delay and project profitability. sigurður guðni sigurðsson september 2007

25
Delay and project profitability. Sigurður Guðni Sigurðsson September 2007

Upload: gregory-blair

Post on 17-Dec-2015

225 views

Category:

Documents


3 download

TRANSCRIPT

Delay and project profitability.

Sigurður Guðni Sigurðsson

September 2007

Delay and project profitability. Presumptions

Total time = Production time + Time of utilization

Total time is constant• Period of production 1 year, duration of operations 5

years– Affect on producer/developer – Affect on buyer

• Period of production 3 years, duration of operations 10 years– Affect on producer/developer– Affect on buyer

• Lump sum payment vs. distributed payment

Reason of delay. Contract variation.

• The owners (buyer) determination that makes delay and extra cost on his accountability.

• Force Majeure. Neither seller or buyer have any control of the cause. The seller can delay the project of such reasons.

• Delay based on sellers action. The seller is responsible and pays for it with penalty.

Short project . Sellers presumptions

Fixed contract price– Payment on delivery.• Cost estimate Kr. 1.000.000• Contribution margin 30%• Contract price Kr. 1.428.571• Duration of production 12 months• Penalty 5 % per month• Maximum penalty 15%• Fixed cost per year 7,5%• Cost of capital 8%• Inflation 4%

Sellers cost distribution Short production time

Cost NPV

0

200.000

400.000

600.000

800.000

1.000.000

1.200.000

1.400.000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Months

kr.

0 1 2 3 4 5 6 7 8 9 10 11 12Delay months

Affection of delay on profit Short production time

Profit and cost

-500.000

-400.000

-300.000

-200.000

-100.000

0

100.000

200.000

300.000

0 1 2 3 4 5 6 7 8 9 10 11 12

Delay months

-500.000

-400.000

-300.000

-200.000

-100.000

0

100.000

200.000

300.000

Fixed costr Financial cost Penaltyr decreased value of payment Profit - no delay Profit NPVr

Relative effect of delay on profit Short production time

Relative affect on profit

-100%

-80%

-60%

-40%

-20%

0%

0 1 2 3 4 5 6 7 8 9 10 11 12

Fixed cost Financial cost penaltyr Decreased value of paymentDelay months

Sensitivity analyzes

No delay

15%

17%

19%

21%

23%

25%

27%

-50% -40% -30% -20% -10% 0% 10% 20% 30% 40% 50%

Fixed cost Financial cost Inflation

12 month delay

-17%

-15%

-13%

-11%

-9%

-7%

-5%

-50% -40% -30% -20% -10% 0% 10% 20% 30% 40% 50%

Fixed cost Financial cost inflation

Short project Buyers presumptions

• Investment – no delay Kr. 1.428.571• Operation cost per year Kr. 1.000.000• Markup 70%• Lifetime 5 years• Financial cost 6 % • Fixed cost per year Kr. 75.000• Inflation 4%• Return on capital 20%

Distribution of income Fixed total income

Distribution of income

0%

50%

100%

150%

200%

250%

1 2 3 4 5

Year

0 1 2 3 4 5 6 7 8 9Case

NPV calculated from income distribution and delay.

NPV

-2.000.000

-1.000.000

0

1.000.000

2.000.000

3.000.000

4.000.000

0 1 2 3 4 5 6 7 8 9 10 11 12

Delay months

kr.

0 1 2 3 4 5 6 7 8 9Case

Internal Rate of Return based on income distribution and delay.

