WORKFACE PLANNINGCONFERENCE‐WIDE SESSIONFROM CONCEPT TO COMMISSIONING
![Page 2: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/2.jpg)
INTRODUCTION
• From Concept to Commissioning: what does it mean?
• Who is on the panel?
Ron Embury | Engineering Team Leader, NOVA Chemicals (Owner)
Ken Kohlruss | Vice President Operations, Commonwealth Construction [CH2M Hill] (CMT)
Jose Herrero | Vice President, Fluor (Engineering Contractor)
Tannis Liviniuk | Lead Construction Analyst, Cenovus Energy (Construction Contractor)
Lloyd Rankin | Researcher, COAA (Facilitator)
![Page 3: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/3.jpg)
INTRODUCTION
![Page 4: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/4.jpg)
Defines the basic design parameters for the intended project. Generation, review, and approval of the DBM is a prerequisite for the development of the Engineering Design Specification (EDS).
DESIGN BASIS MEMORANDUM (DBM)
![Page 5: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/5.jpg)
DESIGN BASIS MEMORANDUM (DBM)
![Page 6: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/6.jpg)
DBM: OWNER
![Page 7: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/7.jpg)
DBM: OWNER
At the DBM phase, we have three documents that set the stage for WorkFace Planning:
• Project Execution Plan
• Construction Execution Plan
• Constructability Implementation Plan
![Page 8: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/8.jpg)
DBM: OWNER
Project Execution Plan (PEP):
• Overall Project Milestone Schedule
• Project Strategy:
o The project will be Construction‐driven
o Engineering and Procurement will sequence their work to meet Construction needs.
o There will be extensive constructability input into the design and Engineering Work Package (EWP)
o WorkFace Planning will be part of the Construction Execution Plan
o No work packages (FIWPs) will start without all engineering, materials, tools, equipment and labour present on site.
o Owner‘s commissioning sequence will be by operating systems and will be introduced in the engineering and construction schedules.
![Page 9: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/9.jpg)
Construction Execution Plan (CEP):
• With respect to WorkFace Planning, the construction execution plan will:
o Set out the Construction Management Organization.
o Describe the Contracting Strategy
o Contain the WorkFace Planning Execution Plan
Workface Planning Approach
Workface Planning Overview
Workface Planning Implementation
Workface Planning Training
Workface Audit Process
o Progress Reporting
DBM: OWNER
![Page 10: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/10.jpg)
DBM: OWNER
Constructability Implementation Plan (CIP)
• CIP is developed and started in the DBM phase. CIP is used to support WFP concepts.
o Led by Construction
o Sponsor(s) identified, Policy Statements described and Constructability Manager is appointed.
o Sets out focus groups between engineering disciplines, Procurement, Owner, etc.
o High‐level construction sequence is developed.
o Details of schedule integration is developed between parties.
i.e., Engineering drawing sequence developed to support FIWP Schedule
i.e., Procurement deliverables developed to support FIWP Schedule.
o Various other activities are completed to promote ease of construction (design, layout, modular design, pre‐fabrication, construction methods, weather, etc.)
![Page 11: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/11.jpg)
DBM: OWNER
Contract types:• C• CM• EP• EPC• EPCM
![Page 12: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/12.jpg)
DBM: CONSTRUCTIONMANAGEMENT TEAM
![Page 13: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/13.jpg)
1.0 Definition2.0 Purpose3.0 Scope4.0 Strategies5.0 Participants6.0 Roles and Responsibilities7.0 Method8.0 Systems9.0 FIWP’S Release Process10. Auditing
WorkFace Planning Execution Plan
DBM: CONSTRUCTION MANAGEMENT TEAM
![Page 14: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/14.jpg)
High‐level project review which leads to Path of Construction
DBM: CONSTRUCTION MANAGEMENT TEAM
![Page 15: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/15.jpg)
MAINTENANCE AISLEWAY
MAINTENANCE AISLEWAY
ROW M
ROW D
ROW C
ROW B
ROW D
ROW C
ROW B
MAIN PIPERACK
ROW A
ROW A
RO
W W
RO
W E
NORTH
SOUTH
2
3
1
Path of Construction
DBM: CONSTRUCTION MANAGEMENT TEAM
![Page 16: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/16.jpg)
DBM: CONSTRUCTION MANAGEMENT TEAM
ConstructSim
V8i
![Page 17: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/17.jpg)
DBM: CONSTRUCTION MANAGEMENT TEAM
![Page 18: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/18.jpg)
DBM: CONSTRUCTIONMANAGEMENT TEAM
• Experienced trainers, educators and assessors (auditors)
• Assessment services
• Self‐assessment tools
![Page 19: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/19.jpg)
DBM: ENGINEERING
![Page 20: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/20.jpg)
DBM: ENGINEERING
999D 999E
999G
800C
999H
999B 999C
Sample plot plan (partial)
![Page 21: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/21.jpg)
DBM: ENGINEERING
![Page 22: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/22.jpg)
Click to see process
Click to see table of contents
DBM: ENGINEERING
PEOPLE TOOLS
PROCESSES
![Page 23: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/23.jpg)
DBM: CONSTRUCTIONCONTRACTOR
![Page 24: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/24.jpg)
• Demonstrate high‐level capacity to support WorkFace Planning
• WorkFace Planning Awareness for Trades People scheduled for delivery February 2011.
• Pre‐beta sample available at this conference
DBM: CONSTRUCTIONCONTRACTOR
![Page 25: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/25.jpg)
WorkFace Planning Awareness for Trades People:
DBM: CONSTRUCTIONCONTRACTOR
![Page 26: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/26.jpg)
WorkFace Planning Course Development Roadmap
DBM: CONSTRUCTIONCONTRACTOR
![Page 27: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/27.jpg)
EDS defines all elements of project scope and is the control document for commencement of detailed engineering and procurement activities on the project. It is also used in scoping the development of the Authorization for Expenditure (AFE).
