HONOLULU RAIL TRANSIT PROJECT 

 

 

February 2020 MONTHLY PROGRESS REPORT 

  

   

www.HonoluluTransit.org  

  

Page 2: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

2 | P a g e

DISCLAIMER NOTICE This document is disseminated under the sponsorship of the United States Department of Transportation, Federal Transit Administration (FTA), in the interest of information exchange. The United States Government assumes no liability for the contents or use thereof. The United States Government does not endorse products or manufacturers. Any trade or manufacturers' names appear herein solely because they are considered essential to the contents of the report.

NO RELIANCE BY THIRD PARTIES This report and all subsidiary reports are prepared solely for the FTA, and should not be relied upon by any party, except the FTA, its Project Management Oversight Contractors (PMOC), and the Honolulu Authority for Rapid Transportation (HART) Board of Directors, in accordance with the purpose as described in the next section.

REPORT FORMAT AND FOCUS This document is submitted in compliance with the terms of FTA Contract No. DTFT60-09-D-00012, Task Order No. 2. Its purpose is to provide information and data to assist the FTA as it continually monitors HART's technical capability and capacity to execute a project efficiently and effectively, and hence, whether HART continues to be ready to receive federal funds for further project development. This document covers the project and quality management activities on the Honolulu Rail Transit Project managed by HART as the project sponsor and partially financed by the FTA under the Full Funding Grant Agreement (FFGA). Concurrent non-project activities and other items not covered by the FFGA may not be included.

INFORMATION REGARDING FORWARD-LOOKING STATEMENTS This document includes forward-looking information. The words "believe”, "anticipate", "expect", "intend", "aim", "plan", "predict", "continue", "assume", "positioned", "may", "will", "should", "shall", "risk" and any other similar expressions that are predictions of or indicate future events and future trends identifies forward-looking information. Forward-looking information includes all matters that are not historical facts. Readers should not place undue reliance on forward-looking information because it involves known and unknown risks, uncertainties and other factors that are in many cases beyond HART's control. By its nature, forward-looking information involves risks and uncertainties because it relates to events and depends on circumstances that may or may not occur in the future. Forward-looking information is not a guarantee of future performance, and HART's actual results of operations, financial condition, and the development of the industry in which it operates may differ materially from those made in or suggested by forward-looking information contained in this document. The cautionary statements set forth above should be considered in connection with any subsequent forward-looking information that HART, or persons acting on its behalf, may issue. Factors that may cause HART's actual results to differ materially from those expressed or implied by the forward-looking statements in this document include but are not limited to the risks described in HART's annual report. For projects funded through the FTA's New Starts program, the FTA and its PMOC use a risk-based assessment process to review and validate a project sponsor's budget and schedule. Any results of an FTA or PMOC risk-based assessment represent a "snapshot in time" for a particular project under the conditions known at that same point in time. The status of any assessment may be altered at any time by new information, changes in circumstances, or further developments in the project. Furthermore, any forward looking statements contained in this document are made as of the date of this report, and HART does not undertake any obligation to update publicly or to revise any of the included forward-looking statements, whether as a result of new information, future events or otherwise, except as expressly required by law. ON THE COVER: Left: UH West O‘ahu Station construction. Upper Right: Construction at the Leeward Community College Station site. Lower Right: Guideway construction on the eastern section of the alignment.

Page 3: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

3 | P a g e

Table of Contents LIST OF ACRONYMS .......................................................................................................................................................................... 4 PROJECT MAP ................................................................................................................................................................................... 9 1 SUMMARY .............................................................................................................................................................................. 10 2 OVERALL PROJECT PROGRESS AND FINANCIALS ................................................................................................................... 13

2.1 Project Progress .................................................................................................................................................... 13 2.2 Project Budget ...................................................................................................................................................... 15 2.3 Project Funding ..................................................................................................................................................... 16

3 SCHEDULE .............................................................................................................................................................................. 18 4 CONTRACT STATUS ................................................................................................................................................................ 21

4.1 System-wide .......................................................................................................................................................... 23 4.2 Section I – West O'ahu/Farrington Highway: East Kapolei to Pearl Highlands ..................................................... 34 4.3 Section II – Kamehameha Highway: Pearl Highlands to Aloha Stadium ............................................................... 46 4.4 Section III – Airport: Aloha Stadium to Middle Street Transit Center Station ...................................................... 55 4.5 Section IV – City Center: Middle Street Transit Center Station to Ala Moana Center .......................................... 58 4.6 Project-Wide ......................................................................................................................................................... 64 4.7 Contract Status by Contract Packaging Plan (CPP) Number ................................................................................. 76

5 OVERALL PROJECT-WIDE ACTIVITIES ..................................................................................................................................... 78 5.1 Overall Key Issues ................................................................................................................................................. 78 5.2 Permits .................................................................................................................................................................. 79 5.3 Hawai'i Department of Transportation (HDOT) Agreements ............................................................................... 79 5.4 Utility Agreements ................................................................................................................................................ 80 5.5 Right-of-Way ......................................................................................................................................................... 82

6 MANAGEMENT AND ADMINISTRATIVE UPDATES ................................................................................................................. 91 6.1 Safety and Security (S&S) ...................................................................................................................................... 91 6.2 Quality Management ............................................................................................................................................ 95 6.3 Buy America Compliance (49 CFR 661 and 49 CFR 663) ....................................................................................... 97 6.4 Disadvantaged Business Enterprise (DBE) ............................................................................................................ 97 6.5 Art-in-Transit (AIT) Program ................................................................................................................................. 97 6.6 Planning and Environment .................................................................................................................................... 99 6.7 Risk Management ............................................................................................................................................... 100 6.8 Construction Claims ............................................................................................................................................ 107 6.9 Community Outreach .......................................................................................................................................... 108 6.10 Staffing ................................................................................................................................................................ 108 6.11 HART Baseline Plans and Procedures Status List ................................................................................................ 110 6.12 Readiness and Activation .................................................................................................................................... 114

APPENDICES ................................................................................................................................................................................. 115 A. Project Costs by SCC – Level 2 ............................................................................................................................ 116 B. Core Accountability Items Including Major Issues .............................................................................................. 118 C. Construction Progress Interim Opening ............................................................................................................. 119 D. Project Organization Chart ................................................................................................................................. 120

Table of Figures

Figure 1. Overall Project Progress (% Complete) ........................................................................................................................... 13 Figure 2. Construction Progress (% Complete) .............................................................................................................................. 13 Figure 3. Design Progress (% Complete) ........................................................................................................................................ 14 Figure 4. Planned vs. Received Project Funding ............................................................................................................................ 16 Figure 5. New Starts Drawdown by Federal Fiscal Year ................................................................................................................ 17 Figure 6. HRTP Master Project Schedule Summary (MPSS) .......................................................................................................... 20 Figure 7. Right-of-Way Status for the Parcels ............................................................................................................................... 83 Figure 8. Relocation Status for the Occupants .............................................................................................................................. 83 Figure 9. Temporary Construction Easements and Utility............................................................................................................. 84 Figure 10. Inter-Governmental Agreement Status ........................................................................................................................ 84 Figure 11. Cost Probability Curve, February 2020 Risk Data ....................................................................................................... 106 Figure 12. Schedule Probability Curve, February 2020 Risk Data ................................................................................................ 106 Figure 13. Staffing Activities ........................................................................................................................................................ 109

Page 4: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

4 | P a g e

A&E Architect/Engineer AAN Accepted as Noted

AANR Accepted as noted, resubmit AC Asphalt Concrete

ACB Articulated Concrete Block ACHP Advisory Council on Historic Preservation

ACI Application Centric Infrastructure ACS Access Control System ADA Americans with Disabilities Act AFA Air Force Association AFE Authorized for Expenditure AG Attorney General

AGS Airport Guideway and Stations AIS Archaeological Inventory Survey AIT Art-in-Transit ALS Aloha Stadium Station

AMP Archaeological Monitoring Plan ANR Accepted as Noted–Resubmit APE Area of Potential Effect API Application Program Interface APS Auxiliary Power Supply

APTA American Public Transportation Association ARRA American Recovery and Reinvestment Act

ASG Airport Station Group ASI Architect Supplemental Information

ASTM American Society for Testing and Materials ASU Airport Section Utilities ATB Asphalt Treated Base ATC Automatic Train Control ATO Automatic Train Operation ATP Automatic Train Protection ATS Automatic Train Supervision AVA Anil Verma Associates, Inc. AVS Address Verification Systems

AW0 Assigned Weight, Empty Vehicle (rail car weight with no passengers) AW3 Assigned Weight, Crush Load (empty weight plus crush load of

standees) BA Buy America

BAC Buy America Compliance BACM Buy America Compliance Matrix BAFO Best and Final Offer

BANCT Best Available Noise Control Technology BAP Buy America Plan

BART Bay Area Rapid Transit BCS Balanced Cantilever System

BFMP Bus Fleet Management Plan BFS Budget and Fiscal Services BIC Ball in Court BLS Blue Light Station

BMP Best Management Practice BOC Backup Operations Center BOD Board of Directors BOH Bank of Hawaii BPS Baseline Project Schedule BUE Bottom-Up Estimate

BUEG Back-up Emergency Generator BWS Board of Water Supply CAD Computer-Aided Design

CAM Construction Access Milestone CAP Corrective Action Plan CAR Corrective Actions CC2 City Center Phase 2 CC3 City Center Phase 3 ccd Consecutive Calendar Days

CCGS City Center Guideway and Stations CCH City and County of Honolulu CCO Contract Change Order

CCTV Closed Circuit Television CCUG City Center Section Utilities and Guideway CCUR City Center Utilities Relocation

CDC Compendium of Design Criteria CDL Commercial Driver License CDR Conceptual Design Review

CDRL Contract Document Requirements List CEB Civil Engineering Branch CEI Construction Engineering and Inspection CEL Certifiable Elements List

CFMP Configuration Management Plan CFO Chief Financial Officer CHB Car History Book CIC Communication Interface Cabinet CIL Certifiable Items List CIP Cast-in-place CJA Condon‐Johnson & Associates

CLOMR Conditional Letter of Map Revision CLR Cultural Landscape Report

CLSM Controlled Low-strength Material CM Construction Manager

CMP Construction Management Plan CMS Contract Management System CMU Concrete Masonry Unit

CNMMP Construction Noise Mitigation and Monitoring Plan CO Change Order

COI Conflict of Interest COMMs Communications CONRAC Consolidated Rental Car Facility

COO Chief Operating Officer COR Corporation Counsel

CORP Central Oahu Regional Park CP Contractor Proposed

CPC Cost Proposals by Consultant CPM Critical Path Method CPO Chief Procurement Officer CPP Contract Packaging Plan

CR Consolidated Resolution CRM Customer-Relationship Management

CRMS Customer Relational Management System CROE Construction Right-of-Entry CRRB Car Readiness Review Board

CSC Core Systems Contract CSCC Construction Specification Conformance Checklist

CSD Department of Customer Services CSDBOM Core System Design-Build-Operate-Maintain

CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant CSSC Core System Support Consultant

CSSM Construction Safety and Security Manager CSSP Construction Safety & Security Plan

CST Customer Service Terminal CTP Central Test Procedure CTS Communications Transmission System CW Contract-Wide

CWA Clean Water Act CWR Continuous Welded Rail

CWRM Commission on Water Resource Management CZM Coastal Zone Management D&C Design & Construction

DAGS Department of Accounting & General Services DAV Disabled American Veterans

DB Design-Build DBB Design-Bid-Build DBE Disadvantaged Business Enterprise

DBEDT Department of Business, Economic Development and Tourism DBF Design-Build-Finance

DBFOM Design-Build-Finance-Operate-Maintain DBOM Design-Build-Operate-Maintain DCAB Disability and Communication Access Board DCCA Department of Commerce and Consumer Affairs DCCC Design Criteria Conformance Checklists DCN Design Change Notice

DD Definitive Design DDC Department of Design and Construction

DDC-MED Department of Design & Construction-Mechanical & Electrical Division

DED Deputy Executive Director DES Department of Environmental Services

LIST OF ACRONYMS

Page 5: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

5 | P a g e

DF Direct Fixation DFF Direct Fixation Fastener

DFIM Design Furnish Install Maintain DFM Department of Facility Maintenance

DHHL Department of Hawaiian Homelands DHR Department of Human Resources DIT Department of Information Technology

DKSG Dillingham and Kaka'ako Station Group DLIR Hawai'i Department of Labor and Industrial Relations

DLNR Department of Land and Natural Resources DOE Department of Education DOH Department of Health DOJ Department of Justice DOL Department of Labor

DPM Deputy Project Managers DPP Department of Planning and Permitting DPR Department of Parks and Recreation DPS Department of Public Safety DRH D.R. Horton

DS Downstream DSDC Design Services During Construction

DTS Department of Transportation Services DTU Dillingham Temporary Utilities DUF Division of Urban Forestry DVT Design Verification Test E&E Elevators and Escalators E&O Errors and Omissions

EA Environmental Assessment EAC Estimate at Completion

EB East Bound EC Environmental Compliance

ECP Environmental Compliance Plan ED-CEO Executive Director and Chief Executive Officer

EDD Executive Decision Document E/E Elevator/Escalator EEC Elevators & Escalators Contractor

EHE-EHMP Environmental Hazard Evaluation and Environmental Hazard Management Plan

EIS Environmental Impact Statement EKP East Kapolei

EMC Electromagnetic Compatibility EMF Electromagnetic Forces EMI Electromagnetic Interference

EMP Emergency Management Panel EMR Elevator Machine Room EMT Electrical Metallic Tubing EOM End of Month EOR Engineer of Record EOS Electrically Operated Switch EPA Environmental Protection Agency EPB Emergency Push Button ERD Environmental Review Documents ESA Environmental Site Assessment ETC Estimate to Complete EV Expected Value

FAA Federal Aviation Administration FACI First Article Configuration Inspection

FAI First Article Inspection FAR Floor Area Ratios FAT Factory Acceptance Tests

FC Fare Collection FCC Federal Communications Commission FCN Field Change Notice FCU Fan Coil Units

FD Final Design FDAS Fire Detection Alarm System

FDC Field Design Change FDR Final Design Review FEIS Final Environmental Impact Statement

FEMA Federal Emergency Management Agency FFC Fixed Facility Contractor

FFGA Full Funding Grant Agreement FHB First Hawaiian Bank

FHSG Farrington Highway Station Group

FHWA Federal Highway Administration FISC Fleet and Industrial Supply Center

FIT Field Integration Test FLSWG Fire/Life-Safety Working Group

FM Force Main FMEA Failure Modes and Effects Analysis

FMECA Failure Modes, Effects, and Criticality Analysis FO Fiber Optic

FOCN Fiber Optic Communication Network FOM Finding of Merit/No Merit

FP Fix Panel FPM Fix Panel Mono FPO Federal Preservation Officer FSC Fare Systems Contract FTA Federal Transit Administration FTE Full-Time Equivalent FUT Functional Unit Testing FWS Fish and Wildlife Service

FY Fiscal Year GAT Great Aleutian Tsunami GBS Gap Breaker Station GDR Geotechnical Data Report GEC General Engineering Consultant GER Geotechnical Engineering Report GET General Excise and Use Tax GGP General Growth Properties GIS Geographic Information System

GOE Grant of Easement GPR Ground Penetrating Radar GRP Glass Reinforced Plastic GSA General Services Administration

GT General Terms GW Guideway HA Hazard Analysis

HABS Historic American Buildings Survey HACBED Hawai‘i Alliance for Community-Based Economic Development

HAER Historic American Engineering Record HALS Historic American Landscape Survey HAR Hawai‘i Administrative Rules

HART Honolulu Authority for Rapid Transportation HCC Honolulu Community College

HCDA Hawai‘i Community Development Authority HCS Historic Context Studies

HCSD Hawai'i Capital Special District HDCC Hawaiian Dredging Construction Company HDD Horizontal Directional Drilling

HDOE Hawai'i Department of Education HDOH Hawai'i Department of Health HDOT Hawai'i Department of Transportation

HDOT-A Hawai'i Department of Transportation Airports Division HDPE High-density polyethylene HECO Hawaiian Electric Company

HEI High Energy Inc. HFD Honolulu Fire Department HHC Howard Hughes Corp HHF Historic Hawai'i Foundation

HHFDC Hawaii Housing Finance & Development Corporation HHM Hardy Heck Moore

HHPRB Hawai'i Historic Places Review Board HIA Honolulu International Airport HIE Hawaii Independent Energy

HILT Hawaiian Islands Land Trust HIOSH Hawaii Occupational Safety and Health Division

HOP Ho'opili HP Historic Preservation

HPC Historic Preservation Committee HPCA Historic Preservation Certification Application

HPCAT Historic Preservation & Cultural Awareness Training HPD Honolulu Police Department HPF Historic Preservation Fund HPL Horizon Partners Ltd. HPU Hawai‘i Pacific University HRH Hitachi Rail Honolulu Joint Venture

HRHP Hawai'i Register of Historic Places

Page 6: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

6 | P a g e

HRI Hitachi Rail Italy HRR Heat Release Rate

HRTP Honolulu Rail Transit Project HRU Hitachi Rail USA, Inc.

HSNWG Hawaiian Station Naming Working Group HSQE Health, Safety, Quality and Environmental

HSSQE Health Safety Security Quality and Environment HTI Hawaiian Telcom HTL Hazard Tracking Log HV High Voltage

HVAC Heating, Ventilation and Air Conditioning I&T Inspection & Testing

IAMR Interstate Access Modification Report IBEW International Brotherhood of Electrical Workers

IC Interim Certification ICCS Integrated Communications Control System ICD Interface Control Documents ICE Independent Cost Estimate

ICM Interface Control Manual ICWG Interim Certification Working Group

IDIQ Indefinite Delivery/Indefinite Quantity IDS Intrusion Detection System IFB Issued for Bid IFC Issued for Construction

IJ Isolation Joint IMP Interface Management Plan

INMS Integrated Network Management System I/O Interim Opening

IOMP Intermediate Operations and Maintenance Period IP Implementing Procedures

IRTP Individual Role Training Plans ITP Inspection and Test Plan ITS Intelligent Transportation Systems IVR Interactive Voice Response

JTMC Joint Traffic Management Center JTMS Joint Traffic Management System JU&O Joint Use & Occupancy JUOA Joint Use and Occupancy Agreement

JV Joint Venture KCC Kapi‘olani Community College

KCDD Kaka'ako Community Development District KCH Kanehili Cultural Hui KHG Kamehameha Highway Guideway KHR Kamehameha Highway Resurfacing

KHSG Kamehameha Highway Station Group KIWC Kiewit Infrastructure West Company KKJV Kiewit/Kobayashi Joint Venture

KPI Key Performance Indicator KVM Keyboard Monitor Mouse

L+E Lea +Elliott LCC Leeward Community College LCP Local Control Panel LD Lagoon Drive

LDS Latter Day Saints LEED Leadership in Energy and Environmental Design

LF Linear Feet LOO Letter of Offer

LOTB Log of Test Borings LPR License Plate Reader LRV Light Rail Vehicle

LT Load Test LTC Load Tap Changer LV Low Voltage

LVPS Low Voltage Power Supply MAI Mason Architects MCY Makai Casting Yard MDS Mobile Data System MED Mechanical/Electrical Division MEP Mechanical, Electrical and Plumbing MIM Manufacture-Install-Maintain MIP Manufacturing and Inspection Plans

MITT Multimodal Integration Technical Team MMIS Maintenance Management Information System MMP Mitigation Monitoring Program

MOA Memorandum of Agreement MOS Minimum Operable Segment MOT Maintenance of Traffic MOU Memorandum of Understanding

MOW Maintenance of Way MPD Multiple Property Documentation MPS Master Project Schedule

MPSS Master Project Schedule Summary MPV Multiple Purpose Vehicle MPY Makai Precast Yard MS4 Municipal Separate Storm Sewer System

MSDS Material Safety Data Sheet MSE Mechanically Stabilized Earth MSF Maintenance and Storage Facility MSP Maintenance Service Plan

MSTC Middle Street Transit Center MSTCS Middle Street Transit Center Station

MTM Modern Track Machineries NAICS North American Industry Classification System

NCE Non-Conformance Evaluation NCR Non-Conformance Report NDC Notice of Design Change

NEPA National Environmental Policy Act NFPA National Fire Protection Association NGO Non-governmental Organization NHL National Historic Landmark NOI Notice of Intent

NPDES National Pollutant Discharge Elimination System NPS National Park Service NR National Register

NRHP National Register of Historic Places NSM Negotiation Strategy Memo NTE Not to Exceed NTP Notice to Proceed NTS Network Time Server

NUC Next Unit of Computing O&M Operations and Maintenance

OCC Operations Control Center OCCC Oahu Community Correctional Center OCCL Office of Conservation and Coastal Lands OCIP Owner-Controlled Insurance Program ODC Other Direct Costs

OEQC Office of Environmental Quality Control OH Overhead

OHA Office of Hawaiian Affairs OIBC O'ahu Island Burial Council

OIC Officer-in-Charge OIL Open Items List OIP Order of Immediate Possession

OMP Operation and Management Plan OMPO Oahu Metropolitan Planning Organization

OP Oversight Procedure OR&L Oahu Railway & Land Co. ORCC Operational Readiness Conformance Checklist

OSB Operations and Servicing Building OSHA Occupational Safety and Health Administration

OSIT On-Site Inspection Test OSM Owner Supplied Materials

OTDR Optical Time Domain Reflectometer OTR One-Time Review OTS Oahu Transit Services

OTW Oceanic Time Warner OTWC Oceanic Time Warner Cable OWG Operation Working Group

P3 Public-Private Partnership PA Programmatic Agreement

PAIS Programmatic Agreement Implementation Schedule PARs Preventative Actions PAT Production Acceptance Test

PB Parsons Brinckerhoff, Inc. PCCP Portland Cement Concrete Pavement

PCI Payment Card Industry PCN Potential Change Notice PCY Precast Yard

Page 7: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

7 | P a g e

PD Position Description PDR Preliminary Design Review

PE Preliminary Engineering PF Power Frequency

PFP Project Financial Plan PGC Pacific Guardian Center PHA Preliminary Hazard Analysis

PHGTC Pearl Highlands Parking Garage and Transit Center PHL Pearl Highlands Station

PHNB Pearl Harbor Naval Base PHPR Pearl Highlands Park and Ride

PHPTR Pearl Highlands Parking Structure, Transit Center and Ramp H2R1 PHS Pearl Harbor Station

PI Public Involvement PICM Project Interface Control Manual

PID Parcel Identification Number PIG Permitted Interaction Group PIM Project Interface Manager PIP Public Involvement Plan PIS Passenger Information Systems

PLA Project Labor Agreement PLO Priority-Listed Offerors PLR Pearlridge Station PM Project Managers

PMC Project Management Consultant PMIM Project Management and Interface Management PMOC Project Management Oversight Contractor

PMP Project Management Plan PMSC Program Management Support Consultant

PNR Park-and-Ride POC Project Oversight Committee POP Period of Performance POS Point of Sales PPE Personal Protective Equipment

PRTCC Pre-revenue Testing Conform Checklist PSC Personal Services Contract PSG Platform Screen Gate

PSGS Platform Screen Gate System PSIT Pre-shipment Inspection Test PSS Public Sector Solutions PT Post-tensioned

PTG Parsons Transportation Group PUA Possession and Use Agreements PUC Public Utilities Commission PUP Property Utilization Plan

PV Passenger Vehicle QA Quality Assurance

QAM Quality Assurance Manager QAP Quality Assurance Plan

QC Quality Control QMP Quality Management Plan QMS Quality Management System QTF Quality Task Force QTO Quantity Takeoff R&A Readiness and Activation R&R Revise & Re-submit

RA Risk Assessment RAC Rail Activation Committee

RAMP Real Estate Acquisition Management Plan RAP Rail Activation Plan RAT Routine Acceptance Test

RC Reinforced Concrete RCMP Risk and Contingency Management Plan

RCP Reinforced Concrete Pipe RE Resident Engineer

READ Real Estate Acquisition Database REC Real Estate Consultant RFB Request for Bids RFC Request for Change

RFCC Request for Change from Contractor RFCR Request for Change by HART RFHB Request for High Bids

RFI Request for Information RFID Requests for Interface Data

RFMP Rail Fleet Management Plan RFP Request for Proposals RFQ Request for Qualifications RFV Request for Variance RHB Road and Highway Builders, LLC RLB Rider Levett Bucknall RLS Request for Legal Services

RMS Risk Management System RMTC R.M. Towill Corporation

RNR Revise and Resubmit ROC Rail Operations Center ROD Record of Decision ROE Right of Entry ROH Revised Ordinances of Honolulu

ROM Rough Order of Magnitude ROW Right-of-Way

RP Recovery Plan RR Risk Register

RSD Revenue Service Date RST Retail Sales Device Training RTE Request to Exceed Negotiation Strategy Memo Target

RTM Requirements Traceability Matrix RTSA Regional Transit Stabilization Agreement

S&S Safety and Security S1 Segment 1

SAIS Supplemental Archaeological Inventory Survey SAV Shared Autonomous Vehicle

SC Substantial Completion SCADA Supervisory Control and Data Acquisition

SCAP Stream Channel Alteration Permit SCC Standard Cost Category SCH Satellite City Hall

SHPD State Historic Preservation Division SHPO State Historic Preservation Officer

SIC Sandwich Isle Communications SIRP Safety Incident Review Panel

SIT System Integration Testing SITP System Integration and Test Plan SITR Site Inspection and Test Report

SL Street Light SLAN Secured Local Area Network

SLR Sea Level Rise SM Service Manager

SMA Special Management Area SMS Structural Monitoring Solutions SOG Slab on Grade SOI Secretary of the Interior

SON Summary of Negotiations SOP Standard Operating Procedures

SOW Scope of Work SP Special Provisions

SQP Supplemental Quality Plan SS System Site

SSC Safety Security Certification SSCP Safety and Security Certification Plan

SSCWG Safety and Security Certification Working Group SSI Sensitive Security Information

SSMP Safety and Security Management Plan SSRC Safety and Security Review Committee SSSP Site Safety Security Plan

STATCOM Static Synchronous Compensator STCC Specification Testing Conformance Checklists STG Shimmick/Traylor/Granite, Joint Venture STP System Test Procedure

SUBD Subdivision Branch SUE Subsurface Utility Engineering

SWPPP Storm Water Pollution Prevention Plan SwRI Southwest Research Institute T&M Time and Material TAC Transit Art Committee TAP Track Allocation Procedure TAT Transient Accommodation Tax

TC Train Control TCA Temporary Configuration Change

Page 8: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

8 | P a g e

TCCR Train Control and Communications Room TCE Temporary Construction Easement TCO Temporary Certificate Occupancy TCP Traffic Control Plan TCS Train Control System

TDFM Travel Demand Forecasting Model TDM Transportation Demand Management

TES Traction Electrification System TIA Time Impact Analysis

TIGER Transportation Investment Generating Economic Recovery TIP Transportation Improvement Program

TMK Tax Map Key TMP Traffic Management Plan

TO Task Order TOC The Outdoor Circle TOD Transit-Oriented Development

TP Technical Provision TP&R Temporary Park & Ride

TPBuGen Traction Power Backup Generator TPO Thermoplastic Polyolefin

TPSS Traction Power Substation TS Traffic Signal

TSA Transportation Security Administration TSI Transportation Safety Institute

TTSP Temporary Traffic Signal Plan TUT Temporary Utility Take TVA Threat and Vulnerability Assessment

TVM Ticket Vending Machine TWF Train Wash Facility UCA Utility Construction Agreement

UFRCRA Utility Facilities Relocation and Cost Reimbursement Agreement UG Underground UH University of Hawai'i

UHPRB UH West O‘ahu Park and Ride & UHWO Campus Road “B” UHWO University of Hawai'i West O'ahu

UL Underwriters Laboratories UPS Uninterruptible Power Supply URA Uniform Relocation Assistance and Real Property Acquisition

Policies Act USACE U.S. Army Corps of Engineers USDOL United States Department of Labor USDOT U.S. Department of Transportation

USN United States Navy USPS U.S. Postal Service

UST Underground Storage Tank UTR Under Technical Review VAR Volt-Ampere Reactive VCR Vertical Conduit Raceway

VE Value Engineering VECP Value Engineering Change Proposal

VISTA Volunteers in Service to America VMS Variable Message Sign VRC Vertical Raceway Column

VRCS Voice Radio Communication System VRF Variable Refrigerant Flow VTP Vehicle Test Procedure WA Work Area

WCS Wireless Communication System WHS Waipahu High School

WKM Walters, Kimoda, Motoda, Inc. WL West Loch

WLO West Loch WOEDA West Oahu Economic Development Association

WOFH West O'ahu/Farrington Highway WOSG West O'ahu Station Group

WQC Water Quality Certification WSS West Side Stations

WSSG West Side Stations Groups WTB Wheel Truing Building WTC Waipahu Transit Center WTP Wayside Test Procedure

WWB Wastewater Branch WWPS Wastewater pump station

WYL West Yard Lead

YCB Yard Control Bungalow YKE Yogi Kwong Engineers YOE Year of Expenditure

Page 9: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

9 | P a g e

Rail Stations Kualaka‘i Station at East Kapolei Keone‘ae Station at UH West O‘ahu Honouliuli Station at Ho‘opili Hō‘ae‘ae Station at West Loch Pouhala Station at Waipahu Transit Center Hālaulani Station at Leeward Community College Waiawa Station at Pearl Highlands Kalauao Station at Pearlridge Hālawa Station at Aloha Stadium Makalapa Station at Pearl Harbor Naval Base Lelepaua Station at Honolulu International Airport Āhua Station at Lagoon Drive Kahauiki Station at Middle Street Transit Center Mokauea Station at Kalihi Niuhelewai Station at Kapalama Kūwili Station at Iwilei Hōlau Station at Chinatown Kuloloia Station at Downtown Ka‘ākaukukui Station at Civic Center Kūkuluae‘o Station at Kaka‘ako Kālia Station at Ala Moana Center

PROJECT MAP

Page 10: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

10 | P a g e

1 SUMMARY

REPORTING DATE AND SUBSEQUENT EVENTS

This report was published on March 27, 2020. Data is presented with a reporting cutoff date of Feb. 29, 2020, unless otherwise noted.

KEY ACTIVITIES IN FEBRUARY Project Overview The fourth train that will be a part of the Honolulu Authority for Rapid Transportation’s (HART’s) interim opening fleet has arrived at the Rail Operations Center (ROC) in Waipahu in February. A total of six trains will be a part of HART’s interim opening fleet.

Train Community Day Approximately 2,500-3,000 people attended HART’s Train Community Day at the Hālaulani Station at Leeward Community College in February. This Train Community Day was the first opportunity the public has had to see a rail station up close. Attendees were able to experience the stations unique architectural and cultural design elements, as well as boarded the train directly from the passenger platform. COST (as of Feb. 29, 2020)

Project Cost Summary ($ in millions)

Description Original FFGA

Budget Recovery Plan

Budget* Current Estimate at Completion (EAC)*

Incurred To Date

Project Capital Costs

Base Cost without Contingency $4,305 $7,312 $7,381 $4,065

Allocated Contingency $542 $765 $696 $0

Unallocated Contingency $102 $222 $88 $0

Total Project Capital Costs $4,949 $8,299 $8,165 $4,065

FFGA Finance Charges $173 $609 $547 $32

Total FFGA Project Costs $5,122 $8,908 $8,712 $4,097

Post-RSD Finance Charges $42 $231 $293 $0

Total Project Costs $5,164 $9,139 $9,005 $4,097

*Total Project Costs excludes Operations and Maintenance.

Original FFGA Budget The Original FFGA Budget reflects the full build-out of the project as executed by the Full Funding Grant Agreement in December 2012. The contingency is a reserve to cover known and unknown, but anticipated, project execution costs and uncertainty due to risk factors such as unresolved design issues, unknown site conditions, schedule impacts and market fluctuations. The Original FFGA Budget reflects $644 million in total contingency. Recovery Plan Budget Total The approved Recovery Plan Project capital cost estimate is $8,299 million (excluding finance costs). The total project cost is $9,139 million, which includes post-Revenue Service Date (RSD) financing costs of $231 million and $8,908 million in FFGA project costs (which includes $765 million in allocated contingency, $222 million in unallocated contingency, and $609 million in financing costs). While this cost is $134 million greater than HART’s cost estimate of $8,165 million, HART has revised the Project cost estimate and identified the additional funding to meet the higher estimate. The Recovery Plan Budget reflects $987 million of total contingency or 13% of the base cost estimate which reflects available funding capacity. Based on FTA requirements on contingency for the current phase of the project, the 13% is sufficient reserve to cover against the risk of cost increases during development of the project.

Page 11: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

11 | P a g e

Current Estimate at Completion (EAC) The current project capital Estimate at Completion (EAC) is $8,712 million, including $784 million in total contingency ($696 million in allocated contingency and $88 million in unallocated contingency) and $547 million in financing costs. The total project costs including post-Revenue Service Date (RSD) financing costs of $293 million is $9,005 million. The total project contingency is based on a December 2025 RSD. Incurred to Date The Incurred-to-date costs are cumulative through February 2020, and exclude third-party reimbursement costs. The $4,097 million to date represents 56% of the base Current EAC. The Incurred-to-date costs increased by $42 million for the period. SCHEDULE The progress reported in the table below provides percent complete based on construction and design contracts. The early and late plans are based on baseline schedules for active contracts and forecasts of future contracts.

Project Progress* Through Feb. 28, 2020

Actual Early Plan Late Plan

Overall Project Progress 55.7% 66.5% 59.5%

Construction Progress 51% 62.4% 56.3%

Design Progress 80.3% 79.6% 76.5%

*Reported percentages complete are based on the Estimate at Completion for the

Minimum Operable Segment (MOS) and December 2025 Revenue Service Date (RSD).

PROGRESS REPORT SUMMARY OF CHANGES The following is a brief summary of major changes that have occurred from the previous month’s report. For more information and detail, please refer to the respective pages in the report.

The Board Meeting Q&A section has been removed, as there were no public questions posed at the February meeting.

Contract Status

The methodology for calculating the Outstanding Issues amount and the corresponding Contractor CP Amount in the construction contract pages has been changed to only account for issues which have a Finding of Merit granted.

Core Systems Contract (CSC)

o The current contract value amount has increased due to change orders. Please see page 23.

Elevators and Escalators Manufacture-Install-Maintain (MIM) o The current contract value amount has increased due to a change order. Please see page 28.

Farrington Highway Station Group (FHSG)

o The projected completion of work date has changed from April 2020 to June 2020. Please see page 41. o The schedule status has changed from “15 months behind” to “17 month behind.” Please see page 41.

Kamehameha Highway Resurfacing (KHR) o The projected completion of work date has changed from February 2020 to March 2020. Please see page

51. o The schedule status has changed from “5 months behind” to “6 month behind.” Please see page 51.

Page 12: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

12 | P a g e

City Center Utilities Relocation (CCUR) Indefinite Delivery/Indefinite Quantity (IDIQ) o The projected completion of relocation work date has changed from December 2022 to September 2022.

Please see page 60. o The schedule status has changed from “7 months behind” to “4 months behind.” Please see page 60. o The Physical % Complete has been changed to “TBD” as CEI is currently working on an EAC for all the work

required prior to the P3 contractor commencing their work. Once this reevaluation of the comprehensive project cost is established, the percent complete in each work area can be determined. Please see page 60.

