location, date, time taken and the items which are to be demolished. Theoriginal film and a copy of it must be submitted to the Engineer prior to starting any

    demolition works. The Contractor shall ascertain that the property to be demolished lies

    within the project area as shown on the drawings and is the lawful property of the Client.

    2.5 Preparation

    1.

    Provide interior and exterior shoring, bracing and support as necessaryto prevent movement, settlement or collapse of both, facilities to be

    demolished and adjacent facilities, which are designated to remain.

    Stop all demolition work and notify the engineer immediately, if the

    stability of the facilities, which are to remain, appears to be in danger.

    If required, extra support shall be provided by the Contractor as

    deemed necessary by the Engineer.

    2.

    Temporary barricades and other forms of protection shall be providedto safeguard personnel and the facilities, which are to remain.

    3. Ensure free and safe access for Clients personnel to move to and from

    occupied portions of the facility.

    4. Prevent the migration of dust and dirt to occupied areas by

    constructing temporary partitions.

    5. Remaining facilities must be protected in the interval between

    completion of demolition and the beginning of the new construction.

    6. Cover and protect equipment, fixtures, surface finishes and floors

    remaining in the demolition area to prevent soiling or damage.

    7. Remove protective measures when work is completed

    8. Maintain and protect utilities, which are to remain, against damage

    during demolition.

    9. Provide bypass connections where necessary to serve occupied

    portions of facilities.

    10. Do not shut down any utilities without prior approval of Engineer.

    2-4

  • 8/12/2019 Technical Specifications of Roads

    9/97

    11. Do not interrupt existing utilities serving occupied facilities, unless

    authorized in writing by the Engineer.

    2.6 Demolition

    A. General

    Support or reinforce existing construction that is weakened by

    demolition in order not to over load structural elements.

    Completely backfill voids and below grade areas resulting from

    demolition work.

    Dust spread must be kept to a minimum by sprinkling anyrubbish with water twice daily.

    Maintain adequate fire protection, including extinguishers and

    operative water-hose lines during demolition of flammable

    materials.

    B. Traffic Control

    Demolition work and debris removal operations are to be

    carried out in such a manner that shall minimize interference

    with roads, streets, walks and/or other adjacent facilities.

    Provide alternative routes around closed or obstructed traffic

    ways as directed by the Engineer.

    Do not close, block or otherwise obstruct roads or facilities

    without written permission from the Client.

    C. Concrete and Masonry

    Demolish concrete and masonry in small sections. Saw cut concrete along straight lines to a depth of not less than

    50 mm, unless otherwise indicated on the Drawings.

    Make cuts in walls perpendicular to the face and aligned with

    the cut in the opposite wall face, and break out the remainder of

    the concrete.

    2-5

  • 8/12/2019 Technical Specifications of Roads

    10/97

    Use removal methods, which will not crack or structurally

    disturb the concrete, which will remain.

    Distribute demolition equipment throughout structure and

    promptly remove debris to avoid overloading supporting walls,slabs, and framing.

    Seal all wall and floor openings as directed by the Engineer.

    D. Pipes, Utilities and Conduits

    All pipelines to be connected shall be cleaned and purged as

    necessary to assure a safe environment before any cutting

    activities.

    The appropriate locations of pipes and conduits are generally

    shown on the Drawings. Where the cutting location is not

    shown, the pipe or conduit shall be removed back to the first

    joint or valve, or to a location approved in advance by the

    Engineer. Seal all remaining pipe ends as directed by the

    Engineer.

    Contractor shall inform the Engineer 72 hours prior to the

    cutting of any pipes or conduits leading to or from a structure

    to be demolished or to be relocated. These operations shall be

    coordinated with the relevant Department/Authority to assure

    that no interruptions are caused.

    All pipes or conduits which are encountered and which are not

    shown on the Drawings shall be brought to the attention of the

    Engineer.

    Utility lines not specifically noted for disposition, but which

    are encountered in the Work shall be capped, extended,

    protected or reworked as necessary for completion of the work

    as directed by the Engineer.

    E. Record of all disconnected services and utilities

    The Contractor shall keep on site, an accurate, up to date record

    of all disconnected services and utilities. Upon completion of

    2-6

  • 8/12/2019 Technical Specifications of Roads

    11/97

    2-7

    2.7 Disposition of materials

    1. All materials resulting from the demolition work, except those

    specifically identified to be salvaged, shall become the

    contractors property.

    2. Remove debris, rubbish, dust, fluids and other demolition

    materials not intended for salvage from the project site bytransporting and legally disposing of the materials off site to a

    dumping site, which is approved by all relevant authorities.

    The Contractor is responsible to pay all costs associated with

    transport and disposal.

    3. If any hazardous materials are encountered during demolition

    operations, the contractor must comply with all applicable

    regulations, laws and ordinances concerning removal, handling

    and protection against exposure or environmental pollution.

    4. Burning of removed materials shall not be permitted on the

    project site.

    2.8 Cleanup and repair

    1. Remove tools, equipment, demolished materials and protective

    devices from the site upon completion of demolition work, and

    leave all areas clean to the satisfaction of the Engineer.

    2. Restore all remaining structures, surfaces and facilities, which

    may have been damaged during demolition work to their

    original condition as required by the Engineer.

  • 8/12/2019 Technical Specifications of Roads

    12/97

    3 GENERAL EARTHWORK AND SITE PREPARATION

    3.1 General

    This Section specifies general requirements for earthworks and site preparation and includes, but is not limited to, the following:

    General Requirements Submittals and samples Quality Control Site Investigation

    Suitable fill material Clearing Preparation of existing ground Placement of fill materials

    3.2 Requirements

    Earthwork shall comply with the following requirements, unless otherwise approved by theEngineer.

    1. No trees or shrubs shall be disturbed, unless approved by

    the Engineer in writing.

    2. Blasting is not permitted.

    3. All excavation and backfilling shall be performed in dry

    conditions.

    4. Earthwork shall be constructed to the lines, grades,elevations, slopes, and cross sections indicated on the

    Drawings. Allowance shall be made as required for the

    thickness of any pavement, blinding concrete, lining and

    riprap.

    5. Levels to be recorded: Benchmarks and baselines are to be agreed with Engineer.

    3-1

  • 8/12/2019 Technical Specifications of Roads

    13/97

    Before the surface of any part of the Site is disturbed, the

    Contractor shall take and record levels on 10 m grids, unless

    otherwise agreed with the Engineer.

    Two working days notice is to be given to the Engineer so that therecording of levels can be performed in the presence of the

    Engineer.

    6. Slopes shall be smooth and uniform upon completion of

    the work.

    7. All excavated materials shall be utilized for the

    construction of embankment, shoulders and other such

    places as directed by the Engineer, unless the material is

    found to be unsuitable. If not immediately re-used, the

    excavated material shall be stockpiled in an area

    designated by the Engineer. Before excavating any

    material, the Contractor shall test to existing material to

    determine if it is suitable to the requirements of fill or

    subgrade material as specified. Suitable and unsuitable

    materials shall be stockpiled separately.

    8. The Contractor shall not waste or otherwise dispose of

    suitable excavated materials without written permission of

    the Engineer.

    9. Any excavated material not required or not suitable for use

    as filling material shall become the property of the

    Contractor and the Contractor shall be entirely responsible

    for its removal from the Site and for its appropriate

    disposal.

    10. If unsuitable materials are encountered in fill areas, such

    unsuitable materials shall be removed as instructed by the

    Engineer. Cross-sections shall be taken before and after

    cutting.

    11. Contractor at his own expense shall remove from the Site

    all material resulting from excess excavations below that

    required for the foundation, lining or bedding and shall

    3-2

  • 8/12/2019 Technical Specifications of Roads

    14/97

    12. If the bottom of any trench or structure excavation, while

    acceptable to the Engineer at the time of his inspection,may subsequently become unacceptable due to exposure to

    weather conditions, equipment traffic, flooding or other

    conditions encountered during the progress of the works,

    the Contractor shall remove such damaged, softened or

    loosened material as directed by the Engineer. The cost

    of the extra excavation and of the additional foundation

    materials required will be the Contractors responsibility if

    necessitated by his negligence.