IRR

0%

50%

100%

150%

200%

250%

300%

0 1 2 3 4 5 6 7 8 9 10 11 12

Delay in months

0 1 2 3 4 5 6 7 8 9Case

Long project period. Sellers presumptions

Fixed contract price – Payment on delivery.• Cost estimate Kr. 1.000.000• Contribution margin 34,1%• Contract price Kr. 1.517.451• Duration of production 3 years• Penalty 2,5 % per month• Maximum penalty 15%• Fixed cost (36 months) Kr. 75.000• Financial cost 8%• Inflation 4%

Affection of delay on profit Long production time

Profit and cost

-600.000

-500.000

-400.000

-300.000

-200.000

-100.000

0

100.000

200.000

300.000

0 1 2 3 4 5 6 7 8 9 10 11 12

Delay in months

Fixed cost Financial cost Penalty Decrease of payment value Profit - no delay Profit - NPV

Sensitivity analyzes

No delay

8%

10%

12%

14%

16%

18%

20%

22%

-50% -40% -30% -20% -10% 0% 10% 20% 30% 40% 50%

Fixed cost Financial cost Inflation

12 month delay

-20%

-18%

-16%

-14%

-12%

-10%

-8%

-6%

-50% -40% -30% -20% -10% 0% 10% 20% 30% 40% 50%

Fastur kostnaður Fjármagnskostnaður Verðbólga

Affect on sellers presumptions

Fixed costFinancial cost Inflation

Estimated time 1 yearNo delay 8,8% 4,0% 4,9%12 m. delay 11,8% 7,4% 7,0%Estimated time 3 yearsNo delay 6,5% 11,1% 13,3%12 m. delay 6,5% 12,0% 13,5%

Sensitivity analysisChange in profit

Long project. Buyers presumptions

• Investment – no delay Kr. 1.517.451• Operation cost per year Kr. 1.000.000• Markup 50%• Lifetime 10 years• Financial cost 8 % • Fixed cost per year Kr. 75.000• Inflation 4%• Return on capital 20%

Distribution of income Fixed total income

Distribution of income

-50%

0%

50%

100%

150%

200%

250%

1 2 3 4 5 6 7 8 9 10

Year

0 1 2 3 4 5 6 7 8 9Case

NPV and IRR

NPV

-2.000.000

-1.000.000

0

1.000.000

2.000.000

3.000.000

4.000.000

5.000.000

0 1 2 3 4 5 6 7 8 9 10 11 12

Delay months

kr.

0 1 2 3 4 5 6 7 8 9Case

IRR

0%

20%

40%

60%

80%

100%

120%

140%

0 1 2 3 4 5 6 7 8 9 10 11 12

Delay in months

0 1 2 3 4 5 6 7 8 9Case

Distributed payment . Long project

Two payment series• Four payments:

Payment order Month. Percentage

Dawn payment 0 10,0%

Payment # 2 12 25,0%

Payment # 3 24 25,0%

Final payment 36 40,0%

• Four payments - 85% of earned value at each time

Sellers profit, Lump sum and distributed payments

- 20%

- 10%

0%

10%

20%

30%

40%

0 1 2 3 4 5 6 7 8 9 10 11 12

Delay months

Lump sum Fixed distribution Progress payment

NPV and distributed payments.The buyers side

NPV Case 0 evenly distributed income

- 100.000

0

100.000

200.000

300.000

400.000

500.000

600.000

700.000

800.000

0 1 2 3 4 5 6 7 8 9 10 11 12

Töf í mán.

Lump sum Distributed payments

NPV Case 8 Decreasing income

0

500.000

1.000.000

1.500.000

2.000.000

2.500.000

3.000.000

3.500.000

0 1 2 3 4 5 6 7 8 9 10 11 12

Töf í mán.

Lump sum distributed payments

Conclusions I

• Time and cost in projects have strong connection.• Delay harm both seller and buyer.• The buyers protection by using penalties protect him

only if income is low in the delay period or the delay is short.

• It is of common interest that the production period is successful.

• The length of the production period and lifetime of the product does not influence the results strongly.

• Sensitivity for changes in presumptions increase with longer delay.

Conclusions II

• The distribution of the income affects the delay impact. More impact as the delivery is later in the product life-cycle.

• It is of great interest to study further interaction between distributed payment and profitability of projects.

• The impact of distributed payments are often higher than penalty.

• Distributed payment is of high value for the seller. • Distributed payment cost the buyer more as the delay

increase.

Thank you