Page 13: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

13 | P a g e

2 OVERALL PROJECT PROGRESS AND FINANCIALS

2.1 Project Progress (data as of Feb. 28, 2020) Reported percentages complete are based on the Estimate at Completion for the MOS and December 2025 RSD. HART will revise its progress curves further when the in-process change orders are executed. This revision is expected to lower the plan values. Note:

Actual = Actual cost of work performed, based on reported work-in-place.

Early Plan = Earliest dates activities can begin and finish, based on logic and durations used in the schedule.

Late Plan = Latest dates activities can begin and finish and not have an impact on completion date, based on logic and durations used in the schedule.

Figure 1. Overall Project Progress (% Complete)

At present "overall" project progress is based on the weighted value progress of the individual construction and design contracts (Design-Build [DB], Design-Bid-Build [DBB], Design-Build-Operate-Maintain [DBOM], Elevator/Escalator Manufacture-Install-Test-Maintain [MIM], Final Design [FD] and DB-DBOM design levels of effort), not including City or non-design consultant labor.

Figure 2. Construction Progress (% Complete)

Overall construction progress is based on the weighted average progress of the individual DBB and E/E MIM construction contracts and the DB-DBOM construction levels of effort, not including consultant Construction Engineering and Inspection (CEI) services.

Page 14: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

14 | P a g e

Figure 3. Design Progress (% Complete)

Overall design progress is based on the weighted average progress of the individual FD contracts and the design levels of effort of the DB and DBOM construction contracts, not including City or non-design consultant labor.

Page 15: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

15 | P a g e

2.2 Project Budget (data as of Feb. 29, 2020)

Project Cost Summary ($ in millions)

Description Original FFGA

Budget Recovery Plan

Budget* Current Estimate at Completion (EAC)*

Project Capital Costs

Base Cost without Contingency $4,305 $7,312 $7,381

Allocated Contingency $542 $765 $696

Unallocated Contingency $102 $222 $88

Total Project Capital Costs $4,949 $8,299 $8,165

FFGA Finance Charges $173 $609 $547

Total FFGA Project Costs $5,122 $8,908 $8,712

Post-RSD Finance Charges $42 $231 $293

Total Project Costs $5,164 $9,139 $9,005

*Total Project Costs excludes Operations and Maintenance.

The Original FFGA Budget reflects the full build-out of the project as executed by the Full Funding Grant Agreement in December 2012. The approved Recovery Plan Project capital cost estimate is $8,299 million (excluding finance costs). While this cost is $134 million greater than HART’s cost estimate of $8,165 million, HART has revised the Project cost estimate and identified the additional funding to meet the higher estimate. Total project contingency remained the same at $784 million ($696 million in allocated contingency and $88 million in unallocated contingency) since last updated.

Contingency Drawdown Curve

Date Jun-2020 Dec-2020 Sep-2022 Jan-2023 Dec-2024 Dec-2025

Milestone P3 NTP Interim

Opening

DBB511 Construction

Complete

DB450 Construction

Complete

P3 Construction

Complete RSD

FTA Minimum Level ($M)

685

592

405

381

215

134

HART Minimum Level ($M)

551

458

271

247

131

85

Page 16: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

16 | P a g e

2.3 Project Funding

Figure 4. Planned vs. Received Project Funding

Planned vs. Received Project Funding

Funding Source

Pre-FFGA Project1

Project Funding Total

Project

2007 - 2009 Actuals

Received

Planned2 2009 -

Present Actuals

Received

2007 - Present Actuals

Received

Actuals Received in

Feb 2020 ($YOE M)

Beginning Project Cash Balance3 - 298 298 - -

Interest Income on Cash Balance5 7 1 9 16 0

FTA Section 5309 New Starts Revenue4 - 1,550 806 806 -

ARRA Funds - 4 4 4 -

EPA Brownfields Grant (FY2018-FY2021)6 - 1 0 0 -

Net General Excise Tax (GET) Surcharge revenues FY2010-FY2031 378 5,990 2,292 2,670

-

Transient Accommodation Tax (TAT) revenue FY2018-FY2031 - 1,182 98 98

-

City Subsidy - HART Administration FY2018-FY2031 - 214 44 44 -

Total 385 9,240 3,551 3,638 0

1 GET and Interest Income received during Pre-Preliminary Engineering (pre-PE) phase prior to entry into PE. 2 Updated to Chapter 6 - Project Finance, Figure 6-2 of HART's Approved Recovery Plan (for beginning cash balance, GET, TAT, grant revenue, city subsidy and interest income).

3 Beginning Project Cash Balance at Entry into Preliminary Engineering (PE) on October 16, 2009 (the FFGA Project start date) = Pre-PE GET, investment and miscellaneous income minus pre-PE expenditures. The $298 million is included in the Pre-FFGA actual amounts received between 2007-2009 of $378 million.

4 New Starts Funds Obligated Through Federal Fiscal Year 2014 Totals $806.3 million. 5 Interest Income received in February 2020 - $85,660.63

6 EPA $900,000 Brownfields Grant must be used by 12/31/2020 - to plan and subsidize the environmental cleanup activities.

EPA Brownfields Grant revenue received to date - $55,260.87

Page 17: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

17 | P a g e

Figure 5. New Starts Drawdown by Federal Fiscal Year

New Starts Grant Information by Federal Fiscal Year (Amounts in Italics are Pending)

Federal Fiscal Year (FFY) Allocation

FTA Obligated Amounts

Actual Drawdown Amounts to Date

Available Balance FFGA Base Case Cash Flow

2008 $15,190,000 $15,190,000 $0

2009 $19,800,000 $19,800,000 $0

2010 $30,000,000 $30,000,000 $0

2011 $55,000,000 $55,000,000 $0 $20,607,242

2012 $200,000,000 $200,000,000 $0 $99,382,758

2013 $236,277,358 $236,277,358 $0 $258,280,277

2014 $250,000,000 $249,991,376 $8,624 $441,719,724

2015* $250,000,000 $0 $0 $0

2016* $250,000,000 $0 $0 $0

2017* $243,732,642 $0 $0 $0

2018 $0 $0 $0 $0

2019 $0 $0 $0 $0

2020 $0 $0 $100,000,000 $100,000,000

2021 $0 $0 $150,000,000 $150,000,000

2022 $0 $0 $150,000,000 $150,000,000

2023 $0 $0 $150,000,000 $150,000,000

2024 $0 $0 $100,000,000 $100,000,000

2025 $0 $0 $50,000,000 $50,000,000

2026 $0 $0 $43,732,642 $30,010,000

Total $1,550,000,000 $806,258,734 $743,741,266 $1,550,000,000 *These years' awards have not been available for drawdown. The availability of dollars are expected to follow the approved HART Recovery Plan and are reflected in the Available Balance column.

Page 18: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

18 | P a g e

3 SCHEDULE (data as of Feb. 28, 2020)

Critical Path Analysis Interim Revenue Service Date is planned for no later than December 2020. The Projected Revenue Service date,

currently forecasted for Oct. 20, 2020, defines operational readiness of the system. The Department of Transportation Services (DTS) makes the final determination of passenger service. o The critical path for Operational Readiness of the passenger rail system from East Kapolei Station to Aloha

Stadium Station is the Communication systems installation at West O‘ahu and Kamehameha Highway Stations, Subsystem acceptance for balance of structure at Pearlridge and Aloha Stadium Stations, and Core Systems Testing.

o For the near critical path, activities include canopy installation at Aloha Stadium Station, the Supervisory Control and Data Acquisition (SCADA) work at West O‘ahu and Kamehameha Highway Stations, Comm. Installation and Testing at Pearl Highlands Station, and Platform Screen Gate (PSG) installation at Pearlridge Station.

Revenue Service Date (RSD) is planned for no later than December 2025 (Projected Revenue Service date defines operational readiness of the system. DTS makes the final determination of passenger service). o This month, the critical path begins with Right of Way acquisition of a property required for utility work (AT&T,

Hawaiian Electric Company [HECO] 46kV, Hawaiian Telcom, Oceanic Time Warner Cable) in City Center Utilities Relocation (CCUR) Area 1C. After the utility relocation is complete, drilled shafts, columns and segments for Area 1C continue into platform and structure construction for Kapalama Station, followed by Core System installation and testing.

o The near critical path includes HECO 12 kV and 46 kV work in CCUR Area 1C, construction of utility bridge between CCUR Areas 1B and 1C, and procurement of the Public-Private Partnership (P3)/City Center Guideway and Stations (CCGS) contract.

Three-Month Look Ahead

Station construction for the west station groups continues to include the following: o Canopies: AECOM’s final shop drawings at Aloha Stadium have been approved and fabrication has commenced.

The Aloha Stadium canopy arms, tension fabric and conduit installation are targeted for completion in May 2020. These activities are on the critical path for Kamehameha Highway Station Group substantial completion.

o University of Hawai‘i West O‘ahu (UHWO) Temporary Park and Ride (“Road B”): The roadway landscaping finishes and repair work continues. Punchlist items are being completed.

o Elevators and Escalators: Complete installation of Pearlridge Station Elevators #1 & 2. Ship and receive Elevator #2 for Aloha Stadium. Perform commissioning activities for West O‘ahu Station Group (WOSG) in preparation for State

elevator inspections. Continue construction interface for Airport Guideway and Stations (AGS).

Core Systems continues to install SCADA, and Fire Detection Alarm System (FDAS) subsystems. o Comms Cable Pull at Waipahu, Leeward Community College (LCC), UH West O‘ahu, East Kapolei, Pearl Highlands,

Pearlridge and Aloha Stadium Stations; ongoing through May 2020. As each station completes Comms Cable Pull, connections will be made, and the Comms equipment

will be installed and tested; March 2020 through May 2020. o Re-submission of required Comms Design submittals and Comms test procedures for Maintenance and Storage

Facility (MSF) official testing. o Continue MSF Comm System punchlist by late April 2020. o Continue Passenger Vehicle (PV) #1 Braking Dynamic Test and PV#3 System Static Test. o Delivery of PV #8 in March 2020, PV #13 in April 2020, and PV #14 in June 2020. o Continue Wayside Test Procedure (WTP) testing at Waipahu, LCC and Pearl Highlands Stations. o Complete PV #4 Dynamic Routine Acceptance Test (RAT) Testing. o Complete PSG On-Site Inspection Test (OSIT) at West Loch Station.

AGS o Completion of HECO construction at Zone 6/6A (Airport area), Zone 8 (Ualena and Waiwai Loop area) and Zone 9

(Middle Street Station area).

Page 19: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

19 | P a g e

o For AGS stations, Pearl Harbor Station continues installation of underground mechanical, electrical, and plumbing work at the station entrance, as well as construction of Elevator Machine Room (EMR) walls. Installation of underground conduit to electrical room and Train Control and Communications Room (TCCR) and platform girder work will continue into 2nd quarter 2020. Honolulu International Airport Station to construct Column 542 and hammerhead at Column 543, grade beam and elevator foundations. Installation of HECO new service infrastructure for Honolulu International Airport (HIA) Station and System Site (SS) #27 will also continue. Lagoon Drive Station to continue steel erection at mauka entrance, metal decking installation and welding. Middle Street Transit Center Station to continue installation of drilled shafts at the station entrance and TCCR foundation. Start the pedestrian bridge foundation work in the middle of Dillingham Boulevard.

CCUR o Finalize design and receive permits for wet utility task orders 09 and 16. o Finalize design and receive permits for dry utility task orders 12, 17, 22, 24, 27, 28 and 32. o Finalize the Kapalama Bridge design and begin bridge fabrication. o Complete wet utility locations in Areas 2 and 3. o Commence jet grout plant and drilling at Pi‘ikoi intersection. o Continue excavation and demolition for waterline installation on Brookfield side of Pi‘ikoi.

CCGS o Technical and price submittal.

Key Schedule Issues

AGS’ Shimmick/Traylor/Granite, Joint Venture (STG) current January schedule update puts Substantial Completion at Feb. 24, 2023. This update was rejected and an acceptable mitigation schedule that shows the expected Substantial Completion date of October 2021 is being analyzed.

The contractor provided an updated, detailed station construction schedule for Pearl Harbor, Airport, Lagoon Drive and Middle Street Stations for HART’s review on Jan. 29, 2020. HART reviewed the detailed station activities and provided comments in early February. The contractor will incorporate HART’s comments and provide an updated mitigation schedule in early March.

The AGS contractor submitted a Time Impact Analysis (TIA) schedule in October, requesting a schedule extension and time-related overhead costs. Construction Engineering and Inspection (CEI) and HART are reviewing the TIA schedule.

Schedule Contingency Drawdown Curve

This month, the critical path begins with Right of Way acquisition of a property required for utility work (AT&T, HECO 46kV, Hawaiian Telcom, Oceanic Time Warner Cable) in CCUR Area 1C. After the utility relocation is complete, drilled shafts, columns and segments for Area 1C continue into platform and structure construction for Kapalama Station, followed by Core Systems installation and component testing and Full System Integration Testing, Trial Run and Pre-Revenue Service Demonstration achieving full Revenue Service Date. The assumed CCGS schedule has not been revised. Secondary mitigation is being explored and will be implemented.

Page 20: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

20 | P a g e

Figure 6. HRTP Master Project Schedule Summary (MPSS) The Master Program Summary Schedule reflects currently approved schedule end dates for contracts that have been awarded, and planned dates for future contracts.

Page 21: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

21 | P a g e

4 CONTRACT STATUS

Contracts in Procurement

Overview Awarded Contracts:

o None.

Active Procurements: o City Center Guideway and Stations / Pearl Highlands Design-Build Finance Operate and Maintain Request

for Proposals (RFP) qualifications proposals in response to RFP Part 1 were received on April 12, 2019. HART released RFP Part 2 to the priority list of offerors on May 3, 2019. Due to the offerors requesting additional time to prepare proposals, the due date for the technical proposals has been extended to April 2020. As such, the Notice to Proceed (NTP) date has moved to June 2020. Despite these changes, the planned full revenue service date remains at December 2025.

o HDOT Design Review Support (WOFH) Request for Qualifications was issued on Oct. 11, 2019. Statements of Qualification submissions were received on Nov. 1, 2019 and the contract is being negotiated.

o Art-in-Transit: HART continues its negotiations with the highest-ranked artists for each of the stations. To date, twelve (12) contracts have been awarded.

o HDOT/DTS Traffic Management Coordination Request for Qualifications was issued on Jan. 17, 2020. Statements of Qualification submissions were received on Feb. 19, 2020 and are currently being evaluated.

o Outside Claims Counsel Request for Sealed Proposals was issued on Jan. 14, 2020. Sealed proposals were received on Feb. 14, 2020.

o Passenger WiFi System Request for Sealed Bids was issued on Jan. 17, 2020. Addendum No. 2 issued on Feb. 11, 2020 extended the solicitation timetable. Sealed bids, originally due on Feb. 18, 2020, are now due on March 3, 2020.

Active Procurements

Contract Code

Contract Name Advertise

Date

Bids or Proposals

Due Issue NTP

Projected Contract

Substantial Completion

Date

AP-00 Art-in-Transit May 09 '13

12 contracts awarded;

active procurement for remaining

stations

Staggered Staggered

DB-550 City Center Guideway and Stations / Pearl Highlands Design-Build Finance Operate And Maintain (DBFOM)

Sep 28 ‘18 Apr 12 ‘19 (RFP Pt. 1)

Jun ‘20 TBD

MM-920 HDOT Design Review Support (WOFH) Oct 11 ‘19 Nov 1 ‘19 TBD TBD

MM-915 HDOT/DTS Traffic Management Coordination

Jan 17 ‘20 Feb 19 ‘20 May ‘20 TBD

MM-980 Outside Claims Counsel Jan 14 ‘20 Feb 14 ‘20 Mar ‘20 TBD

DBOM-920 Passenger WiFi System Jan 17 ‘20 Mar 3 ‘20 Mar ‘20 TBD

Page 22: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

22 | P a g e

Upcoming Procurement Under Evaluation

Contract Code Contract Name Issue Date

MM-960 Archaeological and Cultural Survey Mar ‘20

DBB-511 City Center Utility Relocation II Apr ‘20

TBD Real Estate Consultant (REC) III TBD

TBD Guideway Bridge Inspection Mar ‘20

TBD Fare Collection System Redundant Fiber Connection Service Apr ‘20

Page 23: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

23 | P a g e

4.1 System-wide

A. Core Systems Contract (CSC) CPP No.: DBOM-920 DBOM Contractor: Hitachi Rail Honolulu Joint Venture (HRH) Contract Start Date: January 2012 Contract Substantial Completion: January 1, 2025 Projected Completion of Work: July 2025

Project Description: A design, build, operate and maintain contract to provide rail passenger vehicles, automated train control system, traction electrification system (TES), communication systems, passenger platform screen gates (PSGs), and operation and maintenance of the Core Systems.

Design & Construction Vehicles Schedule Status

Physical % Complete 67.0% 71.6% On time for 2025

opening Early Plan* 84.0% 96.1%

Late Plan* 60.8% 54.9% *Data as of Feb. 28, 2020. The progress chart reflects early program expectations. Progress is being tracked against interim Construction Access Milestone dates, which show the project is "On-Time".

________________________________________________________________________________________________________________________________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $419,568

DBE % Attained: 0.068%

Contract Changes in February

Change No. Description Amount ($)

Cumulative Previously Reported $208,820,903

00061 Portable Lifts $703,840

00062 Portable Backup Generator for TCCRs $211,630

Cumulative Current Report $209,736,373

Original Contract: $573,782,793 Incurred-to-Date: $413,391,550

Current Contract Value1: $783,519,166 Incurred in February: $02

Outstanding Issues3: 4 Contractor CP Amount: $1,009,097

1Current Contract Value = Original contract value (excluding original O&M budget) + executed Change Orders 2 Work has progressed and incurred amounts will be reflected as invoices are approved in the City’s C2HERPS system. 3 The methodology for calculating the Outstanding Issues amount and the corresponding Contractor CP Amount has been changed to only account for issues which have a Finding of Merit granted.

Page 24: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

24 | P a g e

SCHEDULE: Upcoming Key Indicators for 2020 Interim Opening 1:

Feb 2020 Mar 2020

• Completion of Mobile Data System (MDS) network in Functional Section (Ho‘opili [HOP] to Leeward Community College [LCC]): Installation in Progress

• Completion of MDS network to EKP

• Energization of 3rd Rail to Pearlridge Station (PLR) (LCC Gap Breaker Station [GBS] + Pearl Highlands Station [PHL] Traction Power Substation [TPSS]): Completed

• Completion of Secured Local Area Network (SLAN) network to LCC GBS: Completed

• Completion of SLAN network to PHL TPSS: Completed

• Completion of LCC Supervisory Control and Data Acquisition (SCADA) TPSS: Completed

• Completion of PHL SCADA TPSS: Completed • Completion of PHL Uninterruptible Power Supply

(UPS): 50% Complete, target to finish on 3/3/2020

• Energization of 3rd Rail to Aloha Stadium Station (ALS) (PLR TPSS + ALS TPSS)

• Completion of SLAN network to PLR TPSS • Completion of SLAN network to ALS TPSS • Completion of PLR SCADA TPSS • Completion of ALS SCADA TPSS • Completion of UHWO UPS: Completed • Completion of PLR UPS

• Completion of PHL Automatic Train Control (ATC) Wayside Test Procedure (WTP): Completed

• Completion of West Yard Lead (WYL) PSGS: 50% Complete

• Completion of LCC PSGS

• Completion of PLR ATC WTP: 30% Complete • Completion of ALS ATC WTP • Completion of EKP PSGS • Completion of UHWO PSGS

• Train #12 Completion of onboard ATC: 95% Complete, target to finish on 3/6/2020

• Train #12 Completion of onboard COM: 5% Complete

• Train # 10 Interim Certified for Dynamic Testing & Dynamic Test Completed: Completed

• Arrival of Train #9: Completed

• Train #10 Completion of onboard ATC and onboard COM

• Train # 11 Interim Certified for Dynamic Testing & Dynamic Test Completed

• Completion of East Kapolei (EKP) Fire Detection Alarm System (FDAS): Completed

• Completion of West Loch (WLO) FDAS

• Completion of COMM Closed Circuit Television (CCTV)/Passenger Information Systems (PIS)/Access Control System (ACS)-Intrusion Detection System (IDS) at HOP: Installation in progress

• Completion of COMM at MSF: 60% Complete

• Completion of COMM CCTV/PIS/ACS-IDS at WLO/WYL

• Completion of UHWO UPS: Completed

• Completion of Station SCADA HOP: Awaiting cable delivery

• Completion of Station SCADA WLO/WYL

Page 25: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

25 | P a g e

WORK PROGRESS: Activities this Month: Design: Review of design submittals is ongoing. Focus is to close

out communications, passenger vehicles and Requirements Traceability Matrix (RTM) issues.

Continued coordination between HRH and the AGS contractor for integration of Core Systems requirements.

Submitted Comms Final Design (FD) for Functional Section.

Manufacturing: Hitachi Rail USA, Inc. (HRU) is continuing with the

production of Trains #7, #8 and #13 through #15 in Pittsburg, CA.

Train #9 was delivered to the MSF on Feb. 14. This is the fourth train of the interim opening fleet.

Testing of ventilation hole retrofit started on Train #3. Installation, Testing and Commissioning: HRH completed Pearlridge TPSS TES feeder cable

installation. HRH completed LCC TPSS testing with SCADA in the

Operations Control Center (OCC). Open items include Blue Light Station (BLS) and Transfer Trip.

HRH started PHL TPSS testing with SCADA in OCC. HRH completed UPS installation in PLR and PHL stations. HRH energized tracks to Pearlridge Station, activating

LCC GBS and PHL TPSS. HRH completed Third Rail collector shoes test toward

Pearlridge Station. HRH completed PSGS mechanical testing and started the

preparation of PSGS functional testing at Waipahu stations.

HRH started the preparation of PSGS mechanical testing at LCC Station.

HRH continues with the remediation of corrosion issues with the PSGS components.

HRH completed ATC WTP testing in PHL and EKP stations.

HRH continues with Communication equipment testing in the MSF/yard.

HRH continues onboard ATC testing with Train #2 in the functional section.

HRH continues with qualification tests using Trains #1 and #3 (95% complete).

HRH conducted acceptance test with Train #10 and Train #11.

HRH achieved interim certification and completed train dynamic testing for Train #10. Train #10 is ready for onboard ATC testing.

HRH substantially completed ATC Routine Acceptance Test (RAT) with Train #12. Remaining test requires Data Radio and PIS functionality in Train#12.

Look Ahead: Design: Close out of open comments to finalize Final

Design of all subsystems. Continue coordination between HRH and

FHSG/KHSG/AGS. Complete Communications Final Design.

Manufacturing: Passenger Vehicle truck fabrication – continue

truck frame and bolster delivery from Italy. Complete car shell fabrication activities in Italy.

Three car shells will be fabricated in Reggio Calabria to replace the car shell used for roof and floor fire re-test and to replace Train #1 and Train #2 car shells with the extrusion defect.

Continue manufacturing of communications and other subsystems equipment.

Installation, Testing and Commissioning: Complete SCADA testing with peripheral devices in

the MSF, after installation is completed. Integration test between TPSS/GBS and OCC to

complete (PHL, PLR and ALS). MSF SLAN/Communications Transmission System

(CTS), CCTV, ICS/IDS, Voice Radio Communication System (VRCS), TEL Acceptance Test to continue.

MSF PIS acceptance test to start. Onboard COMM acceptance test to start. PSGS Commissioning test at WTC, LCC, EKP and

UHWO to complete in March 2020. Complete Vehicle Test Procedure, Central Test

Procedure, and System Test Procedure in Functional Section.

Continue System Integration Testing with train(s) in the Yard.

Complete remediation of corrosion issues with the PSGS components.

Continue ATC Wayside testing in PLR and ALS Train Control and Communications Room (TCCR).

Conducting energization testing to extend the test area toward Aloha Stadium Station (PLR and ALS TPSS to be utilized).

Resolve the cabling compliance issue for FDAS installation.

Start communication system testing in HOP Station.

Start station SCADA testing in HOP. Complete Train #12 onboard ATC and onboard

COM testing. Complete Train #10 onboard ATC and onboard

COM testing. Achieve Train #11 (March 2020) Interim Certificate

for dynamic testing.

Page 26: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

26 | P a g e

Activities this Month (continued): HRH continues with the communication system

installation in HOP, West Loch, Waipahu and LCC station. HRH completed EKP FDAS installation and standalone

test.

Look Ahead (continued): Arrival of Train #8 in the MSF.

________________________________________________________________________________________________________________________________________________________________________________________________________________________

KEY ISSUES:

Key Issues with Contractor Proposal Title CPC Code

Vehicle Extended Warranty for Carbody Bolster(Extrusion) No Cost

Macton Aug 2018 Lift Repair MSF A

Changing of Vehicle "Square Key" Locks (square to triangle key)

VMS Signs - AGS End of Platform

A A

LEGEND: A = less than $1 million; B = $1 million-$5 million; C = greater than $5 million; P = pending contractor submittal ________________________________________________________________________________________________________________________________________________________________________________________________________________________

KEY MILESTONES:

Interim Opening Fleet (6 trains) to be on-site by April 2020. Energization of Segment 1 in Q1 2020.

________________________________________________________________________________________________________________________________________________________________________________________________________________________

QUALITY MANAGEMENT:

Hitachi has indicated that the two remaining car shells that require replacement of the bolster assemblies due to the aluminum extrusion defects, will be scrapped instead of repaired. Hitachi is in the process of ordering additional material for the fabrication of three (3) new car shells; one to replace the car shell used to expedite the floor and roof fire re-test and two to replace the car shells with extrusion defects.

End Car 1 of Train #12 was damaged (about 2.0 ft. long x ¾ in. wide x ¼ in. deep gouge on the left side, which did not penetrate the aluminum extrusion skin, and about ½ in. diameter penetration in the first set of the Door Panel on the right side of End Car 1) during transit from Pittsburg, CA to Honolulu, HI. Repair procedure is being developed.

CSC NCR Log (Issued by HRH)

Total Closed Open

HRH & Subs 57 51 6

Hitachi Rail 2,022 1,708 314

TOTAL 2,079 1,759 320

Page 27: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

27 | P a g e

TRAIN SCHEDULE:

Page 28: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

28 | P a g e

B. Elevators and Escalators Manufacture-Install-Maintain (MIM) CPP No.: MI-930 Contractor: Schindler Elevator Corporation Contract Start Date: August 2013 Contract Substantial Completion: May 2021 Projected Completion of Work: February 2024 (see the Schedule section below) Project Description: A contract to design, fabricate, install, test, commission, and maintain all elevators and escalators at all 21 stations.

Progress Schedule Status

Physical % Complete 45.3%

Just in Time** Early Plan* 56.5%

Late Plan* TBD *Data as of Feb. 28, 2020. **The E&E schedule is dependent on other contractors' schedules. Actual release for manufacturing will be coordinated for a 'just in time' delivery.

_______________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $0

DBE % Attained: 0%

Contract Changes in February

Change No. Description Amount ($)

Cumulative Previously Reported $4,867,726

00028 RFCR 00010 - LCC Train Day $12,000

Cumulative Current Report $4,879,726

_______________________________________________________________________________________________________

SCHEDULE:

The Elevators and Escalators (E&E) contract substantial completion date is May 2021, based on the AGS contract substantial completion date. The final completion date for the E&E contract will be based on the CCGS contract’s scheduled installation dates after award of the CCGS contract.

Original Contract: $50,982,714 Incurred-to-Date: $26,954,759

Current Contract Value1: $55,862,440 Incurred in February: $310,457

Outstanding Issues2: 2 Contractor CP Amount: $129,468 1Current Contract Value = Original contract value with Design Allowance + executed Change Orders 2 The methodology for calculating the Outstanding Issues amount and the corresponding Contractor CP Amount has been changed to only account for issues which have a Finding of Merit granted.

Page 29: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

29 | P a g e

WORK PROGRESS:

Activities this Month: Elevator CEI inspections are occurring at the Aloha

Stadium Station to ensure that the required specifications for the installation of the elevator and escalator supplier are met.

HART is continuing to coordinate with the AGS contractor and the E&E contractor to firm up required equipment installation dates. The ordering of the equipment has begun based on anticipated need dates.

At Pearlridge Station, Escalators #1 and #2 installation is complete. Elevators #1 and #2 installation is continuing with an estimated completion date in March 2020.

At Aloha Stadium, installation of Escalators #1 and #2 is continuing.

The State has begun Pre-inspections for all of the equipment installed at the West O‘ahu Station Group and the Farrington Highway Station Group so that when the Final inspections are called in, the acceptance should go smoothly.

The State has completed the inspection at Ho‘opili Station and Leeward Community College and has provided a punch list for each. These punch lists have been shared with the station contractors so that these items can be addressed and corrected prior to the States final inspection and acceptance.

Look Ahead: The E&E substantial completion date for the

remaining eight east-side stations will be established once the contract is awarded for the CCGS and the schedule for this contract is accepted.

At Aloha Stadium Station, installation of Elevator #1 is estimated to begin in early March 2020 upon arrival and Elevator #2 is estimated to begin in late March/early April 2020 upon arrival.

_______________________________________________________________________________________________________

KEY ISSUES:

Key Issues with Contractor Proposal Title CPC Code

EEC pre-operations maintenance delay

LCC Train Day

A A

LEGEND: A = less than $1 million; B = $1 million-$5 million; C = greater than $5 million; P = pending contractor submittal

_______________________________________________________________________________________________________

KEY MILESTONES:

Preventive maintenance requirements along with the required final testing is continuing for the elevators that have been installed. The only remaining elevators for which installation has not started is at Aloha Stadium Station (2 total), as the elevators are in transit from the mainland.

State Pre-inspections on all of the equipment installed at WOSG and FHSG began in November 2019 and is continuing. This will facilitate the State Final Inspections which are required to allow the public to use the installed equipment.

_______________________________________________________________________________________________________

QUALITY MANAGEMENT:

Elevators and Escalators NCR Log (Issued by Schindler)

Total NCRs Issued To Date Closed Open

0 0 0

Page 30: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

30 | P a g e

C. Fare Collection System CPP No.: MI-900 Contractor: INIT, Innovations in Transportation, Inc. Contract Start Date: April 2016 Projected Completion of Design-Build Work: December 2025

Project Description: The fare collection system is a joint HART and City and County of Honolulu [Department of Transportation Services (DTS), Department of Information Technology (DIT), Budget and Fiscal Services (BFS)] project that will consist of a multi-modal, closed loop, account based smart card system. The Fare System vendor, INIT Innovations in Transportation, Inc., is responsible for design, manufacture, testing, installation and operation of the entire system inclusive of hardware and software. The rail portion of the project will consist of Ticket Vending Machines (TVMs) and fare gates at stations that accept smart cards which can also be used for payment on board TheBus and facilitate a seamless transfer between modes. Equipment and software to be used by both HART and the City and County will include transaction processing, fare equipment monitoring, and customer service systems, as well as a Data Warehouse. TheBus equipment will consist of stand-alone smart card readers on board.

Progress Schedule Status

Percent Complete 46.6% 12 Months Behind Milestone Schedule

Payment** Early Plan* 82.9%

Late Plan* 76.1% *Data as of Feb. 28, 2020. Planned information is being evaluated based on the current (full-alignment) scope versus the revised requirements of the Interim Revenue Service completion date. **Although the contract is 12 months behind schedule, it does not impact the Interim Opening or the RSD.

_______________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $0

DBE % Attained: 0%

Contract Changes in February

Change No. Description Amount ($)

Cumulative Previously Reported $444,026

None N/A ---

Cumulative Current Report $444,026

_______________________________________________________________________________________________________

SCHEDULE: Bus and Back Office System Acceptance Milestone anticipated for March 31, 2020. This is delayed only for

documentation submission not system performance. Production Acceptance Test (PAT) scheduled for April 20-21 for the faregates and June 3 for the TVMs.

Original Contract: $15,464,198 Incurred-to-Date: $6,367,210

Current Contract Value1: $15,908,224 Incurred in February: $0

Outstanding Issues2: 0 Contractor CP Amount: $0 1Current Contract Value = Original contract value with Design Allowance + executed Change Orders 2 The methodology for calculating the Outstanding Issues amount and the corresponding Contractor CP Amount has been changed to only account for issues which have a Finding of Merit granted.

Page 31: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

31 | P a g e

WORK PROGRESS:

Activities this Month: Sent final draft of Operations Plan to DTS for comment. Sent draft Key Performance Indicator (KPI) reports to

DTS for comment. Reviewed Field Device Manuals and provided comments

to vendor. Sent to DTS for comments. Updated Sequencing schedule based on additional

manufacturing deliverables dates data. Installed retail app for card loading and adult card sales

at 8 TIMES supermarkets. Installed customer service terminals at Downtown

Satellite City Hall location. Issued youth cards at LCC High School event and senior,

youth and adult cards at LCC\train day. Assisted the City with reconciling Pilot deliverables in

order to pay Init invoices. Assisted City with comments on System Manager RFP. Provided comments and confirmed System Integration

Testing (SIT) test plan for TVMs and faregates. Completed draft business case for mobile payments.

Look Ahead:

Review PAT plans. Implement Pilot changes. Complete documentation for Bus and Back Office

System Acceptance. Finalize Operations Plan. Complete FOM for Fire Detection Alarm System

(FDAS) relay install and additional faregate installation work.

Install customer service terminals at remaining Satellite City Halls.

Start retail installations at test 7-Eleven stores and complete installation at the remaining 3 TIMES locations (Foodland will be rolled out with the DTS System Manager).

Complete Functional Unit Testing (FUT). Complete procurement for fiber connection to

City Network from a west side station.

_______________________________________________________________________________________________________________________________________

KEY ISSUES:

Key Issues with Contractor Proposal Title CPC Code

None N/A

LEGEND: A = less than $1 million; B = $1 million-$5 million; C = greater than $5 million; P = pending contractor submittal _______________________________________________________________________________________________________________________________________

KEY MILESTONES:

System Acceptance Bus and Back Office March 31, 2020.

Rail System Integration Testing April 2020. Production Acceptance Testing June 2020.

_______________________________________________________________________________________________________________________________________

QUALITY MANAGEMENT:

Fare Collection NCR Log (Issued by INIT)

Total NCRs Issued To Date Closed Open

0 0 0

Page 32: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

32 | P a g e

D. On-Call Construction IV CPP No.: MM-949 Contractor: Royal Contracting Co., Ltd. Contract Start Date: January 2018 Contract Substantial Completion: January 2023 Projected Completion of Work: January 2023 Project Description: This is an on-call contract to perform a variety of construction services by issuance of Task Orders. The construction services to be provided will include, but are not limited to, maintenance, renovations to existing privately owned properties, demolition of buildings/structures, repairs to existing HART facilities, temporary utilities installations, utilities relocation, new construction projects or services, maintenance of roadways inclusive of, filling potholes, removing dead animals, landscape maintenance, repairing/replacing signage, and other such activities to HDOT and/or City and County of Honolulu standards, work in support of HART’s ongoing construction activities, and work in support of other HART contractors.

Progress Schedule Status

Physical % Complete* 72.6%

On Time Early Plan* 100%

Late Plan* TBD *Data as of Feb. 28, 2020.