    3.3 Submittals

    1. The contractor shall submit sufficient information to the

    Engineer, prior to purchase, in order to verify compliance

    with the specifications. Such information shall include at

    least the following: manufacturers name, suppliers name,

    product description, manufacturers technical data sheet,

    storage instructions, and application instructions.

    2. Samples shall be supplied for at least the following

    products or as requested by the Engineer.

    Borrow pit material (50 kgs) Excavated material (50 kgs) Water for soil compaction (1.5 l) Geotextile (30cm x 30cm)

    3. The Contractor shall provide separate method statements

    for at least the following activities or as requested by the

    Engineer.

    General excavation, backfill and compaction.

    3-3

  • 8/12/2019 Technical Specifications of Roads

    15/97

    Dewatering activities

    4. The Contractor shall submit drawings for at least cross

    sections for cut and fill areas.

    3.4 Quality control

    1. Inspection Requests shall be submitted to the Engineer

    during the on site installation work prior to proceeding

    with at least the following activities. Minimum

    notification time shall be 24 hours. Start of excavation Start of backfilling Sampling and testing

    2. Testing of all fill materials shall be carried out by a

    suitably equipped laboratory. The proposed laboratory

    shall be submitted to the Engineer for his review and

    approval at least 30 days before commencing earthwork.

    3. During the course of the work, tests shall be carried out

    under the supervision of the Engineer, to :

    Identify materials, and determine suitability. Determine compaction characteristics. Determine moisture content, and field

    density.

    4. Test Methods Maximum dry density of all soils shall be

    determined by BS 1377: Part 4: Method

    3.5/3.6.

    3-4

  • 8/12/2019 Technical Specifications of Roads

    16/97

    In situ field density of compacted soils shall

    be determined by BS 1377: Part 9 method

    2.1 or 2.2 (Sand Replacement Method).

    Other tests (C.B.R., Sieve analysis,Atterberg limits, etc.) shall be determined

    by relevant BS, AASHTO & ASTM

    methods as directed by the Engineer.

    5. Testing Density tests shall be made prior to removal

    of dewatering systems.

    Contractor shall adjust his operations to

    permit time to make tests and shall excavate

    and fill such holes as may be required for

    sampling and testing.

    A subsequent layer cannot be placed until

    the density of the proceeding layer has been

    tested and the area is approved by the

    Engineer.

    The minimum number of field density tests

    to be performed shall be one for every 1000

    m2 per layer of compacted existing ground

    or fill, unless otherwise approved by the

    Engineer.

    The minimum number of compaction tests to

    determine the maximum dry density (MDD)

    of the soil shall be at least one for every 30

    consecutive field density tests conducted or

    as directed by the Engineer due to changes

    in the soil.

    All other specified tests shall be carried out

    on every 2500m3 of fill material or as

    directed by the Engineer due to changes in

    materials.

    3-5

  • 8/12/2019 Technical Specifications of Roads

    17/97

    The Contractor shall maintain a daily log of

    all tests carried out for the Engineers

    review.

    6. Allowable Tolerances Finished surfaces: + 25 mm from specified

    level, unless otherwise approved by the

    Engineer.

    3.5 Delivery, storage and handling

    Delivery, stockpiling, storage and handling shall be according to the method statement or

    manufacturers recommendations along with the following provisions:

    Transportation, handling and storage shall at all

    times be performed in a manner to avoid product

    damage.

    Do not store products directly on ground, unless

    approved by the Engineer. Ensure adequate timber

    blocking is utilized to provide sufficient support.

    If stored outside, cover products as recommended

    by the manufacturer.

    All excavated or borrow materials shall be stock

    piled at least one meter away from the edge of the

    trenches.

    Stockpiling of the materials shall be in such a

    manner that segregation shall be kept to a minimum.

    The Contractor shall visually inspect all products

    upon delivery and report any damage to the

    Engineer. Any products damaged during delivery,

    storage or installation shall be marked by the

    Contractor and set aside. Any damaged products

    deemed unsuitable for repair by the Engineer shall

    3-6

  • 8/12/2019 Technical Specifications of Roads

    18/97

    3.6 Site investigation

    1. A soil investigation report may be provided

    by the Client or Engineer. Such reports are

    for information only and without any

    warranty as to the correctness of the

    information contained therein. Availability

    of this report to the Contractor does notrelieve him of his:

    a. Obligation to thoroughly investigate for himself the nature of the Site and

    the sub-soil conditions therein.

    b. Obligations and responsibilities under the terms and conditions of the

    Contract.

    2. Contractor shall be deemed to have visited

    the Site prior to submitting his Tender and

    made all necessary inspections and

    investigations and allowed for the following

    in his Tender:

    a. Means of access and working space.

    b. Nature of the ground and sub-soils.

    c. Presence of existing foundations or other hidden obstructions.

    d. Level of the water table.

    e. Extent of rock.

    f. Support to neighboring properties and structures.

    g. All factors affecting the Work.

    3. Any information made available to the

    Contractor, either in these documents or by

    any other source, will not relieve the

    3-7

  • 8/12/2019 Technical Specifications of Roads

    19/97

    4. Contractor shall be deemed to have

    contacted the relevant authorities to establish

    the existence of any existing, live or

    redundant services adjacent to or passing

    through the area of work and shall be

    deemed to have allowed in his Tender for

    their location, diversion, demolition or

    removal.

    5. Boring logs and related information depict

    subsurface conditions only at the specific

    locations and at the particular time

    designated on the logs.

    a. Soil conditions at other locations may differ from conditions occurring at

    the boring locations.

    b. Passage of time may result in a change of the subsurface conditions or

    water levels at the boring locations.

    c. Client does not guarantee any statements, opinions, or conclusions

    contained in the report.

    d. Contractor shall assume all responsibility for:

    Deductions and conclusions made by him

    regarding the nature of the materials to be

    excavated;

    Maintaining the required excavations; Carrying out the work affected by the subsurface

    conditions at the site of the works.

    e. Neither the Client nor the Engineer shall be liable for any loss sustained, if

    the actual conditions encountered during progress of the work differs from

    the borings, samples, tests, and/or reports provided.

    3-8

  • 8/12/2019 Technical Specifications of Roads

    20/97

    3.7 Products

    3.7.1

    Existing groundAfter site clearing, the top compacted 200mm of the existing ground shall be comprised of

    material having the minimum qualities of suitable fill and shall be compacted to 95% of the

    MDD, unless otherwise directed by the Engineer.

    3.7.2 Fill material

    1. Suitable fill material shall consist of

    excavated or borrow material free fromrubbish, vegetation, perishable matter, tree

    and plant stumps and other objectionable

    matter.

    2. Suitable fill material shall comply with the

    following requirements, unless otherwise

    approved by the Engineer.

    For Embankments with maximum height 2m, fill materials

    should comply with "AASHTO" classifications A-1, A-2-4

    or A-2-5 materials with min. C.B.R. Soaked value of 10%

    at 95% of M.D.D., Materials classified as A-3 may only be

    utilized in areas approved by the Engineer. Generally,

    materials classified as A-5,A-6, A-7 shall never be used to

    construct any Embankment height .

    For Embankment higher than 2m, the top 2m shall comply

    with the previous requirement. The remaining height (lower

    part of Embankment) should comply with the same req.

    except if A-2-6, A-2-7 or A-4 have been improved and

    accepted by the Engineer to comply with the following:

    Min.C.B.R. soaked value = 3% at 95% of M.D.D. Max. swelling of C.B.R. test 3%

    3-9

  • 8/12/2019 Technical Specifications of Roads

    21/97

    Rock fill may be utilized except for the top 2m of

    Embankment only as directed by the Engineer and

    specified later.

    3.

