Cementing
Cementing Processes• Casing• Liner• Squeeze• Plug
Density of Mixtures Cementing Equipment
3
Read:
Applied Drilling Engineering, Ch. 3
HW #15 - Well Control – W&Wdue 11-18-02
4
Cement is used in Drilling Operations to...
Support and protect the casing Prevent the movement of fluid through the annular space outside the casing Stop the movement of fluid into vugular or fractured formations Close an abandoned well or a portion of a well Sidetracking
5
Types of Cementing Processes
I. Primary Cementing
1. Full String
2. Liners
3. Large Pipe (lesson 31)
4. Stage (lesson 31)
A. Survey and perforate
B. Stage collars
6
Primary Cementing
Full String Cementing
Steel Casing
Borehole
Cement
Steel Liner
Liner Cementing
7
Types of Cementing Processes
II. Squeeze Cementing
1. Shoe
2. Casing (up-hole)
3. Open-hole (lost-circulation)
8
NEW SLURRY
9
Types of Cementing Processes
III. Plugging
1. Open-hole plug back
A. Fishing Operations
B. Abandonment
2. Casing
10
11
Types of Cementing Processes
IV. Special Techniques
1. Land
2. Off-shore
12
Mixing Cement(basis is 1 sk. of cmt.)
The density-volume formula:
Slurry Yield (volume of mixture/sk):
mixnbcw WW...WWW
sk
cu.ft.
48.7
v
sk
galvv...vvv mix
mixnbcw
mixmixnnbnwcww vv...vvv
13
Rotary Drilling Cementing(basis is 1 sk of cmt.)
Density of Each Component in Slurry:
e.g. Density of Barite =
Specific Gravity of Barite * Density of Water
lb/gal 33.8*23.4b
lb/gal 35.2b
14
Rotary Drilling Cementing(basis is 1 sk. of cmt.)
mix
mixmix
ii
iii
mix
Density of Cement Slurry:
volume
mass
15
16
17
18
Wiper Plugs
Wiper plugs are equipped with rubber-cupped fins which wipe mud from the walls of the casing ahead of the cement and clean the walls of casing behind the slurry.
Examples of wiper plugs are shown in the next slide. The top plug also serves as a means of determining when the cement is in place.
19
20
Mud film thickness Feet of fill per 1000’
5 1/2” 7”
1/16” 1.6mm 50.6 40
1/32” 0.8mm 25.5 20
1/64” 0.4mm 12.6 10
21