__________________________________________________________________________________________________________________________________________________________________________________________________________________________

COST INFORMATION:

DBE Participation Task Orders

Actual DBE Participation: $0

Number of Task Orders Issued

Amount ($)

DBE % Attained: 0% Task Orders Previously Issued 66 $45,388,043

Task Orders Issued this Month 1 $110,938

Amendments to Task Orders 5 ($95,476)

Total Task Orders Issued 67 $45,403,505

__________________________________________________________________________________________________________________________________________________________________________________________________________________________

SCHEDULE:

The On-Call Contract is a Task Order based Indefinite Delivery/Indefinite Quantity (IDIQ) contract. The work consists of meeting the objectivities of HART’s Joint Use and Occupancy Agreements (JUOA) requirements, maintaining HART properties, performing Cost to Cure activities, and performing permanent utility relocation work. Each Task Order has its own start and finish date, and as such, there is no overall schedule requirements for the On-Call contract proper. The contract NTP was issued on Jan. 8, 2018 and ends on Jan. 7, 2023 with two one-year options.

Original Contract: $46,000,000 Incurred-to-Date: $31,047,078

Current Contract Value1: $46,000,000 Incurred in February: $1,062,007

1Current Contract Value = Original contract value + executed Change Orders

Page 33: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

33 | P a g e

WORK PROGRESS: Activities this Month: Continued maintenance of the HDOT roadways along

Farrington Highway and Kamehameha Highway, per the JUOA.

Work on new sidewalk, new curb and gutter, and road widening at Cutter Dodge, Stuart Plaza and UH Urban Gardens is continuing. At approximately 95% complete.

Continued to complete HDOT elements of work as required by the HDOT agreements.

Continued to work on AGS HECO Zone’s 6A, 8A and 9. Continued work at Dillingham Plaza which is a cost to

cure activity. Work is at 97% complete. Continued work at LCC on the Ka‘aahi Substation and

storage area for HECO vehicles. Work is at 85% complete.

Work for HECO Zone 4 and HECO Zone 6A – ductbank 1638 was completed in February.

Look Ahead: Continue to maintain HDOT roadways, as required

by the JUOA. Continue work on new sidewalk, new curb and

gutter, and road widening at Cutter Dodge, Stuart Plaza and UH Urban Gardens.

Continue to complete HDOT elements of work as required by the HDOT agreements.

Continue to work on Cost to Cure property’s located on Dillingham Boulevard.

The Cost to Cure work at Dillingham Plaza will be completed in March.

The planned completion for HECO Zone 6A duct bank 1639 is scheduled for March 2020.

_______________________________________________________________________________________________________________________________________

KEY ISSUES (new issues are in bold font): Need to receive timely Right of Entry agreements.

Need to continue to have Maintenance of Traffic plans reviewed and accepted in a reasonable time frame. _______________________________________________________________________________________________________________________________________

KEY MILESTONES: The completion of the work at UH Urban Gardens – Cutter Dodge will provide the required road widening at this

section of Kamehameha Highway; March 2020 completion date. The completion of this work was severely hampered by over 2 weeks of continuous rain in the first half of January and also in February.

_______________________________________________________________________________________________________________________________________

QUALITY MANAGEMENT:

On-Call Construction IV NCR Log (Issued by Royal Contracting)

Total NCRs Issued To Date Closed Open

0 0 0

Page 34: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

34 | P a g e

4.2 Section I – West O'ahu/Farrington Highway: East Kapolei to Pearl Highlands

A. West O'ahu/Farrington Highway Guideway (WOFH) CPP No.: DB-120 DB Contractor: Kiewit Infrastructure West Company (KIWC) Contract Start Date: December 2009 Date of Substantial Completion Notification: December 13, 2018

Project Description: Design and construction of 6.8 miles of rail alignment, starting at the East Kapolei Station and ending at the Pearl Highlands Station.

Progress Schedule Status

Physical % Complete 100% Substantial Completion Obtained**

Early Plan* 100%

Late Plan* 100% *Data as of Feb. 28, 2020. **Further explanation is provided in the Schedule section.

_______________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $17,119,976

DBE % Attained: 2.57%

Contract Changes in February

Change No. Description Amount ($)

Cumulative Previously Reported $185,351,685

None N/A ---

Cumulative Current Report $185,351,685

_______________________________________________________________________________________________________

SCHEDULE:

Complete Acoustical Monitoring installation – March 2020. Contract closeout – May 2020.

_______________________________________________________________________________________________________

WORK PROGRESS: Activities this Month: Acoustical Monitoring installation continues.

Look Ahead: Complete Installation and Commissioning of the

Acoustical Monitoring System. Respond to Request for Final Acceptance letter.

Original Contract: $482,430,201 Incurred-to-Date: $667,781,906

Current Contract Value1: $667,781,886 Incurred in February: $0

1Current Contract Value = Original contract value + executed Change Orders

Page 35: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

35 | P a g e

KEY ISSUES:

Key Issues with Contractor Proposal Title CPC Code

None N/A

LEGEND: A = less than $1 million; B = $1 million-$5 million; C = greater than $5 million; P = pending contractor submittal _______________________________________________________________________________________________________

KEY MILESTONES:

One-year project warranty period commenced on Jan. 14, 2019, per Contract Change Order (CCO) No. 00170. One-year project warranty period ended on Jan. 14, 2020.

_______________________________________________________________________________________________________

SUBSTANTIAL COMPLETION:

Substantial Completion is Dec. 13, 2018. _______________________________________________________________________________________________________

QUALITY MANAGEMENT:

WOFH NCR LOG (Issued by KIWC)

Total NCRs Issued to Date Closed Open

586 586 0

Page 36: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

36 | P a g e

B. University of Hawai‘i West O‘ahu (UHWO) Station Temporary Park-and-Ride & UHWO Campus Road “B” CPP No.: DBB-602 Contractor: Nan, Inc. Contract Start Date: December 2017 Contract Substantial Completion: July 2019 Completion of Work: January 2020 Project Description: The project consists of the construction of a temporary park & ride, Road “B” and associated site work in the vicinity of UH West O‘ahu Station. The project includes clearing, grubbing, erosion and dust control, grading and hauling, drainage, installation of underground and overhead utilities, installation of traffic signal, street lighting, and park & ride area electrical and communication systems, concrete curbs, sidewalks and wheelchair ramps, asphalt and concrete pavement structures, signing and striping, bus shelters, landscaping including installation of an irrigation system, and other appurtenances associated with roadway and park & ride facilities.

Progress Schedule Status

Physical % Complete 100% Work

Completed** Early Plan* 100%

Late Plan* 100% *Data as of Feb. 28, 2020. NTP issued Dec. 15, 2017. **Pending contract actions will extend contract completion date.

_______________________________________________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $108,454

DBE % Attained: 0.86%

Contract Changes in February

Change No. Description Amount ($)

Cumulative Previously Reported $1,611,930

None N/A ---

Cumulative Current Report $1,611,930

_______________________________________________________________________________________________________________________________________

SCHEDULE:

Substantial completion date is Oct. 23, 2019, per a substantial completion letter dated Dec. 13, 2019. Change Order (CO) for Communication Interface Cabinet (CIC) cabinet work is complete. Construction work on

the DBB-602 contract was completed in January 2020. Change Order pending to extend contract completion date.

Original Contract: $11,589,300 Incurred-to-Date: $12,193,721

Current Contract Value1: $13,201,230 Incurred in February: $1,096,437

Outstanding Issues2: 2 Contractor CP Amount: -$29,780

1Current Contract Value = Original contract value + executed Change Orders 2 The methodology for calculating the Outstanding Issues amount and the corresponding Contractor CP Amount has been changed to only account for issues which have a Finding of Merit granted.

Page 37: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

37 | P a g e

WORK PROGRESS: Activities this Month: Worked on punchlist items.

Look Ahead: Complete punchlist items. Coordinate Board of Water Supply (BWS) meter

installation. Complete electrical testing.

_______________________________________________________________________________________________________________________________________

KEY ISSUES:

Key Issues with Contractor Proposal Title CPC Code

Survey Modeling Costs - RFI No. 00045 - Contour Grades and Driveway Profiles

Delete Traffic Signal Work at Road B (D. R. Horton to Complete)

A A

LEGEND: A = less than $1 million; B = $1 million-$5 million; C = greater than $5 million; P = pending contractor submittal _______________________________________________________________________________________________________________________________________

KEY MILESTONES:

Complete punchlist work – March 2020. _______________________________________________________________________________________________________________________________________

QUALITY MANAGEMENT:

UHWO Station Temporary Park-and-Ride & UHWO Campus Road “B” NCR Log

(Issued by Nan)

Total NCRs Issued to Date Closed Open

4 0 4

Page 38: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

38 | P a g e

C. West O'ahu Station Group (WOSG) CPP No.: DBB-171 Contractor: Nan, Inc. Contract Start Date: October 2015 Contract Substantial Completion: January 31, 2020 Date of Substantial Completion: January 31, 2020

Project Description: The West O'ahu Station Group construction contract includes services to build three (3) transit stations along Kualaka'i Parkway and Farrington Highway. The stations are East Kapolei (EKP), UH West O'ahu (UHWO), and Ho'opili (HOP) Stations. In addition to the transit stations, operational ancillary buildings, a traction power substation, and adjacent areas are included in this project.

Progress Schedule Status

Physical % Complete 98.0%** Substantial Completion

Obtained Early Plan* 100%

Late Plan* 100% *Data as of Feb. 28, 2020. **Remaining work includes punchlist, contract change orders and closeout.

__________________________________________________________________________________________________________________________________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $858,189

DBE % Attained: 1.38%

Contract Changes in February

Change No. Description Amount ($)

Cumulative Previously Reported $31,810,294

None N/A --- ---

Cumulative Current Report $31,810,294

Original Contract: $56,088,470 Incurred-to-Date: $81,216,892

Current Contract Value1: $87,898,764 Incurred in February: $1,295,544

Outstanding Issues2: 2 Contractor CP Amount: $217,534 1Current Contract Value = Original contract value + executed Change Orders 2 The methodology for calculating the Outstanding Issues amount and the corresponding Contractor CP Amount has been changed to only account for issues which have a Finding of Merit granted.

Page 39: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

39 | P a g e

SCHEDULE:

Coordinating with CSC and the contractor to meet HRH’s schedule for access turnover for functional testing and interim service milestones.

Change order work, base contract work impacted by pending change orders, and pending change order work to be completed.

WORK PROGRESS: Activities this Month: East Kapolei

Installing balustrades at concourse level. Utility room painting. Water and sewer work. Site utility and grading work. Faregate area tiling. Site sidewalk and driveway installation. Site fencing installation. Escalator cladding installation. Canopy drain installation.

UH West O‘ahu

Heating, Ventilation and Air Conditioning (HVAC) Testing and Balance.

Painting of stations. Rough-in for the service and light posts is ongoing.

Faregate wall installation, including tile work, continues. Electrical rough-in for platform service and light posts. Landscaping and irrigation. HECO energized the station. Completion of site work around the west entrance

building. Tensile fabric installation completed. Drainage swale and channel riprap installation. Fencing installation. Elevator #3 and #5 hoistway work. Concrete staining/floor tiles. Canopy drain installation.

Ho‘opili

Site work utilities and sidewalk construction. Painting of balustrade at stairs, landing and platforms. Landscaping and access road.

Look Ahead: East Kapolei Complete site utility work. Complete site work and landscaping. Signage installation. Concrete staining/floor tiles.

UH West O‘ahu Landscaping. Concrete staining. Signage installation. Traffic signal installation. Canopy drain installation.

Ho‘opili Paint balustrade at stairs, landings and

platforms. Plumbing fixture testing. Site work and utilities installation. Signage installation. Landscape installation. Concrete staining/floor tiles.

KEY ISSUES:

Key Issues with Contractor Proposal Title CPC Code

16” Non-Potable Water connection

24” Sewer

A A

LEGEND: A = less than $1 million; B = $1 million-$5 million; C = greater than $5 million; P = pending contractor submittal

Page 40: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

40 | P a g e

KEY MILESTONES: UHWO Station:

HECO energization.

QUALITY MANAGEMENT: Conducted bi-weekly Quality Task Force Meetings.

WOSG NCR Log (Issued by Nan)

NCRs Issued to Date

Closed Open

East Kapolei 10 9 1

UH West O‘ahu 34 31 3

Ho‘opili 27 23 4

Contract Wide 9 9 0

TOTAL 80 72 8

Page 41: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

41 | P a g e

D. Farrington Highway Station Group (FHSG) CPP No.: DBB-271 Contractor: Hawaiian Dredging Construction Company, Inc. (HDCC) Contract Start Date: August 2015 Contract Substantial Completion: January 2019 Projected Completion of Work: June 2020

Project Description: The Farrington Highway Station Group construction contract includes services to build three (3) transit stations along Farrington Highway. The stations are West Loch (WLO), Waipahu Transit Center (WTC), and Leeward Community College (LCC) Stations. The station work includes operational ancillary buildings, a traction power substation at WLO, and a Kiss-and-Ride lot at WLO.

Progress Schedule Status

Physical % Complete 95.7% 17 months behind**

Early Plan* 100%

Late Plan* 100% *Data as of Feb. 28, 2020. **Further explanation is provided in the Schedule section.

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $4,246,684

DBE % Attained: 5.15%

Contract Changes in February

Change No. Description Amount ($)

Cumulative Previously Reported $18,487,980

None N/A ---

Cumulative Current Report $18,487,980

Original Contract: $78,999,000 Incurred-to-Date: $89,256,357

Current Contract Value1: $97,486,980 Incurred in February: $1,180,323

Outstanding Issues2: 13 Contractor CP Amount: $294,896

1Current Contract Value = Original contract value + executed Change Orders 2 The methodology for calculating the Outstanding Issues amount and the corresponding Contractor CP Amount has been changed to only account for issues which have a Finding of Merit granted.

Page 42: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

42 | P a g e

SCHEDULE:

LCC canopy fabric was fully deployed and iterative tensioning is ongoing. HDCC installed bipod struts at WTC. WLO bipod installation is scheduled for the week of March 9. Canopy fabric installation to be completed in April 2020; delay due to contractor delay in fabrication of the

bipod struts. Faregate canopy is scheduled for April/May 2020, due to contractor delay/late fabrication. ________________________________________________________________________________________________________________________________________________________________________________________________________________________

WORK PROGRESS: Activities this Month:

West Loch ● Weld access plates on canopy. ● Pull power cable to canopies. ● Install Communication Interface Cabinet (CIC) risers on platform

level. Leeward Community College ● Tension canopy fabric. ● Complete punch list items. Waipahu Transit Center ● Repaired and installed Frame 5. ● Installed CIC risers and comm conduit on platform level. ● Installed bipod struts. All Stations ● Coordinating canopy fabric installation, NCRs, change orders,

and other closeout items. Signage fabrication.

Look Ahead: West Loch

● Kiss n Ride pavement striping. ● Faregate canopy bipods and fabric. ● Faregate canopy fabrication.

Leeward Community College ● Complete clamping and flashing

installation canopy. Waipahu Transit Center

● Moloalo sidewalk redesign. ● Deploy and tension fabric. ● Fare gate canopy.

All Stations Punch list walk.

________________________________________________________________________________________________________________________________________________________________________________________________________________________

KEY ISSUES:

Key Issues with Contractor Proposal Title CPC Code ● CC VRF De-Scoping (Credit) ● CC Signage Changes (includes Issue ASI 22) ● Various Electrical Changes ● CC Canopy Bale Ring Changes SUB 736 RFI 1238 and 755 ● CC De-Scope Cold Water Insulation (Credit) ● EL201 Changes - RFI 451 ● C3 Sign Types B3 & C2 Mounting Detail at Stairs 1 & 2 CPC 152 ● RFI 00491 WTC Street Lighting (Credit) ● CC Sign Type C1.b Bottom Unit RFI 1403 (Credit) ● Signage Wall Mount Sealant RFI 1499 ● Sign Type B4 Mount Detail RFI 1179, 1500 ● Sign Type C1a C2 Maps ● Sign Type D Ceiling Mounting

A A A A A A A A A A A A A

LEGEND: A = less than $1 million; B = $1 million-$5 million; C = greater than $5 million; P = pending contractor submittal ________________________________________________________________________________________________________________________________________________________________________________________________________________________

KEY MILESTONES:

Platform canopy installation is scheduled to be completed April 2020. Faregate canopies are scheduled to be complete by May 2020.

Page 43: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

43 | P a g e

QUALITY MANAGEMENT:

The CEI team is working with HDCC to ensure required submittals are approved prior to related construction activities.

FHSG NCR Log (Issued by HDCC)

NCRs Issued to Date

Closed Open

West Loch 33 31 2

Waipahu Transit Center 22 14 8

West Loch/Waipahu Transit Center 3 2 1

Leeward Community College 20 15 5

Contract Wide 19 17 2

Void 2 2 0

TOTAL 99 81 18

Page 44: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

44 | P a g e

E. Maintenance and Storage Facility (MSF) CPP No.: DB-200 Contractor: Kiewit/Kobayashi Joint Venture (KKJV) Contract Start Date: July 25, 2011 Contract Substantial Completion Date: July 2, 2016

Project Description: The MSF contract consists of the Operations and Servicing Building (OSB), Maintenance of Way (MOW), Train Wash Facility (TWF) and Wheel Truing Building (WTB). In addition to the four (4) facility buildings, MSF includes rail procurement, special trackwork, ties, third rail and other track material for the four guideway segments on the project.

Progress Schedule Status

Physical % Complete 100% Substantial Completion Obtained*

Early Plan 100%

Late Plan 100% *Further explanation is provided in the Schedule section.

_______________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $710,987

DBE % Attained: 0.25%

Contract Changes in February

Change No. Description Amount ($)

Cumulative Previously Reported $86,517,032

None N/A ---

Cumulative Current Report $86,517,032

______________________________________________________________________________________________________________________________________________________

SCHEDULE:

HART to close remaining issues first quarter 2020. ______________________________________________________________________________________________________________________________________________________

WORK PROGRESS:

Activities this Month: Final acceptance letter routing for signature.

Look Ahead: Final retention release. Final Acceptance Letter from HART. Process final payment.

MSF Construction Status 100% Complete Overall

Element % Complete*

OSB 100%

MOW Building 100%

WTB 100%

TWF 100%

Rail 100%

Paving 100% *Not including testing and commissioning.

Original Contract: $195,258,000 Incurred-to-Date: $281,775,032

Current Contract Value1: $281,775,032 Incurred in February: $0

1Current Contract Value = Original contract value + executed Change Orders

Page 45: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

45 | P a g e

KEY ISSUES:

Key Issues with Contractor Proposal Title CPC Code

None N/A

LEGEND: A = less than $1 million; B = $1 million-$5 million; C = greater than $5 million; P = pending contractor submittal _______________________________________________________________________________________________________

KEY MILESTONES:

None. _______________________________________________________________________________________________________

QUALITY MANAGEMENT: Overall quality of the contract is good.

MSF NCR Log (Issued by KKJV)

Total NCRs Issued to Date Closed Open

37 37 0

Page 46: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

46 | P a g e

4.3 Section II – Kamehameha Highway: Pearl Highlands to Aloha Stadium A. Kamehameha Highway Guideway (KHG)

CPP No.: DB-320 Contractor: Kiewit Infrastructure West Company (KIWC) Contract Start Date: June 2011 Date of Substantial Completion Notification: December 13, 2018

Project Description: Kamehameha Highway Guideway DB Contract (KHG) consists of 3.9 miles and starts 400 feet east of the Pearl Highlands Station and terminates 1,400 feet beyond the Aloha Stadium Station. KHG work scope is made up of utility relocations, traffic signal improvements, highway widening, drilled shaft foundations, columns, and aerial structure.

Progress Schedule Status

Physical % Complete 100% Substantial Completion Obtained**

Early Plan* 100%

Late Plan* 100% *Data as of Feb. 28, 2020. **Further explanation is provided in the Schedule section.

_______________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $860,191

DBE % Attained: 0.22%

Contract Changes in February

Change No. Description Amount ($)

Cumulative Previously Reported $31,405,774

None N/A ---

Cumulative Current Report $31,405,774

SCHEDULE: Close contract, pending signed Release and Certificate of Final Payment from KIWC.

_______________________________________________________________________________________________________

WORK PROGRESS: Activities this Month: None.

Look Ahead: Receive the contractor’s signed Release and

Certificate of Final Payment. Payment of final retention release.

Original Contract: $372,150,000 Incurred-to-Date: $403,589,030

Current Contract Value1: $403,555,774 Incurred in February: $0

1Current Contract Value = Original contract value + executed Change Orders

Page 47: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

47 | P a g e

KEY ISSUES:

Key Issues with Contractor Proposal Title CPC Code

None N/A

LEGEND: A = less than $1 million; B = $1 million-$5 million; C = greater than $5 million; P = pending contractor submittal _______________________________________________________________________________________________________

KEY MILESTONES:

One-year project warranty period commenced on Jan. 14, 2019, in accordance with CCO No. 00076. One-year project warranty ended on Jan. 14, 2020.

_______________________________________________________________________________________________________

SUBSTANTIAL COMPLETION:

Substantial Completion was Dec. 13, 2018. _______________________________________________________________________________________________________

QUALITY MANAGEMENT:

KHG NCR Log (Issued by KIWC)

Total NCRs Issued to Date Closed Open

252 252 0

Page 48: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

48 | P a g e

B. Kamehameha Highway Station Group (KHSG) CPP No.: DBB-371 Contractor: Nan, Inc. Contract Start Date:

Notice to Commence Administrative Work: April 2016 Notice to Commence Investigative/Pre-Construction Work at Pearl Highlands: July 2016 Full Notice to Proceed (NTP): October 3, 2016

Contract Substantial Completion: April 2020 Projected Completion of Work: May 2020

Project Description: The Kamehameha Highway Station Group construction contract includes services to build three (3) transit stations along Kamehameha Highway. The stations are Pearl Highlands Station (PHL), Pearlridge Station (PLR), and Aloha Stadium Station (ALS). Operational ancillary buildings, pedestrian crossing improvements, Train Control and Communications Rooms (TCCRs), and landscaping of the station sites are included in addition to the transit stations. The Pearl Highlands Station will include a transit center. The Pearl Highlands and Aloha Stadium Stations include both a Park-and-Ride lot and a Kiss-and-Ride lot.

Progress Schedule Status

Physical % Complete 90.7%

1 month behind** Early Plan* TBD

Late Plan* TBD *Data as of Feb. 28, 2020. Planned values will be updated once a revised baseline schedule reflecting April 30, 2020 is incorporated. **Further explanation is provided in the Schedule section.

_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $0

DBE % Attained: 0%

Contract Changes in February

Change No. Description Amount ($)

Cumulative Previously Reported $15,219,828

None N/A ---

Cumulative Current Report $15,219,828

Original Contract: $115,805,845 Incurred-to-Date: $112,558,850

Current Contract Value1: $131,025,673 Incurred in February: $5,456,894

Outstanding Issues2: 1 Contractor CP Amount: $112,717

1Current Contract Value = Original contract value with Design Allowance + executed Change Orders 2 The methodology for calculating the Outstanding Issues amount and the corresponding Contractor CP Amount has been changed to only account for issues which have a Finding of Merit granted.

Page 49: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

49 | P a g e

SCHEDULE:

Ongoing coordination with CSC and the contractor to meet HRH’s schedule for access turnover and interim opening.

Schedule delayed by canopy and fabric delivery. Working with the station and systems contractors to mitigate any impact on interim opening resulting from canopy design revisions in progress.

CCO 44 revised the contract substantial completion date to April 30, 2020. ________________________________________________________________________________________________________________________________________________________________________________________________________________________

WORK PROGRESS: Activities this Month: Pearl Highlands

Continued rock slope protection installation near Waiawa Stream.

Commenced Elevator 1 thermoplastic polyolefin (TPO) roofing installation.

Continued painting of all steel. Continued Articulated Concrete Block installation. Commenced elevator door and window jamb

installation. Completed elevator glazing installation. Completed stair and escalator lighting installation. Continued forming/reinforcement for beams and

slabs for entrance ramp and utility corridor. Commenced cutting of box beam girder and patch

guideway clearance. Commenced and completed FM200 testing.

Pearlridge Continued painting all steel. Continued installation of under roof canopy

lighting. Continued fiberglass conduit installation. Completed platform to concourse conduit

installation. Continued sidewalk and streetlight work. Completed canopy assembly and erection. Completed bus pad reconstruction work. Commenced and completed FM200 testing. Commenced escalator cladding installation.

Aloha Stadium Continuing driveway B rigid paving concrete pours. Continuing subgrade preparation for driveway B. Completed installation of metal roofing. Continuing ceramic tile installation. Completed sewer line installation across Salt Lake

Boulevard into Aloha Stadium property. Commenced Architectural fence installation. Commenced and completed FM 200 testing. Commenced lighting installation. Commenced visual screen support and balustrade

installation.

Look Ahead: Pearl Highlands

Commence Variable Message Sign (VMS) support installation.

Complete Elevator 1 TPO roofing installation. Commence Elevator 2 TPO roofing installation. Complete forming/reinforcement and concrete pour

for beams and slabs for entrance ramp and utility corridor.

Complete rock slope protection installation near Waiawa Stream.

Complete installing elevator door and window jamb. Complete cutting of box beam girder and patch

guideway clearance. Commence escalator cladding installation.

Pearlridge Commence chain-link fence installation. Complete sidewalk and streetlight work. Commence mauka sewer line work and grinder pump

installation. Commence elevator glazing installation. Complete lighting installation. Commence elevator TPO roofing installation. Commence installation of frame and enclosure for

Roll up door and Emergency Management Panel (EMP).

Aloha Stadium Complete driveway B ridged paving concrete pours. Commence highway sign footing installation. Commence elevator shaft roof and deck installation. Complete ceramic tile installation. Complete visual screen support and balustrade

installation. Commence installation of frame and enclosure for

Roll up door and EMP.

Page 50: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

50 | P a g e

KEY ISSUES:

Key Issues with Contractor Proposal Title CPC Code

PLR Mauka Sewerline A

LEGEND: A = less than $1 million; B = $1 million-$5 million; C = greater than $5 million; P = pending contractor submittal

________________________________________________________________________________________________________________________________________________________________________________________________________________________

KEY MILESTONES:

Pearlridge Station TCCR and UPS Building – Pathway to guideway conduit installation is complete. TCCR and UPS rooms are now being shared with the Core Systems Contractor.

Aloha Stadium Station TCCR and UPS Rooms – Pathway to guideway conduits complete. TCCR and UPS rooms are now being shared with the Core Systems Contractor.

Current canopy delivery schedule: PHL – Delivered December 2019, PLR – Delivered January 2020, ALS – April 2020. Working with the contractor to improve the schedule.

Energization of Pearl Highlands and Pearlridge – February 2020. ________________________________________________________________________________________________________________________________________________________________________________________________________________________

QUALITY MANAGEMENT:

KHSG NCR Log (Issued by Nan)

NCRs Issued to Date

Closed Open

Pearl Highlands 26 22 4

Pearlridge 24 24 0

Aloha Stadium 3 2 1

Contract Wide 0 0 0

TOTAL 53 48 5

Page 51: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

51 | P a g e

C. Kamehameha Highway Resurfacing (KHR) CPP No.: DBB-701 Contractor: Road and Highway Builders, LLC (RHB) Contract Start Date: Notice to Proceed NTP #1: August 2018 Contract Substantial Completion: September 2019 Projected Completion of Work: March 2020

Project Description: The project consists of pavement resurfacing and other roadway reconstruction associated with completion of the Kamehameha Highway Guideway contract. Construction includes, but is not limited to, clearing, grubbing, erosion and dust control, grading and hauling, maintenance of traffic, pavement resurfacing, and installation of pavement markings and striping, roadway signs, curb ramps, drainage, waterlines, gas lines, traffic signal loop detectors, retaining wall, guard railing, fencing and bus shelters.

Progress Schedule Status

Physical % Complete 92.1% 6 months

behind Early Plan* 100%

Late Plan* 100% *Data as of Feb. 28, 2020.

__________________________________________________________________________________________________________________________________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $1,732,870

DBE % Attained: 6.67%

Contract Changes in February

Change No. Description Amount ($)

Cumulative Previously Reported $2,145,340

None N/A ---

Cumulative Current Report $2,145,340

__________________________________________________________________________________________________________________________________________________________________________________________________________________________

SCHEDULE: The contract completion date will be extended due to delays in road widening at Kaahumanu Street and

Construction Right-of-Entry (CROE) for construction of retaining wall #9. A time extension is pending. Completion of currently contracted work is March 2020. Developing additional change orders that will extend the completion date to October 2020.

_______________________________________________________________________________________________________________________________________

WORK PROGRESS: Activities this Month: Held various meetings, such as pre-activity,

progress, environmental, traffic quality, safety, and public interface meetings.

Completed concrete flatwork and utility work at Kaonohi Street widening.

Continued permanent striping work and lowering manholes between Kuleana Road to Aloha Stadium.

Completed median work and asphalt treated base (ATB) work between Kanuku and Kaonohi Street.

Look Ahead: Complete pedestrian island concrete work, traffic

signal work and streetlight work at Kaonohi intersection.

Grout abandoned utilities. Complete permanent striping work and lowering

manholes between Kuleana Road and Aloha Stadium. Complete installation of traffic loops between Kuleana

Road and Aloha Stadium.

Original Contract: $25,989,989 Incurred-to-Date: $26,265,076

Current Contract Value1: $28,135,329 Incurred in February: $2,268,757

Outstanding Issues2: 1 Contractor CP Amount: $285,562

1Current Contract Value = Original contract value + executed Change Orders 2 The methodology for calculating the Outstanding Issues amount and the corresponding Contractor CP Amount has been changed to only account for issues which have a Finding of Merit granted.

Page 52: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

52 | P a g e

Activities this Month (continued): Began and completed fence installation and

landscaping work in median. Began and completed mill and overlay work at

Kaonohi intersection. Began pedestrian island concrete work, traffic

signal work and streetlight work at Kaonohi intersection.

Began installing traffic loops between Kuleana Road and Aloha Stadium.

Continue streetlight work near Pearlridge Station. Completed retaining wall 9 construction at Kaonohi

Street.

Look Ahead (continued): Preparing Finding of Merit for RFCR 00011 KHR

Miscellaneous Changes (CROE, Bus Shelter, EVC Loops & others).

Preparing Finding of Merit for RFCR 00012 Left Turn into Kuala Street.

Preparing Finding of Merit for RFCR 00013 Pearl City Stream Median Guardrail.

_______________________________________________________________________________________________________________________________________

KEY ISSUES:

Key Issues with Contractor Proposal Title CPC Code

Gas Line Work A

LEGEND: A = less than $1 million; B = $1 million-$5 million; C = greater than $5 million; P = pending contractor submittal _______________________________________________________________________________________________________________________________________

KEY MILESTONES:

Completed mill and overlay paving from Kaonohi Street to ALS. _______________________________________________________________________________________________________________________________________

QUALITY MANAGEMENT:

KHR continues to follow established quality processes through quality monitoring and audits.

KHR NCR Log (Issued by Road and Highway Builders)

Total NCRs Issued to Date Closed Open

0 0 0

Page 53: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

53 | P a g e

D. Design Services for 138kV Utilities Relocation at KHG

CPP No.: FD-700 Contractor: R.M. Towill Corporation (RMTC) Contract Start Date: September 2018 Contract Substantial Completion: November 2021 Project Description: Architectural and Engineering Services for the final design to relocate the existing 138kV overhead electrical lines to underground lines at Kamehameha Highway Guideway and Stations.

Progress Schedule Status

Based on Expenditures* 45.2%

TBD Early Plan* 50.6%

Late Plan* 37.8% *Data as of Feb. 28, 2020.

_______________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $0

DBE % Attained: 0%

Contract Changes in February

Change No. Description Amount ($)

Cumulative Previously Reported $0

None N/A ---

Cumulative Current Report $0

_____________________________________________________________________________________________________

SCHEDULE:

An updated preliminary design submittal (to HECO), incorporating additional HECO review comments on the previous updated preliminary design submittal, was made on Feb. 21, 2020. These updated preliminary design drawings are currently being used by HECO for sway calculations.

_______________________________________________________________________________________________________

WORK PROGRESS: Activities this Month: The design consultant continues traffic counts for preliminary

Maintenance of Traffic (MOT) plans. The design consultant is performing additional topographic

survey work, and is tentatively scheduled to complete it by mid-March 2020.

The design consultant continues discussions with a local contractor for constructability purposes.

A site walk-through was performed on Feb. 27, 2020 (HART, HECO, a local contractor, and design consultants) to compliment design work (sway calculations, pole design, and traffic control plans).

Look Ahead: Continue periodic HECO meetings. Continue refining preliminary design work. Continue to meet with third party agencies

to discuss their comments/concerns on the preliminary submittal.

Complete additional surveying work required due to modifications to the alignment.

Continue traffic count. Perform geotechnical investigation for the

purpose of HECO’s pole foundation design.

Original Contract: $8,766,327 Incurred-to-Date: $3,821,186

Current Contract Value1: $8,766,327 Incurred in February: $152,863 1Current Contract Value = Original contract value with Design Allowance + executed Change Orders

Page 54: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

54 | P a g e

Activities this Month (continued): On Feb. 27, 2020, HECO requested geotechnical engineering

investigations and testing for the purpose of pole foundation analysis and design. The design consultant will provide these requested services.

We are waiting for additional comments on the schedule from HECO, but we will continue to follow our schedule. HART is in the process of updating its internal schedule to reflect current developments with land acquisition and permitting.

HECO preliminary sway calculations are currently anticipated by mid-March 2020, and finalized results are anticipated by mid-April 2020.

The preliminary design has been submitted to affected third party agencies, and the design consultant continues to schedule meetings with each agency to discuss third party agency comments.

Look Ahead (continued): Complete constructability discussions with a

local contractor.

_______________________________________________________________________________________________________

KEY ISSUES (new issues are in bold font):

The design consultant needs to continue to coordinate with third party agencies to determine if the alignment needs to be modified.

_______________________________________________________________________________________________________

KEY MILESTONES:

Based on schedule information we currently have, key upcoming milestones are as follows: o Prefinal Design: Oct. 14, 2020. o Final Design: April 21, 2021.

Page 55: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

55 | P a g e

4.4 Section III – Airport: Aloha Stadium to Middle Street Transit Center Station A. Airport Section Guideway and Stations (AGS)

CPP No.: DB-450 Contractor: Shimmick/Traylor/Granite, JV (STG) Contract Start Date: December 2016

Contract Substantial Completion: May 2021

Projected Completion of Work: October 2021

Project Description: The Airport Guideway and Stations Design-Build contract consists of the design and construction of 5.2 miles of elevated guideway, four (4) stations, and associated facilities between Aloha Stadium and the Middle Street Transit Center. The contractor will begin by interfacing with design disciplines, third-party stakeholders, and construction contracts within the corridor of the project to coordinate and resolve utilities conflicts. Design field verification efforts (potholing and geotechnical exploration) will be followed by construction activities once design packages have been approved.

Progress Schedule Status

Physical % Complete* 60.6%

5 months behind** Early Plan* 85.4%

Late Plan 70.4% *Data as of Feb. 28, 2020. **Further explanation is provided in the Schedule section.

________________________________________________________________________________________________________________________________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $41,938,167

DBE % Attained: 4.83%

Contract Changes in February

Change No. Description Amount ($)

Cumulative Previously Reported $11,054,752

None N/A ---

Cumulative Current Report $11,054,752

Original Contract: $874,750,000 Incurred-to-Date: $517,780,890

Current Contract Value1: $885,804,752 Incurred in February: $02

Outstanding Issues3: 3 Contractor CP Amount: $3,577,140 1Current Contract Value = Original contract value + executed Change Orders 2 Work has progressed and incurred amounts will be reflected as invoices are approved in the City’s C2HERPS system. 3 The methodology for calculating the Outstanding Issues amount and the corresponding Contractor CP Amount has been changed to only account for issues which have a Finding of Merit granted.