    When sufficient quantities of suitable fillmaterials cannot be obtained from site

    excavations, additional material meeting the

    requirements of Fill Materials shall be

    obtained from approved borrow areas.

    4. The Contractor shall be responsible for the

    arrangement and payment for all borrow

    material.

    3.7.3 Water

    Water used for compacting fill shall be clean and free from oil, grease, organic matter,

    suspended fine sediment or deleterious materials, unless otherwise approved by the Engineer.

    3.8 Execution

    3.8.1 Protection

    Protect benchmarks and other permanent structures in the Site area from damage or

    displacement.

    3.8.2 Clearing

    A. General

    1. Contractor shall clear the Site area of

    all vegetation, rubbish, debris and

    other objectionable materials. Soils

    suitable for landscaping or

    agricultural purposes shall be

    stockpiled separately for replacement

    if directed by the Engineer.

    3-10

  • 8/12/2019 Technical Specifications of Roads

    22/97

    2. Contractor shall also clear the access

    routes to the Site and any other areas

    deemed necessary by the Engineer to

    facilitate the construction of theWorks.

    3. When clearing vegetation, the

    Contractor shall ensure that the roots

    of the trees, bushes, shrubs, etc. are

    fully removed. Holes left by stumps

    or roots shall be filed with suitable

    material to the satisfaction of the

    Engineer.

    4. Contractor shall dispose of all

    cleared vegetation, rubbish, debris

    and other objectionable materials in a

    controlled manner to a location

    approved by the relevant authorities.

    5. Contractor shall be responsible for

    the proper upkeep and maintenance

    of the Site and the Works and shall

    remove from the Site, rubbish and

    other waste as it accumulates.

    6. Existing roads, improvements,

    facilities, adjacent property etc. shall

    be protected to the satisfaction of the

    Engineer.

    B. Existing services

    1. Contractor shall check with the

    relevant authorities to determine

    what existing underground services

    are present in the Site area.

    3-11

  • 8/12/2019 Technical Specifications of Roads

    23/97

    2. Contractor shall locate and

    effectively seal off drain ends.

    3. When necessary, the Contractor shall

    divert services still in use and provide all temporary works

    necessary to maintain such services

    in full functional order. Such

    services shall be reinstated to the

    approval of the relevant authorities at

    the earliest opportunity when

    carrying out such work. The

    contractor must comply with

    regulations and obtain necessary

    permits and No Objection

    Certificates.

    3.8.3 Existing ground preparation

    1. After site clearing, the existing ground surfaces shall be graded to

    remove surface irregularities.

    2. In cut areas, excavation shall extend for the full-designated width

    down to the bottom of the excavation.

    3. The ground surface shall be scarified and loosened to a minimum

    depth of 200 mm (except where the material is classified as rock).

    If unsuitable materials are encountered, they shall be

    excavated to a depth as directed by the Engineer.

    The scarified material shall watered as necessary to

    achieve uniform moisture content suitable for

    compaction.

    The scarified material shall then be compacted to at least

    95% MDD below structures, roadways or parking areas

    and at least 90% below landscaped or open areas.

    3-12

  • 8/12/2019 Technical Specifications of Roads

    24/97

    4. Surface materials of the existing ground shall be compacted and

    bonded with the first layer of earth fill as specified for subsequent

    layers of earth fill.

    5.

    Rock Foundations All rock foundation and abutment surfaces shall be

    cleared of all loose materials by hand or other effective

    means and shall be free of standing water when fill is

    placed.

    Fill placed immediately adjacent to such rock foundations

    or where not accessible with large compaction equipment

    shall be compacted to the specified density by means of

    manually directed power tampers or plate vibrators.

    6. Benching Where slope of existing soils to receive fill exceeds

    1H:3V, horizontal benches shall be cut to key the new fill

    material to the existing soils.

    At least 600 mm of existing soil normal to the original

    slope shall be removed and re-compacted as the new fill

    is brought up in layers.

    3.8.4 Placement of fill material

    1. Placement of fill materials shall comply with the following

    requirements:

    Distribution of materials throughout each layer shall be

    essentially uniform.

    Fill shall be free from lenses, pockets, streaks, or layers of

    material differing substantially in texture or gradation from the

    surrounding material.

    If the surface of any layer becomes too hard and/or smooth for

    proper bond with the succeeding layer, it shall be scarified

    parallel to the axis of the fill to a depth not less than 75 mm

    before the next layer is placed.

    3-13

  • 8/12/2019 Technical Specifications of Roads

    25/97

    3-14

    Top surface of each layer of fill shall be approximately level

    during construction. The final surface of fill shall be finished

    with a 2 percent crown or cross-slope as suitable for site

    drainage, unless shown otherwise on the drawings.2. Field Compaction

    Fill material in landscaped or open areas shall be compacted in

    loose lifts up to 250mm thick to at least than 90% MDD.

    Fill material below structures and paved areas shall be

    compacted to at least 95% MDD in 200mm maximum loose

    lifts, unless otherwise directed by the Engineer.

    All fill shall be moistened or aerated to control the moisture

    content to within a range of 3% of the optimum moisture

    content when compacted.

    Uniform moisture distribution shall be obtained by any

    approved method prior to the compaction of the layer.

    If the top surface of the preceding layer of compacted fill or

    foundation becomes too dry or wet to permit suitable bond, it

    shall be scarified and moistened by sprinkling or aerated to

    acceptable moisture content prior to the placement of the next

    layer.

  • 8/12/2019 Technical Specifications of Roads

    26/97

    4 ROADS AND FOOTPATHS

    This section covers all road works and footpaths and includes, but is not limited to, the

    following: Geo-textile Fabric Pre-cast Concrete Curbs Interlocking Paving Blocks Free draining materials Stabilizing rock fill Rock fill

    Subgrade Granular Sub Base Granular Road Base Bituminous Paving Courses Road Markings Traffic Signs Trench Excavation and Reinstatement in Roads

    4.1 Definitions

    The following definitions shall pertain to words or phrases as utilized in this Section:

    Embankment shall mean any fill placed above the existing

    ground or cut.

    Fill shall mean suitable material utilized to raise an embankment

    up to the bottom of subgrade. Subgrade shall mean the compacted top surface (150 to 300mm)

    of the existing ground (or in some cases fill) below the formation

    level.

    Formation level shall mean top of subgrade after final

    compaction.

    Formation shall mean the top surface of the subgrade after

    preparation for subsequent layers of material.

    4-1

  • 8/12/2019 Technical Specifications of Roads

    27/97

    Wearing course shall mean the top layer of asphalt concrete

    directly supporting the traffic.

    Asphalt concrete shall mean a hot mixture of asphalt cement and

    well-graded, high quality aggregate, thoroughly compacted into auniform dense mass.

    Borrow material shall mean suitable fill material taken from an

    approved source.

    OMC shall mean optimum moisture content. MDD shall mean maximum dry density. CBR shall mean California bearing ratio. Prime Coat shall mean a thin film of liquid asphalt applied on a

    previously prepared untreated soil.

    Tack Coat shall mean a thin film of liquid asphalt applied on a

    previously prepared bituminous course or to an existing bituminous

    surface.

    Foot Path shall mean a passage paved by interlocking blocks for

    pedestrian traffic.

    Coarse aggregate shall mean that material retained on a 4.75 mm

    sieve.

    Fine aggregate shall mean that material passing a 4.75 mm sieve.

    4.2 General Requirements

    Product manufacturer, testing and installation shall comply with the following requirements,

    unless otherwise approved by the Engineer.

    Paving shall conform to the lines and levels on the drawings unless

    otherwise approved by the Engineer.

    All materials for use in construction shall be obtained only from

    sources approved by the Engineer.

    The specific source of materials shall not be changed without prior

    written approval of the Engineer.

    If the grading and quality of material delivered to the site does not

    conform to the grading and quality as previously inspected and

    4-2

  • 8/12/2019 Technical Specifications of Roads

    28/97

    Sufficient materials must be stored in stockpiles to allow for testing

    and approval of such materials prior to use in works.