ENGINEERING DESIGNSPECIFICATION: DEFINITION
![Page 28: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/28.jpg)
ENGINEERING DESIGNSPECIFICATION (EDS)
![Page 29: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/29.jpg)
EDS: ENGINEERING
![Page 30: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/30.jpg)
EDS: ENGINEERING
Level 2 Schedule
![Page 31: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/31.jpg)
EDS: ENGINEERING
EWP Release Plan
![Page 32: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/32.jpg)
WBI/EWP Structure • Activity code breaks down discipline code into different activities
Discipline Code
Model Type
0 Civil Works1 Concrete2 Structural Steel3 Buildings4 Equipment5 Piping6 Electrical7 Control Systems
U Underground
N New construction, stick built above ground
P Paving and Road.
L Miscellaneous steel
T Electrical Heat Tracing
F Equipment Fireproofing
DBM: ENGINEERING
![Page 33: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/33.jpg)
EDS: ENGINEERING
Level 3 Schedule
![Page 34: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/34.jpg)
EDS: CONSTRUCTION MANAGEMENT TEAM
![Page 35: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/35.jpg)
Proactively resolve conflicts
EDS: CONSTRUCTION MANAGEMENT TEAM
![Page 36: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/36.jpg)
Review and integrate WFP processes and support functions
EDS: CONSTRUCTIONMANAGEMENT TEAM
![Page 37: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/37.jpg)
Ensure all databases are up to date
EDS: CONSTRUCTIONMANAGEMENT TEAM
![Page 38: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/38.jpg)
EDS: CONSTRUCTION
![Page 39: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/39.jpg)
Define and Issue CWP release plan
• Identify the size and description of all CWPs
• Determine when those CWPs will be developed and released
• These can be reported in Excel spreadsheets, Primavera schedules, and other documents
• The EWP schedule will be driven by the CWP schedule
EDS: CONSTRUCTION
![Page 40: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/40.jpg)
Appoint lead planner and commence WFP process
EDS: CONSTRUCTION
![Page 41: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/41.jpg)
Define and Issue FIWP release plan
• Identify the size and description of all FIWPs
• Determine when those FIWPs will be developed and released
• These can be reported in Excel spreadsheets, Primavera schedules, and other documents
• FIWP development is driven by the CWPs
EDS: CONSTRUCTION
![Page 42: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/42.jpg)
DETAILED ENGINEERING
![Page 43: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/43.jpg)
DETAILED ENGINEERING: CONSTRUCTION CONTRACTORS
![Page 44: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/44.jpg)
DETAILED ENGINEERING: CONSTRUCTION CONTRACTORS
Construction develops and delivers CWPs
![Page 45: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/45.jpg)
Detailed Level 4 Schedule
• This is a schedule of the release of the Field Installation Work Packages (FIWPs)
• These can be reported in Excel spreadsheets, Primavera schedules, and other documents
DETAILED ENGINEERING: CONSTRUCTION CONTRACTORS
![Page 46: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/46.jpg)
Break CWPs into FIWPs
DETAILED ENGINEERING: CONSTRUCTION
CWP
FIWP
FIWP
FIWP
![Page 47: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/47.jpg)
DETAILED ENGINEERING: CONSTRUCTION
![Page 48: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/48.jpg)
DETAILED ENGINEERING: CONSTRUCTION
![Page 49: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/49.jpg)
DETAILED ENGINEERING: ENGINEERING
![Page 50: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/50.jpg)
DETAILED ENGINEERING: ENGINEERING
![Page 51: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/51.jpg)
CONSTRUCTION PHASE
![Page 52: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/52.jpg)
CONSTRUCTION PHASE: CONSTRUCTION CONTRACTOR
![Page 53: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/53.jpg)
Implement and Release FIWP
CONSTRUCTION PHASE: CONSTRUCTION CONTRACTOR
![Page 54: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/54.jpg)
Execute FIWP
CONSTRUCTION PHASE: CONSTRUCTION CONTRACTOR
One of our silver‐level sponsors ‐ Phoenix Industrial ‐ has incorporated their maintenance experience into the Phoenix WorkFace Planning approach.
![Page 55: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/55.jpg)
CONSTRUCTION PHASE: CONSTRUCTION CONTRACTOR
Progress project
![Page 56: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/56.jpg)
What if execution doesn’t go according to plan?
CONSTRUCTION PHASE: CONSTRUCTION CONTRACTOR
BACKLOG‘PLAN B’RISK
EVENTS
![Page 57: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/57.jpg)
CONSTRUCTION PHASE: OWNER
![Page 58: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/58.jpg)
WorkFace Planning Lessons Learned:
• Conduct Lessons Learned at the end of each phase of the project
• Do ‘temperature checks’ during each phase
• At the end of the project, conduct a final Lessons Learned.
CONSTRUCTION PHASE: OWNER
![Page 59: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/59.jpg)
Two of our sponsors have been recognized by COAA, winning awards for their excellence and
leadership in WorkFace Planning.
WORKFACE PLANNINGEXCELLENCE
![Page 60: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/60.jpg)
![Page 61: WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project Execution Plan (PEP): † Overall Project Milestone Schedule † Project Strategy:](https://reader033.vdocuments.net/reader033/viewer/2022060903/609f49ae168bd570b9225887/html5/thumbnails/61.jpg)
AUDIENCE FEEDBACK
NOTE: The information collected is anonymous and may be used for research purposes. By participating, you are giving your consent for the use of this data.