Page 56: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

56 | P a g e

SCHEDULE:

A series of schedule workshops were held in order to come to an agreed upon Oct. 31, 2021 completion date. Additional workshops are continuing to further define station activities.

________________________________________________________________________________________________________________________________________________________________________________________________________________________

WORK PROGRESS: AGS Construction Status as of 02/28/2020

Guideway Structure Element

Total to Date

Total Qty % Complete

Shafts 170 225 75.6%

Columns 157 232 67.7%

Segment Casting 2,473 2,708 91.3%

Spans Stressed 82 211 38.9%

Spans Grouted 76 211 36.0%

Trackwork 0 * 0.0%

Third Rail 0 * 0.0%

Mill & Overlay 0 * 0.0% * Amounts to be determined.

Activities this Month: Guideway, Rail and Utility Work Gantry 1 crane continued; erected/stressed 2 spans

at 482 and 483. Gantry 2 crane continued; erected/stressed 3 spans at 523 through 525.

Utilities – HECO Zone 4 was completed; Zones 6A and 8 continued. System Site (SS) #25 and SS#27 are ongoing.

Rail welding continued at LCC staging area. Reach A: Traffic Signal (TS) continued on

Kamehameha Highway at Kalaloa and Halawa Drive. Median restoration commenced from Piers 423-426.

Reach C: HDOT-A comm, Street Light (SL), fuel and wet utility relocations continued. Completed road widening from Piers 558-569 for Maintenance of Traffic (MOT) switch and drilling of shaft foundations.

Reach D: Infrastructure for Hawaiian Telcom (HTI)/Oceanic Time Warner Cable (OTWC) comm.

Continued assembly of Gantry 3 in Ke‘ehi Lagoon Park.

Pearl Harbor Naval Base (PHNB) Station Underground mechanical and plumbing at Station

Entrance. Completed “Makai Landing” elevator slab and HECO transformer pads.

Honolulu International Airport (HIA) Station Grade beam and elevator foundations continued.

Hammerhead construction for Piers 541 and 543. Lagoon Drive (LD) Station TCCR underground utilities and grade beam and stem

wall at Mauka Entrance continued. Continued structural steel erection for Mauka Entrance.

Middle Street Transit Center (MSTC) Station Drilled 2/5 shafts for TCCR and completed micropiles

for station entrance.

Look Ahead: Guideway, Rail and Utility Work Design Submittals Approved:

o Reach A, B and E – Civil and Composite Utilities Issued for Construction (IFC)

o Civil Common Drawings and Intelligent Transportation Systems (ITS) IFC

o MSTC Station IFC Form/rebar/pour Reaches C and E columns and

segment casting. Continue pouring C-Bents and Straddle Bents, and

columns in Reach B, Reach C and Reach E. Begin hauling and installation of rail work. Complete electrical relocation work in HECO Zones

6A, 8 and 9. Coordination taking place with third-parties. Continue drilled shaft construction in Reaches C and

E. Continue assembly of Gantry 3 in Ke‘ehi Lagoon Park.

PHNB Station Complete underground mechanical and electrical at

station entrance and TCCR. Begin platform girder forming erection. Structural steel delivery.

HIA Station Install grounding grid for entrance and Ancillary

Building and place structure backfill. LD Station Complete Mauka entrance steel erection and

continue with metal deck installation. MSTC Station Complete drilled shafts for TCCR and pedestrian

bridge. Continue with TCCR foundation and entrance structures.

Page 57: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

57 | P a g e

KEY ISSUES:

Key Issues with Contractor Proposal Title CPC Code

City Fiber Networks - Traffic Signal Systems

Lagoon Dr Station - Additional Infrastructure for Interim Opening Part II

HIA Site Redevelopment

A B B

LEGEND: A = less than $1 million; B = $1 million-$5 million; C = greater than $5 million; P = pending contractor submittal ________________________________________________________________________________________________________________________________________________________________________________________________________________________

KEY MILESTONES: MSTC Station Entrance drilled shafts completed on Feb. 7, 2020. Segment 2,450 (90% complete) was cast on Feb. 20, 2020. HECO Zone 4 completed on Feb. 26, 2020. Span 525 (first curve into Airport near USPS) completed on Feb. 27, 2020.

________________________________________________________________________________________________________________________________________________________________________________________________________________________

QUALITY MANAGEMENT:

Pre-Activity Meetings continue.

AGS NCR Log (Issued by STG)

NCRs Issued to Date

Closed Open

Guideway 280 211 69 Pearl Harbor Naval Base Station 28 18 10 Honolulu International Airport Station 21 16 5 Lagoon Drive Station 12 9 3 Middle Street Transit Center Station 2 0 2 Contract Wide 15 14 1 TOTAL 358 268 90

Page 58: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

58 | P a g e

4.5 Section IV – City Center: Middle Street Transit Center Station to Ala Moana Center A. City Center Section Utilities and Guideway

CPP No.: FD-530 Contractor: AECOM Technical Services, Inc., Final Design Consultant (Engineer of Record) Contract Start Date: July 2012 Contract Substantial Completion: July 2020 Projected Completion of Work: July 2020

Project Description: The original City Center Section Utilities and Guideway (CCUG) final design contract consisted of utility relocations, roadway widening, and 4.12 miles of elevated transit guideway serving eight (8) passenger stations. The scope of the CCUG contract has been reduced to include only the design of utility relocations and roadway widening to facilitate future guideway design and construction by others. The remaining work is herein referred to as the City Center Utilities Relocation (CCUR) design.

Progress Schedule Status

Based on Expenditures* 97.7% On time (based on contract substantial completion date)**

Early Plan* 100%

Late Plan* 99.9% *Data as of Feb. 28, 2020. **Further explanation is provided in the Schedule section.

_______________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $191,227

DBE % Attained: 0.41%

Contract Changes in February

Change No. Description Amount ($)

Cumulative Previously Reported $13,941,087

None N/A ---

Cumulative Current Report $13,941,087

SCHEDULE: Due to changes to save cost and delays by third party reviews, CCUR final design is scheduled to conclude in

early third quarter 2020. The completion date is July 31, 2020. __________________________________________________________________________________________________

WORK PROGRESS: Activities this Month: Coordination with City and utility third parties to address review comments

for Task Orders (TOs) within the review process: TO17 DRAFT Rev.0 (2/19/20), TO22 Draft Rev. 0 V.2 (2/28/20), TO22-138 Rev. E (2/28/20), TO23A Draft Rev. 0 (2/7/20), TO23B Rev. E (2/14/20), TO27 Draft Rev. 0 (2/7/20), TO32 Draft Rev. 0 (2/11/20), and Traffic Signals/Street Lights Package-Dillingham (11/27/19), Traffic Signal (TS)/Street Light (SL) Package – Nimitz (1/20/20), TS/SL – Kakaako (1/20/20) and the Roadway Package Issued for Construction (IFC) V2 (2/19/20).

Look Ahead: Complete and submit final design

drawings for TOs 17, 22, 24, 23A, 23B, 32, 25, 28, 2 and 13.

Continue coordination with third parties on seeking variances to allow reduced spacing between utilities relative to preferred spacing requirements, especially on Dillingham.

Original Contract: $43,948,220 Incurred-to-Date: $57,023,894

Current Contract Value1: $57,889,307 Incurred in February: $02

1Current Contract Value = Original contract value with Design Allowance + executed Change Orders 2 Work has progressed and incurred amounts will be reflected as invoices are approved in the City’s C2HERPS system.

Page 59: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

59 | P a g e

Activities this Month (continued): Design Package submittals/resubmittals this month included: TO23A DRAFT

Rev. 0 to DTS and Utilities on 2/7/20 and HDOT on 2/11/20. TO27 DRAFT Rev. 0 to DTS, HDOT and Utilities on 2/7/20. TO32 DRAFT Rev. 0 to DTS and Utilities on 2/11/20. TO23B Rev. E to DTS and Utilities on 2/14/20. TO2A Draft Rev. 1 V2 to City, HDOT and Hawai‘i Gas on 2/14/20. TO17 DRAFT Rev. 0 to Utilities on 2/19/20. TO2B Draft Rev. 1 V2 to City, HDOT and Hawai‘i Gas on 2/25/20. TO22 DRAFT Rev. 0 V2 to DTS and Utilities on 2/28/20. TO22-138 Rev. E to City (ePlans only) on 2/28/20. Roadway Package IFC Rev 2 to City and HDOT on 2/21/20.

Received official comments for TO23A Draft Rev. 0 from AT&T Corp. (2/26/20); TO27 Draft Rev. 0 from HTI (2/20/20); Traffic Signals/Street Lights – Kakaako from DTS (2/21/20); and Traffic Signals/Street Lights – Nimitz from DTS (2/26/20).

CCGU-FD Issue 00034 Update to Cathodic Protection – Design and Engineering Services, and CCGU-FD Issue 00033 Kapalama Canal Hydraulic/Hydrology Analysis Reevaluation were both signed and executed on 2/25/20.

Continuing coordination with HECO and other concerned third party utility agencies (i.e. Board of Water Supply [BWS], Hawaiian Telcom [HTI], etc.) to finalize utility concerns and comments for pending design package submittal.

Continued coordination with other agencies with projects within City Center, as well as landowners and their consultants/contractors for development projects.

Continued support during construction via Request for Information (RFI) with CCUR contractors.

Continued coordination with utilities for all utility layouts for remaining dry utility task order packages, Traffic Signal and Street Light, as well as the final Roadway Packages.

Coordination with City and State agencies to process One-Time Review (OTR) and required permit approvals to allow construction to start.

Continued coordination with ROW team for ongoing negotiations for acquisitions.

Continued coordination and bi-weekly meetings with the DPP Director and staff for ongoing design task order packages review.

Look Ahead (continued): Third party review and comments for

Task Orders 27, 24, 17, 28, 2, 13, 26, 25, Street Lights and Traffic Signal, and Roadway Packages.

Finalize details for 138kV steel pole foundation design.

Finalize details for micropile needed for 138kV / BWS facilities crossing(s) on Dillingham Boulevard.

Finalize hydraulic/hydrology analysis for Kapalama Canal.

Six submittals in the upcoming month are expected.

Negotiations for a change order to extend the contract to the end of CCUR for design services during construction, as well as final submittal packages.

____________________________________________________________________________________________________________________________________________________________________________________

KEY ISSUES (new issues are in bold font): Met with City agencies this month to better coordinate criteria for flood elevation at Kapalama Canal given the

current design for Utility Bridges as proposed. No documented determination was provided other than a verbal confirmation that the City will review and recommend HART to adhere to City standards and regulations. The onus is now on HART to decide the path forward on the proposed Utility Bridges. Note: 90% submittal submitted by Nan, Inc. this month.

Working through details and finalizing cost and schedule impact for the following proposals already submitted as a change in scope: (1) 138kV pole foundation design, (2) micropile structure design for crossings of 138kV and 42” waterline facilities (3) management scope, (4) repackaging of Task Orders and (5) Design Services During Construction (DSDC) work to date. These will be processed accordingly, per HART change procedures.

HART is working with third party utilities as well as City agencies to better streamline reviews to prevent further slippage in design schedules.

____________________________________________________________________________________________________________________________________________________________________________________

KEY MILESTONES: Submittal of TO23A DRAFT Rev. 0 , TO27 DRAFT Rev. 0, TO32 DRAFT Rev. 0, TO23B Rev. E, TO2A Draft Rev. 1 V2, TO17

DRAFT Rev. 0, TO2B Draft Rev. 1 V2, TO22 DRAFT Rev. 0 V2, TO22-138 Rev. E and Roadway Package IFC Rev 2, as per schedule.

Executive Decision Document (EDD) Design & Construction (D&C) – 064 Transfer of Design Support Balance Funds Airport Guideway Utilities FD-430 to City Center Guideway Utility FD-530 Contract was signed and executed on Feb. 25, 2020.

Page 60: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

60 | P a g e

B. City Center Utilities Relocation (CCUR) Indefinite Delivery/Indefinite Quantity (IDIQ) CPP No.: DBB-511 Contractor: Nan, Inc. Contract Start Date: May 2018 Contract Term Completion: May 2022 Projected Completion of Relocation Work: September 2022

Project Description: The CCUR contract is a unit priced, task order contract that relocates utilities in advance of the City Center Guideway and Stations construction work. It provides utility relocation construction services for a variety of utilities along the civil roadway construction throughout the City Center segment of the HRTP. The construction services to be provided will include, but are not limited to, permanent and temporary wet and dry utility relocation work which will include miscellaneous, as-needed site work, installation of permanent/temporary utility poles, duct bank construction, and other utility installation support structures.

Progress Schedule Status

Physical % Complete* TBD**

4 months behind*** Early Plan* 43.0%

Late Plan* 33.1% *Data as of Feb. 28, 2020. **CEI is currently working on an EAC for all the work required prior to the P3 contractor commencing their work. Once this reevaluation of the comprehensive project cost is established, the percent complete in each work area can be determined. ***Execution Plan under review based on work in place, work remaining and assessment of design alternatives. Mitigation efforts are being incorporated.

________________________________________________________________________________________________________________________________________________________________________________________________________________________

COST INFORMATION:

DBE Participation Task Orders

Actual DBE Participation: $0 Number of Task

Orders Issued Amount ($)

DBE % Attained: 0% Task Orders Previously Issued 14 $371,066,449

Task Orders Issued this Month 0 $0

Amendments to Task Orders 1 $7,928,149

Total Task Orders Issued 14 $378,994,598

________________________________________________________________________________________________________________________________________________________________________________________________________________________

SCHEDULE: Mitigations, including allowance for concurrency of specific activities along with long lead material procurement

duration improvements and descoping of certain civil improvements that would be more appropriately performed by the P3 contract, have been incorporated into the schedule accounting for the Projected Completion of Relocation Work to move from December 2022 to September 2022.

Cleared 22% of proposed shaft locations, based on current design decisions. All Traffic Signals and Street Lights 90% design submitted by Q1 2020. 90% design complete – end of Q2 2020. All Wet Utility task orders under construction Q3 2020. All Dry Utility task orders under construction Q3 2020. HECO completes all electrical design requirements Q4 2020. Final roadway revision encompassing all changes Q1 2020.

Original Contract: $400,000,000 Incurred-to-Date: $22,016,928

Current Contract Value1: $400,000,000 Incurred in February: $02

1Current Contract Value = Original contract value + executed Change Orders 2 Work has progressed and incurred amounts will be reflected as invoices are approved in the City’s C2HERPS system.

Page 61: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

61 | P a g e

WORK PROGRESS: Activities this Month: All Area 1: Dillingham Controlled Access Technical Memo

Rev. B received as anticipated on Feb. 21, 2020; submittal currently on an expedited review path by HART, DTS and HDOT.

Area 1A: Hawaiian Telcom (HTI) and AT&T infrastructure nighttime installation continues, with approximately 2,300 linear feet (LF) of communication duct bank installed. Four manholes set. An additional Draft Rev. 0 IFC distributed to all utility agencies Feb. 28, 2020.

Area 1B: The Executive Decision Document (EDD) was approved for the straddle bent at Kalihi Kai and left-turn at McNeil. Kapalama Utility Bridge 90% plans were submitted to DPP and HART, as expected on Feb. 28, 2020. DPP confirmed acceptance of multi-use bridge and agreed all agencies will review for structural purposes.

Area 1C: Potholing based off 60% roll plot continues. Area 2: Obtained dry trenching permit. HECO provided

preliminary material list. Jet grouting soil stabilization commenced for electrical and communications utilities. Jet grout columns completed for new manholes.

Area 3: Demolition of existing sewer and waterline continues to clear future guideway foundations. Day work approved with ongoing travel time monitoring, allowing the more disruptive work to occur during off-peak daytime hours to increase productivity and limit community impact. Commencing layout and preparations for soil stabilization of new utility trenches.

Area 4: Temporary Traffic Signal Plan (TTSP) approved. Hawai‘i Community Development Authority (HCDA) extended Construction Right-of-Entry (CROE) contract through June 2021.

Area 5: Draft Rev. 0 for dry (TO-17) submitted to utilities for review. HART and DTS are in concurrence to proceed with a roadway design that incorporates the roundabout. Draft Rev. 0 submitted Feb. 18, 2020 as planned.

Area 6: Mobilization of jet grout plant for trench stabilization and excavation for wet and dry utility installation continues. HART authorized Nan to proceed with arrangements for HECO forces to excavate and expose the excess Fluidized Thermal Backfill surrounding the 138kV at Pi‘ikoi to clear conflicts with proposed utility trenches.

Look Ahead: All Area 1: Dillingham Controlled Access

Technical Memo finalization, and Traffic Control Plan (TCP) implementation to facilitate work zone productivity and mitigate work duration.

Area 1A: Develop and review AT&T temporary connection plan with the respective utility owners to facilitate other electrical and comms infrastructure installation. Begin HECO low-risk duct bank work, pending design and inspection concurrence from HECO.

Area 1B: Box culvert demolition and replacement shop drawings and procurement estimated duration 4-6 weeks with work estimated to begin in April.

Area 1C: Initial wet and dry design plans (Rev. D) for TO-13, TO-25, TO-36 are expected.

Area 2: Soil stabilization below water table and installation will continue for new infrastructure and HECO manholes along with completion of existing sewer jacketing.

Area 3: Obtain dry utility package (TO-27) One-Time Review (OTR) approval along with TCP and temporary traffic signal modifications. Demolition/removal of existing and abandoned utilities and new infrastructure to continue.

Area 4: Receive Tech Memo for 24-hours closure. Negotiation of Task Order scope of work to be scheduled for the work area between Richards and Cooke.

Area 5: Commence wet and dry utility relocation and civil improvements. Contractor to request full intersection closure to expedite roundabout construction.

Area 6: 138kV - HECO to chip duct bank overpour to clear conflicts with new infrastructure. Nan to continue waterline and commence communications duct work.

________________________________________________________________________________________________________________________________________________________________________________________________________________________

KEY ISSUES (new issues are in bold font):

Cost or schedule for the CCUR contract may be impacted significantly if these issues aren’t resolved: o Design Finalization: Completion of the dry utility plans by AECOM, and approval by the utilities. Design

decisions are being finalized and incorporated into plans and profiles for review and approval by utilities. CCUR Area Target Finish dates continue to be impacted by extended completion of IFC design due to ongoing and additional outstanding comment resolution items from the reviewing parties. Mitigations to the construction schedule have been incorporated to compensate and improve the projected completion, however final design approvals are critical to meeting the projected construction duration.

Page 62: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

62 | P a g e

o Mitigation efforts: AECOM is scheduled to complete 90% submittals by Q2 2020. The review time is subject to the City and third parties’ review and interface. AECOM is coordinating with utility agencies to shorten the remaining design review process by holding informal comment resolution review sessions. HART is continuously strategizing with utility stakeholders on steps to shorten review and approval response time. In parallel, HART CEI and Nan along with the utility stakeholders, are analyzing and agreeing on work scope that can start at limited risk based on current design levels to mitigate IFC design schedule extensions.

o HART Right-of-Way: Currently working to complete acquisition of property within CCUR. Current focus is on the following properties: Takara Printing, Kapalama Canal Utility Bridge Easement, Bishop Estate – Club Cleopatra, Iwilei Station - HECO, General Services Administration (GSA) – Halekauwila St. by Mililani St., Howard Hughes and HCDA.

o Mitigation efforts: DAGS and Honolulu Community College (HCC) anticipated acquisition to be completed by Q1 2020. Contractor provided the required Temporary Construction Easements (TCE’s) to incorporate into the final HCC agreement. Access to construct the bridges across the Kapalama Canal is needed before August 2020 to mitigate the critical path of Area 1B. The necessary mapping data for the Kapalama Pedestrian Bridges was submitted to the Department of Facility Maintenance (DFM) to facilitate and expedite access for bridge work to start. Tiger Team is exploring the possibility of horizontal directional drilling (HDD) or micro-tunneling utilities across Kapalama Canal, while simultaneously proceeding with the original construction of the Kapalama utility bridges.

o Permitting: Trenching and street usage permits are taking a significant amount of time and coordination to obtain. The contractor is doing what they can to respond to concerns and issues, however concerns such as controlled access along Dillingham require more time for planning and higher-level agreements. These efforts are currently underway in order to ensure a high degree of collaboration amongst all stakeholders.

o Mitigation efforts: A comment resolution meeting was held Feb. 6, 2020 with all reviewing agencies for the Controlled Access Technical Memorandum supplement to the Dillingham Traffic Management Plan. Subsequent meetings with both HDOT and DTS reviewers were held Feb. 10 and Feb. 13. Full revision was received on Feb. 21, 2020, and currently distributed for an expedited review by HART, DTS and HDOT.

o HECO Agreements: The Nov. 25, 2013 agreement with HECO allows HECO to complete the electrical design up to 2 years after receiving the final infrastructure design. Completion of relocation activities relies on more aggressive completion durations in order to meet the project’s needs. HART and HECO are currently working together to ensure the construction schedule is met.

o Mitigation efforts: Ongoing coordination efforts between HART and HECO are conducted bi-weekly to review schedule assumptions and requirements to maintain and improve the schedule based on the general agreement, as well as informally on a weekly basis. General agreement is in place, as of Q4 2019, to expedite electrical design times to meet schedule needs. Based on the Feb. 24, 2020 meeting with HECO and HART, HECO agreed to allow HART to work at risk with true 90% design submittal plans.

o Long lead Material Procurement: Estimates for the duration of long lead materials have been adjusted in the February update based on information provided by HECO for electrical equipment to be purchased under the CCUR contract. These corrected durations have contributed to the critical paths associated with CCUR Area Target Finish dates.

o Mitigation efforts: HART CEI will work with Nan who will expedite the orders timely and coordinate with HECO regularly to obtain the additional listings as HECO is provided the infrastructure designs necessary to begin their electrical design and develop the lists.

Page 63: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

63 | P a g e

KEY MILESTONES:

Construction1

NTP Target Finish2 Installed Complete3

Area 1A: Dillingham: Middle to Mokauea 20-Sep-19 01-Oct-21 TBD

Area 1B: Dillingham: Mokauea to Waiakamilo 20-Sep-19 07-Sept-22 TBD

Area 1C: Dillingham: Waiakamilo to Ka‘aahi 01-Feb-20 01-Aug-22 TBD

Area 2: Ka‘aahi Street 02-Feb-19 12-Jan-21 TBD

Area 3: Nimitz Highway 20-Sep-19 04-Aug-21 TBD

Area 4: Halekauwila Street 24-Jan-20 28-Apr-22 TBD

Area 5: Queen Street 01-Oct-18 01-Apr-21 TBD

Area 6: Kona Street 01-Mar-19 01-Jul-21 TBD

1 Based on 2/29/2020 data date. Multiple Design Packages are incorporated into each area. 2 Based on double shifts, 6 days per week, 10 hours per shift 3 CEI is currently working on an Estimated Cost at Completion for all the work required prior to the P3 contractor commencing their work. Once this reevaluation of the comprehensive project cost is established, the percent complete in each work area can be determined. __________________________________________________________________________________________________________________________________________________________

QUALITY MANAGEMENT:

No major quality issues identified this period.

CCUR NCR Log (Issued by Nan)

Total NCRs Issued to Date Closed Open

5 5 0

Page 64: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

64 | P a g e

4.6 Project-Wide A. Program Management Contractor Contract

CPP No.: MM-902 Contractor: HDR Engineering, Inc. Contract Start Date: January 1, 2017 Contract Completion Date: December 31, 2022 Description of Work: Oversee the successful design and construction of the full Honolulu Rail Transit Project (HRTP), which includes providing personnel with relevant transit design, construction and operations experience and leadership in the various areas, including construction management, design management, project controls, procurement and contracts, right of way, public and business outreach, safety and security, quality assurance, environmental planning, and federal programmatic compliance.

________________________________________________________________________________________________________________________________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $192,962

DBE % Attained: 0.30%

Contract Changes in February

Change No. Description Amount ($)

Cumulative Previously Reported $0

None N/A ---

Cumulative Current Report $0

Jan

-17

Mar

-17

May

-17

Jul-

17

Sep

-17

No

v-1

7

Jan

-18

Mar

-18

May

-18

Jul-

18

Sep

-18

No

v-1

8

Jan

-19

Mar

-19

May

-19

Jul-

19

Sep

-19

No

v-1

9

Jan

-20

Mar

-20

May

-20

Jul-

20

Sep

-20

No

v-2

0

Jan

-21

Mar

-21

May

-21

Jul-

21

Sep

-21

No

v-2

1

Jan

-22

Mar

-22

May

-22

Jul-

22

Sep

-22

No

v-2

2

Actual $ Per Month Forecast $ Per Month Actual % Forecast %

Actual 59.5 %

02/2020

Original Contract: $63,522,953 Incurred-to-Date: $34,623,644

Current Contract Value1: $63,522,953 Incurred in February: $937,822

1Current Contract Value = Original contract value + executed Change Orders

Page 65: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

65 | P a g e

WORK PROGRESS: Activities this Month:

21 HDR staff contracted through HART. Approved AGTL, Inc. as a new subcontractor to

provide oversight of the CCUR contract. Approved Hills23 as a new subcontractor to oversee

and support construction and project management activities and to provide assistance in the acquisition of properties and all other matters related to securing right-of-way for the HRTP.

Look Ahead: Continue to support the design and

construction of the HRTP, including assessing management needs in Project Controls.

KEY ISSUES:

Based on the average monthly expenditure rate, the current contract total will be exhausted by June 2021.

Subcontractor charges paid to date (from beginning of contract) is $5,260,322.04.

Page 66: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

66 | P a g e

B. Construction Engineering and Inspection (CEI) West CPP No.: MM-290 Contractor: PGH Wong Engineering, Inc. Contract Start Date: January 9, 2014 Contract Completion Date: July 7, 2020 (Amendment #4) Note: Amendment #4 revised the contract completion date to July 7, 2020 with no additional funding. West CEI and HART are currently negotiating Amendment #5 to add staffing budget and extend West CEI Services beyond the July 7, 2020 completion date to enable West CEI Services to complete station contracts closeout actions that will extend beyond July 7, 2020 due to continuing delayed completion of the construction contract works. Description of Work: Provides construction, engineering, and inspection services for construction contract compliance, construction scheduling, construction cost estimating, support, on-site field oversight, project controls and related construction support for the west section of the project.

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $11,825,748

DBE % Attained: 16.84%

Contract Changes in February

Change No. Description Amount ($)

Cumulative Previously Reported $36,000,000

None N/A ---

Cumulative Current Report $36,000,000

Jan

-14

Feb

-14

Mar

-14

Ap

r-1

4

May

-14

Jun

-14

Jul-

14

Au

g-1

4

Sep

-14

Oct

-14

No

v-1

4

Dec

-14

Jan

-15

Feb

-15

Mar

-15

Ap

r-1

5

May

-15

Jun

-15

Jul-

15

Au

g-1

5

Sep

-15

Oct

-15

No

v-1

5

Dec

-15

Jan

-16

Feb

-16

Mar

-16

Ap

r-1

6

May

-16

Jun

-16

Jul-

16

Au

g-1

6

Sep

-16

Oct

-16

No

v-1

6

Dec

-16

Jan

-17

Feb

-17

Mar

-17

Ap

r-1

7

May

-17

Jun

-17

Jul-

17

Au

g-1

7

Sep

-17

Oct

-17

No

v-1

7

Dec

-17

Jan

-18

Feb

-18

Mar

-18

Ap

r-1

8

May

-18

Jun

-18

Jul-

18

Au

g-1

8

Sep

-18

Oct

-18

No

v-1

8

Dec

-18

Jan

-19

Feb

-19

Mar

-19

Ap

r-1

9

May

-19

Jun

-19

Jul-

19

Au

g-1

9

Sep

-19

Oct

-19

No

v-1

9

Dec

-19

Jan

-20

Feb

-20

Mar

-20

Ap

r-2

0

May

-20

Jun

-20

Jul-

20

Actual $ Per Month Forecast $ Per Month Actual % Forecast %

Actual 98.1 %

02/2020

Original Contract: $54,232,480 Incurred-to-Date: $85,594,556

Current Contract Value1: $90,232,480 Incurred in February: $1,013,505

1Current Contract Value = Original contract value + executed Change Orders

Page 67: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

67 | P a g e

WORK PROGRESS: Activities this Month: Resident Engineers (REs) provided the weekly project status and

issues briefings at the weekly HART Project Managers (PM) meetings.

RE’s managed assigned projects as the HART on-site field representatives for CEI, managing contract correspondence and contract change administrative processes, issuing Field Change Notices (FCNs) when required, and overseeing work.

Continued monitoring fabrication of Hālawa (Aloha Stadium) Station canopy supports and installation of the canopies at FHSG and KHSG stations. Installation of canopy fabric was completed at Hālaulani (Leeward Community College) Station. Canopy support erection was completed at Kalauao (Pearlridge) Station under the KHSG contract.

Updated Monthly Progress Report Dashboards for all stations. Work-off of backlogged claims and changes progressed. Continue implementation of contract closeout processes for

WOSG and FHSG in anticipation of completion in the 2nd quarter of 2020.

Look Ahead: Turning over infrastructure to allow

Core Systems to continue their installation.

Continue to monitor and track station canopy fabrication and installation activities.

Oversee construction of assigned projects.

Closeout the UH West O‘ahu Park and Ride & UHWO Campus Road “B” (UHPRB) contract.

Continue closeout processes for WOSG and FHSG contracts and start them for KHR.

Change Orders Processed

CONTRACT FOM NSM SON CCO

UHPRB 2 1 1 1

WOSG 1 1 1 0

FHSG 1 0 0 1

KHSG 0 0 0 0

KHR 0 0 0 0

_______________________________________________________________________________________________________

KEY ISSUES:

Completing Core Systems access requirements and balance of structures conduit for CSC follow on work.

Continuation and completion of canopy installations.

Continue working-off of backlog of outstanding claims/change issues.

Page 68: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

68 | P a g e

C. Construction Engineering and Inspection (CEI) East CPP No.: MM-596 Contractor: Stantec Consulting Services Inc. Contract Start Date: September 14, 2015 Contract Completion Date: December 31, 2021 Description of Work: Provides construction, engineering, and inspection services for construction contract compliance, construction scheduling, construction cost estimating, support, on-site field oversight, project controls and related construction support for the east section of the project.

_______________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $22,088,276

DBE % Attained: 40.13%

Contract Changes in February

Change No. Description Amount ($)

Cumulative Previously Reported $47,000,000

None N/A ---

Cumulative Current Report $47,000,000

WORK PROGRESS: Activities this Month: Current Stantec East CEI support for the HRTP is at

approximately 62.6% of total contract value. Performed CEI services for the AGS DB, On-Call III, On-Call

IV, CCGS DB/P3, and CCUR projects throughout the east section project limits.

Look Ahead: Working with HART to monitor construction

progress in support of the current substantial completion dates for ongoing AGS DB and CCUR projects.

Sep

-15

Oct

-15

No

v-1

5

Dec

-15

Jan

-16

Feb

-16

Mar

-16

Ap

r-1

6

May

-16

Jun

-16

Jul-

16

Au

g-1

6

Sep

-16

Oct

-16

No

v-1

6

Dec

-16

Jan

-17

Feb

-17

Mar

-17

Ap

r-1

7

May

-17

Jun

-17

Jul-

17

Au

g-1

7

Sep

-17

Oct

-17

No

v-1

7

Dec

-17

Jan

-18

Feb

-18

Mar

-18

Ap

r-1

8

May

-18

Jun

-18

Jul-

18

Au

g-1

8

Sep

-18

Oct

-18

No

v-1

8

Dec

-18

Jan

-19

Feb

-19

Mar

-19

Ap

r-1

9

May

-19

Jun

-19

Jul-

19

Au

g-1

9

Sep

-19

Oct

-19

No

v-1

9

Dec

-19

Jan

-20

Feb

-20

Mar

-20

Ap

r-2

0

May

-20

Jun

-20

Jul-

20

Au

g-2

0

Sep

-20

Oct

-20

No

v-2

0

Dec

-20

Jan

-21

Feb

-21

Mar

-21

Ap

r-2

1

May

-21

Jun

-21

Jul-

21

Au

g-2

1

Sep

-21

Oct

-21

No

v-2

1

Dec

-21

Actual $ Per Month Forecast $ Per Month Actual % Forecast %

Actual 62.6 %

02/2020

Original Contract: $55,036,130 Incurred-to-Date: $60,042,864

Current Contract Value1: $102,036,130 Incurred in February: $02

1Current Contract Value = Original contract value + executed Change Orders 2 Work has progressed and incurred amounts will be reflected as invoices are approved in the City’s C2HERPS system.

Page 69: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

69 | P a g e

Activities this Month (continued): AGS DB overall construction progress is at 61% - Guideway

progress is at approximately 64%, and Stations are at approximately 7%.

Provided detailed schedules relating to multiple scenarios for the CCUR construction activity required in support of the P3 access dates.

Provided CEO consultant evaluation summary of Stantec contract for construction progress of ongoing projects along the East Section.

Look Ahead (continued): Continuing to monitor staff resources and

overall East CEI II project budget with additional HART scope requests.

Continue to work with HART in support of construction completion to support the P3 planned activities.

Supporting HART with the potential addition of a second contractor for CCUR to include the review of phasing, CEI II staffing, and potential schedule improvements to support the P3 planned activities.

Identify a Public Involvement (PI) manager to replace the current manager who will leave the project in March 2020.

_______________________________________________________________________________________________________

KEY ISSUES:

No current contractual issues.

Page 70: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

70 | P a g e

D. General Engineering Consultant CPP No.: MM-913 Contractor: CH2M Hill, Inc. Contract Start Date: December 5, 2013 Contract Completion Date: July 4, 2021 Description of Work: Task 01 – Scheduling and Estimating Support: Task Order 01 provides staff augmentation to support scheduling and cost estimating services through the design and construction phase of the Project.

Task 02 – Interface Management and Coordination: Provide oversight of technical coordination and Configuration Management.

Task 03 – Environmental and Planning: Provide environmental and planning support to ensure compliance with appropriate decision documents for the Project; integration with other applicable state or city entities for systems, station, land use, and operation planning.

Task 04 – Design Management Services: Engineering and architectural design management services for the duration of the project.

Task 05 – Program Management and Deliverables: Program Management services throughout the entire duration of the Project to include, but not limited to the Work Breakdown Structure, Budget Staffing Plan, Monthly Progress and Status Reports, and Contract Administration.

________________________________________________________________________________________________________________________________________________________________________________________________________________________

COST INFORMATION:

Task Description Original Value Current Value Incurred-to-Date

1 Scheduling and Estimating Support $13,187,310 $22,556,723 $17,971,285

2 Interface Management and Coordination $5,644,829 $4,097,085 $3,357,942

3 Environmental and Planning $6,537,705 $20,303,965 $11,866,793

4 Design Management Services $16,986,250 $34,866,501 $28,292,270

5 Program Management and Deliverables $2,434,232 $1,565,057 $1,307,321

OD Other Direct Expenses $1,352,951 $1,339,444 $973,373

Total $46,143,277 $84,728,775 $63,768,983

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $7,644,864

DBE % Attained: 11.99%

Contract Changes in February

Change No. Description Amount ($)

Cumulative Previously Reported $38,585,498

None N/A ---

Cumulative Current Report $38,585,498

Original Contract: $46,143,277 Incurred-to-Date: $63,768,983

Current Contract Value1: $84,728,775 Incurred in February: $02

1Current Contract Value = Original contract value + executed Change Orders 2 Work has progressed and incurred amounts will be reflected as invoices are approved in the City’s C2HERPS system.