    4.3 Submittals

    The contractor shall submit sufficient information to the Engineer, prior to purchase, in order

    to verify compliance with the specifications. Such information shall include at least thefollowing, unless otherwise required by the Engineer.

    Manufacturers name. Suppliers name. Product name and description. Manufacturers technical data. Storage instructions. Relevant test results of all materials specified. Application or installation instructions. Details of asphalt plant, location and calibration results

    4.3.1 Samples

    Samples shall be supplied for at least the products included in Table 4-1 or as requested by

    the Engineer. All sampling shall be witnessed by the Engineer, unless agreed otherwise.

    4.3.2 Method Statement

    The Contractor shall provide separate method statements for at least the following activities

    or as requested by the Engineer.

    Site clearing and earthwork. Dewatering activities (if necessary).

    4-3

  • 8/12/2019 Technical Specifications of Roads

    29/97

    Method of mixing and laying for sub-base, road base

    and wet-mix.

    Method of surface preparations and application of prime

    and tack coat. Method of mixing, laying and compaction of bitumen

    mixtures.

    Asphalt plant calibration.

    4.3.3 Shop Drawings

    The Contractor shall submit shop drawings for at least the proposed roadway Sections.

    Table 4-1. Sampling Schedule

    Item Sample

    Geo-textile Fabric: 20cm x 20cm sample of each proposed fabric.

    Pre-cast Concrete Curbs If requested, three sample of each size.

    Concrete Paving Blocks Fifteen sample of each size and color and as required for

    testing.

    Aggregates 100 kgs of each size and type.

    Fill Material 100 kgs from each source.

    Existing Material 100 kgs from each source.

    Free Draining Material 50 kgs from each source.

    Subgrade Material 100 kgs from each source.

    Rock fill Material 500kgs from each source.

    Granular sub-base Material 100kgs from each source.

    Road Base Material 100kgs from each source.Bedding Sand 25kgs from each source.

    Bituminous Mixes 50kgs from each source.

    Prime Coat 3 liters from each source.

    Tack Coat 3 liters from each source.

    Bitumen 3 liters from each source.

    Road Marking Materials Applied samples and or as requested by the Engineer.

    Signs Prepared samples as requested by the Engineer.

    4-4

  • 8/12/2019 Technical Specifications of Roads

    30/97

    4.3.4 Mock-up

    The Contractor shall prepare a mock-up for at least the following installations or as requested

    by the Engineer.1. Concrete Paving Blocks

    Provide mockup of paving layout where directed by the

    Engineer.

    Size: 15 - 20 m 2. Laying of bedding course, installation of paving blocks and

    accessories to indicated pattern shall be included.

    Show range of shades, color, and texture of pavers. Accepted mockup may become part of the work.

    2. Rock Fill Provide mock-up of laying trial as directed by the Engineer. Length 100 m, width 4 m.

    3. Sub-Base Provide mock-up of laying trial as directed by the Engineer. Length 30 m, width 4 m.

    4. Road Base Provide mock-up of laying trial as directed by the Engineer. Length 30 m, width 4 m.

    5. Binder Course Provide mock-up of laying trial as directed by the Engineer. Length 30 m, width 4 m.

    6. Asphalt Wearing Course Provide laying trial as directed by the Engineer. Length 30 m, width 4 m.

    4-5

  • 8/12/2019 Technical Specifications of Roads

    31/97

    4.4 Quality Control

    1. Prior to dispatch from the factory, the

    Contractor shall notify the Engineer, insufficient time to allow the Engineer or his

    representatives to inspect and test the products,

    if so desired. All notifications shall be made by

    written Inspection Requests. An advance

    copy may be faxed to the Engineers office, but

    the original must arrive before the scheduled day

    of inspection.2. Inspection Requests shall be submitted to the

    Engineer during the on site installation work

    prior to proceeding with at least the following

    activities. Minimum notification time shall be

    24 hours.

    Start of excavation Start of backfilling Start of free draining material Start of stabilizing material Start of rock fill Start of subgrade Start of sub-base and road base and wet mix mixing and laying. Start of prime coat and tack coat application. Start of bituminous paving mixtures. Sampling and testing.

    3. Testing of all materials shall be carried out by a

    suitably equipped site laboratory or in an

    approved independent laboratory.

    Routine materials testing and site testing shall always be

    conducted in the site laboratory, unless otherwise agreed by the

    Engineer.

    4-6

  • 8/12/2019 Technical Specifications of Roads

    32/97

    All sampling shall be witnessed by the Engineer, unless

    otherwise directed by the Engineer.

    During the course of the work, all required tests shall be carried

    out under the supervision of the Engineer, to ascertain thesuitability of materials according to this speciation.

    The Contractor shall maintain a daily log of all tests carried out

    for the Engineers review.

    4. Test Methods Compaction tests to establish maximum dry density for

    all soils shall be determined by BS 1377: Part 4:

    Method 3.5/3.6 as appropriate.

    In situ density of compacted soils shall be determined

    by BS 1377: Part 9 Method 2.1 or 2.2 (as appropriate).

    Cone penetration test: TRL Method or BS 1377 as

    directed by the Engineer.

    Density tests shall be made prior to removal of

    dewatering systems.

    Contractor shall adjust his operations to permit time to

    make tests and shall excavate and fill such holes as may

    be required for sampling and testing.

    A subsequent layer cannot be placed until the density of

    the proceeding layer has been tested and the area

    approved.

    At least one field density test shall be conducted for

    each layer at each structure (or every 200m2), unless

    otherwise directed by the Engineer.

    At least one compaction test (MDD/OMC) shall be

    conducted for every 30 field. Density tests conducted or

    as directed by the Engineer due to changes in the soil.

    At least one complete soil analysis shall be carried on

    each type of material as specified in relevant Clauses or

    as directed by the Engineer due to changes in the soil.

    4-7

  • 8/12/2019 Technical Specifications of Roads

    33/97

    The allowable soil-bearing load shall be verified by

    dynamic cone penetration test if directed by the

    Engineer.

    4.5 Delivery, Storage and Handling

    Delivery, storage and handling shall be according to the manufacturers recommendations

    along with the following provisions:

    Transportation, handling and storage shall at all times be

    performed in a manner to avoid product damage.

    Only nylon slings shall be allowed for lifting products.Steel chains, clamps or cables shall not be allowed for

    lifting purposes, unless approved by the Engineer. Steel

    chains or cables may be allowed for securing products

    during transport or storage provided protective padding or

    timber blocking is utilized.

    Do not store products directly on ground, unless approved

    by the Engineer. Ensure adequate timber blocking is

    utilized to provide sufficient support.

    Where product manufacturer recommends storage under

    controlled temperatures, the Contractor must provide an

    enclosed, insulated, cool store maintained at the proper

    temperature 24 hours a day.

    If stored outside, cover products to prevent UV degradation

    as recommended by the manufacturer.

    The Contractor shall visually inspect all products upon

    delivery and report any damage to the Engineer.

    a. Any products damaged during delivery, storage or

    installation shall be marked by the Contractor and set aside.

    b. Proposals for repair of any damaged products shall be

    submitted in writing to the Engineer for approval.

    c. No repairs to damaged products shall be attempted without

    the Engineers approval.

    4-8

  • 8/12/2019 Technical Specifications of Roads

    34/97

    d. Any damaged products deemed unsuitable for repair by the

    Engineer shall be removed from site and replaced at the

    Contractors expense.

    4.6 Products

    4.6.1 Subgrade

    1. Suitable subgrade materials shall be a minim. 30

    cm thick after compaction in both Embankment

    and cut areas using materials of the followingrequirements:

    Materials classified by "AASHTO" as A-1-a(0) , A-1-b(0) and A-

    2-4(0).

    Materials having a min. soaked C.B.R. of 15% at 98% of M.D.D. Materials being reasonably well graded with sufficient fines to

    permit compaction and compaction testing.

