Brio Rapid Transit System

Update on Stations and Timetables

July 10, 2012

Page 2: Brio Rapid Transit System Update on Stations and Timetables July 10, 2012

• Progress Update• Timetable• Station Sizes • Station Features / Amenities• Station Art

Brio Overview

Page 3: Brio Rapid Transit System Update on Stations and Timetables July 10, 2012

PROGRESS UPDATE – JULY 2012MESA & ALAMEDA RTS CORRIDORS• Investigation / Data Collection

• Metes & Bounds Surveys for Mesa Underway

• All Other Items Complete

• Station Locations

• Finalized for Mesa Corridor

• Camille relocated to far side due to property encroachments

• Adjustments Remain for Alameda Corridor

• Additional right-of-way needs being assessed for stations and amenities improvements

• Station Design & Branding

• Station Design Approved by Mass Transportation Board (MTB)

• System Name “Brio”

• Color and Logo Next Branding Items

• Artists Developing Station - Specific Designs

Page 4: Brio Rapid Transit System Update on Stations and Timetables July 10, 2012

PROGRESS UPDATE – JULY 2012MESA & ALAMEDA RTS

CORRIDORS

•Schedule• Mesa Corridor

• Preliminary (30%) Plans Submitted September 28, 2011

• Pre-Final (60%) Plans Submitted March 1, 2012

• Final (100%) Plans – August 8, 2012

• Alameda Corridor• Preliminary (30%) Plans Submitted December 15, 2011

• Pre-Final (60%) Plans – July 26, 2012

• Final (100%) Plans – October 2, 2012

Page 5: Brio Rapid Transit System Update on Stations and Timetables July 10, 2012

PROGRESS UPDATE – JULY 2012MESA & ALAMEDA RTS CORRIDORS

•Key Next Steps• Continued Coordination with TxDOT and FTA

• Continued Coordination with Planning Regarding Illumination

• Continued Coordination with Private and Public Utilities

• Branding – Color & Logo

• Public Art – Finalize Installations / Concepts

Page 6: Brio Rapid Transit System Update on Stations and Timetables July 10, 2012

Alameda (In Design)• 15.25 miles• 17 proposed stations• Design: May 2011 – Oct 2012• Procurement: Jan – March 2012• Procurement: Dec. 2012 – April 2013• Construction April 2012 – Sept. 2013• Construction: April 2013 – April 2014

Mesa (In Design)• 8.4 miles• 13 proposed stations• Design: June 2011 – Aug 2012• Procurement: July – Sept. 2012• Procurement: Nov. 2012 – Feb 2013• Construction Oct. 2012 – Sept. 2013• Construction: Feb 2013 – Jan 2014

Brio Corridors

Page 7: Brio Rapid Transit System Update on Stations and Timetables July 10, 2012

Dyer ($15.4M FTA Funding Approved - $5M Short; Will reapply for shortfall Sept 2012)

• 11.7 miles• 12 proposed stations• Design: Jan - Dec 2013• Procurement: Jan - March 2014• Construction: March 2014 – Sept 2015

Montana (Will apply Sept 2012)• 18.4 miles• 18 proposed stations• Design: Jan - Dec 2014• Procurement: Jan - March 2015• Construction: April 2015 – Sept 2016

Brio Corridors

Page 8: Brio Rapid Transit System Update on Stations and Timetables July 10, 2012

Brio Stations• Four (4) Station Canopy Sizes

– 6’ deep by 37’ long– 6’ deep by 46’ long– 6’ deep by 62.5 long– 9’ deep by 37’ long– 9’ deep by 46’ long– 9’ deep by 62.5’ long

• Station Platform Size– 9’ to 28’ deep– 65’ to 85’ long– All platform sizes are 65’

• Size based upon:– Expected ridership– Available ROW– Geometric restrictions

Page 9: Brio Rapid Transit System Update on Stations and Timetables July 10, 2012

Brio Station Features• Pedestrian Illuminations

− Every 30’ – 50’− 220’ (maximum) from centerpoint of

station or to nearest intersection• Landscaping

− Native trees/plants− Trees every 30’ as geometry permits− Shade trees− 220’ (maximum) from centerpoint of

station of to nearest intersection• Free Wi-Fi

− In station− Onboard RTS vehicles

Page 10: Brio Rapid Transit System Update on Stations and Timetables July 10, 2012

Brio STATION PUBLIC FOOTPRINT

Page 11: Brio Rapid Transit System Update on Stations and Timetables July 10, 2012

Brio STATION PUBLIC FOOTPRINT

Page 12: Brio Rapid Transit System Update on Stations and Timetables July 10, 2012

Brio STATION PUBLIC FOOTPRINT

Page 13: Brio Rapid Transit System Update on Stations and Timetables July 10, 2012

Brio Station Public Art Concepts - Mesa

Page 14: Brio Rapid Transit System Update on Stations and Timetables July 10, 2012

Brio Station Public Art Concepts - Mesa

Resizing of shelter does not alter the look.

Page 15: Brio Rapid Transit System Update on Stations and Timetables July 10, 2012

Brio Station Public Art Concepts - Alameda

Page 16: Brio Rapid Transit System Update on Stations and Timetables July 10, 2012

46’ CANOPY

Page 17: Brio Rapid Transit System Update on Stations and Timetables July 10, 2012

Questions?