Page 71: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

71 | P a g e

________________________________________________________________________________________________________________________________________________________________________________________________________________________

WORK PROGRESS: Activities this Month: Look Ahead: Task 01: Produced January schedule updates for PMOC meetings. Outlined

schedule updates and progress. Maintained HART’s Master Project Integrated Schedule; December 2025

Substantial Completion with 83 days of contingency. Operation Readiness – Segment 1 Turnover date is Oct. 20, 2020.

Provided review and analysis of STG’s Over the Shoulder Mitigation Schedules.

Reviewed Elevators & Escalators schedule for coordination of installation activities in the station contracts.

Continued supporting Design and Construction with City Center Utility and Guideway/Station coordination of activity predecessors.

Provided Independent Cost Estimate (ICE) Cost to Complete for the following: o 100 Year Hydraulic Evaluation o Kapalama Utility Bridges o Additional Train Wash Facility o Build Future Elevator Shafts at Stations o CCUR Task Order No. 20 Update o Kuala Street Left Turn Lane

Produced Monthly Internal Schedule Progress Report. Report outlines progress on all ongoing projects.

Continued the implementation of existing HART projects into the Oracle Unifier system.

Continued validating previous CCUR vendor invoices to reconcile with the Oracle Unifier system.

Met with CEI CCUR review team to review billing process on all Task Orders.

Worked with Core Systems to set up Power Back Up Generators Contract with PAC Electric for Cost Loaded Scheduling, Cost Workbook, and Cost Code Verification sheets for the contractor.

Task 01: On-going support of ICE development or reviews of

cost estimates prepared by the CEI team for independent quality assessments. The following are projected ICE’s: o Update quantity takeoffs and Costs for CCUR

Wet/Dry Utility Task Orders o ICE for UH West O‘ahu Entrance Building,

Waipahu Transit Center Makai Entrance Building, UH West O‘ahu Park & Ride, FHSG Claims to Closeout

o ICE for Requests for Change from Contractor (RFCC’s) and Requests for Change by HART (RFCR’s)

o FOM/Negotiation Strategy Memo (NSM) Review and Approval

Continue updates of Monthly Schedule reports and analysis.

Evaluate AGS mitigation schedule and added schedule details on stations.

Continue to implement the existing HART projects into the Oracle Unifier system.

Continue validating CCUR vendor invoices. Meet with Risk Management to review risk

processes and provide assistance as necessary.

Dec

-13

Jan

-14

Feb

-14

Mar

-14

Ap

r-1

4M

ay-1

4Ju

n-1

4Ju

l-1

4A

ug-

14

Sep

-14

Oct

-14

No

v-1

4D

ec-1

4Ja

n-1

5Fe

b-1

5M

ar-1

5A

pr-

15

May

-15

Jun

-15

Jul-

15

Au

g-1

5Se

p-1

5O

ct-1

5N

ov-

15

Dec

-15

Jan

-16

Feb

-16

Mar

-16

Ap

r-1

6M

ay-1

6Ju

n-1

6Ju

l-1

6A

ug-

16

Sep

-16

Oct

-16

No

v-1

6D

ec-1

6Ja

n-1

7Fe

b-1

7M

ar-1

7A

pr-

17

May

-17

Jun

-17

Jul-

17

Au

g-1

7Se

p-1

7O

ct-1

7N

ov-

17

Dec

-17

Jan

-18

Feb

-18

Mar

-18

Ap

r-1

8M

ay-1

8Ju

n-1

8Ju

l-1

8A

ug-

18

Sep

-18

Oct

-18

No

v-1

8D

ec-1

8Ja

n-1

9Fe

b-1

9M

ar-1

9A

pr-

19

May

-19

Jun

-19

Jul-

19

Au

g-1

9Se

p-1

9O

ct-1

9N

ov-

19

Dec

-19

Jan

-20

Feb

-20

Mar

-20

Ap

r-2

0M

ay-2

0Ju

n-2

0Ju

l-2

0A

ug-

20

Sep

-20

Oct

-20

No

v-2

0D

ec-2

0Ja

n-2

1Fe

b-2

1M

ar-2

1A

pr-

21

May

-21

Jun

-21

Jul-

21

Actual $ Per Month Forecast $ Per Month Actual % Forecast %

Actual 81.2 %

02/2020

Page 72: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

72 | P a g e

Activities this Month (continued): Task 02:

Configuration Management (CM) and Close-out activities performed: o Researched the Contract Specifications for each of the West Side

Stations Groups (WSSG) contracts and created a spreadsheet detailing all the equipment and materials described in each Specification. Further, reviewed the O&M manuals that are currently available for any supplemental parts information.

o Drafted a revision of the Configuration Management Plan (CFMP). o Participated in walk-through inspections for two of the westside

stations to document remaining work and punchlist items. o Chaired weekly Elevated Issues meetings for the WSSG contracts. o Met over 30 times with various HART personnel to discuss strategies for

development of a list of spare parts for the first two years of service, closeout of the WSSG contracts with special emphasis on the operations and maintenance manuals and the status of as-built drawings, and proposed revisions to the CFMP.

o Scheduled and chaired a meeting of the Configuration Control Committee. Also, wrote the meeting minutes and circulated to all attendees for review and comment.

Look Ahead (continued): Task 02:

Configuration Management and Close-out activities that will be worked on are: o Address and reconcile review comments on the

recent revision of the Configuration Management Plan.

o Schedule, organize and chair meetings of the HART Configuration Control Committee.

o Attend Contract Change Committee meetings. o Continued refinement of the comprehensive

checklists for the closeout for the West Side Stations Groups contracts and commence tracking status.

o Further verification of HRH’s compliance with their CM procedures.

o Schedule, organize and chair weekly WSSG Elevated Issues meetings.

Task 03: Permits – drafted a letter requesting extension of the Stream Channel

Alteration Permit (SCAP) for Kalihi Stream. Following extension of the existing SCAP, a new SCAP application will be filed for Kalihi Stream to cover design changes in guideway and concourse piers. Preparation of that application is underway.

Environmental Analyses and Documentation – subconsultant Ebisu & Assoc. conducted a noise study to evaluate potential impacts resulting from a design change to the enclosure for the emergency backup generator at Hō‘ae‘ae (West Loch) Station. The generator, which is located across the street from Waipahu Fire Station, is approximately 14 feet higher than originally planned. The noise study found that impacts could be mitigated through deployment of best available (noise emission) control technology.

Programmatic Agreement (PA) Compliance – prepared a work plan for the Parks Improvement Plan (required by Stipulation VIII.D of the Programmatic Agreement) and convened an initial planning meeting with HART staff. The Parks Improvement Plan will include three adversely affected parks (Mother Waldron Park, Irwin Park, and Walker Park) and must be completed before construction of the rail project is complete. Charrette style kick-off meetings are expected to take place in late summer 2020.

On-Call Support for Right of Way, Utilities, Environmental Planning – completed a 6-minute video showing traffic control on a portion of Dillingham Boulevard (Mokauea Street to Kalihi Street) during utility relocation and guideway construction. The dynamic visualization is being used in presentations to stakeholders and community members.

Task 03: Permits – complete stream-related permit applications

for the Kapalama Canal utility/pedestrian bridges, prepare extension request for the Waiawa Stream SCAP, and prepare WOFH community noise permit application.

Environmental Analyses & Documentation – complete draft 4(f) analysis for straddle bents affecting Mother Waldron Park. Prepare environmental review documents for straddle bents on Dillingham Boulevard at Kalihi Kai Elementary School and in front of six Quonset huts, and for the Pouhala (Waipahu) Station makai entrance building.

PA Compliance – with subconsultants HACBED/Purple Maia address comments on Stipulation VII educational products in response to review comments from the Consulting Parties. Subconsultant HHF Planners expects to finalize the Cultural Landscape Reports for Mother Waldron Park and Walker Park.

On-Call Support for Right of Way, Utilities, Environmental Planning – prepare photo simulations of traffic control scenarios on Halekauwila Street in the vicinity of Mother Waldron Park.

Task 04: Conducted a field visit with HDOT staff to observe erosion occurring along

Kaloi Channel. Coordinated with artists and station contractors on artwork installation

details for EK, UHWO, Ho‘opili, LCC, Pearl Highlands, Pearlridge and Aloha Stadium.

Continued as-needed support for the fabrication and installation of the west station canopies.

Reviewed 4 design submittals, 36 NCRs, 6 Field Design Changes, and 6 Notice of Design Changes for the Airport Guideway and Stations contract. Attended Task Force Meetings, presubmittal workshops and comment resolution meetings.

Provided comments on City Center Project Agreement Exhibit 7A-7E. Continuing designs on various scope gap items on the westside stations. Presented to DTS on HART Art & Culture and Signage Programs to support

their rail branding process.

Task 04: Prepare a draft scope of work for corrective action to

mitigate the erosion at certain WOFH piers along Kaloi Channel.

Continue to provide engineering support to CCUR to evaluate possible guideway configuration changes to minimize utility relocation costs.

Continue to provide technical support to the CEI team overseeing the Airport Guideway and Stations contract.

Continue participation in third-party coordination meetings (technical meetings and management meetings) for various contracts. Third parties include HECO, HDOT, Department of Health (DOH), Airport, Navy and UH West O‘ahu.

Continue to perform design reviews in support of the KHG 138kV undergrounding contract.

Continue to provide construction support for the Kamehameha Highway Resurfacing project.

Page 73: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

73 | P a g e

Activities this Month (continued): Task 05: Monitored contract labor and sub-consultant expenditures. Updated Monthly Estimate at Completion (EAC). Participated in preparation of monthly reports. Met with new GEC III on-site rep and GEC III corporate rep. Discussed overall performance of all tasks. Explained GEC III on-site rep responsibilities and attendance at a bi-weekly

meeting. Explained need for submittal of chart describing contract cost trends.

Look Ahead (continued): Task 05: Discuss various tasks. Continue to monitor contract labor and sub-consultant

expenditures. Update Monthly EAC. Participate in preparation of monthly reports. Discussion of changes with scheduling staff.

________________________________________________________________________________________________________________________________________________________________________________________________________________________

KEY ISSUES: Task 01:

No current contractual issues. Task 02:

No current contractual issues. Task 03:

No current contractual issues. Task 04:

No current contractual issues. Task 05:

No current contractual issues.

Page 74: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

74 | P a g e

E. Core Systems Support CPP No.: MM-962 Contractor: Lea+Elliott, Inc. Contract Start Date: February 11, 2014 Contract Completion Date: September 10, 2022

Description of Work: Provide design and construction management oversight for the Core System Design-Build-Operate-Maintain (CSDBOM) Contract, to include system commissioning, passenger services start-up, and pre-revenue operations and maintenance activities.

_______________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $1,593,368

DBE % Attained: 3.62%

Contract Changes in February

Change No. Description Amount ($) Cumulative Previously Reported $33,784,957

None N/A ---

Cumulative Current Report $33,784,957

WORK PROGRESS: Activities this Month: Project Management:

o Six (6) letters were received from HRH and reviewed. Five letters were finalized and issued by the Core Systems Oversight Consultant (CSOC).

o Worked on mobilizing additional resources. o Six RFIs were received and 6 RFIs were responded to this period. o The CSOC received 85 submittals and completed 103 submittal reviews during this period.

Look Ahead: Continue to monitor, observe,

witness, and report on the Core Systems Contractor’s daily activities on-site and at the factories.

Feb

-14

Ap

r-1

4

Jun

-14

Au

g-1

4

Oct

-14

Dec

-14

Feb

-15

Ap

r-1

5

Jun

-15

Au

g-1

5

Oct

-15

Dec

-15

Feb

-16

Ap

r-1

6

Jun

-16

Au

g-1

6

Oct

-16

Dec

-16

Feb

-17

Ap

r-1

7

Jun

-17

Au

g-1

7

Oct

-17

Dec

-17

Feb

-18

Ap

r-1

8

Jun

-18

Au

g-1

8

Oct

-18

Dec

-18

Feb

-19

Ap

r-1

9

Jun

-19

Au

g-1

9

Oct

-19

Dec

-19

Feb

-20

Ap

r-2

0

Jun

-20

Au

g-2

0

Oct

-20

Dec

-20

Feb

-21

Ap

r-2

1

Jun

-21

Au

g-2

1

Oct

-21

Dec

-21

Feb

-22

Ap

r-2

2

Jun

-22

Au

g-2

2

Actual $ Per Month Forecast $ Per Month Actual % Forecast %

Actual 60.38 %

02/2020

Original Contract: $43,988,989 Incurred-to-Date: $44,703,873

Current Contract Value1: $77,773,946 Incurred in February: $659,617

1Current Contract Value = Original contract value + executed Change Orders

Page 75: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

75 | P a g e

Activities this Month (continued): o Executed Change Order 00061 Portable Lifts. o Executed Change Order 00062 Portable Backup Generators for TCCRs. o Developed the Independent Cost Estimate (ICE) for RFCR 00058 Variable Message Sign

(VMS) Signs. o Reviewed and validated HRH’s Request for Payment #98 for work reported by HRH during

January 2020. Interface Management:

o Led station handover walk-through at WLO, WTC and LCC stations. o Continued to support HART with the CSC’s planning and coordination for canopy device

installation with Fixed Facility Contractors (FFCs). o Supported HART with HRH and PAC Electric’s Interface for Traction Power Backup

Generators. o Coordinated STG Rail Haul from the LCC laydown yard to STG guideway area east of Aloha

Stadium. Manufacturing Oversight and Factory Inspection:

o Completed receiving inspection of Train #9 at the MSF. o Commenced shipping inspection of Train #8 for transit to Honolulu. o Completed support of Interim Certification for Trains #10 and #11.

Installation Oversight: o Completed oversight of FDAS installation at EKP. o Continued oversight for MDS installation on guideway. o Continued oversight for Comms installation at HOP, WLO, WTC and LCC.

System Acceptance, Testing, and Commissioning: o Witnessing of the following testing activities:

CCTV testing in the MSF/Yard ACS/IDS testing in the MSF/Yard Train dynamic qualification test in the dynamic section with Trains #1 and #3 Train #9 delivery and inspection Train #10 dynamic acceptance test Train #11 static acceptance test Train #12 onboard ATC acceptance testing Onboard ATC Vehicle Test Procedure (VTP)/Central Test Procedure (CTP) testing

in the functional section extended to EKP ATC wayside testing in PHL and EKP stations LCC GBS and PHL TPSS testing with SCADA OCC TES Transfer Trip functionality testing EKP, WLO, HOP and WYL TPSS. WYL PSGS commissioning Passenger Vehicle (PV) 3rd Rail Shoe Test to PLR station EKP FDAS Standalone Test MSF BLS12, Electrically Operated Switch (EOS) 17 and EOS 19 TES Loop Resistance Test for LCC GBS and PHL TPSS 3rd Rail Initial Energization test from LCC to PLR station, utilizing LCC GBS and PHL

TPSS P2R testing to close derailment report PV 5.7% climb capability test

Other Assignments: o Provided Data Room Update #6 for the P3. o Supported HART with P3 workshops and P3 Procurement activities. o Reviewed technical submittals, schedule submittal, payment schedule submittal, and other

contractual documents for the Traction Power Backup Generator (TPBuGen) Contract. o Supported HART with PMOC/FTA Audit. o Supported HART with generating final Addendums for WiFi Procurement. o Responded to RFIs for WiFi Procurement. o Conducted investigation on the voltage fluctuation and HECO Load Tap Changer (LTC)

equipment excessive movement issues identified during train testing. o Provided updated 12kV Voltage Impact Study with latest power profile for Interim Opening

#1.

Look Ahead (continued): Continue to assist HART with

resolution of change and claim issues.

Continue to assist HART with the Track Allocation Procedure.

Continue to support HART to address outstanding issues related to construction access at stations.

Continue to support HART to meet MSF Operational schedule objective and Interim Opening activities.

Continue to support HART to prepare the functional section to start integration testing on the mainline.

Support HART on P3 activities, as required.

Continue to support HART with HECO issues, including work on power quality and mitigation analysis.

Review final design, O&M, plans, and test procedures/report submittals.

Finalize PV design solution to add car shell ventilation holes.

Finalize PV design solution to add four additional CCTV cameras.

Continue to mobilize personnel to support additional tasks added to the CSOC’s scope.

_______________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

KEY ISSUES: o No issues.

Page 76: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

76 | P a g e

4.7 Contract Status by Contract Packaging Plan (CPP) Number

Contract Summary by CPP

(data as of Feb 29, 2020) A B C = A + B D E = D / C

CPP # CPP Title

Original Contract

Value

Change

Orders

Current Contract

Value Incurred % Exp.

Award

Date

Original

Completion

Date

Revised

Completion

Date

DB-120 West Oahu/Farrington Hwy Guideway 482,430,201 185,351,685 667,781,886 667,781,906 100% Nov-2009 Oct-2013 Dec-2018

DB-122 Westside Bird Control 0 0 0 0 0% TBD TBD TBD

DB-172 DR Horton Parking / Interim PnR Ho'opili 0 0 0 0 0% TBD TBD TBD

DB-200 Maintenance & Storage Facility 195,258,000 86,517,032 281,775,032 281,775,032 100% Jun-2011 Dec-2014 Jul-2016

DB-275 Pearl Highlands Garage, Bus Terminal, H2 Ramp 0 0 0 0 0% TBD TBD TBD

DB-320 Kamehameha Hwy Guideway 372,150,000 31,405,774 403,555,774 403,589,030 100% Jun-2011 Oct-2014 Dec-2018

DB-450 Airport Section Guideway/Stations 874,750,000 11,054,752 885,804,752 517,780,890 59% Sep-2016 May-2021 May-2021

DB-550 City Center Guideway and Station (CCGS) 100,000 134,000 234,000 206,546 88% Jan-2018 Nov-2024 Nov-2024

DBB-121 WOFM Median Landscaping 0 0 0 0 0% TBD TBD TBD

DBB-171 West Oahu Station Group 56,088,470 31,810,294 87,898,764 81,216,892 92% Jul-2015 Mar-2018 Mar-2019

DBB-271 Farrington Highway Station Group 78,999,000 18,487,980 97,486,980 89,256,357 92% Jun-2015 Jan-2018 Jan-2019

DBB-272 Waipahu Makai Entrance 0 0 0 0 0% TBD TBD TBD

DBB-371 Kamehameha Hwy Station Group 115,805,845 15,219,828 131,025,673 112,558,850 86% Jan-2016 May-2019 May-2019

DBB-385 Ramp H2R2 5,203,646 332,250 5,535,896 5,535,896 100% May-2015 Oct-2016 Nov-2017

DBB-505 Airport Section Utilities Construction 27,993,290 726,200 28,719,489 28,719,489 100% Jun-2014 Feb-2016 Oct-2016

DBB-511 City Center Utilities Relocation Construction 400,000,000 0 400,000,000 22,016,928 6% May-2018 May-2020 May-2022

DBB-525 Airport Section Guideway 7-Pier 3,973,000 54,843 4,027,843 4,027,843 100% Sep-2014 Feb-2015 Apr-2015

DBB-551 Advanced Guideway Foundations in Kaka'ako 0 0 0 0 0% TBD TBD TBD

DBB-600 Park-and-ride Lots Construction 0 0 0 0 0% TBD TBD TBD

DBB-602 UHWO Temp PnR and Campus Rd B 11,589,300 1,611,930 13,201,230 12,193,721 92% Dec-2017 Jul-2019 Jul-2019

DBB-701 Kamehameha Highway Resurfacing 25,989,989 2,145,340 28,135,329 26,265,076 93% Jul-2018 Sep-2019 Sep-2019

DBB-921 WiFi Passenger Vehicles 0 0 0 0 0% TBD TBD TBD

DBOM-920 Core Systems Design Build O/M 573,782,793 209,736,373 783,519,166 413,391,550 53% Nov-2011 Mar-2019 Jan-2025

FD-140 West Oahu Station Group 7,789,000 6,442,995 14,231,995 13,215,801 93% Jun-2012 Nov-2016 May-2020

FD-145 Dillingham / Kaka'ako (Eastside) SG FD 0 0 0 0 0% TBD TBD TBD

FD-240 Farrington Highway Stations Group 9,300,696 7,197,120 16,497,816 16,211,164 98% Jan-2011 Nov-2016 Mar-2020

FD-340 Kamehameha Hwy Station Group 8,702,592 4,785,962 13,488,554 13,061,253 97% Nov-2012 Jun-2017 Nov-2019

FD-430 Airport Sect. Guideway/Util 38,840,960 4,111,440 42,952,400 42,371,374 99% Dec-2011 Aug-2013 Jun-2017

FD-440 Airport Station Group 10,177,365 (117,545) 10,059,820 10,059,820 100% Nov-2012 Jan-2014 Jul-2015

FD-530 City Center Guideway/Util 43,948,220 13,941,087 57,889,307 57,023,894 99% Jul-2012 Mar-2014 Jul-2020

FD-550 Dillingham and Kaka'ako Station Group 18,321,918 (6,020,837) 12,301,081 12,341,565 100% Aug-2013 Sep-2014 Aug-2016

FD-600 KHG 138kV Underground Design 0 0 0 0 0% TBD TBD TBD

FD-700 Design Services for 138kV Util. Reloc. at KHG 8,766,327 0 8,766,327 3,821,186 44% Aug-2018 Nov-2021 Nov-2021

FD-701 KH Civil Design 60,000 0 60,000 60,000 100% Jan-2018 Jan-2019 Jan-2019

MI-900 Fare Collection DFI 15,464,198 444,026 15,908,224 6,367,210 40% Mar-2016 Jan-2029 Jan-2029

MI-930 Elevators & Escalators Install/Maint 50,982,714 4,879,726 55,862,440 26,954,759 48% Jul-2013 May-2018 May-2021

MI-940 Core Systems Backup Generators 0 0 0 0 0% TBD TBD TBD

MI-950 Volt Ampere Reactive Equipment 0 0 0 0 0% TBD TBD TBD

MM-945 On-Call Construction I 1,000,000 1,000,000 2,000,000 1,999,983 100% Aug-2014 Jul-2019 Dec-2016

MM-947 On-Call Construction II 7,500,000 0 7,500,000 7,495,772 100% May-2015 May-2020 May-2020

MM-948 On-Call Construction III 20,000,000 6,000,000 26,000,000 25,558,603 98% May-2016 May-2023 May-2023

MM-949 On-Call Construction IV 46,000,000 0 46,000,000 31,047,078 68% Jan-2018 Nov-2024 Nov-2024

Page 77: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

77 | P a g e

Contract Summary by CPP

(data as of Feb 29, 2020) A B C = A + B D E = D / C

CPP # CPP Title

Original Contract

Value

Change

Orders

Current Contract

Value Incurred % Exp.

Award

Date

Original

Completion

Date

Revised

Completion

Date

MM-290 Construction Engrg & Insp CEI West 54,232,480 36,000,000 90,232,480 85,594,556 95% Jan-2014 Jan-2020 Jan-2020

MM-595 Construction Engrg & Insp CEI East I 63,083,417 (50,377,317) 12,706,100 12,711,366 100% Jan-2014 Jan-2019 Jan-2016

MM-596 Construction Engrg & Insp CEI East II 55,036,130 47,000,000 102,036,130 60,042,864 59% Sep-2015 Dec-2019 Dec-2021

MM-901 Program Mgt Support Conslt II 33,376,897 16,359,765 49,736,662 49,736,662 100% Feb-2012 Mar-2015 Mar-2017

MM-902 Program Mgt Support Conslt III 63,522,953 0 63,522,953 34,623,644 55% Jan-2017 Dec-2022 Dec-2022

MM-905 MM-905 Gen Engrg Conslt EIS/PE 0 75,995,982 75,995,982 75,995,982 100% Aug-2007 Feb-2010 Feb-2011

MM-910 MM-910 Gen Engrg Conslt FD-Construct 150,226,265 0 150,226,265 150,226,265 100% Jun-2011 Dec-2014 Dec-2014

MM-913 MM-913 Gen Engrg Recompete 46,143,277 38,585,498 84,728,775 63,768,983 75% Dec-2013 Apr-2019 Jul-2021

MM-915 HDOT Traffic Mgmt. Consult. 1,600,000 5,010,000 6,610,000 6,056,562 92% Jun-2012 Jun-2017 Jun-2019

MM-920 HDOT Coordination Conslt WOFH 3,000,000 6,500,000 9,500,000 9,483,733 100% Jun-2011 Jun-2016 Dec-2018

MM-921 HDOT Coordination Conslt KHG 16,138,390 (1,400,000) 14,738,390 7,837,003 53% Jun-2012 Feb-2025 Feb-2025

MM-922 HDOT Coordination Conslt. East 17,560,000 (7,631,360) 9,928,640 5,723,401 58% Jun-2012 Dec-2024 Dec-2024

MM-925 HDOT - WOFH/KHG Imprv Agreements 550,000 2,865,633 3,415,633 2,761,830 81% Oct-2010 Oct-2019 Oct-2019

MM-930 HDOT State SOA Manager & Consultant 1,272,400 583,142 1,855,542 990,437 53% Feb-2012 Aug-2017 Aug-2017

MM-940 Kako'o Consultant I 1,000,000 (3,106) 996,894 531,609 53% Mar-2012 Mar-2022 Mar-2022

MM-941 Kako'o Consultant II 200,000 200,000 400,000 350,000 88% Dec-2015 Jan-2018 Jan-2020

MM-946 On-Call Hazmat Assessment Consultant 12,006,227 2,075,000 14,081,227 6,776,331 48% Feb-2018 Feb-2023 Feb-2023

MM-950 OCIP Consultant I 1,250,000 0 1,250,000 1,250,000 100% May-2012 Jun-2017 May-2017

MM-951 Owner-Controlled Insurance Program 41,000,000 8,640,674 49,640,674 43,280,007 87% Apr-2014 Apr-2020 Mar-2019

MM-953 OCIP Consultant II 415,000 0 415,000 371,672 90% May-2017 May-2020 May-2020

MM-960 Archeological & Cultural Monitoring 2,489,748 0 2,489,748 2,929,473 118% Jan-2014 Jan-2019 Jan-2019

MM-962 Core Systems Support 43,988,989 33,784,957 77,773,946 44,703,873 58% Feb-2014 Sep-2019 Sep-2022

MM-964 Safety and Security Consultant 21,699,279 5,549,188 27,248,468 14,690,752 54% Apr-2014 Jan-2017 Jan-2019

MM-970 Fare Collection Consultant 1,178,300 640,620 1,818,920 866,104 48% Sep-2015 Dec-2019 Dec-2019

MM-975 LEED Commissioning Services for MSF 278,630 7,845 286,475 286,475 100% Oct-2010 Jan-2016 Aug-2017

PA-102 Programmatic Agreement HPC 667,275 (175,947) 491,329 274,585 56% Jul-2013 Jan-2019 Jan-2019

ART ART Contracts 2,139,500 10,000 2,149,500 606,250 28% Jan-2016 Jul-2019 Jul-2019

MM-935 Real Estate Consultant 3,000,000 5,077,665 8,077,665 7,504,910 93% Mar-2012 Mar-2017 Mar-2017

MM-936 Real Estate Consultant II 8,190,000 0 8,190,000 5,927,870 72% Sep-2016 Sep-2020 Sep-2020

MM-937 Real Estate Consultant - Maps/Surv. 2,998,000 1,130,000 4,128,000 2,974,656 72% May-2014 May-2017 May-2019

MM-981 Complex Real Property Nego. Lit. Sup 600,000 (21) 599,979 602,241 100% Sep-2016 Sep-2018 Sep-2018

MM-982 On Call Appraiser 4,000,000 0 4,000,000 520,321 13% Jun-2016 Dec-2022 Dec-2022

MM-983 Land Court Petition Services 1,200,000 0 1,200,000 81,026 7% Oct-2016 Oct-2019 Oct-2019

MM-985 On Call Appraisers II 1,261,308 0 1,261,308 354,144 28% Apr-2017 Apr-2022 Apr-2022

MM-986 Real Estate Legal Services 5,800,000 0 5,800,000 2,068,938 36% Oct-2017 Dec-2022 Dec-2022

MM-990 Design Review Consultant 4,027,781 0 4,027,781 375,795 9% Mar-2018 Dec-2024 Dec-2024

MM-991 P3 Financial Legal Services 4,282,333 5,007,500 9,289,833 6,711,245 72% Oct-2018 TBD TBD

UTIL Utility Contracts and Agreements 144,141,812 27,632,834 171,774,646 72,498,109 42% Dec-2009 Dec-2018 Jun-2018

HART-201 HART Expenses & ODCs 38,985,433 0 38,985,433 30,945,820 79% N/A N/A N/A

HART-202 Precast Yard Agreement 32,254,379 16,101,392 48,355,771 7,445,800 15% N/A N/A N/A

4,395,763,727 912,422,199 5,308,185,926 3,754,386,760

Source: HART CMS. Note: Excludes Right-of-Way transactions, debt financing costs, and City/HART contract packages, which are included in Appendix A. 2

Non-Contractual Expenses

(data as of Feb 29, 2020)

CPP # CPP Title

Current Contract

Value Incurred

ROW Real Estate Docs/ 3P Agreements 175,364,042

CCH-100 HART/CITY CCH

14,925,228

CCH-101 HART/ City Dept of BFS 0

CCH-102 HART/ City DDC Land Division

173,182

CCH-107 HART/ City Corporation Counsel (COR) 3,088,688

CCH-108 HART / Board of Water Supply (BWS)

928,325

HART-200 HART - Labor 80,149,708

HART-201 HART Expenses & ODCs

36,381,847

OTHER Debt Financing Costs 31,775,028

TOTAL 342,786,047

Source: HART CMS.

Page 78: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

78 | P a g e

5 OVERALL PROJECT-WIDE ACTIVITIES

5.1 Overall Key Issues Overview

Experienced Personnel: Having experienced and qualified personnel from HRH to deal with all challenges between now and Interim Opening is being addressed as a top priority. This includes personnel in management, testing, commissioning, construction, quality and safety certification. HRH has recently brought in a number of subcontractors to help support the team. There are ongoing discussions with their upper management team to provide more technical support.

O&M Documentation: HRH has assigned prime responsibility for documentation development to Horizon Partners Ltd. (HPL). HRH completed a Health, Safety, Quality and Environment (HSQE) workshop in mid-February in collaboration with DTS and agreed on final required edits to conform the HRH documents to the Agency Safety Plan.

O&M Training: A major focus for HRH is to commence formal training classes during the first week of April, and to date this appears to be on schedule.

HRH’s development of the Maintenance Management Information System (MMIS) (Maximo) is critical for Interim Opening. HRH/HPL submitted an over the shoulder (OTS) draft of the MMIS Functional Design Document, Cloud Infrastructure Specifications, and Master Data Definition spreadsheet for review. The MMIS design documents are critical elements for the maintenance service plan (MSP) document development. HRH will hold a follow-up MMIS workshop starting March 3.

Automated Yard Operation: Closure of open design issues of the DBOM Core Systems contract is needed, particularly the communications system design and the integration with the vehicles and automated train control systems. HART has requested a recovery schedule to show how the critical goals missed in February are re-sequenced to meet Interim Opening.

Functional Track Integration Testing is planned to be completed in three phases: (1) ATC/ PSG Integration (without Mobile Data System [MDS] poles) [phase 1 complete], (2) ATC/ PSG Integration (with MDS poles), and (3) final communications after installation of the canopies (KHSG installation slippage will affect final completion). Core Systems is working with the construction team to pull back these delays. All Core Systems-related Fixed Facilities work and Core Systems installation work at Ho‘opili, West Loch and Waipahu stations and the associated guideway must be completed, energized (including LCC), and tested prior to integration testing. HART has requested a recovery schedule to show how the critical goals missed in February are re-sequenced to meet Interim Opening.

AGS integrated schedule: Currently, STG’s schedule for station construction needs more detail for Core Systems to plan installation and testing coordination. The first draft of the schedule shows a delay of turnover dates to the Core Systems Contractor. This would impact Interim Opening #2. Core Systems is working with the construction team to pull back these delays.

Procurement of materials by HRH has been delayed and caused schedule slippage. HRH management is working to add on-site procurement personnel and obtain additional support from headquarters.

Canopy arms are installed at all stations with the exception of Hālawa (Aloha Stadium) Station. Those arms are scheduled for installation in April 2020. Canopy fabric is installed at Kualaka‘i (East Kapolei), Keone‘ae (University of Hawai‘i West O‘ahu), Honouliuli (Ho‘opili) and Hālaulani (Leeward Community College). Pouhala (Waipahu Transit Center) fabric is scheduled for March 2020. Hō‘ae‘ae (West Loch), Waiawa (Pearl Highlands), and Kalauao (Pearlridge) are scheduled for April 2020. Hālawa (Aloha Stadium) fabric is scheduled for May 2020. Coordinating canopy arm and fabric installation with Core systems to lessen the impact on train testing.

HART is dependent on the electrical design prepared by HECO for the electrical power line relocation work that must be performed by HART’s CCUR contractor. The designs for the CCUR contract are not yet completed. HART is continuing to meet at all levels within HECO to complete the required designs for the CCUR contract.

The ability to meet the required CCUR construction access dates as put forth in the P3/DB solicitation is critical. HART is considering bringing a second contractor on board to facilitate construction as this would provide additional resources and means and methods to prosecute the work.

Page 79: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

79 | P a g e

5.2 Permits Permits Submitted and In-Progress

HART submitted the request for an extension of the Stream Channel Alteration Permit (SCAP) to the Department of Land and Natural Resources for work in Kalihi Stream.

HART completed the updated Water Quality and Biological Survey for Kapālama Canal, in support of the Clean Water Act Section 401 and 404 permit applications.

HART received the National Pollutant Discharge Elimination System (NPDES) permit for construction on Kuala Street.

HART received the updated grading permit for Waipahu Transit Center. HART submitted a trenching permit for additional work areas in the City Center section.

Look Ahead

HART will be submitting permit applications for the Kamehameha Highway 138kV activities, once design is 60% complete.

HART will be submitting the SCAP extension for Waiawa Stream and Tributary in the next couple of months.

5.3 Hawai'i Department of Transportation (HDOT) Agreements Activities this Month

HDOT Attorney General is currently reviewing the WOFH Master Agreement and Joint Use and Occupancy Agreement (JUOA) Amendment 1 draft amendments. Completion of review is expected in March 2020.

Ongoing tracking of the progress of the projects for the Highway Improvement Agreement. Coordinating documentation of the highway improvement projects with HDOT and Federal Highway Administration (FHWA) for reimbursement. FHWA is reviewing files for compliance on the solicitation of items that require a waiver to disburse funding for the Highway Improvements.

Look Ahead

Route externally for execution of the West O‘ahu Farrington Highway Master Agreement and Joint Use and Occupancy Agreement Amendment 1. Route to BFS, followed by final legal review, estimated first quarter 2020. Presentation to the Board and City Council to follow, estimated second quarter 2020.

West O‘ahu Farrington Highway Joint Use and Occupancy Agreement Amendment 2 includes maintenance agreements related to guideway related permanent Best Management Practices (BMPs) and traffic signal mounts on the pedestrian bridge at the UHWO Station. Begin DTS coordination in March 2020.