    Materials with max. size 75mm. Materials free from organic matter, shale and other deleterious

    material

    2. Minimum test frequency One sample shall be tested to confirm the above properties for

    every 1500m (or part there of) placed or compacted.

    Two in-situ density tests shall be made every 800m2 of subgrade

    laid.

    4.6.2 Rock fill

    1. Rock fill used as stabilizing materials where Embankment

    foundation is found unstable:

    Shall be 100% hard durable crushed rock of suitable size. Free from organic matter, shale and other deleterious material.

    4-9

  • 8/12/2019 Technical Specifications of Roads

    35/97

    Shall bind readily to form a stable mass with sound, smooth, well-

    knit upper surface free from loose material.

    2.

    Rock fill used to construct high Embankments: Materials consisting predominantly of rock fragments of such a

    size that it cannot be placed in layers of the thickness allowed

    without crushing , or further breaking down, may be placed in high

    Embankment in layers not exceeding twice the average size of the

    larger fragments. However, no layer of rock fill shall exceed 80 cm

    loose thickness.

    Top surface voids should be completely filled with smaller

    fragments sand or gravel.

    Materials should be approved by the Engineer.

    4.6.3 Pre-cast Concrete Curbs

    1. A company specializing in curbstone manufacturing with at

    least three (3) years experience, unless otherwise agreed by the

    Engineer.

    2. Pre-cast curbs shall conform to BS 7263: Part 1: 1994 except as

    modified in this Section.

    3. This Section covers non-mountable curbs, dropped curbs, heel

    curbs, quadrants, flush curbs, curb ramps, noses, channel

    blocks and edgings.

    4. Materials for precast curbs Cement

    a. Portland cement, conforming to BS 4027 or ASTM C 150, Type V.

    b. Minimum cement content shall be 300 kg/m 3.

    Aggregates

    a. Combined gradation shall be as follows, unless otherwise agreed by the

    Engineer. Sieve analysis shall be according to BS 812: Part 103.

    Table 4-2. Aggregate gradation for precast curbs

    4-10

  • 8/12/2019 Technical Specifications of Roads

    36/97

    ASTM Sieve Size(mm)

    % By WeightPassing

    20.0 95 -10014.0 80 - 100

    10.0 60 - 855.0 40 - 652.36 22 - 421.18 12 - 32

    0.600 7-230.300 4 - 150.150 2 - 100.075 0 - 2

    5. Manufacturer: Elements shall be manufactured to the

    designated dimensions as shown on the Contract Drawings,

    unless otherwise directed by the Engineer. Precast curbs shall

    be formed by elements 900 mm long where required to be laid

    in straight lines, unless otherwise approved by the Engineer.

    May be reduced to 200 mm long where required to be laid to

    curves depending on the radii of the curves. Pre-cast

    curbstones shall be hydraulically pressed precast products

    manufactured in a fully automatic batching plant and

    complying with the requirements of BS 7263: Part 1 except as

    modified hereunder.

    a. They shall be uniform in color free from cracks, flaws of other

    defects and shall have well defined arises.

    b. If required by the Engineer 100mm diameter cores shall be

    taken from the pre-cast elements to ascertain that the concrete

    strength is not less than specified value.

    Cores shall be tested to BS 1881: Part 120 A sample of 3 products shall be taken from a

    consignment of not more than 1000 products.

    Two cores shall be cut form each of three samples. Mean compression strength of two cores shall

    reported as the compressive strength of that

    product.

    4-11

  • 8/12/2019 Technical Specifications of Roads

    37/97

    Average compressive strength of 3 products shall

    not be less than 250kg/cm 2.

    Mean water absorption of cubes when tested in

    accordance with B7263: Part 1 shall not be greaterthan 3.0%.

    Cure units by either: low-pressure steam, steam

    vapor, or other similar process as approved by the

    Engineer.

    c. Finishes Ensure exposed-to-view finish surfaces of pre-cast

    concrete members are fair faced, uniform in color

    and appearance.

    Cure members under identical conditions to

    develop required quality. Minimize appearance

    blemishes such as non-uniformity, staining, or

    surface cracking.

    Small surfaces holes, normal form joint marks,

    and minor chips are acceptable, if approved by the

    Engineer. Major or unsightly imperfections,

    honeycombs, or structural defects are not

    acceptable.

    d. Tolerances: Tolerances of manufacture shall be 3 mm in any

    one dimension and end faces shall be truly perpendicular to the

    base.

    e. Testing Frequency: As directed by the Engineer.

    4.6.4 In-situ concrete curbs

    1. A. Cast in-situ curbs shall comply with the following except as

    modified by the Engineer.

    Min. compressive strength of cubes after 28 days, 250

    kg/cm2.

    4-12

  • 8/12/2019 Technical Specifications of Roads

    38/97

    Cement used shall conform BS4027 or ASTM C150 Type

    V.

    Use of additives may be allowed if approved by the

    Engineer.

    4.6.5 Interlocking paving blocks

    1. Concrete Paving Blocks Manufacturer: A company specializing in exterior

    concrete paving block manufacturing with three (3) years

    experience unless otherwise agreed by the Engineer.

    Installer: A company specializing in installing exterior

    pavers with three (3) years experience, unless otherwise

    agreed by the Engineer.

    2. Materials and Manufacture Portland cement conforming to BS 4027 or ASTM, C150

    Type V.

    Thickness shall be 60mm or 80mm on footpaths, unless

    otherwise shown on the Drawings or instructed by the

    Engineer.

    Color and pattern of the blocks shall be as noted on the

    drawings or as directed by the Engineer.

    Pigment (inorganic) shall comply with BS 1014.

    Minimum pigment content shall be 5% by weight of

    cement, unless otherwise approved by the Engineer.

    Compressive Strength.

    a. 350 kg/cm 2 for roads (8 cm thickness).

    b. Strength 250 kg/cm 2 for footpath (6 cm thickness).

    Water Absorption

    a. Average of 3 specimens tested in accordance with ASTM C140 shall not

    be greater than 5%.

    4-13

  • 8/12/2019 Technical Specifications of Roads

    39/97

    b. No individual result shall be greater than 7%.

    Sulphate and Chlorides

    a. The total sulphate content shall not be more than 4.0% by weight of thecement in the mix.

    b. The total chloride content shall not be more than 0.15% weight of mix.

    Bedding Sand Shall consist of non-plastic sand meeting the following

    properties, unless otherwise approved by the Engineer.

    Table 4-3. Properties of bedding sand

    Sieve Size (mm) Percent Passing by Wet Sieving

    10 1005.0 95 100

    2.36 80 1001.18 50 85

    0.300 10 300.150 5 15

    0.075 0 3Test Standard Limit

    Clay, silt and dust content BS 812: Part 103.1 3.0% Max

    Sulphates (SO 3) BSI 377: Part 3 Method 5 0.3% Max

    Chlorides (Cl) BSI 3777: Part 3 Method 7 0.5% Max

    4.6.6 Granular Sub Base

    1. Hard, durable gravel and/or crushed gravel or crushed stone

    with sand and silt.

    2. Free of clay balls or other deleterious substances.

    3. If required approved binding material shall be added to the

    coarse gravel to improve the binding property of sub-base

    material but in no case, the percentage of binding material

    added shall not be more than 20% of the sub-base.

    4-14

  • 8/12/2019 Technical Specifications of Roads

    40/97

    4. Grading shall be one of the following classes when tested in

    accordance with BS 1377: Part 2: Method 9.2. Selected class

    shall be as directed by the Engineer

    Table 4-4. Gradation of Granular Sub Base

    % By Weight PassingSieve Size / No.

