• Progress Update• Timetable• Station Sizes • Station Features / Amenities• Station Art
Brio Overview
PROGRESS UPDATE – JULY 2012MESA & ALAMEDA RTS CORRIDORS• Investigation / Data Collection
• Metes & Bounds Surveys for Mesa Underway
• All Other Items Complete
• Station Locations
• Finalized for Mesa Corridor
• Camille relocated to far side due to property encroachments
• Adjustments Remain for Alameda Corridor
• Additional right-of-way needs being assessed for stations and amenities improvements
• Station Design & Branding
• Station Design Approved by Mass Transportation Board (MTB)
• System Name “Brio”
• Color and Logo Next Branding Items
• Artists Developing Station - Specific Designs
PROGRESS UPDATE – JULY 2012MESA & ALAMEDA RTS
CORRIDORS
•Schedule• Mesa Corridor
• Preliminary (30%) Plans Submitted September 28, 2011
• Pre-Final (60%) Plans Submitted March 1, 2012
• Final (100%) Plans – August 8, 2012
• Alameda Corridor• Preliminary (30%) Plans Submitted December 15, 2011
• Pre-Final (60%) Plans – July 26, 2012
• Final (100%) Plans – October 2, 2012
PROGRESS UPDATE – JULY 2012MESA & ALAMEDA RTS CORRIDORS
•Key Next Steps• Continued Coordination with TxDOT and FTA
• Continued Coordination with Planning Regarding Illumination
• Continued Coordination with Private and Public Utilities
• Branding – Color & Logo
• Public Art – Finalize Installations / Concepts
Alameda (In Design)• 15.25 miles• 17 proposed stations• Design: May 2011 – Oct 2012• Procurement: Jan – March 2012• Procurement: Dec. 2012 – April 2013• Construction April 2012 – Sept. 2013• Construction: April 2013 – April 2014
Mesa (In Design)• 8.4 miles• 13 proposed stations• Design: June 2011 – Aug 2012• Procurement: July – Sept. 2012• Procurement: Nov. 2012 – Feb 2013• Construction Oct. 2012 – Sept. 2013• Construction: Feb 2013 – Jan 2014
Brio Corridors
Dyer ($15.4M FTA Funding Approved - $5M Short; Will reapply for shortfall Sept 2012)
• 11.7 miles• 12 proposed stations• Design: Jan - Dec 2013• Procurement: Jan - March 2014• Construction: March 2014 – Sept 2015
Montana (Will apply Sept 2012)• 18.4 miles• 18 proposed stations• Design: Jan - Dec 2014• Procurement: Jan - March 2015• Construction: April 2015 – Sept 2016
Brio Corridors
Brio Stations• Four (4) Station Canopy Sizes
– 6’ deep by 37’ long– 6’ deep by 46’ long– 6’ deep by 62.5 long– 9’ deep by 37’ long– 9’ deep by 46’ long– 9’ deep by 62.5’ long
• Station Platform Size– 9’ to 28’ deep– 65’ to 85’ long– All platform sizes are 65’
• Size based upon:– Expected ridership– Available ROW– Geometric restrictions
Brio Station Features• Pedestrian Illuminations
− Every 30’ – 50’− 220’ (maximum) from centerpoint of
station or to nearest intersection• Landscaping
− Native trees/plants− Trees every 30’ as geometry permits− Shade trees− 220’ (maximum) from centerpoint of
station of to nearest intersection• Free Wi-Fi
− In station− Onboard RTS vehicles
Brio STATION PUBLIC FOOTPRINT
Brio STATION PUBLIC FOOTPRINT
Brio STATION PUBLIC FOOTPRINT
Brio Station Public Art Concepts - Mesa
Brio Station Public Art Concepts - Mesa
Resizing of shelter does not alter the look.
Brio Station Public Art Concepts - Alameda
46’ CANOPY
Questions?