Page 80: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

80 | P a g e

5.4 Utility Agreements

Utility Agreements Status Matrix

Utility Owner Status WOFH KHG Airport City Center

ESA UCA ESA UCA UCA COMBINED ESA UCA

AT&T (Corporation)

Executed 05/11/11 12/20/11 5/18/12

Including with ESA

Not Required

12/26/13 05/03/17 NTP 05/12/11 12/21/11

Amd 01 07/01/11 HRS Ch. 104 11/22/16

AT&T Corp. (Public Sector)

Executed 12/26/13 08/27/18 12/26/13

NTP

Chevron

Executed 12/04/09

11/04/11

NTP 12/22/09 11/15/11

Amd 01 07/01/11

Hawaiian Telcom

Executed 05/20/10 11/17/14 05/10/12 12/31/14 05/28/15 09/27/13 04/06/17

NTP 06/14/10 11/18/14

Amd 01 07/01/11 04/13/15 05/11/17 11/19/18 09/20/19

Amd 02 05/10/12

HECO

Design

Services Construction

Services Design

Services Construction

Services Design

Services Construction

Services Design

Services Construction

Services

Executed 11/20/13 11/29/13 11/20/13 11/29/13 11/20/13

11/25/13

NTP 11/20/13 11/29/13 11/20/13 11/29/13 11/20/13 11/25/13

Executed 05/16/18

Change Order 01

06/30/17 11/13/19 02/22/18

Change Order 02

02/22/18 11/13/19

Mem

ora

nd

um

s o

f

Un

der

stan

din

g

08/07/14 – Construction Drawings

05/01/15 – Access

05/15/15 – Derrick Truck

06/23/15 – Master Agreement

06/09/15 – MSF Advanced Construction

09/16/15 – Right of Entry

10/12/15 – Clearance (West) 11/10/15 – Dillingham Blvd Materials

07/13/16 – KHG Vertical Clearance

Power Quality MOU (Working on MOU)

08/16/18 - Airport Clearance Agreement

05/15/19 – Vehicle Storage MOU

Airport Energization MOU 08/13/19 - Executed

Charter Communications/Oceanic Time Warner Cable

Executed 12/08/09 12/21/11 01/09/12 06/02/14 12/19/14

04/03/13 9/22/16

NTP 12/22/09 04/04/13 9/30/16

Amd 01 07/01/11 02/27/14 HRS Ch. 104 07/06/18 Waiting for final design drawings.

Amd 02 10/07/13 HRS Ch. 104

Pacific Lightnet/ Wavecom

Executed 04/28/10 03/12/12 02/15/12

NTP 04/29/10 03/13/12 02/16/12

Amd 01 07/01/11 HRS Ch. 104

Sandwich Isle Communications

Executed 05/20/10 04/20/12

NTP 06/08/10

Amd 01 07/01/11

Page 81: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

81 | P a g e

Utility Agreements Status Matrix

Utility Owner Status WOFH KHG Airport City Center

ESA UCA ESA UCA UCA COMBINED ESA UCA

Hawai'i GAS

Executed 12/18/09 06/30/11 06/01/12 04/14/14

08/19/14 09/27/13

05/08/15

NTP 12/22/09 07/12/11 08/20/14 05/11/15

Amd 01 07/01/11 10/17/14 08/28/14 08/31/17 10/24/17

Amd 02 05/09/16 10/23/15 11/03/19

Amd 03 HRS Ch. 104

Level 3/TW Telecom

Executed 12/02/09

02/14/12 Oceanic to relocate for TW Telecom

10/11/12 Oceanic to relocate for TW Telecom NTP 12/22/09 02/16/12

Amd 01 07/01/11

Tesoro

Executed

02/15/12 09/12/13

08/27/13

NTP 02/16/12 09/03/13

Amd 01 09/12/14

Amd 02 05/13/15

Amd 03 HRS Ch. 104

Legend = Action this month COR = Corporation Counsel UCA = Utility Construction Agreement

= Not applicable ESA = Engineering Services Agreement

UFRCRA = Combined Engineering and Construction Utility Agreement

Overall Key Issues

No key issues to report this month. HECO

Ka‘aahi Substation near MSF area o Supplemental Agreement – HART sent a letter to HECO on Feb. 24 to formally respond to HECO’s letters

dated Oct. 14, 2019 and Jan. 31, 2020 to reiterate its position that there is no regulatory requirement for a Supplemental Agreement, that the Public Utilities Commission (PUC) established a framework for addressing HECO’s cost recovery risks in the future, that HART worked with HECO to make the substation site available to HECO on July 5, 2019, and to again request for HECO’s determination as to whether the required service date for the substation will change or if the substation is needed at all per HART’s latest power usage projection provided to HECO on Jan. 15.

Mitigation of Horizontal Working Clearance Requirements o KHG 138kV Relocation project: Refer to the Design Services for 138kV Utilities Relocation at KHG contract

page in Section 4.3 for the latest updates. o Specialized Vehicle Storage Yard at MSF: The security fencing is targeted to be complete by the end of

March 2020. In the meantime, HECO has stored two of its older vehicles at the MSF while storing its new specialized vehicles at its own yard.

Page 82: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

82 | P a g e

5.5 Right-of-Way Key Issues ROW is engaging with property owners along the City Center Guideway and Stations (CCGS) Section to acquire the requisite property rights, via Right of Entry and Possession and Use Agreements (ROE/PUA) for Land Court properties pending final Grant of Easement or Deed. When acquisition by purchase is not reasonably available, ROW uses eminent domain to acquire the requisite property interests. HART’s counsel prosecutes its eminent domain actions and the respective motions for immediate possession of the property so that the construction access may be obtained. Current eminent domain actions:

o West O‘ahu/Farrington: Parcel Identification Number (PID) 102 R. Lee: HART has possession of the property, while the

Lees remediate contamination on the parcel. The judge overseeing this case has been serving as a mediator and facilitator, assisting the property owner in completing its obligations under the settlement. The judge holds biweekly status conferences with the parties and has engaged the Hawai‘i Department of Health (HDOH) in facilitating the completion of the remediation of the property. The HDOH has issued one “no further action” letter and there now remain three sections of the property to remediate.

o Airport: HART has possession of the subject property in the four cases filed with the court. For

PID 318 Masters, the parties are closing on a settlement. PID 306 SCI and PID 319 SCI were consolidated and mediation is scheduled for April 2020 and trial in July 2020.

o City Center: Eight cases are filed with the court and are active (PID 400 Blood Bank, PID 472A Desky, PID 439

Yamauchi, PID 485 Scott Shoe, Howard Hughes various parcels, PID 433 HECO Iwilei, PID 502 Yung Soon Tajima Trust, PID 503 JY Trading Co.). HART filed its eminent domain action and motion for order putting HART in possession of PID 433 HECO Iwilei. HECO filed a challenge to HART’s Order of Possession of the property for the HECO Dillingham Avenue property. The parties are completing negotiations to perform a Phase II environmental survey on this property and HECO downtown property on Ala Moana Boulevard. PID 439 Yamauchi executed a settlement agreement and counsel will formally dismiss this case once the Land Court process is completed. Possession has been granted for PID 400 Blood Bank, PID 472A Desky, 485 Scott Shoe, Howard Hughes various parcels, and 503 JY Trading Co.

During the month of May, the FTA conducted a review of the relocation program and the FTA issued a report on Sept. 23, 2019 regarding its findings. The report details measures that must be taken to bring the closed relocation files into compliance, including interviewing the relocated parties. The FTA approved HART’s plan to bring the files into compliance, which was transmitted on Oct. 31, 2019. HART contracted with a team that met with the FTA in January 2020 to discuss the implementation of the plan. The corrective action plan team is now reviewing files and preparing to contact displaced parties.

Regular meetings between the CCUR team, Project Controls and ROW to track progress, identify opportunities and foresee obstacles to access for critically needed parcels are ongoing. Revisions in designs made necessary by guideway and utility redesigns will require revised and new acquisitions along Dillingham and Halekauwila Street, including acquisitions currently in negotiation.

The FTA agreed to the proposed multi-agency approach to the acquisition and tenant relocations for PID 493 Watumull which is the site for the Ala Moana Station. HART has partnered with the City and County of Honolulu’s DTS, Department of Design and Construction (DDC), and BFS to facilitate. Relocation assistance work is underway. An offer is currently being prepared for transmission to the owner.

HART recently entered into agreements with Latter Day Saints (LDS), Otani and General Growth Properties (GGP) Ala Moana to obtain necessary property rights; the properties are currently in escrow.

Page 83: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

83 | P a g e

Relocation assistance is being provided to the tenant and PID 404 Takara. HART is currently negotiating the acquisition with the owner.

ROW continues to monitor negotiations between Design and Construction and HECO regarding issues involving

clearance requirements due to maintenance equipment staging needs for 138kV poles and lines located next to the HART guideway system. These discussions will likely identify additional acquisitions of non-asset easements on behalf of HECO or other utility agencies and/or companies.

Negotiations are continuing with UH, including securing a construction ROE Agreement with the Honolulu

Community College.

Acquisitions Figure 7. Right-of-Way Status for the Parcels

Relocations Figure 8. Relocation Status for the Occupants

Page 84: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

84 | P a g e

Non-Right of Way Figure 9. Temporary Construction Easements and Utility

Status of Inter-Governmental Agreements Figure 10. Inter-Governmental Agreement Status The status of agreements between HART and other government entities. Objectives are:

1) Obtain Construction Right of Entry, Executive Orders, Set Asides, Jurisdiction Transfers, Joint Use Agreements, licenses, easements, Memorandum of Understanding (MOUs), Memorandum of Agreement (MOAs), etc. with impacted government agencies. Government agencies HART is working with include: Federal (GSA, Navy, USPS, Office of Interior), State (HDOT-Hwys & Air, DLNR, DAGS, HCDA, DOE, Aloha Stadium, UH), and County Agencies (DTS, DPP, DFM, BFS, DDC, Parks, DLM, ENV). Some government agencies may choose to issue the final documents after construction is substantially underway or near completion.

2) To help negotiate and/or obtain Rights of Entry for certain other construction-related activities as requested by Design and Construction. Such agreements may include: geotechnical borings, soil testing, environmental surveys, bus stop agreements, construction lay down surveys, and other construction-related needs. There may be other Rights of Entry and Agreements which may not involve ROW acquisition or relocation. ROW will assist other HART departments, should requests be authorized and funded.

3) Agreements to be executed are in white. Executed agreements are in grey at the end of the table, and while these parcels may be accessible at this time for construction, further documentation may also be required to complete the acquisition.

Inter-Governmental Agreements

Agency

Pending Agreements (Executed Agreements

are shaded grey)

Target

Section

Construction Right of Entry

(CROE) Obtained

Notes/Remarks

STATE AGREEMENTS

UH – University of Hawai‘i, West O‘ahu (UHWO-125)

Construction Right of Entry and Occupancy & Use Agreement for East Kapolei Park & Ride

TBD/ Estimate

2021

WOFH Yes Temporary park and ride completed.

3rd Amendment to CROE has been fully executed. It allows for

installation of electrical connections from Road B to

station area and subsequently into interim parking.

Page 85: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

85 | P a g e

Inter-Governmental Agreements

Agency

Pending Agreements (Executed Agreements

are shaded grey)

Target

Section

Construction Right of Entry

(CROE) Obtained

Notes/Remarks

UH – Urban Gardens (201A) Conveyance to HDOT (H) – Dept. of Transportation Highways

May 2020

KHG Yes

2nd Amendment to HART ROE fully executed. Based on final Phase II

results, HDOT has issued concurrence letter. Construction is

nearing completion. Quitclaim deed under review by

HDOT-Highways. Subdivision map completed.

UH – Honolulu Community College (HCC) (424A)

Construction Right of Entry for guideway & station

May 2020

City Center No Pending design finalization. Working with UH regarding ROE

Agreement. Draft ROE Agreement under review by COR. ROE will be broken down into phases starting

with least intrusive activity. Demolition and preliminary

construction activities completed under letter agreement with Royal

Construction.

DLNR – Dept of Land & Natural Resources (124)

Kapolei Easement Agreement for overhead guideway and for park and ride facility

May 2020

WOFH

Yes In process. DPP approved subdivision application.

Transmitted to DLNR for land court submittal. Discussions are

ongoing regarding language permitting guideway easement.

DLNR/C&C Wastewater Div (437B)

Easement Agreement May 2020

City Center In process. DLNR working with DAGS survey group to address

questions regarding final easement map. Ongoing

discussion with DLNR regarding easement agreement terms.

DOE - Waipahu H.S. (118) Permanent Easement (State owned portion)

May 2020

WOFH Yes

In process. Construction is not impacted as the ROE for right to access and construct is executed.

With DOE for review. Working with DLNR for permanent rights.

DOE – Waipahu H.S. (117) Permanent Easement (City portion)

May 2020

WOFH Yes Permanent easement from City in process. DLM has indicated they will delay the transfer of the City portion to the State until HART has permanent entitlements in

place. HART is revisiting this strategy. Construction is not

impacted as the Master/ Construction Agreement is

executed. Working with BFS for permanent rights.

Aloha Stadium / Dept. of Accounting & General Services (DAGS) (207A to C)

Easement Agreement May 2020

KHG Yes In process. Creating maps that are separating the parking area from

the station and guideway easements.

Page 86: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

86 | P a g e

Inter-Governmental Agreements

Agency

Pending Agreements (Executed Agreements

are shaded grey)

Target

Section

Construction Right of Entry

(CROE) Obtained

Notes/Remarks

Aloha Stadium/ DAGS (207B)

Ground Lease Agreement for bus interface and shared parking area

July 2020

KHG Yes In process. Agreement format may impact map approvals from

Stadium Authority, DAGS and DLNR. Construction is not

impacted as the ROE for right to access and construct is executed. Parking area rights will be granted

via long term lease. Relocation clause to accommodate TOD

development.

HDOT(H) – Dept. of Transportation Highways (100,100-A, 304, 400-A, 400-B)

Master Agreement Amendment

March 2020

WOFH Yes Construction is not impacted as the Joint Use & Occupancy (JU&O) Agreement for right to access and

construct is executed.

HDOT(H) and (A) – Dept of Transportation Highways & Airports (100,100-A, 301, 304, 304, 400-A, 400-B)

Master Agreement for KHG, Airport and City Center Amendment

March 2020

KHG, Airport,

City Center

Yes for KHG & Airport

Construction is not impacted as the JU&O for right to access and construct for City Center will be

executed when the Notice to Proceed (NTP) is issued.

HDOT(H) (100,100-A, 304, 400-A, 400-B)

JU&O Sub-agreement March 2020

WOFH Yes In process. Construction is not impacted as the JU&O for right to access and construct is executed.

HDOT(H) (100,100-A, 304, 400-A, 400-B)

JU&O Sub-agreement March 2020

City Center In process. Construction is not impacted as the JU&O will be executed when NTP is issued.

HCDA -HI Community Development Authority (444A, 450,463BE-5-B, 475)

Construction ROE, License Agreement, & Final Disposition

March 2020

City Center Coordination is ongoing. ROE for Royal Contracting pre-

construction activities extended. Final disposition pending revised

design.

DAGS (441-A) Construction Right of Entry July 2020

City Center A street is being designed substantially within the footprint of Easement U as requested by DAGS as a precondition to ROE.

The street will be provided as in-kind consideration for a staging yard for the 3rd party contractor.

Survey for staging area being conducted and street concept plan undergoing refinement.

Utility work descoped; will now be performed by P-3 contractor.

DAGS (441-A) Guideway and Utility Easement Agreement

August 2020

City Center In process. Stakeholder’s meeting the week of Feb. 17-21, 2020. Design plans for Kaaahi Street

extension completed.

DAGS (443-A) Utility, Guideway and TCE Agreement

June 2020

City Center No On-going negotiations with DAGS to secure right of entry.

DAGS (443-B) Utility, Guideway and TCE Agreement

June 2020

City Center No On-going negotiations with DAGS to secure right of entry.

Kalihi Kai Elementary (501) Right of Entry from DOE/DLNR

June 2020

City Center On hold pending design finalization.

Page 87: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

87 | P a g e

Inter-Governmental Agreements

Agency

Pending Agreements (Executed Agreements

are shaded grey)

Target

Section

Construction Right of Entry

(CROE) Obtained

Notes/Remarks

Kalihi Kai Elementary (501) Easement Agreement 2020 City Center On hold pending design finalization. Once ROE is in place, subdivision map to be completed

and submitted to DPP.

State of Hawaii - DOT (504) Easement Agreement Pending City Center HECO amending easement design and under review.

FEDERAL AGREEMENTS

USPS (301) Permanent Easement 2020 Airport Via GOE Construction is not impacted. Grant of Easements were

recorded in Regular System to facilitate entry onto property for

construction even though the property is registered in Land Court. Now petitions for Land

Court designation of easements are being developed for submittal

to Land Court.

U.S. Gov't/General Services Administration (GSA)/Federal Courthouse (443C)

Master Agreement, Security & Landscape License Agreement, Utility License Agreement, Guideway License Agreement

2020 City Center Master Agreement fully executed on 8/13/19.

Waiting for design changes,

propose to relocate guideway support onto GSA property.

GSA Federal Courthouse Quitclaim Easement Documents for Utility and Guideway Easements

2020 City Center Under review.

CITY AGREEMENTS

BFS – Dept. of Budget & Fiscal Svcs (204A)

Intra-Agency coordination which may take the form of a ROE, letter agreement, or license (Continental Investment)

2020 KHG Via intra-agency

coordination

In process.

DFM (423A) Work Permit (Kapalama Stream for Street, Bridge, and Guideway Improvements)

2020 City Center Per BFS, no ROE necessary. Only a work permit will be needed. The

contractor and HART Planning and Construction departments are in

process of obtaining a work permit. Possible adjustments to design are being contemplated

and may change this.

DFM (423A) Easement Agreement for Utilities

2020 City Center Utility agreements on hold pending design finalization. Letter requesting access in draft form for

COR review and approval.

DTS – Dept. of Transportation Svcs (322)

Intra-Agency coordination which may take the form of a ROE, letter agreement, or license (Middle Street Station)

2020 Airport Via intra agency

coordination

In process.

OTHER AGREEMENTS

Page 88: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

88 | P a g e

Inter-Governmental Agreements

Agency

Pending Agreements (Executed Agreements

are shaded grey)

Target

Section

Construction Right of Entry

(CROE) Obtained

Notes/Remarks

D.R. Horton (101B) MOU Construction Right of Entry Amendment – D.R. Horton & HART Easement Agreement – D.R. Horton & HECO

April 2020

WOFH Yes MOU draft circulating for comments. PH I environmental

survey in process. Received comments from D.R. Horton (DRH) counsel on license agreement and

being reviewed by COR.

D.R. Horton Final Easement Agreement July 2020

WOFH Yes Construction is not impacted. D.R. Horton is completing further

subdivision of the property. Maps will be updated with new Tax Map

Key prior to submittal of application to DPP.

EXECUTED AGREEMENTS

CITY AGREEMENTS

BFS (205A) Jurisdictional transfer from DFM to HART of Kamehameha Hwy/Makalapa Manor

Airport Yes Jurisdictional Transfer from BFS Letter dated 8/26/11.

DPR - Dept. of Parks & Recreation (119)

Construction consent to construct for MSF drainage

WOFH Yes

BFS / DFM (Dept. of Facility & Maintenance) (437C)

Jurisdictional Transfer (Awa Triangle, N. Nimitz & Awa St.)

City Center Jurisdictional transfer completed July 9, 2018.

STATE AGREEMENTS

DLNR/C&C Wastewater Div (437B)

Construction Right of Entry

City Center Yes Construction ROE obtained from

DLNR 10/21/17. Subdivision submitted with DPP 1/1/18.

UH – University of Hawai‘i Master Agreement is not needed as the ROE for right to access and construct will be executed separately by each campus.

WOFH, KHG, City

Center

Will be executed by each campus

Construction is not impacted as the ROE for right to access and

construct will be executed by each campus.

UH Pre-Construction Right of Entry and Amendment

WOFH, KHG, City

Center

Yes

UH - West O‘ahu (UHWO) (125)

Construction Right of Entry for Station, Temporary Park & Ride, and Amendment for Construction of Road B

WOFH Yes

UH - Leeward Community College (LCC) (122)

Construction Right of Entry for Guideway

WOFH Yes

UH – LCC (122) Construction Right of Entry for Station

WOFH Yes

UH - Urban Gardens (201A)

Construction Right of Entry KHG Yes

DLNR – Dept. of Land and Natural Resources (124)

Kapolei Construction Right of Entry for overhead guideway and for park and ride facility

WOFH Yes CROE has been granted once a year by letter. Working on

permanent Easement with DLNR. Currently with DPP for

subdivision.

Page 89: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

89 | P a g e

Inter-Governmental Agreements

Agency

Pending Agreements (Executed Agreements

are shaded grey)

Target

Section

Construction Right of Entry

(CROE) Obtained

Notes/Remarks

DLNR (320) Keehi Lagoon Construction Right of Entry

Airport Yes

DOE – Dept. of Education Waipahu H.S. (117, 118)

Master/Construction Agreement

WOFH Yes

DOE/DLNR for Waipahu H.S. (118)

Construction Right of Entry WOFH Yes Executed by DLNR with DOE concurrence.

Aloha Stadium / Dept of Accounting & General Services (DAGS) (207)

MOU for guideway & station KHG Yes

Aloha Stadium/DAGS Construction Right of Entry for guideway

KHG Yes

Aloha Stadium/DAGS Construction Right of Entry for station park and ride

KHG Yes

HDOT(H) – Dept. of Transportation Highways (100)

Master Agreement for HDOT Highways for WOFH

WOFH Yes

HDOT(H) and (A) – Dept. of Transportation Highways & Airports

Master Agreement for HDOT Highways and Airports, for KHG, Airport and City Center Sections

KHG, Airport,

City Center

Yes except for City Center

whose JU&O will be

executed when the NTP

is issued

HDOT(H) JU&O Sub-agreement WOFH Yes

HDOT(H) JU&O Sub-agreement KHG Yes

HDOT(H) JU&O Sub-agreement Airport Yes

HDOT (A) - Dept. of Transportation Airports

Airport Special Provisions for Right of Entry

Airport Yes

HDOT(A) JU&O Sub-agreement for Airport Division parcels

Airport Yes

HDOT(A) (301A) Easement document for Airport Division parcel (Main guideway easement)

Airport Yes Ongoing intra-agency coordination. Construction is not

impacted as the Special Provisions and the JU&O for right to access

and construct is executed.

DHHL - Dept. of Hawaiian Home Lands (Exchange w/ Varona Village) (115A)

MOA, License/ROE from DHHL, City Council Resolution

WOFH, MSF Yes DLNR approves withdraw from GEO 571 7/14/17. DFM accepts

road widening and now City jurisdiction.

OCCC - Dept. of Public Safety, Oahu Community Correctional Center (400A)

MOU

City Center Yes

OCCC/DLNR Construction Right of Entry

City Center Yes

DLNR/OCCC Letter of Responsibility from City-DFM/Road

City Center Yes

HCDA -HI Community Development Authority (444A, 450, 463B, E-5-B, 475)

Pre-construction Right of Entry

City Center Yes, effective upon request

Verbal approval granted by the HCDA Board in 6/2016.

Page 90: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

90 | P a g e

Inter-Governmental Agreements

Agency

Pending Agreements (Executed Agreements

are shaded grey)

Target

Section

Construction Right of Entry

(CROE) Obtained

Notes/Remarks

FEDERAL AGREEMENTS

U.S. Navy (116A) Grant of Easements for Maintenance & Storage Facility (MSF)/Rail Operations Center (ROC) offsite drainage and sewer easements

WOFH Yes Per Letter #N62478-12-RP00011 dated 6/28/12 confirming

easement from Navy.

U.S. Navy (300) Licenses/Construction Right of Entry

WOFH, KHG,

Airport

Yes 6/22/15 – 5 Yrs. License ends in 2020. All utility work needs to be

completed by then.

U.S. Navy Easement Agreements WOFH, KHG,

Airport

Yes Grant of Easement executed. Grant of Easement 8/22/16.

U.S. Navy Pearl Harbor Station Acquisition of Fee Transfer

Airport Yes Quitclaim deed executed 2/25/16.

U.S. Post Office (USPS) (301)

Honolulu Processing Center acquisition

Airport Yes Acquisition completed in regular system. Need to process through Land Court to complete process. Funds already paid. USPS Land

Court share to complete process is in escrow.

OTHER AGREEMENTS

D.R. Horton Construction Right of Entry - D.R. Horton & HECO

WOFH Yes Executed 5/11/2018.

Page 91: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

91 | P a g e

6 MANAGEMENT AND ADMINISTRATIVE UPDATES

6.1 Safety and Security (S&S) Key Milestone Progress HART Safety has been working with the Core Systems Oversight Consultant (CSOC) to oversee HRH preparation for

MSF Attended Operations in the yard and the Functional Track Section. o HRH requirements for the Attended Operations Milestone are expected to be complete in April 2020.

HART Safety has been holding monthly certification meetings with each station group project team to close out safety and security critical Open Items in preparation for substantial completion.

HART Safety is working with Project Controls to ensure that Safety and Security Certification Milestones and related activities are identified and updated on the Master Project Schedule.

Key Issues Scheduled certification milestones for Segment 1 may be delayed due to the following open requirements:

MSF Attended Operations Milestone (Hold Point) o HRH to complete open items in regards to ATC, COMM, SIT and SCADA.

Specification Testing Conformance Checklists (STCC) Open Items (59)

ATC – 8 Open out of 21

Communications – 36 Open out of 38

System Integration & Testing – 9 Open out of 22

SCADA – 6 Open out of 14 o HRH to complete 8 open items in regards to Operational Readiness o HRH to complete 26 STCC open items for PVs fleet design verification and individual certifications. o MSF Yard Control Bungalow (YCB) civil contract certification

Critical items verified. Visual verification of non-critical items completed; Pending Safety and Security Review

Committee (SSRC) acceptance in March 2020 o MSF YCB Systems Contract Certification (5 STCC Open Items)

Inspection and Test Procedures for MSF YCB Communication Inspection and Test Report for MSF YCB Communication On-site Inspection and Test Report for MSF YCB Fire Detection Alarm System (FDAS) On-site Inspection and Test Report for MSF YCB Uninterruptible Power Supply (UPS) Panel Distribution Unit Low Voltage (LV) Schematic Drawing for MSF YCB UPS

o Maintenance of Way vehicles certification – pending approved specification testing documentation for vehicle acceptance.

STCC open items (3):

Multiple Purpose Vehicle (MPV) (HNL-23015 Accepted as Noted –Resubmit [ANR]: O&M Manual) – Due first quarter 2020

Grinder (HNL-23043 ANR: O&M Manual) – Due first quarter 2020

Enclosed Trailer (HNL-23105 ANR: O&M Manual) – Due first quarter 2020

Page 92: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

92 | P a g e

6.1.1 Project Overall Certification Status

Project Overall Certification Status - Progress

Total Items

Total Verified 1/1/20

Total Verified 2/29/20

Total Remaining

Δ YTD %

Complete % Remaining

Segment 1 Revenue Service 23,772 20,095 20,457 3,315 362 86% 14%

Segment 2 Revenue Service 10,037 4,951 4,989 5,048 38 50% 50%

Segment 3 Revenue Service 7,652 4 4 7,648 0 0% 100%

Final Overall 41,461 25,050 25,450 16,011 400 62% 38%

6.1.2 Segment 1 Revenue Service Date Certification Status

Segment 1 Certification Status - Progress

Anticipated Completion

Total Items

Total Verified 1/1/20

Total Verified 2/29/20

Total Remainin

g

Δ YTD

% Complet

e

MSF (Civil & Systems) MAY 2020 740 725 725 15 0 98%

Guideway (Civil & Systems) CLOSED 7,368 7,368 7,368 0 - 100%

Stations & Parking (Civil & Systems) MAY 2020 7,221 6,884 7,008 213 124 97%

Passenger Vehicles (8-13) and Fleet Req’s NOV 2020 1,400 519 746 654 227 53%

MOW Vehicles MAR 2020 458 454 455 3 1 99%

Traction Electrification System (TES) APR 2020 270 204 207 63 3 77%

Automatic Train Control (ATC) JUN 2020 346 301 301 45 0 87%

Supervisory Control and Data Acquisition (SCADA) JUN 2020

84 56 56 28 0 67%

Communication JUN 2020 983 676 677 306 1 69%

System Integration Testing (SIT) AUG 2020 138 71 71 67 0 51%

Platform Screen Gate System (PSGS) JUN 2020 96 66 67 29 1 70%

Elevators / Escalators AUG 2020 508 295 295 213 0 58%

Fare Collection System AUG 2020 78 28 28 50 0 36%

Art in Transit AUG 2020 168 14 14 154 0 8%

Operational Readiness NOV 2020 756 123 123 633 0 16%

Risk Management NOV 2020 3,158 2,311 2,316 842 5 73%

23,772 20,095 20,457 3,315 362

Page 93: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

93 | P a g e

6.1.3 Segment 2 Revenue Service Date Certification Status

Segment 2 Certification Status - Progress Total Items Total

Verified 1/1/20

Total Verified 2/29/20

Total Remaining

Δ YTD

% Complete

Guideway (Civil & Systems) 3,021 1624 1,649 1,372 25 55%

Stations & Parking (Civil & Systems) 1,990 1525 1,525 465 0 77%

Passenger Vehicles (1-7 & 14-20) 2,354 676 684 1,670 8 29%

Traction Electrification System (TES) 54 4 4 50 0 7%

Automatic Train Control (ATC) 29 12 12 17 0 41%

Supervisory Control and Data Acquisition (SCADA)

47 8 8 39 0 17%

Communication 32 0 0 32 0 0%

Platform Screen Gate System (PSGS) 8 0 0 8 0 0%

System Integration Testing (SIT) 44 0 0 44 0 0%

Elevators / Escalators 33 0 0 33 0 0%

Fare Collection System 50 0 0 50 0 0%

Art in Transit 63 0 0 63 0 0%

Operational Readiness 555 0 0 555 0 0%

Risk Management 1,757 1,102 1,107 650 5 63%

10,037 4,951 4,989 5,048 38 6.1.4 Segment 3 Revenue Service Date Certification Status

Segment 3 Certification Status - Progress Total Items

Total Verified 1/1/20

Total Verified 2/29/20

Total Remaining

Δ YTD %

Complete

Guideway (Civil & Systems) 1,772 0 0 1,772 0 0%

Stations & Parking (Civil & Systems) 4,908 0 0 4,908 0 0%

Traction Electrification System (TES) 39 4 4 35 0 10%

Automatic Train Control (ATC) 29 0 0 29 0 0%

Supervisory Control and Data Acquisition (SCADA) 47 0 0 47 0 0%

Communication 47 0 0 47 0 0%

Platform Screen Gate System (PSGS) 16 0 0 16 0 0%

System Integration Testing (SIT) 44 0 0 44 0 0%

Elevators / Escalators 33 0 0 33 0 0%

Fare Collection System 50 0 0 50 0 0%

Art in Transit 112 0 0 112 0 0%

Operational Readiness 555 0 0 555 0 0%

Risk Management 0 0 0 0 0 0%

7,652 4 4 7,648 0

Page 94: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

94 | P a g e

6.1.5 Construction Safety and Security: Safety and Security Incidents Incidents for Feb. 1-29, 2020:

Recordable Safety Incidents (Medical Treatment/Lost Time): o None.

Security Incidents (Thefts/Arrests): o None.

Note: The 2014, 2015 and 2017 National incident rate and the 2016 Hawaii incident rate for the North American Industry Classification System (NAICS) 237 (for heavy and civil engineering construction) have been corrected.

Page 95: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

95 | P a g e

6.2 Quality Management Key Issues

HART NCR Log

Total NCRs Issued To Date Closed Open

100 (Audits) 97 3

2 (Construction) 1 1 Note: HART Issued NCRs for Construction are shown on each respective contract.

Resolution of major NCRs that need to be addressed and corrected to prevent recurrence, and to mitigate impact on the overall progress of the project. The major NCRs are described below: o Retrofit of Eight (8) Car Shells under frame to rectify aluminum extrusion defects continues. Retrofit of car shell

underframe to rectify aluminum extrusion defects continues in Italy. Five (5) out of six (6) retrofitted car shells have been received in Pittsburg, CA. HRI opted out to manufacture two (2) new Carbody for Train #1 and Train #2. Therefore, the defective two (2) Carbody will be scrapped.

o Cracks in Canopy Structural Steel Members. Cracks on the Canopy Structural Steel members were found in the WOSG and FHSG station groups. HART is in the process of finding the “root cause” of the defects, the disposition, and appropriate corrective action to prevent recurrence. All lower portions of the canopy arms (grade 100 steel) will be replaced at WOSG, FHSG and KHSG. Please see Section 5.1 Overall Key Issues, for the latest status on the canopies.

o Train #12. End Car 1 of Train #12 was damaged (about 2.0 ft. long x ¾ in. wide x ¼ in. deep gouge on the left side, which did not penetrate the aluminum extrusion skin, and about ½ in. diameter penetration in the first set of the Door Panel on the right side of End Car 1) during transit from Pittsburg, CA to Honolulu, HI. HRI determined that cosmetic repairs will be required. A qualified and certified surface finisher repair crew is scheduled to be in Honolulu to fix the damage using an approved repair procedure once it is available.

o KHSG Platforms. The platforms of the PHL, PLR and ALS will require shaving to attain dynamic clearances required by the train. The work is scheduled to be completed by the end of March 2020.

Audit Look Ahead Prepared and issued (Revision 1) the Project Combined Management Systems Audit Schedule for 2020 to HART and all

contractors, consultants and suppliers. Planning for the audits to be performed in March 2020: Audit No. 20-002 AGS (Surveying) – Quality Assurance (QA)

Audit of STG on March 5-6, 2020 and Audit No. 20-003 AGS (Casting Facility) Combined QA, Buy America (BA) and Environmental Compliance (EC) Audit of STG on March 26-27, 2020.

Performed Audit No. 20-001 AGS (Construction) Combined QA, BA and EC Audit of STG on Feb. 27-28, 2020. The Audit Team found eight (8) Positive Findings (5-QA/3-EC), seven (7) Observations (4-QA/3-EC), and five (5) EC Suggestions.

Performed Audit No. 20-016 Internal QA Audit of HART 5.CA-11 Contract Changes Procedure. The Audit Team found three (3) Positive Findings, three (3) Observations and two (2) Suggestions.

Issued Audit Report on Audit No. 19-018 CEI (West) to PGH Wong on Jan. 14, 2020. The Audit Team found two (2) Positive Findings and three (3) Observations (2-QA/1-EC).

Issued Audit Report on Audit No. 19-019 HART Combined QA, Safety and Security (S&S) and EC Internal Audit of HART on Jan. 17. 2020. The Audit Team found: three (3) Positives, three (3) NCRs, nine (9) Observations, and three (3)

Suggestions on QA; two (2) Observations, and two (2) Suggestions on S&S; and one (1) Positive on EC. Oversight and Monitoring Attended and participated in Pre-activity meetings, Inspections and Testing on the project

o FHSG: Best Management Practice (BMP)/Environmental Inspections, LCC Walkthrough. o KHSG: VRF A/C System Testing, BMP/Environmental Inspection, Energized Switchboards. o WOSG: Manual Transfer Switch, BMP/Environmental Inspections. o AGS: BMP/Environmental Inspections. o CSC: PV Shoe Collection and 3rd Rail Testing. o CCUR: Tree Repurposing, BMP/Environmental Inspection.