    Class A Class B Class C

    3" 100 100 100

    2" 90 - 100 90-100 90-100

    No. 4 35 - 70 40-90 50-100

    No. 200 0 - 20 0-20 0-30

    5. Materials shall conform with the following requirements:

    Table 4-5. Requirements of Granular Sub Base

    Test Standard Limit

    Liquid Limit BS 1377: Part 2 : Method 4.5 max 30%Plasticity Index BS 1377 : Part 2 : Method 5 max 8%

    % water absorption after 24 hours

    submerged in waterLocal codes max 10%

    Clay lumps and friable particles in

    aggregatesLocal codes-T 113 max 10%

    Los Angeles Abrasion ASTM C131/C535 max 50%

    Compaction Test (MDD) BS 1377: Part 4: Method 3.6 2.1 Mg/m Min

    In-situ Density Test BS 1377: Part 9: Method 2.2 min 98%

    CBR at 98% MDD (96 hour soaked) BS 1377: Part 4 Method 7 min 25%

    Swelling of soaked C.B.R. moulds No swelling

    6. Minimum Test Frequency

    4-15

  • 8/12/2019 Technical Specifications of Roads

    41/97

    One sample every 1000m shall be tested for

    complete analysis unless otherwise approved by

    the Engineer.

    Three in-situ density tests shall be made every1000m of granular sub base laid, unless

    otherwise approved by the Engineer.

    One in-situ density shall be carried out for every

    150 linear meter of shoulder or footpath, unless

    otherwise approved the Engineer.

    4.6.7 Aggregate Road Base

    1. Hard, durable crushed gravel or crushed stone. The amount of

    crushing shall be such that at least 80% (by weight) of the

    pieces retained on 4.75mm sieve shall have at least one

    mechanically fractured face. Material shall consist of uniform

    mixtures of gravel and or crushed gravel with sand, silt and

    clay conforming to the following gradation limits.

    2. Free of organic matter or other deleterious substances.

    3. Grading shall be one of the following classes when tested in

    accordance with BS 1377: Part 2: Method 9.2. Selected class

    shall be as directed by the Engineer

    Table 4-6. Gradation of Aggregate Road Base

    % by Weight PassingSieve Size

    /No. Class A Class B Class C

    2" 100

    1.5" 70 -100 100

    1" 55 - 85 70-100 100

    3/4" 50 - 80 60-90 70-100

    3/8" 40 - 70 45-75 50-80

    No.4 30 - 60 30-60 35-65

    4-16

  • 8/12/2019 Technical Specifications of Roads

    42/97

    No.10 20 - 50 20-50 25-50

    No.40 10 - 30 10-30 15-30

    N0.200 5 - 15 5-15 5-15

    4. Material shall conform with the following requirements:

    Table 4-7. Requirements of Aggregate Road Base

    Test Standard Limit

    Liquid Limit BS 1377: Part 2: Method 4.5 max 30%

    Plasticity Index BS 1377: Part 2: Method 5 max 8%

    Linear shrinkage BS 1377: Part 2: Method 6.5 Max 7%

    Organic Impurities BS 1377: Part 3: Method 3 Max 0.2%

    % absorption submerged in water for 24

    hours.

    Local codes max 10%

    Clay lumps and friable particles Local codes T-113 max 5%

    Los Angeles Abrasion ASTM C131/C535 max 50%

    Thin and Elongated particles Local codes Max 10%

    Compaction Test (MDD) BS 1377: Part 4: Method 3.6 min 2.2

    Mg/m

    In-situ Density Test BS 1377: Part 9: Method 2.2 100%

    CBR at 100% MDD (96 hr. soaked) BS 1377: Part 4: Method 7 min 80%

    Swelling of soaked C.B.R. moulds No swelling

    5. Minimum Test Frequency

    One sample every 1000 m 3 shall be tested. Two in-situ density tests shall be made every 500 m 2 of

    aggregate road base laid.

    4-17

  • 8/12/2019 Technical Specifications of Roads

    43/97

    4.6.8 Materials for Asphalt Concrete

    1. Mineral aggregates for bituminous paving course shall consist

    of coarse aggregates, fine aggregates and filler material all

    complying with the following requirements.2. Prior to the production of aggregates or delivery of aggregates

    the Contractor shall notify the Engineer of the source of

    aggregates for inspection of the borrow or quarry area. All

    sources of aggregates shall be approved by the Engineer prior

    to the processing of material.

    3. The properties of aggregates specified in this section shall be

    for aggregates from individual sources or individual stockpiles.

    4. If the grading and other specified properties of the material

    delivered to the site does not conform to the same properties of

    originally approved samples or does not comply with the

    specification, the Engineer reserves the right to reject such

    materials at the site of the work. If required by the Engineer

    the Contractor shall submit to the Engineer the original

    invoices for any delivery of mineral aggregates including filler.

    5. Coarse Aggregates (those retained on a 4.75mm sieve) Shall consist of crushed rock or crushed gravel. Shall be clean, hard, tough, durable and sound. Shall be of uniform quality and free from decomposed

    stone, shale, clay lumps and other deleterious substances.

    Mineralogical tests shall be carried out on the aggregates,

    if requested by the Engineer

    Crushed gravel. Consists of products obtained by

    crushing material that has first been screened in such a

    manner that not less than 90% of the material to be

    crushed is retained on an ASTM 9.5 mm sieve.

    100% (by weight) of each stockpile of aggregate retained

    on 2.36mm sieve shall have at least one crushed face.

    4-18

  • 8/12/2019 Technical Specifications of Roads

    44/97

    At least 85% (by weight) of each separate stockpile of

    aggregate retained on 2.36m sieve shall have all faces

    crushed, unless otherwise approved by the Engineer.

    Coarse aggregate in each individual stock pile shall have

    properties which comply with the following values:

    Table 4-8. Requirements of Materials for Asphalt Concrete

    Test Standard Binder Course Wearing Course

    Los Angeles Abrasion ASTM C131/C535 max 40% max 40%

    Thin & Elongated particles Local codes max 10% max 10%

    Clay lumps and friable particlesLocal codes 0%* 0%*

    % water absorption Local codes max 5% max 5%

    Organic Impurities BS 1377 Max 0.05% Max 0.05%

    6. Fine aggregate shall be obtained from 100% crushed gravel or

    crushed rock, unless otherwise approved by the Engineer.

    If approved by the Engineer, a maximum of 25%

    (by weight) of fine aggregate may be uncrushed if it

    is separately fed into the plant.

    Use of dune sand shall not be permitted. Fine aggregates shall be Non-Plastic when tested for

    Plasticity Index:

    7. Filler Material When the combined grading of the coarse and fine

    aggregates is deficient in material passing the

    ASTM No. 200 sieve, external mineral filler shall

    be added as approved by the Engineer at the

    Contractors expense.

    Mineral filler shall consist of finely ground non-

    plastic particles of limestone or cement.

    4-19

  • 8/12/2019 Technical Specifications of Roads

    45/97

    Mineral filler shall be thoroughly dry and free from

    organic substances and clay.

    Test frequency is as directed by the Engineer.

    8. Bitumen Binder Shall be penetration grade 40/50 or 60/70 as

    directed by the Engineer.

    Bitumen shall be prepared by refining crude

    petroleum.

    Shall be homogeneous and free from water. Shall not foam when heated to 175C. Shall conform to the following requirements, unless

    otherwise accepted by the Engineer.

    Bitumen heated 100C above the maximum

    temperature obtained form viscosity temperature

    relationship shall be considered over-heated and

    shall be removed from site and disposed of by the

    Contractor at his own expense. Bitumen shall be

    heated only in approved boilers or bulk storage

    containers equipped with adequate and accurate

    thermometers.

    When filling the bitumen from distributors boilers

    or bulk containers, the bitumen shall be passed

    through a filter of fine wire gauge.

    The Contractor shall take every reasonable pre-

    cautions to avoid fire or heath hazards.

    A sample of bitumen that the Contractor propose to

    use in the work together with a statement as to its

    source and properties shall be submitted to and

    approved by the Engineer at least 45 days before

    Construction begins.

    4-20

  • 8/12/2019 Technical Specifications of Roads

    46/97

    The properties of bitumen shall be as specified by

    the Local code unless otherwise approved by the

    Engineer.

    Only the bitumen represented by the approvedsample shall be used by the Contractor.