Prepared and issued Project NCRs Trend Analysis from July 2019 to February 2020 (Revision 49). The trend for this month: Trains: went up 13 from 12 to25; Core System: went up 2 from zero to 2; Fixed Facilities: went up three (3) from 18 to 21. The trend is relatively flat in the last eight (8) months. See the next page for the Project NCRs Trend Analysis.

Page 96: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

96 | P a g e

Page 97: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

97 | P a g e

6.3 Buy America Compliance (49 CFR 661 and 49 CFR 663) Overview and Key Issues

HRH continues to execute the corrective action plan to meet the PV Buy America requirements. The implementation of all required corrective action identified in the Post-Delivery Report has not yet been completed on all previously delivered trains. The CSC will be updating the monthly Buy America compliance report with the Buy America retrofit status of each train to demonstrate compliance with the Corrective Action Plan. An Interim Opening (I/O) documentation audit for the compliance of the I/O fleet will need to be conducted when the last train for I/O #1 is delivered and commissioned, then a final Buy America (BA) report must be issued for full opening.

Train # Anticipated Date for BA Compliance

Open Issues

1 TBD Carshell structural retrofit, fire resistivity retrofit, and BA retrofit.

2 TBD Carshell structural retrofit, fire resistivity retrofit, and BA retrofit.

3 TBD Interior panels in M-Cars requires replacement for BA compliance.

4 TBD Requires M-car interior panel and Auxiliary Power Supply (APS) retrofit in accordance with BA Corrective Action Plan.

5 Completed Requires fire resistivity retrofit.

6 Completed Requires fire resistivity retrofit.

7 December 2020 Requires fire resistivity retrofit.

8 (I/O Fleet) Completed No issue.

9 (I/O Fleet) Completed No issue and delivered to MSF on Feb. 14, 2020.

10 (I/O Fleet) Completed No issue and delivered to MSF on Dec. 9, 2019.

11 (I/O Fleet) Completed No issue and delivered to MSF on Jan. 9, 2020.

12 (I/O Fleet) Completed No issue and delivered to MSF on Oct. 26, 2019.

13 (I/O Fleet) April 2020 Manufacturing activities ongoing.

14 December 2020 Manufacturing activities ongoing.

15 December 2020 Manufacturing activities ongoing.

16 December 2020 Manufacturing activities ongoing.

17 December 2020 Manufacturing activities ongoing.

18 December 2020 Manufacturing activities ongoing.

19 TBD Manufacturing activities ongoing.

20 TBD Manufacturing activities ongoing.

6.4 Disadvantaged Business Enterprise (DBE) Activities this Month

$145,434,352 = total dollar participation for all DBEs on all HART contracts from 9/24/07 to 2/29/20 o 18.03% = DBE utilization on total disbursed FTA funds received to date ($145,434,352 divided by

$806,258,734) o 8.25% = DBE utilization to date on total Project FTA funds ($145,434,352 divided by $1,763,903,901) o 9.38% = DBE utilization to date on 5309 Project FTA funds ($145,434,352 divided by $1,550,000,000)

6.5 Art-in-Transit (AIT) Program The Honolulu Rail Transit Project's December 2012 FFGA grant (Sitework and Special Conditions) includes a public art program. In addition, the Revised Ordinances of Honolulu (ROH) Section 3-2.7, "Art in City Buildings," provides for the inclusion of art in city-owned buildings frequented by the public. For the rail project, the AIT staff negotiates and manages contracts for the west-side stations and AGS. AIT contracts are managed in five NTP phases:

NTP1 - Conceptual design NTP2 - Design development, final design, and construction documents

Page 98: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

98 | P a g e

NTP3 - Mobilization NTP4 - Fabrication, transportation, and installation NTP5 - Final acceptance

Conceptual and final designs are presented to the Mayor's Commission on Culture and the Arts for review and comment. The Transit Art Committee (TAC) evaluates and makes the final recommendation and approval.

Station / Facility Name Artist Name NTP Phase Comments

East Kapolei Station Robert Flint NTP3

The artist completed all required technical documentation and Material Safety Data Sheet (MSDS) information for Safety & Security Design Criteria Conformance Checklist (DCCC) review. Waiting for Safety & Security DCCC review and approval. Waiting for the station contractor to implement changes to the art wall for final dimensions and finishes to commence fabrication of ceramic mural.

University of Hawai‘i West O‘ahu Station

Satoru Abe NTP3

Assisting the artist with DCCC submittal documents. Received the fabricatorʻs full-scale mock up for Safety and Security Certification DCCC review and approval.

Ho‘opili Station Karen Lucas NTP3

Working with the fabricator and artist on high resolution digital scaled maquette to refine color selections and to create custom colored glass tesserae to accurately replicate the details of the original drawings. Waiting for temporary holding tank system to be installed to drain water from art locations so algae can be cleaned and dimensions and directional placement of artworks can be verified before fabrication.

West Loch Station Hans Ladislaus NTP3

Working with the artist on required technical documentation and MSDS information for Safety & Security Design Criteria Conformance Checklist review. The artist needs to provide scaled depth and texture studies. Station contractor to implement changes to art wall.

Waipahu Transit Center Station

John Koga NTP1 The TAC reviewed conceptual design submittal #5; revisions recommended.

Rail Operations Center – Operations & Servicing Building

Shigeru Miyamoto

NTP3

Working with the artist on required technical documentation and MSDS information for Safety & Security Design Criteria Conformance Checklist review. The artist needs to submit color samples during NTP3 and NTP4.

Leeward Community College

Donald Lipski NTP3

The artists fabrication team submitted engineered shop drawings and MSDS for Safety & Security DCCC review and approval. Verification of “as builts” of hanging brackets for art installation completed.

Pearlridge Station Robert Kushner NTP4

The artist is working with the fabricator on the production of two 7’x 20’ glass and stone mosaic murals. Awaiting the station contractorʻs implementation of changes to art wall and paving area to integrate artwork.

Aloha Stadium Station Jay Wilson NTP1 Revising conceptual design.

Pearl Harbor Naval Base Station

Carol Bennett NTP2 Conceptual design accepted, moved to NTP2.

Page 99: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

99 | P a g e

Station / Facility Name Artist Name NTP Phase Comments

Honolulu International Airport Station

Mamoru Sato NTP1

The artist submitted revised conceptual designs for the Mauka and Makai artworks. Design work is pending refinement of mullion system used for artwork installation.

Lagoon Drive Station Carol Yotsuda NTP1 Revising conceptual design.

6.6 Planning and Environment Activities this Month

Environmental Compliance o Environmental Due Diligence: Staff completed two Phase I Environmental Site Assessments in preparation

of acquisitions. Staff responded to the Department of Health (DOH) comments for remediation at the Iwilei Station. Staff finalized the Phase II Work Plan for the Civic Center. Staff submitted two site investigation reports for the airport area and submitted a site specific Environmental Hazard Evaluation and Environmental Hazard Management Plan for the airport station. Remediation of the Lee Property, near Pearl Highlands Transit Center, has restarted.

Project Mitigation Commitments o Historic Resource Documentation: The pre-draft Historic American Buildings Survey (HABS) documentation

for Chinatown and the pre-draft of the Chinatown Historic District National Register (NR) Update are still under review. Additional peer review comments were received for chapter 7 of the pre-draft of the Historic Context Studies (HHM) and additional comments are in preparation for the remaining two chapters. Staff are reviewing the pre-draft National Register of Historic Places (NRHP) nominations for Holau Market and Wo Fat Chop Sui House. Staff completed comment review matrices for the Dillingham Transportation Building and the Wo Fat Chop Sui House. Work continued on the Historic Preservation Certification Application (HPCA) Part II for the latter building as well. Draft nominations for Waimalu Stream, Kalauao Springs and Kalauao Stream Bridges as well as Nu‘uanu Stream (Queen Street) Bridge, O'ahu Rail & Land Co. Terminal Building, and Wood Tenement Buildings will be finalized for submittal to the State Historic Preservation Division (SHPD) on March 6, 2020 for public hearing by the Hawai‘i Historic Places Review Board on July 30, 2020.

o Cultural Landscape Reports: Helber Hastert & Fee completed responses for the Mother Waldron Park and Playground Cultural Landscape Report (CLR) and transmitted them to HART staff to add comments. Responses for Walker Park CLR are still in preparation.

o Historic Preservation Fund: Staff began planning efforts for the public meetings for round 2 of the Historic Preservation Fund, including potential topics and speakers.

o Interpretive and Educational Materials: Staff are reviewing comments on the prototype Stipulation VII educational materials and are working to finalize the comment response matrix.

o Reporting: Staff finalized the 2019 Quarter 4 Mitigation Monitoring Program report and submitted it to the required agencies.

o Section 106 Programmatic Agreement: The FTA Annual Programmatic Agreement (PA) meeting is scheduled for March 10, 2020, and FTA plans to be in attendance. HART staff finalized the packet of pre-meeting materials and provided it to the Consulting Parties. The January PA report is in final review and will be submitted to the Consulting Parties upon completion.

Sustainable Mobility o Sustainability: At the Hālaulani train day on Feb. 8, staff collaborated with the Hawaii Bicycling League and

Malama Pu‘uloa on a sustainability display related to a placemaking project around the Pearl Harbor Historic Trail. Staff followed up with site visits and additional project planning with Waipahu High School students and HI SOUP. Staff also leveraged some of the design work from the Ka Maka Inana field guide to engage the community on train day. The intent of the project is to install placemaking interventions on the Pearl Harbor Historic Trail that will connect to Hālaulani Station and other multimodal facilities.

Page 100: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

100 | P a g e

o Transportation Planning: Staff continued to work with University of Hawai‘i Engineering faculty on autonomous vehicle related research. Staff supplied a letter of support and commitment of in-kind match to resource a research project modeling elements of first and last mile connections to rail stations and new and emerging mobility services. This work is related to an existing project to model the long-term impacts of shared autonomous vehicle (SAV) deployments and other new mobility technology. The intent is to use the regional Travel Demand Forecasting Model (TDFM) to test several technology deployment scenarios for first/last mile connections and the respective impacts on rail ridership.

Look Ahead

Preparation of Post-Record of Decision (ROD) and other environmental documentation: o Intelligent Transportation Systems (ITS): SHPD continues to review documentation for an amendment of the

Project Area of Potential Effect (APE) to cover ITS work. o East Kapolei Park-and-Ride Lot: Staff continue to prepare documentation for the relocation and

reconfiguration of the 900-stall park-and-ride lot at the Kualaka‘i (East Kapolei) Station. o City Center/Pearl Highlands: Any project final design refinements or new right-of-way takes will be assessed

and submitted to the FTA, as appropriate. o Kamehameha 138kV Relocation: Overhead 138kV lines are to be relocated between the Waiau Power Plant

and Aloha Stadium in order to provide the required working clearances around the guideway. Analysis is pending development of the preliminary design drawings.

6.7 Risk Management Following is a progress report highlighting top risks and mitigation efforts from the February 2020 monthly risk update.

6.7.1 Top Risk Summary

Top Cost Risks

ROW

CCUR: difficult underground conditions

AGS TIA for HECO Zone 8 Delay

Core Systems (until assigned to P3)

Affordability Cap being exceeded

Environmental, due to Risk Transfers to HART

Delay in obtaining City Agency permitting

Utilities: misidentified and unidentified

ROW: Mauka entrance to Downtown Station

Possible revocation of noise variance

ROW: Makai entrance to Downtown Station

Utility/Pedestrian bridges over stream (risk should be transferred to budget)

P3 and CCUR interface impacts

CCUR Access Dates if not met for P3

CCUR non-standard work hours

Core Systems, incomplete interface details

ROW – numerous small property acquisitions for straddle bent foundations

Fare Collection Systems: delay if station electrical systems not ready (applies to interim RSD)

Archaeological: unanticipated finds could delay CCGS work

See additional low risks highlighted in green in the table below

Opportunities for Cost Savings

P3 competitiveness, innovation for CCGS

CCUR to eliminate unnecessary utility relocations with guideway shift

Top Schedule Risks: Critical Path

CCUR: difficult underground conditions

Affordability Cap being exceeded (time to resolve)

Environmental, due to Risk Transfers to HART

Possible Revocation of Noise Variance

Utilities: misidentified and unidentified

P3 and CCUR interface impacts

CCUR Access Dates if not met for P3

Core Systems, incomplete interface details

ROW – numerous small property acquisitions for straddle bent foundations (currently not critical, but could become critical if delays occur)

Archaeological: unanticipated finds could delay CCGS work

Opportunities for Maintaining Schedule

CCUR opportunity to save time by eliminating unnecessary utility relocations, particularly the 42” water main along Dillingham

Aggressive CEI oversight of CCUR with fully qualified field staff

Page 101: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

101 | P a g e

Watch List Risks

Coronavirus Concerns. No risk impacts noted in the February 2020 report. Will status with project teams and HART management in the March 2020 risk update, considering project schedule, contingency, project funding.

Opportunities for Maintaining Schedule (continued)

ROW to maintain schedule for new acquisitions based on final CCGS alignment, through appropriate staff and consultant support

Maintain P3 Procurement schedule, through filling vacant staff positions and with existing staff and consultant support

6.7.2 Top Risk Threats and Mitigations

Risk ID Risk Description Risk Threat Score

Risk Mitigation

ROW 60.01_01

ROW: Value of property acquisitions necessary for Rail could increase.

18 1. HART continues to negotiate in good faith with property owners. 2. Appraisals and due diligence through the courts have been supporting HART’s position in obtaining necessary ROW at a reasonable cost.

DBB511 SIT 40.02_02

CCUR: Cost to deal with underground conditions could exceed contract allowances.

18 1. CCUR team continues to explore the most cost-effective ways of dealing with the geotechnical conditions along Dillingham.

DB450 SIT 40.02_11

AGS: HECO Zone 8 Delay. 15 HART is evaluating the Time Impact Analysis (TIA) for concurrent delays.

DBOM920 SYS 50.01_12

Core Systems: Risk of additional work by Core Systems Contractor following recent settlement, until assigned to P3.

12 1. HART is troubleshooting systems interface issues with West stations work to avoid further cost due to changed conditions. 2. Plan for 2-phase testing at platforms has allowed more time for canopy arm installation, followed by Core Systems devices and testing.

P3-DB550 PRO 80.01_07

P3 for CCGS and PH: Risk of Affordability Cap being exceeded for the capital construction and/or the future O&M.

12 1. The Affordability Cap for Capital as well as O&M were provided to the P3 PLO(s) on 26JUL2019 in order to allow HART sufficient time to respond in case concerns are expressed by the PLO(s). 2. HART’s ICE estimate was reviewed and received concurrence from E&Y and from HART’s Project Execution Consultant.

P3-DB550 SIT 40.03_03 (schedule) and 40.03_02 (cost)

P3 for CCGS and PH: Environmental Cleanup, Cost and Schedule Impacts to HART (2 separate risks, but combined here for scoring). The Risk Management System (RMS) adjusted the cost portion of this risk slightly downward based on the expectation that CCUR work will uncover most, if not all, pockets of contamination. The P3 RFP has been modified to place HART at risk of paying for environmental cleanup.

12 1. Although HART would be responsible for the cost and schedule impact for cleanup of undisclosed contamination, the P3 would be responsible for the schedule risk associated with the cleanup of disclosed contamination. Some cleanup activities could be non-critical path delays depending upon where they occur in the project. 2. HART will handle the cleanup with on-call contractors familiar with this work and who can execute the work most efficiently.

DBB511 SIT 40.08_01

CCUR: Delay in obtaining City Agency Permitting had been forecast and continues to result in delays to critical utility relocation work.

12 HART continues to coordinate with City permitting agencies to provide any further design information that is needed, and to reduce the timeframes for review and permitting of utility relocation work.

DBB511 SIT 40.02_07

CCUR: Scope and schedule of construction could be impacted by the discovery of misidentified and unidentified Utilities

12 HART will pay for differences in quantities of utility relocations based on as-bid unit rates.

ROW 60.01_17

ROW: Parcel Scope changes for Mauka Entrance to Downtown Station

12 HART and DTS are evaluating the preferred Mauka station entrance location for the downtown station. The preferred location is within the courtyard of the existing Pacific Guardian Center (PGC). Initial discussions with the Property Manager have taken place.

Page 102: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

102 | P a g e

Risk ID Risk Description Risk Threat Score

Risk Mitigation

P3-DB550 SIT 40.04_09

P3 for CCGS and PH: Revocation of Noise Variance which allows night and weekend work. This could have a cost and schedule impact to the CCGS project. This is a new risk added in the Feb. 2020 Risk Refresh.

9 HART will pursue greater involvement with the community to inform them of construction activities and be more responsive to their concerns. HART can mitigate by compensating the contractor to utilize noise mitigation strategies and by maintaining open communication with DOH who controls the noise variance.

ROW 60.01_10

ROW: HECO Downtown Makai Parcel Scope Changes. Late agreement with HECO for Downtown makai parcel, currently an old power plant, could impact DB contract requirements.

9 Get agreement with HECO and perform early subsurface investigations. Include report in bid documents.

DBB511 SIT 40.06_01

CCUR: Design Build of utility & pedestrian bridges over Kapalama Stream.

9 The alternative to use utility and pedestrian bridges has been reviewed and is believed to be the appropriate solution meeting utility company and environmental requirements. Some portion of this risk may be in the base CCUR cost which will be reviewed in the March 2020 Risk update.

P3-DB550 SYS 50.03_01

P3 for CCGS and PH: Interface impacts between CCGS and other contracts including CCUR and Core Systems Contractor.

9 While this risk value increased in the November 2019 Risk Refresh, HART is working to make sure CCUR work is completed as expeditiously as possible, and that achievable access dates to the P3 (area by area in the CCGS corridor) are included in the P3 RFP.

P3-DB550 SIT 40.05_02

P3 for CCGS and PH: Potential for CCUR work to extend beyond Access Dates committed to the P3 for CCGS. If committed access dates are not met, then the P3's start of work in those areas could potentially be delayed, placing HART at risk of having to compensate the P3 for owner-caused delay.

9 The P3 Procurement Documents include a list of Access Dates that HART is committing to meet. This risk pertains to HART's guarantee to the P3 that CCUR work will be completed by certain committed dates area by area through the CCGS project.

DBB511 SIT 40.08_07

CCUR: Requirement for Non-standard Work Hours on CCUR work.

9 HART will work with the contractor and approving agencies to mitigate the extent of non-standard work hours potentially being required on the project, which can increase contract costs significantly.

DBOM920 SYS 50.01_01

Core Systems: Incomplete Interface Details (Stations & Guideway).

9 Final interface details are being worked out as West Stations progress much closer to final completion.

ROW 60.01_19

ROW: Cost and time impacts for numerous small property acquisitions necessary for foundations to support straddle bents along Dillingham Blvd and elsewhere.

9 HART Management has begun meetings with affected property owners to advise of the need for straddle bent foundations at specific locations and to attempt to minimize the impacts to the property owners and to seek their cooperation with HART's plan.

MI900 SYS 50.06_11

Fare Collection: Rail Station installation of Fare Systems equipment could be delayed if Stations’ electrical systems are not ready in time for Revenue Service.

9 Coordinate with station contractors to develop and share station as-builts with the Fare System Vendor. Coordinate schedules as well to allow sufficient time for testing and installation at each of the stations.

P3-DB550 GUI 10.04_01

P3 for CCGS and PH: Discovery of unanticipated archaeological findings could result in added cost and schedule impact to HART.

8 The HART Procurement and technical team for the P3 has been working on an appropriate level of risk for the P3 to undertake in dealing appropriately with archaeological finds. HART will be responsible for finds that cause undue cost and schedule delay.

DBOM920 SIT 40.04_01

Core Systems: Operating Noise Exceeds Environmental Impact Statement (EIS) Defined Limits.

6 Tangent track noise test compliant with Technical Provision (TP) requirements. Noise testing in curves still required. Evaluation against EIS noise levels outstanding. Mitigation may require installation of track lubricators along the alignment, implementation of a rail engineer grinding program, and/or noise absorption panels.

ROW 60.01_18

ROW: Net cost to HART for Land Trade for Rail Operations Center.

6 HART is working with the City on this land exchange. The City needs to approve this exchange once it is worked out by Dept. of Hawaiian Homelands (DHHL).

DBB271 STA 20.05_04

FHSGC: Consolidated Resolution, capturing numerous risks into one agreement with the contractor.

6 HART is continuing to negotiate with the contractor for a fair settlement of all remaining issues through final closeout of the project.

Page 103: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

103 | P a g e

Risk ID Risk Description Risk Threat Score

Risk Mitigation

DBB271 STA 20.01_26

FHSGC: Plan B Canopy Redesign Delay Claim.

6 HART is continuing to negotiate with the contractor for a fair settlement of all remaining issues through final closeout of the project.

DBB371 STA 20.02_05

KHSGC: HART Open Changes. 6 HART is continuing to negotiate with the contractor for a fair settlement of all remaining issues through final closeout of the project.

DBB600 SUP 30.01_01

Park-and-Ride Lots: Contingency for Park-and-Ride Lots construction.

6 HART is holding a contingency value until the final park-and-ride locations are determined, designs are complete, and construction is underway.

MI900 SYS 50.06_20

Fare Systems Vendor could experience additional costs.

6 Negotiate change orders with the proper contractor and/or award separate contract as needed for Fare Systems requirements. These requirements pertain to startup and rollout costs that are not included in the scopes of work for the Fare Systems Contractor or Technical Consultant.

UTIL68 SIT 40.02_08

Private Utilities: Construction sequencing for City Center creates additional work for utility companies.

6 HART is working with utility companies to understand the requirement for additional inspectors as the sequence of the CCUR work becomes more apparent through schedule coordination with the contractors involved.

UTIL68 SYS 50.03_01

Private Utilities: HECO Substation needed on land from UH adjacent to MSF, for reliable power for train operations.

6 The substation will need to be tested in June 2020 in time for Interim Revenue of Service in Dec. 2020; otherwise, the frequency of trains passing through this area will need to be reduced until the substation is on line. The substation requires PUC approval which HECO is now applying for.

UTIL68 SIT 40.02_09

HECO KHG 138 kV Relocation to provide adequate separation from guideway.

6 HART will coordinate with the design firm (RM Towill) to guide the scope to remain within reasonable limits, while meeting all necessary HECO requirements. A potholing program is underway to determine the locations of existing utilities along the route, and the reasonableness of undergrounding the 138kV along the highway. The project is in the concept design phase.

MI930 STA 20.07_03

Elevators/Escalators: Increase in Elevator and Escalator Quantity Requirements

6 The final number of additional escalators on all east stations have been determined to be two for AGS, and 11 additional for CCGS. Still need to negotiate a favorable resolution with E&E contractor for CCGS. This risk will be revisited after award of the City Center DB contract.

DBB371 STA 20.02_22

KHSGC: Potential Electrical and Structural Canopy Design Issues.

4 HART is continuing to negotiate with the contractor for a fair settlement of all remaining issues through final closeout of the project.

DB450 SIT 40.02_04

AGS: Conflict Resolution – Costs for Utility Relocations.

4 HART is coordinating with the contractor and utility agencies to mitigate any utility delay risks that could result in cost or schedule impact to the project.

Risk Scoring for Risk Threats The following risk scoring table (used in the calculation of the risk threat scores shown above) is in accordance with FTA guidelines for summarizing the overall severity of project risks. HART has adjusted the cost and schedule ranges shown below in order to scale to the HART Project size.

Risk Scoring for Risk Threats

Impact Scores Legend

Low 1

Medium 2

High 3

(P) Probability <10% >10% <50% >50%

(C) Cost Impact <$10 M >$10 M <$50 M >$50 M

(S) Schedule Impact <1 month >1 month <4 months >4 months

Rating <6 7 - 12 13 - 18

Score = (Cost + Schedule) * Probability

Risks are assessed based on the probability of occurrence, potential (and most likely) cost impact, and potential (and most likely) schedule delay. The total score is arrived at by adding the cost and schedule impact scores, multiplied by the probability score. For example:

Page 104: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

104 | P a g e

40% Probability = 2; A $60 million Cost Impact = 3; A five month Schedule Impact = 3 Resulting Score = 3 + 3 = 6 x 2 = 12; a Medium Risk.

6.7.3 Top Risk Opportunities

Risk ID Risk Description Risk Opportunity Score

Risk Mitigation

P3-550 SIT 40.05_01

P3 for CCGS: Opportunities for P3 innovation through Alternative Technical Concepts (ATC’s).

15 1. HART plans to evaluate and approve ATC’s that are beneficial to the Project. 2. There were ATC’s that were received for previous HART projects, so there is precedence for this possible savings.

DB511 SIT 40.02_15

CCUR: Continue to find opportunities to eliminate unnecessary utility relocations based on results of potholing which is identifying specific utility locations, and ability to shift planned locations of guideway foundations (shafts).

10 1. The CCUR team has identified significant savings to date. 2. There is a reasonable probability that additional savings can be realized which should provide sufficient contingency with the CCUR contract to address further unknowns that will need to be dealt with as City Center utility relocations continue.

275 PRO 80.01_01

P3-PHPTR: Opportunity for P3 to present a modest cost reduction for construction of the Pearl Highlands Garage and Transit Center.

9 HART has been working to make the RFP as performance-based as possible so that it allows creativity from the P3 team(s).

P3-DB550 PRO 80.01_02

P3 for CCGS: Opportunity for P3 to present a modest cost reduction for construction of City Center Guideway and Stations, and remaining Core Systems work.

6 HART has been working to make the RFP as performance-based as possible so that it allows creativity from the P3 team(s).

Risk Scoring for Risk Opportunities

Risk Scoring for Risk Opportunities

Impact Scores Legend

Low 1

Medium 2

High 3

(P) Probability <10% >10% <50% >50%

(C) Cost Impact <$10 M >$10 M <$50 M >$50 M

(S) Schedule Impact <1 month >1 month <4 months >4 months

Rating <6 7 - 12 13 - 18

Score = (Cost + Schedule) * Probability

Similar to the legend for scoring of Risk Threats, Risk Opportunities are assessed based on the probability of occurrence, potential (and most likely) cost impact, and potential (and most likely) schedule delay. The total score is arrived at by adding the cost and schedule impact scores, multiplied by the probability score. The scoring calculation for Risk Opportunities is the same as for Risk Threats; however, in the Opportunities scoring table above, high opportunity scores are colored green (versus red), low opportunity scores are colored blue (versus green), and medium opportunity scores are still colored yellow. 6.7.4. Recent Risk Updates

The most recent monthly risk update occurred in February 2020, the results of which are discussed herein. The P65 results now place the projected forecast at $8.222 billion, which is $57 million above HART’s budget goal of $8.165 billion, and $77 million below the overall budget goal of $8.299 billion as recommended by PMOC and FTA.

At the most recent quarterly update held in February 2020, the Risk Refresh was facilitated by the Risk Manager. This involved face to face meetings with project team members to review each risk, discuss their validity and if any adjustments are needed to the post-mitigated responses, discuss if any new risks are necessary, and to explore ongoing risk mitigation efforts. The results of the February 2020 Risk Refresh are shown herein, and will be summarized in the meeting with FTA and the PMOC at the next FTA Quarterly Meeting. The next quarterly Risk Refresh will be held in mid-May 2020.

Page 105: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

105 | P a g e

Two significant adjustments in the February 2020 Risk Refresh included: P3 for CCGS and PHPTR

1. New Risk: Revocation of Noise Variance which allows night and weekend work. This risk poses a modest direct cost impact, and a potential schedule impact. The Risk Manager understands that this risk was transferred to HART from the P3. The Risk Manager added this new risk and its associated value based on meetings and conversations with HART Environmental and construction oversight staff.

2. Environmental Risk adjustment, due to Risk Transfers to HART. This means HART will have cost and some schedule responsibility for environmental cleanup which has the potential to delay the P3 for CCGS. Adjusted this risk based on meetings and conversations with HART Environmental and construction oversight staff.

Several significant adjustments in the prior risk updates for January 2020 and December 2019 risk updates included:

1. Numerous risks were retired in the west station contracts in the January 2020 risk update, due to the execution of change orders in January 2020 from HART’s consolidated resolutions with the respective contractors. Since the change order values were reflected in risk values up until the execution of the change orders, there is no additional net savings to the overall risk forecast for the west stations from the February 2020 risk update. However, the November 2019 Risk Refresh took credit for the results of the Consolidated Resolutions with the contractors, having turned a savings back into the Project, which offset the escalation costs for the planned CCGS work. Note that the Risk Model still preserves risk values for final resolution of station canopy issues that are not covered by the Consolidated Resolutions.

2. Increase in CCUR cost risk to include utility/pedestrian bridges over the Kapalama Stream, which are part of the current utility relocation plan. (Updated in December 2019. This cost will need to transfer from risk to being a budgeted project cost, but for now is being held as a risk value.) The Risk Manager will review with Project Controls and the CCUR team what portion of this risk may already be in the base CCUR budget, and any appropriate adjustment will be provided in the March 2020 Risk update.

3. Modest increase in ROW risk reflecting the requirement for new acquisitions related to property necessary for straddle bent foundations along Dillingham Boulevard and other sections of the CCGS route, recognizing that time will be required for environmental clearances and the property acquisition process. (Updated in November 2019.)

4. Modest increase in CCUR schedule risk causing several months of extension of the schedule for turning over key areas to the P3. The Risk Model assumes that realistic access dates will be included in the P3 RFP based on thorough schedule reviews by the HART Project Controls team. The Risk Model therefore includes escalation of the P3 costs for implementing the CCGS work several months later, which is believed by Risk Management to be a much safer approach compared to promising access dates that are too aggressive and could result in delay claims from the P3 which would be more expensive compared to escalation costs. (Updated in November 2019.)

5. Modest increase in the Procurement timeframe leading to an NTP for the P3; however, this is a concurrent risk with completion of CCUR activities, so the Procurement risk is not currently a critical path risk. (Updated in November 2019.)

Page 106: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

106 | P a g e

6.7.5. Cost and Schedule Probability Curves from February 2020 Risk Refresh Figure 11. Cost Probability Curve, February 2020 Risk Data

The update shown in Figure 11 resulted in a $44 million increase to the P65 risk expected value when comparing the February 2020 update (shown above) to the January 2020 update (shown in the prior report). This increase is due to risk adjustments over the last month as outlined above, that will be discussed in detail with HART Management, and the PMOC in the March 2020 monthly meeting, and with FTA in the next FTA Quarterly meeting. The P65 for the overall HART project is now $8.222 billion, which is $57 million above HART’s budget goal of $8.165 billion, and is $77 million below FTA/PMOC’s recommended budget of $8.299 billion.

Figure 12. Schedule Probability Curve, February 2020 Risk Data

Page 107: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

107 | P a g e

The schedule update shown in Figure 12 resulted a 1-month extension in the P65 schedule risk assessment when comparing the February 2020 update (August 2026 shown above) to the January 2020 update (July 2026 shown in the prior report). Schedule risks will be discussed in detail with HART Management and the PMOC in the March 2020 monthly meeting and the next FTA Quarterly Meeting. The P65 for the overall HART project is now August 2026, which is 8 months beyond HART’s stated schedule goal of December 2025, and 1 month prior to the PMOC recommended target date of September 2026 for meeting final revenue service. 6.7.6. Ongoing Risk Mitigation Efforts The P65 schedule extension to August 2026 from the February 2020 Risk Refresh (formerly July 2026 from the January 2020 and December 2019 risk updates) is a significant concern to HART. The project delivery timeframe for CCGS to still accomplish the full RSD by December 2025 is still a HART goal, requiring particular focus on the following risk areas:

1. Expedite the ROW acquisition schedule for necessary acquisitions to accommodate utility relocations (CCUR) and necessary space for straddle bent foundations along the CCGS route. Ensure qualified ROW staff are in place and necessary support is received from HART’s Real Estate Consultant. All necessary ROW must be acquired in time for P3 Access Dates to be met.

2. Expedite the City Center Utilities Relocations and Road work (CCUR) in time to meet area by area Access Dates being committed to the P3 PLO’s in the procurement documents. This can be accomplished by securing all third party agreements and permits in advance, and maintaining the right level of qualified CEI staff for design oversight and field construction oversight. Ensure that the CCUR contractor is executing the work as proactively as possible with qualified construction staff, equipment selections, and effective maintenance-of-traffic planning.

3. Ensure that the approach to dealing with both identified and unidentified environmental contamination, and/or archaeological finds, are agreed with DOH and other oversight agencies in advance, in order to deal with the impacts encountered during construction appropriately and as expeditiously as possible. HART will need to set aside adequate contingency to pay for this cleanup work due to the risk transfers from the P3 to HART, which HART believes can be effectively managed by HART’s on-call environmental cleanup contractors.

4. Incentivize the future P3 contractor to complete the CCGS and Pearl Highlands Garage, Transit Center and Ramps work on time, for final RSD if possible on or before December 2025.

5. Ensure all necessary procurement procedures are being followed correctly. Minimize the possibility of a protest over procedural issues related to this important procurement.

6. Ensure final completion and closeout of the west station projects in early 2020, in order to meet the Interim Revenue Service goal of October 2020, and to have this west section fully functional and ready for turnover to the P3 at the date specified in the P3 RFP.

As reflected above, the current schedule risk forecast identifies potential concerns with risks in the categories of Right-of-Way, Utilities Relocations, Environmental, Archaeological, and Procurement. The schedule risk forecast suggests if ongoing mitigation efforts related to these risks fail, the delay consequences could be severe.

6.8 Construction Claims Pursuant to FTA Circular 4220.1F, HART is obligated to notify the FTA and PMOC about third-party claims and litigation with which it is involved. HART considers a “claim” to arise when a third-party contractor submits a request for a final written decision by the Contracting Officer. Pursuant to Hawai‘i Revised Statutes Section 103D-711 and Hawai‘i Administrative Rules Section 3-126-28, the Contracting Officer’s decision is deemed final and the basis on which the aggrieved party can initiate an action in Circuit Court within six (6) months of receipt of the Contracting Officer’s decision.

Page 108: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

108 | P a g e

HART is tracking the following claims:

Contract Contractor Claim Description Claim Amount Status

FHSG Hawaiian Dredging

Construction Co.

HDCC seeks compensation for premium costs to furnish manpower from out-of-state for the period from April 2017 through August 2017 due to the unavailability of local manpower.

$103,167 HDCC submitted a request for a final written decision by the Contracting Officer on Jan. 22, 2019. This matter has been taken under consideration.

FHSG Hawaiian Dredging

Construction Co.

HDCC seeks compensation for additional staffing and resources from Notice to Proceed through January 2018.

$3,438,061 HDCC submitted a request for a final written decision by the Contracting Officer on Feb. 12, 2019. This matter has been taken under consideration.

FHSG Hawaiian Dredging

Construction Co.

HDCC seeks compensation for providing NEMA Type 4X, stainless steel electrical enclosures.

$194,360 HDCC submitted a request for a final written decision by the Contracting Officer on Jan. 22, 2019. This matter has been taken under consideration.

FHSG Hawaiian Dredging

Construction Co.

HDCC seeks compensation for shoring for the Waipahu Transit Center platform box girder construction.

$670,060 HDCC submitted a request for a final written decision by the Contracting Officer on Jan. 22, 2019. This matter has been taken under consideration.

6.9 Community Outreach Overview

Since the inception of HART, the outreach team has participated in: o 1,500 Public Presentations and Events

The HART Public Involvement (PI) team participated in a total of 27 events and presentations in February 2020.

Community outreach events included the presentation of HART Youth Train Community Day event (west-side high school students on Feb. 7) and HART Train Community Day event (general public on Feb. 8) at Hālaulani (Leeward Community College Station). The public involvement team also participated in the Honolulu Night + Market event in Kaka‘ako, Hawai‘i Tourism Day at the Hawai‘i State Capital, Hawaii Technology Academy STEAM (science, technology, engineering and math) Day event, and the Eat the Street Block Festival at Kahala Mall. HART public involvement’s community outreach efforts also included a series of five community outreach events entitled “HART Garage Meetings” to connect with residential homeowners and their neighbors along Dillingham Boulevard to discuss upcoming construction plans for the City Center Utility Relocation project.

o 879 Neighborhood Board Meetings HART attended 8 Neighborhood Board Meetings in February 2020.

Community Input

HART's public outreach team responded to 96 public inquiries and comments via the 24-hour project hotline and project email ([email protected]) during the month of February 2020. Inquiries were generally related to construction issues along the 20-mile corridor.

6.10 Staffing Overview

Organization: The latest organizational chart is dated Jan. 29, 2020. Please see Appendix D. Project Staffing:

o Target (Allocated) City Positions: 135 Full-Time Equivalent (FTE) City Staff. Does not include Project Management Support consultants below.

Page 109: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

109 | P a g e

o Filled City Positions: 117 Employees: (98) Personal Services Contract [PSC] Employees, (1) Civil Service, (5) Appointees, (5) 89-day contract, (8) Interns

o Vacancy Rate: 13.3% o Project Management Support Consultant (HDR) Staff Total: 18 HDR employees embedded in the HART

organization directly participating in the management of the project, 2 HDR employees working for the State Historic Preservation Division (SHPD) providing support services, and 1 HDR employee assisting HART on a part-time basis with risk modeling (statistical analysis and risk report production).

Positions Filled in February: o Budget Analyst IV o Deputy Director of Contract Administration, Procurement

Projected Position Fills: o Deputy Director of Administrative Services, Administrative Services – April o Accountant I - March o Accountant II –March o Accountant V - March o Secretary I – March o Right of Way Specialist – March o Computer Programmer I - March o Information Specialist I - April o Internal Controls Analyst III – April o Fixed Asset Specialist – April

February Departures: o Accountant IV

Projected Departures: o N/A

Figure 13. Staffing Activities

Staffing Activities

Title Group

New/Existing HART

Position (City or PMC)

Position Status* Start Month

P3 , Core Systems, and Readiness and Activation

Engineer Core Systems Existing (City) Recruiting - PSC

Engineer Readiness and Activation New (City) Recruiting - PSC

Design & Construction

Program Manager Production East Area Construction Existing (City) Recruiting - PSC

Assistant Area Manager East Area Construction Existing (City) Recruiting - PSC

Secretary I Design & Construction Existing (City) Selected – PSC March

Transportation Planner Third Party and Traffic Engineering

New (City) Recruiting - PSC

Transit Property Acquisition & Relocation

Right of Way Specialist Transit Property Acquisition & Relocation

Existing (City) Selected - PSC March

Right of Way Specialist Transit Property Acquisition & Relocation

Existing (City) Recruiting - PSC

Planning

Planner Planning Existing (City) Recruiting – PSC

Hazmat Planner Planning Existing (City) Recruiting - PSC

Transportation Planner Planning Existing (City) Recruiting - PSC

Budget & Finance

Financial Services Manager Budget & Finance Existing (City) Filled Temp Agency

Budget Analyst IV Budget & Finance Existing (City) Filled – PSC Feb

Accountant I Budget & Finance Existing (City) Selected – PSC March

Accountant II Budget & Finance Existing (City) Selected – PSC March

Accountant V Budget & Accounting Existing (City) Selected – PSC March

Internal Controls Analyst III Budget & Accounting Existing (City) Selected – PSC April

Page 110: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

110 | P a g e

Staffing Activities

Title Group

New/Existing HART

Position (City or PMC)

Position Status* Start Month

Financial Analyst/Management Analyst

Budget & Finance Existing (City) Filled Temp Agency

Financial/Management Analyst (Financing)

Budget & Finance Existing (City) Filled Temp Agency

OCIP/Risk Compliance Budget & Finance Existing (City) Filled Temp Agency

Project Controls

Financial Analyst Project Controls Existing (City) Recruiting – PSC

Computer Programmer Project Controls Existing (City) Selected – PSC March

Procurement, Contracts & Construction Claims

Director Procurement, Contracts, and Construction Claims

Procurement, Contracts and Construction Claims

Existing (City) Recruiting – PSC

Procurement & Specifications Specialist

Procurement & Consultant Contracts

Existing (City) Recruiting - PSC

Procurement & Specifications Specialist

Procurement & Consultant Contracts

Existing (City) Recruiting - PSC

Deputy Director of Contract Administration

Contract Administration New (City) Filled – PSC Feb

Contracts Manager Contract Administration Existing (City) Recruiting – PSC

Construction Claims Manager Construction Claims Existing (City) Recruiting - PSC

Administrative Services

Deputy Director of Administrative Services

Administrative Services New (City) Selected – PSC April

Human Resources Specialist V Administrative Services Existing (City) Recruiting - PSC

Public Involvement

Public Involvement Officer Public Involvement Existing (City) Recruiting - PSC

Information Specialist Public Involvement Existing (City) Selected - PSC April

System Safety and Security

System Safety Engineer Safety Existing (City) Recruiting - PSC

Asset Management

Fixed Asset Specialist Executive Management New (City) Selected – PSC April

*Personal Services Contracts are limited to one year per the Revised Charter of the City and County of Honolulu, Sec. 6-1103(g).

6.11 HART Baseline Plans and Procedures Status List The status of the Baseline Plans and Procedures is shown below (NOTE: changes, if any, are in bold font):

Owner Plan/Procedure Revision Level Date Approved Status

Project Management (Sam Carnaggio)

Project Management Plan (PMP)

7.0 December 10, 2018 Approved/Baselined

Safety and Security (Ralph McKinney)

Construction Safety and Security Plan (CSSP)

5.0 March 5, 2019 Approved/Baselined

Safety and Security Certification Plan (SSCP)

7.0 January 30, 2019 Approved/Baselined

Safety and Security Management Plan (SSMP)

8.0 February 11, 2019 Approved/Baselined

Sensitive Safety Information Plan

1.0 December 13, 2017 Approved/Baselined

Page 111: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

111 | P a g e

Owner Plan/Procedure Revision Level Date Approved Status

Preliminary Hazard Analysis (PHA)

4.0 July 3, 2019 Approved/Baselined

Threat and Vulnerability Assessment (TVA)

2.0 January 12, 2018 Approved/Baselined

Incident Investigation Procedure

0.0 February 28, 2019 Approved/Baselined

Quality Assurance (Alberto Bonifacio)

1.PP-02, Project Procedure and Plan Revision and Control Procedure

4.0 February 22, 2019 Approved/Baselined

1.PP-03, Standard Terms, Definitions, and Acronyms Procedure

3.0 February 21, 2019 Approved/Baselined

3.PM-05, Meeting Minutes Procedure

4.0 January 28, 2019 Approved/Baselined

6.CM-01, Submittal Processing Procedure

4.0 January 28, 2019 Approved/Baselined

Quality Management Plan (QMP)

4.0 November 9, 2018 Approved/Baselined

Procurement, Contracts, and Construction

2.PA-09, Procurement Standards of Conduct Procedure

2.0 March 6, 2019 Approved/Baselined

Claims (David Ha)

2.PA-10, Procurement Methods Procedure

1.0 February 13, 2019 Approved/Baselined

2.PA-11, Procurement Full and Open Competition Procedure

1.0 February 13, 2019 Approved/Baselined

2.PA-12, Procurement Federal Compliance Procedure

1.0 March 5, 2019 Approved/Baselined

2.PA-13, Procurement Protests Procedure

2.0 February 13, 2019 Approved/Baselined

2.PA-14, Procurement Record-keeping Procedure

1.0 April 2, 2019 Approved/Baselined

2.PA-15, Stipend Payment Procedure

1.0 February 11, 2019 Approved/Baselined

2.PA-16 Executive Decision Document (EDD) Procedure

0.0 January 24, 2019 Approved/Baselined

5.CA-06, Project Closeout Procedure

3.0 April 23, 2019 Approved/Baselined

5.CA-11, Contract Changes Procedure

5.0 April 25, 2019 Approved/Baselined

5.CA-12 Professional Services and Utility Engineering Services Agreement Contract Closeout Procedure

0.0 November 4, 2019 Approved/Baselined

Buy America Plan (BAP) 3.0 April 9, 2019 Approved/Baselined

Page 112: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

112 | P a g e

Owner Plan/Procedure Revision Level Date Approved Status

HART Procurement Manual

1.0 April 25, 2019 Approved/Baselined

(David Uchiyama) 5.CA-13 Consultant Performance Milestone Evaluation Procedure

0.0 February 24, 2020 Approved/Baselined

5.CA-14 Consultant Performance Evaluation Procedure

0.0 February 24, 2020 Approved/Baselined

Project Controls (Nate Meddings)

2.PA-04, Project-wide Document Control and Project Library Procedure

4.0 November 25, 2019 Approved/Baselined

3.PM-01, Contract Management System Procedure

3.0 March 13, 2019 Approved/Baselined

4.PC-03, Project Progress Report Procedure

3.0 March 19, 2019 Approved/Baselined

4.PC-04, Project Scheduling Procedure

4.0 August 15, 2018 Approved/Baselined

4.PC-06, Cost Estimating Procedure

3.0 December 13, 2017 Approved/Baselined

4.PC-07, Cost Control Procedure

3.0 March 25, 2019 Approved/Baselined

4.PC-09, Contingency Management Procedure

2.0 March 5, 2019 Approved/Baselined

Contract Packaging Plan (CPP)

6.0 October 4, 2018 Approved/Baselined

Budget and Finance (Ruth Lohr)

5.CA-03, Contractor Payment Application Procedure

3.0 March 22, 2019 Approved/Baselined

5.CA-10, Consultant Invoice Payment Procedure

1.0 March 27, 2019 Approved/Baselined

7.GA-04, Petty Cash Procedure

3.0 January 9, 2019 Approved/Baselined

7.GA-06, Travel Procedure

3.0 March 29, 2019 Approved/Baselined

Project Financial Plan (PFP): Revised Recovery Plan

1.0 November 19, 2018 Approved/Baselined

Planning and Permitting (Ryan Tam)

6.CM-08, Environmental Procedure

1.0 April 1, 2019 Approved/Baselined

Before-and-After Study Plan

1.0 March 25, 2019 Approved/Baselined

Bus Fleet Management Plan (BFMP)

5.0 April 15, 2019 Approved/Baselined

Mitigation Monitoring Plan (MMP)

3.0 March 7, 2019 Approved/Baselined

Page 113: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

113 | P a g e

Owner Plan/Procedure Revision Level Date Approved Status

Right-of-Way (Dylan Jones)

Real Estate Acquisition Management Plan (RAMP)

7.0 January 23, 2019 Approved/Baselined

Public Information (Joyce Oliveira)

2.PA-06, Community Relations and Media Contacts Procedure

3.0 March 6, 2019 Approved/Baselined

3.PM-04, Public Involvement Communications Procedure

3.0 March 6, 2019 Approved/Baselined

Public Involvement Plan (PIP)

2.0 March 4, 2019 Approved/Baselined

Design and Construction (Frank Kosich)

6.CM-02, Request for Information (RFI) Processing Procedure

3.0 March 15, 2019 Approved/Baselined

CADD Procedures 2.0 March 19, 2019 Approved/Baselined

Configuration Management Plan (CFMP)

4.0 March 27, 2019 Approved/Baselined

Construction Management Plan (CMP)

4.0 March 25, 2019 Approved/Baselined

Operation and Maintenance (Robert Good/DTS)

Interface Management Plan (IMP)

4.0 March 6, 2019 Approved/Baselined

System Integration and Test Plan (SITP)

2.0 March 1, 2019 Approved/Baselined

Rail Fleet Management Plan (RFMP)

2.0 March 28, 2019 Approved/Baselined

Operation and Management Plan (OMP)

2.0 March 28, 2019 Approved/Baselined

Rail Activation Plan 2.0 February 11, 2019 Approved/Baselined

2. PA-17 DTS – HART Communication Procedure

0.0 July 15, 2019 Approved/Baselined

Administrative Services (Dexter Suzuki)

1.PP-05, Identification Badge Procedure

3.0 January 24, 2019 Approved/Baselined

2.PA-03, Email Management Procedure

3.0 January 31, 2019 Approved/Baselined

2.PA-07, Training Procedure

3.0 January 31, 2019 Approved/Baselined

Staffing and Succession Plan

6.0 March 20, 2019 Approved/Baselined

Risk Management (Paul Johnson)

4.PC-08, Risk Management Procedure

3.0 March 8, 2019 Approved/Baselined

Risk and Contingency Management Plan (RCMP)

3.0 March 8, 2019 Approved/Baselined

Page 114: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

114 | P a g e

6.12 Readiness and Activation

Overview of Key Responsibilities Oversight of the Core System Contractor’s Operations and Maintenance (O&M) development and mobilization. Review and support of HART project activities with an emphasis on O&M impact assessment. Collaborating with DTS to ensure readiness for O&M responsibilities.

Ongoing Activities Supporting P3 procurement process. Concluded support of HRH O&M contract negotiations (change order executed). Supported February HART Board briefing on readiness and activation. Key HRH Mobilization Activities

o Document Preparation Health, Safety, Quality and Environmental (HSQE) documents being finalized. HRH Training Program Plan was approved (ANR). O&M Management and Staffing Plan and Trial Run Plan submitted for review. Developing Trial Run Scenarios and Test Cases. O&M Mobilization Team is supported by up to 30 FTE experienced rail consultants.

o O&M Training is scheduled to start the 1st week of April. o HRH continues to actively recruit key positions and experienced rail transit personnel.

HRH Head of O&M – Americas is currently supporting on-site mobilization effort for at least 2 months.

Identified candidate for permanent O&M Director. Identified candidate for Operations Director. Mass recruitment efforts on track to exceed February and March targets.

o Maintenance Activities Passenger Vehicle Maintenance Service Plan submitted for review. Draft MMIS Functional Design Document, Cloud Infrastructure Specifications, and Master Data

Definition submitted for preliminary review. MMIS workshop to finalize design is scheduled for the 1st week of March.

Module development and implementation “Sprints”.

Prototyping preventative maintenance workflow. Continued oversight and auditing of the HRH maintenance program and Key Performance

Indicators (KPIs). DTS and project stakeholder coordination

o Facilitate Interim Opening Task Force Meeting with DTS, BFS, and City Stakeholders. o Supporting document reviews per HART Charter Amendment 4 MOU procedure. o Facilitating negotiations for Amendment 1 and 2 to the HDOT West O‘ahu Farrington Highway Master

Agreement, and Joint Use and Occupancy Agreement. o Supporting development of joint HART-DTS schedule and identification of critical path items for

Intermediate Operations and Maintenance Period (IOMP) 1. o Transit Agency Rail Safety Plan and System Security Plan in final preparation stages for submittal to HDOT.

Supporting HART Safety revisions of Operational Readiness Conformance Checklist (ORCC) to correspond with HRH Training Program Structure.

Actively recruiting the HART position to support HRH Mobilization oversight, technical reviews, and asset management program development. Also recruiting a summer engineering intern to assist the Facility Maintenance Manager and Fare Systems Manager.

Fare Systems (see Fare Systems section of report).

Look Ahead

O&M Rule Book Workshop (March/April).

HRH and HART developing a consolidated Hazard Log, target completion by end of April.

Oversight Procedure (OP) 54 discussion with HDOT is scheduled for May/June. o FTA review is scheduled for July.

Page 115: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

115 | P a g e

APPENDICES

Page 116: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Ho

no

lulu

Rai

l Tra

nsi

t P

roje

ct M

on

thly

Pro

gre

ss R

ep

ort

Fe

bru

ary

20

20

11

6 |

Pa

ge

A

pp

en

dix

A.

Pro

ject

Co

sts

by

SCC

– L

eve

l 2 (d

ata

as o

f Fe

b. 2

9, 2

02

0)

Co

st r

epo

rts

are

run

fro

m t

he

HA

RT

Co

ntr

act

Man

agem

ent

Syst

em

(C

MS)

SCC

De

scri

pti

on

Bas

e C

ost

Co

nti

nge

ncy

Tota

lB

ase

Co

stC

on

tin

gen

cyTo

tal

Incu

rre

d

10

GU

IDEW

AY

& T

RA

CK

ELE

MEN

TS1

,38

5,6

13

,35

0

22

2,8

68

,32

5

1

,60

8,4

81

,67

5

1,4

75

,56

0,1

92

1

32

,92

1,4

84

1,6

08

,48

1,6

76

8

61

,90

6,2

84

10

.02

Gu

idew

ay:

At-

gra

de

sem

i-ex

clu

sive

17

,37

8

-

1

7,3

78

17

,37

8

-

1

7,3

78

17

,37

8

1

0.0

4G

uid

ewa

y: A

eria

l st

ruct

ure

1,2

43

,17

0,3

39

2

14

,66

8,3

25

1,4

57

,83

8,6

64

1

,33

3,1

17

,18

1

12

4,7

21

,48

4

1

,45

7,8

38

,66

5

77

6,5

39

,64

2

1

0.0

5G

uid

ewa

y: B

uil

t-u

p f

ill

-

-

-

-

-

-

5,0

54

,74

4

1

0.0

6G

uid

ewa

y: U

nd

ergr

ou

nd

Cu

t &

Cvr

-

-

-

-

-

-

(1,2

28

,00

0)

1

0.0

8G

uid

ewa

y: R

eta

ined

cu

t o

r fi

ll1

42

,42

5,6

33

8,2

00

,00

0

1

50

,62

5,6

33

14

2,4

25

,63

3

8

,20

0,0

00

15

0,6

25

,63

3

-

1

0.0

9Tr

ack

: Dir

ect

fixa

tio

n-

-

-

-

-

-

7

7,5

97

,27

1

10

.11

Tra

ck: B

all

ast

ed-

-

-

-

-

-

2

,39

4,3

73

10

.12

Tra

ck: S

pec

ial

(sw

itch

es, t

urn

ou

ts)

-

-

-

-

-

-

1,5

30

,87

6

2

0ST

ATI

ON

S, S

TOP

S, T

ERM

INA

LS, I

NTE

RM

OD

A7

40

,27

8,8

79

91

,42

3,1

95

8

31

,70

2,0

74

81

5,1

57

,99

6

1

7,4

52

,95

1

83

2,6

10

,94

7

2

50

,23

0,6

82

20

.01

At-

gra

de

sta

tio

n, s

top

, sh

elte

r, m

all

, ter

min

al,

pla

tfo

rm4

,95

6,1

81

8,5

05

,32

5

1

3,4

61

,50

6

4,9

56

,18

1

8

,50

5,3

25

13

,46

1,5

06

1

74

,59

0

20

.02

Aer

ial

sta

tio

n, s

top

, sh

elte

r, m

all

, ter

min

al,

pla

tfo

rm5

48

,21

9,0

08

54

,49

6,4

53

6

02

,71

5,4

61

62

9,4

17

,87

8

(2

5,7

93

,54

4)

6

03

,62

4,3

34

23

3,6

20

,89

4

2

0.0

4O

ther

sta

tio

ns,

la

nd

ings

, ter

min

al

-

-

-

-

-

-

-

20

.06

Au

tom

ob

ile

pa

rkin

g m

ult

i-st

ory

str

uct

ure

12

1,6

09

,47

3

2

6,6

32

,47

5

14

8,2

41

,94

8

1

23

,25

9,4

73

24

,98

2,4

75

1

48

,24

1,9

48

-

20

.07

Elev

ato

rs, e

sca

lato

rs6

5,4

94

,21

7

1,7

88

,94

2

6

7,2

83

,15

9

57

,52

4,4

64

9

,75

8,6

95

67

,28

3,1

59

1

6,4

35

,19

8

30

SUP

PO

RT

FAC

ILIT

IES:

YA

RD

S, S

HO

PS,

AD

MIN

. BLD

GS

10

0,8

06

,85

4

-

1

00

,80

6,8

54

10

0,8

06

,85

4

-

1

00

,80

6,8

54

12

2,2

67

,69

2

3

0.0

1A

dm

inis

tra

tio

n B

uil

din

g: O

ffic

e, S

ale

s-

-

-

-

-

-

2

31

,25

0

30

.02

Ligh

t M

ain

ten

an

ce F

aci

lity

3

,05

7,2

40

-

3,0

57

,24

0

3

,05

7,2

40

-

3,0

57

,24

0

7

,58

2,7

04

30

.03

Hea

vy M

ain

ten

an

ce F

aci

lity

64

,47

9,5

56

-

6

4,4

79

,55

6

64

,47

9,5

56

-

6

4,4

79

,55

6

46

,29

5,3

66

3

0.0

4St

ora

ge o

r M

ain

ten

an

ce o

f W

ay

Bu

ild

ing

8,6

19

,23

0

-

8

,61

9,2

30

8,6

19

,23

0

-

8

,61

9,2

30

8,8

92

,73

9

3

0.0

5Ya

rd a

nd

Ya

rd T

rack

24

,65

0,8

28

-

2

4,6

50

,82

8

24

,65

0,8

28

-

2

4,6

50

,82

8

59

,26

5,6

33

4

0SI

TEW

OR

K &

SP

ECIA

L C

ON

DIT

ION

S2

,31

5,2

94

,49

0

23

0,4

42

,93

2

2

,54

5,7

37

,42

2

2,1

80

,17

9,9

61

3

59

,63

5,8

19

2,5

39

,81

5,7

80

1

,02

5,9

62

,78

9

40

.01

Dem

oli

tio

n, C

lea

rin

g, E

art

hw

ork

33

,44

6,0

29

1

,03

8,0

00

34

,48

4,0

29

3

3,4

46

,02

9

1,0

38

,00

0

3

4,4

84

,02

9

6,0

93

,39

3

4

0.0

2Si

te U

tili

ties

, Uti

lity

Rel

oca

tio

n7

84

,99

3,4

74

97

,12

6,8

74

8

82

,12

0,3

48

77

5,3

73

,62

1

9

9,7

40

,08

5

87

5,1

13

,70

6

2

15

,56

2,9

36

40

.03

Ha

z. M

at’

l, c

on

tam

’d s

oil

rem

ova

l/m

itig

ati

on

, gro

un

d w

ate

r tr

eatm

ents

33

,82

9,6

83

5

15

,00

0

34

,34

4,6

83

3

3,8

29

,68

3

51

5,0

00

3

4,3

44

,68

3

20

,59

3,3

87

4

0.0

4En

viro

nm

enta

l m

itig

ati

on

, e.g

. wet

lan

ds,

his

tori

c/a

rch

eolo

gic,

pa

rks

5,5

18

,86

4

-

5

,51

8,8

64

8,4

17

,86

4

(2

,89

9,0

00

)

5,5

18

,86

4

1

5,4

77

,53

1

40

.05

Site

str

uct

ure

s in

clu

din

g re

tain

ing

wa

lls,

so

un

d w

all

s2

1,7

64

,98

5

6,8

84

,51

1

2

8,6

49

,49

6

21

,76

4,9

85

6

,88

4,5

11

28

,64

9,4

96

1

3,1

25

,04

2

40

.06

Ped

estr

ian

/ b

ike

acc

ess

an

d a

cco

mm

od

ati

on

, la

nd

sca

pin

g1

4,7

44

,27

6

50

0,0

00

1

5,2

44

,27

6

14

,74

4,2

76

5

00

,00

0

15

,24

4,2

76

2

,13

3,6

06

40

.07

Au

tom

ob

ile,

bu

s, v

an

acc

essw

ays

in

clu

din

g ro

ad

s, p

ark

ing

lots

26

4,5

80

,52

4

2

9,2

37

,56

8

29

3,8

18

,09

2

2

69

,70

6,5

25

24

,11

1,5

67

2

93

,81

8,0

92

86

,14

4,0

99

4

0.0

8Te

mp

ora

ry F

aci

liti

es a

nd

oth

er i

nd

irec

t co

sts

du

rin

g co

nst

ruct

ion

1,1

56

,41

6,6

55

9

5,1

40

,97

9

1,2

51

,55

7,6

34

1

,02

2,8

96

,97

8

22

9,7

45

,65

6

1

,25

2,6

42

,63

4

66

6,8

32

,79

6

5

0SY

STEM

S3

13

,98

3,9

39

16

,03

3,6

68

3

30

,01

7,6

07

32

7,8

68

,39

1

6

,60

1,9

84

33

4,4

70

,37

5

1

58

,34

3,0

01

50

.01

Tra

in c

on

tro

l a

nd

sig

na

ls1

57

,07

7,7

32

7,7

56

,52

2

1

64

,83

4,2

54

17

0,2

82

,50

4

(9

95

,48

2)

16

9,2

87

,02

2

6

8,3

90

,86

2

50

.02

Tra

ffic

sig

na

ls a

nd

cro

ssin

g p

rote

ctio

n3

,17

2,1

31

59

8,7

25

3

,77

0,8

56

3,1

72

,13

1

5

98

,72

5

3,7

70

,85

6

9

8,0

00

50

.03

Tra

ctio

n p

ow

er s

up

ply

: su

bst

ati

on

s 3

2,3

96

,80

8

-

32

,39

6,8

08

3

2,3

96

,80

8

-

32

,39

6,8

08

4

,00

3,9

71

50

.04

Tra

ctio

n p

ow

er d

istr

ibu

tio

n: c

ate

na

ry a

nd

th

ird

ra

il3

7,1

20

,97

7

-

37

,12

0,9

77

3

7,1

20

,97

7

-

37

,12

0,9

77

4

1,6

15

,38

0

50

.05

Co

mm

un

ica

tio

ns

65

,39

0,7

42

-

6

5,3

90

,74

2

65

,39

0,7

42

-

6

5,3

90

,74

2

35

,26

0,0

27

5

0.0

6Fa

re c

oll

ecti

on

sys

tem

an

d e

qu

ipm

ent

15

,01

5,2

06

7

,67

8,4

21

22

,69

3,6

27

1

5,6

94

,88

6

6,9

98

,74

1

2

2,6

93

,62

7

5,6

55

,70

9

5

0.0

7C

entr

al

Co

ntr

ol

3,8

10

,34

3

-

3

,81

0,3

43

3,8

10

,34

3

-

3

,81

0,3

43

3,3

19

,05

2

C

on

stru

ctio

n S

ub

tota

l (1

0 –

50

)4

,85

5,9

77

,51

2

56

0,7

68

,12

0

5

,41

6,7

45

,63

2

4,8

99

,57

3,3

94

5

16

,61

2,2

38

5,4

16

,18

5,6

32

2

,41

8,7

10

,44

8

Re

cove

ry P

lan

Bu

dge

tEs

tim

ate

At

Co

mp

leti

on

Page 117: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Ho

no

lulu

Rai

l Tra

nsi

t P

roje

ct M

on

thly

Pro

gre

ss R

ep

ort

Fe

bru

ary

20

20

11

7 |

Pa

ge

SCC

De

scri

pti

on

Bas

e C

ost

Co

nti

nge

ncy

Tota

lB

ase

Co

stC

on

tin

gen

cyTo

tal

Incu

rre

d

60

RO

W, L

AN

D, E

XIS

TIN

G IM

PR

OV

EMEN

TS2

54

,83

5,5

74

10

6,7

89

,89

0

3

61

,62

5,4

64

26

3,6

35

,57

4

9

7,9

89

,89

0

36

1,6

25

,46

4

1

92

,86

9,0

71

60

.01

Pu

rch

ase

or

lea

se o

f re

al

esta

te

17

1,4

00

,00

0

1

01

,50

0,0

00

27

2,9

00

,00

0

1

80

,20

0,0

00

92

,70

0,0

00

2

72

,90

0,0

00

19

2,5

91

,27

1

6

0.0

2R

elo

cati

on

of

exis

tin

g h

ou

seh

old

s a

nd

bu

sin

esse

s8

3,4

35

,57

4

5,2

89

,89

0

8

8,7

25

,46

4

83

,43

5,5

74

5

,28

9,8

90

88

,72

5,4

64

2

77

,80

0

70

VEH

ICLE

S2

11

,38

9,9

52

-

21

1,3

89

,95

2

2

11

,38

9,9

52

-

21

1,3

89

,95

2

1

26

,18

0,6

92

70

.01

Ligh

t R

ail

19

0,3

83

,69

4

-

1

90

,38

3,6

94

19

0,3

83

,69

4

-

1

90

,38

3,6

94

11

3,6

55

,93

4

7

0.0

2H

eavy

Ra

il-

-

-

-

-

-

-

7

0.0

5O

ther

12

8,7

00

-

1

28

,70

0

12

8,7

00

-

1

28

,70

0

49

3,7

00

7

0.0

6N

on

-rev

enu

e ve

hic

les

14

,37

1,3

44

-

1

4,3

71

,34

4

14

,37

1,3

44

-

1

4,3

71

,34

4

12

,03

1,0

58

7

0.0

7Sp

are

pa

rts

6,5

06

,21

4

-

6

,50

6,2

14

6,5

06

,21

4

-

6

,50

6,2

14

-

80

PR

OFE

SSIO

NA

L SE

RV

ICES

1,9

89

,87

0,7

25

9

7,6

30

,13

9

2,0

87

,50

0,8

64

2

,00

6,0

98

,45

5

81

,96

2,4

09

2

,08

8,0

60

,86

4

1,3

27

,63

7,5

68

8

0.0

1P

reli

min

ary

En

gin

eeri

ng

54

,75

3,8

40

-

5

4,7

53

,84

0

54

,75

3,8

40

-

5

4,7

53

,84

0

18

0,7

05

,91

6

8

0.0

2Fi

na

l D

esig

n5

84

,14

9,8

99

31

,51

2,6

97

6

15

,66

2,5

96

58

6,4

77

,62

9

2

9,1

84

,96

7

61

5,6

62

,59

6

3

65

,95

3,6

48

80

.03

Pro

ject

Ma

na

gem

ent

for

Des

ign

an

d C

on

stru

ctio

n6

68

,55

7,9

25

29

,85

1,8

33

6

98

,40

9,7

58

66

8,5

57

,92

5

2

9,8

51

,83

3

69

8,4

09

,75

8

4

81

,89

6,2

21

80

.04

Co

nst

ruct

ion

Ad

min

istr

ati

on

& M

an

age

men

t 2

78

,64

0,4

20

28

,22

0,0

08

3

06

,86

0,4

28

29

2,5

40

,42

0

1

4,3

20

,00

8

30

6,8

60

,42

8

2

14

,58

9,2

70

80

.05

Pro

fess

ion

al

Lia

bil

ity

an

d o

ther

No

n-C

on

stru

ctio

n I

nsu

ran

ce

99

,34

0,0

00

4

,00

0,0

00

10

3,3

40

,00

0

9

9,3

40

,00

0

4,0

00

,00

0

1

03

,34

0,0

00

45

,60

2,1

79

8

0.0

6Le

gal;

Per

mit

s; R

evie

w F

ees

by

oth

er a

gen

cies

, cit

ies,

etc

.9

9,9

28

,69

8

3,7

68

,43

9

1

03

,69

7,1

37

99

,92

8,6

98

3

,76

8,4

39

10

3,6

97

,13

7

3

3,2

28

,76

1

80

.07

Surv

eys,

Tes

tin

g, I

nve

stig

ati

on

, In

spec

tio

n1

41

,68

6,6

22

27

7,1

62

1

41

,96

3,7

84

14

1,6

86

,62

2

2

77

,16

2

14

1,9

63

,78

4

4

,05

2,7

00

80

.08

Sta

rt u

p6

2,8

13

,32

1

-

62

,81

3,3

21

6

2,8

13

,32

1

56

0,0

00

6

3,3

73

,32

1

1,6

08

,87

3

9

0Su

bto

tal (

10

– 8

0)

7,3

12

,07

3,7

63

7

65

,18

8,1

49

8,0

77

,26

1,9

12

7

,38

0,6

97

,37

5

69

6,5

64

,53

7

8

,07

7,2

61

,91

2

4,0

65

,39

7,7

79

U

NA

LLO

CA

TED

CO

NTI

NG

ENC

Y-

2

21

,73

8,0

87

22

1,7

38

,08

7

-

8

7,7

92

,27

9

87

,79

2,2

79

1

00

Sub

tota

l (1

0 –

90

)7

,31

2,0

73

,76

3

98

6,9

26

,23

6

8

,29

8,9

99

,99

9

7,3

80

,69

7,3

75

7

84

,35

6,8

16

8,1

65

,05

4,1

91

4

,06

5,3

97

,77

9

FIN

AN

CE

CH

AR

GES

60

9,0

00

,00

0

-

6

09

,00

0,0

00

54

7,0

00

,00

0

-

5

47

,00

0,0

00

31

,77

5,0

28

To

tal P

roje

ct C

ost

(1

0 –

10

0)

7,9

21

,07

3,7

63

9

86

,92

6,2

36

8,9

07

,99

9,9

99

7

,92

7,6

97

,37

5

78

4,3

56

,81

6

8

,71

2,0

54

,19

1

4,0

97

,17

2,8

07

Tota

l FFG

A P

roje

ct C

ost

(1

0 –

10

0)

7,9

21

,07

3,7

63

9

86

,92

6,2

36

8,9

07

,99

9,9

99

7

,92

7,6

97

,37

5

78

4,3

56

,81

6

8

,71

2,0

54

,19

1

4,0

97

,17

2,8

07

Esti

mat

e A

t C

om

ple

tio

nR

eco

very

Pla

n B

ud

get

Page 118: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

118 | P a g e

Appendix B. Core Accountability Items Including Major Issues

Core Accountability Items Including Major Issues – February 2020 Note that HART’s Recovery Plan, with revised budget and RSD, was approved by the FTA on Sept. 5, 2019; however, HART intends to continue to manage the project to its current EAC of December 2025.

Project Status: ($ are in millions) Original Budget

at FFGA HART

Current EAC Recovery Plan

Cost Base Cost w/o Contingency

$4,305 $7,381 $7,312

Contingency

Allocated $542 $696 $765

Unallocated Contingency $102 $88 $222

FFGA Finance Charges

$173 $547 $609

Post RSD Finance Charges

$42 $293 $231

Total Project Costs

$5,164 $9,005 $9,139

Schedule Revenue Service Date (RSD) January 31, 2020 December 2025 September 2026

Project Status: ($ are in millions) Amount ($) Percent

(as % of total)

Planned Value to Date $2,935 59.5%

Earned Value to Date $2,745 55.7%

Actual cost $4,097 55.5%

Contracts

Total Contracts Awarded to Date $5,351 72.5%

Total Construction Contract Awarded* (Construction Contracts Only)

$2,926 71.4%

Physical Construction Work Completed** (Amount of Construction Actually Completed)

$2,061 50.3%

Date of Next Quarterly Meeting TBD

*Percentage calculation in prior month was incorrect. It is calculated by taking Construction Contracts Only divided by Actual Cost **Percentage calculation in prior month was incorrect. It is calculated by taking Physical Construction Work divided by Actual Cost

Page 119: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

119 | P a g e

Appendix C. Construction Progress Interim Opening

Page 120: Cover February 2020 Monthly Progress Report DRAFThartdocs.honolulu.gov/docushare/dsweb/Get/Document-23516/Febru… · CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant

Honolulu Rail Transit Project Monthly Progress Report February 2020

120 | P a g e

Appendix D. Project Organization Chart