    Blending of bitumen from different refineries will

    not be permitted.

    Test Frequency. One full analysis shall be carried

    out on a sample from every 80ton.

    4.6.9 Asphalt Concrete

    1. When tested according to ASTM C117 and ASTM C136, the combined

    aggregates shall conform to the following grading having a smooth curve

    to the appropriate limits and shall not vary from the low limit on one sieve

    to the high limit on the adjacent or vice-versa.

    Table 4-9. Gradation of aggregate to used in asphalt concrete

    Sieve size/No. % By Weight Passing

    Binder Course Wearing Course

    1" 100 100

    3/4" 75-100 80-100

    1/2" NA NA

    3/8" 45-70 60-80

    No 4 30-50 48-65

    No 8 20-35 35-50

    No 30 5-20 19-36

    No 50 3-12 13-23

    No 80 2-8 7-15

    No 200 0-4 3-8

    2.

    Combined mineral aggregate shall be non-plastic.

    4-21

  • 8/12/2019 Technical Specifications of Roads

    47/97

    3. Coarse aggregate, shall show no detrimental amount of stripping when

    tested in accordance with ASTM D 1664. The area coated shall be

    evaluated not only at 25C but also after the aggregate has been soaked

    in water at 40C and 60C. Minimum value of non-stripped area shall be 95%. If stripping occurs, the aggregate shall be rejected

    unless:

    a. An approved method of treatment shall be carried out as specified to

    change the material from a hydrophilic to a hydrophobic state.

    b. Only approved additives shall be used with the bituminous binder.

    4. When necessary to change the hydrophilic character of aggregates to

    hydrophobic, additives of approved type will be added to the

    bituminous material in such percentage as required to obtain

    satisfactory results from the test performed in accordance with ASTM

    D1664. Approved additive will be used in accordance with Technical

    Specifications issued by the manufacturer and approved by the

    Engineer after appropriate testing. No extra payment will be made for

    required anti-stripping additives.

    5. Design Criteria: The following table summarizes the design criteria of

    asphalt concrete. However, the exact percentage of bitumen to be used

    shall be fixed by the Engineer based on the laboratory mix and full-

    scale plant trial mix results.

    Table 4-10. Design Criteria of Asphalt Concrete

    PropertiesBinder

    course

    Wearing

    course

    Bitumen Content (% of total mix) Marshall Specimens: 3 - 6 4 - 7.5

    Number of Compaction blow at each end of specimen. 75 75

    Air voids in total mix (VIM %) 3 - 8 3 - 5

    Voids in mineral aggregate (VMA %) Min. 14 Min. 15

    Stability (kg) Min. 700 Min. 900

    4-22

  • 8/12/2019 Technical Specifications of Roads

    48/97

    Flow (mm) 2 - 4 2 - 4

    6.

    Job mix for Bituminous Paving Courses: field trials with the followingrecommendations shall be taken into account.

    Combined aggregate gradation should be

    adjusted within the allowable limits to achieve

    maximum stability whilst not going below the

    minimum requirement for void content.

    Minimum bitumen binder content should be

    used according to the results of the Marshall

    Method of Mix Design, if it will still satisfy all

    the specified requirements.

    Final job mix must display all characteristics as

    specified for Asphalt Concrete mixes.

    After receiving approval of the aggregates and

    bitumen from the Engineer, the Contractor shall

    make a written request for the approval of the

    job-mix formula from the Engineer at least

    thirty, (30) days prior to the date he intends to

    begin production of plant-mix Bituminous

    Paving Course Mixes. Formula will be

    prepared by the Contractor under the

    supervision of the Engineer in the Laboratory.

    The laboratory job mix formula shall define:

    a. Percentage of aggregate passing each required sieve size.

    b. Percentage of bitumen binder to be added to the aggregate.

    c. Temperature at which the mix is to be emptied from the mixer.

    d. Temperature at which the mix is to be delivered to the works site.

    Before the start of the permanent work, mock-

    ups or trial areas having lengths of at least 30

    m shall be laid to the specified layer thickness

    4-23

  • 8/12/2019 Technical Specifications of Roads

    49/97

    a. Materials used in the trials shall be those

    approved for use in the bituminous paving courses.

    b. Equipment used shall be that according

    to the Contractors approved method

    statement and the program of work.

    c. The object of these trials is to determine

    adequacy of the Contractors equipment,

    loose depth measurements necessary to

    result in the specified compacted layer

    depths, and relationship between the

    number of compaction passes and the

    resulting density of the material.

    d. Additionally at least two samples of non-

    compacted material and two cores of

    specified diameter shall be taken from

    the trial area in accordance with

    AASHTO T-168 and analyzed in the

    presence of the Engineer to determine

    aggregate grading, binder content,

    stability, flow, bulk density, and voids.

    Results shall be submitted to the

    Engineer for approval before further

    mixing and laying are carried out.

    If the laboratory job mix formula fails to

    produce a satisfactory trial, the mix proportions

    may be modified by agreement with the

    Engineer, within the applicable specification

    requirements to produce a mix of satisfactory

    workability and acceptable surface finish.

    4-24

  • 8/12/2019 Technical Specifications of Roads

    50/97

    All mixes produced shall conform to the

    properties of Job Standard Mix approved by the

    Engineer, within the ranges of tolerance

    specified in Table 22. Should a change in a material be encountered or

    should a change in a source of material be made,

    a new Job-Standard Mix shall be submitted by

    the Contractor and approved by the Engineer

    before the mix containing the new materials is

    delivered. Job materials will be rejected if they

    do not possess the same characteristics of the

    approved Job Standard Mix.

    Table 4-11. Job Mix Tolerance

    Aggregate retained on 4.75 mm sieve or larger + 5%

    Aggregate passing 4.75 mm sieve and retained on 0.075mm sieve

    + 4%

    Aggregate passing 0.075 mm sieve + 2%Bitumen Binder + 0.25%

    Temperature for mixing and placing 10C

    7. Samples of Bituminous paving course mixes shall be taken from the

    mixing plant and/or behind the paver prior to compaction, as decided

    by the Engineer, to check compliance with the approved job mix

    requirements. Density of the compacted mixes shall be related to the

    job standard density or the daily Marshall Density at the option of the

    Engineer, which shall be determined by making four Standard

    Marshall specimens from samples of the mix taken from the mixing

    plant or paver.

    Density of each sample shall be determined and

    compared with the mean value.

    Any individual result, which varies from the

    mean by more than 0.015 g/cc, shall be rejected.

    4-25

  • 8/12/2019 Technical Specifications of Roads

    51/97

    Marshall tests shall be repeated on a daily basis

    to establish the daily Marshal Density for that

    particular days production.

    Daily Marshall Density shall not vary from theJob Mix Design Density by more than + 1%.

    8. Assistance of the Engineer in the preparation of the job standard mix

    shall in no way relieve the Contractor of his responsibility for

    producing a bituminous mix meeting the requirements of the

    Specifications.

    9. Preparation of Bitumen Binder Temperature of the bitumen binder for mixing

    and compacting shall be in accordance with

    ASTM D1559. The Contractor shall submit a

    temperature / viscosity chart for each grade of

    bitumen to be used.

    10. Preparation of Mineral Aggregate for Bituminous Mix Coarse and fine aggregate shall be stored at the

    asphalt plant in such a manner that separate

    stockpiles will not become intermixed.

    a. Stockpiles shall be of sufficient size to provide a minimum quantity of one

    weeks continuous production of asphalt mix.

    b. Aggregates brought to the asphalt plant to supplement stocks should be

    tested and approved prior to placing in the existing approved stockpiles.

    Cold bins shall be calibrated with the materials

    to be used and the settings shall be such as to

    produce a combined gradation in accordance

    with the job mix formula.

    a. Proportioning shall be such that surpluses and shortages

    in the hot bins will not occur.

    b. Neither the dryer nor the screens shall be overloaded.

    4-26

  • 8/12/2019 Technical Specifications of Roads

    52/97

    c. All the above shall be as approved by the Engineer.

    Materials shall be thoroughly dried and heated

    so that their temperature is within 8C of the

    temperature needed to satisfy the viscosityrequirements of the asphalt cement.

    a. Moisture content of the heated and dried materials shall not exceed 0.5%.

    b. Quantity of materials fed through the drier shall in all cases be held to an

    amount, which can be thoroughly dried and heated within the limits

    specified.

    Immediately after heating, the aggregates shall

    be screened into at least five sizes and conveyed

    into separate bins ready for batching and mixing

    with bituminous materials. When the aggregates

    supplied are of such size and grading that

    separating into five bins is impractical, the

    number of required separations may be reduced

    to four or to three with the approval of the

    Engineer.

    Efficiency of the screening operations shall be

    sufficient to produce (at plant operating

    capacity) gradations (in all sizes of heated and

    dried aggregates) which are reasonably uniform

    and result in the production of a mix complying

    with the limits specified for the aggregate

    gradation.

    11. Preparation of Bituminous Mix Asphalt concrete shall be prepared in a central

    mixing plant conforming to the requirements of

    ASTM D995.

    a. The plant shall be equipped with an efficient mechanical dust extraction

    system and storage silos.

    4-27

  • 8/12/2019 Technical Specifications of Roads

    53/97

    b. Its design shall be provided for the controlled return of some of the filler to

    the mix, when necessary, by means of filler weighing bin discharging in to

    the pugmil.

    c. The dust collection system shall be powerful enough to keep the mineralfiller contents the in hot sand bin below 2%.

    d. The plant settings once established shall not be changed without the

    approval of the Engineer.

    e. The minimum mixing time shall not be less than that recommended by the

    manufacturer. The mixing time may be increased by the Engineer if

    additional time is necessary to obtain a homogeneous mix and satisfactory

    coating.

    f. Bitumen binder shall be introduced into the mix in the proportion specified

    by the job-mix formula.

    Initial mixing time will be designated by the

    Engineer. Mixing time may be increased by the

    Engineer if additional time is necessary to obtain

    a homogeneous mix and satisfactory coating.

    Timing at the batch plant for mixing shall begin

    at the start of the introduction of the bitumen

    into the pugmill.

    Temperature of the aggregate immediately prior

    to mixing shall be within + 8 C of the

    temperature of the bitumen binder.

    a. Temperature of the aggregate and asphalt prior to mixing shall be

    approximately that of the completed mix as defined in the job mix formula

    approved by the Engineer.

    b. Mix temperature shall be within the limits set out in the job mix formula

    when emptied from the mixer.

    12. Minimum test requirements for bituminous courses Bitumen material: One sample shall be tested for

    penetration and Ring ball test for every 80 tons

    or part thereof, unless otherwise agreed by the

    Engineer.

    4-28

  • 8/12/2019 Technical Specifications of Roads

    54/97

    Aggregate: One sample for each stockpile or

    every 1,000 m. Perform all the required tests.

    Bituminous mix: one sample of mix shall be

    obtained from at least every 200 tons. Performall the required tests.

    4.6.10 Prime and Tack coats

    1. Prime coat shall be a medium curing cut back

    asphalt (MC-70) .

    Sampling shall be in accordance with ASTM D140. Frequency of the testing shall be as directed by the

    Engineer.

    2. Tack Coat shall be Rapid Curing cut back asphalt (

    RC-250 ).

    Sampling shall be in accordance with ASTM D140. Frequency of the testing shall be as required by the

    Engineer.

    3. Depending on the possibilities of obtaining

    Bituminous materials, the Engineer may modify the

    type and gradation of the materials for the prime

    coat and tack coat.

    4.6.11 Road marking materials

    1. Thermoplastic Materials shall comply with

    BS3262 hot-applied thermoplastic road

    marking materials and shall be suitable for

    road surface temperature of up to 80C,

    unless otherwise approved by the

    Engineer. Proportions, testing

    requirements and type of materials used

    shall be as mentioned in the Contractors

    approved method statement.

    2. Road marking paint shall be either

    chlorinated rubber, one pack epoxy or

    4-29

  • 8/12/2019 Technical Specifications of Roads

    55/97

    4.6.12 Traffic signs

    1. Permanent traffic signs shall be

    reflector and shall comply with the

    following requirements except as

    modified here under or as directed by

    the Engineer.

    2. Sign plates shall be manufactured

    from sheet aluminum with a

    minimum thickness of 3mm, unless

    otherwise approved by the Engineer.

    3. Information on signs shall be

    constructed in extruded aluminum

    plank sections, which will either be

    self-locking or rear fixing, and the

    aluminum shall be BS EN 485, or BS

    1490 or other approved equivalent

    International Standard.

    4. All sign plates shall have clean,

    smooth edges cut to the required

    shape of the sign and shall be etched

    4-30

  • 8/12/2019 Technical Specifications of Roads

    56/97

    5.

    Sign shall be covered with HighIntensity reflective sheeting.

    Sheeting must have

    the manufacturers

    guarantee for a period

    of not less than 5

    years for Engineering

    Grade and 7 years for

    High Intensity.

    Rear faces shall be

    non-reflective grey

    and should give a

    similar life span to the

    sign face.

    Reflective sheeting

    shall be fixed to the

    sign plate either with

    a heat activated

    adhesive using

    vacuum applicator or

    with a pressure

    sensitive adhesive

    using a pressure roller

    in accordance with the

    sheeting

    manufacturers

    instructions.

    Sign faces shall be

    formed from a single

    piece of reflective

    4-31

  • 8/12/2019 Technical Specifications of Roads

    57/97

    Sheeting, after

    application to the sign

    base, will not come

    off at the edges nor

    shall it peel off or

    warp. Surface shall

    be smooth, flat and

    free from any bubbles,

    pimples, edge

    chipping or edge

    shattering. Surface

    4-32

  • 8/12/2019 Technical Specifications of Roads

    58/97

    Corners of all

    direction signs shall be rounded to a radius

    of 75 mm.

    6. Stiffening and Framing All stiffening and

    framing shall be of hot

    dipped galvanized

    steel.

    Signs constructed of

    aluminum sheet shall,

    when recommended

    by the Traffic Sign

    Manual, be framed on

    all edges using hot

    dipped galvanized

    steel angle.

    Stiffening to signs

    constructed of

    aluminum sheet,

    having an area

    exceeding 0.10 sq.m.

    shall be confined to

    horizontal lengths at

    the top and bottom

    edges of the sign

    plate.

    7. All rivets or other devices fixing sign

    plates to their framework shall be of

    non-staining steel or other materials

    approved by the Engineer and shall

    4-33

  • 8/12/2019 Technical Specifications of Roads

    59/97

    All rivet and boltholes

    shall be edge-sealed

    with clear lacquer

    after the application of

    the plastics sheeting.

    Rivets shall be spaced

    at not more than 150

    mm apart, around the

    outside edge of the

    sign plate and on

    cross braces the

    spacing shall be not

    more than 300 mm.

    Any rivet brought

    through the sign face

    shall be colored to

    match the sign face.

    Any rivet or other

    device fixing sign

    plates to their

    framework shall have

    protective washer of

    nylon or other

    approved insulating

    material inserted

    where they would be

    in contact.

    8. All materials shall be supplied in

    new and unused condition except in

    4-34

  • 8/12/2019 Technical Specifications of Roads

    60/97

    4.7

    ExecutionAll operations shall be performed in accordance with the specification, and in conformity

    with the lines, grades, thickness and typical cross Section shown on the plans or established

    by the Engineer. Only approved material shall be used in the construction. The embankment

    and sub grade in fill shall be constructed utilizing only suitable material obtained from

    roadway excavation or imported fill material from sources previously approved by the

    competent authority.

    4.7.1 Placement of fill

    1. Prior to the placement of any fill

    materials, the Contractor shall

    conduct trial compaction tests as

    directed by the Engineer.

    Fill material used in the trials shall be with the proposed borrow or

    excav